M E M O R A N D U M
DATE: May 27, 2016
TO: Members of the Technical Committee on Sprinkler System Installation Criteria
FROM: David R. Hague, Principal Fire Protection Engineer/NFPA Staff Liaison
SUBJECT: AUT-SSI AGENDA PACKAGE – A2018 Pre-First Draft Meeting Enclosed is the agenda for the Pre-First Draft meeting for NFPA 13, Standard for the Installation of
Sprinkler Systems, NFPA 13 has entered the Annual 2018 revision cycle and will produce a 2019 Edition.
It is imperative that you review the attached in advance, with your ideas and substantiations for your
views. If you have alternate suggestions for text changes, please come prepared with the words and
respective substantiation.
For administrative questions, please feel free to contact Elena Carroll at (617) 984-7952. For technical
questions, please feel free to contact Dave Hague at (617) 984-7273. You can also reach either of us via
e-mail at [email protected] or [email protected]. We look forward to meeting everyone in San Antonio
Riverwalk.
Technical Committee on Sprinkler System Installation Criteria
Pre-First Draft Meeting
June 27-28, 2016
Courtyard by Marriott San Antonio Riverwalk
207 N. St. Mary's St.
San Antonio, TX 78205
AGENDA
Monday June 27, 2016
1. Call to Order – 8:00 AM
2. Introductions of Members and Staff
3. Review and Approval of A2015 2nd Draft Meeting Minutes
4. Review of A2018 Revision Cycle and Meeting Schedule
5. Review of Distributed Material and Workload
a. Overview of Public Input
b. Overview of Potential Committee First Revisions
c. Review of document reformat
d. Overview of NFPA 13M
6. Establish Task Groups
7. Recess for Task Group Meetings (TBD)
Tuesday June 28, 2016
8. Reconvene for Task Group Reports – 8:00AM
9. Adjourn 12:00 PM
10. Lunch 12:00 PM – 1:00 PM
11. Fire Protection Research Foundation – Sprinkler Research Council Review and Planning
Meeting (all Committee Members are welcome) 1:00 PM – 4:00 PM
Table of Contents
Part 1 - Meeting Agenda
Part 2 - Committee Address List
Part 3 – New Process Worksheets
Part 4 – A2015 Second Draft Meeting Minutes
Part 5 - A2018 Key Dates
PART 2 –
COMMITTEE ADDRESS LIST
Address List No PhoneSprinkler System Installation Criteria AUT-SSI
Automatic Sprinkler Systems
David R. Hague05/27/2016
AUT-SSI
Raymond A. Grill
ChairArup1120 Connecticut Avenue, NW, Suite 1110Washington, DC 20036
SE 12/08/2015AUT-SSI
Roland A. Asp
PrincipalNational Fire Sprinkler Association, Inc.40 Jon Barrett RoadPatterson, NY 12563-2164National Fire Sprinkler AssociationDesign TechnicianAlternate: Jeffrey A. Hewitt
M 07/29/2013
AUT-SSI
Hamid R. Bahadori
PrincipalJENSEN HUGHES725 Primera Boulevard, Suite 215Lake Mary, FL 32746Alternate: Mark Hopkins
SE 4/17/1998AUT-SSI
Weston C. Baker, Jr.
PrincipalFM Global1151 Boston Providence TurnpikePO Box 9102Norwood, MA 02062-9102Alternate: Angele Morcos
I 9/30/2004
AUT-SSI
Cecil Bilbo, Jr.
