Upload
glenn-tarbox
View
222
Download
5
Embed Size (px)
Citation preview
Page 1
GLENN S. TARBOX, P.E., F. ASCE, S.E.C.B., P. Eng.
POSITION IN FIRM: SENIOR TECHNICAL ADVISOR, DAMS & HYDRO, MWH now Part of
STANTEC
YEARS WITH FIRM: 2 1
TOTAL YEARS OF EXPERIENCE: OVER 45
KEY QUALIFICATIONS:
Mr. Tarbox has over 45 years of experience as a civil/structural engineer in all facets of water resource
project development and management. He offers expertise in planning, design, management and
construction of dams, hydroelectric plants, transmission lines, tunnels and other major civil works projects.
His early career developed as a dam design and construction engineer and Assistant Chief, Dams Branch
with the U.S. Bureau of Reclamation; the past 33 years have been spent with the private sector. Glenn has
served as Design Engineer, Project Manager or Principal-In-Charge on more than 26 major domestic and
international dams and is often called upon to serve as a dam expert on consulting boards for new or
upgraded projects, a FERC certified Part 12 Independent Safety Consultant and Failure Mode Analysis
Facilitator and as an expert forensics witness related to dams.
Glenn has written computer programs for analyzing concrete gravity, arch and buttress dams. He was part of
the team of engineers that computerized the Trial Load Method of Analysis into the program known as
“ADSAS.” He was the first engineer to introduce the Finite Element Method of analysis for concrete dams
into the Bureau of Reclamation on Nambe Falls Dam, supervised the addition of dynamic analysis into
ADSAS and he introduced the use of RCC into the Bureau for Upper Stillwater Dam. He was one of the key
authors of the Bureau of Reclamation’s, “Design of Gravity Dams” and Design of Arch Dams.” He has been
the design manager of several major arch and gravity dam designs including Auburn, Nambe Falls, Crystal,
Mountain Park, Swift, Swan Lake, Coulee Third, Pejengkolan, Upper Stillwater, and Olivenhain (see
details in the paragraphs that follow). He is experienced in the application of the Finite Element Method of
analysis for static and dynamic loading on arch, gravity and buttress dams. Glenn is also an authority on the
subject of uplift and the stability of concrete dams and their foundations. He is experienced in the design of
contraction joints, concrete cooling systems, contraction joint grouting systems, foundation treatments such
as consolidation and deep curtain grouting, foundation drainage curtains and dental concrete. Glenn has
worked on the safety of existing dams of all types dealing with matters related to concrete deterioration
(ASR), cracking, leakage, and repairs to improve stability, reduce uplift pressure, reduce leakage and
rehabilitate aging concrete structures. As the Assistant Chief, Dams Branch, Glenn was responsible for
administering the Bureau of Reclamation’s inaugural SEED (Safety Evaluation of Existing Dams) Program.
EDUCATION:
Bachelor of Science, Civil Engineering, University of Maryland, 1961
Graduate Studies
University of Colorado, 1966-1970 Master of Science Academic Requirements
Colorado School of Mines, 1970/71 (Mathematics and Operations Research)
University of California, Berkeley, 1969 (Finite Element Analysis)
Cornell University, 1975 (Earthquake Engineering)
Page 1
Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.
Senior Technical Advisor, Dams & Hydro
Continuing Education: Supervision/Management Courses: Supervision & Group Performance; An
Introduction to Basic Supervision of People; Effective Executive Practices; Counseling Troubled
Employees; Middle Management Institute; Management Institute for Scientists, Eng. & Profs.; PERT/CPM;
Effective Time Management; Finite Element Method of Analysis; Control of Cracking in Mass Concrete
Structures; Earthquake Engineering; Structural Design for Earthquakes; Concrete Control Course USBR;
Concrete Polymer Materials Course; Cold Regions Engineering; New Perspectives on the Safety of Dams;
Construction/Contract Administration: Construction Law/Contract Negotiations; Construction Claims:
Analysis, Presentation/Defense; Practical Construction Law. MWH University courses include Pricing and
Negotiations and Business Unit Management. Bechtel Training Center courses include Bechtel Executive
Plan XVI and Bechtel Marketing Plan IV. FERC PFMA Facilitator Training Course.
Professional Organizations: United States Society on Dams (USSD); Formerly member of Committee on
Numerical Analysis; Currently member of Committee on Concrete; Formerly Chairman of Committee on
Financing of Dams; Formerly member of the Board of Directors (Treasurer '93, Vice President, '94,
President '95-'97); United States Committee on Irrigation and Drainage (USCID); The Society of American
Military Engineers; American Society of Civil Engineers (ASCE); Fellow; Formerly member of Seismic
Effects Committee/Structures Division; Formerly member of Publications Committee/Geotechnical
Engineering Division; American Concrete Institute (ACI); Currently member of Committee 207 on Mass
Concrete; Earthquake Engineering Research Institute (EERI); Construction Industry Institute; Formerly
alternate-member - Board of Advisors; Former member - Research Committee; Civil Engineering Research
Foundation; Formerly member - Corporate Advisory Board; Formerly member - Executive Committee;
National Institute of Standards and Technology; Panel Member - Building and Fire Research Laboratory
(1992 - 1995)
Professional Registrations: Civil Engineer / Alaska / 1980 / #4871; Civil Engineer / Arizona / 1984 /
#16736; Professional Engineer / Colorado / 2000 / #9311; Professional Engineer / Georgia / 1989 / #18035;
Professional Engineer / Illinois / 1989 / #062-044980; Professional Engineer / Montana / 1998 / #8292PE;
Professional Engineer / Texas / 1986 / #59105; Professional Engineer / Utah / 1998 / #167339-2202;
Professional Engineer / Wyoming / 1987 / #4759; Professional Engineer/Civil / Washington / 1984 /
#22012; Professional Engineer / Idaho / 2003 / #11113; Professional Engineer/Civil / New Brunswick /
2000 / L3458; Professional Engineer Civil / Saskatchewan / 34850 / Certified Structural Engineer/ S.E.C.B/1589-
1105
EXPERIENCE RECORD:
Wanapum Dam Mitigation Studies and Repairs of Cracked Spillway
Client: Grant County PUD
Senior Technical Advisor and Quality Manager for this project, which involved conducting forensic
investigations to determine the extent of cracking in one of the spillway bays, establishing the field and
laboratory investigation and testing program to test the material and strength properties of the existing
foundation and spillway monolith concrete conditions, conduct of 2 and 3-dimentional structural and thermal
analytical studies to assess the conditions of the cracked dam, preparation of mitigation designs to restore the
stability and integrity of the structure and to determine the effectiveness of those designs under static and
dynamic loading conditions. The design measures included grouting, drainage, prestressed anchors and
upgrades to the instrumentation and monitoring systems. Final solution included the installation of 61 strand
tendon post-tensioned anchors (2145 kips each) and 3-inch bar post-tensioned anchors (580 kips each) in each
monolith with a maximum added design stability force of up to 11,000,000 pounds per 65-foot wide monolith.
(2014-2015)
Page 1
Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.
