21
Page 1 GLENN S. TARBOX, P.E., F. ASCE, S.E.C.B., P. Eng. POSITION IN FIRM: SENIOR TECHNICAL ADVISOR, DAMS & HYDRO, MWH now Part of STANTEC YEARS WITH FIRM: 2 1 TOTAL YEARS OF EXPERIENCE: OVER 45 KEY QUALIFICATIONS: Mr. Tarbox has over 45 years of experience as a civil/structural engineer in all facets of water resource project development and management. He offers expertise in planning, design, management and construction of dams, hydroelectric plants, transmission lines, tunnels and other major civil works projects. His early career developed as a dam design and construction engineer and Assistant Chief, Dams Branch with the U.S. Bureau of Reclamation; the past 33 years have been spent with the private sector. Glenn has served as Design Engineer, Project Manager or Principal-In-Charge on more than 26 major domestic and international dams and is often called upon to serve as a dam expert on consulting boards for new or upgraded projects, a FERC certified Part 12 Independent Safety Consultant and Failure Mode Analysis Facilitator and as an expert forensics witness related to dams. Glenn has written computer programs for analyzing concrete gravity, arch and buttress dams. He was part of the team of engineers that computerized the Trial Load Method of Analysis into the program known as “ADSAS.” He was the first engineer to introduce the Finite Element Method of analysis for concrete dams into the Bureau of Reclamation on Nambe Falls Dam, supervised the addition of dynamic analysis into ADSAS and he introduced the use of RCC into the Bureau for Upper Stillwater Dam. He was one of the key authors of the Bureau of Reclamation’s, “Design of Gravity Dams” and Design of Arch Dams.” He has been the design manager of several major arch and gravity dam designs including Auburn, Nambe Falls, Crystal, Mountain Park, Swift, Swan Lake, Coulee Third, Pejengkolan, Upper Stillwater, and Olivenhain (see details in the paragraphs that follow). He is experienced in the application of the Finite Element Method of analysis for static and dynamic loading on arch, gravity and buttress dams. Glenn is also an authority on the subject of uplift and the stability of concrete dams and their foundations. He is experienced in the design of contraction joints, concrete cooling systems, contraction joint grouting systems, foundation treatments such as consolidation and deep curtain grouting, foundation drainage curtains and dental concrete. Glenn has worked on the safety of existing dams of all types dealing with matters related to concrete deterioration (ASR), cracking, leakage, and repairs to improve stability, reduce uplift pressure, reduce leakage and rehabilitate aging concrete structures. As the Assistant Chief, Dams Branch, Glenn was responsible for administering the Bureau of Reclamation’s inaugural SEED (Safety Evaluation of Existing Dams) Program. EDUCATION: Bachelor of Science, Civil Engineering, University of Maryland, 1961 Graduate Studies University of Colorado, 1966-1970 Master of Science Academic Requirements Colorado School of Mines, 1970/71 (Mathematics and Operations Research) University of California, Berkeley, 1969 (Finite Element Analysis) Cornell University, 1975 (Earthquake Engineering)

Tarbox-GS Resume 10-19-2016

Embed Size (px)

Citation preview

Page 1

GLENN S. TARBOX, P.E., F. ASCE, S.E.C.B., P. Eng.

POSITION IN FIRM: SENIOR TECHNICAL ADVISOR, DAMS & HYDRO, MWH now Part of

STANTEC

YEARS WITH FIRM: 2 1

TOTAL YEARS OF EXPERIENCE: OVER 45

KEY QUALIFICATIONS:

Mr. Tarbox has over 45 years of experience as a civil/structural engineer in all facets of water resource

project development and management. He offers expertise in planning, design, management and

construction of dams, hydroelectric plants, transmission lines, tunnels and other major civil works projects.

His early career developed as a dam design and construction engineer and Assistant Chief, Dams Branch

with the U.S. Bureau of Reclamation; the past 33 years have been spent with the private sector. Glenn has

served as Design Engineer, Project Manager or Principal-In-Charge on more than 26 major domestic and

international dams and is often called upon to serve as a dam expert on consulting boards for new or

upgraded projects, a FERC certified Part 12 Independent Safety Consultant and Failure Mode Analysis

Facilitator and as an expert forensics witness related to dams.

Glenn has written computer programs for analyzing concrete gravity, arch and buttress dams. He was part of

the team of engineers that computerized the Trial Load Method of Analysis into the program known as

“ADSAS.” He was the first engineer to introduce the Finite Element Method of analysis for concrete dams

into the Bureau of Reclamation on Nambe Falls Dam, supervised the addition of dynamic analysis into

ADSAS and he introduced the use of RCC into the Bureau for Upper Stillwater Dam. He was one of the key

authors of the Bureau of Reclamation’s, “Design of Gravity Dams” and Design of Arch Dams.” He has been

the design manager of several major arch and gravity dam designs including Auburn, Nambe Falls, Crystal,

Mountain Park, Swift, Swan Lake, Coulee Third, Pejengkolan, Upper Stillwater, and Olivenhain (see

details in the paragraphs that follow). He is experienced in the application of the Finite Element Method of

analysis for static and dynamic loading on arch, gravity and buttress dams. Glenn is also an authority on the

subject of uplift and the stability of concrete dams and their foundations. He is experienced in the design of

contraction joints, concrete cooling systems, contraction joint grouting systems, foundation treatments such

as consolidation and deep curtain grouting, foundation drainage curtains and dental concrete. Glenn has

worked on the safety of existing dams of all types dealing with matters related to concrete deterioration

(ASR), cracking, leakage, and repairs to improve stability, reduce uplift pressure, reduce leakage and

rehabilitate aging concrete structures. As the Assistant Chief, Dams Branch, Glenn was responsible for

administering the Bureau of Reclamation’s inaugural SEED (Safety Evaluation of Existing Dams) Program.

EDUCATION:

Bachelor of Science, Civil Engineering, University of Maryland, 1961

Graduate Studies

University of Colorado, 1966-1970 Master of Science Academic Requirements

Colorado School of Mines, 1970/71 (Mathematics and Operations Research)

University of California, Berkeley, 1969 (Finite Element Analysis)

Cornell University, 1975 (Earthquake Engineering)

Page 1

Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.

Senior Technical Advisor, Dams & Hydro

Continuing Education: Supervision/Management Courses: Supervision & Group Performance; An

Introduction to Basic Supervision of People; Effective Executive Practices; Counseling Troubled

Employees; Middle Management Institute; Management Institute for Scientists, Eng. & Profs.; PERT/CPM;

Effective Time Management; Finite Element Method of Analysis; Control of Cracking in Mass Concrete

Structures; Earthquake Engineering; Structural Design for Earthquakes; Concrete Control Course USBR;

Concrete Polymer Materials Course; Cold Regions Engineering; New Perspectives on the Safety of Dams;

Construction/Contract Administration: Construction Law/Contract Negotiations; Construction Claims:

Analysis, Presentation/Defense; Practical Construction Law. MWH University courses include Pricing and

Negotiations and Business Unit Management. Bechtel Training Center courses include Bechtel Executive

Plan XVI and Bechtel Marketing Plan IV. FERC PFMA Facilitator Training Course.

