60
SVENSKA KRAFTNÄT SWEDISH NATIONAL GRID February 14*, 2014 2014/228 Swedish Interconnectors COMP Case No 39351 Monitoring Report No 10

SWEDISH NATIONAL GRID - Start | Svenska kraftnät corridors between internal areas SE1-SE2 SE2-SE3 SE3-SE4 SEi-FI SE1-NO4 SE2-NO3 SE2-NO4 SE3-DK1 SE3-FI SE3-NO1 SE4-DE SE4-DK2 SE4-PL

Embed Size (px)

Citation preview

SVENSKA KRAFTNÄT SWEDISH NATIONAL GRID

February 14*, 2014 2014/228

Swedish Interconnectors COMP Case No 39351

Monitoring Report No 10

Introduction This report is submitted to comply with section 5 (Monitoring provisions) of Svenska kraftnät' s Commitments (26 January 2010) under Artide 9 of Council Regulation No. 1/2003 in connection with the European Commission investigation in Case COMP/39351 - Swedish Interconnectors. The Commitments were adopted and made binding by decision of the Commission on 14 April 2010. Regarding this, Svenska kraftnät would like to emphasize that that we are monitoring the development of the European Network Codes continuously and how they will reläte to our Commitment.

The report is prepared in good faith and aims at providing any information the Commission may need in order to judge whether Svenska kraftnät is proceeding in accordance with the Commitments. Additional information can be provided to the Commission upon request.

In accordance with what was stated in last (ninth) monitoring report this tenth monitoring report has been submitted before 14 February 2014.

In order to have sufficient time for proper assessments (in line with what is stated in the Commitment) and internal processes the next (eleventh) monitoring report will be submitted by 13 February 2015 at latest, covering the whole year of 2014.

Svenska kraftnät confirms that the report does not contain any confidential information and may be freely distributed to third parties.

Sundbyberg, February 14* 2014

^m Mikael Odeiroerg

Table of Contents

i Capacities and prices after introduction of bidding zones 7

1.1 2013 Qi 7 1.1.1 Allocation of trading capacity 8 1.1.2 Comments on each interconnector 12

1.2 2013 Q2 14 1.2.1 Allocation of trading capacity 15 1.2.2 Comments on each interconnector 19

1.3 2013Q3 21

1.3.1 Allocation of trading capacity 22 1.3.2 Comments on each interconnector 26

1.4 2013 Q4 2& 1.4.1 Allocation of trading capacity 29 1.4.2 Comments on each interconnector 33

Appendix A - 2 0 1 3 Qi 35

Appendix B - 2013 Q2 42

Appendix C - 2013 Q3 49

Appendix D - 2013 Q4 55

i Capacities and prices after introduction of bidding zones

As committed, Svenska kraftnät has subdivided the Swedish part of the Nordic electricity märket into several bidding zones and the Swedish Transmission System is operated on this basis since November i, 2011. Congestion in the Swedish Transmission System, with exception of Congestion in the West Coast Corridor, is generally managed without limiting Trading Capacity on Interconnectors. This can be seen in subsequent chapters, and is particularly evident in Table 3, Table 8, Table 13 and Table 18.

1.1 2013 Qi This section describes operational experience and measures regarding allocation of trading capacity in the period January 1 to March 31, 2013.

In the period, totally 2 159 hours, the main direction of the power flow was southbound.

Table 1 below shows the average prices in Sweden and all neighbouring areas for the above mentioned period (excluding Germany and Poland). Table 2 summarises the number of hours where price differences occurred between the respective zones.

Area

SEi

SE2

SE3

SE4

DKi

DK2

Fl

NOi

NO3

NO4

Average Price Level

(EUR)

41,85

41,85

42,01

42,16

40,19

40,91

42,09

42,51

41,90

41,85

Maximum Price

(EUR)

95,69

95,69

98,51

98,51

98,51

98,51

199,95

98,51

95,69

95,69

Minimum Price

(EUR)

21,81

21,8l

21,81

21,81

-0,07

-0,07

21,8l

29,74

28,61

28,61

Table l. Average, maximum, and minimum prices for areas within Nord Pool Spöt.

7/60

N o of h o u r s w h e r e p r i c e f o r r o w a r e a > c o l u m n a r e a

SEi

SE2

S E 3

SE4

DKi

DK2

F l

N O i

N O 3

NO4

S E i

-

0

32

100

264

254

125

678

74

54

SE2

0

-

32

100

264

254

125

678

74

54

SE3

0

0

-

6 8

234

224

121

646

74

54

SE4

0

0

0

-

219

2 0 3

114

646

74

54

DKi

644

644

644

657

-

339

701

918

6 6 0

659

DK2

392

392

392

392

6 8

-

476

738

414

4 0 7

F l

8

8

34

101

262

250

-

667

79

61

N O i

16

16

16

75

231

225

123

-

27

26

NO3

0

0

32

100

264

254

125

668

-

0

NO4

25

25

56

122

282

275

150

6 9 0

46

-

Table 2. Number of hours where the price for the area in the row was higher than for the area in the column.

Summary of Table 1 and 2:

• NOi had the highest average price, followed by SE4, Fl, SE3, NO3, NO4, SEi, SE2, DK2 and DKi respectively

• SEi and SE2 had a common price during all hours.

1.1.1 Allocation of trading capacity Table 3 below summarises how often Svenska kraftnät have allocated less trading capacity than maximum NTC for interconnectors and corridors between internal areas in the period.

8/60

Interconnectors /

corridors b e t w e e n

internal areas

SE1-SE2

SE2-SE3

SE3-SE4

SEl-FI

SE1-NO4

SE2-NO3

SE2-NO4

SE3-DK1

SE3-FI

SE3-NO1

SE4-DE

SE4-DK2

SE4-PL

N o of l imited hours

Export/ South­bound

109

2159

2159

2159

1 0

0

0

354

2159

1257

0

264

0

Import / North­b o u n d

0

0

0

0

10

0

0

1429

2159

0

1180

1361

1144

N o of days with l imitat ion

Export/ South­b o u n d

5

90

90

90

1

0

0

15

90

89

0

11

0

Import / North­bound

0

0

0

0

1

0

0

90

90

0

89

90

89

Average reduct ion

Export/ South­b o u n d

0%

5 %

7%

4%

0%

0%

0%

8%

3 5 %

19%

0 %

3 %

0%

Import / North­b o u n d

0 %

0 %

0%

-5%

0%

0%

0%

27%

3 5 %

0 %

18%

2 1 %

16%

Table 3. Limitations in trading capacity on interconnectors and corridors between internal areas as enforced by Svenska kraftnät. The columns with average reductions shows the average NTC divided by maximum NTC.

The majority of the limitations of export capacity on the interconnector SEl-FI, enforced by Svenska kraftnät during the period, are because of that the NTC depends on forecasted transfer between Kalix - Ossauskoski and Ivalo - Varangerbotn. The forecasted transfer can both increase and decrease the NTC (which also explains the negative average reduction for SEi-FI in Table 4).

Table 4 below summarises the time during which neighbouring TSOs have allocated less trading capacity than maximum NTC to interconnectors in the period.

9/60

Interconnectors /

corridors be tween

internal areas

SE1-SE2

SE2-SE3

SE3-SE4

SEi-FI

SE1-NO4

SE2-NO3

SE2-NO4

SE3-DK1

SE3-FI

SE3-NO1

SE4-DE

SE4-DK2

SE4-PL

N o of l imited h o u r s

Export/ South­b o u n d

-

-

-

2159

2159

10

2159

366

2159

704

75

912

703

Import / North­b o u n d

-

-

-

54

2159

0

2159

366

2159

1971

802

912

2159

N o of days with l imitat ion

Export/ South­b o u n d

-

-

-

90

90

1

90

16

90

31

9

38

90

Import / North­b o u n d

-

-

-

13

90

0

90

16

90

83

49

38

90

Average reduction

Export/ South­b o u n d

-

-

-

5%

25%

0%

17%

9%

38%

5%

1%

16%

28%

Import / North­b o u n d

-

-

-

-4%

7%

0%

40%

9%

38%

14%

18%

17%

72%

Table 4. Limitations in trading capacity on interconnectors as enforced by neighbouring TSOs. The columns with average reductions shows the average NTC divided by maximum NTC.

Table 5 below summarises the time during which capacities on interconnectors and corridors between internal areas have been reduced, taking into account reductions by both Svenska kraftnät and neighbouring TSOs.

10/60

Interconnectors /

corridors be tween

internal areas

SE1-SE2

SE2-SE3

SE3-SE4

SEl-FI

SE1-NO4

SE2-NO3

SE2-NO4

SE3-DK1

SE3-FI

SE3-NO1

SE4-DE

SE4-DK2

SE4-PL

N o of l imited hours

Export/ South­b o u n d

109

2159

2159

2159

2159

10

2159

366

2159

1562

75

912

720

Import /

North­

b o u n d

0

0

0

54

2159

0

2159

1441

2159

1971

1577

1674

2159

N o of days wi th

l imitation

Export/ South­b o u n d

5

9 0

9 0

9 0

9 0

1

9 0

16

9 0

89

9

38

9 0

Import / North­b o u n d

0

0

0

13

9 0

0

9 0

9 0

9 0

8 3

9 0

9 0

9 0

Average reduction

Export/ South­b o u n d

0 %

5 %

7 %

5 %

2 5 %

0%

1 7 %

9 %

3 8 %

2 1 %

1 %

1 6 %

2 9 %

Import / North­b o u n d

0 %

0 %

0%

- 4 %

8 %

0 %

4 0 %

2 8 %

3 8 %

1 4 %

3 0 %

2 8 %

7 3 %

Table 5. Final limitations in trading capacity on interconnectors and corridors between internal areas as enforced by both Svenska kraftnät and neighbouring TSOs. The columns with average reductions shows the average NTC divided by maximum NTC.

