SPEC NO.: PIF/ Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page - 1 - of 58

ANNEXURE - I TO TENDER NO: SHAR/SCSD/2020013160

Specification for

SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF

MULTI ENTRY ESCAPE CHUTE FOR PIF

OWNER : INDIAN SPACE RESEARCH ORGANISATION

PROJECT : PSLV INTEGRATION FACILITY (PIF) PROJECT

LOCATION : SATISH DHAWAN SPACE CENTRE SHAR

SRIHARIKOTA

PSLV INTEGRATION FACILITY (PIF) PROJECT

SATISH DHAWAN SPACE CENTRE SHAR

SRIHARIKOTA 524 124

INDIAN SPACE RESEARCH ORGANISATION

Page 3: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/ Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page - 2 - of 58

CONTENTS

SECTION TITLE Page No.

Section A General Terms and Conditions 3

Section B Scope of Enquiry and General Project Information

26

Section C Technical Specifications 29

Section D Annexures (D1-D10) 40 – 54

Page 4: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/ Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page - 3 - of 58

SECTION A

GENERAL TERMS AND CONDITIONS

OF THE CONTRACT

Page 5: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: A

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 4 of 58

PROPOSAL DOCUMENT, CLARIFICATION AND ADDENDUM

Quotations are invited from the interested bidders for the enclosed scope of work in two

part bid. Part-1 Technical & unpriced part of the work and Part-2 Priced commercial part.

Only experienced Bidders who are qualifying in bid-qualification criteria given in

Section D2 (Page No. 43-44) only should quote.

This document is organized in four sections as follows.

Section –A General Specification, Terms and Conditions of the Contract

Section –B Scope of Enquiry & General Project information

Section –C Technical Specification.

Section –D Annexures

Title of the proposal:“Supply, Installation, Testing and Commissioning of Multi Entry

Escape chute for PIF (PSLV INTEGRATION FACILITY PROJECT)”

Date Public Notification issued by ISRO: As per notification

Last Date of downloading tender Document by tenderer: As per notification

Last date of submission of tender documents in online by tenderer: As per

notification

Last date of Bid sealing in online by ISRO: As per notification

Last date for giving open authorisation in online by tenderer: As per notification

A PROPOSAL DOCUMENT

1.1. Bidder shall sign & stamp each page of the tender document as token of his

acceptance and submit the same along with his offer.

1.2. Proposal documents shall remain the property of SDSC SHAR and shall not be

used for any another purpose without the consent of SDSC SHAR.

1.3. The proposal shall be completely filled in all respects and shall be tendered

together with requisite information & Annexure. Any offer incomplete in any

particulars is liable to be rejected.

1.4. The Proposal (Unpriced Techno-commercial bid) with a complete set of the

required documents shall be up-loaded in ISRO e-procurement website.

1.5. The Proposals shall be submitted on-line before the time limit for bid submission

specified in the Tender.

1.6. Supplier shall submit the open authorisation on-line with in the time limit specified

in the Tender.

Page 6: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: A

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 5 of 58

1.7. The Proposal will be opened on the date and on the time specified in the Letter

Inviting Bid or as soon thereafter as convenient. Proposal not received in time will

not be considered.

1.8. Bidders shall set their quotations in firm figures and without variations/additions in

the terms of the Proposal documents.

1.9. AMBIGUITY

Should there be any ambiguity or doubt as to the meaning of any of the tender

clause/condition or if any further information is required, the matter shall be

immediately brought to the notice of Head, Purchase & Stores of SDSC SHAR in

writing.

B. PREPARATION OF BIDS

Site Visit

Bidder is advised to visit & examine the site and its surrounding to familiarize

himself of the existing facilities & environment and shall collect all other information

which may be required for preparing & submitting the Bid and entering into the

contract with in the stipulated period. Claims and objections due to ignorance of

existing conditions or inadequacy of information will not be considered after

submission of the Bid and during implementation.

Validity of Offer

Bid shall remain valid for acceptance for a minimum period of 4 (four) months from

the due date of submission of the Bid. The Bidder shall not be entitled during the

said period to revoke or revise his Bid or to vary the Bid except and to the extent

required by SDSC SHAR in writing. Bid shall be revalidated for extended period as

required by SDSC SHAR in writing. In such cases, unless otherwise specified, it is

understood that validity is sought and provided without varying either the quoted

price or any other terms & conditions of Bid finalized till that time.

Cost of Bidding

All direct and indirect costs associated with the preparation and submission of bid

shall be to Bidder's account and SDSC SHAR will in no case be responsible or

liable for those costs, regardless of the conduct or outcome of the bid process.

Applicable Language/ measurements

The bid and all correspondence incidental to and concerning the bid shall be in the

Page 7: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: A

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 6 of 58

English Language. For supporting document and printing literature submitted in any

other language, an accurate English Translation shall also be submitted.

Responsibility for correctness in translation shall lie with the Bidder. All the

measurements shall be given in metric system.

Arrangement of Bid

The Bid shall be neatly presented on white paper with consecutively numbered

pages. It should not contain any terms and conditions which are not applicable to

the Bid. The Bid and all details submitted by the Bidder shall be signed and

stamped on each page as token of acceptance, by a person legally authorised to

enter into agreement on behalf of the Bidder. (Corrections/ alteration, if any, shall

also be signed by the same person).

Schedule of Prices

The schedule of prices shall be read in conjunction with all the sections of proposal

document. The price must be filled online in the same format of ‘Schedule of

Prices’ in Section D1 (Page No. 41&42) . No copy of price bid shall be enclosed

along with other document and upload the same anywhere in the e-procurement

portal.

Documents Comprising the Bid

Bids shall be arranged in the following order.

1.1.1 Part – I : Technical and Unpriced Commercial Part

Technical and unpriced commercial part shall comprise the attachments,

specifying attachment number arranged in the order as follows:

(a) Submission of bid letter.

(b) Power of attorney in favour of authorised signatory of the bid / proposal

documents.

(c) All the annexure in Section-D1 to D9 (Page No. 41 to 53) enclosed in

proposal duly filled, signed and sealed.

(d) Bid qualification criteria for supply, erection, commissioning and testing of

Multi Entry Escape chute and all supporting documents.

(e) General arrangement drawings of Multi Entry Escape chute.

(f) Write-up on the procedure proposed to be followed for erection &

commissioning of Multi Entry Escape chute.

Page 8: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: A

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 7 of 58

(g) Unpriced copy of schedule of prices with all other commercial terms,

taxes, duties, exemption certificates and conditions duly filled (Prices to be

kept blank), signed and stamped.

(h) Audited balance sheet including profit and loss account for last three

financial years showing annual turnover

(i) Latest income tax certificate.

(j) Latest solvency certificate for Rs. 20 Lakhs from a scheduled bank.

(k) Description of the procedures adapted for material procurement,

fabrication & control assembly with deviations from technical specification

and proposed design modifications.

(l) Data sheets for all the equipment & checklists enclosed in proposal duly

filled, signed & stamped.

(m) Technical literature & data sheets of equipment / machinery used by him

and any other document as mentioned in the proposal.

(n) Project execution plan

(o) Bar chart for supply & erection schedule indicating the date of completion

of various activities so as to complete the execution of the contract within

the time frame stipulated in the tender specification.

(p) List of items which require Customs from SDSC-SHAR.

(q) List of recommended spares including unit prices.

(r) Any other relevant document, bidder desires to submit.

1.1.2 Part – II :Priced Commercial Bid

Priced commercial bid shall be filled online in the price bid format. Schedule of

prices also to be filled in the online format and no separate document shall be

attached. Deviations in terms and conditions, assumptions, discounts etc. shall be

stipulated in format specified in the portal. SDSC SHAR will not take cognizance of

any such statement and may at their discretion reject such bids.

C. BID SUBMISSION

Bids duly filled in by the Bidder should invariably be submitted as stipulated in the

Letter inviting bid. Bids shall be submitted in the following manner.

1.1 Part – I : Unpriced Techno-Commercial Part of the Bid for the Work

Complete Techno–commercial part of the bid shall be filled online in the “vendor

Page 9: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: A

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 8 of 58

Specified Terms’ form of the e-tender. Any documents related technical literature,

guarantee / warrantee certificates and any other relevant documents as per the

tender shall be scanned in lower resolution format and uploaded to the e-tender

under ‘Documents solicited from Vendor’ form only in ISRO e-procurement

portal (https://eprocure.isro.gov.in). In case of any clarification please mail to

[email protected] or [email protected]

The deviation statement and checklist shall be filled online, without which the bid

will not be considered.

Part – II: Price Part of the Bid for the Work

Price bid shall be filled in the on-line ‘price bid’ form of the e-tender only in ISRO e-

procurement website “https://eprocure.isro.gov.in”. The cost of spares and other

prices shall be filled in the respective forms available on-line in the e-portal. Any other

terms and conditions given in this part shall not be considered and if insisted upon by

the Bidder, bids are liable for rejection.

a) SDSC SHAR may open Part – I of the bid on the due date of opening subject to

meeting the minimum evaluation criteria. Price Bids (Part-II) of technically and

commercially acceptable offers shall be opened at a later date.

b) SDSC SHAR reserves the right to reject any or all the Bids without assigning any

reasons thereof.

c) Any bids/offers with price details in Techno-Commercial Offer (Part –I) shall be

rejected.

d) SDSC SHAR reserve rights to place order for either full quantities of all items or

partial quantities and partial items based on the unit rates available.

D. VENDOR EVALUATION FORMAT

SDSC SHAR seeks response to the given questionnaire for assimilating data which

would be used for evaluating the capability of the supplier for executing the referred

work. Hence, the supplier is requested to provide only genuine data and any

discrepancy found at a later point of time may result in rejection of the supplier from

purchase process. Furnishing of data cannot be construed as automatic qualification

for participation in the tender. Questionnaire should be signed by a responsible and

authorized person of the Company / Agency.

Schedule of general particulars / vendor evaluation format shall be filled as per

Section: D4 (Page No. 46 &47) . Schedule of Bidders experience and details of

present works executed or being executed are to be filled as per Section: D7 (Page

Page 10: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: A

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 9 of 58

No. 50&51).

Note: In order to consider as valid experience, all the experience has to be supported

with the technical details, completion certificate and purchase order.

E. DETERMINATION OF RESPONSIVENESS

SDSC SHAR will scrutinize tenders to determine whether the tender is substantially

responsive to the requirements of the tender documents. For the purpose of this

clause, a substantially responsive tender is one which inter-alia conforms to all the

terms and conditions of the entire Tender document without any deviations and

reservations. The decision of SDSC SHAR shall be final in this regard.

G BID EVALUATION

1) During evaluation, SDSC SHAR may request bidder for any clarification on the

bid or additional documents.

2) Techno-commercial discussion shall be arranged with bidder, if needed.

Bidder shall depute his authorised representatives for attending discussions.

The representatives attending the discussions shall produce authorisation from

his organisation to attend the discussion and sign minutes of meeting on

behalf of his organisation if required. The authorised representative must be

competent and empowered to settle/decide on all technical and commercial

issues.

3) Bidder must provide the point by point compliance to the technical

specifications along with deviations as per “schedule of deviations” attached in

Section D6 (Page No. 49). The tender will be rejected, if the deviations are not

acceptable to the department.

4) Performance of bidder on similar nature of works executed/ under execution

shall be taken into consideration before selecting the bidder for opening his

price bid.

5) The time schedule for completion is given in the proposal document. Bidder is

required to confirm the completion period unconditionally.

6) If necessary, to arrive at evaluated prices, wherever applicable, loading on

total quoted prices shall be done.

7) SDSC SHAR reserves the right to accept a bid other than a lowest and to

accept or reject any bid in full or part without assigning any reasons. Such

decisions by SDSC SHAR shall bear no liability whatsoever consequent upon

such decision.

8) SDSC SHAR reserves the right to split the order or alter the quantities

Page 11: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: A

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 10 of 58

specified based on prices quoted for part work or unit rate quoted by bidder.