PrincipalAcademy of Fire Sprinkler Technology, Inc.301 North Neil Street, Suite 426Champaign, IL 61820-3170Alternate: Mark G. Karr
SE 7/26/2007AUT-SSI
Pat D. Brock
PrincipalOklahoma State UniversityFire Protection & Safety Technology1424 West Liberty AvenueStillwater, OK 74075Alternate: Floyd Luinstra
SE 8/5/2009
AUT-SSI
Robert G. Caputo
PrincipalTelgian Corporation2615 South Industrial Park AvenueTempe, AZ 85282-1821Alternate: Russell B. Leavitt
SE 1/16/1998AUT-SSI
Scott T. Franson
PrincipalThe Viking Corporation210 North Industrial Park RoadHastings, MI 49058National Fire Sprinkler AssociationManufacturer
M 10/29/2012
AUT-SSI
Jeff Hebenstreit
PrincipalUL LLC484 Tamarach DriveEdwardsville, IL 62025-5246Alternate: Kerry M. Bell
RT 08/11/2014AUT-SSI
Luke Hilton
PrincipalLiberty Mutual Property13830 Ballantyne Corporate Place, Suite 525Charlotte, NC 20277-2711Alternate: Glenn E. Thompson
I 1/18/2001
AUT-SSI
Elwin G. Joyce, II
PrincipalEastern Kentucky University2148 Alexandria DriveLexington, KY 40504NFPA Industrial Fire Protection SectionAlternate: Anthony R. Cole
U 10/10/1997AUT-SSI
Larry Keeping
PrincipalPLC Fire Safety Solutions3413 Wolfedale Road, Suite 6Mississauga, ON L5C 1V8 Canada
SE 10/10/1997
1
Address List No PhoneSprinkler System Installation Criteria AUT-SSI
Automatic Sprinkler Systems
David R. Hague05/27/2016
AUT-SSI
John Kelly
PrincipalWashington DC Fire & EMS DepartmentOffice of the Fire Marshal719 Opus AvenueCapitol Heights, MD 20743
E 08/09/2012AUT-SSI
Charles W. Ketner
PrincipalNational Automatic Sprinkler Fitters LU 669Joint Apprenticeship & Training Committee7050 Oakland Mills RoadColumbia, MD 20732United Assn. of Journeymen & Apprentices of thePlumbing & Pipe Fitting IndustryAlternate: Michael A. Rothmier
L 1/10/2008
AUT-SSI
Kenneth W. Linder
PrincipalSwiss Re2 Waterside Crossing, Suite 200Windsor, CT 06095-1588Alternate: Todd A. Dillon
I 1/1/1984AUT-SSI
David O. Lowrey
PrincipalCity of Boulder Fire Rescue1805 33rd StreetBoulder, CO 80301
E 08/09/2012
AUT-SSI
Rodney A. McPhee
PrincipalCanadian Wood Council99 Bank Street, Suite 400Ottawa, ON K1P 6B9 CanadaAlternate: Dennis A. Richardson
U 10/10/1997AUT-SSI
Michael F. Meehan
PrincipalVSC Fire & Security1417 Miller Store Road, Suite CVirginia Beach, VA 23455-3327American Fire Sprinkler AssociationDesignAlternate: E. Parks Moore
IM 1/16/1998
AUT-SSI
Joe W. Noble
PrincipalNoble Consulting Services, LLC6345 South Jones Blvd., #100Las Vegas, NV 89130International Fire Marshals Association
E 10/10/1997AUT-SSI
Thomas A. Noble
PrincipalCity of Henderson, Building & Fire Safety10029 Floragold CourtLas Vegas, NV 89147-7726
E 8/5/2009
AUT-SSI
Steven J. Scandaliato
PrincipalSDG, LLCP.O. Box 19798Fountain Hills, AZ 85269
SE 10/03/2002AUT-SSI
Peter T. Schwab
PrincipalWayne Automatic Fire Sprinklers, Inc.222 Capitol CourtOcoee, FL 34761-3033
IM 3/15/2007
AUT-SSI
LeJay Slocum
PrincipalAon Fire Protection Engineering7230 McGinnis Ferry Road, Suite 200Suwanee, GA 30024-1287Alternate: Steven M. Tomlin
I 7/20/2000AUT-SSI
Austin L. Smith
PrincipalConsolidated Nuclear Security, LLC, Y-12PO Box 2009, MS 8107Oak Ridge, TN 37831-8107
U 3/1/2011
2
Address List No PhoneSprinkler System Installation Criteria AUT-SSI
Automatic Sprinkler Systems
David R. Hague05/27/2016
AUT-SSI
William B. Smith
