TBM Drives at the Gotthard Base Tunnel
29.8.2017
AFER Certification – Meeting with Amberg Engineering AG
TBM Drives at the Gotthard Base Tunnel Challenges in the Faido section
Thomas Jesel, MSc, Amberg Engineering AG
TBM Drives at the Gotthard Base Tunnel
29.8.2017
AFER Certification – Meeting with Amberg Engineering AG
TBM Drives at the Gotthard Base Tunnel
29.8.2017
AFER Certification – Meeting with Amberg Engineering AG
Project Main Information
Client Alp Transit AG (ATG)
Location Switzerland
Design Level All design stages up to detailed design
Design Joint Venture JV with Pöyry Infra AG and Lombardi SA under lead of Amberg Engineering AG
Project Phases & Design Schedule Design 1990-2016 Construction 1993-2016 Commissioning 2017
Design Costs 485 Mio. CHF (part of AE: 165 Mio. CHF)
Total Project Costs 12.2 billion CHF
TBM Drives at the Gotthard Base Tunnel
29.8.2017
AFER Certification – Meeting with Amberg Engineering AG
Design Responsibilities
Preliminary Design Amberg within JV, responsible for the whole tunnel itself
Basic Design Amberg within JV, responsible for the whole tunnel itself
Detailed Design Amberg within JV, responsible for the Faido section
Tender Design Amberg within JV, responsible for the Faido section
Assistance on Site Amberg within JV, responsible for Bodio, Faido and partially Sedrun
Site Supervision Amberg within JV, mainly Faido but also Bodio and Sedrun
TBM Drives at the Gotthard Base Tunnel
29.8.2017
AFER Certification – Meeting with Amberg Engineering AG
Gotthard Base Tunnel, www.alptransit.ch
http://www.alptransit.ch/
TBM Drives at the Gotthard Base Tunnel
29.8.2017
AFER Certification – Meeting with Amberg Engineering AG
Excavation method
TBM Drives at the Gotthard Base Tunnel
29.8.2017
AFER Certification – Meeting with Amberg Engineering AG
TBM
4 Herrenknecht TBM
Open gripper shield
Length
TBM: 26 m
Back-up: 450 m
Cutter head
Diameter: 9.43 m
Shifted, max: 9.53 m
Weight: 240 t
Discs:
Number: 66
Diameter: 17’’
TBM Drives at the Gotthard Base Tunnel
29.8.2017
AFER Certification – Meeting with Amberg Engineering AG
Experience Faido
Cutter head wear
Water inflow
Rock burst
Squeezing rock
Blocked TBM
Excavation rates
TBM Drives at the Gotthard Base Tunnel
29.8.2017
AFER Certification – Meeting with Amberg Engineering AG
Cutter head wear I
Abrasivity with Cherchar index
Tender design: CAI 2.8
Medelser Granite CAI 4.4
Lucomagno Gneiss CAI 3.4
Medelser Granit
Lucomagno Gneis
TBM Drives at the Gotthard Base Tunnel
29.8.2017
AFER Certification – Meeting with Amberg Engineering AG
Cutter head wear II
Instable face
Not all discs at face
Reduced face pressure
Reduced cutting speed
Blocks at the face
Cutter head as crusher
Rolling blocks hits the disks
TBM Drives at the Gotthard Base Tunnel
29.8.2017
AFER Certification – Meeting with Amberg Engineering AG
Cutter head wear III
CAI much higher than prognosis
Damaged Disks due to blocks
Often longer maintenance shifts
Reduced pressure due to instable
face
Determinating for advance rate
TBM Drives at the Gotthard Base Tunnel
29.8.2017
AFER Certification – Meeting with Amberg Engineering AG
Water inflow I
Water pressure up to 200 bar
Probe drillings require preventer
(in sensitive areas)
Needs specification in tender docs
1:1 tests on site recommended
before start
Works well for both percussion
and core drillings
TBM Drives at the Gotthard Base Tunnel
29.8.2017
AFER Certification – Meeting with Amberg Engineering AG
Water inflow II
Water inflow initial max 100 l/s
Ascending tunnel
600 mm drainage pipe
No problem
But 48°C!
Cooling system limited
Reduced working hours
Frequent pauses required
Reduced advance rate
TBM Drives at the Gotthard Base Tunnel
29.8.2017
AFER Certification – Meeting with Amberg Engineering AG
Rock burst I
TBM Drives at the Gotthard Base Tunnel
29.8.2017
AFER Certification – Meeting with Amberg Engineering AG
Rock burst II
Difficult to predict
Without warning – suddenly!
Rock support cannot prevent
rock burst
But must protect staff
TBM helps!
