Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Slide No. 1 of 30 3/1/12
Systems Life Cycle Cost
Considerations Applied to
Stability and Reconstruction
Operations
John V. Farr, Ph.D., P.E.Professor of Engineering Management andDirector of the Center for Nation Reconstruction and Capacity DevelopmentDepartment of Systems EngineeringUnited States Military Academy at West PointWest Point, NY 10996-1779Office: (845) 938-5206 Cell: (845) 667-9573Email: [email protected] or [email protected]
Slide No. 2 of 30 3/1/12
• Introduction
• The Classical Systems
Challenges
• Stability and
Reconstruction
• Life Cycle Considerations
• Summary
Agenda
Slide No. 3 of 30 3/1/12
The mission for the Center for Nation Reconstruction and Capacity Development is to take an interdisciplinary and systems approach in facilitating and focusing research, professional practice, training, and
information dissemination in the planning, execution, and assessment of efforts to construct infrastructure, policies, and competencies mainly in
support of building partner capacity for communities and nations primarily in developing countries. The Center will have a strong focus on
professional practice in support of developing current and future Army leaders through its creation of cultural immersion and research
opportunities for both cadets and faculty.
Mission Statement
Slide No. 4 of 30 3/1/12
• Energy Security
• Resource Allocation and
Efficiencies
• Operations and Disaster
Resiliency
• Social and Environmental
Sustainability
• Energy Security
• Resource Allocation and
Efficiencies
• Operations and Disaster
Resiliency
• Social and Environmental
Sustainability
• Future Technologies and
Concepts
• Ilities - Sustainability,
Supportability, Affordability,
and Adaptability
• Future Technologies and
Concepts
• Ilities - Sustainability,
Supportability, Affordability,
and Adaptability
• Nation Reconstruction
• Forward Operating Bases
• Theater Security
Cooperation
• Host Nation Capacity and
Economic Development
• Assessment and Policy
• Reconstruction Training
• Nation Reconstruction
• Forward Operating Bases
• Theater Security
Cooperation
• Host Nation Capacity and
Economic Development
• Assessment and Policy
• Reconstruction Training
Warfighting Installation Operations Future Concepts
Our Research Agenda
Infrastructure and Other Supporting Enablers:People, Policies, and Technology
Conflict Non Conflict Conflict/Non Conflict
Methods Processes, and Tools (MPTs)
Advance the state of knowledge in complex socio-technological systems as related to
infrastructure in support of nation reconstruction, security cooperation, and
operational needs
Slide No. 5 of 30 3/1/12
Our Competencies
Life Cycle Cost AnalysisResource AllocationAssessmentDecision AnalysisSystems ThinkingModeling and SimulationInfrastructure AssessmentEconomic Development
Slide No. 6 of 30 3/1/12
Life Cycle Cost Analysis
Formal definition of life-cycle costingA general method of economic evaluation which takes into account all relevant costs over a given period of time adjusting for differences in the timing and the true value of those costs.
What is life-cycle cost?Life-cycle cost (LCC) is the total cost of ownership of a product, structure, or system over its useful life.
