Surefli

Embed Size (px)

Citation preview

  • 8/6/2019 Surefli

    1/26

    Project Management

    Planning & Control

    SureFli Case Study1

    1 Copyright H.A.Ainsworth April 1999, 2002

    Page 1 of 26

  • 8/6/2019 Surefli

    2/26

    SureFli Ground Services PLC

    1.0 IntroductionSureFli Ground Services PLC has been providing a wide range of services at airports andto airline companies. Recently it has expanded its operations into the field of aircraft

    maintenance.The Civil Aviation authorities require that all aircraft are subjected to rigorousmaintenance inspection at stipulated regular intervals.The expansion is part of the long term strategy of SureFli in accordance with its missionto be ... the leading provider of a complete range of high quality civil aircraft services....The timing of the decision to proceed coincides with an opportunity to tender for a fiveyear contract to provide the maintenance for the Airbus fleet of a major internationalpassenger airline.

    1.1 Company OrganizationThe current company organisation structure is shown below. The new division is to be

    called Aircraft Maintenance. Each division is headed by a director with a place on theBoard of Directors.

    C a t e r i n g

    D i v i s i o n

    A i r p o r t R e t a i l

    S e r v i c e s

    D i v i s i o n

    C a r g o H a n d l i n g

    D i v i s i o n

    S u r e F l i

    B o a r d o f D i r e c t o r s

    1.2 The Proposed Aircraft Maintenance DivisionBefore establishing this division a feasibility study is to be conducted which will need toevaluate a range of problematic areas and propose viable solutions. It is clear from

    discussions held with the airline that turn-round time, safety standards and emergencysupport will be key factors when the tenders are examined.The Director himself has taken charge of the project to put together a tender as he has hadsome experience of project management and feels the sensible application of thetechniques will give the best possible chance of success. However you have beeninstructed to carry out the feasibility study project with the brief to examine a range ofissues, namely turn-round time, staffing, costs, project structure, quality assurance, costand time monitoring methods etc.

    1.3 Aircraft MaintenanceThe requirements, spelled out in the tender documents, cover full maintenance of the

    aircraft engines, its airframe and fuel tanks and all landing gear. After the aircraft has beenchecked in and all the relevant data recorded it will be moved to a maintenance hangar andpositioned ready for work to begin. The first activities are concerned with conducting adetailed inspection of all the three areas of concern by suitably qualified inspectionengineers. From this a complete list of required rectifications is produced for the relevantfitters to perform. Once the rectifications have been done thorough checking is carried outbefore the aircraft is signed off and moved from the hangar ready to resume service.Clearly it is desirable to minimise the loss of income incurred by the airline by completing

    Page 2 of 26

  • 8/6/2019 Surefli

    3/26

    the maintenance as quickly as possible. However safety should never be compromised forthe sake of shorter turnaround.

    2.0 Project DataAs a first step in the planning process the Project Manager should develop a first levelWork Breakdown Structure (see Fig 1 below) before proceeding to gather detailed data.

    The packages at the first level may be called Phases, Stages or whatever is mostappropriate. As the lower levels of the structure are produced and the work packagesbroken down into activities or tasks vital data is recorded for later analysis.

    P r e p a

    A i r c r a

    I n s p e

    A i r c r a

    R e c t i

    A i r c r a

    C h e c

    R e c t i f i c

    M a i n t e

    Figure 1

    Further analysis of each work package produces the second level of the WBS shown inFigure 2 overleaf.

    The packages at the second level might be called Activities (see Table 1 over for adetailed description of each activity). Chapter 4 of Burke gives a thorough evaluation ofWBS (see also Chapter 9 of the MBA Project Management study guide).

    A

    P r e p a r e

    A i r c r a f t

    B C D

    I n s p e c t

    A i r c r a f t

    E F G

    R e c t i f y

    A i r c r a f t

    H

    C h e c k

    R e c t i f i c a t i

    M a i n t e n a

    Figure 2

    Exercise 2

    Page 3 of 26

    Work Package

    Second Level

    Project Title

    Activities

  • 8/6/2019 Surefli

    4/26

    By considering the breakdown of the Aircraft into its main maintenance parts try todevelop an alternative WBS for SureFli.Discuss the organisational structure issues which arise from these two approaches?