Detailed information for each limitation is provided in the attached Tables A2 to A5 in Appendix A and in the attachment. This information includes the reason for each limitation.

11/60

1.1.2 Comments on each interconnector

SEl-FI, North Finland Svenska kraftnät has reduced the export capacity for all hours for the interconnector between SEi and Fl, because the NTC depends on forecasted transfer between Kalix - Ossauskoski and Ivalo - Varangerbotn.

SE1-NO4, North Norway Svenska kraftnät has reduced the export and import capacity for 10 hours, for the interconnector between SEi and NO4. The reason for the reduction was planned maintenance on the interconnector. In total, the export and import on the interconnector have been reduced for all hours.

SE2-NO3, Central Norway Svenska kraftnät has not reduced the capacity for the interconnector between SE2 and NO3. In total, the export and import on the interconnector have been reduced for 10 and o hours, respectively.

SE2-NO4, North Norway Svenska kraftnät has not reduced the capacity for the interconnector between SE2 and NO4. In total, the export and import on the interconnector have both been reduced for all hours.

SE3-DK1, West Denmark Svenska kraftnät has reduced the export and import capacity for 354 and 1429 hours, respectively, for the interconnector between SE3 and DKi. The main reasons for reductions set by Svenska kraftnät were congestion in the West Coast Corridor (only import reductions), as well as planned maintenance or disturbances on the interconnector (both export and import reductions). In total, the export and import on the interconnector have been reduced for 366 and 1441 hours, respectively.

SE3-FI, South Finland Svenska kraftnät has reduced the export and import capacity for all hours for the interconnector between SE3 and Fl. The main reasons for export and import reductions set by Svenska kraftnät was refurbishment of one of DC-links connecting SE3 and Fl and a cable fault on the same DC-link.

SE3-NO1, North Norway Svenska kraftnät has reduced the export and import capacity for 1257 and o hours, respectively, for the interconnector between SE3 and NOi. The main reasons for reductions set by Svenska kraftnät were congestion in the West Coast Corridor (only export reductions), as well as planned maintenance in the vicinity of the interconnector (both export and import reductions). In total, the export and import on the interconnector have been reduced for 1562 and 1971 hours, respectively.

SE4-DE, Germany Svenska kraftnät has reduced the export and import capacity for o and 1180 hours, respectively, for the interconnector between SE4 and DE. The reason for reductions set by Svenska kraftnät was congestion in the West Coast Corridor (only import reductions). In total, the export and import on the interconnector have been reduced for 75 and 1 577 hours, respectively.

12/60

SE4-DK2, East Denmark Svenska kraftnät has reduced the export and import capacity for 264 and 1361 hours, respectively, for the interconnector between SE4 and DK2. The main reasons for reductions set by Svenska kraftnät were congestion in the West Coast Corridor (only import reductions), as well as planned maintenance on the interconnector (both export and import reductions). In total, the export and import on the interconnector have been reduced for 912 and 1674 hours, respectively.

SE4-PL, Poland Svenska kraftnät has reduced the export and import capacity for o and 1144 hours, respectively, for the interconnector between SE4 and PL. The reason for reductions set by Svenska kraftnät was congestion in the West Coast Corridor (only import reductions). In total, the export and import on the interconnector have been reduced for 720 and 2 159 hours, respectively.

13/60

1.2 2013 Q2 This section describes operational experience and measures regarding allocation of trading capacity in the period April i to June 30, 2013.

In the period, totally 2 184 hours, the main direction of the power flow was southbound.

Table 6 below shows the average prices in Sweden and all neighbouring areas for the above mentioned period (excluding Germany and Poland). Table 7 summarises the number of hours where price differences occurred between the respective zones.

A r e a

SEi

SE2

SE3

SE4

DKi

DK2

Fl

NOi

NO3

NO4

Average P r i c e Level

(EUR)

38,30

38,30

38,30

38,45

42,40

38,41

39,93

39,03

39,16

38,44

M a x i m u m Pr i ce

(EUR)

109,55

109,55

109,55

109,55

2 000,00

109,55

120,07

109,55

109,55

109,55

M i n i m u m P r i c e

(EUR)

1,38

1,38

1,38

1,38

1,38

1,38

1,38

1,38

1,38

1,38

Table 6. Average, maximum, and minimum prices for areas within Nord Pool Spöt.

14/60

No of hours where price for row area > column area SEi

SE2

S E 3

SE4

DKi

DK2

F l

N O i

N O 3

NO4

S E i

-

0

0

53

174

157

244

6 2 8

3 9 8

293

SE2

0

-

0

53

174

157

244

6 2 8

3 9 8

2 9 3

SE3

0

0

-

53

174

157

244

6 2 8

3 9 8

293

SE4

0

0

0

-

151

124

244

623

3 9 8

293

DKi

3 2 8

3 2 8

3 2 8

347

-

299

495

731

654

550

DK2

79

79

79

79

71

-

3 2 0

641

447

342

F l

0

0

0

35

1 5 2

135

-

625

3 9 8

2 9 3

N O i

449

449

449

4 6 0

4 3 0

4 8 4

543

-

576

478

NO3

57

57

57

1 0 2

194

172

3 0 0

6 0 0

-

11

NO4

183

183

183

224

3 0 0

289

4 0 9

715

2 0 3

-

Table 7. Number of hours where the price for the area in the row was higher than for the area in the column.

Summary of Table 6 and 7:

• DKi had the highest average price, followed by Fl, NO3, NOi, SE4, NO4, DK2, SEi, SE2 and SE3 respectively

• SEi, SE2 and SE3 had a common price during all hours.

1.2.1 Allocation of trading capacity Table 8 below summarises how often Svenska kraftnät have allocated less trading capacity than maximum NTC for interconnectors and corridors between internal areas in the period.

15/60

Interconnectors /

corridors be tween

internal areas

SE1-SE2

SE2-SE3

SE3-SE4

SEl-FI

SE1-NO4

SE2-NO3

SE2-NO4

SE3-DK1

SE3-FI

SE3-NO1

SE4-DE

SE4-DK2

SE4-PL

N o of l imited hours

Export/ South­b o u n d

817

2184

2184

1749

56

15

12

490

2184

1393

46

161

276

Import / North­b o u n d

0

0

0

371

56

15

0

1240

2184

418

1069

1209

1094

N o of days wi th l imitat ion

Export/ South­b o u n d

35

91

91

79

5

1

1

2 2

91

79

4

9

14

Import / North­b o u n d

0

0

0

2 1

5

1

0

71

91

19

71

76

72

Average reduction

Export/ South­b o u n d

3 %

15%

19%

3%

2 %

0 %

0 %

1 2 %

18%

24%

1 %

2 %

1 2 %

Import / North­b o u n d

0%

0%

0%

3%

2 %

1 %

0 %

31%

3 2 %

1 1 %

2 0 %

23%

25%

Table 8. Limitations in trading capacity on interconnectors and corridors between internal areas as enforced by Svenska kraftnät. The columns with average reductions shows the average NTC divided by maximum NTC.

The majority of the limitations of export capacity on the interconnector SEl-FI, enforced by Svenska kraftnät during the period, are because of that the NTC depends on forecasted transfer between Kalix - Ossauskoski and Ivalo - Varangerbotn. The forecasted transfer can both increase and decrease the NTC (which also explains the negative average reduction for SEl-FI in Table 9).

Table 9 below summarises the time during which neighbouring TSOs have allocated less trading capacity than maximum NTC to interconnectors in the period.

16/60

Interconnectors / corridors be tween internal areas

SE1-SE2

SE2-SE3

SE3-SE4

SEl-FI

SE1-NO4

SE2-NO3

SE2-NO4

SE3-DK1

SE3-FI

SE3-NO1

SE4-DE

SE4-DK2

SE4-PL

N o of l imited hours

Export/ South­bound

-

-

-

1782

2184

602

2184

727

2184

954

119

472

968

Import / North­b o u n d

-

-

-

314

2184

0

2184

727

2184

1653

606

472

2184

N o of days with l imitation

Export/ South­b o u n d

-

-

-

80

91

31

91

32

91

44

9

2 2

91

Import /

North­

b o u n d

-

-

-

19

91

0

91

32

91

70

38

2 2

91

Average reduction

Export/ South­b o u n d

-

-

-

3%

31%

1 0 %

27%

16%

17%

1 2 %

2 %

6%

40%

Import / North­b o u n d

-

-

-

- 2 %

15%

0 %

4 2 %

14%

17%

2 0 %

13%

9%

78%

Table 9. Limitations in trading capacity on interconnectors as enforced by neighbouring TSOs. The columns with average reductions shows the average NTC divided by maximum NTC.

Table 10 below summarises the time during which capacities on interconnectors and corridors between internal areas have been reduced, taking into account reductions by both Svenska kraftnät and neighbouring TSOs.

17/60

Interconnectors / corridors b e t w e e n internal areas

SE1-SE2

SE2-SE3

SE3-SE4

SEl-FI

SE1-NO4

SE2-NO3

SE2-NO4

SE3-DK1

SE3-FI

SE3-NO1

SE4-DE

SE4-DK2

SE4-PL

N o of l imited hours

Export/ South­b o u n d

817

2184

2184

1785

2184

617

2184

727

2184

1737

165

633

998

Import / North­b o u n d

436

2184

15

2184

1420

2184

1751

1520

1457

2184

N o of days with l imitation

Export/ South­b o u n d

35

91

91

81

91

32

91

32

91

83

13

31

91

Import / North­b o u n d

26

91

1

91

76

91

74

84

80

91

Average reduct ion

Export/ South­b o u n d

3%

15%

19%

3%

32%

11%

27%

17%

20%

30%

3%

9%

4 1 %

Import / North­b o u n d

0%

0%

0%

3 %

16%

1%

42%

3 3 %

3 4 %

28%

3 1 %

29%

7 8 %

Table 10. Final limitations in trading capacity on interconnectors and corridors between internal areas as enforced by both Svenska kraftnät and neighbouring TSOs. The columns with average reductions shows the average NTC divided by maximum NTC.