PrincipalCode Consultants, Inc.2043 Woodland Parkway, Suite 300St. Louis, MO 63146-4235Alternate: David J. Burkhart
SE 10/27/2005AUT-SSI
Paul A. Statt
PrincipalEastman Kodak Company41 Monaco DriveRochester, NY 14624
U 1/10/2008
AUT-SSI
Zeljko Sucevic
PrincipalVipond Fire Protection6380 Vipond DriveMississauga, ON L6M 3C1 CanadaCanadian Automatic Sprinkler AssociationAlternate: Jason W. Ryckman
IM 08/09/2012AUT-SSI
Lynn K. Underwood
PrincipalAxis US Property303 West Madison Street, Suite 500Chicago, IL 60606Alternate: Adam Seghi
I 10/1/1997
AUT-SSI
Terry L. Victor
PrincipalTyco/SimplexGrinnell705 Digital Drive, Suite NLinthicum, MD 21090-2267
M 10/3/2002AUT-SSI
Robert Vincent
PrincipalShambaugh & Son, L.P.7614 Opportunity DriveFort Wayne, IN 46825-3363National Fire Sprinkler AssociationContractorAlternate: James A. Charrette
IM 4/3/2003
AUT-SSI
Daniel P. Wake
PrincipalVictaulic Company of America4901 Kesslersville RoadPO Box 31Easton, PA 18040-6714Alternate: Ahmed Saleh
M 08/09/2012AUT-SSI
Thomas G. Wellen
PrincipalAmerican Fire Sprinkler Association, Inc.12750 Merit Drive, Suite 350Dallas, TX 75251American Fire Sprinkler AssociationInstaller/MaintainerAlternate: Jason Gill
IM 04/05/2016
AUT-SSI
Kerry M. Bell
AlternateUL LLC333 Pfingsten RoadNorthbrook, IL 60062-2096Principal: Jeff Hebenstreit
RT 4/15/2004AUT-SSI
David J. Burkhart
AlternateCode Consultants, Inc.2043 Woodland Parkway, Suite 300St. Louis, MO 63146-4235Principal: William B. Smith
SE 03/07/2013
AUT-SSI
James A. Charrette
AlternateAllan Automatic Sprinkler Corp. of So. California3233 Enterprise StreetBrea, CA 92821National Fire Sprinkler AssociationContractorPrincipal: Robert Vincent
IM 7/26/2007AUT-SSI
Anthony R. Cole
AlternateAman Fire Engineering226 Stable WayNicholasville, KY 40356-8046NFPA Industrial Fire Protection SectionPrincipal: Elwin G. Joyce, II
U 8/11/2014
3
Address List No PhoneSprinkler System Installation Criteria AUT-SSI
Automatic Sprinkler Systems
David R. Hague05/27/2016
AUT-SSI
Todd A. Dillon
AlternateGlobal Asset Protection Services1620 Winton AvenueLakewood, OH 44107Principal: Kenneth W. Linder
I 7/16/2003AUT-SSI
Jason Gill
AlternateFire & Life Safety America3017 Vernon Road, Suite 100Richmond, VA 23228American Fire Sprinkler AssociationInstaller/MaintainerPrincipal: Thomas G. Wellen
IM 04/05/2016
AUT-SSI
Jeffrey A. Hewitt
AlternateAmerican Fire Protection, Inc.5525 Eastcliff Industrial LoopBirmingham, AL 35210-5418National Fire Sprinkler AssociationDesign TechnicianPrincipal: Roland A. Asp
M 10/29/2012AUT-SSI
Mark Hopkins
AlternateJENSEN HUGHES3610 Commerce Drive, Suite 817Baltimore, MD 21227-1652Principal: Hamid R. Bahadori
SE 3/4/2008
AUT-SSI
Mark G. Karr
AlternateAcademy of Fire Sprinkler Technology, Inc.301 North Neil Street, Suite 426Champaign, IL 61820-3170Principal: Cecil Bilbo, Jr.
SE 10/28/2014AUT-SSI
Russell B. Leavitt
AlternateTelgian Corporation10230 S. 50th PlacePhoenix, AZ 85044Principal: Robert G. Caputo
SE 04/05/2016
AUT-SSI
Floyd Luinstra
AlternateOklahoma State University499 Cordell SouthStillwater, OK 74078Principal: Pat D. Brock
SE 10/29/2012AUT-SSI
E. Parks Moore
AlternateS & S Sprinkler Company, LLCPO Box 7453Mobile, AL 36670American Fire Sprinkler AssociationDesignPrincipal: Michael F. Meehan
IM 04/05/2016
AUT-SSI
Angele Morcos
AlternateFM Global1151 Boston-Providence TurnpikeNorwood, MA 02062-9102Principal: Weston C. Baker, Jr.