Professional Organizations: United States Society on Dams (USSD); Formerly member of Committee on

Numerical Analysis; Currently member of Committee on Concrete; Formerly Chairman of Committee on

Financing of Dams; Formerly member of the Board of Directors (Treasurer '93, Vice President, '94,

President '95-'97); United States Committee on Irrigation and Drainage (USCID); The Society of American

Military Engineers; American Society of Civil Engineers (ASCE); Fellow; Formerly member of Seismic

Effects Committee/Structures Division; Formerly member of Publications Committee/Geotechnical

Engineering Division; American Concrete Institute (ACI); Currently member of Committee 207 on Mass

Concrete; Earthquake Engineering Research Institute (EERI); Construction Industry Institute; Formerly

alternate-member - Board of Advisors; Former member - Research Committee; Civil Engineering Research

Foundation; Formerly member - Corporate Advisory Board; Formerly member - Executive Committee;

National Institute of Standards and Technology; Panel Member - Building and Fire Research Laboratory

(1992 - 1995)

Professional Registrations: Civil Engineer / Alaska / 1980 / #4871; Civil Engineer / Arizona / 1984 /

#16736; Professional Engineer / Colorado / 2000 / #9311; Professional Engineer / Georgia / 1989 / #18035;

Professional Engineer / Illinois / 1989 / #062-044980; Professional Engineer / Montana / 1998 / #8292PE;

Professional Engineer / Texas / 1986 / #59105; Professional Engineer / Utah / 1998 / #167339-2202;

Professional Engineer / Wyoming / 1987 / #4759; Professional Engineer/Civil / Washington / 1984 /

#22012; Professional Engineer / Idaho / 2003 / #11113; Professional Engineer/Civil / New Brunswick /

2000 / L3458; Professional Engineer Civil / Saskatchewan / 34850 / Certified Structural Engineer/ S.E.C.B/1589-

1105

EXPERIENCE RECORD:

Wanapum Dam Mitigation Studies and Repairs of Cracked Spillway

Client: Grant County PUD

Senior Technical Advisor and Quality Manager for this project, which involved conducting forensic

investigations to determine the extent of cracking in one of the spillway bays, establishing the field and

laboratory investigation and testing program to test the material and strength properties of the existing

foundation and spillway monolith concrete conditions, conduct of 2 and 3-dimentional structural and thermal

analytical studies to assess the conditions of the cracked dam, preparation of mitigation designs to restore the

stability and integrity of the structure and to determine the effectiveness of those designs under static and

dynamic loading conditions. The design measures included grouting, drainage, prestressed anchors and

upgrades to the instrumentation and monitoring systems. Final solution included the installation of 61 strand

tendon post-tensioned anchors (2145 kips each) and 3-inch bar post-tensioned anchors (580 kips each) in each

monolith with a maximum added design stability force of up to 11,000,000 pounds per 65-foot wide monolith.

(2014-2015)

Page 1

Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.

Senior Technical Advisor, Dams & Hydro

Neelum Jhelum Project, Pakistan Client: WAPDA

Senior Advisor and Principal Structural Engineering reviewer of the design and analysis of the 969 MW

Neelum Jhelum Hydroelectric Project. The 45 m high diversion dam on the Neelum River will divert water

via a headrace tunnel (7.5 to 10 m diameter) into an underground powerhouse and the 3.63 km tailrace

tunnels will discharge into the Jhelum River. The total length of the headrace tunnel is 28.6 km developing a

420 m gross head. (2012-Present)

Susitna Project Watana Dam, Alaska Client: Alaska Energy Authority

Senior Advisor and Principal Structural Engineering reviewer of the design and analysis of the 715-ft high

Watana RCC Dam and 850MW surface powerhouse. (2011-Present)

Caroni Hydroelectric Projects Client: EDELCA, PortoOrdas/Caracus, Venezuela

Member Board of Review to review designs, construction management and O&M of the four projects’

(Guri, Tacoma, Caruachi, and Macagua) 17,472 MW of installed capacity of the Lower Caroni River

Project. (2009-Present)

Romaine 1, 2, 3, and 4 Hydroelectric Projects Client: Hydro Quebec, Montreal, Canada

Member Board of Review to review designs and construction management of the 640MW Romaine 2

Hydroelectric Project as part of the 4 Power Plant Romaine River Developments (1,550MW total installed

capacity). (2008-Present)

Eastmain 1A & La Sarcelle Hydroelectric Projects Client: SEBJ/Hydro Quebec, Montreal, Canada

Member Board of Review to review designs and construction management of the 768MW Eastmain 1A and

150MW La Sarcelle Hydroelectric Projects as part of the Rupert Diversion. (2007-Present)

San Vicente Dam Raise Project, U.S.A. Client: San Diego County Water Authority (SDCWA) and City of San Diego (City)

Task Leader, Principal Structural Engineer for design of 337-ft-high San Vicente RCC Dam (117-ft raise

from height of 220-ft to 318-ft) including RCC mix designs, optimization of raised design cross-section,

FEM static and dynamic stress analyses, thermal studies, instrumentation design, facing systems, galleries

and saddle dam. The project also featured two tunnels, a 9-foot diameter penetration through the existing

dam into a submerged cofferdam at the upstream face and a 17-foot tunnel and shaft beneath the raised dam

while maintaining the reservoir. (2006-Present)

Mosul Dam, Iraq Client: Ministry of Water and Energy Resources

Expert in structural engineering and earthquake analysis serving on International Panel of Experts (POE)

for Minister of Water, to provide technical review, advice, and oversight of all dam projects in operation,

under design, or investigation for planning and future development. Recommended remediation of

dam/foundation by construction of cut-off wall installed from crest of dam though the karstic foundation.

Award of contract to Bauer Construction for design and construction of world record 625 foot deep positive

cut-off wall pending final approval of Iraq Ministry of Water Resources. (2006 – Present)

Upper San Joaquin River Basin Storage Project, California, U.S.A. Client: U.S. Bureau of Reclamation

Member of Reclamation’s ten-person Value Planning Study Team of the Upper San Joaquin River Basin

Storage Investigation (USJRBSI). The estimated cost of the baseline concept was approximately

Page 1

Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.

Senior Technical Advisor, Dams & Hydro

$2,072,490.00. The maximum savings potential if the estimated savings of all the alternative design

concepts were to be accepted was $640,190,000. The cost of the study was approximately $200,000. The

main project features were proposed to be constructed at Temperance Flat and included: a main dam with an

uncontrolled spillway to pass flood flows, a powerhouse to generate electricity, and outlet works for other

controlled releases. The Temperance Flat Dam would be constructed of RCC about 640 feet high.

Upstream and downstream cofferdams would be required for river diversion. Diversion tunnels to route

river flows around the construction zone would be required during construction. A multiple-port selective

level intake structure (SLIS) would be constructed to improve management of the cold water pool in the

reservoir for releases to Millerton Lake upstream of Friant Dam. The powerhouse would have a capacity of

135 MW.

Tekeze Arch Dam and Hydroelectric Project, Ethiopia Client: Ethiopian Electric Power Corporation

Senior Advisor and Principal Structural Engineer responsible for technical review and field inspection of

project works, quarry development, aggregate processing, concrete mix designs, consolidation grouting of

foundation and finite element seismic stress analyses of a 190-m high thin-arch concrete dam. Special

studies of foundation shaping necessary to accommodate insufficient ground topography in the upper left

abutment region including rock slope stability assessment, rock reinforcement and anchor design, and

design and analysis of a combination shaping and thrust block structure to reconstitute the upper left

abutment ground contours were recommended and reviewed. Tekeze is highest arch dam on the continent of

Africa and the 300MW underground powerhouse generation output added 40% more energy to electrical

grid in Ethiopia. (2005 – 2009)

Karahjnukar Dam and Hydroelectric Project, Iceland Client: Landsvjirkjun Public Utility Corporation

Senior Advisor and Principal Structural Engineer reviewer for 200-m high CFRD (concrete-faced-rockfill

dam) in Iceland; QA review of foundations, instrumentation, design and analysis of special 40-m high

concrete gravity toe wall to resist tectonic displacements of faults existing in the foundation, RCC mix

design, and PVC water-proofing membrane. The 690MW underground power plant generates 4600GWh of

electrical energy to a nearby aluminum smelting plant. (2005 – 2008)

San Clemente Dam Remediation Project, California, U.S.A. Client: California-American Water Company

Principal-in-Charge for the feasibility engineering studies for the seismic retrofit of or removal of the San

Clemente Dam. The dam is a concrete arch constructed in 1920-1921 with a maximum structural height of

106 feet and a crest length of 300 feet. The California DSOD required that the dam owners meet dam safety

criteria to withstand the MCE and safely pass the PMF. This could be met by strengthening the dam, by

notching the dam to a level where DSOD requirements would be met, or by removing the dam. General

rehabilitation concepts, rerouting of the Carmel River into San Clemente Creek, sediment stabilization

schemes and notching or removal of the dam were developed and preliminary construction cost estimates

were prepared for each concept. (2004 – 2005)

Columbia River Off-Stream Storage Study, U.S.A. Client: USBR

Project Manager for the Columbia River Off-Stream Storage Study to identify off-stream versus on-stream

reservoir sites of 300,000 are-feet or larger for pumped storage and/or modification of existing facilities to

allow for additional storage. (2004-2005)

Page 1

Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.

