Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
OFFICIAL USE
OFFICIAL USE
Framework DTM 48171: Green Cities Framework
Sub-project DTM 49668 GrCF Banja Luka Water Project
Technical, Financial and Environmental & Social Due Diligence
TERMS OF REFERENCE
1. TERMINOLOGY – DEFINITIONS
The Assignment: the Contract of which these Terms of Reference form a part.
The Bank: The European Bank for Reconstruction and Development, the EBRD
The City: Banja Luka, Capital of Republika Srpska, one of the two political entities that make Bosnia
and Herzegovina.
The Company: Vodovod Banja Luka, a joint stock company majority (65 per cent) owned by the City
in charge of water supply and wastewater collection and treatment in the City.
The Client: The City will be the Client for this assignment.
The Consultant: The Entity contracted to carry out the works described in these Terms of Reference.
The Lenders: The EBRD.
The Project: Expansion and reconstruction of the water supply and wastewater system in the City of
Banja Luka
2. INTRODUCTION
The utility company “Vodovod Banja Luka” (the “Company”) supported by the City of Banja Luka
(the “City”), approached the European Bank for Reconstruction and Development (the “EBRD”, or the
“Bank”) with a request to finance the priority investments (Priority Investment Programme, or “PIP”)
aimed at improving water supply and wastewater services (the “Project”). The Project will support the
City in improving its provision of water and wastewater services, particularly to the currently
underserved population. The loan proceeds will finance expansion and rehabilitation of existing
drinking water supply and wastewater networks. The exact scope of the proposed PIP will be shared
with the Consultants in order to perform the due diligence. Total capex needs are estimated at EUR 10
million to be provided in two equal tranches of EUR 5 million each. The loan will be on-lent through a
legislated cascade of sub-loans from BiH via Republika Srpska (“RS”) to the City.
As an economic, financial, political and administrative centre of the Republic of Srpska (“RS”), the
City entrusted water supply and wastewater collection activities to the Company. The Company is a
joint stock company, with base equity of EUR 18.1 million as of end 2016, divided into 35.4 million of
shares. The City of Banja Luka holds the majority of the Company’s shares of 65 per cent, 15 per cent
is held by the Pension and Restitution Funds owned by the Government of the Republic of Srpska, and
the remainder is under the ownership of private funds.
The Company provides services to 186,000 consumers in the City of Banja Luka, the municipality of
Celinac and a portion of the municipality of Laktasi. It has 339 employees (as of end 2016), of which
94 are women.
OFFICIAL USE
OFFICIAL USE
The water and wastewater infrastructure in the City of Banja Luka suffers from historic
underinvestment. The poor condition of the network is also accompanied by a relatively low
connection rate of inhabitants. In this context, specifically the settlements with a high population rate
of refugees are not yet connected. Only about 20 per cent of the water supply networks have been
recently built and in the old parts of the network water losses are in places higher than 50 per cent.
Illegal connections are another issue that the Company faces, present mostly in rural areas. Users
illegally route water for uncontrolled irrigation and household use. This practice is unsafe as
inhabitants are manually diverting water supplies, which compromises system performance.
The existing drinking water system consists of groundwater wells, water treatment plants, storage and
distribution pipework. It is understood that there is sufficient water supply to meet water demand for
the foreseeable future provided that the system losses are addressed. The drinking water distribution
network length is 830 km. During 2016, the Company produced and distributed 27.3 million m3 of
drinking water, of which 17.2 million m3 was charged to consumers. Non-Revenue Water (“NRW”) is
37.0 per cent of the water put into distribution. The Company has managed to achieve improvements
of 2.1 per cent reduction of water losses over the 2014- 2016 period, and for further improvements the
company should ideally progress to its economic level of leakage, addressing both physical and
commercial losses.
The wastewater system is underdeveloped: the wastewater collection network currently covers
approximately 60 per cent of inhabitants of the City with many individual households connected to
septic tanks, where many of these tanks are sub-standard. The City has no centralised wastewater
treatment plant and the wastewater collected is discharged into the rivers Vrbanja and Vrbas untreated.
Septic waste collection is poorly managed with little arriving at designated sanitary landfill sites.
Whilst the lack of formal wastewater treatment of sewage is not unusual for the country it causes
environmental and social harm and needs to be addressed. The scale and impact of this harm is
unknown and may be exacerbated with increased water and wastewater connections – this will be
confirmed during technical, environmental and social due diligence. The collectors that are currently in
use date back to 1912, and they are in urgent need of rehabilitation. The wastewater system has not
followed the expansion of the water supply network and totals 397 km.
The City and the Company are preparing design documentation for the Project. Signing of the Loan is
planned in the first half of 2019 and works are planned to start in July 2019. To that effect an advanced
procurement process will be launched in the first quarter of the 2019 that is when the priority
investment components to be financed by the first tranche of the Loan are identified and confirmed by
this assignment. Design and tendering for the components that will be financed by the second tranche
of the Loan will be done in the second half of 2019.
The Bank wishes to commission a suitably qualified consultant (the “Consultant”) to prepare a detailed
Technical, Financial, and Environmental and Social Due Diligence study as well as the resilience of
the Project to climate change.
3. ASSIGNMENT OBJECTIVES
The overall objective of the assignment is to prepare and carry out Technical, Financial, and
Environmental and Social Due Diligence, which the Bank can use to appraise the Project and take a
decision on the prospective financing.
This Project will be based on an effective least cost short-term investment programme, designed on
the basis of a long-term development plan. The short-term investment plan will be justified on the
basis of thorough technical, financial and economic analysis. Furthermore, the Consultant will
develop an efficient Project Implementation Plan, including procurement schedule, and carry out an
energy saving and environmental assessment (including resource utilisation and the impact on GHG
emissions) of the short-term investment programme
Specific objectives of the assignment shall, inter alia:
OFFICIAL USE
OFFICIAL USE
Confirm the need for investment;
Identify a cost-efficient and sustainable Priority Investment Programme to be financed by the
Loan and advise on the most appropriate project implementation arrangements including
tender packaging, contracting, supervision and a need for external procurement support;
Analyse the ability of the Company to service its debt including this Loan within the
generally accepted limits for the affordability of tariffs limits;
To the extent possible:
- Assess the potential impacts of climate change on the project in order to build in resilience
to climate change related risks;
- Assess the resource efficiency opportunities (including energy and water efficiency and
waste minimisation potential and the impact on GHG emissions) on the project;
Establish the key technical, institutional and social risks that could impede project success
and identification of measures to reduce, remove or mitigate these risks;
Analyse possible options and recommend, on the least cost basis, the best solution for
collection and treatment of households and industrial wastewater as well as for the rainfall
water;
Review baseline assessment work data from the Technical DD assignment and carry out some
additional baseline data collection to assess the current situation;
Verify the project category as B under the 2014 EBRD Environmental and Social Policy
(“ESP”)1. If the Consultant considers the project category should be revised as A, they shall
immediately notify the EBRD.
Carry out an Environmental and Social Assessment (Environmental and Social Due Diligence
- ESDD) of the Project, against the 2014 ESP and associated Performance Requirements
(“PRs”), to identify its environmental and social risks, impacts and benefits and to structure
the Project to comply with the Bank's Environmental and Social Policy ("ESP") and
Procurement Policies and Rules ("PRs").
Calculate the Bank’s standard measuring indicators and GET impact indicators (Annex 2).
4. SCOPE OF WORK
In order to meet the objectives above, the Consultant shall undertake the following tasks:
(1) Baseline Study/Review/Description and Assessment of Existing Situation;
(2) Environmental and social assessment (“ESA”);
(3) Long-Term Development Plan;
(4) Short-Term Investment Programme
(5) Financial Analysis;
(6) Economic Analysis;
(7) Project Implementation Plan;
1 http://www.ebrd.com/news/publications/policies/environmental-and-social-policy-esp.html
OFFICIAL USE
OFFICIAL USE
4.1 Baseline Study/Review/Description and Assessment of Existing Situation
This task involves the review of the present management practices of the Company and status of the
water and wastewater services in the City so as to identify and assess any risks that are associated
with the Company and their existing operations. This review shall allow the Bank to better understand
the present situation in institutional, legal, financial, technical and environmental and social terms.
The Study shall also identify respective needs and concerns of different disadvantaged groups and/or
those with less voice, such as women, to be addressed in the design, implementation, and monitoring
and evaluation of the project.
The following shall, inter alia, be addressed:
4.1.1. Financial assessment
The Consultant will prepare a description and analysis of the financial position and prospects of the
Company. To this end, the Consultant will, inter alia:
A. Current financial and tax situation
i) Prepare an Income Statement, Balance Sheet, and Cash Flow Statement for the current and
previous 2 years restated in accordance with International Accounting Standards;
ii) Prepare a revenue breakdown by customer group including collection rate (overall and in
cash) presented for each customer group separately;
iii) Review the capital structure, detailed cost breakdown between different services, fixed and
variable costs for each category (personnel, electricity, materials, etc.), including an
explanation of real term increases/decreases compared to previous years, indebtedness,
sources of funds for operation and capital expenditure, degree of financial self-sufficiency;
iv) Assess the total asset value with breakdown in major categories of assets, explanation of the
latest asset revaluation (with explanation of how any such revaluations were accounted for),
confirmation of depreciation rates for the different categories of assets, calculation
methodology and assessment of the adequacy of deprecations;
v) Analyse extraordinary revenue, in particular received subsidies and proceeds from sales of
assets;
vi) Analyse extraordinary expenditures, in particular tax and other late payment penalties (basis
and amounts);
vii) Assess the current use of "profits" (Appropriations Fund and Reserve Funds);
viii) Review all rules regarding tax, VAT, duties etc. which are relevant for the investment
programme and the financial performance of participating Company.