I 12/08/2015AUT-SSI
Dennis A. Richardson
AlternateAmerican Wood Council2777 Yulupa Avenue, #126Santa Rosa, CA 95405-8584Principal: Rodney A. McPhee
U 08/17/2015
AUT-SSI
Michael A. Rothmier
AlternateUA Joint Apprenticeship Committee LU 6691315 Berrytree DriveSugarland, TX 77479United Assn. of Journeymen & Apprentices of thePlumbing & Pipe Fitting IndustryPrincipal: Charles W. Ketner
L 1/16/1998AUT-SSI
Jason W. Ryckman
AlternateCanadian Automatic Sprinkler Association335 Renfrew Drive, Suite 302Markham, ON L3R 9S9 CanadaPrincipal: Zeljko Sucevic
IM 10/28/2014
4
Address List No PhoneSprinkler System Installation Criteria AUT-SSI
Automatic Sprinkler Systems
David R. Hague05/27/2016
AUT-SSI
Ahmed Saleh
AlternateVictaulic Company of America4901 Kesslersville RoadEaston, PA 18040-6714Principal: Daniel P. Wake
M 12/08/2015AUT-SSI
Adam Seghi
AlternateCoda Risk Analysis9624 Vista View DriveAustin, TX 78750Principal: Lynn K. Underwood
I 10/29/2012
AUT-SSI
Glenn E. Thompson
AlternateLiberty Mutual InsuranceNI Property - West Division790 The City Drive, Suite 200Orange, CA 92868Principal: Luke Hilton
I 10/27/2005AUT-SSI
Steven M. Tomlin
AlternateAon/Schirmer Engineering Corporation335 Renfrew Drive, Suite 101Markham, ON L3R 9S9 CanadaPrincipal: LeJay Slocum
I 10/27/2009
AUT-SSI
Barry M. Lee
Nonvoting MemberTyco International16 Payten StreetKogarah Bay, NSW 2217 Australia
M 10/10/1997AUT-SSI
David R. Hague
Staff LiaisonNational Fire Protection Assocation1 Batterymarch ParkQuincy, MA 02169-7471
3/18/2016
5
PART 3 –
NEW PROCESS WORKSHEETS
March 13, 2012
TERMS New Terms Old Terms
Input Stage – Stage where Public Input is sought to develop the First Draft.
Report on Proposals (ROP) Stage
Public Input (PI) – A recommended change submitted for consideration by the Technical Committee. Each Public Input (PI) shall include new, modified or deleted text as appropriate and technical substantiation to support the recommended change.
Download a Public Input Form for documents in Fall 2013 and subsequent cycles
Proposal
First Draft Meeting ROP Meeting
First Revision (FR) – Proposed changes to the text of an NFPA Standard developed by the responsible Committee(s) in the Input Stage. Each First Revision shall contain the new, modified or deleted text as appropriate. A First Revision shall be established through a Meeting Vote and shall only require a simple majority to proceed to ballot. Only First Revisions that pass ballot will show in the First Draft. Each First Revision shall contain a Committee Statement that substantiates the proposed change to the document.
Committee Proposal or Accepted Public Proposal
Committee Input (CI) – A CI can be established during the First Draft Technical Committee meeting (without balloting) in order to highlight the concept to obtain public comment; often used for newer ideas, topics that aren’t fully fleshed out or controversial topics. A Committee Input (CI) can also be a First Revision (FR) that fails to receive support of the technical committee through letter ballot. Committee Inputs shall maintain the original FR Committee Statement and shall contain a notification to the reviewer documenting that the CI represents a failed FR.
“Trial Balloon” or an Accepted Proposal (or Committee Proposal) that Failed Ballot
Committee Statement (CS) – A Committee Statement is the committee’s response to a Public Input (PI), Public Comment (PC) or the committee’s technical substantiation for a proposed First Revision. A committee statement shall be established through a Meeting Vote and shall only require a simple majority to proceed.
Committee Statement
First Draft Report – The First Draft Report documents the Input Stage; it shall contain the First Draft, Public Input, Committee Input, Committee and Correlating Committee Statements, Correlating Input, Correlating Notes and Ballot Statements.
ROP
First Draft – The draft of the proposed new or revised standard showing in legislative text all First Revisions and First Correlating Revisions that have passed ballot.
ROP Draft
Correlating Committee (CC) Technical Correlating Committee
Correlating Committee Statement – The Correlating Committee’s response to a Public Input (PI), Committee Input (CI), Public Comment (PC) or the Correlating Committee’s technical substantiation for a correlating change to proposed Revision or a correlative CCFR. It shall be established through a Meeting Vote and shall only require a simple majority to proceed.
TCC Note
Correlating Committee First Revision (CCFR) – Correlating Committee First Revisions are proposed revisions to the Technical Committee’s First Revisions that are required to correlate the proposed document. Each CCFR shall contain a Correlating Committee Statement that substantiates the Revision. A CCFR shall be established through a Meeting Vote and shall only require a simple majority to proceed to letter ballot. CCFRs that fail to receive CC support through letter ballot shall not be published as part of the First Draft.
