191
Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For the text of the statute/rule, please go to 40 CFR Part 63, Subpart EEE (1 of 191) Start 40 CFR 63, Subpart EEE does not apply. Yes End Is the source a hazardous waste combustor and either an area source or a major source? Yes No §63.1200 §63.1200(a) Does the combustor meet the criteria in Table 1 of §63.1200(b)? §63.1200(b) No 1 Is the combustor a hazardous waste incinerator? §63.1219 No Is the combustor a hazardous waste burning cement kiln? §63.1220 No Is the incinerator an existing source? 101 201 Yes §63.1219(a) No Is the kiln an existing source? 301 401 Yes §63.1220(a) No Yes Yes 09/30/2010 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008 These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For the text of the statute/rule, please go to

40 CFR Part 63, Subpart EEE(1 of 191)

Start

40 CFR 63, Subpart EEE does not apply.

Yes End

Is the sourcea hazardous waste

combustor and either an areasource or a major

source?

Yes

No

§63.1200§63.1200(a)

Does thecombustor meet thecriteria in Table 1 of

§63.1200(b)?

§63.1200(b)

No

1

Is the combustor a hazardous waste

incinerator?

§63.1219

No

Isthe combustor

a hazardous wasteburning cement

kiln?§63.1220

No

Is theincinerator an existing

source?101

201

Yes

§63.1219(a)

No

Is thekiln an existing

source?301

401

Yes

§63.1220(a)

No

Yes

Yes

09/30/2010 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Page 2: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(2 of 191)

Is thecombustor a hazardous waste burning lightweight aggregate

kiln?

1

§63.1221

No

Is the combustor a solid fuel boiler that burns

hazardous waste?

§63.1216

No

Is the combustor a liquid fuel boiler that burns

hazardous waste?

§63.1217No

Is thecombustor a HCl production

furnace that burns hazardouswaste?

§63.1218

No

40 CFR 63, Subpart EEE does not apply.

End

501

601

Yes

§63.1221(a)

No

Yes

Is theboiler an existing

source?701

801

Yes

§63.1216(a)

No

Yes

Is thekiln an existing

source?

Is theboiler an existing

source?901

1001

Yes

§63.1217(a)

No

Yes

Is thefurnace an existing

source?1101Yes

§63.1218(a)

No

Yes

1301

Page 3: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(3 of 191)

Dioxins,Furans

101

Pb, Cd, Se

103

106

Applicant must go through the flowchart for each

pollutant group.

Sb, As, Be, Cr, Co, Mn, Ni

CO, THC

107

108

111Total

Chlorine

113

112

POHC

115

PM

Hg

Have allpollutant paths been

completed? End

§63.1219

No

Continue through next path.

102

Page 4: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(4 of 191)

Is the incineratorequipped with either a wasteheat boiler or dry air pollution

control system?

103

§63.1219(a)(1)(i)

No

Yes

Is thecombustion gas

temperature at the inletto the initial particulate matter

control device 400 deg. F or lowerbased on the average of

the test runaverages?

§63.1219(a)(1)(i)(B)

No

105

104

Yes

Comply with the following:Standard

§63.1219(a)(1)(ii)[G]§63.1206(c)(6)(iii)

[G]§63.1207(l)(2)§63.1209(k), (k)(1)(i), (k)(2)(i)-(ii)

[G]§63.1209(k)(3)-(4), (k)(5), [G](k)(6)-(9)§63.1219(d)

Monitoring/Testing[T][G]§63.1207(b)(2), [T](c)(3), (g)(1)(i)(A)

§63.1207(g)(1)(i)(B), (g)(2)(ii), (g)(2)(v)[G]§63.1208(b)(1)

§63.1209(k)(2)(i), [G](k)(3), [G](k)(8)Recordkeeping

§63.1209(k)(2)(i), [G](k)(3)Reporting

§63.1207(f)(1)(xv), (f)(1)(xvii), (f)(1)(xix)[G]§63.1207(f)(1)(xx)-(xxi), (f)(1)(xxii)

§63.1207(f)(2)(ii), (j)(2)§63.1210(b)(3)(i), (c)(1)(i)

117

Page 5: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(5 of 191)

104

Comply with the following:Standard

§63.1219(a)(1)(i)(A)[G]§63.1206(c)(6)(iii)

[G]§63.1207(l)(2)§63.1209(k), (k)(1)(i), (k)(2)(i)-(ii)

[G]§63.1209(k)(3)-(4), (k)(5), [G](k)(6)-(9)§63.1219(d)

Monitoring/Testing[T][G]§63.1207(b)(2), [T](c)(3), (g)(1)(i)(A)

§63.1207(g)(1)(i)(B), (g)(2)(ii), (g)(2)(v)[G]§63.1208(b)(1)

§63.1209(k)(2)(i), [G](k)(3), [G](k)(8)Recordkeeping

§63.1209(k)(2)(i), [G](k)(3)Reporting

§63.1207(f)(1)(xv), (f)(1)(xvii), (f)(1)(xix)[G]§63.1207(f)(1)(xx)-(xxi), (f)(1)(xxii)

§63.1207(f)(2)(ii), (j)(2)§63.1210(b)(3)(i), (c)(1)(i)

Comply with the following:Standard

§63.1219(a)(1)(i)(B)[G]§63.1206(c)(6)(iii)

[G]§63.1207(l)(2)§63.1209(k), (k)(1)(i), (k)(2)(i)-(ii)

[G]§63.1209(k)(3)-(4), (k)(5), [G](k)(6)-(9)§63.1219(d)

Monitoring/Testing[T][G]§63.1207(b)(2), [T](c)(3), (g)(1)(i)(A)

§63.1207(g)(1)(i)(B), (g)(2)(ii), (g)(2)(v)[G]§63.1208(b)(1)

§63.1209(k)(2)(i), [G](k)(3), [G](k)(8)Recordkeeping

§63.1209(k)(2)(i), [G](k)(3)Reporting

§63.1207(f)(1)(xv), (f)(1)(xvii), (f)(1)(xix)[G]§63.1207(f)(1)(xx)-(xxi), (f)(1)(xxii)

§63.1207(f)(2)(ii), (j)(2)§63.1210(b)(3)(i), (c)(1)(i)

105

117

Page 6: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(6 of 191)

106

Comply with the following:Standard

§63.1219(a)(2)[G]§63.1206(c)(6)(iii)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1219(d)

Monitoring/Testing[T]§63.1207(c)(3), (g)(1)(i)(B), [G](m)(1)-(2)

§63.1208(b)(2)§63.1209(a)(5)Recordkeeping

[G]§63.1207(m)(1)-(2)Reporting

§63.1207(f)(1)(xvi), (f)(1)(xxvi), (m)(5)§63.1209(g)(1)(iv)(B)

§63.1210(b)(3)(i), (c)(1)(i)

Are yourequesting to

extrapolate mercury feedrate limits from comprehensive

performance testlevels?

§63.1207(f)(1)(x)§63.1209(l)(1)(v)

Comply with the following:Standard

[G]§63.1209(l)(1)(v)Monitoring/Testing

[T][G]§63.1207(f)(1)(x)Reporting

[G]§63.1207(f)(1)(x)[G]§63.1209(l)(1)(v)

Yes

No

Comply with the following:Standard

§63.1209(l), (l)(1)(i)Monitoring/Testing§63.1209(l), (l)(1)(i)

117

Page 7: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(7 of 191)

Is the owneror operator complying withalternative metal emission

requirements?

107

§63.1219(e)(1)

Yes

In lieu of complying with particulate matter standard in §63.1219(a)(7), you may elect to comply with alternative metal emission

control requirements.

Comply with the following:Standard

§63.1219(a)(3)[G]§63.1206(c)(6)(iii)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1219(d)Monitoring/Testing

[T]§63.1207(c)(3), (f)(1)(xi), (g)(1)(i)(B)[G]§63.1207(m)(1)-(2)

§63.1208(b)(3)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

Reporting§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)

§63.1207(f)(1)(xxvi), (m)(5)§63.1209(g)(1)(iv)(A)

§63.1210(b)(3)(i), (c)(1)(i)

Comply with the following:Standard

§63.1219(e)(2)(i)[G]§63.1206(c)(6)(iii)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1219(e)(4)Monitoring/Testing

[T]§63.1207(c)(3), (f)(1)(xi), (g)(1)(i)(B)[G]§63.1207(m)(1)-(2)

§63.1208(b)(3)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

Reporting§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)

§63.1207(f)(1)(xxvi), (m)(5)§63.1209(g)(1)(iv)(A)

§63.1210(b)(3)(i), (c)(1)(i)

109

No

Page 8: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(8 of 191)

Is the owneror operator complying withalternative metal emission

requirements?

108

§63.1219(e)(1)

Yes

In lieu of complying with particulate matter standard in §63.1219(a)(7), you may elect to comply with alternative metal emission

control requirements.

Comply with the following:Standard

§63.1219(a)(4)[G]§63.1206(c)(6)(iii)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1219(d)Monitoring/Testing

[T]§63.1207(c)(3), (f)(1)(xi), (g)(1)(i)(B)[G]§63.1207(m)(1)-(2)

§63.1208(b)(4)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

Reporting§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)

§63.1207(f)(1)(xxvi), (m)(5)§63.1209(g)(1)(iv)(A)

§63.1210(b)(3)(i), (c)(1)(i)

Comply with the following:Standard

§63.1219(e)(2)(ii)[G]§63.1206(c)(6)(iii)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1219(e)(4)Monitoring/Testing

[T]§63.1207(c)(3), (f)(1)(xi), (g)(1)(i)(B)[G]§63.1207(m)(1)-(2)

§63.1208(b)(4)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

Reporting§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)

§63.1207(f)(1)(xxvi), (m)(5)§63.1209(g)(1)(iv)(A)

§63.1210(b)(3)(i), (c)(1)(i)

No

110

Page 9: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(9 of 191)

Are yourequesting to

extrapolate metal feedrate limits from comprehensive

performance testlevels?

Comply with the following:Standard

[G]§63.1209(n)(2)(vii)Monitoring/Testing

[G]§63.1207(f)(1)(x)[G]§63.1209(n)(2)(vii)

Reporting[G]§63.1207(f)(1)(x)

109

Yes

§63.1207(f)(1)(x)§63.1209(n)(2)(vii)

No

Comply with the following:Standard

§63.1209(n)(2)(i)-(ii)Monitoring/Testing§63.1209(n)(2)(ii)

Are yourequesting to

extrapolate metal feedrate limits from comprehensive

performance testlevels?

110

§63.1207(f)(1)(x)§63.1209(n)(2)(vii)

No

Comply with the following:Standard

§63.1209(n)(2)(i)-(ii), (n)(2)(vi)Monitoring/Testing

§63.1209(n)(2)(ii), (n)(2)(vi)

Yes

117

Page 10: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(10 of 191)

Is the owner oroperator complying with theCO standard rather than the

THC standard?

111

§63.1219(a)(5)(i)

No

Comply with the following:Standard

§63.1219(a)(5)(i)[G]§63.1206(c)(6)(iii)

§63.1219(d)Monitoring/Testing[G]§63.1206(b)(6)

[T]§63.1207(c)(3), [T](g)(2)(i), (g)(2)(v)§63.1209(a)(1)(i), (a)(2), [G](a)(3)

[G]§63.1209(a)(6), (a)(7)Reporting

§63.1207(f)(2)(i)§63.1210(b)(3)(i), (c)(1)(i)

Comply with the following:Standard

§63.1219(a)(5)(ii)[G]§63.1206(c)(6)(iii)

§63.1219(d)Monitoring/Testing[G]§63.1206(b)(6)

[T]§63.1207(c)(3), [T](g)(2)(i), (g)(2)(v)§63.1209(a)(1)(i), (a)(2), [G](a)(4)

[G]§63.1209(a)(6), (a)(7)Reporting

§63.1207(f)(2)(i)§63.1210(b)(3)(i), (c)(1)(i)

Yes

117

Page 11: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(11 of 191)

112

Comply with the following:Standard

§63.1219(a)(6)[G]§63.1206(c)(6)(iii)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n)(4), (o), (o)(1)(i), [G](o)(2)-(3)

§63.1209(o)(4)§63.1219(d)

Monitoring/Testing[T]§63.1207(c)(3), (f)(1)(xi), (g)(2)(iii)

[G]§63.1207(m)(1)-(2)[G]§63.1208(b)(5)(i), (b)(5)(ii)

[G]§63.1208(b)(5)(ii)(B)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

Reporting§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)

§63.1207(f)(1)(xxv)-(xxvi), (f)(2)(iii), (m)(5)§63.1210(b)(3)(i), (c)(1)(i)

117

Page 12: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(12 of 191)

Is the owneror operator complying withalternative metal emission

requirements?

113

§63.1219(e)(1)

Yes

In lieu of complying with particulate matter standard in §63.1219(a)(7), you may electto comply with alternative metal emission

control requirements.

Comply with the following:Standard

§63.1219(a)(7)§63.1206(b)(8)(v)-(vii), [G](c)(6)(iii)

§63.1209(m), [G](m)(1)(i), [G](m)(1)(iv)[G]§63.1209(m)(2), (m)(3), (n)(3)

§63.1219(d)Monitoring/Testing

[G]§63.1206(b)(8)(iii)[T]§63.1207(c)(3), (g)(1)(i)(C), (g)(2)(iv)

§63.1208(b)(6)§63.1209(a)(1)(iii), (a)(5), (m), [G](m)(1)(i)[G]§63.1209(m)(1)(iv), [G](m)(2), (m)(3)

Reporting[G]§63.1206(b)(8)(iii)

§63.1207(f)(1)(xvii), (f)(1)(xxiii)[G]§63.1207(f)(1)(xxiv), (f)(2)(iv)

§63.1210(b)(3)(i), (c)(1)(i)

114

102

No

Comply with §63.1219(e)(2)(i) and (ii) found in the appropriate

metals paths.

Page 13: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(13 of 191)

Is thecombustor equipped with a

baghouse?

§63.1206(c)(8)(i)

Is a particulatematter detection system

being used?

§63.1206(c)(8)(i)(B)

No

Comply with the following:Standard

§63.1206(c)(8)(i)(B), [G](c)(9)

Comply with the following:Standard

§63.1206(c)(8)(i)(A), [G](c)(8)(ii)-(iii)Recordkeeping

[G]§63.1206(c)(8)(iv)Reporting

§63.1206(c)(8)(i)(A), [G](c)(8)(iv)

114

Yes

Yes No

117

Page 14: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(14 of 191)

Does the incinerator burn the

dioxin-listed hazardous wastes F020, F021, F022, F023, F026,

or F027?

115

§63.1219(c)(2)

Comply with the following:Standard

§63.1219(c)(1)[G]§63.1206(c)(6)(iii)

[G]§63.1209(j)§63.1219(c)(3)(i)-(ii)Monitoring/Testing

[T]§63.1207(c)(3), [T](f)(1)(ii)(D)[G]§63.1209(j)

Reporting§63.1207(f)(1)(ii)(D), (f)(1)(xvii), (f)(1)(xix)

§63.1210(b)(3)(i), (c)(1)(i)

Comply with the following:Standard

§63.1219(c)(2)[G]§63.1206(c)(6)(iii)

[G]§63.1209(j)§63.1219(c)(3)(i)-(ii)Monitoring/Testing

[T]§63.1207(c)(3), [T](f)(1)(ii)(D)[G]§63.1209(j)

Reporting§63.1207(f)(1)(ii)(D), (f)(1)(xvii), (f)(1)(xix)

§63.1210(b)(3)(i), (c)(1)(i)

116

No Yes

Page 15: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(15 of 191)

Did the sourceprevious testing to document

conformance with theDRE standard?

Yes

§63.1206(b)(7)(iii)

Comply with the following:Recordkeeping

[G]§63.1206(b)(7)(i)

NoComply with the following:

Monitoring/Testing[T]§63.1206(b)(7)(iii)

Does the sourcefeed hazardous waste

at a location in the combustion systemother than the normal

flame zone?

Comply with the following:Standard

§63.1206(b)(7)(ii)(A), (7)(ii)(B)(2)Yes

§63.1206(b)(7)(ii)

No

116

117

117

Page 16: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(16 of 191)

Comply with the following:Standard

[G]§63.1206(b)(5), [G](c)(1)-(5), (c)(6)(i)-(ii)[G]§63.1206(c)(6)(v)-(vi), [G](c)(7)

§63.1207(g)(1)(iii)(A), [G](k), [G](l)(1)§63.1209(c)(1), [G](c)(2), [G](d), (i), (p), [G](q)

§63.1211(c)(1)-(2), (c)(4)Monitoring/Testing

[G]§63.1206(b)(5), [G](b)(12), [G](c)(3)[T]§63.1207(a), [T](b)(1), [T][G](d)-(e)

[T][G]§63.1207(f)(1)(i), [T](f)(1)(ii)[T]§63.1207(f)(1)(ii)(A)-(C), [T][G](f)(1)(iii)

[T]§63.1207(f)(1)(iv)-(ix), [T](f)(1)(xii)[T]§63.1207(f)(1)(xxvii), (g), (g)(1)(ii)

[T][G]§63.1207(h)-(i), [T][G](l)(1)§63.1208(b)(7)-(8)

§63.1209(b)(1), [G](b)(2), (b)(3)-(4), [G](b)(5)[G]§63.1209(c)(4), [G](d), [G](f), (g)(1)(i)-(ii)

§63.1209(i), (p), [G](q), (r)Recordkeeping

[G]§63.1206(b)(5), (b)(11), [G](b)(12)[G]§63.1206(c)(1)-(5), (c)(6)(vii), [G](c)(7)

§63.1207(f)(1)(xii), (g)(1)(iii)(A)§63.1209(b)(1), [G](c)(2), [G](c)(4), [G](q)

§63.1211(b), [G](c)(3), [G](d)Reporting

[G]§63.1206(b)(5), (b)(11), [G](c)(2)-(4)[G]§63.1207(e), [G](f)(1)(i), (f)(1)(ii)§63.1207(f)(1)(ii)(A)-(C), [G](f)(1)(iii)

§63.1207(f)(1)(iv)-(ix), (f)(1)(xii), (f)(1)(xviii)§63.1207(f)(1)(xxvii), (f)(2)(v)-(x), [G](h)-(i)

[G]§63.1207(j)(1), (j)(3)-(5), [G](k)[G]§63.1207(l)(1), (l)(3)

§63.1209(c)(3), (g)(1)(i)-(ii), [G](g)(1)(iii)[G]§63.1210(a), [G](b)(1), (b)(2), (c)(2)

[G]§63.1210(c)(3)-(4), [G](d)§63.1211(a), [G](c)(3), [G](d)

§63.1212(a)

117

102

Page 17: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(17 of 191)

Dioxins,Furans

201

Pb, Cd, Se

203

204

Sb, As, Be, Cr, Co, Mn, Ni

CO, THC

205

206

209Total

Chlorine

211

210

POHC

213

PM

Hg

Applicant must go through the flowchart for each

pollutant group.

Have allpollutant paths been

completed? End

§63.1219

No

Continue through next path.

202

Page 18: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(18 of 191)

Is the incineratorequipped with either a wasteheat boiler or dry air pollution

control system?

203

§63.1219(b)(1)(i)

Yes

Comply with the following:Standard

§63.1219(b)(1)(ii)[G]§63.1206(c)(6)(iii)

[G]§63.1207(l)(2)§63.1209(k), (k)(1)(i), (k)(2)(i)-(ii)

[G]§63.1209(k)(3)-(4), (k)(5), [G](k)(6)-(9)§63.1219(d)

Monitoring/Testing[T][G]§63.1207(b)(2), [T](c)(3), (g)(1)(i)(A)

§63.1207(g)(1)(i)(B), (g)(2)(ii), (g)(2)(v)[G]§63.1208(b)(1)

§63.1209(k)(2)(i), [G](k)(3), [G](k)(8)Recordkeeping

§63.1209(k)(2)(i), [G](k)(3)[G]§63.1212(c)

Reporting§63.1207(f)(1)(xv), (f)(1)(xvii), (f)(1)(xix)[G]§63.1207(f)(1)(xx)-(xxi), (f)(1)(xxii)

§63.1207(f)(2)(ii), (j)(2)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

215

Comply with the following:Standard

§63.1219(b)(1)(i)[G]§63.1206(c)(6)(iii)

[G]§63.1207(l)(2)§63.1209(k), (k)(1)(i), (k)(2)(i)-(ii)

[G]§63.1209(k)(3)-(4), (k)(5), [G](k)(6)-(9)§63.1219(d)

Monitoring/Testing[T][G]§63.1207(b)(2), [T](c)(3), (g)(1)(i)(A)

§63.1207(g)(1)(i)(B), (g)(2)(ii), (g)(2)(v)[G]§63.1208(b)(1)

§63.1209(k)(2)(i), [G](k)(3), [G](k)(8)Recordkeeping

§63.1209(k)(2)(i), [G](k)(3)[G]§63.1212(c)

Reporting§63.1207(f)(1)(xv), (f)(1)(xvii), (f)(1)(xix)[G]§63.1207(f)(1)(xx)-(xxi), (f)(1)(xxii)

§63.1207(f)(2)(ii), (j)(2)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

No

Page 19: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(19 of 191)

204

Comply with the following:Standard

§63.1219(b)(2)[G]§63.1206(c)(6)(iii)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1219(d)

Monitoring/Testing[T]§63.1207(c)(3), (g)(1)(i)(B), [G](m)(1)-(2)

§63.1208(b)(2)§63.1209(a)(5)Recordkeeping

[G]§63.1207(m)(1)-(2)[G]§63.1212(c)

Reporting§63.1207(f)(1)(xvi), (f)(1)(xxvi), (m)(5)

§63.1209(g)(1)(iv)(B)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

Are yourequesting to

extrapolate mercury feedrate limits from comprehensive

performance testlevels?

§63.1207(f)(1)(x)§63.1209(l)(1)(v)

Comply with the following:Standard

[G]§63.1209(l)(1)(v)Monitoring/Testing

[T][G]§63.1207(f)(1)(x)Reporting

[G]§63.1207(f)(1)(x)[G]§63.1209(l)(1)(v)

Yes

No

Comply with the following:Standard

§63.1209(l), (l)(1)(i)Monitoring/Testing§63.1209(l), (l)(1)(i)

215

Page 20: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(20 of 191)

Is the owneror operator complying withalternative metal emission

requirements?

205

§63.1219(e)(1)

Yes

In lieu of complying with particulate matter standard in §63.1219(b)(7), you may elect to comply with alternative metal emission

control requirements.

Comply with the following:Standard

§63.1219(b)(3)[G]§63.1206(c)(6)(iii)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1219(d)Monitoring/Testing

[T]§63.1207(c)(3), (f)(1)(xi), (g)(1)(i)(B)[G]§63.1207(m)(1)-(2)

§63.1208(b)(3)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

[G]§63.1212(c)Reporting

§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)§63.1207(f)(1)(xxvi), (m)(5)

§63.1209(g)(1)(iv)(A)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

Comply with the following:Standard

§63.1219(e)(3)(i)[G]§63.1206(c)(6)(iii)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1219(e)(4)Monitoring/Testing

[T]§63.1207(c)(3), (f)(1)(xi), (g)(1)(i)(B)[G]§63.1207(m)(1)-(2)

§63.1208(b)(3)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

[G]§63.1212(c)Reporting

§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)§63.1207(f)(1)(xxvi), (m)(5)

§63.1209(g)(1)(iv)(A)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

207

No

Page 21: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(21 of 191)

Is the owneror operator complying withalternative metal emission

requirements?

206

§63.1219(e)(1)

Yes

In lieu of complying with particulate matter standard in §63.1219(B)(7), you may elect to comply with alternative metal emission

control requirements.

Comply with the following:Standard

§63.1219(b)(4)[G]§63.1206(c)(6)(iii)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1219(d)Monitoring/Testing

[T]§63.1207(c)(3), (f)(1)(xi), (g)(1)(i)(B)[G]§63.1207(m)(1)-(2)

§63.1208(b)(4)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

[G]§63.1212(c)Reporting

§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)§63.1207(f)(1)(xxvi), (m)(5)

§63.1209(g)(1)(iv)(A)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

Comply with the following:Standard

§63.1219(e)(3)(ii)[G]§63.1206(c)(6)(iii)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1219(e)(4)Monitoring/Testing

[T]§63.1207(c)(3), (f)(1)(xi), (g)(1)(i)(B)[G]§63.1207(m)(1)-(2)

§63.1208(b)(4)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

[G]§63.1212(c)Reporting

§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)§63.1207(f)(1)(xxvi), (m)(5)

§63.1209(g)(1)(iv)(A)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

208

No

Page 22: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(22 of 191)

Are yourequesting to

extrapolate metal feedrate limits from comprehensive

performance testlevels?

Comply with the following:Standard

[G]§63.1209(n)(2)(vii)Monitoring/Testing

[G]§63.1207(f)(1)(x)[G]§63.1209(n)(2)(vii)

Reporting[G]§63.1207(f)(1)(x)

207

Yes

§63.1207(f)(1)(x)§63.1209(n)(2)(vii)

No

Comply with the following:Standard

§63.1209(n)(2)(i)-(ii)Monitoring/Testing§63.1209(n)(2)(ii)

Are yourequesting to

extrapolate metal feedrate limits from comprehensive

performance testlevels?

208

Yes

§63.1207(f)(1)(x)§63.1209(n)(2)(vii)

No

Comply with the following:Standard

§63.1209(n)(2)(i)-(ii), (n)(2)(vi)Monitoring/Testing

§63.1209(n)(2)(ii), (n)(2)(vi)

215

Page 23: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(23 of 191)

Is the owner oroperator complying with theCO standard rather than the

THC standard?