R&D Investment O&SF-16 Fighter 2% 20% 78%M-2 Bradley 2% 14% 84%
Slide No. 7 of 30 3/1/12
• Introduction
• The Classical
Systems Challenges
• Stability and
Reconstruction
• Life Cycle
Considerations
• Summary
Agenda
Slide No. 8 of 30 3/1/12
Cost in the Systems Process
HighAbility toInfluence
LCC(70-75%of Cost
DecisionsMade)
(10%-15%)
72% Life Cycle Cost28% Life Cycle Cost
Less Ability to Influence LCC (85% of Cost Decisions Made)
Little Ability to Influence LCC (90-95% of Cost Decisions Made)
(5%-10%)
Minimum Ability to Influence LCC (95% of Cost Decisions Made)
Conceptual Exploration
ComponentAdvanced
Development
SystemsIntegration/Preliminary
Design
SystemsDemonstration,
Test, andEvaluation
Production Operations,Support, &Disposal
Slide No. 9 of 30 3/1/12
• Increased system complexity• External funding instability• Loss of “mission urgency” at the end of of each major engagement• Diminished depth of talent in the government and/or contractor community• Requirements creep• The need to satisfy demands from an increasingly diverse user community• Inadequate up-front project planning• Lack of management oversight• Accountability• Clear metrics on both the government and contractor sides• Exponential growth in, and reliance on, software• Complex owner/prime/sub interdependencies
The Problem
Slide No. 10 of 30 3/1/12
1969
1955
1969
1970
1953
1954
1946
F-14
UH-1
F-15
SSN 688
AIM-9
KC-135
B-52
1973
1959
1975
1976
1955
1957
1955
2010+
2004+
2010+
2026+
2025+
2017+
2040+
41+ Years
49+ Years
51+ Years
56+ Years
72+ Years
86+ Years
94+ Years
Extended LifeNotional Projected Lifetime
DevelopmentStart
Base Model IOCPlan Phase Out(Last Model)
Current Trends in Military Systems
Similar Reality for Enterprise Level IT Systems
Many Applications Pre-Date the Internet and the Client-Server Architectural Paradigm
We must start designing like private industry• Modularity• Open
source/architecture• Commercial
standards• Vendor can no
longer own elements• Upgradability must
be a key performance parameter
• Tradeoff performance for upgradability and sustainability
Slide No. 11 of 30 3/1/12
The Problem - DoD
Primary StructuralMaterials/Platforms
MechanicalSystems/Weapon
C4 ISR Infrastructure
Sensors
Communications
IT Hardware
IT Software
15 – 30 yrs
10 – 15 yrs
5 – 8 yrs
3 – 5 yrs
1 – 3
.5 - 2
.5 - 1
Improvised ExplosiveDevises .01 - 1
Car Bombs .01 - 1
Technology Cycle Times
? ?
Incremental Acquisition (Pre-Planned Product Improvement) implies known or fixed requirements
Evolutionary Acquisition implies evolutionary requirements
We cannot operate inside ourenemies cycle time - processes are
to cumbersome
Slide No. 12 of 30 3/1/12
Impact of “Front -End” InvestmentA NASA View of the Benefits of SE
Analysis of Gruhl's NASA Data
-50
0
50
100
150
200
250
0 5 10 15 20 25
%RQTDEF
%
• Recent National Academies study recommended that we spent more systems engineering resources during concept definition
• USAF has embraced this for all future programs
• As complexity increases we must spend more upfront to better develop requirements and manage expectations
• Upgradability (modularity, “openness”, no propriatarysoftware, COTs, etc) must be a key performance parameter when buying
Slide No. 13 of 30 3/1/12
Must Better Manage Contractors
• Fewer contractors with decreasing government budgets
• Are sophisticated global players • Must be smarter buyers/contract writers• Must develop like Toyota, Nokia, Apple• Re-examine the relationships between
buyers and vendors
Slide No. 14 of 30 3/1/12
Parametric Cost Estimation
Analogy
Detailed Engineering Build Up
Primary Technique Some Applicability Little or No Utility
Conceptual
Exploratio
n
Component
Advanced
Develop-
ment
Systems
Integration/
Preliminary
Design
SystemsDemon-stration,Test, andEvaluation
Productio
nOperations,
Support, &
Disposal
How Do We Cost Systems
Slide No. 15 of 30 3/1/12
Estimating Techniques
• Traditional approaches for measuring the technical scope of a development project include top-down, bottoms-up, and analogous estimating techniques.
• Top-down estimation starts with an estimate for what the project can or should cost and then allocates it to the various aspects of the project (management, systems engineering, software engineering, hardware engineering, integration testing, system delivery, and system support).
– The top-down estimate is often used to obtain a rough-order-of-magnitude estimate of what the project should cost.
• Bottoms-up estimation relies on engineers and management personnel to provide task-level estimates from a WBS at some level of detail based on experience; the task-level detail is then summed to produce an overall project estimate.
• Analogous estimation predicts future performance based on past performance.
• It is normally best if more than one technique is used to estimate a project’s technical scope, cost, and schedule for the purposes of accuracy.
• Type I (unknown cost categories) are more devastating than Type II (known category but bad cost data)
Slide No. 16 of 30 3/1/12
Cost and Schedule Estimates are constantly refined as the technical baseline work products are refined
Baseline
Created
Technical Work Products from
which estimate is developed
Typical review at which
technical work products
and associated cost /
schedule are baselined.
