424
CONTRACT DOCUMENTS AND TECHNICAL SPECIFICATIONS FOR RELOCATION OF SEWER LINE AT LOT L-1 AIRLINE DRIVE KENNER,LA. MAYOR "Ben" Zahn III COUNCIL Kristi K. McKinney, Councilwoman at Large Division A Thomas P. "Tom" Willmott, Councilwoman at Large Division B Gregory W. Carroll, Councilwoman District 1 Michael G. Sigur, Councilman District 2 Glenn W. Hayes Sr., Councilman District 3 George L. Branigan, Councilwoman District 4 Brian Brennan, Councilman District 5 CHIEF OF POLICE Michael J. Glaser Rahman and Associates, Inc. 3645 Williams Blvd., Suite 208 Kenner, Louisiana 70065 Project No. RA2 1905 PUBLIC WORKS PROJECT NO. PW-2018-14-SW

TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

CONTRACT DOCUMENTS

AND

TECHNICAL SPECIFICATIONS

FOR

RELOCATION OF SEWER LINE AT LOT L-1 AIRLINE DRIVE

KENNER,LA.

MAYOR"Ben" Zahn III

COUNCIL

Kristi K. McKinney, Councilwoman at Large Division A Thomas P. "Tom" Willmott, Councilwoman at Large Division B

Gregory W. Carroll, Councilwoman District 1Michael G. Sigur, Councilman District 2

Glenn W. Hayes Sr., Councilman District 3 George L. Branigan, Councilwoman District 4

Brian Brennan, Councilman District 5

CHIEF OF POLICEMichael J. Glaser

Rahman and Associates, Inc. 3645 Williams Blvd., Suite

208Kenner, Louisiana 70065

Project No. RA2 1905

PUBLIC WORKS PROJECT NO. PW-2018-14-SW

SEALED BID 19-6513

1

Page 2: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

2

TABLE OF CONTENTS

TABLE OF CONTENTS.........................................................................................................................1 thru 3

INVITATION TO BID............................................................................................................................4 thru 5

INFORMATION AVAILABLE TO BIDDERS……………………………………………………….6 thru 12

INSTRUCTIONS TO BIDDERS…. .......................................................................................................... …

SECTION I.BIDDING AND CONTRACT DOCUMENTS REQUIRED OF ALL BIDDERS

BID FORM ..........................................................................................................................................13 thru 16

BID BOND ..........................................................................................................................................17 thru 18

SECTION II.DOCUMENTS REQUIRED OF SUCCESSFUL BIDDER

AFFIDAVIT ...................................................................................................................................................19

CORPORATE RESOLUTION (SAMPLE) ...................................................................................................20

AGREEMENT.................................................................................................................................... 21 thru 26

HOLD HARMLESS AGREEMENT .............................................................................................................27

PERFORMANCE BOND...................................................................................................................28 thru 29

LABOR AND MATERIALS (PAYMENT BOND) ...........................................................................30 thru 31

AFFIDAVIT-EMPLOYMENT STATUS VERIFICATIONS………………………………………….........32

ATTESTATION CLAUSE OF PAST CRIMINAL CONVICTIONS…………………………………… 33

SECTION III.

SUPPLEMENTARY CONDITIONS.....................................................................................SC-1 to SC-11

GENERAL CONDITIONS……………………………………………………….………... GC-1 to GC-41

SECTION IV.TECHNICAL SPECIFICATIONS

DIVISION I - GENERAL REQUIREMENTS

Page 3: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

TC-1

TABLE OF CONTENTS

Page No.DIVISION III – TECHNICAL SPECIFICATIONS

SECTION 01010 – SUMMARY OF WORK.........................................................................1 thru 3

SECTION 01025 – MEASUREMENT AND PAYMENT...................................................1 thru 11

SECTION 01030 – SPECIAL PROJECT PROCEDURES....................................................1 thru 4

SECTION 01041 – PROJECT COORDINATION.................................................................1 thru 3

SECTION 01043 – JOB SITE ADMINISTRATION.......................................................................1

SECTION 01045 – CUTTING AND PATCHING...........................................................................1

SECTION 01051 – CONSTRUCTION LAYOUT...........................................................................1

SECTION 01060 – REGULATORY REQUIREMENTS................................................................1

SECTION 01070 – ABBREVIATIONS, SYMBOLS, TRADENAMES AND MATERIALS..................................................................1 thru 2

SECTION 01090 – REFERENCE STANDARDS...........................................................................1

SECTION 01115 – CONTROL OF WORK..........................................................................1 thru 4

SECTION 01152 – REQUEST FOR PAYMENT..................................................................1 thru 2

SECTION 01153 – CHANGE ORDER PROCEDURES.......................................................1 thru 5

SECTION 01200 – PROJECT MEETINGS...........................................................................1 thru 4

SECTION 01311 – CONSTRUCTION SCHEDULES..........................................................1 thru 2

SECTION 01340 – SHOP DRAWINGS, PRODUCT DATA AND SAMPLES....................1 thru 5

SECTION 01370 – SCHEDULE OF VALUES.....................................................................1 thru 2

SECTION 01390 – EXCAVATION PLAN...........................................................................1 thru 2

SECTION 01400 – QUALITY CONTROL...........................................................................1 thru 2

SECTION 01410 – TESTING LABORATORY SERVICES.................................................1 thru 6

SECTION 01505 – MOBILIZATION....................................................................................1 thru 2

Page 4: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

TC-2

TABLE OF CONTENTS (Continued)

SECTION 01510 – TEMPORARY UTILITIES.....................................................................1 thru 4

SECTION 01530 – PROTECTION OF EXISTING FACILITIESAND PROPERTY.................................................................................1 thru 11

SECTION 01600 – MATERIAL AND EQUIPMENT.....................................................................1

SECTION 01610 – TRANSPORTATION AND HANDLING........................................................1

SECTION 01620 – STORAGE AND PROTECTION...........................................................1 thru 2

SECTION 01630 – PRODUCT OPTIONS AND SUBSTITUTIONS..............................................1

SECTION 01700 – DEMOBILIZATION...............................................................................1 thru 2

SECTION 01720 – PROJECT RECORD DOCUMENTS.....................................................1 thru 3

SECTION 01740 – WARRANTIES AND BONDS.........................................................................1

SECTION 02100 – SITE PREPARATION......................................................................................1

SECTION 02110 – SALVAGE OR ABANDONMENT OF EXISTING MATERIALS..................1

SECTION 02120 – REMOVAL OF STRUCTURES AND OBSTRUCTIONS..............................1

SECTION 02140 - DEWATERING AND PRESSURE RELIEF...........................................1 thru 3

SECTION 02160 - SHEETING, SHORING, AND BRACING.............................................1 thru 3

SECTION 02210 – GRADING........................................................................................................1

SECTION 02221 – EXCAVATION, BACKFILLING FOR TRENCHES,PAVEMENT AND STRUCTURES........................................................1 thru 5

SECTION 02272 – GEOTEXTILE FABRIC.........................................................................1 thru 2

SECTION 02622 - POLYVINYL CHLORIDE PIPE............................................................1 thru 4

SECTION 02950 - LANDSCAPING.....................................................................................1 thru 3

SECTION 02999 – MISCELLANEOUS WORK AND CLEANUP...................................1 thru 2

SECTION 03100 – CONCRETE FORMWORK.................................................................1 thru 6

SECTION 03200 – CONCRETE REINFORCEMENT.......................................................1 thru 3

Page 5: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

TC-3

TABLE OF CONTENTS (Continued)

SECTION 03300 – CAST-IN-PLACE CONCRETE...........................................................1 thru 9

SECTION 05500 – MISCELLANEOUS METAL...............................................................1 thru 5

SECTION 706 – CONCRETE WALKS, DRIVES AND INCIDENTAL PAVING...........1 thru 2

SECTION 707 – CURBS AND GUTTER TECH SPECS...................................................1 thru 2

SECTION 708 – GRAVITY SANITARY SEWER SYSTEM TECH SPECS....................1 thru 8

Page 6: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

4

INVITATION TO BID

The City of Kenner will receive sealed bids for Relocation of Sewer Line at Lot L-1, Airline Drive, Kenner, Louisiana. The proposed work includes: The project requires installation of new 10” sewer main along east site of the lot L-1 with four manholes and connect with existing manholes on each end. Abandon existing 8” sewer main and fill with cement sand mixture.

Sealed Bids will be received by the City of Kenner, in the Finance Department, 1610 Rev. Richard Wilson Drive, Kenner, Louisiana 70062 until December 10, 2019 at 9:45 a.m.. Bids will not be accepted after this time. All interested parties are invited to attend the bid opening on the same day at 10:00 a.m. in the City of Kenner Building D Auditorium, 1610 Rev. Richard Wilson Drive, Kenner, Louisiana, at which time they will be publicly read.

There will be a pre-bid meeting on Tuesday, November 26, 2019 at 2 P.M. at the City of Kenner Building D Auditorium, 1610 Rev. Richard Wilson Drive, Kenner, LA 70062. All interested bidders are encouraged to attend.

All Bids must be in accordance with the Contract Documents on file with Rahman and Associates, Inc., 3645 Williams Blvd., Suite 208, Kenner, LA 70065 the Design Consulting Professionals for this project.

Copies of Bidding Contract Documents for review or for use in preparing bids may be obtained from Rahman and Associates, Inc., 3645 Williams Blvd., Suite 208, Kenner, LA 70065 upon deposit of $150.00 for each set of documents. Deposits on the first set of documents furnished bona fide prime bidders will be refunded upon return of the documents in good condition no later than ten days after receipt of bids.

Contractors may also obtain copies of bidding contract documents for review and may also submit bids electronically by visiting www.centralauctionhouse.com. If submitting bid electronically, a bid bond is the only acceptable form of bid security. A cashier’s or certified check will NOT be accepted.

Any bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq. Bidders must write their Louisiana State Contractor’s license number on the outside of the bid envelope prior to bid submission for public works construction projects estimated at $50,000 and above. In the case of an electronic bid proposal, a contractor may submit an authentic digital signature on the electronic bid proposal accompanied by the contractor’s license number in order to meet the requirements of LSA-R.S. 37:2163. Except as otherwise provided herein, if the bid does not contain the contractor’s certification and show the contractor’s license number on the bid envelope, the bid shall be automatically rejected, shall be returned to the bidder marked “REJECTED” and shall not be read aloud.

Bids will be received on a lump sum price basis. If a Contract for the Work is to be awarded, it will be awarded to the lowest responsive Bidder, who had Bid in accordance with the requirements of the Bidding Documents, as determined by the Owner's evaluation of the corresponding Bid Form and Bid Form Attachments. Determination of the lowest Bidder shall be on the basis of the sum of the Base Bid and any Alternates accepted by the Owner, subject to the Owner's and the Design

Page 7: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

5

Professional's evaluation of the corresponding Bid Form and Bid Form Attachments in accordance with all applicable bidding Requirements and the provisions of Louisiana Public Contracts Law.

The bid prices shall include all such taxes and the costs of all required permits, insurance and bonds, if any.

The Work is to commence within 10 days after the Notice to Proceed. Completion of the Work is required within 40 calendar days from Notice to Proceed.

In accordance with LA R.S. 38:2212 and Louisiana Administrative Code 34:III.Chapter 3 §307, bid submission shall conform to those requirements as stipulated on the Louisiana Uniform Public Work Bid Form. Bidder must submit a bid security in the form of bid bond, cashier’s check, or certified check in the amount of 5% of the contract price in favor of the City of Kenner. If submitting bid electronically, a bid bond is the only acceptable form of bid security. A cashier’s or certified check will be NOT accepted

The successful Bidder will be required to furnish a Performance Bond and Payment Bond in the amount equal to 100 percent of the Contract Price guaranteeing faithful performance and the payment of all bids and obligations arising from the performance of the contract. Bonds submitted in accordance with the requirements of this contract shall be provided by a company or companies having at least an "A" or better financial rating and a Class B or better General Policy holders rating according to the latest A.M. Best Company ratings.

Sureties will be required to meet qualifications set forth in the Contract Documents.

No Bid may be withdrawn within a period of 45 days after the date fixed for opening bids.

For just cause, the City of Kenner reserves the right to reject any and all Bids, and to waive informalities.

CITY OF KENNER

Sealed Bid No. 19-6513 /s/Michael T. Wetzel Chief Financial Officer

Advertisement:The AdvocateNovember 13, 20, 27, 2019

Page 8: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

6

INFORMATION AVAILABLE TO BIDDERS

INSTRUCTIONS TO BIDDERS - LIST OF SUBJECTS

B-1 CROSS REFERENCE TO PRIMARY STATEMENTS B-2 QUALIFICATION OF BIDDERSB-3 LOUISIANA LICENSE REQUIREMENTSB-4 FAMILIARIZATION WITH THE WORKB-4.01. Site ConditionsB-5 INTERPRETATIONSB-6 TAXES AND PERMITSB-7 BID SECURITYB-8 RETURN OF BID SECURITYB-9 CONTRACT TIMEB-10 SUBCONTRACTORSB-10.01. SuppliersB-11 BIDSB-11.01. Bid Form B-11.02. Bid PricingB-11.03. Submission of BidsB-11.04. Modification and Withdrawal of Bids B-11.05. Bids to Remain OpenB-12 AWARD OF CONTRACTB-13 EXECUTION OF AGREEMENTB-14 COPIES OF CONTRACT DOCUMENTSB-15 LOCAL MATERIALS AND FIRMSB-16 WORK SCHEDULINGB-17 WORK ON PRIVATE PROPERTYB-18 USE OF POTABLE WATERB-19 PURPOSE AND INTENT OF PROJECTB-20 PERFORMANCE AND PAYMENT BONDB-21 SUPPLEMENTARY INSURANCEB-22 FORMS

Page 9: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

7

B-1 CROSS REFERENCE TO PRIMARY STATEMENTS . Definitions, requirements, and limitations affecting the bidding are contained in the various contract documents, and are not necessarily repeated in these instructions. The following is a partial list of applicable provisions and their locations:

Availability of Land General Conditions and Division 1Bonds and Insurance General and Supplemental ConditionsDefinitions General and Supplemental Conditions Detailed Description of the Work Division 1Liquidated Damages AgreementLaws and Regulations General and Supplemental ConditionsRetainage Agreement and Supplemental Conditions Subsurface Investigations General and Supplemental Conditions

B-2 QUALIFICATIONS OF BIDDERS . Bidders may be required to submit evidence that they have a practical knowledge of the particular Work bid upon, and that they have the financial resources to complete the proposed Work.

In determining the Bidder's qualifications, the following factors will be considered: Work previously completed by the Bidder and whether the Bidder (a) maintains a permanent place of business, (b) has adequate plant and equipment to do the Work properly and expeditiously, (c) has the financial resources to meet all obligations incidental to the Work, and (d) has appropriate technical experience.

Each Bidder may be required to show that former work has been handled and that no just claims are pending against such work. No Bid will be accepted from a Bidder who is engaged in any work which would impair the Bidder's ability to perform or financially manage this Work.

B-3 LOUISIANA LICENSE REQUIREMENTS . State regulations require that any prospective Bidder on construction contracts of $50,000.00 or greater obtain a Louisiana Contractor's License prior to either acquiring bidding documents or submitting a bid. Each prospective Bidder shall produce evidence that the Bidder possesses the proper Louisiana Contractor's License before the Bidder will be allowed to acquire copies of bidding documents, all in accordance with LSA-R.S.37:2157D.

B-4 FAMILIARIZATION WITH THE WORK . Before submitting a Bid, each prospective Bidder shall become familiar with the Work, the site where the Work is to be performed, local labor conditions and all laws, regulations and other factors affecting performance of the Work. The Bidder shall carefully correlate its observations with requirements of the Contract Documents and otherwise become satisfied with the expense and difficulties attending performance of the Work.The submission of a Bid will constitute a representation of compliance by the Bidder. There will be no subsequent financial adjustment for lack of such familiarization.

B-4.01. Site Conditions. Each Bidder shall visit the site of the Work and become completely informed relative to construction hazards and procedure, the availability of lands, the character and quantity of surface and subsurface materials, utilities to be encountered, the arrangement and condition of existing structures and facilities, the procedure necessary for maintenance or uninterrupted operation of existing facilities, the character of construction equipment and facilities

Page 10: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

8

needed for performance of the Work, and facilities for transportation, handling, and storage of materials and equipment. All such factors shall be properly investigated and considered in the preparation of the Bid.

B-5. INTERPRETATIONS. All questions about the meaning or intent of the Contract Documents shall be submitted to Design Professional in writing. Replies will be issued by Addenda mailed or delivered to all parties recorded by Design Professional as having received the bidding documents. Addenda will be issued at least three (3) days (excluding weekends and holidays) prior to the time stated for opening bids. Questions received less than ten (10) working days prior to the date for opening of bids will not be answered. Only answers furnished by formal written Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect.

B-6. TAXES AND PERMITS. Attention is directed to the requirements of the General and Supplementary Conditions regarding payment of taxes and obtaining permits. All taxes that are lawfully assessed against Owner or Contractor in connection with the Work shall be paid by the Contractor. The bid prices shall include all such taxes and the costs of all required permits.

B-7. BID SECURITY. The amount of bid security is as stated in the Invitation to Bid. The required security must be in the form of a certified or bank cashiers check or bid bond. The bid bond must be executed by a surety meeting the requirements set forth in General Conditions.

The bid security shall be made payable without condition to City of Kenner, Louisiana, the Owner. The bid security may be retained by and shall be forfeited to the Owner as liquidated damages if the Bid is accepted and a contract based thereon is awarded and the Bidder should fail to enter into a contract in the form prescribed, with legally responsible sureties, within thirty (30) days after such award is made by Owner.

B-8 RETURN OF BID SECURITY. The bid security of the successful Bidder will be retained until execution of the Agreement and furnishing of the required Contract Security, whereupon checks furnished as bid security will be returned; if the successful Bidder fails to execute and deliver the Agreement and furnish the required Contract Security within thirty (30) days of the Notice of Award, Owner may annul the Notice of Award and the bid security of that Bidder will be forfeited. The bid security of any Bidder whom Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the seventh (7th) day after the executed Agreement is delivered by Owner to Contractor and the required Contract Security is furnished but shall not exceed sixty (60) days after the Bid opening. Checks furnished as bid security by other Bidders will be returned within seven (7) days of the Bid opening.

B-9. CONTRACT TIME. The Contract Time is an essential part of the contract and it will be necessary for each Bidder to satisfy Owner of its ability to complete the Work within the time set forth in the Bid Form. Provisions for delays, liquidated damages, and extensions of time are set forth in the General and Supplementary Conditions.

B-10. SUBCONTRACTORS. Within seven (7) days after Bids are opened, the apparent low Bidder, and any other Bidder so requested, shall submit a list of all Subcontractors expected to be

Page 11: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

9

used in the Work. The use of Subcontractors listed by the Bidder and accepted by Owner prior to the Notice of Award will be required in the performance of the Work.

B-10.01. Suppliers. The list of subcontractors shall also include the suppliers and manufacturers of principal items of materials and equipment the Bidder expects to use in the work unless such suppliers or manufacturers are named in the bid.

B-11. BIDS.

B-11.01. Bid Form. A separate copy of the Bid Form is provided for purposes of submitting a bid. Bid forms must be completed in ink. Bids by corporations must be executed in the corporate name by the appropriate corporate officer, accompanied by evidence of authority to sign, and attested by the secretary or an assistant secretary. The state of incorporation shall be shown below the corporate name. Bids by partnerships must be executed in the partnership name and signed by a partner; title and the official address of the partnership must be shown below the signature. Bids by joint ventures shall be signed by each participant in the joint venture or by an authorized agent of each participant.

The names of all persons signing must be legibly printed below their signature. A Bid by a person who affixes to his/her signature the word "president", "secretary", "agent", or other designation without disclosing his/her principal may be held to be the Bid of the individual signing. When requested by Owner, evidence of the authority of the person signing shall be furnished.

All blank spaces in the Bid Form shall be filled. A bid price shall be indicated for each lump sum item and/or unit price item listed therein. Bids received without all items completed may be considered non-responsive.

The Bid shall contain an acknowledgment of receipt of all Addenda, the numbers and dates of which shall be filled in on the Bid Form.

No alterations in Bids, or in the printed forms therefore, by erasures, interpolations, or otherwise will be acceptable unless each such alteration is signed and initialed by the Bidder; if initialed, Owner may require the Bidder to identify any alteration so initialed.

B-11.02. Bid Pricing. The Bidder shall complete the schedule of all unit and lump sum prices included in the Bid Form and shall accept all fixed unit prices listed therein.

The total Bid will be determined as the sum of the products of the estimated quantity of each item and the unit price bid. The final Contract Price will be subject to adjustment according to final measured, used, or delivered quantities as provided in Division 1, and the unit prices in the bid will apply to such final quantities except that unit prices will be subject to change by Change Order if quantities vary more than twenty-five percent (25%).

B-11.03. Submission of Bids. Two copies of the bid forms must be submitted with the Bid.

Each Bid and accompanying data shall be enclosed in a sealed opaque envelope or wrapping, addressed to:

Page 12: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

10

City of Kenner Finance Department

1610 Rev. Richard Wilson Drive Kenner, Louisiana 70062

and identified on the outside with the Bidder's name and Louisiana Contractor's license number and with the words Relocation of Sewer Line at Lot L-1, Airline Drive.

If the bid is sent by mail, the sealed envelope shall be enclosed in a separate mailing envelope with the notation "BID ENCLOSED" on the face thereof.

Bids shall be deposited at the designated location prior to the time and date for receipt of Bids indicated in the Invitation to Bid, or the modified time and date indicated by Addendum. Bids received after the time and date for receipt of Bids will be returned unopened.

Bidder shall assume full responsibility for timely delivery at the location designated for receipt of Bids.

Oral, telephone, or telegraph Bids are invalid and will not receive consideration.

No Bidder may submit more than one Bid. Multiple Bids under different names will not be accepted from one firm or association.

B-11.04. Modification and Withdrawal of Bids. Bids may be modified or withdrawn by an appropriate document duly executed (in the manner that a Bid must be executed) and delivered to the place where Bids are to be submitted at any time prior to the opening of Bids.

No Bids may be withdrawn after the scheduled closing time for receipt of Bids, nor for at least forty- five (45) days thereafter, except that Bids containing patently obvious mechanical, clerical, or mathematical errors may be withdrawn by the Bidder if clear and convincing sworn, written evidence is furnished to the Owner within 48 hours of the bid opening excluding Saturdays, Sundays, and legal holidays, in accordance with the Louisiana Public Bid Law. Under no circumstances may a Bidder be allowed to raise any prices as contained in the initial Bid. A Bidder who attempts to withdraw a Bid under provisions of this section shall be allowed to resubmit a Bid on the same contract in the event that it is re-advertised.

B-11.05. Bids to Remain Open. All Bids shall remain open for forty-five (45) days after the day of the Bid opening. Owner shall release Bids and return Bid securities as specified in this section under "Return of Bid Security".

B-12. AWARD OF CONTRACT. Owner shall award a contract to the Bidder who, in Owner's judgment, is the lowest responsive, responsible Bidder. Owner reserves the right to reject any or all Bids, to waive informalities, and to reject nonconforming, non-responsive, or conditional Bids.

In evaluating Bids, Owner shall consider the qualifications of the Bidders, whether or not the Bids comply with the prescribed requirements, alternatives and unit prices if requested in the Bid Form.

Page 13: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

11

Owner may consider the qualifications and experience of Subcontractors and may reject the Bid of any Bidder who does not pass any such evaluation to Owner's satisfaction. The rejection procedure will be in accordance with the Louisiana Public Bid Law, LSA-R.S. 38:2212 et seq.

If the contract is awarded, Owner shall do so within forty-five (45) days of the Bid Opening, unless the successful Bidder has agreed in writing to hold its bid price for a longer period.

B-13 EXECUTION OF THE AGREEMENT . No less than seventeen (17) days after award, Design Professional shall furnish to Contractor six (6) copies of the Agreement and other Contract Documents bound therewith. Within twelve (12) days, Contractor shall execute the Agreement, insert executed copies of the required bonds and Power of Attorney and submit all copies to Owner, together with required Certificates of Insurance. The date of contract on the Agreement and Bond forms shall be left blank for filling in by Owner. The certification date on the power of attorney also shall be left blank for filling in by Owner.

Owner shall execute the Contract Documents, insert the date of contract on the Agreement, Bonds, and Power of Attorney, and return copies to Design Professional for review and distribution.

Contractor shall be responsible for filing one complete copy of the executed Contract Documents with the Recorder of Mortgages in Jefferson Parish, and promptly furnish recordation information to Owner. No payment shall be made until this requirement is fulfilled.

B-14 COPIES OF CONTRACT DOCUMENTS . Copies of the drawings and specifications for use in preparing Bids may be obtained from the Design Professional in accordance with the Invitation to Bid. Payment in cash or check, payable to the Design Professional in accordance with the Invitation to Bid, will be required for the documents on the following basis:

One (1) complete set of plans and specifications............$150.00

Deposits will be refunded in accordance with LSA- R.S. 38:2212 provided the documents do not contain any permanent markings and can be reused for Contract Documents.

The Contractor to whom a contract is awarded will be furnished five (5) copies of the specifications and the drawings, together with all Addenda thereto for Contractors use in performing the work.

B-15. LOCAL MATERIALS AND FIRMS. By statutory authority, preference is hereby given to materials, supplies, and provisions produced, manufactured or grown in Louisiana, quality being equal to articles offered by competitors outside of the State (LSA R.S. 38:2251), and preference is hereby given to firms doing business in the State of Louisiana (LSA R.S. 38:2253).Please refer to Supplementary Conditions, Paragraph SC-17.

B-16. WORK SCHEDULING. Because of the nature of this contract, it may be necessary for the Contractor to respond to emergencies immediately upon notification.

B-17. WORK ADJACENT TO PRIVATE PROPERTY. The Contractor shall be aware that work may be performed adjacent to private property. The Contractor shall notify, prior to the start of work in the area, all property owners adjacent to and along the route of construction by means of

Page 14: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

12

either a printed circular or form letter giving the general details of the work. The letter shall also include names and telephone numbers for key project personnel of the Contractor so that property owners may report problems. These contact telephone numbers shall be given so that appropriate personnel may be contacted 24 hours a day, seven days a week.

B-18. USE OF POTABLE WATER. If the Contractor intends to use water from the Parish water system, Contractor shall first obtain a water meter from the Jefferson Parish Department of Water. The Contractor will be responsible for all costs incurred with water usage.

B-19. PURPOSE AND INTENT OF PROJECT: The project requires installation of new 10” sewer main along east site of the lot L-1 with four manholes and connect with existing manholes on each end. Abandon existing 8” sewer main and fill with cement sand mixture.

B-20. PERFORMANCE AND PAYMENT BOND. The successful Bidder will be required to furnish a Performance Bond guaranteeing faithful performance and a Labor and Materials Payment Bond guaranteeing the payment of all bills and obligations arising from the performance of the contract. Companies providing the bonds shall have a minimum rating of A, an A.M. Best Rating Classification. The amount of these bonds shall be the total contract amount.

B-21 SUPPLEMENTARY INSURANCE. The successful Bidder will be required to furnish insurance that meets the requirements set out in the General and Supplemental Conditions. A number of the insurance requirements are contingent on certain categories of risk being present on the Relocation of Sewer Line at Lot L-1, Airline Drive. While the nature of the insurable risk on the project may change, an initial assessment of the project shows that the contingent insurances below will be required for this project.

a) Builder's Risk Insurance as detailed in SC-2.07 ( Not Required)b) Contractor’s Pollution (Owner's Protective Liability) as detailed in SC-2.05 (Not

Currently Required)c) Automobile Coverage including the Transpiration of Pollutants as detailed in SC-2.02(e)

(Not Currently Required)d) Lift Risk Liability (Not Currently Required)e) Maritime Liability (Not Currently Required)f) Umbrella Liability Policy as detailed in SC-2.04 (Not Currently Required)

B-22 FORMS

END OF SECTION

Page 15: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

13

LOUISIANA UNIFORM PUBLIC WORK BID FORM

TO: _City of Kenner __Finance Department _

BID FOR: Relocation of Sewer Line at Lot L-1 Airline Drive _

_1610 Rev. Richard Wilson Drive _ _ _Kenner, LA 70062 _ (Owner to provide name and address of owner) (Owner to provide name of project and other identifying information)

The undersigned bidder hereby declares and represents that she/he: a) has carefully examined and understands the Bidding Documents, b) has not received, relied on, or based his bid on any verbal instructions contrary to the Bidding Documents or any addenda, c) has personally inspected and is familiar with the project site, and hereby proposes to provide all labor, materials, tools, appliances and facilities as required to perform, in a workmanlike manner, all work and services for the construction and completion of the referenced project, all in strict accordance with the Bidding Documents prepared by: Hartman Engineering, Inc. and dated: (Owner to provide name of entity preparing bidding documents.)

Bidders must acknowledge all addenda. The Bidder acknowledges receipt of the following ADDENDA: (Enter the number

the Designer has assigned to each of the addenda that the Bidder is acknowledging .

TOTAL BASE BID: For all work required by the Bidding Documents (including any and all unit prices designated “Base Bid” * but not alternates) the sum of:

Dollars ($ )

ALTERNATES: For any and all work required by the Bidding Documents for Alternates including any and all unit prices designated as alternates in the unit price description.

Alternate No. 1 (Owner to provide description of alternate and state whether add or deduct) for the lump sum of:

N/A Dollars ($ )

Alternate No. 2 (Owner to provide description of alternate and state whether add or deduct) for the lump sum of:

N/A Dollars ($ )

Alternate No. 3 (Owner to provide description of alternate and state whether add or deduct) for the lump sum of:

N/A Dollars ($ )

NAME OF BIDDER:

ADDRESS OF BIDDER:

LOUISIANA CONTRACTOR’S LICENSE NUMBER:

NAME OF AUTHORIZED SIGNATORY OF BIDDER:

TITLE OF AUTHORIZED SIGNATORY OF BIDDER:

SIGNATURE OF AUTHORIZED SIGNATORY OF BIDDER **:

DATE:

THE FOLLOWING ITEMS ARE TO BE INCLUDED WITH THE SUBMISSION OF THIS LOUISIANA UNIFORM PUBLIC WORK BID FORM:* The Unit Price Form shall be used if the contract includes unit prices. Otherwise it is not required and need not be included with the form. The number of unit prices that may be included is not limited and additional sheets may be included if needed.

** A CORPORATE RESOLUTION OR WRITTEN EVIDENCE of the authority of the person signing the bid for the public work as prescribed by LA R.S. 38:2212(B)(5).

BID SECURITY in the form of a bid bond, certified check or cashier’s check as prescribed by LA R.S. 38:2218(A) attached to and made a part of this bid.

Page 16: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

14

LOUISIANA UNIFORM PUBLIC WORK BID FORM UNIT PRICE FORM

TO: City of Kenner BID FOR: : Relocation of Sewer Line at Lot L-1 Airline Drive Finance Department 1610 Rev. Richard Wilson Drive Kenner, LA 70065 (Owner to provide name and address of owner) (Owner to provide name of project and other identifying information)

UNIT PRICES: This form shall be used for any and all work required by the Bidding Documents and described as unit prices. Amounts shall be stated in figures and only in figures.DESCRIPTION: Base Bid or Alt.# SEEDING & FERTILIZER

REF. NO. QUANTITY: UNIT OF MEASURE: UNIT PRICE UNIT PRICE EXTENSION (Quantity times Unit Price)

1 LUMP LUMP SUM

DESCRIPTION: Base Bid or Alt.# REMOVAL OF STRUCTURES & OBSTRUCTIONS, NOT TO EXCEEDREF. NO. QUANTITY: UNIT OF MEASURE: UNIT PRICE UNIT PRICE EXTENSION (Quantity times Unit Price)

2 LUMP LUMP SUM $1500.00 $1500.00

DESCRIPTION: Base Bid or Alt.# INSTALL SEWER MAIN (10”) (PVC/SDR 26 PIPE)REF. NO. QUANTITY: UNIT OF MEASURE: UNIT PRICE UNIT PRICE EXTENSION (Quantity times Unit Price)

3 765.95 LIN.FT.

DESCRIPTION: Base Bid or Alt.# INSTALL SEWER MANHOLEREF. NO. QUANTITY: UNIT OF MEASURE: UNIT PRICE UNIT PRICE EXTENSION (Quantity times Unit Price)

4 42.30 VFH

DESCRIPTION: Base Bid or Alt.# LIFESAVER STAINLESS STEEL STOPPER, MANHOLE INSERTREF. NO. QUANTITY: UNIT OF MEASURE: UNIT PRICE UNIT PRICE EXTENSION (Quantity times Unit Price)

5 4 EACH

DESCRIPTION: Base Bid or Alt.# ABANDON EXISTING SEWER MANHOLES & FILL VOID WITH SANDREF. NO. QUANTITY: UNIT OF MEASURE: UNIT PRICE UNIT PRICE EXTENSION (Quantity times Unit Price)

6 2.00 EACH

DESCRIPTION: Base Bid or Alt.# PLUG EXISTING SEWER MAIN @ MANHOLES & FILL WITH FLOWABLE MATERIAL(CEMENT/SAND MIXTURE)

QUANTITY: UNIT OF MEASURE: UNIT PRICE UNIT PRICE EXTENSION (Quantity times Unit Price)

7 830.00 LIN.FT.

DESCRIPTION: Base Bid or Alt.# INSTALL 12” RCPREF. NO. QUANTITY: UNIT OF MEASURE: UNIT PRICE UNIT PRICE EXTENSION (Quantity times Unit Price)

8 25.00 LIN.FT.

Wording for “DESCRIPTION” is to be provided by the Owner. All quantities are estimated. The contractor will be paid based upon actual quantities as verified by the Owner.

Page 17: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

15

LOUISIANA UNIFORM PUBLIC WORK BID FORM UNIT PRICE FORM

TO: City of Kenner BID FOR: : Relocation of Sewer Line at Lot L-1 Airline Drive Finance Department 1610 Rev. Richard Wilson Drive Kenner, LA 70065 (Owner to provide name and address of owner) (Owner to provide name of project and other identifying information)

UNIT PRICES: This form shall be used for any and all work required by the Bidding Documents and described as unit prices. Amounts shall be stated in figures and only in figures.DESCRIPTION: Base Bid or Alt.# UTILITY EXPLORATION

REF. NO. QUANTITY: UNIT OF MEASURE: UNIT PRICE UNIT PRICE EXTENSION (Quantity times Unit Price)

9 4.00 EACH

DESCRIPTION: Base Bid or Alt.# MOBILIZATIONREF. NO. QUANTITY: UNIT OF MEASURE: UNIT PRICE UNIT PRICE EXTENSION (Quantity times Unit Price)

10 LUMP LUMP SUM

DESCRIPTION: Base Bid or Alt.# CONSTRUCTION LAYOUTREF. NO. QUANTITY: UNIT OF MEASURE: UNIT PRICE UNIT PRICE EXTENSION (Quantity times Unit Price)

11 LUMP LUMP SUM

DESCRIPTION: Base Bid or Alt.# REMOVAL OF CONCRETE WALKS & DRIVESREF. NO. QUANTITY: UNIT OF MEASURE: UNIT PRICE UNIT PRICE EXTENSION (Quantity times Unit Price)

12 900.0 SQ.YD.

DESCRIPTION: Base Bid or Alt.# CONCRETE DRIVE (6” THICK)

REF. NO. QUANTITY: UNIT OF MEASURE: UNIT PRICE UNIT PRICE EXTENSION (Quantity times Unit Price)

13 890 SQ.YD.

DESCRIPTION: Base Bid or Alt.# CONCRETE WALK (4” THICK)REF. NO. QUANTITY: UNIT OF MEASURE: UNIT PRICE UNIT PRICE EXTENSION (Quantity times Unit Price)

14 10 SQ.YD.

DESCRIPTION: Base Bid or Alt.# CONCRETE CURBREF. NO. QUANTITY: UNIT OF MEASURE: UNIT PRICE UNIT PRICE EXTENSION (Quantity times Unit Price)

15 430 LIN.FT.

Wording for “DESCRIPTION” is to be provided by the Owner. All quantities are estimated. The contractor will be paid based upon actual quantities as verified by the Owner.

Page 18: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

16

Wording for “DESCRIPTION” is to be provided by the Owner. All quantities are estimated. The contractor will be paid based upon actual quantities as verified by the Owner.

Page 19: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

17

BID BOND

KNOW ALL MEN BY THESE PRESENTS that we, the undersigned, as PRINCIPAL, and as SURETY, are held and firmly bound unto the City of Kenner, State of Louisiana, acting herein by and through the City Council, the governing authority for said City, hereinafter called the "OWNER", in the penal sum of:

DOLLARS ($ ) lawful money of the United States, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors, and assigns, jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION IS SUCH, that whereas the Principal has submitted the accompanying Bid dated , , for Relocation of Sewer Line at Lot L-1, Airline Drive

NOW, THEREFORE, if the Principal shall not withdraw said Bid within the period specified herein after the opening of the same or, if no period be specified, within sixty (60) days after the said opening, and shall within the period specified therefor or, if no period be specified, within twelve (12) days after the prescribed forms are presented to him for signature, enter into a written Contract with the OWNER in accordance with the Bid as accepted, and give bond with good sufficient surety and sureties, as may be required, for the faithful performance and proper fulfillment of such Contact; or in the event of the withdrawal of said Bid within the period specified, or the failure to enter into such Contract and give such bond within the time specified, if the Principal shall pay the OWNER the difference between the amount specified in said bid and the amount for which the OWNER may procure the required work or supplies, or both, if the latter be in excess of the former, then the above obligation shall be void and of no effect, otherwise, to remain in full force and virtue.

IN WITNESS WHEREOF, the above bounded parties have executed this instrument under their several seals this day of , , and these presents signed by its undersigned representative, pursuant to authority of its governing body.

In Presence of:

(Individual Principal)

(Business Address, including Zip Code)

(Partnership) (Seal)

Page 20: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

18

ATTEST: BY:

(Corporate Principal

(Business Address, including Zip Code)

ATTEST:

(Corporate Surety)

(Business Address, including Zip Code)

BY: AFFIX CORPORATE SEAL

Countersigned:

BY: Attorney-in-Fact*

State of :

*Power-of-Attorney for person signing for surety company must be attached to bond.

Page 21: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

19

NON-COLLUSION AFFIDAVIT

STATE OF LOUISIANA PARISH OF JEFFERSON

BEFORE ME, the undersigned authority, personally came and appeared,

(Name)

who after being by me duly sworn and deposed said that he is the fully authorized

(Title)of (hereinafter referred to as bidder), the party who

(Name of Bidder)

submitted a bid for Relocation of Sewer Line at Lot L-1, Airline Drive was received by City of Kenner on , 2019 and said affiant further said:

(1) The bidder employed no person, corporation, firm, association, or other organization, either directly or indirectly, to secure the public contract under which he received payment, other than persons regularly employed by the bidder whose services in connection with the construction of the public building or project or in securing the public contract were in the regular course of their duties for bidder, and

(2) That no part of the contract price received by bidder was paid or will be paid to any person, corporation, firm, association, or other organization for soliciting the contract, other than the payment of their normal compensation to persons regularly employed by the bidder whose services in connection with the construction of the public building or project were in the regular course of their duties for bidder.

(3) Said bid is genuine and the bidder has not colluded, conspired, or agreed, directly or indirectly, with any other bidder to offer a sham or collusive bid.

(4) Said bidder has not in any manner, directly or indirectly, agreed with any other person to fix the bid price of affiant or any other bidder, or to fix any overhead profit or cost element of said bid price, or that of any other bidder, or to induce any other person to refrain from bidding.

(5) Said bid is not intended to secure an unfair advantage of benefit from the Parish of Jefferson or in favor of any person interested in the proposed contract.

(6) All statements contained in said bid are true and correct.

(7) Neither affiant nor any member of his company has divulged information regarding said bid or any data relative thereto any other person, firm, or corporation.

SWORN TO AND SUBSCRIBEDBEFORE ME THIS DAY OF 20 . (Authorized Signature)

NOTARY PUBLIC

Page 22: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

20

SAMPLE CORPORATE RESOLUTION

EXCERPT FROM MINUTES OF MEETING OF THE BOARD OF DIRECTORS OF

AT THE MEETING OF DIRECTORS OF , DULY NOTICED AND HELD ON , , A QUORUM BEING THERE PRESENT, ON MOTION DULY MADE AND SECONDED, IT WAS RESOLVED THAT , BE AND IS HEREBY APPOINTED, CONSTITUTED AND DESIGNATED AS AGENT AND ATTORNEY-IN- FACT OF THE CORPORATION WITH FULL POWER AND AUTHORITY TO ACT ON BEHALF OF THIS CORPORATION IN ALL NEGOTIATIONS, BIDDING, CONCERNS AND TRANSACTIONS WITH THE CITY OF KENNER OR ANY OF ITS AGENCIES, DEPARTMENTS, EMPLOYEES OR AGENTS, INCLUDING BUT NOT LIMITED TO, THE EXECUTION OF ALL BIDS, PAPERS, DOCUMENTS, AFFIDAVITS, BONDS, SURETIES, CONTRACTS AND ACTS AND TO RECEIVE AND RECEIPT THEREFOR ALL PURCHASE ORDERS AND NOTICES ISSUED PURSUANT TO THE PROVISIONS OF ANY SUCH BID OR CONTRACT, THIS CORPORATION HEREBY RATIFYING, APPROVING, CONFIRMING AND ACCEPTING EACH AND EVERY SUCH ACT PERFORMED BY SAID AGENT AND ATTORNEY-IN-FACT.

I HEREBY CERTIFY THE FOREGOING TO BE A TRUE AND CORRECT COPY OF AN EXCERPT OF THE MINUTES OF THE ABOVE DATED MEETING OF THE BOARD OF DIRECTORS OF SAID CORPORATION, AND THE SAME HAS NOT BEEN REVOKED OR RESCINDED.

SECRETARY

DATE

Page 23: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

21

AGREEMENT

THIS AGREEMENT, made the day of , 20 , by and between, City of Kenner, Jefferson Parish, Louisiana, referred to in these Contract Documents as "Owner" acting through its Mayor, and referred to in these Contract Documents as "Contractor":

WITNESSETH:

THAT WHEREAS: in accordance with law, Owner has caused Contract Documents to be prepared and an Invitation to Bid to be published, for and in connection with Relocation of Sewer Line at Lot L-1, Airline Drive

WHEREAS, Contractor, in response to the Invitation to Bid, has submitted to Owner, in the manner and at the time specified, a sealed Bid in accordance with Instructions to Bidders; and

WHEREAS, Owner, in the manner prescribed by law, has publicly opened, examined, and canvassed the Bids submitted, and has determined Contractor to be the lowest and best Bidder for the Work and duly awarded to Contractor a contract therefore, for the sum or sums named in Contractor's Bid.

NOW, THEREFORE, in consideration of the compensation to be paid to Contractor and of the mutual agreements herein contained, the parties to these presents have agreed and hereby agree, Owner for itself and its successors, and Contractor for itself, himself, or themselves, and its, his, or their successors and assigns, and its, his, or their executors and administrators, as follows:

ARTICLE I. All notices, letters, and other communication directed to Owner shall be delivered or addressed and mailed, postage prepaid to:

City of Kenner Public Works1610 Rev. Richard Wilson Dr. Kenner, Louisiana 70062

The business address of Contractor given in the Bid Form and Contractor's office in the vicinity of the Work are both hereby designated as the places to which all notices, letters, and other communication to Contractor will be mailed or delivered.

Contractor may change his address at any time by written notification to Owner.

ARTICLE II. The Contractor shall perform all Work, including the assumption of all obligations, duties and responsibilities necessary to the successful completion of the contract and the furnishing of all materials and equipment required to be incorporated in and form a permanent part of the Work; tools, equipment, supplies, transportation, facilities, labor, superintendence and services required to perform the Work; and Bond, insurance and submittals; all as indicated or specified in the Contract Documents to be performed or furnished by Contractor for the Work included in and

Page 24: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

22

covered by Owner's official award of this contract to Contractor, such award being based on the acceptance by Owner of Contractor's Bid.

ARTICLE III. That owner shall pay to Contractor for performance of the Work embraced in this contract, and Contractor shall accept as full compensation therefore, the sum (subject to adjustment as provided in the Contract Documents) of dollars ($ ) for all Work covered by and included in the contract award and designated in the foregoing Article I; payment thereof to be made in current funds in the manner provided in the Contract Documents.

ARTICLE IV. That Contractor shall complete all Work within 40 calendar days, after the commencement of Contract Time (as defined in General Conditions).

ARTICLE V. Time is an essential condition of the contract. Should Contractor fail to perform the Work within the Contract Time stipulated herein, Contractor shall pay to Owner, as liquidated damages and not as a penalty, 0.1% of the contract amount including change orders per calendar day of default, or $1,000.00 per day, whichever is greater, unless the Contract Time is extended by Owner.

After ENGINEER and OWNER conduct a Final Inspection of the Work, a Punch List of outstanding items to be completed, if any, will be issued to the CONTRACTOR. CONTRACTOR shall have thirty (30) calendar days to complete any outstanding items of Work remaining to be completed or corrected as detailed as a result of the Final inspection. If upon expiration of said thirty (30) calendar days the aforementioned outstanding items of Work have not been completed, liquidated damages in the amount of 0.1% of the contract amount including change orders per day will be reinstated for every day in which the outstanding items of Work have not been completed.

In case of joint responsibility for delay in the final completion of the Work, where two or more separate contracts are in force at the same time and cover related work at the same location, liquidated damages assessed against any one Contractor will be based upon the individual responsibility of that Contractor for the delay as determined by, and in the judgment of, Design Professional.

The expiration of the Contract Time shall ipso facto constitute a putting in default where Contractor has failed to perform the Work, and Owner need not formally place the Contractor in default. Contractor hereby waives any and all notices of default.

ARTICLE VI. Pursuant to LSA-R.S. 38:2248 (Public Contract Law), Owner shall retain the following percentages of each progress payment until payment is due under the terms and conditions governing substantial completion or final payment.

CONTRACT AMOUNT RETAINAGE$0-$499,999.99 10%$500,000 or greater 5%

Page 25: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

23

ARTICLE VII. That the Contract Documents which comprise the contract between Owner and Contractor, attached hereto and made a part of the documents listed in Table of Contents, and the documents identified below.

Addenda numbers:

Information submitted by Contractor prior to the time Owner issues Notice of Award including the following:Notice to Proceed.

Any Modifications (as defined in General Conditions) duly delivered after execution of this Agreement.

The Contract Drawings consist of 6 sheets. Sheet titles are listed on sheet 1 of the Drawings. In addition, each sheet bears the following general title: Relocation of Sewer Line Lot L-1 Airline Drive.

Any Notice of Partial Utilization.

Notices of Final Completion and Acceptance.

ARTICLE VIII. In order to induce Owner to enter into this Agreement, and to the extent of their applicability to the work, Contractor makes the following representations,

1. Contractor has familiarized himself with the nature and extent of the Contract Documents, Work, locality, and with all local conditions and federal, state, and local laws, ordinances, rules, and regulations that in any manner may affect cost, progress of performance of the Work.

2. Contractor has studied carefully all reports of investigations and tests of subsurface and latent physical conditions at the site or otherwise affecting cost, progress or performance of the Work which were relied upon by Design Professional in the preparation of the Drawings and Specifications and which have been identified in the Supplementary Conditions.

3. Contractor has made or caused to be made examinations, investigations and tests and studies of such reports and related data in addition to those referred to in paragraph 2 as he deems necessary for the performance of the Work at the Contract price, within the Contract Time and in accordance with the other terms and conditions of the Contract Documents; and no additional examinations, investigations, tests, reports, or similar data are or will be required by Contractor for such purposes.

4. Contractor has correlated the results of all such observations, examinations, investigations, tests, reports, and data with the terms and conditions of the Contract Documents.

Page 26: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

24

5. Contractor has given Design Professional written notice of all conflicts, errors, or discrepancies that he has discovered in the Contract Documents and the written resolution thereof by Design Professional is acceptable to Contractor.

ARTICLE IX. EQUAL OPPORTUNITY CLAUSE: 40 CFR PART 8.

During the performance of this contract, the contractor agrees as follows:

(1) The contractor will not discriminate against any employee or applicant for employment because of race, color, religion, sex, or national origin. The contractor will take affirmative action to ensure that applicants are employed, and that employees are treated during employment, without regard to their race, color, religion, sex, or national origin. Such action shall include, but not limited to, the following: Employment, upgrading, demotion, or transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other forms of compensation; and selection for training, including apprenticeship. The contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices to be provided by the contracting officer setting forth the provisions of this equal opportunity clause.

(2) The contractor will, in all solicitations or advertisements for employees placed by or on behalf of the contractor, state that all qualified applicants will receive consideration for employment without regard to race, color, religion, sex, or national origin.

(3) The contractor will send to each labor union or representative of workers with which he has a collective bargaining agreement or other contract, or understanding, a notice to be provided by the agency contracting officer, advising the labor union or worker's representative of the contractor's commitments under this equal opportunity clause, and shall post copies of the notice in conspicuous places available to employees and applicants for employment.

(4) The contractor will comply with all provisions of Executive Order No. 11246 of September 24, 1965, and of the rules, regulations, and relevant orders of the Secretary of Labor.

(5) The contractor will furnish all information and reports required by Executive Order No. 11246 of September 24, 1965, and by the rules, regulations, and orders of the Secretary of Labor, or pursuant thereto, and will permit access to his books, records, and accounts by the contracting agency and the Secretary of Labor for purposes of investigation to ascertain compliance with such rules, regulations, and orders.

(6) In the event of the contractors noncompliance with the equal opportunity clause of this contract or with any of the said rules, regulations, or orders, this contract may be canceled, terminated, or suspended, in whole or in part, and the contractor may be declared ineligible for further Government contracts in accordance with procedures authorized in Executive Order No. 11246 of September 24, 1965, and such other

Page 27: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

25

sanctions may be imposed and remedies invoked as provided in Executive Order No.

Page 28: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

26

11246 of September 24, 1965, or by rule, regulation, or order of the Secretary of Labor, or as otherwise provided by law.

(7) The contractor will include the portion of the sentence immediately preceding paragraph (1) and the provisions of paragraph (1) through (7) in every subcontract or purchase order unless exempted by rules, regulations, or orders of the Secretary of Labor issued pursuant to section 204 of Executive Order No. 11246 of September 24, 1965, so that such provisions will be binding upon each subcontractor or vendor. The contractor will take such action with respect to any subcontract or purchase order as the contracting agency may direct as a means of enforcing such provisions, including sanctions for noncompliance: Provided, however, that in the event the contractor becomes involved in, or is threatened with, litigation with a subcontractor or vendor as a result of each direction by the contracting agency, the contractor may request the United States to enter into such litigation to protect the interests of the United States.

ARTICLE X. HISTORICAL PRESERVATION CLAUSE: 36 CFR PART 800

The contractor agrees that, should evidence of historical or archeological sites be discovered during construction, all work in the area will cease immediately and the owner will be informed of the discovery. The owner will, in turn, promptly notify the Municipal Facilities Division of the Louisiana Department of Environmental Quality (DEQ).

After consulting with the appropriate State and Federal agencies, the DEQ will advise the owner of any protective measures that may be required.

ARTICLE XI. ENDANGERED SPECIES CLAUSE: ENDANGERED SPECIES ACT OF 1973, AS AMENDED

The contractor agrees that, should plants or animals belonging to either endangered or threatened species be discovered in the area of construction or adjacent areas, all work in the area will cease immediately, and the owner will be informed of the discovery. The owner will, in turn, promptly notify the Municipal Division of the Louisiana Department of Environmental Quality (DEQ).

After consulting with the appropriate State and Federal agencies, the DEQ will advise the owner of any protective measures that may be required.

ARTICLE XII. PRESIDENTIAL EXECUTIVE ORDERS

The contractor is required to comply with the following Presidential Executive Orders:

(1) 11625, 12138, and 12434 - Women's and Minority Business Enterprise;(2) 12549 - Debarment and Suspension(3) 11246 - Equal Employment Opportunity.

IN WITNESS WHEREOF, the parties hereto have executed this Agreement on the date first

Page 29: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

27

hereinabove written.

WITNESSES:

By:

Title:

CITY OF KENNER

By: Title: Mayor

Approved As to Form –City Attorney’s Office:

Page 30: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

28

HOLD HARMLESS AGREEMENT

If (hereafter “CONTRACTOR”) is the successful bidder for, Relocation of Sewer Line Lot L-1, Airline Drive then, to the fullest extent permitted by law, CONTRACTOR shall indemnify and hold harmless the City of Kenner, including its elected and appointed officials, employees, servants, volunteers, and agents, specifically the firm of Rahman & Associates, Inc. (collectively, “OWNER”) from against any and all claims, demands, suits, costs, liabilities or judgments for sums of money, and fines or penalties asserted by any party, firm or organization for loss of life or injury or damages to person or property, growing out of, resulting from, or by reason of any negligent acts, errors, and/or omissions, by CONTRACTOR, its agents, servants or employees, while engaged upon or in connection with the work required to be performed by CONTRACTOR.

Further, CONTRACTOR hereby agrees to indemnify OWNER for all reasonable expenses and attorneys’ fees incurred by or imposed upon OWNER in connection therewith for any loss, damage, injury or other casualty pursuant to this section. CONTRACTOR further agrees to pay all reasonable expenses and attorneys’ fees incurred by OWNER in establishing the right to indemnity pursuant to the provision of this Agreement.

The above indemnification shall not apply to those claims, demands, and/or causes of action arising out of the negligence of OWNER.