Detailed information for each limitation is provided in the attached Tables B2 to B5 in Appendix B and in the attachment. This information includes the reason for each limitation.

18/60

1.2.2 Comments on each interconnector

SEl-FI, North Finland Svenska kraftnät has reduced the export and import capacity for 1749 and 371 hours, respectively, for the interconnector between SEi and FL The export was reduced for most hours during the period, because the NTC depends on forecasted transfer between Kalix - Ossauskoski and Ivalo - Varangerbotn (and the forecasted transfer can both increase and decrease the NTC).

Reasons for export reductions set by Svenska kraftnät were planned maintenances in the vicinity of the interconnector and due to failure on the interconnector. The import reductions were due to planned maintenances, and failure, in the vicinity of the interconnector. In total, the export and import on the interconnector have been reduced for 1785 and 436 hours, respectively.

SE1-NO4, North Norway Svenska kraftnät has reduced the export and import capacity for 56 and 56 hours, respectively, for the interconnector between SEi and NO4. The reasons for reductions set by Svenska kraftnät were planned maintenances on and in the vicinity of the interconnector for export, and on the interconnector for import. In total, the export and import on the interconnector have been reduced for 2 184 and 2 184 hours, respectively.

SE2-NO3, Central Norway Svenska kraftnät has reduced the export and import capacity for 15 and 15 hours, respectively, for the interconnector between SE2 and NO3. The only reason for reducing the capacity to and from NO3 set by Svenska kraftnät was planned maintenance in the vicinity of the interconnector. In total, the export and import on the interconnector have been reduced for 617 and 15 hours, respectively.

SE2-NO4, North Norway Svenska kraftnät has reduced the export and import capacity for o and o hours, respectively, for the interconnector between SE2 and NO4. In total, the export and import on the interconnector have been reduced for 2 184 and 2 184 hours, respectively.

SE3-DK1, West Denmark Svenska kraftnät has reduced the export and import capacity for 490 and 1240 hours, respectively, for the interconnector between SE3 and DKi. The main reasons for reductions set by Svenska kraftnät were congestion in the West Coast Corridor (only import reductions), as well as planned maintenances on and in the vicinity of the interconnector (both export and import reductions). In total, the export and import on the interconnector have been reduced for 727 and 1420 hours, respectively.

SE3-FI, South Finland Svenska kraftnät has reduced the export and import capacity for 2 184 and 2 i84hours, respectively, for the interconnector between SE3 and Fl. The reasons for export and import reductions set by Svenska kraftnät were planned maintenances on and in the vicinity of the interconnector, but also due to failure on the interconnector. In addition, during warm weather (typically summer time) the capacity between Southern Finland and Sweden is reduced by 50 MW, because of higher cable temperature. In total, the export and import on the interconnector have been reduced for 2 184 and 2 184 hours, respectively.

19/60

SE3-NO1, North Norway Svenska kraftnät has reduced the export and import capacity for 1393 and 418 hours, respectively, for the interconnector between SE3 and NOi. The main reasons for reductions set by Svenska kraftnät were congestion in the West Coast Corridor (only export reductions), as well as planned maintenances on and in the vicinity of the interconnector (both export and import reductions). In total, the export and import on the interconnector have been reduced for 1737 and 1751 hours, respectively.

SE4-DE, Germany Svenska kraftnät has reduced the export and import capacity for 46 and 1069 hours, respectively, for the interconnector between SE4 and DE. The main reasons for reductions set by Svenska kraftnät were congestion in the West Coast Corridor (only import reductions), as well as planned maintenances in the vicinity of the interconnector (both export and import reductions). In total, the export and import on the interconnector have been reduced for 165 and 1520 hours, respectively.

SE4-DK2, East Denmark Svenska kraftnät has reduced the export and import capacity for 161 and 1 209 hours, respectively, for the interconnector between SE4 and DK2. The main reasons for reductions set by Svenska kraftnät were congestion in the West Coast Corridor (only import reductions), as well as planned maintenances in the vicinity of the interconnector (both export and import reductions). In total, the export and import on the interconnector have been reduced for 633 and 1457 hours, respectively.

SE4-PL, Poland Svenska kraftnät has reduced the export and import capacity for 276 and 1098 hours, respectively, for the interconnector between SE4 and PL. The main reasons for reductions set by Svenska kraftnät were congestion in the West Coast Corridor (only import reductions), as well as planned maintenances on and in the vicinity of the interconnector (both export and import reductions). In total, the export and import on the interconnector have been reduced for 998 and 2 184 hours, respectively.

20/60

1.3 2013 Q3 This section describes operational experience and measures regarding allocation of trading capacity in the period July i to September 30, 2013.

In the period, totaUy 2 208 hours, the main direction of the power flow was southbound.

Table 11 below shows the average prices in Sweden and all neighbouring areas for the above mentioned period (excluding Germany and Poland). Table 12 summarises the number of hours where price differences occurred between the respective zones.

A r e a

SEi

SE2

SE3

SE4

DKi

DK2

Fl

NOi

NO3

NO4

Average Pr ice Level

(EUR)

39,68

39,68

40,04

40,37

39,99

41,32

42,70

33,73

37,78

37,18

M a x i m u m Pr ice

(EUR)

74,33

74,33

79,98

79,98

130,27

130,27

120 ,00

39,68

64,51

64,51

M i n i m u m P r i c e

(EUR)

9,84

9,84

9,84

9,84

5,83

5,83

9,84

16,12

10,66

10,66

Table 11. Average, maximum, and minimum prices for areas within Nord Pool Spöt.

21/60

No of hours where price for row area > column area S E i

SE2

S E 3

SE4

DKi

DK2

F l

N O i

N O 3

N O 4

S E i

-

0

8 9

199

4 6 7

465

678

46

14

14

SE2

0

-

89

199

467

465

678

4 6

14

14

SE3

0

0

-

1 2 0

411

4 0 7

6 0 8

46

14

14

SE4

0

0

0

-

376

362

5 8 8

46

14

14

DKi

644

644

644

655

-

6 0 9

1090

3 3 3

642

642

DK2

63

63

63

63

2 8

-

624

8 3

74

74

F l

0

0

9

79

3 2 8

316

-

46

14

14

N O i

1563

1563

1563

1598

1214

1576

1739

-

1564

1564

NO3

636

636

687

770

825

872

1070

46

-

1

NO4

734

734

763

8 3 8

8 6 5

9 2 3

1135

46

229

-

Table 12. Number of hours where the price for the area in the row was higher than for the area in the column.

Summary of Table 11 and 12:

• Fl had the highest average price, followed by DK2, SE4, SE3, DKi, SEi, SE2, NO3, NO4 and NOi respectively

• SEi and SE2 had a common price during all hours.

1.3.1 Allocation of trading capacity Table 13 below summarises how often Svenska kraftnät have allocated less trading capacity than maximum NTC for interconnectors and corridors between internal areas in the period.

22/60

Interconnectors / corridors be tween internal areas

SE1-SE2

SE2-SE3

SE3-SE4

SEl-FI

SE1-NO4

SE2-NO3

SE2-NO4

SE3-DK1

SE3-FI

SE3-NO1

SE4-DE

SE4-DK2

SE4-PL

N o of l imited hours

Export/ South­bound

7 6 1

2 2 0 8

2 2 0 8

2 0 4 0

0

0

87

948

2 2 0 8

8 0 7

1 8 4

2 1 6

101

Import / North­bound

0

0

0

5 4 0

537

0

6 1

1433

2 2 0 8

3 2 9

5 4 1

547

4 5 1

N o of days with l imitat ion

Export/ South­b o u n d

34

9 2

9 2

85

0

0

7

4 1

9 2

5 2

10

11

5

Import / North­b o u n d

0

0

0

2 6

2 9

0

3

79

9 2

16

44

43

39

Average reduction

Export/ South­bound

8%

1 8 %

2 5 %

5%

0%

0%

3%

2 5 %

1 6 %

1 3 %

6%

5%

2 %

Import /

North­

b o u n d

0 %

0 %

0 %

1 %

6%

0 %

3 %

3 8 %

3 8 %

5 %

1 2 %

1 0 %

8 %

Table 13. Limitations in trading capacity on interconnectors and corridors between internal areas as enforced by Svenska kraftnät. The columns with average reductions shows the average NTC divided by maximum NTC.

The majority of the limitations of export capacity on the interconnector SEl-FI, enforced by Svenska kraftnät during the period, are because of that the NTC depends on forecasted transfer between Kalix - Ossauskoski and Ivalo - Varangerbotn. The forecasted transfer can both increase and decrease the NTC (which also explains the negative average reduction for SEl-FI in Table 13 and 14).

Table 14 below summarises the time during which neighbouring TSOs have allocated less trading capacity than maximum NTC to interconnectors in the period.

23/60

Interconnectors / corridors b e t w e e n internal areas

SE1-SE2

SE2-SE3

SE3-SE4

SEl-FI

SE1-NO4

SE2-NO3

SE2-NO4

SE3-DK1

SE3-FI

SE3-NO1

SE4-DE

SE4-DK2

SE4-PL

N o of l imited hours

Export/ South­b o u n d

-

-

-

2023

2208

727

2208

1022

2208

2133

1652

767

764

Import / North­b o u n d

-

-

-

131

2208

238

2208

995

2208

2208

1979

747

2208

N o of days with l imitation

Export/ South­b o u n d

-

-

-

85

92

35

92

45

92

89

70

34

92

Import / North­b o u n d

-

-

-

9

92

13

92

42

92

92

85

33

92

Average reduction

Export/

South­

b o u n d

-

-

-

3 %

37%

13%

2 4 %

2 1 %

17%

46%

71%

11%

3 0 %

Import / North­b o u n d

-

-

-

-4%

19%

6%

43%

2 2 %

17%

50%

78%

14%

8 0 %

Table 14. Limitations in trading capacity on interconnectors as enforced by neighbouring TSOs. The columns with average reductions shows the average NTC divided by maximum NTC.

