12
Team 22 Automate Packaging of Greeting Card Package February 11, 2014 Hailey Bryant Communication David Yen Technical Contributions Yi Yu Project Management Olzhas Zhanabek Creativity & Innovation

Team 22 Automate Packaging of Greeting Card Package February 11, 2014 Hailey Bryant Communication David Yen Technical Contributions Yi Yu Project Management

Embed Size (px)

Citation preview

Page 1: Team 22 Automate Packaging of Greeting Card Package February 11, 2014 Hailey Bryant Communication David Yen Technical Contributions Yi Yu Project Management

Team 22

Automate Packaging of Greeting Card Package

February 11, 2014

Hailey Bryant

Communication

David Yen

Technical Contributions

Yi Yu

Project Management

Olzhas Zhanabek

Creativity & Innovation

Page 2: Team 22 Automate Packaging of Greeting Card Package February 11, 2014 Hailey Bryant Communication David Yen Technical Contributions Yi Yu Project Management

Agenda

•Introduction•Background Information•Recommended Approach•Expected Results/ measurable•Project Management

Page 3: Team 22 Automate Packaging of Greeting Card Package February 11, 2014 Hailey Bryant Communication David Yen Technical Contributions Yi Yu Project Management

American Greetings CorporationBardstown, KY

Introduction Our Client

Page 4: Team 22 Automate Packaging of Greeting Card Package February 11, 2014 Hailey Bryant Communication David Yen Technical Contributions Yi Yu Project Management

Automate the process of placing wholesale packages into shipping carton

Statement of Need

Page 5: Team 22 Automate Packaging of Greeting Card Package February 11, 2014 Hailey Bryant Communication David Yen Technical Contributions Yi Yu Project Management

• Robotic Arms• Reverse Engineering

Envelope Pre-Loader• Magazine Loading &

Coin Slot Identifier• Gravity Feed & Nose

Conveyer• Lid Dispenser

Recommended Approach

Page 6: Team 22 Automate Packaging of Greeting Card Package February 11, 2014 Hailey Bryant Communication David Yen Technical Contributions Yi Yu Project Management

• Make a completely automated system– Move cards into box– Place lid on box– Move box onto automated

Palletizer

• IRR the most important variable

• Consider space availability • Design meets OSHA

standards

Expected Results

Page 7: Team 22 Automate Packaging of Greeting Card Package February 11, 2014 Hailey Bryant Communication David Yen Technical Contributions Yi Yu Project Management

• Robotic Approach– Moves cards into box

• Too Slow

• Reverse Engineering Approach– Could handle Speed

• Too Much Variability

• Continuous Feed– Handle Speed and

Variability• Cost and Dimensions

Unknown

Expected Results Continued

Page 8: Team 22 Automate Packaging of Greeting Card Package February 11, 2014 Hailey Bryant Communication David Yen Technical Contributions Yi Yu Project Management

Gantt Chart

Page 9: Team 22 Automate Packaging of Greeting Card Package February 11, 2014 Hailey Bryant Communication David Yen Technical Contributions Yi Yu Project Management

Gantt Chart

Page 10: Team 22 Automate Packaging of Greeting Card Package February 11, 2014 Hailey Bryant Communication David Yen Technical Contributions Yi Yu Project Management

Cost Analysis

Page 11: Team 22 Automate Packaging of Greeting Card Package February 11, 2014 Hailey Bryant Communication David Yen Technical Contributions Yi Yu Project Management

Week 1 - Jan 27 Hours Cost Per Hour Total CostTotal Individual Hours 8 100.00$ 800.00$ Total Team Meeting Hours 2 400.00$ 800.00$ Total Account Executive Hours 0 200.00$ -$ Total Onsite Hours 0 600.00$ -$ Total Transportation Cost 0 35.20$ -$ Total Weekly Cost 1,600.00$ Week 2 - Feb 3 Hours Cost Per Hour Total CostTotal Individual Hours 12 100.00$ 1,200.00$ Total Team Meeting Hours 6 400.00$ 2,400.00$ Total Account Executive Hours 0 200.00$ -$ Total Onsite Hours 2 600.00$ 1,200.00$ Total Transportation Cost 7 35.20$ 246.40$ Total Weekly Cost 5,046.40$ Week 3 - Feb 10 Hours Cost Per Hour Total CostTotal Individual Hours 8 100.00$ 800.00$ Total Team Meeting Hours 4 400.00$ 1,600.00$ Total Account Executive Hours 0.5 200.00$ 100.00$ Total Onsite Hours 0 600.00$ -$ Total Transportation Cost 0 35.20$ -$ Total Weekly Cost 2,500.00$

Week 4 - Feb 17 Hours Cost Per Hour Total CostTotal Individual Hours 8 100.00$ 800.00$ Total Team Meeting Hours 4 400.00$ 1,600.00$ Total Account Executive Hours 0 200.00$ -$ Total Onsite Hours 0 600.00$ -$ Total Transportation Cost 0 35.20$ -$ Total Weekly Cost 2,400.00$ Week 5 - Feb 24 Hours Cost Per Hour Total CostTotal Individual Hours 8 100.00$ 800.00$ Total Team Meeting Hours 4 400.00$ 1,600.00$ Total Account Executive Hours 0 200.00$ -$ Total Onsite Hours 0 600.00$ -$ Total Transportation Cost 0 35.20$ -$ Total Weekly Cost 2,400.00$ Week 6 - Mar 3 Hours Cost Per Hour Total CostTotal Individual Hours 12 100.00$ 1,200.00$ Total Team Meeting Hours 6 400.00$ 2,400.00$ Total Account Executive Hours 1 200.00$ 200.00$ Total Onsite Hours 0 600.00$ -$ Total Transportation Cost 0 35.20$ -$ Total Weekly Cost 3,800.00$

Cost Analysis

Page 12: Team 22 Automate Packaging of Greeting Card Package February 11, 2014 Hailey Bryant Communication David Yen Technical Contributions Yi Yu Project Management