TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARD Procurement: Planning and Processes Procurement: Planning and Processes 29 th April, 2014

TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARD

Procurement: Planning and ProcessesProcurement: Planning and Processes

29th April, 2014

Page 2: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

Contents

1 Background

2 Stages of Procurement

3 Details of Tender Documents

2

Page 3: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

Background (1/2)

TN Transparency in Tenders Act and Rules

TNIDB Act: All projects above Rs. 500 cr and all PPP projects

above Rs.10 cr

3

above Rs.10 cr

� TN Transparency in Tenders (PPP) Rules, 2012

� All PPPs above Rs.25 lakh

Page 4: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

Background (2/2)

Single Stage vs. Multi-stage tendering

Multi-stage tendering

Two compulsory

stages

Two optional

stages

4

stages

Request for

Qualification (RfQ)

Request for Proposal

(RfP)

stages

Request for Expression

of Interest (REOI)

Request for Technical

Proposal (RTP)

TNTIT Act does not preclude these stages in non-PPP projects

1

2

1

2

Page 5: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

Step 1Formation of Tender Inviting Authority (TIA), the Tender

Scrutiny and Evaluation Committee (TSEC) and the

Tender Accepting Authority (TAA) [MANDATORY]

Preparatory Stage (1/4) Stage I

Tender Scrutiny and Evaluation Committee obligatory

for each stage of procurement and will include:

� Head of the Procuring Entity or nominee

(Rule 7, TNTIT PPPP Rules 2012 and Section 7 , TNTIT Act 1998)

Step 2 Engaging Consultants or Advisors [OPTIONAL]

� Head of the Procuring Entity or nominee

� Secretaries of the Administrative Department, Law

Department, Finance Department or nominees

� Representative of the TNIDB where required

� Up to 3 Experts

© Tamil Nadu Infrastructure Development Board5

(Rule 8, TNTIT PPPP, 2012)

Page 6: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

Step 3Procurement Process Modalities – Single stage vs. Multi-

stage process

Procurement

Options

How well defined is the

project?

Factors to be Considered

How well are the bidders defined?

How much work will the proposals

require?

Single Stage : RFP �Project scope is clear Number of interested bidders is limited.

Preparatory Stage (2/4) Stage I

(TNTIT PPPP Rules 3, 4, 5,6)

Single Stage : RFP �Project scope is clear

�Service options have

been well defined

Number of interested bidders is limited.

Potential bidders are known and identified

It is not necessary to identify interested

bidders or to reduce their number

Multi-Stage Option

1: RFQ +RFP

(With/Without

RTP)

�Project scope is not

clear

�Extensive discussions

are needed to finalise

service options

Potential bidders are known and

identified, but the number of interested

bidders is large

Considerable effort required by bidders to

submit proposals

In this case, RFQ is use to reduce the

number of bidders

© Tamil Nadu Infrastructure Development Board6

Page 7: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

Step 3Procurement Process Modalities – Single stage vs. Multi-

stage process (continued…)

Procurement

Options

How well defined is

the project?

Factors to be Considered

How well are the bidders defined?

How much work will the proposals require?

Multi-Stage

Option 2: EOI

+RFP

Project scope is not

clear

Extensive

Number of interested bidders likely to be limited,

but potential bidders not yet well known or

identified

Preparatory Stage (3/4)Stage I

+RFP

(With/Without

RTP)

Extensive

discussions are

needed to finalise

service options

identified

Considerable effort required by bidders to submit

proposals .

In this case EOI is useful to identify useful bidders.

Multi-Stage

Option 3: EOI

+RFQ+RFP

(With/Without

RTP)

Project scope is not

clear

Extensive

discussions are

needed to finalise

service options

Uncertainty about the level of interest in the

project – unknown if interest is limited or large

potential bidders not yet well known or identified

Considerable effort required by bidders to submit

proposals.