209

§63.1219(b)(5)(i)

Comply with the following:Standard

§63.1219(b)(5)(i)[G]§63.1206(c)(6)(iii)

§63.1219(d)Monitoring/Testing[G]§63.1206(b)(6)

[T]§63.1207(c)(3), [T](g)(2)(i), (g)(2)(v)§63.1209(a)(1)(i), (a)(2), [G](a)(3)

[G]§63.1209(a)(6), (a)(7)Recordkeeping[G]§63.1212(c)

Reporting§63.1207(f)(2)(i)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

Comply with the following:Standard

§63.1219(b)(5)(ii)[G]§63.1206(c)(6)(iii)

§63.1219(d)Monitoring/Testing[G]§63.1206(b)(6)

[T]§63.1207(c)(3), [T](g)(2)(i), (g)(2)(v)§63.1209(a)(1)(i), (a)(2), [G](a)(4)

[G]§63.1209(a)(6), (a)(7)Recordkeeping[G]§63.1212(c)

Reporting§63.1207(f)(2)(i)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

Yes No

215

Page 24: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(24 of 191)

210

Comply with the following:Standard

§63.1219(b)(6)[G]§63.1206(c)(6)(iii)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n)(4), (o), (o)(1)(i)[G]§63.1209(o)(2)-(3), (o)(4)

§63.1219(d)Monitoring/Testing

[T]§63.1207(c)(3), (f)(1)(xi), (g)(2)(iii)[G]§63.1207(m)(1)-(2)

[G]§63.1208(b)(5)(i), (b)(5)(ii)[G]§63.1208(b)(5)(ii)(B)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

[G]§63.1212(c)Reporting

§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)§63.1207(f)(1)(xxv)-(xxvi), (f)(2)(iii), (m)(5)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

215

Page 25: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(25 of 191)

Is the owneror operator complying withalternative metal emission

requirements?

211

§63.1219(e)(1)

Yes

In lieu of complying with particulate matter standard in §63.1219(b)(7), you may elect to

comply with alternative metal emission control requirements.

Comply with the following:Standard

§63.1219(b)(7)§63.1206(b)(8)(v)-(vii), [G](c)(6)(iii)

§63.1209(m), [G](m)(1)(i), [G](m)(1)(iv)[G]§63.1209(m)(2), (m)(3), (n)(3)

§63.1219(d)Monitoring/Testing

[G]§63.1206(b)(8)(iii)[T]§63.1207(c)(3), (g)(1)(i)(C), (g)(2)(iv)

§63.1208(b)(6)§63.1209(a)(1)(iii), (a)(5), (m), [G](m)(1)(i)[G]§63.1209(m)(1)(iv), [G](m)(2), (m)(3)

Recordkeeping[G]§63.1212(c)

Reporting[G]§63.1206(b)(8)(iii)

§63.1207(f)(1)(xvii), (f)(1)(xxiii)[G]§63.1207(f)(1)(xxiv), (f)(2)(iv)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

212

202

No

Comply with §63.1219(e)(3)(i) and (ii) found in the appropriate

metals paths.

Page 26: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(26 of 191)

Is thecombustor equipped with a

baghouse?

§63.1206(c)(8)(i)

Is a particulatematter detection system

being used?

§63.1206(c)(8)(i)(B)

No

Comply with the following:Standard

§63.1206(c)(8)(i)(B), [G](c)(9)

Comply with the following:Standard

§63.1206(c)(8)(i)(A), [G](c)(8)(ii)-(iii)Recordkeeping

[G]§63.1206(c)(8)(iv)Reporting

§63.1206(c)(8)(i)(A), [G](c)(8)(iv)

212

Yes

NoYes

215

Page 27: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(27 of 191)

213

§63.1219(c)(2)

Comply with the following:Standard

§63.1219(c)(1)[G]§63.1206(c)(6)(iii)

[G]§63.1209(j)§63.1219(c)(3)(i)-(ii)Monitoring/Testing

[T]§63.1207(c)(3), [T](f)(1)(ii)(D)[G]§63.1209(j)Recordkeeping[G]§63.1212(c)

Reporting§63.1207(f)(1)(ii)(D), (f)(1)(xvii), (f)(1)(xix)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

Comply with the following:Standard

§63.1219(c)(2)[G]§63.1206(c)(6)(iii)

[G]§63.1209(j)§63.1219(c)(3)(i)-(ii)Monitoring/Testing

[T]§63.1207(c)(3), [T](f)(1)(ii)(D)[G]§63.1209(j)Recordkeeping[G]§63.1212(c)

Reporting§63.1207(f)(1)(ii)(D), (f)(1)(xvii), (f)(1)(xix)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

214

Does the incinerator burn the

dioxin-listed hazardous wastes F020, F021, F022, F023,

F026, or F027?

No Yes

Page 28: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(28 of 191)

Did the sourceprevious testing to document

conformance with theDRE standard?

Yes

§63.1206(b)(7)(iii)

Comply with the following:Recordkeeping

[G]§63.1206(b)(7)(i)

NoComply with the following:

Monitoring/Testing[T]§63.1206(b)(7)(iii)

Does the sourcefeed hazardous waste at

a location in the combustion systemother than the normal

flame zone?

Comply with the following:Standard

§63.1206(b)(7)(ii)(A), (7)(ii)(B)(2)Yes

§63.1206(b)(7)(ii)

No

214

215

215

Page 29: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(29 of 191)

Comply with the following:Standard

[G]§63.1206(b)(5), [G](c)(1)-(5), (c)(6)(i)-(ii)[G]§63.1206(c)(6)(v)-(vi), [G](c)(7)

§63.1207(g)(1)(iii)(A), [G](k), [G](l)(1)§63.1209(c)(1), [G](c)(2), [G](d), (i), (p), [G](q)

§63.1211(c)(1)-(2), (c)(4)Monitoring/Testing

[G]§63.1206(b)(5), [G](b)(12), [G](c)(3)[T]§63.1207(a), [T](b)(1), [T][G](d)-(e)

[T][G]§63.1207(f)(1)(i), [T](f)(1)(ii)[T]§63.1207(f)(1)(ii)(A)-(C), [T][G](f)(1)(iii)

[T]§63.1207(f)(1)(iv)-(ix), [T](f)(1)(xii)[T]§63.1207(f)(1)(xxvii), (g), (g)(1)(ii)

[T][G]§63.1207(h)-(i), [T][G](l)(1)§63.1208(b)(7)-(8)

§63.1209(b)(1), [G](b)(2), (b)(3)-(4), [G](b)(5)[G]§63.1209(c)(4), [G](d), [G](f), (g)(1)(i)-(ii)

§63.1209(i), (p), [G](q), (r)Recordkeeping

[G]§63.1206(b)(5), (b)(11), [G](b)(12)[G]§63.1206(c)(1)-(5), (c)(6)(vii), [G](c)(7)

§63.1207(f)(1)(xii), (g)(1)(iii)(A)§63.1209(b)(1), [G](c)(2), [G](c)(4), [G](q)

§63.1211(b), [G](c)(3), [G](d)Reporting

[G]§63.1206(b)(5), (b)(11), [G](c)(2)-(4)[G]§63.1207(e), [G](f)(1)(i), (f)(1)(ii)§63.1207(f)(1)(ii)(A)-(C), [G](f)(1)(iii)

§63.1207(f)(1)(iv)-(ix), (f)(1)(xii), (f)(1)(xviii)§63.1207(f)(1)(xxvii), (f)(2)(v)-(x), [G](h)-(i)

[G]§63.1207(j)(1), (j)(3)-(5), [G](k)[G]§63.1207(l)(1), (l)(3)

§63.1209(c)(3), (g)(1)(i)-(ii), [G](g)(1)(iii)[G]§63.1210(a), [G](b)(1), (b)(2), (c)(2)

[G]§63.1210(c)(3)-(4), [G](d)§63.1211(a), [G](c)(3), [G](d)

§63.1212(a)

215

202

Page 30: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(30 of 191)

Dioxins,Furans

301

Pb, Cd, Se

303

304

Sb, As, Be, Cr, Co, Mn, Ni

CO, THC

307

308

311Total

Chlorine

318

317

POHC

321

PM

Hg

Applicant must go through the flowchart for each

pollutant group.

PM(Opacity) 320

Have allpollutant paths been

completed? End

§63.1220

No

Continue through next path.

302

Page 31: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(31 of 191)

303

Is the combustion gas temperature at the inlet

to the initial particulate matter control device 400 deg. F or lower based on

the average of the test run averages?

§63.1220(a)(1)(ii)

Comply with the following:Standard

§63.1220(a)(1)(i)[G]§63.1206(c)(6)(iv)

[G]§63.1207(l)(2)§63.1209(k), (k)(1)(i), (k)(2)(ii)

[G]§63.1209(k)(3)-(4), (k)(5), [G](k)(6)-(9)§63.1220(f)

Monitoring/Testing[T][G]§63.1207(b)(2), [T](c)(3), (g)(1)(i)(A)

§63.1207(g)(2)(ii), (g)(2)(v)[G]§63.1208(b)(1)

[G]§63.1209(k)(3), [G](k)(8)Recordkeeping

[G]§63.1209(k)(3)Reporting

§63.1207(f)(1)(xv), (f)(1)(xvii), (f)(1)(xix)[G]§63.1207(f)(1)(xx)-(xxi), (f)(1)(xxii)

§63.1207(f)(2)(ii), (j)(2)§63.1210(b)(3)(i), (c)(1)(i)

Comply with the following:Standard

§63.1220(a)(1)(ii)[G]§63.1206(c)(6)(iv)

[G]§63.1207(l)(2)§63.1209(k), (k)(1)(i), (k)(2)(ii)

[G]§63.1209(k)(3)-(4), (k)(5), [G](k)(6)-(9)§63.1220(f)

Monitoring/Testing[T][G]§63.1207(b)(2), [T](c)(3), (g)(1)(i)(A)

§63.1207(g)(2)(ii), (g)(2)(v)[G]§63.1208(b)(1)

[G]§63.1209(k)(3), [G](k)(8)Recordkeeping

[G]§63.1209(k)(3)Reporting

§63.1207(f)(1)(xv), (f)(1)(xvii), (f)(1)(xix)[G]§63.1207(f)(1)(xx)-(xxi), (f)(1)(xxii)

§63.1207(f)(2)(ii), (j)(2)§63.1210(b)(3)(i), (c)(1)(i)

303A

No Yes

Page 32: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(32 of 191)

Does the kilnhave in-line kiln raw mill

with dual stacks?Yes

Comply with the following:Standard

§63.1220(d)(1)(iv)Monitoring/Testing§63.1220(d)(1)(v)

Reporting§63.1220(d)(1)(v)

No

§63.1220(d)

303A

323

Page 33: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(33 of 191)

304

Comply with the following:Standard

§63.1220(a)(2)(i)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(4)§63.1220(f)

Monitoring/Testing[T]§63.1207(c)(3), [G](m)(1)-(2)

§63.1208(b)(2)§63.1209(a)(5)Recordkeeping

[G]§63.1207(m)(1)-(2)Reporting

§63.1207(f)(1)(xvi), (f)(1)(xxvi), (m)(5)§63.1209(g)(1)(iv)(B)

§63.1210(b)(3)(i), (c)(1)(i)

Has an alternativestandards petition for Hg

been submitted to theAdministrator?

§63.1206(b)(10)(i)

No

Comply with the following:Standard

§63.1206(b)(10)(i)§63.1206(b)(10)(iii), [G](b)(10)(vii)

Reporting[G]§63.1206(b)(10)(iv), (b)(10)(v)-(vi)

Yes

302

Is theMTEC used as a

limit?

§63.1220(a)(2)(ii)(B)

Comply with the following:Standard

§63.1220(a)(2)(ii)(B)

Comply with the following:Standard

§63.1220(a)(2)(ii)(A)305

306

No

Yes

Page 34: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(34 of 191)

Are yourequesting to

extrapolate mercury feedrate limits from comprehensive

performance testlevels?

Comply with the following:Standard

[G]§63.1209(l)(1)(v)Monitoring/Testing

[G]§63.1207(f)(1)(x)Reporting

[G]§63.1207(f)(1)(x)[G]§63.1209(l)(1)(v)

305

Yes

§63.1207(f)(1)(x)§63.1209(l)(1)(v)

No

Comply with the following:Standard

§63.1209(l), [G](l)(1)(iii)(A)§63.1209(l)(1)(iii)(B)Monitoring/Testing

§63.1209(l), [G](l)(1)(iii)(A)§63.1209(l)(1)(iii)(B)

Are yourequesting to

extrapolate mercury feedrate limits from comprehensive

performance testlevels?

306

Yes

§63.1207(f)(1)(x)§63.1209(l)(1)(v)

No

Comply with the following:Standard

§63.1209(l), [G](l)(1)(iii)(A)§63.1209(l)(1)(iii)(B)

[G]§63.1209(l)(1)(iii)(C)-(D)Monitoring/Testing

§63.1209(l), [G](l)(1)(iii)(A)§63.1209(l)(1)(iii)(B)

[G]§63.1209(l)(1)(iii)(C)-(D)

323

Page 35: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(35 of 191)

307

Comply with the following:Standard

[G]§63.1220(a)(3)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1220(f)Monitoring/Testing

[T]§63.1207(c)(3), (f)(1)(xi), [G](m)(1)-(2)§63.1208(b)(3)

§63.1209(a)(5), (c)(5)Recordkeeping

[G]§63.1207(m)(1)-(2)Reporting

§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)§63.1207(f)(1)(xxvi), (m)(5)

§63.1209(g)(1)(iv)(A)§63.1210(b)(3)(i), (c)(1)(i)

309

Has analternative standards

petition for semivolatile metals been submitted to theAdministrator?

§63.1206(b)(10)(i)

Comply with the following:Standard

§63.1206(b)(10)(i)§63.1206(b)(10)(iii), [G](b)(10)(vii)

Reporting[G]§63.1206(b)(10)(iv), (b)(10)(v)-(vi)

YesNo

302

Page 36: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(36 of 191)

308

Comply with the following:Standard

[G]§63.1220(a)(4)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1220(f)Monitoring/Testing

[T]§63.1207(c)(3), (f)(1)(xi), [G](m)(1)-(2)§63.1208(b)(4)

§63.1209(a)(5), (c)(5)Recordkeeping

[G]§63.1207(m)(1)-(2)Reporting

§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)§63.1207(f)(1)(xxvi), (m)(5)

§63.1209(g)(1)(iv)(A)§63.1210(b)(3)(i), (c)(1)(i)

310

Has analternative standards

petition for low volatile metals been submitted to theAdministrator?

§63.1206(b)(10)(i)

Comply with the following:Standard

§63.1206(b)(10)(i)§63.1206(b)(10)(iii), [G](b)(10)(vii)

Reporting[G]§63.1206(b)(10)(iv), (b)(10)(v)-(vi)

YesNo

302

Page 37: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(37 of 191)

Are yourequesting to

extrapolate metal feedrate limits from comprehensive

performance testlevels?

Comply with the following:Standard

[G]§63.1209(n)(2)(vii)Monitoring/Testing

[G]§63.1207(f)(1)(x)[G]§63.1209(n)(2)(vii)

Reporting[G]§63.1207(f)(1)(x)

309

Yes

§63.1207(f)(1)(x)§63.1209(n)(2)(vii)

No

Comply with the following:Standard

§63.1209(n)(2)(i), [G](n)(2)(iii)Monitoring/Testing

[G]§63.1209(n)(2)(iii)

Are yourequesting to

extrapolate metal feedrate limits from comprehensive

performance testlevels?

310

Yes

§63.1207(f)(1)(x)§63.1209(n)(2)(vii)

No

Comply with the following:Standard

§63.1209(n)(2)(i), [G](n)(2)(iii)§63.1209(n)(2)(vi)Monitoring/Testing

[G]§63.1209(n)(2)(iii), (n)(2)(vi)

323

Page 38: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(38 of 191)

311

Does thecement kiln feed

hazardous waste at a locationother than the end where products are

normally discharged and wherefuels are normally

fired?

§63.1206(b)(13)

Yes

Is hazardouswaste only fired upstream

of the bypass duct and at the kilnend where products

are discharged?

§63.1206(b)(13)(i)(A)(3)

Yes

314

No

Are hydrocarbonsmonitored at the by-pass duct and

preheater tower?

§63.1206(b)(13)(i)(A)(2)

Yes

315

No

316

Is the kilnequipped with a by-pass duct

or midkiln gas samplingsystem?

§63.1220(a)(5)(i)

Yes

312

313

No

No

Page 39: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(39 of 191)

Is the owner oroperator complying with theCO standard rather than the

THC standard?

312

§63.1220(a)(5)(i)(A)

Comply with the following:Standard

§63.1220(a)(5)(i)(A)[G]§63.1206(c)(6)(iv)

§63.1220(f)Monitoring/Testing[G]§63.1206(b)(6)

[T]§63.1207(c)(3), [T](g)(2)(i), (g)(2)(v)§63.1209(a)(1)(i), (a)(2), [G](a)(3)

[G]§63.1209(a)(6), (a)(7)Reporting

§63.1207(f)(2)(i)§63.1210(b)(3)(i), (c)(1)(i)

Comply with the following:Standard

§63.1220(a)(5)(i)(B)[G]§63.1206(c)(6)(iv)

§63.1220(f)Monitoring/Testing[G]§63.1206(b)(6)

[T]§63.1207(c)(3), [T](g)(2)(i), (g)(2)(v)§63.1209(a)(1)(i), (a)(2), [G](a)(4)

[G]§63.1209(a)(6), (a)(7)Reporting

§63.1207(f)(2)(i)§63.1210(b)(3)(i), (c)(1)(i)

Yes No

323

Page 40: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(40 of 191)

Is the owner oroperator complying with theCO standard rather than the

THC standard?

313

§63.1220(a)(5)(ii)(B)

No

Comply with the following:Standard

§63.1220(a)(5)(ii)(B)[G]§63.1206(c)(6)(iv)

§63.1220(f)Monitoring/Testing[G]§63.1206(b)(6)

[T]§63.1207(c)(3), [T](g)(2)(i), (g)(2)(v)§63.1209(a)(1)(i), (a)(2), [G](a)(3)

[G]§63.1209(a)(6), (a)(7)Reporting

§63.1207(f)(2)(i)§63.1210(b)(3)(i), (c)(1)(i)

Comply with the following:Standard

§63.1220(a)(5)(ii)(A)[G]§63.1206(c)(6)(iv)

§63.1220(f)Monitoring/Testing[G]§63.1206(b)(6)

[T]§63.1207(c)(3), [T](g)(2)(i), (g)(2)(v)§63.1209(a)(1)(i), (a)(2), [G](a)(4)

[G]§63.1209(a)(6), (a)(7)Reporting

§63.1207(f)(2)(i)§63.1210(b)(3)(i), (c)(1)(i)

Yes

323

Page 41: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(41 of 191)

314

Comply with the following:Standard

§63.1206(b)(13)(i)(A)(3)[G]§63.1206(c)(6)(iv)Monitoring/Testing[G]§63.1206(b)(6)

[T]§63.1207(c)(3), [T](g)(2)(i), (g)(2)(v)§63.1209(a)(1)(i), (a)(2), [G](a)(3)

[G]§63.1209(a)(6), (a)(7)Reporting

§63.1207(f)(2)(i)§63.1210(b)(3)(i), (c)(1)(i)

315

Comply with the following:Standard

§63.1206(b)(13)(i)(A)(2)[G]§63.1206(c)(6)(iv)Monitoring/Testing[G]§63.1206(b)(6)

[T]§63.1207(c)(3), [T](g)(2)(i), (g)(2)(v)§63.1209(a)(1)(i), (a)(2), [G](a)(4)

[G]§63.1209(a)(6), (a)(7)Reporting

§63.1207(f)(2)(i)§63.1210(b)(3)(i), (c)(1)(i)

323

Page 42: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(42 of 191)

316

Comply with the following:Standard

§63.1206(b)(13)(i)(A)(1)[G]§63.1206(c)(6)(iv)Monitoring/Testing[G]§63.1206(b)(6)

[T]§63.1207(c)(3), [T](g)(2)(i), (g)(2)(v)§63.1209(a)(1)(i), (a)(2), [G](a)(4)

[G]§63.1209(a)(6), (a)(7)Reporting

§63.1207(f)(2)(i)§63.1210(b)(3)(i), (c)(1)(i)

323

Page 43: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(43 of 191)

317

Comply with the following:Standard

§63.1220(a)(6)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n)(4), (o), (o)(1)(i)[G]§63.1209(o)(2)-(3), (o)(4)

§63.1220(f)Monitoring/Testing

[T]§63.1207(c)(3), (f)(1)(xi), (g)(2)(iii)[G]§63.1207(m)(1)-(2)

[G]§63.1208(b)(5)(i), (b)(5)(ii), (b)(5)(ii)(A)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

Reporting§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)

§63.1207(f)(1)(xxv)-(xxvi), (f)(2)(iii), (m)(5)§63.1210(b)(3)(i), (c)(1)(i)

Has an alternativestandards petition for

hydrogen chloride/chlorine gas been submitted to the

Administrator?

§63.1206(b)(10)(i)

Comply with the following:Standard

§63.1206(b)(10)(i)§63.1206(b)(10)(iii), [G](b)(10)(vii)

Reporting[G]§63.1206(b)(10)(iv), (b)(10)(v)-(vi)

YesNo

323

302

Page 44: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(44 of 191)

318

Comply with the following:Standard

§63.1220(a)(7)(i)§63.1206(b)(8)(v)-(vii), [G](c)(6)(iv)

§63.1209(m), [G](m)(1)(i), [G](m)(1)(iv)[G]§63.1209(m)(2), (n)(3)

§63.1220(f)Monitoring/Testing

[G]§63.1206(b)(8)(iii)[T]§63.1207(c)(3), (g)(1)(i)(C), (g)(1)(iii)(B)

§63.1207(g)(2)(iv)§63.1208(b)(6)

§63.1209(a)(1)(iii), (a)(5), [G](m)(1)(i)[G]§63.1209(m)(1)(iv), [G](m)(2)

Recordkeeping§63.1207(g)(1)(iii)(B)

Reporting[G]§63.1206(b)(8)(iii)

§63.1207(f)(1)(xvii), (f)(1)(xxiii)[G]§63.1207(f)(1)(xxiv), (f)(2)(iv)

§63.1210(b)(3)(i), (c)(1)(i)

319

Page 45: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(45 of 191)

Is thecombustor equipped with a

baghouse?

§63.1206(c)(8)(i)

Is a particulatematter detection system

being used?

§63.1206(c)(8)(i)(B)

NoComply with the following:

Standard§63.1206(c)(8)(i)(B), [G](c)(9)

Comply with the following:Standard

§63.1206(c)(8)(i)(A), [G](c)(8)(ii)-(iii)Recordkeeping

[G]§63.1206(c)(8)(iv)Reporting

§63.1206(c)(8)(i)(A), [G](c)(8)(iv)

Yes

319

NoYes

323

Page 46: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(46 of 191)

Is the sourceequipped with leak detection

under §63.1206(c)(8) or particulatematter detection under

§63.1206(c)(9)?

320

§63.1220(a)(7)(ii)

Yes

Comply with the following:Standard

§63.1220(a)(7)(ii)§63.1206(b)(8)(v)-(vii), [G](c)(6)(iv)

§63.1220(f)Monitoring/Testing

[G]§63.1206(b)(8)(iii)[T]§63.1207(c)(3)

§63.1208(b)(9)§63.1209(a)(2)

Reporting[G]§63.1206(b)(8)(iii)§63.1207(f)(1)(xvii)

§63.1210(b)(3)(i), (c)(1)(i)

Sources equipped with a bag leak detection system under

§63.1206(c)(8) or a particulate matter detection system under §63.1206(c)(9) are not subject

to opacity standards.

No

323

302

Page 47: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(47 of 191)

Does theincinerator burn the

dioxin-listed hazardous wastes F020, F021, F022, F023, F026,

or F027?

321

§63.1220(c)(2)

Comply with the following:Standard

§63.1220(c)(1)[G]§63.1206(c)(6)(iv)

[G]§63.1209(j)§63.1220(c)(3)(i)-(ii)Monitoring/Testing

[T]§63.1207(c)(3), [T](f)(1)(ii)(D)[G]§63.1209(j)

Reporting§63.1207(f)(1)(ii)(D)

§63.1207(f)(1)(xvii), (f)(1)(xix)§63.1210(b)(3)(i)-(ii), (c)(1)(i)-(ii)

Comply with the following:Standard

§63.1220(c)(2)[G]§63.1206(c)(6)(iv)

[G]§63.1209(j)§63.1220(c)(3)(i)-(ii)Monitoring/Testing

[T]§63.1207(c)(3), [T](f)(1)(ii)(D)[G]§63.1209(j)

Reporting§63.1207(f)(1)(ii)(D)

§63.1207(f)(1)(xvii), (f)(1)(xix)§63.1210(b)(3)(i)-(ii), (c)(1)(i)-(ii)

322

YesNo

Page 48: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(48 of 191)

Did the sourceprevious testing to document

conformance with theDRE standard?

Yes

§63.1206(b)(7)(iii)

Comply with the following:Recordkeeping

[G]§63.1206(b)(7)(i)

NoComply with the following:

Monitoring/Testing[T]§63.1206(b)(7)(iii)

Does the sourcefeed hazardous waste at a

location in the combustion systemother than the normal

flame zone?

