Suo-Motu Determination of Tariff for Generation and Distribution – Order dated 11-12-2014 Tamil Nadu Electricity Regulatory Commission Page 246 December 2014 In this context, Commission directs TANGEDCO to provide the monthly energy demand and availability and its plan of scheduling power in accordance to MoD on quarterly basis. For power procurement from unapproved sources, TANGEDCO is directed to take prior approval of the Commission before purchasing energy. Summary of power purchase costs 4.141 The summary of power purchase costs approved by the Commission for FY 2014-15 from own generation and other sources after considering MoD is tabulated below: Table 185: Summary of power purchase cost approved by the Commission for FY 2014-15 Source Units (MU) Capacity Charges(Rs. Crore) Energy Charges (Rs. Crore) Energy Charges (Rs./ Unit ) Total Cost (Rs. Crore) Own Generation Stations Ennore TPS - 276 - 3.34 276 Tuticorin TPS 7,183 468 2,324 3.24 2,792 Mettur TPS 6,005 329 1,871 3.12 2,200 North Chennai TPS 4,502 376 1,204 2.67 1,580 NCTPS Stage-II** (Unit 1) 4,059 586 1,107 2.73 1,693 NCTPS Stage-II** (Unit 2) 3,725 379 1,016 2.73 1,395 MTPS Stage-III** - 671 - 3.37 671 Total Thermal 25,474 3,085 7,522 2.95 10,607 Tirumakottai GTPS 706 82 153 2.16 235 Kuttalam GTPS 651 91 146 2.25 237 Basin Bridge GTPS - 51 - 20.62 51 Valuthur GTPS 1,243 163 267 2.15 429 Total Gas 2,599 387 565 2.18 952 Erode HEP 1,365 332 0.0 0.00 332 Kadamparai HEP - 79 - - 79 Kundah HEP 2,257 206 0.2 0.00 206 Tirunelveli HEP 964 120 0.3 0.00 120 Total Hydro 4,586 736 0.53 0.00 736 Wind mills 12 3 - - 3 Total Own Generation 32,671 4,211 8,088 2.48 12,299 Central Generation Stations NTPC SR (I&II) 3,983 225 837 2.10 1,062 NTPC SR III 996 94 264 2.65 357 NLC TS - I 3,469 274 715 2.06 988 NLC TS - II 3,235 185 690 2.13 875 NLC TS Expansion I 1,469 194 445 3.03 639 NTPC Talcher 3,323 284 524 1.58 808 NTPC Simhadri 1,532 269 363 2.37 632

Tariff Order 9 of 2014-TANGEDCO(4).247-248

  • Upload
    ac

  • View
    224

  • Download
    1

Embed Size (px)

DESCRIPTION

TANGEDCO PP

Citation preview

  • Suo-Motu Determination of Tariff for Generation and Distribution Order dated 11-12-2014

    Tamil Nadu Electricity Regulatory Commission Page 246

    December 2014

    In this context, Commission directs TANGEDCO to provide the monthly energy

    demand and availability and its plan of scheduling power in accordance to MoD on

    quarterly basis. For power procurement from unapproved sources, TANGEDCO is directed

    to take prior approval of the Commission before purchasing energy.

    Summary of power purchase costs

    4.141 The summary of power purchase costs approved by the Commission for FY 2014-15

    from own generation and other sources after considering MoD is tabulated below:

    Table 185: Summary of power purchase cost approved by the Commission for FY 2014-15

    Source Units (MU)

    Capacity

    Charges(Rs.

    Crore)

    Energy

    Charges (Rs.

    Crore)

    Energy

    Charges

    (Rs./ Unit )

    Total Cost

    (Rs. Crore)

    Own Generation Stations

    Ennore TPS - 276 - 3.34 276

    Tuticorin TPS 7,183 468 2,324 3.24 2,792

    Mettur TPS 6,005 329 1,871 3.12 2,200

    North Chennai TPS 4,502 376 1,204 2.67 1,580

    NCTPS Stage-II** (Unit

    1) 4,059 586 1,107 2.73 1,693

    NCTPS Stage-II** (Unit

    2) 3,725 379 1,016 2.73 1,395

    MTPS Stage-III** - 671 - 3.37 671

    Total Thermal 25,474 3,085 7,522 2.95 10,607

    Tirumakottai GTPS 706 82 153 2.16 235

    Kuttalam GTPS 651 91 146 2.25 237

    Basin Bridge GTPS - 51 - 20.62 51

    Valuthur GTPS 1,243 163 267 2.15 429

    Total Gas 2,599 387 565 2.18 952

    Erode HEP 1,365 332 0.0 0.00 332

    Kadamparai HEP - 79 - - 79

    Kundah HEP 2,257 206 0.2 0.00 206

    Tirunelveli HEP 964 120 0.3 0.00 120

    Total Hydro 4,586 736 0.53 0.00 736

    Wind mills 12 3 - - 3

    Total Own Generation 32,671 4,211 8,088 2.48 12,299

    Central Generation Stations

    NTPC SR (I&II) 3,983 225 837 2.10 1,062

    NTPC SR III 996 94 264 2.65 357

    NLC TS - I 3,469 274 715 2.06 988

    NLC TS - II 3,235 185 690 2.13 875

    NLC TS Expansion I 1,469 194 445 3.03 639

    NTPC Talcher 3,323 284 524 1.58 808

    NTPC Simhadri 1,532 269 363 2.37 632

  • Suo-Motu Determination of Tariff for Generation and Distribution Order dated 11-12-2014

    Tamil Nadu Electricity Regulatory Commission Page 247

    December 2014

    Source Units (MU)

    Capacity

    Charges(Rs.

    Crore)

    Energy

    Charges (Rs.

    Crore)

    Energy

    Charges

    (Rs./ Unit )

    Total Cost

    (Rs. Crore)

    MAPS 1,573 - 332 2.11 332

    KAIGA 1,211 - 375 3.10 375

    NTPC Vallur - Unit 1 &

    Unit 2 4,882 745 1,257 2.57 2,002

    Kudankulum - Unit 1` 2,188 - 777 3.55 777

    New Plants 4,988 873 1,247 2.50 2,120

    NTPC ER 363 34 95 2.61 129

    Total CGS 33,212 3,176 7,920 2.38 11,097

    Renewables

    Wind 5,228 - 1,783 3.41 1,783

    Biomass 6 - 3 4.25 3

    Cogeneration 817 - 293 3.59 293

    Captive - - - 3.75 -

    Solar 97 - 52 5.37 52

    Total Renewable 6,148 - 2,131 3.47 2,131

    IPPs

    Samalpatti - 135 - - 135

    Madurai Power Corpn - 136 - - 136

    Pillaiperumalnallur - 122 - - 122

    STCMS - Neyveli 1,660 347 384 2.32 731

    LANCO Power (Aban co) 783 120 156 2.00 277

    PIONEER Power co.

    (Penna) 356 55 73 2.04 128

    Total IPPs 2,799 915 614 2.19 1,528

    Case 1 - Bidding (MTOA)

    Jindal Power 1,752 385 476 2.72 861

    Adani Power 1,182 296 390 3.30 686

    Lanco Power (NETS) 876 215 213 2.43 428

    NTPC NVVN 35 - 16 4.43 16

    Total Other sources 3,845 896 1,095 2.85 1,991

    PGCIL charges

    PGCIL - ER & SR 855

    PGCIL - Reactive Energy

    Charges 25

    Total transmission

    charges 880

    Total Power Purchases 46,004 4,987 11,760 2.56 17,627

    Total Own generation &

    Power Purchase 78,675 9,198 19,848 2.52 29,926