Upload
skkpblr
View
54
Download
5
Tags:
Embed Size (px)
DESCRIPTION
Survey camp manual. its very useful for students and then now 2013 regulation survey camp will be conducted on the IV sem vacation time period.
Citation preview
CHAPTER 1CONTOURING1.1 INTRODUCTION:A Contour is an imaginary line drawn joining the various points of equal elevation in the group. It is a line, which the surface of ground is intersected by a level surface. The imaginary line on the map represents a contour.
In our survey camp we obtain contours of two types of terrains. They are1. Plain terrain2. Rolling terrain
1.2 THEORY:The vertical between any two consecutive contours is called contour interval. The contour interval is kept constant for a contour plan. Otherwise the general appearance of the map will be misleading. The choice of proper contour interval appearance depends upon the following consideration.1.The Nature of the Ground2.The scale of the map3.The purpose and extent of surveyTwo contour lines of different elevation cannot cross each other. A closed contour line with one or more higher ones inside it represents a hill. In general, however the field of contouring may be divided into two classes1.Direct method2.Indirect methodWe carried out indirect method in which some suitable guide points are selected and surveyed. The guide have been serving as basis for the interpolation of contours
1.3 INSTRUMENTS REQUIRED:Dumpy level, Theodolite, Leveling staff, Chain, Tape, Pegs
1.4 EXPERRIMENTAL PROCEDURE:1.4.1 PLAIN TERRAIN COUNTOURING:To do the plain terrain contouring, we selected the ground near Knowledge center as the region of survey. We formed a square on the ground of size nearly 360m2. By using dumpy level, we formed grids of size 5m x 5m and then marked the base line using lime powder for reference. The instrument was then set up in the instrument station and the initial adjustments were made. The B.M. was taken. Then we started taking readings for the continuous grids. The leveling staffs were held at the corner of each grid and the readings are taken. The observations and calculations are shown in table 1. The details of the contour drawn are shown in figure 1.
1.4.2 ROLLING TERREIN CONTOURING:In rolling terrain contouring, the contour lines are to be laid in radial manner. The center of the base line was marked. The instrument is then setup in the ground and the initial adjustments are made the B.M. was taken the level was then rotated in clockwise direction from 0 to 45 and the ranging rod are adjusted in the direction in order to get that radial lines and the value of levels are taken. The procedure is repeated to from successive radial lines by rotating the telescope.
GRID CONTOURING:S.NOB.SI.SF.SH.IR.LREMARKS
011.250101.250100.00B.M
021.41099.840A0
031.43099.820A1
041.46099.790A2
051.50099.750A3
061.52099.730A4
071.53099.720A5
081.58099.670A6
091.56099.690A7
101.57099.680A8
111.57099.680A9
121.58099.670A10
131.42099.830B0
141.41099.840B1
151.45099.800B2
161.46099.790B3
171.42099.830B4
181.45099.800B5
191.46099.790B6
201.46099.790B7
211.49099.760B8
221.50099.750B9
231.52099.730B10
241.48099.770C0
S.NOB.SI.SF.SH.IR.LREMARKS
251.49099.760C1
261.50099.750C2
271.51099.740C3
281.51099.740C4
291.47099.780C5
301.45099.800C6
311.48099.770C7
321.45099.800C8
331.50099.750C9
341.50099.750C10
351.48099.770D0
361.46099.790D1
371.53099.720D2
381.60099.650D3
391.57099.680D4
401.58099.670D5
411.54099.710D6
421.45099.800D7
431.41099.840D8
441.40099.850D9
451.39099.860D10
461.48099.770E0
471.55099.700E1
481.55099.700E2
491.50099.750E3
501.52099.730E4
511.52099.730E5
521.51099.740E6
531.50099.750E7
541.49099.760E8
551.46099.790E9
S.NOB.SI.SF.SH.IR.LREMARKS
561.45099.800E10
571.38099.870F0
581.45099.800F1
591.48099.770F2
601.52099.730F3
611.55099.700F4
621.60099.650F5
631.60099.670F6
641.58099.610F7
651.64099.650F8
661.60099.690F9
671.56099.660F10