Methodologies used to develop cost (and schedule) estimate from technical work
products
Customer 1. Customer ( or Stakeholder /
Business) Requirements
- Capabilities and
Characteristics
2. ConOps or Business processes
Business Requirements
Review or Proposal
Estimates are based on experience and historical data
Estimates are a ROM (rough order of magnitude) and +- 75%
Top Down
• Based on number / complexity of requirements
• Based on number / complexity of scenarios
• Based on external interface complexity
Analogous
• Estimate based on complexity of technical work products compared to similar complexity
of known completed projects.
System 1. System Requirements –
including high level test
strategy for each
requirement)
2. Preliminary Architecture
System Requirements
Review
Estimates are based on experience and/or a tool (COTS or developed) Estimates are
preliminary and +- 50%
Top Down
• Based on number / complexity of requirements (functional and non-functional)
• Based on number / complexity of scenarios
• Based on architecture complexity, technology maturity, etc.
Analogous
•Estimate based on complexity of technical work products compared to similar complexity
of known completed projects
Bottoms Up
• Estimates based on architecture
Component
(HW, SW,
Process)
1. Component Requirements
(for each SW, HW, or
process) – and test strategy.
2. System Architecture
(documenting all HW, SW,
and processes, and interfaces
between them)
3. Test Architecture defined
Preliminary Design Review Estimates usually developed using a tool (function point, COCOMO suite, number and
complexity of HW components, WBS, etc).
Estimates are detailed and +- 10%
Bottoms Up
• Estimates from each development group providing their cost and schedule based on the
requirements allocated to their component, the system architecture, and the technologies
selected.
Design, Test,
and
Production
1. HW, SW, and Process Design
2. Test strategies, plans, cases,
environment setup
3. System into Production (SW,
HW, and processes) and
Service Level Agreements
1. Critical Design
Review
2. Test Readiness
Review
3. Production Readiness
Review
Estimates are based on detailed technical work products
Bottoms Up
1.Updated cost and schedule estimates based on design details
2.Test cost and schedule updated estimates based on technical work products
3.Operational, support, and maintenance costs updated based on delivered solution
The Problem
Slide No. 17 of 30 3/1/12
• Introduction
• The Classical Systems
Challenges
• Stability and Reconstruction
• Enterprise Challenges Versus
Systems
• Learning Organizations
• Summary
Agenda
Slide No. 18 of 30 3/1/12
S&R Is A Complex System
Surprising EmergenceEvolves on Its Own as a WholeActs RobustlyThrives on DiversityMany Factors at PlayStimulates Different Perspectives Ever ChangingInforms the ObserverPerforms OpenlyInternal and External Relationships are KeySelf-OrganizedSensitive to Small EffectsExhibits Tight and Loose Couplings
System
SoS
Enterprise
ComplexSystem
From work by Brian White at Mitre and Vernon Ireland
Increases in Complexity Produces• More Stakeholders• More Requirements Creep• Potential For Funding Cuts• Complex Contractor/Subcontractor/Owner Relationships• Challenges in Expectations Management• Technology Challenges
Slide No. 19 of 30 3/1/12
How do we invest scarce resources to promote cessation of COIN and promote stability and economic development?