Table 15 below summarises the time during which capacities on interconnectors and corridors between internal areas have been reduced, taking into account reductions by both Svenska kraftnät and neighbouring TSOs.

24/60

Interconnectors /

corridors b e t w e e n

internal areas

SE1-SE2

SE2-SE3

SE3-SE4

SEl-FI

SE1-NO4

SE2-NO3

SE2-NO4

SE3-DK1

SE3-FI

SE3-NO1

SE4-DE

SE4-DK2

SE4-PL

N o of l imited hours

Export/ South­b o u n d

761

2208

2208

2040

2208

727

2208

1069

2208

2196

1712

870

831

Import / North­b o u n d

0

0

0

548

2208

238

2208

1527

2208

2208

2119

1256

2208

N o of days with

l imitation

Export/ South­bound

34

92

92

85

92

35

92

48

92

92

73

39

92

Import / North­b o u n d

0

0

0

28

92

13

92

83

92

92

92

72

92

Average reduction

Export/ South­bound

8%

18%

25%

5%

37%

13%

24%

26%

18%

51%

72%

15%

3 1 %

Import / North­b o u n d

0%

0%

0%

2%

2 0 %

6%

43%

4 0 %

39%

49%

8 2 %

24%

80%

Table 15. Final limitations in trading capacity on interconnectors and corridors between internal areas as enforced by both Svenska kraftnät and neighbouring TSOs. The columns with average reductions shows the average NTC divided by maximum NTC.

Detailed information for each limitation is provided in the attached Tables C2 to C5 in Appendix C and in the attachment. This information includes the reason for each limitation.

25/60

1.3-2 Comments on each interconnector

SEl-FI, North Finland Svenska kraftnät has reduced the export and import capacity for 2 040 and 540 hours, respectively, for the interconnector between SEi and Fl. The majority of the export reductions are because the NTC depends on forecasted transfer between Kalix - Ossauskoski and Ivalo - Varangerbotn (and the forecasted transfer can both increase and decrease the NTC). Besides that, the reasons for both import and export reductions set by Svenska kraftnät were planned maintenances in the vicinity of the interconnector. In total, the export and import on the interconnector have been reduced for 2 040 and 548 hours, respectively.

SE1-NO4, North Norway Svenska kraftnät has reduced the export and import capacity for o and 537 hours, respectively, for the interconnector between SEi and NO4. The reasons for import reductions set by Svenska kraftnät were planned maintenances in the vicinity of the interconnector. In total, the export and import on the interconnector have both been reduced for all hours.

SE2-NO3, Central Norway Svenska kraftnät has not reduced the capacity for the interconnector between SE2 and NO3. In total, the export and import on the interconnector have been reduced for 727 and 238 hours, respectively.

SE2-NO4, North Norway Svenska kraftnät has reduced the export and import capacity for 87 and 61 hours, respectively, for the interconnector between SE2 and NO4. The reasons for import reductions set by Svenska kraftnät were planned maintenances in the vicinity of the interconnector. In total, the export and import on the interconnector have both been reduced all hours.

SE3-DK1, West Denmark Svenska kraftnät has reduced the export and import capacity for 948 and 1433 hours, respectively, for the interconnector between SE3 and DKi. The main reasons for export reductions set by Svenska kraftnät were failure and maintenance on the interconnector. The main reasons for import reductions set by Svenska kraftnät were failure on the interconnector, maintenance on and in the vicinity of the interconnector, and congestion in the West Coast Corridor. In total, the export and import on the interconnector have been reduced for 1069 and 1527 hours, respectively.

SE3-FI, South Finland Svenska kraftnät has reduced both the export and import capacity for all hours for the interconnector between SE3 and Fl. The reasons for export and import reductions set by Svenska kraftnät were maintenance and thermal limitation on the interconnector, and maintenance in the vicinity of the interconnector.

SE3-NO1, North Norway Svenska kraftnät has reduced the export and import capacity for 807 and 329 hours, respectively, for the interconnector between SE3 and NOi. The main reasons for export reductions set by Svenska kraftnät were congestion in the West Coast Corridor (only export reductions), but for some hours also due to maintenance on the interconnector and maintenance in the vicinity of the interconnector. The reasons for import

26/60

reductions set by Svenska kraftnät were maintenance on the interconnector and maintenance in the vicinity of the interconnector. In total, the export and import on the interconnector have been reduced for 2 196 and 2 208 hours, respectively.

SE4-DE, Germany Svenska kraftnät has reduced the export and import capacity for 184 and 541 hours, respectively, for the interconnector between SE4 and DE. The reason for export reductions set by Svenska kraftnät was maintenance in the vicinity of the interconnector, and for import reductions congestion in the West Coast Corridor. In total, the export and import on the interconnector have been reduced for 1712 and 2 119 hours, respectively.

SE4-DK2, East Denmark Svenska kraftnät has reduced the export and import capacity for 216 and 547 hours, respectively, for the interconnector between SE4 and DK2. The reasons for export reductions set by Svenska kraftnät were planned maintenance in the vicinity of the interconnector. The reason for import reductions set by Svenska kraftnät was mainly due to congestion in the West Coast Corridor and maintenance in the vicinity of the interconnector. In total, the export and import on the interconnector have been reduced for 870 and 1256 hours, respectively.

SE4-PL, Poland Svenska kraftnät has reduced the export and import capacity for 101 and 451 hours, respectively, for the interconnector between SE4 and PL. The reason for export reductions set by Svenska kraftnät was due to maintenance in the vicinity of the interconnector, and for import reductions due to congestion in the West Coast Corridor and maintenance in the vicinity of the interconnector. In total, the export and import on the interconnector have been reduced for 831 and 2 208 hours, respectively.

27/60

1.4 2013 Q4 This section describes operational experience and measures regarding allocation of trading capacity in the period October i to December 31, 2013.

In the period, totally 2 209 hours, the main direction of the power flow was southbound.

Table 16 below shows the average prices in Sweden and all neighbouring areas for the above mentioned period (excluding Germany and Poland). Table 17 summarises the number of hours where price differences occurred between the respective zones.

Area

SEi

SE2

SE3

SE4

DKi

DK2

Fl

NOi

NO3

NO4

Average Price Level (EUR)

36,97

36,97

37,48

38,76

33,40

37,79

39,90

35,io

37,05

37,oo

Maximum Price (EUR)

63,39

63,39

94,30

m , 5 7

94,30

in ,57

210,01

85,23

63,39

63,39

Minimum Price

(EUR)

11,05

11,05

11,05

11,05

-62,03

-62,03

11,05

26,11

11,05

11,05

Table 16. Average, maximum, and minimum prices for areas within Nord Pool Spöt.

28/60

No of hours where price for row area > column area S E i

SE2

S E 3

SE4

DKi

DK2

Fl

N O i

N O 3

N O 4

S E i

-

0

109

3 0 6

217

4 0 8

616

219

119

51

SE2

0

-

109

3 0 6

217

4 0 8

616

219

119

51

SE3

0

0

-

2 2 1

141

332

539

211

119

51

SE4

0

0

0

-

91

192

475

211

119

51

DKi

1379

1379

1393

1528

-

1063

1678

1181

1429

1396

DK2

585

585

585

585

24

-

1 0 2 2

665

665

609

Fl

0

0

0

194

118

3 0 2

-

211

118

51

N O i

1258

1258

1263

1311

592

1019

1495

-

1349

1277

NO3

52

52

147

325

240

424

629

2 0 1

-

0

NO4

53

53

148

326

241

425

629

2 1 7

82

-

Table 17. Number of hours where the price for the area in the row was higher than for the area in the column.

Summary of Table 16 and 17:

• Fl had the highest average price, followed by SE4, DK2, SE3, NO3, NO4, SEi, SE2, NOi and DKi respectively

• SEi and SE2 had a common price during all hours.

1.4.1 Allocation of trading capacity Table 18 below summarises how often Svenska kraftnät have allocated less trading capacity than maximum NTC for interconnectors and corridors between internal areas in the period.

29/60

Interconnectors / corridors b e t w e e n internal areas

SE1-SE2

SE2-SE3

SE3-SE4

SEl-FI

SE1-NO4

SE2-NO3

SE2-NO4

SE3-DK1

SE3-FI

SE3-NO1

SE4-DE

SE4-DK2

SE4-PL

N o of l imited hours

Export/ South­b o u n d

616

2209

2209

2 197

0

0

0

549

2209

8 8 9

9 0

" 3

62

Import / North­b o u n d

0

0

0

166

121

0

0

1379

2209

155

724

833

695

N o of days wi th l imitat ion

Export/ South­b o u n d

26

92

92

92

0

0

0

23

92

62

6

6

4

Import / North­b o u n d

0

0

0

8

6

0

0

85

92

9

60

63

6 0

Average reduct ion

Export/ South­b o u n d

4%

11%

1 9 %

1 1 %

0 %

0 %

0 %

14%

1 2 %

1 3 %

3 %

3%

3%

Import / North­b o u n d

0 %

0 %

0%

- 2 %

4%

0%

0%

3 1 %

1 2 %

2 %

1 2 %

14%

1 1 %

Table 18. Limitations in trading capacity on interconnectors and corridors between internal areas as enforced by Svenska kraftnät. The columns with average reductions shows the average NTC divided by maximum NTC.

The majority of the limitations of export capacity on the interconnector SEi-FI, enforced by Svenska kraftnät during the period, are because of that the NTC depends on forecasted transfer between Kalix - Ossauskoski and Ivalo - Varangerbotn. The forecasted transfer can both increase and decrease the NTC (which also explains the negative average reduction for SEi-FI in Table 18 and 19).

Table 19 below summarises the time during which neighbouring TSOs have allocated less trading capacity than maximum NTC to interconnectors in the period.