Comply with the following:Standard

§63.1206(b)(7)(ii)(A)[G]§63.1206(b)(7)(ii)(B)(1)

§63.1206(b)(7)(ii)(B)(2)

Yes

§63.1206(b)(7)(ii)

No

322

323

323

Page 49: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(49 of 191)

323

324

Comply with the following:Standard

[G]§63.1206(b)(5), [G](c)(1)-(5), (c)(6)(i)-(ii)[G]§63.1206(c)(6)(v)-(vi), [G](c)(7)

§63.1207(g)(1)(iii)(A), [G](k), [G](l)(1)§63.1209(c)(1), [G](c)(2), [G](d), (i), (p), [G](q)

§63.1211(c)(1)-(2), (c)(4)Monitoring/Testing

[G]§63.1206(b)(5), [G](b)(12), [G](c)(3)[T]§63.1207(a), [T](b)(1), [T][G](d)-(e)

[T][G]§63.1207(f)(1)(i), [T](f)(1)(ii)[T]§63.1207(f)(1)(ii)(A)-(C), [T][G](f)(1)(iii)

[T]§63.1207(f)(1)(iv)-(ix), [T](f)(1)(xii)[T]§63.1207(f)(1)(xxvii), (g), (g)(1)(ii)

[T][G]§63.1207(h)-(i), [T][G](l)(1)§63.1208(b)(7)-(8)

§63.1209(b)(1), [G](b)(2), (b)(3)-(4), [G](b)(5)[G]§63.1209(c)(4), [G](d), [G](f), (g)(1)(i)-(ii)

§63.1209(i), (p), [G](q), (r)Recordkeeping

[G]§63.1206(b)(5), (b)(11), [G](b)(12)[G]§63.1206(c)(1)-(5), (c)(6)(vii), [G](c)(7)

§63.1207(f)(1)(xii), (g)(1)(iii)(A)§63.1209(b)(1), [G](c)(2), [G](c)(4), [G](q)

§63.1211(b), [G](c)(3), [G](d)Reporting

[G]§63.1206(b)(5), (b)(11), [G](c)(2)-(4)[G]§63.1207(e), [G](f)(1)(i), (f)(1)(ii)§63.1207(f)(1)(ii)(A)-(C), [G](f)(1)(iii)

§63.1207(f)(1)(iv)-(ix), (f)(1)(xii), (f)(1)(xviii)§63.1207(f)(1)(xxvii), (f)(2)(v)-(x), [G](h)-(i)

[G]§63.1207(j)(1), (j)(3)-(5), [G](k)[G]§63.1207(l)(1), (l)(3)

§63.1209(c)(3), (g)(1)(i)-(ii), [G](g)(1)(iii)[G]§63.1210(a), [G](b)(1), (b)(2), (c)(2)

[G]§63.1210(c)(3)-(4), [G](d)§63.1211(a), [G](c)(3), [G](d)

§63.1212(a)

Page 50: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(50 of 191)

Does thekiln have in-line kiln

raw mill?

§63.1220(d)Yes

Is the kilnpreheater or preheater/

precalciner kiln withdual stacks?

324

Comply with the following:Monitoring/Testing

§63.1220(d)(1)(i), (d)(1)(iii)Recordkeeping

§63.1220(d)(1)(ii)

§63.1220(e)

Yes

Comply with the following:Monitoring/Testing

§63.1220(e)(1)

No

No

302

Page 51: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(51 of 191)

Dioxins,Furans

401

Pb, Cd, Se

403

404

Sb, As, Be, Cr, Co, Mn, Ni

CO, THC

407

408

411Total

Chlorine

418

417

POHC

421

PM

Hg

Applicant must go through the flowchart for each

pollutant group.

PM(Opacity) 420

Have allpollutant paths been

completed? End

§63.1220

No

Continue through next path.

402

Page 52: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(52 of 191)

403

Is thecombustion gas

temperature at the inlet to theinitial particulate matter control device 400

deg. F or lower based on the average of the test run

averages?

§63.1220(b)(1)(ii)

Comply with the following:Standard

§63.1220(b)(1)(i)[G]§63.1206(c)(6)(iv)

[G]§63.1207(l)(2)§63.1209(k), (k)(1)(i), (k)(2)(ii)

[G]§63.1209(k)(3)-(4), (k)(5), [G](k)(6)-(9)§63.1220(f)

Monitoring/Testing[T][G]§63.1207(b)(2), [T](c)(3)

§63.1207(g)(1)(i)(A), (g)(2)(ii), (g)(2)(v)[G]§63.1208(b)(1)

[G]§63.1209(k)(3), [G](k)(8)Recordkeeping

[G]§63.1209(k)(3)[G]§63.1212(c)

Reporting§63.1207(f)(1)(xv), (f)(1)(xvii), (f)(1)(xix)[G]§63.1207(f)(1)(xx)-(xxi), (f)(1)(xxii)

§63.1207(f)(2)(ii), (j)(2)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

Comply with the following:Standard

§63.1220(b)(1)(ii)[G]§63.1206(c)(6)(iv)

[G]§63.1207(l)(2)§63.1209(k), (k)(1)(i), (k)(2)(ii)

[G]§63.1209(k)(3)-(4), (k)(5), [G](k)(6)-(9)§63.1220(f)

Monitoring/Testing[T][G]§63.1207(b)(2), [T](c)(3)

§63.1207(g)(1)(i)(A), (g)(2)(ii), (g)(2)(v)[G]§63.1208(b)(1)

[G]§63.1209(k)(3), [G](k)(8)Recordkeeping

[G]§63.1209(k)(3)[G]§63.1212(c)

Reporting§63.1207(f)(1)(xv), (f)(1)(xvii), (f)(1)(xix)[G]§63.1207(f)(1)(xx)-(xxi), (f)(1)(xxii)

§63.1207(f)(2)(ii), (j)(2)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

403A

YesNo

Page 53: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(53 of 191)

Does the kilnhave in-line kiln raw mill with

dual stacks?Yes

Comply with the following:Standard

§63.1220(d)(1)(iv)Monitoring/Testing§63.1220(d)(1)(v)

Reporting§63.1220(d)(1)(v)

No

§63.1220(d)

403A

423

Page 54: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(54 of 191)

404

Comply with the following:Standard

§63.1220(b)(2)(i)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(4)§63.1220(f)

Monitoring/Testing[T]§63.1207(c)(3), [G](m)(1)-(2)

§63.1208(b)(2)§63.1209(a)(5)Recordkeeping

[G]§63.1207(m)(1)-(2)[G]§63.1212(c)

Reporting§63.1207(f)(1)(xvi), (f)(1)(xxvi), (m)(5)

§63.1209(g)(1)(iv)(B)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

Has an alternativestandards petition for Hg

been submitted to theAdministrator?

§63.1206(b)(10)(i)

No

Comply with the following:Standard

§63.1206(b)(10)(i)§63.1206(b)(10)(iii), [G](b)(10)(vii)

Reporting[G]§63.1206(b)(10)(iv), (b)(10)(v)-(vi)

Yes

402

405Is the

MTEC used as alimit?

§63.1220(b)(2)(ii)(B)

YesComply with the following:

Standard§63.1220(b)(2)(ii)(B)

Comply with the following:Standard

§63.1220(b)(2)(ii)(A)No

406

Page 55: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(55 of 191)

Are yourequesting to

extrapolate mercury feedrate limits from comprehensive

performance testlevels?

Comply with the following:Standard

[G]§63.1209(l)(1)(v)Monitoring/Testing

[G]§63.1207(f)(1)(x)Reporting

[G]§63.1207(f)(1)(x)[G]§63.1209(l)(1)(v)

405

Yes

§63.1207(f)(1)(x)§63.1209(l)(1)(v)

No

Comply with the following:Standard

§63.1209(l), [G](l)(1)(iii)(A)§63.1209(l)(1)(iii)(B)Monitoring/Testing

§63.1209(l), [G](l)(1)(iii)(A)§63.1209(l)(1)(iii)(B)

Are yourequesting to

extrapolate mercury feedrate limits from comprehensive

performance testlevels?

406

Yes

§63.1207(f)(1)(x)§63.1209(l)(1)(v)

No

Comply with the following:Standard

§63.1209(l), [G](l)(1)(iii)(A)§63.1209(l)(1)(iii)(B)

[G]§63.1209(l)(1)(iii)(C)-(D)Monitoring/Testing

§63.1209(l), [G](l)(1)(iii)(A)§63.1209(l)(1)(iii)(B)

[G]§63.1209(l)(1)(iii)(C)-(D)

423

Page 56: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(56 of 191)

407

Comply with the following:Standard

[G]§63.1220(b)(3)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1220(f)Monitoring/Testing

[T]§63.1207(c)(3), (f)(1)(xi), [G](m)(1)-(2)§63.1208(b)(3)

§63.1209(a)(5), (c)(5)Recordkeeping

[G]§63.1207(m)(1)-(2)[G]§63.1212(c)

Reporting§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)

§63.1207(f)(1)(xxvi), (m)(5)§63.1209(g)(1)(iv)(A)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

409

Has analternative standards

petition for semivolatile metals been submitted to theAdministrator?

§63.1206(b)(10)(i)

Comply with the following:Standard

§63.1206(b)(10)(i)§63.1206(b)(10)(iii), [G](b)(10)(vii)

Reporting[G]§63.1206(b)(10)(iv), (b)(10)(v)-(vi)

Yes

402

No

Page 57: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(57 of 191)

408

Comply with the following:Standard

[G]§63.1220(b)(4)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1220(f)Monitoring/Testing

[T]§63.1207(c)(3), (f)(1)(xi), [G](m)(1)-(2)§63.1208(b)(4)

§63.1209(a)(5), (c)(5)Recordkeeping

[G]§63.1207(m)(1)-(2)[G]§63.1212(c)

Reporting§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)

§63.1207(f)(1)(xxvi), (m)(5)§63.1209(g)(1)(iv)(A)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

410

Has analternative standards

petition for low volatile metals been submitted to theAdministrator?

§63.1206(b)(10)(i)

Comply with the following:Standard

§63.1206(b)(10)(i)§63.1206(b)(10)(iii), [G](b)(10)(vii)

Reporting[G]§63.1206(b)(10)(iv), (b)(10)(v)-(vi)

Yes

402

No

Page 58: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(58 of 191)

Are yourequesting to

extrapolate metal feedrate limits from comprehensive

performance testlevels?

Comply with the following:Standard

[G]§63.1209(n)(2)(vii)Monitoring/Testing

[T][G]§63.1207(f)(1)(x)[G]§63.1209(n)(2)(vii)

Reporting[G]§63.1207(f)(1)(x)

409

Yes

§63.1207(f)(1)(x)§63.1209(n)(2)(vii)

No

Comply with the following:Standard

§63.1209(n)(2)(i), [G](n)(2)(iii)Monitoring/Testing

[G]§63.1209(n)(2)(iii)

Are yourequesting to

extrapolate metal feedrate limits from comprehensive

performance testlevels?

410

Yes

§63.1207(f)(1)(x)§63.1209(n)(2)(vii)

No

Comply with the following:Standard

§63.1209(n)(2)(i), [G](n)(2)(iii)§63.1209(n)(2)(vi)Monitoring/Testing

[G]§63.1209(n)(2)(iii), (n)(2)(vi)

423

Page 59: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(59 of 191)

411

Does thecement kiln feed

hazardous waste at a locationother than the end where products are

normally discharged and wherefuels are normally

fired?

§63.1206(b)(13)

Yes

Is hazardouswaste only fired upstream

of the bypass duct and at the kilnend where products

are discharged?

§63.1206(b)(13)(i)(B)(3)

Yes

414

No

Are hydrocarbonsmonitored at the by-pass duct and

preheater tower?

§63.1206(b)(13)(i)(B)(2)

Yes

415No

416

Is the kilnequipped with a by-pass duct

or midkiln gas samplingsystem?

§63.1220(b)(5)(i)

Yes

412

413

No

No

Page 60: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(60 of 191)

Is the owner oroperator complying with theCO standard rather than the

THC standard?

412

§63.1220(b)(5)(i)(A)(1)

Yes

No

Comply with the following:Standard

§63.1220(b)(5)(i)(A)(1)[G]§63.1206(c)(6)(iv)

§63.1220(f)Monitoring/Testing[G]§63.1206(b)(6)

[T]§63.1207(c)(3), [T](g)(2)(i), (g)(2)(v)§63.1209(a)(1)(i), (a)(2), [G](a)(3)

[G]§63.1209(a)(6), (a)(7)Recordkeeping[G]§63.1212(c)

Reporting§63.1207(f)(2)(i)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

Comply with the following:Standard

§63.1220(b)(5)(i)(A)(2)[G]§63.1206(c)(6)(iv)

§63.1220(f)Monitoring/Testing[G]§63.1206(b)(6)

[T]§63.1207(c)(3), [T](g)(2)(i), (g)(2)(v)§63.1209(a)(1)(i), (a)(2), [G](a)(4)

[G]§63.1209(a)(6), (a)(7)Recordkeeping[G]§63.1212(c)

Reporting§63.1207(f)(2)(i)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

Was thekiln constructed

after April 19, 1996 at asite where a cement kiln

did not previouslyexist?

§63.1220(b)(5)(i)(B)

Yes

No

Comply with the following:Standard

§63.1220(b)(5)(i)(B)423

Page 61: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(61 of 191)

Is the owner oroperator complying with theCO standard rather than the

THC standard?

413

§63.1220(b)(5)(ii)(B)(1)

Yes

No

Comply with the following:Standard

§63.1220(b)(5)(ii)(B)(1)[G]§63.1206(c)(6)(iv)

§63.1220(f)§63.1220(b)(5)(ii)(B)(2)

Monitoring/Testing[G]§63.1206(b)(6)

[T]§63.1207(c)(3), [T](g)(2)(i), (g)(2)(v)§63.1209(a)(1)(i), (a)(2), [G](a)(3)

[G]§63.1209(a)(6), (a)(7)Recordkeeping[G]§63.1212(c)

Reporting§63.1207(f)(2)(i)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

Comply with the following:Standard

§63.1220(b)(5)(ii)(A)[G]§63.1206(c)(6)(iv)

§63.1220(f)Monitoring/Testing[G]§63.1206(b)(6)

[T]§63.1207(c)(3), [T](g)(2)(i), (g)(2)(v)§63.1209(a)(1)(i), (a)(2), [G](a)(4)

[G]§63.1209(a)(6), (a)(7)Recordkeeping[G]§63.1212(c)

Reporting§63.1207(f)(2)(i)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

Was thekiln constructed

after April 19, 1996 at asite where a cement kiln

did not previouslyexist?

§63.1220(b)(5)(ii)(B)(3)

Yes

No

Comply with the following:Standard

§63.1220(b)(5)(ii)(B)(3)

423

Page 62: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(62 of 191)

414

Comply with the following:Standard

§63.1206(b)(13)(i)(B)(3)(i)[G]§63.1206(c)(6)(iv)Monitoring/Testing[G]§63.1206(b)(6)

[T]§63.1207(c)(3), [T](g)(2)(i), (g)(2)(v)§63.1209(a)(1)(i), (a)(2), [G](a)(4)

[G]§63.1209(a)(6), (a)(7)Recordkeeping[G]§63.1212(c)

Reporting§63.1207(f)(2)(i)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

415

Comply with the following:Standard

§63.1206(b)(13)(i)(B)(2)(i)[G]§63.1206(c)(6)(iv)Monitoring/Testing[G]§63.1206(b)(6)

[T]§63.1207(c)(3), [T](g)(2)(i), (g)(2)(v)§63.1209(a)(1)(i), (a)(2), [G](a)(4)

[G]§63.1209(a)(6), (a)(7)Recordkeeping[G]§63.1212(c)

Reporting§63.1207(f)(2)(i)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

§63.1206(b)(13)(i)(B)(2)(ii)

Was thekiln constructed

after April 19, 1996 at asite where a cement kiln

did not previouslyexist?

Yes

No

Comply with the following:Standard

§63.1206(b)(13)(i)(B)(2)(ii)423

Page 63: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(63 of 191)

416

Comply with the following:Standard

§63.1206(b)(13)(i)(B)(1)[G]§63.1206(c)(6)(iv)Monitoring/Testing[G]§63.1206(b)(6)

[T]§63.1207(c)(3), [T](g)(2)(i), (g)(2)(v)§63.1209(a)(1)(i), (a)(2), [G](a)(4)

[G]§63.1209(a)(6), (a)(7)Recordkeeping[G]§63.1212(c)

Reporting§63.1207(f)(2)(i)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

423

Page 64: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(64 of 191)

417

Comply with the following:Standard

§63.1220(b)(6)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n)(4), (o), (o)(1)(i), [G](o)(2)-(3)

§63.1209(o)(4)§63.1220(f)

Monitoring/Testing[T]§63.1207(c)(3), (f)(1)(xi)

§63.1207(g)(2)(iii), [G](m)(1)-(2)[G]§63.1208(b)(5)(i), (b)(5)(ii), (b)(5)(ii)(A)

§63.1209(a)(5), (c)(5)Recordkeeping

[G]§63.1207(m)(1)-(2)[G]§63.1212(c)

Reporting§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)

§63.1207(f)(1)(xxv)-(xxvi), (f)(2)(iii), (m)(5)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

Has an alternativestandards petition for

hydrogen chloride/chlorine gas been submitted to the

Administrator?

§63.1206(b)(10)(i)

Comply with the following:Standard

§63.1206(b)(10)(i)§63.1206(b)(10)(iii), [G](b)(10)(vii)

Reporting[G]§63.1206(b)(10)(iv), (b)(10)(v)-(vi)

Yes

402

No

423

Page 65: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(65 of 191)

418

Comply with the following:Standard

§63.1220(b)(7)(i)§63.1206(b)(8)(v)-(vii), [G](c)(6)(iv)

§63.1209(m), [G](m)(1)(i), [G](m)(1)(iv)[G]§63.1209(m)(2), (n)(3)

§63.1220(f)Monitoring/Testing

[G]§63.1206(b)(8)(iii)[T]§63.1207(c)(3), (g)(1)(i)(C), (g)(1)(iii)(B)

§63.1207(g)(2)(iv)§63.1208(b)(6)

§63.1209(a)(1)(iii), (a)(5), (m), [G](m)(1)(i)[G]§63.1209(m)(1)(iv), [G](m)(2)

Recordkeeping§63.1207(g)(1)(iii)(B)

[G]§63.1212(c)Reporting

[G]§63.1206(b)(8)(iii)§63.1207(f)(1)(xvii), (f)(1)(xxiii)

[G]§63.1207(f)(1)(xxiv), (f)(2)(iv)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

419

Page 66: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(66 of 191)

Is thecombustor equipped with a

baghouse?

§63.1206(c)(8)(i)

Is a particulatematter detection system

being used?

§63.1206(c)(8)(i)(B)

No Comply with the following:Standard

§63.1206(c)(8)(i)(B), [G](c)(9)

Comply with the following:Standard

§63.1206(c)(8)(i)(A), [G](c)(8)(ii)-(iii)Recordkeeping

[G]§63.1206(c)(8)(iv)Reporting

§63.1206(c)(8)(i)(A), [G](c)(8)(iv)

Yes

419

Yes No

423

Page 67: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(67 of 191)

Is the sourceequipped with leak detection

under §63.1206(c)(8) or particulatematter detection under

§63.1206(c)(9)?

420

§63.1220(a)(7)(ii)

Yes

Comply with the following:Standard

§63.1220(b)(7)(ii)§63.1206(b)(8)(v)-(vii), [G](c)(6)(iv)

§63.1220(f)Monitoring/Testing

[G]§63.1206(b)(8)(iii)[T]§63.1207(c)(3)

§63.1208(b)(9)§63.1209(a)(2)Recordkeeping[G]§63.1212(c)

Reporting[G]§63.1206(b)(8)(iii)§63.1207(f)(1)(xvii)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

Sources equipped with a bag leak detection system under

§63.1206(c)(8) or a particulate matter detection system under §63.1206(c)(9) are not subject

to opacity standards.

402

No

423

Page 68: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(68 of 191)

Does theincinerator burn

the dioxin-listed hazardous wastes F020, F021, F022,

F023, F026,or F027?

421

§63.1220(c)(2)

Comply with the following:Standard

§63.1220(c)(1)[G]§63.1206(c)(6)(iv)

[G]§63.1209(j)§63.1220(c)(3)(i)-(ii)Monitoring/Testing

[T]§63.1207(c)(3), [T](f)(1)(ii)(D)[G]§63.1209(j)Recordkeeping[G]§63.1212(c)

Reporting§63.1207(f)(1)(ii)(D), (f)(1)(xvii)

§63.1207(f)(1)(xix)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

Comply with the following:Standard

§63.1220(c)(2)[G]§63.1206(c)(6)(iv)

[G]§63.1209(j)§63.1220(c)(3)(i)-(ii)Monitoring/Testing

[T]§63.1207(c)(3), [T](f)(1)(ii)(D)[G]§63.1209(j)Recordkeeping[G]§63.1212(c)

Reporting§63.1207(f)(1)(ii)(D), (f)(1)(xvii)

§63.1207(f)(1)(xix)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

422

YesNo

Page 69: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(69 of 191)

Did the sourceprevious testing to document

conformance with theDRE standard?

Yes

§63.1206(b)(7)(iii)

Comply with the following:Recordkeeping

[G]§63.1206(b)(7)(i)

NoComply with the following:

Monitoring/Testing[T]§63.1206(b)(7)(iii)

Does the sourcefeed hazardous waste at

a location in the combustion systemother than the normal

flame zone?

Comply with the following:Standard

§63.1206(b)(7)(ii)(A)[G]§63.1206(b)(7)(ii)(B)(1)

§63.1206(b)(7)(ii)(B)(2)

Yes

§63.1206(b)(7)(ii)

No

422

423

423

Page 70: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(70 of 191)

Comply with the following:Standard

[G]§63.1206(b)(5), [G](c)(1)-(5), (c)(6)(i)-(ii)[G]§63.1206(c)(6)(v)-(vi), [G](c)(7)

§63.1207(g)(1)(iii)(A), [G](k), [G](l)(1)§63.1209(c)(1), [G](c)(2), [G](d), (i), (p), [G](q)

§63.1211(c)(1)-(2), (c)(4)Monitoring/Testing

[G]§63.1206(b)(5), [G](b)(12), [G](c)(3)[T]§63.1207(a), [T](b)(1), [T][G](d)-(e)

[T][G]§63.1207(f)(1)(i), [T](f)(1)(ii)[T]§63.1207(f)(1)(ii)(A)-(C), [T][G](f)(1)(iii)

[T]§63.1207(f)(1)(iv)-(ix), [T](f)(1)(xii)[T]§63.1207(f)(1)(xxvii), (g), (g)(1)(ii)

[T][G]§63.1207(h)-(i), [T][G](l)(1)§63.1208(b)(7)-(8)

§63.1209(b)(1), [G](b)(2), (b)(3)-(4), [G](b)(5)[G]§63.1209(c)(4), [G](d), [G](f), (g)(1)(i)-(ii)

§63.1209(i), (p), [G](q), (r)Recordkeeping

[G]§63.1206(b)(5), (b)(11), [G](b)(12)[G]§63.1206(c)(1)-(5), (c)(6)(vii), [G](c)(7)

§63.1207(f)(1)(xii), (g)(1)(iii)(A)§63.1209(b)(1), [G](c)(2), [G](c)(4), [G](q)

§63.1211(b), [G](c)(3), [G](d)Reporting

[G]§63.1206(b)(5), (b)(11), [G](c)(2)-(4)[G]§63.1207(e), [G](f)(1)(i), (f)(1)(ii)§63.1207(f)(1)(ii)(A)-(C), [G](f)(1)(iii)

§63.1207(f)(1)(iv)-(ix), (f)(1)(xii), (f)(1)(xviii)§63.1207(f)(1)(xxvii), (f)(2)(v)-(x), [G](h)-(i)

[G]§63.1207(j)(1), (j)(3)-(5), [G](k)[G]§63.1207(l)(1), (l)(3)

§63.1209(c)(3), (g)(1)(i)-(ii), [G](g)(1)(iii)[G]§63.1210(a), [G](b)(1), (b)(2), (c)(2)

[G]§63.1210(c)(3)-(4), [G](d)§63.1211(a), [G](c)(3), [G](d)

§63.1212(a)

423

424

Page 71: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(71 of 191)

Does thekiln have in-line kiln

raw mill?

§63.1220(d)Yes

Is the kilnpreheater or preheater/

precalciner kiln withdual stacks?

424

Comply with the following:Monitoring/Testing

§63.1220(d)(1)(i), (d)(1)(iii)Recordkeeping

§63.1220(d)(1)(ii)

§63.1220(e)

Yes

Comply with the following:Monitoring/Testing

§63.1220(e)(1)402

No

No

Page 72: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(72 of 191)

Dioxins,Furans

501

Pb, Cd, Se

503

504

Sb, As, Be, Cr, Co, Mn, Ni

CO, THC

509

510

513Total

Chlorine

515

514

POHC

517

PM

Hg

Applicant must go through the flowchart for each

pollutant group.

Have allpollutant paths been

completed? End

§63.1221

No

Continue through next path.

502

Page 73: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(73 of 191)

503

§63.1221(a)(1)(ii)

Comply with the following:Standard

§63.1221(a)(1)(i)[G]§63.1206(c)(6)(iv)

[G]§63.1207(l)(2)§63.1209(k), (k)(1)(ii), (k)(2)(i)-(ii)

[G]§63.1209(k)(3)-(4), (k)(5), [G](k)(6)-(9)§63.1221(d)

Monitoring/Testing[T][G]§63.1207(b)(2), [T](c)(3)

§63.1207(g)(1)(i)(A), (g)(2)(ii), (g)(2)(v)[G]§63.1208(b)(1)

§63.1209(k)(2)(i), [G](k)(3), [G](k)(8)Recordkeeping

§63.1209(k)(2)(i), [G](k)(3)Reporting

§63.1207(f)(1)(xv), (f)(1)(xvii), (f)(1)(xix)[G]§63.1207(f)(1)(xx)-(xxi), (f)(1)(xxii)

§63.1207(f)(2)(ii), (j)(2)§63.1210(b)(3)(i), (c)(1)(i)

519

Comply with the following:Standard

§63.1221(a)(1)(ii)[G]§63.1206(c)(6)(iv)

[G]§63.1207(l)(2)§63.1209(k), (k)(1)(ii), (k)(2)(i)-(ii)

[G]§63.1209(k)(3)-(4), (k)(5), [G](k)(6)-(9)§63.1221(d)

Monitoring/Testing[T][G]§63.1207(b)(2)-(3), [T](c)(3)

§63.1207(g)(1)(i)(A)§63.1207(g)(2)(ii), (g)(2)(v)

[G]§63.1208(b)(1)§63.1209(k)(2)(i), [G](k)(3), [G](k)(8)

Recordkeeping§63.1209(k)(2)(i), [G](k)(3)

Reporting§63.1207(f)(1)(xv), (f)(1)(xvii), (f)(1)(xix)[G]§63.1207(f)(1)(xx)-(xxi), (f)(1)(xxii)

§63.1207(f)(2)(ii), (j)(2)§63.1210(b)(3)(i), (c)(1)(i)

YesNo

Is thecombustion gas

temperature at the inlet to theinitial particulate matter control device 400

deg. F or lower based on theaverage of the test run

averages?

