Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Task Force Balancing
20/11/2014
Agenda
Task Force Balancing – 20/11/2014 2
Status Update Ancillary Services 2015
o Contracting
o STAR 2015
Qualitative common comparison study on the subject of a
BE-NL-DE Coordinated Balancing Area
Status update project R2- wind
Solar eclipse 20/3/2015
Planned Enhancements Balancing Publications 2015
Feedback Expert Working Group
Short Term Sourcing R3
STAR – 2015
Short Term Auction Reserves & new bidding instructions 2015
TF Balancing 20/11/2014
Short Term Auction R1 & R2 - Introduction
Changes resulit in new Bidding Instructions & auction rules which can be
found on the Elia website
http://www.elia.be/en/grid-data/extranet-for-customers/STAR
• Status presented last taskforce Balancing :
• Second consultation Elia: 100% short term tendering for all R1 and R2 products
• Evolutions since last taskforce Balancing:
• 100% of the volume will be proccured via Short term auction:
• 83MW Primary Control Power (R1) – entso-e defined (200mHz)
• 140MW Secondary Control Power (R2) – Up and Down
• Multiple R1 types
• Small updates in the process/timings
• Update publications results on Elia website
Task Force Balancing – 20/11/2014
• Primary Control Power (R1) – entso-e defined (200mHz)
• R1 100mHz from generators + R1 Load + R1 Down
• R1 200mHz R1 Down from Generators
• R1 200mHz from France (see next slide)
• 1MW R1 200mHz = 0,5MW R1 100mHz + 0,5MW R1 Load + 0,5 MW R1 Down
• R1 from Generators can be combined with Secondary Control Power (R2) – Up and
Down
Short Term Auction R1 & R2 – Multiple R1 types
5 Task Force Balancing – 20/11/2014
R1 France
• Same product as R1 200mHz in Belgium
• In order to make a fair trade-off between domestic and cross border offers, Elia must
currently pay reconstitution costs applied by & agreed contractually with RTE on the
FR-BE border, which equal 1,025€/MW/h and which are taken into account during the
optimization of the total reservation procurement costs.
• Capped op 70% R1 need and 70MW (58MW for 2015)
Short Term Auction R1 & R2 – R1 France
6 Task Force Balancing – 20/11/2014
Short Term Auction R1 & R2 – minor changes to
process
7
Gate 1 open: introduce
offers
Gate 1 closed: second gate
trigger
Gate 2 open: reply to Elia’s request for new offers
Gate 2 closed: Elia selects the offers
Auction is closed, results are published
Gate 1:
Tuesday of the week in
which the 15th takes
place in month M-1 at
14h00
Gate 2:
Wednesday of the week
in which the 15th takes
place in month M-1 at
14h00
24hours after final
gate closure time
Trigger Gate 2
Criteria 1: Offered volume satisfaction
Criteria 2: Selected volume satisfaction
Criteria 3: Selection Price satisfaction
Task Force Balancing – 20/11/2014
Short Term Auction R1 & R2 – Calendar 2015
8 Task Force Balancing – 20/11/2014
EU regulation on transparency requirements on submission and publication of data in
electricity markets, will become obligatory from January 2015 onwards and which was
published by the Commission Regulation (EU) No 543/2013 on the 14 th of June 2013.
• Elia will publish per product- type, the overall retained volume & average price of
each monthly selection.