9) The bidder, whose bid is accepted by SDSC SHAR, shall be issued a Letter Of

Intent (LOI) /Purchase Order (PO) to proceed with the work. Bidder shall

confirm acceptance by returning a signed copy of the LOI/PO.

Page 12: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: A

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 11 of 58

GENERAL SPECIFICATION

Page 13: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: A

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 12 of 58

1. INTRODUCTION

SDSC SHAR invites tenders in sealed covers from reputed firms with proven ability

for “Supply, Installation, Testing and Commissioning of Multi Entry Escape

Chute for PIF” as per the specifications.

2. SCOPE OF WORK AND TECHNICAL SPECIFICATIONS

The detailed scope of work and technical specifications are given in Section B (Page

No. 26) & Section C (Page No. 29) of this document. The general terms and

conditions are given below.

3. SUPPLIER's OBLIGATIONS & FUNCTIONS

3.1. SPECIFICATIONS AND DRAWINGS

The Supplier shall execute the works in compliance with the provisions of

CONTRACT, good engineering practices and codes requirements.

3.2. SUBMISSION OF TECHNICAL DOCUMENTS

Supplier shall prepare and submit to SDSC SHAR for approval of following

documents and drawings :

3.2.1. Technical literature & data sheets of equipment used by him.

3.2.2. Chute material, test details, certification etc at manufacturer site.

3.2.3. General arrangement drawings and assembly plan at supplier site.

3.2.4. Details of testing plan

3.2.5. Erection sequence schedule along with erection drawings, interface study

details, floor level interface drawings.

3.2.6. No activity shall be executed unless SDSC SHAR’s approval is obtained.

The above documents shall be submitted in a format approved by SDSC

SHAR.

3.3. DESIGN VERIFICATION & SUPPLY

Supplier shall carry out Design verification and supply of Multi entry escape

chute in accordance with the scope, technical specifications and terms &

conditions of contract.

Page 14: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: A

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 13 of 58

3.4. DELIVERY AND STORAGE

3.4.1. Dispatch Instructions given in the Contract shall be strictly followed. Failure

to comply with the instructions may result in delay in payment apart from

imposing any other charges as may be deemed fit.

3.4.2. The supplier shall be responsible for transporting all the equipment to site,

unloading and storage.

3.4.3. No equipment shall be delivered without obtaining dispatch clearance from

SDSC SHAR.

3.4.4. All the equipment shall be properly packed to avoid any damage during

transportation / handling / storage.

3.4.5. The equipment received at site shall be stored at a place assigned for this

purpose.

4. INSTALLATION & TESTING

4.1. GENERAL

4.1.1. Supplier’s staff shall include adequate number of competent erection

engineers with proven experience on similar works to supervise the erection

works and sufficient skilled, unskilled and semiskilled labour to ensure

completion of work in time.

4.1.2. Supplier's erection staff shall arrive at site on date agreed by SDSC SHAR.

Prior to proceeding to work, Supplier shall however, first ensure that

required/sufficient part of his supply has arrived at site.

4.1.3. Erection of equipment may be phased in such a manner so as not to

obstruct the work being done by other Suppliers and / or operating staff who

may be present at that time.

4.1.4. During erection, Department's quality team / their engineer will visit site from

time to time with or without Supplier’s engineer to establish conformity of the

work with specification. Any deviations, deficiencies or evidence of

unsatisfactory workmanship shall be corrected as instructed by Department.

4.1.5. Supplier shall carry out work in a true professional manner and strictly

adhere to the approved drawings. Any damage caused by Supplier during

erection to new or existing building / environment shall be made good at no

extra cost to Department.

Page 15: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: A

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 14 of 58

4.2. RECORDS

Supplier shall maintain records pertaining to the quality of erection work in a

format approved by Department. Whenever erection work is complete, Supplier

shall offer erected equipment for inspection to Department's engineer who

along with Supplier's engineer will sign such records on acceptance.

4.3. SAFETY

Supplier shall follow the safety regulations / codes and shall take necessary

measures at his own cost.

4.4. ERECTION & CONSTRUCTION POWER

4.4.1. Electrical power and available material handling equipment may be

extended by SDSC SHAR on chargeable basis, as per the tariff rules of

State Electricity Board and SDSC SHAR. Reasonable quality of normal

Construction power will be made available at one point (415V, 3 phase, 50

Hz). However onward distribution shall be by the supplier. Installation of

necessary energy meters, switchgear & distribution system, etc for

Construction power in a safe manner in strict conformity with local rules &

regulations will be responsibility of supplier.

4.4.2. During non-availability of power, supplier shall make his own arrangement of

alternate power source at their cost.

4.5. WORK RULES AT SDSC-SHAR

The work shall be carried out on SDSC-SHAR working days only or permission

to be obtained from the contract manager for late hours / holidays.

4.6. SITE CLEARANCE

Upon completion of work, supplier shall remove all his equipment and material

from the site within one month or time mutually agreed. Supplier at all times

shall keep site in clean condition and remove all unwanted material at regular

intervals. In case supplier fails to remove all their equipment and material within

the mutually agreed time, it is deemed that SDSC SHAR will arrange to remove

the same at Supplier’s cost.

4.7. ACCOMMODATION

4.7.1. Accommodation will not be provided by SDSC SHAR to Contractors.

4.7.2. Supplier shall make their own arrangement for accommodation,

transportation & canteen facility for all his staff, technicians, labour &

workers.

Page 16: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: A

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 15 of 58

4.8. MEDICAL FACILITIES

No medical facilities will be provided by SDSC SHAR. Supplier shall make their

own arrangement at their own expenses for medical facilities for site personnel.

4.9. WORK PROGRAMME

Supplier shall prepare a detailed programme schedule for review / approval by

SDSC SHAR. Supplier as per exigencies of work shall revise and update

programme periodically.

4.10. SUB-CONTRACTS

4.10.1. No work shall be sub-contracted without prior approval of SDSC SHAR.

4.10.2. Supplier shall be responsible for the proper execution of any sub-contract

placed by him in connection with this purchase order.

4.10.3. Supplier shall furnish to SDSC SHAR the copies of all un-priced sub-

orders showing promised delivery dates and places.

4.11. CHANGES AND MODIFICATION TO SPECIFICATIONS, DRAWINGS AND

QUALITATIVE / QUANTITATIVE REQUIREMENTS

4.11.1. Supplier shall obtain approval from SDSC SHAR before initiating the action

for procurement of bought out items.

4.11.2. During the fabrication review, supplier has to carry out the mutually agreed

modifications to meet the overall requirement.

5. RECORD OF DRAWINGS AND O&M MANUALS

5.1. Supplier shall submit 3 hard copies & one soft copy of all the approved drawings

incorporating any modification / changes made during the execution of

CONTRACT. All these drawings shall be marked as 'As Built'.

5.2. Supplier shall submit 3 hard & one soft copy of O&M manual. These manuals

should indicate weekly, monthly and yearly maintenance schedule and other

instructions necessary for safe maintenance of equipment.

5.3. Submission of the drawings and manuals shall be a precondition for releasing of

any final payment due to Supplier.

6. IGST Concession:

As per the Notifications No.47/2017-Integrated tax(Rate) dated 14.11.2017 issued by

Ministry of Finance (Department of Revenue), SDSC SHAR is eligible for a reduced

rate of 5% IGST only wherever IGST is applicable. Accordingly, Concession Certificate

Page 17: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: A

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 16 of 58

will also be provided).

7. CUSTOMS DUTY

We are entitled for Partial Customs Duty Exemption (10.775%) vide Notification

No.05/2018 dt: 25-01-2018 for imports. Confirm whether CD is applicable and if so

whether CD Exemption Certificate is acceptable and the same is required for

exemption.

8. RISK COVERAGE

The Supplier shall arrange comprehensive risk coverage at his own cost covering

the value of equipment including transportation to the site from manufacturer’s

works, storage at site, installation, testing and commissioning at site. The period of

such coverage shall be up to contractual completion period or any extension granted

by Department thereof.

9. INCOME TAX

Income tax at the prevailing rate as applicable and if applicable from time to time

shall be deducted from the supplier's bills as per Income Tax Act and a certificate

issued (TDS Certificate).

10. PERFORMANCE SECURITY

A Bank Guarantee for 10% of the order value shall be provided immediately within

10 days after supply or along with supply towards the performance of the system.

The Bank Guarantee should be from a Nationalised / Scheduled Bank in Rs100/-

non-judicial stamp paper valid till the successful completion of warranty period plus

60 days. This will not carry any interest and shall be returned to you after successful

completion of warranty period against your request. In case of non-

performance/poor performance the Bank Guarantee shall be forfeited.

11. PACKING AND FORWARDING

11.1. The Supplier shall arrange to have all the material suitably packed as per the

standards and as specified in the contract. Unless otherwise provided for in the

contract, all containers (including packing cases, boxes, tins, drums, and

wrappings) used by the Supplier shall be non-returnable.

11.2. All packing and transport charges, transit handling costs, transit risk coverage

and transport fees of agents employed at the place of delivery or elsewhere,

shall be deemed included in the price to be paid to the Supplier.

Page 18: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: A

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 17 of 58

12. ARBITRATION

In the event of any dispute/s, difference/s or claim/s arising out of or relating to the interpretation and application of the Contract, such dispute/s or difference/s or claim/s shall be settled amicably by mutual consultations of the good Offices of the respective Parties and recognizing their mutual interests attempt to reach a solution satisfactory to both the parties. If such a resolution is not possible, within 30 days from the date of receipt of written notice of the existence of such dispute/s, then the unresolved dispute/s or difference/s or claim/s shall be referred to the Sole Arbitrator appointed by the Parties by mutual consent in accordance with the rules and procedures of Arbitration and Conciliation Act 1996 as amended from time to time. The arbitration shall be conducted in Bengaluru in the Arbitration and Conciliation Centre –Bengaluru (Domestic and International) as per its rules and regulations. The expenses for the Arbitration shall be shared equally or as may be determined by the Arbitrator. The considered and written decision of the Arbitrator shall be final and binding between the Parties. The applicable language for Arbitration shall be “English” only.

Work under the Contract shall be continued by the CONTRACTOR during the pendency of arbitration proceedings, without prejudice to a final adjustment in accordance with the decision of the Arbitrator unless otherwise directed in writing by the DEPARTMENT or unless the matter is such that the works cannot be possibly continued until the decision (whether final or interim) of the Arbitrator is obtained.

13. APPLICABLE LAW AND JURISDICTION

The laws of India shall govern this purchase order for the time being in force. The

Courts of Andhra Pradesh, India only shall have jurisdiction to be with and decide

any legal matters or disputes what so ever arising out of the purchase order.

14. GUARANTIES

The Supplier shall guarantee that the equipment furnished by him is in conformance

with the requirement of the specifications. Goods covered by the contract shall be

free from defects in materials or workmanship for a period of Twelve months from

the date of successful commissioning & acceptance by Department.

15. WARRANTY

The bidder shall provide 12 months warranty for the entire system for a defect

liability, after final official handing over at his cost. During this period, supplier has to

provide and adhere to the following:

Page 19: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: A

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 18 of 58

15.1. He has to attend quarterly based preventive maintenance visits and breakdown

maintenance calls. All the defective components have to be replaced or rectified

on one to one basis.

15.2. Break down maintenance should be responded within 48 Hours time and shall

be completed within 48 Hours after respond.

15.3. Department will not provide any transport/accommodation.

15.4. Incase vendor failed to attend and repair the system within 7 days from the date

of reporting the problem, Department will reserve right to forfeiting the BG apart

from withheld of any payment payable to the vendor.

15.5. Where defects in items are remedied under warranty, the period for which the

warranty operates shall be extended by such period, as the items were not

available to SDSC SHAR. Where defect items are replaced by new ones, the

full warranty period stipulated in the purchase order shall apply to such

replacement items as from the date of their delivery.

16. SCHEDULE OF PRICE

16.1. CONTRACT price shall include all costs of “Supply, Installation, Testing and

Commissioning of Multi Entry Escape Chute for PIF”, shop testing, packing,

forwarding, transport to site, unloading, storage, all risk coverage, erection,

installation, testing & evaluation and commissioning of equipment including any

other cost for proper and complete execution of the CONTRACT.