B. Accounts receivable
i) Assess the current billing and collection system, including any plans for its development;
ii) Assess the total amount of accounts receivable, breakdown by category and age and
expressed as a percentage of annual revenues by customer groups, paying particular attention
to the amounts due and collection record of the budgetary entities (municipal, regional, and
federal – military, defence industry, education, etc.);
iii) Collate a list of all major debtors indicating their ownership, the list shall include all debtors
whose debt exceed 5 per cent of the total amount of accounts receivable, and at least the 10
largest debtors for each participating Company;
iv) Assess the scope for reduction of receivables, and the likelihood that current receivables are
collectible;
OFFICIAL USE
OFFICIAL USE
v) Identify what kind of collection methods have been used (default interest or other penalties,
judgements, threat of bankruptcy proceedings, cut-off of water supply etc.), and if these have
proved unsuccessful, evaluate why; and
vi) Review the criteria for estimating the provision to cover losses resulting from bad debts and
analysis the adequacy of bad debt provisions.
C. Liabilities
i) Analyse the total amount of debt, breakdown by category and age and expressed as
percentage of annual costs by creditor groups;
ii) Collate a list of all major creditors, the list shall include all creditors whose debt exceed 10
per cent of the total debt, and at least the 5 largest creditors for each participating Company;
iii) Identify what kind of collection methods have been used by the creditors to collect their
receivables, in particular any legal or other enforcement measures (default interest or other
penalties, judgements, threat of bankruptcy proceedings, non-delivery of supplies, employees
industrial actions etc.) and to what extent this has caused disruptions to ordinary activities of
participating Company; and
iv) Analyse wages and tax arrears.
D. Non-cash settlements
i) Analyse the extent and effects of non-cash settlements;
ii) Identify those clients whose accounts are regularly settled, directly or indirectly, through off-
setting, describe the amounts involved, whether or not settlements are made at nominal value,
regularity and mechanisms used, and identify the possible tax or other consequences;
iii) Identify the extent of barter settlements, describe amounts involved, regularity, major clients
with which barter is used, breakdown of major type of goods or services involved, how the
goods or services are evaluated, on-traded and at what prices (profit or loss), and identify the
possible tax or other consequences hereof; and
iv) Identify the extent of tax settlements with all levels of government: municipal, regional,
federal, identify regularity and amounts involved.
E. Conclusion
Based on the conclusions from the sub-tasks outlined above the Consultant shall prepare a summary
which will conclude on at least the following points: financial standing of the Company (s); level of
costs and operational efficiency; and adequacy of current tariff level.
4.1.2. Institutional and legal assessment
The Consultant will assess the present legal status of the Company and the institutional framework in
which it operates. To this end, the Consultant will, inter alia:
i) Identify the respective roles of central, regional, and local authorities in financing and
management including for example: the method and responsibilities for setting of tariffs; the
regulatory responsibilities of various organisations that exist and the nature of their
relationship with the Company. As a part of this work the Consultant shall collect, translate
(the relevant parts) and outline the main contents of relevant laws and regulations governing
these relations.
ii) Analyse the relationship between the Company and the City. This analysis shall include a
specification of the rights and responsibilities of Company and to what extent it operates at an
“arms-length” basis from the City (i.e. are the objectives of the Company clearly defined, to
which extend does it operate flexibly and freely in pursuit of those objectives, and the degree
of accountability that characterises the relationship). Describe the legal status of the Company
and present the statutory documents in English.
OFFICIAL USE
OFFICIAL USE
iii) Assess and update the relationship between the Company and owner (City), and in particular
how the owner governs the Company, including the role of the General Director, if
applicable, and formal and informal ways of influencing the Company by the owner.
iv) Assess and update the ownership of the Company and the Company assets, and identify to
what extent the ownership will affect the implementation of the Project
v) Update the legal and institutional framework governing the status and operations of the
Company (legislation, statutes, service agreement etc.) and define, if any changes needed.
vi) Identify any legal requirements for the implementation of the Project.
vii) Assess and update the efficiency of the existing organisational structure and identify what
changes are needed
viii) Assess and update the influence from applicable legislation on the Company’s
operations, particularly any price regulation mechanisms (e.g. tariff regulation), and identify
legal requirements influencing the implementation of the investment programme
ix) Identify legal/political issues or problems, which would prevent the Company from evolving
into the autonomous Company (including specifically the creation of a joint stock Company)
or outsourcing non-core business. Consider specifically issues related to ownership and
control of assets, the establishment of tariffs, management independence, investment and
personnel decisions, etc.
x) Identify shortcomings of the current organisational/institutional framework and make
recommendations how to enhance them.
xi) Identify shortcoming of the current governance structure, and propose feasible improvements
in the medium term.
xii) Recommend reasonable loan covenants and implementation timing in this area.
xiii) Identify which stakeholders (non-governmental organisations, academic community,
donors, local experts, the media, users’ groups, etc.) are working on issues related to water
supply broadly and more specifically, on sustainable water supply/sanitation, gender equality
goals and access-related questions.
xiv) Assess and update the linkages developed with stakeholders in original FSTechnical DD, such
as with women’s groups, in order to incorporate their concerns into the Project, so as to
improve communication, information and services and to better reach out to women or other
user groups.
xv) Assess and update interactions between the management of the Company and representatives
of consumer groups and other stakeholders.
4.1.3. Operational efficiency assessment
The Consultant shall make an assessment of the financial and operational efficiency of the Company,
and in particular identify areas where cost savings could be achieved through planning,
rationalisation, system development, more efficient resource use and separation of non-core-
activities. In addition to key areas, such as collection performance and unit electricity costs covered in
other tasks, the Consultant will, inter alia:
i) Assess the organisational structure and management: number, number and percentage of
women and men in total staff count as well as across all levels/categories, skills and attributes
of employees; human resources development policies and practices, including training and
incentive schemes (identify any potential employment opportunities for women as part of the
new services to be offered, if applicable); appropriateness of the organisational structure;
operation of major departments or groups identified on the existing table of organisation;
policies and practices relative to strategic planning, project preparation and implementation,
operational planning and control, allocation of tasks, supervision of task execution, and
related matters.
OFFICIAL USE
OFFICIAL USE
ii) Assess the administrative systems and procedures: customer service, accounting and record
keeping, personnel management and training programs, financial record keeping, financial
planning and management, investment planning and execution, and management information
system and related matters.
iii) Define relevant benchmarks of operational efficiency of the Company (such as Infrastructure
Leakage Index, non-revenue water, number of connections per employee, number of residents
served per employee, level of breakdowns, response time for breakdown/accident reporting,
number of administrative staff, resource use per unit of output etc.. Comparison should be
made with best practice from other comparable cases.
iv) Assess operation and maintenance (O&M) of assets: methods, policies, and procedures
relating to the operation and maintenance of facilities, including support systems such as
repair facilities and spare parts inventories, existence of preventive maintenance programs,
meter management, monitoring of energy use, system information and mapping, and other
matters relating to O&M. As a result of such assessment the Consultant shall identify
measures of efficiency improvements which will lead to substantial reduction of operating
costs.
4.1.4. Demand and affordability assessment/Socio-Economic data
A. General
Based on 3-5 years of historical data and information readily available (Consultant’s reports, data
generated by City, Republika Srpska institutions etc.) the Consultant will compile and present socio-
economic data of relevance to the project including, inter alia:
i) population data including historical development (number of people, general spatial
distribution, in and out migration, minority and vulnerable groups, etc), trends, growth rates,
and review of proposed municipal development plans to obtain basis for population
projections;
ii) Update sex disaggregated data on household incomes and expenditures, including income and
expenditures per decile, household sizes, number of breadwinners, average expenditures for
essential goods, profile and geographic distribution of poverty, percentage of single-headed
households, people living with disabilities, war veterans, and any other circumstances, etc
iii) household incomes, household sizes, number of breadwinners, average expenditures for
essential goods etc.;
iv) Update an overview of consumption behaviour of the City, particularly water consumption
and level of awareness on efficient water use;
v) health information, with regard to mortality and morbidity associated with water borne
diseases;
vi) Update health information with regard to any adverse health effects related to the lack of or
insufficient quality of water and wastewater services disaggregated by sex and other relevant
socio-economic and demographic variables.
B. Affordability
Update the affordability analysis in consultation with the EBRD’s Office of Chief Economist. The
affordability analysis will be based on desktop research and available data.
The Consultant will establish at which levels tariffs would be affordable to customers without causing
a socially or politically unacceptable financial strain.
It is recognised that the tariff adjustments required for the realisation of the Project can only be
determined in detail at a later stage of project preparation, but the Consultant should gain a clear
understanding of the limits of affordability as early as possible.
For example, if the data is available, the Consultant shall examine differences in the affordability to
pay for the services by different socio-demographic groups at both individual and household level (i.e.