Absorb kinetic energy
Not easy to classify,
subjective
Code of classification
Potential measures
TBM Drives at the Gotthard Base Tunnel
29.8.2017
AFER Certification – Meeting with Amberg Engineering AG
TBM Drives at the Gotthard Base Tunnel
29.8.2017
AFER Certification – Meeting with Amberg Engineering AG
Squeezing rock I
Started with Steel arches and
rock bolts and shotcrete
Soon deformations (30 cm)
Shotcrete destroyed
Steel arches plastified
TBM Drives at the Gotthard Base Tunnel
29.8.2017
AFER Certification – Meeting with Amberg Engineering AG
Squeezing rock II
Second TBM even worse
Back up was squeezed in
Heave in the invert
Reconstruction of the invert
still under the TBM
TBM Drives at the Gotthard Base Tunnel
29.8.2017
AFER Certification – Meeting with Amberg Engineering AG
Squeezing rock III
TBM got through – at the end
Intensive back calculations
New loads, new design
Tunnel redone on 400 m
TBM Drives at the Gotthard Base Tunnel
29.8.2017
AFER Certification – Meeting with Amberg Engineering AG
Squeezing rock IV
D&B in this area had less problems
Rock support can be installed direct
at the front, with TBM not possible
Distance between face and installed
rock support is important
Shield must be as short as possible
Styrofoam elements worked well to
protect young shotcrete
Inclined cross passages allowed to
redo the tunnels without interrupting
the TBM
TBM Drives at the Gotthard Base Tunnel
29.8.2017
AFER Certification – Meeting with Amberg Engineering AG
Blocked TBM I
First machine passed
Some over brake
Second machine got stocked
Several attempts with backing
and restart were not successful
1’100 m spiles installed
Voids filled up with 48 m3
concrete and 47 m3 grout
TBM Drives at the Gotthard Base Tunnel
29.8.2017
AFER Certification – Meeting with Amberg Engineering AG
Blocked TBM II
Still not successful
A lot of material was taken
out without any progress
Massive cavern above tunnel
Extensive probe drilling
TBM Drives at the Gotthard Base Tunnel
29.8.2017
AFER Certification – Meeting with Amberg Engineering AG
Blocked TBM III
Stabilize loos material
Grouting campaign from a niche,
east tunnel
Counter heading to secure the time
schedule
TBM Drives at the Gotthard Base Tunnel
29.8.2017
AFER Certification – Meeting with Amberg Engineering AG
Blocked TBM IV
Action plan was very helpful,
reduced reaction time significantly
Expert panel was important
Close collaboration and clear
communication was crucial
Decision need to be taken fast,
immediately at the face
Willingness to solve the problem
compulsory
TBM Drives at the Gotthard Base Tunnel
29.8.2017
AFER Certification – Meeting with Amberg Engineering AG
Ost West
Penetration mm/U 8.28 8.46
Netto advance rate m/h 2.51 2.64Advance rates I
Design: 2.33 m/h
TBM Drives at the Gotthard Base Tunnel
29.8.2017
AFER Certification – Meeting with Amberg Engineering AG
Advance rates II
Joint and foliation angle
important influence
Penetration around 10 mm
while perpendicular
Drops down to 70% while flat
TBM Drives at the Gotthard Base Tunnel
29.8.2017
AFER Certification – Meeting with Amberg Engineering AG
Advance rates III
TBM Drives at the Gotthard Base Tunnel
29.8.2017
AFER Certification – Meeting with Amberg Engineering AG
Lessons learned I
Optimize TBM for most probable
geology – set right focus
Make sure, that TBM can handle
worst case
Open gripper TBM was right
decision - flexibility was needed
Shotcrete in L1 was necessary and
feasible, main shotcrete in L2
Rock bolts in L2 were not used.
Bolts are needed as close to the
face as possible
TBM Drives at the Gotthard Base Tunnel
29.8.2017
AFER Certification – Meeting with Amberg Engineering AG
Lessons learned II
A continuous probe drilling from the
TBM was very useful (low cost, no
time)
In such difficult geology it is
inevitable to have competent staff on
site (contractor, designer bust also
client)
Decisions need to be taken fast, to
keep TBM running
Logistic is important. Keep other
activities as low as possible
TBM produces a lot of data. Data
evaluation needs a clear concept to
get significant results
TBM Drives at the Gotthard Base Tunnel
29.8.2017
AFER Certification – Meeting with Amberg Engineering AG
Main challenge: Communication!
TBM Drives at the Gotthard Base Tunnel
29.8.2017
AFER Certification – Meeting with Amberg Engineering AG
Thank you for your attention! [email protected]