In this case, EOI is useful to identify interested

bidders and level of interest; RFQ is useful to

reduce the number of bidders

© Tamil Nadu Infrastructure Development Board 7

Page 8: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

Step 4 Preparation of Bidding Documents

Preparatory Stage (4/4)Stage I

� TNIDB to prescribe standard tender documents

� Model tender documents and model draft concession

agreements for PPP projects prepared by Union Planning

Commission may be used

Step 5Approval of Bidding Documents and Draft Concession

Agreement by TSEC

© Tamil Nadu Infrastructure Development Board 8

Page 9: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

Step 1 Submission and Approval of Bidding Documents

Approval of Tender Documents & Draft

Concession Agreement by TNIDBStage II

The sponsoring agency may with prior concurrence of the

Board may issue a REOI at any time

Approval For Approving Authority

Approval of

Tender

Documents

and Draft

Concession

Agreement

EC: For Projects exceeding Rs. 1,000

crore

SC: For Projects up to Rs. 1,000 crore

CEO: For Projects up to Rs. 100 crore

© Tamil Nadu Infrastructure Development Board9

(Source: Delegation of Powers to Executive Committee/Sub-committee/Chief Executive

Officer)

Page 10: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

Publication of Notice Inviting Tenders – Notice Boards and Websites

Notice Inviting Tenders Stage III

Project Value > Rs. 50

crore

�To be published in

Indian Trade Journal

�Director of Information

and Public Relations is

the Competent authority

for release of tender

Project Value > Rs. 50

lakh

�Notice Inviting

Tenders to be

published as per the

instructions of the

Procuring Entity

Project Value > Rs. 200

crore

�Notice Inviting Tenders

shall be published once

every week for 3

consecutive weeks in

atleast 2 national

newspapers (one for release of tender newspapers (one

financial/business) and

one local newspaper in

the project district/city

Supply of Tenders

�To be made available in both soft and hard copies

�Payment mechanism adopted should be feasible for both download and purchase from

offices of the procuring entity or Tender Inviting Authority

© Tamil Nadu Infrastructure Development Board

10

(TNTIT PPPP Rules 11)

Page 11: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

Key points to be considered

Record of Tender

ProceedingsConflict of Interest Confidentiality

Bid Process StageStage IV

REOI RFQ RTP RFP

A B C D

© Tamil Nadu Infrastructure Development Board11

Page 12: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

Issue of REOIStep 1

Pre-submission

MeetingStep 2

The REOI should have

a) Basic project details

b) Request for Expression of Interest

c) Closing date for seeking

clarifications

The Pre-submission meeting

convened should be held at least 7

Request for Expression of InterestStage IV-

A

MeetingStep 2

Submission of REOIStep 3

convened should be held at least 7

days before the due date and

clarifications on the queries should

be issued not less than 4 days before

the due date

The due date should ordinarily be

not less than 30 days from the date

of advertisement or notification of

the REOI whichever is later

© Tamil Nadu Infrastructure Development Board12

Page 13: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

Issue of RFQStep 1

Pre-Submission

MeetingStep 2

Pre-submission meeting – 3 weeks

before due date

Issue of clarifications – not less than 1

week before due date

Notifications in RFQ – not less than 1

week before due date

Request for Qualifications (1/2)Stage IV-

B

Submission of RFQStep 3

Removal of Conflict of

InterestStep 4

week before due date

The due date should ordinarily be not

less than 30 days from the date of

advertisement or notification of the

RFQ whichever is later

Within 10 days after the due date, an

applicant can be allowed by the

procuring entity to remove an

member who suffers from a Conflict

of Interest

© Tamil Nadu Infrastructure Development Board13

Page 14: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

Evaluation of

ApplicationsStep 5

Notification of

� Evaluation by TSEC

� Assessment on basis on the

pre-specified minimum pass

or fail threshold

� Notification to each

Request for Qualifications (2/2)Stage IV-

B

Notification of

QualificationsStep 6

� Notification to each

applicant whether

qualified or not qualified

� TAA can decide not to

proceed if the number of

qualified applicants is

inadequate

© Tamil Nadu Infrastructure Development Board14

Page 15: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

Suitable for

projects that

are technically

complex –

Issue of RTP to all applicants

found qualified in the RFQ

Stage

Step 1

Step 2 Pre-submission meeting

Request for Technical Proposal (1/2)Stage IV-

C

complex –

Should be

issued before

issuance of RFP

Step 2 Pre-submission meeting

Pre-submission meeting – 3

weeks before due date

Issue of clarifications – not less

than 1 week before due date

Notifications in RFQ – not less

than 1 week before due date

© Tamil Nadu Infrastructure Development Board15

Page 16: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

Technical EvaluationStep 3

Request for Technical Proposal (2/2)Stage IV-

C

� Evaluation by TSEC

� Assessment on basis on the

pre-specified minimum pass

or fail threshold

� Notification to each Step 4 Notification to Applicants

� Notification to each

applicant whether

qualified or not qualified

© Tamil Nadu Infrastructure Development Board16

Page 17: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

Issue of RFPStep 1

Pre-submission

meetingStep 2

Before

proceeding with

RFP, the project

details, type of

bidders, service

Request for Proposal (1/2)Stage IV-

D

bidders, service

level

expectations and

financial impact

on the State

should be

established.