Accepted By:

Company Name:

Signature:

Title:

Date Accepted:

Page 31: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

29

FORM OF PERFORMANCE BOND

KNOW ALL MEN BY THESE PRESENTS:

That we, ,(Name of Contractor)

a , hereinafter called Principal, and

, hereinafter called the "Surety", are(Name of Surety)

held and firmly bound unto the City of Kenner, Louisiana, hereinafter called "Owner”, in the

penal sum of

Dollars ($ ) in lawful money of the United States, for the payment of which

sum well and truly to be made, we bind ourselves, our heirs, executors, administrators, and

successors, jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION is such that Whereas, the Principal entered into a certain contract with the Owner, dated the day of , , a copy of which is hereto attached and made apart hereof for the construction of:

RELOCATION OF SEWER LINE, LOT L-1, AIRLINE DRIVE

NOW, THEREFORE, if the Principal shall well, truly and faithfully perform its duties, all the undertakings, covenants terms, conditions, and agreements of said contract during the original term thereof, and any extensions thereof which may be granted by the Owner, with or without notice to the Surety, and if he shall satisfy all claims and demands incurred under such contract, and shall fully indemnify and save harmless the Owner from all costs and damages which it may suffer by reason of failure to do so, and shall reimburse and repay the Owner all outlay and expense which the Owner may incur in making good any default in connection with the construction of such work, and all insurance premiums on said work, whether by subcontractor or otherwise, then this obligation shall be void; otherwise to remain in full force and effect.

PROVIDED, FURTHER, that the said Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the contract or to the work to be performed thereunder or the specifications accompanying the same shall in any way affect its obligation on this bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the contract or to the work or to the specifications.

PROVIDED, FURTHER, that no final settlement between the Owner and the Contractor shall abridge the right of any beneficiary hereunder, whose claim may be unsatisfied.

Page 32: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

30

IN WITNESS WHEREOF, this instrument is executed in counterparts, each one of which shall be deemed an original, this the day of , .

WITNESSES:

By: _ (Principal)

Title:

(Surety)

By: (Attorney-in-fact)

(Address)

NOTE: Date of Bond must not be prior to date of Contract. If Contractor is Partnership, all partners should execute bond.

Page 33: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

31

LABOR AND MATERIALS PAYMENT BOND

KNOW ALL MEN BY THESE PRESENTS: that

, a (Name of Contractor -see Note 1) (Entity - see Note 2)

hereinafter called Principal, and: (Address of Contractor)

(Name of Surety - see Note 3)

(Address of Surety)

hereinafter called Surety, are held and firmly bound unto the City of Kenner, State of Louisiana, acting herein by and through the Kenner City Council, the Governing Authority for said City, hereinafter called Owner, in the penal sum of Dollars ($ ) in lawful money of the United States, for the payment of which sum well and truly be made, we bind ourselves, successors, and assigns, jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION is such that whereas, the Principal entered into a certain contract with the Owner, dated the day of , , a copy of which is hereto attached and made a part hereof for the construction of:

RELOCATION OF SEWER LINE, LOT L-1 AIRLINE DRIVE

NOW, THEREFORE, if the Principal shall promptly pay all persons, firms, subcontractors, and corporations furnishing materials for or performing labor in the prosecution of the work provided for in such contract, and any authorized extension or modification thereof, including all amounts due for materials, lubricants, oil, gasoline, coal and coke, repairs on machinery, equipment and tools, consumed or used in connection with the construction of such work, and all insurance premiums on said work, and for all labor, performed in such work whether by subcontractor or otherwise, then this obligation shall be void; otherwise to remain in full force and effect.

PROVIDED, FURTHER, that the said Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the contract or to the work to be performed thereunder or the specifications accompanying the same shall in any way affect its obligation on this bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the contract or to the work or to the specifications.

PROVIDED, FURTHER, that no final settlement between the Owner and the Contractor shall abridge the right of any beneficiary hereunder, whose claim may be unsatisfied.

Page 34: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

32

IN WITNESS WHEREOF, this instrument is executed in counterparts, each one of which shall be deemed an original, this the day of , .

WITNESSES:

(Principal)BY:

WITNESSES:

(Surety)BY:

(Attorney-in-fact)

NOTE: Date of Bond must not be prior to date of Contract.1. Correct name of Contractor2. A Corporation, A partnership, or an Individual3. Correct Name of Surety

Page 35: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

33

AFFIDAVITEmployment Status Verification

STATE OF LOUISIANA PARISH OF JEFFERSON

BEFORE ME, the undersigned authority, personally came and appeared,

, who after being duly sworn, deposed and said that he/she is

the fully authorized of

(hereinafter referred to as bidder), the party who submitted a bid for ,

Bid Number and said bidder further said:

(1) That bidder is registered and participates in a status verification system to verify that all employees in the State of Louisiana are legal citizens of the United States or are legal aliens.

(2) That bidder shall continue, during the term of the contract, to utilize a status verification system to verify the legal status of all new employees in the state of Louisiana.

(3) That bidder shall require all subcontractors to submit to the bidder a sworn affidavit verifying compliance with statements (1) and (2).

Signature of Affiant

SWORN TO AND SUBSCRIBED BEFORE ME ON THIS DAY OF , 20 .

NOTARY PUBLIC

Page 36: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

34

_RELOCATION OF SEWER LINE, LOT L-1 AIRLINE DRIVE

NAME OF PROJECT

PROJECT NUMBER DATE OF BID

ATTESTATION CLAUSE REQUIRED BYLA. R.S. 38:2227 (PAST CRIMINAL CONVICTIONS OF BIDDERS)

Appearer, as a Bidder on the above-entitled Public Works Project, does hereby attest that:

A. No sole proprietor or individual partner, incorporator, director, manager, officer, organizer, Or member who has a minimum of a ten percent (10%) ownership in the bidding entity Name below has been convicted of, or has entered a plea of guilty or nolo contendere toAny of the following state crimes or equivalent federal crimes:

(a) Public bribery (R.S. 14:118) (c) Extortion (R.S. 14:66)(b) Corrupt influencing (R.S. 14:120) (d) Money Laundering (R.S. 14:23)

B. Within the past five years from the project bid date, no sole proprietor or individual partner, incorporator, director, manager, officer, organizer, or member who has a minimum of a ten percent (10%) ownership in the bidding entity named below has been convicted of, or has entered a pleas of guilty or nolo contendre to any of the following state crimes or equivalent federal crimes, during the solicitation or execution of a contract or bid awarded pursuant to the provision of Chapter 10 of Title 38 of the Louisiana Revised Statutes:

(a) Theft (R.S. 14:67) (f) Bank fraud (R.S. 14:71.1)(b) Identity Theft (R. S. 14:67.16) (g) Forgery (R. S. 14:72)(c) Theft of a business record (h) Contractors; misapplication of

(R. S. 14:67.20) payments (R.S. 14:202)(d) False accounting (R.S. 14:70) (i) Malfeasance in office (R. S. 14:134)(e) Issuing worthless

checks (R. S. 14:71)

NAME OF BIDDER NAME OF AUTHORIZED SIGNATORY OF BIDDER

DATE TITLE OF AUTHORIZED SIGNATORY OF BIDDER

SIGNATURE OF AUTHORIZED SIGNATORY OF BIDDER

Page 37: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

SC - 1

SUPPLEMENTARY CONDITIONSList of Subjects

SC-1 SCOPE

SC-2 INSURANCESC-2.01 Workers Compensation and Employer's Liability SC-2.02 Comprehensive Automobile LiabilitySC-2.03 Comprehensive General LiabilitySC-2.04 Umbrella Liability PolicySC-2.05 Owner's Protective LiabilitySC-2.06 Installation Floater (Property Insurance)SC-2.07 Builder's Risk InsuranceSC-2.08 DeductiblesSC-2.09 IndemnitySC-2.10 Settlement of Insurance Claims

SC-3 BID, PERFORMANCE AND PAYMENT BONDS

SC-4 OVERTIME WORK

SC-5 CORRECTION PERIOD

SC-6 PAYMENT OF LIQUIDATED DAMAGES

SC-7 DOCUMENTATION TO ACCOMPANY APPLICATIONS FOR PAYMENTSC-7.01 Material and EquipmentSC-7.02 Schedules and DataSC-7.03 Documentation for Final Payment

SC-8 SPECIFICATIONS

SC-9 RESPONSIBILITY FOR PAYMENT

SC-10 UNDERGROUND INSTALLATIONS

SC-11 HISTORICAL OR ARCHAEOLOGICAL DEPOSITS

SC-12 CONTRACT TIMESC-12.01 Delays and DamagesSC-12.02 Time Extensions for Weather Conditions

SC-13 SUBSTANTIAL COMPLETION

SC-14 ORDER OF PRECEDENCE

SC-15 ASSIGNMENT

SC-16 PREFERENCE AND PRIORTY TO LOUISIANA RESIDENT CONTRACTOR

SC-17 EMERGENCY PERSONNEL REQUIREMENTS

SC-18 COORDINATION OF WORK

Page 38: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

SC - 2

SUPPLEMENTARY CONDITIONSList of Subjects - Continued

SC-19 COOPERATION BETWEEN CONTRACTORS

SC-20 PRE-CONSTRUCTION CONFERENCE

SC-21 SCHEDULE OF VALUES AND PROJECT WORK

SCHEDULE SC-22 SHOP DRAWINGS AND SAMPLES

SC-23 ACCEPTANCE OF INSURANCE

Page 39: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

SUPPLEMENTARY CONDITIONS

SC-1 SCOPE. These Supplementary Conditions amend or supplement the General Conditions (EJCDC No. C-700, 2002 Edition), and amend or supplement other provisions of the Contract Documents. All provisions not so amended or modified remain in full force and effect.

SC-2 INSURANCE. The insurance requirements in Article 5 of the General Conditions are as modified herein. All liability and property insurance shall be purchased and maintained by Contractor as set forth herein.

Section 2.7 of the General Conditions is revised to require that the valid certificates of insurance showing the required waivers be submitted with the Contract when the Contractor returns the contract for signature by the Mayor of the City of Kenner.

The Contractor shall purchase in its name and maintain at its sole cost and expense such liability and other insurance as set out herein. This insurance will provide primary coverage for claims and/or suits which may arise out of or result from the Contractor’s performance and furnishing of the Work, whether it is performed by the Contractor, any sub-contractor, partner, supplier, or by anyone directly or indirectly employed by any of them to perform or furnish any of the Work, or by anyone for whose acts any of them may be liable.

If applicable, the Contractor shall require all sub-contractors to maintain, in limits equal to or greater than Contractor’s, the same insurance coverage for Work performed or materials provided for the Work. Contractor shall insert this requirement in all contracts or agreements written and/or oral with all entities and/or persons who perform any Work under this contract. At no time shall Contractor allow any sub-contractors to perform Work without the required types and limits of insurance coverage.

All insurance shall include a waiver of subrogation in favor of the Owner and any principals for whom the Owner is working, including any and all co-lessors of such principal, and shall be subject to the approval of the Owner. Insurance provided for Commercial General Liability, Commercial Automobile Liability, and Umbrella Liability shall name the Owner as an additional insured and shall be primary to any insurance carried by the Owner. Contractor shall furnish the Owner with certificates of insurance as evidence of the above insurance.

If Owner has any objections to the coverage afforded by or other provision of the insurance required to be purchased and maintained by the Contractor in accordance with Paragraph 5.3 and5.4 of the General Conditions on the basis of its not complying with the Contract Documents, Owner will notify Contractor in writing thereof within thirty (30) calendar days of the date of delivery of such certificates to Owner in accordance with Paragraph 2.7 of the General Conditions.

SC-2.01 Workers’ Compensation and Employer's Liability Insurance. The Contractor shall purchase in its name, and maintain during the life of this contract, Worker's Compensation Insurance for all his employees in any way engaged in this project. If any Subcontractor does not carry Workers' Compensation Insurance, such coverage must be included under the Contractor's policy. The policy shall provide coverage at least equal to the requirements of the State of Louisiana and shall include Employer's Liability Coverage. If any of the Work is above, on, or alongside bodies of water, U S Longshoreman & Harbor Workers insurance in equal amounts ($1,000,000) is to be included in the policy. Policy limits and endorsements shall be as follows:

Page 40: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

SC - 4

a. State Act- Louisiana Statutory Requirements; Provide Other States coverage, if applicable;

b. Employer’s Liability with Minimum limits of $1,000,000/1,000,000/1,000,000; andc. Waiver of Subrogation to include written contracts in favor of The City of

Kenner, its elected and appointed officials, agents, directors, servants, employees, volunteers, and any other entities who may require waivers by specific contract.

SC-2.02 Commercial Automobile Liability Insurance. The Contractor shall purchase in its name, and maintain during the life of this contract, Commercial Automobile Liability Insurance to protect the Owner, Contractor and Subcontractors performing work under this contract from claims arising from any operations or work in connection with this contract. The Commercial Automobile Liability Insurance coverage is to be on an occurrence basis, with minimum limits and endorsements as follows:

a. Minimal acceptable limit: $1,000,000 Combined Single Limit;b. Liability coverage to be provided for Any Auto or for all Owned Autos and Hired

and Non-owned Autos. If Contractor owns no vehicles, then a Hired and Non- owned Auto Liability policy is required;

c. Additional Insured endorsement in favor of The City of Kenner, its elected and appointed officials, agents, directors, servants, employees, and volunteers;

d. Waiver of Transfer of Rights of Recovery Against Others to Us to include written contracts in favor of The City of Kenner, its elected and appointed officials, agents, directors, servants, employees, and volunteers; and

e. If transporting any pollutants, the policy is to include the Broad Form Transportation Pollution Form CA 99 48, or the most current form available.

SC-2.03 Commercial General Liability Insurance. The Contractor shall purchase in its name, and maintain during the life of this contract, Commercial General Liability Insurance, including Products and Completed Operations Insurance to protect the Owner, Contractor and Subcontractors performing work under this contract from claims arising from any operations or work in connection with this contract. The policy shall provide the following limits and endorsements:

a. Commercial General Liability Form CA 00 01 or pre-approved equivalent;b. Minimal acceptable limits: $1,000,000 per occurrence; $2,000,000 general

aggregate, $2,000,000 products/completed operations aggregate;c. Amendment-Aggregate limits of insurance (per project), the most recent edition in

use in Louisiana or pre-approved equivalent;d. Additional Insured endorsement in favor of The City of Kenner, its elected and

appointed officials, agents, directors, servants, employees and volunteers on CG 20 10 Form B (edition 07 04) or approved equivalent; and

e. Waiver of Transfer of Rights of Recovery Against Others to Us to include written contracts in favor of The City of Kenner, its elected and appointed officials, agents, directors, servants, employees, and volunteers.

f. If any crane operations are involved the policy shall provide lift risk liability coverage with minimum limits of $1,000,000.

SC-2.04 Umbrella / Excess Liability Coverage. [Not applicable for this project]

SC-2.05 Contractor’s Pollution, if applicable. If the Work involves pollutants of any kind, in any manner, including cleanup, this section applies. The Contractor shall purchase in its name, and maintain during the life of this contract, a pollution liability policy covering losses caused by

Page 41: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

SC - 5

pollution conditions that arise from the operations of the Contractor. The policy shall provide the following limits and endorsements:

a. Minimum acceptable limits: $1,000,000 each incident; $2,000,000 aggregate;b. Broad Form Named Insured endorsement;c. Fines, penalties and punitive damages to be included;d. Clean up costs to be included;e. Additional Insured endorsement in favor of The City of Kenner, its elected and

appointed officials, agents, directors, servants, employees, and volunteers;f. Waiver of Transfer of Rights of Recovery Against Others to Us to include written

contracts in favor of The City of Kenner, its elected and appointed officials, agents, directors, servants, employees, and volunteers;

h. If claims-made coverage is accepted, the retroactive date, if any, must precede the commencement of the performance of the contract; and

i. Any retrospective date applicable to coverage will be maintained or an extended discovery period will be exercised for a period of three (3) years beginning when the Contract is completed or terminated.

SC-2.06 Builder's Risk Insurance, if applicable. If the construction project involves a structure of any kind, this section applies. The Contractor shall purchase and maintain Builder’s Risk insurance upon the entire Work which is the subject of the Contract, at the site, to the full insurable value thereof. The Contractor shall purchase the policy with the Owner as the First Named Insured and maintain an “all risk” builder’s risk insurance on the entire Work. If the Contractor has a blanket Builder’s Risk policy, it shall be endorsed to include the Work, with the Owner listed as a Named Insured with regard to the Work. These policies must at a minimum cover for such amount of the Work as is determined by the Engineer and/or Architect. This insurance shall include, the Contractor, any Subcontractors and/or vendors deemed appropriate by the Contractor shall also be Named Insureds.

The policy shall insure against the perils of fire, flood, and extended coverage and shall include, "all risk", insurance for physical damage including, without duplication of coverage: theft; testing as appropriate for the type of project; debris removal; damage to any Work-related property stored in the open, resulting from a non-excluded peril; and vandalism.

If not covered under the "all risk" insurance or otherwise provided in the Contract, the Contractor shall effect and maintain similar insurance on portions of the Work stored off the site when such portions of the Work are to be included in any applications for payment and such procedures have been approved by the Owner.

The Builder’s Risk insurance shall be written and provided such that any portions of a building or site vacated by the Owner to accommodate the Work are protected and covered by the terms of the insurance. The insurance shall not be cancelled or permitted to lapse because of such vacancy. Coverage is to provide for use and/or occupancy, without qualification, of any and all portions of the Work, or the premises where the Work is being conducted, whether the Work has been accepted by the Owner or not. The policy shall remain in full force and effect until all work has been accepted by the Owner and no repairs, remediation or operations of any type are required from the Contractor, as determined by the Owner. Coverage for Builder’s Risk Soft Costs is to be included.

SC-2.07 Deductibles / Self-Insured Retentions. The cost of all deductible or retained amounts shall be borne by the Contractor.

Page 42: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

SC - 6

SC-2.08 Indemnity. To the fullest extent permitted by law, Contractor agrees to protect, defend, indemnify and save the Owner, its agents, officials, employees, or any firm, company, organization, or individual, or their contractors, or subcontractors for whom the Owner may be contracted to, harmless from and against any and all claims, demands, actions, and causes of action of every kind and character including but not limited to claims based on negligence, strict liability, and absolute liability which may arise in favor of any person or persons on account of illness, disease, loss of property, services, wages, death or personal injuries resulting from operations contemplated by this contract.

Further, Contractor hereby agrees to indemnify all parties above for all reasonable expenses and attorneys' fees incurred by or imposed upon the Owner in connection therewith for any such loss, damage, injury or other casualty. Contractor further agrees to pay all reasonable expenses and attorneys' fees incurred by the Owner in establishing the right to indemnity.

SC-2.09 Settlement of Insurance Claims. Losses insured under policies that include Owner as a named insured shall be adjusted with the Owner and made payable to the Owner as trustee for the Insureds, as their interests may appear.

SC-3 Bid, Performance, and Payment Bonds. All Bonds shall be in the form prescribed by the Contract except as provided otherwise by applicable Laws or Regulations and shall be executed only by sureties meeting the requirements and qualifications set forth herein.

If the surety on any Bond furnished by the Contractor is declared bankrupt, becomes insolvent, loses its right to do business in any state where any part of the Project or Work is located, or ceases to meet the requirements of paragraphs 3.1, 3.2, and/or 3.3 C below, the Contractor shall within twenty (20) days thereafter substitute another Bond and surety, both of which shall comply with the requirements herein.

SC-3.1 Bid Bond / Evidence of Good Faith - The Contractor’s Bid shall be accompanied by a certified check, cashier’s check or bid bond in an amount equal to five percent (5%) of the Contractor’s Bid as an evidence of good faith. If a Bond is used the surety or insurance company must be currently on the U.S. Department of Treasury Financial Management Service list of approved bonding companies which is published annually in the Federal Register, or by a Louisiana domiciled insurance company with at least an A- rating in the latest edition of the A. M. Best’s Key Rating Guide.

SC-3.2 Performance and Payment Bonds - The Contractor shall purchase and furnish performance and payment bonds each in an amount at least equal to one hundred percent (100%) of the Contract price, including but not limited to, the obligations for actual damages and liquidated damages in accordance with the provisions in the Contract, regarding delay in completion of the Work within the contract times as security for faithful performance and payment of all Contractor’s obligations under the Contract. Contractor shall also furnish such other Bonds as are required by the Contract. Separate Performance and Payment Bonds shall be provided. A combined Performance and Payment Bond will not be acceptable.

SC-3.3 Qualification of Surety – Performance and Payment Bonds - Any surety Bond written for Owner shall be written by a surety or insurance company currently on the U.S. Department of Treasury Financial Management Service list of approved bonding companies which is published annually in the Federal Register, or by a Louisiana domiciled insurance company with at least an A- rating in the latest edition of the A. M. Best’s Key Rating Guide to write individual Bonds up to ten percent (10%) of policy holders’ surplus, or by a surety company that complies with the requirements of LSA-R.S. 38:2219.

Page 43: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

SC - 7

SC-3.4 Resident Agent Required - No surety will be accepted from a bondsman that does not have a permanent agent or representative in the State of Louisiana upon whom notices referred to in the General Conditions may be served. Service of said notice on said agent or representative in the State shall be equal to service of notice on the president of the surety, or such other officer as may be concerned. Should the Contractor’s surety, even though approved and accepted by the Owner subsequently remove its agency or representative from the State or terminate its residency or license in the State or become insolvent, bankrupt, or otherwise fail, the Contractor shall immediately furnish a new Bond from another company approved by the Owner at no additional cost to the Owner. The new Bond shall be executed upon the same terms and conditions as the original Bond.

SC-3.5 Alternative Security – The Owner, may, at its discretion accept alternativesecurity pursuant to the requirements set forth in the Louisiana Public Contract Law (LSA-R.S. 38:2211 et seq.)

SC-3.6 Scope of the Bond and Obligation of the Surety - The Contractor’s surety shall obligate itself to all the terms and covenants of the Contract covering the Work to be performed there under. The Owner reserves the right to order extra work or to make changes by altering, adding to, or deducting from the Work under the conditions and in the manner herein described without notice to the Contractor’s surety and without in any manner affecting the liability of the bondsman or releasing it from any of its obligations hereunder.

The Bond shall also secure for the Owner the faithful performance of the Contract in strict accordance with the plans and specifications of the Contract. It shall protect the Owner against all lien laws of the State and shall provide for payment of reasonable attorney’s fees for enforcement of the Contract and institution of concursus proceedings, if such proceedings become necessary. Likewise it shall provide that if the Engineer is put to labor or expense by enforcement of the Contract and institution of concursus proceedings or through delinquency or insolvency of the Contract he shall be equitably paid for such extra expense and services involved.

The surety of the Contractor shall be and does hereby declare and acknowledge itself by acceptance to be bound to the Owner as guarantor jointly and in solido with the Contractor for fulfillment of the foregoing items including, but not limited to any provisions for actual or liquidated damages.

SC-4 OVERTIME WORK. No work shall be done between 6:00 p.m. and 7:00 a.m. nor on Saturdays, Sundays or legal holidays without permission of Owner. However, emergency work may be done without prior permission.

Night work may be undertaken as a regular procedure with the permission of Owner; such permission, however, may be revoked at any time by Owner if Contractor fails to maintain adequate equipment and supervision for the proper prosecution and control of the work at night. Regular working hours shall not exceed a maximum of 40 hours per week. Requests to work during other than regular working hours as established by Contractor must be submitted to the Design Professional at least 72 hours in advance of the period proposed for such overtime work and shall set forth the proposed schedule for work to give the Design Professional ample time to arrange for his personnel to be at the site of the work.

The Contractor shall pay for all additional engineering charges to the Owner on account of the overtime work which may be authorized as stated above. Such engineering charges shall be a subsidiary obligation of the Contractor and no extra payment shall be made by the Owner on

Page 44: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

SC - 8

account of such overtime work. Design Professional overtime charges shall be assessed in accordance with the terms of the Design Professional's Agreement with the Owner.

SC-5 CORRECTION PERIOD. Paragraph 13.12 of the General Conditions is hereby modified so that the correction period is one year after the date of City Council Acceptance. Nothing in the General Conditions Article 13 concerning the correction period shall establish a period of limitation with respect to any other obligation which Contractor has under the Contract Documents. The establishment of time periods relates only to the specific obligations of the Contractor to correct the work, and has no relationship to the time within which his obligations under the Contract Documents may be commenced to establish his liability with respect to his obligations other than to specifically correct the work.

SC-6 PAYMENT OF LIQUIDATED DAMAGES. Article 14 of the General Conditions is hereby modified to include provisions for collecting liquidated damages. When Contractor is in default for nonperformance within the stipulated contract time (as set forth in the Liquidated Damages paragraph), Owner shall deduct the liquidated damages amount from the Contractor's payment request.

SC-7 DOCUMENTATION TO ACCOMPANY APPLICATIONS FOR PAYMENT .In addition to the provisions set forth in GC-14.2 and 14.12, the Contractor's Applications for Payment shall be accompanied by the documentation specified in SC 7.01, 7.02 and 7.03.

SC-7.01 Materials and Equipment. If payment is requested for materials and equipment not incorporated in the work, but delivered and suitably stored at the site or at another location agreed to in writing, the Application for Progress Payment shall be accompanied by such data, satisfactory to the Owner, as will establish the Owner's title to the material and equipment and protect his interest therein, including applicable insurance. Payments for such materials and equipment shall be based only upon the actual cost of the materials and equipment to the Contractor and shall not include any overhead or profit to the Contractor.

The Contractor shall be cognizant of the fact that other work may be under construction at the same time that this Contract is active. There shall be complete cooperation with any other contractor in the area, and any unavoidable conflicts shall be immediately brought to the Design Professional's attention.

SC-7.02 Schedules and Data. Each Application for Progress Payment shall be accompanied by the Contractor's updated schedule of operations, or progress report, with such shop drawings, schedules, procurement schedules, value of material on hand included in application, and other data specified in Division 1 or reasonably required by the Design Professional. With each pay request the Contractor shall submit a breakdown of pay items by work order site, listing location, description of work and cost supported by foreman's report; and a standard A.I.A. billing form indicating bid items, unit prices bid, current quantities installed, value of current work installed, previous quantity installed and total quantity and cost to date.

SC-7.03 Documentation for Final Payment. Contractor's Application for Final Payment shall be accompanied by consent of the Surety to final payment and clear lien and privilege certificates issued by the Clerk of Court and Ex-Officio Recorder of Mortgages for Jefferson Parish.

SC-8 SPECIFICATIONS. The specifications which govern the materials and equipment to be furnished and the work to be performed under this contract are listed in the Table of Contents at the beginning of this volume.

Page 45: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

SC - 9

SC-9 RESPONSIBILITY FOR PAYMENT. Except for items specifically identified as provided by the Owner, Contractor shall pay for all labor, materials, and other costs incurred under this Contract.

SC-10 UNDERGROUND INSTALLATIONS . Active underground pipelines and utilities are indicated on the Drawings only to the extent such information was made available to or discovered by Design Professional in preparing drawings. There is no guarantee as to the accuracy or completeness of such information, and all responsibility for the accuracy and completeness thereof is expressly disclaimed by the Owner and the Design Professional.

Service connections are not indicated on the Drawings.

Contractor shall be responsible for discovery of all existing underground installations, in advance of excavating or trenching, by contacting all local utilities, and by prospecting.

SC-11 HISTORICAL OR ARCHAEOLOGICAL DEPOSITS. If, during the course of construction, evidence of deposits of historical or archaeological interest is found, Contractor shall cease operations affecting the find and shall notify Owner who shall notify the State Historic Preservation Officer. No further disturbance of the deposits shall ensue until Contractor has been notified by Owner that he may proceed. Owner will issue a notice to proceed only after the state official has surveyed the find and made a determination to the Owner. Compensation to Contractor, if any, for lost time or changes in construction to avoid the find, shall be determined in accordance with changed conditions or change order provisions of the Contract Documents.

SC-12. CONTRACT TIME .

SC-12.01 Delays and Damages. Contractor shall accept the risk of any delays caused by the rate of progress of the work performed under this contract or other contract. In the event the Contractor is delayed in the prosecution and completion of the work because of such conditions, the Contractor shall have no claim against the Owner for damages or contract adjustment other than an extension of contract time and the waiving of liquidated damages during the period occasioned by the delay.

Time limitations required by the Owner shall be for the benefit of the Owner and contractors, under other contracts, who have entered into such contracts with the Owner in reliance on the time limitations set forth in these Contract Documents. Any claim by the Contractor for damages due to delay by another contractor shall be asserted against that Contractor.

SC-12.02 Time Extensions for Weather Conditions. The Contractor shall note that weather conditions shall not be an automatic cause for time extension. The contract time specified in the bidding documents and contract agreement include an allowance as stated in those documents for inclement weather. In order to document and claim days lost to inclement weather conditions, the Contractor shall, on a semi-monthly basis submit a report to the Design Professional, stating the time lost to inclement weather, within seven (7) days of the end of the report period. The Design Professional will review the report and make recommendations for either acceptance or rejection of each claimed time period lost to inclement weather. The Owner will then instruct the Design Professional to approve or reject the report.

The report for lost days due to inclement weather shall account for all days during the reporting period, including weekends and holidays. Claims for lost days on either weekends or holidays

Page 46: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

SC - 10

will not be considered unless the Contractor can show that the inclement weather affected work production on the following work day. The reporting periods shall be from the first day of the month through and including the fifteenth day of the month and from the sixteenth day of the month through and including the last day of the month. Lost time accounting shall be in one-half day increments.

Lost time shall be considered only if the weather occurrence is in excess of the normal weather patterns as established by the nearest office of the National Weather Service, U.S. Department of Commerce. When the Contract utilizes critical path method scheduling (C.P.M.), the Design Professional will determine if the days lost due to weather conditions actual affected the critical path activities then no time extension will be granted.

SC-13 SUBSTANTIAL COMPLETION. Paragraph 14.8 of the General Conditions is hereby deleted entirely, and the following is substituted: When the Contractor considers the work 100% complete, the Contractor shall declare in writing to the Owner and the Design Professional that the work has been completed in accordance with the plans and specifications, and shall request a Final Inspection of the work. Upon receipt of such notification the Design Professional shall , as quickly as practical, schedule and conduct a Final Inspection of the work and shall prepare and furnish to the Contractor a Punch List of outstanding items to be completed or corrected, all in accordance with Paragraph 14.11 of the General Conditions.

Upon completion of the Punch List items and verification by the Design Professional and the Owner as acceptable and complete, the City Council will, by Resolution, accept the project as complete for purposes of commencement of the statutory lien period. Until completion of the Punch List, however, the contract time will continue to run.

SC-14 ORDER OF PRECEDENCE. In the event of an inconsistency in the Contract Documents, the order or precedence shall be as follows:

a) Agreementb) Addenda/Change Orders/Written Amendmentc) Contractor's Bidd) Supplementary Conditionse) Invitation to Bidf) Instructions to Biddersg) General Conditionsh) Technical Specificationsi) Referenced Standard Specificationsj) Drawings

With reference to the drawings, the order of precedence is as follows:Figures govern over scaled dimensions; detail drawings over general drawings; addenda/change order drawings govern over standard drawings and shop drawings.

SC-15 ASSIGNMENT. Neither party to this contract shall assign or sublet his interest in this contract without written consent of the other, nor shall Contractor assign any monies due or to become due him under this contract without previous written consent of Owner, nor without the consent of the Surety unless the Surety has waived its right to notice of assignment. The Contractor shall perform at least fifty percent (50%) of all work covered in the Contract Documents. Contractor shall not employ any subcontractor, other personnel or organization,Whether initially or at any time during the contract time, to assist the Contractor in the execution of the Contractor’s fifty percent (50%) of the work.

Page 47: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

SC - 11

SC-16 PREFERENCE AND PRIORITY TO LOUISIANA RESIDENTCONTRACTORS. By statutory authority, certain preference and priority is given to Louisiana Resident Contractors in the award of public work contracts (LSA-R.S. 38:2225). If applicable, Bidder must make request in writing, to accompany bid submission.

SC-17 EMERGENCY PERSONNEL REQUIREMENTS. The work demands of this contract will require the Contractor to be able to respond to emergencies within one hour of notification.

SC-18 COORDINATION OF WORK. The Contractor performing work under this contract shall be required to coordinate his operations with all City of Kenner and/or Parish Public Works Departments as may be required.

SC-19 COOPERATION BETWEEN CONTRACTORS. The Contractor shall at all times be cognizant that other work may be under construction at the same time that this Project is active. There shall be complete cooperation with any other contractor(s) on the site or in the immediate vicinity of Contractor’s work area, and any unavoidable conflicts shall be brought immediately to the attention of the Design Professional for resolution.

SC-20 PRE-CONSTRUCTION CONFERENCE. Prior to the commencement of construction the Design Professional shall schedule a Pre-Construction Conference. The Contractor shall be represented at the conference by the Project Superintendent and any other personnel as Contractor may desire. An Owner’s representative shall be present, and where advisable, representatives of utility companies shall also be present.

SC-21 SCHEDULE OF VALUES AND PROJECT WORK SCHEDULE. The Contractorshall submit to the Design Professional a detailed Schedule of Values and a complete work schedule (CPM schedule) prior to the issuance of a “Notice to Proceed”.

SC-22 SHOP DRAWINGS AND SAMPLES. In Article 6, Paragraphs 6.24.1, 6.24.2,6.26, 6.27, and 6.28 of the General Conditions, the words “...and approved...” are hereby deleted.

SC-23 ACCEPTANCE OF INSURANCE. The first sentence of Article 5, Paragraph 5.3 of the General Conditions is hereby amended to read as follows:

If Owner has any objections to the coverage afforded by, or any other provision of the insurance required to be purchased and maintained by the Contractor in accordance with Paragraphs 5.3 and5.4 on the basis of its not complying with the Contract Documents, Owner will notify Contractor in writing thereof within thirty (30) calendar days of the date of delivery of such certificates to Owner in accordance with Paragraph 2.7.

END OF SUPPLEMENTARY CONDITIONS

Page 48: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC-0

This document has important legal consequences; consultation with an attorney is encouraged with respect to its use or modification. This document should be adapted to the particular circumstances of the contemplated Project and the Controlling Law.

STANDARD GENERAL CONDITIONS

OF THE CONSTRUCTION CONTRACT

Prepared by

ENGINEERS JOINT CONTRACT DOCUMENTS COMMITTEE

and

Issued and Published Jointly By

PROFESSIONAL ENGINEERS IN PRIVATE PRACTICEa practice division of the

NATIONAL SOCIETY OF PROFESSIONAL ENGINEERS

AMERICAN COUNCIL OF ENGINEERING COMPANIES

AMERICAN SOCIETY OF CIVIL ENGINEERS

This document has been approved and endorsed by

The Associated General Contractors of America

Construction Specifications Institute

Page 49: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC-1

Copyright ©2002

National Society of Professional Engineers 1420 King Street, Alexandria, VA 22314

American Council of Engineering Companies 1015 15th Street, N.W., Washington, DC 20005

American Society of Civil Engineers1801 Alexander Bell Drive, Reston, VA 20191-4400

These General Conditions have been prepared for use with the Suggested Forms of Agreement Between Owner and Contractor Nos. C-520 or C-525 (2002 Editions). Their provisions are interrelated and a change in one may necessitate a change in the other. Comments concerning their usage are contained in the EJCDC Construction Documents, General and Instructions (No. C-001) (2002 Edition). For guidance in the preparation of Supplementary Conditions, see Guide to the Preparation of Supplementary Conditions (No. C-800) (2002 Edition).

Page 50: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC-2

TABLE OF CONTENTS

Page

ARTICLE 1 - DEFINITIONS AND TERMINOLOGY...............................................................................................................61.01 Defined Terms...........................................................................................................................................................61.02 Terminology..............................................................................................................................................................8

ARTICLE 2 - PRELIMINARY MATTERS.................................................................................................................................92.01 Delivery of Bonds and Evidence of Insurance..........................................................................................................92.02 Copies of Documents.................................................................................................................................................92.03 Commencement of Contract Times; Notice to Proceed............................................................................................92.04 Starting the Work......................................................................................................................................................92.05 Before Starting Construction....................................................................................................................................92.06 Preconstruction Conference......................................................................................................................................92.07 Initial Acceptance of Schedules.................................................................................................................................9

ARTICLE 3 - CONTRACT DOCUMENTS: INTENT, AMENDING, REUSE.......................................................................103.01 Intent........................................................................................................................................................................103.02 Reference Standards................................................................................................................................................103.03 Reporting and Resolving Discrepancies.................................................................................................................103.04 Amending and Supplementing Contract Documents...............................................................................................113.05 Reuse of Documents................................................................................................................................................113.06 Electronic Data.......................................................................................................................................................11

ARTICLE 4 - AVAILABILITY OF LANDS; SUBSURFACE AND PHYSICAL CONDITIONS; HAZARDOUS ENVIRONMENTAL CONDITIONS; REFERENCE POINTS.................................................................................................11

4.01 Availability of Lands...............................................................................................................................................114.02 Subsurface and Physical Conditions.......................................................................................................................124.03 Differing Subsurface or Physical Conditions..........................................................................................................124.04 Underground Facilities...........................................................................................................................................134.05 Reference Points......................................................................................................................................................134.06 Hazardous Environmental Condition at Site..........................................................................................................13

ARTICLE 5 - BONDS AND INSURANCE...............................................................................................................................145.01 Performance, Payment, and Other Bonds...............................................................................................................145.02 Licensed Sureties and Insurers...............................................................................................................................155.03 Certificates of Insurance.........................................................................................................................................155.04 Contractor’s Liability Insurance.............................................................................................................................155.05 Owner’s Liability Insurance....................................................................................................................................165.06 Property Insurance..................................................................................................................................................165.07 Waiver of Rights......................................................................................................................................................175.08 Receipt and Application of Insurance Proceeds.....................................................................................................175.09 Acceptance of Bonds and Insurance; Option to Replace........................................................................................175.10 Partial Utilization, Acknowledgment of Property Insurer......................................................................................18

ARTICLE 6 - CONTRACTOR’S RESPONSIBILITIES...........................................................................................................186.01 Supervision and Superintendence...........................................................................................................................186.02 Labor; Working Hours............................................................................................................................................186.03 Services, Materials, and Equipment........................................................................................................................186.04 Progress Schedule...................................................................................................................................................186.05 Substitutes and “Or-Equals”..................................................................................................................................196.06 Concerning Subcontractors, Suppliers, and Others................................................................................................206.07 Patent Fees and Royalties.......................................................................................................................................216.08 Permits....................................................................................................................................................................216.09 Laws and Regulations.............................................................................................................................................216.10 Taxes........................................................................................................................................................................226.11 Use of Site and Other Areas....................................................................................................................................226.12 Record Documents..................................................................................................................................................226.13 Safety and Protection..............................................................................................................................................226.14 Safety Representative..............................................................................................................................................236.15 Hazard Communication Programs.........................................................................................................................23

Page 51: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC-3

6.16 Emergencies............................................................................................................................................................236.17 Shop Drawings and Samples...................................................................................................................................236.18 Continuing the Work...............................................................................................................................................246.19 Contractor’s General Warranty and Guarantee.....................................................................................................246.20 Indemnification........................................................................................................................................................246.21 Delegation of Professional Design Services...........................................................................................................25

ARTICLE 7 - OTHER WORK AT THE SITE...........................................................................................................................257.01 Related Work at Site................................................................................................................................................257.02 Coordination...........................................................................................................................................................267.03 Legal Relationships.................................................................................................................................................26

ARTICLE 8 - OWNER’S RESPONSIBILITIES.......................................................................................................................268.01 Communications to Contractor...............................................................................................................................268.02 Replacement of Engineer.........................................................................................................................................268.03 Furnish Data...........................................................................................................................................................268.04 Pay When Due.........................................................................................................................................................268.05 Lands and Easements; Reports and Tests...............................................................................................................268.06 Insurance.................................................................................................................................................................268.07 Change Orders........................................................................................................................................................268.08 Inspections, Tests, and Approvals...........................................................................................................................268.09 Limitations on Owner’s Responsibilities.................................................................................................................278.10 Undisclosed Hazardous Environmental Condition.................................................................................................278.11 Evidence of Financial Arrangements......................................................................................................................27

ARTICLE 9 - ENGINEER’S STATUS DURING CONSTRUCTION......................................................................................279.01 Owner’s Representative..........................................................................................................................................279.02 Visits to Site.............................................................................................................................................................279.03 Project Representative............................................................................................................................................279.04 Authorized Variations in Work................................................................................................................................279.05 Rejecting Defective Work........................................................................................................................................279.06 Shop Drawings, Change Orders and Payments......................................................................................................289.07 Determinations for Unit Price Work.......................................................................................................................289.08 Decisions on Requirements of Contract Documents and Acceptability of Work....................................................289.09 Limitations on Engineer’s Authority and Responsibilities......................................................................................28

ARTICLE 10 - CHANGES IN THE WORK; CLAIMS............................................................................................................2810.01 Authorized Changes in the Work.............................................................................................................................2810.02 Unauthorized Changes in the Work........................................................................................................................2910.03 Execution of Change Orders...................................................................................................................................2910.04 Notification to Surety..............................................................................................................................................2910.05 Claims......................................................................................................................................................................29

ARTICLE 11 - COST OF THE WORK; ALLOWANCES; UNIT PRICE WORK..................................................................3011.01 Cost of the Work......................................................................................................................................................3011.02 Allowances...............................................................................................................................................................3111.03 Unit Price Work......................................................................................................................................................31

ARTICLE 12 - CHANGE OF CONTRACT PRICE; CHANGE OF CONTRACT TIMES......................................................3212.01 Change of Contract Price........................................................................................................................................3212.02 Change of Contract Times.......................................................................................................................................3312.03 Delays......................................................................................................................................................................33

ARTICLE 13 - TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF DEFECTIVE WORK.......3313.01 Notice of Defects.....................................................................................................................................................3313.02 Access to Work........................................................................................................................................................3313.03 Tests and Inspections..............................................................................................................................................3313.04 Uncovering Work....................................................................................................................................................3413.05 Owner May Stop the Work......................................................................................................................................3413.06 Correction or Removal of Defective Work..............................................................................................................3413.07 Correction Period....................................................................................................................................................3413.08 Acceptance of Defective Work.................................................................................................................................3513.09 Owner May Correct Defective Work.......................................................................................................................35

ARTICLE 14 - PAYMENTS TO CONTRACTOR AND COMPLETION...............................................................................3614.01 Schedule of Values...................................................................................................................................................3614.02 Progress Payments..................................................................................................................................................3614.03 Contractor’s Warranty of Title...............................................................................................................................3714.04 Substantial Completion...........................................................................................................................................37

Page 52: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC-4

14.05 Partial Utilization....................................................................................................................................................3814.06 Final Inspection.......................................................................................................................................................3814.07 Final Payment.........................................................................................................................................................3814.08 Final Completion Delayed......................................................................................................................................3914.09 Waiver of Claims.....................................................................................................................................................39

ARTICLE 15 - SUSPENSION OF WORK AND TERMINATION..........................................................................................3915.01 Owner May Suspend Work......................................................................................................................................3915.02 Owner May Terminate for Cause............................................................................................................................3915.03 Owner May Terminate For Convenience................................................................................................................4015.04 Contractor May Stop Work or Terminate...............................................................................................................40

ARTICLE 16 - DISPUTE RESOLUTION.................................................................................................................................4116.01 Methods and Procedures.........................................................................................................................................41

ARTICLE 17 - MISCELLANEOUS..........................................................................................................................................4117.01 Giving Notice...........................................................................................................................................................4117.02 Computation of Times.............................................................................................................................................4117.03 Cumulative Remedies..............................................................................................................................................4117.04 Survival of Obligations............................................................................................................................................4117.05 Controlling Law......................................................................................................................................................4117.06 Headings..................................................................................................................................................................41

Page 53: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC-5

GENERAL CONDITIONS

ARTICLE 1 - DEFINITIONS AND TERMINOLOGY

1.01 Defined Terms

A. Wherever used in the Bidding Requirements or Contract Documents and printed with initial capital letters, the terms listed below will have the meanings indicated which are applicable to both the singular and plural thereof. In addition to terms specifically defined, terms with initial capital letters in the Contract Documents include references to identified articles and paragraphs, and the titles of other documents or forms.

1. Addenda--Written or graphic instruments issued prior to the opening of Bids which clarify, correct, or change the Bidding Requirements or the proposed Contract Documents.

2. Agreement--The written instrument which is evidence of the agreement between Owner and Contractor covering the Work.

3. Application for Payment--The form acceptable to Engineer which is to be used by Contractor during the course of the Work in requesting progress or final payments and which is to be accompanied by such supporting documentation as is required by the Contract Documents.

4. Asbestos--Any material that contains more than one percent asbestos and is friable or is releasing asbestos fibers into the air above current action levels established by the United States Occupational Safety and Health Administration.

5. Bid--The offer or proposal of a Bidder submitted on the prescribed form setting forth the prices for the Work to be performed.

6. Bidder--The individual or entity who submits a Bid directly to Owner.

7. Bidding Documents--The Bidding Requirements and the proposed Contract Documents (including all Addenda).

8. Bidding Requirements--The Advertisement or Invitation to Bid, Instructions to Bidders, bid security of acceptable form, if any, and the Bid Form with any supplements.

9. Change Order--A document recommended by Engineer which is signed by Contractor and Owner and authorizes an addition, deletion, or revision in the Work or an adjustment in the Contract Price or the Contract Times, issued on or after the Effective Date of the Agreement.

10. Claim--A demand or assertion by Owner or Contractor seeking an adjustment of Contract Price or Contract Times, or both, or other relief with respect to the terms of the Contract. A demand for money or services by a third party is not a Claim.

11. Contract--The entire and integrated written agreement between the Owner and Contractor concerning the Work. The Contract supersedes prior negotiations, representations, or agreements, whether written or oral.

12. Contract Documents-- Those items so designated in the Agreement. Only printed or hard copies of the items listed in the Agreement are Contract Documents. Approved Shop Drawings, other Contractor’s submittals, and the reports and drawings of subsurface and physical conditions are not Contract Documents.

13. Contract Price--The moneys payable by Owner to Contractor for completion of the Work in accordance with the Contract Documents as stated in the Agreement (subject to the provisions of Paragraph 11.03 in the case of Unit Price Work).

14. Contract Times--The number of days or the dates stated in the Agreement to: (i) achieve Milestones, if any, (ii) achieve Substantial Completion; and (iii) com- plete the Work so that it is ready for final payment as evidenced by Engineer’s written recommendation of final payment.

15. Contractor--The individual or entity with whom Owner has entered into the Agreement.

16. Cost of the Work--See Paragraph 11.01.A for definition.

17. Drawings--That part of the Contract Documents prepared or approved by Engineer which graphically shows the scope, extent, and character of the Work to be performed by Contractor. Shop Drawings and other Contractor submittals are not Drawings as so defined.

18. Effective Date of the Agreement--The date indicated in the Agreement on which it becomes effective, but if no such date is indicated, it means the date on which the Agreement is signed and delivered by the last of the two parties to sign and deliver.

19. Engineer--The individual or entity named as such in the Agreement.

Page 54: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC-6

20. Field Order--A written order issued by Engineer which requires minor changes in the Work but which does not involve a change in the Contract Price or the Contract Times.

21. General Requirements--Sections of Division 1 of the Specifications. The General Requirements pertain to all sections of the Specifications.

22. Hazardous Environmental Condition--The presence at the Site of Asbestos, PCBs, Petroleum, Hazardous Waste, or Radioactive Material in such quantities or circumstances that may present a substantial danger to persons or property exposed thereto in connection with the Work.

23. Hazardous Waste--The term Hazardous Waste shall have the meaning provided in Section 1004 of the Solid Waste Disposal Act (42 USC Section 6903) as amended from time to time.

24. Laws and Regulations; Laws or Regulations--Any and all applicable laws, rules, regulations, ordinanc- es, codes, and orders of any and all governmental bodies, agencies, authorities, and courts having jurisdiction.

25. Liens--Charges, security interests, or encumbrances upon Project funds, real property, or personal property.

26. Milestone--A principal event specified in the Contract Documents relating to an intermediate comple- tion date or time prior to Substantial Completion of all the Work.

27. Notice of Award--The written notice by Owner to the Successful Bidder stating that upon timely compliance by the Successful Bidder with the conditions precedent listed therein, Owner will sign and deliver the Agreement.

28. Notice to Proceed--A written notice given by Owner to Contractor fixing the date on which the Con- tract Times will commence to run and on which Contractor shall start to perform the Work under the Contract Documents.

29. Owner--The individual or entity with whom Contractor has entered into the Agreement and for whom the Work is to be performed.

30. PCBs--Polychlorinated biphenyls.

31. Petroleum--Petroleum, including crude oil or any fraction thereof which is liquid at standard conditions of temperature and pressure (60 degrees Fahrenheit and14.7 pounds per square inch absolute), such as oil, petroleum, fuel oil, oil sludge, oil refuse, gasoline, kerosene, and oil mixed with other non-Hazardous Waste and crude oils.

32. Progress Schedule--A schedule, prepared and maintained by Contractor, describing the sequence and duration of the activities comprising the Contractor’s plan to accomplish the Work within the Contract Times.

33. Project--The total construction of which the Work to be performed under the Contract Documents may be the whole, or a part.

34. Project Manual--The bound documentary information prepared for bidding and constructing the Work. A listing of the contents of the Project Manual, which may be bound in one or more volumes, is contained in the table(s) of contents.

35. Radioactive Material--Source, special nucle- ar, or byproduct material as defined by the Atomic Energy Act of 1954 (42 USC Section 2011 et seq.) as amended from time to time.

36. Related Entity -- An officer, director, partner, employee, agent, consultant, or subcontractor.

37. Resident Project Representative--The autho- rized representative of Engineer who may be assigned to the Site or any part thereof.

38. Samples--Physical examples of materials, equipment, or workmanship that are representative of some portion of the Work and which establish the standards by which such portion of the Work will be judged.

39. Schedule of Submittals--A schedule, prepared and maintained by Contractor, of required submittals and the time requirements to support scheduled performance of related construction activities.

40. Schedule of Values--A schedule, prepared and maintained by Contractor, allocating portions of the Contract Price to various portions of the Work and used as the basis for reviewing Contractor’s Applications for Payment.

41. Shop Drawings--All drawings, diagrams, illustrations, schedules, and other data or information which are specifically prepared or assembled by or for Contractor and submitted by Contractor to illustrate some portion of the Work.

42. Site--Lands or areas indicated in the Contract Documents as being furnished by Owner upon which the Work is to be performed, including rights-of-way and easements for access thereto, and such other lands furnished by Owner which are designated for the use of Contractor.

43. Specifications--That part of the Contract Documents consisting of written requirements for materials, equipment, systems, standards and

Page 55: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC-7

workmanship as applied to the Work, and certain

Page 56: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC-8

administrative requirements and procedural matters applicable thereto.

44. Subcontractor--An individual or entity having a direct contract with Contractor or with any other Subcontractor for the performance of a part of the Work at the Site.

45. Substantial Completion--The time at which the Work (or a specified part thereof) has progressed to the point where, in the opinion of Engineer, the Work (or a specified part thereof) is sufficiently complete, in accordance with the Contract Documents, so that the Work (or a specified part thereof) can be utilized for the purposes for which it is intended. The terms “substantially complete” and “substantially completed” as applied to all or part of the Work refer to Substantial Completion thereof.

46. Successful Bidder--The Bidder submitting a responsive Bid to whom Owner makes an award.

47. Supplementary Conditions--That part of the Contract Documents which amends or supplements these General Conditions.

48. Supplier--A manufacturer, fabricator, suppli- er, distributor, materialman, or vendor having a direct contract with Contractor or with any Subcontractor to furnish materials or equipment to be incorporated in the Work by Contractor or any Subcontractor.

49. Underground Facilities--All underground pipelines, conduits, ducts, cables, wires, manholes, vaults, tanks, tunnels, or other such facilities or attachments, and any encasements containing such facilities, including those that convey electricity, gases, steam, liquid petroleum products, telephone or other communications, cable television, water, wastewater, storm water, other liquids or chemicals, or traffic or other control systems.

50. Unit Price Work--Work to be paid for on the basis of unit prices.

51. Work--The entire construction or the various separately identifiable parts thereof required to be provided under the Contract Documents. Work includes and is the result of performing or providing all labor, services, and documentation necessary to produce such construction, and furnishing, installing, and incorporating all materials and equipment into such construction, all as required by the Contract Documents.

52. Work Change Directive--A written statement to Contractor issued on or after the Effective Date of the Agreement and signed by Owner and recommended by Engineer ordering an addition, deletion, or revision in the Work, or responding to differing or unforeseen subsurface or physical conditions under which the Work is to be performed or to emergencies. A Work Change Directive will not change the Contract Price or the Contract Times

but is evidence that the parties expect that the change ordered or documented by a Work Change Directive will be incorporated in a subsequently issued Change Order following negotiations by the parties as to its effect, if any, on the Contract Price or Contract Times.

1.02 Terminology

1. The following words or terms are not defined but, when used in the Bidding Requirements or Contract Documents, have the following meaning.

2. Intent of Certain Terms or Adjectives

1. The Contract Documents include the terms “as allowed,” “as approved,” “as ordered”, “as directed” or terms of like effect or import to authorize an exercise of professional judgment by Engineer. In addition, the adjectives “reasonable,” “suitable,” “acceptable,” “proper,” “satisfactory,” or adjectives of like effect or import are used to describe an action or determination of Engineer as to the Work. It is intended that such exercise of professional judgment, action or determination will be solely to evaluate, in general, the Work for compliance with the requirements of and information in the Contract Documents and conformance with the design concept of the completed Project as a functioning whole as shown or indicated in the Contract Documents (unless there is a specific statement indicating otherwise). The use of any such term or adjective is not intended to and shall not be effective to assign to Engineer any duty or authority to supervise or direct the performance of the Work or any duty or authority to undertake responsibility contrary to the provisions of Paragraph 9.09 or any other provision of the Contract Documents.

