  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 2 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    Contents 1. PURPOSE ............................................................................................................................... 3 2. SCOPE .................................................................................................................................... 3 3. DEFINITIONS AND ABBREVIATIONS .................................................................................... 3 3.1 Definitions ............................................................................................................................ 3 3.2 Abbreviation ......................................................................................................................... 3 4. REFERENCED DOCUMENTS ................................................................................................ 3 5. RESPONSIBILITIES ................................................................................................................ 4 6. PROCEDURE .......................................................................................................................... 4 6.1 EQUIPMENT STANDARDISATION PHILOSOPHY ............................................................. 4 7. SELECTION OF SUBCONTRACTORS ................................................................................... 4 7.1 Subcontracting Plan ............................................................................................................. 4 7.2 SUBCONTRACTOR Bid Lists .............................................................................................. 4 7.3 Pre-Qualification Requirements ............................................................................................ 6 7.4 Subcontractor Evaluation & Award ....................................................................................... 6 7.5 Commercial Terms and Conditions ...................................................................................... 8 8. SELECTION OF VENDORS .................................................................................................... 8 8.1 Procurement Plan ................................................................................................................ 8 8.2 Vendor Lists ......................................................................................................................... 8 8.3 Pre-Qualification Requirements .......................................................................................... 10 8.4 Vendor Evaluation & Award ................................................................................................ 10 8.5 Commercial Terms and Conditions .................................................................................... 11 9. LOCAL AND REGIONAL RESOURCES ................................................................................ 11 10. COMPANY SELECTION OF OTHER THAN RECOMMENDED SUBCONTRACTOR / VENDOR ...................................................................................................................................... 12 ATTACHMENT 1: PRELIMINARY SUBCONTRACTING PLAN.................................................. 13 ATTACHMENT 2: SUBCONTRACTOR LIST ............................................................................. 14 ATTACHMENT 3: FORM FOR PROPOSING SUBCONTRACTORS ......................................... 17 ATTACHMENT 4: COMPANY WORK GROUP LISTING ........................................................... 18 ATTACHMENT 5: PRE-QUALIFICATION REQUIREMENT FOR SUBCONTRACTORS ........... 41 ATTACHMENT 6: NOMINATED/RESTRICTED VENDOR LIST ................................................. 43 ATTACHMENT 7: VENDOR LIST FOR MAJOR GOODS .......................................................... 45 ATTACHMENT 8: FORM FOR PROPOSING ADDITIONAL VENDORS .................................. 115 ATTACHMENT 9: COMPANY PRODUCT GROUP LISTING ................................................... 116 ATTACHMENT 10: PRE-QUALIFICATION REQUIREMENTS FOR VENDORS ...................... 143 ATTACHMENT 11: VENDOR LIST FOR STANDARDISED EQUIPMENT ............................... 145

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 3 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    1. PURPOSE

    The purpose of this document is to ensure that CONTRACTOR shall perform all procurement activities necessary for completion of the WORK following this criteria for selection of SUBCONTRACTORS and VENDORS.

    2. SCOPE

    This document defines the process for selecting SUBCONTRACTORS and VENDORS for procurement of major GOODS and / or services. COMPANYS strategy is to provide CONTRACTOR with a degree of flexibility in sourcing GOODS utilising its own experience and market knowledge to enhance quality and reduce overall cost. At the same time, COMPANY requires the CONTRACTOR to comply with COMPANYS standard requirements.

    3. DEFINITIONS AND ABBREVIATIONS

    3.1 Definitions

    Refer to ARTICLES OF AGREEMENT.

    3.2 Abbreviation

    AVL Additional Vendors List

    EPC Engineering, Procurement and Construction

    ICS Integrated Control System

    Q Qualified

    SL SUBCONTRACTOR List

    TBQ To be Qualified

    VL VENDOR List

    4. REFERENCED DOCUMENTS

    This document shall be read and construed in accordance with the relevant provisions contained in the documents listed below:

    Document Number Document Title

    CC01A-0-00000-PM-PHL-0001 Equipment Standardisation Philosophy

    CC01A-0-00000-PS-PRO-0003 Procurement Guidelines

    CC01A-0-00000-PS-PRO-0002 Procurement Services

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 4 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    The edition of the Reference Documents shall be the edition current at the EFFECTIVE DATE of the AGREEMENT.

    CONTRACTOR shall comply with COMPANY instruction to comply with any changed Reference Documents.

    CONTRACTOR shall advise COMPANY of any conflict between the referenced documents and any technical specification. COMPANY shall determine which shall govern.

    5. RESPONSIBILITIES

    The CONTRACTOR is responsible to comply with the implementation of this Procedure.

    6. PROCEDURE

    6.1 EQUIPMENT STANDARDISATION PHILOSOPHY

    The document Equipment Standardisation Philosophy advises the basis for the Standardisation Philosophy and identifies the equipment types which are subject to this philosophy (Refer to Document No CC01A-0-00000-PM-PHL-0001). For equipment types not listed in the Equipment Standardisation Philosophy, the CONTRACTOR is free to nominate VENDORS and SUBCONTRACTORS in accordance with the procedure contained in this document.

    7. SELECTION OF SUBCONTRACTORS

    Selection of any SUBCONTRACTOR for performance of any portion of the WORK shall be based, amongst other factors, on technical merit and the ability to comply with the SCHEDULE.

    For the purpose of this Section 7, SUBCONTRACTORS excludes VENDORS. Refer to Section 8 of this document for requirements for selection of VENDORS.

    7.1 Subcontracting Plan

    CONTRACTORS preliminary Subcontracting Plan is included as Attachment 1 (Preliminary Subcontracting Plan). The requirements relating to the establishment and updating of the Subcontracting Plan are covered in Procurement Services (Refer to Document No. CC01A-0-00000-PS-PRO-0002).

    7.2 SUBCONTRACTOR Bid Lists

    CONTRACTOR shall comply with the following provisions for selection of SUBCONTRACTORS to be included on the SUBCONTRACTOR lists for the WORK (refer to Attachment 2 SUBCONTRACTORS List)

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 5 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    7.2.1 SUBCONTRACTOR List (SL)

    The SUBCONTRACTOR List (SL) in Attachment-2 contains the approved potential SUBCONTRACTORS being categorized under Class Q of the first tier and other subcontracts of significance.

    CONTRACTOR shall be free to issue enquiries to any/all potential SUBCONTRACTORS included in the SL for their respective scope.

    It is anticipated during the EPC selection process an approved SUBCONTRACTORS list will be developed from CONTRACTORS input at Tender stage. CONTRACTOR shall submit for COMPANYS approval its SUBCONTRACTOR List utilizing the qualified SUBCONTRACTOR List given in attachment 2 along with its request for deviation from this list (with justification therefore) during the Technical Evaluation of CONTRACTORS Tender. A Pre-qualification Dossier containing information as stated in Attachment 5 Method A of this document shall be submitted for all proposed SUBCONTRACTORS deviated from the qualified list of Attachment 2 for COMPANYS review and approval.

    It is COMPANYS intention to review the proposed SUBCONTRACTORS and classify them as Q, TBQ, or Not Acceptable in accordance with Criteria for Selection of Subcontractors and Vendors as stated in Attachment 5 Method A and shall advise the CONTRACTOR accordingly. This Subcontractor List shall constitute the Contractors Approved List

    CONTRACTOR shall ensure, prior to issuing Invitation to Tender, that there are at least three (3) SUBCONTRACTORS in Category Q for each item.

    CONTRACTOR shall not issue enquiries to any SUBCONTRACTOR other than those included in the Approved SL under Class Q except with prior approval of COMPANY, which will be granted only under exceptional circumstances

    The SUBCONTRACTORS List agreed by COMPANY with the CONTRACTOR shall contain all the SUBCONTRACTORS classified as Q or TBQ and will be included as Attachment 2 of this document CC000-0-00000-PS-PRO-0004 - Criteria for Selection of Subcontractors and Vendors. This list will ultimately become an exhibit to the AGREEMENT.

    7.2.2 Additional SUBCONTRACTORS

    For any proposed additional WORK and WORK where a list of SUBCONTRACTORS has not been pre-approved, CONTRACTOR shall submit to COMPANY within forty five (45) days of the EFFECTIVE DATE or four (4) weeks prior to the date set for issuance of inquiry for a SUBCONTRACTOR, whichever is the earlier, its list proposing SUBCONTRACTORS. This submission shall use the form in Attachment 3, and CONTRACTOR shall complete the forms using the COMPANYS Work Group Listing in Attachment 4.

    COMPANY will evaluate CONTRACTORS proposed SUBCONTRACTOR lists and assign one of the following classifications:

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 6 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    Class Q

    This classification will be given to SUBCONTRACTORS who comply with COMPANYS registration requirements and who are known to COMPANY from a previous project. An inquiry can be issued Class Q SUBCONTRACTORS without further approvals from COMPANY.

    Class TBQ

    This classification will be given to SUBCONTRACTORS who do not comply with COMPANYs registration requirements and/or who are not known to COMPANY.

    CONTRACTOR may issue enquiries to Class TBQ SUBCONTRACTORS at its discretion, however, these shall be considered for evaluation only after upgrade from Class TBQ to Class Q. However, CONTRACTOR shall issue enquiries to all Q category SUBCONTRACTORS before considering any TBQ VENDOR for issue of enquiry.

    Class Not Acceptable

    This will be given by COMPANY to those SUBCONTRACTORS in respect of which information is available confirming inadequate capability or unacceptable past performance or other reason. COMPANY reserves the right to reject any subcontractor nominated by CONTRACTOR. CONTRACTOR shall not issue inquires to such SUBCONTRACTORS.

    7.3 Pre-Qualification Requirements

    In order to upgrade a proposed SUBCONTRACTOR from Class TBQ to Class Q, CONTRACTOR shall submit a Pre-qualification Dossier containing information as stated in Attachment 5 Method A and Method B for COMPANYS review.

    CONTRACTOR shall plan its activities in a manner so as to allow sufficient time for pre-qualification of the proposed SUBCONTRACTORS without affecting the SCHEDULE.

    7.4 Subcontractor Evaluation & Award

    7.4.1 CONTRACTOR shall technically evaluate the SUBCONTRACTORS and submit evaluations for COMPANY approval. Following COMPANY approval of the technical evaluation, CONTRACTOR shall submit the award recommendation at least four (4) weeks prior to the date set for award of the subcontract.