�Pre-submission meeting

should be held at least 4

weeks before the due date

�Clarification on queries should

be issued not less than 2

weeks before the due date

�Notifications of amendments

in the RFP should be issued

not less than 1 week before

the due date

© Tamil Nadu Infrastructure Development Board17

Page 18: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

Submission of TendersStep 3 � The due date for

submission should not be

ordinarily less than 8 weeks

from the date of

notification of RFP or from

the date of advertisement

whichever is later

Request for Proposal (2/2)Stage IV-

D

Evaluation of TendersStep 4 � Evaluation by TSEC

� Determination of the

Lowest Tenderer

© Tamil Nadu Infrastructure Development Board18

Page 19: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

Opening of TendersStep 1 � Use of Digital Signature in

case of e-tenders

� Opening of tenders should

happen immediately after

the deadline for submission

Initial Response Assessment

Bid Finalisation Stage (1/5)Stage V

Initial Response AssessmentTSEC would examine the following factors

� Tenderers meets the eligibility criteria laid down in the tender document

� Documents are duly signed

� Documents have been authenticated by digital signature in case the tenders

submitted electronically

� Requisite EMD with appropriate validity is furnished

� Tender is substantially responsive to the technical specifications and

commercial conditions

© Tamil Nadu Infrastructure Development Board19

Page 20: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

Selection and Evaluation of Lowest TendererStep 2

Bidding Round Selection Attendant Process

Round 1 Lowest Tenderer All qualified tenders shall be ranked as per the

evaluation criteria and the Tenderer with the

most advantageous financial offer shall be

Lowest Tenderer

Bid Finalisation Stage (2/5)Stage V

Round 1

Outcome

The lowest tenderer may accept the negotiated terms and conditions of

the Tender Inviting Authority (OR)

The Lowest Tenderer withdraws or has been found to be banned by any

procuring entity. In such event the TIA may invite another round of

tenderers

Round 2 Invite all the

remaining tenderers

Extend / Revalidate EMD

Invite other tenderers to match the Lowest

Tenderer in Round 1

Round 2

Outcome 1

Only 1 tenderer

matches the L1 of

Round 1

The tenderer matching L1 will be the Lowest

Tenderer and Selected

20

Page 21: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

Selection and Evaluation of Lowest TendererStep 2

Bidding Round Selection Attendant Process

Round 2

Outcome 2

More than 1 tenderer

match the L1 of Round

1

Ranking will be equal for Round 2 + Ranking

based on Round 1

Hence the tenderer whose bid was more

attractive than the others in Round 1 + Round

Bid Finalisation Stage (3/5)Stage V

attractive than the others in Round 1 + Round

2 will be the lowest tenderer

Round 2

Outcome 3

No tenderer matches

the L1 of Round 1

Extend/Revalidate EMD

Initiate 3rd round of bidding

Round 3 L2 of Round 1 becomes

the price of reckoning

Rank the offers which are lower than the price

offered by L2 in Round 1 and pick the most

preferred offer

© Tamil Nadu Infrastructure Development Board21

Page 22: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

Treatment of Two Equal

Tenders

a) The experience score of the

tenderer as evaluated in RFQ

stage should be taken and the

tenderer with the higher score

would be selected OR

Treatment of Speculative

Tenders

The price quoted by the tenderer is

abnormally low or high in relation to

the subject matter ?

� Opportunity to explain their

rationale in writing before such

Bid Finalisation Stage (4/5)Stage V

would be selected OR

b) Both parties would be asked to

provide a best and final offer

and the tenderer providing a

better offer would be adjudged

as the lowest tenderer

rationale in writing before such

rejection .

� Proceedings will be recorded

� Whatever the outcome, the

decision of the Tender Accepting

Authority shall be communicated

to the tenderer.