3. Day

1. The word “day” means a calendar day of 24 hours measured from midnight to the next midnight.

4. Defective

1. The word “defective,” when modifying the word “Work,” refers to Work that is unsatisfactory, faulty, or deficient in that it:

a. does not conform to the Contract Documents, or

b. does not meet the requirements of any applicable inspection, reference standard, test, or approval referred to in the Contract Documents, or

c. has been damaged prior to Engineer’s - recommendation of final payment (unless responsibility for the protection thereof has been assumed by Owner at Substantial Completion in accordance with Paragraph 14.04 or 14.05).

Page 57: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC-9

5. Furnish, Install, Perform, Provide

1. The word “furnish,” when used in connection with services, materials, or equipment, shall mean to supply and deliver said services, materials, or equipment to the Site (or some other specified location) ready for use or installation and in usable or operable condition.

2. The word “install,” when used in connection with services, materials, or equipment, shall mean to put into use or place in final position said services, materials, or equipment complete and ready for intended use.

3. The words “perform” or “provide,” when used in connection with services, materials, or equipment, shall mean to furnish and install said services, materials, or equipment complete and ready for intended use.

4. When “furnish,” “install,” “perform,” or “pro- vide” is not used in connection with services, materials, or equipment in a context clearly requiring an obligation of Contractor, “provide” is implied.

6. Unless stated otherwise in the Contract Docu- ments, words or phrases which have a well-known technical or construction industry or trade meaning are used in the Contract Documents in accordance with such recognized meaning.

ARTICLE 2 - PRELIMINARY MATTERS

2.01 Delivery of Bonds and Evidence of Insurance

A. When Contractor delivers the executed counterparts of the Agreement to Owner, Contractor shall also deliver to Owner such bonds as Contractor may be required to furnish.

B. Evidence of Insurance: Before any Work at the Site is started, Contractor and Owner shall each deliver to the other, with copies to each additional insured identified in the Supplementary Conditions, certificates of insurance (and other evidence of insurance which either of them or any additional insured may reasonably request) which Contractor and Owner respectively are required to purchase and maintain in accordance with Article 5.

2.02 Copies of Documents

A. Owner shall furnish to Contractor up to ten printed or hard copies of the Drawings and Project Manual. Additional copies will be furnished upon request at the cost of reproduction.

2.03 Commencement of Contract Times; Notice to Proceed

A. The Contract Times will commence to run on the thirtieth day after the Effective Date of the Agreement

or, if a Notice to Proceed is given, on the day indicated in the Notice to Proceed. A Notice to Proceed may be given at any time within 30 days after the Effective Date of the Agreement. In no event will the Contract Times com- mence to run later than the sixtieth day after the day of Bid opening or the thirtieth day after the Effective Date of the Agreement, whichever date is earlier.

2.04 Starting the Work

A. Contractor shall start to perform the Work on the date when the Contract Times commence to run. No Work shall be done at the Site prior to the date on which the Contract Times commence to run.

2.05 Before Starting Construction

A. Preliminary Schedules: Within 10 days after the Effective Date of the Agreement (unless otherwise specified in the General Requirements), Contractor shall submit to Engineer for timely review:

A. a preliminary Progress Schedule; indicating the times (numbers of days or dates) for starting and completing the various stages of the Work, including any Milestones specified in the Contract Documents;

B.a preliminary Schedule of Submittals; and

C.a preliminary Schedule of Values for all of the Work which includes quantities and prices of items which when added together equal the Contract Price and subdi- vides the Work into component parts in sufficient detail to serve as the basis for progress payments during performance of the Work. Such prices will include an appropriate amount of overhead and profit applicable to each item of Work.

2.06 Preconstruction Conference

A. Before any Work at the Site is started, a conference attended by Owner, Contractor, Engineer, and others as appropriate will be held to establish a working understanding among the parties as to the Work and to discuss the schedules referred to in Paragraph 2.05.A, procedures for handling Shop Drawings and other submittals, processing Applications for Payment, and maintaining required records.

2.07 Initial Acceptance of Schedules

A. At least 10 days before submission of the first Application for Payment a conference attended by Contractor, Engineer, and others as appropriate will be held to review for acceptability to Engineer as provided below the schedules submitted in accordance with Paragraph 2.05.A. Contractor shall have an additional 10 days to make corrections and adjustments and to complete and resubmit the schedules. No progress payment shall be made to Contractor until acceptable schedules are

Page 58: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC-10

submitted to Engineer.

Page 59: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC-11

A. The Progress Schedule will be acceptable to Engineer if it provides an orderly progression of the Work to completion within the Contract Times. Such acceptance will not impose on Engineer responsibility for the Progress Schedule, for sequencing, scheduling, or progress of the Work nor interfere with or relieve Contractor from Contractor’s full responsibility therefor.

B. Contractor’s Schedule of Submittals will be acceptable to Engineer if it provides a workable arrangement for reviewing and processing the required submittals.

C. Contractor’s Schedule of Values will be acceptable to Engineer as to form and substance if it provides a reasonable allocation of the Contract Price to component parts of the Work.

ARTICLE 3 - CONTRACT DOCUMENTS: INTENT, AMENDING, REUSE

3.01 Intent

A. The Contract Documents are complementary; what is required by one is as binding as if required by all.

B. It is the intent of the Contract Documents to describe a functionally complete Project (or part thereof) to be constructed in accordance with the Contract Docu- ments. Any labor, documentation, services, materials, or equipment that may reasonably be inferred from the Contract Documents or from prevailing custom or trade usage as being required to produce the intended result will be provided whether or not specifically called for at no additional cost to Owner.

C. Clarifications and interpretations of the Contract Documents shall be issued by Engineer as provided in Article 9.

3.02 Reference Standards

A. Standards, Specifications, Codes, Laws, and Regulations

1. Reference to standards, specifications, manuals, or codes of any technical society, organization, or association, or to Laws or Regulations, whether such reference be specific or by implication, shall mean the standard, specification, manual, code, or Laws or Regula- tions in effect at the time of opening of Bids (or on the Effective Date of the Agreement if there were no Bids), except as may be otherwise specifically stated in the Contract Documents.

2. No provision of any such standard, specification, manual or code, or any instruction of a Supplier shall be effective to change the duties or

responsibilities of Owner, Contractor, or Engineer, or any of their subcontractors, consultants, agents, or employees from those set forth in the Contract Documents. No such provision or instruction shall be effective to assign to Owner, or Engineer, or any of, their Related Entities, any duty or authority to supervise or direct the performance of the Work or any duty or authority to undertake respon- sibility inconsistent with the provisions of the Contract Documents.

3.03 Reporting and Resolving Discrepancies

A. Reporting Discrepancies

1. Contractor’s Review of Contract Documents Before Starting Work: Before undertaking each part of the Work, Contractor shall carefully study and compare the Contract Documents and check and verify pertinent figures therein and all applicable field measurements. Contractor shall promptly report in writing to Engineer any conflict, error, ambiguity, or discrepancy which Contractor may discover and shall obtain a written interpretation or clarification from Engineer before proceeding with any Work affected thereby.

2. Contractor’s Review of Contract Documents During Performance of Work: If, during the performance of the Work, Contractor discovers any conflict, error, ambiguity, or discrepancy within the Contract Documents or between the Contract Documents and any provision of any Law or Regulation applicable to the performance of the Work or of any standard, specification, manual or code, or of any instruction of any Supplier, Contractor shall promptly report it to Engineer in writing. Contractor shall not proceed with the Work affected thereby (except in an emergency as required by Paragraph 6.16.A) until an amendment or supplement to the Contract Documents has been issued by one of the methods indicated in Paragraph 3.04.

3. Contractor shall not be liable to Owner or Engineer for failure to report any conflict, error, ambigu- ity, or discrepancy in the Contract Documents unless Contractor knew or reasonably should have known thereof.

B. Resolving Discrepancies

1. Except as may be otherwise specifically stated in the Contract Documents, the provisions of the Contract Documents shall take precedence in resolving any conflict, error, ambiguity, or discrepancy between the provisions of the Contract Documents and:

a. the provisions of any standard, specification, manual, code, or instruction (whether or not specifically incorporated by reference in the Contract Documents); or

b. the provisions of any Laws or Regulations applicable to the performance of the Work

Page 60: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 10

(unless such an interpretation of the provisions of the Contract Documents would result in viola- tion of such Law or Regulation).

3.04 Amending and Supplementing Contract Documents

A. The Contract Documents may be amended to provide for additions, deletions, and revisions in the Work or to modify the terms and conditions thereof by either a Change Order or a Work Change Directive.

B. The requirements of the Contract Documents may be supplemented, and minor variations and deviations in the Work may be authorized, by one or more of the following ways:

1. A Field Order;

2. Engineer’s approval of a Shop Drawing or Sample; (Subject to the provisions of Paragraph 6.17.D.3); or

3. Engineer’s written interpretation or clarification.

3.05 Reuse of Documents

A. Contractor and any Subcontractor or Supplier or other individual or entity performing or furnishing all of the Work under a direct or indirect contract with Contractor, shall not:

1. have or acquire any title to or ownership rights in any of the Drawings, Specifications, or

other documents (or copies of any thereof) prepared by or bearing the seal of Engineer or Engineer’s consultants, including electronic media editions; or

2. reuse any of such Drawings, Specifications, other documents, or copies thereof on extensions

of the Project or any other project without written consent of Owner and Engineer and specific written verification or adaption by Engineer.

B. The prohibition of this Paragraph 3.05 will survive final payment, or termination of the Contract. Nothing herein shall preclude Contractor from retaining copies of the Contract Documents for record purposes.

3.06 Electronic Data

A. Copies of data furnished by Owner or Engineer to Contractor or Contractor to Owner or Engineer that may be relied upon are limited to the printed copies (also known as hard copies). Files in electronic media format of text, data, graphics, or other types are furnished only for the convenience of the receiving party. Any conclusion or information obtained or derived from such electronic files will be at the user’s

sole risk. If there is a discrepancy between the electronic files and the hard copies, the hard copies govern.

B. Because data stored in electronic media format can deteriorate or be modified inadvertently or otherwise without authorization of the data’s creator, the party receiving electronic files agrees that it will perform acceptance tests or procedures within 60 days, after which the receiving party shall be deemed to have accepted the data thus transferred. Any errors detected within the 60- day acceptance period will be corrected by the transferring party..

C. When transferring documents in electronic media format, the transferring party makes no representations as to long term compatibility, usability, or readability of documents resulting from the use of software application packages, operating systems, or computer hardware differing from those used by the data’s creator.

ARTICLE 4 - AVAILABILITY OF LANDS; SUBSURFACE AND PHYSICAL CONDITIONS; HAZARDOUS ENVIRONMENTAL CONDITIONS; REFERENCE POINTS

4.01 Availability of Lands

A. Owner shall furnish the Site. Owner shall notify Contractor of any encumbrances or restrictions not of general application but specifically related to use of the Site with which Contractor must comply in performing the Work. Owner will obtain in a timely manner and pay for easements for permanent structures or permanent changes in existing facilities. If Contractor and Owner are unable to agree on entitlement to or on the amount or extent, if any, of any adjustment in the Contract Price or Contract Times, or both, as a result of any delay in Owner’s furnishing the Site or a part thereof, Contractor may make a Claim therefor as provided in Paragraph 10.05.

B. Upon reasonable written request, Owner shall furnish Contractor with a current statement of record legal title and legal description of the lands upon which the Work is to be performed and Owner’s interest therein as necessary for giving notice of or filing a mechanic's or construction lien against such lands in accordance with applicable Laws and Regulations.

C. Contractor shall provide for all additional lands and access thereto that may be required for temporary construction facilities or storage of materials and equipment.

Page 61: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 11

4.02 Subsurface and Physical Conditions

A. Reports and Drawings: The Supplementary Conditions identify:

1. those reports of explorations and tests of subsurface conditions at or contiguous to the Site that Engineer has used in preparing the Contract Documents; and

2. those drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the Site (except Underground Facilities) that Engineer has used in preparing the Contract Documents.

B. Limited Reliance by Contractor on Technical Data Authorized: Contractor may rely upon the general accuracy of the “technical data” contained in such reports and drawings, but such reports and drawings are not Contract Documents. Such “technical data” is identified in the Supplementary Conditions. Except for such reliance on such “technical data,” Contractor may not rely upon or make any claim against Owner or Engineer, or any of their Related Entities with respect to:

1. the completeness of such reports and drawings for Contractor’s purposes, including, but not limited to, any aspects of the means, methods, techniques, sequences, and procedures of construction to be employed by Contractor, and safety precautions and programs incident thereto; or

2. other data, interpretations, opinions, and information contained in such reports or shown or indicated in such drawings; or

3. any Contractor interpretation of or conclusion drawn from any "technical data" or any such other data, interpretations, opinions, or information.

4.03 Differing Subsurface or Physical Conditions

A. Notice: If Contractor believes that any subsur- face or physical condition at or contiguous to the Site that is uncovered or revealed either:

1. is of such a nature as to establish that any “technical data” on which Contractor is entitled to rely as provided in Paragraph 4.02 is materially inaccurate; or

2. is of such a nature as to require a change in the Contract Documents; or

3. differs materially from that shown or indicated in the Contract Documents; or

4. is of an unusual nature, and differs materially from conditions ordinarily encountered and generally recognized as inherent in work of the character provided for in the Contract Documents;

then Contractor shall, promptly after becoming aware thereof and before further disturbing the subsurface or physical conditions or performing any Work in connec- tion therewith (except in an emergency as required by Paragraph 6.16.A), notify Owner and Engineer in writing about such condition. Contractor shall not further disturb such condition or perform any Work in connection therewith (except as aforesaid) until receipt of written order to do so.

B. Engineer’s Review: After receipt of written notice as required by Paragraph 4.03.A, Engineer will promptly review the pertinent condition, determine the necessity of Owner's obtaining additional exploration or tests with respect thereto, and advise Owner in writing (with a copy to Contractor) of Engineer’s findings and conclusions.

C. Possible Price and Times Adjustments

1. The Contract Price or the Contract Times, or both, will be equitably adjusted to the extent that the existence of such differing subsurface or physical condition causes an increase or decrease in Contractor’s cost of, or time required for, performance of the Work; subject, however, to the following:

a. such condition must meet any one or more of the categories described in Paragraph 4.03.A; and

b. with respect to Work that is paid for on a Unit Price Basis, any adjustment in Contract Price will be subject to the provisions of Paragraphs 9.07 and 11.03.

2. Contractor shall not be entitled to any adjustment in the Contract Price or Contract Times if:

a. Contractor knew of the existence of such conditions at the time Contractor made a final commitment to Owner with respect to Contract Price and Contract Times by the submission of a Bid or becoming bound under a negotiated contract; or

b. the existence of such condition could reasonably have been discovered or revealed as a result of any examination, investigation, explo- ration, test, or study of the Site and contiguous areas required by the Bidding Requirements or Contract Documents to be conducted by or for Contractor prior to Contractor's making such final commitment; or

Page 62: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 12

c. Contractor failed to give the written notice as required by Paragraph 4.03.A.

3. If Owner and Contractor are unable to agree on entitlement to or on the amount or extent, if any, of any adjustment in the Contract Price or Contract Times, or both, a Claim may be made therefor as provided in Paragraph 10.05. However, Owner and Engineer, and any of their Related Entities shall not be liable to Contractor for any claims, costs, losses, or damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) sustained by Contractor on or in connection with any other project or anticipated project.

4.04 Underground Facilities

A. Shown or Indicated: The information and data shown or indicated in the Contract Documents with respect to existing Underground Facilities at or contiguous to the Site is based on information and data furnished to Owner or Engineer by the owners of such Underground Facilities, including Owner, or by others. Unless it is otherwise expressly provided in the Sup- plementary Conditions:

1. Owner and Engineer shall not be responsible for the accuracy or completeness of any such information or data; and

2. the cost of all of the following will be included in the Contract Price, and Contractor shall have full responsibility for:

a. reviewing and checking all such information and data,

b. locating all Underground Facilities shown or indicated in the Contract Documents,

c. coordination of the Work with the owners of such Underground Facilities, including Owner, during construction, and

d. the safety and protection of all such Under- ground Facilities and repairing any damage thereto resulting from the Work.

B. Not Shown or Indicated

1. If an Underground Facility is uncovered or revealed at or contiguous to the Site which was not shown or indicated, or not shown or indicated with reasonable accuracy in the Contract Documents, Contractor shall, promptly after becoming aware thereof and before further disturbing conditions affected thereby or performing any Work in connection therewith (except in an emergency as required by Paragraph 6.16.A), identify the owner of such Underground Facility and give written notice to that owner and to Owner and Engineer. Engineer will

promptly review the Underground Facility and determine the extent, if any, to which a change is required in the Contract Documents to reflect and document the consequences of the existence or location of the Under- ground Facility. During such time, Contractor shall be responsible for the safety and protection of such Underground Facility.

2. If Engineer concludes that a change in the Contract Documents is required, a Work Change Directive or a Change Order will be issued to reflect and document such consequences. An equitable adjustment shall be made in the Contract Price or Contract Times, or both, to the extent that they are attributable to the existence or location of any Underground Facility that was not shown or indicated or not shown or indicated with reasonable accuracy in the Contract Documents and that Contractor did not know of and could not reasonably have been expected to be aware of or to have anticipated. If Owner and Contractor are unable to agree on entitlement to or on the amount or extent, if any, of any such adjustment in Contract Price or Contract Times, Owner or Contractor may make a Claim therefor as provided in Paragraph 10.05.

4.05 Reference Points

A. Owner shall provide engineering surveys to establish reference points for construction which in Engineer’s judgment are necessary to enable Contractor to proceed with the Work. Contractor shall be responsible for laying out the Work, shall protect and preserve the established reference points and property monuments, and shall make no changes or relocations without the prior written approval of Owner. Contractor shall report to Engineer whenever any reference point or property monument is lost or destroyed or requires relocation because of necessary changes in grades or locations, and shall be responsible for the accurate replacement or relocation of such reference points or property monuments by professionally qualified personnel.

4.06 Hazardous Environmental Condition at Site

A. Reports and Drawings: Reference is made to the Supplementary Conditions for the identification of those reports and drawings relating to a Hazardous Environmental Condition identified at the Site, if any, that have been utilized by the Engineer in the preparation of the Contract Documents.

B. Limited Reliance by Contractor on Technical Data Authorized: Contractor may rely upon the general accuracy of the “technical data” contained in such reports and drawings, but such reports and drawings are not Contract Documents. Such “technical data” is identified in the Supplementary Conditions. Except for such reliance on such “technical data,” Contractor may not rely upon or make any claim against Owner or Engineer, or any of their Related Entities with respect to:

Page 63: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 13

1. the completeness of such reports and drawings for Contractor’s purposes, including, but not limited to, any aspects of the means, methods, techniques, sequences and procedures of construction to be employed by Contractor and safety precautions and programs incident thereto; or

2. other data, interpretations, opinions and information contained in such reports or shown or indicated in such drawings; or

3. any Contractor interpretation of or conclusion drawn from any “technical data” or any such other data, interpretations, opinions or information.

C. Contractor shall not be responsible for any Hazardous Environmental Condition uncovered or re- vealed at the Site which was not shown or indicated in Drawings or Specifications or identified in the Contract Documents to be within the scope of the Work. Contractor shall be responsible for a Hazardous Environmental Condition created with any materials brought to the Site by Contractor, Subcontractors, Suppliers, or anyone else for whom Contractor is responsible.

D. If Contractor encounters a Hazardous Environmental Condition or if Contractor or anyone for whom Contractor is responsible creates a Hazardous Environmental Condition, Contractor shall immediately:(i) secure or otherwise isolate such condition; (ii) stop all Work in connection with such condition and in any area affected thereby (except in an emergency as required by Paragraph 6.16.A); and (iii) notify Owner and Engineer (and promptly thereafter confirm such notice in writing). Owner shall promptly consult with Engineer concerning the necessity for Owner to retain a qualified expert to evaluate such condition or take corrective action, if any.

E. Contractor shall not be required to resume Work in connection with such condition or in any affected area until after Owner has obtained any required permits related thereto and delivered to Contractor written notice:(i) specifying that such condition and any affected area is or has been rendered safe for the resumption of Work; or(ii) specifying any special conditions under which such Work may be resumed safely. If Owner and Contractor cannot agree as to entitlement to or on the amount or extent, if any, of any adjustment in Contract Price or Contract Times, or both, as a result of such Work stop-

entitlement to or on the amount or extent, if any, of an adjustment in Contract Price or Contract Times as a result of deleting such portion of the Work, then either party may make a Claim therefor as provided in Paragraph10.05. Owner may have such deleted portion of the Work performed by Owner’s own forces or others in accordance with Article 7.

G. To the fullest extent permitted by Laws and Regulations, Owner shall indemnify and hold harmless Contractor, Subcontractors, and Engineer, and the officers, directors, partners, employees, agents, consultants, and subcontractors of each and any of them from and against all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to a Hazardous Environmental Condition, provided that such Hazardous Environmental Condition: (i) was not shown or indicated in the Drawings or Specifications or identified in the Contract Documents to be included within the scope of the Work, and (ii) was not created by Contractor or by anyone for whom Contractor is responsible. Nothing in this Paragraph 4.06. G shall obligate Owner to indemnify any individual or entity from and against the conse- quences of that individual’s or entity’s own negligence.

H. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold harmless Owner and Engineer, and the officers, directors, partners, employees, agents, consultants, and subcontractors of each and any of them from and against all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to a Hazardous Environmental Condition created by Contractor or by anyone for whom Contractor is responsible. Nothing in this Paragraph 4.06.H shall obligate Contractor to indemnify any individual or entity from and against the consequences of that individual’s or entity’s own negligence.

I. The provisions of Paragraphs 4.02, 4.03, and4.04 do not apply to a Hazardous Environmental Condition uncovered or revealed at the Site.

ARTICLE 5 - BONDS AND INSURANCEpage or such special conditions under which Work is agreed to be resumed by Contractor, either party maymake a Claim therefor as provided in Paragraph 10.05.

F. If after receipt of such written notice Contractor does not agree to resume such Work based on a reasonable belief it is unsafe, or does not agree to resume such Work under such special conditions, then Owner may order the portion of the Work that is in the area affected by such condition to be deleted from the Work. If Owner and Contractor cannot agree as to

5.01 Performance, Payment, and Other Bonds

A. Contractor shall furnish performance and payment bonds, each in an amount at least equal to the Contract Price as security for the faithful performance and payment of all of Contractor’s obligations under the Contract Documents. These bonds shall remain in effect until one year after the date when final payment becomes

Page 64: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 14

due or until completion of the correction period specified

Page 65: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 15

in Paragraph 13.07, whichever is later, except as provided otherwise by Laws or Regulations or by the Contract Documents. Contractor shall also furnish such other bonds as are required by the Contract Documents.

B. All bonds shall be in the form prescribed by the Contract Documents except as provided otherwise by Laws or Regulations, and shall be executed by such sureties as are named in the current list of “Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and as Acceptable Reinsuring Compa- nies” as published in Circular 570 (amended) by the Financial Management Service, Surety Bond Branch, U.S. Department of the Treasury. All bonds signed by an agent must be accompanied by a certified copy of the agent’s authority to act.

C. If the surety on any bond furnished by Contractor is declared bankrupt or becomes insolvent or its right to do business is terminated in any state where any part of the Project is located or it ceases to meet the requirements of Paragraph 5.01.B, Contractor shall promptly notify Owner and Engineer and shall, within 20 days after the event giving rise to such notification, provide another bond and surety, both of which shall comply with the requirements of Paragraphs 5.01.B and 5.02.

5.02 Licensed Sureties and Insurers

A. All bonds and insurance required by the Contract Documents to be purchased and maintained by Owner or Contractor shall be obtained from surety or insurance companies that are duly licensed or authorized in the jurisdiction in which the Project is located to issue bonds or insurance policies for the limits and coverages so required. Such surety and insurance companies shall also meet such additional requirements and qualifications as may be provided in the Supplementary Conditions.

5.03 Certificates of Insurance

A. Contractor shall deliver to Owner, with copies to each additional insured identified in the Supplementary Conditions, certificates of insurance (and other evidence of insurance requested by Owner or any other additional insured) which Contractor is required to purchase and maintain.

B. Owner shall deliver to Contractor, with copies to each additional insured identified in the Supplementary Conditions, certificates of insurance (and other evidence of insurance requested by Contractor or any other additional insured) which Owner is required to purchase and maintain.

5.04 Contractor’s Liability Insurance

A. Contractor shall purchase and maintain such liability and other insurance as is appropriate for the Work being performed and as will provide protection

from claims set forth below which may arise out of or result from Contractor’s performance of the Work and Contractor’s other obligations under the Contract Documents, whether it is to be performed by Contractor, any Subcontractor or Supplier, or by anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts any of them may be liable:

1. claims under workers’ compensation, disability benefits, and other similar employee benefit acts;

2. claims for damages because of bodily injury, occupational sickness or disease, or death of Contractor’s employees;

3. claims for damages because of bodily injury, sickness or disease, or death of any person other than Contractor’s employees;

4. claims for damages insured by reasonably available personal injury liability coverage which are sus- tained:

a. by any person as a result of an offense directly or indirectly related to the employment of such person by Contractor, or

b. by any other person for any other reason;

5. claims for damages, other than to the Work itself, because of injury to or destruction of tangible property wherever located, including loss of use resulting therefrom; and

6. claims for damages because of bodily injury or death of any person or property damage arising out of the ownership, maintenance or use of any motor vehicle.

B. The policies of insurance required by this Paragraph 5.04 shall:

1. with respect to insurance required by Paragraphs 5.04.A.3 through 5.04.A.6 inclusive, include as additional insured (subject to any customary exclusion regarding professional liability) Owner and Engineer, and any other individuals or entities identified in the Supple- mentary Conditions, all of whom shall be listed as addi- tional insureds, and include coverage for the respective officers, directors, partners, employees, agents, consultants and subcontractors of each and any of all such additional insureds, and the insurance afforded to these additional insureds shall provide primary coverage for all claims covered thereby;

2. include at least the specific coverages and be written for not less than the limits of liability provided in the Supplementary Conditions or required by Laws or Regulations, whichever is greater;

Page 66: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 16

3. include completed operations insurance;

4. include contractual liability insurance covering Contractor’s indemnity obligations under Paragraphs 6.11 and 6.20;

5. contain a provision or endorsement that the coverage afforded will not be canceled, materially changed or renewal refused until at least 30 days prior written notice has been given to Owner and Contractor and to each other additional insured identified in the Supplementary Conditions to whom a certificate of insurance has been issued (and the certificates of insurance furnished by the Contractor pursuant to Paragraph 5.03 will so provide);

6. remain in effect at least until final payment and at all times thereafter when Contractor may be correcting, removing, or replacing defective Work in accordance with Paragraph 13.07; and

7. with respect to completed operations insur- ance, and any insurance coverage written on a claims- made basis, remain in effect for at least two years after final payment.

a. Contractor shall furnish Owner and each other additional insured identified in the Supple- mentary Conditions, to whom a certificate of insurance has been issued, evidence satisfactory to Owner and any such additional insured of continuation of such insurance at final payment and one year thereafter.

5.05 Owner’s Liability Insurance

A. In addition to the insurance required to be provided by Contractor under Paragraph 5.04, Owner, at Owner’s option, may purchase and maintain at Owner’s expense Owner’s own liability insurance as will protect Owner against claims which may arise from operations under the Contract Documents.

5.06 Property Insurance

A. Unless otherwise provided in the Supple- mentary Conditions, Owner shall purchase and maintain property insurance upon the Work at the Site in the amount of the full replacement cost thereof (subject to such deductible amounts as may be provided in the Supplementary Conditions or required by Laws and Regulations). This insurance shall:

1. include the interests of Owner, Contractor, Subcontractors, and Engineer, and any other individuals or entities identified in the Supplementary Conditions, and the officers, directors, partners, employees, agents, consultants and subcontractors of each and any of them, each of whom is deemed to have an insurable interest and shall be listed as an insured or additional insured;

2. be written on a Builder’s Risk “all-risk” or open peril or special causes of loss policy form that shall at least include insurance for physical loss or damage to the Work, temporary buildings, false work, and materials and equipment in transit, and shall insure against at least the following perils or causes of loss: fire, lightning, extended coverage, theft, vandalism and malicious mischief, earthquake, collapse, debris removal, demolition occasioned by enforcement of Laws and Regulations, water damage, (other than caused by flood) and such other perils or causes of loss as may be specifi- cally required by the Supplementary Conditions;

3. include expenses incurred in the repair or replacement of any insured property (including but not limited to fees and charges of engineers and architects);

4. cover materials and equipment stored at the Site or at another location that was agreed to in writing by Owner prior to being incorporated in the Work, provided that such materials and equipment have been included in an Application for Payment recommended by Engineer;

5. allow for partial utilization of the Work byOwner;

6. include testing and startup; and

7. be maintained in effect until final payment is made unless otherwise agreed to in writing by Owner, Contractor, and Engineer with 30 days written notice to each other additional insured to whom a certificate of insurance has been issued.

B. Owner shall purchase and maintain such boiler and machinery insurance or additional property insurance as may be required by the Supplementary Conditions or Laws and Regulations which will include the interests of Owner, Contractor, Subcontractors, and Engineer, and any other individuals or entities identified in the Supplementary Conditions, and the officers, directors, partners, employees, agents, consultants and subcontractors of each and any of them, each of whom is deemed to have an insurable interest and shall be listed as an insured or additional insured.

C. All the policies of insurance (and the certifi- cates or other evidence thereof) required to be purchased and maintained in accordance with Paragraph 5.06 will contain a provision or endorsement that the coverage afforded will not be canceled or materially changed or renewal refused until at least 30 days prior written notice has been given to Owner and Contractor and to each other additional insured to whom a certificate of insurance has been issued and will contain waiver provisions in accor- dance with Paragraph 5.07.

D. Owner shall not be responsible for purchasing and maintaining any property insurance specified in this Paragraph 5.06 to protect the interests of Contractor,

Page 67: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 17

Subcontractors, or others in the Work to the extent of any

Page 68: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 18

deductible amounts that are identified in the Supple- mentary Conditions. The risk of loss within such identified deductible amount will be borne by Contractor, Subcontractors, or others suffering any such loss, and if any of them wishes property insurance coverage within the limits of such amounts, each may purchase and maintain it at the purchaser’s own expense.

E. If Contractor requests in writing that other special insurance be included in the property insurance policies provided under Paragraph 5.06, Owner shall, if possible, include such insurance, and the cost thereof will be charged to Contractor by appropriate Change Order. Prior to commencement of the Work at the Site, Owner shall in writing advise Contractor whether or not such other insurance has been procured by Owner.

5.07 Waiver of Rights

A. Owner and Contractor intend that all policies purchased in accordance with Paragraph 5.06 will protect Owner, Contractor, Subcontractors, and Engineer, and all other individuals or entities identified in the Supple- mentary Conditions to be listed as insureds or additional insureds (and the officers, directors, partners, employees, agents, consultants and subcontractors of each and any of them) in such policies and will provide primary coverage for all losses and damages caused by the perils or causes of loss covered thereby. All such policies shall contain provisions to the effect that in the event of payment of any loss or damage the insurers will have no rights of recovery against any of the insureds or additional insureds thereunder. Owner and Contractor waive all rights against each other and their respective officers, directors, partners, employees, agents, consultants and subcontractors of each and any of them for all losses and damages caused by, arising out of or resulting from any of the perils or causes of loss covered by such policies and any other property insurance applicable to the Work; and, in addition, waive all such rights against Subcontractors, and Engineer, and all other individuals or entities identified in the Supplementary Conditions to be listed as insured or additional insured (and the officers, directors, partners, employees, agents, consultants and subcontractors of each and any of them) under such policies for losses and damages so caused. None of the above waivers shall extend to the rights that any party making such waiver may have to the proceeds of insurance held by Owner as trustee or otherwise payable under any policy so issued.

B. Owner waives all rights against Contractor, Subcontractors, and Engineer, and the officers, directors, partners, employees, agents, consultants and subcontractors of each and any of them for:

1. loss due to business interruption, loss of use, or other consequential loss extending beyond direct physical loss or damage to Owner’s property or the Work caused by, arising out of, or resulting from fire or other perils whether or not insured by Owner; and

2. loss or damage to the completed Project or part thereof caused by, arising out of, or resulting from fire or other insured peril or cause of loss covered by any property insurance maintained on the completed Project or part thereof by Owner during partial utilization pursuant to Paragraph 14.05, after Substantial Completion pursuant to Paragraph 14.04, or after final payment pursuant to Paragraph 14.07.

C. Any insurance policy maintained by Owner covering any loss, damage or consequential loss referred to in Paragraph 5.07.B shall contain provisions to the effect that in the event of payment of any such loss, damage, or consequential loss, the insurers will have no rights of recovery against Contractor, Subcontractors, or Engineer, and the officers, directors, partners, employees, agents, consultants and subcontractors of each and any of them.

5.08 Receipt and Application of Insurance Proceeds

A. Any insured loss under the policies of insurance required by Paragraph 5.06 will be adjusted with Owner and made payable to Owner as fiduciary for the insureds, as their interests may appear, subject to the requirements of any applicable mortgage clause and of Paragraph 5.08.B. Owner shall deposit in a separate account any money so received and shall distribute it in accordance with such agreement as the parties in interest may reach. If no other special agreement is reached, the damaged Work shall be repaired or replaced, the moneys so received applied on account thereof, and the Work and the cost thereof covered by an appropriate Change Order .

B. Owner as fiduciary shall have power to adjust and settle any loss with the insurers unless one of the parties in interest shall object in writing within 15 days after the occurrence of loss to Owner’s exercise of this power. If such objection be made, Owner as fiduciary shall make settlement with the insurers in accordance with such agreement as the parties in interest may reach. If no such agreement among the parties in interest is reached, Owner as fiduciary shall adjust and settle the loss with the insurers and, if required in writing by any party in interest, Owner as fiduciary shall give bond for the proper performance of such duties.

5.09 Acceptance of Bonds and Insurance; Option to Replace

A. If either Owner or Contractor has any objection to the coverage afforded by or other provisions of the bonds or insurance required to be purchased and maintained by the other party in accordance with Article 5

Page 69: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 19

on the basis of non-conformance with the Contract

Page 70: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 20

Documents, the objecting party shall so notify the other party in writing within 10 days after receipt of the certificates (or other evidence requested) required by Paragraph 2.01.B. Owner and Contractor shall each provide to the other such additional information in respect of insurance provided as the other may reasonably request. If either party does not purchase or maintain all of the bonds and insurance required of such party by the Contract Documents, such party shall notify the other party in writing of such failure to purchase prior to the start of the Work, or of such failure to maintain prior to any change in the required coverage. Without prejudice to any other right or remedy, the other party may elect to obtain equivalent bonds or insurance to protect such other party's interests at the expense of the party who was required to provide such coverage, and a Change Order shall be issued to adjust the Contract Price accordingly.

5.10 Partial Utilization, Acknowledgment of Property Insurer

A. If Owner finds it necessary to occupy or use a portion or portions of the Work prior to Substantial Completion of all the Work as provided in Paragraph 14.05, no such use or occupancy shall commence before the insurers providing the property insurance pursuant to Paragraph 5.06 have acknowledged notice thereof and in writing effected any changes in coverage necessitated thereby. The insurers providing the property insurance shall consent by endorsement on the policy or policies, but the property insurance shall not be canceled or permitted to lapse on account of any such partial use or occupancy.

ARTICLE 6 - CONTRACTOR’S RESPONSIBILITIES

6.01 Supervision and Superintendence

A. Contractor shall supervise, inspect, and direct the Work competently and efficiently, devoting such attention thereto and applying such skills and expertise as may be necessary to perform the Work in accordance with the Contract Documents. Contractor shall be solely responsible for the means, methods, techniques, sequences, and procedures of construction. Contractor shall not be responsible for the negligence of Owner or Engineer in the design or specification of a specific means, method, technique, sequence, or procedure of construction which is shown or indicated in and expressly required by the Contract Documents.

B. At all times during the progress of the Work, Contractor shall assign a competent resident superin- tendent who shall not be replaced without written notice to Owner and Engineer except under extraordinary circumstances. The superintendent will be Contractor’s representative at the Site and shall have authority to act on behalf of Contractor. All communications given to or

received from the superintendent shall be binding on Contractor.

6.02 Labor; Working Hours

A. Contractor shall provide competent, suitably qualified personnel to survey and lay out the Work and perform construction as required by the Contract Docu- ments. Contractor shall at all times maintain good disci- pline and order at the Site.

B. Except as otherwise required for the safety or protection of persons or the Work or property at the Site or adjacent thereto, and except as otherwise stated in the Contract Documents, all Work at the Site shall be performed during regular working hours. Contractor will not permit the performance of Work on a Saturday, Sunday, or any legal holiday without Owner’s written consent (which will not be unreasonably withheld) given after prior written notice to Engineer.

6.03 Services, Materials, and Equipment

A. Unless otherwise specified in the Contract Documents, Contractor shall provide and assume full responsibility for all services, materials, equipment, labor, transportation, construction equipment and machinery, tools, appliances, fuel, power, light, heat, telephone, water, sanitary facilities, temporary facilities, and all other facilities and incidentals necessary for the performance, testing, start-up, and completion of the Work.

B. All materials and equipment incorporated into the Work shall be as specified or, if not specified, shall be of good quality and new, except as otherwise provided in the Contract Documents. All special warranties and guarantees required by the Specifications shall expressly run to the benefit of Owner. If required by Engineer, Contractor shall furnish satisfactory evidence (including reports of required tests) as to the source, kind, and quality of materials and equipment.

C. All materials and equipment shall be stored, applied, installed, connected, erected, protected, used, cleaned, and conditioned in accordance with instructions of the applicable Supplier, except as otherwise may be provided in the Contract Documents.

6.04 Progress Schedule

A. Contractor shall adhere to the Progress Schedule established in accordance with Paragraph 2.07 as it may be adjusted from time to time as provided below.

Page 71: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 21

1. Contractor shall submit to Engineer for acceptance (to the extent indicated in Paragraph 2.07) proposed adjustments in the Progress Schedule that will not result in changing the Contract Times. Such adjust- ments will comply with any provisions of the General Re- quirements applicable thereto.

2. Proposed adjustments in the Progress Schedule that will change the Contract Times shall be submitted in accordance with the requirements of Article12. Adjustments in Contract Times may only be made by a Change Order.

6.05 Substitutes and “Or-Equals”

A. Whenever an item of material or equipment is specified or described in the Contract Documents by using the name of a proprietary item or the name of a particular Supplier, the specification or description is intended to establish the type, function, appearance, and quality required. The name of certain brand, make Manufacturer, or definite specification is utilized only to denote the quality standard of product desired and the bidder is not restricted to the specific brand, make, manufacturer, or definite specification named.The specific brand, make manufacturer, or definite specification named is used only to convey to prospective bidders the general style, type, character and quality of product desired. Equivalent products will be acceptable if preapproved by the professionally employed engineer for this project.

1. “Or-Equal” Items: If in Engineer’s sole discretion an item of material or equipment proposed by Contractor is functionally equal to that named and sufficiently similar so that no change in related Work will be required, it may be considered by Engineer as an “or-equal” item, in which case review and approval of the proposed item may, in Engineer’s sole discretion, be accomplished without compliance with some or all of the requirements for approval of proposed substitute items. For the purposes of this Paragraph 6.05.A.1, a proposed item of material or equipment will be considered functionally equal to an item so named if:

a. in the exercise of reasonable judgment Engineer determines that:

1) it is at least equal in materials of construction, quality, durability, appearance, strength, and design characteristics;

2) it will reliably perform at least equally well the function and achieve the results imposed by the design concept of the completed Project as a functioning whole,

3) it has a proven record of performance and availability of responsive service; and

b. Contractor certifies that, if approved and incorporated into the Work:

1) there will be no increase in cost to the Owner or increase in Contract Times, and

2) it will conform substantially to the detailed requirements of the item named in the Contract Documents.

2. Substitute Items

a. If in Engineer’s sole discretion an item of material or equipment proposed by Contractor does not qualify as an “or-equal” item under Paragraph 6.05.A.1, it will be considered a proposed substitute item.

b. Contractor shall submit sufficient information as provided below to allow Engineer to determine that the item of material or equipment proposed is essentially equivalent to that named and an acceptable substitute therefor. Requests for review of proposed substitute items of material or equipment will not be accepted by Engineer from anyone other than Contractor.

c. The requirements for review by Engineer will be as set forth in Paragraph 6.05.A.2.d, as supplemented in the General Requirements and as Engineer may decide is appropriate under the circumstances.

d. Contractor shall make written application to Engineer for review of a proposed substitute item of material or equipment that Contractor seeks to furnish or use. The application:

1) shall certify that the proposed substi- tute item will:

a) perform adequately the functions and achieve the results called for by the general design,

b) be similar in substance to that specified, and

c) be suited to the same use as that specified;

2) will state:

a) the extent, if any, to which the use of the proposed substitute item will preju- dice Contractor’s achievement of Substantial Completion on time;

b) whether or not use of the proposed substitute item in the Work will require

Page 72: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 22

a change in any of the Contract Docu-

Page 73: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 23

ments (or in the provisions of any other direct contract with Owner for other work on the Project) to adapt the design to the proposed substitute item; and

c) whether or not incorporation or use of the proposed substitute item in con- nection with the Work is subject to payment of any license fee or royalty;

3) will identify:

a) all variations of the proposed substitute item from that specified , and

b) available engineering, sales, maintenance, repair, and replacement services;

4) and shall contain an itemized esti- mate of all costs or credits that will result directly or indirectly from use of such substitute item, including costs of redesign and claims of other contractors affected by any resulting change,

B. Substitute Construction Methods or Proce- dures: If a specific means, method, technique, sequence, or procedure of construction is expressly required by the Contract Documents, Contractor may furnish or utilize a substitute means, method, technique, sequence, or procedure of construction approved by Engineer. Contractor shall submit sufficient information to allow Engineer, in Engineer’s sole discretion, to determine that the substitute proposed is equivalent to that expressly called for by the Contract Documents. The requirements for review by Engineer will be similar to those provided in Paragraph 6.05.A.2.

C. Engineer’s Evaluation: Engineer will be allowed a reasonable time within which to evaluate each proposal or submittal made pursuant to Paragraphs 6.05.A and 6.05.B. Engineer may require Contractor to furnish additional data about the proposed substitute item. Engineer will be the sole judge of acceptability. No “or equal” or substitute will be ordered, installed or utilized until Engineer’s review is complete, which will be evidenced by either a Change Order for a substitute or an approved Shop Drawing for an “or equal.” Engineer will advise Contractor in writing of any negative determination.

D. Special Guarantee: Owner may require Contractor to furnish at Contractor’s expense a special performance guarantee or other surety with respect to any substitute.

E. Engineer’s Cost Reimbursement: Engineer will record Engineer’s costs in evaluating a substitute proposed or submitted by Contractor pursuant to Paragraphs 6.05.A.2 and 6.05.B Whether or not Engineer

approves a substitute item so proposed or submitted by Contractor, Contractor shall reimburse Owner for the charges of Engineer for evaluating each such proposed substitute. Contractor shall also reimburse Owner for the charges of Engineer for making changes in the Contract Documents (or in the provisions of any other direct contract with Owner) resulting from the acceptance of each proposed substitute.

F. Contractor’s Expense: Contractor shall provide all data in support of any proposed substitute or “or-equal” at Contractor’s expense.

6.06 Concerning Subcontractors, Suppliers, and Others

A. Contractor shall not employ any Subcon- tractor, Supplier, or other individual or entity (including those acceptable to Owner as indicated in Paragraph 6.06.B), whether initially or as a replacement, against whom Owner may have reasonable objection. Contractor shall not be required to employ any Subcontractor, Supplier, or other individual or entity to furnish or perform any of the Work against whom Contractor has reasonable objection.

B. If the Supplementary Conditions require the identity of certain Subcontractors, Suppliers, or other individuals or entities to be submitted to Owner in advance for acceptance by Owner by a specified date prior to the Effective Date of the Agreement, and if Contractor has submitted a list thereof in accordance with the Supplementary Conditions, Owner’s acceptance (either in writing or by failing to make written objection thereto by the date indicated for acceptance or objection in the Bidding Documents or the Contract Documents) of any such Subcontractor, Supplier, or other individual or entity so identified may be revoked on the basis of reason- able objection after due investigation. Contractor shall submit an acceptable replacement for the rejected Subcontractor, Supplier, or other individual or entity, and the Contract Price will be adjusted by the difference in the cost occasioned by such replacement, and an appropriate Change Order will be issued . No acceptance by Owner of any such Subcontractor, Supplier, or other individual or entity, whether initially or as a replacement, shall consti- tute a waiver of any right of Owner or Engineer to reject defective Work.

C. Contractor shall be fully responsible to Owner and Engineer for all acts and omissions of the Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the Work just as Contractor is responsible for Contractor’s own acts and omissions. Nothing in the Contract Documents:

Page 74: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 20

1. shall create for the benefit of any such Subcontractor, Supplier, or other individual or entity any contractual relationship between Owner or Engineer and any such Subcontractor, Supplier or other individual or entity, nor

2. shall anything in the Contract Documents create any obligation on the part of Owner or Engineer to

pay or to see to the payment of any moneys due any such Subcontractor, Supplier, or other individual or entity

except as may otherwise be required by Lawsand Regulations.

D. Contractor shall be solely responsible for scheduling and coordinating the Work of Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the Work under a direct or indirect contract with Contractor.

E. Contractor shall require all Subcontractors, Suppliers, and such other individuals or entities per- forming or furnishing any of the Work to communicate with Engineer through Contractor.

F. The divisions and sections of the Specifica- tions and the identifications of any Drawings shall not control Contractor in dividing the Work among Subcon- tractors or Suppliers or delineating the Work to be performed by any specific trade.

G. All Work performed for Contractor by a Subcontractor or Supplier will be pursuant to an appro- priate agreement between Contractor and the Subcontractor or Supplier which specifically binds the Subcontractor or Supplier to the applicable terms and conditions of the Contract Documents for the benefit of Owner and Engineer. Whenever any such agreement is with a Subcontractor or Supplier who is listed as an additional insured on the property insurance provided in Paragraph 5.06, the agreement between the Contractor and the Subcontractor or Supplier will contain provisions whereby the Subcontractor or Supplier waives all rights against Owner, Contractor, and Engineer,, and all other individuals or entities identified in the Supplementary Conditions to be listed as insureds or additional insureds (and the officers, directors, partners, employees, agents, consultants and subcontractors of each and any of them) for all losses and damages caused by, arising out of, relating to, or resulting from any of the perils or causes of loss covered by such policies and any other property insurance applicable to the Work. If the insurers on any such policies require separate waiver forms to be signed by any Subcontractor or Supplier, Contractor will obtain the same.

6.07 Patent Fees and Royalties

A. Contractor shall pay all license fees and royalties and assume all costs incident to the use in the performance of the Work or the incorporation in the Work of any invention, design, process, product, or device

which is the subject of patent rights or copyrights held by others. If a particular invention, design, process, product, or device is specified in the Contract Documents for use in the performance of the Work and if to the actual knowledge of Owner or Engineer its use is subject to patent rights or copyrights calling for the payment of any license fee or royalty to others, the existence of such rights shall be disclosed by Owner in the Contract Documents.

B. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold harmless Owner and Engineer, and the officers, directors, partners, employees, agents, consultants and subcontractors of each and any of them from and against all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to any infringement of patent rights or copyrights incident to the use in the performance of the Work or resulting from the incorporation in the Work of any invention, design, process, product, or device not specified in the Contract Documents.

6.08 Permits

A. Unless otherwise provided in the Supple- mentary Conditions, Contractor shall obtain and pay for all construction permits and licenses. Owner shall assist Contractor, when necessary, in obtaining such permits and licenses. Contractor shall pay all governmental charges and inspection fees necessary for the prosecution of the Work which are applicable at the time of opening of Bids, or, if there are no Bids, on the Effective Date of the Agreement. Owner shall pay all charges of utility owners for connections for providing permanent service to the Work.

6.09 Laws and Regulations

A. Contractor shall give all notices required by and shall comply with all Laws and Regulations applica- ble to the performance of the Work. Except where otherwise expressly required by applicable Laws and Regulations, neither Owner nor Engineer shall be responsible for monitoring Contractor’s compliance with any Laws or Regulations.

B. If Contractor performs any Work knowing or having reason to know that it is contrary to Laws or Regulations, Contractor shall bear all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to such Work. However, it shall not be Contractor’s primary responsibility to make certain that the Specifications and Drawings are in accordance with Laws and Regulations, but this shall not relieve Contractor of Contractor’s

Page 75: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 21

obligations under Paragraph 3.03.

Page 76: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 22

C. Changes in Laws or Regulations not known at the time of opening of Bids (or, on the Effective Date of the Agreement if there were no Bids) having an effect on the cost or time of performance of the Work shall be the subject of an adjustment in Contract Price or Contract Times. If Owner and Contractor are unable to agree on entitlement to or on the amount or extent, if any, of any such adjustment, a Claim may be made therefor as provided in Paragraph 10.05.

6.10 Taxes

A. Contractor shall pay all sales, consumer, use, and other similar taxes required to be paid by Contractor in accordance with the Laws and Regulations of the place of the Project which are applicable during the performance of the Work.

6.11 Use of Site and Other Areas

A. Limitation on Use of Site and Other Areas

1. Contractor shall confine construction equip- ment, the storage of materials and equipment, and the operations of workers to the Site and other areas permitted by Laws and Regulations, and shall not unreasonably encumber the Site and other areas with construction equipment or other materials or equipment. Contractor shall assume full responsibility for any damage to any such land or area, or to the owner or occupant thereof, or of any adjacent land or areas resulting from the performance of the Work.

2. Should any claim be made by any such owner or occupant because of the performance of the Work, Contractor shall promptly settle with such other party by negotiation or otherwise resolve the claim by arbitration or other dispute resolution proceeding or at law.

3. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold harmless Owner and Engineer, and the officers, directors, partners, employees, agents, consultants and subcontractors of each and any of them from and against all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to any claim or action, legal or equitable, brought by any such owner or occupant against Owner, Engineer, or any other party indemnified hereunder to the extent caused by or based upon Contractor's performance of the Work.

B. Removal of Debris During Performance of the Work: During the progress of the Work Contractor shall keep the Site and other areas free from accumulations of waste materials, rubbish, and other debris. Removal and disposal of such waste materials, rubbish, and other debris shall conform to applicable Laws and Regulations.

C. Cleaning: Prior to Substantial Completion of the Work Contractor shall clean the Site and the Work and make it ready for utilization by Owner. At the com- pletion of the Work Contractor shall remove from the Site all tools, appliances, construction equipment and machinery, and surplus materials and shall restore to original condition all property not designated for alteration by the Contract Documents.

D. Loading Structures: Contractor shall not load nor permit any part of any structure to be loaded in any manner that will endanger the structure, nor shall Contractor subject any part of the Work or adjacent property to stresses or pressures that will endanger it.

6.12 Record Documents

A. Contractor shall maintain in a safe place at the Site one record copy of all Drawings, Specifications, Addenda, Change Orders, Work Change Directives, Field Orders, and written interpretations and clarifications in good order and annotated to show changes made during construction. These record documents together with all approved Samples and a counterpart of all approved Shop Drawings will be available to Engineer for reference. Upon completion of the Work, these record documents, Samples, and Shop Drawings will be delivered to Engi- neer for Owner.

6.13 Safety and Protection

A. Contractor shall be solely responsible for initiating, maintaining and supervising all safety precau- tions and programs in connection with the Work. Contractor shall take all necessary precautions for the safety of, and shall provide the necessary protection to prevent damage, injury or loss to:

1. all persons on the Site or who may be affected by the Work;

2. all the Work and materials and equipment to be incorporated therein, whether in storage on or off the Site; and

3. other property at the Site or adjacent thereto, including trees, shrubs, lawns, walks, pavements, roadways, structures, utilities, and Underground Facilities not designated for removal, relocation, or replacement in the course of construction.

B. Contractor shall comply with all applicable Laws and Regulations relating to the safety of persons or property, or to the protection of persons or property from damage, injury, or loss; and shall erect and maintain all necessary safeguards for such safety and protection. Contractor shall notify owners of adjacent property and of Underground Facilities and other utility owners when prosecution of the Work may affect them, and shall

Page 77: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 23

cooperate with them in the protection, removal, relocation, and replacement of their property.

C. All damage, injury, or loss to any property referred to in Paragraph 6.13.A.2 or 6.13.A.3 caused, directly or indirectly, in whole or in part, by Contractor, any Subcontractor, Supplier, or any other individual or entity directly or indirectly employed by any of them to perform any of the Work, or anyone for whose acts any of them may be liable, shall be remedied by Contractor (except damage or loss attributable to the fault of Draw- ings or Specifications or to the acts or omissions of Owner or Engineer or , or anyone employed by any of them, or anyone for whose acts any of them may be liable, and not attributable, directly or indirectly, in whole or in part, to the fault or negligence of Contractor or any Subcontractor, Supplier, or other individual or entity directly or indirectly employed by any of them).

D. Contractor’s duties and responsibilities for safety and for protection of the Work shall continue until such time as all the Work is completed and Engineer has issued a notice to Owner and Contractor in accordance with Paragraph 14.07.B that the Work is acceptable (except as otherwise expressly provided in connection with Substantial Completion).