Senior Technical Advisor, Dams & Hydro
Neelum Jhelum Project, Pakistan Client: WAPDA
Senior Advisor and Principal Structural Engineering reviewer of the design and analysis of the 969 MW
Neelum Jhelum Hydroelectric Project. The 45 m high diversion dam on the Neelum River will divert water
via a headrace tunnel (7.5 to 10 m diameter) into an underground powerhouse and the 3.63 km tailrace
tunnels will discharge into the Jhelum River. The total length of the headrace tunnel is 28.6 km developing a
420 m gross head. (2012-Present)
Susitna Project Watana Dam, Alaska Client: Alaska Energy Authority
Senior Advisor and Principal Structural Engineering reviewer of the design and analysis of the 715-ft high
Watana RCC Dam and 850MW surface powerhouse. (2011-Present)
Caroni Hydroelectric Projects Client: EDELCA, PortoOrdas/Caracus, Venezuela
Member Board of Review to review designs, construction management and O&M of the four projects’
(Guri, Tacoma, Caruachi, and Macagua) 17,472 MW of installed capacity of the Lower Caroni River
Project. (2009-Present)
Romaine 1, 2, 3, and 4 Hydroelectric Projects Client: Hydro Quebec, Montreal, Canada
Member Board of Review to review designs and construction management of the 640MW Romaine 2
Hydroelectric Project as part of the 4 Power Plant Romaine River Developments (1,550MW total installed
capacity). (2008-Present)
Eastmain 1A & La Sarcelle Hydroelectric Projects Client: SEBJ/Hydro Quebec, Montreal, Canada
Member Board of Review to review designs and construction management of the 768MW Eastmain 1A and
150MW La Sarcelle Hydroelectric Projects as part of the Rupert Diversion. (2007-Present)
San Vicente Dam Raise Project, U.S.A. Client: San Diego County Water Authority (SDCWA) and City of San Diego (City)
Task Leader, Principal Structural Engineer for design of 337-ft-high San Vicente RCC Dam (117-ft raise
from height of 220-ft to 318-ft) including RCC mix designs, optimization of raised design cross-section,
FEM static and dynamic stress analyses, thermal studies, instrumentation design, facing systems, galleries
and saddle dam. The project also featured two tunnels, a 9-foot diameter penetration through the existing
dam into a submerged cofferdam at the upstream face and a 17-foot tunnel and shaft beneath the raised dam
while maintaining the reservoir. (2006-Present)
Mosul Dam, Iraq Client: Ministry of Water and Energy Resources
Expert in structural engineering and earthquake analysis serving on International Panel of Experts (POE)
for Minister of Water, to provide technical review, advice, and oversight of all dam projects in operation,
under design, or investigation for planning and future development. Recommended remediation of
dam/foundation by construction of cut-off wall installed from crest of dam though the karstic foundation.
Award of contract to Bauer Construction for design and construction of world record 625 foot deep positive
cut-off wall pending final approval of Iraq Ministry of Water Resources. (2006 – Present)
Upper San Joaquin River Basin Storage Project, California, U.S.A. Client: U.S. Bureau of Reclamation
Member of Reclamation’s ten-person Value Planning Study Team of the Upper San Joaquin River Basin
Storage Investigation (USJRBSI). The estimated cost of the baseline concept was approximately
Page 1
Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.
Senior Technical Advisor, Dams & Hydro
$2,072,490.00. The maximum savings potential if the estimated savings of all the alternative design
concepts were to be accepted was $640,190,000. The cost of the study was approximately $200,000. The
main project features were proposed to be constructed at Temperance Flat and included: a main dam with an
uncontrolled spillway to pass flood flows, a powerhouse to generate electricity, and outlet works for other
controlled releases. The Temperance Flat Dam would be constructed of RCC about 640 feet high.
Upstream and downstream cofferdams would be required for river diversion. Diversion tunnels to route
river flows around the construction zone would be required during construction. A multiple-port selective
level intake structure (SLIS) would be constructed to improve management of the cold water pool in the
reservoir for releases to Millerton Lake upstream of Friant Dam. The powerhouse would have a capacity of
135 MW.
Tekeze Arch Dam and Hydroelectric Project, Ethiopia Client: Ethiopian Electric Power Corporation
Senior Advisor and Principal Structural Engineer responsible for technical review and field inspection of
project works, quarry development, aggregate processing, concrete mix designs, consolidation grouting of
foundation and finite element seismic stress analyses of a 190-m high thin-arch concrete dam. Special
studies of foundation shaping necessary to accommodate insufficient ground topography in the upper left
abutment region including rock slope stability assessment, rock reinforcement and anchor design, and
design and analysis of a combination shaping and thrust block structure to reconstitute the upper left
abutment ground contours were recommended and reviewed. Tekeze is highest arch dam on the continent of
Africa and the 300MW underground powerhouse generation output added 40% more energy to electrical
grid in Ethiopia. (2005 – 2009)
Karahjnukar Dam and Hydroelectric Project, Iceland Client: Landsvjirkjun Public Utility Corporation
Senior Advisor and Principal Structural Engineer reviewer for 200-m high CFRD (concrete-faced-rockfill
dam) in Iceland; QA review of foundations, instrumentation, design and analysis of special 40-m high
concrete gravity toe wall to resist tectonic displacements of faults existing in the foundation, RCC mix
design, and PVC water-proofing membrane. The 690MW underground power plant generates 4600GWh of
electrical energy to a nearby aluminum smelting plant. (2005 – 2008)
San Clemente Dam Remediation Project, California, U.S.A. Client: California-American Water Company
Principal-in-Charge for the feasibility engineering studies for the seismic retrofit of or removal of the San
Clemente Dam. The dam is a concrete arch constructed in 1920-1921 with a maximum structural height of
106 feet and a crest length of 300 feet. The California DSOD required that the dam owners meet dam safety
criteria to withstand the MCE and safely pass the PMF. This could be met by strengthening the dam, by
notching the dam to a level where DSOD requirements would be met, or by removing the dam. General
rehabilitation concepts, rerouting of the Carmel River into San Clemente Creek, sediment stabilization
schemes and notching or removal of the dam were developed and preliminary construction cost estimates
were prepared for each concept. (2004 – 2005)
Columbia River Off-Stream Storage Study, U.S.A. Client: USBR
Project Manager for the Columbia River Off-Stream Storage Study to identify off-stream versus on-stream
reservoir sites of 300,000 are-feet or larger for pumped storage and/or modification of existing facilities to
allow for additional storage. (2004-2005)
Page 1
Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.
Senior Technical Advisor, Dams & Hydro
Al Wehdah Dam, Jordan Client: Jordan Valley Authority
Senior Advisor and Principal Structural Engineering reviewer of the design and analysis of the 140-m high
Al Wehdah RCC Dam. (2001-2002)
Olivenhain RCC Dam, California, U.S.A. Client: San Diego Water Authority
Mr. Tarbox was Montgomery Watson Harza’s (MWH) Project Manager for the detailed design of this 318
foot high, 1.4 million cubic yard RCC gravity dam with a six level selective withdrawal I/O tower and a
stair stepped cascade spillway on the downstream face of the dam. The dam created an off stream reservoir
to provide emergency water supply to the more than 3.5 million residents of San Diego County in the event
an earthquake severs the aqueducts and pipelines that deliver water to the region. The $140 million dam is
part of the $950 million Emergency Storage Project and will be the highest RCC dam in North America
when completed and the first new RCC dam constructed in California. Included in the design were the 10-
foot diameter Lake Hodges Tunnel portal, tunnel stub and shaft for the future Lake Hodges Pumped Storage
Project. The Team was also responsible for the preparation of specifications, drawings and contract
documents for four separate construction contracts and is providing engineering services to the Authority
during construction. (1998-2003)
Big Tujunga Dam Stability Evaluation, California, U.S.A. Client: Los Angeles County Department of Public Works
Principal-in-Charge for the final design and stability evaluation of the Big Tujunga Dam, a 251-foot high
concrete arch dam. Performed seismic dynamic finite element analyses of the dam using ground motion
records modified to spectrally match a target spectrum. Developed six general rehabilitation concepts and
analyzed each concept using the finite element method. The selected concept consisted of placing RCC on
the downstream side of the existing dam that transformed the dam from a thin to a thick arch dam for
seismic strengthening and spillway modifications for hydraulic rehabilitation. (1999 – 2011)
Santa Anita Dam Re-Analysis, California, U.S.A. Client: Los Angeles County Department of Public Works
Principal-in-Charge for re-analysis of Santa Anita Dam, a 225-foot high concrete arch dam built in 1924-27.