Page 74: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(74 of 191)

504

Has an alternativestandards petition for Hg

been submitted to theAdministrator?

§63.1206(b)(9)(i)

No

Comply with the following:Standard

§63.1206(b)(9)(i)§63.1206(b)(9)(iii), [G](b)(9)(vii)

Reporting[G]§63.1206(b)(9)(iv), (b)(9)(v)-(vi)

Yes

502

Is the kiln meeting a maximum theoretical emission concentration

(MTEC)?

§63.1221(a)(2)(ii)

No

Yes

505

506

Page 75: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(75 of 191)

Comply with the following:Standard

§63.1221(a)(2)(i)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(4)§63.1221(d)

Monitoring/Testing[T]§63.1207(c)(3), [G](m)(1)-(2)

§63.1208(b)(2)§63.1209(a)(5)Recordkeeping

[G]§63.1207(m)(1)-(2)Reporting

§63.1207(f)(1)(xvi), (f)(1)(xxvi), (m)(5)§63.1209(g)(1)(iv)(B)

§63.1210(b)(3)(i), (c)(1)(i)

Comply with the following:Standard

§63.1221(a)(2)(ii)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(4)§63.1221(d)

Monitoring/Testing[T]§63.1207(c)(3), [G](m)(1)-(2)

§63.1208(b)(2)§63.1209(a)(5)Recordkeeping

[G]§63.1207(m)(1)-(2)Reporting

§63.1207(f)(1)(xvi), (f)(1)(xxvi), (m)(5)§63.1209(g)(1)(iv)(B)

§63.1210(b)(3)(i), (c)(1)(i)

507 508

505 506

Page 76: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(76 of 191)

Are yourequesting to

extrapolate mercury feedrate limits from comprehensive

performance testlevels?

Comply with the following:Standard

[G]§63.1209(l)(1)(v)Monitoring/Testing

[T][G]§63.1207(f)(1)(x)Reporting

[G]§63.1207(f)(1)(x)[G]§63.1209(l)(1)(v)

507

Yes

§63.1207(f)(1)(x)§63.1209(l)(1)(v)

No

Comply with the following:Standard

§63.1209(l), (l)(1)(iv)(A)Monitoring/Testing

§63.1209(l), (l)(1)(iv)(A)

519

Are yourequesting to

extrapolate mercury feedrate limits from comprehensive

performance testlevels?

508

Yes

§63.1207(f)(1)(x)§63.1209(l)(1)(v)

No

Comply with the following:Standard

§63.1209(l), [G](l)(1)(iv)(B)-(C)Monitoring/Testing

§63.1209(l), [G](l)(1)(iv)(B)-(C)

Page 77: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(77 of 191)

509

Comply with the following:Standard

[G]§63.1221(a)(3)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1221(d)Monitoring/Testing

[T]§63.1207(c)(3), (f)(1)(xi), [G](m)(1)-(2)§63.1208(b)(3)

§63.1209(a)(5), (c)(5)Recordkeeping

[G]§63.1207(m)(1)-(2)Reporting

§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)§63.1207(f)(1)(xxvi), (m)(5)

§63.1209(g)(1)(iv)(A)§63.1210(b)(3)(i), (c)(1)(i)

511

Has an alternative standards

petition for semivolatile metals been submitted to the

Administrator?

§63.1206(b)(9)(i)

Comply with the following:Standard

§63.1206(b)(9)(i)§63.1206(b)(9)(iii), [G](b)(9)(vii)

Reporting[G]§63.1206(b)(9)(iv), (b)(9)(v)-(vi)

Yes

502

No

Page 78: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(78 of 191)

510

Comply with the following:Standard

[G]§63.1221(a)(4)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1221(d)Monitoring/Testing

[T]§63.1207(c)(3), (f)(1)(xi), [G](m)(1)-(2)§63.1208(b)(4)

§63.1209(a)(5), (c)(5)Recordkeeping

[G]§63.1207(m)(1)-(2)Reporting

§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)§63.1207(f)(1)(xxvi), (m)(5)

§63.1209(g)(1)(iv)(A)§63.1210(b)(3)(i), (c)(1)(i)

512

Has analternative standards

petition for low volatile metals been submitted to the

Administrator?

§63.1206(b)(9)(i)

Comply with the following:Standard

§63.1206(b)(9)(i)§63.1206(b)(9)(iii), [G](b)(9)(vii)

Reporting[G]§63.1206(b)(9)(iv), (b)(9)(v)-(vi)

Yes

502

No

Page 79: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(79 of 191)

Are yourequesting to

extrapolate metal feedrate limits from comprehensive

performance testlevels?

Comply with the following:Standard

[G]§63.1209(n)(2)(vii)Monitoring/Testing

[T][G]§63.1207(f)(1)(x)[G]§63.1209(n)(2)(vii)

Reporting[G]§63.1207(f)(1)(x)

511

Yes

§63.1207(f)(1)(x)§63.1209(n)(2)(vii)

No

Comply with the following:Standard

§63.1209(n)(2)(i), [G](n)(2)(iv)Monitoring/Testing

[G]§63.1209(n)(2)(iv)

519

Are yourequesting to

extrapolate metal feedrate limits from comprehensive

performance testlevels?

512

Yes

§63.1207(f)(1)(x)§63.1209(n)(2)(vii)

No

Comply with the following:Standard

§63.1209(n)(2)(i), [G](n)(2)(iv)§63.1209(n)(2)(vi)Monitoring/Testing

[G]§63.1209(n)(2)(iv), (n)(2)(vi)

Page 80: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(80 of 191)

Is the owner oroperator complying with theCO standard rather than the

THC standard?

513

§63.1221(a)(5)(i)

No

Comply with the following:Standard

§63.1221(a)(5)(i)[G]§63.1206(c)(6)(iv)

§63.1221(d)Monitoring/Testing[G]§63.1206(b)(6)

[T]§63.1207(c)(3), [T](g)(2)(i), (g)(2)(v)§63.1209(a)(1)(i), (a)(2), [G](a)(3)

[G]§63.1209(a)(6), (a)(7)Reporting

§63.1207(f)(2)(i)§63.1210(b)(3)(i), (c)(1)(i)

Comply with the following:Standard

§63.1221(a)(5)(ii)[G]§63.1206(c)(6)(iv)

§63.1221(d)Monitoring/Testing[G]§63.1206(b)(6)

[T]§63.1207(c)(3), [T](g)(2)(i), (g)(2)(v)§63.1209(a)(1)(i), (a)(2), [G](a)(4)

[G]§63.1209(a)(6), (a)(7)Reporting

§63.1207(f)(2)(i)§63.1210(b)(3)(i), (c)(1)(i)

Yes

519

Page 81: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(81 of 191)

514

Comply with the following:Standard

§63.1221(a)(6)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n)(4), (o), (o)(1)(i), [G](o)(2)-(3)

§63.1209(o)(4)§63.1221(d)

Monitoring/Testing[T]§63.1207(c)(3), (f)(1)(xi)

§63.1207(g)(2)(iii), [G](m)(1)-(2)[G]§63.1208(b)(5)(i), (b)(5)(ii)

[G]§63.1208(b)(5)(ii)(B)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

Reporting§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)§63.1207(f)(1)(xxv)-(xxvi), (f)(2)(iii)

§63.1207(m)(5)§63.1210(b)(3)(i), (c)(1)(i)

Has an alternativestandards petition for

hydrogen chloride/chlorine gas been submitted to the

Administrator?

§63.1206(b)(9)(i)

Comply with the following:Standard

§63.1206(b)(9)(i)§63.1206(b)(9)(iii), [G](b)(9)(vii)

Reporting[G]§63.1206(b)(9)(iv), (b)(9)(v)-(vi)

Yes

502

No

519

Page 82: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(82 of 191)

515

Comply with the following:Standard

§63.1221(a)(7)§63.1206(b)(8)(v)-(vii), [G](c)(6)(iv)

§63.1209(m), [G](m)(1)(i), [G](m)(1)(iv)[G]§63.1209(m)(2), (n)(3)

§63.1221(d)Monitoring/Testing

[G]§63.1206(b)(8)(iii)[T]§63.1207(c)(3), (g)(1)(i)(C), (g)(2)(iv)

§63.1208(b)(6)§63.1209(a)(1)(iii), (a)(5), [G](m)(1)(i)

[G]§63.1209(m)(1)(iv), [G](m)(2)Reporting

[G]§63.1206(b)(8)(iii)§63.1207(f)(1)(xvii), (f)(1)(xxiii)

[G]§63.1207(f)(1)(xxiv), (f)(2)(iv)§63.1210(b)(3)(i), (c)(1)(i)

516

Page 83: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(83 of 191)

Is thecombustor equipped with a

baghouse?

§63.1206(c)(8)(i)

Is a particulatematter detection system

being used?§63.1206(c)(8)(i)(B)

NoComply with the following:

Standard§63.1206(c)(8)(i)(B), [G](c)(9)

Comply with the following:Standard

§63.1206(c)(8)(i)(A), [G](c)(8)(ii)-(iii)Recordkeeping

[G]§63.1206(c)(8)(iv)Reporting

§63.1206(c)(8)(i)(A), [G](c)(8)(iv)

Yes

516

NoYes

519

Page 84: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(84 of 191)

Does theincinerator burn

the dioxin-listed hazardous wastes F020, F021, F022,

F023, F026, or F027?

517

§63.1221(c)(2)

Comply with the following:Standard

§63.1221(c)(1)[G]§63.1206(c)(6)(iv)

[G]§63.1209(j)§63.1221(c)(3)(i)-(ii)Monitoring/Testing

[T]§63.1207(c)(3), [T](f)(1)(ii)(D)[G]§63.1209(j)

Reporting§63.1207(f)(1)(ii)(D), (f)(1)(xvii)

§63.1207(f)(1)(xix)§63.1210(b)(3)(i), (c)(1)(i)

Comply with the following:Standard

§63.1221(c)(2)[G]§63.1206(c)(6)(iv)

[G]§63.1209(j)§63.1221(c)(3)(i)-(ii)Monitoring/Testing

[T]§63.1207(c)(3), [T](f)(1)(ii)(D)[G]§63.1209(j)

Reporting§63.1207(f)(1)(ii)(D), (f)(1)(xvii)

§63.1207((f)(1)(xix)§63.1210(b)(3)(i), (c)(1)(i)

518

No Yes

Page 85: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(85 of 191)

Did the sourceprevious testing to document

conformance with theDRE standard?

Yes

§63.1206(b)(7)(iii)

Comply with the following:Recordkeeping

[G]§63.1206(b)(7)(i)

NoComply with the following:

Monitoring/Testing[T]§63.1206(b)(7)(iii)

Does the sourcefeed hazardous waste at

a location in the combustion systemother than the normal

flame zone?

Comply with the following:Standard

§63.1206(b)(7)(ii)(A), (7)(ii)(B)(2)Yes

§63.1206(b)(7)(ii)

No

518

519

519

Page 86: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(86 of 191)

Comply with the following:Standard

[G]§63.1206(b)(5), [G](c)(1)-(5), (c)(6)(i)-(ii)[G]§63.1206(c)(6)(v)-(vi), [G](c)(7)

§63.1207(g)(1)(iii)(A), [G](k), [G](l)(1)§63.1209(c)(1), [G](c)(2), [G](d), (i), (p), [G](q)

§63.1211(c)(1)-(2), (c)(4)Monitoring/Testing

[G]§63.1206(b)(5), [G](b)(12), [G](c)(3)[T]§63.1207(a), [T](b)(1), [T][G](d)-(e)

[T][G]§63.1207(f)(1)(i), [T](f)(1)(ii)[T]§63.1207(f)(1)(ii)(A)-(C), [T][G](f)(1)(iii)

[T]§63.1207(f)(1)(iv)-(ix), [T](f)(1)(xii)[T]§63.1207(f)(1)(xxvii), (g), (g)(1)(ii)

[T][G]§63.1207(h)-(i), [T][G](l)(1)§63.1208(b)(7)-(8)

§63.1209(b)(1), [G](b)(2), (b)(3)-(4), [G](b)(5)[G]§63.1209(c)(4), [G](d), [G](f), (g)(1)(i)-(ii)

§63.1209(i), (p), [G](q), (r)Recordkeeping

[G]§63.1206(b)(5), (b)(11), [G](b)(12)[G]§63.1206(c)(1)-(5), (c)(6)(vii), [G](c)(7)

§63.1207(f)(1)(xii), (g)(1)(iii)(A)§63.1209(b)(1), [G](c)(2), [G](c)(4), [G](q)

§63.1211(b), [G](c)(3), [G](d)Reporting

[G]§63.1206(b)(5), (b)(11), [G](c)(2)-(4)[G]§63.1207(e), [G](f)(1)(i), (f)(1)(ii)

§63.1207(f)(1)(ii)(A)-(C), [G](f)(1)(iii)§63.1207(f)(1)(iv)-(ix), (f)(1)(xii), (f)(1)(xviii)§63.1207(f)(1)(xxvii), (f)(2)(v)-(x), [G](h)-(i)

[G]§63.1207(j)(1), (j)(3)-(5), [G](k)[G]§63.1207(l)(1), (l)(3)

§63.1209(c)(3), (g)(1)(i)-(ii), [G](g)(1)(iii)[G]§63.1210(a), [G](b)(1), (b)(2), (c)(2)

[G]§63.1210(c)(3)-(4), [G](d)§63.1211(a), [G](c)(3), [G](d)

§63.1212(a)

519

502

Page 87: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(87 of 191)

Dioxins,Furans

601

Pb, Cd, Se

603

604

Sb, As, Be, Cr, Co, Mn, Ni

CO, THC

609

610

613Total

Chlorine

615

614

POHC

617

PM

Hg

Applicant must go through the flowchart for each

pollutant group.

Have allpollutant paths been

completed? End

§63.1221

No

Continue through next path.

602

Page 88: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(88 of 191)

603

Is thecombustion gas

temperature at the inlet to theinitial particulate matter control device 400

deg. F or lower based on theaverage of the test run

averages?

§63.1221(b)(1)(ii)

Comply with the following:Standard

§63.1221(b)(1)(i)[G]§63.1206(c)(6)(iv)

[G]§63.1207(l)(2)§63.1209(k), (k)(1)(ii), (k)(2)(i)-(ii)

[G]§63.1209(k)(3)-(4), (k)(5), [G](k)(6)-(9)§63.1221(d)

Monitoring/Testing[T][G]§63.1207(b)(2), [T](c)(3)

§63.1207(g)(1)(i)(A), (g)(2)(ii), (g)(2)(v)[G]§63.1208(b)(1)

§63.1209(k)(2)(i), [G](k)(3), [G](k)(8)Recordkeeping

§63.1209(k)(2)(i), [G](k)(3)[G]§63.1212(c)

Reporting§63.1207(f)(1)(xv), (f)(1)(xvii), (f)(1)(xix)[G]§63.1207(f)(1)(xx)-(xxi), (f)(1)(xxii)

§63.1207(f)(2)(ii), (j)(2)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

619

Comply with the following:Standard

§63.1221(b)(1)(ii)[G]§63.1206(c)(6)(iv)

[G]§63.1207(l)(2)§63.1209(k), (k)(1)(ii), (k)(2)(i)-(ii)

[G]§63.1209(k)(3)-(4), (k)(5), [G](k)(6)-(9)§63.1221(d)

Monitoring/Testing[T][G]§63.1207(b)(2)-(3), [T](c)(3)

§63.1207(g)(1)(i)(A)§63.1207(g)(2)(ii), (g)(2)(v)

[G]§63.1208(b)(1)§63.1209(k)(2)(i), [G](k)(3), [G](k)(8)

Recordkeeping§63.1209(k)(2)(i), [G](k)(3)

[G]§63.1212(c)Reporting

§63.1207(f)(1)(xv), (f)(1)(xvii), (f)(1)(xix)[G]§63.1207(f)(1)(xx)-(xxi), (f)(1)(xxii)

§63.1207(f)(2)(ii), (j)(2)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

No Yes

Page 89: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(89 of 191)

604

Has an alternativestandards petition for Hg

been submitted to theAdministrator?

§63.1206(b)(9)(i)

No

Comply with the following:Standard

§63.1206(b)(9)(i)§63.1206(b)(9)(iii), [G](b)(9)(vii)

Reporting[G]§63.1206(b)(9)(iv), (b)(9)(v)-(vi)

Yes

602

Is the kilnmeeting a maximum theoretical emission

concentration(MTEC)?

§63.1221(b)(2)(ii)

No

Yes

605

606

Page 90: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(90 of 191)

Comply with the following:Standard

§63.1221(b)(2)(i)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(4)§63.1221(d)

Monitoring/Testing[T]§63.1207(c)(3), [G](m)(1)-(2)

§63.1208(b)(2)§63.1209(a)(5)Recordkeeping

[G]§63.1207(m)(1)-(2)[G]§63.1212(c)

Reporting§63.1207(f)(1)(xvi), (f)(1)(xxvi), (m)(5)

§63.1209(g)(1)(iv)(B)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

Comply with the following:Standard

§63.1221(b)(2)(ii)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(4)§63.1221(d)

Monitoring/Testing[T]§63.1207(c)(3), [G](m)(1)-(2)

§63.1208(b)(2)§63.1209(a)(5)Recordkeeping

[G]§63.1207(m)(1)-(2)[G]§63.1212(c)

Reporting§63.1207(f)(1)(xvi), (f)(1)(xxvi), (m)(5)

§63.1209(g)(1)(iv)(B)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

607 608

605 606

Page 91: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(91 of 191)

Are yourequesting to

extrapolate mercury feedrate limits from comprehensive

performance testlevels?

Comply with the following:Standard

[G]§63.1209(l)(1)(v)Monitoring/Testing

[T][G]§63.1207(f)(1)(x)Reporting

[G]§63.1207(f)(1)(x)[G]§63.1209(l)(1)(v)

607

Yes§63.1207(f)(1)(x)§63.1209(l)(1)(v)

No

Comply with the following:Standard

§63.1209(l), (l)(1)(iv)(A)Monitoring/Testing

§63.1209(l), (l)(1)(iv)(A)

Are yourequesting to

extrapolate mercury feedrate limits from comprehensive

performance testlevels?

608

Yes

§63.1207(f)(1)(x)§63.1209(l)(1)(v)

No

Comply with the following:Standard

§63.1209(l), [G](l)(1)(iv)(B)-(C)Monitoring/Testing

§63.1209(l), [G](l)(1)(iv)(B)-(C)

619

Page 92: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(92 of 191)

609

Comply with the following:Standard

[G]§63.1221(b)(3)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1221(d)Monitoring/Testing

[T]§63.1207(c)(3), (f)(1)(xi), [G](m)(1)-(2)§63.1208(b)(3)

§63.1209(a)(5), (c)(5)Recordkeeping

[G]§63.1207(m)(1)-(2)[G]§63.1212(c)

Reporting§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)

§63.1207(f)(1)(xxvi), (m)(5)§63.1209(g)(1)(iv)(A)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

611

Has analternative standards

petition for semivolatile metals been submitted to the

Administrator?

§63.1206(b)(9)(i)

Comply with the following:Standard

§63.1206(b)(9)(i)§63.1206(b)(9)(iii), [G](b)(9)(vii)

Reporting[G]§63.1206(b)(9)(iv), (b)(9)(v)-(vi)

Yes

602

No

Page 93: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(93 of 191)

610

Comply with the following:Standard

[G]§63.1221(b)(4)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1221(d)Monitoring/Testing

[T]§63.1207(c)(3), (f)(1)(xi), [G](m)(1)-(2)§63.1208(b)(4)

§63.1209(a)(5), (c)(5)Recordkeeping

[G]§63.1207(m)(1)-(2)[G]§63.1212(c)

Reporting§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)

§63.1207(f)(1)(xxvi), (m)(5)§63.1209(g)(1)(iv)(A)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

612

Has analternative standards

petition for low volatile metals been submitted to the

Administrator?

§63.1206(b)(9)(i)

Comply with the following:Standard

§63.1206(b)(9)(i)§63.1206(b)(9)(iii), [G](b)(9)(vii)

Reporting[G]§63.1206(b)(9)(iv), (b)(9)(v)-(vi)

YesNo

602

Page 94: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(94 of 191)

Are yourequesting to

extrapolate metal feedrate limits from comprehensive

performance testlevels?

Comply with the following:Standard

[G]§63.1209(n)(2)(vii)Monitoring/Testing

[T][G]§63.1207(f)(1)(x)[G]§63.1209(n)(2)(vii)

Reporting[G]§63.1207(f)(1)(x)

611

Yes

§63.1207(f)(1)(x)§63.1209(n)(2)(vii)

No

Comply with the following:Standard

§63.1209(n)(2)(i), [G](n)(2)(iv)Monitoring/Testing

[G]§63.1209(n)(2)(iv)

Are yourequesting to

extrapolate metal feedrate limits from comprehensive

performance testlevels?

612

Yes

§63.1207(f)(1)(x)§63.1209(n)(2)(vii)

No

Comply with the following:Standard

§63.1209(n)(2)(i), [G](n)(2)(iv)§63.1209(n)(2)(vi)Monitoring/Testing

[G]§63.1209(n)(2)(iv), (n)(2)(vi)

619

Page 95: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(95 of 191)

Is the owner oroperator complying with theCO standard rather than the

THC standard?

613

§63.1221(b)(5)(i)

Comply with the following:Standard

§63.1221(b)(5)(i)[G]§63.1206(c)(6)(iv)

§63.1221(d)Monitoring/Testing[G]§63.1206(b)(6)

[T]§63.1207(c)(3), [T](g)(2)(i), (g)(2)(v)§63.1209(a)(1)(i), (a)(2), [G](a)(3)

[G]§63.1209(a)(6), (a)(7)Recordkeeping[G]§63.1212(c)

Reporting§63.1207(f)(2)(i)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

Comply with the following:Standard

§63.1221(b)(5)(ii)[G]§63.1206(c)(6)(iv)

§63.1221(d)Monitoring/Testing[G]§63.1206(b)(6)

[T]§63.1207(c)(3), [T](g)(2)(i), (g)(2)(v)§63.1209(a)(1)(i), (a)(2), [G](a)(4)

[G]§63.1209(a)(6), (a)(7)Recordkeeping[G]§63.1212(c)

Reporting§63.1207(f)(2)(i)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

Yes No

619

Page 96: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(96 of 191)

614

Comply with the following:Standard

§63.1221(b)(6)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n)(4), (o), (o)(1)(i), [G](o)(2)-(3)

§63.1209(o)(4)§63.1221(d)

Monitoring/Testing[T]§63.1207(c)(3), (f)(1)(xi), (g)(2)(iii)

[G]§63.1207(m)(1)-(2)[G]§63.1208(b)(5)(i), (b)(5)(ii)

[G]§63.1208(b)(5)(ii)(B)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

[G]§63.1212(c)Reporting

§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)§63.1207(f)(1)(xxv)-(xxvi), (f)(2)(iii)

§63.1207(m)(5)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

Has an alternativestandards petition for

hydrogen chloride/chlorine gas been submitted to the

Administrator?

§63.1206(b)(9)(i)

Comply with the following:Standard

§63.1206(b)(9)(i)§63.1206(b)(9)(iii), [G](b)(9)(vii)

Reporting[G]§63.1206(b)(9)(iv), (b)(9)(v)-(vi)

YesNo

619

602

Page 97: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(97 of 191)

615

Comply with the following:Standard

§63.1221(b)(7)§63.1206(b)(8)(v)-(vii), [G](c)(6)(iv)

§63.1209(m), [G](m)(1)(i), [G](m)(1)(iv)[G]§63.1209(m)(2), (n)(3)

§63.1221(d)Monitoring/Testing

[G]§63.1206(b)(8)(iii)[T]§63.1207(c)(3), (g)(1)(i)(C), (g)(2)(iv)

§63.1208(b)(6)§63.1209(a)(1)(iii), (a)(5), (m), [G](m)(1)(i)

[G]§63.1209(m)(1)(iv), [G](m)(2)Recordkeeping[G]§63.1212(c)

Reporting[G]§63.1206(b)(8)(iii)

§63.1207(f)(1)(xvii), (f)(1)(xxiii)[G]§63.1207(f)(1)(xxiv), (f)(2)(iv)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

616

Page 98: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(98 of 191)

Is thecombustor equipped with

a baghouse?

§63.1206(c)(8)(i)

Is a particulatematter detection system

being used?

§63.1206(c)(8)(i)(B)

NoComply with the following:

Standard§63.1206(c)(8)(i)(B), [G](c)(9)

Comply with the following:Standard

§63.1206(c)(8)(i)(A), [G](c)(8)(ii)-(iii)Recordkeeping

[G]§63.1206(c)(8)(iv)Reporting

§63.1206(c)(8)(i)(A), [G](c)(8)(iv)

Yes

616

NoYes

619

Page 99: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(99 of 191)

Does theincinerator burn the dioxin-

listed hazardous wastes F020, F021, F022, F023, F026,

or F027?

617

§63.1221(c)(2)

Comply with the following:Standard

§63.1221(c)(1)[G]§63.1206(c)(6)(iv)

[G]§63.1209(j)§63.1221(c)(3)(i)-(ii)Monitoring/Testing

[T]§63.1207(c)(3), [T](f)(1)(ii)(D)[G]§63.1209(j)Recordkeeping[G]§63.1212(c)

Reporting§63.1207(f)(1)(ii)(D), (f)(1)(xvii)

§63.1207(f)(1)(xix)§63.1210(b)(3)(i)-(ii), (c)(1)(i)-(ii)

[G]§63.1212(b)-(c)

Comply with the following:Standard

§63.1221(c)(2)[G]§63.1206(c)(6)(iv)

[G]§63.1209(j)§63.1221(c)(3)(i)-(ii)Monitoring/Testing

[T]§63.1207(c)(3), [T](f)(1)(ii)(D)[G]§63.1209(j)Recordkeeping[G]§63.1212(c)

Reporting§63.1207(f)(1)(ii)(D), (f)(1)(xvii)

§63.1207(f)(1)(xix)§63.1210(b)(3)(i)-(ii), (c)(1)(i)-(ii)

[G]§63.1212(b)-(c)

618

No Yes

Page 100: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(100 of 191)

Did the sourceprevious testing to document

conformance with theDRE standard?