16.2. CONTRACT prices shall also include all travelling expenses, living expenses,

salaries, overtime, benefit and any other compensation for engineers,

supervisors, skilled, semiskilled workmen, watch and ward staff, labours and

other staff employed by the Supplier, cost of tools and tackles required for

erection and other consumable material required, and all taxes, duties, and

levies as applicable on the date of submission of bid.

16.3. Price shall be firm & fixed.

16.4. Supplier shall quote the prices similar to price bid format enclosed as Section–

D1 (Page No. 41)

16.5. The rate quoted shall be on FOR SDSC SHAR, Sriharikota basis.

16.6. The taxes applicable for supply, transportation and erection & commissioning

shall be indicated separately in the price bid. If the offers submitted by the

tenderers are silent on taxes, it will be presumed that quoted rates are inclusive

of taxes & duties and no claim in this regard will be entertained later.

Page 20: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: A

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 19 of 58

17. DISCOUNTS

Tenderer shall not indicate any discount separately and quoted price should be

after deducting the discount.

18. MODE OF PAYMENT

All the payments due to Supplier will be made through PFMS/RTGS. Bidders can

submit the banker details.

18.1. FOR SUPPLY,ERECTION, TESTING AND COMMISSIONING OF MULTI

ENTRY ESCAPE CHUTE SYSTEM

18.1.1. 30 % of Order value as advance against submission of bank guarantee for

an equivalent amount valid till supply period plus 2 months claim period.

18.1.2. 50 % of Order cost payment against receipt of complete material at

Purchasers / Department site, along with 100% GST/IGST.

18.1.3. 10 % of Order cost after successful assembly/Installation of the multi entry

escape chute at site/building.

18.1.4. 10 % of Order cost against successful testing and commissioning &

acceptance by Department of equipment and system covered under

contract and against submission of Performance bank guarantee of equal

amount valid till warranty period plus 3-2 months claim period.

19. PERFORMANCE BANK GUARANTEE

A Bank Guarantee for 10% of the order value shall be provided immediately within 10 days after supply or along with supply towards the performance of the system. The Bank Guarantee should be from a Nationalised / Scheduled Bank in Rs100/- non-judicial stamp paper valid till the successful completion of warranty period plus 60 days. This will not carry any interest and shall be returned to you after successful completion of warranty period against your request. In case of non performance/poor performance the Bank Guarantee shall be forfeited.

20. COMBINED BANK GUARANTEE FOR SECURITY DEPOSIT CUM

PERFORMANCE BANK GUARANTEE

In case, if parties are unable to provide two separate BGs, i.e., one for SD &

one for PBG, they can submit a combined BG for SD & PBG for 10% of the

Order value valid till the completion of total contractual obligation (i.e., Supply

period + warranty period + 60 days).

A combined Bank Guarantee (as per the format enclosed) for 10% of the order

value) shall be provided immediately within 10 days after receipt of order

towards the performance of the contract & the performance of the system. The

Page 21: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: A

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 20 of 58

Bank Guarantee should be from a Nationalised/ Scheduled Bank (as per the

format enclosed) in Rs.100 non-judicial stamp paper valid till the successful

completion of contractual obligation (i.e., for the period of supply + warranty +

60 days). This will not carry any interest and shall be returned to you after

successful completion of contractual obligations. In case of non

performance/poor performance the Bank Guarantee shall be forfeited. If you are

not submitted the BG within the specified period, this order is liable to be

cancelled.

21. Purchase / Price preference to MSEs:-

Purchase/Price preference will be applicable in addition to product reservation

admissible to the Micro and Small Enterprises. Purchase/Price Preference shall

be extended to the MSEs under the Public Procurement Policy for MSEs

formulated under the Micro, Small and Medium Enterprises Development Act,

2006. The participating MSEs in a tender, quoting price within the band of L-1 +

15% may also be allowed to supply a portion of the requirement by bringing

down their price to the L-1 price, in a situation where L-1 price is from someone

other than an MSE. Such MSEs may be allowed to supply upto 25% of the total

tendered value. In case of more than one such eligible MSE, the supply will be

shared equally.

Note : Applicability of the above mentioned is subject to technical possibility.

Micro & Small Enterprises which have technical capability to deliver the goods

& Services as per prescribed technical & quality specifications and may not be

able to meet the qualification criterion relating to prior experience-prior turnover

may be relaxed as per guidelines issued by Ministry of MSMEs & as amended

from time to time.

22. DELIVERY SCHEDULE

The commissioning of MULTI ENTRY ESCAPE CHUTE within the schedule is

very essential. Hence, bidders are requested to adhere to the completion time

strictly. Multi entry escape chute as per the specifications of the contract shall be

delivered within 2 (Two) months from the date of release of Purchase Order.

Installation, testing & commissioning shall be carried out within one month from

date of clearance by the Department. Department will intimate the readiness, at

least seven (7) days in advance. However, the commissioning will be carried out

within months from the date of supply.

Page 22: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: A

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 21 of 58

23. LIQUIDATED DAMAGES

In the event of the Supplier failing to complete the work within the delivery period

specified in the contract agreement or in extension agreed thereto, Department

shall reserve the right to recover from the Supplier as liquidated damages, a sum

of 0.5 percentage per week or part thereof of the undelivered portion of the total

contract price of equipment or work. However, the total liquidated damages shall

not exceed 10.0 percentage of the total Contract price. The LD reckoning date

shall be 2 months onwards for supply portion from the date of release of

purchase order and after 1 month from date of site clearance by Department for

installation, testing and commissioning.

24. FORCE MAJEURE

If at any time during the continuance of the order the performance in whole or

part by either party of any obligation under this order shall be prevented or

delayed by reasons of any war, hostility, acts of public enemy, civil

commotion, sabotage, fire, floods, lightening, epidemic, quarantine restrictions,

strikes, go-slow, lockout or acts of God, notice of which is given either party to the

other within 21 days from the date of occurrence thereof, neither party shall be

reasons of such eventually be entitled to terminate this order nor shall either party

have any claim for damages against the other in respect of such non-

performance or delay in performance.

25. DISCLOSURE AND USE OF INFORMATION

25.1. If the documents supplied by SDSC SHAR are marked “Strictly Confidential”,

supplier shall take all necessary steps to ensure the same.

25.2. Supplier shall guarantee that all information and data received during execution

of Purchase Order from SDSC SHAR shall be classified as “confidential”

within the meaning of the Official Secrets Act and will not be divulged to any

third party without prior written permission of SDSC SHAR. All drawings &

documents shall be returned after execution of work.

25.3. No publicity of any kind whatsoever regarding this work shall be given without

prior clearance from SDSC-SHAR.

Page 23: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: A

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 22 of 58

26. ACCEPTANCE AND REJECTION:

ACCEPTANCE AND REJECTION:

On completion of the work or part of the work as specified in the contract, the

representative of the Department referred to, shall check as soon as possible, but

in any event within one month of notification of readiness for acceptance that the

work performed complies with the contract requirements as regards quantity and

quality.

In the event of rejection of any of the articles, whereby the Supplier feels himself

aggrieved, he may within eight days of the receipt of notification of rejection and

before such articles have been removed from the place of inspection, give the

Department notice of objection. Such objection shall be considered by a Board of

Appeals of the Department. The Department shall, without prejudice to the

arbitration clause in the contract, take a decision upon presentation of the Board's

findings.

On completion of tests, the members of the Inspection Organisation of the

Department or Inspection agency appointed by Department shall prepare a

report, which must be countersigned by the Supplier.

27. SUSPENSION:

27.1. Department may notify the Supplier to suspend performance of any or all of his

obligations under the Contract. Such notice will specify the reasons for

suspension and the effective date of suspension. Supplier there upon shall

suspend the performance of such obligations until ordered in writing to resume

performance of Contract by Department.

27.2. If Supplier’s performance or his obligations remain suspended or the rate of

progress is reduced, then, the time of completion will be suitably extended and

all costs incurred by Supplier as a result of suspension or reduction in rate of

progress will be paid to Supplier provided that the suspension or reduction in the

rate of progress is not by reasons of Supplier's default or breach of Contract.

28. CANCELLATION

28.1. GENERAL RULE

The Department shall have the right at any time to cancel a contract either

wholly or in part by giving written notice by registered mail. From the time of

receipt of the written notice, the Supplier shall undertake to observe the

Page 24: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: A

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 23 of 58

instructions of the Department as to the winding up of the contract both on his

own part and on the part of his sub-suppliers.

28.2. WITHOUT FAULT OF SUPPLIER

In the case of cancellation of a contract by the Department without any fault of

the Supplier, the Supplier shall on receipt of Department's instructions forthwith

take the necessary steps to implement them. The period to be allowed to

implement them shall be fixed by the Department after conclusion with the

Supplier and, in general, shall not exceed three months.

Subject to the Supplier confirming, Department shall take over from the Supplier

at a fair and reasonable price all finished parts not yet delivered to the

Department, all unused and undamaged material, bought-out components and

articles in course of manufacture in the possession of the supplier and property

obtained by or supplied to the Supplier for the performance of the contract,

except such material, bought-out components and articles in course of

manufacture as the supplier shall, with the agreement of the Department, elect

to retain.

28.3. WITH FAULT OF SUPPLIER:

The Department reserves the right, after full consideration of all relevant

circumstances, including the observations of the supplier, to cancel a contract in

any of the following circumstances.

28.3.1. In the event of the Supplier's failure to meet

(i) The Technical requirements of the Supplier.

(ii) The Progress and/or delivery requirements.

28.3.2. If the Supplier has not observed the provisions of the contract concerning

the disclosure and use of information provided by the Department.

28.3.3. If the Supplier fails to comply with the provisions of the contract concerning

the equipment, supplies and technical documents made available by the

Department.

28.3.4. If the Supplier transfers his contract without the Department's authorization

or concludes sub-contracts against the Department's explicit directives.

28.3.5. In the event that Supplier unjustifiably repudiates the Contract or fails to

ship or dispatch all or part of the goods ordered for reasons other than

those attributed to the Department’s actions or as provided in the Force

Majeure clause, the Department may, by giving an appropriate notice in

Page 25: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: A

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 24 of 58

writing to the Supplier, fix a Date of Essence by which the Supplier must

complete the dispatch in full. If the Supplier fails to do so, the Department,

in addition to his right to recover Liquidated Damages in terms of the

Contract, shall also have the right to cancel this Contract and make

substitute purchases from other sources. If the goods are in a partial state

of fabrication, Department may have the fabrication completed by other

means, in which event Supplier shall be liable to Department for the

additional expenses incurred thereby, but shall not have any claim on

savings, if any, in such cases.

In the event of such cancellation, the Department shall unless otherwise

specified in the contract, only pays.

- In the case of a fixed-cost contract for the supply of equipment or material.

The contractual value of items delivered and accepted under the contract

before receipt of notification of cancellation, or to be accepted under the

special conditions of cancellation.

- In the other cases.

A fair and reasonable price in respect of such work as has been carried out

prior to the receipt by the Supplier of notification of cancellation.

29. FRAUDULENT PRACTICES, BRIBERY AND CORRUPTION OF

GOVERNMENT SERVANTS

The contractor represents and undertakes that he has not given, offered or promised

to give, directly or indirectly any amount, gift, consideration, reward, commission,

fees, brokerage or inducement to any person in service of the department or

otherwise in procuring the contracts or forbearing to do or for having done or

forborne to do any act in relation to the obtaining or execution of the contract or any

other contract with the Government for obtaining a contract or showing or forbearing

to show favour or disfavour to any person in relation to the contract or any other

contract with the government. Any breach of the aforesaid undertaking by the

contract or any one employed by him or acting on his behalf or for his benefit

(whether with or without the knowledge of the contractor) or the commissioning of

any offence by contractor or any one employed by him or acting on his behalf, as

defined in chapter IX of the Indian Penal code, 1860 or the prevention of corruption

Act. 1947 or any other Act enacted for the prevention of corruption shall, without

prejudice to any other legal action, entitle the Department to cancel the contract

either wholly or in part, and all or any other contracts with Contractor and recover

Page 26: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: A

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 25 of 58

from the Contractor such amount or the monetary value thereof and the amount of

any loss arising from such cancellation without any entitlement or compensation to

the Contractor. The Department will also have the right to recover any such amount

from any contracts concluded earlier between the contractor and the Government of

India. The contractor will also be liable to be debarred from entering into any contract

with the Government of India for a minimum period of five years. A decision of the

Department to the effect that a breach of the undertaking had been committed shall

be final and binding on the Contractor.

