Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
T13: Estimate of Maturity, Risks, Milestones, and the Path to CD-2 Frank ChlebanaFermilab
US-MTD Technical Review15-16 November 2018
F. Chlebana – T13 Estimate of Maturity, Risks, and Milestones US-MTD Technical Review 2
MTD and US-MTD organizationUS scope and scope options Preparation of detailed plan in P6 and milestones Status of supporting documentation Risks, mitigation, and response Estimate of maturity of design R&D, remaining technical decisions, prototype plan, and
path to CD-2 Summary
Outline
F. Chlebana – T13 Estimate of Maturity, Risks, and Milestones US-MTD Technical Review 3
Frank Chlebana, Senior Scientist (Fermilab) Role in US-MTD: Deputy L2 Manager Experience in construction, commissioning, operations,
and project planning while on ZEUS, CDF, and CMS. Former head of the DAQ group at CDF Former CMS HCAL DPG convener HGCal DPG co-convener (ramping down) Deputy L2 manager for the HCAL Phase 1 upgrades Deputy head of the Fermilab CMS Department
Biographical SketchCharge #6
F. Chlebana – T13 Estimate of Maturity, Risks, and Milestones US-MTD Technical Review 4
MTD Organization Chart
DocID:13653
: US personnel
This management structure was put in place in the last few months.Grey areas also covered but not recorded here.
Charge #6
https://cms-docdb.cern.ch/cgi-bin/DocDB/ShowDocument?docid=13653
F. Chlebana – T13 Estimate of Maturity, Risks, and Milestones US-MTD Technical Review 5
US-MTD Organization Chart
L2 Manager: Chris Neu
Deputies:Frank Chlebana
David Stuart
US-MTD Advisory Team
Steve Nahn, Jeff Spalding, Jim Strait
USCMS HL-LHC Project Office:Vivian O’Dell, Anders Ryd
Vaia Papadimitriou, Lucas TaylorBill Freeman, Carol Wilkinson,
TJ Sarlina
L3: Barrel Timing Layer (BTL)Adi Bornheim
L3: Endcap Timing Layer (ETL)
Artur Apresyan
L4: BTL SiPMsMitch Wayne
L4: BTL AssemblyAdi Bornheim
L4: BTL Concentrator CardYurii Maravin
L4: BTL I&CAdi Bornheim
L4: LGAD SensorsChris Rogan
L4: ETL AssemblySlavek Tkaczyk
L4: ETL Front-end ASICsTed Liu
L4: I&CSlavek Tkaczyk
U.S. CMS HL-LHC Advisory Board
L3: Common Systems
Chris Rogan
L4: Back-end ElectronicsToyoko Orimoto
L4: System TestingLindsey Gray
L4: LYSO ScintillatorChris Neu
Charge #6
DocID:13678
All US-MTD positions are filled
We are well integrated into the MTD technical leadership
https://cms-docdb.cern.ch/cgi-bin/DocDB/ShowDocument?docid=13678
F. Chlebana – T13 Estimate of Maturity, Risks, and Milestones US-MTD Technical Review 6
Overall cost range is between $12 and 15M, including contingency and risk US scope at $15M:
BTL: Assembly of 60% of the BTL trays and associated QC testing, delivery to CERN Design, prototyping, provision and QC testing of 100% of the BTL CCs Prototype, pre-production SiPM studies and QC testing of 50% of the BTL SiPMs Purchase of ~30% of the BTL LYSO crystals and SiPMs
ETL: Assembly of 35% of the ETL modules and associated QC testing, delivery to CERN Design, prototyping, provision and QC testing of at least 40% of the FE ASICs
Common system contributions: Integrated system testing with prototype/pre-production components System infrastructure contribution (eg., CO2 costs)
Scope options: Downscope options:
Build fewer ETL modules Build fewer BTL trays Reduce core contribution to ETL ASICs
Upscope options: Provision of off-detector BE electronics for BTL, ETL or both Building additional ETL modules Purchase of additional core commodities
These scope options have been discussed with international MTD project. In making a scope decision we would further consult with iMTD and iCMS.