Senior Technical Advisor, Dams & Hydro

Al Wehdah Dam, Jordan Client: Jordan Valley Authority

Senior Advisor and Principal Structural Engineering reviewer of the design and analysis of the 140-m high

Al Wehdah RCC Dam. (2001-2002)

Olivenhain RCC Dam, California, U.S.A. Client: San Diego Water Authority

Mr. Tarbox was Montgomery Watson Harza’s (MWH) Project Manager for the detailed design of this 318

foot high, 1.4 million cubic yard RCC gravity dam with a six level selective withdrawal I/O tower and a

stair stepped cascade spillway on the downstream face of the dam. The dam created an off stream reservoir

to provide emergency water supply to the more than 3.5 million residents of San Diego County in the event

an earthquake severs the aqueducts and pipelines that deliver water to the region. The $140 million dam is

part of the $950 million Emergency Storage Project and will be the highest RCC dam in North America

when completed and the first new RCC dam constructed in California. Included in the design were the 10-

foot diameter Lake Hodges Tunnel portal, tunnel stub and shaft for the future Lake Hodges Pumped Storage

Project. The Team was also responsible for the preparation of specifications, drawings and contract

documents for four separate construction contracts and is providing engineering services to the Authority

during construction. (1998-2003)

Big Tujunga Dam Stability Evaluation, California, U.S.A. Client: Los Angeles County Department of Public Works

Principal-in-Charge for the final design and stability evaluation of the Big Tujunga Dam, a 251-foot high

concrete arch dam. Performed seismic dynamic finite element analyses of the dam using ground motion

records modified to spectrally match a target spectrum. Developed six general rehabilitation concepts and

analyzed each concept using the finite element method. The selected concept consisted of placing RCC on

the downstream side of the existing dam that transformed the dam from a thin to a thick arch dam for

seismic strengthening and spillway modifications for hydraulic rehabilitation. (1999 – 2011)

Santa Anita Dam Re-Analysis, California, U.S.A. Client: Los Angeles County Department of Public Works

Principal-in-Charge for re-analysis of Santa Anita Dam, a 225-foot high concrete arch dam built in 1924-27.

The primary issues of concern include Alkali-Aggregate Reaction (AAR) within the dam concrete, seismic

stability to withstand the current Maximum Credible Earthquake (MCE), and hydraulic adequacy of the

existing spillway to handle updated Probable Maximum Flood (PMF). Performed an engineering/safety

inspection and investigation of the dam. Cores were obtained to assess the existing condition of the concrete

(including petrographic analysis). Design earthquakes were developed using actual ground motion records

scaled to spectrally match a target spectrum. Linear-elastic and non-linear finite element analyses were

performed to assess the seismic stability of the dam. Updated hydrologic analyses were performed to

develop inflow hydrology for evaluation of the existing spillway. (1999 – Present)

Mactaquac Dam & Generating Station, Fredericton, New Brunswick Client: New Brunswick Power Corporation,

Member Board of Review for annual review and evaluation of monitoring and mitigation programs

conducted by NB Power dealing with severe autogenous growth problems in the concrete of the head works

dam, spillways and powerhouse structures due to AAR (Alkali Aggregate Reactivity). Unprecedented

expansion due to AAR has resulted in NB Power adopting a range of measures to combat the ongoing

expansion including a regular program of saw-cutting monolith blocks in the head works adjacent to the

spillway, between generation bays in the powerhouse, and in spillway access bridge slabs, excising portions

of six penstock encasements and replacement with expansion couplings and a program of continuous

realignment of the turbine and generator shafts to accommodate out-of-round and out-of-plumb ness of the

units due to the AAR expansion. (1998-present)

Page 1

Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.

Senior Technical Advisor, Dams & Hydro

Gillespie Dam, Phoenix, AZ, U.S.A. Client: Mesch, Clark & Rothschild, P.C.

Engineering Team Leader of support services for the defense attorneys who conducted the litigation

proceedings related to the failure of Gillespie Dam. The dam is a multiple arch buttress diversion dam, 1800

feet long, rising 20 feet above a concrete apron and spanning the Gila River near Gila Bend, AZ. Services

provided included the conduct of field and laboratory testing of concrete materials, 2-D hydraulic

mathematical modeling of flood flows over the dam, 3-D finite element structural analyses of the dam and

foundation, scour studies, preparation of reports and affidavits, expert testimony and technical support

during the discovery and deposition process. (1996 to 2005)

Falcon Dam, Risk Assessment of Gas Well Drilling in Restricted Zone under Reservoir, TX, U.S.A. Client: International Boundary and Water Commission

Senior Advisor and Principal Reviewer of the risk analysis of drilling and producing natural gas from 34

wells beneath reservoir. The wells would be drilled from two pads located outside the Restricted Zone, but

would extend beneath the Restricted Zone using directional drilling. The median of the total expected value

of risk was about $1.7 million and was primarily due to surface settlement risks. The potential loss of life

from dam failure due to the proposed natural gas drilling and production was approximated and compared

with USBR guidelines for loss of life from dam failure. (2004)

Baise Multipurpose Dam Project, Guangxi, China Client: Guangxi Youjiang Water & Power Corporation (YWP)

Mr. Tarbox was MWH's Project Manager for the review of designs, operating policy, environmental impact

assessment, economic and financial analysis and alternative flood protection possibilities for the $500

million Baise multipurpose Project that includes a 130-m-high (430 ft), 2 million cubic meter, RCC dam,

two rockfill dams and a 540-MW underground powerplant. (1999-2000)

Portugues Dam, Ponce, Puerto Rico Client: Jacksonville District Corps of Engineers

Mr. Tarbox is currently providing technical review of design, constructability and construction management

for this 1,600-foot-long, 280-foot-high, concrete arch dam. Portugues Dam is the first RCC arch dam to be

designed and constructed in the U.S. or its territories. (1995-2006)

Pardee Dam and Reservoir Enlargement Project, Mokelumne Watershed, California, U.S.A. Client: East Bay Municipal Utility District

Chairman Independent Review Board charged with reviewing the District’s plans for either raising the

existing Pardee Dam or siting and constructing an entirely new dam downstream. A raised or new Pardee

dam would provide for 150,000 acre feet or more of additional storage of domestic water supply for Contra

Costa and Alameda Counties. (1996-1997)

Swan Lake Dam & Hydroelectric Project, Alaska, U.S.A. Client: Ketchikan Public Utilities

As Project Manager, Mr. Tarbox oversaw engineering and economic feasibility studies for the $120 million,

22.5-MW Swan Lake Hydroelectric Project in Ketchikan, Alaska. He also managed the FERC license

processing, final designs, preparation of contract documents and construction supervision for all features on

the project, including a 175-foot-high double-curvature, elliptical concrete arch dam, a 2,300-foot power

tunnel and a 30-mile, 115-kV transmission line. It has a free overflow spillway at the crest of the dam with a

capacity of 37,150 cfs. Swan Lake Dam was the first elliptical arch dam constructed in North America. In

addition, he managed the construction of a two-story work crew dormitory building, a vehicle shop and

maintenance building, a waste incinerator facility, a barge handling facility and dock, three year-round

Page 1

Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.

Senior Technical Advisor, Dams & Hydro

operators’ houses, a microwave telecommunications link, recreational/picnic facilities at the powerhouse, a

boat ramp and trails at the reservoir. (1979-1983)

Ertan Dam & Hydroelectric Project, China (PRC) Client: ERTAN Hydroelectric Development Corporation

As Vice President, Chief Engineer served as a senior design reviewer of the final dam design and Contract

Documents for the 3300 MW hydropower project featuring an underground powerhouse with 6

turbine/generators, a 220-meter high, double-curvature arch dam and ancillary hydraulic structures (1988-

1990).

Rocky Mountain Hydroelectric Project, Georgia, U.S.A. Client: Oglethorpe Power Corporation

Responsibilities as Chief Engineer included overall QA/QC program for the Rocky Mountain Hydroelectric

Project. He was Vice President of Engineering during the design of the project, which included an upper

reservoir ring embankment dam, eight lower reservoir dams and a 750-MW pumped storage power station.