OFFICIAL USE
OFFICIAL USE
females and males; single-headed households, elderly; people living with disabilities, ethnic
minorities and vulnerable groups in the community) and reflect them in the affordability analysis and
the assessment. The Consultant should follow EBRD methodology on affordability analysis and
assess and comment on the current social safety nets covering minimum water consumption of
vulnerable households and households with specific needs
The Consultant will design and implement a survey instrument, which will provide data to assess the
affordability and willingness to pay of both domestic and industrial customers taking into account the
improved services and current customer perception of service quality. On the basis of this survey, and
by other means, such as interviews and focus groups, the Consultant will:
i) Assess the level of tariffs that would be affordable for domestic customers, particularly mid
and low level income households. Document and explain the research and analyses carried
out that support the opinions offered and state methodological assumptions. Examine the
issues over the life of the project, making assumptions about how real income will increase,
how attitudes may change, etc. Present comparisons with other countries/cities.
ii) Evaluate whether non-residential users have any particular reason to object to the new tariff
levels. Assess whether there could be any impact on industrial or business location decisions.
iii) Assess whether there are other factors that could lead to serious objections by users, City
officials or politicians, or particular interest groups.
C. Tariff Setting and Subsidy Payment Policy
The tariff setting and subsidy payment policy for the water and wastewater services during the
financing period is a fundamental issue. The long term financial health of municipal utilities is
partially reliant upon: (i) a tariff setting formula/ methodology that allows for the recovery of all
recurrent costs including capital investment costs; (ii) adequate billing and collection practices; and
(iii) receipt of adequate subsidy payments when consumer tariffs are below cost recovery levels.
The Consultant will evaluate current tariff setting and subsidy payment policies, and recommend
improvements. To this end, the Consultant will, inter alia,
i) examine the current billing and collection methodologies and prepare recommendations on
further improvements in accordance with industry best practices;
ii) evaluate the current tariff by consumer groups and business lines, to determine to what extent
all recurrent costs are included;
iii) recommend changes to the tariff setting formulae that ensure that the benefits associated with
gains in efficiency are shared between the Company and customers in an equitable and
transparent manner;
iv) Evaluate and update the degree of receivables by consumer groups and suggest the solutions
to reduce them if necessary
v) identify any cross subsidies and establish a plan for the orderly phasing-out of cross-subsidies
over a three to four year period, ensuring that customer tariffs remain affordable;
vi) describe the mechanism for the calculation and payment of subsidies (if relevant) and make
recommendations for the implementation of any formula or operational changes;
vii) Identify what the Bank should require for the Bank financed project (with specific timing);
viii) Identify any protection mechanisms available to the most vulnerable decile of the
population regarding payment of utility bills;
ix) Recommend reasonable loan covenants and implementation timing in this area.
4.1.5. Technical evaluation of municipal service infrastructure
The Consultant will evaluate the current technical quality and quality of service provision. To this
end, the Consultant will:
OFFICIAL USE
OFFICIAL USE
A. Service characteristic assessment
Describe and assess the key attributes of the current service and the service development over the last
3 years, including inter alia:
i) Service area: physical, administrative and political delineation
ii) Customers: number of customers and people served by category, i.e. domestic, industrial,
commercial, official, public etc.
iii) Quality of service: provided in terms of water availability, from water resources resilience to
customers (pressure, reliability) using Water quality monitoring: practices and standards.
B. Infrastructure evaluation
Assess the Company infrastructure and equipment components in terms of capacity, energy
efficiency, performance, state of repair, maintenance practices, age, quality of materials and
equipment, adequacy and environmental impact.
In each case, the Consultant will identify opportunities for improvements in technical efficiency
through the use of alternative technologies and/or infrastructure solutions.
4.1.6. Resource Use
i) Identify the main physical raw materials or resources used in providing services (i.e., natural
gas, oil or coal for heat, electricity for pumping etc.) and show monthly consumption of each
for the previous 2 year period;
ii) Indicate comparative values of material or resource input required to provide similar service
levels according to reasonable standards of international best practice for similar operations;
iii) Indicate levels of material or resource savings which may be anticipated as a result of meeting
such standards of international best practice for similar operations (expressed in terms of
gross savings and savings per unit of output); and
iv) Ensure the relevant data in the Resource Utilisation and GHG Emissions Table is completed
(See Attachment 1).
4.1.7. GHG emission assessment
i) Assessment of GHG emissions associated to the operations including identification of main
source of emissions;
ii) If applicable, indication of allocation of CO2 emission allowance (as per EU ETS) and
estimated costs associated to comply with such allocation and the provisions of the EU ETS;
and
iii) Ensure the relevant data in the Resource Utilisation and GHG Emissions Table is completed
(See Attachment 1).
4.1.8. Resilience to climate change
The baseline study should take account of the current climatic conditions and projected climate
change in so far as they have the potential to affect water supply and wastewater discharges.
i) The Consultant shall compile readily available data on existing climate conditions using
reliable sources such as the IPPC Data Distribution Centre, the Royal Netherlands
Meteorological Institute (“KNMI”) and other sources as appropriate;
ii) The Consultant shall collate and analyse future climate projections from Global Climate
Models (“GCM”) using readily available information from reliable sources, e.g. Climate
Wizard (www.climatewizard.org) and from Bosnia and Herzegovina’s Second National
Communication to the UNFCCC;
iii) The Consultant shall analyse the collated data, determine the risks associated with climate
change and advise on the level of confidence associated with climate change projects and the
implications for the project.
OFFICIAL USE
OFFICIAL USE
iv) The Consultant shall assess the implications of climate change arising from analysis of this
data including:
Rising temperatures leading to the melting of glaciers and consequent impact of river
systems and flows.
Adequacy of and changes in water supply (both surface water and groundwater).
Drinking water quality.
Power supply, energy availability and energy costs.
Asset protection and maintenance.
Water demand and changes in demand, e.g. increased demand due to more extreme heat
days.
Please refer to Annex 0 for additional information on sourcing data on climate change projections.
Please also note that the time period for assessing risk is the lifetime of the project and not just the
lifetime of the loan.
4.2 Environmental and social assessment (“ESA”)
Prior to undertaking the environmental and social assessment, the Consultant is required to confirm
the scope of PIP and screen the Project proposal against the EBRD’s Environmental and Social2
Policy (“ESP”)3 and associated Performance Requirements (“PRs”) to confirm the project category (A
or B). New large-scale groundwater abstraction activities exceeding 10 million cubic metres annually,
or greenfield Waste Water Treatment Plants (WWTPs) of the capacity over 150,000 PE (or major
expansions of the existing WWTPs by over that amount) are typically categorised as A, while
upgrades of the existing water and wastewater facilities and networks are typically categorised as B.
The results of the screening and the Project category will need to be discussed and agreed with
the EBRD (ESD) prior to proceeding with E&S Assessment task.
The scope of work described below is applicable to a typical brownfield category B project, which is
the most typical of assignments in the water/wastewater sector. Should the Project proposal (PIP)
involve any Category A components, the terms of reference for the ESA will be revised by the EBRD
to include an Environmental and Social Impact Assessment (“ESIA”) in line with the ESP. The
revised ToR will be agreed with the Consultant together with the necessary cost implications.
Objectives of the E&S Assessment
The objective of the E&S Assessment is to identify and assess the potentially significant existing and
future adverse environmental and social impacts associated with the Client’s current operations and
the proposed Project, assess compliance with applicable laws and the EBRD ESP and PRs, determine
the measures needed to prevent or minimise and mitigate the adverse impacts, and identify potential
environmental and social opportunities, including those that would improve the environmental and
social sustainability of the Project and/or the associated current operations.
The assessment process will be commensurate with, and proportional to, the potential impacts and
issues of the Project and the Client’s existing operations. The assessment will cover, in an integrated
way, all relevant direct, indirect and cumulative environmental and social risks, impacts and benefits
of the Client’s operations, the Project and the relevant stages of the project cycle (e.g. pre-
construction, construction, operation, and decommissioning or closure and reinstatement).
2 The ESP (2014) defines social as “those issues which pertain to project-affected people and their communities and workers
and related to socioeconomic status, vulnerability, gender identity, human rights, sexual orientation, cultural heritage, labour
and working conditions, health and safety and participation in decision making”. 3 Available at http://www.ebrd.com/downloads/research/policies/esp-final.pdf
OFFICIAL USE
OFFICIAL USE
An Environmental and Social Audit (as defined in Section Error! Reference source not found.3) is
required to assess the Client’s current operations in terms of compliance with national legislation,
national or local permitting requirements, the relevant provisions of the EBRD Environmental and
Social Policy and Performance Requirements (2014), including EU environmental standards. Further,
the audit must review possible historical environmental and social issues, such as potential
contamination of soil and/or groundwater or land acquisition disputes.
The Environmental and Social Assessment (as defined in Section 4.2.4) will also determine whether
further studies are required, focusing on specific risks and impacts, such as climate change,
resettlement, retrenchment, biodiversity, human rights and / or gender.
Specifically, the Consultant will:
Identify existing and Project-related environmental and social impacts and risks.
Describe and characterise a relevant environmental and social baseline commensurate with
the risks posed by the current site operations and the Project.
Assess potential gender aspects and priorities among nearby communities to understand
women and men’s concerns (e.g. determine women’s current activity schedules/ water use
practices, attitudes towards public health etc.).
Carry out E&S Assessment and Audit and develop a draft E&S Assessment report in
accordance with the Bank’s requirements as defined in the ESP, including a Compliance
Summary table with the Bank’s PRs.
Prepare a Livelihood Restoration Framework, if needed;
Prepare a draft Stakeholder Engagement Plan (SEP), draft Environmental and Social Action
Plan (ESAP) and draft Non-Technical Summary (NTS).
Identify if any additional studies will be required to cover relevant aspects in greater detail
(e.g. biodiversity, resettlement, retrenchment, etc.). (Any such work will be commissioned
under separate Terms of Reference).
