T1 status and plans INFN Genova November 2014 Collaboration
Meeting
Slide 2
T1 at Point 5 F.Ferro - T1 status and plans
Slide 3
Already done Readout Replaced out-of-sync VFATs Extensive check
of ground connections Replaced VFATs with bad occupancy patterns
Replaced position sensors Sensors measuring z still to be checked
by Joao Mechanics Installation test and mechanics checks on both
halves Commissioning DAQ tested on all quarters HV tested on all
quarters with Ar/CO 2 /CF 4 mix Test of trigger To be done Replace
radiation monitor (waiting for Federico) Stoppers preparation
(Roman) Commissioning Set up thresholds Maintenance &
commissioning F.Ferro - T1 status and plans Status to be checked...
Likely during 15-19 Dec. week
Slide 4
Installation: outlook F.Ferro - T1 status and plans CMS
schedule is being deeply reviewed T1 installation schedule is
strongly affected (T1 probably installed in February) Tasks 1 and 2
done in October (before magnet test). Tasks 3-12 to be done as soon
as CMS ready to receive T1 (overall time needed for one side of T1
when HF on 2 risers is ~2 days).
Slide 5
T1 services on YE4 T1 services on YE4 Petals and cables
installed on YE4 Minus side Plus side
Slide 6
T1 Maratons 4 repaired Maratons installed (2 per side)
Slide 7
Looking forward to... F.Ferro - T1 status and
plans...reinstalling both T 1 s during LS1(February?)