Page 27: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: B

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 26 of 58

SECTION B

SCOPE OF ENQUIRY AND GENERAL

PROJECT INFORMATION

Page 28: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: B

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 27 of 58

1.0 SCOPE OF ENQUIRY

1.1. This specification covers design, engineering, manufacture/procurement,

inspection and testing at BIDDER’s and/or his SUB-VENDOR’s works, packing,

transportation from place of manufacture to site, unloading and storage at site,

cleaning, installation, testing, commissioning and performance testing at site for

Multi Entry Escape Chute for PSLV Integration Facility (PIF) of Indian Space

Research Organization (ISRO), at Satish Dhawan Space Centre SHAR,

Sriharikota, SPSR Nellore District, Andhra Pradesh, India.

1.2. It is not the intent to specify completely herein all the details of design,

construction of the equipment, erection, commissioning and testing

requirements. However, the component / assemblies / equipment shall conform

in all respects to high standards of engineering design and workmanship and be

capable of performing in continuous commercial operation upto the BIDDER’s

guarantee ensuring high degree of reliability, ease of operation and

maintenance of the equipment in a manner acceptable to the Department who

will interpret the meaning of drawings and specifications and shall be entitled to

reject any work or material which in his judgment is not in full accordance

therewith.

1.3. The extent of supply under the contract includes all items shown in the

drawings, notwithstanding the fact that such items may have been omittedfrom

the specifications or Schedules. Similarly the extent of supply alsoincludes all

items mentioned in the specification and/or Schedules, notwithstanding the fact

that such items may have been omitted in the drawings.

1.4. In the event of conflict between requirements of any two clauses of the

specification documents or requirements of different codes/standards, specified,

the more stringent requirement as per the interpretation of theDepartment shall

apply.

1.5. All necessary co-ordination with regard to sub-contracted equipment shall be

carried out by the BIDDER. The Department will communicate only with the

BIDDER for all matters pertaining to this contract.

Page 29: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: B

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 28 of 58

2.0 PROJECT INFORMATION

2.1. Project Title : PSLV Integration Facility (PIF)

2.2. Dimension of the building : 30 m x 35 m x 64m (LXWXH)

2.3. Location of site : Sriharikota, AP

2.4. No. of Floors : 15 Nos. of various height

2.5. Access to Site : By Road

From North of Chennai is approximately 100

km.

From East of Sullurpeta in Nellore dist is

approx. 28km.

By Rail (Nearest railway station: Sullurpeta)

Chennai – Vijayawada rail track line.

2.6. Climatic Conditions

a) Temperature

Mean of daily max : 42.2 °C

Mean of daily min. : 11.8 °C

Maximum Temperature : 44.6 °C

i. Design ambient temperature : 45.0 °C

for performance guarantee

ii. For electrical system design : 50 °C

b) Relative humidity

i. Range : 15% to 100%

ii. Design relative humidity : 70%

for performance guarantee

Page 30: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: C

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 29 of 58

SECTION -C

MULTI ENTRY ESCAPE CHUTE

TECHNICAL SPECIFICATION

Page 31: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: C

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 30 of 58

I. TECHNICAL DATA SHEET:

1. TYPE OF ESCAPE CHUTE: 3 Layer Multi Entry Personnel Escape Chute.

2. MATERIAL : a) Inner layer--- Shall be made of Twaron/Kevlar fibre

along the entire length and chloro vinylique yarn across

the length to provide adequate strength.

b) Middle layer--- Expandable material like lycra and

modalacryl elastomer.

c) Outer layer--- Shall be made glass fibre fabric, non

flammable in nature to protect against external fire.

d). * Material used for the construction of chute, sleeve

should not be of polyester coated with fire retardant

or wire sewn or series of stainless steel coiled

springs sewn.

** certificate for the same shall be provided.

e) The entrance frame of chute material shall be made of

high grade aluminum alloy of AlSi6 or LM 23 or equivalent

material and certificate for the same to be provided.

3. CHUTE DIAMETER : a) Inner layer--- diameter shall not exceed 60cm.

b) Middle layer--- diameter shall not exceed 22cm, shall

be expandable to minimum three times of its diameter.

C) Outer layer--- diameter shall be of 62 2cm

d) The size of entry point of the chute shall not be

less than 58cm.

4. LOAD CARRYING CAPACITY : Inner layer--- Shall withstand the total load of the

chute and it shall have load carrying capacity of 10

tons (10,000 kg) or a maximum load of 5600kg per

meter width of fabric. The details of the load

carrying capacity of the material and as an

integrated system to be submitted.

5. WEIGHT OF CHUTE MATERIAL: a) Inner layer--- weight of the chute material shall

not exceed 300g/m2

b) Middle layer--- The weight of the chute material

shall not exceed 260g/m2

c) Outer layer--- weight of the chute material shall

not exceed 420g/m2

Page 32: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: C

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 31 of 58

6. QUANTITY :

S/No LENGTH/TYPE OF CHUTE QTY ( in Nos)

A. Inserting type(overlap) chute 4.6 m length 03

B. Terminal chute with cushion pad of 4.5 m length 01

C. Inserting type(overlap) chute 4.4 m length 01

D. Inserting type(overlap) chute 4.3 m length 01

E. Inserting type(overlap) chute 3.7 m length 02

F. Inserting type(overlap) chute 3.4 m length 01

G. Terminal chute with cushion pad of 3.3 m length 01

H. Inserting type(overlap) chute 3.2 m length 01

I. Terminal chute with cushion pad of 2.6 m length 01

J. Terminal chute with cushion pad of 2.1 m length 01

Note : Supplier should quote compulsorily for the individual items required for completing

the project including above listed items for considering the offer

7. CHUTE STORAGE BOX : All the chutes shall be supplied with suitable

individual boxes made of stainless steel material,

which act as storage for the chutes. The box shall be

designed such that deployment of chute shall be

simple and automatic in addition to the protection of

chute when not in use.

8. TEMPERATURE/ FIRE RESISTANCE : a) Inner layer--- Made of fire resistance

material and shall functional upto 4500C.

Decompose temperature shall not be less than

5000C. Test certificate shall be produced along with

the supply of chute.

b) Middle layer--- Middle layer shall be functional

upto 1750C. Test certificate shall be produced along

with the supply of chute.

c) Outer layer--- Outer layer shall be functional upto

7500C and softening point shall be of 8000C. Test

certificate shall be produced along with the supply of

chute.

Page 33: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: C

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 32 of 58

9. CERTIFICATION/CODE : a) Chute material/manufacturing and testing shall be

as relevant EU/international/Indian standard.

b) Quality certificate/certificate of conformity by the

manufacturer shall be produced along with the

supply of chute.

Total amount for items A – J shall be taken into account for arriving at the lowest

bid.

Items listed are not exhaustive, over and above any accessories, items required to

complete the project should be considered in the scope of work and supply / installation

to be made.

10. Escape chute scheme layout drawing is attached in Annexure – II (Page No. 57)

and as per this drawing, the erection and commissioning to be carried out by the

supplier.

Note : All above specifications, shall be met by supplier and confirmation for

meeting the above specification shall be submitted along with technical bid.

Without the above confirmation, tender will not be considered for price bid.

II. TYPE OF CHUTE ENDS:

a) Terminal chute: The chute which ends at a floor and not into another chute is

termed as terminal chute. The operational length of the chute shall stop at 600 -

800 mm above the floor level. A cushioned bed made up of non flameproof

materials shall be attached to the ends of the chute by suitable means and shall

rest on the floor. The bed shall make the landing of the evacuees less strainful

compared to landing on concrete floor.

b) Inserting chute (overlap): Other than terminal floors, the chute ends shall be

inserted into the below level floor chute with an overlap of 400 mm. This is to

enable the evacuee to continue escaping.

III. BACKGROUND INFORMATION / FUNCTIONAL REQUIREMENT

PSLV Integration facility is a 30 m x 35 m x 74 m tall concrete structure mainly

intended for receiving and integrating satellite launch vehicle. This building consist

of 15 floors. 11 floors are going to be provided with emergency escape chute in

two location 1.5 m apart in every floor from first floor. Presently only one chute is

planned in this building in staggering arrangement for every 4/3 floors as given in

Annexure II. Along with this two additional chutes are planned in 3rd to 2nd floor and

2nd to 1st floor as shown in Annexure II for the purpose of training. In case of any

emergency, the occupants need to be evacuated in a very fast manner. Hence, it is

proposed to install multi entry escape chute for PIF.

The multi entry escape chute is to provide complete escape system which shall be

Page 34: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: C

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 33 of 58

always ready for use - and it should protect the user as he escapes. It shall be

used successfully without any previous practice.

Average speed for evacuee with right behavior is to be considered for 2.5 m per

second. It should take within 35 – 40 seconds to descend a chute from 50 metres

to be considered. A maximum of 30 persons a minute shall be evacuated at height

from fire or danger. To control a fast, descend of a second person, the escape

chute shall have a provision to twist the chute (i.e. 2 turns) between the first and

the second person. By twisting the chute at full length and by slowly untwisting the

chute, the descending speed shall be controlled. This chute should be able to

enable injured on stretcher, unconscious or disabled people to be transported

down slowly and safely.

The chutes are proposed to be installed in openings provided on the floors in a

staggered manner so that multiple persons can escape through the chutes.

IV. DETAILED SCOPE OF WORK

1.1. Submission of Technical specification, Installation, Testing and commissioning

procedure for Multi Entry Vertical Emergency Escape chute for PIF facility and

getting approval from ISRO.

1.2. Submission of the drawings and documents as per the technical specification

along with test details and certificates.

1.3. Supply of all the equipment to SDSC SHAR, Sriharikota.

1.4. Installation of Multi Entry Vertical Emergency Escape chute at PIF facility,

SDSC SHAR, Sriharikota.

1.5. Testing and Commissioning at PIF facility, SDSC SHAR, Sriharikota

1.6. Implementation of safety at different stages of erection and commissioning.

1.7. Reliability and quality assurance during manufacture and testing of the

equipment.

1.8. Submission of guarantee for efficient and specified performance of the total

equipment. In case, any item is found to mal-operate or fails to provide

specified performance during inspection/ testing at SDSC SHAR or during

commissioning/ trial runs of the system or during guarantee period after

commissioning, the Supplier shall attend to the faulty/defective item within

shortest possible time and make necessary repairs/ replacements to the

satisfaction of the Department, without any commercial implication.

Page 35: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: C

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 34 of 58

V. PERFORMANCE DATA REQUIREMENTS

1. The escape chute shall be ready for immediate use as emergency exit.

2. Average speed for evacuee shall be of 2.5 m/s. It should take approximately 35 – 40

seconds to descend a chute of up to 50 metres length.

3. A maximum of 15 persons a minute can be evacuated at height from fire or danger.

4. The multiple protective layers of chute shall protect evacuee passing down the chute

from flame, heat, and smoke.

5. To operate the chute, there shall be no power source required.

6. The vertical gravity descend system shall relies solely on body weight, and test

proved that all evacuees regardless of body size, shape and weight, injured on

special designed stretcher and unconscious people, once inside the chute tube will

arrive at ground level quickly and relatively safely.

7. It shall transport a continuous flow of evacuees.

8. It shall require a little or no instruction for use.

9. It shall require a little physical exertion in sliding down the chutes.

10. Users shall have the ability to self-control the speed of own descends and also allow

external means to control the speed of one’s descend from the outside at ground.