The primary issues of concern include Alkali-Aggregate Reaction (AAR) within the dam concrete, seismic
stability to withstand the current Maximum Credible Earthquake (MCE), and hydraulic adequacy of the
existing spillway to handle updated Probable Maximum Flood (PMF). Performed an engineering/safety
inspection and investigation of the dam. Cores were obtained to assess the existing condition of the concrete
(including petrographic analysis). Design earthquakes were developed using actual ground motion records
scaled to spectrally match a target spectrum. Linear-elastic and non-linear finite element analyses were
performed to assess the seismic stability of the dam. Updated hydrologic analyses were performed to
develop inflow hydrology for evaluation of the existing spillway. (1999 – Present)
Mactaquac Dam & Generating Station, Fredericton, New Brunswick Client: New Brunswick Power Corporation,
Member Board of Review for annual review and evaluation of monitoring and mitigation programs
conducted by NB Power dealing with severe autogenous growth problems in the concrete of the head works
dam, spillways and powerhouse structures due to AAR (Alkali Aggregate Reactivity). Unprecedented
expansion due to AAR has resulted in NB Power adopting a range of measures to combat the ongoing
expansion including a regular program of saw-cutting monolith blocks in the head works adjacent to the
spillway, between generation bays in the powerhouse, and in spillway access bridge slabs, excising portions
of six penstock encasements and replacement with expansion couplings and a program of continuous
realignment of the turbine and generator shafts to accommodate out-of-round and out-of-plumb ness of the
units due to the AAR expansion. (1998-present)
Page 1
Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.
Senior Technical Advisor, Dams & Hydro
Gillespie Dam, Phoenix, AZ, U.S.A. Client: Mesch, Clark & Rothschild, P.C.
Engineering Team Leader of support services for the defense attorneys who conducted the litigation
proceedings related to the failure of Gillespie Dam. The dam is a multiple arch buttress diversion dam, 1800
feet long, rising 20 feet above a concrete apron and spanning the Gila River near Gila Bend, AZ. Services
provided included the conduct of field and laboratory testing of concrete materials, 2-D hydraulic
mathematical modeling of flood flows over the dam, 3-D finite element structural analyses of the dam and
foundation, scour studies, preparation of reports and affidavits, expert testimony and technical support
during the discovery and deposition process. (1996 to 2005)
Falcon Dam, Risk Assessment of Gas Well Drilling in Restricted Zone under Reservoir, TX, U.S.A. Client: International Boundary and Water Commission
Senior Advisor and Principal Reviewer of the risk analysis of drilling and producing natural gas from 34
wells beneath reservoir. The wells would be drilled from two pads located outside the Restricted Zone, but
would extend beneath the Restricted Zone using directional drilling. The median of the total expected value
of risk was about $1.7 million and was primarily due to surface settlement risks. The potential loss of life
from dam failure due to the proposed natural gas drilling and production was approximated and compared
with USBR guidelines for loss of life from dam failure. (2004)
Baise Multipurpose Dam Project, Guangxi, China Client: Guangxi Youjiang Water & Power Corporation (YWP)
Mr. Tarbox was MWH's Project Manager for the review of designs, operating policy, environmental impact
assessment, economic and financial analysis and alternative flood protection possibilities for the $500
million Baise multipurpose Project that includes a 130-m-high (430 ft), 2 million cubic meter, RCC dam,
two rockfill dams and a 540-MW underground powerplant. (1999-2000)
Portugues Dam, Ponce, Puerto Rico Client: Jacksonville District Corps of Engineers
Mr. Tarbox is currently providing technical review of design, constructability and construction management
for this 1,600-foot-long, 280-foot-high, concrete arch dam. Portugues Dam is the first RCC arch dam to be
designed and constructed in the U.S. or its territories. (1995-2006)
Pardee Dam and Reservoir Enlargement Project, Mokelumne Watershed, California, U.S.A. Client: East Bay Municipal Utility District
Chairman Independent Review Board charged with reviewing the District’s plans for either raising the
existing Pardee Dam or siting and constructing an entirely new dam downstream. A raised or new Pardee
dam would provide for 150,000 acre feet or more of additional storage of domestic water supply for Contra
Costa and Alameda Counties. (1996-1997)
Swan Lake Dam & Hydroelectric Project, Alaska, U.S.A. Client: Ketchikan Public Utilities
As Project Manager, Mr. Tarbox oversaw engineering and economic feasibility studies for the $120 million,
22.5-MW Swan Lake Hydroelectric Project in Ketchikan, Alaska. He also managed the FERC license
processing, final designs, preparation of contract documents and construction supervision for all features on
the project, including a 175-foot-high double-curvature, elliptical concrete arch dam, a 2,300-foot power
tunnel and a 30-mile, 115-kV transmission line. It has a free overflow spillway at the crest of the dam with a
capacity of 37,150 cfs. Swan Lake Dam was the first elliptical arch dam constructed in North America. In
addition, he managed the construction of a two-story work crew dormitory building, a vehicle shop and
maintenance building, a waste incinerator facility, a barge handling facility and dock, three year-round
Page 1
Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.
Senior Technical Advisor, Dams & Hydro
operators’ houses, a microwave telecommunications link, recreational/picnic facilities at the powerhouse, a
boat ramp and trails at the reservoir. (1979-1983)
Ertan Dam & Hydroelectric Project, China (PRC) Client: ERTAN Hydroelectric Development Corporation
As Vice President, Chief Engineer served as a senior design reviewer of the final dam design and Contract
Documents for the 3300 MW hydropower project featuring an underground powerhouse with 6
turbine/generators, a 220-meter high, double-curvature arch dam and ancillary hydraulic structures (1988-
1990).
Rocky Mountain Hydroelectric Project, Georgia, U.S.A. Client: Oglethorpe Power Corporation
Responsibilities as Chief Engineer included overall QA/QC program for the Rocky Mountain Hydroelectric
Project. He was Vice President of Engineering during the design of the project, which included an upper
reservoir ring embankment dam, eight lower reservoir dams and a 750-MW pumped storage power station.
(1988-1990)
Cowlitz Falls Dam and Hydroelectric Project, Washington, U.S.A. Client: Lewis County Public Utility District
As Principal-in-Charge, Mr. Tarbox was Vice President responsible for the overall direction of the project
during design and construction of the 145-foot-high gravity dam with four gated and one un-gated spillway
bays and 70-MW power station containing two 35 MW Kaplan turbine units. (1990-1994)
Bradley Lake Dam & Hydroelectric Project, Alaska, U.S.A. Client: Alaska Power Authority
As Principal-in-Charge, Mr. Tarbox was Vice President responsible for overall management of water
resource projects during the construction of the 125-foot high concrete-decked, rock-fill dam, 120-MW
power station, 18-mile 115 kV transmission line and a 3.4-mile, 10.8-foot diameter concrete/steel-lined
tunnel. The $355 million Bradley Lake Project was constructed in environmentally sensitive wetlands and
wildlife habitat, which required the enforcement of stringent mitigation measures in order to protect the
existing habitat. Complete living accommodations, vehicle storage and maintenance facilities, warehouses,
an airstrip and port facilities were also constructed because of the remote location of the project. (1990-
1994)
Boundary Dam, Spillway and Outlet Works Plunge Pool TDG, Washington, U.S.A. Client: Seattle City Light
Mr. Tarbox was a member of a three person Panel of Experts that provided oversight and technical reviews
of a program to study alternative project modifications to reduce the level of total dissolved gases in the
plunge pool and tailrace area of the project. The overall long-term objectives of the field, laboratory and
CFD studies were to identify operational measures and to support low level spillway sluices and upper level
radial gated spillway modifications that could be implemented to improve TDG performance of the energy
dissipating plunge pool. A 1:25 scale physical hydraulic model was constructed and a test program
conceived to develop rating curves for all flow outlets, making velocity measurements in the project tailrace
(for use in CFD model calibration), and characterizing the performance of the existing dam. The physical
model was used to examine; rating curves, trajectory, and throttled flow behavior. Computational fluid
dynamics was applied to develop a detailed examination of the expansion of flow as water exits the sluice
gates as well as examination of the jet as it interacts with the plunge pool. Successful alternatives were
selected for implementation that helped to reduce the TDG issues. (2006-2012)
Dwaar Kill Dam & Reservoir, Orange County, New York, U.S.A.