681.59099.720G0
691.53099.740G1
701.51099.700G2
711.55099.690G3
721.56099.820G4
731.43099.800G5
741.45099.900G6
751.35099.970G7
761.28099.990G8
771.260100.050G9
781.200100.080G10
791.170100.060H0
801.190100.070H1
811.18099.940H2
821.31099.910H3
831.34099.900H4
841.35099.910H5
851.34099.850H6
861.40099.890H7
S.NOB.SI.SF.SH.IR.LREMARKS
871.36099.840H8
881.41099.820H9
891.43099.830H10
901.42099.800I0
911.45099.850I1
921.40099.910I2
931.34099.830I3
941.42099.790I4
951.46099.840I5
961.41099.870I6
971.38099.880I7
981.37099.890I8
991.36099.910I9
1001.34099.9100I10
1011.34099.900J0
1021.35099.890J1
1031.36099.850J2
1041.40099.840J3
1051.41099.900J4
1061.35099.800J5
1071.45099.790J6
1081.46099.730J7
1091.52099.800J8
1101.45099.760J9
1111.49099.700J10
1121.55099.840K0
1131.41099.860K1
1141.39099.990K2
1151.26099.900K3
1161.35099.890K4
1171.36099.860K5
S.NOB.SI.SF.SH.IR.LREMARKS
1181.39099.870K6
1191.38099.860K7
1201.41099.870K8
1211.40099.840K9
1221.41099.850K10
1231.41099.840-
CHECK: LAST RL-FIRST RL=B.S-F.S 99.840-100.00=1.250-1.410 -0.160=-0.160 Hence Ok. RADIAL CONTOUR TABULATION:S.NOB.SI.SF.SH.IR.LREMARKS
011.500101.500100.00B.M
021.190100.310A1
030.800100.700A2
040.200100.300A3
050.060101.440A4
061.260101.240B1
071.300101.200B2
080.700101.800B3
090.050102.450B4
101.410101.090C1
111.550100.950C2
121.435101.065C3
131.440101.060C4
142.54099.960D1
S.NOB.SI.SF.SH.IR.LREMARKS
152.280100.220D2
161.610100.890D3
171.530100.970D4
181.660100.840E1
191.760100.740E2
202.280100.220E3
213.08099.420E4
221.710100.790F1
231.890100.330F2
242.35099.340F3
253.340101.270F4
261.410100.470G1
272.210100.820G2
281.86099.680G3
293.000101.680G4
301.000100.990H1
311.690101.060H2
321.620100.370H3
332.310101.340H4
341.340101.150I1
351.530100.860I2
361.820100.260I3
371.240I4
CHECK:LAST RL-FIRST RL=B.S-F.S 100.260-100.00=1.500-1.240 0.260=0.260
1.5 RESULT:Thus by using the reduced level we can draw the contour. CHAPTER 2 TRIANGULATION2.1 INTRODUTION:Triangulation is a part of geodetic surveying, where the areas of given region if found out by forming well defined triangles. It is based on the trigonometrically propositions then if one side and to angles of the triangle are known, the remaining sides can be computed by the application of sine rule. In this method, suitable points called the triangulation stations are selected and established through the area to be surveyed. 2.2 THEORYThe horizontal control is in geo tech survey is established either triangulation or precise traverse. In triangulation system a no of interconnected triangle in which the length of only one line called the base line and the triangles measured very precisely. Knowing the length of one side to and two angles, the length of the other two sides of each triangle can be computed. The apexes of the triangulation system or triangulation figure. The defect of triangulation is that to accumulate errors of length and azimuth, since the length and azimuth of proceeding line. To control the accumulation of errors, subsidiary bases are also selected. At a certain stations, astronomical observations for azimuth and longitude are also made. These stations are subsidiary stations.
2.3 INSTRUMENT USED:1. The Following are the instruments used in the triangulation survey2. Ranging rod,3. Plumb bob
2.4 PROCEDURE:The given plot is divided in to well condition triangle. Calculate the area of triangle by using the formula S= a+b+c/2, A= adding the all the area of triangle to obtain the total area.
2.5 OBSERVATION:S.NOLINELENGTH(m)
01AC44.60
02AD33.00
03CD30.00
04BD33.00
05BC44.60
CALCULATION: S= a+b+c/2
S1=a1+b1+c1/2Here a1=33m b1=44.60m c1=30m put the values in above equation we get S1=53.80mS2=a2+b2+c2/2Here a2=33m b2=44.60m c2=30m put the values in above equation we get S2=53.80m.A1=495.00m2.A2=495.00m2. A=A1+A2A=495.00+495.00A=990.00m2.CHECK:(2n-4)90=1800(2*3-4)90=18001800=1800Hence ok.