    COMPANY requirements for technical evaluation and award recommendation are contained in Procurement Services procedure (document no. CC01A-0-00000-PS-PRO-0002).

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 7 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    7.4.2 CONTRACTORS Technical Evaluation shall address COMPANYS selection criteria that follow:

    Registration Requirements

    Valid Trade License from Abu Dhabi Municipality covering the services to be provided.

    Valid Registration Certificate from Abu Dhabi Chamber of Commerce & Industry covering the services to be provided.

    Oil and Gas Classification for above.

    Contractor Classification from Abu Dhabi Planning Department, if available.

    Valid Consultant Registration Certificate from Abu Dhabi Planning Department (for Consultant only), if available.

    Registration with COMPANY.

    Technical Requirements

    Compliance with SUBCONTRACT scope of work.

    Compliance with SPECIFICATIONS.

    Structured organisation, manpower and equipment in a condition that allows safe operation and in quantities that would meet job requirements.

    Adequate direct experience in jobs of similar scope and order of magnitude in the last five years, especially in the UAE or Gulf region.

    Current workload and availability of resources to comply with SCHEDULE requirements.

    Documented Quality Assurance / Quality Control Programs (typically ISO 9001).

    Documented Health, Safety and Environmental Systems and Procedures (typically compliance with ISO 14001).

    Excellent Safety Record.

    Financial soundness and solvency.

    Compliance with Insurance Coverage requirements.

    7.4.3 Subject to compliance with the registration and technical requirements of the selection criteria, COMPANY will approve the technical bid evaluation recommendations submitted by CONTRACTOR.

    Final approval of selected SUBCONTRACTOR and approval for award shall be subject to the provisions of Section 10 of this document.

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 8 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    7.5 Commercial Terms and Conditions

    CONTRACTOR shall be responsible for finalising with the SUBCONTRACTORS commercial terms and conditions which comply with the requirements of the AGREEMENT.

    8. SELECTION OF VENDORS

    Selection of any VENDOR for supply of GOODS for the WORK shall be based, amongst other factors, on technical merit and lowest life cycle value. In this context life cycle cost means the total cost over a ten year period considering capital, maintenance and operating cost associated with the equipment.

    8.1 Procurement Plan

    CONTRACTORS Procurement Plan shall be established and updated in accordance with the Procurement Services procedure (document no. CC01A-0-00000-PS-PRO-0002).

    8.2 Vendor Lists

    8.2.1 Nominated/Restricted VENDORS

    The lists of nominated/restricted VENDORS based on requirements such as technical compatibility and/or standardisation is enclosed in Attachment 6 and Attachment 11. CONTRACTOR shall negotiate directly with such nominated/restricted VENDORS for the supply of the specific GOODS in question.

    In some cases, Attachment 11 contains more than one VENDOR for Standardised Equipment. It is anticipated that during EPC selection / execution, one single VENDOR will be confirmed and advised by COMPANY.

    If a single VENDOR has not been confirmed, CONTRACTOR may issue inquiries to any/all VENDORS listed. In this case, CONTRACTORs inquiry shall also specify that VENDORs pricing shall be applicable to the entire PROJECT, including any future enquiries from other L/EPC CONTRACTORS.

    CONTRACTORS bid evaluation shall be submitted to COMPANY as defined elsewhere in the AGREEMENT. If COMPANY accepts CONTRACTORs proposed VENDOR, the VENDOR shall become the single APPROVED VENDOR for that category of Standardised Equipment.

    8.2.2 VENDOR List for Major GOODS (VL)

    The VL in Attachment 7 contains the pre-approved VENDORS from which CONTRACTOR may procure major GOODS. CONTRACTOR must also comply with the requirements of the nominated/restricted VENDOR list.

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 9 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    CONTRACTOR may proceed to issue inquiries to any/all potential VENDORS that are Class Q from the pre-approved VENDORS for their respective GOODS.

    It is anticipated during the EPC selection process an approved VENDORS list will be developed from CONTRACTORS input at Tender stage. CONTRACTOR shall submit for COMPANYS approval its VENDORS List utilizing the qualified VENDORS List given in attachment 7 along with its request for deviation if any from this list (with justification therefore) during the Technical Evaluation of CONTRACTORS Tender. A Pre-qualification Dossier containing information as stated in Attachment 10 Method A of this document shall be submitted for all proposed VENDORS deviated from the qualified list of Attachment 7 for COMPANYS review and approval.

    It is COMPANYS intention to review the proposed VENDORS and classify them as Q, TBQ, or Not Acceptable in accordance with Criteria for Selection of Subcontractors and Vendors as stated in Attachment 10 Method A and shall advise the CONTRACTOR accordingly. This VENDOR List shall constitute the CONTRACTORS Approved List

    CONTRACTOR shall ensure, prior to issuing Invitation to Tender, that there are at least three (3) VENDORS in Category Q for each item.

    CONTRACTOR shall not issue enquiries to any VENDOR other than those included in the Approved VL under Class Q except with prior approval of COMPANY, which will be granted only under exceptional circumstances.

    The VENDOR List agreed by COMPANY with the CONTRACTOR shall contain all the VENDORS classified as Q or TBQ and will be included as Attachment 7 of this document CC01A-0-00000-PS-PRO-0004 - Criteria for Selection of Subcontractors and Vendors. This list will ultimately become an exhibit to the AGREEMENT.

    8.2.3 Additional VENDOR List for Other GOODS (AVL)

    CONTRACTOR shall submit the detailed list of additional GOODS required for the WORK. Within forty five (45) days of the EFFECTIVE DATE or four (4) weeks prior to the date set for issuance of an inquiry for a purchase order, whichever is earlier, CONTRACTOR shall submit to COMPANY a detailed list identifying proposed VENDORS for additional GOODS utilising the form in Attachment 8. CONTRACTOR shall refer to COMPANYS Product Group Listing in Attachment 9 to complete the forms.

    COMPANY will evaluate CONTRACTORS proposed VENDOR lists and assign the following classification:

    Class Q

    This classification will be given to VENDORS who comply with COMPANYS registration requirements and who are known to COMPANY from a previous project. An enquiry can be issued Class Q VENDORS without further approvals from COMPANY.

    Class TBQ

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 10 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    This classification will be given to VENDORS who do not comply with COMPANYs registration requirements and/or who are not known to COMPANY.

    CONTRACTOR may issue inquiries to Class TBQ VENDORS at its discretion, however, these shall be considered for evaluation only after upgrade from Class TBQ to Class Q. However, CONTRACTOR shall issue enquiries to all Q category VENDORS before considering any T.B.Q VENDOR for issue of enquiry.

    Class Not Acceptable

    This will be from VENDORs list in Attachment 7 as Not Acceptable VENDORS in respect of which information is available confirming inadequate capability or unacceptable past performance. CONTRACTOR shall not issue enquires to such VENDORS.

    8.3 Pre-Qualification Requirements

    In order to upgrade a proposed VENDOR from Class TBQ to Class Q, CONTRACTOR shall submit a Pre-qualification Dossier containing information as stated in Attachment 10 Method A and Method B for COMPANYs review.

    CONTRACTOR shall plan its activities in a manner so as to allow sufficient time for pre-qualification of the proposed VENDORS without affecting the SCHEDULE.

    8.4 Vendor Evaluation & Award

    8.4.1 CONTRACTOR shall technically evaluate the VENDORS offers and submit evaluations for APPROVAL. Following COMPANY approval of the technical evaluation, CONTRACTOR shall submit the award recommendation at least four (4) weeks prior to the date set for award of purchase order.

    COMPANY requirements for technical evaluation and award recommendation are contained in Procurement Services procedure (document no. CC01A-0-00000-PS-PRO-0002).

    8.4.2 CONTRACTORS Technical Evaluation shall address COMPANYS selection criteria that follow:

    Registration Requirements

    Agency Agreement with an Abu Dhabi company endorsed by the required UAE authorities (applicable to non Abu Dhabi based VENDORS).

    Registration with COMPANY.

    Technical Requirements

    Compliance with scope of supply.

    Compliance with SPECIFICATIONS.

    Internationally recognised for high quality and reliability.

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 11 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    Advanced level of technology with capability to upgrade in future.

    Compliance with the essential requirements of ISO 9001:2008.

    Excellent Safety Record.

    Compliance with SCHEDULE.

    Current workload and availability of resources.

    Availability of after sales support facilities in Abu Dhabi such as stock of spare parts, repair facility, technical support and training centres for plant operators and technician.

    Good performance track record in terms of quality, responsiveness, cost control, safety, completion schedule, business ethics, etc.

    Adequate past experience in supply of similar items in the last five years, especially in the UAE or the Gulf region. Past experience with ADNOC Group of Companies will be preferred.

    Commitment for continued provision of spares for the life of the GOODS.

    Financial soundness and solvency.

    Life cycle operating cost.

    Operating spare parts cost.

    All Stockists / Distributors / Trading Houses shall only be considered subject to COMPANY acceptance of satisfactory source of manufacturer/origin.

    GOODS supplied for piping materials, or mechanical valves must be supplied by reputable VENDORS or mills which can provide experience of similar GOODS supply.

    COMPANY reserves the right to reject any Vendor nominated by CONTRACTOR.

    Engineering companies and packagers shall be considered subject to approval of major sub-suppliers by COMPANY.

    Subject to compliance with the registration and technical requirements of the selection criteria, COMPANY will approve the technical bid evaluation recommendations submitted by CONTRACTOR. Final approval of the selected VENDOR and approval for award shall be subject to the provisions contained in section 10 of this document.

    8.5 Commercial Terms and Conditions

    CONTRACTOR shall be responsible for finalising with the VENDORS the commercial terms and conditions which comply with the requirements of the AGREEMENT.

    9. LOCAL AND REGIONAL RESOURCES

    COMPANY requires that the CONTRACTOR maximises, wherever possible, the involvement of local and regional resources in the implementation of the WORK.

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 12 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    10. COMPANY SELECTION OF OTHER THAN RECOMMENDED SUBCONTRACTOR / VENDOR

    COMPANY reserves the right to select, from amongst the technically acceptable SUBCONTRACTORS/VENDORS, a SUBCONTRACTOR/VENDOR other than the one recommended by CONTRACTOR. Frequent exercising of this right by COMPANY is not anticipated. Any additional costs to CONTRACTOR, directly attributable to exercising of this right by COMPANY, shall be reimbursed to CONTRACTOR in accordance with the provisions of the AGREEMENT. Should COMPANY exercise this right, COMPANY shall have the right of access to the original priced quotations by SUBCONTRACTORS/VENDORS.