Page 1
Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.
Senior Technical Advisor, Dams & Hydro
Client: Orange County Water Authority
Mr. Tarbox was the senior staff member responsible for conceptual designs and overall quality control for a
feasibility investigation and design study of a water supply project that involved a 267-meter long
embankment dam and a 256-meter long RCC dam designed to impound a 16 million cubic meter reservoir.
(1988-1990)
Norway and Oakdale Dams Risk Assessment, Monticello, Indiana, U.S.A. Client: Northern Indiana Public Service Company (NIPSCO), (Including PFMA & Risk Assessment)
Participated in the risk assessment of two dams on the Bear River. The study was conducted by MWH with
the concurrence of FERC and under the joint leadership of Larry Von Thun and David Bowles. Key
elements of the risk assessment included a failure mode analysis for each dam, risk assessment and
evaluation of mitigation measures for the hydrological loading conditions. The results were presented to the
Federal Energy Regulatory Commission (FERC) by the Owner to illustrate the threat posed to downstream
property and lives. The Owner’s proposals for upgrading the dams were based on the results of the risk
assessment and were accepted by the FERC. (2006-07)
Bear River Dams Risk Assessment, Utah, U.S.A. Client: Utah Power & Light
Project Manager for the risk assessment of a series of dams on the Bear River. The study demonstrated an
Incremental Consequence Assessment (ICA) for the four dams, Soda Point, Grace, Oneida and Cutler. A key
element of the risk assessment included a failure mode analysis for each dam. The results were presented to
the Federal Energy Regulatory Commission (FERC) by the Owner to illustrate the threat posed to
downstream dams by upstream dams in a cascading failure scenario in probabilistic, economic and safety
terms. The Owner’s proposals for upgrading the dams were based on the results of the risk assessment and
were accepted by the FERC. (1988)
Tongue River Dam Risk Assessment, Montana, U.S.A. Client: Montana Department of Natural Resources
Project Manager for conducting a risk assessment of the 91-foot high embankment dam and free overflow
spillway. Responsible for the studies to conduct a failure mode analysis and to evaluate a number of
alternative actions to mitigate the high risk costs of property loss and threat to lives lost The risk assessment
illustrated how a risk-based comparison of several structural and non-structural alternatives can be used to
address spillway inadequacies. The evaluations were presented in probabilistic terms and also as cost-to-
save-a-life for each remedial action alternative. The risk assessment was used by the Owner to continue
operating restrictions, improve the dam break flood warning system and to seek government funding for
upgrading the dam. (1986)
Upper Stillwater Dam, Utah, U.S.A. Client: U.S. Bureau of Reclamation
As Head of the Concrete Dams Section, initiated and directed the studies for developing the concepts,
designs and cost estimates for the Bureau’s first state-of-the-art RCC dam. It is a 310 foot high gravity dam,
2670 feet long and contains 1,400,000 cubic yards of roller compacted concrete located on Rock Creek. It
was the largest RCC dam constructed at the time of its completion. (1978-1981)
Nambe Falls Dam, New Mexico, U.S.A. Client: U.S. Bureau of Reclamation
Supervisory Structural Engineer responsible for the design of the 150-foot high, 320-foot long double
curvature thin arch concrete dam located on the Rio Nambe near Santa Fe. It is a composite dam with a
concrete gravity thrust block for the left abutment of the arch dam designed to replicate the sloping canyon
topography. The thrust block is also the right abutment for a 144-foot high, 670-foot long embankment dam
that ties the composite structure to the high point of the reservoir on the left abutment. A unique scheme was
conceived to pre-stress the arch dam by installing Freysinet flat jacks over the entire surface of the central
contraction joint and then inflating them using a water/glycol mixture to expand the arch upstream against
Page 1
Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.
Senior Technical Advisor, Dams & Hydro
the reservoir. This operation resulted in locking into the arch dam a pattern of stresses at the abutments and
the crown that overcame tensile stresses due to severe winter temperatures that occur at the site. The use of
3D FEM analysis made it possible to analyze the complex combination of concrete structures and the
prestressing effects. (1976-1977)
Mountain Park Dam, Oklahoma, U.S.A. Client: U.S. Bureau of Reclamation
As Head of the Analytical Design Unit, responsible for the design and analyses of the 133-foot high double
curvature thin arch concrete dam located on the West Otter Creek River. It is 6 feet thick at the crest and 17
feet at its base. It is flanked by thrust blocks at both abutments and has a free-overflow crest spillway with
a capacity of 38,300 cfs. (1976)
Klang Gates Arch Dam Modification, Kuala Lumpur, Maylasia. Client: U.S. Bureau of Reclamation
Supervisory Structural Engineer responsible for the design and analysis of a ten-foot raise to an existing 111
foot high thick arch dam. Initiated and designed a laboratory testing program to investigate the nature of
bond strengths between new concrete and old on horizontal, sloping and vertical surfaces. The test results
led to the conclusion that it was feasible to construct the raise without extraordinary measures to ensure
bond between the raised portion of the dam and the original concrete beyond normal surface preparation
procedures (1974-1975).
Pueblo Dam, Colorado, U.S.A. Client: U.S. Bureau of Reclamation
Supervisory Structural Engineer responsible for stress analyses of the 250-foot high, 1,750-foot long
massive head buttress dam and spillway portion of Pueblo Dam located on the Arkansas River. (1970)
Coulee Forebay Dam & Hydroelectric Project, Washington, U.S.A. Client: Bureau of Reclamation
Supervisory Structural Engineer responsible for the analytical design unit that designed the 200-foot-high
gravity forebay dam in association with a 3,600-MW power station addition. The Grand Coulee Dam,
located on the Columbia River in Washington has a reservoir capacity of 9,652,000 acre-feet used for
hydroelectric power generation, irrigation and flood control. (1970)
Crystal Dam and Hydroelectric Power Station, Colorado, U.S.A. Client: U.S. Bureau of Reclamation
Senior Structural Engineer responsible for the design layouts and analytical stress analyses of the 323-foot-
high double-curvature, concrete arch dam that created a reservoir on the Gunnison River in Colorado for the
28-MW hydroelectric power station located at the toe of the dam. The dam has a crest width of 10 feet, a
base width of 29 feet and a free overflow spillway with capacity of 40,000 cfs. (1971-1972)
Auburn Dam and Hydroelectric Project, California, U.S.A. Client: U.S. Bureau of Reclamation
Design Manager for the 685-foot high, double-curvature, elliptical concrete arch dam to have been
constructed on the North Fork of the American River. Responsibilities included the development of
computer programs to analyze the reduction of uniaxial and radial jacking test data and in-situ stress
relief testing. Implemented the first applications of two dimensional finite element analysis to
determine the effective deformation modulus of the dam foundation, revised the computer program
ADSAS (Arch Dam
Stress Analysis System) to accommodate elliptical arch geometry and to perform dynamic analysis
for earthquake ground motions. The first application of the three dimensional finite element method
was introduced to analyze the dam for static and dynamic stresses. Mr. Tarbox initiated and helped to
develop a laboratory testing program to determine the rapid strain rate tensile strength and modulus
Page 1
Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.
Senior Technical Advisor, Dams & Hydro
of rupture for mass concrete that demonstrated the reserve strength of mass concrete during earthquake
loading conditions and the increase in modulus of elasticity during dynamic response. This also
marked the first time that comparisons were made for a Bureau of Reclamation designed dam
between the stresses determined by three-dimensional physical laboratory models, ADSAS and 3D
FEM. The design of the first fully automated instrumentation system for structural behavior monitoring
of a Bureau dam was also introduced and included in the specifications and drawings. (1969-1977)
AAR Investigations of Salt River Dams, Arizona, U.S.A.