2.6 RESULT: The total area of the given plot by cross staff surveying method. Total area of the given plot by triangulation survey method 990.00m2
CHAPTER-3 TRILATERATION3.1 INTRODUCTION:Trilateration is a plot of geodetic surveying where the area of given region found out forming well-defined triangles. Here the length of the sides of the triangles is found out and finally and the sum of area of all triangles will give the area of the given region.
3.2 THEORY:In trilateration process, the given region is divided into a number of well-defined triangles. The well-defined triangle is the one in which two of these angles are well-defined that is not less than 30degree and not more than 120degree. Thus the given region was divided into such triangle and their sides were measured using tape. The well-defined triangle was set up using the theodolite. The tripod stand was shifted to other points on 3.3 INSTRUMENTS USED:1.Tape2.Ranging rod3.Theodolite4.Cross staff5.Arrows6.Chain7.Plumb bob
3.4 PROCEDURE:The given plot is divided into no of triangle and trapezium. Affixed the ranging rods at A,B,C,D,E measure the base line AC by use of chain take offsets from B,D,E on AC to F,G,H respectively. Also measure the offset distances. Calculate the area of triangle and trapezium from the above measurements. Thus the field or plot whose area is to be found out, is divided into triangle and trapezium total area of the plot is then worked out by the following relations area of triangle = * base * perpendicular offsetArea of trapezium = base * sum of perpendicular offset/2
3.5 OBSERVATION:S.NOLINELENGTH(m)
01BC50
02BD30
03CD40
04AD30
05AC50
CALCULATION: Area of a total ABC A=1/2 B*H A=1/2*60*40 A=1200m2.
3.6 RESULT:The total area of the plot =1200m2.
CHAPTER 4 4. LONGITUDINAL AND CROSS SECTION4.1 INTRODUCTION:Longitudinal section is the process of determine the elevations of points at short intervals along a fixed line such as the center line of railway, highway, canal or sewer. The fixed line may be a single straight line or may be composed of a succession of the straight lines or of series of straight lines connected by curves.Cross sections are run at right angle to the longitudinal profile and on either side of it. 4.2 THEOREY:The longitudinal and cross section may be worked together or separately. In the former case, to additional columns are required in the level field book to give the distance, left s and right of the center line, as illustrated in table. To avoid confusion, the bookings of each cross section should be entered separately and clearly and full information as to the number of the cross section, whether on the left or right of the center line, with any other matter which may be useful, should be recorded.
4.3 INSTRUMENTS REQUIRED:Dumpy levelTripod stand Leveling staffChainTape Arrows
4.4 EXPERIMENTAL PROCEDURE:LONGITUDINAL SECTION:The level is setup on firm ground at suitable portion. A back sight is than taken on the benchmark entered in the back sight. The readings are taken from the starting point A. 0m Are entered in the I.S. the staff readings are taken at the representative points when it is found exceeding about 500m. the instrument is then moved forward and setup on firm ground at the L or before and setup on back sight in then take on the change point just established to find the elevations of new plane of collimation. They may be used as change points whatever possible in order to check the reduced level of the benchmark. CROSS SECTION: Cross section are the section at right angle of the center line and are either side it for the purpose for determine the later outline of the ground surface for the purpose they are each 6m section on the center line. CROSS SECTIONING BY LEVELING:To being with the line is set out first to and on either side of the center line ,at the station on the and the station on the center staff is than hard at each 10m points and other points and other points in appreciable change is slop have been previously on the by means of whites. The reading are then with a level and the distance of staff points measured with the tap and right of the center section.CALCULATION:S.NOB.SI.SF.SH.IR.LREMARKS