Yes

§63.1206(b)(7)(iii)

Comply with the following:Recordkeeping

[G]§63.1206(b)(7)(i)

NoComply with the following:

Monitoring/Testing[T]§63.1206(b)(7)(iii)

Does the sourcefeed hazardous waste at a

location in the combustion systemother than the normal

flame zone?

Comply with the following:Standard

§63.1206(b)(7)(ii)(A), (7)(ii)(B)(2)Yes

§63.1206(b)(7)(ii)

No

618

619

619

Page 101: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(101 of 191)

Comply with the following:Standard

[G]§63.1206(b)(5), [G](c)(1)-(5), (c)(6)(i)-(ii)[G]§63.1206(c)(6)(v)-(vi), [G](c)(7)

§63.1207(g)(1)(iii)(A), [G](k), [G](l)(1)§63.1209(c)(1), [G](c)(2), [G](d), (i), (p), [G](q)

§63.1211(c)(1)-(2), (c)(4)Monitoring/Testing

[G]§63.1206(b)(5), [G](b)(12), [G](c)(3)[T]§63.1207(a), [T](b)(1), [T][G](d)-(e)

[T][G]§63.1207(f)(1)(i), [T](f)(1)(ii)[T]§63.1207(f)(1)(ii)(A)-(C), [T][G](f)(1)(iii)

[T]§63.1207(f)(1)(iv)-(ix), [T](f)(1)(xii)[T]§63.1207(f)(1)(xxvii), (g), (g)(1)(ii)

[T][G]§63.1207(h)-(i), [T][G](l)(1)§63.1208(b)(7)-(8)

§63.1209(b)(1), [G](b)(2), (b)(3)-(4), [G](b)(5)[G]§63.1209(c)(4), [G](d), [G](f), (g)(1)(i)-(ii)

§63.1209(i), (p), [G](q), (r)Recordkeeping

[G]§63.1206(b)(5), (b)(11), [G](b)(12)[G]§63.1206(c)(1)-(5), (c)(6)(vii), [G](c)(7)

§63.1207(f)(1)(xii), (g)(1)(iii)(A)§63.1209(b)(1), [G](c)(2), [G](c)(4), [G](q)

§63.1211(b), [G](c)(3), [G](d)Reporting

[G]§63.1206(b)(5), (b)(11), [G](c)(2)-(4)[G]§63.1207(e), [G](f)(1)(i), (f)(1)(ii)

§63.1207(f)(1)(ii)(A)-(C), [G](f)(1)(iii)§63.1207(f)(1)(iv)-(ix), (f)(1)(xii), (f)(1)(xviii)§63.1207(f)(1)(xxvii), (f)(2)(v)-(x), [G](h)-(i)

[G]§63.1207(j)(1), (j)(3)-(5), [G](k)[G]§63.1207(l)(1), (l)(3)

§63.1209(c)(3), (g)(1)(i)-(ii), [G](g)(1)(iii)[G]§63.1210(a), [G](b)(1), (b)(2), (c)(2)

[G]§63.1210(c)(3)-(4), [G](d)§63.1211(a), [G](c)(3), [G](d)

§63.1212(a)

619

602

Page 102: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(102 of 191)

Dioxins,Furans

701

Pb, Cd, Se

703

704

Sb, As, Be, Cr, Co, Mn, Ni

CO, THC

705

706

709Total

Chlorine

711

710

POHC

713

PM

Hg

Applicant must go through the flowchart for each

pollutant group.

Have allpollutant paths been

completed? End

§63.1216

No

Continue through next path.

702

Page 103: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(103 of 191)

703

§63.1216(a)(1)

Comply with the following:Standard

§63.1216(a)(1)§63.1216(a)(5)(i)

[G]§63.1206(c)(6)(iv)[G]§63.1207(l)(2)

§63.1209(k), (k)(1)(i), (k)(2)(i)-(ii)[G]§63.1209(k)(3)-(4), (k)(5), [G](k)(6)-(9)

§63.1216(d)Monitoring/Testing

[T][G]§63.1207(b)(2)-(3), [T](c)(1)[T][G]§63.1207(c)(2)

§63.1207(g)(1)(i)(A), (g)(2)(ii), (g)(2)(v)[G]§63.1208(b)(1)

§63.1209(k)(2)(i), [G](k)(3), [G](k)(8)Recordkeeping

§63.1209(k)(2)(i), [G](k)(3)Reporting

§63.1207(f)(1)(xv), (f)(1)(xvii), (f)(1)(xix)[G]§63.1207(f)(1)(xx)-(xxi), (f)(1)(xxii)

§63.1207(f)(2)(ii), (j)(2)§63.1210(b)(3)(i), (c)(1)(i)

715

Comply with the following:Standard

§63.1216(a)(1)§63.1216(a)(5)(ii)

[G]§63.1206(c)(6)(iv)[G]§63.1207(l)(2)

§63.1209(k), (k)(1)(i), (k)(2)(i)-(ii)[G]§63.1209(k)(3)-(4), (k)(5), [G](k)(6)-(9)

§63.1216(d)Monitoring/Testing

[T][G]§63.1207(b)(2)-(3), [T](c)(1)[T][G]§63.1207(c)(2)

§63.1207(g)(1)(i)(A), (g)(2)(ii), (g)(2)(v)[G]§63.1208(b)(1)

§63.1209(k)(2)(i), [G](k)(3), [G](k)(8)Recordkeeping

§63.1209(k)(2)(i), [G](k)(3)Reporting

§63.1207(f)(1)(xv), (f)(1)(xvii), (f)(1)(xix)[G]§63.1207(f)(1)(xx)-(xxi), (f)(1)(xxii)

§63.1207(f)(2)(ii), (j)(2)§63.1210(b)(3)(i), (c)(1)(i)

Is the owner oroperator complying with theCO standard rather than the

THC standard?

No Yes

Page 104: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(104 of 191)

704

Comply with the following:Standard

§63.1216(a)(2)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1216(d)

Monitoring/Testing[T]§63.1207(c)(1), [T][G](c)(2)

[G]§63.1207(m)(1)-(2)§63.1208(b)(2)§63.1209(a)(5)Recordkeeping

[G]§63.1207(m)(1)-(2)Reporting

§63.1207(f)(1)(xvi), (f)(1)(xxvi), (m)(5)§63.1209(g)(1)(iv)(B)

§63.1210(b)(3)(i), (c)(1)(i)

Are yourequesting to

extrapolate mercury feedrate limits from comprehensive

performance testlevels?

§63.1207(f)(1)(x)§63.1209(l)(1)(v)

Comply with the following:Standard

[G]§63.1209(l)(1)(v)Monitoring/Testing

[T][G]§63.1207(f)(1)(x)Reporting

[G]§63.1207(f)(1)(x)[G]§63.1209(l)(1)(v)

Yes

No

Comply with the following:Standard

§63.1209(l), (l)(1)(i)Monitoring/Testing§63.1209(l), (l)(1)(i)

715

Page 105: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(105 of 191)

Is the owneror operator complying withalternative metal emission

requirements?

705

§63.1216(e)

Yes

In lieu of complying with particulate matter standard in §63.1216(a)(7), you

may elect to comply with alternative metal emission control requirements.

Comply with the following:Standard

§63.1216(a)(3)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1216(d)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)[G]§63.1207(m)(1)-(2)

§63.1208(b)(3)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

Reporting§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)

§63.1207(f)(1)(xxvi), (m)(5)§63.1209(g)(1)(iv)(A)

§63.1210(b)(3)(i), (c)(1)(i)

Comply with the following:Standard

§63.1216(e)(2)(i)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1216(e)(4)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)[G]§63.1207(m)(1)-(2)

§63.1208(b)(3)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

Reporting§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)

§63.1207(f)(1)(xxvi), (m)(5)§63.1209(g)(1)(iv)(A)

§63.1210(b)(3)(i), (c)(1)(i)

707

No

Is thesource an area

source?No

Yes

§63.1216(a)(3)

702

Is the sourceelecting to comply

with §63.1216?

§63.1216(f)

No Yes

Page 106: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(106 of 191)

Is the owneror operator complying withalternative metal emission

requirements?

706

§63.1216(e)

Yes

Comply with the following:Standard

§63.1216(a)(4)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1216(d)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)[G]§63.1207(m)(1)-(2)

§63.1208(b)(4)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

Reporting§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)

§63.1207(f)(1)(xxvi), (m)(5)§63.1209(g)(1)(iv)(A)

§63.1210(b)(3)(i), (c)(1)(i)

Comply with the following:Standard

§63.1216(e)(2)(ii)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1216(e)(4)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)[G]§63.1207(m)(1)-(2)

§63.1208(b)(4)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

Reporting§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)

§63.1207(f)(1)(xxvi), (m)(5)§63.1209(g)(1)(iv)(A)

§63.1210(b)(3)(i), (c)(1)(i)

708

§63.1216(a)(4)

No

In lieu of complying with particulate matter standard in §63.1216(a)(7), you

may elect to comply with alternative metal emission control requirements.

Is thesource an area

source?No

Yes

Is the sourceelecting to comply

with §63.1216?

§63.1216(f)

YesNo

702

Page 107: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(107 of 191)

Are yourequesting to

extrapolate metal feedrate limits from comprehensive

performance testlevels?

Comply with the following:Standard

[G]§63.1209(n)(2)(vii)Monitoring/Testing

[T][G]§63.1207(f)(1)(x)[G]§63.1209(n)(2)(vii)

Reporting[G]§63.1207(f)(1)(x)

707

Yes

§63.1207(f)(1)(x)§63.1209(n)(2)(vii)

No

Comply with the following:Standard

§63.1209(n)(2)(i)-(ii)Monitoring/Testing§63.1209(n)(2)(ii)

Are yourequesting to

extrapolate metal feedrate limits from comprehensive

performance testlevels?

708

Yes

§63.1207(f)(1)(x)§63.1209(n)(2)(vii)

No

Comply with the following:Standard

§63.1209(n)(2)(i)-(ii), (n)(2)(vi)Monitoring/Testing

§63.1209(n)(2)(ii), (n)(2)(vi)

715

Page 108: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(108 of 191)

Is the owner oroperator complying with theCO standard rather than the

THC standard?

709

§63.1216(a)(5)(i)

No

Comply with the following:Standard

§63.1216(a)(5)(i)[G]§63.1206(c)(6)(iv)

§63.1216(d)Monitoring/Testing[G]§63.1206(b)(6)

[T]§63.1207(c)(1), [T][G](c)(2)[T]§63.1207(g)(2)(i), (g)(2)(v)

§63.1209(a)(1)(i), (a)(2), [G](a)(3)[G]§63.1209(a)(6), (a)(7)

Reporting§63.1207(f)(2)(i)

§63.1210(b)(3)(i), (c)(1)(i)

Comply with the following:Standard

§63.1216(a)(5)(ii)[G]§63.1206(c)(6)(iv)

§63.1216(d)Monitoring/Testing[G]§63.1206(b)(6)

[T]§63.1207(c)(1), [T][G](c)(2)[T]§63.1207(g)(2)(i), (g)(2)(v)

§63.1209(a)(1)(i), (a)(2), [G](a)(4)[G]§63.1209(a)(6), (a)(7)

Reporting§63.1207(f)(2)(i)

§63.1210(b)(3)(i), (c)(1)(i)

Yes

715

Page 109: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(109 of 191)

710

Comply with the following:Standard

§63.1216(a)(6)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n)(4), (o), (o)(1)(i)[G]§63.1209(o)(2)-(3), (o)(4)

§63.1216(d)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)§63.1207(g)(2)(iii), [G]§63.1207(m)(1)-(2)

[G]§63.1208(b)(5)(i), (b)(5)(ii)[G]§63.1208(b)(5)(ii)(B)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

Reporting§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)

§63.1207(f)(1)(xxv)-(xxvi), (f)(2)(iii), (m)(5)§63.1210(b)(3)(i), (c)(1)(i)

No

YesIs the

source an areasource?

§63.1216(a)(6)

Is the sourceelecting to comply

with §63.1216?

§63.1216(f)No

Yes

715

702

Page 110: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(110 of 191)

Is the owneror operator complying withalternative metal emission

requirements?

711

§63.1216(e)

Yes

Comply with the following:Standard

§63.1216(a)(7)§63.1206(b)(8)(v)-(vii), [G](c)(6)(iv)

§63.1209(m), [G](m)(1)(i), [G](m)(1)(iv)[G]§63.1209(m)(2), (m)(3), (n)(3)

§63.1216(d)Monitoring/Testing

[G]§63.1206(b)(8)(iii)[T]§63.1207(c)(1), [T][G](c)(2)§63.1207(g)(1)(i)(C), (g)(2)(iv)

§63.1208(b)(6)§63.1209(a)(1)(iii), (a)(5), [G](m)(1)(i)

[G]§63.1209(m)(1)(iv), [G](m)(2), (m)(3)Reporting

[G]§63.1206(b)(8)(iii)§63.1207(f)(1)(xvii), (f)(1)(xxiii)

[G]§63.1207(f)(1)(xxiv), (f)(2)(iv)§63.1210(b)(3)(i), (c)(1)(i)

712

No

Comply with §63.1216(e)(2)(i) and (ii) found in the appropriate metals paths.

§63.1216(a)(7)

In lieu of complying with particulate matter standard in §63.1216(a)(7), you

may elect to comply with alternative metal emission control requirements.

Is thesource an area

source?No

Yes

Is the sourceelecting to comply

with §63.1216?

§63.1216(f)

YesNo

702

702

Page 111: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(111 of 191)

Is thecombustor equipped with a

baghouse?

§63.1206(c)(8)(i)

Is a particulatematter detection system

being used?

§63.1206(c)(8)(i)(B)

NoComply with the following:

Standard§63.1206(c)(8)(i)(B), [G](c)(9)

Comply with the following:Standard

§63.1206(c)(8)(i)(A), [G](c)(8)(ii)-(iii)Recordkeeping

[G]§63.1206(c)(8)(iv)Reporting

§63.1206(c)(8)(i)(A), [G](c)(8)(iv)

Yes

712

NoYes

715

Page 112: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(112 of 191)

Does theincinerator burn

the dioxin-listed hazardous wastes F020, F021, F022,

F023, F026, or F027?

713

§63.1216(c)(2)

Comply with the following:Standard

§63.1216(c)(1)[G]§63.1206(c)(6)(iv)

[G]§63.1209(j)§63.1216(c)(3)(i)-(ii)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2)[T]§63.1207(f)(1)(ii)(D)

[G]§63.1209(j)Reporting

§63.1207(f)(1)(ii)(D), (f)(1)(xvii), (f)(1)(xix)§63.1210(b)(3)(i), (c)(1)(i)

Comply with the following:Standard

§63.1216(c)(2)[G]§63.1206(c)(6)(iv)

[G]§63.1209(j)§63.1216(c)(3)(i)-(ii)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2)[T]§63.1207(f)(1)(ii)(D)

[G]§63.1209(j)Reporting

§63.1207(f)(1)(ii)(D), (f)(1)(xvii), (f)(1)(xix)§63.1210(b)(3)(i), (c)(1)(i)

714

No Yes

Page 113: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(113 of 191)

Did the sourceprevious testing to document

conformance with theDRE standard?

Yes

§63.1206(b)(7)(iii)

Comply with the following:Recordkeeping

[G]§63.1206(b)(7)(i)

NoComply with the following:

Monitoring/Testing[T]§63.1206(b)(7)(iii)

Does the sourcefeed hazardous waste at a

location in the combustion systemother than the normal

flame zone?

Comply with the following:Standard

§63.1206(b)(7)(ii)(A), (7)(ii)(B)(2)Yes

§63.1206(b)(7)(ii)

No

714

715

715

Page 114: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(114 of 191)

Comply with the following:Standard

[G]§63.1206(b)(5), [G](c)(1)-(5), (c)(6)(i)-(ii)[G]§63.1206(c)(6)(v)-(vi), [G](c)(7)

§63.1207(g)(1)(iii)(A), [G](k), [G](l)(1)§63.1209(c)(1), [G](c)(2), [G](d), (i), (p), [G](q)

§63.1211(c)(1)-(2), (c)(4)Monitoring/Testing

[G]§63.1206(b)(5), [G](b)(12), [G](c)(3)[T]§63.1207(a), [T](b)(1), [T][G](d)-(e)

[T][G]§63.1207(f)(1)(i), [T](f)(1)(ii)[T]§63.1207(f)(1)(ii)(A)-(C), [T][G](f)(1)(iii)

[T]§63.1207(f)(1)(iv)-(ix), [T](f)(1)(xii)[T]§63.1207(f)(1)(xxvii), (g), (g)(1)(ii)

[T][G]§63.1207(h)-(i), [T][G](l)(1)§63.1208(b)(7)-(8)

§63.1209(b)(1), [G](b)(2), (b)(3)-(4), [G](b)(5)[G]§63.1209(c)(4), [G](d), [G](f), (g)(1)(i)-(ii)

§63.1209(i), (p), [G](q), (r)Recordkeeping

[G]§63.1206(b)(5), (b)(11), [G](b)(12)[G]§63.1206(c)(1)-(5), (c)(6)(vii), [G](c)(7)

§63.1207(f)(1)(xii), (g)(1)(iii)(A)§63.1209(b)(1), [G](c)(2), [G](c)(4), [G](q)

§63.1211(b), [G](c)(3), [G](d)Reporting

[G]§63.1206(b)(5), (b)(11), [G](c)(2)-(4)[G]§63.1207(e), [G](f)(1)(i), (f)(1)(ii)

§63.1207(f)(1)(ii)(A)-(C), [G](f)(1)(iii)§63.1207(f)(1)(iv)-(ix), (f)(1)(xii), (f)(1)(xviii)§63.1207(f)(1)(xxvii), (f)(2)(v)-(x), [G](h)-(i)

[G]§63.1207(j)(1), (j)(3)-(5), [G](k)[G]§63.1207(l)(1), (l)(3)

§63.1209(c)(3), (g)(1)(i)-(ii), [G](g)(1)(iii)[G]§63.1210(a), [G](b)(1), (b)(2), (c)(2)

[G]§63.1210(c)(3)-(4), [G](d)§63.1211(a), [G](c)(3), [G](d)

§63.1212(a)

715

702

Page 115: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(115 of 191)

Dioxins,Furans

801

Pb, Cd, Se

803

804

Sb, As, Be, Cr, Co, Mn, Ni

CO, THC

805

806

809Total

Chlorine

811

810

POHC

813

PM

Hg

Applicant must go through the flowchart for

each pollutant group.

Have allpollutant paths been

completed? End

§63.1216

No

Continue through next path.

802

Page 116: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(116 of 191)

803

§63.1216(b)(1)

Comply with the following:Standard

§63.1216(b)(1)§63.1216(b)(5)(i)

[G]§63.1206(c)(6)(iv)[G]§63.1207(l)(2)

§63.1209(k), (k)(1)(i), (k)(2)(i)-(ii)[G]§63.1209(k)(3)-(4), (k)(5), [G](k)(6)-(9)

§63.1216(d)Monitoring/Testing

[T][G]§63.1207(b)(2)-(3), [T](c)(1)[T][G]§63.1207(c)(2)

§63.1207(g)(1)(i)(A), (g)(2)(ii), (g)(2)(v)[G]§63.1208(b)(1)

§63.1209(k)(2)(i), (k)(3), (k)(8)Recordkeeping

§63.1209(k)(2)(i), (k)(3)[G]§63.1212(c)

Reporting§63.1207(f)(1)(xv), (f)(1)(xvii), (f)(1)(xix)[G]§63.1207(f)(1)(xx)-(xxi), (f)(1)(xxii)

§63.1207(f)(2)(ii), (j)(2)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

815

Comply with the following:Standard

§63.1216(b)(1)§63.1216(b)(5)(ii)

[G]§63.1206(c)(6)(iv)[G]§63.1207(l)(2)

§63.1209(k), (k)(1)(i), (k)(2)(i)-(ii)[G]§63.1209(k)(3)-(4), (k)(5), [G](k)(6)-(9)

§63.1216(d)Monitoring/Testing

[T][G]§63.1207(b)(2)-(3), [T](c)(1)[T][G]§63.1207(c)(2)

§63.1207(g)(1)(i)(A), (g)(2)(ii), (g)(2)(v)[G]§63.1208(b)(1)

§63.1209(k)(2)(i), (k)(3), (k)(8)Recordkeeping

§63.1209(k)(2)(i), (k)(3)[G]§63.1212(c)

Reporting§63.1207(f)(1)(xv), (f)(1)(xvii), (f)(1)(xix)[G]§63.1207(f)(1)(xx)-(xxi), (f)(1)(xxii)

§63.1207(f)(2)(ii), (j)(2)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

Is the owner oroperator complying with theCO standard rather than the

THC standard?

No Yes

Page 117: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(117 of 191)

804

Comply with the following:Standard

§63.1216(b)(2)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1216(d)

Monitoring/Testing[T]§63.1207(c)(1), [T][G](c)(2)

[G]§63.1207(m)(1)-(2)§63.1208(b)(2)§63.1209(a)(5)Recordkeeping

[G]§63.1207(m)(1)-(2)[G]§63.1212(c)

Reporting§63.1207(f)(1)(xvi), (f)(1)(xxvi), (m)(5)

§63.1209(g)(1)(iv)(B)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

Are yourequesting to

extrapolate mercury feedrate limits from comprehensive

performance testlevels?

§63.1207(f)(1)(x)§63.1209(l)(1)(v)

Comply with the following:Standard

[G]§63.1209(l)(1)(v)Monitoring/Testing

[T][G]§63.1207(f)(1)(x)Reporting

[G]§63.1207(f)(1)(x)[G]§63.1209(l)(1)(v)

Yes

No

Comply with the following:Standard

§63.1209(l), (l)(1)(i)Monitoring/Testing§63.1209(l), (l)(1)(i)

815

Page 118: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(118 of 191)

Is the owneror operator complying withalternative metal emission

requirements?

805

§63.1216(e)

Yes

Comply with the following:Standard

§63.1216(b)(3)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1216(d)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)[G]§63.1207(m)(1)-(2)

§63.1208(b)(3)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

[G]§63.1212(c)Reporting

§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)§63.1207(f)(1)(xxvi), (m)(5)

§63.1209(g)(1)(iv)(A)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

Comply with the following:Standard

§63.1216(e)(3)(i)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1216(e)(4)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)[G]§63.1207(m)(1)-(2)

§63.1208(b)(3)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

[G]§63.1212(c)Reporting

§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)§63.1207(f)(1)(xxvi), (m)(5)

§63.1209(g)(1)(iv)(A)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

807

No

§63.1216(b)(3)

802

In lieu of complying with particulate matter standard in §63.1216(b)(7), you

may elect to comply with alternative metal emission control requirements.

Is thesource an area

source?No

Yes

Is the sourceelecting to comply

with §63.1216?

§63.1216(f)

YesNo

Page 119: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(119 of 191)

Is the owneror operator complying withalternative metal emission

requirements?

806

§63.1216(e)

Yes

Comply with the following:Standard

§63.1216(b)(4)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1216(d)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)[G]§63.1207(m)(1)-(2)

§63.1208(b)(4)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

[G]§63.1212(c)Reporting

§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)§63.1207(f)(1)(xxvi), (m)(5)

§63.1209(g)(1)(iv)(A)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

Comply with the following:Standard

§63.1216(e)(3)(ii)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1216(e)(4)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)[G]§63.1207(m)(1)-(2)

§63.1208(b)(4)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

[G]§63.1212(c)Reporting

§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)§63.1207(f)(1)(xxvi), (m)(5)

§63.1209(g)(1)(iv)(A)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

808

§63.1216(b)(4)

No

In lieu of complying with particulate matter standard in §63.1216(b)(7), you

may elect to comply with alternative metal emission control requirements.

Is thesource an area

source?No

Yes

Is the sourceelecting to comply

with §63.1216?

§63.1216(f)

YesNo

802

Page 120: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(120 of 191)

Are yourequesting to

extrapolate metal feedrate limits from comprehensive

performance testlevels?

Comply with the following:Standard

[G]§63.1209(n)(2)(vii)Monitoring/Testing

[T][G]§63.1207(f)(1)(x)[G]§63.1209(n)(2)(vii)

Reporting[G]§63.1207(f)(1)(x)

807

Yes

§63.1207(f)(1)(x)§63.1209(n)(2)(vii)

No

Comply with the following:Standard

§63.1209(n)(2)(i)-(ii)Monitoring/Testing§63.1209(n)(2)(ii)

Are yourequesting to

extrapolate metal feedrate limits from comprehensive

performance testlevels?

808

Yes

§63.1207(f)(1)(x)§63.1209(n)(2)(vii)

No

Comply with the following:Standard

§63.1209(n)(2)(i)-(ii), (n)(2)(vi)Monitoring/Testing

§63.1209(n)(2)(ii), (n)(2)(vi)

815

Page 121: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(121 of 191)

Is the owner oroperator complying with theCO standard rather than the

THC standard?

809

§63.1216(b)(5)(i)

Comply with the following:Standard

§63.1216(b)(5)(i)[G]§63.1206(c)(6)(iv)

§63.1216(d)Monitoring/Testing[G]§63.1206(b)(6)

[T]§63.1207(c)(1), [T][G](c)(2)[T]§63.1207(g)(2)(i), (g)(2)(v)

§63.1209(a)(1)(i), (a)(2), [G](a)(3)[G]§63.1209(a)(6), (a)(7)

Recordkeeping[G]§63.1212(c)

Reporting§63.1207(f)(2)(i)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

Comply with the following:Standard

§63.1216(b)(5)(ii)[G]§63.1206(c)(6)(iv)

§63.1216(d)Monitoring/Testing[G]§63.1206(b)(6)

[T]§63.1207(c)(1), [T][G](c)(2)[T]§63.1207(g)(2)(i), (g)(2)(v)

§63.1209(a)(1)(i), (a)(2), [G](a)(4)[G]§63.1209(a)(6), (a)(7)

Recordkeeping[G]§63.1212(c)

Reporting§63.1207(f)(2)(i)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

Yes No

815

Page 122: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(122 of 191)

810

Comply with the following:Standard

§63.1216(b)(6)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n)(4), (o), (o)(1)(i)[G]§63.1209(o)(2)-(3), (o)(4)

§63.1216(d)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)§63.1207(g)(2)(iii), [G]§63.1207(m)(1)-(2)

[G]§63.1208(b)(5)(i), (b)(5)(ii)[G]§63.1208(b)(5)(ii)(B)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

[G]§63.1212(c)Reporting

§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)§63.1207(f)(1)(xxv)-(xxvi), (f)(2)(iii), (m)(5)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

No

Is thesource an area

source?§63.1216(b)(6)

Yes

Is the sourceelecting to comply

with §63.1216?