US-MTD scope
Updated scope wrt CDR document:• Areas of
engagement unchanged
• Adjustments in level of contribution
• Backend electronics as upscope
Charge #10
F. Chlebana – T13 Estimate of Maturity, Risks, and Milestones US-MTD Technical Review 7
KPPs
DocID: 13682
F. Chlebana – T13 Estimate of Maturity, Risks, and Milestones US-MTD Technical Review 8
BOEs and Schedule Development
para
Parametric excel sheet allows us to adjustment cost estimates and part numbersUsed to generate the BOE Labor and M&S tables
Basis of estimate documentDetailed description of scope and cost summary
Activity listNotes on each activity and connection logic used to develop the detailed RLS
Vendor quotes and supporting documentation for cost estimates
Cost and schedule will be examined during the OPSS CSR review in Jan 2019
Charge #3
Example DocDB entries for the BTL Concentrator Cards
Basis of Estimates and supporting documentation are uploaded in DocDB and is used when developing the detailed schedule in P6
F. Chlebana – T13 Estimate of Maturity, Risks, and Milestones US-MTD Technical Review 9
BOEs and Schedule Development
Vendor quotes for the major cost drivers are available and up to date, and mostly loaded in DocDB
LYSO: Vendor quote availableSiPM: Hamamatsu-SiPM (Sep 27, 2018)Concentrator Cards: BOM parts list, PCB production (Sep 10, 2018)BTL Assembly: Pick and place gantry and stencil printer (Aug 15, 2018)
LGAD: Shipping estimate (Sep, 2018), FBK-LGAD (Nov 10, 2018)ASIC: MWP, Fabrication, Estimates based on contractual agreement between CERN and vendor for 65nm submission ETL Assembly: Vendor contacted
BE electronics: BOM and parts costed in Barrel section of the projectSystem testing: Estimate based on previous experience
Estimates for the major cost drivers are based on recent vendor quotes (or will soon be)
Charge #3
F. Chlebana – T13 Estimate of Maturity, Risks, and Milestones US-MTD Technical Review 10
Schedule DevelopmentWe initially developed a coarse schedule in P6 to get cost estimates.
BTL LYSOBLT Module Assembly (threshold KPP)BTL I&C (objective KPP)ETL LGADETL Module Assembly (threshold KPP)ETL I&C (objective KPP)
A more detailed schedule is being developed
BTL SiPMBTL Concentrator CardsETL ASIC
The detailed schedule will be completed and scrubbed ahead of the OPSS CSR review in Jan 2019
F. Chlebana – T13 Estimate of Maturity, Risks, and Milestones US-MTD Technical Review 11
Key Dates – BTL SiPMWe have compiled a list of milestones that we will use to monitor progress. These are in the process of being entered into P6 as we build up the detailed schedule
Charge #10
F. Chlebana – T13 Estimate of Maturity, Risks, and Milestones US-MTD Technical Review 12
Key Dates – ETL ASICCharge #10
F. Chlebana – T13 Estimate of Maturity, Risks, and Milestones US-MTD Technical Review 13
Key Dates – BTL and ETLWe identified milestones for all areas and will include them as the detailed schedule is developed
Charge #10
F. Chlebana – T13 Estimate of Maturity, Risks, and Milestones US-MTD Technical Review 14
BTL Key Dates
TDR Submission Q2 2019BTL Engineering Design Review Q2 2020Start of installation of BTL trays onto the tracker support tube Q3 2022Delivery of BTL assembled trays to CERN completed Q4 2022 (threshold KPP)Completion of BLT I&C (objective KPP)TKR installation in support tube Q4 2023
Charge #10
We are working together with iMTD on updating the schedule for the TDR to ensure consistency, and have provided input based on the planning we have done in P6
F. Chlebana – T13 Estimate of Maturity, Risks, and Milestones US-MTD Technical Review 15
ETL Key Dates
ASIC availability for module production, Q3 2023Delivery of ETL modules to CERN completed, Q3 2024 (threshsold KPP) Installation and commissioning of ETL modules onto DEEs, Q3 2025 (objective KPP)Installation of DEEs onto HGCal, Q4 2025Commissioning of ETL after installation onto HGCal, Q1 2026
Baseline plan is to install DEEs onto HGCal in UX5 (pit)We have some flexibility to install DEEs on HGCal earlier in SX5 (surface) or at a later date during a YETS
Charge #10
F. Chlebana – T13 Estimate of Maturity, Risks, and Milestones US-MTD Technical Review 16
Project Documentation
KPPs: draft update uploaded to DocDB
QAP appendix for MTD in preparation
All document updates will be complete and reviewed ahead of the Director’s Review
WBS dictionary to be updated
Science requirements doneCDR: Updated MTD Chapter will be final on conclusion of this review
Design maturity done. To be inserted in final document
Requirements: done. Interfaces: initial list prepared, full document/template in preparation
Initial BoEs and P6 RLS, cost roll-up done. Detailed tasks and logic being fleshed out. (Detailed milestones are part of this.) Final scrub ahead of OPSS Review.