30/60

Interconnectors /

corridors be tween

internal areas

SE1-SE2

SE2-SE3

SE3-SE4

SEi-FI

SE1-NO4

SE2-NO3

SE2-NO4

SE3-DK1

SE3-FI

SE3-NO1

SE4-DE

SE4-DK2

SE4-PL

N o of l imited hours

Export/ South­b o u n d

-

-

-

2197

2209

1086

2209

596

2209

1233

275

1268

834

Import / North­b o u n d

-

-

-

107

2209

35

2209

738

2209

2102

1949

1294

2209

N o of days wi th l imitat ion

Export/ South­b o u n d

-

-

-

92

92

47

92

27

92

53

13

61

92

Import / North­b o u n d

-

-

-

5

92

2

92

34

92

89

88

61

92

Average reduction

Export/ South­b o u n d

-

-

-

8%

26%

2 0 %

18%

14%

12%

35%

6%

13%

32%

Import / North­b o u n d

-

-

-

-3%

8%

1%

4 0 %

14%

12%

38%

4 4 %

22%

80%

Table 19. Limitations in trading capacity on interconnectors as enforced by neighbouring TSOs. The columns with average reductions shows the average NTC divided by maximum NTC.

Table 20 below summarises the time during which capacities on interconnectors and corridors between internal areas have been reduced, taking into account reductions by both Svenska kraftnät and neighbouring TSOs.

31/60

Interconnectors /

corridors be tween

internal areas

SE1-SE2

SE2-SE3

SE3-SE4

SEl-FI

SE1-NO4

SE2-NO3

SE2-NO4

SE3-DK1

SE3-FI

SE3-NO1

SE4-DE

SE4-DK2

SE4-PL

N o of l imited hours

Export/ South­b o u n d

616

2209

2209

2 197

2209

1086

2209

597

2209

1773

344

1381

844

Import /

North­

b o u n d

0

0

0

166

2209

35

2209

1522

2209

2102

2 149

1892

2 2 0 9

N o of days with l imitat ion

Export/ South­b o u n d

26

92

92

92

92

47

92

27

92

8 8

17

67

92

Import / North­bound

0

0

0

8

92

2

92

8 8

92

89

92

89

92

Average reduction

Export/ South­b o u n d

4%

1 1 %

1 9 %

1 1 %

2 6 %

2 0 %

1 8 %

15%

1 2 %

4 4 %

9%

16%

3 4 %

Import / North­b o u n d

0 %

0 %

0 %

- 2 %

1 2 %

1%

4 0 %

3 2 %

1 2 %

3 9 %

4 9 %

3 3 %

8 0 %

Table 20. Final limitations in trading capacity on interconnectors and corridors between internal areas as enforced by both Svenska kraftnät and neighbouring TSOs. The columns with average reductions shows the average NTC divided by maximum NTC.

Detailed information for each limitation is provided in the attached Tables D2 to D5 in Appendix D and in the attachment. This information includes the reason for each limitation.

32/60

1.4-2 Comments on each interconnector

SEl-FI, North Finland Svenska kraftnät has reduced the export and import capacity for 2 197 and 166 hours, respectively, for the interconnector between SEi and FL The majority of the export reductions are because the NTC depends on forecasted transfer between Kalix - Ossauskoski and Ivalo - Varangerbotn (and the forecasted transfer can both increase and decrease the NTC). Besides that, the reasons for both import and export reductions set by Svenska kraftnät were planned maintenances in the vicinity of the interconnector and on the interconnector. In total, the export and import on the interconnector have been reduced for 2 197 and 166 hours, respectively.

SE1-NO4, North Norway Svenska kraftnät has reduced the export and import capacity for o and 166 hours, respectively, for the interconnector between SEi and NO4. The reasons for import reductions set by Svenska kraftnät were planned maintenances in the vicinity of the interconnector. In total, the export and import on the interconnector have been reduced for 2 209 and 2 209 hours, respectively.

SE2-NO3, Central Norway Svenska kraftnät has reduced the export and import capacity for o and o hours, respectively, for the interconnector between SE2 and NO3. In total, the export and import on the interconnector have been reduced for 1 086 and 35 hours, respectively.

SE2-NO4, North Norway Svenska kraftnät has reduced the export and import capacity for o and o hours, respectively, for the interconnector between SE2 and NO4. In total, the export and import on the interconnector have been reduced for 2 209 and 2 209 hours, respectively.

SE3-DK1, West Denmark Svenska kraftnät has reduced the export and import capacity for 549 and 1379 hours, respectively, for the interconnector between SE3 and DKi. The main reasons for export reductions set by Svenska kraftnät were failure on the interconnector, but some hours also due to maintenance on the interconnector. The main reasons for import reductions set by Svenska kraftnät were failure on the interconnector and congestion in the West Coast Corridor, but some hours also due to maintenance on and in the vicinity of the interconnector. In total, the export and import on the interconnector have been reduced for 597 and 1522 hours, respectively.

SE3-FI, South Finland Svenska kraftnät has reduced the export and import capacity for 2 209 and 2 209 hours, respectively, for the interconnector between SE3 and Fl. The reasons for export and import reductions set by Svenska kraftnät were failure and thermal limitation on the interconnector. In total, the export and import on the interconnector have been reduced for 2 209 and 2 209 hours, respectively.

SE3-NO1, North Norway Svenska kraftnät has reduced the export and import capacity for 889 and 155 hours, respectively, for the interconnector between SE3 and NOi. The main reasons for export reductions set by Svenska kraftnät were congestion in the West Coast Corridor (only export reductions), but for some hours also due to failure on the

33/6o

interconnector and maintenance in the vicinity of the interconnector. The reasons for import reductions set by Svenska kraftnät were failure on the interconnector and maintenance in the vicinity of the interconnector. In total, the export and import on the interconnector have been reduced for 1773 and 2 102 hours, respectively.

SE4-DE, Germany Svenska kraftnät has reduced the export and import capacity for 90 and 724 hours, respectively, for the interconnector between SE4 and DE. The reason for export reductions set by Svenska kraftnät was maintenances in the vicinity of the interconnector, and for import reductions congestion in the West Coast Corridor. In total, the export and import on the interconnector have been reduced for 344 and 2 149 hours, respectively.

SE4-DK2, East Denmark Svenska kraftnät has reduced the export and import capacity for 113 and 833 hours, respectively, for the interconnector between SE4 and DK2. The reasons for export reductions set by Svenska kraftnät were planned maintenances in the vicinity of the interconnector and failure on the interconnector. The reason for import reductions set by Svenska kraftnät was mainly due to congestion in the West Coast Corridor, but for some hours also due to failure on and in the vicinity of the interconnector (as well as maintenance in the vicinity of the interconnector). In total, the export and import on the interconnector have been reduced for 1 381 and 1892 hours, respectively.

SE4-PL, Poland Svenska kraftnät has reduced the export and import capacity for 62 and 674 hours, respectively, for the interconnector between SE4 and PL. The reason for export reductions set by Svenska kraftnät was due to maintenance in the vicinity of the interconnector, and for import reductions due to congestion in the West Coast Corridor. In total, the export and import on the interconnector have been reduced for 844 and 2 209 hours, respectively.

34/60

Appendix A - 2013 Qi

The attached spreadsheet contains data for each hour during the period. Each value in the spreadsheet is explained in the Table below.

Value

Maximum NTC export/southbound (MW) Maximum NTC import/northbound (MW)

SvK NTC export (MW) SvK NTC import (MW)

SvK Reduction export (Y/N) SvK Reduction import (Y/N)

SvK Reduction export (MW) SvK Reduction import (MW)

SvK Reason for export reduction SvK Reason for import reduction

Neighbouring TSO NTC export (MW) Neighbouring TSO NTC import (MW)

Explanation

Maximum NTC for export/import, as agreed by TSOs on both sides, and maximum NTC for corridors between internal areas in south/north direction. These values normally only change after the network has been reinforced.

Svenska kraftnäfs view of NTC for export/import.

Yes (Y), if Svenska kraftnäfs view of NTC for export/import is lower than maximum NTC, otherwise No (N).

Difference between maximum NTC and Svenska kraftnäfs view of NTC.

Reason codes for Svenska kraftnäfs reduction of capacities. Reduction codes are according Nord Pool Spof s instructions only reported when the reduction is greater than 100 MW. Because of this principle, there might be mismatches between the figures shown in Table 3 and 5 and Tables A2 to A5. See separate sheet in spreadsheet file for explanation of the codes.

Neighbouring TSO's view of NTC for export/import.

35/60

Final NTC export/southbound (MW) Final NTC import/northbound (MW)

Final Reduction export/southbound (Y/N) Final Reduction import/northbound (Y/N)

Final Reduction export/southbound (MW) Final Reduction import/northbound (MW)

Final Reason for export/southbound reduction Final Reason for import/northbound reduction

Registered physical flow (positive for imports and negative for exports/positive for southbound and negative for northbound)

Electricity price level SE1/SE2/SE3/SE4/DK1/DK2/NO1/NO3/NO4/FI (EUR)

Price difference (Y/N)

Final NTC for corridors between internal areas in south/north direction, and the minimum of Svenska kraftnäfs view and the neighbouring TSO's view of the export/import NTC on interconnectors.

Yes (Y), if the final NTC is lower than the maximum NTC, otherwise No (N).

Difference between maximum NTC and final NTC.

Reason codes for reduction of the final capacities. Reduction codes are according Nord Pool Spof s instructions only reported when the reduction is greater than 100 MW. Because of this principle, there might be mismatches between the figures shown in Table 3 and 5 and Tables A2 to A5. See separate sheet in spreadsheet file for explanation of the codes.

Measured flow on interconnectors and corridors between internal areas.

Price level in SEi, SE2, SE3, SE4, DKi, DK2, NOi, NO3, NO4 and FL Prices for DE and PL are not available, since they are not part of Nord Pool Spöt. Red figures indicate a higher price than neighbouring SE-area, and blue indicates a lower price.