© Tamil Nadu Infrastructure Development Board22

Page 23: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

Finalization and Award of ProjectStep 3 (i) The Tender Inviting Authority shall submit the

results of the selection to the Tender Accepting

Authority for approval.

(ii) Notification about the Lowest Tenderer to all

the tenderers

(iii) Issue the Letter of Award (LOA) in duplicate to

Approval for Approving

Authority

Approval of

Concession

EC: For Projects

exceeding Rs.

Bid Finalisation Stage (5/5)Stage V

(iii) Issue the Letter of Award (LOA) in duplicate to

the Lowest Tenderer

(iv) The Lowest Tenderer shall on receipt of the LOA

return a duly signed copy within 7 (seven days).

(v) The Sponsoring Agency shall forward to the

Board the Concession Agreement with a

certificate

(vi) Subject to the conditions precedent in the RFP

and LOA the Lowest Tenderer shall execute the

Concession Agreement with the Procuring Entity

Concession

Agreement if

any changes

have been

made to the

Final DCA

exceeding Rs.

1,000 crore

SC: For Projects

up to Rs. 1,000

crore

CEO: For

Projects up to

Rs. 100 crore

© Tamil Nadu Infrastructure Development Board 23

Page 24: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

Draft Concession Agreement – Key Aspects

Conditions precedent, mutual rights and obligations

Performance indicators and penalties

Payments

24

Appointment of independent auditor, independent engineer and lead

financial institution

Performance indicators and penalties

Financial Closure

Default, breach, termination

Page 25: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

Annexure I: Details of Tender DocumentsAnnexure I: Details of Tender Documents

25

Page 26: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

Elements of REOII

The REOI should contain

Project DescriptionRequest for Expression

of Interest

A Closing Date for

Seeking Clarifications

Timelines Corrigenda/

Notification of

Amendments

Submission

Due Date

Pre-

submission

meeting

Clarification

of Queries

Amendments

Date of

Advertisement/Notification

whichever is later

Change of

Timelines

�Approval from Authority superior to TIA

�Approval from Board (if applicable)

23 26 300

© Tamil Nadu Infrastructure Development Board 26

Page 27: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

Elements of RFQ (1/3)II

The RFQ should contain

Project Description and

Project Cost

Tender Process

Description and ScheduleEligibility Condition

Timelines Corrigenda/N

otification of

Amendments

Submission

Due Date

Pre-

submission

meeting

Clarification

of Queries

Amendments

Date of

Advertisement/Notification

whichever is later

Change of

Timelines

�Approval from Authority superior to TIA

�Approval from Board (if applicable)

23 26 300

© Tamil Nadu Infrastructure Development Board 27

Page 28: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

Element of RFQ (2/3)II

Elements of RFQ

Timelines (Weeks)

Pre-

submission

meeting

Date of

Advertisement/

Notification

whichever is

later

3

0

Project Description and

Project Cost

Tender Process

Description and Schedule

Eligibility Condition

Change of Timelines

�Approval from

Authority superior

to TIA

Submission Due

Date (8 Weeks)

�Clarification of

Queries

�Corrigenda/Noti

fication of

Amendments

1

8

Information Sought and

Format for furnishing

Information

Parameters for Evaluation

Grounds of

Disqualification Removal of

Applicants with

Conflict of Interest

(10 days after due

date)

to TIA

�Approval from

Board (if applicable)

© Tamil Nadu Infrastructure Development Board 28

Page 29: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

Element of RFQ (3/3)II

Eligibility Criteria

�An applicant may be single

entity or a consortium

�No applicant either

individually or as a member

of the consortium can be

member of another

applicant

Technical Criteria Financial Criteria

�Track record and

experience in similar

projects

�Execution track record and

service level track record

�Ability to invest capital in

project

�Net worth

�Average turnover for a

minimum of preceding 3

years

�Average net cash accrual

for a period of preceding 3

yearsapplicant

�An applicant may be a

natural person, private

entity or a combination or a

combination with a public

agency

The foundation for evaluation is selection and not rejection.