Risk Workshop held. Final updates to Risk Register to be done.
pHAR updated
Value engineering: 2 paragraphs to be inserted into document
Config Management: 2 links to be added to document
Full documentation set for CD1 and MTD Specific Sections
Need report form this technical review and our follow up
F. Chlebana – T13 Estimate of Maturity, Risks, and Milestones US-MTD Technical Review 17
Configuration Management PlanCharge #8
Need to ensure changes to technical specifications and/or requirements are communicated effectively to all affected groups
Overlap between MTD technical leadership and the US-MTD project, ensures efficient communication.
We are following the project wide procedure to ensure changes are recorded, archived, and following the process for distributing changes in a formal manner. Detailed in:
1) The USCMS HL-LHC Configuration Management Plan (DocID:12907)
Details configuration management, interface control and change control.
Specifies the personnel and organizations providing the configuration control, defines the configuration-controlled system, describes the change control process, and specifies the plan for configuration status accounting and acceptance.
2) The MTD Interface Control Document (DocID:13536)
In this document we have assembled our external constraints and interfaces, and have started to assemble the list of responsible people within MTD and at CMS who will sign off on them.
Will review interfaces with Advisory Team to identify any omissionsWill finalize all defined owners of each technical interface and specificationInterface Control Document will be finalized prior to the Directors Review in early CY2019
F. Chlebana – T13 Estimate of Maturity, Risks, and Milestones US-MTD Technical Review 18
Risk Workshop
Reviewers found that we have addressed most risks
Summary and descriptions need to be improved and harmonized across the different risks
Ensure all necessary information if filled in.Check start, stop, retirement dates
Clarify mitigation vs response
Identified some risks that should be split into separate risks
Feedback on fine tuning cost and schedule impact
Use spares to mitigate loss/damage during batch production
Charge #4
The Risk Workshop was last week… and we are implementing the reviewers feedback and suggestions…
BTL Risk Workshop: Nov 7, 2018: https://indico.fnal.gov/event/19025/ETL Risk Workshop: Nov 8, 2018: https://indico.fnal.gov/event/19026/Reviewers: Julie Whitmore, Marco Verzocchi, Aseet Mukherjee, David Christian
F. Chlebana – T13 Estimate of Maturity, Risks, and Milestones US-MTD Technical Review 19
Risk RankingCharge #4
F. Chlebana – T13 Estimate of Maturity, Risks, and Milestones US-MTD Technical Review 20
… plus 15 low ranked risks
Sum (P*Impact) ≈ $0.6M Risk contingency at 90% C.L. will be O($1M)
Timing Layer – Top-ranked risks (high & medium)Charge #4
F. Chlebana – T13 Estimate of Maturity, Risks, and Milestones US-MTD Technical Review 21
General Timing Layer RisksCharge #4
F. Chlebana – T13 Estimate of Maturity, Risks, and Milestones US-MTD Technical Review 22
Barrel Timing Layer RisksCharge #4
F. Chlebana – T13 Estimate of Maturity, Risks, and Milestones US-MTD Technical Review 23
Endcap Timing Layer Risks
(opportunity)
Charge #4
F. Chlebana – T13 Estimate of Maturity, Risks, and Milestones US-MTD Technical Review 24
Leading ETL RiskCharge #4
RT-402-8-03-D ETL - Front End ASIC does not meet specifications - requires another pre-production run
Probability: 10%
Schedule Impact: 6 - 7.5 - 9 months
Cost Impact: 907 - 971 - 1035 k$
Estimate: The M&S cost is $690k for masks and wafer and $25k for a single set up to package a few chips. The labor cost for the additional engineering effort is a 3-pt triangular PDF: 0.25-0.375-0.5 FTE. The min/likely/max cost is hence 781/813/846 k$.