Finalise all documentation further to the EBRD, other lenders’ (if involved) and Client’s
comments.
This Terms of Reference for the E&S Assessment refer to various E&S guidance documents (e.g.
E&S Guidance 1). These are available as a separate package of E&S guidance documents.
4.2.1. Applicable requirements:
The E&S Assessment is to be carried out in accordance with:
Applicable local, national and regional requirements, including those related with ESIAs /
EIAs and associated public disclosure and consultation requirements.
The EBRD’s ESP (and the incorporated Performance Requirements (PRs)), and relevant
European Union (EU) requirements (including, but not limited to, the EU EIA Directive (as
amended), EU Drinking Water Directive (98/83/EC), EU Urban Waste Water Treatment
Directive (91/271/EEC), EU Water Framework Directive, Sewage Sludge Directive
(86/278/EEC), IE Directive etc.).
Requirements of other potential lenders, such as other International Financing Institutions
(IFIs) and commercial banks adhering to the Equator Principles4.
Relevant international conventions and protocols relating to environmental and social issues,
as transposed into national legislation.
4.2.2. Review of Available Data and Site Visit
4 Information on the Equator Principles is available at: www.equator-principles.com
OFFICIAL USE
OFFICIAL USE
The Consultant will review the following studies and baseline data available from the Client.
Data and documentation are in English and local language in use in Bosnia and Herzegovina. This list
is not exhaustive and the Consultant must be prepared to review, and also request, further
documentation that does not appear above.
Following the review of available data, the Consultant will visit the site, to obtain any supplementary
information needed to complete the E&S Assessment (Sec. 4.2.44) and carry out the on-site activities
necessary to fulfil the E&S Audit reporting requirements (Sec. Error! Reference source not
found.3).
The data review process will include a simple media search to determine whether any relevant issues
regarding the Project, Client or Beneficiary have been reported through the media and to determine
the importance of these through additional verification during the due diligence work. If no relevant
issues are identified through this process the Consultant will include a statement to this effect in its
report.
Following completion of the data review and site visit the Consultant will deliver a summary of key
findings.
4.2.3. Environmental and Social Audit
The E&S Audit is required to review the current and, to a limited extent, past operational performance
of the Client’s existing operations and facilities in terms of their compliance with relevant national
environmental laws and regulations and EBRD PRs, including relevant EU environmental standards
and guidelines. Consultant should provide cross-reference with the respective sections of the
Technical DD study, in case of any overlap.
Key issues to be covered under the E&S Audit may include, but not be limited to:
A review of the Company’s existing environmental and social management systems, policies
and practices;
Organisational capacity and resources, including description of the number of personnel;
number and percentage of women and men in total staff count as well as across all
levels/categories;
Human Resources and employment (e.g. child labour, forced labour, and non-discrimination,
workers’ organisations, contractor management, retrenchment and employment) policies;
A review of equal opportunities policies and practices in the Company; assessment of
potential employment opportunities for under-represented groups in the workplace (i.e.
women or men, people with the disabilities, different age groups, ethnic groups, etc.) and
recommendations on what measures need to be made or what policies need to be revised to
ensure equality of opportunity in the Company;
Occupational health and safety (local and national requirements, applicable EU/ international
requirement and standards, key health and safety issues, control and major accident hazards,
current health and safety monitoring programme, summary of regulatory compliance status,
summary of health and safety expenditures, emergency response etc.);
Pollution prevention measures available at both facilities and overall regulatory compliance
with national requirements and pertinent EU standards including applicable Best Available
Techniques and Best Available Techniques Reference Documents. In addition, this
assessment will need to review compliance with best international practice as a benchmark
against current operations and planned plant upgrades;
Industrial hygiene (including worker exposure, and rates of industrial diseases) and worker
health and safety;
OFFICIAL USE
OFFICIAL USE
Use and management of hazardous substances (including chlorine and other chemicals
handling);
Community health, safety and security as it relates to the Company’s existing operations;
Major hazards assessment and management; environmental management plans in the event of
an incident, accident of spill both on land and water;
Current company policy and practice in relation to avoidance of third party intrusion into
potentially hazardous areas (fences, security, personnel, others);
Management of potentially hazardous works (including excavation works, work in confined
places, etc.);
Traffic management;
Contractor management and oversight;
Waste management and waste minimisation;
Sludge management practices;
Noise and vibrations both during construction and operation of the Company’s facilities;
Other construction related impacts (aerosol emission, dust, temporary severance to traffic,
water cuts, others);
Procedures for identifying and safe handling of UXOs (unexploded ordnance);
Overview of current Client’s policy and procedures regarding land acquisition (compensation
policy, consultation activities related to land acquisition including grievance management, if
applicable);
Review the Client’s corporate procedures for assessing projects with potential biodiversity
impact;
Identification of potential past environmental liabilities which may affect the Bank (e.g. soil
and ground water contamination as a consequence of past and present operations);
Overview of the Client’s supply chain (e.g. suppliers of main materials and resources
including energy; presence of women-owned businesses) and identification of relevant
environmental, social, labour and/or reputation issues; and
Public interaction, including historical responsiveness to public comments, complaints and
questions. The audit should also identify the Company’s main stakeholder groups and current
stakeholder engagement activities in line with PR10.
Monitoring practices and results.
The Consultant will be guided by the relevant requirements of the Bank’s E&S Performance
Requirements. The findings of the E&S Audit should also be considered in the completion of the PR
compliance assessment.
4.2.4. Environmental and Social Assessment
Please note that that the environmental and social assessment should be commensurate with the
Project and its associated risks and impacts. It should be a high level assessment focusing on key
risks and impacts. A comprehensive Environmental and Social Impact Assessment of the Project is
not required. Where available the E&S assessment should refer to (and review) the local EIA done
for the Project.
Project Description & Identification of Relevant Associated Activities & Operations:
The Consultant will prepare a description of the Project including details of any alternatives5
considered for the project and information on neighbouring operations and activities. In accordance
with EBRD PR1, paragraph 9, the Consultant will identify:
Any potentially significant environmental and social issues or risks associated with relevant
other activities or facilities, which are not part of the Project but which may be directly or
5 Project alternatives to include: Zero (“no project”) alternative, siting and routing alternatives, infrastructure and traffic
connection alternatives, design alternatives
OFFICIAL USE
OFFICIAL USE
indirectly influenced by the Project, exist solely because of the Project or could present a risk
to the Project
Cumulative impacts of the Project in combination with impacts from other relevant past,
present and reasonably foreseeable developments.
Unplanned but predictable activities enabled by the Project that may occur later or at a
different location.
Environmental and social risks associated with the primary supply chains central to the
Project’s core operational functions.
Analysis of Legal Requirements
The Consultant will identify applicable local, regional and national environmental and social laws and
regulatory requirements of the jurisdictions in which the Project operates, including those laws
implementing host country obligations under international law. The Consultant will analyse
local/national assessment and permitting requirements and the EBRD environmental and social
requirements and compare them within a gap analysis in tabular format. In EU Member States,
provide copies of permitting documents issued by Competent Authorities and opine whether the EIA
screening process has met relevant EU requirements.
As required, the Consultant will identify any issues that require legal interpretations for the Bank to
raise with its legal advisors. The Consultant is not required to provide legal opinions.
The Consultant will identify, review and take into consideration any relevant strategic level
assessment documentation.
Baseline Conditions
The E&S Assessment will include a review of the aspects of the physical, biological and socio-
economic environment likely to be affected by the proposed Project. The Study shall also identify
respective needs and concerns of different disadvantaged groups and/or those with less voice, such as
women, to be addressed in the design, implementation, and monitoring and evaluation of the project.
Indicative guidance on the contents of the overall assessment is provided in E&S Guidance 1 of the
E&S guidance pack and in Annex 1 below.
The baseline assessment will include consideration of the Baseline Study in section 4.1 and the inter-
relationship between the relevant factors, as well as the exposure, vulnerability and resilience of these
factors to natural and manmade disaster risks.
Project Assessment
In accordance with the Bank’s ESP (2014), the Consultant will analyse the potential environmental
and social impacts and risks of the Project, as well as opportunities that the Project may provide,
including infrastructure development (e.g. water, wastewater, a heat and electricity distribution
networks, transportation access) and other associated facilities, for which the EBRD financing is
being sought.
The E&S Assessment will include a review of the likely effects of the proposed Project on the
physical, biological and socio-economic environment to provide an identification and characterisation
of potential E&S impacts, including beneficial (as well as adverse) impacts.
This review will be structured to include all relevant stages of the Project’s life, e.g. construction,
operation and maintenance, closure and decommissioning, and residual E&S impacts. The level of
analysis and reporting will be commensurate with the risk magnitude of the identified issues.
Indicative guidance on the contents of the overall assessment is provided in E&S Guidance 1 of the
E&S guidance pack and Annex 1 attached to this document.
OFFICIAL USE
OFFICIAL USE
As part of the Project Assessment, the Consultant will also:
Include confirmation of whether:
o the Project involves large-scale groundwater abstraction activities with abstraction
volumes exceeding 10 million cubic metres per year and are abstraction volumes are
sustainable (noting the water use, including surface water bodies);
o the Project is in line with the EU Water Framework Directive;
o the Project is in compliance with the EU Drinking Water Directive (98/83/EC);
o the capacity of the municipal wastewater treatment plants (greenfield and/or
expansions) will exceed 150,000 population equivalent;
o the project is in compliance with the Urban Wastewater Treatment Directive
(91/271/EEC), including treatment standards;
If an EIA has been prepared under the national requirements, include a summary statement of
compliance of the national EIA’s process with the EU EIA Directive, including:
o how the project was screened by the national authorities;
o which EIA procedure was followed;
o how public participation process was carried out;
o potential cumulative impacts and area of influence issues (e.g. raw material sourcing);
and,
o whether any impact on designated or identified nature conservation areas or other
sensitive areas has been identified.