§63.1216(f)No

Yes

815

802

Page 123: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(123 of 191)

Is the owneror operator complying withalternative metal emission

requirements?

811

§63.1216(e)

Yes

In lieu of complying with particulate matter standard in §63.1216(b)(7), you

may elect to comply with alternative metal emission control requirements.

Comply with the following:Standard

§63.1216(b)(7)§63.1206(b)(8)(v)-(vii), [G](c)(6)(iv)

§63.1209(m), [G](m)(1)(i), [G](m)(1)(iv)[G]§63.1209(m)(2), (m)(3), (n)(3)

§63.1216(d)Monitoring/Testing

[G]§63.1206(b)(8)(iii)[T]§63.1207(c)(1), [T][G](c)(2)§63.1207(g)(1)(i)(C), (g)(2)(iv)

§63.1208(b)(6)§63.1209(a)(1)(iii), (a)(5), [G](m)(1)(i)

[G]§63.1209(m)(1)(iv), [G](m)(2), (m)(3)Recordkeeping[G]§63.1212(c)

Reporting[G]§63.1206(b)(8)(iii)

§63.1207(f)(1)(xvii), (f)(1)(xxiii)[G]§63.1207(f)(1)(xxiv), (f)(2)(iv)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

812

No

Comply with §63.1216(e)(3)(i) and (ii) found in the appropriate metals paths.

§63.1216(b)(7)

Is thesource an area

source?No

Yes

Is the sourceelecting to comply

with §63.1216?

§63.1216(f)

YesNo

802

802

Page 124: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(124 of 191)

Is thecombustor equipped with

a baghouse?

§63.1206(c)(8)(i)

Is a particulatematter detection system

being used?

§63.1206(c)(8)(i)(B)

NoComply with the following:

Standard§63.1206(c)(8)(i)(B), [G](c)(9)

Comply with the following:Standard

§63.1206(c)(8)(i)(A), [G](c)(8)(ii)-(iii)Recordkeeping

[G]§63.1206(c)(8)(iv)Reporting

§63.1206(c)(8)(i)(A), [G](c)(8)(iv)

Yes

812

NoYes

815

Page 125: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(125 of 191)

Does theincinerator burn

the dioxin-listed hazardous wastes F020, F021, F022,

F023, F026,or F027?

813

§63.1216(c)(2)

Comply with the following:Standard

§63.1216(c)(1)[G]§63.1206(c)(6)(iv)

[G]§63.1209(j)§63.1216(c)(3)(i)-(ii)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2)[T]§63.1207(f)(1)(ii)(D)

[G]§63.1209(j)Recordkeeping[G]§63.1212(c)

Reporting§63.1207(f)(1)(ii)(D), (f)(1)(xvii)

§63.1207((f)(1)(xix)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

Comply with the following:Standard

§63.1216(c)(2)[G]§63.1206(c)(6)(iv)

[G]§63.1209(j)§63.1216(c)(3)(i)-(ii)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2)[T]§63.1207(f)(1)(ii)(D)

[G]§63.1209(j)Recordkeeping[G]§63.1212(c)

Reporting§63.1207(f)(1)(ii)(D), (f)(1)(xvii)

§63.1207((f)(1)(xix)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

814

No Yes

Page 126: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(126 of 191)

814

Did the sourceComply with the following:

previous testing to documentNo Monitoring/Testing

conformance with the[T]§63.1206(b)(7)(iii)

DRE standard?

§63.1206(b)(7)(iii)

Yes815

Does the sourcefeed hazardous waste at a Comply with the following:

location in the combustion system Yes Standardother than the normal §63.1206(b)(7)(ii)(A), (7)(ii)(B)(2)

flame zone?

§63.1206(b)(7)(ii)

No

Comply with the following:Recordkeeping 815

[G]§63.1206(b)(7)(i)

Page 127: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(127 of 191)

Comply with the following:Standard

[G]§63.1206(b)(5), [G](c)(1)-(5), (c)(6)(i)-(ii)[G]§63.1206(c)(6)(v)-(vi), [G](c)(7)

§63.1207(g)(1)(iii)(A), [G](k), [G](l)(1)§63.1209(c)(1), [G](c)(2), [G](d), (i), (p), [G](q)

§63.1211(c)(1)-(2), (c)(4)Monitoring/Testing

[G]§63.1206(b)(5), [G](b)(12), [G](c)(3)[T]§63.1207(a), [T](b)(1), [T][G](d)-(e)

[T][G]§63.1207(f)(1)(i), [T](f)(1)(ii)[T]§63.1207(f)(1)(ii)(A)-(C), [T][G](f)(1)(iii)

[T]§63.1207(f)(1)(iv)-(ix), [T](f)(1)(xii)[T]§63.1207(f)(1)(xxvii), (g), (g)(1)(ii)

[T][G]§63.1207(h)-(i), [T][G](l)(1)§63.1208(b)(7)-(8)

§63.1209(b)(1), [G](b)(2), (b)(3)-(4), [G](b)(5)[G]§63.1209(c)(4), [G](d), [G](f), (g)(1)(i)-(ii)

§63.1209(i), (p), [G](q), (r)Recordkeeping

[G]§63.1206(b)(5), (b)(11), [G](b)(12)[G]§63.1206(c)(1)-(5), (c)(6)(vii), [G](c)(7)

§63.1207(f)(1)(xii), (g)(1)(iii)(A)§63.1209(b)(1), [G](c)(2), [G](c)(4), [G](q)

§63.1211(b), [G](c)(3), [G](d)Reporting

[G]§63.1206(b)(5), (b)(11), [G](c)(2)-(4)[G]§63.1207(e), [G](f)(1)(i), (f)(1)(ii)

§63.1207(f)(1)(ii)(A)-(C), [G](f)(1)(iii)§63.1207(f)(1)(iv)-(ix), (f)(1)(xii), (f)(1)(xviii)§63.1207(f)(1)(xxvii), (f)(2)(v)-(x), [G](h)-(i)

[G]§63.1207(j)(1), (j)(3)-(5), [G](k)[G]§63.1207(l)(1), (l)(3)

§63.1209(c)(3), (g)(1)(i)-(ii), [G](g)(1)(iii)[G]§63.1210(a), [G](b)(1), (b)(2), (c)(2)

[G]§63.1210(c)(3)-(4), [G](d)§63.1211(a), [G](c)(3), [G](d)

§63.1212(a)

815

802

Page 128: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(128 of 191)

Dioxins,Furans

901

Pb, Cd, Se

903

905

Sb, As, Be, Cr, Co, Mn, Ni

CO, THC

908

915

922Total

Chlorine

924

923

POHC

926

PM

Hg

Applicant must go through the flowchart for

each pollutant group.

Have allpollutant paths been

completed? End

§63.1217

No

Continue through next path.

902

Page 129: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(129 of 191)

Is the boilerequipped with a dry air pollution

control system?903

§63.1217(a)(1)(i)Yes

Comply with the following:Standard

§63.1217(a)(1)(i)[G]§63.1206(c)(6)(iv)

[G]§63.1207(l)(2)§63.1209(k), (k)(1)(i), (k)(2)(i)-(ii)

[G]§63.1209(k)(3)-(4), (k)(5), [G](k)(6)-(9)§63.1217(d)

Monitoring/Testing[T][G]§63.1207(b)(2), [T](c)(1), [T][G](c)(2)

§63.1207(g)(1)(i)(A), (g)(2)(ii), (g)(2)(v)[G]§63.1208(b)(1)

§63.1209(k)(2)(i), [G](k)(3), [G](k)(8)Recordkeeping

§63.1209(k)(2)(i), [G](k)(3)Reporting

§63.1207(f)(1)(xv), (f)(1)(xvii), (f)(1)(xix)[G]§63.1207(f)(1)(xx)-(xxi), (f)(1)(xxii)

§63.1207(f)(2)(ii), (j)(2)§63.1210(b)(3)(i), (c)(1)(i)

928

904No

Page 130: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(130 of 191)

Is the owner oroperator complying with theCO standard rather than the

THC standard?

904

§63.1217(a)(1)(ii)

Comply with the following:Standard

§63.1217(a)(1)(ii)[G]§63.1206(c)(6)(iv)

[G]§63.1207(l)(2)§63.1209(k), (k)(1)(i), (k)(2)(i)-(ii)

[G]§63.1209(k)(3)-(4), (k)(5), [G](k)(6)-(9)§63.1217(d)

Monitoring/Testing[T][G]§63.1207(b)(2)-(3), [T](c)(1)

[T][G]§63.1207(c)(2)§63.1207(g)(1)(i)(A), (g)(2)(ii), (g)(2)(v)

[G]§63.1208(b)(1)§63.1209(k)(2)(i), [G](k)(3), [G](k)(8)

Recordkeeping§63.1209(k)(2)(i), [G](k)(3)

Reporting§63.1207(f)(1)(xv), (f)(1)(xvii), (f)(1)(xix)[G]§63.1207(f)(1)(xx)-(xxi), (f)(1)(xxii)

§63.1207(f)(2)(ii), (j)(2)§63.1210(b)(3)(i), (c)(1)(i)

Comply with the following:Standard

§63.1217(a)(1)(ii)[G]§63.1206(c)(6)(iv)

[G]§63.1207(l)(2)§63.1209(k), (k)(1)(i), (k)(2)(i)-(ii)

[G]§63.1209(k)(3)-(4), (k)(5), [G](k)(6)-(9)§63.1217(d)

Monitoring/Testing[T][G]§63.1207(b)(2)-(3), [T](c)(1)

[T][G]§63.1207(c)(2)§63.1207(g)(1)(i)(A), (g)(2)(ii), (g)(2)(v)

[G]§63.1208(b)(1)§63.1209(k)(2)(i), [G](k)(3), [G](k)(8)

Recordkeeping§63.1209(k)(2)(i), [G](k)(3)

Reporting§63.1207(f)(1)(xv), (f)(1)(xvii), (f)(1)(xix)[G]§63.1207(f)(1)(xx)-(xxi), (f)(1)(xxii)

§63.1207(f)(2)(ii), (j)(2)§63.1210(b)(3)(i), (c)(1)(i)

Yes No

928

Page 131: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(131 of 191)

905

§63.1217(a)(2)(i)

No

Comply with the following:Standard

§63.1217(a)(2)(i)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1217(d)

Monitoring/Testing[T]§63.1207(c)(1), [T][G](c)(2)

[G]§63.1207(m)(1)-(2)§63.1208(b)(2)§63.1209(a)(5)Recordkeeping

[G]§63.1207(m)(1)-(2)Reporting

§63.1207(f)(1)(xvi), (f)(1)(xxvi), (m)(5)§63.1209(g)(1)(iv)(B)

§63.1210(b)(3)(i), (c)(1)(i)

Comply with the following:Standard

§63.1217(a)(2)(ii)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1217(d)

Monitoring/Testing[T]§63.1207(c)(1), [T][G](c)(2)

[G]§63.1207(m)(1)-(2)§63.1208(b)(2)§63.1209(a)(5)Recordkeeping

[G]§63.1207(m)(1)-(2)Reporting

§63.1207(f)(1)(xvi), (f)(1)(xxvi), (m)(5)§63.1209(g)(1)(iv)(B)

§63.1210(b)(3)(i), (c)(1)(i)

906 907

Doesthe boiler burn

hazardous waste withan as-fired heating value

less than 10,000Btu/lb

Yes

Page 132: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(132 of 191)

Are yourequesting to

extrapolate mercury feedrate limits from comprehensive

performance testlevels?

Comply with the following:Standard

[G]§63.1209(l)(1)(v)Monitoring/Testing

[T][G]§63.1207(f)(1)(x)Reporting

[G]§63.1207(f)(1)(x)[G]§63.1209(l)(1)(v)

906

Yes

§63.1207(f)(1)(x)§63.1209(l)(1)(v)

No

Comply with the following:Standard

§63.1209(l), (l)(1)(ii), (l)(1)(ii)(A)[G]§63.1209(l)(1)(ii)(C)-(D)

Monitoring/Testing§63.1209(l), (l)(1)(ii), (l)(1)(ii)(A)

[G]§63.1209(l)(1)(ii)(C)-(D)

Are yourequesting to

extrapolate mercury feedrate limits from comprehensive

performance testlevels?

907

Yes

§63.1207(f)(1)(x)§63.1209(l)(1)(v)

No

Comply with the following:Standard

§63.1209(l), (l)(1)(ii), (l)(1)(ii)(A)[G]§63.1209(l)(1)(ii)(B)[G]§63.1209(l)(1)(ii)(D)

Monitoring/Testing§63.1209(l), (l)(1)(ii), (l)(1)(ii)(A)

[G]§63.1209(l)(1)(ii)(B)[G]§63.1209(l)(1)(ii)(D)

928

Page 133: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(133 of 191)

Is the owneror operator complying withalternative metal emission

requirements?

908

§63.1217(e)

YesNo

§63.1217(a)(3)

902

Doesthe boiler burn

hazardous waste withan as-fired heating value

less than 10,000Btu/lb?

§63.1217(a)(3)(i)

Doesthe boiler burn

hazardous waste withan as-fired heating value

less than 10,000Btu/lb?

§63.1217(e)(2)(i)(A)

No No

910 912

Yes Yes

909 911

In lieu of complying with particulate matter standard in §63.1217(a)(7), you

may elect to comply with alternative metal emission control requirements.

Is thesource an area

source?No

Yes

Is the sourceelecting to comply

with §63.1217?

§63.1217(f)

No

Yes

Page 134: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(134 of 191)

Comply with the following:Standard

§63.1217(a)(3)(i)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1217(d)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)[G]§63.1207(m)(1)-(2)

§63.1208(b)(3)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

Reporting§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)

§63.1207(f)(1)(xxvi), (m)(5)§63.1209(g)(1)(iv)(A)

§63.1210(b)(3)(i), (c)(1)(i)

Comply with the following:Standard

§63.1217(a)(3)(ii)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1217(d)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)[G]§63.1207(m)(1)-(2)

§63.1208(b)(3)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

Reporting§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)

§63.1207(f)(1)(xxvi), (m)(5)§63.1209(g)(1)(iv)(A)

§63.1210(b)(3)(i), (c)(1)(i)

913 914

909 910

Page 135: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(135 of 191)

Comply with the following:Standard

§63.1217(e)(2)(i)(A)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1217(e)(4)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)[G]§63.1207(m)(1)-(2)

§63.1208(b)(3)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

Reporting§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)

§63.1207(f)(1)(xxvi), (m)(5)§63.1209(g)(1)(iv)(A)

§63.1210(b)(3)(i), (c)(1)(i)

Comply with the following:Standard

§63.1217(e)(2)(ii)(A)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1217(e)(4)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)[G]§63.1207(m)(1)-(2)

§63.1208(b)(3)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

Reporting§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)

§63.1207(f)(1)(xxvi), (m)(5)§63.1209(g)(1)(iv)(A)

§63.1210(b)(3)(i), (c)(1)(i)

911 912

913 914

Page 136: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(136 of 191)

Are yourequesting to

extrapolate metal feedrate limits from comprehensive

performance testlevels?

Comply with the following:Standard

[G]§63.1209(n)(2)(vii)Monitoring/Testing

[T][G]§63.1207(f)(1)(x)[G]§63.1209(n)(2)(vii)

Reporting[G]§63.1207(f)(1)(x)

913

Yes

§63.1207(f)(1)(x)§63.1209(n)(2)(vii)

No

Comply with the following:Standard

§63.1209(n)(2)(i), (n)(2)(v)(A)§63.1209(n)(2)(v)(A)(1)

[G]§63.1209(n)(2)(v)(A)(3)Monitoring/Testing

§63.1209(n)(2)(v)(A)§63.1209(n)(2)(v)(A)(1)

[G]§63.1209(n)(2)(v)(A)(3)

Are yourequesting to

extrapolate metal feedrate limits from comprehensive

performance testlevels?

914

Yes

§63.1207(f)(1)(x)§63.1209(n)(2)(vii)

No

Comply with the following:Standard

§63.1209(n)(2)(i), (n)(2)(v)(A)§63.1209(n)(2)(v)(A)(1)

[G]§63.1209(n)(2)(v)(A)(2)Monitoring/Testing

§63.1209(n)(2)(v)(A)§63.1209(n)(2)(v)(A)(1)

[G]§63.1209(n)(2)(v)(A)(2)

928

Page 137: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(137 of 191)

Is the owneror operator complying withalternative metal emission

requirements?

915

§63.1217(e)

YesNo

§63.1217(a)(4)

Doesthe boiler burn

hazardous waste withan as-fired heating value

less than 10,000Btu/lb?

§63.1217(a)(4)(i)

Doesthe boiler burn

hazardous waste withan as-fired heating value

less than 10,000Btu/lb?

§63.1217(e)(2)(i)(B)

No No

917 919

Yes Yes

916 918

In lieu of complying with particulate matter standard in §63.1217(a)(7), you

may elect to comply with alternative metal emission control requirements.

Is thesource an area

source?No

Yes

Is the sourceelecting to comply

with §63.1217?

§63.1217(f)No

Yes

902

Page 138: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(138 of 191)

Comply with the following:Standard

§63.1217(a)(4)(i)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1217(d)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)[G]§63.1207(m)(1)-(2)

§63.1208(b)(4)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

Reporting§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)

§63.1207(f)(1)(xxvi), (m)(5)§63.1209(g)(1)(iv)(A)

§63.1210(b)(3)(i), (c)(1)(i)

Comply with the following:Standard

§63.1217(a)(4)(ii)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1217(d)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)[G]§63.1207(m)(1)-(2)

§63.1208(b)(4)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

Reporting§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)

§63.1207(f)(1)(xxvi), (m)(5)§63.1209(g)(1)(iv)(A)

§63.1210(b)(3)(i), (c)(1)(i)

920 921

916 917

Page 139: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(139 of 191)

Comply with the following:Standard

§63.1217(e)(2)(i)(B)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1217(e)(4)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)[G]§63.1207(m)(1)-(2)

§63.1208(b)(4)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

Reporting§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)

§63.1207(f)(1)(xxvi), (m)(5)§63.1209(g)(1)(iv)(A)

§63.1210(b)(3)(i), (c)(1)(i)

Comply with the following:Standard

§63.1217(e)(2)(ii)(B)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1217(e)(4)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)[G]§63.1207(m)(1)-(2)

§63.1208(b)(4)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

Reporting§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)

§63.1207(f)(1)(xxvi), (m)(5)§63.1209(g)(1)(iv)(A)

§63.1210(b)(3)(i), (c)(1)(i)

918 919

920 921

Page 140: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(140 of 191)

Are yourequesting to

extrapolate metal feedrate limits from comprehensive

performance testlevels?

Comply with the following:Standard

[G]§63.1209(n)(2)(vii)Monitoring/Testing

[T][G]§63.1207(f)(1)(x)[G]§63.1209(n)(2)(vii)

Reporting[G]§63.1207(f)(1)(x)

920

Yes

§63.1207(f)(1)(x)§63.1209(n)(2)(vii)

No

Comply with the following:Standard

§63.1209(n)(2)(i)§63.1209(n)(2)(v)(B)(2), (n)(2)(vi)

Monitoring/Testing§63.1209(n)(2)(v)(B)(2), (n)(2)(vi)

Are yourequesting to

extrapolate metal feedrate limits from comprehensive

performance testlevels?

921

Yes

§63.1207(f)(1)(x)§63.1209(n)(2)(vii)

No

Comply with the following:Standard

§63.1209(n)(2)(i)[G]§63.1209(n)(2)(v)(B)(1)

§63.1209(n)(2)(vi)Monitoring/Testing

[G]§63.1209(n)(2)(v)(B)(1)§63.1209(n)(2)(vi)

928

Page 141: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(141 of 191)

Is the owner oroperator complying with theCO standard rather than the

THC standard?

922

§63.1217(a)(5)(i)

No

Comply with the following:Standard

§63.1217(a)(5)(i)[G]§63.1206(c)(6)(iv)

§63.1217(d)Monitoring/Testing[G]§63.1206(b)(6)

[T]§63.1207(c)(1), [T][G](c)(2)[T]§63.1207(g)(2)(i), (g)(2)(v)

§63.1209(a)(1)(i), (a)(2), [G](a)(3)[G]§63.1209(a)(6), (a)(7)

Reporting§63.1207(f)(2)(i)

§63.1210(b)(3)(i), (c)(1)(i)

Comply with the following:Standard

§63.1217(a)(5)(ii)[G]§63.1206(c)(6)(iv)

§63.1217(d)Monitoring/Testing[G]§63.1206(b)(6)

[T]§63.1207(c)(1), [T][G](c)(2)[T]§63.1207(g)(2)(i), (g)(2)(v)

§63.1209(a)(1)(i), (a)(2), [G](a)(4)[G]§63.1209(a)(6), (a)(7)

Reporting§63.1207(f)(2)(i)

§63.1210(b)(3)(i), (c)(1)(i)

Yes

928

Page 142: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(142 of 191)

923Is the

source an areasource?

§63.1217(a)(6)

Doesthe boiler burn

hazardous waste withan as-fired heating value

less than 10,000Btu/lb?

§63.1217(a)(6)(i)

No

Comply with the following:Standard

§63.1217(a)(6)(i)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n)(4), (o), (o)(1)(ii)(B)

[G]§63.1209(o)(2)-(3), (o)(4)§63.1217(d)

Monitoring/Testing[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)

§63.1207(g)(2)(iii), [G]§63.1207(m)(1)-(2)[G]§63.1208(b)(5)(i), (b)(5)(ii)

[G]§63.1208(b)(5)(ii)(B)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

Reporting§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)

§63.1207(f)(1)(xxv)-(xxvi), (f)(2)(iii), (m)(5)§63.1210(b)(3)(i), (c)(1)(i)

Comply with the following:Standard

§63.1217(a)(6)(ii)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n)(4), (o), [G](o)(1)(ii)(A)

[G]§63.1209(o)(2)-(3), (o)(4)§63.1217(d)

Monitoring/Testing[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)

§63.1207(g)(2)(iii), [G]§63.1207(m)(1)-(2)[G]§63.1208(b)(5)(i), (b)(5)(ii)

[G]§63.1208(b)(5)(ii)(B)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

Reporting§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)

§63.1207(f)(1)(xxv)-(xxvi), (f)(2)(iii), (m)(5)§63.1210(b)(3)(i), (c)(1)(i)

Yes

No

Yes

Is the sourceelecting to comply

with §63.1217?

§63.1217(f)

YesNo

928

902

Page 143: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(143 of 191)

Is the owneror operator complying withalternative metal emission

requirements?

924

§63.1217(e)

Yes

Comply with the following:Standard

§63.1217(a)(7)§63.1206(b)(8)(v)-(vii), [G](c)(6)(iv)

§63.1209(m), [G](m)(1)(i), [G](m)(1)(iv)[G]§63.1209(m)(2), (m)(3), (n)(3)

§63.1217(d)Monitoring/Testing

[G]§63.1206(b)(8)(iii)[T]§63.1207(c)(1), [T][G](c)(2), (g)(1)(i)(C)

§63.1207(g)(2)(iv)§63.1208(b)(6)

§63.1209(a)(1)(iii), (a)(5), (m), [G](m)(1)(i)[G]§63.1209(m)(1)(iv), [G](m)(2), (m)(3)

Reporting[G]§63.1206(b)(8)(iii)

§63.1207(f)(1)(xvii), (f)(1)(xxiii)[G]§63.1207(f)(1)(xxiv), (f)(2)(iv)

§63.1210(b)(3)(i), (c)(1)(i)

925

No

Comply with §63.1217(e)(2)(i) and (ii) found in the appropriate metals paths.

§63.1217(a)(7)

In lieu of complying with particulate matter standard in §63.1217(a)(7), you

may elect to comply with alternative metal emission control requirements.

Is thesource an area

source?No

Yes

Is the sourceelecting to comply

with §63.1217?

§63.1217(f)

YesNo

902

902

Page 144: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(144 of 191)

925

Is theYes combustor equipped with No

a baghouse?

§63.1206(c)(8)(i)

Is a particulatematter detection system Yes

being used?

§63.1206(c)(8)(i)(B)Comply with the following:

No Standard§63.1206(c)(8)(i)(B), [G](c)(9)

Comply with the following:Standard

§63.1206(c)(8)(i)(A), [G](c)(8)(ii)-(iii)Recordkeeping 928

[G]§63.1206(c)(8)(iv)Reporting

§63.1206(c)(8)(i)(A), [G](c)(8)(iv)

Page 145: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(145 of 191)

Does theincinerator burn the

dioxin-listed hazardous wastes F020, F021, F022, F023,

F026, or F027?

926

§63.1217(c)(2)

Comply with the following:Standard

§63.1217(c)(1)[G]§63.1206(c)(6)(iv)

[G]§63.1209(j)§63.1217(c)(3)(i)-(ii)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2)[T]§63.1207(f)(1)(ii)(D)

[G]§63.1209(j)Reporting

§63.1207(f)(1)(ii)(D), (f)(1)(xvii)§63.1207(f)(1)(xix)

§63.1210(b)(3)(i), (c)(1)(i)

Comply with the following:Standard

§63.1217(c)(2)[G]§63.1206(c)(6)(iv)

[G]§63.1209(j)§63.1217(c)(3)(i)-(ii)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2)[T]§63.1207(f)(1)(ii)(D)

[G]§63.1209(j)Reporting

§63.1207(f)(1)(ii)(D), (f)(1)(xvii)§63.1207(f)(1)(xix)

§63.1210(b)(3)(i), (c)(1)(i)

927

No Yes

Page 146: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(146 of 191)

Did the sourceprevious testing to document

conformance with theDRE standard?