    CONTRACTORs award recommendations shall accordingly include the difference payable by COMPANY to CONTRACTOR for each of the technically approved SUBCONTRACTORS/VENDORS other than the one recommended by CONTRACTOR.

    In addition to above, COMPANY may require CONTRACTOR to provide in respect of certain equipment/items a detailed life cycle cost analysis. This information shall be provided as part of the award recommendations wherever required by COMPANY.

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 13 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    ATTACHMENT 1: PRELIMINARY SUBCONTRACTING PLAN

    CONTRACTORs approved Preliminary Subcontracting Plan to be inserted here.

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 14 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    ATTACHMENT 2: SUBCONTRACTOR LIST

    SL WORK DESCRIPTION

    WORK GROUP

    No. SUBCONTRACTOR NAME

    BOROUGE/ GASCO/ TAKREER

    REGISTRATION No. REMARKS

    1 TEMPORARY SITE FACILITIES AND CAMP

    280010 GALFAR

    GRANITE

    TARGET

    IMECO

    DYWIDAG

    AL MASSOD

    EMCO

    KENTZ

    2 CIVIL WORKS 230000 AL JABER

    GALFAR

    GRANITE

    DAEWOO

    TARGET

    DYWIDAG

    BELHASA SIX CONSTRUCT

    AL GEEMI

    KETTANEH

    KHANSAHEB

    NASSER AL HAJRI

    EMCO

    3 PILING 210090 SWISS BORING

    DUTCH FOUNDATION

    BAUER

    4 MARINE WORKS 210020 BELHASA SIX CONSTRUCT

    ARCHIRODON CONSTRUCTION

    INTERBETON

    TARGET

    5 MECHANICAL WORKS 240000 DAEWOO

    PUNJ LLOYED

    DESCON

    LAHOUD

    TARGET

    LERSEN & TOUBRO

    DODSAL

    AL JABER

    GALFAR

    NASSER AL HAJRI

    CCC

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 15 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    SL

    WORK DESCRIPTION WORK GROUP

    No. SUBCONTRACTOR NAME

    BOROUGE/ GASCO/ TAKREER

    REGISTRATION No. REMARKS

    6 ELECTRICAL WORKS 260000 TICB

    DAEWOO

    TOZZI SUD

    TARGET

    KENTZ

    CONTROL APPLICATION EMIRATES

    CEGELEC OIL

    DODSAL

    7 ICS EPC SERVICES 270020 HONEYWELL MIDDLE EAST LTD - ABU DHABI

    NOMINATED CONTRACTOR

    8 INSTRUMENTATION WORKS 270020 TICB

    DAEWOO

    TOZZI SUD

    TARGET

    KENTZ

    CONTROL APPLICATION EMIRATES

    CEGELEC OIL

    DODSAL

    9 INSULATION & PAINTING WORKS 372000 CAPE EAST LIMETED W.L.L

    KEFER LLC

    INSULCO EMIRATES

    INCO LTD

    MAZRUI & HAWI

    GLOBAL ESSA COATING

    FAME

    10 BUILDINGS WORKS 230095 ZAMIL STEEL

    GALFAR

    GRANITE

    DYWIDAG

    TARGET

    AL JABER

    AL GEEMI

    GROUP3

    KIRBY BUILDING SYSTEM

    11 PRE ENGINEERED BUILDINGS 230095 AMANA

    KIRBY BUILDING SYSTEM

    BUTLER

    12 HVAC WORKS 240060 CCTC

    KETTANEH

    ETA

    EMCO

    KENTZ

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 16 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    SL

    WORK DESCRIPTION WORK GROUP

    No. SUBCONTRACTOR NAME

    BOROUGE/ GASCO/ TAKREER REGISTRATION No.

    REMARKS

    13 FREIGHT FORWARDING & CLEARANCE 374025 MICCO

    SERVICES SALEM FREIGHT INTERNATIONAL

    KUHNE & NAGEL

    MATRIX

    GAC

    14 HEAVY TRANSPORTATION SERVICES 280042 AL JABER TRANSPORT

    MAMOET

    ALE

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 17 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    ATTACHMENT 3: FORM FOR PROPOSING SUBCONTRACTORS

    SL. Work Description Work

    Group No. Proposed Sub-

    Contractor Company

    Registration No. Remarks

    1

    2

    3

    4

    5

    NOTE: CONTRACTOR to insert more lines as appropriate.

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 18 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    ATTACHMENT 4: COMPANY WORK GROUP LISTING

    CONTENTS

    DESCRIPTION PAGE NO.

    1.0 PROJECTS & PLANT CONSULTANCY/ENGINEERING

    1.1 PROJECT CONSULTANCY/ENGINEERING

    1.2 OPERATING PLANT CONSULTANCY

    2.0 CONSTRUCTION WORKS (MAJOR PROJECTS)

    2.1 EPC CONTRACTS

    2.2 EPCM CONTRACTS

    2.3 CIVIL WORKS

    2.4 MECHANICAL WORKS

    2.5 PIPELINE WORKS

    2.6 ELECTRICAL WORKS

    2.7 INSTRUMENTATION & TELECOM. WORKS

    2.8 GENERAL CONTRACTS (MAJOR PROJECTS)

    3.0 PLANT OPERATION & MAINTENANCE

    3.1 CIVIL WORKS/MAINTENANCE

    3.2 MECHANICAL PLANT/EQUIPMENT WORKS/MAINT.

    3.2.1 Turbines - Maintenance

    3.2.2 Pumps, Compressors, Other Rotating Eqpt. Maintenance

    3.2.3 Processing Plant & Equipments - Maintenance

    3.2.4 Boilers, Furnaces & Reactors - Maintenance

    3.2.5 Heat Exchangers - Maintenance

    3.2.6 Material Handling Equipments - Maintenance

    3.2.7 Shut Down Maintenance

    3.2.8 Other Mechanical Plants - Maintenance

    3.3 PIPING, COLUMNS AND TANKS - MAINTENANCE

    3.3.1 Piping - Maintenance

    3.3.2 Columns, Tanks, Vessels & Others - Maintenance

    3.4 ELECTRICAL PLANT & EQUIPMENT - MAINT.

    3.4.1 Motors & Generators - Maintenance

    3.4.2 Sub-Stations, Switch Gears & Transformers - Maintenance

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 19 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    DESCRIPTION PAGE NO.

    3.4.3 Cables, Transmission And Distribution - Maintenance

    3.4.4 Other Electrical Plant & Equipment - Maintenance.

    3.5 INSTRUMENTATION & TELECOM. SYSTEMS - MAINTENANCE

    3.6 INSPECTION/TESTING/COMMISSIONING SERVICES

    3.6.1 Inspection & Testing Services

    3.6.2 Commissioning Services

    3.7 GENERAL PLANT MAINTENANCE SERVICES

    3.7.1 Hiring Services - Plants

    3.7.2 Painting Services - Plants

    3.7.3 Plant Cleaning Services

    3.7.4 Other Plant Operation/Maintenance Services

    4.0 INFORMATION SYSTEMS & TECHNOLOGIES

    5.0 EXPLORATION & PRODUCTION RELATED SERVICES

    6.0 PERSONNEL & MANPOWER SERVICES

    6.1 MANPOWER SUPPLY - ENGINEERS

    6.2 MANPOWER SUPPLY - SUPERVISORS/TECHNICIANS

    6.3 MANPOWER SUPPLY - NON TECHNICAL PERSONNEL

    6.4 OTHER PERSONNEL CONTRACTS/SERVICES

    7.0 FINANCE SERVICES

    8.0 MARKETING SERVICES

    9.0 ADMINISTRATION & GENERAL SERVICES

    9.1 CATERING SERVICES

    9.2 LEASING SERVICES

    9.3 MEDICAL & HSE SERVICES

    9.4 OFFICES, BUILDINGS AND VILLAS MAINTENANCE

    9.5 TRANSPORTATION SERVICES

    9.6 CLEANING SERVICES

    9.7 OTHER GENERAL SERVICES

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 20 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    WG CODE WORK GROUP (WG) DESCRIPTION

    GROUP1.0 PROJECTS & PLANT CONSULTANCY/ENGINEERING

    Sub-Group 1.1 covers Front End Engineering and Design (FEED), Basic Engineering, Project Management/Consultancy Detailed Engineering, for major project.

    1.1 PROJECT CONSULTANCY/ENGINEERING

    110010 Advanced Process Control

    110020 Aerial Surveys

    110030 Architecture & Interior Decoration

    110040 Cathodic Protection Systems Consultancy

    110050 Chemical Injection Systems

    110060 Civil & Structural (Industrial)

    110070 Civil & Structural (Non Industrial)

    110080 Cold Industrial Insulation Consultancy

    110085 Conceptual Design

    110090 De-Salination/Water Treatment Consultancy

    110100 Environmental Eng. (Pollution Control/Effluent Treatment)

    110110 Front End Engineering Design (Feed)

    110115 Optimization Studies

    110117 Special Studies/Design

    110120 Gas Processing

    110135 Gas Production Onshore

    110140 Gas Treatment Equipment

    110150 Gas Gathering Centers

    110160 Instrumentation And Control Systems

    110165 Landscaping Consultancy

    110167 LNG/LPG Tanks - Consultancy

    110170 Management Information Systems

    110180 Marine Engineering

    110190 Marine Surveys

    110200 Material Selection For Corrosion Control consultancy

    110210 Onshore Surveys

    110220 Packaged Process Module

    110260 Pipeline - Onshore (Oil & Gas)

    110270 Power Generation, Transmission & Distribution

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 21 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    WG CODE WORK GROUP (WG) DESCRIPTION

    GROUP1.0 PROJECTS & PLANT CONSULTANCY/ENGINEERING

    110280 Process Licensors

    110290 Project Management Industrial

    110295 Project Management Non-Industrial

    110300 Quality Control Consultants

    110305 Scada System Consultancy

    110320 Soil Investigation - Onshore

    110325 Sulphur Recovery/Forming & Handling Consultancy

    110330 Telecommunication Network And Telemetry

    110333 Techno - Economic Feasibility Study

    110335 Town Planning/Master Plan

    110340 Water Injection Systems

    110345 Gas Injection Systems

    110350 Water Supply/Distribution Networks Consultancy

    110360 Sewage / Drainage Networks Consultancy

    Sub-Group 1.2 Covers Operating Plant, Consultancy Services.

