TBWG Toronto, Ontario November 18, 2008 GSA Project Update

TBWG Toronto, Ontario November 18, 2008 GSA Project Update

Embed Size (px)

Citation preview

Page 1: TBWG Toronto, Ontario November 18, 2008 GSA Project Update

TBWGToronto, Ontario

November 18, 2008

GSA Project Update

Page 2: TBWG Toronto, Ontario November 18, 2008 GSA Project Update

Projects in Construction

1. Calais, Maine

2. Jackman, Maine

3. Champlain, New York

4. Massena, New York

5. Warroad, Minnesota

6. Portal, North Dakota

7. Blaine (Peace Arch), Washington

Page 3: TBWG Toronto, Ontario November 18, 2008 GSA Project Update

Jackman, Maine

• Progress is at 53%• Project is ahead of the

scheduled July 2010 completion

• Close coordination with MTQ concerning highway alignment

• Close coordination with Hydro Quebec concerning three phase power

Page 4: TBWG Toronto, Ontario November 18, 2008 GSA Project Update

Calais, Maine

• Progress is at 60%• Estimated completion is

November 2009• Additional funding in 2009

required to maintain scheduled completion date

• Discovery of significant ledge at time of construction start

Page 5: TBWG Toronto, Ontario November 18, 2008 GSA Project Update

Champlain, New York

• Cargo Facility Completed in 2007

• Administration building completed in 2008

• Overall Project completion December 2008

• Project delivered on time and within budget

Page 6: TBWG Toronto, Ontario November 18, 2008 GSA Project Update

Massena, NY

• Progress is at 57%• Estimated completion is

October 2009• Project is within budget• Project included

reconstruction of a traffic circle

• Close coordination with NYSDOT

Page 7: TBWG Toronto, Ontario November 18, 2008 GSA Project Update

Warroad, Minnesota

• Progress is at 10%• Estimated completion is

January 2010• Significant wetlands in

the vicinity• Port facilities will be

located about a mile south of boundary

Page 8: TBWG Toronto, Ontario November 18, 2008 GSA Project Update

Portal, North Dakota

• Progress is at 19%• Estimated completion is

September 2011

• Remaining funding will be available in 2009

• Construction of ancillary facilities will occur in 2009

Page 9: TBWG Toronto, Ontario November 18, 2008 GSA Project Update

Peace Arch, WA

• Progress is at 10%• Estimated completion is

August 2010• Additional funding

required in 2009 to maintain schedule

• Crossing will be operational for 2010 Olympics

Page 10: TBWG Toronto, Ontario November 18, 2008 GSA Project Update

Out-Year Construction

1. Derby Line, Vermont (2009)

2. Alexandria Bay, New York (2010)

3 Madawaska, Maine (2011)

Page 11: TBWG Toronto, Ontario November 18, 2008 GSA Project Update

Derby Line, VT

• Design award is pending

• Site adaptation will be utilized to expedite project

• Construction start planned for 2009

• Completion 2011

Page 12: TBWG Toronto, Ontario November 18, 2008 GSA Project Update

Alexandria Bay, New York

• Design is underway• Conceptual stage is

complete• Significant site/civil work• Construction start is

planned for 2010• Completion 2012

Page 13: TBWG Toronto, Ontario November 18, 2008 GSA Project Update

Madawaska, Maine

• Design is underway• Concepts under

development• Inspection facilities will be

remote from the bridge landing

• Construction start is planned for 2011

• Completion 2013

Page 14: TBWG Toronto, Ontario November 18, 2008 GSA Project Update

Other LPOE Projects

1. Lewiston, NY (NFBC)

2. Peace Bridge – Buffalo, NY (PBA)

3. New International Crossing – Detroit (MDOT)

4. Blue Water Bridge – Port Huron, MI (MDOT)

Page 15: TBWG Toronto, Ontario November 18, 2008 GSA Project Update

Questions?

Thank You