• By aggregating results are anonymized & give sufficient transparency towards the
market parties for each product type
http://www.elia.be/en/suppliers/purchasing-categories/energy-purchases/Ancillary-Services-Volumes-Prices/
Short Term Auction R1 & R2 – Publications
9
Tendering &
Contracting Period Delivery Period Reserve Type
Reserve
Product
Total
Contracted
Volume [MW]
Average
Price
[€/MW/h]
Tariff Period
[PEAK/L-OFFPEAK/BASE] Symmetry Type
Generation
Load type
December 2014 Januari 2015
R1
R1-200mHz XX 1,11 BASE SYM Generation
December 2014 Januari 2015 R1-dow n XX 1,11 BASE ASYM-DOWN Generation
December 2014 Januari 2015 R1-load XX 1,11 BASE ASYM-UP Load
December 2014 Januari 2015 R2
R2-up XX 1,11 BASE ASYM-UP Generation
December 2014 Januari 2015 R2-dow n XX 1,11 BASE ASYM-DOWN Generation
Task Force Balancing – 20/11/2014
Minor Change:
• Granularity is set to 1MW
Bidding instructions – no change: Highlights of important principles in order to create a well
functioning market:
• Number of bids (minimum 25% - 50% - 75% - 100%, based on economical logic) –
details can be found in the bidding instructions
• Offer maximum technical capacity
• Not obligatory
Short Term Auction R1 & R2 –Bidding instruction
10 Task Force Balancing – 20/11/2014
1. Become a Qualified Supplier:
- Application forms to be requested at [email protected]
- The deadline for application is the 1st of month M-2 to participate in delivery of
month M
2. Sign the General Framework (the same for all suppliers)
- The deadline for application is the 1st of month M-1 to participate in delivery of
month M
Supplier can be reassessed at all times
Short Term Auction R1 & R2 – How to participate
11 Task Force Balancing – 20/11/2014
Status procurement R3 – R3DP – ICH
2015
TF Balancing 20/11/2014
Status procurement R3 – R3DP – ICH 2015
Task Force Balancing – 20/11/2014
Qualitative common comparison study on
the subject of a BE-NL-DE Coordinated Balancing Area
TF Balancing 20/11/2014
Content
• Context
• Feedback results XB Balancing comparison study between BE-
NL –DE
15 Task Force Balancing – 20/11/2014
Context: Objective of Network Code on Electricity Balancing
• The core goal of the Network Code on Balancing is to establish an European wide
integrated cross-border balancing market where TSOs balance the system in a
coordinated way in order to use the most efficient balancing resources taking into
account transmission capacities.
• Current way of balancing
R2 requested by RTE
R3 requested by RTE
• Future way of balancing
R2 requested by RTE
R3 requested by RTE
16 Task Force Balancing – 20/11/2014
A. Imbalance Netting (IN)
B. Replacement Reserve (RR)
C. Manual Frequency Restoration (mFRR/R3)
D. Automatic Frequency Restoration
(aFRR/R2)
E. Frequency Containment Reserve (FCR/R1)
A B C
D E
AESAG - 9 July 2014
Pilot iGCC
Pilot GCC
Pilot AUT-CH Pilot BENL
Pilot BENL
• Currently 8 different pilot projects investigate the implementation of the NC on EB
2
1 2
2 3
Pilot GCC
Pilot Nordic Pilot eGCC
Pilot UK-NL
Pilot Terre
Context: Pilot Projects on XB Balancing
Task Force Balancing – 20/11/2014
Potential cross-border balancing cooperation between
TenneT, Elia and German TSOs
Study between the members of pilot BE-NL and pilot GCC
Task Force Balancing – 20/11/2014
The study was conducted in two steps:
Detailed comparison of the existing balancing market design of all three countries
Detailed analysis to evaluate any potential cooperation model and their impact on the existing balancing market design.
Objectives of the study
The German, Belgian and Dutch TSOs have, together with E-Bridge and the Institute of
Power Systems and Power Economics (IAEW) of RWTH Aachen University, completed a qualitative common comparison study on the subject of a BE-NL-DE Coordinated Balancing Area (CoBA)
This study was published on the website of Elia on 17/10/2014
The goal of the study was to analyse the options for cross-border cooperation in
balancing between the Belgium, Dutch and German TSOs taking into account the requirements of the relevant draft European Network Codes and Framework Guidelines.
19
2
1
Task Force Balancing – 20/11/2014
Detailed comparison shows large differences
between countries
20
Product FCR Automatic FRR Manual FRR
Product definition
Procurement period
(capacity)
Bid selection
(capacity)
Remuneration
(capacity)
Product resolution
(activation energy)
Bid selection
(activation energy)
Bid activation
Settlement
(activation energy)
Detailed comparison
shows large differences
between countries
Detailed comparison
shows large differences
between countries
Detailed comparison
shows that DE and NL are
(almost) same, BE is
different
Task Force Balancing – 20/11/2014
Cooperation for FRR reserve capacity
There are multiple ways to achieve benefits in terms of reserve capacity procurement:
• All options require available cross zonal capacity: either reservation of capacity (proof of socio-economic welfare required) or application of a probabilistic approach as suggested in the Framework Guidelines on Electricity Balancing.
• Exchanging FRR reserve capacity (and taking additional bids into account) requires cross zonal cooperation for FRR energy.
• Exchanging reserve capacity will not be the first step for cooperation, but may make business case for implementing ‘cooperation on activation of FRR energy activation’ positive.
21
Reduce the reserve capacity volume in
the system
Reduce procured volumes:
Reserve capacity sharing
Reduce volume needs
Common dimensioning LFC&R Block subject to XZ capacity
Ensure efficient procurement to ensure
the availability of required reserve capacity
Exchange of reserve capacity
Procure less reserve capacity by taking
(local and cross border) additional bids into account (no total reserve capacity volume reduction).