(1988-1990)

Cowlitz Falls Dam and Hydroelectric Project, Washington, U.S.A. Client: Lewis County Public Utility District

As Principal-in-Charge, Mr. Tarbox was Vice President responsible for the overall direction of the project

during design and construction of the 145-foot-high gravity dam with four gated and one un-gated spillway

bays and 70-MW power station containing two 35 MW Kaplan turbine units. (1990-1994)

Bradley Lake Dam & Hydroelectric Project, Alaska, U.S.A. Client: Alaska Power Authority

As Principal-in-Charge, Mr. Tarbox was Vice President responsible for overall management of water

resource projects during the construction of the 125-foot high concrete-decked, rock-fill dam, 120-MW

power station, 18-mile 115 kV transmission line and a 3.4-mile, 10.8-foot diameter concrete/steel-lined

tunnel. The $355 million Bradley Lake Project was constructed in environmentally sensitive wetlands and

wildlife habitat, which required the enforcement of stringent mitigation measures in order to protect the

existing habitat. Complete living accommodations, vehicle storage and maintenance facilities, warehouses,

an airstrip and port facilities were also constructed because of the remote location of the project. (1990-

1994)

Boundary Dam, Spillway and Outlet Works Plunge Pool TDG, Washington, U.S.A. Client: Seattle City Light

Mr. Tarbox was a member of a three person Panel of Experts that provided oversight and technical reviews

of a program to study alternative project modifications to reduce the level of total dissolved gases in the

plunge pool and tailrace area of the project. The overall long-term objectives of the field, laboratory and

CFD studies were to identify operational measures and to support low level spillway sluices and upper level

radial gated spillway modifications that could be implemented to improve TDG performance of the energy

dissipating plunge pool. A 1:25 scale physical hydraulic model was constructed and a test program

conceived to develop rating curves for all flow outlets, making velocity measurements in the project tailrace

(for use in CFD model calibration), and characterizing the performance of the existing dam. The physical

model was used to examine; rating curves, trajectory, and throttled flow behavior. Computational fluid

dynamics was applied to develop a detailed examination of the expansion of flow as water exits the sluice

gates as well as examination of the jet as it interacts with the plunge pool. Successful alternatives were

selected for implementation that helped to reduce the TDG issues. (2006-2012)

Dwaar Kill Dam & Reservoir, Orange County, New York, U.S.A.

Page 1

Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.

Senior Technical Advisor, Dams & Hydro

Client: Orange County Water Authority

Mr. Tarbox was the senior staff member responsible for conceptual designs and overall quality control for a

feasibility investigation and design study of a water supply project that involved a 267-meter long

embankment dam and a 256-meter long RCC dam designed to impound a 16 million cubic meter reservoir.

(1988-1990)

Norway and Oakdale Dams Risk Assessment, Monticello, Indiana, U.S.A. Client: Northern Indiana Public Service Company (NIPSCO), (Including PFMA & Risk Assessment)

Participated in the risk assessment of two dams on the Bear River. The study was conducted by MWH with

the concurrence of FERC and under the joint leadership of Larry Von Thun and David Bowles. Key

elements of the risk assessment included a failure mode analysis for each dam, risk assessment and

evaluation of mitigation measures for the hydrological loading conditions. The results were presented to the

Federal Energy Regulatory Commission (FERC) by the Owner to illustrate the threat posed to downstream

property and lives. The Owner’s proposals for upgrading the dams were based on the results of the risk

assessment and were accepted by the FERC. (2006-07)

Bear River Dams Risk Assessment, Utah, U.S.A. Client: Utah Power & Light

Project Manager for the risk assessment of a series of dams on the Bear River. The study demonstrated an

Incremental Consequence Assessment (ICA) for the four dams, Soda Point, Grace, Oneida and Cutler. A key

element of the risk assessment included a failure mode analysis for each dam. The results were presented to

the Federal Energy Regulatory Commission (FERC) by the Owner to illustrate the threat posed to

downstream dams by upstream dams in a cascading failure scenario in probabilistic, economic and safety

terms. The Owner’s proposals for upgrading the dams were based on the results of the risk assessment and

were accepted by the FERC. (1988)

Tongue River Dam Risk Assessment, Montana, U.S.A. Client: Montana Department of Natural Resources

Project Manager for conducting a risk assessment of the 91-foot high embankment dam and free overflow

spillway. Responsible for the studies to conduct a failure mode analysis and to evaluate a number of

alternative actions to mitigate the high risk costs of property loss and threat to lives lost The risk assessment

illustrated how a risk-based comparison of several structural and non-structural alternatives can be used to

address spillway inadequacies. The evaluations were presented in probabilistic terms and also as cost-to-

save-a-life for each remedial action alternative. The risk assessment was used by the Owner to continue

operating restrictions, improve the dam break flood warning system and to seek government funding for

upgrading the dam. (1986)

Upper Stillwater Dam, Utah, U.S.A. Client: U.S. Bureau of Reclamation

As Head of the Concrete Dams Section, initiated and directed the studies for developing the concepts,

designs and cost estimates for the Bureau’s first state-of-the-art RCC dam. It is a 310 foot high gravity dam,

2670 feet long and contains 1,400,000 cubic yards of roller compacted concrete located on Rock Creek. It

was the largest RCC dam constructed at the time of its completion. (1978-1981)

Nambe Falls Dam, New Mexico, U.S.A. Client: U.S. Bureau of Reclamation

Supervisory Structural Engineer responsible for the design of the 150-foot high, 320-foot long double

curvature thin arch concrete dam located on the Rio Nambe near Santa Fe. It is a composite dam with a

concrete gravity thrust block for the left abutment of the arch dam designed to replicate the sloping canyon

topography. The thrust block is also the right abutment for a 144-foot high, 670-foot long embankment dam

that ties the composite structure to the high point of the reservoir on the left abutment. A unique scheme was

conceived to pre-stress the arch dam by installing Freysinet flat jacks over the entire surface of the central

contraction joint and then inflating them using a water/glycol mixture to expand the arch upstream against

Page 1

Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.

Senior Technical Advisor, Dams & Hydro

the reservoir. This operation resulted in locking into the arch dam a pattern of stresses at the abutments and

the crown that overcame tensile stresses due to severe winter temperatures that occur at the site. The use of

3D FEM analysis made it possible to analyze the complex combination of concrete structures and the

prestressing effects. (1976-1977)

Mountain Park Dam, Oklahoma, U.S.A. Client: U.S. Bureau of Reclamation

As Head of the Analytical Design Unit, responsible for the design and analyses of the 133-foot high double

curvature thin arch concrete dam located on the West Otter Creek River. It is 6 feet thick at the crest and 17

feet at its base. It is flanked by thrust blocks at both abutments and has a free-overflow crest spillway with

a capacity of 38,300 cfs. (1976)

Klang Gates Arch Dam Modification, Kuala Lumpur, Maylasia. Client: U.S. Bureau of Reclamation

Supervisory Structural Engineer responsible for the design and analysis of a ten-foot raise to an existing 111

foot high thick arch dam. Initiated and designed a laboratory testing program to investigate the nature of

bond strengths between new concrete and old on horizontal, sloping and vertical surfaces. The test results

led to the conclusion that it was feasible to construct the raise without extraordinary measures to ensure

bond between the raised portion of the dam and the original concrete beyond normal surface preparation

procedures (1974-1975).

Pueblo Dam, Colorado, U.S.A. Client: U.S. Bureau of Reclamation

Supervisory Structural Engineer responsible for stress analyses of the 250-foot high, 1,750-foot long

massive head buttress dam and spillway portion of Pueblo Dam located on the Arkansas River. (1970)

Coulee Forebay Dam & Hydroelectric Project, Washington, U.S.A. Client: Bureau of Reclamation

Supervisory Structural Engineer responsible for the analytical design unit that designed the 200-foot-high

gravity forebay dam in association with a 3,600-MW power station addition. The Grand Coulee Dam,

located on the Columbia River in Washington has a reservoir capacity of 9,652,000 acre-feet used for

hydroelectric power generation, irrigation and flood control. (1970)

Crystal Dam and Hydroelectric Power Station, Colorado, U.S.A. Client: U.S. Bureau of Reclamation

Senior Structural Engineer responsible for the design layouts and analytical stress analyses of the 323-foot-

high double-curvature, concrete arch dam that created a reservoir on the Gunnison River in Colorado for the

28-MW hydroelectric power station located at the toe of the dam. The dam has a crest width of 10 feet, a

base width of 29 feet and a free overflow spillway with capacity of 40,000 cfs. (1971-1972)

Auburn Dam and Hydroelectric Project, California, U.S.A. Client: U.S. Bureau of Reclamation

Design Manager for the 685-foot high, double-curvature, elliptical concrete arch dam to have been

constructed on the North Fork of the American River. Responsibilities included the development of

computer programs to analyze the reduction of uniaxial and radial jacking test data and in-situ stress

relief testing. Implemented the first applications of two dimensional finite element analysis to

determine the effective deformation modulus of the dam foundation, revised the computer program

ADSAS (Arch Dam

Stress Analysis System) to accommodate elliptical arch geometry and to perform dynamic analysis

for earthquake ground motions. The first application of the three dimensional finite element method

was introduced to analyze the dam for static and dynamic stresses. Mr. Tarbox initiated and helped to

develop a laboratory testing program to determine the rapid strain rate tensile strength and modulus

Page 1

Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.