6.14 Safety Representative

A. Contractor shall designate a qualified and experienced safety representative at the Site whose duties and responsibilities shall be the prevention of accidents and the maintaining and supervising of safety precautions and programs.

6.15 Hazard Communication Programs

A. Contractor shall be responsible for coordi- nating any exchange of material safety data sheets or other hazard communication information required to be made available to or exchanged between or among employers at the Site in accordance with Laws or Regulations.

6.16 Emergencies

A. In emergencies affecting the safety or protec- tion of persons or the Work or property at the Site or adjacent thereto, Contractor is obligated to act to prevent threatened damage, injury, or loss. Contractor shall give Engineer prompt written notice if Contractor believes that any significant changes in the Work or variations from the Contract Documents have been caused thereby or are required as a result thereof. If Engineer determines that a change in the Contract Documents is required because of the action taken by Contractor in response to such an emergency, a Work Change Directive or Change Order will be issued.

6.17 Shop Drawings and Samples

A. Contractor shall submit Shop Drawings and Samples to Engineer for review and approval in accor- dance with the acceptable Schedule of Submittals (as required by Paragraph 2.07). Each submittal will be identified as Engineer may require.

1. Shop Drawings

a. Submit number of copies specified in the General Requirements.

b. Data shown on the Shop Drawings will be complete with respect to quantities, dimensions, specified performance and design criteria, materials, and similar data to show Engineer the services, materials, and equipment Contractor proposes to provide and to enable Engineer to review the information for the limited purposes required by Paragraph 6.17.D.

2. Samples: Contractor shall also submit Samples to Engineer for review and approval in accor- dance with the acceptable schedule of Shop Drawings and Sample submittals.

a. Submit number of Samples specified in the Specifications.

b. Clearly identify each Sample as to material, Supplier, pertinent data such as catalog numbers, the use for which intended and other data as Engineer may require to enable Engineer to review the submittal for the limited purposes required by Paragraph 6.17.D.

B. Where a Shop Drawing or Sample is required by the Contract Documents or the Schedule of Submittals, any related Work performed prior to Engineer’s review and approval of the pertinent submittal will be at the sole expense and responsibility of Contractor.

C. Submittal Procedures

1. Before submitting each Shop Drawing or Sample, Contractor shall have determined and verified:

a. all field measurements, quantities, dimensions, specified performance and design criteria, installation requirements, materials, catalog numbers, and similar information with respect thereto;

b. the suitability of all materials with respect to intended use, fabrication, shipping, handling, storage, assembly, and installation pertaining to the performance of the Work;

c. all information relative to Contractor’s

Page 78: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 24

responsibilities for means, methods, techniques,

Page 79: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 25

sequences, and procedures of construction, and safety precautions and programs incident thereto; and

d. shall also have reviewed and coordinated each Shop Drawing or Sample with other Shop Drawings and Samples and with the requirements of the Work and the Contract Documents.

2. Each submittal shall bear a stamp or specific written certification that Contractor has satisfied Contractor’s obligations under the Contract Documents with respect to Contractor’s review and approval of that submittal.

3. With each submittal, Contractor shall give Engineer specific written notice of any variations, that the Shop Drawing or Sample may have from the requirements of the Contract Documents. This notice shall be both a written communication separate from the Shop Drawing’s or Sample Submittal; and, in addition, by a specific notation made on each Shop Drawing or Sample submit- ted to Engineer for review and approval of each such variation.

D. Engineer’s Review

1. Engineer will provide timely review of Shop Drawings and Samples in accordance with the Schedule of Submittals acceptable to Engineer. Engineer’s review and approval will be only to determine if the items covered by the submittals will, after installation or incorporation in the Work, conform to the information given in the Contract Documents and be compatible with the design concept of the completed Project as a functioning whole as indicated by the Contract Docu- ments.

2. Engineer’s review and approval will not extend to means, methods, techniques, sequences, or procedures of construction (except where a particular means, method, technique, sequence, or procedure of con- struction is specifically and expressly called for by the Contract Documents) or to safety precautions or programs incident thereto. The review and approval of a separate item as such will not indicate approval of the assembly in which the item functions.

3. Engineer’s review and approval shall not relieve Contractor from responsibility for any variation from the requirements of the Contract Documents unless Contractor has complied with the requirements of Paragraph 6.17.C.3 and Engineer has given written approval of each such variation by specific written notation thereof incorporated in or accompanying the Shop Drawing or Sample. Engineer’s review and approval shall not relieve Contractor from responsibility for complying with the requirements of Paragraph 6.17.C.1.

E. Resubmittal Procedures

1. Contractor shall make corrections required by Engineer and shall return the required number of cor- rected copies of Shop Drawings and submit, as required, new Samples for review and approval. Contractor shall direct specific attention in writing to revisions other than the corrections called for by Engineer on previous submittals.

6.18 Continuing the Work

A. Contractor shall carry on the Work and adhere to the Progress Schedule during all disputes or disagreements with Owner. No Work shall be delayed or postponed pending resolution of any disputes or disagreements, except as permitted by Paragraph 15.04 or as Owner and Contractor may otherwise agree in writing.

6.19 Contractor’s General Warranty and Guarantee

A. Contractor warrants and guarantees to Owner that all Work will be in accordance with the Contract Documents and will not be defective. Engineer and its Related Entities shall be entitled to rely on representation of Contractor’s warranty and guarantee.

B. Contractor’s warranty and guarantee hereunder excludes defects or damage caused by:

1. abuse, modification, or improper maintenance or operation by persons other than Contractor, Sub- contractors, Suppliers, or any other individual or entity for whom Contractor is responsible; or

2. normal wear and tear under normal usage.

C. Contractor’s obligation to perform and complete the Work in accordance with the Contract Documents shall be absolute. None of the following will constitute an acceptance of Work that is not in accordance with the Contract Documents or a release of Contractor’s obligation to perform the Work in accordance with the Contract Documents:

1. observations by Engineer;

2. recommendation by Engineer or payment by Owner of any progress or final payment;

3. the issuance of a certificate of Substantial Completion by Engineer or any payment related thereto by Owner;

4. use or occupancy of the Work or any part thereof by Owner;

5. any review and approval of a Shop Drawing or Sample submittal or the issuance of a notice of acceptabil- ity by Engineer;

Page 80: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 26

6. any inspection, test, or approval by others; or

7. any correction of defective Work by Owner.

6.20 Indemnification

A. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold harmless Owner and Engineer, and the officers, directors, partners, employees, agents, consultants and subcontractors of each and any of them from and against all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to the performance of the Work, provided that any such claim, cost, loss, or damage is attributable to bodily injury, sickness, disease, or death, or to injury to or destruction of tangible property (other than the Work itself), including the loss of use resulting therefrom but only to the extent caused by any negligent act or omission of Contractor, any Subcontractor, any Supplier, or any individual or entity directly or indirectly employed by any of them to perform any of the Work or anyone for whose acts any of them may be liable .

B. In any and all claims against Owner or Engineer or any of their respective consultants, agents, officers, directors, partners, or employees by any employ- ee (or the survivor or personal representative of such employee) of Contractor, any Subcontractor, any Supplier, or any individual or entity directly or indirectly employed by any of them to perform any of the Work, or anyone for whose acts any of them may be liable, the indemnification obligation under Paragraph 6.20.A shall not be limited in any way by any limitation on the amount or type of damages, compensation, or benefits payable by or for Contractor or any such Subcontractor, Supplier, or other individual or entity under workers’ compensation acts, disability benefit acts, or other employee benefit acts.

C. The indemnification obligations of Contractor under Paragraph 6.20.A shall not extend to the liability of Engineer and Engineer’s officers, directors, partners,

portion of the Work or unless such services are required to carry out Contractor’s responsibilities for construction means, methods, techniques, sequences and procedures. Contractor shall not be required to provide professional services in violation of applicable law.

B. If professional design services or certifications by a design professional related to systems, materials or equipment are specifically required of Contractor by the Contract Documents, Owner and Engineer will specify all performance and design criteria that such services must satisfy. Contractor shall cause such services or certifications to be provided by a properly licensed professional, whose signature and seal shall appear on all drawings, calculations, specifications, certifications, Shop Drawings and other submittals prepared by such professional. Shop Drawings and other submittals related to the Work designed or certified by such professional, if prepared by others, shall bear such professional’s written approval when submitted to Engineer.

C. Owner and Engineer shall be entitled to rely upon the adequacy, accuracy and completeness of the services, certifications or approvals performed by such design professionals, provided Owner and Engineer have specified to Contractor all performance and design criteria that such services must satisfy.

D. Pursuant to this Paragraph 6.21, Engineer’s review and approval of design calculations and design drawings will be only for the limited purpose of checking for conformance with performance and design criteria given and the design concept expressed in the Contract Documents. Engineer’s review and approval of Shop Drawings and other submittals (except design calculations and design drawings) will be only for the purpose stated in Paragraph 6.17.D.1.

E. Contractor shall not be responsible for the adequacy of the performance or design criteria required by the Contract Documents.

ARTICLE 7 - OTHER WORK AT THE SITEemployees, agents, consultants and subcontractors arising out of:

1. the preparation or approval of, or the failure to prepare or approve, maps, Drawings, opinions, reports, surveys, Change Orders, designs, or Specifications; or

2. giving directions or instructions, or failing to give them, if that is the primary cause of the injury or damage.

6.21 Delegation of Professional Design Services

A. Contractor will not be required to provide professional design services unless such services are

specifically required by the Contract Documents for a

Page 81: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 27

7.01 Related Work at Site

A. Owner may perform other work related to the Project at the Site with Owner’s employees, or via other direct contracts therefor, or have other work performed by utility owners. If such other work is not noted in the Con- tract Documents, then:

1. written notice thereof will be given to Contractor prior to starting any such other work; and

2. if Owner and Contractor are unable to agree on entitlement to or on the amount or extent, if any, of any adjustment in the Contract Price or Contract Times

Page 82: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 28

that should be allowed as a result of such other work, a Claim may be made therefor as provided in Paragraph 10.05.

B. Contractor shall afford each other contractor who is a party to such a direct contract, each utility owner and Owner, if Owner is performing other work with Owner’s employees, proper and safe access to the Site, a reasonable opportunity for the introduction and storage of materials and equipment and the execution of such other work, and shall properly coordinate the Work with theirs. Contractor shall do all cutting, fitting, and patching of the Work that may be required to properly connect or otherwise make its several parts come together and properly integrate with such other work. Contractor shall not endanger any work of others by cutting, excavating,

A. Paragraphs 7.01.A and 7.02 are not applicable for utilities not under the control of Owner.

B. Each other direct contract of Owner under Paragraph 7.01.A shall provide that the other contractor is liable to Owner and Contractor for the reasonable direct delay and disruption costs incurred by Contractor as a result of the other contractor’s actions or inactions.

C. Contractor shall be liable to Owner and any other contractor for the reasonable direct delay and disruption costs incurred by such other contractor as a result of Contractor’s action or inactions.

ARTICLE 8 - OWNER’S RESPONSIBILITIESor otherwise altering their work and will only cut or alter their work with the written consent of Engineer and theothers whose work will be affected. The duties and responsibilities of Contractor under this Paragraph are for the benefit of such utility owners and other contractors to the extent that there are comparable provisions for the benefit of Contractor in said direct contracts between Owner and such utility owners and other contractors.

C. If the proper execution or results of any part of Contractor’s Work depends upon work performed by others under this Article 7, Contractor shall inspect such other work and promptly report to Engineer in writing any delays, defects, or deficiencies in such other work that render it unavailable or unsuitable for the proper execution and results of Contractor’s Work. Contractor’s failure to so report will constitute an acceptance of such other work as fit and proper for integration with Contractor’s Work except for latent defects and deficiencies in such other work.

7.02 Coordination

A. If Owner intends to contract with others for the performance of other work on the Project at the Site, the following will be set forth in Supplementary Condi- tions:

8.01 Communications to Contractor

A. Except as otherwise provided in these General Conditions, Owner shall issue all communications to Contractor through Engineer.

8.02 Replacement of Engineer

A. In case of termination of the employment of Engineer, Owner shall appoint an engineer to whom Contractor makes no reasonable objection, whose status under the Contract Documents shall be that of the former Engineer.

8.03 Furnish Data

A. Owner shall promptly furnish the data required of Owner under the Contract Documents.

8.04 Pay When Due

A. Owner shall make payments to Contractor when they are due as provided in Paragraphs 14.02.C and 14.07.C.

8.05 Lands and Easements; Reports and Tests1. the individual or entity who will have

authority and responsibility for coordination of the activities among the various contractors will be identified;

2. the specific matters to be covered by such authority and responsibility will be itemized; and

3. the extent of such authority and responsibili- ties will be provided.

B. Unless otherwise provided in the Supplementary Conditions, Owner shall have sole authority and responsibility for such coordination.

7.03 Legal Relationships

A. Owner’s duties in respect of providing lands and easements and providing engineering surveys to establish reference points are set forth in Paragraphs 4.01 and 4.05. Paragraph 4.02 refers to Owner’s identifying and making available to Contractor copies of reports of explorations and tests of subsurface conditions and drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the Site that have been utilized by Engineer in preparing the Contract Documents.

8.06 Insurance

A. Owner’s responsibilities, if any, in respect to purchasing and maintaining liability and property insur-

Page 83: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 29

ance are set forth in Article 5.

Page 84: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 30

8.07 Change Orders

A. Owner is obligated to execute Change Orders as indicated in Paragraph 10.03.

8.08 Inspections, Tests, and Approvals

A. Owner’s responsibility in respect to certain inspections, tests, and approvals is set forth in Paragraph 13.03.B.

8.09 Limitations on Owner’s Responsibilities

A. The Owner shall not supervise, direct, or have control or authority over, nor be responsible for, Contractor’s means, methods, techniques, sequences, or procedures of construction, or the safety precautions and programs incident thereto, or for any failure of Contractor to comply with Laws and Regulations applicable to the performance of the Work. Owner will not be responsible for Contractor’s failure to perform the Work in accordance with the Contract Documents.

8.10 Undisclosed Hazardous Environmental Condition

A. Owner’s responsibility in respect to an undis- closed Hazardous Environmental Condition is set forth in Paragraph 4.06.

8.11 Evidence of Financial Arrangements

A. If and to the extent Owner has agreed to furnish Contractor reasonable evidence that financial arrangements have been made to satisfy Owner’s obligations under the Contract Documents, Owner’s responsibility in respect thereof will be as set forth in the Supplementary Conditions.

ARTICLE 9 - ENGINEER’S STATUS DURING CONSTRUCTION

9.01 Owner’s Representative

A. Engineer will be Owner’s representative during the construction period. The duties and responsi- bilities and the limitations of authority of Engineer as Owner’s representative during construction are set forth in the Contract Documents and will not be changed without written consent of Owner and Engineer.

9.02 Visits to Site

A. Engineer will make visits to the Site at inter- vals appropriate to the various stages of construction as Engineer deems necessary in order to observe as an experienced and qualified design professional the progress that has been made and the quality of the various

aspects of Contractor’s executed Work. Based on information obtained during such visits and observations, Engineer, for the benefit of Owner, will determine, in general, if the Work is proceeding in accordance with the Contract Documents. Engineer will not be required to make exhaustive or continuous inspections on the Site to check the quality or quantity of the Work. Engineer’s efforts will be directed toward providing for Owner a greater degree of confidence that the completed Work will conform generally to the Contract Documents. On the basis of such visits and observations, Engineer will keep Owner informed of the progress of the Work and will endeavor to guard Owner against defective Work.

B. Engineer’s visits and observations are subject to all the limitations on Engineer’s authority and responsibility set forth in Paragraph 9.09. Particularly, but without limitation, during or as a result of Engineer's visits or observations of Contractor's Work Engineer will not supervise, direct, control, or have authority over or be responsible for Contractor’s means, methods, techniques, sequences, or procedures of construction, or the safety precautions and programs incident thereto, or for any failure of Contractor to comply with Laws and Regulations applicable to the performance of the Work.

9.03 Project Representative

A. If Owner and Engineer agree, Engineer will furnish a Resident Project Representative to assist Engineer in providing more extensive observation of the Work. The authority and responsibilities of any such Resident Project Representative and assistants will be as provided in the Supplementary Conditions, and limitations on the responsibilities thereof will be as provided in Paragraph 9.09. If Owner designates another representative or agent to represent Owner at the Site who is not Engineer’s consultant, agent or employee, the responsibilities and authority and limitations thereon of such other individual or entity will be as provided in the Supplementary Conditions.

9.04 Authorized Variations in Work

A. Engineer may authorize minor variations in the Work from the requirements of the Contract Documents which do not involve an adjustment in the Contract Price or the Contract Times and are compatible with the design concept of the completed Project as a functioning whole as indicated by the Contract Docu- ments. These may be accomplished by a Field Order and will be binding on Owner and also on Contractor, who shall perform the Work involved promptly. If Owner or Contractor believes that a Field Order justifies an adjustment in the Contract Price or Contract Times, or both, and the parties are unable to agree on entitlement to or on the amount or extent, if any, of any such adjustment, a Claim may be made therefor as provided in Paragraph 10.05.

Page 85: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 31

9.05 Rejecting Defective Work

A. Engineer will have authority to reject Work which Engineer believes to be defective, or that Engineer believes will not produce a completed Project that conforms to the Contract Documents or that will prejudice the integrity of the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. Engineer will also have authority to require special inspection or testing of the Work as provided in Paragraph 13.04, whether or not the Work is fabricated, installed, or completed.

9.06 Shop Drawings, Change Orders and Payments

A. In connection with Engineer’s authority, and limitations thereof, as to Shop Drawings and Samples, see Paragraph 6.17.

B. In connection with Engineer’s authority, and limitations thereof, as to design calculations and design drawings submitted in response to a delegation of professional design services, if any, see Paragraph 6.21.

C. In connection with Engineer’s authority as to Change Orders, see Articles 10, 11, and 12.

D. In connection with Engineer’s authority as to Applications for Payment, see Article 14.

9.07 Determinations for Unit Price Work

A. Engineer will determine the actual quantities and classifications of Unit Price Work performed by Contractor. Engineer will review with Contractor the Engineer’s preliminary determinations on such matters before rendering a written decision thereon (by recommendation of an Application for Payment or otherwise). Engineer’s written decision thereon will be final and binding (except as modified by Engineer to reflect changed factual conditions or more accurate data) upon Owner and Contractor, subject to the provisions of Paragraph 10.05.

9.08 Decisions on Requirements of Contract Documents and Acceptability of Work

A. Engineer will be the initial interpreter of the requirements of the Contract Documents and judge of the acceptability of the Work thereunder. All matters in question and other matters between Owner and Contractor arising prior to the date final payment is due relating to the acceptability of the Work, and the interpretation of the requirements of the Contract Documents pertaining to the performance of the Work, will be referred initially to Engineer in writing within 30 days of the event giving rise to the question

B. Engineer will, with reasonable promptness, render a written decision on the issue referred. If Owner or Contractor believe that any such decision entitles them

to an adjustment in the Contract Price or Contract Times or both, a Claim may be made under Paragraph 10.05. The date of Engineer’s decision shall be the date of the event giving rise to the issues referenced for the purposes of Paragraph 10.05.B.

C. Engineer’s written decision on the issue referred will be final and binding on Owner and Contractor, subject to the provisions of Paragraph 10.05.

D. When functioning as interpreter and judge under this Paragraph 9.08, Engineer will not show partiality to Owner or Contractor and will not be liable in connection with any interpretation or decision rendered in good faith in such capacity.

9.09 Limitations on Engineer’s Authority and Responsibilities

A. Neither Engineer’s authority or responsibility under this Article 9 or under any other provision of the Contract Documents nor any decision made by Engineer in good faith either to exercise or not exercise such authority or responsibility or the undertaking, exercise, or performance of any authority or responsibility by Engineer shall create, impose, or give rise to any duty in contract, tort, or otherwise owed by Engineer to Contractor, any Subcontractor, any Supplier, any other individual or entity, or to any surety for or employee or agent of any of them.

B. Engineer will not supervise, direct, control, or have authority over or be responsible for Contractor’s means, methods, techniques, sequences, or procedures of construction, or the safety precautions and programs incident thereto, or for any failure of Contractor to comply with Laws and Regulations applicable to the performance of the Work. Engineer will not be respon- sible for Contractor’s failure to perform the Work in accordance with the Contract Documents.

C. Engineer will not be responsible for the acts or omissions of Contractor or of any Subcontractor, any Supplier, or of any other individual or entity performing any of the Work.

D. Engineer’s review of the final Application for Payment and accompanying documentation and all maintenance and operating instructions, schedules, guarantees, bonds, certificates of inspection, tests and approvals, and other documentation required to be delivered by Paragraph 14.07.A will only be to determine generally that their content complies with the require- ments of, and in the case of certificates of inspections, tests, and approvals that the results certified indicate compliance with the Contract Documents.

E. The limitations upon authority and responsi- bility set forth in this Paragraph 9.09 shall also apply to, the Resident Project Representative, if any, and assistants,

Page 86: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 32

if any.

Page 87: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 33

ARTICLE 10 - CHANGES IN THE WORK; CLAIMS

10.01 Authorized Changes in the Work

A. Without invalidating the Contract and without notice to any surety, Owner may, at any time or from time to time, order additions, deletions, or revisions in the Work by a Change Order, or a Work Change Directive. Upon receipt of any such document, Contractor shall promptly proceed with the Work involved which will be performed under the applicable conditions of the Contract Documents (except as otherwise specifically provided).

B. If Owner and Contractor are unable to agree on entitlement to, or on the amount or extent, if any, of an adjustment in the Contract Price or Contract Times, or both, that should be allowed as a result of a Work Change Directive, a Claim may be made therefor as provided in Paragraph 10.05.

10.02 Unauthorized Changes in the Work

A.Contractor shall not be entitled to an increase in the Contract Price or an extension of the Contract Times with respect to any work performed that is not required by the Contract Documents as amended, modified, or supplemented as provided in Paragraph 3.04, except in the case of an emergency as provided in Paragraph 6.16 or in the case of uncovering Work as provided in Paragraph 13.04.B.

10.03 Execution of Change Orders

A. Owner and Contractor shall execute appropri- ate Change Orders recommended by Engineer covering:

A.changes in the Work which are: (i) ordered by Owner pursuant to Paragraph 10.01.A, (ii) required because of acceptance of defective Work under Paragraph13.08.A or Owner’s correction of defective Work under Paragraph 13.09, or (iii) agreed to by the parties;

B. changes in the Contract Price or Contract Times which are agreed to by the parties, including any undisputed sum or amount of time for Work actually performed in accordance with a Work Change Directive; and

C. changes in the Contract Price or Contract Times which embody the substance of any written decision rendered by Engineer pursuant to Paragraph 10.05; provided that, in lieu of executing any such Change Order, an appeal may be taken from any such decision in accordance with the provisions of the Contract Documents and applicable Laws and Regulations, but during any such appeal, Contractor shall carry on the Work and adhere to the Progress Schedule as provided in Paragraph 6.18.A.

10.04 Notification to Surety

A. If notice of any change affecting the general scope of the Work or the provisions of the Contract Documents (including, but not limited to, Contract Price or Contract Times) is required by the provisions of any bond to be given to a surety, the giving of any such notice will be Contractor’s responsibility. The amount of each applicable bond will be adjusted to reflect the effect of any such change.

10.05 Claims

A. Engineer’s Decision Required: All Claims, except those waived pursuant to Paragraph 14.09, shall be referred to the Engineer for decision. A decision by Engineer shall be required as a condition precedent to any exercise by Owner or Contractor of any rights or remedies either may otherwise have under the Contract Documents or by Laws and Regulations in respect of such Claims.

B. Notice: Written notice stating the general nature of each Claim, shall be delivered by the claimant to Engineer and the other party to the Contract promptly (but in no event later than 30 days) after the start of the event giving rise thereto. The responsibility to substantiate a Claim shall rest with the party making the Claim. Notice of the amount or extent of the Claim, with supporting data shall be delivered to the Engineer and the other party to the Contract within 60 days after the start of such event (unless Engineer allows additional time for claimant to submit additional or more accurate data in support of such Claim). A Claim for an adjustment in Contract Price shall be prepared in accordance with the provisions of Paragraph 12.01.B. A Claim for an adjustment in Contract Time shall be prepared in accordance with the provisions of Paragraph 12.02.B. Each Claim shall be accompanied by claimant's written statement that the adjustment claimed is the entire adjustment to which the claimant believes it is entitled as a result of said event. The opposing party shall submit any response to Engineer and the claimant within 30 days after receipt of the claimant’s last submittal (unless Engineer allows additional time).

C. Engineer’s Action: Engineer will review each Claim and, within 30 days after receipt of the last submittal of the claimant or the last submittal of the opposing party, if any, take one of the following actions in writing:

Page 88: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 34

1. deny the Claim in whole or in part,

2. approve the Claim, or

3. notify the parties that the Engineer is unable to resolve the Claim if, in the Engineer’s sole discretion, it would be inappropriate for the Engineer to do so. For purposes of further resolution of the Claim, such notice shall be deemed a denial.

D. In the event that Engineer does not take action on a Claim within said 30 days, the Claim shall be deemed denied.

E. Engineer’s written action under Paragraph10.05.C or denial pursuant to Paragraphs 10.05.C.3 or10.05.D will be final and binding upon Owner and Contractor, unless Owner or Contractor invoke the dispute resolution procedure set forth in Article 16 within 30 days of such action or denial.

F. No Claim for an adjustment in Contract Price or Contract Times will be valid if not submitted in accordance with this Paragraph 10.05.

ARTICLE 11 - COST OF THE WORK; ALLOWANCES; UNIT PRICE WORK

11.01 Cost of the Work

A. Costs Included: The term Cost of the Work means the sum of all costs, except those excluded in Paragraph 11.01.B, necessarily incurred and paid by Contractor in the proper performance of the Work. When the value of any Work covered by a Change Order or when a Claim for an adjustment in Contract Price is determined on the basis of Cost of the Work, the costs to be reimbursed to Contractor will be only those additional or incremental costs required because of the change in the Work or because of the event giving rise to the Claim. Except as otherwise may be agreed to in writing by Owner, such costs shall be in amounts no higher than those prevailing in the locality of the Project, shall include only the following items, and shall not include any of the costs itemized in Paragraph 11.01.B.

1. Payroll costs for employees in the direct employ of Contractor in the performance of the Work under schedules of job classifications agreed upon by Owner and Contractor. Such employees shall include, without limitation, superintendents, foremen, and other personnel employed full time at the Site. Payroll costs for employees not employed full time on the Work shall be apportioned on the basis of their time spent on the Work. Payroll costs shall include, but not be limited to, salaries and wages plus the cost of fringe benefits, which shall include social security contributions, unemployment, excise, and payroll taxes, workers’ compensation, health and retirement benefits, bonuses, sick leave, vacation and

holiday pay applicable thereto. The expenses of performing Work outside of regular working hours, on Saturday, Sunday, or legal holidays, shall be included in the above to the extent authorized by Owner.

2. Cost of all materials and equipment furnished and incorporated in the Work, including costs of transportation and storage thereof, and Suppliers’ field services required in connection therewith. All cash discounts shall accrue to Contractor unless Owner deposits funds with Contractor with which to make pay- ments, in which case the cash discounts shall accrue to Owner. All trade discounts, rebates and refunds and returns from sale of surplus materials and equipment shall accrue to Owner, and Contractor shall make provisions so that they may be obtained.

3. Payments made by Contractor to Subcontractors for Work performed by Subcontractors. If required by Owner, Contractor shall obtain competitive bids from subcontractors acceptable to Owner and Contractor and shall deliver such bids to Owner, who will then determine, with the advice of Engineer, which bids, if any, will be acceptable. If any subcontract provides that the Subcontractor is to be paid on the basis of Cost of the Work plus a fee, the Subcontractor’s Cost of the Work and fee shall be determined in the same manner as Contractor’s Cost of the Work and fee as provided in this Paragraph 11.01.

4. Costs of special consultants (including but not limited to Engineers, architects, testing laboratories, surveyors, attorneys, and accountants) employed for services specifically related to the Work.

5. Supplemental costs including the following:

a. The proportion of necessary transportation, travel, and subsistence expenses of Contractor’s employees incurred in discharge of duties connected with the Work.

b. Cost, including transportation and mainte- nance, of all materials, supplies, equipment, machinery, appliances, office, and temporary facilities at the Site, and hand tools not owned by the workers, which are consumed in the perfor- mance of the Work, and cost, less market value, of such items used but not consumed which remain the property of Contractor.

c. Rentals of all construction equipment and machinery, and the parts thereof whether rented from Contractor or others in accordance with rental agreements approved by Owner with the advice of Engineer, and the costs of transportation, loading, unloading, assembly, dismantling, and removal thereof. All such costs shall be in accordance with the terms of said rental agreements. The rental of any such equip-

Page 89: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 30

ment, machinery, or parts shall cease when the use thereof is no longer necessary for the Work.

d. Sales, consumer, use, and other similar taxes related to the Work, and for which Contractor is liable, imposed by Laws and Regulations.

e. Deposits lost for causes other than negligence of Contractor, any Subcontractor, or anyone directly or indirectly employed by any of them or for whose acts any of them may be liable, and royalty payments and fees for permits and licenses.

f. Losses and damages (and related expenses) caused by damage to the Work, not compensated by insurance or otherwise, sustained by Contractor in connection with the performance of the Work (except losses and damages within the deductible amounts of property insurance established in accordance with Paragraph 5.06.D), provided such losses and damages have resulted from causes other than the negligence of Contractor, any Subcontractor, or anyone directly or indirectly employed by any of them or for whose acts any of them may be liable. Such losses shall include settlements made with the written consent and approval of Owner. No such losses, damages, and expenses shall be included in the Cost of the Work for the purpose of determining Contractor’s fee.

g. The cost of utilities, fuel, and sanitary facilities at the Site.

h. Minor expenses such as telegrams, long distance telephone calls, telephone service at the Site, expresses, and similar petty cash items in connection with the Work.

i. The costs of premiums for all bonds and insurance Contractor is required by the Contract Documents to purchase and maintain.

B. Costs Excluded: The term Cost of the Work shall not include any of the following items:

1. Payroll costs and other compensation of Contractor’s officers, executives, principals (of partnerships and sole proprietorships), general managers, safety managers, engineers, architects, estimators, attor- neys, auditors, accountants, purchasing and contracting agents, expediters, timekeepers, clerks, and other personnel employed by Contractor, whether at the Site or in Contractor’s principal or branch office for general administration of the Work and not specifically included in the agreed upon schedule of job classifications referred to in Paragraph 11.01.A.1 or specifically covered by Paragraph 11.01.A.4, all of which are to be considered administrative costs covered by the Contractor’s fee.

2. Expenses of Contractor’s principal and branch offices other than Contractor’s office at the Site.

3. Any part of Contractor’s capital expenses, including interest on Contractor’s capital employed for the Work and charges against Contractor for delinquent payments.

4. Costs due to the negligence of Contractor, any Subcontractor, or anyone directly or indirectly employed by any of them or for whose acts any of them may be liable, including but not limited to, the correction of defective Work, disposal of materials or equipment wrongly supplied, and making good any damage to property.

5. Other overhead or general expense costs of any kind and the costs of any item not specifically and expressly included in Paragraphs 11.01.A and 11.01.B.

C. Contractor’s Fee: When all the Work is performed on the basis of cost-plus, Contractor’s fee shall be determined as set forth in the Agreement. When the value of any Work covered by a Change Order or when a Claim for an adjustment in Contract Price is determined on the basis of Cost of the Work, Contractor’s fee shall be determined as set forth in Paragraph 12.01.C.

D. Documentation: Whenever the Cost of the Work for any purpose is to be determined pursuant to Paragraphs 11.01.A and 11.01.B, Contractor will establish and maintain records thereof in accordance with generally accepted accounting practices and submit in a form acceptable to Engineer an itemized cost breakdown together with supporting data.

11.02 Allowances

A. It is understood that Contractor has included in the Contract Price all allowances so named in the Contract Documents and shall cause the Work so covered to be performed for such sums and by such persons or entities as may be acceptable to Owner and Engineer.

B. Cash Allowances

1. Contractor agrees that:

a. the cash allowances include the cost to Contractor (less any applicable trade discounts) of materials and equipment required by the allowances to be delivered at the Site, and all applicable taxes; and

b. Contractor’s costs for unloading and handling on the Site, labor, installation , overhead, profit, and other expenses contemplated for the cash allowances have been included in the Contract Price and not in the allowances, and no demand for additional payment on account of any of the

Page 90: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 31

foregoing will be valid.

Page 91: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 32

C. Contingency Allowance

1. Contractor agrees that a contingency allowance, if any, is for the sole use of Owner to cover unanticipated costs.

D. Prior to final payment, an appropriate Change Order will be issued as recommended by Engineer to reflect actual amounts due Contractor on account of Work covered by allowances, and the Contract Price shall be correspondingly adjusted.

11.03 Unit Price Work

A. Where the Contract Documents provide that all or part of the Work is to be Unit Price Work, initially the Contract Price will be deemed to include for all Unit Price Work an amount equal to the sum of the unit price for each separately identified item of Unit Price Work times the estimated quantity of each item as indicated in the Agreement.

B. The estimated quantities of items of Unit Price Work are not guaranteed and are solely for the purpose of comparison of Bids and determining an initial Contract Price. Determinations of the actual quantities and classifications of Unit Price Work performed by Contractor will be made by Engineer subject to the provisions of Paragraph 9.07.

C. Each unit price will be deemed to include an amount considered by Contractor to be adequate to cover Contractor’s overhead and profit for each separately identified item.

D. Owner or Contractor may make a Claim for an adjustment in the Contract Price in accordance with Paragraph 10.05 if:

1. the quantity of any item of Unit Price Work performed by Contractor differs materially and signifi- cantly from the estimated quantity of such item indicated in the Agreement; and

2. there is no corresponding adjustment with respect any other item of Work; and

3. Contractor believes that Contractor is entitled to an increase in Contract Price as a result of having incurred additional expense or Owner believes that Owner is entitled to a decrease in Contract Price and the parties are unable to agree as to the amount of any such increase or decrease.

ARTICLE 12 - CHANGE OF CONTRACT PRICE; CHANGE OF CONTRACT TIMES

12.01 Change of Contract Price

A. The Contract Price may only be changed by a Change Order. Any Claim for an adjustment in the Contract Price shall be based on written notice submitted by the party making the Claim to the Engineer and the other party to the Contract in accordance with the provisions of Paragraph 10.05.

B. The value of any Work covered by a Change Order or of any Claim for an adjustment in the Contract Price will be determined as follows:

1. where the Work involved is covered by unit prices contained in the Contract Documents, by applica- tion of such unit prices to the quantities of the items involved (subject to the provisions of Paragraph 11.03); or

2. where the Work involved is not covered by unit prices contained in the Contract Documents, by a mutually agreed lump sum (which may include an allowance for overhead and profit not necessarily in accordance with Paragraph 12.01.C.2); or

3. where the Work involved is not covered by unit prices contained in the Contract Documents and agreement to a lump sum is not reached under Paragraph 12.01.B.2, on the basis of the Cost of the Work (determined as provided in Paragraph 11.01) plus a Contractor’s fee for overhead and profit (determined as provided in Paragraph 12.01.C).

C. Contractor’s Fee: The Contractor’s fee for overhead and profit shall be determined as follows:

1. a mutually acceptable fixed fee; or

2. if a fixed fee is not agreed upon, then a fee based on the following percentages of the various portions of the Cost of the Work:

a. for costs incurred under Paragraphs 11.01.A.1 and 11.01.A.2, the Contractor’s fee shall be 15 percent;

b. for costs incurred under Paragraph 11.01.A.3, the Contractor’s fee shall be five percent;

c. where one or more tiers of subcontracts are on the basis of Cost of the Work plus a fee and no fixed fee is agreed upon, the intent of Paragraph 12.01.C.2.a is that the Subcontractor who actually performs the Work, at whatever tier, will be paid a fee of 15 percent of the costs incurred by such Subcontractor under Paragraphs11.01.A.1 and 11.01.A.2 and that any higher tier

Page 92: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 33

Subcontractor and Contractor will each be paid a fee of five percent of the amount paid to the next lower tier Subcontractor;

d. no fee shall be payable on the basis of costs itemized under Paragraphs 11.01.A.4, 11.01.A.5, and 11.01.B;

e. the amount of credit to be allowed by Contractor to Owner for any change which results in a net decrease in cost will be the amount of the actual net decrease in cost plus a deduction in Contractor’s fee by an amount equal to five percent of such net decrease; and

f. when both additions and credits are involved in any one change, the adjustment in Contractor’s fee shall be computed on the basis of the net change in accordance with Paragraphs 12.01.C.2.a through 12.01.C.2.e, inclusive.

12.02 Change of Contract Times

A. The Contract Times may only be changed by a Change Order. Any Claim for an adjustment in the Contract Times shall be based on written notice submitted by the party making the Claim to the Engineer and the other party to the Contract in accordance with the provisions of Paragraph 10.05.

B. Any adjustment of the Contract Times

C If Contractor is delayed in the performance or progress of the Work by fire, flood, epidemic, abnormal weather conditions, acts of God, acts or failures to act of utility owners not under the control of Owner, or other causes not the fault of and beyond control of Owner and Contractor, then Contractor shall be entitled to an equitable adjustment in Contract Times, if such adjustment is essential to Contractor’s ability to complete the Work within the Contract Times. Such an adjustment shall be Contractor’s sole and exclusive remedy for the delays described in this Paragraph 12.03.C.

D. Owner, Engineer and the Related Entities of each of them shall not be liable to Contractor for any claims, costs, losses, or damages (including but not limited to all fees and charges of Engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) sustained by Contractor on or in connection with any other project or anticipated project.

E. Contractor shall not be entitled to an adjustment in Contract Price or Contract Times for delays within the control of Contractor. Delays attributable to and within the control of a Subcontractor or Supplier shall be deemed to be delays within the control of Contractor.

ARTICLE 13 - TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF DEFECTIVE WORK

covered by a Change Order or any Claim for an adjustment in the Contract Times will be determined inaccordance with the provisions of this Article 12.

12.03 Delays

A. Where Contractor is prevented from completing any part of the Work within the Contract Times due to delay beyond the control of Contractor, the Contract Times will be extended in an amount equal to the time lost due to such delay if a Claim is made therefor as provided in Paragraph 12.02.A. Delays beyond the control of Contractor shall include, but not be limited to, acts or neglect by Owner, acts or neglect of utility owners or other contractors performing other work as contemplat- ed by Article 7, fires, floods, epidemics, abnormal weather conditions, or acts of God.

B. If Owner, Engineer, or other contractors or utility owners performing other work for Owner as contemplated by Article 7, or anyone for whom Owner is responsible, delays, disrupts, or interferes with the performance or progress of the Work, then Contractor shall be entitled to an equitable adjustment in the Contract Price or the Contract Times , or both. Contractor’s entitlement to an adjustment of the Contract Times is conditioned on such adjustment being essential to Contractor’s ability to complete the Work within the Contract Times.

13.01 Notice of Defects

A. Prompt notice of all defective Work of which Owner or Engineer has actual knowledge will be given to Contractor. All defective Work may be rejected, corrected, or accepted as provided in this Article 13.

13.02 Access to Work

A. Owner, Engineer, their consultants and other representatives and personnel of Owner, independent testing laboratories, and governmental agencies with jurisdictional interests will have access to the Site and the Work at reasonable times for their observation, inspecting, and testing. Contractor shall provide them proper and safe conditions for such access and advise them of Contractor’s Site safety procedures and programs so that they may comply therewith as applicable.

13.03 Tests and Inspections

A. Contractor shall give Engineer timely notice of readiness of the Work for all required inspections, tests, or approvals and shall cooperate with inspection and testing personnel to facilitate required inspections or tests.

B. Owner shall employ and pay for the services

Page 93: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 34

of an independent testing laboratory to perform all

Page 94: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 35

inspections, tests, or approvals required by the Contract Documents except:

1. for inspections, tests, or approvals covered by Paragraphs 13.03.C and 13.03.D below;

2. that costs incurred in connection with tests or inspections conducted pursuant to Paragraph 13.04.B shall be paid as provided in said Paragraph 13.04.C; and

3. as otherwise specifically provided in the Con- tract Documents.

C. If Laws or Regulations of any public body having jurisdiction require any Work (or part thereof) specifically to be inspected, tested, or approved by an employee or other representative of such public body, Contractor shall assume full responsibility for arranging and obtaining such inspections, tests, or approvals, pay all costs in connection therewith, and furnish Engineer the required certificates of inspection or approval.

D. Contractor shall be responsible for arranging and obtaining and shall pay all costs in connection with any inspections, tests, or approvals required for Owner’s and Engineer’s acceptance of materials or equipment to be incorporated in the Work; or acceptance of materials, mix designs, or equipment submitted for approval prior to Contractor’s purchase thereof for incorporation in the Work. Such inspections, tests, or approvals shall be performed by organizations acceptable to Owner and Engineer.

E. If any Work (or the work of others) that is to be inspected, tested, or approved is covered by Contractor without written concurrence of Engineer, it must, if requested by Engineer, be uncovered for observation.

F. Uncovering Work as provided in Paragraph13.03.E shall be at Contractor’s expense unless Contractor has given Engineer timely notice of Contractor’s intention to cover the same and Engineer has not acted with reasonable promptness in response to such notice.

13.04 Uncovering Work

A. If any Work is covered contrary to the written request of Engineer, it must, if requested by Engineer, be uncovered for Engineer’s observation and replaced at Contractor’s expense.

B. If Engineer considers it necessary or advisable that covered Work be observed by Engineer or inspected or tested by others, Contractor, at Engineer’s request, shall uncover, expose, or otherwise make available for observation, inspection, or testing as Engineer may require, that portion of the Work in question, furnishing all necessary labor, material, and equipment.

C. If it is found that the uncovered Work is defective, Contractor shall pay all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to such uncovering, exposure, observation, inspection, and testing, and of satisfactory replacement or reconstruction (including but not limited to all costs of repair or replacement of work of others); and Owner shall be entitled to an appropriate decrease in the Contract Price. If the parties are unable to agree as to the amount thereof, Owner may make a Claim therefor as provided in Paragraph 10.05.

D. If, the uncovered Work is not found to be defective, Contractor shall be allowed an increase in the Contract Price or an extension of the Contract Times, or both, directly attributable to such uncovering, exposure, observation, inspection, testing, replacement, and reconstruction. If the parties are unable to agree as to the amount or extent thereof, Contractor may make a Claim therefor as provided in Paragraph 10.05.

13.05 Owner May Stop the Work

A. If the Work is defective, or Contractor fails to supply sufficient skilled workers or suitable materials or equipment, or fails to perform the Work in such a way that the completed Work will conform to the Contract Documents, Owner may order Contractor to stop the Work, or any portion thereof, until the cause for such order has been eliminated; however, this right of Owner to stop the Work shall not give rise to any duty on the part of Owner to exercise this right for the benefit of Contractor, any Subcontractor, any Supplier, any other individual or entity, or any surety for, or employee or agent of any of them.

13.06 Correction or Removal of Defective Work

A. Promptly after receipt of notice, Contractor shall correct all defective Work, whether or not fabricated, installed, or completed, or, if the Work has been rejected by Engineer, remove it from the Project and replace it with Work that is not defective. Contractor shall pay all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to such correction or removal (including but not limited to all costs of repair or replacement of work of others).

B. When correcting defective Work under the terms of this Paragraph 13.06 or Paragraph 13.07, Contractor shall take no action that would void or otherwise impair Owner’s special warranty and guarantee, if any, on said Work.

Page 95: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 36

13.07 Correction Period

A. If within one year after the date of Substantial Completion (or such longer period of time as may be prescribed by the terms of any applicable special guarantee required by the Contract Documents) or by any specific provision of the Contract Documents, any Work is found to be defective, or if the repair of any damages to the land or areas made available for Contractor’s use by Owner or permitted by Laws and Regulations as contemplated in Paragraph 6.11.A is found to be defective, Contractor shall promptly, without cost to Owner and in accordance with Owner’s written instructions:

1. repair such defective land or areas; or

2. correct such defective Work; or

3. if the defective Work has been rejected by Owner, remove it from the Project and replace it with Work that is not defective, and

4. satisfactorily correct or repair or remove and replace any damage to other Work, to the work of others or other land or areas resulting therefrom.

B. If Contractor does not promptly comply with the terms of Owner’s written instructions, or in an emergency where delay would cause serious risk of loss or damage, Owner may have the defective Work corrected or repaired or may have the rejected Work re- moved and replaced. All claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to such correction or repair or such removal and replacement (including but not limited to all costs of repair or replacement of work of others) will be paid by Contractor.

C. In special circumstances where a particular item of equipment is placed in continuous service before Substantial Completion of all the Work, the correction period for that item may start to run from an earlier date if so provided in the Specifications .

D. Where defective Work (and damage to other Work resulting therefrom) has been corrected or removed and replaced under this Paragraph 13.07, the correction period hereunder with respect to such Work will be extended for an additional period of one year after such correction or removal and replacement has been satisfactorily completed.

E. Contractor’s obligations under this Paragraph13.07 are in addition to any other obligation or warranty. The provisions of this Paragraph 13.07 shall not be construed as a substitute for or a waiver of the provisions of any applicable statute of limitation or repose.

13.08 Acceptance of Defective Work

A. If, instead of requiring correction or removal and replacement of defective Work, Owner (and, prior to Engineer’s recommendation of final payment, Engineer) prefers to accept it, Owner may do so. Contractor shall pay all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) attributable to Owner’s evaluation of and determination to accept such defective Work (such costs to be approved by Engineer as to reasonableness) and the diminished value of the Work to the extent not otherwise paid by Contractor pursuant to this sentence. If any such acceptance occurs prior to Engineer’s recommendation of final payment, a Change Order will be issued incorporating the necessary revisions in the Contract Documents with respect to the Work, and Owner shall be entitled to an appropriate decrease in the Contract Price, reflecting the diminished value of Work so accepted. If the parties are unable to agree as to the amount thereof, Owner may make a Claim therefor as provided in Paragraph 10.05. If the acceptance occurs after such recommendation, an appropriate amount will be paid by Contractor to Owner.

13.09 Owner May Correct Defective Work

A. If Contractor fails within a reasonable time after written notice from Engineer to correct defective Work or to remove and replace rejected Work as required by Engineer in accordance with Paragraph 13.06.A, or if Contractor fails to perform the Work in accordance with the Contract Documents, or if Contractor fails to comply with any other provision of the Contract Documents, Owner may, after seven days written notice to Contractor, correct or remedy any such deficiency.

B. In exercising the rights and remedies under this Paragraph 13.09, Owner shall proceed expeditiously. In connection with such corrective or remedial action, Owner may exclude Contractor from all or part of the Site, take possession of all or part of the Work and suspend Contractor’s services related thereto, take posses- sion of Contractor’s tools, appliances, construction equipment and machinery at the Site, and incorporate in the Work all materials and equipment stored at the Site or for which Owner has paid Contractor but which are stored elsewhere. Contractor shall allow Owner, Owner’s representatives, agents and employees, Owner’s other contractors, and Engineer and Engineer’s consultants access to the Site to enable Owner to exercise the rights and remedies under this Paragraph.

C. All claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) incurred or sustained by Owner in exercising the rights and remedies under this Paragraph 13.09 will be

Page 96: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 37

charged against Contractor, and a Change Order will be

Page 97: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 38

issued incorporating the necessary revisions in the Contract Documents with respect to the Work; and Owner shall be entitled to an appropriate decrease in the Contract Price. If the parties are unable to agree as to the amount of the adjustment, Owner may make a Claim therefor as provided in Paragraph 10.05. Such claims, costs, losses and damages will include but not be limited to all costs of repair, or replacement of work of others destroyed or damaged by correction, removal, or replacement of Contractor’s defective Work.

D. Contractor shall not be allowed an extension of the Contract Times because of any delay in the performance of the Work attributable to the exercise by Owner of Owner’s rights and remedies under this Paragraph 13.09.

ARTICLE 14 - PAYMENTS TO CONTRACTOR AND COMPLETION

14.01 Schedule of Values

A. The Schedule of Values established as provid- ed in Paragraph 2.07.A will serve as the basis for progress payments and will be incorporated into a form of Applica- tion for Payment acceptable to Engineer. Progress payments on account of Unit Price Work will be based on the number of units completed.

14.02 Progress Payments

A. Applications for Payments

1. At least 20 days before the date established in the Agreement for each progress payment (but not more often than once a month), Contractor shall submit to Engineer for review an Application for Payment filled out and signed by Contractor covering the Work completed as of the date of the Application and accompanied by such supporting documentation as is required by the Contract Documents. If payment is requested on the basis of materials and equipment not incorporated in the Work but delivered and suitably stored at the Site or at another location agreed to in writing, the Application for Payment shall also be accompanied by a bill of sale, invoice, or other documentation warranting that Owner has received the materials and equipment free and clear of all Liens and evidence that the materials and equipment are covered by appropriate property insurance or other arrangements to protect Owner’s interest therein, all of which must be satisfactory to Owner.

2. Beginning with the second Application for Payment, each Application shall include an affidavit of Contractor stating that all previous progress payments received on account of the Work have been applied on account to discharge Contractor’s legitimate obligations associated with prior Applications for Payment.

3. The amount of retainage with respect to progress payments will be as stipulated in the Agreement.

B. Review of Applications

1. Engineer will, within 10 days after receipt of each Application for Payment, either indicate in writing a recommendation of payment and present the Application to Owner or return the Application to Contractor indicating in writing Engineer’s reasons for refusing to recommend payment. In the latter case, Contractor may make the necessary corrections and resubmit the Application.

2. Engineer’s recommendation of any payment requested in an Application for Payment will constitute a representation by Engineer to Owner, based on Engineer’s observations on the Site of the executed Work as an experienced and qualified design professional and on Engineer's review of the Application for Payment and the accompanying data and schedules, that to the best of Engineer’s knowledge, information and belief:

a. the Work has progressed to the point indicat- ed;

b. the quality of the Work is generally in accor- dance with the Contract Documents (subject to an evaluation of the Work as a functioning whole prior to or upon Substantial Completion, to the results of any subsequent tests called for in the Contract Documents, to a final determination of quantities and classifications for Unit Price Work under Paragraph 9.07, and to any other qualifications stated in the recommendation); and

c. the conditions precedent to Contractor’s being entitled to such payment appear to have been fulfilled in so far as it is Engineer’s responsibility to observe the Work.

3. By recommending any such payment Engineer will not thereby be deemed to have represented that:

a. inspections made to check the quality or the quantity of the Work as it has been performed have been exhaustive, extended to every aspect of the Work in progress, or involved detailed inspections of the Work beyond the responsi- bilities specifically assigned to Engineer in the Contract Documents; or

b. that there may not be other matters or issues between the parties that might entitle Contractor to be paid additionally by Owner or entitle Owner to withhold payment to Contractor.

Page 98: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 39

4. Neither Engineer’s review of Contractor’s Work for the purposes of recommending payments nor Engineer’s recommendation of any payment, including final payment, will impose responsibility on Engineer:

a. to supervise, direct, or control the Work, or

b. for the means, methods, techniques, sequences, or procedures of construction, or the safety precautions and programs incident thereto, or

c. for Contractor’s failure to comply with Laws and Regulations applicable to Contractor’s performance of the Work, or

d. to make any examination to ascertain how or for what purposes Contractor has used the moneys paid on account of the Contract Price, or

e. to determine that title to any of the Work, materials, or equipment has passed to Owner free and clear of any Liens.

5. Engineer may refuse to recommend the whole or any part of any payment if, in Engineer’s opinion, it would be incorrect to make the representations to Owner stated in Paragraph 14.02.B.2. Engineer may also refuse to recommend any such payment or, because of subse- quently discovered evidence or the results of subsequent inspections or tests, revise or revoke any such payment recommendation previously made, to such extent as may be necessary in Engineer’s opinion to protect Owner from loss because:

a. the Work is defective, or completed Work has been damaged, requiring correction or replace- ment;

b. the Contract Price has been reduced by Change Orders;

c. Owner has been required to correct defective Work or complete Work in accordance with Paragraph 13.09; or

d. Engineer has actual knowledge of the occurrence of any of the events enumerated in Paragraph 15.02.A.

C. Payment Becomes Due

1. Ten days after presentation of the Application for Payment to Owner with Engineer’s recommendation, the amount recommended will (subject to the provisions of Paragraph 14.02.D) become due, and when due will be paid by Owner to Contractor.

D. Reduction in Payment

1. Owner may refuse to make payment of the full amount recommended by Engineer because:

a. claims have been made against Owner on account of Contractor’s performance or furnish- ing of the Work;

b. Liens have been filed in connection with the Work, except where Contractor has delivered a specific bond satisfactory to Owner to secure the satisfaction and discharge of such Liens;

c. there are other items entitling Owner to a set-off against the amount recommended; or

d. Owner has actual knowledge of the occurrence of any of the events enumerated in Paragraphs 14.02.B.5.a through 14.02.B.5.c or Paragraph 15.02.A.

2. If Owner refuses to make payment of the full amount recommended by Engineer, Owner will give Contractor immediate written notice (with a copy to Engineer) stating the reasons for such action and promptly pay Contractor any amount remaining after deduction of the amount so withheld. Owner shall promptly pay Contractor the amount so withheld, or any adjustment thereto agreed to by Owner and Contractor, when Contractor corrects to Owner’s satisfaction the reasons for such action.

3. If it is subsequently determined that Owner’s refusal of payment was not justified, the amount wrongfully withheld shall be treated as an amount due as determined by Paragraph 14.02.C.1.