11. It shall be suitable for all ages and physical conditions of evacuees, including

disabled people.

12. It shall be constructed in such a way that it enables rescue personnel to control the

evacuation process.

VI. INSTALLATION

1. Chute shall be installed permanently in the 660mmX660mm square opening

provided in the every floor.

2. The installation of chute will be after the clearance from the Department official at

SDSC SHAR.

3. The chute shall be installed in such a way that it allows facility occupants to gain

access to the chute at each floor where working personnel at several levels shall be

evacuated simultaneously from the facility.

4. The chute shall be installed in segments at each floor inside the duct provided in the

facility.

5. The escape chute installation should be designed as per the Building Specifications

in terms of Floor Heights and Total Height.

Page 36: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: C

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 35 of 58

VII. PACKING, TRANSPORTATION & SAFE STORAGE OF ITEMS AT SDSC SHAR

a) No equipment shall be delivered without obtaining dispatch clearance from SDSC

SHAR.

b) Party has to pack all the items in seaworthy packing to protect against corrosion. All

the equipment shall be properly packed to avoid any damage during transportation/

handling/storage

c) The supplier shall be responsible for transporting all the equipment to site, unloading

and storage.

d) The equipment received at site shall be stored at a place assigned for this purpose.

VIII. GENERAL ERECTION PROCEDURE

a) Equipment delivered at site to be inspected and checked as per Packing List.

b) The chute hatch shall be properly aligned and fixed to the cutout provided in the facility.

c) The chute hatch shall be fixed such a way that it is able to carry the load transferred to it.

d) Levels of chute to be rechecked after full installation.

IX. INSPECTION, TESTING AND COMMISSIONING AT SUPPLIER’S SITE

a) All the multi entry escape chute shall be tested at suppliers/manufactures site as per

the EN/IS/EU or relevant standards and all the test certificates shall be produced

along with the supply of material.

X. INSPECTION, TESTING AND COMMISSIONING AT DEPT. SITE

a) Functional testing of chute at site after erection and commissioning.

b) Checking the free flow of men/material through the escape chute as per the indent

specification.

c) In case, any equipment is found to malfunction or giving sub-standard performance

during this activity, it shall be replaced free of cost.

XI. DOCUMENTS TO BE SUBMITTED

DOCUMENTS TO BE SUBMITTED ALONG WITH THE OFFER

1. Signed copy of this Technical Specification as a proof of compliance to all the

requirements of the document.

Page 37: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: C

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 36 of 58

2. Confirmation of meeting specification given for Multi Entry Escape chute.

3. Dimensional details of the proposed Multi entry escape chutes.

4. Preliminary design calculations for Multi entry escape chute system.

5. Preliminary Quality Assurance Plan (QAP) which will be followed.

6. Detailed specification, schematic drawing, Bill of Material (BOM), complete with the

features indicated in the order specification.

7. Any other relevant data/information.

XII. DOCUMENTS TO BE SUBMITTED AFTER PLACEMENT OF OFFER

1. A bar-chart/ PERT network for all activities such as design, approval, procurement,

manufacturing, assembly, testing, inspection, delivery, erection, commissioning etc.

shall be submitted within two weeks of placement of order.

2. Detailed specification, schematic drawing, Bill of Material (BOM), complete with all

specification of all multi entry escape chute segments incorporating all the required

details against the features indicated in the order specification

3. General arrangement drawings and cross sectional details indicating dimensional

details for the equipment and bill of material.

4. Certified detailed technical literature of all components highlighting all the features of

the items finally selected.

5. Safety, reliability and quality assurance plans followed for each type of equipment.

6. Installation drawings and instructions for various segments of multi entry escape

chute.

7. Weight of each segments of multi entry escape chute.

8. Copies of Purchase Orders for bought-out items blanking price part (one copy only)

9. Any other relevant data/information.

XIII. DOCUMENTS TO BE SUBMITTED AFTER COMMISSIONING

1. Three (3) sets of Operation and Maintenance Manuals, spare parts catalogue,

engineering data sheets and part lists covering each item including bought out

components along with all drawing shall be compiled and submitted.

2. One set of reproducible and soft copy on CD/DVD for all drawing and operation &

maintained manuals.

3. As-built drawings (3 copies).

Page 38: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: C

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 37 of 58

4. Design calculation and analysis data if any.

5. Complete Inspection / test results (3 copies).

6. Inspection certificate & guarantee certificate (3 copies).

XIV. QUALITY ASSURANCE PLAN

1. Tenderer shall have an established and effective Quality Assurance plan during

manufacturing the system. The SR & QA plan shall be submitted for approval of

ISRO.

2. Tenderer shall ensure that the item supplied is absolutely safe for use in the

stipulated work environment and conform to applicable safety norms and standards

3. During manufacture, fabrication assembly, testing and delivery, the vendor shall

strictly comply with Quality Assurance instruction including Cleanliness Control,

procurement Control, Design change Control, Deviation Control, Failure Reporting &

Analysis, Calibration Control, documents control & Training requirements.

XV. GENERAL INSTRUCTION TO THE CONTRACTOR

1. The items covered in this specification shall confirm to technical specifications,

latest revision of relevant standards and requirements in respect of accuracy,

performance, dimensions, materials of construction, manufacturing, safety,

reliability & quality assurance, inspection and testing.

2. The supplier shall keep essential commissioning spares available at Sriharikota

during commissioning phase, a list of such spares shall be furnished in four

weeks after order placement.

3. All the equipment and accessories to be supplied under this package shall be

new & from the latest product range of the supplier.

4. The Supplier shall list out all the equipment along with their components/ parts,

including make, type, model number and the other details for the approval of

SDSC SHAR. Any deviation from it after approval shall not be permitted.

5. All correspondences /documents shall be in English language and the data /

other dimensional details shall be submitted in Metric Units only.

6. The supplier shall indicate any assumption made in respect of specification, data

of any other details that have not been mentioned in this order but considered

necessary for sizing & selection of equipment to meet the specified application

requirements. All such assumptions will not be binding on ISRO unless expressly

agreed upon. The supplier, under these conditions, shall supply equipment based

Page 39: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: C

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 38 of 58

on the data accepted to ISRO without any commercial implication.

7. All necessary facilities including tools, testing equipment, instruments,

accessories, manpower assistance etc. shall be provided by the supplier to

enable inspection of equipment by ISRO during its manufacture/ fabrication/

assembly & inspection.

8. The supplier shall be responsible for adherence to all the applicable rules,

regulations & requirements of statutory bodies of the Andhra Pradesh State

Government and Central Government of India, as required.

XVI. COMPLIANCE TO STANDARDS

All the items supplied or used shall be new and of first quality and shall be

manufactured/ fabricated and tested in accordance with the latest editions of the

relevant Indian/Intentional Standards. Any components or systems where no

specific standards are applicable shall be fabricated as per the instructions and

directions of the purchaser or its authorized nominee.

XVII. QUALITY OF MATERIALS AND WORKMANSHIP

All equipment, materials and articles incorporated in the work should be new, free

from defects and of the most suitable grade for the purpose intended. All work under

this contract shall be performed in a skilful and workman-like manner and shall be

consistent with the best practices of the industry.

If at any time SDSC SHAR (ISRO) notifies that any such equipment, material, article

or workmanship fails to meet the foregoing standards, the contractor shall promptly

take all the remedial steps required to meet those standards.

XVIII. OPERATION INSTRUCTION AND PROCEDURE

The Supplier has to submit the ‘brief step-by-step operation procedure’ as conceived

by the designer for approval at detailed design stage itself. After testing and

commissioning stage the updated document shall be submitted for final clearance

and approval. Three copies of the same shall be supplied. Permanent physical

identification, which are legible, clearly visible at any stage of operation etc. and

markings shall be given on the system where the operator has to carry out his work.

Procedure should be well detailed and it should identify all checkpoints before

carrying out any operation. For each operation, a checklist has to be made for

systematic check-up and operation.

Operation manual shall include all minute activities and checkpoints in very detailed

manner. The manual also shall include trouble shooting, possible causes and

Page 40: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: C

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 39 of 58

remedial measures to be adopted.

XIX. MAINTENANCE INSTRUCTIONS AND PROCEDURE

Brief maintenance provisions/ procedure document shall be prepared and submitted

at detailed Engineering stage itself. After testing and commissioning stage, the

detailed document shall be submitted for final clearance and approval.

Three copies of the same shall be supplied.

Maintenance document shall include but shall not be limited to the following:

01. Block diagram of the system

02. Applicable drawings

03. List of all bought out items, detailed specifications and catalogues

04. History of the system

05. List of tools

06. Parts bins

07. List of consumables and maintenance schedules

08. List of spares

09. Systematic health checks procedure

10. Work prior to starting maintenance

11. Step by step procedure for dismantling of a sub-system

12. Step by step procedure for carrying of repair

13. Step by step procedure for re-assembling

14. Test results

15. Final report

Page 41: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: D

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 40 of 58

SECTION -D

ANNEXURES

Page 42: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT SECTION: D1

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 41 of 58

SCHEDULE OF PRICES & GENERAL PARTICULARS

1. Bidders shall not alter the contents of this schedule of prices. If the bidder wants any additions / alterations, these shall be brought out separately in the format as given in this schedule of prices.

2. Equipment and material to be supplied and erected shall be in accordance with requirements stated in the various sections of this specification.

3. The quantities indicated are an order of magnitude only. In case there is any variation in the quantities of items actually supplied and installed from the quoted quantities, the price of the same shall be adjusted based on the unit rates furnished by the bidder. The unit rates shall be valid for both upward and downward variation in quantities.

4. The quoted price shall be price in Indian Rupees for design, preparation of drawings, manufacture, inspection and testing at manufacturer’s works, packing, forwarding, transportation from place of manufacture to site, transit insurance, unloading / receipt at site, storage / handling at site, installation, testing, commissioning and carrying out performance test at site inclusive of all taxes and duties as applicable except sales tax on finished products and service tax which shall be separately indicated in the price bid.

5. Total price for recommended spares shall be provided by the BIDDER and details of prices for recommended spares shall be filled up by the BIDDER separately in price bid.

6. Proposed essential maintenance tools & tackles and essential start-up spares shall be submitted separately as per format enclosed in Section D9 & D10 (Page No 53 & 54) in a sealed cover along with technical bid.

Department reserves the right to accept/reject the essential maintenance tools & tackles

and Start-up spares proposed by party as a whole/partially.

Page 43: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT SECTION: D1

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 42 of 58

(A) UNPRICED SCHEDULE OF UNIT PRICE (Prices column to be kept blank)

Sl. No. Item Qty.

1. Multi Entry Escape chute system Lot Quoted

in price

bid

2. GST on total supply price (price mentioned in Sl.

No.: 1) @ applicable on above items.

---

---- %

3. Service tax on Erection and commissioning price

(price mentioned in Sl. No:1) @ __________

applicable on above items.

--- ST ___%

on ___%

of quote

4. Any other taxes and duties

TOTAL COST: Quoted in price bid

SIGNATURE

SEAL OF THE COMPANY NAME

DESIGNATION

DATE

Page 44: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: D2

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 43 of 58

BID QUALIFICATION CRITERIA FOR SUPPLY OF MULTI ENTRY ESCAPE CHUTE SYSTEM

Bidders who are qualifying / meeting following Technical and financial criteria are eligible to participate in the bid for supply of Multi Entry Escape Chute system for PIF, SDSC SHAR. Bidder shall furnish all the information mentioned in the criteria with documentary proof and submit along with quotation. Bids of the parties which are not meeting the following criteria will not be considered for evaluation and will be rejected without seeking any further clarifications.

A. Technical Qualification Requirements:

The bidder shall meet the following technical qualifying requirements and shall submit relevant certificates to establish his credentials.

1. The Bidder shall be an organization with long experience in having executed contracts for supply, erection, testing and commissioning of Multi Entry Escape Chute system.

2. The firm shall have successfully completed Installation, Testing and Commissioning of at least 5 Multi Entry Escape chute system in a high rise building of not less than 70 m tall / height in INDIA. Bidders have to provide relevant certificates from the end users along with the submission of bid for consideration of bid document.