Quantify the environmental benefits of the proposed investments, focusing on quantifying the
pollution reductions and cross-border environmental benefits resultant from the project. (See
Annex 2)
Assess the extent to which relevant national and European Union environmental, social,
health and safety laws, regulations and standards will be met within the framework of the
proposed investment programme.
Assess the occupational health and safety issues by the Company and its contractors
undertaking the Project related works, including employees and workers exposure to noise,
dust, electricity, physical and other risks during modernization and refurbishment works.
Assess public safety and security issues and the impacts on stakeholders. This should include
an assessment of potential gender-specific health and security issues and impacts (i.e. impacts
during construction and maintenance phase of the service, temporary or permanent disruption
of the service, timetable of the provision of water, safety concerns of accessing the water
supply depending on the water supply system/location and any other security aspects (for
example, an increase of male workers in the area, which may lead to an increase in the risk of
harassment and assaults).
Assess community health, safety and security risks and benefits, including traffic
management and potential nuisance to local community during both construction and
operation of the Project.
Assess whether or not the proposed investment programme would disproportionally affect
women and identify any opportunities to specifically address their needs and concerns so as
to enable them to benefit to an even greater extent from project activities.
In case resettlement or displacement is anticipated, the Resettlement Action Plan and
Livelihood Restoration Plan shall provide provisions to compensate women as well as men
for loss of livelihood, address gender issues in planning and executing the resettlement
throughout the whole resettlement process (consultation and participation, resettlement
planning, and resettlement and rehabilitation) in line with PR5.
Verify and confirm to the Bank whether categorisation as “B” for the Project is correct.
The Bank has previously identified high rates of worker accidents on water and waste water projects,
which are associated with excavations, working in confined spaces and the movement of vehicles and
mobile plant. Therefore the consultant shall pay particular attention during E&S assessment to the
capacity and competency of the company to manage risks associated with these hazards, comparing
them against good internal practice.
OFFICIAL USE
OFFICIAL USE
In addition to mentioned above the Consultant is required to perform the Energy Saving Analysis to
estimate the savings in energy consumption and Greenhouse Gas (GHG) emissions reduction
resulting from reduced energy consumption of the upgraded system components, and the implications
for GHG emissions (positive and/or negative) of any changes in the way waste water and sewage
sludge are treated. EBRD’s methodology for the quantification of GHGs is recommended for use (see
the EBRD’s website for details6).
Management of Impacts and Issues
For each identified adverse future impact, issue and/or risk, the Consultant will propose measures to
avoid, minimise, mitigate or compensate for them.
EBRD PR Compliance Assessment
Based on the results of the E&S Assessment, the Consultant shall evaluate the compliance status of
the Project with the EBRD PRs using the format provided in E&S Guidance 2 of the E&S guidance
pack. Note that the compliance assessment should also take into consideration the findings of the E&S
Audit (Sec. Error! Reference source not found.3)
4.3 Long-Term Development Plan
The Consultant will develop an affordable, least cost strategic investment programme for the
forthcoming 15 years. This plan will outline the general development direction and determine the
basic polices and parameters which will lead to least cost improvements within financial constraints.
4.3.1. Service objectives, standards and policies The Consultant will, if necessary, revise present service objectives, policies, planning criteria and
design parameters, standards and specifications. The Consultant shall propose policies and criteria,
which will guide later planning and design effort. These shall be discussed and agreed with the
Company, and other agencies concerned. In conclusion, the Consultant will, inter alia:
a) Define the service area in view of political, administrative and technical criteria;
b) Estimate projections of population and broad trends in its spatial distribution in the service area;
c) Estimate projections of industrial development as it pertains to municipal service development.
d) Define norms and standards
e) Estimate future service demand projections.
f) Define future sector development policies, including performance objectives over time.
4.3.2. Long-term investment programme – water Different potential investment strategies or options shall be broadly outlined (and tentative cost
estimates prepared) including at least: (i) a minimum cost facilities rehabilitation strategy (to maintain
the increased level of service/repair established by the project); and (ii) outline of strategic
development plans including improvement, rehabilitation and expansion over the next 15 years with a
view to meeting the criteria developed in Section 4.2.1.
The preferred option will be selected on the basis of both financial and technical criteria, and be
further developed into the long-term investment programme. For this programme, the Consultant shall
6 EBRD’s GHG Assessment Methodology can be found at
http://www.ebrd.com/downloads/about/sustainability/ghgguide.pdf
OFFICIAL USE
OFFICIAL USE
summarise in appropriate maps the location, capacity, and staging of major infrastructure components
and to explain and justify the proposed course of action.
Particular attention shall be given to:
a) existing facilities and studies and projects already prepared including their consistency with
national and EU norms on drinking water quality;
b) examining alternative solutions within the context of existing system configuration and capacities;
c) the rehabilitation, repair and upgrading of existing facilities and operational improvements;
d) the scope for improved resource and raw material ustilisation through both efficiency
improvements and (where possible) use of renewable energy sources (e.g. biogas generation and
utilisation)
e) measures aimed to control and reduce GHG emissions associated to the operations
f) least cost staging/phasing of system expansions;
g) maintenance and operation implications, specifically the effect of expected increases in the costs of
electricity and gas; and
h) effects of conservation (demand management) and loss reductions on future system capacity
requirements.
4.3.3. Long-term investment programme – waste water
Wastewater services:
Taking into consideration studies carried out earlier (by the Company and others) and other
information available, the Consultant shall compile, present and interpret data and information,
covering the past three years, on service characteristics, including:
Service area: physical and administrative delineation;
Connections: number of wastewater connections by user category, i.e. domestic (number of
people served by the wastewater network), domestic (number of people served by septic tanks),
industrial, commercial, official, public, etc.
Establish the extent of foul only and combined (foul and surface water) systems present and the
proportion of connections to both
Wastewater flows and characteristics: total and per capita flows, diurnal variation, solids and
organic loadings or other important characteristics of strength of wastewater, if important,
distinguish between industrial and other wastewater sources (such as tankered waste),
determination of relationships between dry weather and wet weather flows for combined
systems, frequency and magnitude of storm water overflows and water bodies to which they
flow, and degree of infiltration within the sewer network and/or exfiltration.
Industrial wastewater: description of wastewater flows from the main industrial sources in
terms of flow volumes and chemical/physical characteristics with special emphasis on
toxic/hazardous materials discharged into the municipal wastewater collection system if
information is available.7
Description of monitoring of wastewater flows and quality: description of standards and
practices used. Establish an overall view of the current flow metering accuracy (+/-x per cent).
Wastewater Collection Systems:
7 The description will be based on available data, the time schedule and budget do not allow survey or production of new
data.
OFFICIAL USE
OFFICIAL USE
Taking into consideration information available, the Consultant shall describe and assess the present
wastewater collection system, including:
Preparation of an overview of existing systems and facilities, including area served, length,
diameter and type of main sewers, whether separate or combined, pump stations, discharge
points and storm water overflows, location of major wastewater contributors (industry). Present
schematic (please, note that detailed configuration map might not be available to the Consultant
due to current security regulation in Bosnia. the Bosnia), and identify scale and possible
implications for environmental pollution in areas not connected to a wastewater network. .
Assessment of main system components: capacity, performance (including total and unitary
energy consumption kWh/m3), state of repair, reliability (blockages per km, sewer collapses per
km, number of serious pollution incidents from overflows, properties internally flooded),
adequacy, operational maintenance practices, age, remaining asset life and quality of materials
and equipment (pipes, valves, pumps, etc.), and infiltration/inflow.
The Consultant shall provide an opinion on the operational performance (effectual drainage) of
the wastewater collection network including relief points based on the evidence acquired. The
Consultant's view will be supplemented with information provided from relevant site visits and
interviews with the operating personnel and taking account of customer contacts.8
Wastewater Treatment, Sludge Management and Disposal
The City of Banja Luka does not have any wastewater treatment facilities. Untreated wastewater from
the network is usually disposed in the nearest recipient and it all eventually ends up the River Vrbas.
Taking into account the information collected about the morphology and geology of the service area,
the quantities and qualities of foul and surface water, the current type of the wastewater network and
the percentage of population coverage the consultant will recommend the most appropriate, least cost
solution for wastewater collection and treatment for the city of Banja Luka. The analyses will include
discussion whether one large WWTP would be more cost efficient or a number of smaller WWTPs.
For each case the consultant will compare at least two wastewater treatment processes and also advise
on the most appropriate sludge treatment and disposal solution. The wastewater collection, its
treatment including wastewater sludge handling shall be compliant with national and EU norms. The
costs that would be compared must include investment cost (in the network and the WWTP(s)) and
the operating costs (including maintenance and depreciation) during the 25 years period. The
consultant will compare the NPV of various options using appropriate discount rate.
The consultant will gather information and present good and bad examples from wider region with
similar climate condition
The consultant will further describe and assess:
Description of applicable laws and regulations concerning wastewater treatment and sludge
disposal: institutional responsibilities and interdependencies (local and regional governments),
including incentives (fees and fines) levied ;
Assess conditions of the effluent receiving water bodies (including River Sava)
Assess the impact of treated and untreated wastewater disposal and storm water overflows have
on the water quality of the receiving waterbody and downstream with special emphasis on
industrial hazardous and toxic waste products and analyse compliance with applicable ambient
water quality standards, effluent standards and applicable regulations.