Senior Technical Advisor, Dams & Hydro

of rupture for mass concrete that demonstrated the reserve strength of mass concrete during earthquake

loading conditions and the increase in modulus of elasticity during dynamic response. This also

marked the first time that comparisons were made for a Bureau of Reclamation designed dam

between the stresses determined by three-dimensional physical laboratory models, ADSAS and 3D

FEM. The design of the first fully automated instrumentation system for structural behavior monitoring

of a Bureau dam was also introduced and included in the specifications and drawings. (1969-1977)

AAR Investigations of Salt River Dams, Arizona, U.S.A.

Client: U.S. Bureau of Reclamation

Senior Structural Engineer responsible for developing computer programs and supporting the laboratory

and field investigation program into the deleterious effects of Alkali Aggregate Reactivity (AAR) on

Mormon Flat, Horse Mesa and Stewart Mountain Dams on the Salt River in Arizona. The procedures for

determining in-situ stresses in the dams due to AAR were developed in the laboratory using over coring

drilling techniques and computer programs to reduce and analyze the data. The results of this work led to

the eventual strengthening and remediation of Stewart Mountain Dam. (1969-1971)

Theodore Roosevelt Dam Raising, Arizona, U.S.A. Client: U.S. Bureau of Reclamation

Mr. Tarbox was a member of the Consultant Review Board responsible for review of all technical design

and construction aspects for this 280 foot gravity arch dam project located on the Salt River in Arizona

between 1986 and 1994. Modifications to the project included a 77 foot raise to the dam and construction

of a new river outlet works through the left abutment. that resulted in increased reservoir storage capacity to

2.3 million acre-feet. The intake consisted of a 19.7-foot-diameter lake-tap shaft constructed in more than

130 feet of water and a gate shaft more than 312 feet deep containing a 13-foot by 16-foot wheel-mounted

gate. Full scale field trials of concrete placed at the interface between the new concrete and the original

downstream face of the dam were confirmed by laboratory test results that adequate bond strength was

developed using conventional surface preparations such as high pressure water jets and absent any dowels

or shear pins. (1986-1996)

Xiaolangdi Multipurpose Dam Project, Henan, China Client: Yellow River Conservancy Commission Ministry of Water Resources

Mr. Tarbox served on the Xiaolangdi Dam Consulting Board, The Xiaolangdi Dam, on the Yellow River in

Henan Province, consists of a 505-foot-high earth and rockfill dam, 15 outlet and power tunnels, an intake

structure, an 1800-MW underground powerhouse and a concrete-lined plunge pool stilling basin. The

intake structure consists of ten towers with a height of 367 feet and a total volume of more than 4.4 million

cubic yards of concrete. There were three 60-foot diameter, 3,600-foot long diversion tunnels, six 25-foot

diameter power tunnels and three 39-foot wide by 62-foot high by 2,950-foot long tailrace tunnels. There

are also six 21-foot diameter posttensioned prestressed tunnels for sluicing of sediment. (1991-2000)

Green River Headworks Modifications, Washington, U.S.A. Client: City of Tacoma

Mr. Tarbox provided QA/QC for this project, which involved modifications to the headworks for the City of

Tacoma’s primary water supply source on the Green River. The project also included a 33-mile pipeline

that to enable the City to deliver a total of 290 cfs to its customers. (1995-1996)

Cedar Falls Masonry Dam Modifications, Washington, U.S.A. Client: Seattle City Light

As Project Manager, Mr. Tarbox was responsible for a feasibility assessment of the Cedar Falls masonry

dam and spillway, in preparation for rehabilitation and modifications to the project. The work at Cedar

Falls involved hydrologic studies and hydraulic sizing to pass the probable maximum flood, flood frequency

and routing studies and design of new hydraulic structures. (1981-1983)

Page 1

Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.

Senior Technical Advisor, Dams & Hydro

Wadaslingtang Dam and Hydroelectric Project, Indonesia Client: Ministry of Public Works, Jakarta

As Principal-in-Charge, Mr. Tarbox was responsible for the feasibility, design and construction management

services for the 640m long, 120m high rockfill dam and 16.5 MW hydro plant. The dam contains

266,000,000 cubic yards of material and was constructed using the “wet core” technique making it the

highest wet core dam constructed to date at that time. (1983-88)

Hydroelectric Plant Rehab and SCADA System, Alaska, U.S.A. Client: Ketchikan Public Utilities

As Program Manager, Mr. Tarbox’s was responsible for the design and construction management of the

Swan Lake Hydroelectric plant. He was also responsible for managing an extensive upgrade and

modernization program for automating and remotely controlling generating and electrical systems at

Ketchikan’s four hydroelectric and two diesel plants. This involved an automation study, a communications

study and the development of plans and specifications for a new, fully redundant SCADA system with a

combination microwave/VHF communications. All new switchgear, electronic governors, motor operated

butterfly control valves, fire suppression systems, generator cooling systems and new plant HVAC systems

were designed and managed during construction. An uninterruptible power supply system was designed to

support the monitoring and control system at all plants. (1979-1983)

Boundary Dam Seismic Hazard Assessment and Dynamic Analysis, Washington, U.S.A.

Client: Seattle City Light

As Project Manager and Concrete Dam Specialist, Mr. Tarbox was responsible for management of a study

to determine the seismic hazard for this 340-foot-high concrete arch dam on the Pend Orielle River in

Washington. The study included a static and dynamic stress analysis of the dam, assessment of the stability

of the reservoir rim, an evaluation of the dam for overtopping in the event of a reservoir landslide,

foundation subsurface investigations, installation of piezometers and evaluation and analysis of strainmeter

instrumentation data for the dam. (1984-1985)

Green Lake Dam & Hydroelectric Project, Alaska, U.S.A. Client: City and Borough of Sitka

Mr. Tarbox, as Head of the Design Department, was responsible for the 16.5-MW Green Lake

Hydroelectric Project to help the City and Borough of Sitka meet its expanding energy needs. The project

included a 210-foot-high, double-curvature concrete arch dam on the Vodopad River, a 64,000-acre-foot

reservoir, a 2,000-foot power tunnel, a 16.5 MW powerhouse, a switchyard, 7 miles of new 69-kV

transmission line and an access road. (1979-1981)

American Falls Dam Replacement Project, Idaho, U.S.A. Client: U.S. Bureau of Reclamation

Supervisory Design Engineer for the $80 million replacement dam. Responsible for analytical design

studies that led to the decision to replace the original dam due to severe deterioration from AAR (Alkali

Aggregate Reactivity). The project included a dam 98-feet high and 1,200 feet long with a 600-foot long

central concrete gravity section. (1974-1976)

Curecanti-Hayden Transmission Line, Colorado, U.S.A. Client: U.S. Bureau of Reclamation

As Field Engineer, Mr. Tarbox was responsible for inspecting the foundation installations and steel tower

erection on the construction of the 170-mile, 230-kV Curecanti-to-Hayden, Colorado transmission line.

(1964)

Flaming Gorge Dam and Hydroelectric Project, Utah, U.S.A.

Page 1

Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.

Senior Technical Advisor, Dams & Hydro

Client: U.S. Bureau of Reclamation

Mr. Tarbox, as Field Engineer, was a field inspector for the 502-foot-high concrete arch dam and its. 26-

foot-diameter spillway tunnel. The dam is located on the Green River and impounds a reservoir of

3,788,900 acre-feet for hydroelectric power generation through its 108-MW power station (1961-1964)

FERC Part 12 Periodic Safety Inspections

Soda Point Dam, Grace Dam, Oneida Dam and Cutler Dam & Hydroelectric Projects Client: Utah Power & Light, Bear River, Utah, U.S.A.