3. The firm shall have facilities for erection, testing and operation demonstration etc. B. Financial Qualification Requirements:

1. The Bidder should have annual turnover of not less than a value of Rs 20 lac per year in

the last two financial years ending with 31.03.2019.

2. IT/ TDS certificate shall be submitted with Loss & Profit for last three years.

3. Bidder shall submit audited statement of financial status for last three years.

C. The following documents shall be submitted along with the Techno-

commercial bid for prequalification of Bidder.

1. Firm establishment certificate and nature of work.

2. Details of work of similar type completed during the last five years ending with 31.01.2020

3. Satisfactory work Completion certificates from the clients, with the work order copies

4. Performance Report of order completed (with years of service) from End users, with addresses and contact person with phone numbers.

5. Documentary evidence (Technical details &. drawings) for fulfilling special technical conditions as per the RFP document

6. Copy of audited Balance Sheets for last three years

7. IT / TDS certificates for last three years.

8. Current Solvency Certificate.

9. List of value, and work order copies of total projects under Execution with purchase order name and address.

10. Structure and Organization chart.

Page 45: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: D2

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 44 of 58

11. List of personnel with qualification &. experience in the firm in the areas of design, production, quality, safety, administration etc.,

12. List of Machinery &Equipment to be used for the work.

D. Bid Selection Procedure and Process of Pre-Qualification

1. Short listing based on documents submitted, satisfying all the eligibility criteria given above by the firm or individual along with their Bid / application. (Non-submission of any document as given in above list within stipulated time leads to rejection of Bid).

2. Subsequently Bidder's competency, their technical achievements and financial status will be evaluated suitable for this project. Feedbacks from Bidder's clients will be verified, if required.

3. Visit to sites by our technical team where Bidder has established above mentioned works, if required.

4. If required, visit will be made to their factory/ firm by our technical team for accessing the capability of manufacturer.

5. Scrutiny of all technical specification and supply conditions mentioned in techno-commercial bid.

Page 46: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: D3

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 45 of 58

SCHEDULE OF PERFORMANCE GURANTEE

The BIDDER shall furnish Performance Guarantees as listed below based on the

requirements specified in Section C of this Specification:

1) The chute material shall be non flameproof and non steel and non wire materials.

2) The chute frame shall fit into a 660 mm x 660 mm square opening provided on the floors.

SIGNATURE :

NAME :

DESIGNATION:

SEAL OF THE COMPANY DATE :

Page 47: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: D4

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 46 of 58

SCHEDULE FOR GENERAL PARTICULARS / VENDOR EVALUATION FORMAT

SR.

NO.

DESCRIPTION

1. Name of Company

2. Address of Company

3. Type of Company (Proprietary/Pvt.Ltd/Public

Ltd/Joint Venure/Consortium)

4. Registration number

5. Year of inception of the company

6. Registered address

7. Name & address of the office of the Chief

Executive of the company

8. Name & Designation of the officer of the Bidder to

whom all correspondence shall be made for

expeditious technical/ commercial co-ordination.

Telephone number

Fax number

E-mail address

9. Locations of the Branches of Company (if any)

10. Annual turn-over of the company for the last three

years

11. IT returns for the last 3 years

12. Major customers (Enclose copies of the Purchase

Orders)

13. Any customers feedback on the services which is

in writing (Pl. enclose copies)

14. Quality certification of the company

15. PAN Card Copy

16. The Profit & Loss Account details for the last 3

years which is duly audited and Submitted as part

Page 48: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: D4

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 47 of 58

SR.

NO.

DESCRIPTION

of the Annual Report

17. Orders executed during last three years, Not less

than 90m tall/height, references are is to be

mentioned. (Separate sheet can be attached).

18. Shop floor area covered

19. No. of employees (Supplier shall mention contract

personnel separately)

Engineers

Supervisors

Technicians

Quality control engineers

Administrative Staff.

20. Testing facility Available:

21. Details of inspection facilities / Instruments

available ( Brief description & specifications shall

be provided)

22. Bid validity period

(Min. 4 months from due date of bid submission)

23. Completion Schedule

24. Period required for Supply (within 4 months)

___ months

25. Period required for Installation, testing and

commissioning at Department site (within 1 month

from date of clearance for installation)

___ months

SIGNATURE :

NAME :

DESIGNATION:

SEAL OF THE COMPANY DATE :

Page 49: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: D5

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 48 of 58

SCHEDULE OF SUB-VENDORS

1.0 GENERAL

1.1 This section provides details of the Approved makes for bought-out items, which form a part of this enquiry package.

1.2 BIDDER shall clearly indicate the makes of all bought-out items and shall at no point in time during execution deviate from those indicated in the offer document.

Page 50: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: D6

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 49 of 58

EXCEPTIONS AND DEVIATIONS

In line with Proposal Document, Bidder may stipulate Exceptions and deviations to the

proposed conditions if considered unavoidable.

Sl

No

Reference in

Specification Dept.

Specification Offered Specification Deviation

Page

No Clause No

NOTE :

Only deviations are to be written in the above form.

Any deviations taken by the Bidder to the stipulations of the Proposal document shall be

brought out strictly as per this format and enclosed along with the bid.

Any deviations not brought out in this Proforma and written elsewhere in the Proposal

document shall not be recognized and the same is treated as null and void.

Any wilful attempt by the Bidders to camouflage the deviations by giving them in the

covering letter or in any other documents that are enclosed may render the Bid itself non-

responsive.

SIGNATURE :

NAME :

DESIGNATION:

SEAL OF THE COMPANY DATE :

Page 51: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: D7

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 50 of 58

SCHEDULE OF BIDDER’S EXPERIENCE

The bidder shall furnish here under a list of relevant works executed by him to whom a reference may be made by the

PURCHASER in case the PURCHASER considers such a reference necessary.

Sl.

No.

Name & address of

Client / Name & address

of project or plant (incl.

tel.no., fax no., e-mail

and name & designation

of person who can be

contacted.

Purchase

Order /

Contact no.

and Date.

Brief

details of

equipment /

system

covered

Scope of

services

(See

Legend)

Contract

price (Rs)

Scheduled

date of

completion

Actual date

of

completion

Reasons for

delay in

completion,

if applicable.

Remarks

LEGEND: E - INSTALLATION, S – SUPPLY, SUP – SUPERVISION OF INSTALLATION, TC – TESTING AND COMMISSIONING

SIGNATURE :

NAME :

DESIGNATION :

COMPANY :

COMPANY SEAL DATE :

Page 52: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: D7

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 51 of 58

SCHEDULE OF BIDDER’S SIMILAR COMPLETED or PRESENT WORK

The bidder shall furnish here under a list of relevant works executed or being executed to whom a reference may be made

by the PURCHASER in case the PURCHASER considers such a reference necessary.

SL.

NO.

Name & address of Client /

Name & address of project or

plant (incl. tel.no., fax no., e-

mail and name & designation of

person who can be contacted.

Purchase Order /

Contact no. and

Date.

Brief details

of equipment

/ system

covered

Scope of

services

(See

Legend)

Contract

price (Rs)

Scheduled

date of

completion

Expected

date of

completion

Remarks

LEGEND: E - INSTALLATION, S – SUPPLY, SUP – SUPERVISION OF INSTALLATION, TC – TESTING AND COMMISSIONING

SIGNATURE :

NAME :

DESIGNATION:

COMPANY :

Company Seal DATE :

Page 53: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: D8

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 52 of 58

SCHEDULE OF TIME FOR SUPPLY AND INSTALLATION AT SITE

The BIDDER shall indicate below the time for manufacture, despatch and completion of

each equipment and shipment time from the date of Letter of Intent (LOI) as shown below:

SL.NO

EQUIPMENT

PR

OC

UR

EM

EN

T F

RO

M

DA

TE

OF

LO

I (W

EE

KS

)

TIM

E F

OR

TE

ST

S A

T

WO

RK

S,

DIS

MA

NT

LIN

G,

PA

CK

ING

AN

D R

EA

DY

FO

R D

ES

PA

TC

H F

RO

M

WO

RK

S (

WE

EK

S)

TIM

E F

OR

SH

IPM

EN

T

TO

SIT

E (

WE

EK

S)

TIM

E F

OR

ER

EC

TIO

N

AN

D C

OM

MIS

SIO

NIN

G

AT

SIT

E (

WE

EK

S)

TO

TA

L T

IME

FR

OM

DA

TE

OF

LO

I T

O

RE

CE

IPT

AT

SIT

E

(WE

EK

S)

1. 2 3 4 5 6 7=(3+4+5+6)

1

2.

3.

4.

5.

6.

7.

8.

9.

10.

11.

12.

13.

14.

15.

16.

17.

COMPANY SEAL SIGNATURE

NAME

DESIGNATION

COMPANY

DATE

Page 54: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: D9

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 53 of 58

SCHEDULE OF MAINTENANCE TOOLS AND TACKLES

The BIDDER shall indicate below Special Maintenance Tools and Tackles for the equipment,

plant or system offered by him.

Sl. No. DESCRIPTION QUANTITY OR NUMBER OF SETS

UNIT PRICE Rs.

TOTAL PRICE Rs

REMARKS

1.

2.

3.

4.

5.

6.

7.

8.

9.

10.

11.

12.

13.

14.

15.

16.

17.

18.

19.

COMPANY SEAL SIGNATURE

NAME

DESIGNATION

COMPANY

DATE

Page 55: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

SECTION: D10

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 54 of 58

SCHEDULE OF START-UP AND COMMISSIONING SPARES

The BIDDER shall indicate below Start-up and Commissioning Spares for equipment, plant

or system offered by him.

SL

.NO

EQ

UIP

ME

NT

TA

G

NU

MB

ER

DE

SC

RIP

TIO

N O

F

SP

AR

E

MA

TE

RIA

L O

F

CO

NS

TR

UC

TIO

N

MA

NU

FA

CT

UR

ER

A

ND

PA

RT

NU

MB

ER

QU

AN

TIT

Y/S

ET

RE

CO

MM

EN

DE

D

PE

R U

NIT

EQ

UIP

ME

NT

UN

IT P

RIC

E Rs

TO

TA

L P

RIC

E Rs

DE

LIV

ER

Y P

ER

IOD

(WE

EK

S)

FR

OM

DA

TE

OF

LO

I

RE

MA

RK

S

1.

2.

3.

4.

5.

6.

7.

8.

9.

10.

11.

12.

13.

14.

15.

16.

17.

18.

19.

20

COMPANY SEAL SIGNATURE

NAME

DESIGNATION

COMPANY

DATE

Page 56: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

Check List

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 55 of 58

CHECKLIST FOR BID SUBMISSION

Sl

no Description

Response

by supplier

1.

All documents related to Prequalification criteria mention in Section D2

(Page No. 43&44) have been met and all related documents are enclosed

in technical Bid

Yes / No

2. Are all the technical particulars as called for in the data sheets Section A,

B&C and commercial details as called for in schedule of prices filled up Yes / No

3. The detailed scope of work and technical specifications are understood

and price was quoted accordingly. Yes / No

4. Confirmation that the quoted prices are firm and fixed till the completion of

scope of work. Yes / No

5. Validity of Offer is 4 months (minimum). Yes / No

6. Vendor Evaluation Format is attached. Yes / No

7. List of Customs Duty Exemption Certificate (CDEC) items are submitted for

providing CDEC by Department. Yes / No

8. List of IGST Concession Certificate items are submitted for providing

EDEC by Department. Yes / No

9. GST to be indicated in percentage (if not mentioned it will be assumed that

the price quoted are inclusive of taxes). Yes / No

10. Delivery Schedule with milestones Yes / No

11. Accepted the Department Payment Terms Yes / No

12. Are General terms and Conditions of Contract for Supply & Erection

included in proposal acceptable? Yes / No

13. If not acceptable, are the deviations brought out in the "Schedule of

Deviations" Yes / No

14. Are there any deviations from enquiry technical specifications? Yes / No

15. If there are technical deviations, are these filled in "Schedule of Deviations

from Tech. Specifications"? Yes / No

16. Warranty for the fully commissioned and accepted system is 12 months Yes / No

17.