Assess alternative solutions for treatment, transport and disposal of sludge if appropriate.
Assess whether the recovery of nutrients in sludge is technologically and economically feasible
and applicable in the Country.
8 Hydraulic modelling will not be included, since the time schedule and budget do not allow sufficient modelling with
calibration, and simple modelling without calibration will not give added value to the study.
OFFICIAL USE
OFFICIAL USE
Analyse the utilisation of reclaimed waste water for irrigation and other likely purposes in
terms of technical and economic aspects and associated environmental and social risks with it.
Present regulatory status for the utilisation of reclaimed waste water.
Assess anaerobic stabilization of sludge and utilisation of waste methane for the generation of
heat or electricity and utilisation of digestate as fertilizer.
The Consultant will identify opportunities for improvements in technical efficiency through the use of
alternative technologies (including energy and water efficiency solutions, resource recovery) and/or
infrastructure solutions (such as rationalising assets). In addition the consultant will give an opinion
on:
The robustness of existing infrastructure repair and renewal programmes including a view of
the balance between proactive and reactive capital maintenance practices
The quality and completeness of asset inventories, asset condition and performance and the
systems used to record, retrieve, monitor and analyse this information
The competency of current asset management practices
4.3.4. Long-term institutional development options
The Consultant will provide a plan for institutional development, with the aim of the Company
moving towards a fully commercial entity. This plan should include intermediate options, for
example, making use of performance based service contracts, and/or management contracts. The plan
should take into account the abilities of the local private sector in the sector.
4.4 Short-Term Investment Programme
On the basis of the long-term investment programme identified above and other information available
the Consultant shall propose, justify and develop in more technical detail a short –term investment
programme for the forthcoming 2 years. This investment programme should be a bankable project,
which the EBRD is able to finance.
4.4.1. Propose and justify the short-term investment programme
The short-term investment programme shall be oriented towards maximisation of operational cost
savings and improved operational efficiency of the Company (including improved energy use and
reduced GHG emissions), improving and sustaining an improved service standard. The selection of all
project components must be clearly explained and justified within the context of the outlined strategic
long-term investment programme and the budget proposed. The Consultant shall also propose a
staging/phasing approach to deal with the issue of possible further budget constraints due to decreased
affordability. Project components shall be shown to be part of least cost solutions (in terms of capital
as well as operation and maintenance costs) in conjunction with an acceptable technical standard (in
terms of quality and reliability).
4.4.2. Detailed Programme Description and Cost Estimates
For each of the sub-components selected, reasonable estimates of quantities and costs (with an error
margin not exceeding 15per cent based on preliminary engineering designs and on applicable previous
bidding experience in the country) shall be prepared. Potential cost savings upon implementation of
the project should be identified and estimated. Operational costs review shall be prepared and costs
are specified among fixed and variable for each sub-component. Project sub-components shall be
designed in a way to minimise foreign currency requirements in operation and maintenance costs
(However, this should not happen at the expense of quality and reliability of services).
OFFICIAL USE
OFFICIAL USE
It is important that due care is shown in preparation of these cost estimates. Taxes, duties, technical
and financial contingencies are to be considered and specified. Financial contingencies are to be
calculated based on an investment schedule translating the implementation schedule (see below) into
investment figures (on a semi-annual basis). Foreign and local costs are to be specified.
4.4.3 Resources and Materials Savings Summary
A detailed breakdown of anticipated savings in resources and raw materials resulting from the
proposed short term investment programme will be prepared. This will refer and compare to the best
practice performance standards identified in Section 4.1.1 (E) above and will also indicate further
savings, if any, anticipated through implementation of the full long term investment programme
described in Section 4.2.2. The anticipated resource savings will be summarised in the Resource
Utilisation and GHG Emissions Table provided as Attachment 1.
4.5 Financial Analysis
The purpose of this task is to confirm that the water Company will have the financial capacity to fully
support the short term investment programme (the project), and the least-cost long-term investment
programme, and thus to demonstrate the financial viability of the project.
The financial viability of the enterprises and the project must be demonstrated by means of financial
projections over the lifetime of the loan. The projections shall be fully consistent with the long-term
development plan and be based on prudent assumptions on the Company’s revenues and expenditures.
Financial projections shall include annual balance sheets, income and cash flow statements. The
model shall be prepared to accommodate variations in the real exchange rate. The model shall address
the issue of tradable vs. non-tradable costs and fixed vs. variable costs. The Bank will provide
forecasts for inflation and exchange rates to be used by the Consultant.
Financial viability requires that the finances of the enterprise, including the financing plan for the
project will be balanced at all times over the project execution period i.e. operational revenues and
contributions must be sufficient to finance all operation and maintenance costs, debt service
obligations etc. The financial IRR and debt service cover ratio for the bank’s loan shall be calculated.
For planning purposes, it shall be assumed that the Project will be financed partly from the internal
cash generation of the Company, partly from contributions from other local sources (if any) and partly
from loans from the Bank and/or other co-financiers. The Bank staff will provide co-ordination in
putting together a feasible financing plan for the Project.
It is likely that tariff levels will have to increase over the project implementation period. The financial
model shall be used to model alternative tariff scenarios and determine an appropriate tariff
adjustment policy, which will ensure the financial viability of the enterprise and give sufficient
comfort to providers of finance. In order to assess the affordability of the project the Consultant shall
calculate the projected tariff affordability ratio and discuss the affordability of the assumed household
and industrial tariffs. It should be noted that balancing on one hand the size of the project and on the
other hand the required increase of tariffs would involve alternative scenarios and iteration.
The financial analysis shall include a calculation and discussion of sensitivity to changes in key
income and expenditure variables, including foreign exchange and interest rates, and assess the risks
for the Company. The Consultants will identify key variables to which the financial status of the
Company is sensitive. In consultation with the EBRD over their scope, a range of scenarios shall be
developed in order to test the sensitivity of the project to changes in key assumptions underlying these
variables.
The model and all its assumptions will be discussed in detail with the Company and the City. The
model shall be constructed in such a way so as to facilitate the explanation of the model.
OFFICIAL USE
OFFICIAL USE
4.6 Economic Analysis
The Consultant will assess the economic cost-benefit of the proposed components to be financed via
the project. The analysis should identify any quantifiable economic benefits and estimate non-
quantifiable benefits to obtain an economic internal rate of return calculation for the project.
Consultant should allocate a limited amount of staff resources and time to this component.
4.7 Project Implementation Plan
The Consultant shall prepare a Project Implementation Plan (PIP) for the Project, which will cover all
aspects of Project implementation, and include, inter alia:
Project programme - a detailed Project programme (using appropriate presentation format: e.g.
linked activity programmes, etc.) for completion of the whole Project - showing all activities and
key events for design, approvals, construction, commissioning, completion, etc.
Project budget - a detailed cost budget for the whole Project. This will be based on existing
proposals of cost estimates.
Procurement - a procurement and expediting plan. This will take into account the procurement
rules of EBRD. The plan shall be organised so as to minimise the number of contracts.
Project risk matrix - a risk matrix outlining the key challenges and risks associated with the
Project and the measures proposed to deal with them.Project institutional plan – a proposal on
how to address the key shortcomings identified in the institutional framework. This will include
appropriate incentive structures, and any contractual agreements required. Consideration should
be given to effective regulation and monitoring of the sector
5. IMPLEMENTATION ARRANGEMENTS AND DELIVERABLES
The duration of the assignment will be 12-14 weeks. The Consultant shall report to the EBRD whilst
liaising with representatives of the Company and the City.
The Company will provide the Consultant with working space, necessary furniture and telephone
connections.
The Company will designate senior officials (or the Head of PIU) to be the primary contact persons
with specific responsibility for assisting the Consultant and co-ordinating activities.
The Company will make available all of their records, plans, reports, designs and other documents as
appropriate, but it will be the responsibility of the Consultant to translate these documents, if
necessary.
The Company will provide access to all of their facilities and employees for questioning or assistance
relative to an understanding of the functioning of system facilities.
The Consultant shall be responsible for paying for all international telephone connections, office
supplies, external printing. The Consultant shall pay for all local transportation required by the
Consultant’s staff throughout the duration of the assignment.
The Consultant shall be responsible for providing suitably qualified interpreters/translators to work
with their staff.
OFFICIAL USE
OFFICIAL USE
5.1 Reporting
The Consultant will report to the EBRD. The Consultant shall produce in the course of the assignment
the following reports:
Inception Report: Within 2 weeks of the assignment commencement, and following the site
visit, initial data review and initial opinion as to a project proposal, the Consultant shall
present to the Bank an Inception Report presenting the initial findings, with an emphasis on
findings having an impact on the time schedule and factors affecting these Terms of
Reference. The Bank will provide comments on the inception report to the Consultant.
