21
System Engineering & Economy Analysis Lecturer Maha Muhaisen College of Applied Engineering& Urban Planning

System Engineering & Economy Analysis Lecturer Maha Muhaisen College of Applied Engineering& Urban Planning

Embed Size (px)

Citation preview

Page 1: System Engineering & Economy Analysis Lecturer Maha Muhaisen College of Applied Engineering& Urban Planning

System Engineering & Economy Analysis

Lecturer

Maha Muhaisen

College of Applied Engineering& Urban Planning

Page 2: System Engineering & Economy Analysis Lecturer Maha Muhaisen College of Applied Engineering& Urban Planning

Lecture (2)

• Decision making process, include :

- Rational Decision making

- Decision making for current cost

- Examples

Page 3: System Engineering & Economy Analysis Lecturer Maha Muhaisen College of Applied Engineering& Urban Planning

Decision making process

• It is the choosing from alternatives, but is this enough for definition?

Page 4: System Engineering & Economy Analysis Lecturer Maha Muhaisen College of Applied Engineering& Urban Planning

Rational Decision Making

• Rational decision making is a complex process that contain nine essential elements.

• Although those nine steps are shown sequentially it is common for decision making to repeat the steps.

• All those steps is required and shown in a logical order.

Page 5: System Engineering & Economy Analysis Lecturer Maha Muhaisen College of Applied Engineering& Urban Planning
Page 6: System Engineering & Economy Analysis Lecturer Maha Muhaisen College of Applied Engineering& Urban Planning

1- Recognize the problem1- Recognize the problem

• Recognition of the problem is obvious and immediate

• Many firms establish programs for total quality management (TQM) or continuous improvement that are designed to identify the problems, so that they can be solved.

Page 7: System Engineering & Economy Analysis Lecturer Maha Muhaisen College of Applied Engineering& Urban Planning

2- Define the Goal or objective2- Define the Goal or objective

• The goal can be a grand, overall goal of a person or a firm.• The presence of multiple goal is often foundation of

complex problem.• But the objective need not to be a grand but the overall

objective may be specific and narrow. “I want to pay a load by may”

• So defining the objective is the act of exactly describing the task and goal

Page 8: System Engineering & Economy Analysis Lecturer Maha Muhaisen College of Applied Engineering& Urban Planning

3- Assemble of relevant data• Good decision good information

• Some data are available immediately at little or no cost, but still other require survey, or consulting with specific knowledgeable people

• Time horizon is part of data as how long equipment, building will last?

• Accounting system is of important source of data

• Financial and cost accounting are designed to show accounting values and the flow of money (cost & benefit)

• What are the cost that related to specific operation , those indirect (overhead) cost, that usually allocated to operations, those may be satisfactory for cost –accounting purposes, but may be unreliable for economic analysis.

• To understand the meaningful analysis see the following example :

Page 9: System Engineering & Economy Analysis Lecturer Maha Muhaisen College of Applied Engineering& Urban Planning

Example• The cost accounting records of a large company show the avg. monthly costs

for the three persons printing dep. The wages of the three dep. members and benefits such as vacation, sick leave, make up the first category of the direct labor. The company’s indirect or overhead costs – such heat , electricity, …etc must be distributed to its various departments in some manner , this one uses floor space as basis for its allocations

• Direct labor cost $6000

• Material and supplies consumed $7000

• Allocated overhead costs

200m2 of the floor area at $25/m2 $5000

The total $ 18000

• The printing dep. charges other dep. for its services to cover 18,000$ monthly cost. For example , the charge to run 1000 copies of an announcement is :

• Direct labor 7.6 $

• Material and supplies 9.8 $

• Over head 9.05

Cost to other dep.s 26.45 $

Page 10: System Engineering & Economy Analysis Lecturer Maha Muhaisen College of Applied Engineering& Urban Planning

Cont.

The shipping dep. checks with a commercial printer which would print 1000 copies for $ 22.95 although the shipping dep. needs only about 30,000 copies printed a month, its Forman decision to stop printing dep. and have work done by outside printer. The manger has asked to study situation and recommend what should be done.

Solution :

Printing dep. Outside Printer

1000 copies

30,000 copies

1000 copies 30,000 copies

Direct cost $ 7.6 $ 228.00

Material and supplies 9.8 294.00 $ 22.95 $ 688.5

overhead 9.05 271.5

Total $ 26.45 $ 793.5 $ 22.95 $ 688.5

Page 11: System Engineering & Economy Analysis Lecturer Maha Muhaisen College of Applied Engineering& Urban Planning

• The firm will save $ 294 in material and may or may not save $ 228 in direct labor if printing dep. no longer does the shipping dep. work.

• The max. saving will be 294 + 228= $ 522

• But if the shipping dep. Is permitted to obtain its printing from outside, the firm will be 688.5$ a month.

• The saving from not doing the shipping dep. work in printing de. Would not exceed $ 522 and it is probably would be $ 294

• The result would be a net increase in cost to firm. For this reason it is not encouraged to print outside.

• Data cost gathering present other difficulty. One way to look at financial consequences , cost-benefit, of various alternative :

• Market consequences : raw material, machinery cost, ..etc.

• Extra market consequences : (shadow prices) as cost of employee injury,…ect.