project

�Ability to raise funds to

finance the project

�Track record in meeting and

capability to meet

contractual terms

years

�Other relevant financial

information

Pass – Fail TestDevelop a marking system that assigns specific marks for each criteria and total score

determines position of applicants

© Tamil Nadu Infrastructure Development Board

29

Page 30: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

Element of RTP (1/2)III

Minimum Technical Requirements

�Physical facilities including capacity,

individual components and related

aspects

�Output specification- target users, levels

of services, quality and performance

parameters

�Design and safety codes including social

Combining RTP with

RFP:

RTP is not a

mandatory stage. It is

desirable where the �Design and safety codes including social

and environmental impact

�Detailed operational requirements

including service levels, redundancy and

impact on waiting, customer redressal,

safety, security, labour relations and

compliance issues

�Maintenance standards, schedules and

requirements

�Key Performance Indicators for testing &

Performance monitoring requirements

desirable where the

projects are of

complex nature. The

RTP should be

technology and brand

neutral

© Tamil Nadu Infrastructure Development Board

30

Page 31: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

Element of RTP (2/2)III

Timelines

Pre-

submission

meeting

Date of

Advertisement/

Notification

whichever is

later

3

0

Documents to be Evaluated

Corporate Information

Experience Details

Submission Due

Date(6 Weeks)

�Clarification of

Queries

�Corrigenda/Noti

fication of

Amendments

1

6

Removal of

Applicants with

Conflict of Interest

(10 days after due

date)

Approach & Methodology

Business Plan - Operational

Business Plan - Financial

© Tamil Nadu Infrastructure Development Board31

Page 32: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

Element of RFP (1/4)IV

By now, the Project

details, type of bidders,

service level

expectations and

financial impact on the

State are more or less

Procuring Entity shall consider need for following in preparing RFP/DCA:

� Revenue sharing/ revenue support mechanisms for possible monopoly situations to mitigate revenue risks, windfall profits or

State are more or less

finalised

Hence, the Draft

Concession Agreement

should be ready

Procuring Entity may combine the RTP stage with RFP stage to

ensure price competition through adequate number of tenders

revenue risks, windfall profits or low revenue

� Need for appointment of Independent Auditor and Engineer

� Role of Lead Financial Institution

� Treatment of variations including triggers to amend Concession Agreement

© Tamil Nadu Infrastructure Development Board32

Page 33: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

Elements of RFP

Project related details

Instruction to tenderers

Draft concession agreement

EMD specification

RFP shall specify the commercial

conditions and the single criterion for

the Final Offer which would be used

to determine the Lowest Tenderer.

Single criterion may be any one or a

combination of:

Element of RFP (2/4)IV

Draft concession agreement

Variation clauses

Project scope

Evaluation criteria

Performance security

specification

combination of:

� State support sought- tariff

� Expected revenue - period of

concession

� Upfront premium - equity stake

revenue share - lease rent

� Annuity - subsidized facilities

� Any other financial criterion relevant to

the project

© Tamil Nadu Infrastructure Development Board33

Page 34: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

• Normally does not exceed 2% of estimated project cost

• For O & M contracts, may be not less than 10% of the likely annual payments or 2% of the project value

Element of RFP (3/4)IV

Earnest Money Deposit (EMD) Performance Security

• Performance Security shall

ordinarily not exceed 5% of the

Project Value

• For O&M contracts Performance

Security may be not more than

50% of the likely annual of the project value whichever is less

• EMD shall remain valid for 30 days beyond the period for validity of the tender specified in the tender documents

50% of the likely annual

payments due

© Tamil Nadu Infrastructure Development Board34

Page 35: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

Element of RFP (4/4)IV

Timelines

Pre-

submission

meeting

Date of

Advertisement/

Notification

whichever is

later

4

0Change in the Composition of Tenders

Application is made 15 days prior to the

due date

There is no change in the lead member

Substitute proposed is atleast equal in

Submission Due

Date(6 Weeks)

�Clarification of

Queries

�Corrigenda/Noti

fication of

Amendments

2

6

Removal of

Applicants with

Conflict of Interest

Substitute proposed is atleast equal in

both technical and financial terms

Modified consortium meets the pre-

qualification criteria and short listing

criteria

New member or members adopt the

responses expressly as if part of the

original consortium

No conflict of interest

© Tamil Nadu Infrastructure Development Board35

Page 36: TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARDtnidb.tn.gov.in/forms/capacity_building/training...Background (1/2) TN Transparency in Tenders Act and Rules TNIDB Act: All projects above

Thank YouThank You