Mitigation: This risk is mitigated by carrying out several prototype cycles and having and increased design simulation and verification effort.
Response: Proceed with the necessary additional pre-production run. If we cannot achieve the baseline installation date, then we would have to install DEEs onto HGCal during a later YETS.
F. Chlebana – T13 Estimate of Maturity, Risks, and Milestones US-MTD Technical Review 25
Estimate of Maturity of DesignFollowing the standard project approach outlined in: “USCMS HL-LHC Design Completion Definition” DocDB 13417
Each L4 manager provided an assessment of the status for each completion criteria of the design phases
If all criteria within a design phase are achieved, we reach the assigned level of design completion Conceptual Design (15%) Preliminary Design (40%)
Charge #3
F. Chlebana – T13 Estimate of Maturity, Risks, and Milestones US-MTD Technical Review 26
Estimate to MaturityUsing this methodology we have estimated the level of maturity for each WBS area as:
Charge #3
The MTD project is past the conceptual design phase and well on the way to the preliminary design phase with an estimated level of maturity of >25%
WBS %402.8.3 BTL402.8.3.1 BTL Lyso Crystals 30402.8.3.2 BTL SiPMs 30402.8.3.3 BTL Concentrator Card 30402.8.3.4 BTL Module/RU/Tray Assembly 20402.8.4 ETL402.8.4.1 LGAD Sensors 30802.8.4.2 ETL FE ASIC 30802.8.4.3 ETL Module Assembly 20402.8.5 Common Systems402.8.5.1 System Test Stands 10402.8.5.2 Backend Electronics 35
Methodology
See docid 13417: USCMS HL-LHC Design Completion Definition Document
See Figure 2 and Table 1 ---->
Methodology
By WBS Section:
(1) List % completion for each of these items
(2) Summarize for the WBS
(3) Summarise for each of these items for the whole project
Note: (2) and (3) are matrixed summary views
providing a cross-check
Sheets in this Workbook
(1) methodology
(2) Summary Table for MTD (public)
(3) Working tables for each WBS section (internal to project)
Interpretation (international equivalent)
Preliminary Design Review = review of the TDR anmd assoc docs by LHCC/UCG
Final Design Review = EDR
We should be past conceptual design and on our way to preliminary
Calibration: Outer Tracker claimed to be at 38% at CD1 (following their TDR review).
Summary Table
MTD Design MaturityValues hand estimated in each sheet
WBS%
402.8.3BTL
402.8.3.1BTL Lyso Crystals30
402.8.3.2BTL SiPMs30
402.8.3.3BTL Concentrator Card30
402.8.3.4BTL Module/RU/Tray Assembly20
402.8.4ETL
402.8.4.1LGAD Sensors30
802.8.4.2ETL FE ASIC30
802.8.4.3ETL Module Assembly20
402.8.5Common Systems
402.8.5.1System Test Stands10
402.8.5.2Backend Electronics35
MTD Design MaturityValues averaged across WBSPrevious version of this table in docid 13417 (October 12, 2018)
Conceptual Design (15%)%
1Alternatives for satisfying the requirements have been evaluated and a preferred alternative has been selected. 90
2R&D tasks identified that will guide the design selection and address risks. 87
3Value engineering performed. 90
4Lessons learned from other experiments are incorporated into the design or planning as relevant. 99
5Initial cost and schedule developed. 87
6Cost and schedule range developed. 100
7Preliminary Hazard Analysis performed. 100
8Preliminary risk analysis performed and documented in Risk Register. 87
9Conceptual Design Report completed. 91
10Conceptual design satisfies Mission Need. 91
Preliminary Design (40%)%
1Baseline design choice has been made. 56
2Preliminary design is sufficiently developed, including preliminary design drawings of major components, final drawings of long duration items to be purchased. 48
3Interfaces have been identified. 57
4Value engineering performed. 66
5Preliminary QA plan developed 45
6Lessons learned from other experiments are incorporated into the design or planning as relevant. 69