Yes (Y), if there is a price difference between neighbouring SE-area and current area, otherwise No (N). Blank for DE and PL.

Table Al. Explanation of data in the attached spreadsheet.

36/60

Tables A2 to A5 shows how of many hours the capacities have been reduced per type of reduction for each interconnector and corridor between internal areas. The reason codes are explained in the attached spreadsheet.

37/6o

SE1-SE2

SE2-SE3

SE3-SE4

SEl-FI

SE1-NO4

SE2-NO3

SE2-NO4

SE3-DK1

SE3-FI

SE3-NO1

SE4-DE

SE4-DK2

SE4-PL

1010

2159

24

2159

2149

2159

2159

1805

336

936

2159

1895

2159

1125

120

1155

10

1226

264

1258

1823

1422

200

28

1423

18

1425

234

1432

24

1522

48

1622

1886

1623

2117

1624

1188

2214

7

2222

1

Table A2. Number of hours per type of export reduction (for interconnectors) and per type of southbound reduction (for corridors between internal areas) enforced by Svenska kraftnät.

38/60

SE1-SE2

SE2-SE3

SE3-SE4

SEl-FI

SE1-NO4

SE2-NO3

SE2-NO4

SE3-DK1

SE3-FI

SE3-NO1

SE4-DE

SE4-DK2

SE4-PL

IOIO

2159

2159

2159

2159

2149

2159

2159

787

336

2159

1189

859

1196

1125

85

1155

10

1226

227

1258

1823

1425

211

1624

IO76

966

1072

963

2326

1

2424

4

Table A3. Number of hours per type of import reduction (for interconnectors) and per type of northbound reduction (for corridors between internal areas) enforced by Svenska kraftnät.

39/60

SE1-SE2

SE2-SE3

SE3-SE4 SEl-FI

SE1-NO4 SE2-NO3

SE2-NO4 SE3-DK1

SE3-FI

SE3-NO1 S E 4 D E

SE4-DK2

SE4-PL

IOIO

2159

24 2101

2149

2159

2159

1793 312 620

2126

1247

1468

1125

132

1126

168

W55

10

1158

109

1226

744

1258

1738

1414

78

1422

200

28

1423

18

1425

234

1432

24

SE1-SE2

SE2-SE3

SE3-SE4

SEl-FI

SE1-NO4

SE2-NO3

SE2-NO4 SE3-DK1

SE3-FI

SE3-NO1 SE4-DE

SE4-DK2

SE4-PL

1522

48

1546

288

1622

1886

1623

2117

1624

1136

2214

7

2 2 2 2

1

2 2 2 4

2

9 9 4 0

58

9999

33

691

Table A4. Number of hours per type of export reduction as enforced by Svenska kraftnät and neighbouring TSOs (for interconnectors) and per type of southbound reduction (for corridors between internal areas) enforced by Svenska kraftnät.

40/60

SE1-SE2

SE2-SE3

SE3-SE4 SEl-FI

SE1-NO4

SE2-NO3 SE2-NO4

SE3-DK1

SE3-FI

SE3-NO1 SE4-DE

SE4-DK2

SE4-PL

SE1-SE2

SE2-SE3

SE3-SE4 SEl-FI

SE1-NO4

SE2-NO3

SE2-NO4 SE3-DK1

SE3-FI

SE3-NO1 SE4-DE

SE4-DIC2

SE4-PL

IOIO

2159

2159

2159 2108

2149

2159

2159

775 312 862

803

519

1414

104

1125

97

1425

211

1126

65

1546

180

1155

10

1624

IO76

755

929 107

1158

110

1745

1012

1226

646

1258

1737

2214

1

9940

51

9999

601

2052

Table A5. Number of hours per type of import reduction as enforced by Svenska kraftnät and neighbouring TSOs (for interconnectors) and per type of northbound reduction (for corridors between internal areas) enforced by Svenska kraftnät.

41/60

Appendix B - 2013 Q2

The attached spreadsheet contains data for each hour during the period. Each value in the spreadsheet is explained in the Table below.

Value

Maximum NTC export/southbound (MW) Maximum NTC import/northbound (MW)

SvK NTC export (MW) SvK NTC import (MW)

SvK Reduction export (Y/N) SvK Reduction import (Y/N)

SvK Reduction export (MW) SvK Reduction import (MW)

SvK Reason for export reduction SvK Reason for import reduction

Neighbouring TSO NTC export (MW) Neighbouring TSO NTC import (MW)

Explanation

Maximum NTC for export/import, as agreed by TSOs on both sides, and maximum NTC for corridors between internal areas in south/north direction. These values normally only change after the network has been reinforced.

Svenska kraftnäfs view of NTC for export/import.

Yes (Y), if Svenska kraftnäfs view of NTC for export/import is lower than maximum NTC, otherwise No (N).

Difference between maximum NTC and Svenska kraftnäfs view of NTC.

Reason codes for Svenska kraftnäfs reduction of capacities. Reduction codes are according Nord Pool Spof s instructions only reported when the reduction is greater than 100 MW. Because of this principle, there might be mismatches between the figures shown in Table 8 and 10 and Tables B2 to B5. Seé separate sheet in spreadsheet file for explanation of the codes.

Neighbouring TSO's view of NTC for export/import.

42/60

Final NTC export/southbound (MW) Final NTC import/northbound (MW)

Final Reduction export/southbound (Y/N) Final Reduction import/northbound (Y/N)

Final Reduction export/southbound (MW) Final Reduction import/northbound (MW)

Final Reason for export/southbound reduction Final Reason for import/northbound reduction

Registered physical flow (positive for imports and negative for exports/positive for southbound and negative for northbound)

Electricity price level SE1/SE2/SE3/SE4/DK1/DK2/NO1/NO3/NO4/FI (EUR)

Price difference (Y/N)

Final NTC for corridors between internal areas in south/north direction, and the minimum of Svenska kraftnäfs view and the neighbouring TSO's view of the export/import NTC on interconnectors.

Yes (Y), if the final NTC is lower than the maximum NTC, otherwise No (N).

Difference between maximum NTC and final NTC.

Reason codes for reduction of the final capacities. Reduction codes are according Nord Pool Spof s instructions only reported when the reduction is greater than 100 MW. Because of this principle, there might be mismatches between the figures shown in Table 8 and 10 and Tables B2 to B5. See separate sheet in spreadsheet file for explanation of the codes.

Measured flow on interconnectors and corridors between internal areas.

Price level in SEi, SE2, SE3, SE4, DKi, DK2, NOi, N03, NO4 and Fl. Prices for DE and PL are not available, since they are not part of Nord Pool Spöt. Red figures indicate a higher price than neighbouring SE-area, and blue indicates a lower price.

Yes (Y), if there is a price difference between neighbouring SE-area and current area, otherwise No (N). Blank for DE and PL.

Table Bl. Explanation of data in the attached spreadsheet.

43/6o

Tables B2 to B5 shows how of many hours the capacities have been reduced per type of reduction for each interconnector and corridor between internal areas. The reason codes are explained in the attached spreadsheet.

44/60

SE1-SE2

SE2-SE3

SE3-SE4

SEl-FI

SE1-NO4

SE2-NO3

SE2-NO4

SE3-DK1

SE3-FI

SE3-NO1

SE4-DE

SE4-DK2

SE4-PL

1010

1751

2165

2128

2169

2184

1694

1007

1015

2138

2029

1908

1125

114

1157

8

1158

11

1162

210

1258

3 6 0

1358

120

1421

52

2 4

1422

8 4 0

1423

919

13

17

13

13

13

1424

4 2

275

2 2 1

1425

75

1431

10

10

7

1432

4 8

4 8

15

1433

8 5

6 8

13

5 3 1

2 6

2 6

26

2 6

1434

7

114

1455

4 6

SE1-SE2

SE2-SE3

SE3-SE4

SEl-FI

SE1-NO4

SE2-NO3

SE2-NO4

SE3-DK1

SE3-FI

SE3-NO1

SE4-DE

SE4-DK2

SE4-PL

1458

11

1462

3

1521

2 4

2 4

1621

3 0 5

1622

1156

1623

1149

1624

8 9 0

1658

72

2214

13

2221

4

2222

7

2223

5

2 2 2 4

1

2

2226

2

2257

1

2258

1

9 9 5 8

6 4

9 9 9 9

2 4

Table B2. Number of hours per type of export reduction (for interconnectors) and per type of southbound reduction (for corridors between internal areas) enforced by Svenska kraftnät.

45/60

SE1-SE2

SE2-SE3

SE3-SE4

SEl-FI

SE1-NO4

SE2-NO3

SE2-NO4

SE3-DK1

SE3-FI

SE3-NO1

SE4-DE

SE4-DK2

SE4-PL

SE1-SE2

SE2-SE3

SE3-SE4

SEl-FI

SE1-NO4

SE2-NO3

SE2-NO4

SE3-DK1

SE3-FI

SE3-NO1

SE4-DE

SE4-DK2

SE4-PL

IOIO

2184

2184

2184

2062

2138

2169

2184

979

983

1854

1260

1013

1212

1455

4 6

1125

88

1458

11

1158

11

1462

3

1162

2 5 0

1521

48

1258

2 6 4

1624

741

7 8 0

898

656

1358

120

1626

1

1423

13

17

13

13

13

I658

72

1424

2 6 2

275

98

104

2 4

2214

10

1425

75

1431

73

7

1432

15

1433

26

651

2 6

2 6

2 6

26

1434

7

114

2223

2

2 2 2 4

2

2226

13

2257

1

2258

1

9958

64

Table B3. Number of hours per type of import reduction (for interconnectors) and per type of northbound reduction (for corridors between internal areas) enforced by Svenska kraftnät.