Draft E&S Assessment report: The Consultant shall submit, also within 8 weeks from the
Assignment Start Date, to the Bank
o Draft Environmental and Social Audit and Assessment Report, which includes a PR
compliance table (see E&S Guidance 1 & 2 of the E&S guidance pack and Annex 1b
below) – within 10 weeks of the Assignment Start Date
o Draft Environmental and Social Action Plan (ESAP) (see E&S Guidance 3 of the
E&S guidance pack) - within 10 weeks of the Assignment Start Date
o Draft Stakeholder Engagement Plan (SEP) (see E&S Guidance 4 of the E&S
guidance pack) – within 10 weeks of the Assignment Start Date
o Draft Non-Technical Summary (NTS) for disclosure to the public (see E&S Guidance
5 of the E&S guidance pack) – within 10 weeks of the Assignment Start Date
o Draft Resettlement-Livelihood Restoration Framework (R-LRF)
The Consultant shall distribute the Draft E&S Assessment report package to the Bank, the Company
and the City for comments and shall organise a joint meeting to present the Report (“Presentation”)
with all parties in the City within 2 weeks after distribution of the Report.
Three copies of all reports in English/local language in use in Bosnia and Herzegovina are required.
All parts of the report in English and local language in use in Bosnia and Herzegovina shall also be
provided in electronic-readable format, in both Word and PDF. Supporting data in the local language
in use in Bosnia and Herzegovina in the appendices need not be translated for English versions of the
documents.
NB: The Consultant will remain available for any further clarifications or questions and, if necessary,
further revisions – as required, at least until the project (or its respective Phase/Tranche) has passed
the EBRD Board and the ESAP with any changes and additional corresponding plans has been agreed
with the Client.
5.2 Steering Committee
The Consultant will organise the following Steering Committee meetings:
i) Inception meeting – this meeting will be held at the outset of the assignment to discuss the
overall implementation of the assignment;
ii) Mid-term meeting – this meeting will be held following the completion of the description of the
existing situation (Task 4.1) and draft long-term development plan (Task 4.2);
iii) Final meeting – this meeting will held following the completion of all tasks, and the delivery of
the draft final report.
5.3 Donor visibility
OFFICIAL USE
OFFICIAL USE
Given the assignment is funded through the EBRD’s donor funded technical cooperation programme,
the Consultant will be required to support the Client to ensure visibility of these resources. Support on
these visibility aspects can be obtained from the Bank’s Communications Department. Measures
could include but not be limited to:
All documents produced by the Consultant should mention donor support and bear the logo of
the donor, when appropriate.
Donor support to the project should be acknowledged in any public communication (press
releases, launch of facilities).
Local representatives of donors should be invited to any public event organised to promote
the project (press conferences, inaugurations, possibly stakeholder participation programmes).
5.4 Facilities for the Consultant, and access to information
The Company (or the City) will provide furnished and services office accommodation for the
Consultant, plus suitable office space for meetings. The City will also provide access to all relevant
information, maps, studies, models, legal documents etc. at no cost to the Consultants. The City (or
the City) will deliver the materials in the original version (i.e. not necessarily in English).
The Consultant will be responsible for all local and international transport, living accommodation and
expenses for its staff, together with communications materials, printing, report production and
translation
5.5 Timetable
The assignment will have a total duration of 14 weeks.
5.6 Deliverables
All deliverables will be sent to the EBRD. The Client will receive copies of the deliverables.
OFFICIAL USE
OFFICIAL USE
Annex 0: Supplementary information on assessment of impacts of climate change
Obtaining data on observed and future climatic conditions
Data on observed trends in climatic conditions is available from www.ipcc-data.org/maps/
(gridded data) and http://climexp.knmi.nl (station data). Broad-scale information on projected
climate change should be drawn from the Intergovernmental Panel on Climate Change Fourth
Assessment Report of Working Group I (IPCC AR4 WGI report), Chapter 11
(http://www.ipcc.ch/publications_and_data/ar4/wg1/en/ ch11.html). Projections of future
climate change (temperature and precipitation) for the City region for the 2050s should be
drawn from a wide range of climate change models, to understand the implications of
uncertainties in climate modelling. BiH’s Second National Communication (SNC) to the
UNFCCC provides information only on a limited number of climate models. However, a
broader set of models is available from http://www.climatewizard.org/. At a minimum, the
mean, minimum and maximum climate model projections from this set should be included, for
the A2, A1B and B1 greenhouse gas emissions scenarios (to capture the effects of emissions
uncertainty). It should be noted that GCMs provide information on changes in climate at a
coarse spatial scale (typically about 250km x 250km) so they may under-represent the changes
that will be experienced at the sites.
1. Assessing the implications of changes in climate as part of the Study
The projected changes in climate will affect a wide range of aspects of relevance to the Study,
including for instance:
Rising temperatures leading to melting of glaciers and consequent impact of river systems and
flows.
Adequacy of and changes in water supply (both surface water and groundwater).
Drinking water quality.
Power supply, energy availability and energy costs.
Asset protection and maintenance.
Water demand and changes in demand, e.g. increased demand due to more extreme heat days.
Further information on climate change impacts for the area is provided in the SNC and this
information can be utilised in the Study. However, as noted above, the SNC is based on a small
number of climate model projections, and so it does not fully capture the uncertainties in climate
modelling which need to be understood as part of the Study. The SNC also does not provide
information on the full set of impacts and mitigation measures that will be relevant to the Study.
Therefore, the risk assessments and development of adaptation measures for the Study will need to
incorporate future climate change projections. The IPCC Task Group on Climate Impact Assessment
(IPCC-TGCIA) has produced guidance9, published by the UNFCCC explaining the use of climate
scenario data in impacts assessments, which will help in undertaking this study. In addition, the
UNFCCC has published a compendium on methods and tools to evaluate impacts of, and vulnerability
and adaptation to, climate change10
.
9 http://unfccc.int/adaptation/nairobi_work_programme/knowledge_resources_and_publications/items/5402.php
10 http://unfccc.int/adaptation/nairobi_workprogramme/knowledge_resources_and_publications/items/5457.php
OFFICIAL USE
OFFICIAL USE
Annex 1. Environmental baseline conditions for water and wastewater projects
1. Potable Water Supply and Distribution
The Consultant will collect and evaluate relevant data related to the nature and integrity of water
sources, potable water treatment processes and distribution networks, quality of the distributed supply
as well any information on the nature of demand (industrial and domestic) as compared to the extent
of supply. The Consultant will draw primarily on existing sources of information though reasonable
effort should be made to verify the validity of this. The Consultant should aim to collect sufficient
information on the environmental baseline of the project so as to allow for subsequent monitoring and
evaluation of the Company’s environmental performance and the environmental impact of the project
using the key E&S impact and performance parameters. The following information is required at a
minimum (the majority of this information has to be already analysed as part of the baseline study
task).
(i) Water Sources
The nature of catchment (watershed) area management, in particular, the level of protection
offered to the quality and quantity of source waters (e.g. from uncontrolled/untreated
discharges, run-off from agricultural land, groundwater contamination, over-abstraction, etc.).
Description of water sources (amounts, seasonal variations, and water quality vis a vis current
national and EU standards).
Based on available information on the impacts of the predicted climate change on water
resources in Bosnia and Herzegovina, such as Bosnia and Herzegovina’s National
Communication to the UNFCCC, assess the vulnerability to climate change impacts of the
Company’s water resources and water supply infrastructure in medium-to-long-term, as well
as where relevant, make recommendations for improving the project’s and the Company’s
operations’ resilience to climate change risk;
Main industrial users and polluters in the catchment area.
Current water quality monitoring of source waters: standards, nature and frequency.
Measures required or being considered to enhance the quality and quantity of water sources in
the catchment area.
(ii) Consumer Demand
Estimation of existing and future demand for water supplies by sector (domestic, commercial,
public, industrial, including survey of major water users, particularly industry); conflicting
demands (present and future).
Domestic water consumption (per capita); comparison with consumption levels in Western
Europe.
(iii) Water Treatment and Distribution Network
Type and quantity of chemicals used for drinking water treatment; chemicals handling,
storage, use and final disposal, contingency planning and emergency response;
Quality of service provided: biological, physical and chemical quality of potable water
provided in comparison with national and EU environmental standards;
Effectiveness and adequacy of water treatment technology used and a general assessment of
whether the existing technology meets existing international best practice for water treatment;
Identify and assess the risks of potential environmental liabilities associated with past and
current operations;
Any environmental or worker and public health and safety issues associated with current
operations;
Anticipated environmental and worker and public health and safety benefits which are likely
to arise from project implementation;
Any actions required to meet applicable national and EU standards. Benchmark the current
drinking water against national normative requirements and EU standards for drinking water
OFFICIAL USE
OFFICIAL USE
quality. Provide an estimate of the investment costs needed to bring the facilities and
operations in compliance with (i) national and (ii) EU standards;
Any areas for immediate improvement including, for example, efficiency improvements,
emission reductions.
(iv) Hot Water Distribution Network (if applicable)
Assess any environmental or health and safety issues associated with hot water distribution
and identify any potential mitigating measures.
2. Wastewater Collection, Treatment and Discharge
The Consultant will collect and evaluate the available data related to the volumes of wastewater and
storm-water generated in the catchment area, methods of effluent treatment and quality and quantity
of wastewater released (with or without treatment) to the environment. The adequacy of the current
wastewater treatment and sewerage systems and their management with respect to existing and
predicted future demand needs also to be considered. The Consultant should aim to use sufficient
information on the environmental baseline of the Project to allow for subsequent monitoring and
evaluation of the Company’s environmental performance and the environmental impact of the Project.