Conflict Spectrum
Typical Timeline for a Typical Regional Conflict
Year 1 2 3 4 5 6 7 8 9 10
Non-intervention Stabilization and Reconstruction (S&R)
Large-ScaleCrisis
orHostilities
Res
ourc
es
COIN and/orCapacity DevelopmentNation Reconstruction
Capacity DevelopmentNation Reconstruction R
esou
rces
for
Cap
acity
Dev
elop
men
t, R
econ
stru
ctio
n, C
ultu
ral
Tran
sfor
mat
ion
and
Und
erst
andi
ngMission of the Center is to change how and whenresources are allocated
Slide No. 20 of 30 3/1/12
Some Thoughts About Stability and Reconstruction
Most of the challenges of reconstruction are social – values, corruption, traditional power bases, etc.Little thought given to the total ownership costs or how to sustain solutionsSuccess is directly related to the lack of complexityWe often do not understand the second order effectsMust balance top down versus bottom ups developmentNon government organizations are the best executors of bottoms up development
Top DownViability of Government
GovernanceLegitimacy
Sustainable and Enduring Development
Bottom Up
Effective Allocation of Resources
DoD
Incr
emen
tal C
osts
(Bill
ions
of F
Y 2
004
Dol
lars
)
S&RCosts
Fiscal years 1991-2004
200
150
100
50
0
Major Combat Operations
Southwest Asia
Somalia
Haiti
Bosnia
Kosovo
Afghanistan
Iraq
Source DoD Comptroller and Congressional Research ServiceIncremental Costs are defined as costs to DoD in excess of normal peacetime operating expensesSlide taken from Defense Science Board 2004 Summer Study on Transition to and from HostilitiesCurrent Incremental Cost in Iraq/Afghanistan is $5.7 billion/month
MajorCombatOperations
Slide No. 21 of 30 3/1/12
• Introduction
• The Classical Systems
Challenges
• Stability and
Reconstruction
• Life Cycle
Considerations
• Summary
Agenda
Design
From the Perspective of the Developer
ProductDevelopment
ProductConception
Production
R&D Cost
Operations andSupport Costs
Disposal Costs
Life Cycle Cost
Logistics Retirement
CapitalInvestment
Slide No. 22 of 30 3/1/12
Life Cycle Categories
Life Cycle Cost Categories
Slide No. 23 of 30 3/1/12
Cost And Schedule OverrunsOn Time, On Budget
Project
Cost Estimators Challenges
Slide No. 24 of 30 3/1/12
Factors That Can Increase Prices
• Incomplete product specifications
• Evolving requirements
• Frequent change requests
• Supplier not meeting commitment (consistently late deliveries, etc.)
• Frequent management/key personnel changes
• Outsourcing
• Product is too complex
• Technology is not mature
• Lack of customer involvement
• Increased software requirements
• COIN
• Corruption
• Lack of competition
• Inefficient ownership (not wholly owned)
• Domain knowledge
• Lack of customer involvement
• Formal legal system
• Lack of infrastructure
• Product is to complex
• Lack of the human capital
• Infrastructure support
• Suppliers
Typical Complex System Reconstruction Project
Slide No. 25 of 30 3/1/12
Project Management
Hardware
Systems Engineering
Life Cycle
Software
Integration
Components of Systems Costing
Both are complex technical, economic, and sociological systems
Traditional Systems Costing
Reconstruction Costing
Project Management
Infrastructure Support
Unknown
Life Cycle
Acquisition/Construction
Social Considerations
Slide No. 26 of 30 3/1/12
Construction Costs (10-
15%)
Operations and Maintenance of Facility (85-
90%)
Supporting Infrastructure and Services Road improvements, Power, People, Equipment, Training, etc.
Components of S&R Costing
Capacity development must be considered in any nation building project
Slide No. 27 of 30 3/1/12
• Introduction
• The Classical Systems
Challenges
• Stability and
Reconstruction
• Life Cycle
Considerations
• Summary
Agenda
Slide No. 28 of 30 3/1/12
• About $1.4T has been spent by the US in
Iraq/Afghanistan since 2001
• Several hundred $B ($53B in Iraq) between DoS,
USAID, DoD/CERP, DoJ, DoA, NGOs, etc. for
reconstruction and not stability operations
• Poor job of building partner capacity and
sustainable development
• Traditional methods (PCE, Bottoms up, etc) of
cost estimating are difficult to use
• We must take a holistic approach to
reconstruction projects ….addressing only
acquisition costs waste scarce resources
Summary
“This is the fault of the Americans,” the deputy minister of electricity, Ra’adal-Haras, said. “They put in place a big, wide-open democracy after the regime. They went from zero democracy to 100 percent. Democracy has to be step by step. You see the result. (from the NY Times)
Slide No. 29 of 30 3/1/12
Summary
For Systems We MustChange the acquisition system – DoD 5000Write good requirementsExperienced SE, PM, etc., throughout the life cycleOpenness must drive solutionsBuy it only if we can pay the TOCInstill a TOC perspectiveBetter manage early cost expectationsIncentivize contractors to save moneyDevelop SoS and complex systems methods
For Stability and Reconstruction We MustInvest in capacity development before projectsInvest in the NGOs (bottoms up)Ensure that the projects align with international goalsUnderstand the second order effectsDo no judge (or contract) based upon our values
Slide No. 30 of 30 3/1/12
Portfolio Problem
…. and that’s everything you need to know about life cycle cost analysis .. any questions
Questions