46/60

SE1-SE2

SE2-SE3

SE3-SE4 SEl-FI

SE1-NO4 SE2-NO3

SE2-NO4 SE3-DK1

SE3-FI

SE3-NO1 SE4-DE

SE4-DK2

SE4-PL

1010

1751

2081

1943 1581 2101

1457

9 4 9

4 6 7

2044 1550

1196

1125

2 6 7

1126

114

1157

8

1158

26

1162

2 4

1225

48

1258

4 3 2

1325

152

1358

120

1414

125

1418

8 2

8 2

1421

52

2 4

1422

8 4 0

1423

919

13

17

13

13

13

1424

4 2

8 2

221

1425

66

1431

94 10

7

1432

4 8

48

15

1433

85

68

13

5 2 6

26

26

26

9

1434

7

114

1442

8 6

1443

3 5 8

1445

2 2 9

SE1-SE2

SE2-SE3

SE3-SE4

SEl-FI

SE1-NO4

SE2-NO3 SE2-NO4

SE3-DK1

SE3-FI

SE3-NO1 SE4-DE

SE4-DK2

SE4-PL

1447

31

4 3 9

31

2 3 5

1450

59

67

52

1455

59

1458

11

1462

3

1521

24

2 4

1545

4 3

1614

18

1621

3 0 5

1622

1156

1623

1149

1624

7 8 9

6

1658

4 8

2214

12

2221

4 2222

7

2223

5

2 2 2 4

1

2

2226

3

2257

1

2258

1

2 4 2 4

7

9958

64

9999

94

9 3 2

Table B4. Number of hours per type of export reduction as enforced by Svenska kraftnät and neighbouring TSOs (for interconnectors) and per type of southbound reduction (for corridors between internal areas) enforced by Svenska kraftnät.

47/60

SE1-SE2

SE2-SE3

SE3-SE4 SEl-FI

SE1-NO4 SE2-NO3

SE2-NO4 SE3-DK1

SE3-FI

SE3-NO1

SE4-DE SE4-DK2

SE4-PL

SE1-SE2

SE2-SE3 SE3-SE4

SEl-FI

SE1-NO4

SE2-NO3

SE2-NO4 SE3-DK1

SE3-FI

SE3-NO1

SE4-DE SE4-DK2

SE4-PL

IOIO

2184

2184

2184

1978

1938

2169

2101

779

9 2 5

672

815

767

1450

74

52

1125

166

1455

59

1126

8 2

1458

11

1158

21

1521

48

1162

54

1545

122

1225

37

1614

32

1258

336

1624

753

751

869 132

1325

139

1626

1

1358

120

1658

4 8

1414

125

1745

348

1418

8 2

2214

11

1423

13

17

13

13

2223

2

1424

2 0 2

275

98 89 10

2 2 2 4

2

1425

69

2226

9

1431

157

7

2245

10

1432

15

2257

1

1433

2 6

651

2 6

2 6

2 6

2258

1

1434

7

114

2 4 2 4

2 4

1443

212

9958

64

1445

3 0 9

9 9 9 9

4 7 4

1964

1447

31

31

2 3 5

Table B5. Number of hours per type of import reduction as enforced by Svenska kraftnät and neighbouring TSOs (for interconnectors) and per type of northbound reduction (for corridors between internal areas) enforced by Svenska kraftnät.

48/60

Appendix C - 2013 Q3

The attached spreadsheet contains data for each hour during the period. Each value in the spreadsheet is explained in the Table below.

Value

Maximum NTC export/southbound (MW) Maximum NTC import/northbound (MW)

SvK NTC export (MW) SvK NTC import (MW)

SvK Reduction export (Y/N) SvK Reduction import (Y/N)

SvK Reduction export (MW) SvK Reduction import (MW)

SvK Reason for export reduction SvK Reason for import reduction

Neighbouring TSO NTC export (MW) Neighbouring TSO NTC import (MW)

Final NTC export/southbound (MW) Final NTC import/northbound (MW)

Explanation

Maximum NTC for export/import, as agreed by TSOs on both sides, and maximum NTC for corridors between internal areas in south/north direction. These values normally only change after the network has been reinforced.

Svenska kraftnäfs view of NTC for export/import.

Yes (Y), if Svenska kraftnäfs view of NTC for export/import is lower than maximum NTC, otherwise No (N).

Difference between maximum NTC and Svenska kraftnäfs view of NTC.

Reason codes for Svenska kraftnäfs reduction of capacities. Reduction codes are according Nord Pool Spof s instructions only reported when the reduction is greater than 100 MW. Because of this principle, there might be mismatches between the figures shown in Table 13 and 15 and Tables C2 to C5. See separate sheet in spreadsheet file for explanation of the codes.

Neighbouring TSO's view of NTC for export/import.

Final NTC for corridors between internal areas in south/north direction, and the minimum of Svenska kraftnäfs view and the neighbouring TSO's view of the export/import NTC on interconnectors.

49/60

Final Reduction export/southbound (Y/N) Final Reduction import/northbound (Y/N)

Final Reduction export/southbound (MW) Final Reduction import/northbound (MW)

Final Reason for export/southbound reduction Final Reason for import/northbound reduction

Registered physical flow (positive for imports and negative for exports/positive for southbound and negative for northbound)

Electricity price level SE1/SE2/SE3/SE4/DK1/DK2/NO1/NO3/NO4/FI (EUR)

Price difference (Y/N)

Yes (Y), if the final NTC is lower than the maximum NTC, otherwise No (N).

Difference between maximum NTC and final NTC.

Reason codes for reduction of the final capacities. Reduction codes are according Nord Pool Spof s instructions only reported when the reduction is greater than 100 MW. Because of this principle, there might be mismatches between the figures shown in Table 13 and 15 and Tables C2 to C5. See separate sheet in spreadsheet file for explanation of the codes.

Measured flow on interconnectors and corridors between internal areas.

Price level in SEi, SE2, SE3, SE4, DKi, DK2, NOi, NO3, NO4 and FL Prices for DE and PL are not available, since they are not part of Nord Pool Spöt. Red figures indicate a higher price than neighbouring SE-area, andblue indicates a lower price.

Yes (Y), if there is a price difference between neighbouring SE-area and current area, otherwise No (N). Blank for DE and PL.

Table Cl. Explanation of data in the attached spreadsheet.

Tables C2 to C5 shows how of many hours the capacities have been reduced per type of reduction for each interconnector and corridor between internal areas. The reason codes are explained in the attached spreadsheet.

50/60

SE1-SE2

SE2-SE3

SE3-SE4

SEl-FI

SE1-NO4

SE2-NO3

SE2-NO4

SE3-DK1

SE3-FI

SE3-NO1

SE4-DE

SE4-DK2

SE4-PL

1010

1448

2101

2208

2208

2147

1260

168

1454

2027

1993

2107

1125

6

1156

61

1158

194

1163

5 8

1225

8 4 4

1258

2 5 6

1358

1590

1414

179

1421

4 4 0

107

1422

155

579

4 2

1423

317

22

22

22

1431

78

16

1432

4 1

4 8

1433

724

76

57

1434

8 4

59

188

57

SE1-SE2

SE2-SE3

SE3-SE4

SEl-FI

SE1-NO4

SE2-NO3

SE2-NO4

SE3-DK1

SE3-FI

SE3-NO1

SE4-DE

SE4-DK2

SE4-PL

1531

2 4

1621

18

1622

8 4 1

1623

1251

1624

4 4 8

1634

552

2214

17

2221

4

2223

4

2226

4

2233

4

2 2 3 4

1

2314

7

9 9 6 2

2

9999

4 2

4 2

Table C2. Number of hours per type of export reduction (for interconnectors) and per type of southbound reduction (for corridors between internal areas) enforced by Svenska kraftnät.

51/60

SE1-SE2

SE2-SE3

SE3-SE4

SEl-FI

SE1-NO4

SE2-NO3

SE2-NO4

SE3-DK1

SE3-FI

SE3-NO1

SE4-DE

SE4-DK2

SE4-PL

1010

2208

2208

2208

1791

1865

2208

2147

7 8 7

168

1879

1704

1680

1793

1125

6

1156

61

1158

186

1163

5 8

1225

8 4 4

1355

3 3

1358

1004

1414

179

1421

107

1422

4 2

1423

22

22

22

1431

35

35

1433

76

8 5 0

9 3

22

22

22

1434

4 2

4 2

1455

275

1457

275

1624

431

4 0 2

4 2 1

3 9 3

2214

8

2226

10

2233

5

2 2 3 4

1

2314

2

2326

1

2 4 2 4

9

Table C3. Number of hours per type of import reduction (for interconnectors) and per type of northbound reduction (for corridors between internal areas) enforced by Svenska kraftnät.

52/60

SE1-SE2

SE2-SE3

SE3-SE4

SEl-FI

SE1-NO4

SE2-NO3

SE2-NO4

SE3-DK1

SE3-FI

SE3-NO1

SE4-DE

SE4-DK2

SE4-PL

1010

1448

2089

1699

1760

1878

1139

168

70

4 9 7

1363

1377

1115

69

1125

6

1126

489

1155

4 3

8

4 3

1156

61

61

1158

190

1225

868

1226

120

1245

4 8 9

1258

191

1358

1566

1417

192

1421

4 4 0

107

1422

155

579

1423

317

22

22

1431

78

16

8

1432

41

4 8

1433

724

4

76

41

35

1434

8 4

59

188

35

1440

3 7

1442

97

1443

17

SE1-SE2

SE2-SE3

SE3-SE4

SEl-FI

SE1-NO4

SE2-NO3

SE2-NO4

SE3-DK1

SE3-FI

SE3-NO1

SE4-DE

SE4-DK2

SE4-PL

1445

1187

1447

9 8

1450

4 5 7

8 1

2 2 6

1458

15

1531

2 4

1550

24

1621

18

1622

8 4 1

1623

1251

1624

413

1634

552

2214

6

2215

5

2221

4

2223

4

2226

8

2233

2

2 2 3 4

1

2245

2

2314

4

9 9 6 2

2

9999

1652

7 9 4

Table C4. Number of hours per type of export reduction as enforced by Svenska kraftnät and neighbouring TSOs (for interconnectors) and per type of southbound reduction (for corridors between internal areas) enforced by Svenska kraftnät.