14.03 Contractor’s Warranty of Title

A. Contractor warrants and guarantees that title to all Work, materials, and equipment covered by any Application for Payment, whether incorporated in the Project or not, will pass to Owner no later than the time of payment free and clear of all Liens.

14.04 Substantial Completion

A. When Contractor considers the entire Work ready for its intended use Contractor shall notify Owner and Engineer in writing that the entire Work is substantially complete (except for items specifically listed by Contractor as incomplete) and request that Engineer issue a certificate of Substantial Completion.

B. Promptly after Contractor’s notification, , Owner, Contractor, and Engineer shall make an inspection of the Work to determine the status of completion. If Engineer does not consider the Work substantially complete, Engineer will notify Contractor in

Page 99: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 40

writing giving the reasons therefor.

Page 100: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 41

C. If Engineer considers the Work substantially complete, Engineer will deliver to Owner a tentative certificate of Substantial Completion which shall fix the date of Substantial Completion. There shall be attached to the certificate a tentative list of items to be completed or corrected before final payment. Owner shall have seven days after receipt of the tentative certificate during which to make written objection to Engineer as to any provisions of the certificate or attached list. If, after considering such objections, Engineer concludes that the Work is not substantially complete, Engineer will within 14 days after submission of the tentative certificate to Owner notify Contractor in writing, stating the reasons therefor. If, after consideration of Owner’s objections, Engineer considers the Work substantially complete, Engineer will within said 14 days execute and deliver to Owner and Contractor a definitive certificate of Substantial Completion (with a revised tentative list of items to be completed or correct- ed) reflecting such changes from the tentative certificate as Engineer believes justified after consideration of any objections from Owner.

D. At the time of delivery of the tentative certificate of Substantial Completion, Engineer will deliver to Owner and Contractor a written recommen- dation as to division of responsibilities pending final payment between Owner and Contractor with respect to security, operation, safety, and protection of the Work, maintenance, heat, utilities, insurance, and warranties and guarantees. Unless Owner and Contractor agree otherwise in writing and so inform Engineer in writing prior to Engineer’s issuing the definitive certificate of Substantial Completion, Engineer’s aforesaid recommendation will be binding on Owner and Contractor until final payment.

E. Owner shall have the right to exclude Contractor from the Site after the date of Substantial Completion subject to allowing Contractor reasonable access to complete or correct items on the tentative list.

14.05 Partial Utilization

A. Prior to Substantial Completion of all the Work, Owner may use or occupy any substantially completed part of the Work which has specifically been identified in the Contract Documents, or which Owner, Engineer, and Contractor agree constitutes a separately functioning and usable part of the Work that can be used by Owner for its intended purpose without significant interference with Contractor’s performance of the remainder of the Work, subject to the following condi- tions.

1. Owner at any time may request Contractor in writing to permit Owner to use or occupy any such part of the Work which Owner believes to be ready for its intended use and substantially complete. If and when Contractor agrees that such part of the Work is substantially complete, Contractor will certify to Owner and Engineer that such part of the Work is substantially

complete and request Engineer to issue a certificate of Substantial Completion for that part of the Work.

2. Contractor at any time may notify Owner and Engineer in writing that Contractor considers any such part of the Work ready for its intended use and substan- tially complete and request Engineer to issue a certificate of Substantial Completion for that part of the Work.

3. Within a reasonable time after either such request, Owner, Contractor, and Engineer shall make an inspection of that part of the Work to determine its status of completion. If Engineer does not consider that part of the Work to be substantially complete, Engineer will notify Owner and Contractor in writing giving the reasons therefor. If Engineer considers that part of the Work to be substantially complete, the provisions of Paragraph 14.04 will apply with respect to certification of Substantial Completion of that part of the Work and the division of responsibility in respect thereof and access thereto.

4. No use or occupancy or separate operation of part of the Work may occur prior to compliance with the requirements of Paragraph 5.10 regarding property insurance.

14.06 Final Inspection

A. Upon written notice from Contractor that the entire Work or an agreed portion thereof is complete, Engineer will promptly make a final inspection with Owner and Contractor and will notify Contractor in writing of all particulars in which this inspection reveals that the Work is incomplete or defective. Contractor shall immediately take such measures as are necessary to complete such Work or remedy such deficiencies.

14.07 Final Payment

A. Application for Payment

1. After Contractor has, in the opinion of Engineer, satisfactorily completed all corrections identified during the final inspection and has delivered, in accordance with the Contract Documents, all maintenance and operating instructions, schedules, guarantees, bonds, certificates or other evidence of insurance certificates of inspection, marked-up record documents (as provided in Paragraph 6.12), and other documents, Contractor may make application for final payment following the procedure for progress payments.

2. The final Application for Payment shall be accompanied (except as previously delivered) by:

a. all documentation called for in the Contract Documents, including but not limited to the evidence of insurance required by Paragraph 5.04.B.7;

b. consent of the surety, if any, to final payment;

Page 101: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 42

c. a list of all Claims against Owner that Contractor believes are unsettled; and

d. complete and legally effective releases or waivers (satisfactory to Owner) of all Lien rights arising out of or Liens filed in connection with the Work.

3. In lieu of the releases or waivers of Liens specified in Paragraph 14.07.A.2 and as approved by Owner, Contractor may furnish receipts or releases in full and an affidavit of Contractor that: (i) the releases and receipts include all labor, services, material, and equipment for which a Lien could be filed; and (ii) all payrolls, material and equipment bills, and other indebtedness connected with the Work for which Owner or Owner's property might in any way be responsible have been paid or otherwise satisfied. If any Subcontractor or Supplier fails to furnish such a release or receipt in full, Contractor may furnish a bond or other collateral satisfactory to Owner to indemnify Owner against any Lien.

B. Engineer’s Review of Application and Acceptance

1. If, on the basis of Engineer’s observation of the Work during construction and final inspection, and Engineer’s review of the final Application for Payment and accompanying documentation as required by the Contract Documents, Engineer is satisfied that the Work has been completed and Contractor’s other obligations under the Contract Documents have been fulfilled, Engineer will, within ten days after receipt of the final Application for Payment, indicate in writing Engineer’s recommendation of payment and present the Application for Payment to Owner for payment. At the same time Engineer will also give written notice to Owner and

Engineer so confirms, Owner shall, upon receipt of Contractor’s final Application for Payment (for Work fully completed and accepted) and recommendation of Engineer, and without terminating the Contract, make payment of the balance due for that portion of the Work fully completed and accepted. If the remaining balance to be held by Owner for Work not fully completed or corrected is less than the retainage stipulated in the Agreement, and if bonds have been furnished as required in Paragraph 5.01, the written consent of the surety to the payment of the balance due for that portion of the Work fully completed and accepted shall be submitted by Contractor to Engineer with the Application for such payment. Such payment shall be made under the terms and conditions governing final payment, except that it shall not constitute a waiver of Claims.

14.09 Waiver of Claims

A. The making and acceptance of final payment will constitute:

1. a waiver of all Claims by Owner against Contractor, except Claims arising from unsettled Liens, from defective Work appearing after final inspection pursuant to Paragraph 14.06, from failure to comply with the Contract Documents or the terms of any special guarantees specified therein, or from Contractor’s continuing obligations under the Contract Documents; and

2. a waiver of all Claims by Contractor against Owner other than those previously made in accordance with the requirements herein and expressly acknowledged by Owner in writing as still unsettled.

ARTICLE 15 - SUSPENSION OF WORK AND TERMINATION

Contractor that the Work is acceptable subject to the provisions of Paragraph 14.09. Otherwise, Engineer willreturn the Application for Payment to Contractor, indicat- ing in writing the reasons for refusing to recommend final payment, in which case Contractor shall make the necessary corrections and resubmit the Application for Payment.

C. Payment Becomes Due

1. Thirty days after the presentation to Owner of the Application for Payment and accompanying docu- mentation, the amount recommended by Engineer, less any sum Owner is entitled to set off against Engineer’s recommendation, including but not limited to liquidated damages, will become due and , will be paid by Owner to Contractor.

14.08 Final Completion Delayed

A. If, through no fault of Contractor, final completion of the Work is significantly delayed, and if

15.01 Owner May Suspend Work

A. At any time and without cause, Owner may suspend the Work or any portion thereof for a period of not more than 90 consecutive days by notice in writing to Contractor and Engineer which will fix the date on which Work will be resumed. Contractor shall resume the Work on the date so fixed. Contractor shall be granted an adjust- ment in the Contract Price or an extension of the Contract Times, or both, directly attributable to any such suspension if Contractor makes a Claim therefor as provided in Paragraph 10.05.

15.02 Owner May Terminate for Cause

A. The occurrence of any one or more of the following events will justify termination for cause:

1. Contractor’s persistent failure to perform the Work in accordance with the Contract Documents

Page 102: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 43

(including, but not limited to, failure to supply sufficient skilled workers or suitable materials or equipment or failure to adhere to the Progress Schedule established under Paragraph 2.07 as adjusted from time to time pursuant to Paragraph 6.04);

2. Contractor’s disregard of Laws or Regulations of any public body having jurisdiction;

3. Contractor’s disregard of the authority of Engineer; or

4. Contractor’s violation in any substantial way of any provisions of the Contract Documents.

B. If one or more of the events identified in Paragraph 15.02.A occur, Owner may, after giving Contractor (and surety ) seven days written notice of its intent to terminate the services of Contractor:

1. exclude Contractor from the Site, and take possession of the Work and of all Contractor’s tools, appliances, construction equipment, and machinery at the Site, and use the same to the full extent they could be used by Contractor (without liability to Contractor for trespass or conversion),

2. incorporate in the Work all materials and equipment stored at the Site or for which Owner has paid Contractor but which are stored elsewhere, and

3. complete the Work as Owner may deem expedient.

C. If Owner proceeds as provided in Paragraph 15.02.B, Contractor shall not be entitled to receive any further payment until the Work is completed. If the unpaid balance of the Contract Price exceeds all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) sustained by Owner arising out of or relating to completing the Work, such excess will be paid to Contractor. If such claims, costs, losses, and damages exceed such unpaid balance, Contractor shall pay the difference to Owner. Such claims, costs, losses, and damages incurred by Owner will be reviewed by Engineer as to their reasonableness and, when so approved by Engineer, incorporated in a Change Order. When exercising any rights or remedies under this Paragraph Owner shall not be required to obtain the lowest price for the Work performed.

D. Notwithstanding Paragraphs 15.02.B and 15.02.C, Contractor’s services will not be terminated if Contractor begins within seven days of receipt of notice of intent to terminate to correct its failure to perform and proceeds diligently to cure such failure within no more than 30 days of receipt of said notice.

E. Where Contractor’s services have been so terminated by Owner, the termination will not affect any rights or remedies of Owner against Contractor then existing or which may thereafter accrue. Any retention or payment of moneys due Contractor by Owner will not release Contractor from liability.

F. If and to the extent that Contractor has provided a performance bond under the provisions of Paragraph 5.01.A, the termination procedures of that bond shall supersede the provisions of Paragraphs 15.02.B, and 15.02.C.

15.03 Owner May Terminate For Convenience

A. Upon seven days written notice to Contractor and Engineer, Owner may, without cause and without prejudice to any other right or remedy of Owner, terminate the Contract. In such case, Contractor shall be paid for (without duplication of any items):

1. completed and acceptable Work executed in accordance with the Contract Documents prior to the effective date of termination, including fair and reasonable sums for overhead and profit on such Work;

2. expenses sustained prior to the effective date of termination in performing services and furnishing labor, materials, or equipment as required by the Contract Documents in connection with uncompleted Work, plus fair and reasonable sums for overhead and profit on such expenses;

3. all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) incurred in settlement of terminated contracts with Subcontractors, Suppliers, and others; and

4. reasonable expenses directly attributable to termination.

B. Contractor shall not be paid on account of loss of anticipated profits or revenue or other economic loss arising out of or resulting from such termination.

15.04 Contractor May Stop Work or Terminate

A. If, through no act or fault of Contractor, (i) the Work is suspended for more than 90 consecutive days by Owner or under an order of court or other public authority, or (ii) Engineer fails to act on any Application for Payment within 30 days after it is submitted, or (iii) Owner fails for 30 days to pay Contractor any sum finally determined to be due, then Contractor may, upon seven days written notice to Owner and Engineer, and provided Owner or Engineer do not remedy such suspension or failure within that time, terminate the Contract and recover from Owner payment on the same terms as

Page 103: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 44

provided in Paragraph 15.03.

Page 104: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 40

ARTICLE 17 - MISCELLANEOUSB. In lieu of terminating the Contract and

without prejudice to any other right or remedy, ifEngineer has failed to act on an Application for Payment within 30 days after it is submitted, or Owner has failed for 30 days to pay Contractor any sum finally determined to be due, Contractor may, seven days after written notice to Owner and Engineer, stop the Work until payment is made of all such amounts due Contractor, including interest thereon. The provisions of this Paragraph 15.04 are not intended to preclude Contractor from making a Claim under Paragraph 10.05 for an adjustment in Contract Price or Contract Times or otherwise for expenses or damage directly attributable to Contractor’s stopping the Work as permitted by this Paragraph.

ARTICLE 16 - DISPUTE RESOLUTION

16.01 Methods and Procedures

A. Either Owner or Contractor may request mediation of any Claim submitted to Engineer for a decision under Paragraph 10.05 before such decision becomes final and binding. The mediation will be governed by the Construction Industry Mediation Rules of the American Arbitration Association in effect as of the Effective Date of the Agreement. The request for mediation shall be submitted in writing to the American Arbitration Association and the other party to the Contract. Timely submission of the request shall stay the effect of Paragraph 10.05.E.

B. Owner and Contractor shall participate in the mediation process in good faith. The process shall be concluded within 60 days of filing of the request. The date of termination of the mediation shall be determined by application of the mediation rules referenced above.

C. If the Claim is not resolved by mediation, Engineer’s action under Paragraph 10.05.C or a denial pursuant to Paragraphs 10.05.C.3 or 10.05.D shall become final and binding 30 days after termination of the mediation unless, within that time period, Owner or Contractor:

1. elects in writing to invoke any dispute resolution process provided for in the Supplementary Conditions, or

2. agrees with the other party to submit the Claim to another dispute resolution process, or

3. gives written notice to the other party of their intent to submit the Claim to a court of competent jurisdiction.

17.01 Giving Notice

A. Whenever any provision of the Contract Documents requires the giving of written notice, it will be deemed to have been validly given if:

1. delivered in person to the individual or to a member of the firm or to an officer of the corporation for whom it is intended, or

2. delivered at or sent by registered or certified mail, postage prepaid, to the last business address known to the giver of the notice.

17.02 Computation of Times

A. When any period of time is referred to in the Contract Documents by days, it will be computed to exclude the first and include the last day of such period. If the last day of any such period falls on a Saturday or Sunday or on a day made a legal holiday by the law of the applicable jurisdiction, such day will be omitted from the computation.

17.03 Cumulative Remedies

A. The duties and obligations imposed by these General Conditions and the rights and remedies available hereunder to the parties hereto are in addition to, and are not to be construed in any way as a limitation of, any rights and remedies available to any or all of them which are otherwise imposed or available by Laws or Regula- tions, by special warranty or guarantee, or by other provisions of the Contract Documents. The provisions of this Paragraph will be as effective as if repeated specifically in the Contract Documents in connection with each particular duty, obligation, right, and remedy to which they apply.

17.04 Survival of Obligations

A. All representations, indemnifications, warran- ties, and guarantees made in, required by, or given in accordance with the Contract Documents, as well as all continuing obligations indicated in the Contract Docu- ments, will survive final payment, completion, and acceptance of the Work or termination or completion of the Contract or termination of the services of Contractor.

17.05 Controlling Law

A. This Contract is to be governed by the law of the state in which the Project is located.

17.06 Headings

Page 105: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

EJCDC C-700 Standard General Conditions of the Construction Contract.Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

GC - 41

A. Article and paragraph headings are inserted for convenience only and do not constitute parts

of these General Conditions.

Page 106: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01010-1

PART 1: GENERAL

SECTION 01010

SUMMARY OF WORK

1.01 WORK COVERED BY CONTRACT DOCUMENTS/REQUIREMENTS INCLUDED

A. Include the furnishing of all labor, equipment, and materials necessary for the construction of the project as shown on the drawings and specified herein.

B. The Contractor shall furnish all labor, materials, equipment, tools, services, and incidentals to complete all work required by these Specifications and as shown on the Drawings.

C. The Contractor shall perform the work complete and shall include repairs, replacements, and restoration required as a result of damages caused during this construction.

D. Furnish and install all materials, equipment, and labor which is reasonably and properly inferable and necessary for the proper completion of the work, whether specifically indicated in the Contract Documents or not.

E. In general the work includes, but is not limited to, installation of a sewer gravity main, sewer manholes with tie-ins and incidental items shown on the plans and in these specifications.

1.02 CONTRACTOR'S DUTIES

A. Contractor shall verify all field and job conditions prior to preparing his bid. Visit and examine the job sites, and with all authorities concerned in order to become familiar with all existing conditions pertinent to the work to be performed thereon. No additional compensation will be allowed for failure to be so informed.

B. Check all specifications and all drawings and bring to attention any conflicts or variations as shown or noted.

D. For any points which are not clear, or from items and/or details which the Contractor feels are in need of clarification, consult the Design Professional before submission of a proposal.

E. In case of discrepancies and/or ambiguities in the drawings and/or in the specifications, the Design Professional shall be consulted prior to

Page 107: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01010-2

submission of a proposal. Failure to do so on the part of the successful bidder shall be construed as explicit agreement on his part to abide by the Design Professional's decision in such matters.

F. Except as specifically noted, provide and pay for:

1. Labor, materials and equipment

2. Tools, construction equipment and machinery.

3. Temporary facilities required for construction.

4. Other facilities and services necessary for proper execution and completion of work.

5. Pay legally required sales, consumer, and use taxes.

G. Secure and pay for, as necessary for proper execution and completion of Work, and as applicable at time of receipt of bids:

1. Permits.

2. Government Fees.

3. Licenses.

H. Give required notices.

I. Comply with codes, ordinances, rules, regulations, and other legal requirements of public authorities that bear on performance of Work.

J. Promptly submit written notice to Design Professional of observed variance of Contract Documents from legal requirements.

1. Appropriate Modifications to Contract Documents will adjust necessary changes.

K. Enforce strict discipline and good order among employees. Do not employ on Work:

1. Unfit persons.

2. Persons not skilled in assigned task.

L. Work by Others:

1. Independent Testing Laboratory Services will be employed and paid for by the Owner.

M. Contractor use of Premises:

1. Confine operations at site to areas permitted by:

Page 108: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01010-3

a. Lawb. Ordinancec. Permitsd. Contract Documentse. Design Professionalf. Owner

N. Do not unreasonably encumber site with materials or equipment.

O. Do not load structures with weight that will endanger structures.

P. Assume full responsibility for protection and safekeeping of products stored on premises.

Q. Move any stored products that interfere with operations of Owner or other Contractors.

1.03 CONTRACTS

Construct the Work under a single lump sum or unit price contract as stated for each item in the bid form.

1.04 WORK SEQUENCE

A. All work to be done under this Contract shall be done with minimum inconvenience to the private property owners adjacent to this project.

B. Construct Work in stages to accommodate the Owner's use of the premises during the construction period; coordinate the construction schedule and operations with the Owner's Representative.

C. Construct the Work in stages to provide for public convenience.

D. Assume full responsibility for the protection and safekeeping of Products under this Contract, stored on the site.

E. Move any stored products, under Contractor's control, which interfere with operations of the Owner or separate contractor.

F. Obtain and pay for the use of additional storage or work areas needed for operations.

PART 2: PRODUCTS (NOT USED)

PART 3: EXECUTION (NOT USED)

END OF SECTION

Page 109: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01025-1

SECTION 01025 MEASUREMENT AND PAYMENT

PART 1 - GENERAL

A. Refer to Bid Schedule A.

B. Payment for the various items of the Bid Schedule, as further specified herein, shall include all compensation to be received by the Contractor for furnishing all tools, equipment, supplies, and manufactured articles, and for all labors, operations, and incidentals appurtenant to the items of work being described, as necessary to complete the various items of the work all in accordance with the requirements of the Contract Documents, including all costs of compliance with the regulations of public agencies having jurisdiction. The Contractor is hereby on notice that no separate payment will be made for any item that is not specifically set forth in the Bid Schedule, and all costs therefore shall be included in the prices named in the Bid Schedule for the various appurtenant items of work.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

PART 4 - MEASUREMENT AND PAYMENT

4.01 GENERAL

The Total Bid Price shall cover all work required by the Contract Documents. All costs in connection with the proper and successful completion of the work, including furnishing all materials, sheeting, bracing, bedding, backfill equipment, supplies, and appurtenances; providing all construction equipment, and tools; and performing all necessary labor and supervision to fully complete the work, shall be included in the unit and lump sum prices bid. All work not specifically set forth as a pay item in the Bid Form shall be considered a subsidiary obligation of the Contractor and all costs in connection therewith shall be included in the prices bid.

4.02 ESTIMATED QUANTITIES

All estimated quantities stipulated in the Bid Form or other Contract Documents are approximate and are to be used only (a) as a basis for estimating the probable cost of the work, and (b) for the purpose of comparing the bids submitted for the work. The actual amounts of work done and materials furnished under unit price items may differ from the estimated quantities. The basis of payment for work and materials will be the actual amount of work done and materials furnished. No compensation will be given for any quantities not used.

Page 110: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01025-2

4.03 SEEDING AND FERTILIZER (BID ITEM NO. 1)

A. Measurement: Measurement for payment for seeding and fertilizer will be made on a lump-sum basis.

B. Payment: Payment for this item will be made at the lump-sum price bid and will constitute full compensation for the seeding and fertilizer as required to complete the project.

4.04 REMOVAL OF STRUCTURES AND OBSTRUCTIONS, NOT TO EXCEED (BID ITEM NO. 2)

A. Measurement: Measurement for payment of removal of structures and obstructions will be made on pre negotiated basis for each unforeseen obstruction encountered that will need to be removed.

B. Payment: Payment for this item will be negotiated on a case by case basis for each item deemed to be in conflict with the progress of the project. Money for removal will be drawn off of the “Not to Exceed” price on the bid sheet. Thecontractor will not start any work towards this item unless directed by the Owner and price negotiations complete.

4.05 INSTALL SEWER MAIN (10”) (PVC/SDR 26 PIPE) (BID ITEM NO. 3)

A. Measurement: Measurement for payment will be made per linear foot installed complete with trench excavation, back filling, compaction etc. Measurement will be made from the center line of the manhole to the center line of the manhole.

B. Payment: The payment for this item will be made at the bid price to install sewer main (10”) (PVC/SDR 26 pipe) per linear foot and shall include, but not limited to, all labor, equipment, and materials necessary to complete all work as required in these specifications and plans and videotaping of completed sewer line. No separate payment will be made for videotaping.

4.06 INSTALL SEWER MANHOLE (BID ITEM NO. 4)

A. Measurement: The measurement for installation of sewer manhole shall be made per vertical foot height measured from invert of the manhole to the top of the manhole cover.

B. Payment: Payment for installation of sewer manhole will be made at theunit price bid per vertical foot height and shall constitute full compensation for all labor materials and equipment required to install sewer manholes in accordance

Page 111: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01025-3

with the plans and specifications.

4.07 LIFESAVER STAINLESS STEEL STOPPER, MANHOLE INSERT (BID ITEM NO. 5)

A. Measurement: Measurement for the lifesaver stainless steel stopper, manhole insert installed will be made per each.

B. Payment: Payment for lifesaver stainless steel stopper, manhole insert shall be made per each installed and will include all labor material and equipment required to complete this work.

4.08 ABANDON EXISTING SEWER MANHOLES & FILL VOID WITH SAND (BID ITEM NO. 6)

A. Measurement: Measurement to abandon existing sewer manholes and fill voids with sand will be made per each.

B. Payment: Payment to abandon existing sewer manholes and fill voids with sand will be made per each at the contract bid price and shall constitute full compensation for all labor materials and equipment required to remove the existing sewer manholes and fill voids with sand.

4.09 PLUG EXISTING SEWER MAIN @ MANHOLES & FILL WITH FLOWABLE MATERIAL (CEMENT/SAND MIXTURE) (BID ITEM NO. 7)

A. Measurement: Measurement to plug existing sewer main @ manholes & fill the pipe void with flowable material will be made per linear foot.

B. Payment: The payment for this item will be made at the bid price to plug existing sewer main @ manholes & fill void with flowable material (cement/sand mixture) per linear foot and shall include, but not limited to, all labor, equipment, and materials necessary to complete all work as required in these specifications and plans.

4.10 INSTALL 12” RCP (BID ITEM NO. 8)

A. Measurement: Measurement for payment will be made per linear foot 12” RCP installed complete with trench excavation, back filling, compaction etc.

B. Payment: The payment for this item will be made at the bid price to install 12” RCP per linear foot and shall include, but not limited to, all labor, equipment, and materials necessary to complete all work as required in these specifications and plans.

Page 112: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01025-4

4.11 UTILITY EXPLORATION (BID ITEM NO. 9)

A. Measurement: The measurement for this item will be on per each basis.

B. Payment for utility exploration will be made at the contract bid price per each and will constitute full compensation to provide all equipment, labor and materials to identify the existing underground utilities within the project limits which may be in conflict with construction.

4.12 MOBILIZATION (BID ITEM NO. 10)

A. Measurement: Measurement for payment will be on a lump-sum basis for mobilization and demobilization as specified herein.

B. Payment: Payment for mobilization shall cover all preparatory work and operating, including the obtaining of all permits, insurance and bonds; movement of personnel, equipment, supplies and incidentals to the project site; the establishment of temporary offices and other construction facilities necessary for work on this project; removal of temporary offices from site, and clean up to place temporary site in original condition, all as required for the proper performance and completion of the work.

Partial payments for mobilization will be made in accordance with the following schedule up to a maximum of 5 percent of the original total contract amount, including this item, and payment of any remaining amount will be made upon completion of all work under the contract.

Percent of Total Contract AllowablePercent of the Amount Earned

Allowable Percent of the Lump SumPrice for the Item

1st Partial Estimate 5050 7575 100

No price adjustments will be made for this item due to changes in the work.

4.13 CONSTRUCTION LAYOUT (BID ITEM NO. 11)

A. Measurement: Measurement for payment will be on a lump sum basis.

B. Payment: The lump sum bid price for construction layout shall include, but not limited to, all labor, equipment, and materials necessary to complete all work as required in Section 01051 of these specifications.

Page 113: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01025-5

4.14 REMOVAL OF CONCRETE WALKS AND DRIVES (BID ITEM NO. 12)

A. Measurement: Measurement for payment will be on a square yard basis.

B. Payment: The payment for removal of concrete walks and drives shall be made per square yard at the bid price. No separate payment shall be made for removal of curb attached with the driveway or sidewalk. The payment shall include, but not limited to, all labor, equipment, and materials necessary to complete all work as required.

4.15 CONCRETE DRIVE (6” THICK) (BID ITEM NO. 13)

A. Measurement: Measurement for payment will be on a square yard basis.

B. Payment: The payment for installation of concrete drive (6” thick) shall be made per square yard at the bid price. The payment shall include, but not limited to, all labor, equipment, and materials necessary to complete all work as required using 4000 PSI concrete. No separate payment shall be made for any reinforcement.

4.16 CONCRETE WALK (4” THICK) (BID ITEM NO. 14)

A. Measurement: Measurement for payment will be on a square yard basis.

B. Payment: The payment for installation of concrete walk (4” thick) shall be made per square yard at the bid price. The payment shall include, but not limited to, all labor, equipment, and materials necessary to complete all work as required using 4000 PSI concrete. No separate payment shall be made for any reinforcement and thickened edge of sidewalk.

4.17 CONCRETE CURB (BID ITEM NO. 15)

A. Measurement: Measurement for payment will be on linear foot basis.

B. Payment: The payment for installation of concrete curb shall be made per linear foot at the bid price. The payment shall include, but not limited to, all labor, equipment, and materials necessary to complete all work as required using 4000 PSI concrete. No separate payment shall be made for any reinforcement.

4.18 ITEMS NOT DIRECTLY PAID FOR

A. The following items of work shall be accomplished with noseparate payment. All costs associated with these items shall be included in other bid items or borne by Contractor:

1. Saw Cut Pavement, Driveway or Sidewalk. No separate paymentshall be made for saw cutting pavement, sidewalk or driveway. All costs

Page 114: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01025-6

associated with these items shall be included in other bid items or borne by Contractor.

2. Other items on the plans labeled as no direct pay.

END OF SECTION

Page 115: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01030-1

SECTION 01030

SPECIAL PROJECT PROCEDURES

PART 1: GENERAL

1.1 CONNECTIONS TO EXISTING SYSTEMS

The Contractor shall perform all work necessary to install the sewer gravity main system, fittings and accessories as shown on the drawings or as directed by the Engineer. The cost for this work shall be included in the price bid for the various items and shall not result in any additional cost to the Owner.

1.2 RELOCATIONS

A. The Contractor shall be responsible for the relocation or removal of structures, including but not limited to light poles, signs, sign poles, fences, piping, conduits and drains that interfere with the positioning of the work as shown on the drawings. The cost of all such relocations or removals shall be paid under bid item no 2. “Removal of Structures and Obstructions, not to exceed.”

1.3 EXISTING UNDERGROUND PIPING, STRUCTURES, AND UTILITIES

A. The attention of the Contractor is drawn to the fact that during excavation, the possibility exists of the Contractor encountering various water, gas, telephone, electrical, or other utility lines not shown on the drawings. The Contractor shall exercise extreme care before and during excavation to locate and flag these lines so as to avoid damage to the existing lines. Should damage occur to an existing line, the Contractor shall repair the line at no cost to the owner.

B. It is the responsibility of the Contractor to ensure that all utility or other poles, the stability of which may be endangered by the close proximity of excavation, are temporarily stayed in position while work proceeds in the vicinity of the pole and that the utility or other companies concerned be given reasonable advance notice of any such excavation by the Contractor.

C. The locations are shown without express or implied representation, assurance, or guarantee that they are complete or correct or that they represent a true picture of underground piping to be encountered.

D. The existing piping and utilities may interfere with the construction of this project. Before any piping and utilities not shown on the drawings are disturbed, the Contractor shall notify the Engineer of the location of the pipeline or utility as

Page 116: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01030-2

directed. All privately owned utility relocations (cable, gas, telephone, electric, etc.) shall be performed by the owner of the utility or his approved contractor as directed by the Engineer.

E. The Contractor shall exercise care in any excavation to locate all existing piping and utilities. All utilities which do not interfere with complete work shall be carefully protected against damage. Any existing utilities damaged in any way by the Contractor shall be restored or replaced by the Contractor at his expense as directed by the Engineer.

1.4 PUMPING

A. The Contractor, with his own equipment, shall do all pumping necessary to prevent flotation of any part of the work during construction operations. No direct pay.

B. The Contractor shall, for the duration of the Contract and with his own equipment, pump out water and wastewater that may seep or leak into the excavations. This shall include bypass pumping of sewer to facilitate construction of manholes, tie- ins or any other work item. No direct pay.

1.5 ADDITIONAL PROVISIONS

A. Before commencing work on any of the existing structures or equipment, the Contractor shall notify the Engineer, in writing, at least ten (10) calendar days in advance of the date he proposes to commence such work.

B. The Contractor shall provide, at his own cost, all necessary temporary facilities for access to, and for protection of, all existing structures. The Owner’s personnel must have ready access at all times to the existing structures. The Contractor is responsible for all damage to existing structures, equipment, and facilities caused by his construction operations, and must repair all such damage when and as ordered by the Engineer.

1.6 SHOP DRAWINGS

The Contractor shall not commence construction of any individual activity until completion of Engineer’s shop drawings review of all material or equipment pertaining to that activity.

Page 117: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01030-3

1.7 SPECIAL PROVISIONS

SP-1 WORKING HOURS

A. CONTRACTOR shall provide competent, suitably qualified personnel to survey, lay out, and construct the Work as required by the Contract Documents. CONTRACTOR shall at all times maintain good discipline and order at the Site.

B. Except as otherwise required for the safety or protection of persons or the Work or property at the Site or adjacent thereto, and except as otherwise stated in the Contract Documents, all Work at the Site shall be performed during regular working hours, and CONTRACTOR will not permit overtime work or the performance of Work on Saturday, Sunday, or any legal holiday without OWNER’S written consent (which will not be unreasonably withheld) given after prior written notice to ENGINEER. For purposes of the foregoing sentence and this Contract “regular working hours” shall mean between 7:00 a.m. and 6:00p.m. Emergency work may be performed without prior permission. CONTRACTOR shall establish a normal work schedule which does not exceed 40 hours per week.

PART 2: PRODUCTS (Not Used)

PART 3: EXECUTION (Not Used)

END OF SECTION

Page 118: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01041-1

SECTION 01041 PROJECT COORDINATION

PART 1 - GENERAL

1.01 REQUIREMENTS

Contractor shall plan, schedule, and coordinate his operations in a manner that will facilitate the simultaneous progress of the work included under other contracts outside the scope of these Contract Documents. Contractor shall plan, schedule and coordinate with all utilities in a manner conducive to timely and efficient progress in the execution of the contract.

1.02 NOTICES TO OWNERS AND AUTHORITIES

A. Contractor shall, as provided in the General Conditions, notify owners of adjacent property and utilities when execution of the Work may affect them.

When it is necessary to temporarily deny the access of owners or tenants to their property, or when any utility service connections must be interrupted, Contractor shall give notices at least 7 days in advance to enable the affected persons to provide for their needs. The Contractors, as a minimum, shall place a door hanger type notice, conforming to any applicable local ordinance, at each residence or business giving notice of pending construction in the area with a brief description of the nature of the work, the estimated time frame involved, appropriate information concerning utility interruptions, and instructions on how to limit their inconvenience.

Utilities and other concerned agencies shall be contacted at least 48 hours prior to cutting or closing streets or other traffic areas or excavating near underground utili- ties or poles lines.

1.03 CONNECTIONS TO EXISTING FACILITIES

Unless otherwise specified or indicated, Contractor shall make all necessary connections to existing facilities including structures, drain lines, and utilities such as water, sewer, gas, telephone, and electric. In each case, Contractor shall receive permission from Owner or the owning utility prior to undertaking connections. Contractor shall protect facilities against deleterious substances and damage.

Connections to existing facilities that are in service shall be thoroughly planned in advance, and all required equipment, materials and labor shall be on hand at the time of undertaking the connections. Work shall proceed continuously (around the clock if necessary) to complete connections in the minimum time. Operation of valves of other appurtenances on existing

Page 119: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01041-2

utilities, when required, shall be by or under the direct supervision of the utility owner.

Page 120: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01041-3

1.04 OPERATION OF EXISTING FACILITIES

All existing facilities must be kept in continuous operation throughout the construction period. No interruption will be permitted which adversely affects the degree of service provided. Provided permission is obtained from Owner in advance, portions of the existing facilities may be taken out of service for short periods corresponding with periods of minimum service demands.

Contractor shall provide temporary facilities and make temporary modifications as necessary to keep the existing facilities in operation during the construction period.

1.05 TESTING LABORATORY

It shall be the Contractor's responsibility to assist in the coordination of the services of the Owner- selected and reimbursed Testing Laboratory to determine that materials and workmanship comply with the requirements of these specifications. Such testing shall meet the requirements of all pertinent codes and regulations and selected standards as specified elsewhere in these Specifications. Testing services shall include the requirements of applicable sections of the Technical Specifica- tions.

Representatives of the testing laboratory shall have access to the work at all times and facilities for such access shall be provided in order that the laboratory may perform its functions properly. The Contractor shall consult the testing laboratory in advance to determine the time required to perform the tests and to issue each of the findings. The testing laboratory shall be notified by the Contractor of any schedule changes. All samples, if any, shall be taken by the testing laboratory and any equipment, supplies, and delivery services that the laboratory requires shall also be provided by the testing laboratory.

The Contractor shall notify the testing laboratory prior to the construction.

1.06 COOPERATION WITHIN THIS CONTRACT

All firms or persons authorized to perform any work under this Contract shall cooperate with the General Contractor and his subcontractors or trades, and shall assist in incorporating the work of other trades where necessary or required.

Cutting and patching, drilling, and fitting shall be carried out where required by the trade or subcontractor having jurisdiction, unless otherwise indicated herein or directed by the Engineer.

END OF SECTION

Page 121: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

SECTION 01043JOB SITE ADMINISTRATION

PART 1 - GENERAL

1.01 SITE ADMINISTRATION

Contractor shall be responsible for all areas of the site used by him, and all subcontractors in the performance of the Work. He will exert full control over the actions of all employees and other persons with respect to the use and preservation of property and existing facilities, except such controls as may be specifically reserved to Owner or others. Contractor has the right to exclude from the site all persons who have no purpose related to the Work or its inspection, and may require all persons on the site to observe the same safety regulations, as he required of his employees. At all working hours a superintendent shall be at the job on a full-time basis.

1.02 UNFAVORABLE CONSTRUCTION CONDITIONS

Contractor shall confine his operations to work, which will not be affected adversely by unfavorable weather, wet ground, or other unsuitable construction conditions. No portion of the Work shall proceed under conditions that would affect adversely the quality or efficiency of the Work, unless suitable special precautions or countermeasures are taken by Contractor.

1.03 LAND FOR CONSTRUCTION PURPOSES

A. Contractor will be permitted to use available land belonging to Owner, on or near the site of the Work, for construction purposes and for the storage of materials and equipment. The location and extent of the areas so used shall be as indicated on the drawings or as directed by the Engineer. Contractor shall immediately move stored material or equipment if any occasion arises, as determined by Owner, requiring access to the storage area. Materials or equipment shall not be placed on the property of Owner until Owner has agreed to the location to be used for storage.

B. It shall be the Contractor’s responsibility to provide arrangements for additional land required for construction or for location of the Resident Project Representative’s office if applicable beyond that furnished by the Owner. This work shall be considered a subsidiary obligation of the Contractor and all costs in connection therewith shall be included in the lump sum price for the applicable item.

PART 2- PRODUCTS (NOT USED)

PART 3- EXECUTION (NOT USED)

END OF SECTION

01043-1

Page 122: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

SECTION 01045 CUTTING AND PATCHING

PART 1 - GENERAL

1.01 As provided in the General Conditions and herein, Contractor shall perform all cutting and patching required for the Work, and as may be necessary in connection with uncovering Work for inspection or for the correction of defective Work.

1.02 Contractor shall perform all cutting and patching required for the installation of improperly timed Work, to remove samples of installed materials for testing, and to provide for alteration of existing facilities or the installation of new Work in existing construction.

1.03 Contractor shall submit to the Engineer enough photographs of the existing roadway so that the Engineer can establish the existing condition of the roadway prior to beginning any work.

1.04 Except when the cutting or removal of existing construction is specified or indicated, Contractor shall not undertake any cutting or demolition, which may affect the structural stability of the Work or existing facilities.

Contractor shall provide all shoring, bracing, supports, and protective devices necessary to safeguard all Work and existing facilities during cutting and patching operations.

1.05 Materials shall be cut and removed to the extent indicated on the drawings or as required to complete the Work. Materials shall be removed in a careful manner with no damage to adjacent facilities or materials. Materials that are not salvageable shall be removed from the site by Contractor.

1.06 All Work and existing facilities affected by cutting operations shall be restored with new materials, or with salvaged materials acceptable to Engineer, to obtain a finished installation with the strength, appearance, and functional capacity required. If necessary, entire surfaces shall be patched and refinished.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION

01045-1

Page 123: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

SECTION 01051 CONSTRUCTION LAYOUT

PART 1 - GENERAL

1.01 This section covers construction layout work required by the Contractor.

1.02 Lines and Grades

A. All Work shall be done to the lines, grades and elevations indicated on the drawings. Basic horizontal and vertical control points will be designated by Engineer on the Project Plans. These points shall be used as datum for the Work. All survey, layout, and measurement Work shall be performed by Contractor as a part of the Work.

B. Contractor shall provide an experienced instrument man, competent assistants, and such instruments, tools, stakes, and other materials required to complete the survey, layout and measurement Work. In addition, Contractor shall furnish, without charge, competent men from his force and such tools, stakes and other materials as Engineer may require in establishing or designating control points, in establishing construction easement boundaries or in checking survey, layout, and measurement Work performed by Contractor. Contractor shall keep Engineer informed, a reasonable time in advance, of the times and places at which he wishes to do Work, so that horizontal and vertical control points may be established and any checking deemed necessary by Engineer may be done within minimum inconvenience to Engineer and minimum delay to Contractor.

C. Before ordering material and before performing work, the Contractor shall verify all measurements as may be required for the proper fitting of various parts of his work or to other work. He shall be responsible for the correctness of his figures and shall satisfactorily correct, without extra cost to the Owner, any of his work, which does not fit, furnishing new work, if necessary for the purpose. Adapting all work to all field variations is Contractor’s responsibility. No extras will be allowed because of minor differences between actual dimensions and dimensions shown on the drawings.

D. Contractor shall remove and reconstruct Work, which is improperly located.

PART 2- PRODUCTS (NOT USED)

PART 3- EXECUTION (NOT USED)

END OF SECTION

01051-1

Page 124: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

1060-1

SECTION 01060 REGULATORY REQUIREMENTS

PART 1 - GENERAL

1.01 The Contractor shall, without additional expense to the Owner, be responsible for obtaining any necessary licenses and permits, and for complying with any applicable Federal, State and municipal laws, codes and regulations, in connection with the prosecution of the Work. He shall take proper safety and health precautions to protect the Work, the workers, the public and the property of others. He shall also be responsible for all materials delivered and work performed until completion and acceptance of the Work.

1.02 The Contractor is hereby advised that any delay in the project as a result of review of any regulatory authority will not be a cause for additional compensation except for possible extension of project time.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION

Page 125: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

1070-1

SECTION 01070ABBREVIATIONS, SYMBOLS, TRADE NAMES AND MATERIALS

PART 1 - GENERAL

1.01 DESCRIPTION

This Section of the Specifications lists many of the trade associations and general standards that are referenced repeatedly in the Specifications, along with the abbreviations commonly used for these references. This also specifies certain general requirements for the Work, in relation with standards, and with trade associations and their published recommendations. Refer to individual Specification Sections for names and abbreviations of other trade associations and standards that are referenced less repeatedly.

1.02 ABBREVIATIONS AND NAMES

The following abbreviations as referenced in the Contract Document are defined to mean the associated names.

AASHTO American Association of State Highway and Transportation Officials

ACI American Concrete InstituteAGA American Gas AssociationAGMA American Gear Manufacturers Association AISC American Institute of Steel Construction AISI American Iron and Steel InstituteANSI American National Standards Institute ASCE American Society of Civil Engineers ASHRAE American Society of Heating, Refrigerating,

and Air Conditioning EngineersASTM American Society for Testing and Materials ASME American Society of Mechanical Engineers AWPA American Wood Preservers Association AWS American Welding SocietyAWWA American Water Works Association CIPRA Cast Iron Pipe Research Association CRSI Concrete Reinforcing Steel Institute Fed. Spec. Federal SpecificationIEEE Institute of Electrical and Electronic

EngineersIES Illuminating Engineering SocietyLDOTD Louisiana Department of Transportation and

DevelopmentNEC National Electric Code

Page 126: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01070-2

NEMA National Electrical Manufacturers Association NFPA National Fire Protection AssociationOSHA Occupational Safety and Health Administration SAE Society of Automotive EngineersSHBI Steel Heating Boiler InstituteUL Underwriters Laboratories, Inc.

1.03 QUALITY ASSURANCE

A. General Applicability Standards. Except where more explicit or more stringent requirements are specified or are required by governing regulations, applicable stan- dards of the construction industry have the same force and effect for the Work; and are made a part of the Contract Documents by reference, as if copied directly into the Contract Documents, or as if published copies were bound herewith.

B. Referenced Standards. Referenced standards shall have precedence over non- referenced standards, which are intended by the manufacturer for application to work similar to that required on the Project.

C. Non-referenced Standards. Industry standards not specifically referenced for applicability to the Work, including standards listed in this Section but not referenced elsewhere, have no particular applicability to the work, except as a general measurement of whether the performed work complies with standards of construction industry.

D. Comply with the standard that was in effect at the date of bidding except where specifically indicated to comply with a publication of another date.

E. Copies of Standards. In general, copies of applicable standards have not been bound with the Contract Documents. Where copies of standards are needed for proper performance of the Work, the Contractor is required to obtain such copies directly from the publication source.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION

Page 127: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01090-1

SECTION 01090 REFERENCE STANDARDS

PART 1 - GENERAL

1.01 SCOPE

This Section of the Specifications covers reference standards required for the contract.

1.02 REFERENCE STANDARDS

Reference to standards of any technical society, organization, or association, or to codes of local or state authorities, shall mean the latest standard, code, specification, or tentative standard adopted and published at the date of receipt of bids, unless specifically stated otherwise.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION

Page 128: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01115-1

PART 1: GENERAL

1.01 WORK PROGRESS

SECTION 01115

CONTROL OF WORK

The Contractor shall furnish personnel and equipment which will be efficient, appropriate, and large enough to secure a satisfactory quality of work and a rate of progress which will insure the completion of the work within the time stipulated in the Proposal. If at any time such personnel or equipment appears to the Design Professional to be inefficient, inappropriate, or insufficient for securing the quality of work required for producing the rate of progress aforesaid, he may order the Contractor to increase the efficiency, change the character, or increase the personnel and equipment, and the Contractor shall conform to such order. Failure of the Design Professional to give such order shall in no way relieve the Contractor of his obligations to secure the quality of the work and rate of progress required.

1.02 PRIVATE LAND

The Contractor shall be aware that some of his work will be performed adjacent to and/or on private property.

1.03 WORK LOCATIONS

Work shall be located substantially as indicated on the Drawings, but the Design Professional reserves the right to make such modifications in locations as may be found desirable to avoid interference with existing structures or for other reasons.

1.04 OPEN EXCAVATIONS

A. All open excavations shall be adequately safeguarded by providing temporary barricades, caution signs, lights, and other means to prevent accidents to persons, and damage to property.

B. Contractor shall be responsible for supplying materials, services, and labor necessary to provide sheeting, shoring and bracing or supports as required to provide a safe working condition for Contractor's personnel and to provide for protection of utilities, buildings, and structures. It shall be the sole responsibility of the Contractor to comply with these requirements.

C. Where excavation is required adjacent to existing power poles or other structures, the contractor has the responsibility to maintain the integrity of the structure by bracing or other means subject to the approval of the Project Design Professional.

1.05 DISTRIBUTION SYSTEMS AND SERVICES

A. The Contractor shall interrupt water, telephone, Cable TV, sewer, gas, or other related utility services and disrupt the normal functioning of the system as little as possible. He shall notify the Design Professional well in advance of any requirement for dewatering, isolating, or relocating a section of a utility, so that necessary arrangements may be made with the appropriate agency.

Page 129: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01115-2

B. If it appears that utility service will be interrupted for an extended period, the Design Professional may order the Contractor to provide temporary service lines. Inconvenience of the users shall be the minimum, consistent with existing conditions. The safety and integrity of the system is of prime importance in scheduling work.

C. Private utilities located on public right-of-way which are required to be permanently relocated at the job site or removed entirely from the jobsite to accommodate the project will be indicated on the plans.

D. Private utilities located on public right-of-way which the contractor requests to be temporarily relocated, disconnected or de-energized for the convenience of construction or for safety reasons shall be done so at the contractor's expense.

E. Disposition of Utilities: Follow rules and regulations of the authority having jurisdiction in executing all Work under this article. Adequately protect active utilities shown on the Drawings from damage and remove or relocate only as indicated or specified. Where active utilities are encountered, but are not shown on the Drawings, advise the Design Professional. Adequately protect, support, or relocate the Work as directed. Remove, plugged or capped inactive and abandoned utilities encountered in excavating and grading operations.

1.06 PROTECTION AND RELOCATION OF EXISTING STRUCTURES AND UTILITIES

A. The Contractor shall assume full responsibility for the protection of all buildings, structures, and utilities, public or private, including poles, signs, services to building utilities, in the street, gas pipes, water pipes, hydrants, sewers, drains, and electric and telephone cables, whether or not they are shown on the Drawings. The Contractor shall carefully support and protect all such structures and utilities from injury of any kind. Any damage resulting from the Contractor's operation shall be repaired by him at his expense.

B. The Contractor shall bear full responsibility for obtaining locations of all underground structures and utilities (including existing water services, drain lines, and sewers). Services to buildings shall be maintained, and all costs or charges resulting from damage thereto shall be paid by the Contractor.

C. Protection and temporary removal and replacement of existing utilities and structures as described in this Section shall be a part of the work under the Contract and all costs in connection therewith shall be included in the unit and or Lump Sum prices established in the Proposal.

D. If, in the opinion of the Design Professional, permanent relocation of a utility owned by the City of Kenner is required, he may direct the Contractor in writing, to perform the work. Work so ordered will be paid for at the Contract unit prices, if applicable, or as extra work under Article 10 of the General Conditions. If relocation of a privately owned utility is required, the Contractor will notify the Utility to perform the work as expeditiously as possible. The Contractor shall fully cooperate with the City of Kenner, City and Utility and shall have no claim for delay due to such relocation. The Contractor shall notify public utility companies in writing at least 48 hours (excluding Saturdays, Sundays, and legal

Page 130: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01115-3

holidays) before excavating near their utilities. Costs of relocating utilities shall be included in the various unit prices of the work to be done or as otherwise provided in these contract documents.

1.07 CARE AND PROTECTION OF PROPERTY

A. The Contractor shall be responsible for the preservation of all public and private property, and shall use every precaution necessary to prevent damage thereto. If any direct or indirect damage is done to public or private property by or on account of any act, omission, neglect, or misconduct in the execution of the work on the part of the Contractor, such property shall be restored by the Contractor, at his expense, to a condition similar or equal to that existing before the damage was done, or he shall make good the damage in another manner acceptable to the Design Professional.

B. The protection, removal, and replacement of existing physical features along the line of work shall be a part of the work under the Contract, and all costs in connection therewith shall be included in the unit and/or lump sum prices established under the items in the Proposal.

1.08 DRAINAGE

Contractor shall impede drainage only in the event such impediment is necessary for the implementation of the work. When impeding drainage is necessary, Contractor shall take the necessary steps to protect life and property. Flooding of adjacent streets and land will not be permitted.

1.09 WATER FOR CONSTRUCTION PURPOSES

A. In locations where public water supply is available, the Contractor may purchase water for all construction purposes.

B. The express approval of the Water Department of the City of Kenner shall be obtained in writing. Hydrants shall only be operated under the supervision of the Water Department personnel of the City of Kenner.

1.10 MAINTENANCE OF FLOW

The Contractor shall at his own cost, provide for the flow of sewers, drains, and water courses interrupted during the progress of the Work, and shall immediately cart away and remove all offensive matter. The entire procedure of maintaining existing flow shall be fully discussed with the Design Professional well in advance of the interruption of any flow. Pavement removal and replacement which, in the opinion of the Contractor, is necessitated by placement of temporary flow control facilities shall be considered as an item for convenience to the Contractor. Such costs for pavement removal and replacement shall, therefore, be borne by the Contractor at his own cost as required for other flow control measures. The intent of this Specification is that pavement removal be limited to the least amount possible and the Contractor shall investigate alternative methods for flow control which require the least amount of pavement removal.

Page 131: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01115-4

1.11 CLEANUP

During the course of the Work, the Contractor shall keep the site of his operations in as clean and neat a condition as is possible. He shall dispose of all residue resulting from the construction work and, at the conclusion of the work, he shall remove and haul away any surplus excavation, broken pavement, lumber, equipment, temporary structures, and any other refuse remaining from the construction operations, and shall leave the entire site of the Work in a neat and orderly condition.

1.12 COOPERATION WITHIN THIS CONTRACT

A. All firms or persons authorized to perform any work under this Contract shall cooperate with the General Contractor and his subcontractors or trades, and shall assist in incorporating the work of other trades where necessary or required.

B. Cutting and patching, drilling, and fitting shall be carried out where required by the trade or subcontractor having jurisdiction, unless otherwise indicated herein or directed by the Design Professional.

1.13 PROTECTION OF CONSTRUCTION AND EQUIPMENT

A. All newly constructed work shall be carefully protected from damage in any way.

B. It is the responsibility of the Contractor to provide protection of all structure. Should any of the work become heaved, cracked, or otherwise damaged, all such damaged portions of the work shall be completely repaired and made good by the Contractor at his own expense and to the satisfaction of the Design Professional. If, in the final inspection of the Work, any defects, faults, or omissions are found, the Contractor shall cause the same workmanship without extra compensation for the materials and labor required. Further, the Contractor shall be fully responsible for the satisfactory maintenance and repair of the construction and other work undertaken herein, for at least the guarantee period described in the Contract.

1.14 PROTECTION OF EXISTING CANAL BANKS

A. The Contractor shall assume full responsibility for the stabilization of all existing canal banks during construction operations including open cutting, dredging, excavation, grading, filling and driving of piles and sheet piles among other miscellaneous activities. Any damage resulting from the Contractor's operation shall be repaired by him at his expense.

PART 2: PRODUCTS (NOT USED)

PART 3: EXECUTION (NOT USED)

END OF SECTION

Page 132: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01152-1

SECTION 01152 REQUEST FOR PAYMENT

PART 1 - GENERAL

1.01 REQUIREMENTS INCLUDED

Submit Applications for Payment to Engineer in accord with the schedule established by Conditions of the Contract and Agreement Between Owner and Contractor.