    1.2 Operating Plant Consultancy

    120010 Air Conditioning & Electro Mechanical Domestic/Industrial

    120020 Concrete Rehabilitation Studies

    120030 Corrosion Audit/Surveys

    120040 Energy Conservation Studies

    120060 Field Testing Of New Applications

    120070 Fire & Safety Consultancy

    120080 Industrial Engineering/Productivity Studies

    120081 ISO 14000/HSE Systems & Procedures

    120082 ISO 9000/Qc Systems & Procedures

    120083 ISO 9000/Qc Certification

    120084 ISO 14000/Qc Certification

    120085 Materials Management Consultancy

    120100 Mech. Plant & Materials Handling System - Onshore

    120110 Noise Surveys & Analysis

    120115 Operating Procedures - Plant Operation/Maint.

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 22 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    WG CODE WORK GROUP (WG) DESCRIPTION

    GROUP1.0 PROJECTS & PLANT CONSULTANCY/ENGINEERING

    120120 Plant Inspection Consultancy Services

    120130 Plant Operation Studies (Reliability, Performance, Failure Etc.)

    120140 Plant Surveys - Mechanical/Electrical

    120150 Preservation Studies & Services - Equipments & Spares

    120160 Risk/Hazard/Safety Studies

    120165 Accident, Damage Investigation Consultancy

    120170 Security Related Consultancy

    120190 Studies On Construction Material And Testing Laboratory

    120200 Technical Audit/Surveys

    120220 Vibration Surveys Of Rotating Equipment

    120230 Waste Control/Effluent Treatment

    120240 Structural Steel Frame Analysis

    WG CODE WORK GROUP (WG) DESCRIPTION

    GROUP 2.0 CONSTRUCTION WORKS (MAJOR PROJECTS)

    Sub-Group 2.1 covers EPC and Sub-Group 2.2 covers EPCM contracts for major projects:

    2.1 ENGINEERING, PROCUREMENT & CONSTRUCTION (EPC) CONTRACTS

    210010 Desalination Units - EPC

    210015 LNG/LPG Tanks- EPC

    210020 Marine Works - EPC

    210025 Nitrogen/Oxygen Plants - EPC

    210040 Oil & Gas Plants - Onshore - EPC

    210045 Oil & Gas Unit Of Plants - Onshore - EPC

    210070 Pipelines Onshore - EPC

    210080 Power Generation Plants - EPC

    210090 Tank Farms EPC

    2.2 ENGINEERING, PROCUREMENT & CONSTRUCTIONS MANAGEMENT (EPCM) CONTRACTS

    220010 Marine Works EPCM

    220030 Gas Plants Onshore - EPCM

    220060 Pipelines Onshore - EPCM

    220070 Power Generation Plants - EPCM

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 23 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    WG CODE WORK GROUP (WG) DESCRIPTION

    GROUP 2.0 CONSTRUCTION WORKS (MAJOR PROJECTS)

    Sub-Groups 2.3 to 2.8 cover Construction Works for all engineering disciplines for major projects:

    2.3 CIVIL WORKS

    230020 Buildings, Offices, Etc. - Construction

    230030 Ceiling And Internal Partitions Works

    230035 Drainage / Sewerage Works

    230040 Dredging/ Reclamation - Offshore

    230050 Industrial Civil Works

    230055 Infrastructure Works

    230060 Interior Decoration Works

    230070 Marine Construction - Jetty, Harbour Etc.

    230090 Piling/Sheet Piling

    230095 Pre-Engineering Buildings/Steel Structure

    230100 Roads/Culverts Works

    230120 Site Preparation Works

    230130 Soil/Foundation Grouting

    230140 Steel Structural Works - Erection

    230145 Steel Structural Works - Fabrication

    230150 Tunnelling/Non-Destructive Road Crossings

    230155 Horizontal Direction Drilling HDD

    230160 Water Supply Networks Works

    2.4 Mechanical Works

    240020 Crane/Overhead Bridge - Erection

    240030 Desalination Units - Erection

    240040 Effluent Treatment Plants

    240045 Environmental Related Works (Pollution Control/Monitoring, Etc.)

    240050 Fabrication Works General

    240060 HV & Ac Works Industrial

    240065 Air-Conditioning High Rise Buildings (Central Chilled Water Systems) - Supply & Installation.

    240070 LPG/LNG Tanks Erection

    240080 Mechanical Equipments - Erection

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 24 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    WG CODE WORK GROUP (WG) DESCRIPTION

    GROUP 2.0 CONSTRUCTION WORKS (MAJOR PROJECTS)

    240090 Molten Sulphur Tanks

    240095 Sulphur Recovery/Forming & Handling Plant - Erection

    240100 Oil & Gas Plants - Erection

    240120 Power Stations - Erection

    240130 Site Work - Tank Farms/Floating Roof

    240140 Telecom Towers

    240145 Water Pumping Station - Erection

    240148 Sewerage Pumping Station Erection

    240150 Water Treatment Plant Works

    2.5 Pipeline Works

    250010 Cement Linings Of Pipes

    250020 Cold & Cryogenic Insulation Works

    250030 Fire Fighting Systems - Piping

    250040 Pipelines - Insulation Work

    250050 Pipelines - Coatings (FBE/PE)

    250051 Pipelines - Coatings Pp (Polypropylene)

    250052 Pipelines - Coating & Wrapping (Coal Tar/Bitumen Enamel)

    250065 Pipelines: Tie-Ins

    250080 Pipelines Construction - Onshore

    250090 Sandblasting & Painting Works

    2.6 Electrical Works

    260005 Building Management Systems

    260010 Cathodic Protection Systems Works

    260020 Electrical Works Industrial

    260030 Electro-Mechanical (Buildings/Domestic)

    260045 Cable Laying And Trench Excavation

    260055 Street Lighting & Accessories

    260060 Power Transmission/Distribution - Overhead

    2.7 Instrumentation & Telecom. Works

    270010 Fire And Safety Works

    270020 Instrumentation & Control Works - Industrial

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 25 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    WG CODE WORK GROUP (WG) DESCRIPTION

    GROUP 2.0 CONSTRUCTION WORKS (MAJOR PROJECTS)

    270030 Telecommunication Works

    2.8 General Contracts (Major Projects)

    280010 Camp Catering For Major Projects Onshore

    280020 Certification (Design/Statutory Requirements)

    280030 Freight Forwarding & Clearing Major Projects

    280040 Land Transportation

    280042 Heavy Lift Transportation Services

    280045 Transportation Aggregate, Sand, Rocks, Etc.

    280070 NDT - Radiographic, Ultrasonic Etc.

    280075 NDT - Radiographic Digitization

    280080 Third Party Inspection

    WG CODE WORK GROUP (WG) DESCRIPTION

    GROUP 3.0 PLANT OPERATION & MAINTENANCE

    Group 3 covers Plant, Maintenance, Rehabilitation, Refurbishment, Minor Construction Works for plant operation, covering all engineering disciplines:

    3.1 CIVIL WORKS / MAINTENANCE

    310010 Aluminium & Glass Works

    310020 Building Construction - Minor

    310021 Civil Industrial Work - Minor

    310022 Building Maintenance

    310024 Building Maintenance/Service Agreements

    310030 Concrete - Pre-Cast

    310032 Concrete - Pre-Stress

    310035 GRC - Glass Reinforced Concrete

    310040 Concrete - Rehabilitation Work

    310045 Concrete - Ready Mix

    310050 Demolition (Plant/Equipment/Foundation)

    310060 Drainage / Sewerage Minor Works

    310065 Excavation And Back Filling

    310070 Earthwork

    310080 Fencing And Gates

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 26 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    WG CODE WORK GROUP (WG) DESCRIPTION

    GROUP 3.0 PLANT OPERATION & MAINTENANCE

    310085 Guniting / Shotcreting Services

    310090 Marine - Rehabilitation

    310095 Masonry Works

    310100 Road Maintenance/Repairs

    310110 Soil Reclamation

    310115 Soil Treatment/Cleaning/Sterilization

    310120 Soil Containment/Stabilization

    310130 Specialist Construction (Glazing, Domes, Shells etc.)

    310140 Fabrication (General)/Steel Structure Minor Works

    310150 Water Proofing Works

    310170 Aerial Survey Works

    3.2 Mechanical Plant/Equipment Works / Maintenance

    3.2.1 Turbines - Maintenance

    321010 Turbines - Gas

    321020 Turbines - Solar

    321030 Turbines - Steam

    32 1040 Turbines Major Components Reconditioning & Repairs

    3.2.2 Pumps, Compressors, Other Rotating Eqpt. - Maintenance

    322010 Air Blowers

    322020 Pumps Overhaul Other Than Cryogenic

    322025 Pumps Overhaul Cryogenic (LNG / LPG / Other Liquid Gases)

    322030 Compressors Overhaul

    322040 Diesel Engines Overhaul

    322050 Gas Compressor Stations Overhaul

    322080 Rotating Equipment - Others

    322090 Rotor Balancing

    3.2.3 Processing Plant & Equipments - Maintenance

    323010 Filters - Air/Process

    323030 Fuel Filtration Equipments

    323040 Process Equipments

    323060 Sulphur Forming Plants

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 27 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    WG CODE WORK GROUP (WG) DESCRIPTION