    More detailed investigation produces the activity data given below:

    Activity Description Duration(days)

    InspectionEngineers

    Fitters

    A Position & jack up aircraft. Clean undercarriage& remove wheels

    2 - 4

    B Inspect engines 2 1 3C Inspect airframe 4 2 1D Inspect undercarriage 2 1 3E Rectify airframe 4 - 3F Rectify engines 3 - 2G Rectify undercarriage & refit wheels 4 - 1H Check rectification & sign off 2 3 1

    Table 1.

    2.1 Project LogicAfter the construction of the WBS for the project more detailed analysis will be neededbefore we can determine how long the project will take and how much it will probablycost. This entails not only collecting the above data but also establishing the logicalrelationships between activities. Essentially all one has to ask about any particular activityis Which activities are stopping it from starting?. These activities are called theimmediate predecessors.

    Exercise 2.1 In the table below three predecessors have been entered, complete the table

    for the other five activities:

    Activity Description ImmediatePredecessors

    A Position & jack up aircraft. Clean undercarriage & remove wheels NoneB Inspect engines AC Inspect airframe

    D Inspect undercarriage

    E Rectify airframe

    F Rectify engines BG Rectify undercarriage

    HCheck Rectification

    Table 2.

    Page 4 of 26

  • 8/6/2019 Surefli

    5/26

    2.2 Network ConstructionFrom the predecessor data a graphical representation of the logic can be produced usingeither activity-on-node (boxes) or activity-on-arrow (arrows) to represent activities.Currently all commercial software uses the former for network construction.The network, using the activity-on-node method, which is also known as precedencediagramming, is shown below.

    Figure 3.

    Exercise 2.2.

    Draw the activity-on-node network for each of the following projects.i) A company specialising in the erection of swimming pools has broken the activitiesdown as shown below. (Source: Project Management Study Guide, Chapter 6 Task 1).

    Activity Predecessors Duration (weeks) Staff Required

    A - 2 2B - 4 3C A 3 2

    D A 5 4E A 1 3

    F C 2 3G D 5 3H B,E 7 3I H 2 2J F,G,I 3 1

    Page 5 of 26

    B F

    start A C E H end

    D G

  • 8/6/2019 Surefli

    6/26

    ii) (Optional) A heavy engineering company has undertaken to install a large turbine at apower station. A breakdown of the activities with estimated durations and their respectivecosts is given below. (Source: Project Management Study Guide, Chapter 6, Task 2)

    Activity Predecessors Duration (weeks) Costs (000)

    A - 6 120

    B - 5 50C - 4 60D A 4 60

    E B 8 60F B,C 8 136G D,E 7 96H F 4 56I H,G 3 64

    2.3 Network AnalysisNetwork Analysis, also known as Critical Path Analysis (CPA), is carried out in twostages.

    1. Starting with the first activities and passing forwards through the network it is nowpossible to determine the Earliest Start (ES) times for every activity. The earlieststart time for H added to the time H is estimated to take will give us the EarliestFinish (EF) time for the project (i.e. its duration).

    2. A backward pass starting with H will enable us to find the Latest Start(LS) timesfor every activity. The Latest Start for each activity is found by subtracting itsduration from the Latest Start Time of its immediate successor. For example DsLS is Gs LS minus Ds duration i.e. 6-2=4. Should an activity have more than

    one immediate successor the one with the earliest LS (i.e. smallest numerically)will decide that activitys LS.

    Activities where ES=LS have no scope for delay and are said to be Critical - suchactivities are said to have zero Float. Activities with scope for delay will have LS > ES.They are said to havefloat.

    The definition ofTotal Float is LS minus ES ( LS ES ). The sequence(s) of activitieswith no float form what is known as the Critical Path(s). Activities with float are callednon-critical these are the tasks which can be delayed without the project finishing late.

    It should be noted that any particular float is usually shared by a sequence of activities;thus if one non-critical activity is delayed this will normally result in a reduction in thefloat of succeeding activities.

    From the earliest and latest start times we can also find the Earliest and Latest Finishtimes (EF & LF) for each activity. Together these provide the manager with valuableinformation for planning and controlling the project.

    The full critical path analysis for SureFli is shown on the network below:

    Page 6 of 26

  • 8/6/2019 Surefli

    7/26

    Figure 4.

    From this we can see the project will take 12 days and the Critical Path is A-C-E-H.

    Exercise 2.3Carry out the critical path analysis for the two projects from Exercise 2.2.

    2.4 Network InformationWe can display the CPA in tabular form as on occasions it is more useful to the manager.

    A partly completed tabulation of the results is shown in Table 3.