Client: U.S. Bureau of Reclamation
Senior Structural Engineer responsible for developing computer programs and supporting the laboratory
and field investigation program into the deleterious effects of Alkali Aggregate Reactivity (AAR) on
Mormon Flat, Horse Mesa and Stewart Mountain Dams on the Salt River in Arizona. The procedures for
determining in-situ stresses in the dams due to AAR were developed in the laboratory using over coring
drilling techniques and computer programs to reduce and analyze the data. The results of this work led to
the eventual strengthening and remediation of Stewart Mountain Dam. (1969-1971)
Theodore Roosevelt Dam Raising, Arizona, U.S.A. Client: U.S. Bureau of Reclamation
Mr. Tarbox was a member of the Consultant Review Board responsible for review of all technical design
and construction aspects for this 280 foot gravity arch dam project located on the Salt River in Arizona
between 1986 and 1994. Modifications to the project included a 77 foot raise to the dam and construction
of a new river outlet works through the left abutment. that resulted in increased reservoir storage capacity to
2.3 million acre-feet. The intake consisted of a 19.7-foot-diameter lake-tap shaft constructed in more than
130 feet of water and a gate shaft more than 312 feet deep containing a 13-foot by 16-foot wheel-mounted
gate. Full scale field trials of concrete placed at the interface between the new concrete and the original
downstream face of the dam were confirmed by laboratory test results that adequate bond strength was
developed using conventional surface preparations such as high pressure water jets and absent any dowels
or shear pins. (1986-1996)
Xiaolangdi Multipurpose Dam Project, Henan, China Client: Yellow River Conservancy Commission Ministry of Water Resources
Mr. Tarbox served on the Xiaolangdi Dam Consulting Board, The Xiaolangdi Dam, on the Yellow River in
Henan Province, consists of a 505-foot-high earth and rockfill dam, 15 outlet and power tunnels, an intake
structure, an 1800-MW underground powerhouse and a concrete-lined plunge pool stilling basin. The
intake structure consists of ten towers with a height of 367 feet and a total volume of more than 4.4 million
cubic yards of concrete. There were three 60-foot diameter, 3,600-foot long diversion tunnels, six 25-foot
diameter power tunnels and three 39-foot wide by 62-foot high by 2,950-foot long tailrace tunnels. There
are also six 21-foot diameter posttensioned prestressed tunnels for sluicing of sediment. (1991-2000)
Green River Headworks Modifications, Washington, U.S.A. Client: City of Tacoma
Mr. Tarbox provided QA/QC for this project, which involved modifications to the headworks for the City of
Tacoma’s primary water supply source on the Green River. The project also included a 33-mile pipeline
that to enable the City to deliver a total of 290 cfs to its customers. (1995-1996)
Cedar Falls Masonry Dam Modifications, Washington, U.S.A. Client: Seattle City Light
As Project Manager, Mr. Tarbox was responsible for a feasibility assessment of the Cedar Falls masonry
dam and spillway, in preparation for rehabilitation and modifications to the project. The work at Cedar
Falls involved hydrologic studies and hydraulic sizing to pass the probable maximum flood, flood frequency
and routing studies and design of new hydraulic structures. (1981-1983)
Page 1
Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.
Senior Technical Advisor, Dams & Hydro
Wadaslingtang Dam and Hydroelectric Project, Indonesia Client: Ministry of Public Works, Jakarta
As Principal-in-Charge, Mr. Tarbox was responsible for the feasibility, design and construction management
services for the 640m long, 120m high rockfill dam and 16.5 MW hydro plant. The dam contains
266,000,000 cubic yards of material and was constructed using the “wet core” technique making it the
highest wet core dam constructed to date at that time. (1983-88)
Hydroelectric Plant Rehab and SCADA System, Alaska, U.S.A. Client: Ketchikan Public Utilities
As Program Manager, Mr. Tarbox’s was responsible for the design and construction management of the
Swan Lake Hydroelectric plant. He was also responsible for managing an extensive upgrade and
modernization program for automating and remotely controlling generating and electrical systems at
Ketchikan’s four hydroelectric and two diesel plants. This involved an automation study, a communications
study and the development of plans and specifications for a new, fully redundant SCADA system with a
combination microwave/VHF communications. All new switchgear, electronic governors, motor operated
butterfly control valves, fire suppression systems, generator cooling systems and new plant HVAC systems
were designed and managed during construction. An uninterruptible power supply system was designed to
support the monitoring and control system at all plants. (1979-1983)
Boundary Dam Seismic Hazard Assessment and Dynamic Analysis, Washington, U.S.A.
Client: Seattle City Light
As Project Manager and Concrete Dam Specialist, Mr. Tarbox was responsible for management of a study
to determine the seismic hazard for this 340-foot-high concrete arch dam on the Pend Orielle River in
Washington. The study included a static and dynamic stress analysis of the dam, assessment of the stability
of the reservoir rim, an evaluation of the dam for overtopping in the event of a reservoir landslide,
foundation subsurface investigations, installation of piezometers and evaluation and analysis of strainmeter
instrumentation data for the dam. (1984-1985)
Green Lake Dam & Hydroelectric Project, Alaska, U.S.A. Client: City and Borough of Sitka
Mr. Tarbox, as Head of the Design Department, was responsible for the 16.5-MW Green Lake
Hydroelectric Project to help the City and Borough of Sitka meet its expanding energy needs. The project
included a 210-foot-high, double-curvature concrete arch dam on the Vodopad River, a 64,000-acre-foot
reservoir, a 2,000-foot power tunnel, a 16.5 MW powerhouse, a switchyard, 7 miles of new 69-kV
transmission line and an access road. (1979-1981)
American Falls Dam Replacement Project, Idaho, U.S.A. Client: U.S. Bureau of Reclamation
Supervisory Design Engineer for the $80 million replacement dam. Responsible for analytical design
studies that led to the decision to replace the original dam due to severe deterioration from AAR (Alkali
Aggregate Reactivity). The project included a dam 98-feet high and 1,200 feet long with a 600-foot long
central concrete gravity section. (1974-1976)
Curecanti-Hayden Transmission Line, Colorado, U.S.A. Client: U.S. Bureau of Reclamation
As Field Engineer, Mr. Tarbox was responsible for inspecting the foundation installations and steel tower
erection on the construction of the 170-mile, 230-kV Curecanti-to-Hayden, Colorado transmission line.
(1964)
Flaming Gorge Dam and Hydroelectric Project, Utah, U.S.A.
Page 1
Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.
Senior Technical Advisor, Dams & Hydro
Client: U.S. Bureau of Reclamation
Mr. Tarbox, as Field Engineer, was a field inspector for the 502-foot-high concrete arch dam and its. 26-
foot-diameter spillway tunnel. The dam is located on the Green River and impounds a reservoir of
3,788,900 acre-feet for hydroelectric power generation through its 108-MW power station (1961-1964)
FERC Part 12 Periodic Safety Inspections
Soda Point Dam, Grace Dam, Oneida Dam and Cutler Dam & Hydroelectric Projects Client: Utah Power & Light, Bear River, Utah, U.S.A.
Clark Fork Project -Cabinet Gorge Dam, Spokane, WA, U.S.A. Client: Avista Utilities
Priest Rapids Dam & Wanapum Dam & Hydroelectric Projects, Ephrata, WA, U.S.A. Client: Grant County PUD
Rock Island Dam, Rocky Reach Dam and Lake Chelan Hydroelectric Projects, Wenatchee, WA,
U.S.A.
Client: Chelan County PUD
Monroe and Columbus Hydroelectric Projects, Nebraska, U.S.A. Client: Loup Power District
Claytor Dam Project Client: American Electric Power
Cowlitz Falls Dam & Hydroelectric Project, Chehalis, WA, U.S.A. Client: Lewis County PUD.(Including PFMA)
Cooper Lake Dam & Hydroelectric Project, Kenai Peninsula Borough, AK, U.S.A.
Client: Chugach Electric Association, Inc.(Including PFMA)
Upper and Lower Baker River Dams, Whatcomb County, WA, U.S.A. Client: Puget Sound Energy, Inc.(Including PFMA)
Boundary Dam, Pend Orielle, WA, U.S.A.