53/6o

SE1-SE2

SE2-SE3

SE3-SE4

SEl-FI

SE1-NO4

SE2-NO3

SE2-NO4

SE3-DK1

SE3-FI

SE3-NO1

SE4-DE

SE4-DK2

SE4-PL

1010

2208

2208

2208

1783

1562

1965

1970

6 9 3

168

2 4

182

971

1115

69

1125

6

1126

5 5 4

1155

8

1156

4 2

19

61

1158

186

1225

8 6 8

1226

120

1245

4 4

1326

17

1355

3 0

1358

1004

1417

146

79

1421

107

1423

22

22

1431

4 3

35

1433

76

8 5 0

92

22

SE1-SE2

SE2-SE3

SE3-SE4

SEl-FI

SE1-NO4

SE2-NO3

SE2-NO4

SE3-DK1

SE3-FI

SE3-NO1

SE4-DE

SE4-DK2

SE4-PL

1434

4 2

4 2

1442

70

1443

17

1445

1264

1447

9

9

1450

4 5 7

9 8

1455

65

1457

275

1624

4 3 1

187

4 2 0

8 2

1945

778

2226

12

2233

4

2 2 3 4

1

2245

1

2314

1

2326

1

2 4 2 4

9

9 9 9 9

1839

2126

Table C5. Number of hours per type of import reduction as enforced by Svenska kraftnät and neighbouring TSOs (for interconnectors) and per type of northbound reduction (for corridors between internal areas) enforced by Svenska kraftnät.

54/6o

Appendix D - 2013 Q4

The attached spreadsheet contains data for each hour during the period. Each value in the spreadsheet is explained in the Table below.

Value

Maximum NTC export/southbound (MW) Maximum NTC import/northbound (MW)

SvK NTC export (MW) SvK NTC import (MW)

SvK Reduction export (Y/N) SvK Reduction import (Y/N)

SvK Reduction export (MW) SvK Reduction import (MW)

SvK Reason for export reduction SvK Reason for import reduction

Neighbouring TSO NTC export (MW) Neighbouring TSO NTC import (MW)

Final NTC export/southbound (MW) Final NTC import/northbound (MW)

Explanation

Maximum NTC for export/import, as agreed by TSOs on both sides, and maximum NTC for corridors between internal areas in south/north direction. These values normally only change after the network has been reinforced.

Svenska kraftnäfs view of NTC for export/import.

Yes (Y), if Svenska kraftnäfs view of NTC for export/import is lower than maximum NTC, otherwise No (N).

Difference between maximum NTC and Svenska kraftnäfs view of NTC.

Reason codes for Svenska kraftnäfs reduction of capacities. Reduction codes are according Nord Pool Spof s instructions only reported when the reduction is greater than 100 MW. Because of this principle, there might be mismatches between the figures shown in Table 18 and 20 and Tables D2 to D5. See separate sheet in spreadsheet file for explanation of the codes.

Neighbouring TSO's view of NTC for export/import.

Final NTC for corridors between internal areas in south/north direction, and the minimum of Svenska kraftnäfs view and the neighbouring TSO's view of the export/import NTC on interconnectors.

55/60

Final Reduction export/southbound (Y/N) Final Reduction import/northbound (Y/N)

Final Reduction export/southbound (MW) Final Reduction import/northbound (MW)

Final Reason for export/southbound reduction Final Reason for import/northbound reduction

Registered physical flow (positive for imports and negative for exports/positive for southbound and negative for northbound)

Electricity price level SE1/SE2/SE3/SE4/DK1/DK2/NO1/NO3/NO4/FI (EUR)

Price difference (Y/N)

Yes (Y), if the final NTC is lower than the maximum NTC, otherwise No (N).

Difference between maximum NTC and final NTC.

Reason codes for reduction of the final capacities. Reduction codes are according Nord Pool Spof s instructions only reported when the reduction is greater than 100 MW. Because of this principle, there might be mismatches between the figures shown in Table 18 and 20 and Tables D2 to D5. See separate sheet in spreadsheet file for explanation of the codes.

Measured flow on interconnectors and corridors between internal areas.

Price level in SEi, SE2, SE3, SE4, DKi, DK2, NOi, NO3, NO4 and FL Prices for DE and PL are not available, since they are not part of Nord Pool Spöt. Red figures indicate a higher price than neighbouring SE-area, and blue indicates a lower price.

Yes (Y), if there is a price difference between neighbouring SE-area and current area, otherwise No (N). Blank for DE and PL.

Table Dl. Explanation of data in the attached spreadsheet.

Tables D2 to D5 shows how of many hours the capacities have been reduced per type of reduction for each interconnector and corridor between internal areas. The reason codes are explained in the attached spreadsheet.

56/60

SE1-SE2

SE2-SE3

SE3-SE4

SEl-FI

SE1-NO4

SE2-NO3

SE2-NO4

SE3-DK1

SE3-FI

SE3-NO1

SE4-DE

SE4-DK2

S E 4 P L

1010

1996

2017

2209

2209

2209

1661

6 9 6

1438

2121

2 096

2 147

1158

9 6

1214

24

1225

5 3 4

1226

4 8

1258

4 8

1358

1369

1421

41

1422

38

1423

37

1425

14

1431

8 4

8 4

1432

13

1433

11

77

13

17

1434

62

88

62

6 2

1457

107

1522

24

SE1-SE2

SE2-SE3

SE3-SE4

SEl-FI

SE1-NO4

SE2-NO3

SE2-NO4

SE3-DK1

SE3-FI

SE3-NO1

SE4-DE

SE4-DK2

SE4-PL

1621

72

1622

2025

1623

2 0 8 9

1624

722

1633

2 4

2214

7

2221

4

2222

4

2223

6

2 2 2 4

1

2226

3

2233

4

2

2257

1

2321

1

Table D2. Number of hours per type of export reduction (for interconnectors) and per type of southbound reduction (for corridors between internal areas) enforced by Svenska kraftnät.

57/6o

SE1-SE2

SE2-SE3

SE3-SE4

SEl-FI

SE1-NO4

SE2-NO3

SE2-NO4

SE3-DK1

SE3-FI

SE3-NO1

SE4-DE

SE4-DK2

SE4-PL

IOIO

2209

2209

2209

2 0 4 3

2 0 9 0

2209

2 209

8 8 2

6 9 6

2 120

1596

1420

1630

1158

9 6

1214

2 4

1225

5 3 4

1226

4 8

1258

4 8

1358

1369

1421

17

17

1425

14

1431

4 2

102

1433

62

6 2

1434

11

1457

107

1534

4 8

1624

716

613

679

579

2214

3

2225

1

2226

3

Table D3. Number of hours per type of import reduction (for interconnectors) and per type of northbound reduction (for corridors between internal areas) enforced by Svenska kraftnät.

58/60

SE1-SE2

SE2-SE3

SE3-SE4 SEl-FI

SE1-NO4 SE2-NO3

SE2-NO4 SE3-DK1

SE3-FI

SE3-NO1

SE4-DE

SE4-DK2

SE4-PL

1010

1996

2 017 2162

1363 2162

1613 7 2 0

W» 1868

8 2 8

1372

1114

4

1125

4

1126

9 0 9

1158

9 6

1214

2 4

1225

5 3 4

1226

3 9 5

1258

48

1326

12

1358

1345

1417

8 4 3

70

1421

41

1422

38

1423

37

1425

14

1431 84

84

1432

13

1433 11

77

13

17

1434

62

67

6 2

4 7

1442

4 4

1445

9 8 4

1447

35

35

1450

12

3

12

SE1-SE2

SE2-SE3

SE3-SE4

SEl-FI

SE1-NO4

SE2-NO3 SE2-NO4 SE3-DK1

SE3-FI

SE3-NO1 SE4-DE SE4-DK2 SE4-PL

1457

107

1522

2 4

1545

3

1621

72

1622

2025

1623

2 0 8 9

1624

5 4 3

1633

24

2214

5

2221

4

2222

4

2223

6

2226

3

2233

4

2

2245

1

2257

1

2321

1

9 9 9 9

274

7 9 0

Table D4. Number of hours per type of export reduction as enforced by Svenska kraftnät and neighbouring TSOs (for interconnectors) and per type of southbound reduction (for corridors between internal areas) enforced by Svenska kraftnät.

59/60

SE1-SE2

SE2-SE3

SE3-SE4 SEl-FI

SE1-NO4 SE2-NO3

SE2-NO4 SE3-DK1

SE3-FI

SE3-NO1 SE4-DE

SE4-DK2

SE4-PL

1010

2209

2209

2209

2 0 4 3

2 0 4 3

2 174 2162

736

720

8 5 7

188

3 4 6

1114

8

1125

4

1126

8 5 3

1158

9 6

1214

2 4

1225

5 3 4

1226

311

1258

4 8

1326

2 4

1358

1345

1417

9 8

1421

17

17

1425

14

1431

4 2

102

1433

62

62

SE1-SE2

SE2-SE3

SE3-SE4 SEl-FI

SE1-NO4

SE2-NO3

SE2-NO4 SE3-DK1

SE3-FI

SE3-NO1

SE4-DE

SE4-DK2

SE4-PL

1434

11

1442

143

1445

9 7 8

1447

3 5

3 5

3 5

1450

12

12

1457

107

1534

4 8

1545

18

1624

715

3 6 6

5 9 3

8 0

1714

158

2214

3

2225

1

2226

2 3

2245

3

9 9 9 9

1 655

2129

Table D5. Number of hours per type of import reduction as enforced by Svenska kraftnät and neighbouring TSOs (for interconnectors) and per type of northbound reduction (for corridors between internal areas) enforced by Svenska kraftnät.

60/60