    Activity Duration Earliest

    Start

    Latest

    Start

    Earliest

    Finish

    Latest

    Finish

    Total

    Float

    A 2 0 0 0

    B 2 2 5 3

    C 4 2

    D 2 2

    E 4 6

    F 3

    G 4

    H 2

    Table 3

    Page 7 of 26

    ES

    2 4 TSK Dur

    B 2 F 3 LS TF

    5 3 7 3

    0 0 2 6 10 12

    start A 2 C 4 E 4 H 2 end

    0 0 2 0 6 0 10 0 12

    2 4

    D 2 G 4

    4 2 6 2

  • 8/6/2019 Surefli

    8/26

    Another valuable way of presenting the information both to members of the project teamand management alike is the Gantt chart. Using time on the horizontal axis this graphicalform lays out a bar for each activity set at the Earliest Start time with length representingthe duration. Activities A and B have been drawn on the Gantt Chart below.

    Days of the Project

    Figure 5

    Exercise 2.4a) Complete Table 3 and the Gantt Chart, Figure 4.b) Consider each of the following and discuss their individual effects on the total project

    time:i) Extra work is required rectifying the undercarriage which will take one day

    longer than expected.ii) Inspection and rectification of airframe takes only 6 days.iii) Due to an emergency on an operational aircraft the engine inspection is

    delayed and does not start until the beginning of the 7th day.

    3.0 Resource PlanningBy superimposing the resources required by each activity onto the Gantt chart above wecan determine the resource requirements for each day of the project - this is called theforward load on resources. Table 4 shows the results for Inspection Engineers ( *indicates activities with Float):

    Activity 1 2 3 4 5 6 7 8 9 10 11 12

    A 0 0B 1 1 * * *C 2 2 2 2

    D 1 1 * *E 0 0 0 0F 0 0 0 * * *G 0 0 0 0 * *H 3 3

    Total 0 0 4 4 2 2 0 0 0 0 3 3

    Table 4

    Page 8 of 26

    Task 1 2 3 4 5 6 7 8 9 10 11 12

    A = = = =

    B = = = = :::::: :::::: ::::::

    C

    D

    E

    F

    G

    H

    Float

    Critical

    Non-critical

  • 8/6/2019 Surefli

    9/26

    Exercise 3.1

    Complete the resource analysis table for the forward load on resources for the Fitters.

    Activity 1 2 3 4 5 6 7 8 9 10 11 12

    A

    B

    CD

    E

    F

    G

    H

    Total

    For this particular schedule we can see that the maximum number of Inspection Engineersrequired is 4 and also that there is uneven utilisation of the fitter resource. This shows upclearly in the histogram of the forward load on the resources (see Graph 1).

    Graph 1This can be smoothed by delaying non-critical activities. If the company has limitedresource the load on resources can be levelled by delaying non-critical and also criticalactivities if necessary. The latter will of course extend the duration of the project.

    Page 9 of 26

    RESOURCE HISTOGRAM

    0

    1

    2

    3

    4

    5

    6

    7

    8

    1 2 3 4 5 6 7 8 9 10 11 12 13

    DAY

    MEN

    Fitters

    Inspection Engineers

  • 8/6/2019 Surefli

    10/26

    When activities are delayed it is vital to look at the implications for successor activities asthey will have to be delayed also.

    Exercise 3.2a) By delaying selected non-critical activities smooth the load on Fitters.b) If SureFli decide they only wish to employ 5 Fitters can they still complete the aircraft

    maintenance in 12 days? If so what is the schedule? If not what is the shortest totalproject time and what is the schedule?

    c) Construct a resource analysis table and histogram for Exercise 2.2(i) (see Page 5).Determine if it is possible to complete the project in the shortest possible time withoutever employing more than ten staff simultaneously on the site.

    4.0 Project CostsIt is now possible to do some cost estimating based on the activity data using appropriatecharge out rates for the engineers and fitters; in this case it was decided after consultationwith the Accounting Department that 250 and 200 per day respectively should be used.In addition some estimate of the costs of materials and spare parts that are likely to be used

    also needed including

    The estimated costs in 00 for each activity including labour, materials and/or replacementparts is shown in Table 5.

    Activity LabourCosts

    OtherCosts

    TotalCost

    A 16 1 17B 17 0.6 17.6C 28 28

    D 17 1.2 18.2E 24 9 33F 12 12G 8 8 16H 19 19

    Table 5.

    Using this data we can calculate the cumulative costs for the project on a day-by-daybasis. This information is useful in identifying any potential difficulties the company mayhave with cash flow and could also be used as part of the control process once the project

    is up and running.