Client: Seattle City Light,(Including PFMA)
Ross Dam, Diablo, WA, U.S.A. Client: Seattle City Light,(Including PFMA)
Diablo Dam, Diablo, WA, U.S.A. Client: Seattle City Light,(Including PFMA)
Gorge Dam, New Halem, WA, U.S.A. Client: Seattle City Light,(Including PFMA)
Foothills Project (Strontia Springs Dam), Denver, CO, U.S.A. Client: Denver Water Board, (Including PFMA)
Page 1
Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.
Senior Technical Advisor, Dams & Hydro
Norway and Oakdale Hydroelectric Project, Monticello, Indiana, U.S.A.
Client: Northern Indiana Public Service Company (NIPSCO), (Including PFMA & Risk Assessment)
Salmon Creek Hydroelectric Project, Juneau, AK, U.S.A. Client: Alaska Electric Light & Power
Cushman #1 and #2 Hydroelectric Project, Tacoma, WA, U.S.A. Client: Tacoma Power, (Including PFMA)
Lake Spaulding Dams No. 1, 2, & 3, Nevada County, CA, U.S.A. Client: Pacific Gas & Electric, (Including PFMA)
FERC Dam Breach and EAP (Emergency Action Plan) Preparation Client: Ketchikan Public Utilities, Ketchikan, AK
Beaver Falls/Lake Silva, Ketchikan Lakes and Swan Lake Hydroelectric projects (1981) Client: Ketchikan Public Utilities, Ketchikan, AK
Jackson Bluff Hydroelectric Project (1982), FL, U.S.A Client: City of Tallahassee
Safety Evaluation of Existing Dams (SEED) Program Client: U.S. Bureau of Reclamation
As Assistant Chief, Dams Branch Mr. Tarbox managed the inaugural dam safety program known as SEED
for more than 355 Reclamation dams, 300 embankment dams and 55 concrete dams. The policies, practices,
publications and procedures initiated in that period were the foundation of what has become the Bureau’s
SOD (Safety of Dams) and TADS (Training Aids for Dam Safety) Program. (1978-1979)
Dam Safety Training and Evaluation Program Client: NIA (National Irrigation Administration) Manila, Philippines
PRC Engineering conducted a five-month dam safety training and evaluation program in the Philippines for
the National Irrigation Administration. The U.S. Team:
Developed a manual which outlined the organization, procedures, technical expertise and other
resources required to implement a dam safety program
Trained the staff in all aspects of performing dam safety monitor in, interpretation, inspection,
evaluation and report preparation
Inspected eight dams: Magat, Baligatan, Maris, Pantabangan, Aya, Masiway, Canili and Mayo, and
inspected the Magat and Pantabangan power plants
Updated an operation and maintenance manual for the Magat Dam and Power Plant Project
Prepared an operation and maintenance manual for the Pantabangan Dam and Power Plant Project
Prepared dam safety reports for each structure
Mr. Tarbox participated on the Team as a lecturer on dams and appurtenant structures during the training
program and he was on the dam inspection team for the eight dams which were used as a field laboratory for
instructing the Philippine engineers in how to conduct onsite safety inspections. (1986)
Dam Safety Inspection Program Client: EGAT (Electricity Generating Authority of Thailand) Bangkok, Thailand (1984-85)
PRC Engineering conducted a comprehensive dam safety inspection program for the eight dams operated
by EGAT. The program included a preliminary evaluation of EGAT's existing dam safety program, a review
Page 1
Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.
Senior Technical Advisor, Dams & Hydro
of design and operation and maintenance data for the dams, a site inspection of each dam and its facilities,
and an evaluation of the need for further investigations and remedial actions. The following table lists the
dams inspected under the program:
Name of Dam
Type
Height (feet)
Crest Length
(feet(
Hydropower
Capacity
(megawatts)
1. Bhumibol Concrete Arch 502 1,595 420
2. Sirikit Earthfill 358 2,494 375
3. Chula Bhorn Rockfil1 230 2,638 40
4. Kang Krachan Earthfill 190 2,494 19
5
.
Sirindhorn
Rockfill
157
3,101
24 6.
Nam Pung Rockfill 131 2,490 6
7.
Jbul Ratana Rockfill 105 2,641 25
8.
Sringrind Rockfill 463 2,015 360
Value Engineering (VE) Team Assignments Client: US Army Corps of Engineers (2006)
The VE Study considered the Integrated Federal Alternative (IFA) developed by the Folsom Dam Raise and
Auxiliary Spillway Alternative Project Alternative Solutions Study (PASS) II, as described in the Draft Final
Report, April 2006.
Client: BC Hydro (2009)
The VE Study considered the seismic retrofit design of the Ruskin Powerhouse, switchyard, power intakes,
turbine-generators and ancillary equipment, power tunnel, penstocks and draft tube gates.
PUBLICATIONS
Author or Co-author of the following:
1. "Deformation Moduli Determined by Joint-Shear Index and Shear Catalogue; Symposium of the
International Society for Rock Mechanics, Nancy, France, 1971.
2. "Beneficiation of Auburn Dam Foundation", ASCE National Water Resources Engineering
Meeting, Washington, D.C., 1973.
3. "Bureau of Reclamation's Design Criteria for Concrete Arch and Gravity Dams - 1975".
Proceedings for International Symposium on Criteria and Assumptions for Numerical Analysis of
Dams, Swansea, U.K., 1975.
4. "Auburn to the Longest Thin Arch Dam", USCOLD Newsletter, Issue No. 47, New York, 1975.
5. "Design of Gravity Dams", U.S. Bureau of Reclamation, Denver, Colorado, 1975.
6. "Design of Arch Dams, U.S. Bureau of Reclamation, Denver, Colorado, 1977.
7. "Design and Analysis of Auburn Dam", U.S. Bureau of Reclamation, Denver, Colorado, 1977.
Page 1
Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.
Senior Technical Advisor, Dams & Hydro
8. "Auburn Dam Instrumentation", joint U.S.A.-U.S.S.R. Seminar on the Design and Construction of
Large Dams in Seismically Active Areas, Hydraulic Institute, Moscow, U.S.S.R., 1977.
9. "Earthquake Design and Analysis of Concrete Dams", joint U.S.A.-U.S.S.R. Seminar on the
Design and Construction of Large Dams in Seismically Active Areas, Hydraulic Institute, Moscow,
U.S.S.R., 1977.
10. "Design of Concrete Dams", Chapter 8, Handbook of Dam Engineering, Van Nostrand Reinhold,
New York, 1977.
11. "Critical Aspects in Design Practice of Concrete Dams", Research Conference on Earthquake
Engineering, Skopje, Yugoslavia, 1980.
12. "Swan Lake Hydroelectric Projects, USCOLD Newsletter, Issue No. 64, New York, 1981.
13. "Small Scale Hydroelectric Projects in Alaska", ASCE Conference Proceedings for Applying
Research to Hydraulic Practice, Jackson, Mississippi, 1982.
14. "Narnbe Falls Dam Flat Jack and Grout Tests", U.S. Bureau of Reclamation, REC-ERC-77-16,
Denver, Colorado, 1977.
15. "Seismic Analysis of Concrete Dams" - Proceedings 13th International Congress on Large Dams,
New Delhi, India, 1979.
16. "Planning, Design and Cost Estimates for RCC Dams" - Proceedings ASCE Specialty Conference,
Roller Compacted Concrete id, San Diego, California, 1988.
17. "Gravity Dam Design and Analysis, "Advanced Dam Engineering for Design. Construction and
Rehabilitation. Van Nostrand Reinhold, New York City, New York 1988.
18. “Arch Dam Design and Analysis", Advance Dam Engineering for Design. Construction and
Rehabilitation Van Reinhold, New York City, New York 1988.
19. "Wet Core Construction (WCC) Technology for Embankment Dams" - Proceedings 16th
International Congress on Large Dams, San Francisco, C.19, San Francisco, CA, 1988.
20. "Pre-Stressing an Arch Dam by Forced Opening of the Joints" - Proceedings International
Workshop on Arch Dams, Coimbra, Portugal, April 1987.