Clark Fork Project -Cabinet Gorge Dam, Spokane, WA, U.S.A. Client: Avista Utilities

Priest Rapids Dam & Wanapum Dam & Hydroelectric Projects, Ephrata, WA, U.S.A. Client: Grant County PUD

Rock Island Dam, Rocky Reach Dam and Lake Chelan Hydroelectric Projects, Wenatchee, WA,

U.S.A.

Client: Chelan County PUD

Monroe and Columbus Hydroelectric Projects, Nebraska, U.S.A. Client: Loup Power District

Claytor Dam Project Client: American Electric Power

Cowlitz Falls Dam & Hydroelectric Project, Chehalis, WA, U.S.A. Client: Lewis County PUD.(Including PFMA)

Cooper Lake Dam & Hydroelectric Project, Kenai Peninsula Borough, AK, U.S.A.

Client: Chugach Electric Association, Inc.(Including PFMA)

Upper and Lower Baker River Dams, Whatcomb County, WA, U.S.A. Client: Puget Sound Energy, Inc.(Including PFMA)

Boundary Dam, Pend Orielle, WA, U.S.A.

Client: Seattle City Light,(Including PFMA)

Ross Dam, Diablo, WA, U.S.A. Client: Seattle City Light,(Including PFMA)

Diablo Dam, Diablo, WA, U.S.A. Client: Seattle City Light,(Including PFMA)

Gorge Dam, New Halem, WA, U.S.A. Client: Seattle City Light,(Including PFMA)

Foothills Project (Strontia Springs Dam), Denver, CO, U.S.A. Client: Denver Water Board, (Including PFMA)

Page 1

Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.

Senior Technical Advisor, Dams & Hydro

Norway and Oakdale Hydroelectric Project, Monticello, Indiana, U.S.A.

Client: Northern Indiana Public Service Company (NIPSCO), (Including PFMA & Risk Assessment)

Salmon Creek Hydroelectric Project, Juneau, AK, U.S.A. Client: Alaska Electric Light & Power

Cushman #1 and #2 Hydroelectric Project, Tacoma, WA, U.S.A. Client: Tacoma Power, (Including PFMA)

Lake Spaulding Dams No. 1, 2, & 3, Nevada County, CA, U.S.A. Client: Pacific Gas & Electric, (Including PFMA)

FERC Dam Breach and EAP (Emergency Action Plan) Preparation Client: Ketchikan Public Utilities, Ketchikan, AK

Beaver Falls/Lake Silva, Ketchikan Lakes and Swan Lake Hydroelectric projects (1981) Client: Ketchikan Public Utilities, Ketchikan, AK

Jackson Bluff Hydroelectric Project (1982), FL, U.S.A Client: City of Tallahassee

Safety Evaluation of Existing Dams (SEED) Program Client: U.S. Bureau of Reclamation

As Assistant Chief, Dams Branch Mr. Tarbox managed the inaugural dam safety program known as SEED

for more than 355 Reclamation dams, 300 embankment dams and 55 concrete dams. The policies, practices,

publications and procedures initiated in that period were the foundation of what has become the Bureau’s

SOD (Safety of Dams) and TADS (Training Aids for Dam Safety) Program. (1978-1979)

Dam Safety Training and Evaluation Program Client: NIA (National Irrigation Administration) Manila, Philippines

PRC Engineering conducted a five-month dam safety training and evaluation program in the Philippines for

the National Irrigation Administration. The U.S. Team:

Developed a manual which outlined the organization, procedures, technical expertise and other

resources required to implement a dam safety program

Trained the staff in all aspects of performing dam safety monitor in, interpretation, inspection,

evaluation and report preparation

Inspected eight dams: Magat, Baligatan, Maris, Pantabangan, Aya, Masiway, Canili and Mayo, and

inspected the Magat and Pantabangan power plants

Updated an operation and maintenance manual for the Magat Dam and Power Plant Project

Prepared an operation and maintenance manual for the Pantabangan Dam and Power Plant Project

Prepared dam safety reports for each structure

Mr. Tarbox participated on the Team as a lecturer on dams and appurtenant structures during the training

program and he was on the dam inspection team for the eight dams which were used as a field laboratory for

instructing the Philippine engineers in how to conduct onsite safety inspections. (1986)

Dam Safety Inspection Program Client: EGAT (Electricity Generating Authority of Thailand) Bangkok, Thailand (1984-85)

PRC Engineering conducted a comprehensive dam safety inspection program for the eight dams operated

by EGAT. The program included a preliminary evaluation of EGAT's existing dam safety program, a review

Page 1

Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.

Senior Technical Advisor, Dams & Hydro

of design and operation and maintenance data for the dams, a site inspection of each dam and its facilities,

and an evaluation of the need for further investigations and remedial actions. The following table lists the

dams inspected under the program:

Name of Dam

Type

Height (feet)

Crest Length

(feet(

Hydropower

Capacity

(megawatts)

1. Bhumibol Concrete Arch 502 1,595 420

2. Sirikit Earthfill 358 2,494 375

3. Chula Bhorn Rockfil1 230 2,638 40

4. Kang Krachan Earthfill 190 2,494 19

5

.

Sirindhorn

Rockfill

157

3,101

24 6.

Nam Pung Rockfill 131 2,490 6

7.

Jbul Ratana Rockfill 105 2,641 25

8.

Sringrind Rockfill 463 2,015 360

Value Engineering (VE) Team Assignments Client: US Army Corps of Engineers (2006)

The VE Study considered the Integrated Federal Alternative (IFA) developed by the Folsom Dam Raise and

Auxiliary Spillway Alternative Project Alternative Solutions Study (PASS) II, as described in the Draft Final

Report, April 2006.

Client: BC Hydro (2009)

The VE Study considered the seismic retrofit design of the Ruskin Powerhouse, switchyard, power intakes,

turbine-generators and ancillary equipment, power tunnel, penstocks and draft tube gates.

PUBLICATIONS

Author or Co-author of the following:

1. "Deformation Moduli Determined by Joint-Shear Index and Shear Catalogue; Symposium of the

International Society for Rock Mechanics, Nancy, France, 1971.

2. "Beneficiation of Auburn Dam Foundation", ASCE National Water Resources Engineering

Meeting, Washington, D.C., 1973.

3. "Bureau of Reclamation's Design Criteria for Concrete Arch and Gravity Dams - 1975".

Proceedings for International Symposium on Criteria and Assumptions for Numerical Analysis of

Dams, Swansea, U.K., 1975.

4. "Auburn to the Longest Thin Arch Dam", USCOLD Newsletter, Issue No. 47, New York, 1975.

5. "Design of Gravity Dams", U.S. Bureau of Reclamation, Denver, Colorado, 1975.

6. "Design of Arch Dams, U.S. Bureau of Reclamation, Denver, Colorado, 1977.

7. "Design and Analysis of Auburn Dam", U.S. Bureau of Reclamation, Denver, Colorado, 1977.

Page 1

Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.

Senior Technical Advisor, Dams & Hydro

8. "Auburn Dam Instrumentation", joint U.S.A.-U.S.S.R. Seminar on the Design and Construction of

Large Dams in Seismically Active Areas, Hydraulic Institute, Moscow, U.S.S.R., 1977.

9. "Earthquake Design and Analysis of Concrete Dams", joint U.S.A.-U.S.S.R. Seminar on the

Design and Construction of Large Dams in Seismically Active Areas, Hydraulic Institute, Moscow,

U.S.S.R., 1977.

10. "Design of Concrete Dams", Chapter 8, Handbook of Dam Engineering, Van Nostrand Reinhold,

New York, 1977.

11. "Critical Aspects in Design Practice of Concrete Dams", Research Conference on Earthquake

Engineering, Skopje, Yugoslavia, 1980.

12. "Swan Lake Hydroelectric Projects, USCOLD Newsletter, Issue No. 64, New York, 1981.

13. "Small Scale Hydroelectric Projects in Alaska", ASCE Conference Proceedings for Applying

Research to Hydraulic Practice, Jackson, Mississippi, 1982.

14. "Narnbe Falls Dam Flat Jack and Grout Tests", U.S. Bureau of Reclamation, REC-ERC-77-16,

Denver, Colorado, 1977.

15. "Seismic Analysis of Concrete Dams" - Proceedings 13th International Congress on Large Dams,

New Delhi, India, 1979.

16. "Planning, Design and Cost Estimates for RCC Dams" - Proceedings ASCE Specialty Conference,

Roller Compacted Concrete id, San Diego, California, 1988.