TCC Note
Technical Committee First Draft meeting - Spring 2012 Page 2 of 34 V.2 3/13/2012
Comment Stage Report on Comments (ROC) Stage
Public Comment – Changes submitted by the public during public Comment Stage.
Public Comment
Second Draft Meeting ROC Meeting
Second Revision (SR) – Similar to First Revision, but in the Comment Stage. Proposed changes to the text by the TC that have passed ballot.
Committee Comment or Accepted Public Comment
Committee Comment – A Committee Comment shall be a Second Revision (SR) that fails to receive support of the TC through ballot. Committee Comments shall maintain the original Committee Statement and shall contain a notification to the reviewer documenting that the Committee Comment represents a failed SR.
Committee Comment that failed ballot
Committee Action – An action by a TC to accept or reject a Comment. This occurs only in the Comment Stage and the action itself is not balloted.
Committee Action
Second Draft Report – The Second Draft Report documents the Comment Stage; it shall contain the Second Draft, Public Comments with corresponding Committee Actions and Committee Statements, Committee Comments, Correlating Revisions and Ballot Statements.
ROC
Second Draft – The draft of the proposed new or revised standard showing in legislative text all Second Revisions and Second Correlating Revisions that have passed ballot.
ROC Draft
Technical Committee First Draft meeting - Spring 2012 Page 3 of 34 V.2 3/13/2012
NEW PROCESS ACTIONS AND MOTIONS
New Process Actions and Motions‐ Final‐ 2/13/2012
Possible Action 1: Resolve PIs, (no change to Section)
Action Required Sample MotionsStep One: Committee generates a statement to respond to (resolve)
each PI #
I make a motion (move) to resolve PI#___ with the following committee statement: Approval by a meeting vote (simple majority) and not subject to ballot (Regs 4.3.7.3 & 4.3.7.3.2)
Possible Action 2: Create First Revision ‐ Change to a Section
Action Required Sample MotionsStep One: (1st option)
Committee generates a First Revision I make a motion (move) to revise Section ___ as follows:………… Approval by a meeting vote (simply majority) and final approval through ballot (Regs 4.3.9.2.3)
Step Two: (1st option)
Committee generates a statement substantiating the change.
Approval by a meeting vote (simply majority) (Regs 4.3.7.3)
Step One: (2nd option)
Committee generates a First Revision using one or more PIs as the starting point.
I make a motion to revise Section __ using PI#__ as the basis for change. Approval by a meeting vote (simply majority) and final approval through ballot (Regs 4.3.9.2.3)
Step Two: (2nd option)
If the revision is associated with one or more PIs the committee generates a statement to respond to (resolve) each PI
I make a motion (move) to resolve PIs # through ## with the following statement: Approval by a meeting vote (simply majority) and not subject to ballot (Regs 4.3.7.3 &
4.3.7.3.1)
Possible Action 3: Create Committee Input – (Trial Balloon/Placeholder)
Action Required Sample Motions Step One:
Committee generates a Committee Input (proposed revision) for public consideration and solicitation of Public Comments
I make a motion (move) to create a CI with a proposed revision to X.X.X as follows: Approval by a meeting vote (simply majority) and not subject to ballot (Regs 4.3.8)
Step Two: Committee generates a statement to explain the intent and why it is seeking public consideration and soliciting Public Comments
Approval by a meeting vote (simply majority) (Regs 4.3.7.1)
Technical Committee First Draft meeting - Spring 2012 Page 8 of 34 V.2 3/13/2012
PART 4 –
A2015 SD MEETING MINUTES
Technical Committee on
Sprinkler System Installation Criteria
Second Draft Meeting Minutes
June 23-25, 2014 San Diego Marriott Del Mar
11966 El Camino Real
San Diego, CA 92130
1. The meeting was called to order by TC Chair Joe Noble at 8:00 AM.
2. The TC reviewed and approved the A2015 First Draft Meeting Minutes.
3. NFPA Staff (Matt Klaus) reviewed the regulations governing technical committee
meetings and outlined the protocol for making motions for the Second Draft meeting.
4. TC Chair Joe Noble reviewed the following items with the TC:
b. Overview of Public Comments
c. Potential Committee Second Revisions based on Task Group Reports Task Group
Reports
5. The Technical Committee heard the following task group reports:
a. Metric Task Group
b. Pipe Venting Task Group
c. Extension Fitting Task Group
d. Compatibility Task Group
e. Cloud Ceiling Task Group
f. Galvanized Pipe Task Group
g. Chapter 1-3 Task Group Report
h. Chapter 6 & 7 Task Group Report
i. Chapter 8a Task Group Report
j. Chapter 25 Task Group Report
6. The Chapter 8b task report was incomplete, therefore the items assigned to this task
group were reviewed by the entire committee.
