Upload
arup-cause
View
214
Download
1
Embed Size (px)
DESCRIPTION
Team No.31
Citation preview
Wu Zhi Qiao Bridge Design Competition
24/06/2010
Page 1 of 2
Introduction
In response to an invitation to the design competition for a new footbridge in Mixia, Yunnan Province in China, a design of a
ribbon structure is presented in the following pages.
This proposed footbridge satisfies the environmental, buildability and maintenance criteria, which are indicated in the
design brief. The designer’s intention is to provide an aesthetically attractive solution, which is in harmony with the local
environment. An artist’s impression of the proposed footbridge is presented in Figure 1.
Figure 1 Artist’s impression of a new footbridge in Mixia, Yunnan (China).
Design concept
It is proposed that a new footbridge in Mixia, Yunnan, will be a ribbon structure, as illustrated in Figure 1. The new
footbridge will be located in a slightly different location to the existing bridge, as illustrated in Figure 2.This new location will
help to reduce the span length from 19,8m to 18,4m. In addition to that, the new footbridge will be located at a higher level
in relation to the river water level, so it will be possible to avoid flooding during the monsoon period. The new structure will
also not require intermediate supports in the river bed, so there is no possibility of these failing during flooding. The
structural form of the footbridge, is based on the assumption that two main carrying ropes, which span across the river, will
carry all the vertical loads. The deck will be seated on the ropes and the handrails will be attached to the deck. The new
proposed ribbon footbridge, may be prone to wobbling in a horizontal direction. In order to eliminate this, the additional
stabilising ropes have been included in the design. The stabilising system consists of the main (longitudinal) and the
secondary (transversal) ropes, connecting to the bridge deck as illustrated in Figure 3. The installation sequence of the
secondary ropes is presented in Figure 5. The construction sequence of the footbridge is explained in Figure 4 and the
modification of the steep approaches is presented in Figure 6. All the main structural components of the footbridge will be
made of sustainable materials, such as bamboo or cane rope. These materials can be easily assembled in the nearby
village and then transported on site.
Figure 2 Plan layout.
19503150 3150
Handrail (bamboo)
Vertical post (bamboo)
Main stabilising rope
Secondary (transversal)
stabilising ropes
Main carrying rope
Looped secondary rope Bamboo members;
stabilising vertical post
varies
1750
1200
Deck
(bamboo)
Figure 3 Deck cross section.
Wu Zhi Qiao Bridge Design Competition
24/06/2010
Page 2 of 2
18400 25002500 500500
4095
Min. water level
Min. water level
Min. water level
Min. water level
Stage 1:
1) Preparation works; removal of the
obstacles, earthworks (soil levelling).
2) Installation of the wooden (or bamboo)
piles, forming the anchorage for the main
ropes.
3) Ground levelling/ profiling at the approach
ramps. Installation of the retaining wall
made of bamboo.
4) Installation of the primary (longitudial)
carrying ropes and the main stabilising
ropes; the stabilising ropes shall be
post-tensioned (stretched).
Stage 2:
5) Installation of the deck, made of bamboo.
The deck shall be built in 2m long intervals.
Each interval consists of the following
sequence:
5a) Installation of the deck elements;
bamboo members shall be placed
transversally on top of the primary ropes.
Each transversal element shall be attached
to the rope by means of installation strings.
5b) After the 2m long deck segment is
complete, the handrail shall be installed.
5c) The secondary stabilising ropes shall be
installed at the position of the handrail
vertical post. The transversal ropes are
attached to the main (longitudinal) stabilising
ropes and a bamboo deck.
Stage 3:
6) Repeat No.5 along the length of the main
ropes.
7) Finishes at the approach ramps.
8) Structure complete.
EarthworksMain stabilising rope
Main carrying rope
Retaining wall (bamboo)
Soil infill Wooden piles
Deck transversal members (bamboo)
Handrail (bamboo)
Vertical posts (bamboo)
Main stabilising rope
Secondary (transversal) stabilising rope
ELEVATION
Figure 4 Construction sequence.
Secondary (transversal)
stabilising ropes
Main stabilising rope
Deck
(bamboo)
1) Deck installation (deck and hanrdails).
2) Secondary stabilising rope, weaved
through the hole in a deck's bamboo.
3) Secondary ropes overhung over the
main stabilising ropes (both sides).
4) Secondary rope, from one side ,
pulled under the bridge deck and
connected (looped) to the transversal
rope on the other side of the deck.
5) The same as No.4, but for the other
side of the deck.
6) Instalation of the secondary
(transversal) stabilising ropes is
completed.
Figure 5 Installation sequence of the secondary (transversal) stabilising ropes.
Horizontal bamboo
forming tread
3x280mm
Bamboo
Existing embankment
Stage 1
Bamboo, approx. 1m long pieces, are
driven vertically into the soil. The
vertical bamboo is installed in line at
different levels of the embankment.
Stage 2
Soil is removed (profiled) and bamboo is
cut-off to its final length. The vertical
bamboo, will form the riser of a step.
Stage 3
Horizontal bamboo is installed between
the vertical bamboo risers, to form the
tread.
Removed soil
Bamboo cut-off to
the final lenght
Figure 6 Stair installation at the footbridge approach.