    GROUP 3.0 PLANT OPERATION & MAINTENANCE

    323070 Sulphur Handling Plants

    323080 Sulphur Recovery Plants

    323090 Water Treatment Plants - Clean Water (Feed)

    323100 Water Treatment Plants - Dirty Water/Effluent

    3.2.4 Boilers, Furnaces & Reactors - Maintenance

    324010 Boilers And H.R.B.

    324020 Heaters & Dryers

    324040 Furnaces

    324060 Reactors

    324070 Refractory Linings - Boilers, Furnaces etc.

    3.2.5 Heat Exchangers - Maintenance

    325010 Heat Exchangers - Refurbishment

    325020 Heat Exchangers Maint. Bundle Refurbishment

    325030 Heat Exchangers Maint. Chemical Cleaning

    325040 Heat Exchangers Maint. Mechanical Cleaning

    325050 Heat Exchangers Maint. Water Jetting

    3.2.6 Material Handling Equipments Maintenance

    326010 Material Handling Systems : Conveyers, Belts etc.

    326020 Earth Moving Equipment Maintenance

    326030 Loading Arms

    3.2.7 Shut Down - Maintenance

    327010 Refinery Shutdown Maintenance - Full Responsibility

    327020 Unit Shutdown Maintenance - Full Responsibility

    3.2.8 Other Mechanical Plants - Maintenance

    328010 Air Cooler Cleaning/Retubing

    328030 Flare Systems & Burn Pits

    328040 HV & AC Maintenance

    328050 Machining And Welding Services

    328075 Platform Maintenance - Onshore

    328100 Valves Refurbishment

    3.3 Piping, Columns And Tanks - Maintenance

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 28 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    WG CODE WORK GROUP (WG) DESCRIPTION

    GROUP 3.0 PLANT OPERATION & MAINTENANCE

    3.3.1 Piping - Maintenance

    331030 Heat Tracing Systems (Steam/Electrical)

    331040 Hot Tapping Works

    331050 On-Line Leak Sealing

    331060 Insulations, Cladding Repairs Piping

    331070 Piping - Low Temperature Service

    331100 Piping & Spools (Steel)Fabrication/Installation/Repairs/Renewal

    331110 Piping (R.T.R.P. & G.R.P.) Fabrication/Installation/Repairs/Renewal

    331120 Duplex Piping Fabrication/Repair/Replacement/Renewal

    3.3.2 Columns, Tanks, Vessels & Other Maintenance

    332010 Columns - Trays & Internals

    332020 Cooling Towers Maintenance

    332030 Rubber Linings (Tanks, Vessels, Columns)

    332040 Insulation, Cladding Repairs Columns, Tanks, Vessels

    332050 Tanks Sludge Removal

    332055 Tanks Overhaul Including Cleaning, Inspection, Repairs etc.

    332060 Internal Linings (Tanks, Vessels, Columns)

    3.4 Electrical Plant & Equipment - Maintenance

    3.4.1 Motors And Generators Maintenance

    341010 Balancing Of Motor Shafts

    341020 Electric Motors Dc/Variable Speed

    341030 Electric Motors Maintenance

    341050 Emergency Diesel Generators

    341060 Generators Overhaul And Repairs

    341070 Motor Operated Valves (M.O.V.)

    341080 Power Generation Maintenance

    341090 Rewinding & Servicing Of Generators

    341100 Rewinding/Repairs Of Motors

    341120 Solar Power Panels

    341140 Thyrister Drives

    3.4.2 Sub Stations, Switch Gears & Transformers - Maintenance

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 29 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    WG CODE WORK GROUP (WG) DESCRIPTION

    GROUP 3.0 PLANT OPERATION & MAINTENANCE

    342010 Transformers Servicing & Rewinding

    342020 Short Circuit Current Limitors

    342030 Substation Equipments Maintenance

    342050 Switch Gears Ht/Lt/MCC Maintenance

    342070 Switchyards

    3.4.3 Cables, Transmission And Distribution - Maintenance

    343010 Cable Trays/Racks Maintenance

    343030 Overhead Transmission Lines Maintenance

    344035 Corrosion Prevention/Monitoring System

    344040 Lighting Maintenance - General

    3.4.4 Other Electrical Plant & Equipments - Maintenance

    344010 Batteries/Battery Chargers / U.P.S.

    344020 Cathodic Protection Systems Maintenance

    344030 Control Panels/Stations Maintenance

    3.4.4 Other Electrical Plant & Equipments - Maintenance

    344035 Corrosion Prevention/Monitoring System

    344040 Lighting Maintenance - General

    344050 Earthing Systems

    344060 Electrical Testing Equipments

    344070 Street Lighting & Accessories - Maintenance

    344080 Industrial Lighting Systems - Hazardous Area

    344090 Industrial Wiring

    344100 Navigational Signalling Systems

    3.5 Instrumentation & Telecom. Systems - Maintenance

    350010 Analyzers

    350030 Anti - Surge Control Systems

    350040 Blending Systems

    350050 CCTV/CATV/MATV/LV Instrumentation Systems - Inst. & Maint.

    350090 Electronic Card Repairs

    350100 Emergency Shutdown Systems

    350110 Explosion & Weatherproof Telephones, Acoustic Booth etc.

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 30 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    WG CODE WORK GROUP (WG) DESCRIPTION

    GROUP 3.0 PLANT OPERATION & MAINTENANCE

    350120 Fire & Gas System Repairs

    350130 Instrument Shelter Cabins

    350135 Scada/ Supervisory & Management Control (SMC) Shelters

    350140 Instrumentation & Comm. Cabling (Underground)

    350150 Instrumentation & Communication Cabling (Overhead)

    350160 Instrumentation Tubing

    350170 Instrumentation Test/Repair Services

    350180 Instruments Measurement/Calibration Services

    350190 Lab Instruments Maintenance/Repairs

    350230 Metering Systems

    350240 Microwave Systems

    350250 Scada Systems/PLC

    350260 Pop Testing Of Safety Relief Valves

    350270 Pressure Regulating Stations

    350280 Process Control & Automation

    350300 Radio Paging Systems

    350320 Safety Control Systems

    350330 Satellite Systems

    350340 Telecommunication Cabling - Fiber Optic

    350350 Telecommunication Cabling - General

    350360 Telecommunication Equipment Repairs

    350370 Telephone Systems

    350380 Training Simulation Systems

    350390 Uhf Radiation

    350400 Vibration Monitoring Systems

    3.6 Inspection/Testing/Commissioning Services

    3.6.1 Inspection And Testing Services

    361010 Combustion/Gas Path Inspection Of Gas Turbines

    361020 Corrosion Inspection

    361030 Crude Assay/Testing

    361040 Heat Exchanger - Eddy Current Testing

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 31 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    WG CODE WORK GROUP (WG) DESCRIPTION

    GROUP 3.0 PLANT OPERATION & MAINTENANCE

    361050 Heat Exchanger - Hydraulic Testing

    361060 Hydraulic/Hydrostatic Testing

    361080 Inspection & Testing Of Lifts, Cranes, Slings, Tackles etc.

    361095 Material Testing Civil

    361096 Material Final Inspection

    361097 Laboratory Testing - Oil/Gas/Water etc.

    361098 Material Testing - Metallurgical

    361099 Material Testing Painting/Coating

    361100 Marine/Diving/Sub-Sea Inspection

    361120 Inspection Pipelines

    361125 Inspection Tanks/Vessels etc.

    361130 Soil Testing

    361140 Stress Analysis

    361150 Vibration Testing Of Rotating Equipments

    3.6.2 Commissioning Services

    362010 Commissioning & Start Up Services - Plant

    362020 Pipelines - Nitrogen Purging

    362030 Pipelines - Pigging Services

    362035 Pipelines Intelligent Pigging Services

    362040 Pipelines - Swabbing, Hydrotesting, Dewatering Drying

    3.7 General Plant Maintenance Services

    3.7.1 Hiring Services Plants

    371010 Hire of Cranes

    371020 Hire of Earth Moving Equipments

    371030 Hire of Heavy Lifts And Trailer Beds

    371040 Hire of Other Mechanical/Electrical Equipments

    371050 Hire of Test Equipments/Instruments

    371060 Hire of Transportation - Bulk Material

    3.7.2 Painting Services - Plants

    372010 Blasting & Painting - Steel Structure

    372020 Blasting & Painting Tanks, Vessels & Columns

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 32 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    WG CODE WORK GROUP (WG) DESCRIPTION

    GROUP 3.0 PLANT OPERATION & MAINTENANCE

    372025 Blasting & Painting - Piping

    372030 Blasting & Painting - Other Equipment

    372035 Blasting & Painting - Special

    372040 Marine Structure - Painting

    372050 Fire Proofing By Intumescent Painting

    372055 Fireproofing Works General

    3.7.3 Plant Cleaning Services

    373010 Chemical/Toxic Cleaning

    373025 Water Tanks Cleaning Industrial

    373030 Dumping Site Clearing

    373040 Excavation, Disposal & Treatment Of Contaminated Soils

    373050 Removal/Disposal of Waste Materials

    373060 Sewage Cleaning/Drainage Clearing Services

    373070 Dewatering Services

    373080 Hydrojetting

    3.7.4 Other Plant Operation/Maintenance Services

    374020 Camp Operation & Maintenance

    374025 Freight Forwarding & Clearance Services

    374027 Custom Clearance

    374029 Liquid Sulphur Transportation By Tankers

    374030 Carpentry Works

    374040 Catalyst Reclamation / Regeneration / Disposal

    374045 Corrosion Protection/Prevention Works

    374060 Dismantling

    374080 Heat Treatment - Post Weld (P.W.H.T.)/Stress Relieving

    374100 Industrial Doors (For Workshop & Factories)

    374110 Industrial Security Systems

    374130 Metal Spraying/Rebuilding

    374140 Cranes Maintenance (O.H)

    374160 Scaffolding Services

    374170 Sign Boards

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 33 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    WG CODE WORK GROUP (WG) DESCRIPTION

    GROUP 3.0 PLANT OPERATION & MAINTENANCE

    374180 Road Markings

    374205 Thermal Insulation - Other Than Pipeline & Pipings

    WG CODE WORK GROUP (WG) DESCRIPTION

    GROUP 4.0 INFORMATION SYSTEMS & TECHNOLOGIES

    Group 4 covers Consultancy, Development, Installation and Maintenance Contracts related to Information Systems & Technologies:

    400010 Computer Hardware (PC Servers & PCS) Maintenance

    400012 Super Computer, Mainframes And Mini Computer Systems (Branded) Maintenance

    400015 Electronic Document Management Systems (Imaging System etc.)

    400020 Computer Network Maintenance Site Work

    400030 Computer Networking And Network Management Turnkey

    400040 Business Application Software Packages (Development, Supply, Installation & Maintenance)

    400050 PCS., Printer, Plotter & Scanners (Supply & Installation)

    400055 Computer Peripherals & Components (Supply & Installation)

    400060 Computerization/It/Automation Studies/Consultancy

    400080 Branded Super Computers, Mainframes And Minicomputer Systems Supply, Installation & Maintenance

    400090 Networking Components (Bridges, Gateways, Routers, Hubs, Analyzer) - Supply & Installation

    400095 Structured Cabling/UTPS/Fiber Optics (Supply, Installation & Maintenance)

    400120 Software Development

    400125 Software Standard And Miscellaneous

    400130 IT Hardware Support Services Hardware Engineers

    400140 IT Software Support Services Software Engineers

    400150 Document Scanning & Indexing Services

    WG CODE WORK GROUP (WG) DESCRIPTION

    GROUP 5.0 EXPLORATION AND PRODUCTION RELATED SERVICES

    Group 5 covers Consultancy, Development, Installation and Maintenance Contracts related to Exploration and Production services:

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 34 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    WG CODE WORK GROUP (WG) DESCRIPTION

    GROUP 5.0 EXPLORATION AND PRODUCTION RELATED SERVICES

    500010 Cartographics Mapping

    500020 Cartographics Studies

    500030 Cartographics Topography

    500040 Drilling - Offshore Development

    500050 Drilling - Offshore Exploration

    500060 Drilling - Onshore Development

    500070 Drilling - Onshore Exploration

    500075 Exploration Related Software

    500080 Enhanced Oil Recovery Studies

    500090 Geological Studies

    500100 Gravitational Studies

    500105 Hydrographic Inspection Survey

    500110 Navigation & Positioning - Onshore

    500120 Oil Exploration Related Studies - Others

    500130 Reservoir Description Studies

    500140 Reservoir Development Studies

    500150 Reservoir Engineering Laboratory Software

    500160 Reservoir Simulation Software

    500170 Reservoir Studies Others

    500180 Reservoir Visualization Software

    500185 Remote Sensing & Image Processing Services

    500190 Seismic Data Acquisition

    500200 Seismic Data Processing / Evaluation

    500210 Seismic Data Interpretation

    500220 Seismic Studies Others

    500230 Seismic Tape Copying

    500240 Well Design

    500250 Well - Log Processing

    500260 Well - Logging & Perforating

    500270 Well Testing

    500280 Coiled Tubing Services

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 35 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    WG CODE WORK GROUP (WG) DESCRIPTION

    GROUP 5.0 EXPLORATION AND PRODUCTION RELATED SERVICES

    500290 Redressing Completion Equipment & SSS Valves

    500300 Wireline Services

    WG CODE WORK GROUP (WG) DESCRIPTION

    GROUP 6.0 PERSONNEL & MANPOWER SERVICES

    Group 6 covers Manpower Supply and other Personnel related Contracts and services:

    6.1 MANPOWER SUPPLY - ENGINEERS

    610010 Architects

    610020 Automation Engineers

    610030 Civil Engineers

    610040 Commissioning Engineers

    610050 Computer Hardware Engineers

    610060 Computer Software Engineers

    610070 Construction Engineers

    610080 Contracts Engineers

    610100 Corrosion Engineers

    610110 Cost Engineers

    610120 Data Network Engineers

    610130 Electrical Engineers

    610135 Geophysicist Engineers

    610140 QA/Qc/Inspection Engineers

    610150 Instrumentation Engineers

    610160 Operation Engineers

    610170 Materials Engineers

    610180 Mechanical Engineers

    610190 Pipeline Engineers

    610200 Process / Operation Engineers

    610210 Project Engineers

    610220 Purchasing Engineers/Buyers

    610222 Reliability Engineers

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 36 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    WG CODE WORK GROUP (WG) DESCRIPTION

    GROUP 6.0 PERSONNEL & MANPOWER SERVICES

    610225 Quantity Surveyors Engineers

    610230 Rotating Eqpt. Engineers

    610240 HSE Engineers (Health, Safety & Environmental)

    610245 System Analysts

    610250 Telecommunication Engineers

    610260 Planning / Scheduling Engineers

    610270 Supplier Qualification Engineers

    610900 Specialist Manpower

    610980 Engineers - Various Disciplines (For Main Consultants Only)

    6.2 MANPOWER SUPPLY - SUPERVISORS/TECHNICIANS

    620010 NDT Supervisor/Technicians

    620020 Coded Welders

    620030 Supervisors - Mech./Elec./Instr./Civil

    620040 Technicians - Mech/Elec./Instr & Pipe Fitters

    620045 Draftsman

    620050 Painters

    620060 Divers

    6.2 MANPOWER SUPPLY - SUPERVISORS/TECHNICIANS

    620070 Programmers

    6.3 MANPOWER SUPPLY NON TECHNICAL PERSONNEL

    630010 Financial Accountants

    630015 Legal Advisor

    630020 Staff For Clerical/Administration Services

    630030 Cleaning Supervisors/Officers

    630040 Catering Supervisors/Officers

    630042 Data Entry Clerks

    630045 Doctors And Medical Staff

    630050 Labours

    630060 Drivers / Operators (For Fork Lift etc.)

    6.4 OTHER PERSONNEL CONTRACTS/SERVICES

    640010 Management, Organisation & Development Consultancy

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 37 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    WG CODE WORK GROUP (WG) DESCRIPTION

    GROUP 6.0 PERSONNEL & MANPOWER SERVICES

    640015 Procedure Manuals & Systems Consultancy

    640020 Recruitment Services For Admin. & Non Technical Personnel

    640030 Recruitment Services For Managerial Personnel & Technical

    640040 Secondment Of Manpower

    640050 Specialized Training Services

    640060 Specialized Training Services HSE

    WG CODE WORK GROUP (WG) DESCRIPTION

    GROUP 7.0 FINANCE & LEGAL SERVICES

    Group 7 covers all Studies and Consultancy Contracts related to Financial Services:

    700010 Accounting Consultancy

    700020 Assets/Inventory And Records Management

    700030 Cost Engineering Consultancy

    700040 Financial Audit

    700045 Insurance Policies

    700050 Contractual/Claims Consultancy

    700052 Claims Consultants/Experts

    700055 Finance Related Policies & Procedure Manuals

    700060 System Audit

    700070 Risk Management & Insurance Consultancy

    710080 Legal Services Consultancy

    WG CODE WORK GROUP (WG) DESCRIPTION

    GROUP 8.0 MARKETING SERVICES

    Group 8 covers all Studies and Consultancy Contracts related to Marketing Services:

    800010 Marketing Studies

    800020 Ship Construction Supervision

    800030 Ship Loading Supervision

    800040 Ship Management

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 38 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    WG CODE WORK GROUP (WG) DESCRIPTION

    GROUP 9.0 ADMINISTRATION & GENERAL SERVICES

    Group 9 covers General Services related to Administration Services including maintenance for Offices, Buildings, Villas, Medical, etc.:

    9.1 CATERING SERVICES

    910020 Catering Services Clubs, Offices etc. Operation & Maintenance

    9.2 LEASING SERVICES

    920010 Leasing - Buses/Cars

    920020 Leasing - Industrial Areas

    920030 Leasing - Office Equipments/Machines

    920040 Leasing Transportation & Material Handling Equipments

    9.3 Medical & Hse Services

    930010 Medical Services (Pharmaceutical etc.)

    930020 Medical Services Management Of Hospitals/Clinics

    930030 Medical Equipment Maintenance

    930040 Studies On Health, Safety & Environment (HSE)

    930045 Study On Oil Spills/Marine Environment Protection

    930047 Harbour Pollution Control/Skimming/Debris Clean-Up Services

    930050 Medical Services Dental Clinics

    9.4 OFFICES, BUILDINGS AND VILLAS MAINTENANCE

    940010 Air Conditioning Central Plant (Chilled Water System) - Supply & Inst.

    940015 Air Conditioning Central Plant (Chilled Water System) Operation & Maint.

    940020 Air Conditioning Package/Split/Window Type - Supply & Inst.

    940022 Air Conditioning Package/Split/Window Type (Operation & Maint.)

    940023 Cold Storage Construction & Maintenance

    940025 Centralized Cooking Gas System

    940028 Fire Alarm & Detection System - Domestic

    940030 Plumbing & Sanitation - Supply & Inst.

    940032 Plumbing & Sanitation - Maintenance

    940040 General Building Maint. (Civil, Elect. & Plumbing)

    940050 Kitchen Cabinets & Fittings Supply, Installation & Maint.

    940060 Lifts / Elevators, Erection/Maintenance

    940070 Office Equipments, Furniture & Fixtures - Supply & Fixing

    940072 Office Equipment - Maintenance

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 39 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    WG CODE WORK GROUP (WG) DESCRIPTION

    GROUP 9.0 ADMINISTRATION & GENERAL SERVICES

    940075 Office Refurbishment & Furnishings - Projects

    940080 Partition (Metal) And Aluminium Claddings

    940090 Portable Buildings (Caravan, Rigid, Butler Buildings)

    940100 Potable Water Tankers For Buildings & Villas

    940102 Hire Of Portacabins/Caravans/Temporary Accommodation Units

    940105 Potable/Bottled Water And Water Cooler Services

    940110 Public Address Systems

    940120 Rubber Floorings (Sports, General)

    940130 H.T. Power Station/Substation/Switch Gear/Transmission Network - Supply & Inst.

    940140 H.T. Power Station/Substation/Switch Gear/Transmission Network - Maintenance

    940150 LV/MV Distribution Network, Panels, Protective Devices etc. - Supply & Inst.

    940160 LV/MV Distribution Network, Panels, Protective Devices etc. - Maintenance

    9.5 TRANSPORTATION SERVICES

    950010 Light Vehicle Maintenance

    950020 Shifting Of Office Partitions Along With Doors

    950030 Transport Maintenance/Repair Services

    950040 Transportation Office Furniture/Equipment & Household

    950050 Transportation Personnel

    9.6 CLEANING SERVICES

    960005 Cleaning/Protection Of Carpets/Upholstery/Curtains

    960010 Cleaning Internal Cleaning Of Buildings

    960015 Outdoor Cleaning & Road Sweeping

    960020 Cleaning HQ & Complex

    960030 Cleaning Public Health & Pest Control

    960035 Janitorial And Hygiene Services

    960040 Cleaning - Site Clearance/ Removal Service

    960045 Laundry Services

    960050 External Building Cleaning Using Cradles

    960060 Water Tanks Domestic (G.R.P., etc.) Cleaning / Repair / Replacement / Renewal

    960070 Tankers For Sewage Removal

    9.7 OTHER GENERAL SERVICES

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 40 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    WG CODE WORK GROUP (WG) DESCRIPTION