7Activity-based resource-loaded baseline cost and schedule fully developed, including a full contingency analysis. 42
8Technical Design Report completed. 46
9Component designs at the 30% level of design completion. 52
402.8.3.1 BTL Lyso Crystals
402.8.3.1 BTL Lyso Crystals: Summary %30
F. Chlebana – T13 Estimate of Maturity, Risks, and Milestones US-MTD Technical Review 27
Prototype and Preproduction Plans: BTL
Details of the prototype and preproduction plans were presented in dedicated talks
LYSO (See M. Toliman’s talk)Evaluating the performance of tile vs bar optionTestbeam is ongoing this week to inform the decision, decision ~Dec 2018
SiPM (See M.Wayne’s talk)R&D focus on maximizing PDE at low power consumption, low DCR, and low priceSelect the two most promising devices for a preproduction run Q2 2019
Concentrator Card (See Y.Maravin’s talk)First power only prototype availablePre-production design depends on lpGBT and DCDC convertors (Q2 2019)Design testing jig and QC protocol by Q3 2019Produce 20 pre-production boards with 8 DCDC converters: Q4 2020
BTL Module Assembly (See A.Bornheim’s talk)FE board and sensor board design is ongoing Cooling plate prototype being built to verify performance (Q1 2019)Start design of the tray assembly procedure in Q3 2019 Engineering design reviews planed before final production
Charge #3
F. Chlebana – T13 Estimate of Maturity, Risks, and Milestones US-MTD Technical Review 28
Prototype and Preproduction Plans: ETL
LGAD (See C.Rogan’s talk)Extensive bench and beam test program is ongoingR&D focus on radiation hardness, fill factor, and uniformityPre-production sensors with final geometry/doping/design (2020-2021)
ASIC (T.Liu)Added additional time for simulation and evaluation of the prototypesPrototype 1, 4x4 pixel matrix (Q2 2019)Prototype 2, 8x8 pixel matrix (Q3 2020)Evaluation of AltiROC as part of the system testing planPreproduction, 16x16 pixel full size chip (Q1 2022)
Module Assembly (S.Tkaczyk)Build mechanical mock-up of an LGAD-ASIC subassembly (June 2019)Using ETL prototype ASIC, build electrically functioning subassembly prototype using a pick-n-place station and read the atom out using simple test stand DAQEngineering design review planed before final production
We have well developed prototype and preproduction plans to optimize the design and to establish the baseline design in time for the CD-2 review
Charge #3
F. Chlebana – T13 Estimate of Maturity, Risks, and Milestones US-MTD Technical Review 29
Summary
The US scope is defined and we are well on the way to develop a detailed RLS in time for the OPSS CSR review in Jan 2019
Identified a set of milestones to monitor progress and we are working closely with iMTD to ensure our planning and schedule are consistent
Risks have been identified and reviewed
We are working through a check list of the work and documentation needed for the CD-1 minireview in Apr 2019
We have a well defined prototype plan that will allow us to optimize the design and to establish the baseline design by CD-2 (Q3 2020)
We are beyond the required level of technical maturity for CD-1, preparing the necessary documentation for the CD-1 minireview, and have a prototype plan to establish the baseline design for CD-2
Slide Number 1OutlineBiographical SketchMTD Organization ChartUS-MTD Organization ChartUS-MTD scopeKPPsBOEs and Schedule DevelopmentBOEs and Schedule DevelopmentSchedule DevelopmentKey Dates – BTL SiPMKey Dates – ETL ASICKey Dates – BTL and ETLBTL Key DatesETL Key DatesProject DocumentationConfiguration Management PlanRisk WorkshopRisk RankingTiming Layer – Top-ranked risks (high & medium)General Timing Layer RisksBarrel Timing Layer RisksEndcap Timing Layer RisksLeading ETL RiskEstimate of Maturity of DesignEstimate to MaturityPrototype and Preproduction Plans: BTLPrototype and Preproduction Plans: ETLSummary