011.230101.230100.0000m
021.27099.960L1
031.200100.030L2
041.41099.820R1
051.41099.820R2
061.45099.7805m
071.210100.020L1
081.190100.040L2
091.160100.070R1
101.31099.920R2
111.32099.91010m
121.100100.130L1
131.090100.140L2
141.100100.130R1
151.25099.980R2
161.31099.92015m
171.030100.200L1
181.040100.190L2
191.010100.220R1
201.160100.070R2
211.29099.94020m
221.000100.230L1
231.000100.230L2
241.010100.220R1
251.120100.110R2
261.275100.00525m
270.890100.340L1
280.900100.330L2
290.895100.335R1
301.015100.215R2
S.NOB.S I.SF.SH.IR.LREMARKS
310.960100.27030m
320.780100.450L1
330.830100.400L2
340.870100.360R1
350.920100.310R2
360.985100.24535m
370.700100.530L1
380.760100.470L2
390.830100.400R1
400.840100.390R2
411.000100.23040m
420.605100.625L1
430.660100.570L2
440.715100.515R1
450.730100.530R2
460.770100.49045m
470.520100.740L1
480.540100.720L2
490.590100.670R1
500.620100.640R2
510.630100.63050m
520.360100.900L1
530.390100.870L2
540.480100.780R1
550.470100.790R2
561.8600.550102.65100.70055m
571.780100.780L1
581.780100.780L2
591.805100.755R1
601.870100.690R2
611.840100.72060m
S.NOB.SI.SF.SH.IR.LREMARKS
621.720100.840L1
631.750100.810L2
641.745100.815R1
651.780100.780R2
661.740100.82065m
671.670100.890L1
681.700100.860L2
691.645100.915R1
701.720100.840R2
711.680100.88070m
721.615100.945L1
731.670100.890L2
741.630100.930R1
751.690100.870R2
761.695100.86575m
771.520101.040L1
781.525101.035L2
791.570100.990R1
801.615100.945R2
811.640100.92080m
821.375101.185L1
831.375101.185L2
841.360101.200R1
851.480101.080R2
861.590101.97085m
871.100102.460L1
881.150102.410L2
891.240102.320R1
901.110102.450R2
911.025102.53590m
920.890102.670L1
S.NOB.SI.SF.SH.IR.LREMARKS
930.910102.650L2
941.040102.520R1
950.880102.680R2
960.805102.75595m
970.650102.910L1
980.735102.825L2
990.910102.650R1
1000.620102.940R2
1010.600102.960100m
1020.500103.060L1
1030.600102.960L2
1040.745102.815R1
1050.450102.110R2
1060.420102.120-
CHECK: B.S-F.S=LAST RL-FIRST RL 3.090-0.970=102.120-100.00 2.120=2.120 Hence ok.
4.6 RESULT:By means of taking the RL reading longitudinal and cross sections has drawn. CHAPTER-5 AZIMUTH OBSERVATION OF THE SUN5.1 INTRODUCTION:The azimuth of a heavenly body is defined as the angle between the observers meridian and the vertical circle passing through the body.
5.2 THEORY:The general procedure is the same as for a sun. Apart from the correction due to fraction, the parallax correction is also to be applied to the observed altitude, since the sun is very close to the earth. The required altitude and the horizontal angles are with respect to the limbs simultaneously. The opposite limbs are observed by changing the face.
5.3 INSTRUMENTS USED:The following are the surveying instruments, they are Theodolite Tripod stand Ranging rods Arrows Plump bop
5.4 EXPERIMENTAL PROCEDURE:For every precise work, the altitude reading should be corrected for the inclination. Set the instrument over the station, mare and level it accurately. Clamp both the plates to zero and sight and reference mark, the telescope is turned towards sun and the altitude and the horizontal angle with the sun in I quadrant of the crosswire system is measure. By the motion in azimuth is slow, and the vertical hair is kept in contact by the upper slow motions crew, the being allowed to make contact with horizontal.
The time of observation is also noted. Using the two tangents screws, as quickly as possible, the sun into 3 quadrant of the crosswire and again read the horizontal and vertical angle. Chronometer time is also observed. Turn to the reference and mare the face and take another sight on the reference mark. Take two more observation the sun precisely in the same way as performed in the same manner as the corresponding star observation. The correct value of the suns declination can be computed by knowing the time of observation, by the method discussed earlier, finally bisect the reference to see that the reading is zero.