1.02 FORMAT AND DATA REQUIRED

A. Submit payment requests in the form required by Owner with itemized data typed on 8 1/2" x 11" white paper continuation sheets.

B. Provide itemized data on continuation sheet. Format, schedules, line items and values shall be those of the Schedule of Values accepted by Engineer.

C. Submit Pay Request Check List Form (provided by engineer).

1.03 SUBSTANTIATING DATA FOR PROGRESS PAYMENTS

A. When the Owner or the Engineer requires substantiating data, Contractor shall submit suitable information, with a cover letter.

B. Submit one copy of data and cover letter for each copy of application.

1.04 PREPARATION OF APPLICATION FOR FINAL PAYMENT

A. Fill in Application form as specified for progress payments.

B. Use continuation sheet for presenting the final statement of accounting as specified in the section pertaining to "Demobilization".

1.05 SUBMITTAL PROCEDURE

A. Submit Applications for Payment to Engineer at the times stipulated in the Agreement.

B. Number: Original and four (4) copies of each Application and attachments.

Page 133: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01152-2

C. When Engineer finds Application properly completed and correct, he will transmit certificate for payment to Owner, with copy of the transmittal letter to Contractor.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION

Page 134: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01153-1

SECTION 01153

CHANGE ORDER PROCEDURES

PART 1-GENERAL

1.01 REQUIREMENTS INCLUDED

A. Promptly implement change order procedures.

1. Provide full written data required to evaluate changes.

2. Maintain detailed records of work done on a time-and-material/ force account basis.

3. Provide full documentation to Engineer on request.

B. Designate in writing the member of Contractor's organization:

1. Who is authorized to accept changes in the Work.

2. Who is responsible for informing others in the Contractor's employ of the authorization of changes in the Work.

C. Owner will designate in writing the person who is authorized to execute Change Orders.

1.02 RELATED REQUIREMENTS

A. Agreement, the amounts of established unit prices, is included in the general Specifications and Conditions.

B. Conditions of the Contract are included in the General Specifications and Conditions.

1. Methods of determining cost or credit to Owner resulting from changes in Work made on a time and material basis.

2. Contractor's claims for additional costs.

1.03 DEFINITIONS

A. Change Order: See General Specifications and Conditions of the Contract.

B. Work Directive Change: A written order to the Contractor, signed by Owner and Engineer, which amends the Contract Documents as described and authorized Contractor to proceed with a change which affects the Contract Sum or the Contract Time, for inclusion in a subsequent Change Order.

C. Field Order: A written order to the Contractor, signed by the Engineer and the Contractor, which is issued to interpret/clarify the Contract Documents, order minor changes in the work and/or memorialize trade-off agreements. The work described by a Field Order is to be accomplished without change to the Contract Sum, Contract Time, and/ or claims for other costs.

Page 135: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01153-2

1.04 PRELIMINARY PROCEDURES

A. Owner or Engineer may initiate changes by submitting a Request for Proposal (RFP) to Contractor. Request will include:

1. Detailed description of the Change, Products and location of the change in the Project.

2. Supplementary or revised Drawings and Specifications.

3. The projected time span for making the change and a specific statement as to whether overtime work is, or is not, authorized.

4. A specific period of time during which the requested price will be considered valid.

5. Such request is for information only and is not an instruction to execute the changes, or to stop work in progress.

B. Contractor may initiate changes by submitting a written notice to Engineer, containing:

1. Description of the proposed changes.

2. Statement of the reason for making the changes.

3. Statement of the effect on the Contract Sum and the Contract Time.

4. Statement of the effect on the work of separate contractors.

5. Documentation supporting any change in Contract Sum or Contract Time, as appropriate.

1.05 WORK DIRECTIVE CHANGE AUTHORIZATION

A. In lieu of a Request for Proposal (RFP), Engineer may issue a work directive change authorization for Contractor to proceed with a change for subsequent inclusion in a Change Order.

B. Authorization will describe changes in the Work, both additions and deletions, with attachments of revised Contract Documents to define details of the change and will designate the method of determining any change in the Contract Sum and any change in Contract Time.

C. Owner and Engineer will sign and date the Work Directive Change Authorization as authorization for the Contractor to proceed with the changes.

D. Contractor may sign and date the Work Directive Change Authorization to indicate agreement with the terms therein.

1.06 DOCUMENTATION OF PROPOSALS AND CLAIMS

A. Support each quotation for a lump-sum proposal and for each unit price, which has not previously been established, with sufficient substantiating data to allow Engineer to evaluate the quotation.

B. On request, provide additional data to support time and cost computations

Page 136: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01153-3

1. Labor required.

2. Equipment required.

3. Products required.

a. Recommended source of purchase and unit cost.b. Quantities required.

4. Taxes, insurance and bonds.

5. Credit for work deleted from Contract, similarly documented.

6. Overhead and profit.

7. Justification for any change in Contract Time.

C. Support each claim for additional costs and for work done on a time-and- material/force account basis, with documentation as required for a lump-sum proposal, plus additional information.

1. Name of the Owner's authorized agent who ordered the work and date of the order.

2. Dates and times work was performed, and by whom.

3. Time record, summary of hours worked, and hourly rates paid.

4. Receipts and invoices for:

a. Equipment used, listing dates and times of use.b. Products used, listing of quantities.c. Subcontracts.

1.07 PREPARATION OF CHANGE ORDERS AND FIELD ORDERS

A. Engineer will prepare each Change Order and Field Order.

B. Change Order will describe changes in the Work, both additions and deletions, with attachments of revised Contract Documents to define details of the change.

C. Change Order will provide an accounting of the adjustment in the Contract Sum and in the Contract Time.

D. Field Order will describe interpretations or clarifications of Contract Documents, order minor changes in the Work, and/or memorialize trade-off agreements.

Page 137: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01153-4

E. Field Order work will be accomplished without change in the Contract Sum, Contract Time, and/or claims for other costs.

F. Change Order and Field Order forms for Owner may be provided by the Engineer. It is the responsibility of the Contractor to provide the correct change and field orders.

1.08 LUMP-SUM/FIXED PRICE CHANGE ORDER

A. Content of Change Orders will be based on, either:

1. Engineer's Proposal Request and Contractor's responsive Proposal as mutually agreed between Owner and Contractor.

2. Contractor's Proposal for a change, as recommended by Engineer.

B. Owner and Engineer will sign and date the Change Order as authorization for the Contractor to proceed with the changes.

C. Contractor will sign and date the Change Order to indicate agreement with the terms therein.

1.09 TIME AND MATERIAL/FORCE ACCOUNT CHANGE ORDER/WORK DIRECTIVE CHANGE AUTHORIZATION

A. Engineer and Owner will issue a Work Directive Change Authorization directing Contractor to proceed with the changes.

B. At completion of the change, Contractor shall submit itemized accounting and supporting data as provided in the Article "Documentation of Proposals and Claims" of this Section.

C. Engineer will determine the allowable cost of such work, as provided in General Conditions and Supplementary Conditions.

D. Engineer will sign and date the Change Order to establish the change in Contract Sum and in Contract Time.

E. Owner and Contractor will sign and date the Change Order to indicate their agreement therewith.

F. All Time and Material Work must be documented and approved by the Project Representative on a daily basis.

1.10 CORRELATION WITH CONTRACTOR'S SUBMITTALS

A. Periodically revise Schedule of Values and Request for Payment forms to record each change as a separate item of Work, and to record the adjusted Contract Sum.

B. Periodically revise the Construction Schedule to reflect each change in Contract Time.

1. Revise sub schedules to show changes for other items of work affected by the changes.

Page 138: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01153-5

C. Upon completion of work under a Change Order, enter pertinent changes in Record Documents.

PART 2-PRODUCTS (NOT USED)

PART 3-EXECUTION (NOT USED)

**END OF SECTION**

Page 139: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01200-1

SECTION 01200 PROJECT MEETINGS

PART 1 - GENERAL

1.01 REQUIREMENTS INCLUDED

A. Engineer shall schedule and administer preconstruction meeting, periodic progress meetings, and specially called meetings throughout progress of the work.

1. Prepare agenda for meetings.

2. Distribute written notice of each meeting four (4) days in advance of meeting date.

3. Make physical arrangements for meetings.

4. Preside at meetings.

5. Record the minutes; include significant proceedings and decisions.

6. Reproduce and distribute copies of minutes within ten (10) days after each meeting.

a. To participants in the meeting.

b. To parties affected by decisions made at the meeting.

B. Representatives of contractors, subcontractors and suppliers attending meetings shall be qualified and authorized to act on behalf of the entity each represents.

1.02 PRECONSTRUCTION MEETING

A. Schedule prior to beginning of construction.

B. Location: A central site, convenient for all parties, designated by Owner.

C. Attendance:

1. Owner's Representative.2. Engineer and his professional consultants.3. Resident Project Representative.4. Contractor's Superintendent.5. Major Subcontractors.

Page 140: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01200-2

6. Major Suppliers.7. Others as appropriate.

D. Suggested Agenda:

1. Distribution and discussion of:

a. List of major subcontractors and supplies.b. Projected Construction Schedules.

2. Critical work sequencing.

3. Major equipment deliveries and priorities.

4. Project Coordination.

a. Designation of responsible personnel.

5. Procedures and processing of:

a. Field decisions.b. Proposal requests.c. Submittals.d. Change Orders.e. Applications for Payment.

6. Adequacy of distribution of Contract Documents.

7. Procedures for maintaining Record Documents.

8. Use of premises:

a. Office, work and storage areas.b. Owner's requirements.

9. Construction facilities, controls and construction aids.

10. Temporary utilities.

11. Safety and first-aid procedures.

12. Security procedures.

13. Housekeeping procedures.

Page 141: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01200-3

1.03 PROGRESS MEETINGS

A. Schedule regular periodic meetings, as required, but not less often than monthly.

B. Hold called meetings as required by progress of work.

C. Location of the meetings: Place chosen by Owner.

D. Attendance:

1. Owner's representative.

2. Engineer, and his professional consultants as needed.

3. Contractor and his subcontractors and/or suppliers as appropriate to the agenda.

4. Others as appropriate to the agenda.

E. Suggested Agenda:

1. Review, approval of minutes of previous meeting.

2. Review of work progress since previous meeting.

3. Field observations, problems, conflicts.

4. Problems that impede Construction Schedule.

5. Review of off-site fabrication, delivery schedules.

6. Corrective measures and procedures to regain projected schedules.

7. Revisions to Construction Schedule.

8. Progress, schedule, during succeeding work period.

9. Coordination of schedules.

10. Review submittal schedules; expedite as required.

11. Maintenance of quality standards.

Page 142: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01200-4

12. Pending changes and substitutions.

13. Review proposed changes for:

a. Effect on Construction Schedule and on completion date.

b. Effect on other contracts of the Project.

14. Other business.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION

Page 143: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01311-1

SECTION 01311

CONSTRUCTION SCHEDULES

PART 1-GENERAL

1.01 REQUIREMENTS INCLUDED

A. Within ten days after the effective date of the Agreement, the Contractor shall submit to the Engineer for review and acceptance an estimated progress schedule indicating the starting and completion dates of the various stages of the work.

B. Submit revised progress schedules (5 copies) monthly with his request for payment.

C. Schedules shall be coordinated with work orders issued by the Engineer through the completion of the project and any variances shall be reported.

1.02 FORM OF SCHEDULES

A. Prepare schedules in the form of a horizontal bar chart.

1. Provide separate horizontal bar for each trade or operation.

2. Horizontal time scale: Identify the first work day of each week.

3. Scale and Spacing: To allow for notations and future revisions.

4. Minimum sheet size: 8-1/2" X 11".

B. Construction Progress Schedule:

1. Show the complete sequence of construction by activity.

2. Show the dates for the beginning and completion of each major element of construction.

3. Show projected percentage of completion for each item, as of the first day of each month.

4. Show an anticipated monthly payment schedule.

C. Submittals Schedule for Shop Drawings, Product Data and Samples, show:

1. The dates for Contractor's submittals.

2. The dates approved submittals will be required from the Engineer.

1.04 PROGRESS REVISIONS

A. Indicate progress of each activity to date of submission.

B. Show changes occurring since previous submission of schedule:1. Major changes in scope.

2. Activities modified since previous submission.

Page 144: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01311-2

3. Revised projections of progress and completion.

4. Other identifiable changes.

C. Provide a narrative report as needed to define:

1. Problem areas, anticipated delays, and the impact on the schedule.

2. Corrective action recommended and its effect.

1.05 SUBMISSIONS

A. Submit initial schedules in accordance with the General Conditions.

1. Engineer will review schedules and return review copy within ten (10) days after receipt.

2. If required, Contractor shall resubmit within seven (7) days after return of review copy.

B. Submit revised progress schedules with each application for payment.

PART 2-PRODUCTS (NOT USED)

PART 3-EXECUTION (NOT USED)

**END OF SECTION**

Page 145: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01340-1

SECTION 01340SHOP DRAWINGS, PRODUCT DATA AND SAMPLES

PART 1 - GENERAL

1.01 DESCRIPTION OF REQUIREMENTS

A. Type of Submittals. This Section of the Specifications describes the procedures for submittal requirements applicable to work-related submittals, such as shop drawings, product data, samples and miscellaneous work-related submittals. It does not include the requirements for administrative submittals, which are described in another section.

B. Individual Section Requirements. The individual submittal requirements are specified in other Sections of the Specifications for each unit of work.

C. Definitions. The work-related submittals of this Section, in addition to the definitions of the General Conditions and elsewhere in the Contract Documents, are further categorized for convenience as follows:

1. Shop drawings include specially prepared technical data of all forms including drawings, diagrams, performance curves, data sheets, schedules, templates, patterns, reports, calculations, instructions, measurements and similar information not in standard printed form for application to more than one project.

2. Product data includes standard printed information on materials, products and systems, not specially prepared for this project, other than the designation of selections from among available choices printed therein.

3. Samples include both fabricated and unfabricated physical examples of materials, products and units of work, both as complete units and as smaller portions of units of work, either for limited visual inspection or (where indicated) for more detailed testing and analysis.

4. Miscellaneous submittals related directly to the work (non-administrative) include warranties, maintenance agreements, workmanship bonds, project photographs, survey data and reports, physical work records, statements of applicability, quality testing and certifying reports, copies of industry standards, record drawings, field measurement data, operating and maintenance materials, overrun stock, security/ protection/safety keys and similar information, devices and materials applicable to the work and not processed as shop drawings, product data or samples. In addition to the above requirements, the Contractor shall submit in writing to the Engineer his proposed excavation plan prior to beginning any excavation operations.

Page 146: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01340-2

1.02 GENERAL SUBMITTAL REQUIREMENTS

A. Scheduling. Where appropriate in various required administrative submittals (listings of products, manufacturers, suppliers and subcontractors, and in job progress schedule), show principal work-related submittal requirements and time schedules for coordination and integration of submittal activity with related work in each instance.

Within ten (10) days after the effective date of the Agreement, a schedule shall be submitted of the items of materials and equipment for which shop drawings are required by the specifications. For each required shop drawing, the date shall be given for intended submission of the drawing to the Engineer for review and the date required for its return to avoid delay in any activity beyond the scheduled start date. Shop drawing submittals shall be included in the critical path schedule.

B. Coordination of Submittal Times. Prepare and transmit each submittal to the Engineer sufficiently in advance of performing related work or other applicable activities, so the installation will not be delayed or improperly sequenced by processing times, including non-approval and resubmittal (if required). Coordinate with other submittals, testing, purchasing, delivery and similar sequenced activities. No extension of time will be authorized because of Contractor's failure to transmit submittals to the Engineer sufficiently in advance of the work.

C. Sequencing Requirements. As applicable in each instance, do not proceed with a unit of work until submittal procedures have been sequenced with related units of work, in a manner which will ensure that the action will not need to be later modified or rescinded by reason of a subsequent submittal which should have been processed earlier or concurrently for coordination.

D. Preparation of Submittals. Provide permanent marking on each submittal to identify project, date, Contractor, subcontractor, submittal name and similar information to distinguish it from other submittals. Show Contractor's executed review and approval marking and provide space for the Engineer's "Action" marking. Package each submittal appropriately for transmittal and handling. Submittals, which are received from sources other than through the Contractor’s office, will be returned "without action".

E. Transmittal Form. The transmittal form used to transmit submittals shall be as enclosed copy . Submittals received without this submittal form will be returned to the Contractor without action.

F. Transmittal Identification.

1. Number transmittals in sequence for each Division of the Specifications. The number after the dash indicates the Section of the Specifications, and

Page 147: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01340-3

the number before the dash is the sequence number of the transmittal (1- 15100 would be the first transmittal applicable to Section 15100 of the Specifications. The number 2-15100 would be the second transmittal for Section 15100, etc.).

2. Identify resubmittals with a letter of the alphabet following the original number, using A for the first resubmittal, B for the second resubmittal, etc. A resubmittal affecting transmittal 1-15100 would then be numbered 1A- 15100. The number 1-15100 would then be entered in the space "Previous Transmittal Number", which is left blank except on resubmittals.

G. Resubmittal. The Contractor shall be allowed to make one (1) resubmittal to address the Engineer's comments if the original submittal is returned for re- submittal. Any review of subsequent re-submittals will be considered Contractor- required engineering services and treated in accordance with the requirements of the specifications. No consideration of time extension shall be given for additional time required for review of repeated submittals.

1.03 SPECIFIC CATEGORY REQUIREMENTS

A. General. Except as otherwise indicated in the individual work sections, comply with general requirements specified herein for each indicated category of submittal. Submittals shall contain:

1. The date of submittal and the dates of any previous submittal.2. The Project title and number.3. Contract identification:4. The names of the:

a. Contractorb. Supplierc. Manufacturer

5. Identification of the product, with the Specification Section number and equipment tag numbers.

6. Field dimensions, clearly identified as such.7. Relation to adjacent or critical features of the work or materials.8. Applicable standards, such as ASTM or Federal Specification numbers.9. Notification to the Engineer in writing, at time of submission, of any

deviations in the submittals from requirements of the Contract Documents.10. Identification of revisions on resubmittals.11. An 8" x 3" blank space for Contractor and Engineer stamps.12. Contractor's stamp, initialed or signed, certifying to review of submittal,

verification of products, field measurements and field construction criteria, and coordination of the information within the submittal with requirements of the Work and of Contract Documents. Engineer's review will not proceed unless Contractor's stamp is on drawings.

13. Submittal sheets or drawings showing more than the particular item under

Page 148: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01340-4

consideration shall have all but the pertinent description of the item for which review is requested crossed out.

B. Shop Drawings. Provide newly prepared information, on reproducible sheets, with graphic information at accurate scale (except as otherwise indicated), with name of preparer (firm name) indicated. The Contract Drawings shall not be traced or reproduced by any method for use as or in lieu of detail shop drawings. Show dimensions and note which are based on field measurement. Identify materials and products in the work shown. Indicate compliance with standards and special coordination requirements. Do not allow shop drawing copies without appropriate final "Action" markings by the Engineer to be used in connection with the Work.

1. Submittal. Minimum of 9 prints are required. Each copy shall be stamped by the Contractor certifying review. Five (5) copies will be retained (2 for engineer, 3 for owner) and remainder will be returned marked with "Action" and any correction or modification (if any) as required.

2. Record Document. Of the four (4) returned copies, one is to be marked-up and maintained by the Contractor as the "Record Document". The other three (3) will be for Contractor's or vendors' use.

3. If the Contractor requires more than 3 copies returned for his (or vendors') use, additional copies beyond the nine (9) shall be submitted.

C. Product Data. Collect required data into one submittal for each unit of work or system, and mark each copy to show which choices and options are applicable to project. Include manufacturer's standard printed recommendations for application and use, compliance with standards, application of labels and seals, notation of field measurements that have been checked, and special coordination requirements. Maintain one set of product data (for each submittal) at project site, available for reference by the Engineer or others.

1. Submittals. Do not submit product data, or allow its use on the project, until compliance with requirements of Contract Documents has been confirmed by the Contractor. Submittal is for information and record, unless otherwise indicated. Initial submittal is final submittal unless returned promptly by the Engineer, marked with an "Action" which indicates an observed noncompliance. Submit nine (9) copies, four (4) of which will be returned. One set shall be kept at job site.

2. Installer's Copy. Do not proceed with installation of materials, products or systems until copy of applicable product data is in possession of installer.

D. Samples. Provide units identical with final condition of proposed materials or products for the work. Include "range" samples (not less than 3 units) where unavoidable variations must be expected, and describe or identify variations

Page 149: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01340-5

between units of each set. Provide full set of optional samples where the Engineer's selection is required. Prepare samples to match the Engineer's sample where so indicated. Include information with each sample to show generic description, source or product name and manufacturer, limitations, and compliance with standards. Samples are submitted for review and confirmation of color, pattern, texture and "kind" by the Engineer. Engineer will not "test" samples (except as otherwise indicated) for other requirements, which are the exclusive responsibility of the Contractor.

1. Submittal. At Contractor's option, provide preliminary submittal of a single set of samples for the Engineer's review and "Action". Otherwise, initial submittal is final submittal unless returned with "Action" which requires resubmittal. Submit six (6) sets of samples in final submittal; one set will be returned.

2. Quality Control Set. Maintain returned final set of samples at project site, in suitable condition and available for quality control comparisons by Engineer and by others.

1.04 DISTRIBUTION

A. General Distribution. Provide additional distribution of submittals (not included in foregoing copy submittal requirements) to subcontractors, suppliers, fabricators, installers, governing authorities and others as necessary for proper performance of the work. Include such additional copies in transmittal to the Engineer where required to receive "Action" marking before final distribution. Show such distributions on transmittal forms.

B. Review Time. Allow a minimum of fifteen (15) calendar days following receipt of submittals for the Engineer's initial processing of each submittal requiring review and response, except allow longer periods where processing must be delayed for coordination with subsequent submittals. The Engineer will advise the Contractor promptly when it is determined that a submittal being processed must be delayed for coordination. Allow two weeks for reprocessing each submittal. Advise the Engineer on each submittal as to whether processing time is critical to progress of the work, and therefore the work would be expedited if processing time could be foreshortened.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION

Page 150: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01370-1

SECTION 01370 SCHEDULE OF VALUES

PART 1 - GENERAL

1.01 REQUIREMENTS INCLUDED

A. The Contractor shall submit to the Engineer a Schedule of Values allocated to the various portions of the Work, within ten (10) days after date of Agreement.

B. Upon request of the Engineer, the Contractor shall support the values with data, which will substantiate their correctness.

C. The Schedule of Values shall be used only as the basis for the Contractor's Applications for Payment on lump sum items.

1.02 FORM AND CONTENT OF SCHEDULE OF VALUES

A. Type schedule on 8 1/2" x 11" white paper; Contractor's standard forms and automated printout will be considered for approval by Engineer upon Contractor's request. Identify schedule with:

1. Title of Project and location.2. Engineer and Project number.3. Name and Address of Contractor.4. Contract designation.5. Date of submission.

B. Schedule shall list the installed value of the component parts for each bid item of the Work in sufficient detail to serve as a basis for computing values for progress payment during construction. Component Parts will be defined as any item with a value of more than $5,000.00 or defined by trade, whichever is of less value.

C. Follow the bid sheets included in this Contract Document as the format for listing component items.

D. The sum of all values listed in the schedule shall equal each individual bid item and the total Contract Sum.

1.03 SUBSCHEDULE OF UNIT MATERIAL VALUES

A. Submit a sub-schedule of unit costs and quantities for products on which progress payments will be requested for stored products.

Page 151: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01370-2

B. The form of submittal shall parallel that of the Schedule of Values with each item identified the same as the line item in the Schedule of Values.

C. The unit quantity of bulk materials shall include an allowance for normal waste.

D. The unit values for the materials shall be broken down into:

1. Cost of the material, delivered and unloaded at the site, with taxes paid.

2. Installation costs, including Contractor's overhead and profit.

E. The installed unit value multiplied by the quantity listed shall equal the cost of that item in the Schedule of Values.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION

Page 152: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01390-1

SECTION 01390 EXCAVATION PLAN

PART 1 - GENERAL

1.01 RELATED ITEMS SPECIFIED ELSEWHERE.

Special Project ProceduresDewatering and Pressure Relief

1.02 SUBMITTALS

Prior to commencing any work, the Contractor shall submit to the Engineer for review his excavation and dewatering plans. Such review is to demonstrate that the Contractor has fulfilled the requirements of this section. Any subsequent deviation from the approved plan or amendments thereto must have the prior approval of the Engineer.

The excavation and dewatering plans shall be stamped and certified by a professional Engineer(s) registered in the State. Said Engineer(s) shall have demonstrated experience in groundwater hydraulics and steel sheet pile cofferdam design, respectively, and as applicable.

The Engineer(s) designing the excavation and dewatering plans shall have professional liability insurance of not less than $500,000.00. Proof of insurance shall be submitted with the plans in the name of the Engineer performing such designs. The submitted insurance certificate shall name City of Kenner and Rahman and Associates, Inc. as holders of the insurance certificate.

Should the design of the Contractor's dewatering plan and the cofferdams not be performed by the same Engineer, such Engineers shall coordinate their designs. Acknowledgement of the design coordination must be submitted with their design by both Engineers.

Any Engineers utilized for the design of the dewatering plan and the cofferdam design shall conform to all of the above requirements.

1.03 SAFETY REQUIREMENTS

The methods and operation outlined in the excavation plan shall comply with all local codes and laws, and authorities having jurisdiction.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION

For each site, the Contractor shall submit his proposed method of construction which shall include the methods for excavating, protection of existing utilities, dewatering and pressure relief, sheeting, shoring and bracing, and backfilling which he plans on using to perform the work included in the contract documents. The plan shall include but not be limited to:

Page 153: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01390-2

a. Type of major excavation equipment and type of equipment and method of driving sheeting (if required)

b. Sheeting, shoring and bracing plan per Section 02160c. Dewatering and pressure relief plan per Section 02140d. Hauling equipment, and proposed excavation quantitiese. Proposed haul routes of excavation and material supply equipmentf. Handling and storage of materials on siteg. Provisions for compliance with permits and regulations

The Contractor shall include in his plan a section describing aspects of the project where a modification of the proposed plan will occur due to field conditions. This shall include a detailed explanation of the methods of construction, which he plans to use in specific areas or as required by the Engineer. The Contractor shall have the excavation plan stamped and certified by a Professional Engineer registered in the State as previously specified.

The Contractor shall revise his plan when the Contractor's construction operation being used on the project changes materially from the original submittal or as required by the Engineer.

END OF SECTION

Page 154: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01400-1

SECTION 01400 QUALITY CONTROL

PART 1 - GENERAL

The Owner shall select and arrange for the service of a testing laboratory to determine that materials and workmanship comply with the requirements of these specifications.

PART 2 - PRODUCTS

Testing shall meet the requirements of all pertinent codes and regulations and selected standards as specified elsewhere in these Specifications.

PART 3 - EXECUTION

3.01 PROCESSING AND DISTRIBUTING

The Testing Laboratory shall process required copies of test reports and related instructions and distribute promptly to ensure all necessary retesting and replacement of materials with the least possible delay in progress of the work. The following copies of all reports shall be distributed:

Owner 4 CopiesEngineer 3 CopiesContractor 1 CopyMaterial Supplier 1 Copy

3.02 PAYMENT FOR TESTING SERVICES

A. The Owner will pay for all initial and routine testing services except as otherwise specified.

B. When initial tests indicate non-compliance with the Contract Documents, perform subsequent retesting occasioned by the non-compliance by the same testing labora- tory at the sole expense of the Contractor reimbursed to the Owner.

C. Inspection or testing performed exclusively for the Contractor's convenience shall be borne by the Contractor.

D. The Contractor shall pay for the concrete batch design. The Owner's approved testing laboratory will test the batch design.

E. Should scheduled testing be canceled due to negligence of the Contractor, the Contractor shall be responsible for costs associated with re-scheduling the tests. All costs associated with re-scheduling tests shall be reimbursed to the Owner.

Page 155: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01400-2

3.03 COOPERATION WITH TESTING LABORATORY

Representative of the testing laboratory shall have access to work at all times. Contractor shall provide facilities for such access in order that the laboratory may perform its functions properly.

3.04 TESTING SCHEDULE

A. The Contractor shall consult the testing laboratory in advance to determine the time required to perform the tests. Include the required time within the construction schedule.

B. When changes of the construction schedule are necessary, coordinate such changes with the testing laboratory as required.

3.05 TAKING SAMPLES

All samples for testing, unless otherwise provided elsewhere in these specifications, shall be taken by the testing laboratory. All sampling equipment and personnel shall be provided by the testing laboratory unless otherwise specified. All deliveries of samples to the testing laboratory shall be performed by the testing laboratory unless otherwise specified.

The Contractor shall promptly remove rejected articles or materials from the site of the Work after notification of rejection.

END OF SECTION

Page 156: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01410-1

SECTION 01410TESTING LABORATORY SERVICES

PART 1 - GENERAL

1.01 DESCRIPTION

A. The Owner shall select and pay for the services of an independent testing laboratory to perform inspection and tests of materials and construction as hereinafter specified and/or as specified in other sections of the plans and specifications. The Contractor shall cooperate with the laboratory to facilitate the execution of its required services. Employment of the laboratory shall in no way relieve Contractor’s obligations to perform the Work of the Contractor.

B. Related Requirements in Other Parts of these Specifications:

1. Inspections and testing required by laws, ordinances, rules, regulations, orders or approvals of public authorities: Conditions of the Contract.

C. Related Requirements Specified in Other Sections:

1. Certification of products: The respective sections of specifications.

2. Laboratory tests required, and standards for testing: Each specification section listed and as specified herein.

1.02 LABORATORY DUTIES

A. Cooperate with Engineer and Contractor; provide qualified personnel after due notice.

B. Perform specified inspections, sampling and testing of materials and methods of construction.

1. Comply with specified standards.

2. Ascertain compliance of materials with requirements of Contract Documents.

C. Immediately notify Engineer and Contractor of observed irregularities of deficiencies of work or products.

D. Notify the Engineer immediately if rain is observed during any concrete pour.

Page 157: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01410-2

E. Promptly submit written reports distributed as per paragraph 3.01. Each report shall include:

1. Date.2. Project title and number.3. Testing laboratory name, address and telephone number.4. Name and signature of laboratory inspector.5. Date and time of sampling or inspection.6. Record of temperature and weather conditions.7. Date of test.8. Identification of product and specification section.9. Location of sample or test in the project.10. Type of inspection or test.11. Results of tests and compliance with Contract Documents.12. Interpretation of test results, when requested by Architect.

F. Perform additional tests as required by Engineer or the Owner.

1.03 LIMITATIONS OF AUTHORITY OF TESTING LABORATORY

A. Laboratory is not authorized to:

1. Release, revoke, alter or enlarge on requirements of Contract Documents.2. Approve or accept any portion of the Work.3. Perform any duties of the Contractor.

B. The laboratory is authorized to reject concrete truck loads and asphalt truck loads as specified in paragraph 1.07 of this section.

1.04 CONTRACTOR’S RESPONSIBILITIES

A. Cooperate with laboratory personnel, provide access to Work, and to Manufacturer’s operations.

B. Make available, without cost, samples of all materials to be tested in accordance with applicable standard specifications. Further he shall secure and deliver to the laboratory adequate quantities of representative samples of materials proposed to be used and which require testing.

C. Provide to the laboratory the preliminary design, mixes proposed to be used for concrete, and other materials’ mixes, which require control by the test laboratory.

Page 158: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01410-3

D. Furnish copies of Products’ test reports as required.

E. Furnish such nominal labor and sheltered working space as is necessary to obtain samples at the project.

1. Provide access to Work to be tested.2. Obtain and handle samples at the project site or at the source of the product

to be tested.3. Facilitate inspections and tests.4. Provide storage and curing of tests samples.

F. Notify laboratory sufficiently in advance of operations to allow for laboratory assignment of personnel and scheduling of tests.

1. When tests or inspections cannot be performed after such notice, reimburse Owner for laboratory personnel and travel expenses incurred due to Contractor’s negligence.

2. The Contractor shall notify the testing laboratory of any concrete pour or asphalt work at least 24 hours in advance.

3. When changes of the construction schedule are necessary, coordinate such changes with the testing laboratory as required.

4. The vibration monitoring shall be done during the pile driving operations and all other construction operations which in the opinion of the Owner/Contractor may produce vibrations of the magnitude which may damage the public property. The contractor shall notify the testing laboratory of his pile driving schedule and other operations requiring vibration monitoring well in advance so as vibration monitoring can be sheduled. No pile driving can begin without testing lab and vibration monitoring equipment in place.

G. Advise the laboratory of the identity of material sources and instruct the suppliers to allow tests or inspections by the laboratory.

1.05 DESCRIPTION OF LABORATORY SERVICES

A. Test Methods: Tests and inspections shall be conducted in accordance with the requirements of these specification or, if not herein specified, in accordance with the

Page 159: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01410-4

latest standards of ASTM or other recognized authorities.

B. Test Reports: The laboratory shall promptly submit written reports to each test and inspection made to the Engineer, Contractor, suppliers of tested products, and to such other parties the Engineer may specify.

C. Rejection of Materials: The laboratory shall notify the Contractor, or his authorized representative, of any materials which are not in full conformance with the specifications, and the Engineer shall be informed of such notification.

1.06 SOIL COMPACTION

A. Soil, Sand and/or Fill - The laboratory shall test all types of soil to be compacted to determine their compliance with these specifications. Then after acceptable sand or soils are provided, the laboratory shall prepare a Modified Proctor curve for each type and make field density tests to determine if the compaction meets the requirements of the specifications.

1.07 CONCRETE AND ASPHALT

A. Mix Design - In advance of concrete or asphalt operations, materials proposed for use will be sampled and tested to determine their compliance with these specifications. Mix proportions shall be reviewed by the laboratory for each strength and type of concrete or asphalt required and reports submitted to the Architect for approval, showing the recommended mix designs.

B. Job Inspection - A representative of the laboratory on the project will check the mixing of the concrete or asphalt and conduct all field tests, such as slump determinations, temperature, etc. as applicable. This representative shall also check and report any substandard operations observed while at the job site.

C. For concrete, the laboratory shall report the quantity of water added to the truck at the site. If the quantity of water added to the truck at the site exceeds the maximum allowable in accordance with the water/cement ratio specified in the approved design mix the laboratory representative shall reject the load of concrete. The mixing truck driver shall carry with him and present to the laboratory representative documentation clearly specifying the maximum allowable quantity of water added at the site or tickets commonly referred to as “state tickets”. The documentation shall be distributed to the Engineer with the laboratory report.

D. For concrete, in addition to slump determination frequencies as specified in ASTM C172, the laboratory shall make and report a slump determination at the beginning of each truckload. The slump determination for the very first truckload of each pour shall be an actual slump determination. Remaining slump determinations in accordance with this paragraph shall be visual unless the slump is suspected to be in

Page 160: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01410-5

violation of the specified slump, in which case, an actual slump determination shall be performed.

E. For Concrete, Cylinders - For each one hundred cubic yards and/or each day’s pour or fraction thereof, four (4) test cylinders or test beams shall be cast for each different strength of concrete placed. One (1) cylinder shall be tested and reported at seven (7) days and two (2) at twenty-eight (28) days, unless otherwise directed. The last cylinder shall be retained in reserve for later testing if required. Test cylinders shall be cast for structural concrete and test beams shall be cast for paving.

F. For asphalt the laboratory shall verify the temperature of the truck and reject the load if it is not in accordance with that required and specified in ACI 301 (latest edition). Additionally, a technician shall be located at the plant to test the mix in accordance with all standard LDOTD requirements.

1.08 ADDITIONAL TESTS

The Engineer reserves the right to require additional tests to those specified or upon materials not herein specified for testing. If such tests are necessary because of apparently defective materials or workmanship, the cost of these additional tests shall be borne by the Contractor whether subsequent tests are in conformance with the Contract Documents or not.

PART 2 - PRODUCTS

Testing shall meet the requirements of all pertinent codes and regulations and selected standards as specified elsewhere in these Specifications.

PART 3 - EXECUTION

3.01 PROCESSING AND DISTRIBUTING

The Testing Laboratory shall process required copies of tests reports and related instructions and distribute promptly to ensure all necessary retesting and replacement of materials with the least possible delay in progress of the work. The following copies of all reports shall be distributed:

Owner 4 copiesEngineer 3 copiesContractor 1 copy Material Supplier 1 copy

3.02 PAYMENT FOR TESTING SERVICES

A. The Owner will pay for all initial and routine testing services except as otherwise specified.

Page 161: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01410-6

B. When initial tests indicate non-compliance with the Contract Documents, perform subsequent retesting occasioned by the non-compliance by the same testing laboratory at the sole expense of the Contractor reimbursed to the Owner (whether subsequent tests are in conformance with the Contract Documents are not).

C. Inspection or testing performed exclusively for the Contractor’s convenience shall be borne by the Contractor.

D. The Contractor shall pay for the concrete batch design.

E. Should scheduled testing be canceled or delayed due to negligence of the Contractor, the Contractor shall be responsible for costs associated with re-scheduling the tests. All costs associated with re-scheduling tests shall be reimbursed to the owner.

3.03 TAKING SAMPLES

All samples for testing, unless otherwise provided elsewhere in these specifications, shall be taken by the testing laboratory. All sampling equipment and personnel shall be provided by the testing laboratory unless otherwise specified. All deliveries of samples to the testing laboratory shall be performed by the testing laboratory unless otherwise specified.

The Contractor shall promptly remove rejected articles or materials from the site of the Work after notification of rejection.

END OF SECTION

Page 162: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01505-1

SECTION 01505 MOBILIZATION

PART 1 - GENERAL

Under this item of work, the Contractor shall set up his necessary general plant including storage areas, temporary facilities (such as sanitary) and other facilities as required by local or state law or regulation; all as required for the proper performance and completion of the Work. The Contractor shall provide all items of work covered in this section, which shall include but not be limited to the following principal items:

A. Moving on to the site of all Contractors’ plant and equipment necessary / required for immediate construction operations.

B. Installing temporary construction power, wiring, and lighting facilities.

C. Establishing fire protection system.

D. Developing construction water supply.

E. Not Used.

F. Providing on-site sanitary facilities and potable water facilities as specified.

G. Arranging for and erection of Contractor's work and storage yard. The contractor will be allowed to store only that material which is required for immediate use. The Contractor shall submit a plan for his storage/work area for the approval of the Project Engineer. Only the approved space will be allowed for the contractor’s operations.

H. Procurement and submittal of all required contractor and subcontractor insurance certificates and bonds.

I. Obtaining all required permits.

J. Posting all OSHA required notices and other information as required by Federal, State and Local Agencies. Establishment of safety programs.

K. Have the Contractor's superintendent at the job site full time.

L. Have provided a detailed construction schedule acceptable to the Owner for project use as specified.

M. Erection of project sign(s) as specified.

Page 163: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01505-2

N. Excavation Plan (See the section pertaining to "Excavation Plan" for further requirements).

O. Project Schedule - Critical Path Method (CPM) Network.

P. Misc. Submittals

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT

USED)

The Contractor may not engage in any field activities (except for surveys) until he satisfactorily submits shop drawings for critical items and has been given authorization by the Owner to proceed with field activities.

END OF SECTION

Page 164: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01510-1

SECTION 01510 TEMPORARY UTILITIES

PART 1 - GENERAL

1.01 THE REQUIREMENT

In addition to the requirements for utilities specified in other sections it shall be the Contractor's responsibility to provide plant and equipment that is adequate for the performance of the Work under this Contract within the time specified. All plant and equipment shall be kept in satisfactory operating condition, shall be capable of safely and efficiently performing the required Work, and shall be subject to inspection and approval by the Owner's representative at any time within the duration of the Contract. All work hereunder shall conform to the applicable requirements of the OSHA Standards for Construction. In addition, all work shall conform with requirements of the National Electric Code and other requirements specified in the Electrical Specifications, Division 16.

1.02 SEPARATE CONTRACTS

Whenever portions of the Work hereunder are let under separate contracts, all of the provisions of this Section shall apply to each such prime contractor, including the requirements for separate field offices and communications facilities.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION

3.01 POWER AND LIGHTING

A. Power

The Contractor shall provide, at its own expense, all necessary power required for its operations under the Contract, and shall provide and maintain all temporary power lines required to perform the Work in a safe and satisfactory manner.

B. Construction Lighting

All Work conducted at night or under conditions of deficient daylight shall be suitably lighted to insure proper Work and to afford adequate facilities for inspection and safe working conditions.

C. Approval of Electrical Connections

All temporary connections for electricity shall be subject to approval of the power

Page 165: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01510-2

company representative, and shall be removed in like manner at the Contractor's expense prior to final acceptance of the Work.

D. Separation of Circuits

Unless otherwise permitted by the Engineer, circuits separate from lighting circuits shall be used for all power purposes.

E. Construction Wiring

All wiring for temporary electric light and power shall be properly installed and maintained and shall be securely fastened in place. All electrical facilities shall conform to the requirements of Subpart K of the OSHA Safety and Health Standards for Construction.

3.02 WATER SUPPLY

A. General

The Contractor shall provide, at its own expense, an adequate supply of water of a quality suitable for construction purposes. The Contractor shall pay the water utility for water used at the job site.

B. The Contractor shall provide and operate all pumping facilities, pipelines, valves, hydrants, storage tanks, and all other equipment necessary for the adequate development and operation of the temporary water supply system. The Contractor shall be solely responsible for the adequate functioning of its water supply system and shall be solely liable for any claims arising from the use of same, including discharge or waste of water therefrom.

C. Potable Water

All drinking water on the site during construction shall be furnished by the Contractor.

D. Water Connections

The Contractor shall not make connection to, or draw water from, any fire hydrant or pipeline without first obtaining permission of the authority having jurisdiction over the use of said fire hydrant or pipeline and from the agency owning the affected water system. For each such connection made, the Contractor shall first attach to the fire hydrant or pipeline a valve and a meter, if required by the said authority, of a size and type acceptable to said authority and agency. In instances where connections are made to water pipelines for the purpose of pressure testing newly

Page 166: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01510-3

constructed force mains or sewers, a double check valve system and pressure gage shall be utilized to prevent back flow into the water main system. In addition, all such testing should be performed in the presence of Jefferson Parish Dept. of Public Utilities personnel.

E. Removal of Water Connections

Before final acceptance of the Work on the project, all temporary connections and piping installed by the Contractor shall be entirely removed, and all affected improvements shall be restored to their original condition, or better, to the satisfac- tion of the Engineer and to the agency owning the affected utility.

F. Fire Protection

The construction plant and all other parts of the Work shall be connected with the Contractor's water supply system and shall be adequately protected against damage by fire. Hose connections and hose, water casks, chemical equipment, or other sufficient means shall be provided for fighting fires in the temporary structures and other portions of the Work, and responsible persons shall be designated and instructed in the operation of such fire apparatus so as to prevent or minimize the hazard of fire. The Contractor's fire protection program shall conform to the requirements of Subpart F of the OSHA Standards for Construction.

3.03 SANITATION

A. Toilet Facilities

Fixed or portable chemical toilets shall be provided wherever needed for the use of employees. Toilets at construction job sites shall conform to the requirements of Subpart D, Section 1026.51 of the OSHA Standards for Construction.

B. Sanitary and Other Organic Wastes

The Contractor shall establish a regular daily collection of all sanitary and organic wastes. All wastes and refuse from sanitary facilities provided by the Contractor or organic material wastes from any other source related to the Contractor's operations shall be disposed of away from the site in a manner satisfactory to the Engineer and in accordance with all laws and regulations pertaining thereto. Disposal of all such wastes shall be at the Contractor's expense.

3.04 COMMUNICATIONS

A. Telephone Services

Page 167: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01510-4

The Contractor shall provide and maintain at all times during the progress of the Work, at its own expense, not less than one telephone in good working order, at its own field construction office, or, if no Contractor field office is provided, near the site of the Work included in the Contract. Each such telephone shall be connected to an established exchange for toll service and with all other telephones utilized by the Contractor.

B. Owner's Telephone

The Contractor shall also install, at its own expense, in each office provided for the use of the Owner's or Engineer's employees if required under Section entitled "Field Office", a separate telephone (separate trunk line) similarly connected to an estab- lished exchange.

C. Telephone Use

The Contractor shall permit the Engineer, the Owner, or their authorized representatives or employees free and unlimited use of said telephone facilities for all calls that do not involve published toll charges. Calls originated by the Engineer, the Owner, their authorized representatives or employees, which involve toll or message unit charges, shall be billed to the Owner by the Contractor at the rates charged by the telephone company.

3.05 SAFETY

Public Safety

During the performance of the Work the Contractor shall erect and maintain temporary fences, bridges, railings, and barriers and shall take all other necessary precautions and place proper guards for the prevention of accidents and he shall erect and maintain suitable and sufficient lights and other signals.

END OF SECTION

Page 168: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01530-1

SECTION 01530PROTECTION OF EXISTING FACILITIES AND PROPERTY

PART 1 - GENERAL

1.01 DESCRIPTION

The Contractor shall protect all existing utilities, structures and improvements not designated for removal and shall restore damaged or temporarily relocated utilities and improvements to a condition equal to or better than they were prior to such damage or temporary relocation, all in accordance with requirements specified herein, and in accordance with the requirements of the Contract Documents.

1.02 CARE AND PROTECTION OF PROPERTY

The Contractor shall be responsible for the preservation of all public and private property, and shall use every precaution necessary to prevent damage thereto. If any direct or indirect damage is done to public or private property by or on account of any act, omission, neglect, or misconduct in the execution of the work on the part of the Contractor, such property shall be restored by the Contractor, at his expense, to a condition similar or equal to that existing before the damage was done, or he shall make good the damage in another manner acceptable to the Engineer.

All sidewalks that are disturbed by the Contractor’s operations shall be restored to their original or better condition by the use of similar or comparable materials. All curbing shall be restored in a condition equal to the original construction and in accordance with the best modern practice.

Along the location of this Work all fences, walks, brushes, trees, shrubbery, and other physical features shall be protected and restored in a thoroughly workmanlike manner. Fences and other features removed by the Contractor shall be replaced in the location indicated by the Engineer as soon as conditions permit. All grass areas beyond the limits of construction that have been damaged by the Contractor shall be regraded and sodded.

Trees close to the work shall be boxed or otherwise protected against injury. The Contractor shall trim all branches that are liable to damage because of his operations, but in no case shall any tree be cut or removed without prior notification of the Engineer. All injuries to bark, trunk, limbs, and roots of trees shall be repaired by dressing, cutting, and painting according to approved methods, using only approved tools and materials.

The protection, removal, and replacement of existing physical features along the line of work shall be a part of the work under the Contract, and all costs in connection therewith shall be included in the unit and/or lump sum prices established under the items in the Proposal.

Page 169: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01530-2

1.03 OPEN EXCAVATIONS

All open excavations shall be adequately safeguarded by providing temporary barricades, caution signs, lights, and other means to prevent accidents to persons, and damage to property. The Contractor shall, at his own expense, provide suitable and safe bridges and other crossings for accommodating travel by pedestrians and workmen.

1.04 UTILITY EXPLORATION

Test pits for the purpose of locating underground pipelines or structures in advance of the construction shall be excavated and backfilled by the Contractor prior to commencement of construction. Test pits shall be backfilled immediately after their purpose has been satisfied and the surface restored and maintained in a manner satisfactory to the Engineer.

The Contractor shall determine the exact locations and depths of all utilities indicated on the drawings. In addition to those indicated, the Contractor shall make exploratory excavations of all utilities. All such exploratory excavations shall be performed as soon as practicable after award of contract and, in any event, a sufficient time in advance of construction to avoid possible delays to the Contractor's work. When such exploratory excavations show the utility location as indicated on the drawings to be in error, the Contractor shall so notify the Engineer. The number of exploratory excavations required shall be that number which is sufficient to determine the alignment of the utility.

1.05 RIGHTS-OF-WAY

The Contractor shall not do any work that would affect any oil, gas, sewer, or water pipeline; any telephone, telegraph, or electric transmission line; any fence; or any other structure, nor shall the Contractor enter upon the rights-of-way involved until the Contractor has secured authority therefore from the proper party. After authority has been obtained, the Contractor shall give said party due notice of his intention to begin work, and shall give said party convenient access and every facility for removing, shoring, supporting, or otherwise protecting such pipeline, transmission line, ditch, fence, or structure, and for replacing same. When 2 or more contracts are being executed at one time on the same or adjacent land in such manner that work on one contract may interfere with that on another, the Owner shall decide which Contractor shall progress at the same time, and in what manner. When the territory of one contract is the necessary or convenient means of access for the execution of another contract, such privilege of access or any other reasonable privilege may be granted by the Owner to the Contractor so desiring, to the extent, amount, in the manner, and at the times permitted. No such decision as to the method or time of conducting the work or the use of territory shall be made the basis of any claim for delay or damage, except as provided for temporary suspension of the work in Article 15, of the General Conditions of the Contract.

The Contractor shall be aware that his work will be performed adjacent to private property. The Contractor shall notify all property owners adjacent to and along the route once at the award of

Page 170: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01530-3

the

Page 171: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01530-4

contract and once at least 48 hrs in advance of construction by means of either a printed circular or form letter of the general details of the construction. The letter shall also include names and telephone numbers for key project personnel so that property owners can report problems. These contact telephone numbers shall be given so that appropriate personnel can be contacted 24 hours a day, seven days a week.

The Contractor shall not enter or occupy private land outside of easements, except by permission of the Owner.

1.06 PROTECTION OF STREET OR ROADWAY MARKERS AND TRAFFIC SIGNS

The Contractor shall not destroy, remove, or otherwise disturb any existing survey markers or other existing street or roadway markers without proper authorization. No pavement breaking or excavation shall be started until all survey or other permanent marker points that will be disturbed by the construction operations have been properly referenced for easy and accurate restoration. It shall be the Contractor's responsibility to notify the proper representatives of the Owner of the time and location that work will be done. Such notification shall be sufficiently in advance of construction so that there will be no delay due to waiting for survey points to be satisfactorily referenced for restoration. All survey markers or points disturbed, without proper authorization by the Engineer, will be accurately restored at the Contractor's expense after all street or roadway resurfacing has been completed. All traffic signs shall be restored to the original condition and location at the Contractor's expense.

1.07 NOTIFICATION BY THE CONTRACTOR

A. Prior to any excavation in the vicinity of any existing underground facilities, including all water, sewer, storm drain, gas, petroleum products, or other pipelines; all buried electric power, communications, or television cables; all traffic signal and street lighting facilities; and all roadway and state highway rights-of-way the Contractor shall notify the respective authorities representing the owners or agencies responsible for such facilities not less than two (2) working days (48 hours), nor more than five (5) working days prior to excavation so that a representative of said owners or agencies can be present during such work if they so desire. The Contractor shall request that each utility Owner mark (or stakeout) in the field the location of existing facilities.

1.08 CONFLICTS WITH OTHER UTILITIES

A. At various locations along the project, the proposed pipeline may closely parallel or cross existing gas lines, buried telephone cables or ducts or other utilities.

B. It shall be the Contractor's responsibility to give the appropriate utility company sufficient advance notice so that their representatives may verify the utility location

Page 172: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01530-5

on the job site when trenching operations begin. The Contractor shall coordinate and cooperate with these utilities to insure that no damages occur that would cause interruption of their services.

C. All temporary support, or minor adjustment which does not require replacement or direct by-pass connections to these existing services (such as all direct-buried telephone cables or two-inch and smaller gas lines) will be the responsibility of the Contractor.

D. Where it may be necessary to relocate or de-energize or re-energize electrical power lines (aerial or buried), gas mains or telephone ducts (defined here as gas lines larger than 2-1/2 inches and telephone cables within ductwork) to allow construction of the new sewerage facilities, or where major relocation of small services requires re- placement or performing connections to the existing lines, all such relocation work must be performed by the respective utility companies personnel, unless written authorization is given to Contractor by utility to perform such work. The Contractor shall immediately notify the proper utility company and the Engineer in writing of the occurrence and location of such required relocations. Any costs associated with this work shall be paid by the Contractor.

E. The Owner will not be responsible for any delay or inconvenience to the Contractor resulting from the existence, removal or adjustment of any utility. Additional costs incurred as a result therefore shall be the expense of the Contractor, and considered as included in the contract bid.

F. Relocation, or re-alignment of storm drains or sewer lines which may interfere with the construction of the new pipe line shall be the responsibility of the Contractor.

G. The Contractor shall remove and replace storm drains and sewers to facilitate pipeline constructions where required.

H. Maintenance of Drainage. Contractor shall be responsible for maintenance of existing drainage patterns by temporary ditches, culverts, etc. All existing drainage facilities shall be returned to original condition prior to completion of contract.

I. The Contractor is ultimately responsible for any construction costs arising from conflicts with other utilities associated with the necessary removal, relocation, or temporary re-routing of all such utilities. All such costs shall be considered incidental to the construction of the facilities shown or indicated in the Contract Documents and shall be included in the lump sum or unit price bid item as applicable.

Page 173: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01530-6

J. Adjustments to existing water or sewer house connections shall be made by the contractor in the case of a conflict which occurs at an elevation between the top and bottom of the proposed utility, or if directed in the field by the engineer. The Contractor shall adequately restore the house connections without work on the private property and without syphons in case of the sewer house connection.

K. Any adjustments to water service house connections shall be made using 3/4" diameter polyethylene tubing PE-3408.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION

3.01 EXISTING UTILITIES AND IMPROVEMENTS

A. General

The Contractor shall protect all utilities and other improvements which may be impaired during construction operations. It shall be the Contractor's responsibility to ascertain the actual location of all existing utilities and other improvements indicated on the drawings that will be encountered in his construction operations and to see that such utilities or other improvements are adequately protected from damage due to such operations. The Contractor shall take all possible precautions for the protection of unforeseen utility lines to provide for uninterrupted service and to provide such special protection as may be directed by the Engineer.