21. “Dam Safety Evaluation for a Series of Utah Power and Light Hydropower Dams, Including Risk
Assessment: Work Plan, Project Description, Remedial Action,” ASDSO Annual Conference,
Albuquerque, New Mexico, October 1-5, 1989.
22. "Safety Assessment of Existing Dams for Earthquake Conditions", Volume C-4 Seismic Analysis
of Concrete Dams, Canadian Electrical Association Research and Development, Report No. 420 G
547, 1990.
23. "Evaluation of Dam Safety at a Series of Hydropower Dams Including Risk Assessment"
-Proceedings of the 6th Conference: The Embankment Dam, University of Nottingham, England,
sponsored by the British Dam Society, 1990.
24. "Roller-Compacted Concrete Dams", Chapter 10 Preliminary Design and Cost Estimates, Roller-
Compacted Dams, 1991.
Page 1
Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.
Senior Technical Advisor, Dams & Hydro
25. "PC Numerical Analysis of Talvacchia Arch Dam", First Benchmark Workshop on Numerical
Analysis of Dams, Bergamo, Italy, sponsored by ICOLD, 1991.
26. "Definition of Critical Thermal States in Arch Dams - A Prerequisite for Cracking Analysis"
Proceedings for the International Conference on Dam Fracture, Denver, Colorado, 1991.
27. "Safety Assessment of Existing Dams for Earthquake Conditions Part III - Seismic Analysis of
Concrete Dams", Part III - Seismic Analysis of Concrete Dams, Proceedings of the 3rd Canadian
Earthquake Engineering Conference, Vancouver, B.C., 1991.
28. "Opening Address", International Conference on Dam Fracture, Boulder, Colorado, 1991.
29. "Examples of Risk Assessment in Dam Safety Decision-Making", Proceedings of Waterpower '91,
Denver, Colorado
30. "A Seismic Screening Procedure for Concrete Gravity Dams" - Proceedings of the Association of
State Dam Safety Officials Annual Conference, Baltimore, Maryland 1992.
31. "Examples of Using Risk Assessment for Dam Safety Decision Making", XXV Congress of the
International Association For Hydraulic Research, Tokyo, Japan, 1993
32. "Innovation, The Spirit of Engineering", the Inaugural Jack Hilf Lecture, University of Colorado,
Boulder, 1993.
33. "Theodore Roosevelt Dam Modification," Proceedings 18th International Congress on Large
Dams, Durban, South Africa, 1994.
34. "Roller-Compacted Mass Concrete - ACI 207.5R-93," ACI Committee 207, American Concrete
Institute, Detroit, Michigan, 1997.
35. “Statewide Review of Headworks Dams: Status, Risks, Future Business Focus and Approach to
Regulation," Proceedings 19th International Congress on Large Dams, Florence, Italy, 1997.
36. “The Role of a Panel of Experts in the Enhancement of Safety,” Proceedings of the International
Symposium on New Trends and Guidelines on Dam Safety, Barcelona, Spain, June 1998.
37. “Seismotectonic Design for the Olivenhain Dam,” Proceedings 22nd
Annual USSD Conference,
San Diego, CA, June 2002.
38. “Design of Roller-Compacted Concrete Features for the Olivenhain Dam,” Proceedings 22nd
Annual USSD Conference, San Diego, CA, June 2002.
39. “Supplementary Olivenhain Dam Trial Mix Program,” Proceedings 22nd
Annual USSD
Conference, San Diego, CA, June 2002.
40. “Structural Design Optimization for the Olivenhain RCC Dam,” Proceedings 22nd
Annual USSD
Conference, San Diego, CA, June 2002.
41. “Olivenhain Dam Design,” Proceedings PCA Seminar on RCC, San Diego, CA, August 2002.
42. “RCC for the Heightening of San Vicente Dam,” International Journal of Hydropower & Dams,
October, 2003.
Page 1
Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.
Senior Technical Advisor, Dams & Hydro
43. “Design and Construction of the Olivenhain RCC Dam,” ASDSO Conference, Minneapolis, MN,
September 2003.
44. “Design and Construction of an Exposed Geomembrane System for the Olivenhain Dam,” USSD
Annual Meeting and Conference, Salt Lake City, UT, June 2005
45 “Exposed Geomembrane Liner Minimizes Seepage at Olivenhain,” The International Journal on
Hydropower & Dams, Volume Twelve, Issue 4, 2005.
46 “Value Engineering at Olivenhain RCC Dam, USA,” Proceedings 22nd International Congress on
Large Dams, Barcelona, Spain, 2006.
47 “Designing the Tallest RCC Dam Raise for San Vicente Dam in Southern California,” Proceedings 5Th
International Symposium on RCC Dams, Guiyang, China, November, 2007.
48 “Big Tujunga Dam Seismic Rehabilitation and Spillway Modification Project,” Proceedings
USSD 28th
Annual Meeting and Conference, Portland, Oregon, April/May, 2008.
49 “Special Issues of Interface Design, Drainage, and Facing Systems for Raising San Vicente Dam,”
Proceedings 23rd International Congress on Large Dams, Brazilia, Brazil, 2009.
50 “Structural Design Optimization with Raising San Vicente Dam,” Proceedings 23rd International
Congress on Large Dams, Brazilia, Brazil, 2009.
51 “Foundation Challenges for Raising San Vicente Dam,” Proceedings 23rd International Congress on
Large Dams, Brazilia, Brazil, 2009.
52 “FEA Optimization of Rehabilitation Design for Big Tujunga Dam,” Proceedings 23rd
International Congress on Large Dams, Brazilia, Brazil, 2009.
53 “Staged Construction Thermal Analysis for San Vicente Dam Raise Project,” Proceedings USSD 29th
Annual Meeting and Conference, Nashville, Tennessee, April, 2009.
54 “Dynamic Characterization of San Vicente Dam,” ASDSO Dam Safety 2009, Hollywood, Florida,
September/October, 2009.
55 “Structural Design for San Vicente Dam Raise,” Proceedings USSD 30th
Annual Meeting and
Conference, San Diego, California, April 2011.
56 “Bracing for Impact at Big Tujunga Dam,” International Water Power & Dam Construction,
December, 2011.
57 “The Seismic and Hydraulic Rehabilitation of Big Tujunga Dam,” ASDSO Dams Safety Journal,
May 2012.
58 “Reaching New Heights at San Vicente,” International Water Power & Dam Construction, July
2013.
59 “Maintaining the Reservoir at Salmon Creek Dam; Evaluation of a 99-Year Old Constant Angle
Arch Dam,” Proceedings ICOLD 2013, Seattle, Washington, August 2013.
60 “Dams of the United States - A Pictorial Display of Landmark Dams,” U.S. Society on Dams, 81st
Annual Meeting of ICOLD, Seattle, Washington, August 2013 (Technical Editor).
Page 1
Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.
Senior Technical Advisor, Dams & Hydro
61 “Achievements and Advancements U. S. Dam Engineering,” U.S. Society on Dams, 81st
Annual
Meeting of ICOLD, Seattle, Washington, August 2013 (Technical Editor).
62 “Current Seismic Tools Used to Evaluate a 1914 Concrete Arch Dam,” Proceedings USSD 34th
Annual
Meeting and Conference, San Francisco, California, April, 2014.
63 “Investigating The Structural Safety of Cracked Concrete Dams,” CEATI International, Generation
Dam Safety Program, Report No. T122700-0226, Montreal, Quebec, Canada, January 2015.
64 “Why Would You Drill Holes in My Dam,” Proceedings ASDSO Dam Safety Meeting, New Orleans,
Louisiana, September, 2015.
65 “Design and Construction of the Upstream Geomembrane Facing System for the San Vicente RCC
Dam Raise,” Proceedings ASDSO Dam Safety Meeting, New Orleans, Louisiana, September, 2015.
66 “Using The Trial Load Method To Optimize The Feasibility Design of Watana Dam,” Proceedings
36th Annual USSD Conference, Denver, Colorado April, 2016.