During the above 4 observation, the sun changes its position consistory and accurate result cannot be obtained by averaging the measured altitudes and the times. However, the time taken between, 1, 2, readings, with the sun in quadrants 3, and 1 vary little and hence the measured altitudes and the corresponding times can be average to get on value of the azimuth. Similarly the altitudes and timings of the last two reading, with the sun in quadrants 2, 3 can be averaged to get another value of the azimuth. The two values of the azimuth so obtained can be average to get the final value of the azimuth.
5.5 OBSERVATION AND CALCULATION: Clockwise angle from reference line=17400010 Mean observed altitude of sun, =1104000Determination of sun =2104000Horizontal parallax=000008.9Altitude of perambalur=1100000Corrected angle=1104000+000008.9 =110408.9Refraction correction=0000057cot110408.9 =0000055.82Corrected angle=1104000+000008.9 =110408.9Co-declination, ps =900+2104000 =11104000Co-altitude, pz=900-110408.9 =7801956.1Co-latitude, zs=900-110 =790 By substituting the values of PS, ZS, PZ, we get A=16205956.1 Azimuth of sun =10600000+11405222.5 =26805956.15.6Result: The azimuth of the sun is=26805956.1CHAPTER-6 PLANE TABLE SURVEYING6.1 INTRODUCTION:Plane tabling is a graphical method of surveying in which the fields work and plotting are done simultaneously. It is most suitable for the filling in of the details between the stations previously fixed by the triangulation or theodolite traversing.
6.2 THEOREY:It is particularly adapted for small scale or medium scale mapping in which great accuracy in detail is not required as for topographical surveys. The plane table consists essentially of (1) a drawing board mounted on a tripod (2) a straight edge called an alidade. There are five methods of surveying with plane table, Radiation Intersection Traversing
6.3INSTRUMENTS USED: A plane table with tripod stands An alidade Plumb bob Ranging rods Tape.
6.4 RADIATION6.4.1 THEOREY:In this method the point is located on plane by drawing a ray from the plane table station to point, and plotting to scale along the way the distance measured from the station to the point. The method is suitable for the survey of the small areas which commanded from a single station.
It chiefly used for locating the details from stations, which have been previously established by other methods of surveying such triangulations or transit tape traversing.
6.4.2 EXPERIMENTAL PROCEDURE:Select a point P so that all points to be located are visible from it. Set up the table at P and after leveling it, clamp the board .Select a point P on the sheet so that it is exactly over the station P on the ground by the use of U frame. The point represents on the sheet the instrument station P on the ground. Mark the direction of the magnetic meridian with the help of the compass in the top corner of the sheet. Centering the altitude on P, sight the various points A, B, C, etc., and draw rays along the fiducially edge of the alidade lightly with the chisel pointed pencil. Measure the distances PA, AB, AC, etc., from P to the various points with the chain or tape, or by stadia and plot them to the scale along the corresponding to the rays. Joint the points a, b, c, etc., to give out line of the surveyor. Care must be taken to see that the alidade is touching the P point p while the sights are being taken. To avoid the confusion, the various rays should be referenced the work can be checked by the distances, AB, BC, CD, etc., and comparing them with their plotted lengths a b, b c, cd, etc.,
6.4.3 CALCULATION:S = a1 +b1 +c1 /2
PAB: S1=12+10.5+18.6/2S1=20.55mA1=58.68m2.
PBC:S2=10.5+12.8+9.70/2S2=16.5m.A2=49.90m2.
PCD:S3=9.70+10.90+9.60/2S3=15.10m2.A3=43.40m2.
PDE:S4=10.90+15.15+11.70/2S4=18.88m.A4=63.52m2.
PEA:S5=15.15+12+14.2/2S5=20.675m.A5=80.10m2.Total area A=A1+A2+A3+A4+A5 A=58.68+49.90+43.40+63.52+80.10 A=295.60m2.
6.4.4 RESULT: The total area of the given plot is 295.60m2
6.5 INTERSECTION METHOD6.5.1 THEORYIn this method the point is fixed on plan by the intersection of the rays drawn from instrument station the line joining the station is called the base line. The method requires only the linear measurement of this line. The method is commonly employed for locating, the detail, the distances and inaccessible points they, broken boundaries, the rivers and the points which may be used subsequently as the instrument station it is suitable when it is difficult or impossible to measure distances assume the case of the survey of a mountains country. It is also used for checking distance object.