17. "Gravity Dam Design and Analysis, "Advanced Dam Engineering for Design. Construction and

Rehabilitation. Van Nostrand Reinhold, New York City, New York 1988.

18. “Arch Dam Design and Analysis", Advance Dam Engineering for Design. Construction and

Rehabilitation Van Reinhold, New York City, New York 1988.

19. "Wet Core Construction (WCC) Technology for Embankment Dams" - Proceedings 16th

International Congress on Large Dams, San Francisco, C.19, San Francisco, CA, 1988.

20. "Pre-Stressing an Arch Dam by Forced Opening of the Joints" - Proceedings International

Workshop on Arch Dams, Coimbra, Portugal, April 1987.

21. “Dam Safety Evaluation for a Series of Utah Power and Light Hydropower Dams, Including Risk

Assessment: Work Plan, Project Description, Remedial Action,” ASDSO Annual Conference,

Albuquerque, New Mexico, October 1-5, 1989.

22. "Safety Assessment of Existing Dams for Earthquake Conditions", Volume C-4 Seismic Analysis

of Concrete Dams, Canadian Electrical Association Research and Development, Report No. 420 G

547, 1990.

23. "Evaluation of Dam Safety at a Series of Hydropower Dams Including Risk Assessment"

-Proceedings of the 6th Conference: The Embankment Dam, University of Nottingham, England,

sponsored by the British Dam Society, 1990.

24. "Roller-Compacted Concrete Dams", Chapter 10 Preliminary Design and Cost Estimates, Roller-

Compacted Dams, 1991.

Page 1

Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.

Senior Technical Advisor, Dams & Hydro

25. "PC Numerical Analysis of Talvacchia Arch Dam", First Benchmark Workshop on Numerical

Analysis of Dams, Bergamo, Italy, sponsored by ICOLD, 1991.

26. "Definition of Critical Thermal States in Arch Dams - A Prerequisite for Cracking Analysis"

Proceedings for the International Conference on Dam Fracture, Denver, Colorado, 1991.

27. "Safety Assessment of Existing Dams for Earthquake Conditions Part III - Seismic Analysis of

Concrete Dams", Part III - Seismic Analysis of Concrete Dams, Proceedings of the 3rd Canadian

Earthquake Engineering Conference, Vancouver, B.C., 1991.

28. "Opening Address", International Conference on Dam Fracture, Boulder, Colorado, 1991.

29. "Examples of Risk Assessment in Dam Safety Decision-Making", Proceedings of Waterpower '91,

Denver, Colorado

30. "A Seismic Screening Procedure for Concrete Gravity Dams" - Proceedings of the Association of

State Dam Safety Officials Annual Conference, Baltimore, Maryland 1992.

31. "Examples of Using Risk Assessment for Dam Safety Decision Making", XXV Congress of the

International Association For Hydraulic Research, Tokyo, Japan, 1993

32. "Innovation, The Spirit of Engineering", the Inaugural Jack Hilf Lecture, University of Colorado,

Boulder, 1993.

33. "Theodore Roosevelt Dam Modification," Proceedings 18th International Congress on Large

Dams, Durban, South Africa, 1994.

34. "Roller-Compacted Mass Concrete - ACI 207.5R-93," ACI Committee 207, American Concrete

Institute, Detroit, Michigan, 1997.

35. “Statewide Review of Headworks Dams: Status, Risks, Future Business Focus and Approach to

Regulation," Proceedings 19th International Congress on Large Dams, Florence, Italy, 1997.

36. “The Role of a Panel of Experts in the Enhancement of Safety,” Proceedings of the International

Symposium on New Trends and Guidelines on Dam Safety, Barcelona, Spain, June 1998.

37. “Seismotectonic Design for the Olivenhain Dam,” Proceedings 22nd

Annual USSD Conference,

San Diego, CA, June 2002.

38. “Design of Roller-Compacted Concrete Features for the Olivenhain Dam,” Proceedings 22nd

Annual USSD Conference, San Diego, CA, June 2002.

39. “Supplementary Olivenhain Dam Trial Mix Program,” Proceedings 22nd

Annual USSD

Conference, San Diego, CA, June 2002.

40. “Structural Design Optimization for the Olivenhain RCC Dam,” Proceedings 22nd

Annual USSD

Conference, San Diego, CA, June 2002.

41. “Olivenhain Dam Design,” Proceedings PCA Seminar on RCC, San Diego, CA, August 2002.

42. “RCC for the Heightening of San Vicente Dam,” International Journal of Hydropower & Dams,

October, 2003.

Page 1

Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.

Senior Technical Advisor, Dams & Hydro

43. “Design and Construction of the Olivenhain RCC Dam,” ASDSO Conference, Minneapolis, MN,

September 2003.

44. “Design and Construction of an Exposed Geomembrane System for the Olivenhain Dam,” USSD

Annual Meeting and Conference, Salt Lake City, UT, June 2005

45 “Exposed Geomembrane Liner Minimizes Seepage at Olivenhain,” The International Journal on

Hydropower & Dams, Volume Twelve, Issue 4, 2005.

46 “Value Engineering at Olivenhain RCC Dam, USA,” Proceedings 22nd International Congress on

Large Dams, Barcelona, Spain, 2006.

47 “Designing the Tallest RCC Dam Raise for San Vicente Dam in Southern California,” Proceedings 5Th

International Symposium on RCC Dams, Guiyang, China, November, 2007.

48 “Big Tujunga Dam Seismic Rehabilitation and Spillway Modification Project,” Proceedings

USSD 28th

Annual Meeting and Conference, Portland, Oregon, April/May, 2008.

49 “Special Issues of Interface Design, Drainage, and Facing Systems for Raising San Vicente Dam,”

Proceedings 23rd International Congress on Large Dams, Brazilia, Brazil, 2009.

50 “Structural Design Optimization with Raising San Vicente Dam,” Proceedings 23rd International

Congress on Large Dams, Brazilia, Brazil, 2009.

51 “Foundation Challenges for Raising San Vicente Dam,” Proceedings 23rd International Congress on

Large Dams, Brazilia, Brazil, 2009.

52 “FEA Optimization of Rehabilitation Design for Big Tujunga Dam,” Proceedings 23rd

International Congress on Large Dams, Brazilia, Brazil, 2009.

53 “Staged Construction Thermal Analysis for San Vicente Dam Raise Project,” Proceedings USSD 29th

Annual Meeting and Conference, Nashville, Tennessee, April, 2009.

54 “Dynamic Characterization of San Vicente Dam,” ASDSO Dam Safety 2009, Hollywood, Florida,

September/October, 2009.

55 “Structural Design for San Vicente Dam Raise,” Proceedings USSD 30th

Annual Meeting and

Conference, San Diego, California, April 2011.

56 “Bracing for Impact at Big Tujunga Dam,” International Water Power & Dam Construction,

December, 2011.

57 “The Seismic and Hydraulic Rehabilitation of Big Tujunga Dam,” ASDSO Dams Safety Journal,

May 2012.

58 “Reaching New Heights at San Vicente,” International Water Power & Dam Construction, July

2013.

59 “Maintaining the Reservoir at Salmon Creek Dam; Evaluation of a 99-Year Old Constant Angle

Arch Dam,” Proceedings ICOLD 2013, Seattle, Washington, August 2013.

60 “Dams of the United States - A Pictorial Display of Landmark Dams,” U.S. Society on Dams, 81st

Annual Meeting of ICOLD, Seattle, Washington, August 2013 (Technical Editor).

Page 1

Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.

Senior Technical Advisor, Dams & Hydro

61 “Achievements and Advancements U. S. Dam Engineering,” U.S. Society on Dams, 81st

Annual

Meeting of ICOLD, Seattle, Washington, August 2013 (Technical Editor).

62 “Current Seismic Tools Used to Evaluate a 1914 Concrete Arch Dam,” Proceedings USSD 34th

Annual

Meeting and Conference, San Francisco, California, April, 2014.

63 “Investigating The Structural Safety of Cracked Concrete Dams,” CEATI International, Generation

Dam Safety Program, Report No. T122700-0226, Montreal, Quebec, Canada, January 2015.

64 “Why Would You Drill Holes in My Dam,” Proceedings ASDSO Dam Safety Meeting, New Orleans,

Louisiana, September, 2015.