• Intangible consequences : numerical analysis probably never fully describe the difference between alternative.

• As how does one evaluate the potential loss of worker’s job due to automation ?

Cont.

Page 12: System Engineering & Economy Analysis Lecturer Maha Muhaisen College of Applied Engineering& Urban Planning

4. Identify feasible alternative

• There is no way to ensure the best alternative is listed among the alternatives considered.

• Sometime a group of people considering alternative in an innovative atmosphere ( brainstorming) can be helpful

• Any good listing of alternative will produce both practical and impractical solutions.

• Only feasible alternative are retained for further analysis.

Page 13: System Engineering & Economy Analysis Lecturer Maha Muhaisen College of Applied Engineering& Urban Planning

5. Select the criterion to determine the best 5. Select the criterion to determine the best alternativealternative

• To choose the best alternative , we must define what we mean by best.

• Criterion or set of criteria must be judged.

• Worst – Bad – Fair – Good – Better – Best

• Several possible criteria are :

– create the least disturbance to the environment

– Improve the distribution of the wealth among people.

– Minimize the expenditure

– Ensure that benefit greater that losses

– Minimize the time to achieve the goal

– Minimize unemployment

– Maximize profit

• Maximize profit is normally selected in engineering decision . When it is used all problems fall into one of the three categories :

• fixed output , fixed input, or neither input nor output.

Page 14: System Engineering & Economy Analysis Lecturer Maha Muhaisen College of Applied Engineering& Urban Planning

Cont.• Fixed input : the amount of money or other input resources (like

labor, material, or equipment) . The objective is no effectively utilize them.

• Example :

– A project engineer has a budget of 350,000$ to renovate a portion of petroleum refinery.

• For ecom\nomic efficiency, the appropriate criterion is to maximize benefits or outputs.

• Fixed output : there is a fixed task (or other output objectives / results) to be accomplished

• Example:

• Civil engineer firm has been given a job of surveying land and preparing a record of survey map.

• purchasing a car without any optional equipment.

Page 15: System Engineering & Economy Analysis Lecturer Maha Muhaisen College of Applied Engineering& Urban Planning

• Neither input nor output fixed : It is the general situation, whereas the amount of money or inputs is not fixed, nor is the amount of benefits or other output.

• Example:

• A consulting eng. Firms has a lot of work, and paying for the staff for evening works to increase the amount of design work.

In this category, maximize the benefit is the criterion, since the difference between input and output is simply the profit.

Cont.

Page 16: System Engineering & Economy Analysis Lecturer Maha Muhaisen College of Applied Engineering& Urban Planning

Cont.

Category Economic Criterion

Fixed input Maximize benefit or other outputs

Fixed output Minimize the costs or other inputs

Neither input nor output

Maximize (benefits or, other output minus costs or other input) or stated another way, maximize profit.

Page 17: System Engineering & Economy Analysis Lecturer Maha Muhaisen College of Applied Engineering& Urban Planning

6. Constructing the model

• Putting various elements together (objective, relevant data, feasible alternatives, and selection criteria)

• Relationship between the elements called model building or constructing model.

• To an engineer, the model is a mathematical equations.

Page 18: System Engineering & Economy Analysis Lecturer Maha Muhaisen College of Applied Engineering& Urban Planning

7. Predicting the outcomes for each alternative.

• Each alternative might produce a variety of outcomes. Studying each alterntive and outcomes for eveyone.

Page 19: System Engineering & Economy Analysis Lecturer Maha Muhaisen College of Applied Engineering& Urban Planning

8. Choose the best alternative

• The selection of the feasible alternative may be key item, with the rest of the analysis a methodical process leading to predictable decision.

Page 20: System Engineering & Economy Analysis Lecturer Maha Muhaisen College of Applied Engineering& Urban Planning

9. Audit the results• It the comparison of what happened against predication.

• Do the results of decision agree with its predications?

• The audit help ensure that projected operating advantages are ultimately obtained.

• On other hand, the economic decision may be unjustifiably optimistic.

Page 21: System Engineering & Economy Analysis Lecturer Maha Muhaisen College of Applied Engineering& Urban Planning

Example• A concrete aggregate mix is required to contain at least 31% sand by volume for proper

batching. One source of material, which has 25% sand and 75% coarse aggregate, sells for $3 per cubic meter (m3). Another source, which has 40% sand and 60% coarse aggregate, sells for $4.40/m3.

Determine the least cost per cubic meter of blended aggregates.SolutionSolution :• The least cost of blended aggregates will result from maximum use of the lower-cost

material. The higher-cost material will be used to increase the proportion of sand up to the minimum level (3 1%) specified.

• Let x = Portion of blended aggregates from $3.00/m3 source• 1 - x = Portion of blended aggregates from $4.40hi3 sourceSand BalanceX(0.25) + (1 -x)(0.40) = 0.310.25x + 0.4-0.4x = 0.31 0.31 – 0.4 = -0.09 0.25 - .04 -0.15 Thus the blended aggregates will contain : 60% of $3.0m3 material, 40% of $4.40/m3

materialThe least cost per cubic meter of blended aggregates is: 0.6($3.00)+ 0.4($4.4) = 1.8+1.76 = $3.56 / m3