10 % of the Order Value shall be submitted as Performance Security for

the performance of the contract along with acceptance of order letter,

which is valid till acceptance of the system.

Yes / No

18.

10 % of the Order Value shall be submitted as Performance Bank

Guarantee, which is valid till completion of the warranty period plus 2

months claim period.

Yes / No

Page 57: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

Check List

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 56 of 58

19. Liquidated Damages are acceptable Yes / No

20. Last three years audited financial results are enclosed Yes / No

21. Registration certificate of the company is enclosed Yes / No

22. All the forms in Section D1 to D10 are filled Yes / No

23. Are all data sheets A/B duly filled in and submitted in offer Yes / No

24. Technical documents / drawings are attached along with technical bid Yes / No

25. Section D9 & D10 is filled separately and sealed cover is sent to SDSC

SHAR for along with hard copy of technical bid. Yes / No

SIGNATURE :

NAME :

DESIGNATION:

SEAL OF THE COMPANY DATE :

Page 58: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

Check List

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 57 of 58

ANNEXURE - II

TO TENDER NO: SHAR/SCSD/2020013160

ESCAPE CHUTE GENERAL ARRANGEMENT

Page 59: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

SPEC NO.: PIF/

Multi Entry Escape chute

PSLV INTEGRATION FACILITY PROJECT

Check List

MULTI ENTRY ESCAPE CHUTE FOR PIF

Page 58 of 58

Page 60: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

Tender No: SHAR/SCSD/2020E1316002 1

Tender Details

Tender No: SHAR/SCSD/2020E1316002

Tender Date: 28/10/2015

Purchase Entity: SHAR CENTRAL SAFETY

Page 61: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

Tender No: SHAR/SCSD/2020E1316002 2

Tender Attachments

Technical Write-up/Drawings

Attachment - I:

IDT01818700000000000isro05401.pdf

Attachment - II:

Attachment - III:

Attachment - IV:

Attachment - V:

TERMS AND CONDITIONS FOR INDIGENIOUS ITEMS

.:

GOVERNMENT OF INDIA

DEPARTMENT OF SPACE

SATISH DHAWAN SPACE CENTRE

PURCHASE DIVISION

Tele No.08623-225023/225174/225127

Fax No.08623-225170/22-5028

e-Mail ID : [email protected], [email protected], [email protected]

Page 62: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

Tender No: SHAR/SCSD/2020E1316002 3

1. Interested tenderers may, at their option, login to https://eprocure.isro.gov.in and submit your offers

.

2. TENDER FEE NOT APPLICABLE

3. EARNEST MONEY DEPOSIT NOT APPLICABLE IF NOT MENTIONED IN THE RFP SPECIFICATIONS

4. Indian agents while quoting on behalf of their principals are requested to attach Principals original

quote necessary authorization letter from their Principals, copy of agency agreement etc in their bid.

5. TWO PART BIDS: In case of Two part tender , price details shall not be uploaded in the Technical &

Commercial Bids (Part I),failing which the bid will be treated as INVALID.

6.The offer should be valid for a minimum period of 120 days for 2 part / 90 days for single part from the

date of opening.

7. Due date & time: Sufficient time has been allotted for Bid submission. Vendors are requested to

complete Bid submission well in advance. Last minute requests for due date extension citing server

problems etc will not be entertained. Bids will not be entertained after the due date and time.

7. Request for the extension of the due date will not be considered.

8.

(a) Bid Opening for Public Tender: In case of Public Tender-Two Part Tenders: Technical and Commercial

Bids will be opened on the first day specified for Tender opening. Interested vendors can attend the

tender opening session to know the bidding details (Bidders presence is not mandatory to consider the

quote for evaluation).

Price Bid opening of the selected vendors will be scheduled later and it will be intimated to the selected

Bidder.

(b) For Limited Tender: Bidders participation is not allowed.

9. Prices are required to be quoted according to the units indicated.

10. Preference will be given to those tenderers offering supplies from ready stocks and on the basis of

FOR destination delivery at site.

11. (a) All available technical literature, catalogues and other data in support of the specifications and

detail of the items should be furnished as attachments.

(b) Samples, if called for, should be submitted free of all charges by the tenderer and the Purchaser shall

not be responsible for any loss or damage thereof due to any reason whatsoever. In the event of non-

acceptance of tender, the tenderer will have to remove the samples at his own expense.

Page 63: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

Tender No: SHAR/SCSD/2020E1316002 4

(c) Approximate net and gross weight of the items offered shall be indicated in your offer. If dimensions

details are available the same should be indicated in your offer.

(d) Specifications: Stores offered should strictly conform to our specifications. Deviations, if any, should

be clearly indicated by the tenderer in their quotation. The tenderer should also indicate the Make/Type

number of the stores offered and provide catalogues, technical literature and samples wherever

necessary. Test certificates wherever necessary should be attached. Whenever options are called for in

our specifications, the tenderer should address all such options. Wherever specifically mentioned by us

the tenderer could suggest changes to specifications with appropriate response for the same.

12. The purchaser shall be under no obligation to accept the lowest or any tender and reserves the right

of acceptance of the whole or any part of the tender or portion of quantity offered and the tenderers

shall supply the same at the rates quoted.

13. All amounts shall be indicated both in words as well as in figures. Where there is difference between

amounts quoted in words and figures, amount quoted in words shall prevail.

14. The tenderer will be required to furnish a document containing the name of his bankers as well as

the latest income-tax clearance certificate duly counter signed by the Income-tax Officer of the Circle

concerned under the Seal of his office, if required by the Purchaser.

15. The Purchaser reserves the right to place order on the successful tenderers for additional quantity

up to 25% of the quantity offered by them at the rates quoted.

16. Sr. Head, Purchase and Stores, SDSC SHAR SRIHARIKOTA reserves the right to accept or reject any

bid in part or full without assigning any reason thereof.

Instructions to Tenderers (PT)

.:

TERMS AND CONDITIONS OF TENDER

1.Price quoted should be on the basis of FOR, SDSC SHAR / delivery at site. The Purchaser will not pay

separately for transit insurance, and the risk and cost during transit shall be exclusively the responsibility

of the Contractor and the purchaser shall pay only for such stores as are actually received in good

condition in accordance with the Contract.

2.Quotation should be valid for at least 90 days from the date of opening of the tender.

Page 64: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

Tender No: SHAR/SCSD/2020E1316002 5

3.The time for and the date of delivery of the stores stipulated in the Purchase Order shall be deemed to

be the essence of the Contract and delivery must be completed not later than the date specified therein,

and failure to do so, without adequate justification, may involve cancellation of the Contract at the

discretion of the Purchaser.

4.(a)Prices are required to be quoted according to the units indicated in the annexed tender form. When

quotations are given in terms of units other than those specified in the tender form, relationship

between the two systems of unit must be furnished.

(b) Corrections, if any, in the quotation must be attested. All amounts shall be indicated both in words

as well as in figures. When there is difference between the amount quoted in words and figures, the

amount quoted in words shall prevail.

5.The Purchaser reserves the right to accept or reject any quotation fully or partly without assigning any

reason therefore.

6.Payment terms shall be as specified in RFP ,if not specifically mentioned the normal payment term is

full payment within 30 days from the date of receipt and acceptance of material ordered. Our Bankers

are State Bank of India, Sriharikota Branch ,Nellore District 524124.

7.Where counter terms and conditions/printed or cyclostyled conditions of sale have been offered by

the tenders, the same shall not be deemed to have been accepted by the Purchaser unless the

Purchaser's specific written acceptance thereof is obtained.

8.Specifications: Stores offered should strictly conform to Purchaser’s specifications. Deviations, if any,

shall be clearly indicated by the tenderer in his quotation. The tenderer should also indicate the

Make/Type number of the stores offered and provide catalogues, technical literature and samples,

wherever necessary, along with the quotation. Test certificate, wherever necessary, should be

forwarded along with supplies. Wherever options are called for in our specifications, the tenderer

should address all such options, wherever specifically mentioned by us, and the tenderer could suggest

changes to specifications with appropriate response for the same. Even in such case, the tenderer

should state why he cannot meet our specification/s and why he is suggesting the change.

9.GST intended to be claimed, should be distinctly shown separately in the tender.

10.Guarantee: The stores offered should be Guaranteed as specified in RFP or for a minimum period of

twelve months after acceptance or longer period as applicable against defective stores design, operation

or manufacture. For defects noticed during the guarantee period, replacement/repair should be

arranged free of cost within a reasonable period of such notification. In cases where our specifications

call for a guarantee period more than 12 months specifically, then such a period shall apply.

11.The Contractor shall at all times indemnify the Purchaser against all claims which may be in respect of

the stores for infringement of any right protected by Patent, Registration or design or Trade Mark and

shall take all risks of accidents or damage which may cause a failure of the supply from whatever causes

Page 65: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

Tender No: SHAR/SCSD/2020E1316002 6

arising and the entire responsibility for the sufficiency of all means used by him for the fulfilment of the

Contract.

12.Arbitration:

In the event of any dispute/s, difference/s or claim/s arising out of or relating to the interpretation and

application of the Contract, such dispute/s or difference/s or claim/s shall be settled amicably by mutual

consultations of the good Offices of the respective Parties and recognizing their mutual interests

attempt to reach a solution satisfactory to both the parties. If such a resolution is not possible, within 30

days from the date of receipt of written notice of the existence of such dispute/s, then the unresolved

dispute/s or difference/s or claim/s shall be referred to the Sole Arbitrator appointed by the Parties by

mutual consent in accordance with the rules and procedures of Arbitration and Conciliation Act 1996 as

amended from time to time. The arbitration shall be conducted in Bengaluru in the Arbitration and

Conciliation Centre –Bengaluru (Domestic and International) as per its rules and regulations. The

expenses for the Arbitration shall be shared equally or as may be determined by the Arbitrator. The

considered and written decision of the Arbitrator shall be final and binding between the Parties. The

applicable language for Arbitration shall be “English” only.

Work under the Contract shall be continued by the CONTRACTOR during the pendency of arbitration

proceedings, without prejudice to a final adjustment in accordance with the decision of the Arbitrator

unless otherwise directed in writing by the DEPARTMENT or unless the matter is such that the works

cannot be possibly continued until the decision (whether final or interim) of the Arbitrator is obtained.

13.Successful tenderer will have to furnish in the form of a Bank Guarantee or in any other form as

called for by the Purchaser towards adequate security for the materials/property provided by the

purchaser for the due execution for the Contract.

14.Packing and Forwarding: The Contractor will be held responsible for the stores being sufficiently and

properly packed for transport by rail, road, sea or air, to withstand transit hazards and ensure safe

arrival at the destination. The packing and marking of packages shall be done by and at the expense to

the Contractor.

15. The delivery date mentioned in the Purchase Order is the essence of the Contract. If the Contractor

fails to deliver the item[s] within the delivery period stipulated, the Purchaser reserves the right to

recover Liquidated Damages @0.5% of the order value per each calendar week of delay subject to a

maximum of 10% of the total order value.

16. Upon the completion of the Contract, the Contractor should furnish a Performance Bank Guarantee

equal to 10% of the order value valid till 2 months beyond the stipulated warranty period.

Page 66: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

Tender No: SHAR/SCSD/2020E1316002 7

STANDARD TERMS AND CONDITIONS

.:

GOVERNMENT OF INDIA

DEPARTMENT OF SPACE

SATISH DHAWAN SPACE CENTRE

PURCHASE DIVISION

Tele No.08623-225023/225174/225127

Fax No.08623-225170/22-5028

e-Mail ID : [email protected], [email protected], [email protected]

<font size=3>STANDARD TERMS AND CONDITIONS

1.Instruction to Indigenous Suppliers:

a) Payment Terms shall be as specified in RFP. If not specifically mentioned Our Normal payment term is

100% within 30 days after receipt and acceptance of the item at our site. Please confirm acceptance in

your quotation.

b) GST/IGST:

Please specify GST percentage, if any, in your offer. Please mention HSN code in your offer and IGST @

5% will be paid as per Notification No. 47/2017 –Integrated Tax (Rate) dated 14.11.2017 and

Government of Andhra Pradesh Goods and Service Tax Act, 2017 (Act No.16 of 2017), G.O.MS.No.599

Dated:12.12.2017. (IGST concession certificate will be provided along with PO) Our GST No. is.