Task Force Balancing – 20/11/2014
Conclusion: low hanging fruit for cooperation
has been picked… … but further potential benefits are still available
22 Task Force Balancing – 20/11/2014
Proposed next steps
1. Fully implement the “less complex” options for cooperation:
• Analyse the participation of Belgium into the existing common procurement for frequency containment reserves between Germany, the Netherlands and Switzerland
• Increase the amount of frequency containment reserve exchange for the Netherlands and Germany (within the security limits set by the draft Network Code Load Frequency Control & Reserves)
• Analyse further potential in sharing manually activated frequency restoration reserves (within the security limits set by the draft Network Code Load Frequency Control & Reserves)
2. Start the discussion on harmonisation of the “more complex” products for cooperation:
• Start the discussion on the harmonisation of the automatic and manual frequency restoration reserves products for cooperation with the aim of establishing a common merit order list
• Investigate the cooperation possibilities for frequency restoration reserves capacity by common dimensioning, the consideration of additional balancing energy bids and the exchange of reserves
23
Partially implemented implemented
Task Force Balancing – 20/11/2014
Downward R2 by windmills:
status update
•TF Balancing 20/11/2014
R2- Wind project: Purpose
25
Project
• Technical pilot project (no commercial product)
• Ancillary Services Research project
• R2 down only
Wind
farm
• Estinnes wind farm (2011) of Windvision
• 11 x E-126 Enercon turbines of 7,5 MW
Involved
parties
• WindVision: owner
• Enercon: manufacturer
• Eneco Energy Trade (NL): ARP / signs R2 contract
Main
challenge
• Loss of Green Certificates (for pilot only: compensated by Elia)
• How to determine production of windmill without curtailment
(determined by wind conditions)?
Task Force Balancing – 20/11/2014
R2 wind project: Available Active Power (AAP)
2 different ways to deliver secondary control on windmills:
• Continuous de-rating towards a guaranteed lower power level (left graph)
• Inefficient; opportunity loss
• Estimate in real-time the Available Active Power (right graph)
• No opportunity loss; however is AAP calculation accurate?
26 Task Force Balancing – 20/11/2014
Objectives (high level)
27
• Communication
• Wind farm response
Level 1 Technical
• AAP* accuracy
• Reliability of R2 nomination
• Accuracy & reliability of R2 delivery
Level 2 Performance
• Insights for sustainable integration of R2 on wind farms
(procurement timeframe, costs…)
• Insights into bidding behavior
(how, risk, penalties…)
Level 3 R2 framework simulations
*AAP = Available Active Power Task Force Balancing – 20/11/2014
Communication
Limited # tests on:
• Wind farm response
• AAP accuracy under
curtailment
Test duration
28
Phase 1: pre-
liminary tests
Phase 2: Participation to R2-
delivery
1 month (not fulltime) 2 months (fulltime)
2 months testing / parallel analysis
• Wind farm response
• AAP accuracy under curtailment
• Reliability of R2 nomination
• Accuracy & reliability of R2 delivery
Limit impact on market parties
• Only impact: NRV • No impact selected R2 volumes or
imbalance price
• First results satisfactory
• Decision to start phase 2
• Phase 2 started on 6/11
• Technical communication issue
Task Force Balancing – 20/11/2014
Goal of preliminary tests
Ability of windfarm to follow continuous setpoint: positive test results
AAP quality of the windfarm under curtailed and non-curtailed conditions
• Test show relative good quality of AAP of the windfarm
• Imperfections in AAP calculation and/or wind fluctuations,… result in more fluctuations
on the delivered R2-test signal than for conventional (CCGT) units
• At first sight not problematic; to be confirmed in phase 2
• General: AAP algorithms will further improve towards the future
Ramp sufficient to provide R2? What is minimum stable power?
• Tests showed high ramping capabilities and very low (~ 0 MW) minimum stable power
First results relatively positive for the AAP method to deliver R2
• No need for continuous de-rating method (less efficient)
However limited number of tests performed yet; need for longer test periods to
cover all conditions and to confirm the results of the preliminary tests
29 Task Force Balancing – 20/11/2014
Ability to follow setpoint: test 1
Windfarm able to follow a control signal in case of continuous de-rating?