    Page 10 of 26

  • 8/6/2019 Surefli

    11/26

    Table 6 shows the breakdown of costs on a daily basis note it has been assumed that thecosts are distributed evenly over the duration of each activity. The cumulative costs areshown in the graph below.

    Days

    1 2 3 4 5 6 7 8 9 10 11 12Activity

    A 850 850 0 0 0 0 0 0 0 0 0 0

    B 0 0 880 880 0 0 0 0 0 0 0 0

    C 0 0 700 700 700 700 0 0 0 0 0 0

    D 0 0 910 910 0 0 0 0 0 0 0 0

    E 0 0 0 0 0 0 825 825 825 825 0 0

    F 0 0 0 0 400 400 400 0 0 0 0 0

    G 0 0 0 0 400 400 400 400 0 0 0 0

    H 0 0 0 0 0 0 0 0 0 0 950 950

    Total

    Cost

    850 850 2490 2490 1500 1500 1625 1225 825 825 950 950

    Cum.Tot.Costs

    850 1700 4190 6680 8180 9680 11305

    12530

    13355

    14180

    15130

    16080

    Table 6.

    Graph 2.

    Page 11 of 26

    SureFli

    Cumulative Costs

    0

    2000

    4000

    6000

    8000

    10000

    12000

    14000

    16000

    18000

    0 5 10 15 20

    Days

  • 8/6/2019 Surefli

    12/26

    Exercise 4.Construct the cost table forExercise 2.2 (i) if the swimming pool company charges out itsstaff at 500 per week and hence draw the cumulative costs graph.

    5.0 Improving The Plan

    The data in Table 1 formed the basis for our first plan. The next stage is to try to improvethat plan. Each of the activities involved was examined in turn and alternative (crash)durations, together with the necessary resources and costs were estimated. These areshown in Table 7 below:

    Activity CrashDuration

    Inspection

    Engineers

    Fitters Estimated TotalCost ($)

    A 1 - 9 1900C 2 2 6 3400

    E 3 - 6 4500F 2 - 4 1600G 2 - 3 2000

    Table 8

    By examining the critical path and selecting the most cost-effective activity to crash theduration of the project can be decreased thus potentially reducing the overhead costs. Thiswill provide management with a range of options from which the final schedule can bechosen after having given full consideration to the resource implications and any necessarytime-cost trade-offs. A characteristic of crash programmes is that inevitably the risk in theproject is increased.

    Exercise 5.5.1 For SureFlia) Determine what alternative schedules are available and their respective total costs.

    b) Find the quickest schedule and its total cost.

    c) If the contract states that there will be a penalty of 1000 per day for each day that theproject takes in excess of 7 days what is the lowest total cost schedule? What is thelowest cost schedule if the penalty is 2000 per day?

    d) If on the other hand the contract states that will be a bonus payment of 2000 per dayfor each day under 12 days what is the optimum schedule now?

    Page 12 of 26

  • 8/6/2019 Surefli

    13/26

    5.2 If a client of the swimming pool company offers a bonus payment of 1000 for everyweek less than the normal finish date and the following tasks can be crashed to thedurations given below for the revised total costs shown finda) the minimum cost b) the quickest schedules.

    Task B D G H J

    CrashDuration

    3 4 3 5 2

    CrashCost

    7500 10500 9000 11500 2000

    5.3 (optional) This exercise uses the problem scenario of Exercise 2.2 (ii) (see Page 6).The data given in the question is to be taken as the normal data resulting in a schedulewith duration 23 weeks at a project cost of $702,000 (see solution to Exercise 4 fromabove). At this stage of the planning you are informed that there is penalty clause inthe contract of $19,000 per week for each week the project lasts beyond 15 weeks (i.e.

    the normal schedule above will incur a penalty of 8 x $19,000 = $152,000) which willbe deducted from the agreed contract price.The following crash cost data is to be used to determine what alternative schedules arepossible and to decide ona) the minimum cost scheduleb) the quickest schedule.

    Activity A B E F G HCrash Duration 4 4 5 6 5 3Crash Cost ($000) 160 60 84 170 120 70

    6.0 Monitoring the ProjectVarious approaches are available depending on the size and complexity of the project. Forsuccessful control three areas must be considered: The original budgeted costs which give a baseline against which to measure The actual costs i.e. the money spent doing The work carried out.