B. Utilities to be Moved

In case it shall be necessary to move the property of any public utility or franchise holder, such utility company or franchise holder will, upon proper application by Contractor, be notified by the Contractor to move such property within a specified reasonable time, and the Contractor shall not interfere with said property until after the expiration of the time stipulated.

C. Owner's Right of Access

The right is reserved to the Owner and to the owner's of public utilities and franchises to enter at any time upon any public street, alley, right-of-way, or easement for the purpose of making changes in their property made necessary by the work of this Contract.

Page 174: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01530-7

D. Known Utilities

Existing utility lines that are shown on the drawings or the locations of which are made known to the Contractor prior to excavation and that are to be retained, and all utility lines that are constructed during excavation operations shall be protected from damage during excavation and backfilling and, if damaged, shall be immediately, repaired by the Contractor at its expense.

E. Unknown Utilities

The Contractor is required to use care in preparing excavations and shall conduct Utility Explorations including utility excavations and field investigations to assess the layout of subsurface facilities at each excavation site prior to the commencement of work. The Contractor shall uncover subsurface obstructions in advance of construction so that existing subsurface facilities may be identified before the work reaches the obstruction. The Contractor shall proceed at all times with caution while excavating.

Should the Contractor encounter subsurface and/or latent conditions at the site substantially different from those shown on the Drawings or indicated in the Specifications, he shall immediately give notification to the Engineer of such conditions. The Engineer shall thereon promptly investigate the conditions and if he finds that they are substantially different from those shown on the Plans or Specifications, he shall make such changes in the Plans and/or Specifications as he may find necessary. Any increase or decrease in the cost resulting from these changes when appropriate shall be adjusted under the applicable provisions of the contract documents.

F. Utilities to be Removed

When utility lines that are to be removed are encountered within the area of operations, the Contractor shall notify the Utility Owner and the Engineer a sufficient time in advance for the necessary measures to be taken to prevent interruption of the service.

G. Approval of Repairs

All repairs to a damaged improvement shall be inspected and approved by an authorized representative of the improvement owner before being concealed by backfill or other work.

Page 175: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01530-8

H. Relocation of Utilities

Where the proper completion of the work requires the temporary or permanent removal and/or relocation of an existing utility or other improvement which is shown on the drawings, the Contractor shall at its own expense and with prior approval from the Owner of the utility, remove and, without unnecessary delay, temporarily replace or relocate such utility or improvement in a manner satisfactory to the Owner of the facility. In all cases of such temporary removal or relocation, restoration to former location shall be accomplished by the Contractor in a manner that will restore or replace the utility or improvement as nearly as possible to its former locations and to as good or better condition than found prior to removal.

I. Maintaining in Service

All oil and gasoline pipelines, power, and telephone or other communication cable ducts, gas and water mains, irrigation lines, sewer lines, storm drain lines, poles, and overhead power and communication wires and cables encountered along the line of the work shall be maintained continuously in service during all the operations under the Contract, unless other arrangements are made satisfactory to the Owner of said pipelines, duct, main, irrigation line, sewer, storm drain, pole, or wire or cable. The Contractor shall be responsible for and shall make good all damage due to its operations, and the provisions of this Section shall not be abated even in the event such damage occurs after backfilling or is not discovered until after completion of the backfilling.

3.02 SEWER HOUSE CONNECTIONS

A. The location and elevations of sewer house connections generally are not shown on the plans. However, the Contractor shall locate them at the trench prior to installation of the proposed utility. The Contractor shall excavate in advance of the utility, locate the sewer house connections and make the necessary adjustments to the force main if any conflict is anticipated.

B. The Contractor shall maintain at all times sewer service to all connections in his route.

C. If a conflict exists between the required utility and sewer house connections, the Contractor shall attempt to resolve such conflict with deflection of the required utility (within allowable limits) and/or vertical offset of the utility (requires engineer's approval) and/or relaying the house connections. In all cases a positive slope must be maintained on the house connection. No siphoning shall be allowed. No work on the private property shall be allowed.

Page 176: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01530-9

D. The limits of work for removal and replacement of any sewer house connection is to the limits of the property line.

E. Bedding and backfill requirements of house connections will be the same as those for proposed pipelines, or per the standards of the owning utility authority if none is shown. All adapters, connections, repair material, etc., shall conform to the requirements of the appropriate utility owner.

3.03 WATER HOUSE CONNECTIONS

A. The location and elevations of water house connections generally are not shown on the plans. However, the Contractor shall locate them at the trench prior to installation of the proposed utility. The Contractor shall excavate in advance of the proposed utility, locate the water house connections and make the necessary adjustments to the proposed utility if any conflict is anticipated.

B. The Contractor shall maintain at all times water service to all connections in his route.

C. If a conflict exists between the required utility and water house connections, the Contractor shall attempt to resolve such conflict with deflection of the piping (within allowable limits) and/or vertical offset of the proposed utility (requires engineer's approval) and/or relaying the water house connections.

D. The limits of work for removal and replacement of any water house connection is to the limits of the property line.

E. Bedding and backfill requirements of water house connections will be the same as those for the proposed utility pipeline or per the utility Owner's standards if none is shown. All adapters, connections, repair material, etc., shall conform to the requirements of the appropriate utility owner.

3.04 SUBSURFACE OBSTRUCTIONS

A. The Contractor shall field determine before pipeline trench and associated excavations are begun the depth and location of existing utilities. Utility locations indicated on the plans were obtained from the records available, but have not been field verified, nor have depths been measured or observed. The Contractor shall submit descriptions, depths and locations of subsurface obstructions to the Engineer for review at the time it is determined that obstructions exist before or after excavation.

Page 177: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01530-10

B. In excavation, backfilling and in laying pipe, care shall be taken not to remove, disturb, or injure existing pipes, conduits or structures. If necessary, the Contractor at his own expense, shall sling, shore-up, and maintain such structures in operation.

C. The Contractor shall obtain the permission of and give sufficient notice to the proper authorities of their intention to remove or disturb any pipe, conduit, etc., and shall abide by their regulations governing such work.

D. In the event that subsurface structures are broken or damaged in the prosecution of the Work, the Contractor shall immediately notify the proper authorities and the Engineer, and at the option of said authority, either repair the damage at once, at his own expense, or pay the proper charges for repairing said damage. Repairs shall be made to the satisfaction of the Owner. The Contractor shall be responsible for any damage to persons or property caused by such breaks or due to his own neglect in reporting and/or repairing such damages.

E. In the event that a conflict with an existing sewer or water service house connection occurs at an elevation between the top and bottom of the proposed utility, the contractor shall make the necessary adjustment to the existing service as shown on the plans or specified herein. Proper notification must be given to the property owner before the adjustment is begun.

3.05 TREES AND SHRUBS WITHIN STREET RIGHTS-OF-WAY AND PROJECT LIMITS

A. General

The Contractor shall exercise all necessary precautions so as not to damage or destroy any trees or shrubs, including those lying within street rights-of-way and within or outside the project limits, and shall not trim, remove or relocate any trees unless such trees have been approved for trimming, removal or relocation by the Engineer and the jurisdictional agency or Owner. All existing trees and shrubs which are damaged during construction due to Contractor’s negligence shall be trimmed, replaced, or relocated by a certified tree company under permit from the jurisdictional Agency or Owner. Tree trimming, replacement, and relocation shall be accomplished in accordance with the following paragraphs. The cost of such work shall be considered incidental to the construction of the facilities proposed and no direct payment will be made. (See Section 02100 “Site Preparation”)

Page 178: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01530-11

B. Preserve

Contractor shall take extra measures to protect trees designated to be preserved, such as erecting barricades, trimming to prevent damage from construction equipment, and installing pipe and other Work by means of hand excavation or tunneling methods. Such trees shall not be endangered by stockpiling excavated material or storing equipment against trunk.

C. Trimming

Symmetry of the tree and shrubs shall be preserved; no stubs or splices or torn branches left; clean cuts shall be made close to trunk or large branch. Spikes shall not be used for climbing live trees. All cuts over 1-1/2 inches in diameter shall be coated with an asphaltic emulsion material.

D. Relocate

Contractor shall remove existing trees and shrubs which conflict with the construction as indicated on the plans and specifications. Damaged trees and shrubs due to contractor’s negligence maybe relocated at the Contractor’s expense as directed by the Engineer and the Owner.

E. Replacement

The Contractor shall immediately notify the jurisdictional agency and/or the Owner if any tree or shrub is damaged by the Contractor's operations. If, in the opinion of said agency or the Owner, the damage is such that replacement is necessary, the Contractor shall replace the tree or shrub at its own expense. The tree or shrub shall be of a like size and variety as the one damaged, or, if of a smaller size, the Contractor shall pay to the Owner of said tree a compensatory payment acceptable to the tree owner, subject to the approval of the Engineer and the jurisdictional agency or Owner.

F. LDOTD Right of Way

Trees within the LDOTD Right of Way may be removed and not replaced.

3.06 POLE RELOCATION AND PROTECTION

A. The Contractor shall take notice of any power, telephone and traffic signal support poles along the length of the project; several may be in proximity to, or direct conflict with, the alignment of the proposed facilities. The relocation of all poles on the plans

Page 179: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01530-12

noted as to be relocated shall be the responsibility of and must be performed by the respective utility companies. The Contractor shall immediately notify the proper utility company and the Engineer in writing of the occurrence and location of such required relocations.

B. For all poles without such notations, it is intended that they shall be supported with mud jackets or by other means of bracing as required by the utility company to maintain them in a stable condition. The temporary support and subsequent stability of these poles will be the Contractor's responsibility.

C. These tasks shall be performed by Contractor at no direct payment.

3.07 EXISTING FENCE LINES AND GATES

At various locations along the length of the project, existing fences and gates might conflict with, or impair construction operations for the installation of the proposed facilities. Contractor shall protect these fences in place where they do not conflict with construction operations. Where a fence or gate may conflict with the backswing of machinery or otherwise impede construction, the Contractor shall contact the owner and arrange for the temporary removal or relocation of the fence. Any fence or gate removed or temporarily relocated shall be restored to its original condition and location unless otherwise indicated on the plans or arranged with owners of the fence. Where it is impossible to salvage the existing materials to reconstruct the fence or gate, the fence shall be replaced "in kind".

END OF SECTION

Page 180: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01600-1

SECTION 01600 MATERIAL AND EQUIPMENT

PART 1 - GENERAL

1.01 REQUIREMENTS

All materials and equipment furnished and installed under this contract shall conform to the general stipulations set forth in this section except as otherwise specified in other sections of the specifications.

1.02 WORKMANSHIP AND MATERIALS

Contractor shall guarantee all equipment against faulty or inadequate design, improper assembly or erection, defective workmanship or materials, and leakage, breakage or other failure. Materials shall be suitable for service conditions.

All equipment shall be designed, fabricated, and assembled in accordance with the best modern engineering and shop practice. Individual parts shall be manufactured to standard sizes and gauges so that repair parts furnished at any time, can be installed in the field. Like parts of duplicate units shall be interchangeable. Equipment shall not have been in service at any time prior to delivery, except as required by tests.

Except where otherwise specified, structural and miscellaneous fabricated steel used in equipment shall conform to AISC standards. All structural members shall be designed for shock or vibratory loads. Unless otherwise specified, all steel which will be submerged, all or in part, during normal operation of the equipment shall be at least 1/4 inch thick.

1.03 RESPONSIBILITY FOR MATERIALS AND EQUIPMENT

Contractor shall be fully responsible for all materials and equipment, which he has furnished, and shall furnish necessary replacements at any time prior to expiration of the Correction Period.

The Contractor shall stock additional supplies of material and equipment, as the Contractor deems necessary for timely and efficient execution of this contract.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION

Page 181: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01610-1

SECTION 01610 TRANSPORTATION AND HANDLING

PART 1 - GENERAL

All materials shall be suitably packaged to facilitate handling and protection against impact, abrasion, discoloration, and other damage. All painted surfaces that are damaged prior to acceptance of equipment shall be repainted to the satisfaction of Engineer.

Each item, package, or bundle of material shall be tagged or marked as identified in the delivery schedule or on the Shop Drawings. Complete packing lists and bills of material shall be included with each shipment.

The Contractor is responsible for transporting all Owner-furnished items from their stored locations to the appropriate jobsite.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION

Page 182: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01620-1

SECTION 01620 STORAGE AND PROTECTION

PART 1 – GENERAL

1.01 STORAGE

Contractor shall be responsible for providing off-site storage agreements. This work shall be considered a subsidiary obligation of the Contractor and all costs in connection therewith shall be included in the unit price or lump sum price items bud. Off-site storage arrangements shall be acceptable to Owner for all materials and equipment not incorporated into the work but included in Applications for Payment. Such off-site storage arrangements shall be presented in writing, and shall afford adequate and satisfactory security and protection. Off-site storage facilities shall be accessible to Engineer.

Contractor will be permitted a limited use of available land belongings to Owner (upon written permission), on or near the site of the Work, for construction purposes and for the storage of materials and equipment. The storage of material on site shall be limited to only the material which shall be used in a day or two days. The location and extent of the areas so used shall be as indicated on the Drawings or as directed by the Engineer.

1.02 SHOP PAINTING

All steel and iron surfaces shall be protected by suitable paint or coatings applied in the shop as specified in the special coating section. Surfaces, which will be inaccessible after assembly, shall be protected for the life of the equipment. Exposed surfaces shall be finished smooth, thoroughly cleaned, and filled as necessary o provide a smooth uniform base for painting. Surfaces to be painted after installation shall be shop painted with at least two coats of a primer that will adequately protect the equipment until finish coats are applied. Electric motors, speed reducers, starters, and other self-contained or enclosed components shall be shop finished with a high grade oil-resistant enamel as long as it does not interfere with operation of the component parts. Coatings shall be suitable for the environment where equipment is installed.

1.03 LUBRICATION

Equipment shall be adequately lubricated by systems that require attention no more frequently than weekly during continuous operation. Lubrication systems shall not require attention during startup or shutdown and shall not waste lubricants.

Lubricants of the type recommended by the equipment manufacturer shall be provided in sufficient quantity to fill lubricant reservoirs and to replace all consumption during testing, startup, and operation prior to acceptance of equipment by Owner.

Lubrication facilities shall be convenient and accessible.

Page 183: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01620-2

1.04 BOLTS

Equipment suppliers shall furnish suitable bolts for each item of equipment. Anchor bolts if required together with templates or setting drawings, shall be delivered sufficiently early to permit setting the anchor bolts when the structural concrete is placed. Bolts shall comply with the requirements specified in other sections.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION

Page 184: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

1630-1

SECTION 01630PRODUCT OPTIONS AND SUBSTITUTIONS

PART 1 - GENERAL

In accordance with applicable state Contractor Statutes, these Contract Documents include provisions for use of equivalent materials and equipment. Requests for review of equivalency shall be submitted in accordance with the Supplemental Conditions, General Conditions and the submittals section.

Other manufacturer's products will be accepted provided sufficient information is submitted to allow Engineer to determine that the products proposed are equivalent to those named. Such items shall be submitted for review by the procedures set forth in the submittals section.

Whenever the names of proprietary products or the names of particular manufacturer's or vendors are used, it shall be understood that the words "or equal" following the enumeration, if not specifically stated, are implied.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION

Page 185: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

1730-1

SECTION 01700 DEMOBILIZATION

PART 1 - GENERAL

1.01 FINAL CLEANUP

The Contractor shall promptly remove from the vicinity of the completed work, all rubbish, construction debris, unused materials, concrete forms, construction equipment, and temporary structures and facilities used during construction. Final acceptance of the Work by the Owner will be withheld until the Contractor has satisfactorily complied with the foregoing requirements for final cleanup of the project site.

1.02 CLOSEOUT TIMETABLE

The Contractor shall establish dates for equipment and system testing, acceptance periods, and on- site instructional periods as required under the Contract. Such dates shall be established not less than two (2) weeks prior to beginning any of the foregoing items, to allow the Owner, the Engineer, and their authorized representatives sufficient time to schedule attendance at such activities.

1.03 FINAL SUBMITTALS

A. After all work is complete, any necessary changes in the Contract Price will be determined, and the necessary adjustments, if any, will be incorporated into a final Change Order. Upon satisfactory completion of closeout activities, Contractor shall submit the Application for Final Payment as provided in the General and Supplementary Conditions.

B. The Contractor, prior to requesting final payment, shall obtain and submit the following items to the Engineer for transmittal to the Owner:

1. Written guarantees, where required.

2. Operating manuals and instructions.

3. Keying schedule.

4. Maintenance stock items, spare parts; special tools.

5. Completed record drawings.

6. Bonds for materials, maintenance, etc, as required.

Page 186: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01700-2

7. Certificates of inspection and acceptance by local and State governing agencies having jurisdiction.

8. Releases from all parties who are entitled to claims against the subject project, property, or improvement pursuant to the provisions of law.

1.04 MAINTENANCE AND GUARANTEE

A. The Contractor shall comply with the maintenance and guarantee requirements of the General Conditions.

B. Replacement of earth fill or backfill, where it has settled below the required finish elevations, shall be considered as a part of such required repair work, and any repair or resurfacing constructed by the Contractor which becomes necessary by reason of such settlement shall likewise be considered as a part of such required repair work unless the Contractor shall have obtained a statement in writing from the affected private owner or public agency releasing the Contractor from further responsibility in connection with such repair or resurfacing.

C. The Contractor shall make all repairs and replacements promptly upon receipt of written order from the Owner. If the Contractor fails to make such repairs or replace- ments promptly, the Owner reserves the right to do the Work and Contractor and his surety shall be liable to the Owner for the cost thereof.

1.05 BOND

A. The Contractor shall provide a bond to guarantee performance of the provisions contained in Paragraph "Maintenance and Guarantee" above, and the General Conditions.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION

Page 187: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01720-1

SECTION 01720 PROJECT RECORD DOCUMENTS

PART 1 - GENERAL

1.01 DESCRIPTION

The Contractor shall maintain at the site for the Owner's permanent records one copy of:

1. Drawings.2. Specifications.3. Addenda.4. Change Orders and other Modifications to the Contract.5. Engineer Field Orders or Written Instructions.6. Approved Shop Drawings, Product Data.7. Field Test Records.8. Construction Photographs.9. As-Built Survey of Gravity Sewer and Sewer Force Main, including all utilities

encountered.

1.02 RELATED WORK SPECIFIED

ELSEWHERE Submittals

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION

3.01 MAINTENANCE OF DOCUMENTS AND SAMPLES

A. The Contractor shall store documents and samples in Contractor's field office apart from documents used for construction.

B. The Contractor shall provide files and racks for storage of documents.

C. The Contractor shall maintain documents in a clean, dry, legible condition and in good order. Do not use record documents for construction purposes.

D. The Contractor shall make documents and samples available at all times for inspection by the Engineer and Owner.

3.02 MARKING-UP RECORD DRAWINGS

The Contractor shall mark with red erasable pencil and, where necessary, use other pencil colors, as required.

Page 188: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01720-2

3.03 RECORDING

A. Label each document (including record prints and shop drawings) "PROJECT RECORD" in neat large printed letters.

B. Record information concurrently with construction progress. Do not conceal any work until required information is recorded.

C. Drawings

Legibly mark field drawings to record actual construction:

1. Location of internal utilities and appurtenances concealed in the construction, referenced to visible and accessible features of the structure.

2. Field changes of dimensions and details.

3. Changes made by Field Order by Change Order.

4. Details not on original Contract Drawings.

D. Specifications and Addenda

The Contractor shall legibly mark each Section to record:

1. Manufacturer, trade name, catalog number and supplier of each product and item of equipment actually installed.

2. Changes made by Field Order or by Change Order.

3.04 AS-BUILT SURVEY

The Contractor shall maintain an "as-built" survey showing the precise location of the installed sewer force main and any other utilities encountered or relocated, as described in other sections of these Specifications.

3.05 SUBMITTALS

A. At Contract close-out deliver Record Documents to the Engineer including marked- up Drawings, As-Built Survey, Specifications, Addenda, Change Orders and other modifications to Contract; Engineers Field Orders and Written Instructions, Approved Shop Drawings, Product Data, Field Test Records and any other documents which serve as a record of actual field installation and construction different from the original Contract Documents. Engineer will submit them to Owner.

Page 189: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01720-3

B. Accompany submittals with transmittal letters in duplicate, containing:

1. Date2. Project title and number3. Contractor's name and address4. Title and number of each Record Document5. Signature of Contractor or his authorized representative.

END OF SECTION

Page 190: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

01740-1

SECTION 01740 WARRANTIES AND BONDS

PART 1 - GENERAL

1.01 Contractor shall maintain and keep in good repair the improvements covered by these Drawings and Specifications during the life of the Contract.

1.02 Contractor shall indemnify the Owner against any repairs which may become necessary to any part of the work performed and to items of equipment and systems procured for or furnished under this Contract, arising from defective workmanship or materials used therein, for a period of one (1) year from the date of final acceptance of the Work by the Owner.

1.03 The Contractor shall, at his own expense, furnish all labor, materials, tools and equipment required and shall make such repairs and removals or shall perform such work or reconstruction as may be made necessary by structural or functional defect or failure resulting from neglect, faulty workmanship or faulty materials, in any part of the Work performed by him.

1.04 Except as noted on the Drawings or as specified, return structures such as embankments and fences to their original condition prior to the completion of the Contract. Repair damage to facilities not designated for removal, resulting from the Contractor's operations, at no cost to the Owner.

1.05 The Contractor shall be responsible for all road, entrance and driveway reconstruction and repairs and maintenance of same for a period of one year from the date of such reconstruction. In the event the repairs and maintenance are not made immediately and it becomes necessary for the Owner of the road to make such repairs, the Contractor shall reimburse the Owner of the road for the cost of such repairs.

1.06 In the event the Contractor fails to proceed to remedy the defects of which he has been notified within 15 days of the date of such notice, the Owner reserves the right to cause the required materials to be procured and the work to be done, as described in the Drawings and Specifications, and to hold the Contractor and the sureties on his bond liable for the cost and expense thereof.

1.07 All warranties, bonds, insurance, etc. shall provide for 30-day advance notice to the Owner prior to cancellation or renewal date. No payment will be made to the Contractor for any work without insurance and bonds being in effect.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION

Page 191: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

02100-1

SECTION 02100 SITE PREPARATION

PART 1- GENERAL

1.01 SCOPE OF WORK

A. The Contractor shall clear and grub all of the area within the limits of construction or as required, which includes, but is not limited to, utility easements (servitudes). The width of the area to be cleared shall be reviewed by the Engineer prior to the beginning of any clearing.

B. The Contractor’s attention is directed to any Soil Erosion and Sediment Control Ordinances in force in the Parish. The Contractor shall comply with all applicable sections of these ordinances.

1.02 SITE AND WORK DESCRIPTION

Any areas damaged by the Contractor shall be filled, graded, watered, seeded and fertilized at no direct cost. Contractor shall perform this repair work immediately after being instructed by the Engineer.

PART 2- PRODUCTS (NOT USED)

PART 3- EXECUTION

3.01 PRESERVATION OF DEVELOPED PRIVATE PROPERTY

A. The Contractor shall exercise extreme care to avoid unnecessary disturbance of developed private property along the route of the construction.

B. Improvements to the land, such as fences, walls, outbuildings, and other structures which of necessity must be removed, shall be replaced with equal quality materials and workmanship.

C. The Contractor shall clean up the construction site adjacent to developed private property directly after construction is completed, upon approval of the Engineer.

3.02 PRESERVATION OF PUBLIC PROPERTY

The appropriate paragraphs of Articles 6.11 of these specifications shall apply to the preservation and restoration of public lands, parks, rights-of-way, easements, servitudes, and all other damaged areas.

END OF SECTION

Page 192: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

02110-1

SECTION 02110SALVAGE OR ABANDONMENT OF EXISTING MATERIALS

PART 1- GENERAL

1.01 SCOPE OF WORK

This section covers the salvage or abandonment of found materials and/or existing materials and equipment.

PART 2- PRODUCTS (NOT USED)

PART 3- EXECUTION

3.01 DESCRIPTION

All materials found shall be removed and shall be salvaged and/or disposed of as specified herein. The entire site shall be graded to match adjacent ground surface and restored in accordance with these specifications.

A. Existing materials and equipment designated by the Engineer as salvageable items which are removed, shall remain Owner’s property, including (but not limited to) pumps, motors, all piping, valves and fittings, etc. Any items, which are not designated as salvageable by the Engineer, shall be removed and disposed of by the Contractor at no cost to the Owner.

B. Contractor shall carefully remove in a manner to prevent damage all materials and equipment specified or indicated to be salvaged or to remain property of Owner

C. Salvaged items shall be removed and delivered to the Owner by Contractor in good condition to a location designated by the Engineer.

D. Any items damaged in removal, storage or handling through carelessness or improper procedures shall be replaced by Contractor in kind or with new items. Any damaged or disturbed area shall be backfilled, compacted, watered, seeded, and fertilized. It shall be finish-graded for positive drainage to the satisfaction of the Engineer.

3.02 PRESERVATION OF PUBLIC PROPERTY

The appropriate paragraphs of section 01530 of these specifications shall apply to the preservation and restoration of public lands, parks, rights-of-way, easements, servitudes, and all other damaged areas.

END OF SECTION

Page 193: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

02120-1

SECTION 02120REMOVAL OF STRUCTURES AND OBSTRUCTIONS

PART 1- GENERAL

1.01 SCOPE OF WORK

This work consists of removal and satisfactory disposal of all structures, culverts, drain line, drain inlets and manholes, and other structures and obstructions not designated or permitted to remain.

PART 2- PRODUCTS (NOT USED)

PART 3- EXECUTION

3.01 DESCRIPTION

All work under this section shall be performed under directions by the project engineer/owner. No work for removal of structures and obstruction will be made until a cost for removal has been agreed to with the project engineer.

END OF SECTION

Page 194: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

02140-1

SECTION 02140

DEWATERING AND PRESSURE RELIEF

PART 1 - GENERAL

1.01 SCOPE

This section shall include supplying materials, equipment, services, and labor necessary to prevent surface water and subsurface or groundwater from flowing into excavations and from flooding project site and surrounding area. The Contractor shall dewater and dispose of the water so as not to cause injury to public or private property, or to cause a nuisance or a menace to the public. It shall be the sole responsibility of the Contractor to have adequate equipment and personnel at the site at all times to comply with these requirements.

1.02 RELATED WORK SPECIFIED ELSEWHERE

A. Section 01390: Excavation Plan.

B. Section 02221: Excavation, Backfilling for trenches, paving and structures

1.03 SUBMITTALS

Prior to beginning dewatering operations, and as a part of the excavation plan, the Contractor shall submit, in writing to the Engineer, his proposed plan to comply with the requirements of this section. Submittal shall contain proposed equipment, methods of conveyance, and discharge point for water removed from excavations. It shall also include a plan for settlement monitoring by the Contractor. Dewatering calculations in the dewatering plan shall be prepared and stamped by a Professional Engineer registered in the State of Louisiana. Engineering calculations to be submitted by the Contractor shall include, among other calculations, radius of influence and drawdown curves.

Settlement adjacent to the excavation should be expected to occur if pressure relief or dewatering lowers the ground water below its current level. Estimates of settlement are highly dependent upon the quality and duration of dewatering and pressure relief. They are also dependent on the depth of excavation and pressure relief requirements as necessitated by site conditions. For these reasons, actual settlement estimates should be made once actual methods are developed. The actual settlement from dewatering and pressure relief should be monitored by elevation control stations during construction.

PART 2 - PRODUCTS (NOT USED)

Page 195: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

02140-2

PART 3 - EXECUTION

3.01 INSTALLATION

A. The Contractor shall install all equipment necessary for dewatering. He shall have on hand, at all times, sufficient pumping equipment and machinery in good working condition and shall have available, at all times, competent workmen for the operation of the pumping equipment. Adequate standby equipment shall be kept available at all times to insure efficient dewatering and maintenance of dewatering operation during power failures.

B. The Contractor is responsible for providing whatever equipment is necessary to adequately dewater the sites in accordance with the requirements of this section, should that equipment be wells, wellpoints, sump pumps or other operations.

3.02 PERFORMANCE

The control of groundwater shall be such that softening of the bottom of excavations or formation of unstable conditions during excavation shall be prevented. Dewatering systems shall be designed and operated to prevent erosion of the natural soils. Care shall be taken to prevent disturbance, due to the method of dewatering, of pipe bedding already in place in the trench. The Contractor is fully responsible for maintaining the integrity of previously placed pipe and bedding during dewatering and the release of groundwater.

During excavation, construction of structures, installation of pipelines and sewers, placement of the structure and trench backfill, and the placing and setting of concrete, excavations shall be kept free of water. The Contractor shall control surface runoff to prevent entry or collection of water in excavations. The static water level shall be controlled in the vicinity of the excavation to maintain the undisturbed state of the foundation soils and allow the placement of any fill or backfill to the required density. The dewatering system shall be installed and operated so that the groundwater level outside the excavation is not altered to an extent that would damage or endanger adjacent structures or property.

3.03 RELEASE OF GROUNDWATER

The release of groundwater to its static level shall be performed in such a manner as to maintain the undisturbed state of the natural foundation soils, prevent disturbance of compacted backfill and prevent flotation or movement of structures, pipelines, and sewers.

3.04 PAYMENT

All work in this section shall be considered a subsidiary obligation of the Contractor and all costs in connection therewith shall be included in the unit price or lump-sum price items bid.

Page 196: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

02140-3

END OF SECTION

Page 197: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

02160-1

SECTION 02160 SHEETING, SHORING, AND BRACING

PART 1 - GENERAL

1.01 SCOPE

This section shall include supplying materials, services, and labor necessary to provide sheeting, shoring, and bracing or supports as required to provide a safe working condition for Contractor's personnel and to provide for protection of utilities, buildings, and structures. It shall be the sole responsibility of the Contractor to comply with these requirements.

1.02 RELATED WORK SPECIFIED ELSEWHERE

A. Section 01390: Excavation Plan

B. Section 02140: Dewatering and Pressure Relief

C. Section 02221: Excavation and Backfilling for Trenches, Pavement and Structures.

1.03 SUBMITTALS

Prior to beginning sheeting and shoring operations, and as a part of the excavation plan, the Contractor shall submit, in writing to the Engineer, his proposed plan to comply with the requirements of this Section. The plan is to be prepared and stamped by a qualified Louisiana licensed engineer. The Contractor is solely responsible to design, provide, install and maintain support systems required to complete the work in a continuous safe manner. No excavation work shall be allowed to commence until the Contractor has fulfilled this requirement.

1.04 SAFETY REQUIREMENTS

All sheeting, shoring, and bracing of excavations shall conform to requirements necessary to comply with local codes and authorities having jurisdiction. Impact pile driving and sheet pile installations will cause vibrations that may affect existing residences or underground utilities in the vicinity of the proposed force main. Peak particle velocities due to pile driving should be monitored at critical locations with a seismograph during the installation of test piles, job piles and sheet piles. The record of peak particle velocities will provide information in assessing the need for changes in driving operations and the types of changes best suited for the project requirements.No piling shall be driven without monitoring equipment and personal on site. The testing laboratory will conduct continuous vibration monitoring during all pile driving. Monitoring will be performed by an independent testing lab retained by the Owner.

PART 2 - PRODUCTS

2.01 WOOD SHEETING

Wood for shoring and sheeting shall be green, rough cut hardwood (i.e. oak or hickory). Planking

Page 198: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

02160-2

for sheeting and foundation lumber shall have a minimum thickness of 2 inches.

2.02 STEEL SHEETING

Steel sheet piling shall be a continuous interlock design. The sheet piling must be in good condition and shall provide a tight interlocking connection, which will retard the infiltration of ground water. The Contractor shall be responsible for the design and installation of cofferdams around the pump station and in other areas if needed. All sheeting around the wet well and valve well shall be permanent and left in place after cutting 3 ft. below the finish roadway grade. This will be considered incidental to Pay Item No. 4 “Construction of new pump station and removal of existing pump station (Including all electrical, mechanical & civil work as shown on the plans to install new pump station & remove the existing)” and no additional payment shall be made.

PART 3 - EXECUTION

3.01 PERFORMANCE

The planning, installation and removal of all sheeting, shoring, bracing, and sheet piling shall be accomplished in such a manner as to maintain the required trench or excavated cross section and to maintain the undisturbed state of the soils adjacent to the trench and below the excavated bottom. All trenches and structural excavations shall be properly sheeted, shored and braced.

The use of horizontal strutting below the barrel of a pipe or structure or the use of a pipe as support for trench bracing will not be permitted.

All steel sheet pilings shall be left in place and the upper part of the sheeting shall be cut off 3 feet below the finished ground surface after backfilling. All bracing above this level shall also be removed. Lower bracing shall be left in place.

No sheeting, shoring or bracing shall be left in place in temporary servitudes without approval from the Engineer.

END OF SECTION

Page 199: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

SECTION 02210 GRADING

PART 1 - GENERAL

This section includes all grading work required for the construction of the gravity sewer lines shown on the Drawings within the project area. Grading operations shall include rough and finish grading of all affected areas to provide adequate drainage for the project area.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION

3.01 Site shall be graded to meet existing contours on adjacent properties to the construction site so as to provide positive drainage into existing catch basins or other drainage structures.

3.02 Finish grading shall include furnishing and placing topsoil, 4 inches thick, using stockpiled excavated material or additional approved topsoil as required to cover entire site to an elevation appropriate for the placing of seed as required elsewhere in these specifications.

END OF SECTION

02210-1

Page 200: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

02221-1

SECTION 02221

EXCAVATION, BACKFILLING FOR TRENCHES, PAVEMENT AND STRUCTURES

PART 1 - GENERAL

1.01 RELATED WORK SPECIFIED ELSEWHERE

A. Dewatering (02210)B. Sheeting, Shoring and Bracing (02160)C. Regulatory Requirements

1.02 DESCRIPTION

The Contractor shall furnish all materials, labor and equipment necessary to remove all earth, rock, water, debris and other materials to the extent required for the construction of the improvements shown on the Drawings. Also included is the preparation of the subgrade or sub-base for the foundation of the improvements and the backfilling and compaction around the improvements to the lines and grades established on the Drawings.

1.03 EXTENT OF WORK

Excavation shall extend to the width and depth shown on the Drawings or as specified, or where not specified, Contractor shall confine his excavation to the least width practicable and shall provide suitable room for installing pipe and appurtenances.

1.04 BEDDING AND BACKFILLING

The Contractor shall furnish and place all sheeting, bracing, and supports for the installation of the gravity sewers. Contractor shall backfill trenches with pumped river sand or select excavated material, as indicated. The bottom of the excavation shall be firm, dry, and in all respects, acceptable. The Contractor shall be required to deposit crushed limestone or recycled portland cement concrete, for pipe bedding in accordance with the Drawings or crushed limestone refill for excavation below grade, directly on the bottom of the trench immediately after excavation has reached the proper depth and before the bottom of the trench has become softened or disturbed by any cause whatsoever.

PART 2 - PRODUCTS

2.01 GRANULAR MATERIAL (BACKFILL)

Granular material known locally as "river sand" shall be used as backfill material for all trench and pit excavations beneath paved areas or where called for on the plans, and shall be free of roots, shells, or any other foreign matter, AASHTO A-4 material or better.

Page 201: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

02221-2

2.02 CRUSHED LIMESTONE

Limestone used as bedding material shall be from a source approved by the LDOTD. Materials shall conform to the requirements of Section 1003 of the Louisiana Standard Specifications for Roads and Bridges, latest edition.

2.03 GEOTEXTILE FABRIC.

The Contractor shall furnish and install geotextile fabric as shown on the plans. Geotextile fabric shall conform to Section 02272 – Geotextile Fabric.

2.04 SELECT EXCAVATED MATERIAL (BACKFILL)

Good sound earth free from waste, rubbish, objectionable organic matter, large rocks, waste concrete, or other unstable or unsuitable material. This material shall be used outside paved areas or structures.

PART 3 - EXECUTION

3.01 EXCAVATION

A. Excavation shall be open cuts with vertical sides using sheeting and bracing as required. All sheeting and bracing for excavations shall be in accordance with OSHA regulations.

B. In case the excavation for any pipeline is carried below the required depth as shown in the bedding details due to an error by the Contractor not for the purpose of removing stumps, roots, logs, etc., the Contractor shall fill and compact the bottom of the excavation up to grade with bedding material in a manner acceptable to the Engineer, without additional compensation for the materials, excavation or the backfilling.

C. All material excavated shall be placed so as to minimize interference with public travel and to permit proper access for inspection of the work.

3.02 DISPOSAL OF MATERIALS

A. Excavated material shall be stocked without excessive surcharge on the trench bank or obstructing free access to hydrants and valves. Inconvenience to traffic and abutters will not be allowed. Site drainage shall be maintained at all times.

B. All excess excavated material shall be removed from the site of the work by the Contractor and disposed of at a legally approved off-site area at no cost to the Owner.

Page 202: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

02221-3

3.03 OVER-EXCAVATION TO REMOVE STUMPS, ROOTS, LOGS

A. Stumps, roots, and logs, which are encountered within the trench area, shall be cut to a depth of one (1) foot below the bottom of the trench. The Contractor shall fill this excavated space with compacted bedding material as described in paragraph 3.06.

B. When so required by the Engineer, the Contractor shall probe one (1) foot below the established bottom of the trench. If any stump, roots, logs, etc., are discovered by this probing, the Contractor shall cut them out just as if they had been visible in the trench.

C. Blasting will not be allowed for the removal of stumps.

3.04 TEST PITS

Test pits for the purpose of locating underground utilities or structures in advance of the construction shall be excavated by the Contractor. Test pits shall be backfilled with compacted river sand immediately after the desired information has been obtained.

3.05 PIPE INSTALLATION

A. Proper implements, tools and facilities shall be provided and used by the Contractor for the safe and convenient prosecution of the work. All pipe, fittings, valves, and appurtenances shall be carefully lowered into the trench piece by piece by means of a derrick, ropes or other suitable tools or equipment in such a manner as to prevent damage to materials and protective coatings and linings. Under no circumstances shall materials be dropped or dumped into the trenches.

B. All pipe, fittings, and appurtenances shall be inspected for defects and cracks prior to being lowered into the trench.

C. The outside of the spigot, the inside of the bell, and any couplings used shall be brushed and wiped clean and dry and free from all foreign matter before the pipe is joined.

D. Every precaution shall be taken to prevent foreign material from entering the pipe while it is being placed in the line. During the laying operations, no debris, tools, clothing or other material shall be placed in the pipe.

E. After placing a length of pipe in the trench, the spigot end shall be centered in the bell and the pipe forced home and brought to correct line and grade. The pipe shall be secured in place with approved backfill material tamped under it as herein specified. Precautions shall be taken to prevent dirt from entering the joint space.

Page 203: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

02221-4

F. At times when pipe laying is not in progress, the open ends of pipe shall be closed by a watertight plug or other means approved by the Engineer. This provision shall apply during the noon hour as well as overnight. If water is in the trench, the seal shall remain in place until the trench is pumped completely dry.

G. Cutting of pipes for inserting fittings or closure pieces shall be done in a neat and workmanlike manner in accordance with instructions of the pipe manufacturer and without damage to the pipe.

3.06 BACKFILLING AND BEDDING

A. As soon as practicable after the pipe has been laid and jointed, backfilling shall begin and thereafter be prosecuted expeditiously. Bedding shall conform to the details on the Drawings or as established in the specifications. When laying pipe, the groove for the pipe and bell hole must be accurately shaped, and the bedding must be closely packed under and around the pipe.

B. Bedding material shall be crushed limestone or crushed concrete placed and compacted as shown on the Drawings. The compaction of the bedding shall consist of the placement of the bedding in lifts not exceeding 8 inches and compacted to a minimum of 95% of the maximum dry density in accordance with ASTM D 698. The bedding and pipe shall be enclosed in a geotextile fabric Geotextile fabrics shall be installed in accordance with the manufacturer's recommendations. All foundation lumber (i.e. planking, sills, and stringers in the trench bottom) shall be No. 2 Common Southern Pine. Installation of foundation lumber and piling shall be in accordance with the Drawings.

C. The remainder of the trench above the bedding shall be backfilled with river sand at locations where open cutting is permitted across roadways. Select excavated backfill material will be allowed for trenches outside pavement areas.

Sand backfill beneath paved areas where indicated on the Drawings shall be placed in layers up to the bottom of the pavement base course and thoroughly compacted by flooding or by mechanical compaction equipment to 97% of maximum dry density in accordance with ASTM D-698. Maximum lifts will be no greater than 8 inches. The 12 inches directly beneath the pavement shall be placed in two lifts and compacted to a minimum of 97% of the maximum dry density determined in accordance with ASTM D 698. Compaction shall be verified by the testing lab a minimum of once every 400 feet. During such test, compaction shall be measured at each lift.

Under non-paved areas, native backfill material shall be placed in layers not exceeding 8 inches deep and compacted to 90% of the maximum dry density determined in accordance with ASTM D 698.

D. Backfill around manholes shall be treated as in paragraph C above.

Page 204: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

02221-5

E. Broken paving shall not be placed in backfill.

3.07 RESTORING TRENCH SURFACE

A. Where the trench occurs adjacent to paved streets, under paved streets, in shoulders, sidewalks, or in open areas, the Contractor shall thoroughly compact the backfill and shall maintain the surface as the work progresses. If settlement takes place, he shall immediately deposit additional fill to restore the level of the ground.

B. The surface of any driveway or any other area which is disturbed by the trench excavation and which is not a part of the paved street shall be restored by the Contractor to a condition at least equal to that existing before work began.

C. In sections where the pipeline passes through grassed areas, the Contractor shall regrade and seed all disturbed areas as specified in other sections or as directed by the Engineer.

END OF SECTION

Page 205: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

02272-1

SECTION 02272

GEOTEXTILE FABRIC

PART 1 – GENERAL

1.01 SCOPE

This work consists of furnishing all labor, materials, equipment and incidentals required to furnish and install the geotextile fabric at the locations shown on the plans, or as directed, in conformance with manufacturer's directions and these specifications.

1.02 RELATED WORK

A. Section 01340 : Shop Drawings, Product Data, and SamplesB. Section 02221 : Earth Excavation and Backfill in Trenches for Pavements and

Structures

1.03 SUBMITTALS

The characteristics and properties of the geotextile fabric to be installed shall be submitted to the Engineer prior to the installation of the fabric in accordance with Section 01340.

PART 2 – PRODUCTS

2.01 ACCEPTABLE PRODUCTS

The geotextile fabric should meet or exceed the material requirements for Class C geotextile fabric as presented in Section 1019.01 of the Louisiana Standard Specifications for Roads and Bridges, 2006 edition.

2.02 MATERIALS

A. The geotextile fabric shall be a woven high strength fabric with high burst and puncture strength. It shall be a woven fabric composed of at least 85% by weight polyester, polyolefins, or polyamides. Geotextile fabric shall meet the requirements as shown in the table below:AOS US Sieve Min (ASTM D4751) 50Grab Tensile, lb., Min. (ASTM D 4632-86) 130Elongation, Min. (ASTM D 4632-86) 50%Burst Strength, psi, Min. (ASTM D3787) 210Trapezoidal Tear, lb., Min. (ASTM D 4533) 40Puncture Resistance, lb., Min. (ASTM D 4833) 40Permittivity Sec-1, min. (ASTM 4491) 1.0Strength Retained at 150 hr weatherometer, % min. (ASTM D 4632) 70

Page 206: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

02272-2

B. The manufacturer of the geotextile fabric shall have been normally engaged in the manufacture of fabrication of this geotextile fabric for at least five continuous years.

2.03 FABRICATION

The geotextile fabric shall be furnished to the Contractor by the manufacturer as a continuous sheet in the widths required for installation in the trench. The length of each sheet shall be such that the total number of sheets to be joined in the field is minimized.

PART 3 – EXECUTION

3.01 HANDLING

A. The Contractor shall handle and store the sheets in accordance with the recommendations of the manufacturer to avoid any damage. Geotextile fabric shall be stored such that it is not exposed to sunlight.

B. Damaged geotextile fabric will not be acceptable for installation until and unless it has been replaced to the satisfaction of the Engineer.

3.02 INSTALLATION

A. The geotextile fabric shall be placed without folds or wrinkles and in accordance with manufacturer's recommendations. Laps shall be as recommended by the manufacturer but in no case shall be less than 24".

B. The recommendations of the manufacturer shall be followed during the installation of the fabric. Care shall be taken during pipe laying, embedment and backfilling operations to avoid damage to the geotextile fabric. Any portion of the fabric damaged during installation shall be removed and replaced or repaired to the satisfaction of the Engineer prior to continuing the installation of the geotextile fabric.

1. Field Joints. The number of field joints shall be minimized. Lap joints shall be used to join sections in the field.

END OF SECTION

Page 207: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

02622-1

` SECTION 02622POLYVINYL CHLORIDE PIPE

PART 1 - GENERAL

1.01 RELATED WORK

1.02 DESCRIPTION

A. The Contractor shall furnish and install the polyvinyl chloride (PVC) pipe along with labor, materials and equipment necessary for installation in accordance with the Plans and Specifications.

1.03 REFERENCES

A. ASTM D1784

B. ASTM D1785

C. ASTM F441

D. AWWA C-900

E. AWWA C-905

F. ASTM D3034

1.04 SUBMITTALS

A. Certified mill tests shall be furnished the Engineer by the manufacturer for all pipe and fittings at least 10 days prior to shipment of material to the job site.

PART 2 - PRODUCTS

2.01 MATERIALS

A. Pipe:

1. All polyvinyl chloride (PVC) pipe shall be extruded from PVC meeting the requirements of cell classification 12454-B as defined in ASTM D1784.

2. All polyvinyl chloride (PVC) pipe used to transport potable water shall be in accordance with AWWA C-900 for sizes 4” to 12” (DR18 class 150) and in accordance with AWWA C-905 for sizes 14” to 24” (DR25, Class 165).

3. All polyvinyl chloride (PVC) pipe used to transport raw sewage, treated

Page 208: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

02622-2

sewage, sludge, etc., by gravity shall be DR 26 PVC pipe and shall meet all requirements of ASTM D3034 specifications.

4. All polyvinyl chloride (PVC) pipe used to transport raw sewage, treated sewage, sludge, etc., under pressure shall have a DR rating of 18 for diameters up to and including 12 inches. The pipe shall have a minimum pressure rating of 150 psi, and compatible for use with cast iron joints and fittings. Polyvinyl chloride (PVC) pipe used to transport raw sewage, treated sewage, sludge, etc., in diameters of 14 inches through 36 inches shall have a DR rating of 25 with a minimum pressure rating of 165 psi. Polyvinyl chloride (PVC) pipe in diameters of 4 inches through 12 inches shall meet all requirements of AWWA C-900 specifications. Polyvinyl chloride (PVC) pipe in diameters of 14 inches through 36 inches shall meet all requirements for AWWA C-905.

B. Fitting and Specials:

1. The polyvinyl chloride fitting used in conjunction with SDR 25 polyvinyl chloride (PVC) pipe shall be in accordance with all applicable sections of ASTM Specifications.

2. The strength class of the fitting shall be not less than the strength of any adjoining pipe.

3. No polyvinyl chloride (PVC) pipe fitting will be allowed on waterlines or PVC pipe used to transport raw sewage, treated sewage, sludge, etc., under pressure. All bends shall be ductile iron fittings in accordance with AWWA C110.

C. Joints:

1. The pipe will have integral bell elastomeric gasketed joints in accordance with ASTM F477. The gaskets shall be inserted into the pipe bell at the factory prior to shipment.

D. Protective Coatings:

1. No protective coating will be required on polyvinyl chloride (PVC) pipe.

E. Restrained Joints:

1. Polyvinyl chloride (PVC) pipe shall be restrained using the Series 1100 PV or 1100 HV MEGALUG mechanical joint thrust restraint as manufactured by EBAA Iron, Inc. or approved equal (if under pressure).

2. The EBAA Iron Series 1100 PV or 1100 HV MEGALUG assembly shall be

Page 209: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

02622-3

cast completely of closely controlled ductile iron conforming to ASTM A536, latest revision, and furnished with silicone bronze IFI 140 Grade 655 bolts. All glands and bolts shall be coated with two (2) coats of coal tar epoxy, Koppers 300-M Bitumastic or approved equal, with a minimum dry film thickness of eight (8) mils per coat.

3. Both types of restraining glands shall be wrapped with an eight (8) mil thick polyethylene tube for additional protection. The polyethylene wrap shall extend a minimum of two (2') feet in either direction from the gland and secured on the end with circumferential turns of tape.

4. All restrained joints shall be inspected at the job site after installation. Field touch-up and repair if needed shall be made by the Contractor under the supervision and inspection of a representative of the coating supplier.

PART 3 - EXECUTION

3.01 TESTING AND INSPECTION

A 5% deflection mandrel shall be used to perform the deflection testing for all new sewer gravity lines.

Deflection testing shall be performed no sooner than 31 days after the pipe has been installed and all backfill operations completed.

Deflection testing shall be performed after all infrastructures, including the compacted roadway foundation, have been installed.

Deflection testing of all gravity lines and submittal of a deflection testing report by an approved testing lab is required prior to final inspection.

The owner, his agent or the contractor shall contact the department of engineering 48 hours in advance for the inspection of the deflection mandrel test.

The mandrel shall be pulled through the pipe by hand to ensure that maximum allowable deflections have not been exceeded.

Lamp test of all sewer gravity lines shall be performed by the City of Kenner engineering department during final inspection.

The contractor shall perform cleaning and video inspections of all new sewer gravity lines (mains and service connections) installed by him as part of final inspection (there will be no direct payment for this item). Sewer line cleaning and video inspection shall be performed after all infrastructures, including the compacted roadway foundation, have been installed. Sewer line cleaning and video inspection shall be done as per Jefferson Parish department of sewerage latest “video inspection” specifications.

END OF SECTION

Page 210: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

02950-1

SECTION 02950 LANDSCAPING

PART 1 - GENERAL

1.01 RELATED WORK NOT INCLUDED

A. Construction Photographs

1.02 DESCRIPTION

A. The Contractor shall furnish all labor, materials, and equipment to satisfactorily return all construction areas to their original conditions or better.

B. The work includes furnishing and placing topsoil, fertilizer, seeding, planting, watering, and maintenance of these areas.

1.03 QUALITY ASSURANCE

A. Requirements

It is the intent of this specification that the Contractor is obliged to deliver satisfactory stand of perennial grass as specified. If necessary, the Contractor shall repeat any or all of the work, including plowing, fertilizing, seeding, and watering, at no additional cost to the Owner until a satisfactory stand is obtained.

B. Satisfactory Stand

For purposes of grassing, a satisfactory stand of grass is herein defined as a full cover over areas to be seeded with grass free of weeds, alive and growing, leaving no bare spots.

PART 2 - PRODUCTS

2.01 MATERIALS

A. Fertilizer

Slow-release type meeting the following minimum requirements: 12 percent nitrogen, 3 percent phosphorus, 6 percent potassium; 40 percent other available materials derived from organic sources. Fertilizer shall be uniform in composition, dry and free flowing delivered to sites in original unopened containers bearing manufacturer's statement or guarantee.

B. Seed

Page 211: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

02950-2

Seed shall be in accordance with Louisiana Standard Specifications for Roads and Bridges, latest edition.

C. Topsoil

Topsoil stockpiled during excavation shall be used. If additional topsoil is required, it shall be obtained off site. Topsoil shall be fertile, natural surface soil, capable of producing all trees, plants, and grassing specified herein.

D. Water

It is the Contractor's responsibility to supply all water to the site, as required during planting operations and through the maintenance period and until the work is accepted. The Contractor shall make whatever arrangements may be necessary to ensure an adequate supply of water to meet the needs to ensure an adequate supply of water to meet the needs for his work. He shall also furnish all necessary hose, equipment, attachments, and accessories for the adequate irrigation of lawns and planted areas as may be required. Water shall be suitable for irrigation and free from ingredients harmful to plant life.

PART 3 - EXECUTION

3.01 TIME OF PLANTING

When the trench backfill has compacted sufficiently, the Contractor shall commence work immediately to minimize erosion, including fine grading as required.

3.02 SOIL PLACEMENT

Areas shall be plowed to a depth of 6". Depressions shall be filled, and sticks and rubbish removed. Following subgrade preparation top soil shall be spaced evenly 4" thick over planting areas; prepare surface by raking or other means so as to establish smooth finish grade with positive drainage. Apply 20 lbs of 12-3-6 fertilizer per 1000 sq ft.

3.03 FINISH GRADING

Areas to be seeded shall be finished graded, raked, and debris removed. Soft spots and uneven grades shall be eliminated. Seeds shall be placed within 24 hours following application of fertilizer.

3.04 REGRASSING

A. Preparation of Subgrade. Unless otherwise specified, subsoil shall be graded and uniformly compacted so that it will be parallel to proposed finished grade.

Page 212: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

02950-3

3.05 CLEANUP

Soil or similar materials brought onto paved areas shall be removed promptly, keeping these areas as clean as possible at all times. During completion of planting operations, all excess soil, stones, and debris remaining shall be promptly removed from the construction areas specifically, from the LDOTD right-of-way.

3.06 LANDSCAPE MAINTENANCE

Maintain landscape work for a period of 90 days immediately following complete installation of work or until Owner accepts project. Include watering, weeding, cultivating, restoration of grade, mowing and trimming grass, protection from insects and diseases, fertilizing and similar operations as needed to ensure normal growth and good health for live plant material.