67 “Post-Construction Coring Evaluation for RCC at the San Vicente Dam Raise Project,” Proceedings
ASDSO Dam Safety Meeting, Philadelphia, Pennsylvania, September, 2016.
68 “Investigating the Structural Safety of Cracked Concrete Dams,” Proceedings USSD 37th Annual
Meeting and Conference, Anaheim, California, April, 2017.
69 “Understanding the Performance of Aging Infrastructure: A 99-Year Old Multiple Arch Dam,”
Proceedings USSD 37th Annual Meeting and Conference, Anaheim, California, April, 2017.
70 “Total Rehab – Notching Santa Anita Dam,” Proceedings USSD 37th Annual Meeting and Conference,
Anaheim, California, April, 2017.
71 “The Emergency and Carryover Storage Project Creates a Lasting Legacy for Water Reliability in San
Diego, California,” Proceedings, ANCOLD/NZSOLD 2016 Conference, “Dams A Lasting Legacy,”
Adelaide, Australia, October 2016.
72 “RCC Post Construction Core Testing and Data Analysis for San Vicente Dam Raise Project,”
Proceedings USSD 37th Annual Meeting and Conference, Anaheim, California, April, 2017.
Page 1
Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.
Senior Technical Advisor, Dams & Hydro
AWARDS
U.S. Bureau of Reclamation: Meritorious Service - Quality Increase 1968
U.S. Bureau of Reclamation: Meritorious Service - Special Achievement 1970
U.S. Bureau of Reclamation: Meritorious Service - Outstanding Performance and Quality Increase 1976
University of Maryland: Centennial Medal of Engineering 1994
Top 20 Individuals: International Water Power & Dam Construction (IWP&DC): Recognized by the
Editorial Board and industry experts from around the world as one of the top 20 individuals having made
the biggest difference in the dam sector, Influencing Engineering, IWP&DC, January 2011.
Lifetime Achievement: USSD (United States Society on Dams): Awarded the 2011 USSD Lifetime
Achievement Award for outstanding contributions to the dam engineering profession, San Diego, California,
April 13, 2011.
Legacy Award 2016 Northwest Region: ENR (Engineering News Record): Awarded the Northwest
Regional Legacy Award for accomplishments in the engineering and construction industry for dams and
hydroelectric projects. His lifetime of contributions to dam design, safety, and construction, as well as to the
global community of engineers merited Glenn the ENR Legacy Award. His groundbreaking design and
technology work – on everything from the trial-load and finite element analysis methods for arch dams in his
early days at the U.S. Bureau of Reclamation to modern designs of roller compacted concrete (RCC) dams–
have helped set the industry standards for dams and hydro projects around the world.
Project Manager, Parsons/Harza JV, Olivenhain RCC Dam – Owner San Diego County Water
Authority/Olivenhain Municipal Water District:
Charles J. Pankow Jr. Award, So. California Chapter of ACI, November 11, 2003
Project of the Year Award, APWA, November 9, 2004
Outstanding Civil Engineering Water Project, Council of the California ASCE, 2004
Project of the Year Award, APWA, September 12, 2005
Excellence in Environmental Engineering Honor Award, American Academy of Environmental
Engineers, 2005
Opal Civil Engineering Award of Merit, ACSE, 2005
Milestone RCC Project 1987-2007, 5th
International Symposium on RCC Dams, Guiyang, China,
2007
Lead Dam Design, MWH Americas, Inc.: San Vicente RCC Dam Raise Project– Owner San Diego
County Water Authority/City of San Diego:
APWA Public Works Projects of the Year, Anaheim, CA, August 2012.
ASCE (American Society of Civil Engineers – San Diego Section) – 2016 Project of the Year
Award - Dams & Reservoirs
Page 1
Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.
Senior Technical Advisor, Dams & Hydro
USSD Award of Excellence in the Constructed Project, San Vicente RCC Dam Raise Project,
D e n v e r , CO, April 2016.
CMAA (Construction Management Association of America – San Diego Chapter) – 2016 Project
Achievement Award – Public Works >$15 million
Principle-in-Charge and Lead Dam Design, MWH Americas, Inc.: Big Tujunga Seismic Rehabilitation
and Spillway Modification Project – Owner Los Angeles Department of Public Works:
ASDSO National Rehabilitation Project of the Year Award, Washington D.C., 2011.
ENR Best Projects – Best Civil Works, Big Tujunga Seismic Retrofit, San Francisco, CA,
December 2011.
USSD Award of Excellence in the Constructed Project, Big Tujunga Dam Seismic Rehabilitation
and Spillway Modification Project, New Orleans, LA, May 2012.
APWA Public Works Projects of the Year, Anaheim, CA, August 2012.
Project Manager, MWH Americas, Inc.: Independent Technical Review (ITR) of Portugues RCC Thick
Arch Dam – Owner U.S. Army Corps of Engineers:
3rd International Milestone RCC Dam Project, 7th International Symposium on Roller Compacted
Concrete (RCC) Dams, Chengdu, China Sept. 24 -25, 2015
ENR (Engineering News Record) 2016 Global Best Project – Water/Wastewater Award of Merit for
Emergency & Carryover Storage Project, San Diego County Water Authority
Project Manager/Lead Dam Designer, MWH Americas Inc.: Olivenhain RCC Dam and Lead
Dam Designer, San Vicente RCC Dam Raise features of the E&CS Project.
LANGUAGE
English (Excellent); Spanish (Poor)
OVERSEAS ASSIGNMENTS
Canada, Australia, China, Indonesia, Philippines, Taiwan, Pakistan, India, Sri Lanka, Panama, Venezuela,
Peru, Argentina, Chile, Colombia, Ecuador, Greece, Turkey, Jordan, Egypt, Ethiopia, Lesotho, Iceland,
Jordan and Iraq
Page 1
Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.
Senior Technical Advisor, Dams & Hydro
EMPLOYMENT HISTORY:
2016 to Present MWH now part of Stantec, Bellevue, Washington, U.S.A. Senior Technical Advisor, Dams & Hydro, Dams & Water Power, MWH now part
of Stantec, Inc.
2011 to 2016 MWH Americas, Bellevue, Washington, U.S.A. Senior Vice President, Global Dams Practice Leader, MWH Americas, Inc.
2010 to 2011 MWH Americas, Bellevue, Washington, U.S.A. Vice President, Dams Practice Leader, MWH Americas, Inc.
2003 to 2010 MWH Americas, Bellevue, Washington, U.S.A. Vice President, Principal Structural Engineer, Dams and Hydropower
2001 to 2003 MWH E&I, Bellevue, Washington/Chicago, Illinois, U.S.A. Vice President, Group Manager, Global Hydropower
1998 to 2001 Harza Engineering Company, Bellevue, Washington, U.S.A. Managing Partner, Hydropower Business Unit
1997 to 1998 Harza Engineering Company, Bellevue, Washington, U.S.A. President, Western Division
1994 to 1997 R. W. Beck, Inc., Seattle, Washington, U.S.A. Vice President and Director of Infrastructure Services
1992 to 1994 Bechtel Corporation, San Francisco, California, U.S.A. Vice President, Manager of Engineering and Construction Technology,
R & D Group
1990 to 1992 Bechtel Corporation, San Francisco, California, U.S.A. Vice President, Manager of Water Resources,
1988 to 1990 Harza Engineering Company, Chicago, Illinois, U.S.A. Vice President, Chief Engineer
1983 to 1988 ECI (Engineering Consultants, Inc.), Denver, Colorado, U.S.A.
Senior Vice President of Engineering
1979 to 1983 R. W. Beck and Associates, Seattle, Washington, U.S.A.
Associate and Head of the Design Department
1961 to 1979 U.S. Bureau of Reclamation, Denver, Colorado, U.S.A. Assistant Chief, Dams Branch
Head, Concrete Dams Section
Supervisor, Analytical Design Unit
Construction Inspector, Flaming Gorge Dam & Hydropower Project