    GROUP 9.0 ADMINISTRATION & GENERAL SERVICES

    970010 Advertisement

    970015 Photography And Videography Services

    970020 Auctioning & Material Disposal

    970030 Automatic Control Doors & Barriers - Inst. & Maint.

    970050 Access Control Systems - Inst. & Maint.

    970060 Document/Office Automation Systems

    970070 Education & School Management

    970080 Education & Training

    970090 Fiber Glass Products Maintenance Services

    970100 Insulation Acoustic Etc. For Bldgs.

    970110 Landscaping/Irrigation Works

    970120 Lock-Smithy Services

    970130 Marble Suppliers and Fixers

    970135 Memberships - Clubs etc.

    970140 Painting Services Buildings

    970160 Printing & Publishing

    970170 Safety And Security - Buildings

    970180 Sand/Right Of Way Clearing

    970190 Spray Painting Of High Quality - Offices

    970200 Technical Documentation Services

    970205 Drafting Services

    970210 Water Tanks Linings Buildings

    970230 Courier Services

    970240 Travel & Tourism Services

    970250 Security & Surveillance Services

    9.7 OTHER GENERAL SERVICES

    970260 Boats : General Services/Maintenance

    970270 Hotels: Accommodation, Banqueting etc.

    970280 Recreational Services (Hotels, Clubs etc.)

    970290 Indoor/Outdoor Plants, Garden - Maintenance

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 41 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    ATTACHMENT 5: PRE-QUALIFICATION REQUIREMENT FOR SUBCONTRACTORS

    Method A: Approved List by ADNOC and its Operating Companies (OPCOs)

    Received Registration/Qualification number of Sub-Contractors holding current positive qualification with ADNOC and its Operating Companies, specifying with which Company they are qualified/registered for each relevant work group experience.

    a. Subcontractors qualified with Takreer/Gasco/Borouge will be assumed as

    prequalified (code Q) for the project for the same commodity code; b. Subcontractors holding current valid qualification with ADNOC or other OPCOs

    (different from the above) will need to be prequalified during the EPC execution by the awarded Contractor but exempted from the commercial section of the prequalification and subject to Company approval;

    c. Subcontractors without current qualification will all be classified as TBQ in full by the Contractor during execution and subject to Company review and approval.

    Method B: Evaluating Technical and Commercial Information

    Technical - Experience and Capability Requirements

    Brief description of the organisation structure (both global and local) and resources (offices, manpower and equipment);

    Details of direct experience of similar jobs in the last five years, tabulating the following:

    Name of the project

    Project scope

    Project value

    Ultimate client

    SUBCONTRACTORs scope and value

    Completion date.

    Current workload and availability of resources to comply with schedule requirements;

    Copy of Quality Assurance Certification;

    Evidence of documented Health, Safety and Environmental Systems and Procedures, such as copy of ISO 14001, an index of the HSE manual, etc.

    Evidence of Safety Record.

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 42 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    Commercial

    Copies of Balance Sheets for the last three years;

    Details of outstanding litigations, if any;

    Typical Insurance Coverage values related to workmen compensation, employers liability, third party liability, plant and equipment, etc;

    Copy of valid Registration Certificate from Abu Dhabi Chamber of Commerce & Industry covering the services to be provided;

    Copy of Oil and Gas Classification for above;

    Copy of valid CONTRACTOR Classification from Abu Dhabi Planning Department, if available;

    Copy of valid Consultant Registration Certificate from Abu Dhabi Planning Department (for Consultant only), if available;

    Copy of Registration with COMPANY.

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 43 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    ATTACHMENT 6: NOMINATED/RESTRICTED VENDOR LIST

    ATTACHMENT 6.1 Vendor List for Standardised Equipment

    Please refer to Attachment 11 for Vendor List for Standardised Equipment.

    ATTACHMENT 6.2 Vendor List for Licensor Equipment

    (a) Where a LICENSOR specifies mandatory VENDORS, CONTRACTOR shall utilise those VENDORS, and the VENDORS listed in this Attachment 6.2 are classified by COMPANY as Class Q (refer to Section 8.2.3 above).

    Nominated/Restricted Vendor List for Licensor Equipment

    SL. Item Description Vendor Name

    1 Platforming Unit Catalyst Regeneration Control System

    UOP

    2 Parex Unit Rotary Valve and peripheral equipment

    UOP

    3 Parex Unit Adsorbent Chamber Control System UOP

    4 Parex Unit Adsorbent Chamber internals UOP 5 Packinox Alfa Laval

    6 High Capacity MD trays (UOP MD and Slotted Sieve tray decks, downcomers, installation hardware and distributors; Raschig Super-Rings, distributors, bed limiters, bed supports and installation hardware)

    UOP

    7 Hi Flux tubing UOP

    (b) Where a Licensor recommends VENDORS, but those VENDORS are not mandatory, CONTRACTOR shall proceed in accordance with Section 8 above including checking if VENDOR is pre-approved for the GOODS (listed in Attachment 7 below) and if necessary, seeking APPROVAL for non-approved VENDORS in accordance with this Procedure.

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS

    AND VENDORS

    Page 44 of 154

    CC01A-0-00000-PS-PRO-0004 Rev3 DSN : 848

    ATTACHMENT 6.3

    Nominated/Restricted Vendor List Other Goods

    SL. Item Description Product Group

    No. Vendor Name Location Local Agent

    1 ICS GOODS 318510 Honeywell Middle East Ltd- Abu Dhabi Abu Dhabi

    Not applicable

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS AND VENDORS

    Page 45 of 154

    CC01A-0-00000-PS-PRO-0004 Rev 3 DSN : 848

    ATTACHMENT 7: VENDOR LIST FOR MAJOR GOODS

    VENDOR LIST FOR MAJOR GOODS

    S/NO Material Group Description Vendor Name Country Comments Vendor Name Country Comments

    1 Structural steel frame

    Al Zamil KSA Ak&P_Factory Abdulla B. Al-Khalita

    KSA

    Geyad For Commerce KSA Energya Steel

    KSA

    Contech UAE Hidada

    KSA

    Icom Engineering ITALY Hanmaek Heavy Industry

    KOREA

    Anors ITALY Kook Jae Metal

    KOREA

    Cleveland Bridge UAE Younghwa Engineering

    KOREA

    NPCC UAE Thai Herrick Co. Ltd.

    THAILAND

    Tiger Steel UAE Emirates Building System

    UAE

    William Hare UK Icom S.R.L. ITALY

    Severfield Reeve International UK

    AIC - Arabian International Co. KSA

    2 Gas/liquid incineration plant

    John Zinc USA Han Yang Industry Co., Ltd.

    KOREA

    Zeeco USA Hwaseong Plant

    KOREA

    Flare Industry

    USA

    Callidus

    USA

    Hamworthy ITALY

    Technip KTI

    ITALY

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS AND VENDORS

    Page 46 of 154

    CC01A-0-00000-PS-PRO-0004 Rev 3 DSN : 848

    3 Thermal Oxidizer

    Hamworthy ITALY

    Callidus

    USA

    Durr

    GERMANY

    Zohn Zink

    USA

    Technip Kti

    ITALY

    Itas ITALY

    Zeeco

    UK

    Nao

    USA

    Alstom

    JAPAN

    Hitachi JAPAN

    4 Carbon steel columns dia

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS AND VENDORS

    Page 47 of 154

    CC01A-0-00000-PS-PRO-0004 Rev 3 DSN : 848

    Il Sung KOREA Nuova Tubital ITALY

    Daekyung Machinery KOREA Inoxtecnica ITALY

    Samsung Heavy KOREA Fai ITALY

    Zamil Steel KSA Omsa ITALY

    Olayan DESCON KSA Inco

    UAE

    Gulf Engineering KSA Gmmos

    UAE

    Isgec INDIA KNM FBM

    UAE

    Godrej INDIA Adyard

    UAE

    NPCC UAE Belleli Energy

    UAE

    Ramsis BAHRAIN Gsme

    UAE

    Gmmos

    UAE

    Maritime Industrial Services (Mis)

    UAE

    Inma

    UAE

    Cimtas

    TURKEY

    5 Carbon steel columns dia 25mm

    Dettin ITALY Wooyang Hc

    KOREA

    Sices ITALY AHA M Tech

    KOREA

    VRV ITALY Daewoo Heavy Ind.

    KOREA

    Sirz ITALY Daebong

    KOREA

    Officine Maraldi ITALY Hanbal

    KOREA

    O.C.S. ITALY DKT

    KOREA

    C.A.M.P.I. ITALY Duro Felguera

    SPAIN

    Brembana ITALY Gbm ITALY

    Nicola & Albia ITALY Gam ITALY

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS AND VENDORS

    Page 48 of 154

    CC01A-0-00000-PS-PRO-0004 Rev 3 DSN : 848

    Cividac ITALY Nuova Tubital ITALY

    Rolle ITALY Simic ITALY

    Wts - Walter Tosto ITALY Sices ITALY

    ATB ITALY Ims Scardellato ITALY

    Mangiarotti ITALY FBM ITALY

    Rosetti Marino ITALY Smim ITALY

    Simic ITALY Fai ITALY

    FBM-KNM FZCO (ex FBM) UAE/ITALY CCM ITALY

    Godrej INDIA Simic ITALY

    Isgec INDIA Vijay Tanks & Vessels

    INDIA

    Larsen & Toubro INDIA KNM FBM

    UAE

    Sung Jin KOREA Adyard

    UAE

    Il Sung KOREA Inma

    UAE

    Hantech KOREA Inco

    UAE

    Sewon KOREA National Petroleum Cons. Co. (Npcc)

