  • TBM Drives at the Gotthard Base Tunnel

    29.8.2017

    AFER Certification – Meeting with Amberg Engineering AG

    TBM Drives at the Gotthard Base Tunnel Challenges in the Faido section

    Thomas Jesel, MSc, Amberg Engineering AG

  • TBM Drives at the Gotthard Base Tunnel

    29.8.2017

    AFER Certification – Meeting with Amberg Engineering AG

  • TBM Drives at the Gotthard Base Tunnel

    29.8.2017

    AFER Certification – Meeting with Amberg Engineering AG

    Project Main Information

    Client Alp Transit AG (ATG)

    Location Switzerland

    Design Level All design stages up to detailed design

    Design Joint Venture JV with Pöyry Infra AG and Lombardi SA under lead of Amberg Engineering AG

    Project Phases & Design Schedule Design 1990-2016 Construction 1993-2016 Commissioning 2017

    Design Costs 485 Mio. CHF (part of AE: 165 Mio. CHF)

    Total Project Costs 12.2 billion CHF

  • TBM Drives at the Gotthard Base Tunnel

    29.8.2017

    AFER Certification – Meeting with Amberg Engineering AG

    Design Responsibilities

    Preliminary Design Amberg within JV, responsible for the whole tunnel itself

    Basic Design Amberg within JV, responsible for the whole tunnel itself

    Detailed Design Amberg within JV, responsible for the Faido section

    Tender Design Amberg within JV, responsible for the Faido section

    Assistance on Site Amberg within JV, responsible for Bodio, Faido and partially Sedrun

    Site Supervision Amberg within JV, mainly Faido but also Bodio and Sedrun

  • TBM Drives at the Gotthard Base Tunnel

    29.8.2017

    AFER Certification – Meeting with Amberg Engineering AG

    Gotthard Base Tunnel, www.alptransit.ch

    http://www.alptransit.ch/

  • TBM Drives at the Gotthard Base Tunnel

    29.8.2017

    AFER Certification – Meeting with Amberg Engineering AG

    Excavation method

  • TBM Drives at the Gotthard Base Tunnel

    29.8.2017

    AFER Certification – Meeting with Amberg Engineering AG

    TBM

    4 Herrenknecht TBM

    Open gripper shield

    Length

    TBM: 26 m

    Back-up: 450 m

    Cutter head

    Diameter: 9.43 m

    Shifted, max: 9.53 m

    Weight: 240 t

    Discs:

    Number: 66

    Diameter: 17’’

  • TBM Drives at the Gotthard Base Tunnel

    29.8.2017

    AFER Certification – Meeting with Amberg Engineering AG

    Experience Faido

    Cutter head wear

    Water inflow

    Rock burst

    Squeezing rock

    Blocked TBM

    Excavation rates

  • TBM Drives at the Gotthard Base Tunnel

    29.8.2017

    AFER Certification – Meeting with Amberg Engineering AG

    Cutter head wear I

    Abrasivity with Cherchar index

    Tender design: CAI 2.8

    Medelser Granite CAI 4.4

    Lucomagno Gneiss CAI 3.4

    Medelser Granit

    Lucomagno Gneis

  • TBM Drives at the Gotthard Base Tunnel

    29.8.2017

    AFER Certification – Meeting with Amberg Engineering AG

    Cutter head wear II

    Instable face

    Not all discs at face

    Reduced face pressure

    Reduced cutting speed

    Blocks at the face

    Cutter head as crusher

    Rolling blocks hits the disks

  • TBM Drives at the Gotthard Base Tunnel

    29.8.2017

    AFER Certification – Meeting with Amberg Engineering AG

    Cutter head wear III

    CAI much higher than prognosis

    Damaged Disks due to blocks

    Often longer maintenance shifts

    Reduced pressure due to instable

    face

    Determinating for advance rate

  • TBM Drives at the Gotthard Base Tunnel

    29.8.2017

    AFER Certification – Meeting with Amberg Engineering AG

    Water inflow I

    Water pressure up to 200 bar

    Probe drillings require preventer

    (in sensitive areas)

    Needs specification in tender docs

    1:1 tests on site recommended

    before start

    Works well for both percussion

    and core drillings

  • TBM Drives at the Gotthard Base Tunnel

    29.8.2017

    AFER Certification – Meeting with Amberg Engineering AG

    Water inflow II

    Water inflow initial max 100 l/s

    Ascending tunnel

    600 mm drainage pipe

    No problem

    But 48°C!

    Cooling system limited

    Reduced working hours

    Frequent pauses required

    Reduced advance rate

  • TBM Drives at the Gotthard Base Tunnel

    29.8.2017

    AFER Certification – Meeting with Amberg Engineering AG

    Rock burst I

  • TBM Drives at the Gotthard Base Tunnel

    29.8.2017

    AFER Certification – Meeting with Amberg Engineering AG

    Rock burst II

    Difficult to predict

    Without warning – suddenly!

    Rock support cannot prevent

    rock burst

    But must protect staff

    TBM helps!