3.07 REPAIRS TO LAWN AREAS DISTURBED BY CONTRACTOR'S OPERATIONS

Areas seeded under this Contract and all areas damaged by the Contractor's operation shall be repaired at once by proper soil preparation, fertilizing, and seeding, in accordance with these Specifications.

END OF SECTION

Page 213: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

02999-1

SECTION 02999 MISCELLANEOUS WORK AND CLEANUP

PART 1 - GENERAL

1.01 SCOPE OF WORK

A. This section includes operations, which cannot be specified in detail as separate items but can be sufficiently described as to the kind and extent of work involved. The Contractor shall furnish all labor, materials, equipment and incidentals to complete the work under this section.

B. The work of the section includes, but is not limited to, the following:

1. Restoring of fences and guard rails2. Crossing utilities3. Restoring easements (servitudes) and rights-of-way4. Cleaning up5. Incidental work

1.02 WORK SPECIFIED UNDER OTHER SECTIONS

All work shall be completed in a workmanlike manner by competent workmen in full compliance with all applicable sections of these specifications.

PART 2 - PRODUCTS

2.01 MATERIALS

Materials required for this section shall be of at least the same type and quality as materials which are to be restored. Where possible, the Contractor shall reuse existing materials which are removed and then replaced, with the exception of paving.

PART 3 - EXECUTION

3.01 RESTORING OF FENCES AND GUARD RAILS

A. It may be necessary for the Contractor to remove, store and replace existing fences and guard rails during construction. Only the section directed by the Engineer shall be removed. If any section of fence is damaged due to the Contractor's negligence, it shall be replaced with fencing equal to or better than that damage at no cost to the Owner, and the work shall be satisfactory to the Engineer.

B. Guard rails in the vicinity of the work shall be protected from damage. If damaged, guard rails shall be replaced in condition equal to that existing before construction began.

Page 214: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

02999-2

3.02 CROSSING UTILITIES

This item shall include any extra work required in crossing culverts, water courses, drains, water mains, and other utilities, including all sheeting and bracing, extra excavation and backfill, or any other work required for the crossing, whether or not shown on the drawings.

3.03 CROSSING OR WORKING AJACENT TO EXISTING GAS LINES, TELEPHONE LINES, ELECTRIC LINES, AND CABLE TV LINES

The Contractor shall notify the proper authority of the utility involved when work adjacent to these lines is required. The Contractor shall coordinate all work by the utility so that the progress of construction will not be hampered. Contractor is to notify the utility company at least 48 hours in advance.

3.04 RESTORING THE EASEMENTS (SERVITUDES) AND RIGHTS-OF-WAY

A. Portions of the construction occur in easements through private property. The Contractor shall be responsible for all damage to private property due to his operations. He shall protect from injury all walls, fences, cultivated shrubbery, pavement, underground facilities, such as water pipe, or other utilities which may be encountered along the easement. If removal and replacement are required, it shall be done in a workmanlike manner so that the replacement is equivalent to that which existed prior to construction.

B. Existing lawn surfaces damaged by construction shall be regraded and resodded. These areas shall be maintained until all work under this contract has been completed and accepted.

3.05 CLEANING UP

The Contractor shall remove all construction material, excess excavation, buildings, equipment and other debris remaining on the job as a result of construction operations and shall render the site of the work in a neat and orderly condition.

3.06 INCIDENTAL WORK

Do all incidental work not otherwise specified, but obviously necessary, for the proper completion of the contract as specified and as shown on the drawings.

END OF SECTION

Page 215: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

03100-1

SECTION 03100 CONCRETE FORMWORK

PART 1 - GENERAL

1.01 SECTION INCLUDES

A. Formwork for cast-in place concrete, with shoring, bracing and anchorage.

B. Form accessories.

C. Form stripping.

1.02 PRODUCTS INSTALLED BUT NOT FURNISHED UNDER THIS SECTION

A. Section 03300 - Cast-In-Place Concrete: Supply of concrete accessories for placement by this Section.

B. Section 05500 - Miscellaneous Metal: Supply of metal fabrications for placement by this Section.

1.03 RELATED SECTIONS

A. Section 03200 - Concrete Reinforcement.

B. Section 03300 - Cast-in-Place Concrete.

1.04 REFERENCES

A. ACI 347 - Recommended Practice For Concrete Formwork.

B. PS-1 - Construction and Industrial Plywood.

1.05 DESIGN REQUIREMENTS

A. Design, engineer, and construct formwork, shoring and bracing to conform to design and code requirements; resultant concrete to conform to required shape, line and dimension.

1.06 SUBMITTALS

A. Submit under provisions of Section 01340.

B. Shop Drawings: Submit diagram of proposed construction joints not shown on Drawings.

C. Product Data: Provide data on form release agent, void form materials and

Page 216: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

03100-2

installation requirements.1.07 QUALITY ASSURANCE

A. Perform Work in accordance with ACI 347, 301, and 318.

B. Maintain one copy of each document on site.

1.08 QUALIFICATIONS

A. Design, engineer and construct forms, shores, bracing and other temporary supports to support loads imposed during construction in accordance with ACI 347. Design formwork under direct supervision of a Professional Structural Engineer experienced in design of this work and licensed in the State of Louisiana.

1.09 REGULATORY REQUIREMENTS

A. Conform to applicable code for design, fabrication, erection and removal of formwork.

1.10 FIELD SAMPLES

A. Provide under provisions of Section 01410. Coordinate with requirements stated in Section 03300.

1.11 DELIVERY, STORAGE, AND HANDLING

A. Delivery, storage, and handing of products shall be in accordance with provisions of Section 01600.

B. Deliver void forms and installation instructions in manufacturer's packaging.

C. Store materials off ground in ventilated and protected manner to prevent deterioration from moisture.

1.12 COORDINATION

A. Coordinate work under provisions of Section 01310.

B. Coordinate this Section with other Sections of work which require attachment of components to formwork.

PART 2 - PRODUCTS

2.01 WOOD FORM MATERIALS

A. Plywood: New, waterproof, synthetic resin bonded, exterior type Douglas Fir or Southern Pine plywood manufactured especially for concrete formwork and shall

Page 217: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

03100-3

conform to the requirements of PS 1 for concrete forms, Class I, and shall be edge sealed. Face adjacent to concrete Grade B or better.

B. Lumber: Southern Pine species; No. 2 grade; with grade stamp clearly visible.

2.02 MANUFACTURERS - RELEASE AGENTS

A. Richmand Screw Anchor Co.

B. Superior Concrete Accessories, Inc.; Strip-eez Form Release.

C. Preco Industries, LTD; Preco Slip-Off.

D. Substitutions: Under provisions of Section 01600.

2.03 PREFABRICATED FORMS

A. Preformed Steel Forms: Minimum 16 gage matched, tight fitting, stiffened to support weight of concrete without deflection detrimental to tolerances and appearance of finished surfaces.

B. Glass Fiber Fabric Reinforced Plastic Forms: Matched, tight fitting, stiffened to support weight of concrete without deflection detrimental to tolerances and appearance of finished concrete surfaces.

C. Void Forms: Moisture resistant treated paper faces, biodegradable, structurally sufficient to support weight of wet concrete mix until initial set; 4 inches thick.

2.04 FORMWORK ACCESSORIES

A. Form Release Agent: Colorless liquids which will not stain concrete, or absorb moisture, or impair natural bonding or color characteristics of coating intended for use on concrete.

B. Corners: Chamfered rigid plastic or wood strip type; 1/2 x 1/2 inch size unless noted otherwise; maximum possible lengths.

C. Nails, Spikes, Lag Bolts, Through Bolts, Anchorages: Sized as required, of sufficient strength and character to maintain formwork in place while placing concrete.

D. Joint Filler: Performed type, 1/2 inch thick, unless shown otherwise.

PART 3 - EXECUTION

3.01 EXAMINATION

Page 218: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

03100-4

A. Verify lines, levels and centers before proceeding with formwork. Ensure that dimensions agree with Drawings.

3.02 EARTH FORMS

A. Hand trim sides and bottom of earth forms. Remove loose soil and prior to placing concrete cover earth with 6 mil polyethylene vapor barrier.

3.03 ERECTION - FORMWORK

A. Erect formwork, shoring and bracing to achieve design requirements, in accordance with requirements of ACI 301.

B. Provide bracing to ensure stability of formwork. Shore or strengthen formwork subject to overstressing by construction loads.

C. Arrange and assemble formwork to permit dismantling and stripping. Do not damage concrete during stripping. Permit removal of remaining principal shores.

D. Align joints and make watertight. Keep form joints to a minimum.

E. Obtain approval before framing openings in structural members which are not indicated on Drawings.

F. Install void forms in accordance with manufacturer's recommendations. Protect forms from moisture or crushing.

3.04 APPLICATION - FORM RELEASE AGENT

A. Apply form release agent on formwork in accordance with manufacturer's recommendations.

B. Apply prior to placement of reinforcing steel, anchoring devices, and embedded items.

C. Do not apply form release agent where concrete surfaces will receive special finishes or applied coverings which are effected by agent. Soak inside surfaces of untreated forms with clean water. Keep surfaces soaked prior to placement of concrete.

3.05 INSERTS, EMBEDDED PARTS, AND OPENINGS

A. Provide formed openings where required for items to be embedded in or passing through concrete work.

B. Locate and set in place items which will be cast directly into concrete.

Page 219: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

03100-5

C. Coordinate work of other Sections in forming and placing openings, slots, recesses, chases, sleeves, bolts, anchors, and other inserts.

D. Install accessories in accordance with manufacturer's instructions, straight, level, and plumb. Ensure items are not disturbed during concrete placement.

3.06 FORM CLEANING

A. Clean and remove foreign matter within forms as erection proceeds.

B. Clean formed cavities of debris prior to placing concrete.

C. Flush with water or use compressed air to remove remaining foreign matter. Ensure that water and debris drain to exterior through clean-out ports.

D. During cold weather, remove ice and snow from within forms. Do not use de-icing salts or water to clean out forms. Use compressed air or other means to remove foreign matter.

3.07 FORMWORK TOLERANCES

A. Construct formwork to maintain tolerances required by ACI 301.

3.08 FIELD QUALITY CONTROL

A. Inspect erected formwork, shoring, and bracing to ensure that work is in accordance with formwork design, and that supports, fastenings, wedges, ties, and items are secure.

B. Do not reuse wood formwork more than 3 times for concrete surfaces to be exposed to view. Do not patch formwork.

3.09 FORM REMOVAL

A. Do not remove forms or bracing until concrete has gained sufficient strength to carry its own weight and imposed loads.

B. Minimum Curing Period Prior to Form Removal:

1. Air Temperature: Above 60F: 3 days.2. Air Temperature: 50F to 60F: 5 days.3. Air Temperature: 40F to 50F: 7 days.4. Air Temperature: Less than 40F: When temperature below 40F prevails,

leave forms until concrete reaches 75% of 28-day design strength.

C. Observance of minimum curing periods listed above does not relieve Contractor of responsibility for safety of structure during construction.

Page 220: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

03100-6

D. Remove wood forms from under floors, ramps, steps, and similar places (through temporary openings if necessary) so no material will be left to rot or to be infested by termites.

E. Loosen forms carefully. Do not wedge pry bars, hammers, or tools against finish concrete surfaces scheduled for exposure to view.

F. Store removed forms in manner that surfaces to be in contact with fresh concrete will not be damaged. Discard damaged forms.

END OF SECTION

Page 221: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

03200-1

SECTION 03200 CONCRETE REINFORCEMENT

PART 1 - GENERAL

1.01 SECTION INCLUDES

A. Reinforcing steel bars, wire fabric and accessories for cast-in-place concrete.

1.02 RELATED SECTIONS

A. Section 03100 - Concrete Formwork.

B. Section 03300 - Cast-in-Place Concrete.

1.03 REFERENCES

A. ACI 301 - Structural Concrete for Buildings.

B. ACI 315 - Details and Detailing for Concrete Reinforcement.

C. ACI 318 - Building Code Requirements For Reinforced Concrete.

D. ACI SP-66 - American Concrete Institute - Detailing Manual.

E. ANSI/ASTM A82 - Cold Drawn Steel Wire for Concrete Reinforcement.

F. ANSI/ASTM A185 - Welded Steel Wire Fabric for Concrete Reinforcement.

G. ANSI/ASTM A496 - Deformed Steel Wire Fabric for Concrete Reinforcement.

H. ANSI/ASTM A497 - Welded Deformed Steel Wire Fabric for Concrete Reinforcement.

I. ASTM A615 - Deformed and Plain Billet Steel Bars for Concrete Reinforcement.

J. CRSI - Concrete Reinforcing Steel Institute Manual of Practice.

K. CRSI 63 - Recommended Practice For Placing Reinforcing Bars.

L. CRSI 65 - Recommended Practice For Placing Bar Supports, Specifications and Nomenclature.

M. AWSD 1.4 - Structural Welding Code Reinforcing Steel.

Page 222: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

03200-2

1.04 SUBMITTALS

A. Submit under provisions of Section 01340.

B. Shop Drawings: Indicate bar sizes, spacings, locations, and quantities of reinforcing steel and wire fabric, bending and cutting schedules, and supporting and spacing devices. Comply with Part B, Chapter 3 of ACI 315 for preparation of shop drawings.

C. Manufacturer's Certificate: Certify that products meet or exceed specified requirements.

1.05 QUALITY ASSURANCE

A. Perform Work in accordance with CRSI 63, 65 and Manual of Practice ACI 301, ACI SP-66 and ACI 318.

B. Maintain one copy of each document on site.

C. Submit certified copies of mill test report of reinforcement materials analysis.

1.06 COORDINATION

A. Coordinate work under provisions of Section 01310.

B. Coordinate with placement of formwork, formed openings and other Work.

PART 2 - PRODUCTS

2.01 REINFORCEMENT

A. Reinforcing Steel: ASTM A615, 60 ksi yield grade; deformed billet steel bars, plain finish.

B. Welded Steel Wire Fabric: ASTM A185 Plain Type in flat sheets; plain finish.

2.02 ACCESSORY MATERIALS

A. Tie Wire: Minimum 16 gage annealed type.

B. Chairs, Bolsters, Bar Supports, Spacers: Sized and shaped for strength and support of reinforcement during concrete placement conditions including load bearing pad on bottom to prevent vapor barrier puncture.

C. Special Chairs, Bolsters, Bar Supports, Spacers Adjacent to Weather Exposed Concrete Surfaces: Plastic coated steel type; size and shape as required.

Page 223: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

03200-3

2.03 FABRICATION

A. Fabricate concrete reinforcing in accordance with CRSI Manual of Practice, ACI SP-66 and ACI 318.

B. Welded reinforcement (AWSD 1.4): Do not weld reinforcement in the shop or field unless approved in writing by the Engineer.

C. Locate reinforcing splices not indicated on Drawings, at point of minimum stress. Review location of splices with Engineer.

PART 3 - EXECUTION

3.01 PLACEMENT

A. Perform concrete reinforcement work in accordance with CRSI Manual of Standard Practice and Documents 63 and 65.

B. Place, support and secure reinforcement against displacement. Do not deviate from required position.

C. Do not displace or damage vapor barrier.

D. Accommodate placement of formed openings.

E. Conform to applicable code for concrete cover over reinforcement.

3.02 FIELD QUALITY CONTROL

A. Field inspection will be performed under provisions of Section 01410.

END OF SECTION

Page 224: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

03300-1

SECTION 03300CAST-IN-PLACE CONCRETE

PART 1 - GENERAL

1.01 SECTION INCLUDES

A. Cast-in-place concrete.

B. Control, and expansion and contraction joint devices associated with concrete work.

C. Equipment pads, drainage structures, thrust blocks, and mechanical supports.

1.02 RELATED SECTIONS

A. Section 03100 - Concrete Formwork

B. Section 03200 - Concrete Reinforcement.

1.03 REFERENCES

A. ACI 212 - Chemical Admixtures for Concrete.

B. ACI 301 - Structural Concrete for Buildings.

C. ACI 302 - Guide for Concrete Floor and Slab Construction.

D. ACI 304 - Recommended Practice for Measuring, Mixing, Transporting and Placing Concrete.

E. ACI 305R - Hot Weather Concreting.

F. ACI 306R - Cold Weather Concreting.

G. ACI 308 - Standard Practice for Curing Concrete.

H. ACI 309R - Guide for Consolidation of Concrete.

I. ACI 318 Building Code Requirements for Reinforced Concrete.

J. ANSI/ASTM D994 - Preformed Expansion Joint Filler for Concrete (Bituminous Type).

K. ANSI/ASTM D1751 - Preformed Expansion Joint Fillers for Concrete Paving and Structural Construction (Nonextruding and Resilient Bituminous Types).

Page 225: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

03300-2

L. ASTM C31 - Standard Method of Making and Curing Concrete Test Speciment in the field.

M. ASTM C33 - Concrete Aggregates.

N. ASTM C39 - Compressive Strength of Cylindrical Concrete Specimens.

O. ASTM C94 - Ready-Mixed Concrete.

P. ASTM C109 - Standard Test Method for Hydraulic Cement Mortars.

Q. ASTM C138 - Standard Test Method for Unit Weight, Yield, and Air Content (Gravimetric) of Concrete.

R. ASTM C143 - Test for Slump of Portland Cement Concrete.

S. ASTM C150 - Portland Cement.

T. ASTM C171 - Sheet Materials for Curing Concrete.

U. ASTM C172 - Compressive Strength of Cylindrical Concrete Specimens.

V. ASTM C173 - Standard Test Method for Air Content of Freshly Mixed Concrete by the Volumetric Method.

W. ASTM C231 - Test Method for Air Content of Freshly Mixed Concrete by Volumetric Method.

X. ASTM C260 - Air Entraining Admixtures for Concrete.

Y. ASTM C309 - Liquid Membrane - Forming Compounds for Curing Concrete.

Z. ASTM C494 - Chemical Admixtures for Concrete.

AA. ASTM C618 - Fly Ash and Raw or Calcinated Natural Pozzolan for Use as a Mineral Admixture in Portland Cement Concrete.

1.04 SUBMITTALS

A. Submit under provisions of Section 01340.

B. Product Data: Provide data on joint devices, attachment accessories, and proposed admixtures.

C. Concrete Manufacturer shall perform and submit the following:

Page 226: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

03300-3

1. Mix Design - In advance of concrete operations, materials proposed for use in concrete will be sampled and tested to determine their compliance with these specifications. Mix proportions shall be reviewed by the laboratory for each strength and type of concrete required and reports submitted to the Engineer for approval, showing the mix designs. Submit mix design in accordance with ACI 301.

2. Include the following information in concrete mix design:

a. Proportions of cement, fine and coarse aggregate, and water.b. Water-cement ratio, 28-day compressive and design strength, slump,

and air content.c. Type of cement and aggregate.d. Aggregate gradation.e. Type and dosage of admixtures.f. Special requirements for pumping.g. Range of ambient temperature and humidity for which design is valid.h. Special characteristics of mix which require precautions in mixing,

placing, or finishing techniques to achieve finished product specified.

1.05 TESTS

A. Required testing will be performed in accordance with ACI 301 by Testing Laboratory employed and paid by Owner.

1. Provide free access to Work and cooperate with appointed firm.

2. Submit proposed mix design of each class of concrete to testing firm for review prior to commencement of Work. Tests of cement and aggregates may be performed to ensure conformance with specified requirements.

3. Notify Testing Laboratory 24 hours prior to proposed concrete pour. Testing Laboratory shall be present at every concrete pour.

B. Testing firm will:

1. Review the Contractor's proposed materials and mix design.

2. Conduct strength tests:

a. Secure composite samples (ASTM C172).

b. Mold, cure specimens from each sample (ASTM C31). A minimum of four concrete test cylinders shall be taken for every 100 or less cu. yds. of each class of concrete placed each day and not less than once for each 5000 sq. ft. of surface area for slabs.

Page 227: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

03300-4

c. Test cylinders in accordance with ASTM C39. Two specimens will be tested at 28 days for acceptance and one will be tested at 7 days for information. One specimen will be retained in reserve for later testing if required.

3. Conduct slump tests: At least one slump test will be taken for each set of four test cylinders taken (ASTM C143).

4. Conduct air content tests: At least one air content test will be made when slump test is taken in accordance with either ASTM C231, ASTM C173, or ASTM C138.

5. Conduct temperature tests: Determine temperature of concrete sample for each strength test.

1.06 PROJECT RECORD DOCUMENTS

A. Submit under provisions of Section 01410.

B. Accurately record actual locations of embedded utilities and components which are concealed from view.

1.07 QUALITY ASSURANCE

A. Perform Work in accordance with ACI 301 and ACI 304.

B. Maintain one copy of each document on site.

C. Acquire cement and aggregate from same source for all work.

D. Conform to ACI 305R when concreting during hot weather.

E. Conform to ACI 306R when concreting during cold weather.

1.08 COORDINATION

A. Coordinate work under provisions of Section 01041.

B. Coordinate the placement of joint devices with erection of concrete formwork and placement of form accessories.

Page 228: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

03300-5

PART 2 - PRODUCTS

2.01 CONCRETE MATERIALS

A. Cement: ASTM C150, Type II.

B. Fine and Coarse Aggregates: ASTM C33.

C. Water: Clean potable water.

2.02 ADMIXTURES

A. Air Entrainment: ASTM C260.

B. Chemical: Admixtures for normal weight concrete may be used at providing the requirements of ACI 212 are met and written approval from the Engineer is obtained by the Contractor.

2.03 ACCESSORIES

A. Bonding Agent: Two component modified epoxy resin; n-solvent two component polysulphide epoxy manufactured by Sika Chemical Corporation.

B. Vapor Barrier: 6 mil thick clear polyethylene film type recommended for below grade application.

C. Non-Shrink Grout: Premixed, non-shrinking, high strength grout compound consisting of non-metallic aggregate, cement, water reducing, plasticizing agents and free of gypsum; compressive strength of 5,000 psi in 28 days.

D. Epoxy Bonding Agent: ASTM C8811. Concessive 1001 LPL by Adhesive Engineering Co.2. Uniweld by Permagile.3. EVA-POX HI MOD GEL #23 by E-Poxy Industries, Inc.

2.04 CURING COMPOUNDS

A. Membrane Curing Compound ASTM C309 Type 1.

B. Manufacturers -1. Curecrete Chemical Company; Ashford Formula2. Sonneburn-Contech; Kure-N-Seal3. W. R. Grace; Clear Seal 1504. L & M Construction Chemicals; Seal Hard5. Gifford-Hill; Sealco.

Page 229: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

03300-6

C. Substitutions: Under provisions of Section 01630.

D. Water: Potable and not detrimental to concrete.

2.05 CONCRETE MIX

A. Mix and deliver concrete in accordance with ACI 304 and ASTM C94.

B. Provide concrete to the following criteria:

1. For concrete exposed to freeze-thaw:a. Compressive Strength:

1) 28 Days: 4,000 psi for all concrete except sidewalks, and driveways.

b. Air Content: 5 1/2%, plus or minus 1%c. Slump: Not to exceed 4 inches maximum.d. Maximum Water-Cement Ratio: 0.45e. Minimum Cement Content: 517 lbs per cu. yd.f. Slabs-on-Grade shall be 4,000 psi @ 28 days (unless otherwise noted)g. Portland Cement Compressive strength for driveways and curb shall be

3,000 psi (min.) @ 3 days and a minimum of 4,000 psi @ 28 days.h. Portland Cement Compressive strength for sidewalks shall be 4,000 psi

(min.) @ 28 days.i. Concrete duct banks shall be 4,000 psi @ 28 days (unless otherwise

noted)

C. Use accelerating admixtures in cold weather only when approved by Engineer. Use of admixtures will not relax cold weather placement requirements.

D. Use calcium chloride only when approved by Engineer.

E. Use set retarding admixtures during hot weather only when approved by Engineer.

F. Admixtures:

1. Air Entraining Admixtures: ASTM C260. Add to concrete mix for concrete work subject's freeze-thaw cycling. Air Content: See above.

PART 3 - EXECUTION

3.01 EXAMINATION

A. Verify existing site conditions.

B. Verify requirements for concrete cover over reinforcement.

Page 230: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

03300-7

C. Verify that anchors, seats, plates, reinforcement and other items to be cast into concrete are accurately placed, positioned securely, and will not cause hardship in placing concrete.

3.02 PREPARATION

A. Prepare previously placed concrete by cleaning with steel brush and applying bonding agent in accordance with manufacturer's instructions.

B. In locations where new concrete is dowelled to existing work, drill holes in existing concrete, insert steel dowels and pack solid with non-shrink grout in accordance with manufacturer's instructions.

3.03 PLACING CONCRETE

A. Place concrete in accordance with ACI 304, ACI 301, ACI 350 and ACI 318.

B. Notify Engineer minimum 24 hours prior to commencement of operations.

C. Ensure reinforcement, inserts, embedded parts, formed joint fillers, and joint devices are not disturbed during concrete placement.

D. Install vapor barrier under slabs on grade. Lap joints minimum 6 inches and seal watertight by sealant applied between overlapping edges and ends taping edges and ends.

E. Repair vapor barrier damaged during placement of concrete reinforcing. Repair with vapor barrier material; lap over damaged areas minimum 6 inches and seal watertight.

F. Install joint fillers in accordance with manufacturer's instructions.

G. Separate slabs on grade from vertical surfaces with 1/2 inch thick joint filler.

H. Extend joint filler from bottom of slab to within 1/2 inch of finished slab surface.

I. Install joint devices in accordance with manufacturer's instructions.

J. Install joint covers in longest practical length, when adjacent construction activity is complete.

K. Maintain records of concrete placement. Record date, location, quantity, air temperature, and test samples taken.

L. Place concrete continuously between predetermined expansion, control, and construction joints.

Page 231: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

03300-8

M. Do not interrupt successive placement; do not permit cold joints to occur.

N. Vibration: As soon as concrete is deposited, thoroughly agitate with mechanical vibrators and suitable hand tools to work mixture into corners of forms and around reinforcing and embedded items. Use mechanical vibrators with minimum frequency of 9000 revolutions/minute. Do not over vibrate or use vibrators to transport concrete within forms. Insert and withdraw vibrators at approximately 18 inches apart. At each insertion, vibrate generally 5-15 seconds, sufficient to consolidate concrete but not long enough to cause segregation. Keep spare vibrator on job site during concrete placement operations. Do not insert vibrator into lower courses that have begun to set.

O. Saw cut joints within 24 hours after placing. Using 3/16 inch thick blade, cut into 1/4 depth of slab thickness.

P. Screed floors and slabs on grade level, maintaining surface flatness of maximum 1/8 inch in 12 ft.

3.04 CONCRETE FINISHING

A. Finish concrete surfaces to requirements ACI 301.

B. Provide formed concrete surfaces to be left exposed with smooth rubbed finish.

C. Provide exterior, exposed concrete slabs with broomed finish.

3.05 FORMED SURFACES

A. Forms shall not be stripped before the concrete has attained a strength of at least 30 percent of the ultimate design strength. This is equivalent of approximately "100 day-degrees" of moist curing.

B. Care shall be exercised to prevent damaging edges or obliterating the lines of chambers or corners when removing the forms or doing any work or work adjacent thereto.

C. Clean all exposed concrete surfaces and adjoining work stained by leakage of concrete, to the satisfaction of the Engineer.

D. Smooth Rubbed finish. Fins and other projections shall be removed as approved.

3.06 CURING AND PROTECTION

A. Immediately after placement, protect concrete from premature drying, excessively hot or cold temperatures, and mechanical injury.

Page 232: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

03300-9

B. Maintain concrete with minimal moisture loss at relatively constant temperature for period necessary for hydration of cement and hardening of concrete.

C. Cure concrete floor surfaces to requirements ACI 308.

D. Horizontal Surfaces

1. Spraying: Fog spray water over floor slab areas and maintain wet for 7 days.

2. Membrane Curing Compound: Apply curing compound in accordance with manufacturer's instructions in 2 coats with second coat at right angles to first. However, the rate of application shall never be less than one (1) gallon per 100 ft2 of exposed area.

E. Vertical Surfaces

1. Spraying: Spray water over surfaces and maintain wet for 7 days.

2. Membrane Curing Compound: Apply curing compound in accordance with manufacturer's instructions in 2 coats with second coat at right angles to first. However, the rate of application shall never be less than one (1) gallon per 100 ft2 of exposed area.

3.07 PATCHING

A. Allow Engineer to inspect concrete surfaces immediately upon removal of forms.

B. Excessive honeycomb or embedded debris in concrete is not acceptable. Notify Engineer upon discovery.

C. Patch imperfections in accordance with ACI 301.

3.08 DEFECTIVE CONCRETE

A. Defective Concrete: Concrete not conforming to required lines, details, dimensions, tolerances or specified requirements.

B. Repair or replacement of defective concrete will be determined by the Engineer.

C. Do not patch, fill, touch-up, repair, or replace exposed concrete except upon express written direction of Engineer for each individual area.

END OF SECTION

Page 233: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

05500-1

SECTION 05500 MISCELLANEOUS METAL

PART 1 - GENERAL

1.01 SCOPE OF WORK

A. Furnish all labor, materials, equipment and incidentals required and install covers, grates, frames, manhole rungs, catch basin castings, and other miscellaneous metal as shown on the drawings and specified herein.

1.02 RELATED WORK

A. Section 06620 – NOT USED.

1.03 COORDINATION

A. The work of this section shall be completely coordinated with the work of other sections. Verify at the site both the dimensions and work of other trades adjoining items of work in this section before fabrication and installation of items herein specified.

B. Furnish to the pertinent trades all items included under this section that are to be built into the work of other sections.

1.04 SHOP DRAWINGS

Detail drawings, as provided for in the General Conditions and Section 01340, showing sizes of members, method of assembly, anchorage, and connection to other members shall be submitted to the Engineer for approval before fabrication.

1.05 FIELD MEASUREMENTS

Field measurements shall be taken at the site to verify or supplement indicated dimensions and to insure proper fitting of all items.

1.06 REFERENCE SPECIFICATIONS

Unless otherwise specified, materials shall conform to the following:

Structural Steel ASTM A36Welded and Seamless Steel Pipe ASTM A53Gray Iron Castings ASTM A48, Class 30Galvanizing, general ASTM A123Galvanizing, hardware ASTM A153

Page 234: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

05500-2

Galvanizing, assemblies ASTM A386Aluminum (extruded shapes) ASTM B209, 6063 T5 (Alum. alloy)Aluminum (extruded pipe) ASTM B209, 6063 T6 (Alum. alloy)Aluminum Sheet and Plate ASTM B209, 6061 T6 (Alum. alloy)Bolts and Nuts ASTM A307Stainless Steel Bolts, Bars, Shapes AISI, Type 302 Stainless Steel Plate and Sheet AISI, Type 304Welding Rods for Steel AWS Spec. for Arc Welding

PART 2 - PRODUCTS

2.01 ANCHORS, BOLTS, AND FASTENING DEVICES

A. Anchors, bolts, etc., shall be furnished as necessary for installation of the work of this section.

B. The bolts used to attach the various members to the anchors shall be the sizes shown or required.

C. For structural purposes, unless otherwise noted, expansion bolts shall be Wej-it "Ankr-Tite", Phillips Drill Co. "Wedge Anchors", or Hilti "Kwik-Bolt". When length of bolt is not called for on the drawings, the length of bolt provided shall be sufficient to place the wedge portion of the bolt a minimum of one inch (1") behind the reinforcing steel within the concrete. Material shall be as noted on the drawings. If not listed, galvanized steel.

2.02 STEEL ITEMS

A. Galvanized steel grating shall be fabricated as shown. Angle frames for hatches, beams, grates, etc., shall be furnished complete with welded strap anchors attached. Furnish all miscellaneous aluminum shown but not otherwise detailed.

B. Sleeves shall be steel or cast iron pipe in walls and floors with end joints as shown on the drawings. All pipe sleeves shall have center anchor around circumference as shown.

C. Miscellaneous steel pipe for sleeves and lifting attachments and other uses as required shall be Schedule 40 pipe fabricated according to the details as shown on the drawings.

D. Miscellaneous steel shall be fabricated and installed in accordance with the drawings and shall include; angles, support brackets, splice plates, anchor bolts (except for equipment furnished in Divisions 11 and 15); and any other miscellaneous steel called for on the drawings and not otherwise specified.

Page 235: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

05500-3

2.03 CAST IRON FRAMES AND COVERS

A. Frames, covers, and grates for manholes shall be of a good quality, strong, tough even grained cast iron except as otherwise specified below. Castings shall be as manufactured by the Vulcan Foundry, Inc., Neenah Foundry, Mechanics Iron Foundry, or equal. Sizes shall be as shown on the drawings. Covers to have letters "SEWER" or "DRAIN" embossed on top, as required.

B. Manhole frames and covers shall be 2'-6" in diameter. unless otherwise shown on the Drawings.

C. Valve Boxes

Valve boxes shall be of strong, tough even-grained cast iron. Valve boxes shall be two-part screw type adjustable with covers having the word "SEWER" or "WATER" embossed on top as applicable. Valve boxes shall be Series No. 6850 as manufactured by Vulcan Foundry, Inc., Tyler Pipe, Type 4905 as manufactured by Opelika Foundry, or equal, unless otherwise specified.

D. Water Meter Boxes

All water meter boxes shall be in accordance with Jefferson Parish Water Standards.

PART 3 - EXECUTION

3.01 FABRICATION

A. All miscellaneous metal work shall be formed true to detail, with clean, straight, sharply defined profiles and smooth surfaces of uniform color and texture and free from defects impairing strength or durability.

B. Connections and accessories shall be of sufficient strength to safely withstand stresses and strains to which they will be subjected. Steel accessories and connections to steel or cast iron shall be steel, unless otherwise specified. Threaded connections shall be made so that the threads are concealed by fitting.

C. Welded joints shall be rigid and continuously welded or spot welded as specified or shown. The face of welds shall be dressed flush and smooth. Exposed joints shall be close fitting and jointed where least conspicuous.

D. Welding of parts shall be in accordance with the Standard Code for Arc and Gas Welding in Building Construction of the AWS and shall only be done where shown, specified, or permitted by the Engineer. All welding shall be done only by welders certified as to their ability to perform welding in accordance with the requirements of the AWS Code. Component parts of built-up members to be welded shall be

Page 236: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

05500-4

adequately supported and clamped or held by other adequate means to hold the parts in proper relation for welding.

E. Welding of aluminum shall conform to the applicable provisions of the AA-30 for aluminum structures. The general recommendations and regulations of AWS D1.1 as applicable shall apply to welded aluminum.

F. Castings shall be of good quality, strong, tough, even-grained, smooth, free from scale, lumps, blisters, sand holes, and defects of any kind which render them unfit for the service for which they are intended. Castings shall be thoroughly cleaned and will be subjected to a hammer inspection in the field by the Engineer. All finished surfaces shown on the drawings and/or specified shall be machined to a true plane surface and shall be true and seat at all points without rocking. Allowances shall be made in the patterns so that the thickness specified or shown shall not be reduced in obtaining finished surfaces. Castings will not be acceptable if the actual weight is less than 95 percent of the theoretical weight computed from the dimensions shown. The Contractor shall provide facilities for weighing castings in the presence of the Engineer showing true weights, certified by the supplier.

G. All steel finish work shall be thoroughly cleaned, by effective means, of all loose mill scale, rust, and foreign matter before shipment and shall be given one shop coat of primer compatible with finish coats specified in Painting Section after fabrication but before shipping. Paint shall be applied to dry surfaces and shall be thoroughly and evenly spread and well worked into joints and other open spaces. Abrasions in the field shall be touched up with primer immediately after erection.

H. Galvanizing, where required, shall be the hot-dip zinc process after fabrication. Following all manufacturing operations, all items to be galvanized shall be thoroughly cleaned, pickled, fluxed, and completely immersed in a bath of molten zinc. The resulting coating shall be adherent and shall be the normal coating to be obtained by immersing the items in a bath of molten zinc and allowing them to remain in the batch until their temperature becomes the same as the bath. Coating shall be not less than 2 oz. per sq. ft. of surface.

3.02 INSTALLATION

A. Install all items furnished except items to be imbedded in concrete which shall be installed under Division 3. Items to be attached to concrete after such work is completed shall be installed in accordance with the details shown. All dimensions shall be verified at the site before fabrication is started.

B. All steel surfaces to come in contact with exposed concrete shall receive a protective coating of an approved heavy bitumastic troweling mastic applied in accordance with the manufacturer's instructions prior to installation.

C. Where aluminum contacts a dissimilar metal, apply a heavy brush coat of zinc-

Page 237: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

05500-5

chromate primer followed by two coats of aluminum metal and masonry paint to the dis-similar metal.

D. Where aluminum contacts concrete, apply a heavy coat of approved alkali resistant paint to the concrete.

END OF SECTION

Page 238: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

TS-706-1

TECHNICAL SPECIFICATIONS

SECTION 706

CONCRETE WALKS, DRIVES, & INCIDENTAL PAVING

706.01 DESCRIPTION

This work consists of furnishing and constructing Portland Cement Concrete walks, drives, and incidental paving slabs in accordance with Section 706 of Louisiana Standard Specifications for Roads and Bridges, 2016 Edition and its latest revisions in conformity with line and grades shown on the plans or established by the Engineer.

706.02 MATERIALS

Materials shall conform to Sections 03100, 03200, 03300 of these specifications.

706.04 MEASUREMENT

Quantities for items installed under this section will be the design quantities as specified and adjusted thereto. Design quantities will be adjusted if engineer makes changes to adjust to field conditions, if design errors are proven, or if design changes are made. All joints with existing pavement shall have clean, straight, edges, be free of damage or defects, and have no deviations in line or grade from new to existing. Excavation, backfill, reinforcing steel, saw cutting and joint materials will not be measured for payment.

706.05 PAYMENT

Payment for walks, driveways, and incidental paving will be made at the contract unit price per square yard. These Pay Items shall include any and all granular material or select fill necessary for grading and placement of concrete walks and drives. The granular material under driveways and sidewalks shall be in accordance with the requirements of Section 723 of Louisiana Standard Specifications for Roads and Bridges, 2016 Edition and its latest revisions. There shall be no direct payment for granular material under driveways and sidewalks. The depth shall be as per plans.

Page 239: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

TS-706-2

Item No. Pay Item Pay Unit

13 Concrete Drive (6” Thick) Sq. Yd.

14 Concrete Walk (4” Thick) Sq. Yd.

END OF SECTION

Page 240: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

TS-707-1

TECHNICAL SPECIFICATIONS

SECTION 707

CURBS AND GUTTERS

707.01 DESCRIPTION

This work consists of furnishing and constructing integral concrete curbs and curb and gutter sections, in accordance with Section 707 of the Louisiana Standard Specifications for Roads and Bridges, 2016 Edition and its latest revisions, the standard requirements of St. Bernard Parish, and in the standard details.

707.02 MATERIALS

All materials shall conform to the specification requirements of Sections 03100, 03200, 03300.

707.03 GENERAL

Curbs for the concrete pavement may be integral construction with roadway slab or doweled steel as per standard plans and constructed later. Integral curbs shall be deposited within thirty (30) minutes after the pavement slab has been broom-finished.

For the installation of new yard drain pipes or if an existing yard drain is encountered during repair of a concrete curb section, the curb shall be removed & replaced a min. 12” from the outer edge of the pipe with a tooled joint. If the location of a tooled joint falls within 1 foot of existing joint, curb shall be removed & replaced to existing joint.

707.04 MEASUREMENT AND PAYMENT

No measurement or direct payment will be made for excavation, backfill, reinforcing steel, joint material, saw cuts, curing membrane, curb transitions or modifications, or other incidentals to this work, but shall be included in the price bid for this work.

Curbs and curb and gutter sections shall be measured by the linear foot in place, plan quantity. Design quantities will be adjusted if the Engineer makes changes to adjust to field conditions, if plan errors are proven, or if design changes are made.

Page 241: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

TS-707-2

Measurement and Payment for the items of work in this section will be under:

Item No. Pay Item Pay Unit

15 Concrete Curb LF

END OF SECTION

Page 242: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

1 of 8

TECHNICAL SPECIFICATIONS

SECTION 708

GRAVITY SANITARY SEWER SYSTEM

I. PART 1: DESCRIPTION:

All “gravity sanitary sewer system” work shall be performed in total conformance with these specifications, and as per materials manufacturer’s requirements and recommendations.

All work associated with the gravity sanitary sewer system shall be performed under this section and to the lines and grades shown on plans.

This work will include furnishing and constructing all manholes, pipes, fittings, couplings, abandoning existing sewer main with flow able fill and other incidentals required and as indicated on the drawings and in accordance with the Specifications herein. Where the word “pipe”, “line”, and/or “sewer line” are used it shall refer to all applicable parts of manholes, pipes (mains & house service connections), fittings, couplings, and other required incidentals unless otherwise noed.

The Contractor shall furnish all labor, equipment and materials required to perform all work required for removal of any existing manholes, pipes, fittings, couplings, etc. and for installation of new manholes, pipes, fittings, couplings, and other required incidentals. Removal and installation, replacement or relocation shall be as indicated on the drawings and specified herein. Damage to any part of the gravity sanitary sewer system by the Contractor, subcontractors, material and equipment suppliers or other persons, prior to acceptance, shall be repaired by the Contractor to the satisfaction of the Engineer and Owner at the expense of the Contractor.

The drawings attempt to indicate the alignment of all known sewer lines within the limits of the work. However, the Contractor shall be responsible to inspect the entire project to verify all existing sewer lines and to determine the existence of any additional conflicts with his work. The location of proposed sewer lines may be field adjusted, with prior approval from the City of Kenner Department of Public works, to avoid conflicts with other utilities.

II. PART 2: COORDINATION:

Removal and replacement or relocation of sewer lines shall be done in close coordination with the Owner (Owner herein shall mean either the City of Kenner Department of Public Works). Removal and replacement or relocation work shall be planned in advance so that inconvenience

Page 243: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

2 of 8

to the Owner and utility users caused by the disruption of service is minimized. The contractor shall be responsible for immediately notifying the Owner and Engineer of existing conditions that differ from that shown on the plans.

The contractor shall notify the Department of Public Works 468 7515, 48 hours prior to any field work relating to the City of Kenner Sanitary Sewer system.

III. PART 3: CONSTRUCTION LAYOUT:

1. The Contractor will be responsible for establishing all lines and grades and staking out all “Sewer System” work on this project from controls provided in the construction documents. There shall be no separate payment for construction layout.

IV. PART 4: MATERIALS:

All materials shall be as specified in the plan and specified here in the specifications. All Ductile Iron Pipes, Fittings, etc. used in sewer gravity system shall have a factory applied interior coating/lining of “Protecto 401” ceramic epoxy lining as per manufacturer’s recommendations and requirements for Sanitary Sewer applications.

Polyethylene Encasement in accordance with ANSI/AWWA C105/A21.5 (Minimum 8 mil thick) shall be required for all Ductile Iron Pipes and Fittings.

V. PART 5: EXECUTION:

A. GENERAL

1. Underground Installation of sewer gravity mains and service connections shall be in accordance with all applicable requirements of ASTM standards.

2. Underground Installation of Thermoplastic sewer gravity mains and service connections shall be in accordance with all applicable requirements of ASTM D-2321 standards.

3. Manholes, pipes, fittings, couplings, and all other incidentals and accessories shall be handled in a manner that will insure installation in sound, undamaged condition. Equipment, tools, and methods used in handling and installing pipe and fittings shall notdamage the pipe and fittings. Hooks inserted in ends of pipe shall have broad, well- padded contact surfaces.

4. All pipe and fitting coatings which have been damaged shall be repaired by the Contractor before installation. Any such repairs shall be done in total conformance with the manufacturer’s requirements and recommendations and shall require prior approval and final acceptance from the City of Kenner Department of Public Works.

Page 244: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

3 of 8

5. Sewer system installation shall be done with pipe sections and fittings such that pipe cutting is not required. Should pipe cutting be required, cutting shall be done in a neat manner, without damage to the pipe or to the lining or coating (any lining or coating which have been damaged shall be repaired by the Contractor before installation. Any such repairs shall be done in total conformance with the manufacturer’s requirements and recommendations and shall require prior approval and final acceptance from the City of Kenner. Cuts shall be smooth, straight, and at right angles to the pipe axis. After cutting, the end of the pipe shall be dressed with a file to remove all roughness and sharp corners.

6. All cutting of ductile iron pipe shall be done with mechanical pipe cutters except where the use of mechanical cutters would be difficult or impracticable. Ends of ductile iron pipe shall be cut with a saw, abrasive wheel, or oxyacetylene torch. Field cut holes for saddles shall be cut with mechanical cutters; oxyacetylene cutting will not be permitted.

7. The interior of all pipe and fittings shall be thoroughly cleaned of foreign matter prior to installation and shall be kept clean until the work has been accepted. Before jointing, all joint contact surfaces shall be wire brushed if necessary, wiped clean, and kept clean until jointing is completed.

8. Precautions shall be taken to prevent foreign material from entering the pipe during installation. Debris, tools, clothing, or other materials shall not be placed in or allowed to enter the pipe.

9. A representative of the City of Kenner, DPW Department shall be present during the installation of all sewer system items or be given the chance, through proper notification requirements, to inspect all sewer system items installed, prior to backfill. The contractor is advised not to take this requirement lightly as City of Kenner reserves the authority to require the contractor to uncover any or all sewer system related items installed for inspection.

B. TRENCHING

1. Excavation work shall be performed in a safe and proper manner with appropriate precautions being taken against all hazards. As always, Trench Safety shall remain the contractor’s responsibility at all times.

2. Excavate and maintain trenches to the indicated or required depth and width. Provide minimum of 12" clearance on both sides of pipe or conduit.

3. Trench construction for sewer mains and service connections shall be in accordance with the JEFFERSON PARISH standard drawings and these specifications. Protect

Page 245: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

4 of 8

excavations by any acceptable methods to prevent cave-in or loose soil from falling into excavation.

4. Notify the Engineer of any undesirable, unexpected subsurface conditions, which would affect the integrity of the system, and discontinue work in affected area until receipt of notification to resume work.

5. Grade excavation top perimeter to prevent surface water run-off into excavation.

6. Hand trim excavation and leave free of loose matter.

7. Correct unauthorized excavation at no cost to Owner.

C. BEDDING AND BACKFILL

1. Both Crushed Limestone and Recycled Portland Cement Concrete are acceptable for pipe Bedding, Haunching, and Initial Backfill as required in the JEFFERSON PARISH Standard Drawings and these Specifications. Haunching and Initial Backfill areas must be compacted to a minimum of:

# 610 Stone – 90% of Standard Proctor (ASTM D698).#57 Stone – 75% of Relative Density (ASTM D4253 & ASTM D4254)

2. Crushed Limestone and Recycled Portland Cement Concrete shall be either # 57 or modified # 610 (as specified herein) depending on the Trench Type. When # 57 mix is used, the Crushed Limestone and Recycled Portland Cement Concrete shall be wrapped with filter fabric (“Mirafi 500X” or “Propex Geotext 200ST” with minimum 18" overlap).

Trench Type Bedding, Haunching, andInitial Backfill

Final Backfill

I # 57 or # 610River Sand, Min. Density

95% Standard Proctor (ASTM D698)

II # 57 or # 610III # 57 or # 610IV # 57V # 57

Page 246: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

5 of 8

57 LIMESTONEU.S. SIEVE METRIC SIEVE PERCENT PASSING

1 ½" 37.5 mm 1001" 25 mm 95-100

1/2" 12.5 mm 25-60# 4 4.75 mm 0-10# 8 2.36 mm 0-5

MODIFIED 610 LIMESTONEU.S. SIEVE METRIC SIEVE PERCENT PASSING

1 ½" 37.5 mm 1001" 25 mm 90-100

3/4" 19 mm 70-1001/2" 12.5 mm 60-903/8" 9.5 mm 50-80# 4 4.75 mm 35-65

# 40 425 µ m 12-32# 200 75 µ m 5-12

3. Backfill material shall be Mississippi River “pumped sand”, AASHTO A-4 or better having a maximum liquid limit of 25 and a maximum plasticity index of 6. All sands shall be free of trash, weeds, lumps, humus, pieces of wood or any other deleterious material. Backfill material shall have a group index number not to exceed 6.

4. If required and proper compaction of required stone is not practical to achieve in the area of Bedding, Haunching, and Initial Backfill of Sewer Service Connections, Sand may be used (by flooding) in the place of the required Crushed Limestone or Recycled Portland Cement Concrete immediately beneath the pipe and above the required foundation lumber and stone. It is recommended that the Crushed Limestone or RecycledPortland Cement Concrete used for these sewer service connections’ foundation to be # 610 stone which does not require to be wrapped with filter fabric. The intention of this variance is to allow the contractor to achieve proper compaction around ServiceConnections’ pipes, fittings, couplings, etc. The contractor shall support all service connection components during placement and compaction of pipe backfill. This variance shall only apply to the Service Connections and not the Mains.

Page 247: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

6 of 8

5. Document and photograph material and installation of all manholes, pipes, fittings, couplings, and other incidentals including pipe trench (mains, service connections, et.) construction prior to backfill. Each photograph must accompany adequate identification information such as manhole number, manhole station, property address for sewer service connections, etc.

6. A representative of the City of Kenner, DPW Department shall inspect all installed sewer system items prior to backfill.

D. CONNECTION TO EXISTING SYSTEM

1. A representative from the City of Kenner, DPW Department must be present during all work being done at the tie-in points.

2. All tie-ins to the existing sewer system shall be done by the Contractor.

3. All tie-in locations shall be identified and tie-in method shall be investigated prior to ordering material and equipment, and especially prior to the scheduled tie-in event.

4. Connections between new work and existing piping shall be made using approved fittings or couplings suitable for the conditions encountered and/or as indicated on the drawings.

5. Each connection to an existing pipe or manhole shall be made at a time and under conditions which will least interfere with service to customers, and as authorized by the Owner.

6. Facilities shall be provided for proper dewatering and for disposal of all ground water (or sewage) removed from the trenches or excavated areas.

E. BYPASS

1. Bypass of sewage (pumping or gravity) shall be done in accordance with all applicable City of Kenner, State, and Federal regulations and requirements. Bypass operations and the bypass method shall be planned in advance so that inconvenience to the owner and utility users is minimized.

2. Install and operate all required plugs, piping, and bypass pumping equipment to maintain sewage flow and to prevent backup or overflow.

3. Obtain approval for bypass pumping equipment and procedures from the Engineer Granting approval shall not relieve thecontractor from total responsibility for the bypass operation.

Page 248: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

7 of 8

4. No sewage shall be diverted into any area outside of sanitary sewer system.

5. In the event of accidental spill or overflow, immediately stop overflow and take action to clean up and disinfect spillage. Promptly notify the authorities so that required documentation and reporting can be made.

6. There shall be no direct payment for Sewage Bypass Operations unless otherwise specified.

F. PIPE CLEANING AND VIDO INSPECTIONS

Pipe cleaning and video inspection shall be per JEFFERSON PARISH Standards. Pipe cleaning and video inspection shall be coordinated and planned in advance so that inconvenience to the owner and utility users is minimized.

VII. PART 6: MEASUREMENT AND PAYMENT:

1. Payment for this work will be made after receipt of approval from the City of Kenner Department of Public Works.

The price and payment shall constitute full compensation for furnishing all labor, materials, and equipment to construct any segment of the sanitary sewer system {all applicable parts of manholes, pipes (mains & house service connections), fittings, couplings, and other required incidentals} including excavation, trenching, bedding, pipe laying, backfill, tie-ins to existing sewer lines, acceptance testing of mains, manholes, and all incidental work necessary for a complete and functional sewer distribution system.

2. Sewer Lines or Mains shall be measured horizontally through manholes along the centerline of pipeline and shall be paid for per linear feet for specific size, complete and in place.

3. Manholes:

a. Shallow Depth Manholes - Payment for shallow depth manholes is on a unit price basis for each manhole installed, complete and in place. Shallow depth manholes have a depth of 5 feet or less measured from top of cover to the sewer manhole invert.

b. Normal Depth Manholes – Payment for normal depth manholes is on a unit price basis for each manhole installed, complete and in place. Normal depth manholes have a depth greater than 5 feet, and up to 8 feet. Manhole depth is measured from top of cover to the sewer manhole invert.

Page 249: TABLE OF CONTENTS - kenner.la.us€¦  · Web viewAny bidder to whom a contract is awarded shall certify that he holds an active license in accordance with LSA-R.S. 37:2150 et. seq

8 of 8

c. Extra Depth Manholes - Payment for extra depth manholes is on a unit price basis per vertical foot installed, complete and in place. Extra depth manholes have a depth greater than 8 feet. Manhole depth is measured from top of cover to the sewer manhole invert.

d. Drop Manholes – Payment for drop manholes is on a unit price basis per vertical foot installed, complete and in place. Manhole depth is measured from top of cover to the sewer manhole invert.

4. Existing Sewer Manhole Rehab shall be measured and paid for per each complete and in place. Manhole Rehab shall be as specified in JEFFERSON PARISH Standard Notes and Drawings and as specified herein.

5. There shall be no direct payment for Bypass Pumping unless otherwise specified.

6. There shall be no direct payment for dewatering unless otherwise specified.

7. There shall be no direct payment for cleaning and video inspections of new sewer gravity mains and service connections, installed by the contractor, as part of final inspection and acceptance.

Install Sewer Main (10”) (PVC/SDR 26 Pipe) Lin. Ft.

Install Sewer Manhole VFH

Lifesaver Stainless Steel Stopper, Manhole Insert Each

Abandon Existing Sewer Manholes & Fill void with sand Each

Plug Existing Sewer Main @ manholes & fill with flowable material(cement/sand mixture) Lin. Ft.