    Only Earned Value Analysis (see Burke Chapter 16) integrates both Time and Cost controlinto one comprehensive framework. In this approach at appropriate times comparison ismade with the baseline costs using the following parameters

    Budget at Completion (BAC) the original planned expenditureBudget Cost for Work Scheduled (BCWS) the original planned cost of the work thatwas planned to have been done by that time.Budget Cost for Work Performed (BCWP) the work that has actually been completedby that time costed at the original budgeted rate.Actual Cost for Work Performed (ACWP) the amount spent achieving the workcompleted by that time.

    Page 13 of 26

  • 8/6/2019 Surefli

    14/26

    From this key data a set ofvariances can be calculated which can be used as indicators ofachievement, an explanation of some of the basic ones follows.Firstly we look at those concerned with monitoring time: Schedule Variance (SV) = BCWP - BCWS SV% = SV/BCWS*100

    A negative SV indicates the project is lagging behind the planned schedule in some way.However it does not necessarily follow that the project will overrun the plannedfinish date as the delays may have been in non-critical activities.

    Secondly we consider the variances which monitor the project costs: Cost Variance (CV) = BCWP - ACWP CV% = CV/BCWP*100

    Here again a negative CV indicates a cost overrun.

    Finally we have

    Estimate at Completion (EAC) the best estimate at that time of how much the project isgoing to cost, initially this will be the same as BAC but later must take into account theperformance during the project so far as follows:EAC = BAC * ACWP / BCWP and

    Variance at Completion = EAC - BAC

    Exercise 6.a) After 6 days activities A, B, C and D are completed. No other activities have been

    started. The total activity costs incurred so far are 8100. Further investigation findsthat the start of both B and D was delayed by 2 days because of an emergency. Othercosts for activity A were 120. Other activity costs as planned. Perform an earnedvalue analysis.

    b) The swimming pool project manager decides to monitor the project (Ex 2.2 (i) normaldurations) on a 3 weekly basis. After 3 weeks he finds that activities A, B and E arecompleted, no other activity having yet started. The total expenditure so far has been9750. Report on the projects progress making any recommendations you considerappropriate.

    c) For Exercise 2.2 (ii) carry out an EVA given that after 13 weeks activities A, B and Care completed, D, E and F are half complete and activities G, H and I have not yetstarted. The total expenditure so far has been $400,000.

    7.0 Project OrganisationEven experienced practitioners find it difficult to explain how one should proceed when

    choosing the organisational structure for a project. The choice is determined by the

    situation, but even so is partly intuitive. There are a few accepted principles of design, and

    no step-by-step procedures that give detailed instructions for determining what kind of

    structure is needed and how it can be built. All we can do is consider the nature of the

    potential project, the characteristics of the various organisational options, the advantages

    and disadvantages of each, and make the best compromise we can.

    Page 14 of 26

  • 8/6/2019 Surefli

    15/26

    In general, the functional form is apt to be the organisational form of choice for projects

    where the main focus must be on the in-depth application of a technology rather than, for

    example, on minimising cost, meeting a specific schedule, or achieving speedy response to

    change. Also, the functional form is preferred for projects that will require large capital

    investments in equipment or buildings of a type normally used by the function.

    If the firm engages in a large number of similar projects (e.g., construction projects), the

    pure project form of organisation is preferred. The same form would generally be used for

    one-time, highly specific, unique tasks that require careful control and are not appropriatefor a single functional area - the development of a new product line, for instance.

    When the project requires the integration of inputs from several functional areas and

    involves reasonably sophisticated technology, but does not require all the technical

    specialists to work for the project on a full-time basis, the matrix organisation is the only

    satisfactory solution. This is particularly true when several such projects must share

    technical experts. But matrix organisations are complex and present a difficult challengefor the PM. They should be avoided when simpler organisational structures are feasible.

    In choosing the structure for a project, the first problem is to determine the kind of work

    that must be accomplished. This is best done by first identifying the primary objective(s)

    of the project and then determining the major tasks associated with each objective. Next,

    this work can be decomposed into work packages. We can then consider just what

    individual organisational elements or subsystems will be contained within the project.

    Additional items to consider are the individuals doing the work and their personalities, the

    technology to be employed and the clients to be served. Environmental factors inside and

    outside the parent organisation must also be taken into account. By understanding the

    various structures, their advantages and disadvantages, a firm can select the organisationalstructure that seems to offer the most effective and efficient choice.