30
Windfarm was asked to
perform continuous de-
rating to 14 MW
Red line shows potential
output of windfarm
without this curtailment
Elia sent out following
setpoint to be followed
by the windfarm
Windfarm produced the
blue output (compared to
black)
Good performance in following a setpoint from an ex-ante constant de-rated output
Task Force Balancing – 20/11/2014
AAP quality (2)
31
Windfarm able to follow a control signal compared to real-time calculated AAP?
• Good AAP quality throughout the test (3 hours); AAP close to measured output
• Relative good performance in delivering the setpoint sent out by Elia
• No evidence of structural bias of AAP during regulation
Task Force Balancing – 20/11/2014
Next steps
Phase 2: continuous testing
• Confirm results of preliminary tests
Start reflections on integration of windfarms in R2 market (changes needed)?
Publication of report on Elia website (~project planning)
32 Task Force Balancing – 20/11/2014
Solar Eclipse – March 20th 2015
TF Balancing 20/11/2014
The solar eclipse will pass through the European power system
• between 07:40 and 11:50 UCT (08:40-12:50 CET)
The reduction in solar radiation will directly affect the output of the photovoltaics
• Expected PV capacity in Continental Europe : 90 GW
• Eclipse may potentially cause a reduction of the PV infeed by more than 30 GW during clear sky
conditions
This is expected to have a serious impact on the secure operation
• The current primary reserves amounts to 3 GW.
Solar Eclipse – 20 March 2015
34
Serious challenges
• To BRPs in terms of forecasting and respect of balance obligations
• To TSOs in terms of secure operaton and imbalance management
But solar eclipse is perfectly predictable
Task Force Balancing – 20/11/2014
Report prepared by Subgroup System Protection and Dynamics (SG SPD) and Subgroup
Coordinated System Operation (SG CSO)
Assumptions
• Installed PV capacity : in Belgium, 3.245MW
• PV generation is concentrated in one spot per country : Brussels
• The duration of the eclipse is considered in each country from its beginning on the western border to its end on the
eastern border of the country : in Belgium, start 08:27 UCT (09:27 CET) – end 10:45 UCT (11:45 CET)
Results
Solar Eclipse – Study
elia presentation template / City, 19.11.2013 / Firstname Lastname 35
Expected power gradient in MW per minute from solar power
during clear sky conditions with and without solar eclipse
Comparison of expected infeed from solar power during clear sky
conditions with and without solar eclipse
34 GW @ 9:43 UTC (10:43 CET) [-400 MW/min ; +800 MW/min]
Belgium max reduction 1.383 MW (4%) Belgium gradient [-17MW/min ; 40MW/min]
Task Force Balancing – 20/11/2014
• The infeed from PV is highly depending on cloud coverage. The results presented
assume clear sky conditions which may not appear.
We would like to request BRPs to carefully and proactively analyse this special
event and take all necessary preventive measures (e.g. in relation with the behaviour of
their solar forecasting tools) to be able balance their portfolio during the eclipse.
• Elia and European TSOs within ENTSO-e are jointly analysing the consequences and
defining measure to be taken.
• We will keep you informed via TF Balancing and WG System Operations
Solar Eclipse - Next Steps
36 Task Force Balancing – 20/11/2014
Enhancements Balancing Publications
2015
TF Balancing 20/11/2014
Publication of minute values
Current publication
Current 2-minutes values of SI and NRV
Proposals
Separate NRV values: ‘Volume R2 + IGCC’ and ‘Volume R3’
Graph with 1-minute values of the last hour
Download of 1-minute data
Frequency data
Current publication
No publication of the frequency
Proposal
Download of data for each month
Enhancements Balancing Publications 2015
38 Task Force Balancing – 20/11/2014
System Warnings
Current publication
No system warnings (IT system failures, information unavailability, problems with ACE calculations, …)
Proposal
Messages published by the TSO to inform all involved parties
SMS services
Current publication
RSS Feed for balancing warnings (request for regulation capacity, inter-TSO activation) and strategic
reserves
Proposal
SMS service in addition to RSS Feed
Enhancements Balancing Publications 2015
39 Task Force Balancing – 20/11/2014
Forecasting tools
Current publication
Proposal
ID Wind forecasting
Enhancements Balancing Publications 2015
40 Task Force Balancing – 20/11/2014
Feedback Expert Working Group
Nov 14th
TF Balancing 20/11/2014
Agenda
• Product design principles SDR from DSO-grid
• Submetering
• Baselining
• Prequalification
• Contract DSO- SDR DSO provider
• R3DP 2016
• STS R3DP
Expert Working Group – 17/11/2014 42
Feedback @TF iSR
Feedback @TF iSR
Submetering
Important principles :
Ownership of meter (allow private meter)
Accuracy/precision of meter data (certification of meter)
Authenticity of transferred meter data
Liability in case of missing/erroneous/false data
Hierarchy: submetering results are not opposable to headmeter results
43
Improves accuracy of determination activated flexibility service/volume
Provides extra liquidity by allowing diversification in offered flexibility services at 1 customer site
Use: subject to product design, submeter is used for
- activation and availability control only or
- for correction of BRP-perimeter
If submeters @ELIA grid baseline is needed to perform activation control
ELIA is currently investigating submetering options @ELIA-grid
Rapport Forbeg dd. 3/2/2014 Expert WG 14/10/2014
Expert Working Group – 1711/2014
44
Sub-meter
EG ELIA 17/11/2014
DSO understands the potential need of sub-meter
When a sub-meter is needed for the market processes, the DSO (as neutral party) must
Place, collect and validate sub-metering data
Calculate flexibility data : cf. base-lining
Facilitate the Settlement: sum of flexibility data per EAN
Control of wipe out effect, correlation between head and sub-meter
Legal framework is missing
Submetering
45
CREG/Cwape:
o submetering, both @TSO-grid and @DSO-grid, must be facilitated in as
from Winter 2015-2016.