The following information is required at a minimum, the majority of this information has to be
already analysed as part of the baseline study:
(i) Wastewater Sources
the number of people served by wastewater network, the number of households/persons
served by septic tanks;
other industrial, commercial, official and public generators of wastewater, to the extent
allowed by available information;
wastewater flows and characteristics: total and per capita flows, organic loads or other
important characteristics of wastewater; if applicable, distinguish between industrial and other
wastewater sources; frequency and magnitude of storm-water overflows and water bodies to
which they flow, and infiltration of wastewater flows into the water supply network. A
discussion of the possible implications for groundwater pollution of areas not connected to
wastewater collection (if applicable);
industrial wastewater flows from the main industrial sources in terms of flow volumes and
chemical/physical characteristics with special emphasis on toxic/hazardous pollutants
discharged into the municipal wastewater collection system to the extent allowed by available
information;
an analysis of the adequacy of pre-treatment of industrial wastewaters vis a vis the efficiency
of wastewater treatment: a description of the effectiveness and adequacy of industrial pre-
treatment facilities, the impact of industrial wastewater on municipal wastewater treatment
plant operation;
a description of the monitoring of wastewater and effluent flows and quality: a description of
the standards and practices used, laboratory capacity.
(ii) Wastewater Collection Network
a description of existing wastewater collection system, including sewage pumping stations
and sewerage network;
an estimate of the condition and effectiveness of the system;
a review of any potential environmental and/or health issues associated with the system.
(iii) Wastewater Treatment Processes, Sludge Management and Disposal
a description of current wastewater treatment processes, including sludge management
(treatment and/or disposal) commenting on process efficiency at various stages vis a vis
industry norms and outline possible causes of under-efficiency. If applicable, an analysis of
the impacts of industrial wastewater on municipal wastewater treatment plant operation,
highlighting the adverse effects of any industrial effluents (if data on industrial effluents is
available), which may impact microbial processes;
OFFICIAL USE
OFFICIAL USE
benchmark the current wastewater discharges against national normative requirements and
EU standards for urban wastewater discharges. Provide an estimate of the investment costs
needed to bring the facilities and operations in compliance with (i) national and (ii) EU
standards;
a description and analysis of sludge management (temporary storage, handling, collection,
treatment and final disposal): condition, maintenance practices; assess whether their
efficiency and whether they currently meet national requirements; compare with EU
requirements, highlighting adverse effects of any industrial effluents on the sludge quality
which may cause the sludge to be classified as hazardous waste and set specific requirements
for the disposal and treatment of the sludge;
assess ability to utilize sludge in agriculture (refer to relevant national requirements and EU
Directive), to recycle the sludge for other type of utilisation and to produce methane for heat
production;
quality of effluent discharge consistency over a three year period and comparison with current
national and EU standards;
worker and public health and safety issues associated with current operations, safety
equipment and practices (inoculations, health checks, protective wear, toxic/explosive gases);
an analysis and assessment of the impact of effluent and untreated wastewater discharges (if
applicable) and storm water overflows on receiving water body quality with special emphasis
on impacts of industrial hazardous and toxic pollutants, analysing compliance with applicable
effluent standards and applicable regulations;
a description of monitoring of wastewater and effluent quality; a description of standards and
practices, an outline of emergency and contingency plans in relation to process breakdown,
storm water overflow, etc.
OFFICIAL USE
OFFICIAL USE
Annex 2: Standard measuring indicators and GET impact indicators
Standard measuring indicators:
Sector Indicator Data point to be collected
Projected after
implementation
completion*
Water Supply
Total population
benefitting from access to
tap water.
Number of persons
connected to improved
access to tap water.
Annual reduction in
tonnes of CO2 equivalent
derived from the lowering
of water losses system-
wide.
Average (for sector) kwh
used to produce 1 m3 of
water
multiplied with,
amount of m3 of water
losses eliminated
multiplied with,
average tons of CO2
generated by energy
generation in the country.
Annual m3 potable water
produced.
Number of persons
connected to improved
access to tap water
multiplied by average
consumption of water in
m3/year.
Wastewater
Total population
benefitting from access to
wastewater services.
Number of persons with
improved access to
wastewater services.
Annual m3 of wastewater
treated.
Total m3/year of
wastewater treated through
improved wastewater
treatment plant and/or total
m3/year of wastewater
supplied to existing
wastewater treatment plant
through improved network.
* measured two years after projected full loan disbursement
GET impact indicators (as applicable):
GET impact
indicator
Unit Data point to be collected
Primary energy
saved
GJ/yr Project energy use compared to baseline11
energy use.
Primary energy includes:
1. Direct use of fossil fuels
2. Direct use of biomass.
3. Use of electricity, multiplied by a loss factor to take
into account country average generation efficiencies and
electricity grid losses12
11 The baseline is defined as the expected conditions without the project two years after full loan disbursement. The baseline
is compared to the conditions projected with implemented project two years after full loan disbursement. 12 For example, with an average electricity generation efficiency of 40% and grid losses of 7%, the primary energy use
(MWh) is 2.7 x the direct electricity use (MWh).
OFFICIAL USE
OFFICIAL USE
CO2 emissions
reduced
ton
CO2e/yr
Project CO2 emissions compared to baseline CO2 emissions.
CO2 emissions include:
1. Emissions as a result of direct use of fossil fuels
2. Indirect emissions as a result of the use of
electricity13
3. Emissions of other Greenhouse gases (in particular
methane14
) expressed in CO2 equivalents.
Water saved m3/yr Project water use compared to baseline water use. Water savings must
be determined for the following project activities:
1. Water recycling projects that recover wastewater
streams for reuse or alternative use.
2. Application of technology or management actions
that lead to effluent water quality improvements in regions
with water scarcity15
3. Water loss prevention and water demand
management
Material savings ton/yr Material use compared to baseline material use. Material savings
must be determined for project activities aimed at
waste minimisation:
1. Minimisation of waste streams by integrated
measures (i.e. improvement of existing installations,
processes or procedures/management)
2. Waste recycling projects that reuse waste as inputs
into new products or as a resource
13 The CO2 emissions as a result of the use of electricity are determined by multiplying the use of electricity (MWh) with the
country specific grid emission factor (ton CO2/ MWh) in line with the joint MDB list of grid emission factors.
14 Tons of methane emissions (ton CH4) can be converted to tons of CO2 equivalents (ton CO2e) by applying the a factor of
25 (ton CO2e/ton CH4) 15 Qualifying for ‘water saved’: treated waste water with an effluent quality at or exceeding internationally accepted effluent
water quality standards.
OFFICIAL USE
OFFICIAL USE
Annex 1: Standard measuring indicators and SRI impact indicators
Standard measuring indicators:
Sector Indicator Data point to be collected
Projected after
implementation
completion*
Water Supply
Total population benefitting
from access to tap water.
Number of persons connected to
improved access to tap water.
Annual reduction in tonnes of
CO2 equivalent derived from
the lowering of water losses
system-wide.
Average (for sector) kwh used to
produce 1 m3 of water
multiplied with,
amount of m3 of water losses
eliminated
multiplied with,
average tons of CO2 generated
by energy generation in the
country.
Annual m3 potable water
produced.
Number of persons connected to
improved access to tap water
multiplied by average
consumption of water in
m3/year.
Wastewater
Total population benefitting
from access to wastewater
services.
Number of persons with
improved access to wastewater
services.
Annual m3 of wastewater
treated.
Total m3/year of wastewater
treated through improved
wastewater treatment plant
and/or total m3/year of
wastewater supplied to existing
wastewater treatment plant
through improved network.
* measured two years after projected full loan disbursement
SRI impact indicators (as applicable):
SRI impact
indicator
Unit Data point to be collected
Primary energy saved GJ/yr Project energy use compared to baseline16
energy use.
Primary energy includes:
4. Direct use of fossil fuels
16 The baseline is defined as the expected conditions without the project two years after full loan disbursement. The baseline
is compared to the conditions projected with implemented project two years after full loan disbursement.
OFFICIAL USE
OFFICIAL USE
5. Direct use of biomass.
6. Use of electricity, multiplied by a loss factor to take into account
country average generation efficiencies and electricity grid losses17
17 For example, with an average electricity generation efficiency of 40% and grid losses of 7%, the primary energy use
(MWh) is 2.7 x the direct electricity use (MWh).
OFFICIAL USE
OFFICIAL USE
CO2 emissions
reduced
ton CO2e/yr Project CO2 emissions compared to baseline CO2 emissions.
CO2 emissions include:
4. Emissions as a result of direct use of fossil fuels
5. Indirect emissions as a result of the use of electricity18
6. Emissions of other Greenhouse gases (in particular methane19
)
expressed in CO2 equivalents.
Water saved m3/yr Project water use compared to baseline water use. Water savings must be
determined for the following project activities:
4. Water recycling projects that recover wastewater streams for reuse
or alternative use.
5. Application of technology or management actions that lead to
effluent water quality improvements in regions with water
scarcity20
6. Water loss prevention and water demand management
Material savings ton/yr Material use compared to baseline material use. Material savings must be
determined for project activities aimed at
waste minimisation:
3. Minimisation of waste streams by integrated measures (i.e.
improvement of existing installations, processes or
procedures/management)
4. Waste recycling projects that reuse waste as inputs into new
products or as a resource
18 The CO2 emissions as a result of the use of electricity are determined by multiplying the use of electricity (MWh) with the
country specific grid emission factor (ton CO2/ MWh) in line with the joint MDB list of grid emission factors.
19 Tons of methane emissions (ton CH4) can be converted to tons of CO2 equivalents (ton CO2e) by applying the a factor of
25 (ton CO2e/ton CH4) 20 Qualifying for ‘water saved’: treated waste water with an effluent quality at or exceeding internationally accepted effluent
water quality standards.