    Page 15 of 26

  • 8/6/2019 Surefli

    16/26

    Since it is our objective to provide criteria for the selection of a project oroanisation, we

    shall illustrate the process with two Case Studies (see Appendix A). In each case, we use

    the following approach.

    1. Define the project with a statement of the objective(s) that identifies the major

    outcomes desired.

    2. Determine the key tasks associated with each objective and locate the units in the

    parent organisation that serve as functional home for these types of tasks.

    3. Arrange the key tasks by sequence and decompose them into work packages.

    4. Determine which project subsystems are required to carry out the work packagesand which subsystems will work particularly closely with which others.

    5. List any special characteristics or assumptions associated with the project

    - for example, level of technology needed, probably length and size of the project,

    any potential problems with the individuals who may be assigned to the work,

    possible political problems between different functions involved, and anything else

    that seems relevant, including the parent firms previous experiences with different

    ways of organising projects.

    Exercise 7.

    i) In light of the above and the analysis carried out discuss the pros and cons of the variousorganizational structures for SureFli.ii) Study the Case Studies in Appendix A and propose a suitable organizational structurefor each.

    Page 16 of 26

  • 8/6/2019 Surefli

    17/26

    Appendix A

    The Trinatronic Co.And

    An Urban Hospital

    Case studies in project organisation

    Based on studies described in Meredith J.R, Mantel S.J., Project Management: AManagerial Approach, Wiley (1995)

    Page 17 of 26

  • 8/6/2019 Surefli

    18/26

    TRINATRONIC. INC

    Project objective: To design, build and market a multi-tasking PC with a 64-bit processor,128 Mbytes RAM, and at least 20 Gbytes of disk space to retail at $2,000 or less.

    Key Issues

    A. Write specifications.B. Design hardware, do initial

    tests.C. Engineer hardware for

    production.D. Set up production line.E. Manufacture small run,

    conduct quality and reliabilitytests.

    F. Write (or adopt) operatingsystems.

    G. Test operating systems.H. Write (or adopt) operating

    systems.I. Test applications software.J. Prepare full documentation,

    repair and user manuals.

    K. Set up service system withmanuals and spare parts.

    L. Prepare marketingprogramme.

    M. Prepare marketingdemonstrations

    Organisational Units

    Mktg. Div. And R&DR&D

    Eng. Dept., Mfg. Div.

    Eng. Dept., Mfg. Div.V.P. staff

    Software Prod. Div.

    Q.A. Dept, Exec. V.P. staffSoftware Prod. Div.

    Q.A. Dept, Exec. V.P. staffTech. Writing Section (EngDiv) and Tech. WritingSection (Software Prod.Div.)Service Dept., Mktg. Div.

    Mktg. Div.

    Mktg. Div.

    Page 18 of 26

  • 8/6/2019 Surefli

    19/26

    Without attempting to generate a specific sequence for these tasks , we note that they seem

    to belong to four categories of work

    1. Design, build and test hardware.

    2. Design, write and test software.

    3. Set up production and service/repair systems with spares and manuals.

    4. Design marketing effort with demonstrations, brochures and manuals.Based on this analysis, it would appear that the project will need the following elements:

    Groups to design the hardware and software.

    Groups to test the hardware and software.

    A group to engineer the production system for the hardware.

    A group to design the marketing programme.

    A group to prepare all appropriate documents and manuals.

    And, lest we forget, a group to administer all the above groups.

    These subsystems represent at least three major divisions and perhaps a half-dozendepartments in the parent organisation. The groups designing the hardware and themultiple operating systems will have to work closely together. The test groups may workquite independently of the hardware and software designers, but results seem to improvewhen they cooperate.

    Trinatronics has people capable of carrying out the project. The design of the hardwareand operating systems is possible in the current state of the art, but to design suchsystems at a cost will allow a retail price of $2,000 or less will require an advance in thestate of the art. The project is estimated to take between 18 and 24 months, and to be themost expensive project yet undertaken by Trinatronics.

    Page 19 of 26

  • 8/6/2019 Surefli

    20/26

    URBAN HOSPITAL

    Project objective: To develop and implement a computerised scheduling system for thehospitals operating rooms.

    Key Issues

    A. Find and prioritise objectives ofthe system.

    B. Build preliminary model.C. Program and testpreliminary

    model.D. Use model in parallel with current

    scheduling system.E. Compare results and present to

    Dept. of Surg.F. If necessary, amend model and

    repeat tasks D and E.G. Install model, including full

    documentation.H. Train Dept. of Surg. clerks in

    operation of model.