Yes

§63.1206(b)(7)(iii)

Comply with the following:Recordkeeping

[G]§63.1206(b)(7)(i)

NoComply with the following:

Monitoring/Testing[T]§63.1206(b)(7)(iii)

Does the sourcefeed hazardous waste at a

location in the combustion systemother than the normal

flame zone?

Comply with the following:Standard

§63.1206(b)(7)(ii)(A), (7)(ii)(B)(2)Yes

§63.1206(b)(7)(ii)

No

927

928

928

Page 147: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(147 of 191)

Comply with the following:Standard

[G]§63.1206(b)(5), [G](c)(1)-(5), (c)(6)(i)-(ii)[G]§63.1206(c)(6)(v)-(vi), [G](c)(7)

§63.1207(g)(1)(iii)(A), [G](k), [G](l)(1)§63.1209(c)(1), [G](c)(2), [G](d), (i), (p), [G](q)

§63.1211(c)(1)-(2), (c)(4)Monitoring/Testing

[G]§63.1206(b)(5), [G](b)(12), [G](c)(3)[T]§63.1207(a), [T](b)(1), [T][G](d)-(e)

[T][G]§63.1207(f)(1)(i), [T](f)(1)(ii)[T]§63.1207(f)(1)(ii)(A)-(C), [T][G](f)(1)(iii)

[T]§63.1207(f)(1)(iv)-(ix), [T](f)(1)(xii)[T]§63.1207(f)(1)(xxvii), (g), (g)(1)(ii)

[T][G]§63.1207(h)-(i), [T][G](l)(1)§63.1208(b)(7)-(8)

§63.1209(b)(1), [G](b)(2), (b)(3)-(4), [G](b)(5)[G]§63.1209(c)(4), [G](d), [G](f), (g)(1)(i)-(ii)

§63.1209(i), (p), [G](q), (r)Recordkeeping

[G]§63.1206(b)(5), (b)(11), [G](b)(12)[G]§63.1206(c)(1)-(5), (c)(6)(vii), [G](c)(7)

§63.1207(f)(1)(xii), (g)(1)(iii)(A)§63.1209(b)(1), [G](c)(2), [G](c)(4), [G](q)

§63.1211(b), [G](c)(3), [G](d)Reporting

[G]§63.1206(b)(5), (b)(11), [G](c)(2)-(4)[G]§63.1207(e), [G](f)(1)(i), (f)(1)(ii)

§63.1207(f)(1)(ii)(A)-(C), [G](f)(1)(iii)§63.1207(f)(1)(iv)-(ix), (f)(1)(xii), (f)(1)(xviii)§63.1207(f)(1)(xxvii), (f)(2)(v)-(x), [G](h)-(i)

[G]§63.1207(j)(1), (j)(3)-(5), [G](k)[G]§63.1207(l)(1), (l)(3)

§63.1209(c)(3), (g)(1)(i)-(ii), [G](g)(1)(iii)[G]§63.1210(a), [G](b)(1), (b)(2), (c)(2)

[G]§63.1210(c)(3)-(4), [G](d)§63.1211(a), [G](c)(3), [G](d)

§63.1212(a)

928

902

Page 148: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(148 of 191)

Dioxins,Furans

1001

Pb, Cd, Se

1003

1005

Sb, As, Be, Cr, Co, Mn, Ni

CO, THC

1008

1015

1022Total

Chlorine

1024

1023

POHC

1026

PM

Hg

Applicant must go through the flowchart for each

pollutant group.

Have allpollutant paths been

completed? End

§63.1217

No

Continue through next path.

1002

Page 149: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(149 of 191)

Is the boilerequipped with a dry air pollution

control system?1003

§63.1217(b)(1)(i)Yes

Comply with the following:Standard

§63.1217(b)(1)(i)[G]§63.1206(c)(6)(iv)

[G]§63.1207(l)(2)§63.1209(k), (k)(1)(i), (k)(2)(i)-(ii)

[G]§63.1209(k)(3)-(4), (k)(5), [G](k)(6)-(9)§63.1217(d)

Monitoring/Testing[T][G]§63.1207(b)(2), [T](c)(1), [T][G](c)(2)

§63.1207(g)(1)(i)(A), (g)(2)(ii), (g)(2)(v)[G]§63.1208(b)(1)

§63.1209(k)(2)(i), [G](k)(3), [G](k)(8)Recordkeeping

§63.1209(k)(2)(i), [G](k)(3)[G]§63.1212(c)

Reporting§63.1207(f)(1)(xv), (f)(1)(xvii), (f)(1)(xix)[G]§63.1207(f)(1)(xx)-(xxi), (f)(1)(xxii)

§63.1207(f)(2)(ii), (j)(2)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

1028

1004No

Page 150: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(150 of 191)

Is the owner oroperator complying with theCO standard rather than the

THC standard?

1004

§63.1217(b)(1)(ii)

Comply with the following:Standard

§63.1217(b)(1)(ii)[G]§63.1206(c)(6)(iv)

[G]§63.1207(l)(2)§63.1209(k), (k)(1)(i), (k)(2)(i)-(ii)

[G]§63.1209(k)(3)-(4), (k)(5), [G](k)(6)-(9)§63.1217(d)

Monitoring/Testing[T][G]§63.1207(b)(2)-(3), [T](c)(1)

[T][G]§63.1207(c)(2)§63.1207(g)(1)(i)(A), (g)(2)(ii), (g)(2)(v)

[G]§63.1208(b)(1)§63.1209(k)(2)(i), [G](k)(3), [G](k)(8)

Recordkeeping§63.1209(k)(2)(i), [G](k)(3

[G]§63.1212(c)Reporting

§63.1207(f)(1)(xv), (f)(1)(xvii), (f)(1)(xix)[G]§63.1207(f)(1)(xx)-(xxi), (f)(1)(xxii)

§63.1207(f)(2)(ii), (j)(2)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

Comply with the following:Standard

§63.1217(b)(1)(ii)[G]§63.1206(c)(6)(iv)

[G]§63.1207(l)(2)§63.1209(k), (k)(1)(i), (k)(2)(i)-(ii)

[G]§63.1209(k)(3)-(4), (k)(5), [G](k)(6)-(9)§63.1217(d)

Monitoring/Testing[T][G]§63.1207(b)(2)-(3), [T](c)(1)

[T][G]§63.1207(c)(2)§63.1207(g)(1)(i)(A), (g)(2)(ii), (g)(2)(v)

[G]§63.1208(b)(1)§63.1209(k)(2)(i), [G](k)(3), [G](k)(8)

Recordkeeping§63.1209(k)(2)(i), [G](k)(3

[G]§63.1212(c)Reporting

§63.1207(f)(1)(xv), (f)(1)(xvii), (f)(1)(xix)[G]§63.1207(f)(1)(xx)-(xxi), (f)(1)(xxii)

§63.1207(f)(2)(ii), (j)(2)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

Yes No

1028

Page 151: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(151 of 191)

1005

§63.1217(b)(2)(i)

No

Comply with the following:Standard

§63.1217(b)(2)(i)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1217(d)

Monitoring/Testing[T]§63.1207(c)(1), [T][G](c)(2)

[G]§63.1207(m)(1)-(2)§63.1208(b)(2)§63.1209(a)(5)Recordkeeping

[G]§63.1207(m)(1)-(2)[G]§63.1212(c)

Reporting§63.1207(f)(1)(xvi), (f)(1)(xxvi), (m)(5)

§63.1209(g)(1)(iv)(B)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

Comply with the following:Standard

§63.1217(b)(2)(ii)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1217(d)

Monitoring/Testing[T]§63.1207(c)(1), [T][G](c)(2)

[G]§63.1207(m)(1)-(2)§63.1208(b)(2)§63.1209(a)(5)Recordkeeping

[G]§63.1207(m)(1)-(2)[G]§63.1212(c)

Reporting§63.1207(f)(1)(xvi), (f)(1)(xxvi), (m)(5)

§63.1209(g)(1)(iv)(B)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

1006 1007

Doesthe boiler burn

hazardous waste withan as-fired heating value

less than 10,000Btu/lb

Yes

Page 152: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(152 of 191)

Are yourequesting to

extrapolate mercury feedrate limits from comprehensive

performance testlevels?

Comply with the following:Standard

[G]§63.1209(l)(1)(v)Monitoring/Testing

[T][G]§63.1207(f)(1)(x)Reporting

[G]§63.1207(f)(1)(x)[G]§63.1209(l)(1)(v)

1006

Yes

§63.1207(f)(1)(x)§63.1209(l)(1)(v)

No

Comply with the following:Standard

§63.1209(l), (l)(1)(ii), (l)(1)(ii)(A)[G]§63.1209(l)(1)(ii)(C)-(D)

Monitoring/Testing§63.1209(l), (l)(1)(ii), (l)(1)(ii)(A)

[G]§63.1209(l)(1)(ii)(C)-(D)

Are yourequesting to

extrapolate mercury feedrate limits from comprehensive

performance testlevels?

1007

Yes

§63.1207(f)(1)(x)§63.1209(l)(1)(v)

No

Comply with the following:Standard

§63.1209(l), (l)(1)(ii), (l)(1)(ii)(A)[G]§63.1209(l)(1)(ii)(B)[G]§63.1209(l)(1)(ii)(D)

Monitoring/Testing§63.1209(l), (l)(1)(ii), (l)(1)(ii)(A)

[G]§63.1209(l)(1)(ii)(B)[G]§63.1209(l)(1)(ii)(D)

1028

Page 153: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(153 of 191)

Is the owneror operator complying withalternative metal emission

requirements?

1008

§63.1217(e)

YesNo

§63.1217(b)(3)

1002

Doesthe boiler burn

hazardous waste withan as-fired heating value

less than 10,000Btu/lb?

§63.1217(b)(3)(i)

Doesthe boiler burn

hazardous waste withan as-fired heating value

less than 10,000Btu/lb?

§63.1217(e)(3)(i)(A)

No No

1010 1012

Yes Yes

1009 1011

In lieu of complying with particulate matter standard in §63.1217(b)(7), you

may elect to comply with alternative metal emission control requirements.

Is thesource an area

source?No

Yes

Is the sourceelecting to comply

with §63.1217?

§63.1217(f)

YesNo

Page 154: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(154 of 191)

Comply with the following:Standard

§63.1217(b)(3)(i)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1217(d)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)[G]§63.1207(m)(1)-(2)

§63.1208(b)(3)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

[G]§63.1212(c)Reporting

§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)§63.1207(f)(1)(xxvi), (m)(5)

§63.1209(g)(1)(iv)(A)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

Comply with the following:Standard

§63.1217(b)(3)(ii)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1217(d)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)[G]§63.1207(m)(1)-(2)

§63.1208(b)(3)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

[G]§63.1212(c)Reporting

§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)§63.1207(f)(1)(xxvi), (m)(5)

§63.1209(g)(1)(iv)(A)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

1013 1014

1009 1010

Page 155: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(155 of 191)

Comply with the following:Standard

§63.1217(e)(3)(i)(A)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1217(e)(4)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)[G]§63.1207(m)(1)-(2)

§63.1208(b)(3)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

[G]§63.1212(c)Reporting

§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)§63.1207(f)(1)(xxvi), (m)(5)

§63.1209(g)(1)(iv)(A)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

Comply with the following:Standard

§63.1217(e)(3)(ii)(A)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1217(e)(4)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)[G]§63.1207(m)(1)-(2)

§63.1208(b)(3)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

[G]§63.1212(c)Reporting

§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)§63.1207(f)(1)(xxvi), (m)(5)

§63.1209(g)(1)(iv)(A)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

1011 1012

1013 1014

Page 156: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(156 of 191)

Are yourequesting to

extrapolate metal feedrate limits from comprehensive

performance testlevels?

Comply with the following:Standard

[G]§63.1209(n)(2)(vii)Monitoring/Testing

[T][G]§63.1207(f)(1)(x)[G]§63.1209(n)(2)(vii)

Reporting[G]§63.1207(f)(1)(x)

1013

Yes

§63.1207(f)(1)(x)§63.1209(n)(2)(vii)

No

Comply with the following:Standard

§63.1209(n)(2)(i), (n)(2)(v)(A)§63.1209(n)(2)(v)(A)(1)

[G]§63.1209(n)(2)(v)(A)(3)Monitoring/Testing

§63.1209(n)(2)(v)(A)§63.1209(n)(2)(v)(A)(1)

[G]§63.1209(n)(2)(v)(A)(3)

Are yourequesting to

extrapolate metal feedrate limits from comprehensive

performance testlevels?

1014

Yes

§63.1207(f)(1)(x)§63.1209(n)(2)(vii)

No

Comply with the following:Standard

§63.1209(n)(2)(i), (n)(2)(v)(A)§63.1209(n)(2)(v)(A)(1)

[G]§63.1209(n)(2)(v)(A)(2)Monitoring/Testing

§63.1209(n)(2)(v)(A)§63.1209(n)(2)(v)(A)(1)

[G]§63.1209(n)(2)(v)(A)(2)

1028

Page 157: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(157 of 191)

Is the owneror operator complying withalternative metal emission

requirements?

1015

§63.1217(e)

YesNo

§63.1217(b)(4)

Doesthe boiler burn

hazardous waste withan as-fired heating value

less than 10,000Btu/lb?

§63.1217(b)(4)(i)

Doesthe boiler burn

hazardous waste withan as-fired heating value

less than 10,000Btu/lb?

§63.1217(e)(3)(i)(B)

No No

1017 1019

Yes Yes

1016 1018

In lieu of complying with particulate matter standard in §63.1217(b)(7), you

may elect to comply with alternative metal emission control requirements.

Is thesource an area

source?No

Yes

Is the sourceelecting to comply

with §63.1217?

§63.1217(f)

YesNo

1002

Page 158: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(158 of 191)

Comply with the following:Standard

§63.1217(b)(4)(i)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1217(d)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)[G]§63.1207(m)(1)-(2)

§63.1208(b)(4)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

[G]§63.1212(c)Reporting

§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)§63.1207(f)(1)(xxvi), (m)(5)

§63.1209(g)(1)(iv)(A)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

Comply with the following:Standard

§63.1217(b)(4)(ii)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1217(d)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)[G]§63.1207(m)(1)-(2)

§63.1208(b)(4)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

[G]§63.1212(c)Reporting

§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)§63.1207(f)(1)(xxvi), (m)(5)

§63.1209(g)(1)(iv)(A)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

1020 1021

1016 1017

Page 159: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(159 of 191)

Comply with the following:Standard

§63.1217(e)(3)(i)(B)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1217(e)(4)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)[G]§63.1207(m)(1)-(2)

§63.1208(b)(4)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

[G]§63.1212(c)Reporting

§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)§63.1207(f)(1)(xxvi), (m)(5)

§63.1209(g)(1)(iv)(A)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

Comply with the following:Standard

§63.1217(e)(3)(ii)(B)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1217(e)(4)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)[G]§63.1207(m)(1)-(2)

§63.1208(b)(4)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

[G]§63.1212(c)Reporting

§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)§63.1207(f)(1)(xxvi), (m)(5)

§63.1209(g)(1)(iv)(A)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

1018 1019

1020 1021

Page 160: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(160 of 191)

Are yourequesting to

extrapolate metal feedrate limits from comprehensive

performance testlevels?

Comply with the following:Standard

[G]§63.1209(n)(2)(vii)Monitoring/Testing

[T][G]§63.1207(f)(1)(x)[G]§63.1209(n)(2)(vii)

Reporting[G]§63.1207(f)(1)(x)

1020

Yes

§63.1207(f)(1)(x)§63.1209(n)(2)(vii)

No

Comply with the following:Standard

§63.1209(n)(2)(i)§63.1209(n)(2)(v)(B)(2), (n)(2)(vi)

Monitoring/Testing§63.1209(n)(2)(v)(B)(2), (n)(2)(vi)

Are yourequesting to

extrapolate metal feedrate limits from comprehensive

performance testlevels?

1021

Yes

§63.1207(f)(1)(x)§63.1209(n)(2)(vii)

No

Comply with the following:Standard

§63.1209(n)(2)(i)[G]§63.1209(n)(2)(v)(B)(1)

§63.1209(n)(2)(vi)Monitoring/Testing

[G]§63.1209(n)(2)(v)(B)(1)§63.1209(n)(2)(vi)

1028

Page 161: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(161 of 191)

Is the owner oroperator complying with theCO standard rather than the

THC standard?

1022

§63.1217(b)(5)(i)

Comply with the following:Standard

§63.1217(b)(5)(i)[G]§63.1206(c)(6)(iv)

§63.1217(d)Monitoring/Testing[G]§63.1206(b)(6)

[T]§63.1207(c)(1), [T][G](c)(2)[T]§63.1207(g)(2)(i), (g)(2)(v)

§63.1209(a)(1)(i), (a)(2), [G](a)(3)[G]§63.1209(a)(6), (a)(7)

Recordkeeping[G]§63.1212(c)

Reporting§63.1207(f)(2)(i)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

Comply with the following:Standard

§63.1217(b)(5)(ii)[G]§63.1206(c)(6)(iv)

§63.1217(d)Monitoring/Testing[G]§63.1206(b)(6)

[T]§63.1207(c)(1), [T][G](c)(2)[T]§63.1207(g)(2)(i), (g)(2)(v)

§63.1209(a)(1)(i), (a)(2), [G](a)(4)[G]§63.1209(a)(6), (a)(7)

Recordkeeping[G]§63.1212(c)

Reporting§63.1207(f)(2)(i)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

Yes No

1028

Page 162: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(162 of 191)

1023

§63.1217(b)(6)

Doesthe boiler burn

hazardous waste withan as-fired heating value

less than 10,000Btu/lb?

§63.1217(b)(6)(i)

No

Comply with the following:Standard

§63.1217(b)(6)(i)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n)(4), (o), (o)(1)(ii)(B)

[G]§63.1209(o)(2)-(3), (o)(4)§63.1217(d)

Monitoring/Testing[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)

§63.1207(g)(2)(iii), [G]§63.1207(m)(1)-(2)[G]§63.1208(b)(5)(i), (b)(5)(ii)

[G]§63.1208(b)(5)(ii)(B)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

[G]§63.1212(c)Reporting

§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)§63.1207(f)(1)(xxv)-(xxvi), (f)(2)(iii), (m)(5)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

Comply with the following:Standard

§63.1217(b)(6)(ii)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n)(4), (o), [G](o)(1)(ii)(A)

[G]§63.1209(o)(2)-(3), (o)(4)§63.1217(d)

Monitoring/Testing[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)

§63.1207(g)(2)(iii), [G]§63.1207(m)(1)-(2)[G]§63.1208(b)(5)(i), (b)(5)(ii)

[G]§63.1208(b)(5)(ii)(B)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

[G]§63.1212(c)Reporting

§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)§63.1207(f)(1)(xxv)-(xxvi), (f)(2)(iii), (m)(5)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

Yes

Is thesource an area

source?No

Yes

Is the sourceelecting to comply

with §63.1217?

§63.1217(f)

YesNo

1028

1002

Page 163: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(163 of 191)

Is the owneror operator complying withalternative metal emission

requirements?

1024

§63.1217(e)

Yes

Comply with the following:Standard

§63.1217(b)(7)§63.1206(b)(8)(v)-(vii), [G](c)(6)(iv)

§63.1209(m), [G](m)(1)(i), [G](m)(1)(iv)[G]§63.1209(m)(2), (m)(3), (n)(3)

§63.1217(d)Monitoring/Testing

[G]§63.1206(b)(8)(iii)[T]§63.1207(c)(1), [T][G](c)(2), (g)(1)(i)(C)

§63.1207(g)(2)(iv)§63.1208(b)(6)

§63.1209(a)(1)(iii), (a)(5), [G](m)(1)(i)[G]§63.1209(m)(1)(iv), [G](m)(2), (m)(3)

Recordkeeping[G]§63.1212(c)

Reporting[G]§63.1206(b)(8)(iii)

§63.1207(f)(1)(xvii), (f)(1)(xxiii)[G]§63.1207(f)(1)(xxiv), (f)(2)(iv)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

1025

No

Comply with §63.1217(e)(3)(i) and (ii) found in the appropriate metals paths.

§63.1217(b)(7)

In lieu of complying with particulate matter standard in §63.1217(b)(7), you

may elect to comply with alternative metal emission control requirements.

Is thesource an area

source?

Yes

Is the sourceelecting to comply

with §63.1217?

§63.1217(f)

No

1002

1002

No

Yes

Page 164: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(164 of 191)

Is thecombustor equipped with a

baghouse?

§63.1206(c)(8)(i)

Yes

No

Is a particulatematter detection system

being used?

§63.1206(c)(8)(i)(B)

NoComply with the following:

Standard§63.1206(c)(8)(i)(B), [G](c)(9)

Comply with the following:Standard

§63.1206(c)(8)(i)(A), [G](c)(8)(ii)-(iii)Recordkeeping

[G]§63.1206(c)(8)(iv)Reporting

§63.1206(c)(8)(i)(A), [G](c)(8)(iv)

Yes

1025

1028

1028

Page 165: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(165 of 191)

Does theincinerator burn the dioxin-

listed hazardous wastes F020, F021, F022, F023, F026,

or F027?

1026

§63.1217(c)(2)

Comply with the following:Standard

§63.1217(c)(1)[G]§63.1206(c)(6)(iv)

[G]§63.1209(j)§63.1217(c)(3)(i)-(ii)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2)[T]§63.1207(f)(1)(ii)(D)

[G]§63.1209(j)Recordkeeping[G]§63.1212(c)

Reporting§63.1207(f)(1)(ii)(D), (f)(1)(xvii)

§63.1207(f)(1)(xix)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

Comply with the following:Standard

§63.1217(c)(2)[G]§63.1206(c)(6)(iv)

[G]§63.1209(j)§63.1217(c)(3)(i)-(ii)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2)[T]§63.1207(f)(1)(ii)(D)

[G]§63.1209(j)Recordkeeping[G]§63.1212(c)

Reporting§63.1207(f)(1)(ii)(D), (f)(1)(xvii)

§63.1207(f)(1)(xix)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

1027

No Yes

Page 166: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(166 of 191)

Did the sourceprevious testing to document

conformance with theDRE standard?

Yes

§63.1206(b)(7)(iii)

Comply with the following:Recordkeeping

[G]§63.1206(b)(7)(i)

NoComply with the following:

Monitoring/Testing[T]§63.1206(b)(7)(iii)

Does the sourcefeed hazardous waste at a

location in the combustion systemother than the normal

flame zone?

Comply with the following:Standard

§63.1206(b)(7)(ii)(A), (7)(ii)(B)(2)Yes

§63.1206(b)(7)(ii)

No

1027

1028

1028

Page 167: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(167 of 191)

Comply with the following:Standard

[G]§63.1206(b)(5), [G](c)(1)-(5), (c)(6)(i)-(ii)[G]§63.1206(c)(6)(v)-(vi), [G](c)(7)

§63.1207(g)(1)(iii)(A), [G](k), [G](l)(1)§63.1209(c)(1), [G](c)(2), [G](d), (i), (p), [G](q)

§63.1211(c)(1)-(2), (c)(4)Monitoring/Testing

[G]§63.1206(b)(5), [G](b)(12), [G](c)(3)[T]§63.1207(a), [T](b)(1), [T][G](d)-(e)

[T][G]§63.1207(f)(1)(i), [T](f)(1)(ii)[T]§63.1207(f)(1)(ii)(A)-(C), [T][G](f)(1)(iii)

[T]§63.1207(f)(1)(iv)-(ix), [T](f)(1)(xii)[T]§63.1207(f)(1)(xxvii), (g), (g)(1)(ii)

[T][G]§63.1207(h)-(i), [T][G](l)(1)§63.1208(b)(7)-(8)

§63.1209(b)(1), [G](b)(2), (b)(3)-(4), [G](b)(5)[G]§63.1209(c)(4), [G](d), [G](f), (g)(1)(i)-(ii)

§63.1209(i), (p), [G](q), (r)Recordkeeping

[G]§63.1206(b)(5), (b)(11), [G](b)(12)[G]§63.1206(c)(1)-(5), (c)(6)(vii), [G](c)(7)

§63.1207(f)(1)(xii), (g)(1)(iii)(A)§63.1209(b)(1), [G](c)(2), [G](c)(4), [G](q)

§63.1211(b), [G](c)(3), [G](d)Reporting

[G]§63.1206(b)(5), (b)(11), [G](c)(2)-(4)[G]§63.1207(e), [G](f)(1)(i), (f)(1)(ii)

§63.1207(f)(1)(ii)(A)-(C), [G](f)(1)(iii)§63.1207(f)(1)(iv)-(ix), (f)(1)(xii), (f)(1)(xviii)§63.1207(f)(1)(xxvii), (f)(2)(v)-(x), [G](h)-(i)

[G]§63.1207(j)(1), (j)(3)-(5), [G](k)[G]§63.1207(l)(1), (l)(3)

§63.1209(c)(3), (g)(1)(i)-(ii), [G](g)(1)(iii)[G]§63.1210(a), [G](b)(1), (b)(2), (c)(2)

[G]§63.1210(c)(3)-(4), [G](d)§63.1211(a), [G](c)(3), [G](d)

§63.1212(a)

1028

1002

Page 168: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(168 of 191)

Dioxins,Furans

1101

Pb, Cd, Se

1103

1104

Sb, As, Be, Cr, Co, Mn, Ni

CO, THC

1105

1106

1107Total

Chlorine

1109

1108

POHC

1111

PM

Hg

Applicant must go through the flowchart for each

pollutant group.

Have allpollutant paths been

completed? End

§63.1218

No

Continue through next path.