o DSOs do not play a role in installing meters, reading nor validating of meter
data as this is a purely commercial activity between 2 parties (ELIA and FSO
acting on behalf of DGU) under the assumption of no correction of BRP-
perimeter.
Febeg
o submetering = pure commercial activity without DSO-involvements
Aggregators
o advocate to at least use the installed private submeters for the purpose of
activation control, and not to impose an additional, equivalent submeter from
the DSO
ELIA and DSOs will continue to investigate how submetering can be facilitated
Task Force Balancing – 20/11/2014
46
Pre-qualification
EG ELIA 17/11/2014
Concerns SDR 2015/2016 & R3DP2016 ”together”
Clear distinction between the client installation and impact
of FSP flexibility on the network (NFS):
Content
Responsibilities
Timing
Process
47
Pre-qualification
EG ELIA 17/11/2014
Proposition of a DSO document (name to be found) describing client installation
Extract of the connection contract
Helps the client to understand the content of his connection contract
Informs the client on what he can offer to an FSP (and what not)
In the context of flexibility but independent from flexibility product
Reduces NFS duration
Provided by the DSO to the client, then by the client to the potential
FSP: pre-requisite for the client to be included in an FSP pool for NFS
Timing must be in line with tendering ELIA SDR 2015/2016
DSO will proactively deliver this document to clients proposed in
R3DP2014 & R3DP2015. Other clients can contact the DSO, directly
or via an FSP
48
Pre-qualification
EG ELIA 17/11/2014
Update of C8-01 :
Limitation to NFS process
Independent of the ELIA product (for instance R3DP & SDR)
Timing must be in line with tendering ELIA SDR 2015/2016
49
DSO/FSP contract
EG ELIA 17/11/2014
Update of DSO/FSP contract :
Unique contract for the ELIA products, for instance R3DP & SDR
Contracted EAN’s by an FSP for an ELIA contract: living annex
Replaces the existing contracts
Proposition (market consultation and approval by regulators) begin
2015, deadline signature (SDR 2015/16) 1/11/2015
More detailed proposition will follow
R3DP 2016
Expert WG 14/10: stakeholders call for stability, i.e. prolongation of existing R3DP 2015 product design while maintaining 100MW volume cap.
50 Task Force Balancing – 20/11/2014
Expert WG 17/11: ELIA proposes to continue with current product design.
However,
CREG requests ELIA to investigate increase of volume cap to 150MW
CREG requests FEBEG to provide technical motiovation in case this increase is not acceptable.
FEBEG calls for investigation of “equivalence” between one MW R3DP and one MW R3Prod
FEBEG requests transparent and non-discriminatory rules for “partial activation
Feedback @next TF Balancing
Short Term Sourcing R3 Prod & R3DP
TF Balancing 20/11/2014
STS R3DP & R3Prod
52
Link to SDR: transition to STS as from 1/1/2016 also favors load to participate to SDR tendering and monthly to R3DP for those months outside of SDR period (Apr – Oct)
Task Force Balancing – 20/11/2014
Expert WG 17/11: subject to CREG approval and related consultation , ELIA envisages to source R3 Prod and R3DP on a monthly basis as from 1/1/2016
However,
ELIA will align with stakeholders on how to modify product design accordingly (# activations/month)
Feedback @next TF Balancing
Thank you !
53 Task Force Balancing – 20/11/2014