    Absorb kinetic energy

    Not easy to classify,

    subjective

    Code of classification

    Potential measures

  • TBM Drives at the Gotthard Base Tunnel

    29.8.2017

    AFER Certification – Meeting with Amberg Engineering AG

  • TBM Drives at the Gotthard Base Tunnel

    29.8.2017

    AFER Certification – Meeting with Amberg Engineering AG

    Squeezing rock I

    Started with Steel arches and

    rock bolts and shotcrete

    Soon deformations (30 cm)

    Shotcrete destroyed

    Steel arches plastified

  • TBM Drives at the Gotthard Base Tunnel

    29.8.2017

    AFER Certification – Meeting with Amberg Engineering AG

    Squeezing rock II

    Second TBM even worse

    Back up was squeezed in

    Heave in the invert

    Reconstruction of the invert

    still under the TBM

  • TBM Drives at the Gotthard Base Tunnel

    29.8.2017

    AFER Certification – Meeting with Amberg Engineering AG

    Squeezing rock III

    TBM got through – at the end

    Intensive back calculations

    New loads, new design

    Tunnel redone on 400 m

  • TBM Drives at the Gotthard Base Tunnel

    29.8.2017

    AFER Certification – Meeting with Amberg Engineering AG

    Squeezing rock IV

    D&B in this area had less problems

    Rock support can be installed direct

    at the front, with TBM not possible

    Distance between face and installed

    rock support is important

    Shield must be as short as possible

    Styrofoam elements worked well to

    protect young shotcrete

    Inclined cross passages allowed to

    redo the tunnels without interrupting

    the TBM

  • TBM Drives at the Gotthard Base Tunnel

    29.8.2017

    AFER Certification – Meeting with Amberg Engineering AG

    Blocked TBM I

    First machine passed

    Some over brake

    Second machine got stocked

    Several attempts with backing

    and restart were not successful

    1’100 m spiles installed

    Voids filled up with 48 m3

    concrete and 47 m3 grout

  • TBM Drives at the Gotthard Base Tunnel

    29.8.2017

    AFER Certification – Meeting with Amberg Engineering AG

    Blocked TBM II

    Still not successful

    A lot of material was taken

    out without any progress

    Massive cavern above tunnel

    Extensive probe drilling

  • TBM Drives at the Gotthard Base Tunnel

    29.8.2017

    AFER Certification – Meeting with Amberg Engineering AG

    Blocked TBM III

    Stabilize loos material

    Grouting campaign from a niche,

    east tunnel

    Counter heading to secure the time

    schedule

  • TBM Drives at the Gotthard Base Tunnel

    29.8.2017

    AFER Certification – Meeting with Amberg Engineering AG

    Blocked TBM IV

    Action plan was very helpful,

    reduced reaction time significantly

    Expert panel was important

    Close collaboration and clear

    communication was crucial

    Decision need to be taken fast,

    immediately at the face

    Willingness to solve the problem

    compulsory

  • TBM Drives at the Gotthard Base Tunnel

    29.8.2017

    AFER Certification – Meeting with Amberg Engineering AG

    Ost West

    Penetration mm/U 8.28 8.46

    Netto advance rate m/h 2.51 2.64Advance rates I

    Design: 2.33 m/h

  • TBM Drives at the Gotthard Base Tunnel

    29.8.2017

    AFER Certification – Meeting with Amberg Engineering AG

    Advance rates II

    Joint and foliation angle

    important influence

    Penetration around 10 mm

    while perpendicular

    Drops down to 70% while flat

  • TBM Drives at the Gotthard Base Tunnel

    29.8.2017

    AFER Certification – Meeting with Amberg Engineering AG

    Advance rates III

  • TBM Drives at the Gotthard Base Tunnel

    29.8.2017

    AFER Certification – Meeting with Amberg Engineering AG

    Lessons learned I

    Optimize TBM for most probable

    geology – set right focus

    Make sure, that TBM can handle

    worst case

    Open gripper TBM was right

    decision - flexibility was needed

    Shotcrete in L1 was necessary and

    feasible, main shotcrete in L2

    Rock bolts in L2 were not used.

    Bolts are needed as close to the

    face as possible

  • TBM Drives at the Gotthard Base Tunnel

    29.8.2017

    AFER Certification – Meeting with Amberg Engineering AG

    Lessons learned II

    A continuous probe drilling from the

    TBM was very useful (low cost, no

    time)

    In such difficult geology it is

    inevitable to have competent staff on

    site (contractor, designer bust also

    client)

    Decisions need to be taken fast, to

    keep TBM running

    Logistic is important. Keep other

    activities as low as possible

    TBM produces a lot of data. Data

    evaluation needs a clear concept to

    get significant results

  • TBM Drives at the Gotthard Base Tunnel

    29.8.2017

    AFER Certification – Meeting with Amberg Engineering AG

    Main challenge: Communication!

  • TBM Drives at the Gotthard Base Tunnel

    29.8.2017

    AFER Certification – Meeting with Amberg Engineering AG

    Thank you for your attention! [email protected]