1102

Page 169: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(169 of 191)

1103

§63.1218(a)(1)

Comply with the following:Standard

§63.1218(a)(1)§63.1218(a)(5)(ii)

[G]§63.1206(c)(6)(iv)[G]§63.1207(l)(2)

§63.1209(k), (k)(1)(i), (k)(2)(i)-(ii)[G]§63.1209(k)(3)-(4), (k)(5), [G](k)(6)-(9)

§63.1218(d)Monitoring/Testing

[T][G]§63.1207(b)(2)-(3), [T](c)(1)[T][G]§63.1207(c)(2)

§63.1207(g)(1)(i)(A), (g)(2)(ii), (g)(2)(v)[G]§63.1208(b)(1)

§63.1209(k)(2)(i), [G](k)(3), [G](k)(8)Recordkeeping

§63.1209(k)(2)(i), [G](k)(3)Reporting

§63.1207(f)(1)(xv), (f)(1)(xvii), (f)(1)(xix)[G]§63.1207(f)(1)(xx)-(xxi), (f)(1)(xxii)

§63.1207(f)(2)(ii), (j)(2)§63.1210(b)(3)(i), (c)(1)(i)

1113

Comply with the following:Standard

§63.1218(a)(1)§63.1218(a)(5)(i)

[G]§63.1206(c)(6)(iv)[G]§63.1207(l)(2)

§63.1209(k), (k)(1)(i), (k)(2)(i)-(ii)[G]§63.1209(k)(3)-(4), (k)(5), [G](k)(6)-(9)

§63.1218(d)Monitoring/Testing

[T][G]§63.1207(b)(2)-(3), [T](c)(1)[T][G]§63.1207(c)(2)

§63.1207(g)(1)(i)(A), (g)(2)(ii), (g)(2)(v)[G]§63.1208(b)(1)

§63.1209(k)(2)(i), [G](k)(3), [G](k)(8)Recordkeeping

§63.1209(k)(2)(i), [G](k)(3)Reporting

§63.1207(f)(1)(xv), (f)(1)(xvii), (f)(1)(xix)[G]§63.1207(f)(1)(xx)-(xxi), (f)(1)(xxii)

§63.1207(f)(2)(ii), (j)(2)§63.1210(b)(3)(i), (c)(1)(i)

Is the owner oroperator complying with theCO standard rather than the

THC standard?

No Yes

Page 170: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(170 of 191)

1104

Comply with the following:Standard

§63.1218(a)(2)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1218(d)

Monitoring/Testing[T]§63.1207(c)(1), [T][G](c)(2)

[G]§63.1207(m)(1)-(2)§63.1208(b)(2)§63.1209(a)(5)Recordkeeping

[G]§63.1207(m)(1)-(2)Reporting

§63.1207(f)(1)(xvi), (f)(1)(xxvi), (m)(5)§63.1209(g)(1)(iv)(B)

§63.1210(b)(3)(i), (c)(1)(i)

1113

Page 171: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(171 of 191)

1105

Comply with the following:Standard

§63.1218(a)(3)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1218(d)Monitoring/Testing

[T]§63.1207(c)(1),[T][G](c)(2), (f)(1)(xi)[G]§63.1207(m)(1)-(2)

§63.1208(b)(3)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

Reporting§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)

§63.1207(f)(1)(xxvi), (m)(5)§63.1209(g)(1)(iv)(A)

§63.1210(b)(3)(i), (c)(1)(i)

No

Is thesource an area

source?

§63.1218(a)(3)

Yes

1102

Is the sourceelecting to comply

with §63.1218?

§63.1218(e)

No

Yes

1113

Page 172: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(172 of 191)

1106

Comply with the following:Standard

§63.1218(a)(4)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1218(d)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)[G]§63.1207(m)(1)-(2)

§63.1208(b)(4)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

Reporting§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)

§63.1207(f)(1)(xxvi), (m)(5)§63.1209(g)(1)(iv)(A)

§63.1210(b)(3)(i), (c)(1)(i)

No

Is thesource an area

source?

§63.1218(a)(4)

Yes

Is the sourceelecting to comply

with §63.1218?

§63.1218(e)

No

Yes

1113

1102

Page 173: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(173 of 191)

Is the owner oroperator complying with theCO standard rather than the

THC standard?

1107

§63.1218(a)(5)(i)

Comply with the following:Standard

§63.1218(a)(5)(i)[G]§63.1206(c)(6)(iv)

§63.1218(d)Monitoring/Testing[G]§63.1206(b)(6)

[T]§63.1207(c)(1), [T][G](c)(2)[T]§63.1207(g)(2)(i), (g)(2)(v)

§63.1209(a)(1)(i), (a)(2), [G](a)(3)[G]§63.1209(a)(6), (a)(7)

Reporting§63.1207(f)(2)(i)

§63.1210(b)(3)(i), (c)(1)(i)

Comply with the following:Standard

§63.1218(a)(5)(ii)[G]§63.1206(c)(6)(iv)

§63.1218(d)Monitoring/Testing[G]§63.1206(b)(6)

[T]§63.1207(c)(1), [T][G](c)(2)[T]§63.1207(g)(2)(i), (g)(2)(v)

§63.1209(a)(1)(i), (a)(2), [G](a)(4)[G]§63.1209(a)(6), (a)(7)

Reporting§63.1207(f)(2)(i)

§63.1210(b)(3)(i), (c)(1)(i)

Yes No

1113

Page 174: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(174 of 191)

Is the facilitymeeting the ppmv emissionstandard (as opposed to the

calculated SRE)?

1108

§63.1218(a)(6)(i)

No

Comply with the following:Standard

§63.1218(a)(6)(i)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n)(4), (o), (o)(1)(i), [G](o)(2)-(3)

§63.1209(o)(4)§63.1218(d)

Monitoring/Testing[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)

§63.1207(g)(2)(iii), [G]§63.1207(m)(1)-(2)[G]§63.1208(b)(5)(i)

§63.1209(a)(5), (c)(5)Recordkeeping

[G]§63.1207(m)(1)-(2)Reporting

§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)§63.1207(f)(1)(xxv)-(xxvi), (f)(2)(iii)

§63.1207(m)(5)§63.1210(b)(3)(i), (c)(1)(i)

Comply with the following:Standard

§63.1218(a)(6)(ii)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n)(4), (o), (o)(1)(i), [G](o)(2)-(3)

§63.1209(o)(4)§63.1218(d)

Monitoring/Testing[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)

§63.1207(g)(2)(iii), [G]§63.1207(m)(1)-(2)[G]§63.1208(b)(5)(i)

§63.1209(a)(5), (c)(5)Recordkeeping

[G]§63.1207(m)(1)-(2)Reporting

§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)§63.1207(f)(1)(xxv)-(xxvi), (f)(2)(iii)

§63.1207(m)(5)§63.1210(b)(3)(i), (c)(1)(i)

Yes

Is thesource an area

source?

§63.1218(a)(6)

Is the source electing to comply with

§63.1218(e)?§63.1218(e)

Yes

NoNo

1113

1102

Page 175: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(175 of 191)

1109

Comply with the following:Standard

§63.1218(a)(7)§63.1206(b)(8)(v)-(vii), [G](c)(6)(iv)

§63.1209(m), [G](m)(1)(i), [G](m)(1)(iv)[G]§63.1209(m)(2), (n)(3)

§63.1218(d)Monitoring/Testing

[G]§63.1206(b)(8)(iii)[T]§63.1207(c)(1), [T][G](c)(2), (g)(1)(i)(C)

§63.1207(g)(2)(iv)§63.1208(b)(6)

§63.1209(a)(1)(iii), (a)(5), [G](m)(1)(i)[G]§63.1209(m)(1)(iv), [G](m)(2)

Reporting[G]§63.1206(b)(8)(iii)

§63.1207(f)(1)(xvii), (f)(1)(xxiii)[G]§63.1207(f)(1)(xxiv), (f)(2)(iv)

§63.1210(b)(3)(i), (c)(1)(i)

1110

No

Is thesource an area

source?§63.1218(a)(7)

Yes

Is the sourceelecting to comply

with §63.1218?

§63.1218(e)

No

Yes

1102

Page 176: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(176 of 191)

Is thecombustor equipped with

a baghouse?

§63.1206(c)(8)(i)

Is a particulatematter detection system

being used?

§63.1206(c)(8)(i)(B)

No

Comply with the following:Standard

§63.1206(c)(8)(i)(B), [G](c)(9)

Comply with the following:Standard

§63.1206(c)(8)(i)(A), [G](c)(8)(ii)-(iii)Recordkeeping

[G]§63.1206(c)(8)(iv)Reporting

§63.1206(c)(8)(i)(A), [G](c)(8)(iv)

Yes

1110

NoYes

1113

Page 177: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(177 of 191)

Does theincinerator burn the dioxin-

listed hazardous wastes F020, F021, F022, F023, F026,

or F027?

1111

§63.1218(c)(2)

Comply with the following:Standard

§63.1218(c)(1)[G]§63.1206(c)(6)(iv)

[G]§63.1209(j)§63.1218(c)(3)(i)-(ii)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2)[T]§63.1207(f)(1)(ii)(D)

[G]§63.1209(j)Reporting

§63.1207(f)(1)(ii)(D), (f)(1)(xvii)§63.1207(f)(1)(xix)

§63.1210(b)(3)(i), (c)(1)(i)

Comply with the following:Standard

§63.1218(c)(2)[G]§63.1206(c)(6)(iv)

[G]§63.1209(j)§63.1218(c)(3)(i)-(ii)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2)[T]§63.1207(f)(1)(ii)(D)

[G]§63.1209(j)Reporting

§63.1207(f)(1)(ii)(D), (f)(1)(xvii)§63.1207(f)(1)(xix)

§63.1210(b)(3)(i), (c)(1)(i)

1112

No Yes

Page 178: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(178 of 191)

Did the source use previous testing to

document conformance with the DRE standard?

Yes

§63.1206(b)(7)(iii)

Comply with the following:Recordkeeping

[G]§63.1206(b)(7)(i)

NoComply with the following:

Monitoring/Testing[T]§63.1206(b)(7)(iii)

Does the sourcefeed hazardous waste at

a location in the combustion systemother than the normal

flame zone?

Comply with the following:Standard

§63.1206(b)(7)(ii)(A), (7)(ii)(B)(2)Yes

§63.1206(b)(7)(ii)

No

1112

1113

1113

Page 179: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(179 of 191)

Comply with the following:Standard

[G]§63.1206(b)(5), [G](c)(1)-(5), (c)(6)(i)-(ii)[G]§63.1206(c)(6)(v)-(vi), [G](c)(7)

§63.1207(g)(1)(iii)(A), [G](k), [G](l)(1)§63.1209(c)(1), [G](c)(2), [G](d), (i), (p), [G](q)

§63.1211(c)(1)-(2), (c)(4)Monitoring/Testing

[G]§63.1206(b)(5), [G](b)(12), [G](c)(3)[T]§63.1207(a), [T](b)(1), [T][G](d)-(e)

[T][G]§63.1207(f)(1)(i), [T](f)(1)(ii)[T]§63.1207(f)(1)(ii)(A)-(C), [T][G](f)(1)(iii)

[T]§63.1207(f)(1)(iv)-(ix), [T](f)(1)(xii)[T]§63.1207(f)(1)(xxvii), (g), (g)(1)(ii)

[T][G]§63.1207(h)-(i), [T][G](l)(1)§63.1208(b)(7)-(8)

§63.1209(b)(1), [G](b)(2), (b)(3)-(4), [G](b)(5)[G]§63.1209(c)(4), [G](d), [G](f), (g)(1)(i)-(ii)

§63.1209(i), (p), [G](q), (r)Recordkeeping

[G]§63.1206(b)(5), (b)(11), [G](b)(12)[G]§63.1206(c)(1)-(5), (c)(6)(vii), [G](c)(7)

§63.1207(f)(1)(xii), (g)(1)(iii)(A)§63.1209(b)(1), [G](c)(2), [G](c)(4), [G](q)

§63.1211(b), [G](c)(3), [G](d)Reporting

[G]§63.1206(b)(5), (b)(11), [G](c)(2)-(4)[G]§63.1207(e), [G](f)(1)(i), (f)(1)(ii)

§63.1207(f)(1)(ii)(A)-(C), [G](f)(1)(iii)§63.1207(f)(1)(iv)-(ix), (f)(1)(xii), (f)(1)(xviii)§63.1207(f)(1)(xxvii), (f)(2)(v)-(x), [G](h)-(i)

[G]§63.1207(j)(1), (j)(3)-(5), [G](k)[G]§63.1207(l)(1), (l)(3)

§63.1209(c)(3), (g)(1)(i)-(ii), [G](g)(1)(iii)[G]§63.1210(a), [G](b)(1), (b)(2), (c)(2)

[G]§63.1210(c)(3)-(4), [G](d)§63.1211(a), [G](c)(3), [G](d)

§63.1212(a)

1113

1102

Page 180: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(180 of 191)

Dioxins,Furans

1301

Pb, Cd, Se

1303

1304

Sb, As, Be, Cr, Co, Mn, Ni

CO, THC

1305

1306

1307Total

Chlorine

1309

1308

POHC

1311

PM

Hg

Applicant must go through the flowchart for each

pollutant group.

Have allpollutant paths been

completed? End

§63.1218

No

Continue through next path.

1302

Page 181: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(181 of 191)

1303

§63.1218(b)(1)

Comply with the following:Standard

§63.1218(b)(1)§63.1218(b)(5)(i)

[G]§63.1206(c)(6)(iv)[G]§63.1207(l)(2)

§63.1209(k), (k)(1)(i), (k)(2)(i)-(ii)[G]§63.1209(k)(3)-(4), (k)(5), [G](k)(6)-(9)

§63.1218(d)Monitoring/Testing

[T][G]§63.1207(b)(2)-(3), [T](c)(1)[T][G]§63.1207(c)(2)

§63.1207(g)(1)(i)(A), (g)(2)(ii), (g)(2)(v)[G]§63.1208(b)(1)

§63.1209(k)(2)(i), [G](k)(3), [G](k)(8)Recordkeeping

§63.1209(k)(2)(i), [G](k)(3)[G]§63.1212(c)

Reporting§63.1207(f)(1)(xv), (f)(1)(xvii), (f)(1)(xix)[G]§63.1207(f)(1)(xx)-(xxi), (f)(1)(xxii)

§63.1207(f)(2)(ii), (j)(2)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

1313

Comply with the following:Standard

§63.1218(b)(1)§63.1218(b)(5)(ii)

[G]§63.1206(c)(6)(iv)[G]§63.1207(l)(2)

§63.1209(k), (k)(1)(i), (k)(2)(i)-(ii)[G]§63.1209(k)(3)-(4), (k)(5), [G](k)(6)-(9)

§63.1218(d)Monitoring/Testing

[T][G]§63.1207(b)(2)-(3), [T](c)(1)[T][G]§63.1207(c)(2)

§63.1207(g)(1)(i)(A), (g)(2)(ii), (g)(2)(v)[G]§63.1208(b)(1)

§63.1209(k)(2)(i), [G](k)(3), [G](k)(8)Recordkeeping

§63.1209(k)(2)(i), [G](k)(3)[G]§63.1212(c)

Reporting§63.1207(f)(1)(xv), (f)(1)(xvii), (f)(1)(xix)[G]§63.1207(f)(1)(xx)-(xxi), (f)(1)(xxii)

§63.1207(f)(2)(ii), (j)(2)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

Is the owner oroperator complying with theCO standard rather than the

THC standard?

YesNo

Page 182: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(182 of 191)

1304

Comply with the following:Standard

§63.1218(b)(2)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1218(d)

Monitoring/Testing§63.1207(c)(1), [G](c)(2)[T][G]§63.1207(m)(1)-(2)

§63.1208(b)(2)§63.1209(a)(5)Recordkeeping

[G]§63.1207(m)(1)-(2)[G]§63.1212(c)

Reporting§63.1207(f)(1)(xvi), (f)(1)(xxvi), (m)(5)

§63.1209(g)(1)(iv)(B)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

1313

Page 183: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(183 of 191)

1305

Comply with the following:Standard

§63.1218(b)(3)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1218(d)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)[G]§63.1207(m)(1)-(2)

§63.1208(b)(3)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

[G]§63.1212(c)Reporting

§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)§63.1207(f)(1)(xxvi), (m)(5)

§63.1209(g)(1)(iv)(A)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

No

Is thesource an area

source?§63.1218(b)(3)

Yes

1302

Is the sourceelecting to comply

with §63.1218?

§63.1218(e)No

Yes

1313

Page 184: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(184 of 191)

1306

Comply with the following:Standard

§63.1218(b)(4)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n), (n)(1), [G](n)(5)

§63.1218(d)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)[G]§63.1207(m)(1)-(2)

§63.1208(b)(4)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

[G]§63.1212(c)Reporting

§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)§63.1207(f)(1)(xxvi), (m)(5)

§63.1209(g)(1)(iv)(A)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

No

Is thesource an area

source?§63.1218(b)(4)

Yes

Is the sourceelecting to comply

with §63.1218?

§63.1218(e)No

Yes

1313

1302

Page 185: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(185 of 191)

Is the owner oroperator complying with theCO standard rather than the

THC standard?

1307

§63.1218(b)(5)(i)

No

Comply with the following:Standard

§63.1218(b)(5)(i)[G]§63.1206(c)(6)(iv)

§63.1218(d)Monitoring/Testing[G]§63.1206(b)(6)

[T]§63.1207(c)(1), [T][G](c)(2)[T]§63.1207(g)(2)(i), (g)(2)(v)

§63.1209(a)(1)(i), (a)(2), [G](a)(3)[G]§63.1209(a)(6), (a)(7)

Recordkeeping[G]§63.1212(c)

Reporting§63.1207(f)(2)(i)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

Comply with the following:Standard

§63.1218(b)(5)(ii)[G]§63.1206(c)(6)(iv)

§63.1218(d)Monitoring/Testing[G]§63.1206(b)(6)

[T]§63.1207(c)(1), [T][G](c)(2)[T]§63.1207(g)(2)(i), (g)(2)(v)

§63.1209(a)(1)(i), (a)(2), [G](a)(4)[G]§63.1209(a)(6), (a)(7)

Recordkeeping[G]§63.1212(c)

Reporting§63.1207(f)(2)(i)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

Yes

1313

Page 186: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(186 of 191)

Is the facilitymeeting the ppmv emissionstandard (as opposed to the

calculated SRE)?

1308

§63.1218(b)(6)(i)

No

Comply with the following:Standard

§63.1218(b)(6)(i)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n)(4), (o), (o)(1)(i)[G]§63.1209(o)(2)-(3), (o)(4)

§63.1218(d)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)§63.1207(g)(2)(iii), [G]§63.1207(m)(1)-(2)

[G]§63.1208(b)(5)(i)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

[G]§63.1212(c)Reporting

§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)§63.1207(f)(1)(xxv)-(xxvi), (f)(2)(iii), (m)(5)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

Comply with the following:Standard

§63.1218(b)(6)(ii)[G]§63.1206(c)(6)(iv)

[G]§63.1207(m)(1)-(2), (m)(3)§63.1209(n)(4), (o), (o)(1)(i)[G]§63.1209(o)(2)-(3), (o)(4)

§63.1218(d)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2), (f)(1)(xi)§63.1207(g)(2)(iii), [G]§63.1207(m)(1)-(2)

[G]§63.1208(b)(5)(i)§63.1209(a)(5), (c)(5)

Recordkeeping[G]§63.1207(m)(1)-(2)

[G]§63.1212(c)Reporting

§63.1207(f)(1)(xi), (f)(1)(xvi)-(xvii)§63.1207(f)(1)(xxv)-(xxvi), (f)(2)(iii), (m)(5)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

Yes1302

Is thesource an area

source?

Is the sourceelecting to comply with

§63.1218(e)?

§63.1218(e)

No

§63.1218(b)(6)

Yes

Yes

No

1313

Page 187: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(187 of 191)

1309

Comply with the following:Standard

§63.1218(b)(7)§63.1206(b)(8)(v)-(vii), [G](c)(6)(iv)

§63.1209(m), [G](m)(1)(i), [G](m)(1)(iv)[G]§63.1209(m)(2), (n)(3)

§63.1218(d)Monitoring/Testing

[G]§63.1206(b)(8)(iii)[T]§63.1207(c)(1), [T][G](c)(2), (g)(1)(i)(C)

§63.1207(g)(2)(iv)§63.1208(b)(6)

§63.1209(a)(1)(iii), (a)(5), [G](m)(1)(i)[G]§63.1209(m)(1)(iv), [G](m)(2)

Recordkeeping[G]§63.1212(c)

Reporting[G]§63.1206(b)(8)(iii)

§63.1207(f)(1)(xvii), (f)(1)(xxiii)[G]§63.1207(f)(1)(xxiv), (f)(2)(iv)

§63.1210(b)(3)(ii), (c)(1)(ii)[G]§63.1212(b)-(c)

1310

No

Is thesource an area

source?§63.1218(b)(7)

Yes

1302

Is the sourceelecting to comply

with §63.1218?

§63.1218(e)

No

Yes

Page 188: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(188 of 191)

Is thecombustor equipped with a

baghouse?

§63.1206(c)(8)(i)

Is a particulatematter detection system

being used?

§63.1206(c)(8)(i)(B)

NoComply with the following:

Standard§63.1206(c)(8)(i)(B), [G](c)(9)

Comply with the following:Standard

§63.1206(c)(8)(i)(A), [G](c)(8)(ii)-(iii)Recordkeeping

[G]§63.1206(c)(8)(iv)Reporting

§63.1206(c)(8)(i)(A), [G](c)(8)(iv)

Yes

1310

NoYes

1313

Page 189: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(189 of 191)

Does theincinerator burn the dioxin-

listed hazardous wastes F020, F021, F022, F023, F026,

or F027?

1311

§63.1218(c)(2)

Comply with the following:Standard

§63.1218(c)(1)[G]§63.1206(c)(6)(iv)

[G]§63.1209(j)§63.1218(c)(3)(i)-(ii)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2)[T]§63.1207(f)(1)(ii)(D)

[G]§63.1209(j)Recordkeeping[G]§63.1212(c)

Reporting§63.1207(f)(1)(ii)(D), (f)(1)(xvii)

§63.1207(f)(1)(xix)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

Comply with the following:Standard

§63.1218(c)(2)[G]§63.1206(c)(6)(iv)

[G]§63.1209(j)§63.1218(c)(3)(i)-(ii)Monitoring/Testing

[T]§63.1207(c)(1), [T][G](c)(2)[T]§63.1207(f)(1)(ii)(D)

[G]§63.1209(j)Recordkeeping[G]§63.1212(c)

Reporting§63.1207(f)(1)(ii)(D), (f)(1)(xvii)

§63.1207(f)(1)(xix)§63.1210(b)(3)(ii), (c)(1)(ii)

[G]§63.1212(b)-(c)

1312

No Yes

Page 190: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(190 of 191)

Did the sourceuse previous testing to

document conformance with the DRE standard?

Yes

§63.1206(b)(7)(iii)

Comply with the following:Recordkeeping

[G]§63.1206(b)(7)(i)

NoComply with the following:

Monitoring/Testing[T]§63.1206(b)(7)(iii)

Does the sourcefeed hazardous waste at

a location in the combustion systemother than the normal

flame zone?

Comply with the following:Standard

§63.1206(b)(7)(ii)(A), (7)(ii)(B)(2)Yes

§63.1206(b)(7)(ii)

No

1312

1313

1313

Page 191: TCEQ - 40 CFR Part 63, Subpart EEE; Flowchart; July 9, 2016Below is a flowchart describing 40 CFR Part 63, Subpart EEE. It will likely not be accessible using a screen reader. For

06/09/2016 From 40 CFR Part 63, Subpart EEE, Amended 10/28/2008These flowcharts are for use by sources subject to the Federal Operating Permit Program and are subject to change. ***

Hazardous Waste Combustors40 CFR Part 63, Subpart EEE

(191 of 191)

Comply with the following:Standard

[G]§63.1206(b)(5), [G](c)(1)-(5), (c)(6)(i)-(ii)[G]§63.1206(c)(6)(v)-(vi), [G](c)(7)

§63.1207(g)(1)(iii)(A), [G](k), [G](l)(1)§63.1209(c)(1), [G](c)(2), [G](d), (i), (p), [G](q)

§63.1211(c)(1)-(2), (c)(4)Monitoring/Testing

[G]§63.1206(b)(5), [G](b)(12), [G](c)(3)[T]§63.1207(a), [T](b)(1), [T][G](d)-(e)

[T][G]§63.1207(f)(1)(i), [T](f)(1)(ii)[T]§63.1207(f)(1)(ii)(A)-(C), [T][G](f)(1)(iii)

[T]§63.1207(f)(1)(iv)-(ix), [T](f)(1)(xii)[T]§63.1207(f)(1)(xxvii), (g), (g)(1)(ii)

[T][G]§63.1207(h)-(i), [T][G](l)(1)§63.1208(b)(7)-(8)

§63.1209(b)(1), [G](b)(2), (b)(3)-(4), [G](b)(5)[G]§63.1209(c)(4), [G](d), [G](f), (g)(1)(i)-(ii)

§63.1209(i), (p), [G](q), (r)Recordkeeping

[G]§63.1206(b)(5), (b)(11), [G](b)(12)[G]§63.1206(c)(1)-(5), (c)(6)(vii), [G](c)(7)

§63.1207(f)(1)(xii), (g)(1)(iii)(A)§63.1209(b)(1), [G](c)(2), [G](c)(4), [G](q)

§63.1211(b), [G](c)(3), [G](d)Reporting

[G]§63.1206(b)(5), (b)(11), [G](c)(2)-(4)[G]§63.1207(e), [G](f)(1)(i), (f)(1)(ii)

§63.1207(f)(1)(ii)(A)-(C), [G](f)(1)(iii)§63.1207(f)(1)(iv)-(ix), (f)(1)(xii), (f)(1)(xviii)§63.1207(f)(1)(xxvii), (f)(2)(v)-(x), [G](h)-(i)

[G]§63.1207(j)(1), (j)(3)-(5), [G](k)[G]§63.1207(l)(1), (l)(3)

§63.1209(c)(3), (g)(1)(i)-(ii), [G](g)(1)(iii)[G]§63.1210(a), [G](b)(1), (b)(2), (c)(2)

[G]§63.1210(c)(3)-(4), [G](d)§63.1211(a), [G](c)(3), [G](d)

§63.1212(a)

1313