    Organisational Units

    Syst. Anal., Admin. Dept., andDept. of Surg.Syst. Anal., Admin. Dept.Syst. Anal., Admin. Dept.

    Syst. Anal., Admin. Dept.

    Syst. Anal., Admin. Dept., andDept. of Surg.Syst. Anal., Admin Dept., andDept of Surg.Syst. Anal., Admin. Dept.

    Syst. Anal., Admin Dept., and Dept. of Surg

    The order in which tasks should be performed is as shown above because all the workmust be done sequentially. There are three major jobs.

    1. Build the model based on input from the users.

    2. Test model on an as if basis and amend if necessary.3. Install model and train operators.

    Only two units will be required for the project, a systems analysis group (housed in theDepartment of Administration) and a user group. Analysts and users will have to worktogether throughout the project. These groups each represent a different part of theparent organisation.

    Consideration was given to the use of an outside consultant to analyse the system anddevelop the model. The internal systems analysts are heavily involved in replacing anoutside vendors accounting software system with one of their own devising. They expect

    to be fully occupied for another six to eight months. On the other hand, some members ofthe Department of Surgery are worried that the hospitals own analysts will not besensitive to the special needs of the department and would be even less likely to tolerateand trust outsiders. Indeed, several of the surgeons are doubtful about the entire project.They are not sure that it makes any sense to set priorities on the objectives for schedulingthe operating rooms because quality of patient care is our only priority.

    Page 20 of 26

  • 8/6/2019 Surefli

    21/26

    Suggested SolutionsExercise 2.

    A

    P r e p

    B F

    E n g i n

    C E

    A i r f r a

    D G

    U n d e r

    H

    C h e c

    M a i n t

    Exercise 2.1

    Activity Description ImmediatePredecessors

    A Position & jack up aircraft. Cleanundercarriage & remove wheels

    None

    B Inspect engines AC Inspect airframe AD Inspect undercarriage AE Rectify airframe CF Rectify engines BG Rectify undercarriage DH Check Rectification E,F,G

    Exercise 2.2 and 2.3 Complete Solutionsi) Critical Path B, H, I and J . Shortest completion time 16 weeks

    Page 21 of 26

    2 5

    C 3 F 2

    8 6 11 6

    0 16

    0 2 7 13

    start A 2 D 5 G 5 J 3 end

    1 1 3 1 8 1 13 016

    2 4 11

    E 1 H 7 I 2

    3 1 4 0 11 0

    0

    B 4

    0 0

  • 8/6/2019 Surefli

    22/26

    ii)Quickest completion time is 23 weeks. Cost $702,000

    Exercise 2.4a)

    N.B. ES=Earliest Start, LS=Latest Start, EF=Earliest Finish, LF=Latest Finish

    b) Class exercise

    Page 22 of 26

    Task Duration ES LS EF LF Float

    A 2 0 0 2 2 0

    B 2 2 5 4 7 3

    C 4 2 2 6 6 0

    D 2 2 4 4 6 2

    E 4 6 6 10 10 0

    F 3 4 7 7 10 3

    G 4 4 6 8 10 2

    H 2 10 10 12 12 0

    0 5 13

    C 4 F 8 H 4

    4 4 8 3 16 3

    0 23

    0 5 13 20

    start B 5 E 8 G 7 I 3 end

    0 0 5 0 13 0 20 0

    23

    0 6

    A 6 D 4

    3 3 9 3

  • 8/6/2019 Surefli

    23/26

    Exercise 3.1.

    Exercise 3.2.

    a)

    b) No the project must be extended to 13 days by delaying B 2 days, F 4 days and H 1 day.

    Page 23 of 26

    Task TF 1 2 3 4 5 6 7 8 9 10 11 12

    A 0 === ===

    B 3 === === :::::::::::::::::::::

    C 0 ============

    D 2 === === ::::::::::::::

    E 0 === === == ===

    F 3 === === === ::::::::::::: :::::::

    G 2 === === === === :::::: :::::::

    H 0 === ===

    Task Dur 1 2 3 4 5 6 7 8 9 10 11 12A 2 0 4 ======B 2 1 3 ======::::::::::::::::::C 4 2 1 ========= ===D 2 1 3 ::::::::::::=== ===E 4 0 3 ============F 3 0 2 === === === ::::::::::::::::::G 4 0 1 ::::::::::::=== === === ===H 2 3 1 === ===