6.5.2PROCEDURESelect two points P and Q in a commanding position so that all points to be plotted are visible from both P and Q. The line joining the station P and Q is known as the base line. With the table set up and leveled at P, select a suitable point p on paper so that it is over the instrument station P on the ground, and mark the direction of the magnetic meridian by means of the compass. With the alidade pivoted on the point p, sight the station Q and the objects. A ,B, C, etc., to be located, and draw rays along the fiducially edge of the alidade towards Q, A, B, C, etc. measure the distance from P and Q, accurately with the steel tape and set it off to scale along the ray drawn to Q thus fixing the position of q on the sheet. Shift the table and set it up at Q. center the table so that the point q is directly above the point Q on the ground and level it. Place the alidade along qp, and after orienting the table by back sighting on P, clamp it. With the alidade touching q, sight the same object the same objects and drawn from p determine the positions of the objects A, B, C etc. on the sheet. Care should be taken to avoid very acute or obtuse intersections. The extreme limits for the angles of intersection being 30 and 120.
6.5.3 CALCULATION: S=a+b+c/2
ABE:S1=21+34.3+29.1/2S1=42.20m.A1=304.28m2.
BCE:S2=15.7+30+34.3/2S2=40m.A2=235.38m2.
CDE:S3=17.4+20.8+30/2S3=34.10m.A3=176.22m2.
Total area A=A1+A2+A3 A=304.28+235.38+176.22 A=715.88m2.
6.5.4 RESULT:A new station is established by intersection method 6.6 TRAVERSING6.6.1 THEORY:This method is similar to that of compass or transit traversing. It is used for running survey lines between stations it have been previously fixed by other methods of surveying to locate the topographical details. It is also suitable for the survey of roads, rivers, etc.,
6.6.2 PROCEDURE:Select the traverse station A, B, C, etc., setup table at A. select the point a suitably on the sheet. Center and level the table when the board is clamped. Mark the direction of the magnetic meridian on the sheet. Centering the alidade on a, sight the ranging rod at B and draw a ray along the beveled edge of the alidade. Measure the chain or tape, and lay it off to scale on the ray drawn towards B, thus fixing the position of b on the sheet, which represents the station B on the ground. Locate the surrounding detail by radiation or by offsets taken in the usual way, and the distant objects by intersection. Shift the instrument and set it up at B. having centered and leveled the, orient it by back sighting on A with the alidade along ba, and clamp the board. With the alidade pivoted on b, sight the station C and draw a ray along the fiducially edge of the alidade. Measure the distance BC with the chain or tape, and set it off to scale on the ray drawn to C to fix the point c on the sheet. The near-by detail is located as before. Continue the process until all the remaining stations are plotted.
CALCULATION:S=a+b+c/2
BCD:S1=20+24.45+38.3/2S1=41.375m.A1=214.54m2.
ABD:S2=38.3+26.5+38.10/2S2=51.45m.A2=474.71m2.
AED:S3=14+31.4+38.1/2S3=41.75m.A3=209.20m2.
Total area A=A1+A2+A3 A=214.54+474.71+209.20 A=898.45m2.
6.6.3 RESULT: A new station is established by traversing method
SUMMARYThe survey camp provided a good opportunity for us, the building civil engineers to test our theoretical learning to the real life problems. It has kindled our skills and widens our knowledge. We went local visit to elambalur and contouring has been conducted. We calculated the area of the playground by dividing the ground into various triangles using triangulation. We also computed the area using triangulation. The azimuth of the sun and the star was and then determined using the theodolite.
REFERENCE1.Dr.B.Cpumina, (2004) Surveying (volume 1, 2, 3) , Lakshmi publication, new Delhi2.Dr .S . C. Rangwala and P .C ..Rangawala ,(1991) Surveying and Levelling . CharoterPublishers , New delhi .3.T .P .Kanetkar and prof .S .V .Kulkarni, (1991) Surveying and Levelling -puneVidhyarthiGirhaPrakasam, Pune.4.S .k .Duggal , (1996) Surveying Volume 1- Tata McGraw Hill Publishing Company Ltd, New Delhi.5.Y .R .Nagarj and Veraraghavan, (1999) Surveying Volume 1-New Chand and Bros ,Roorkee.6.A .M . Chandra Higher Surveying- New Age International Private Ltd, publishers, New Delhi.