    UAE

    Daekyung Machinery KOREA Descon Engineering Fze

    UAE

    Doosan KOREA Belleli Energy

    UAE

    G&G BELGIUM Gmmos

    UAE

    Ramsis BAHRAIN Cimtas

    TURKEY

    Olayan KSA

    Zamil Steel KSA

    Gulf Engineering KSA

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS AND VENDORS

    Page 49 of 154

    CC01A-0-00000-PS-PRO-0004 Rev 3 DSN : 848

    6 Structured packings Baretti Giovanni ITALY Hanbal KOREA

    Koch Glitsch Italia ITALY

    Saint-Gobain NorPro (UK) ex Norton UK

    Sulzer Chemtech Italia ITALY

    Raschig GERMANY

    7 Valve trays Baretti Giovanni ITALY

    Hanbal KOREA

    Koch Glitsch Italia ITALY

    Saint-Gobain NorPro (UK) ex Norton UK

    Sulzer Chemtech ITALY

    8 Carbon steel atmospheric vessels

    GBM ITALY Daebong Acrotec

    KOREA

    Nuova Tubital ITALY Seoul Machinery

    KOREA

    InoxTecnica ITALY AHA M Tech

    KOREA

    GAM ITALY Doosan Mecatec

    KOREA

    SICES ITALY DKT

    KOREA

    NPCC UAE Sewon

    KOREA

    Zamil Steel

    KSA

    Smim ITALY

    Gam ITALY

    Omsa ITALY

    Modomec ITALY

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS AND VENDORS

    Page 50 of 154

    CC01A-0-00000-PS-PRO-0004 Rev 3 DSN : 848

    KNM FBM

    UAE

    Godrej

    INDIA

    Descon Engineering Fze

    UAE

    Adyard

    UAE

    Inco

    UAE

    Ferrofab

    9 Stainless steel atmospheric vessels

    NPCC UAE Daebong Acrotec

    KOREA

    Dettin ITALY Seoul Machinery

    KOREA

    InoxTecnica ITALY AHA M Tech

    KOREA

    GAM ITALY Doosan Mecatec

    KOREA

    Nuova Tubital ITALY DKT

    KOREA

    GBM ITALY Il Sung

    KOREA

    Zamil Steel

    KSA

    Knm

    UAE

    Godrej

    INDIA

    Descon Engineering Fze

    UAE

    Adyard

    UAE

    Ferrofab

    UAE

    10 Carbon steel pressure vessels thickness

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS AND VENDORS

    Page 51 of 154

    CC01A-0-00000-PS-PRO-0004 Rev 3 DSN : 848

    GBM ITALY AHA M Tech

    KOREA

    ISGEC ITALY Doosan Mecatec

    KOREA

    SIMIC ITALY Zamil Steel

    KSA

    I.M.S. Scardellato ITALY Omsa ITALY

    InoxTecnica ITALY Smim ITALY

    Mangiarotti ITALY Inco

    UAE

    Nuova Tubital ITALY Godrej

    INDIA

    Gam ITALY Descon Engineering Fze

    UAE

    C.A.M.P.I. ITALY Ferrofab

    UAE

    FBM-KNM FZCO (ex FBM) UAE

    NPCC UAE

    Hantech KOREA

    Sungjin KOREA

    Ramsis BAHRAIN

    ASB GERMANY

    OLYAN DESCON PAKISTAN

    11 Carbon steel pressure vessels thickness 2500mm

    Nicola & Albia ITALY DKT

    KOREA

    GAM ITALY Sewon

    KOREA

    Dettin ITALY Wooyang Hc

    KOREA

    Simic ITALY Daebong

    KOREA

    I.M.S. Scardellato ITALY Seoul Machinery

    KOREA

    InoxTecnica ITALY Aha M Tech

    KOREA

    FBM-KNM FZCO (ex FBM) UAE Il Sung

    KOREA

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS AND VENDORS

    Page 52 of 154

    CC01A-0-00000-PS-PRO-0004 Rev 3 DSN : 848

    Sung Jin KOREA Doosan Mecatec

    KOREA

    Hantech KOREA Zamil Steel

    KSA

    Daekyung Machinery KOREA Mangiarotti

    ITALY

    Gulf Engineering KSA Gbm

    ITALY

    Olayan DESCON KSA Rolle

    ITALY

    Ramsis BAHRAIN Omsa

    ITALY

    ASB GERMANY Nuova Tubital

    ITALY

    Smim

    ITALY

    Sices

    ITALY

    Brembana

    ITALY

    SICES

    ITALY

    Isgec

    INDIA

    Godrej

    INDIA

    Ferrofab

    UAE

    Inma

    UAE

    Maritime Industrial Services (Mis)

    UAE

    Knm

    UAE

    Adyard

    UAE

    Descon Engineering Fze

    UAE

    Inco

    UAE

    12 Carbon steel pressure

    vessels thickness >50mm

    Wts - Walter Tosto ITALY DKT

    KOREA

    VRV ITALY Hantech

    Korea

    Sices ITALY Belleli Energy

    ITALY

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS AND VENDORS

    Page 53 of 154

    CC01A-0-00000-PS-PRO-0004 Rev 3 DSN : 848

    Mangiarotti ITALY Vijay Tanks & Vessels

    INDIA

    Cividac ITALY Cimtas

    TURKEY

    I.M.S. Scardellato ITALY

    Off. Luigi Resta ITALY

    Rosetti Marino ITALY

    Sirz ITALY

    FBM-KNM FZCO (ex FBM) UAE

    Dettin ITALY

    Orlandi Impianti ITALY

    I.M.S. Scardellato ITALY

    Simic ITALY

    ASB GERMANY

    Sewon KOREA

    Sung Jin KOREA

    Il Sung KOREA

    Hantech KOREA

    Doosan KOREA

    Larsen & Toubro INDIA

    Isgec INDIA

    Godrej INDIA

    NPCC UAE

    Ramsis BAHRAIN

    Gulf Engineering KSA

    Olayan DESCON PAKISTAN

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS AND VENDORS

    Page 54 of 154

    CC01A-0-00000-PS-PRO-0004 Rev 3 DSN : 848

    13 S.S. pressure vessels thickness

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS AND VENDORS

    Page 55 of 154

    CC01A-0-00000-PS-PRO-0004 Rev 3 DSN : 848

    14 Stainless steel pressure vessels thickness >25mm

    SIMIC ITALY DKT

    KOREA

    Dettin ITALY Wooyang Hc

    KOREA

    Daebong

    KOREA

    Orlandi Impianti ITALY AHA M Tech

    KOREA

    Cividac ITALY Doosan Mecatec

    KOREA

    Sices ITALY Zamil Steel

    KSA

    Mangiarotti ITALY SICES ITALY

    Wts - Walter Tosto ITALY Gbm ITALY

    Inox Tecnica ITALY Inoxtecnica ITALY

    Nicola & Albia ITALY Brembana ITALY

    Sirz ITALY Omsa ITALY

    C.A.M.P.I. ITALY Smim ITALY

    Sung Jin KOREA Godrej

    INDIA

    Il Sung KOREA Vijay Tanks & Vessels

    INDIA

    Hantech KOREA Duro Felguera

    SPAIN

    G.A.M. ITALY Adyard

    UAE

    I.M.S. Scardellato ITALY Descon Engineering Fze

    UAE

    Gulf Engineering KSA Ferrofab

    UAE

    Isgec INDIA Maritime Industrial Services (Mis)

    UAE

    Larsen & Toubro INDIA Cimtas

    TURKEY

    Ramsis BAHRAIN

    NPCC UAE

    FBM-KNM FZCO (ex FBM) UAE

    Olayan DESCON PAKISTAN

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS AND VENDORS

    Page 56 of 154

    CC01A-0-00000-PS-PRO-0004 Rev 3 DSN : 848

    ASB GERMANY

    Sewon KOREA

    15 API storage tanks site assembled

    CBI USA/UAE Hascon Engineering ITALY

    TKK Japan Descon Engineering Fze

    UAE

    NPCC UAE Hantech

    KOREA

    Olayan Descon KSA

    16 Silencers and sound enclosure

    Boldrocchi ITALY

    CTM ITALY

    Bosco Italia ITALY

    Burgess Manning (UK) UK

    17 C.S. shell and tube heat exchangers dia

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS AND VENDORS

    Page 57 of 154

    CC01A-0-00000-PS-PRO-0004 Rev 3 DSN : 848

    Metallurgica Medolago ITALY Smim ITALY

    Rolle ITALY Precision

    INDIA

    SIMIC ITALY Descon Engineering Fze

    UAE

    Il Sung KOREA

    Sung Jin KOREA

    Daekyung Machinery KOREA

    Olayan Descon KSA

    ZAMIL STEEL KSA

    FBM-KNM FZCO (ex FBM) UAE

    Gulf Engineering KSA

    Ramsis BAHRAIN

    18 C.S. shell and tube heat exchangers dia >1m

    FBM-KNM FZCO (ex FBM) UAE Hantech KOREA

    Samsung Heavy KOREA Tsm Tech KOREA

    Il Sung KOREA Sewon Cellontech KOREA

    Hantech KOREA Wooyang Hc KOREA

    Doosan KOREA DKT KOREA

    Sewon KOREA Jmc KOREA

    Sung Jin KOREA Daekyung Technos KOREA

    Sices ITALY Daekyung Machinery KOREA

    Mangiarotti ITALY Bumwoo Eng. Co., Ltd. KOREA

    Koch Heat Transfer (ex IMB-Brown Fintube

    ITALY Daebong Acrotec KOREA

    Olmi ITALY Bronswerk NL

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS AND VENDORS

    Page 58 of 154

    CC01A-0-00000-PS-PRO-0004 Rev 3 DSN : 848

    Cividac ITALY Omsa ITALY

    Off. Luigi Resta ITALY Gbm ITALY

    VRV ITALY Smim ITALY

    Brembana ITALY Resta ITALY

    Nicola & Albia ITALIA Precision INDIA

    Rolle ITALY Descon Engineering Fze UAE

    C.A.M.P.I. ITALY

    Villa Scambiatori ITALY

    Ravagnan ITALY

    Ims Scardellato ITALY

    Dettin ITALY

    SIMIC ITALY

    Metallurgica Medolago ITALY

    Olayan Descon KSA

    Gulf Engineering KSA

    Ramsis BAHRAIN

    19 S.S. shell and tube heat exchangers dia

  • PROJECT PROCEDURE

    CRITERIA FOR SELECTION OF SUBCONTRACTORS AND VENDORS

    Page 59 of 154

    CC01A-0-00000-PS-PRO-0004 Rev 3 DSN : 848

    Cividac ITALY Jmc

    KOREA

    Metallurgica Medolago ITALY Bronswerk

    NL

    SICES ITALY Descon Engineering Fze

    UAE

    Ravagnan ITALY