    Insp.Eng 0 0 3 3 3 3 0 0 0 0 3 3Fitters 4 4 4 4 6 6 6 4 4 4 1 1

    Task 1 2 3 4 5 6 7 8 9 10 11 12 13

    A == ==

    B ::::: ::::: == == :::::

    C == == == ==

    D == == ::::: :::::

    E == == == ==

    F ::::: ::::: ::::: ::::: == == ==

    G == == == == ::::: :::::

    H ::::: == ==

    Fitter 4 4 4 4 5 5 4 4 5 5 2 1 1

  • 8/6/2019 Surefli

    24/26

    c)

    Exercise 4 All costs in '000sTask Costs 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

    A 2 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0

    B 6 1.5 1.5 1.5 1.5 0 0 0 0 0 0 0 0 0 0 0 0

    C 3 0 0 1 1 1 0 0 0 0 0 0 0 0 0 0 0

    D 10 0 0 2 2 2 2 2 0 0 0 0 0 0 0 0 0

    E 1.5 0 0 2 0 0 0 0 0 0 0 0 0 0 0 0 0

    F 3 0 0 0 0 0 1.5 1.5 0 0 0 0 0 0 0 0 0

    G 7.5 0 0 0 0 0 0 0 1.5 1.5 1.5 1.5 1.5 0 0 0 0

    H 10.5 0 0 0 0 1.5 1.5 1.5 1.5 1.5 1.5 1.5 0 0 0 0 0

    I 2 0 0 0 0 0 0 0 0 0 0 0 1 1 0 0 0

    J 1.5 0 0 0 0 0 0 0 0 0 0 0 0 0 0.5 0.5 0.5

    Total 47

    Total Cost 2.5 2.5 6 4.5 4.5 5 5 3 3 3 3 2.5 1 0.5 0.5 1

    Cum Cost 2.5 5 11 15.5 20 25 30 33 36 39 42 44.5 45.5 46 46.5 47

    Page 24 of 26

  • 8/6/2019 Surefli

    25/26

    Exercise 55.1 a), b), c) & d) Class5.2 First crash J then H to give a new activity cost of 48500. As the CP is now ADGJ and durationis 14 weeks you have gained 2000 in bonuses. Thus the real cost is 46500. Now crash D(cheapest at this stage) giving duration 13 weeks and CPs of ADGJ and BHIJ. Net cost to date46000 this is the least cost option. A quicker option is to now crash B & G to finish in 12 weeks

    but increase the net cost by 2000 to 48500.5.3 Begin by identifying the Critical Path - these are the only activities worth crashing initially or atany stage. Take an incremental approach crashing one activity at a time and then examine the newcritical path by doing the appropriate analysis - this is the only way you can be sure that the savingsin time you are paying for are obtained in practice. If it is not possible to shorten the critical path inthis way it may be necessary to crash several activities simultaneously - this only happens whenthere is more than one critical path. In this way the following schedules can be obtained:

    Original 1 2 3 4 5 6

    ActivitiesCrashed

    None B G E A,B,E B,E,G,H A,B,E,G,F

    Duration(weeks)

    23 22 21 20 19 18 17

    ActivityCost

    702 712 726 726 776 774 834

    PenaltyCost

    152 133 114 95 76 57 38

    TotalCost

    854 845 840 821 852 831 872

    Note: 1)All money figures are in $000. 2) Duplicate solutions giving the same time are possible - only the overall

    cheapest schedule is shown.

    Exercise 6.(a) Class Exercise

    (b)BCWS = 11, BCWP=9.5, ACWP = 9.75, SV= -1.5, CV= - 0.25 EAC= 47* 9.75/9.5Project Finishes in 16 weeks

    Page 25 of 26

  • 8/6/2019 Surefli

    26/26

    Budgeted Expenditure Work Done Actual Cost

    BCWS BCWP ACWP BAC

    A 120 A 120

    B 50 B 50

    C 60 C 60

    D 60 0.5D 30

    E 60 0.5E 30F 136 0.5F 68

    486 358 400 702

    Earned Value Analysis

    edule Variance = 358 - 486 = -128

    SV% = -12800 / 486 = -26.34%

    ost Variance = 358 - 400 = -42

    CV% = -4200 / 358 = -11.73%

    Est. At Completion = 702 * 400 / 358 = 784

    E 8/2

    F 8/2

    D 4/2

    G 7 I 3 end

    13

    13

    13

    H 4

    17

    17

    24 27

    Completion time 27 weeks

    Cost $702,000+42,000

    = $744,000