65 “Design and Construction of the Upstream Geomembrane Facing System for the San Vicente RCC

Dam Raise,” Proceedings ASDSO Dam Safety Meeting, New Orleans, Louisiana, September, 2015.

66 “Using The Trial Load Method To Optimize The Feasibility Design of Watana Dam,” Proceedings

36th Annual USSD Conference, Denver, Colorado April, 2016.

67 “Post-Construction Coring Evaluation for RCC at the San Vicente Dam Raise Project,” Proceedings

ASDSO Dam Safety Meeting, Philadelphia, Pennsylvania, September, 2016.

68 “Investigating the Structural Safety of Cracked Concrete Dams,” Proceedings USSD 37th Annual

Meeting and Conference, Anaheim, California, April, 2017.

69 “Understanding the Performance of Aging Infrastructure: A 99-Year Old Multiple Arch Dam,”

Proceedings USSD 37th Annual Meeting and Conference, Anaheim, California, April, 2017.

70 “Total Rehab – Notching Santa Anita Dam,” Proceedings USSD 37th Annual Meeting and Conference,

Anaheim, California, April, 2017.

71 “The Emergency and Carryover Storage Project Creates a Lasting Legacy for Water Reliability in San

Diego, California,” Proceedings, ANCOLD/NZSOLD 2016 Conference, “Dams A Lasting Legacy,”

Adelaide, Australia, October 2016.

72 “RCC Post Construction Core Testing and Data Analysis for San Vicente Dam Raise Project,”

Proceedings USSD 37th Annual Meeting and Conference, Anaheim, California, April, 2017.

Page 1

Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.

Senior Technical Advisor, Dams & Hydro

AWARDS

U.S. Bureau of Reclamation: Meritorious Service - Quality Increase 1968

U.S. Bureau of Reclamation: Meritorious Service - Special Achievement 1970

U.S. Bureau of Reclamation: Meritorious Service - Outstanding Performance and Quality Increase 1976

University of Maryland: Centennial Medal of Engineering 1994

Top 20 Individuals: International Water Power & Dam Construction (IWP&DC): Recognized by the

Editorial Board and industry experts from around the world as one of the top 20 individuals having made

the biggest difference in the dam sector, Influencing Engineering, IWP&DC, January 2011.

Lifetime Achievement: USSD (United States Society on Dams): Awarded the 2011 USSD Lifetime

Achievement Award for outstanding contributions to the dam engineering profession, San Diego, California,

April 13, 2011.

Legacy Award 2016 Northwest Region: ENR (Engineering News Record): Awarded the Northwest

Regional Legacy Award for accomplishments in the engineering and construction industry for dams and

hydroelectric projects. His lifetime of contributions to dam design, safety, and construction, as well as to the

global community of engineers merited Glenn the ENR Legacy Award. His groundbreaking design and

technology work – on everything from the trial-load and finite element analysis methods for arch dams in his

early days at the U.S. Bureau of Reclamation to modern designs of roller compacted concrete (RCC) dams–

have helped set the industry standards for dams and hydro projects around the world.

Project Manager, Parsons/Harza JV, Olivenhain RCC Dam – Owner San Diego County Water

Authority/Olivenhain Municipal Water District:

Charles J. Pankow Jr. Award, So. California Chapter of ACI, November 11, 2003

Project of the Year Award, APWA, November 9, 2004

Outstanding Civil Engineering Water Project, Council of the California ASCE, 2004

Project of the Year Award, APWA, September 12, 2005

Excellence in Environmental Engineering Honor Award, American Academy of Environmental

Engineers, 2005

Opal Civil Engineering Award of Merit, ACSE, 2005

Milestone RCC Project 1987-2007, 5th

International Symposium on RCC Dams, Guiyang, China,

2007

Lead Dam Design, MWH Americas, Inc.: San Vicente RCC Dam Raise Project– Owner San Diego

County Water Authority/City of San Diego:

APWA Public Works Projects of the Year, Anaheim, CA, August 2012.

ASCE (American Society of Civil Engineers – San Diego Section) – 2016 Project of the Year

Award - Dams & Reservoirs

Page 1

Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.

Senior Technical Advisor, Dams & Hydro

USSD Award of Excellence in the Constructed Project, San Vicente RCC Dam Raise Project,

D e n v e r , CO, April 2016.

CMAA (Construction Management Association of America – San Diego Chapter) – 2016 Project

Achievement Award – Public Works >$15 million

Principle-in-Charge and Lead Dam Design, MWH Americas, Inc.: Big Tujunga Seismic Rehabilitation

and Spillway Modification Project – Owner Los Angeles Department of Public Works:

ASDSO National Rehabilitation Project of the Year Award, Washington D.C., 2011.

ENR Best Projects – Best Civil Works, Big Tujunga Seismic Retrofit, San Francisco, CA,

December 2011.

USSD Award of Excellence in the Constructed Project, Big Tujunga Dam Seismic Rehabilitation

and Spillway Modification Project, New Orleans, LA, May 2012.

APWA Public Works Projects of the Year, Anaheim, CA, August 2012.

Project Manager, MWH Americas, Inc.: Independent Technical Review (ITR) of Portugues RCC Thick

Arch Dam – Owner U.S. Army Corps of Engineers:

3rd International Milestone RCC Dam Project, 7th International Symposium on Roller Compacted

Concrete (RCC) Dams, Chengdu, China Sept. 24 -25, 2015

ENR (Engineering News Record) 2016 Global Best Project – Water/Wastewater Award of Merit for

Emergency & Carryover Storage Project, San Diego County Water Authority

Project Manager/Lead Dam Designer, MWH Americas Inc.: Olivenhain RCC Dam and Lead

Dam Designer, San Vicente RCC Dam Raise features of the E&CS Project.

LANGUAGE

English (Excellent); Spanish (Poor)

OVERSEAS ASSIGNMENTS

Canada, Australia, China, Indonesia, Philippines, Taiwan, Pakistan, India, Sri Lanka, Panama, Venezuela,

Peru, Argentina, Chile, Colombia, Ecuador, Greece, Turkey, Jordan, Egypt, Ethiopia, Lesotho, Iceland,

Jordan and Iraq

Page 1

Glenn S. Tarbox, P.E., F. ASCE, S.E.C.B.

Senior Technical Advisor, Dams & Hydro

EMPLOYMENT HISTORY:

2016 to Present MWH now part of Stantec, Bellevue, Washington, U.S.A. Senior Technical Advisor, Dams & Hydro, Dams & Water Power, MWH now part

of Stantec, Inc.

2011 to 2016 MWH Americas, Bellevue, Washington, U.S.A. Senior Vice President, Global Dams Practice Leader, MWH Americas, Inc.

2010 to 2011 MWH Americas, Bellevue, Washington, U.S.A. Vice President, Dams Practice Leader, MWH Americas, Inc.

2003 to 2010 MWH Americas, Bellevue, Washington, U.S.A. Vice President, Principal Structural Engineer, Dams and Hydropower

2001 to 2003 MWH E&I, Bellevue, Washington/Chicago, Illinois, U.S.A. Vice President, Group Manager, Global Hydropower

1998 to 2001 Harza Engineering Company, Bellevue, Washington, U.S.A. Managing Partner, Hydropower Business Unit

1997 to 1998 Harza Engineering Company, Bellevue, Washington, U.S.A. President, Western Division

1994 to 1997 R. W. Beck, Inc., Seattle, Washington, U.S.A. Vice President and Director of Infrastructure Services

1992 to 1994 Bechtel Corporation, San Francisco, California, U.S.A. Vice President, Manager of Engineering and Construction Technology,

R & D Group

1990 to 1992 Bechtel Corporation, San Francisco, California, U.S.A. Vice President, Manager of Water Resources,

1988 to 1990 Harza Engineering Company, Chicago, Illinois, U.S.A. Vice President, Chief Engineer

1983 to 1988 ECI (Engineering Consultants, Inc.), Denver, Colorado, U.S.A.

Senior Vice President of Engineering

1979 to 1983 R. W. Beck and Associates, Seattle, Washington, U.S.A.

Associate and Head of the Design Department

1961 to 1979 U.S. Bureau of Reclamation, Denver, Colorado, U.S.A. Assistant Chief, Dams Branch

Head, Concrete Dams Section

Supervisor, Analytical Design Unit

Construction Inspector, Flaming Gorge Dam & Hydropower Project