7. TC Chair Joe Noble called for new business. The following item was presented to the
task group:
a. The TC would like to encourage the FPRF to conduct further studies on cloud
ceiling arrangements. This may include sloped clouds, staggered clouds, clouds
with holes and other arrangements.
8. The meeting was adjourned at 2:30 PM local time.
SD (SSI) Attendees 6/23‐25/2014
Principals: Joe Noble Roland Asp Weston Baker Cecil Bilbo Pat Brock Phillip Brown Robert Caputo Donald Goosman Luke Hilton Brian Hoening Larry Keeping Kenneth Linder David Lowrey Rodney McPhee Michael Meehan Thomas Noble Peter Schwab LeJay Slocum William Smith Zeljko Sucevic Terry Victor Robert Vincent Daniel Wake
Alternates Kerry Bell Scott Franson James Golinveaux Mark Hopkins Floyd Luinstra Steven Scandaliato Adam Seghi Peter Thomas
Matt Klaus, NFPA Staff Liaison
Guests: Jeff Hebenstreit Jacqueline Wilmot Les Easter Mark Fessendon Jim Parks Karl Wiegand Robert Gehrke Eliseo Gutierrez Thomas Zaremba William Koffel Lisa Cunningham David Royse
PART 5 –
A2018 KEY DATES
Process
StageProcess Step Dates for TC
Dates for TC
with CC
Public Input Closing Date 6/29/2016 6/29/2016
Final date for TC First Draft Meeting 12/7/2016 9/7/2016Posting of First Draft and TC Ballot 1/25/2017 10/19/2016Final date for Receipt of TC First Draft ballot 2/15/2017 11/9/2016Final date for Receipt of TC First Draft ballot ‐ recirc 2/22/2017 11/16/2016Posting of First Draft for CC Meeting 11/23/2016Final date for CC First Draft Meeting 1/4/2017Posting of First Draft and CC Ballot 1/25/2017Final date for Receipt of CC First Draft ballot 2/15/2017Final date for Receipt of CC First Draft ballot ‐ recirc 2/22/2017Post First Draft Report for Public Comment 3/1/2017 3/1/2017
Public Comment closing date 5/10/2017 5/10/2017
Notice published on Consent Standards (Standards that receive No Comments). Note: Date varies and determined via TC ballot.
_ _
Appeal Closing Date for Consent Standards (15 Days) (Standards That Received
No Comments)_ _
Final date for TC Second Draft Meeting 11/8/2017 8/2/2017Posting of Second Draft and TC Ballot 12/20/2017 9/13/2017Final date for Receipt of TC Second Draft Ballot 1/10/2018 10/4/2017Final date for receipt of TC Second Draft ballot ‐ recirc 1/17/2018 10/11/2017Posting of Second Draft for CC Mtg 10/18/2017Final date for CC Second Draft Meeting 11/29/2017Posting of Second Draft for CC Ballot 12/20/2017Final date for Receipt of CC Second Draft ballot 1/10/2018Final date for Receipt of CC Second Draft ballot ‐ recirc 1/17/2018Post Second Draft Report for NITMAM Review 1/24/2018 1/24/2018
Notice of Intent to Make a Motion (NITMAM) Closing Date 2/21/2018 2/21/2018Posting of Certified Amending Motions (CAMs) and Consent Standards 4/4/2018 4/4/2018Appeal Closing Date for Consent Standards (15 Days after posting) 4/19/2018 4/19/2018SC Issuance Date for Consent Standards (10 Days) 4/29/2018 4/29/2018
Tech Session Association Meeting for Standards with CAMs 6/4‐7/2018 6/4‐7/2018
Appeal Closing Date for Standards with CAMs (20 Days after ATM) 6/27/2018 6/27/2018Council Issuance Date for Standards with CAMs* 8/14/2018 8/14/2018
Comment
Stage (Second
Draft)
Tech Session
Preparation
(& Issuance)
Appeals and
Issuance
2018 ANNUAL REVISION CYCLE
Public Input
Stage
(First Draft)
* Public Input Closing Dates may vary according to standards and schedules for Revision Cycles may change. Please check the
NFPA Website for the most up‐to‐date information on Public Input Closing Dates and schedules at www.nfpa.org/document # (i.e.
www.nfpa.org/101) and click on Next Edition tab.