37AAAGS1366J1Z1.

c) Purchase / Price preference to MSEs

Purchase/Price preference will be applicable to the product reservation admissible to the Micro and

Small Enterprises. Purchase/Price Preference shall be extended to the MSEs under the Public

Procurement Policy for MSEs formulated under the Micro, Small and Medium Enterprises Development

Act, 2006. The participating MSEs in a tender, quoting price within the band of L-1 + 15% may also be

allowed to supply a portion of the requirement by bringing down their price to the L-1 price, in a

situation where L-1 price is from someone other than an MSE. Such MSEs may be allowed to supply upto

Page 67: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

Tender No: SHAR/SCSD/2020E1316002 8

20% of the total tendered value. In case of more than one such eligible MSE, the supply will be shared

equally.

Micro & Small Enterprises which have technical capability to deliver the goods & Services as per

prescribed technical & quality specifications and may not be able to meet the qualification criterion

relating to prior experience-prior turnover may be relaxed as per guidelines issued by Ministry of

MSMEs & as amended from time to time.

Interested vendors shall specifically claim the benefit with supporting documents

2.Instruction to foreign Suppliers:-

a)Payment Terms shall be as specified in RFP. If not specifically mentioned Our normal payment term is

SIGHT DRAFT, Please confirm acceptance in your offer, if you insist for L/C, and all bank charges shall be

to your account. Confirm acceptance.

b)Please specify whether any export clearance is required in case of an order on you.

c)Warranty/Guarantee applicable for the item shall be mentioned in your offer

d)Special Certification for packing Material : as per Plant Quarantine (Regulation of Control into India)

Order 2003, Articles packed with packing material of plant origin viz., hay, straw, wood shavings, wood

chips, saw dust, wood waste, wooden pallets, Dunn age Mats, wooden packages, coir pith, pear or

sphagnum moss etc., will be allowed entry by Customs only with a Phytosanitary Certificate. In case if a

Purchase Order, if you propose to us any of the above material for packing such a certificate issued by

your local Plant Quarantine Authority shall be furnished.

e)Confirm whether any Export License is required and for which End User Certificate is to be provided by

us, in case of an Order on you. (Enclose format for EUC, if applicable)

f)Either Indian Agent on behalf of the foreign principals or the foreign principal directly can quote

against this order, but not both. In either case an Indian agent cannot represent more than one

principal against the same tender.

g) In case the quote is in INR we prefer to execute the same on HSS Basis and for which Concessional

Customs duty as per Notification no.50/2017 Cutoms dated 30.06.2017,Serial No.539(A) as amended by

Notification no.05/2018 dated 25.01.2018. In case the quote is on Indian Rupee (Outside High Sea Sale),

the price shall include taxes and duties if any. We shall not able to provide any duty or IGST tax

exemption/concession certificates. If the item quote is of USA make, please quote for all-inclusive price

since we prefer to get the item on FOR destination basis.

Common terms to Indigenous and foreign suppliers

3.Warranty

Page 68: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

Tender No: SHAR/SCSD/2020E1316002 9

You shall provide applicable warranty for the items offered by you without fail. For the applicable period

you shall provide necessary warranty certificate.

4.Performance Bank Guarantee

Towards the performance of the systems during the warranty period you shall submit a performance

bank guarantee equivalent to 10% of the order value to cover the warranty period. This PBG shall be

interest free and the same shall be returned to you on successful completion of all contractual

obligations. The said PBG shall have a further claim period of 2 months.

5.Security Deposit

On acceptance of the order, you shall submit an interest free amount equivalent to 10% of the total

contract/order value towards security deposit. This security deposit is collected towards the

performance of the Contract. The said Security Deposit shall be submitted either in the form of Bank

Guarantee/Demand Draft/FDR receipts duly endorsed in the name of the centre. The Security Deposit

will be returned to you on successful completion of the Contractual obligations; failing which it shall be

forfeited/adjusted.

6.Offer Validity

Your offer shall be valid for 120 days in case of 2 part / 90 days in case of single part from the date of

tender opening. In case you offer validity is less than the mentioned above, the said offer is liable for

rejection which may please be noted.

7.Liquidated Damages:

If you fail to deliver the ordered items satisfactorily within the time specified or any extension thereof,

Liquidated Damage @ 0.5%(zero point five percent) of the order value or part thereof the un-delivered

items for each calendar weeks of delay shall be recovered from your bill. However total Liquidated

Damage shall not exceed 10% (ten percent) of the order value.

8.Offers received through post,courier, fax or email will not be considered.

9. Technical and commercial bid (Part-I) shall not contain any price details. Optional accessories or other

price details, if any shall be uploaded in Supporting documents related to Price Bid, to be opened along

with Price Bid.10. In respect of FIM being issued, the fabricator shall submit Bank Guarantee for

equivalent sum compulsorily. In case, submission of Bank Guarantee is not possible, the reasons there

for shall be clearly mentioned. However, for such cases the fabricators at their cost shall secure such

FIM through Insurance Policy with Director, LPSC as beneficiary. In case of PSU and Government

Organization, Indemnity Bond in lieu of Bank Guarantee is acceptable. Balance FIM/Scrap, if any shall be

returned along with the supply of the items. Please confirm acceptance in your quotation.

12.SDSC SHAR shall have the right to place part order among the parties for the items for which they are

the lowest.

Page 69: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

Tender No: SHAR/SCSD/2020E1316002 10

13. Arbitration:

In the event of any dispute/s, difference/s or claim/s arising out of or relating to the interpretation and

application of the Contract, such dispute/s or difference/s or claim/s shall be settled amicably by mutual

consultations of the good Offices of the respective Parties and recognizing their mutual interests

attempt to reach a solution satisfactory to both the parties. If such a resolution is not possible, within 30

days from the date of receipt of written notice of the existence of such dispute/s, then the unresolved

dispute/s or difference/s or claim/s shall be referred to the Sole Arbitrator appointed by the Parties by

mutual consent in accordance with the rules and procedures of Arbitration and Conciliation Act 1996 as

amended from time to time. The arbitration shall be conducted in Bengaluru in the Arbitration and

Conciliation Centre –Bengaluru (Domestic and International) as per its rules and regulations. The

expenses for the Arbitration shall be shared equally or as may be determined by the Arbitrator. The

considered and written decision of the Arbitrator shall be final and binding between the Parties. The

applicable language for Arbitration shall be “English” only.

Work under the Contract shall be continued by the CONTRACTOR during the pendency of arbitration

proceedings, without prejudice to a final adjustment in accordance with the decision of the Arbitrator

unless otherwise directed in writing by the DEPARTMENT or unless the matter is such that the works

cannot be possibly continued until the decision (whether final or interim) of the Arbitrator is obtained.

Instructions to tenders for Two part bid

.:

TWO PART -INSTRUCTION TO TENDERERS

1. This requirement can be quoted only through online e-procurement mode using ISRO portal

https://eprocure.isro.gov.in. No manual tender will be considered.

2. The vendors have to get themselves registered in above site to download the tender details. To

register in above ISRO portal(https://eprocure.isro.gov.in) the vendors need to have digital certificate

The digital certificate can be obtained from any digital certifying authority like M/s (n)Code solutions;

M/s Tata Consultancy Ltd., M/s Satyam Information System etc.

3. THE PARTIES ARE ADVISED TO DOWNLOAD THE TENDER AND SUBMIT THE BID ON ONLINE AT LEAST

TWO DAYS PRIOR TO TENDER CLOSING DATE TO AVOID LAST MINUTE NETWORK PROBLEM. THE DUE

DATE SHALL NOT BE EXTENDED DUE TO NETWORK OR COMPUTER RELATED PROBLEMS.

4.TENDER FEE NOT APPLICABLE.

5. This being a two part tender “ Technical & Commercial Part and Price Part separately, the tenders

should not attach any documents containing Pricing information along with Technical & Commercial Bid.

Page 70: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

Tender No: SHAR/SCSD/2020E1316002 11

Normally we do not open PART-II (Commercial Offer), if PART-I (Technical Offer) does not meet with our

technical specification requirements.

6. Our Tender Enquiry contains technical requirements and specification. The detailed technical

specification of your offer should be covered in the technical part. The Technical documents need to be

attached online as a single PDF file without any prior information. The tenders attachment containing

Price details will be treated as unsolicited offers and rejected.

7. The quote should indicate quantity wise unit rate seperately which have to be filled online. The Prices

are to be mentioned both in figures as well as in words. The taxes, duties etc. are to be calculated

andindicated in the column provided in online forms explicitly.

8. Bidders are expected to comply with the technical & commercial and other terms and conditions

given in vendor specified terms of this tender. In case of any deviation, the reasons thereof should be

clearly specified in the vendor specified terms column.

9. The vendors have to compulsorily submit the compliance statement online otherwise their offer will

not be considered for further evaluation. Before entering the compliance statement, vendors areadvised

to refer the detailed specification provided in the Technical Writeup/ Drawings document. The

specification offered by the vendors may also be indicated in the compliance statement wherever

necessary.

10. The Technical Specification / Drawing / Product Catalogues / Works carried by vendor / Make

offered etc. as a single PDF file without any financial details has to uploaded online mode by the vendor.

This being TWO PART TENDER the PDF document uploaded should not contain any commercial/pricing

details. If the attached PDF contains any pricing detail the offer will be treated as unsolicited and will be

summarily rejected.

11. Original Equipment Manufacturer (OEM) or their representative can submit bid to SDSC SHAR. Indian

agents while quoting on behalf of their principals are requested to attach necessary authorization letter

from their Principals in their bid.

12. Instructions on Indian Agent (if any):- Bidders are required to provide the following information in

respect of their authorised Indan Agent, if any, alongwith technical bid as the same is mandatory as is

required for consideration of the bid. Name, Address, Telephone no. , fax no., email of the Indian Agent

including the contact person.

13. A letter from the OEM in the current date certifying that the said Indian Agent is their authorised

Indian Agent and also indicating the responsibilities/role of the Indian Agent under the proposed

purchase. Renumeration/service charges payable to the Indian Agent under the proposed purchase.

14. The offer should be valid for a minimum period of 120 days from the date of tender opening.

Page 71: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

Tender No: SHAR/SCSD/2020E1316002 12

15. Due date & time: Sufficient time has been allotted for Bid submission. Vendors are requested to

complete Bid submission well in advance. Last minute requests for due date extension citing server

problems etc will not be entertained. Bids will not be entertained after the due date and time.

16. The vendors who have submitted the bids before the closing have to give Open Authorization as per

schedule after the tender closing date.

17. The vendors may contact 080-67807786/020-25315555 or [email protected] for any

technical assistance in vendor registration and bid submission.

18. Once the offer is submitted in on line mode by the vendor and Bid Sealing is done by SDSC SHAR,

vendor will not be able to provide revised offer.

19. Request for the extension of the due date will not be considered.

20. Tender which are not prepared in terms of these instructions are liable to be rejected.

21. Based on the response to the e-Public Tender Notice, SDSC SHAR reserves theright to change any

milestone date of the tendering activity.

22. SDSC SHAR reserves the right to verify all claims made by the bidder.

23. Tender Opening : The Technical and Commercial Bid [Part-I] will be opened on the specified day

mentioned in the schedule and incase any further clarification/ discussion are required, such

clarification/discussion shall be called for before opening the Price Bid.

24. The exact date and time of opening of price bid of successful tenderers will be intimated later.

25. Tenderers can participate in the said tender opening to know the details on for which, the

representative of the firm shall be duly authorized by Competent Authority. Against proper

authorization only such representatives shall be allowed to attend the tender opening. Tenderer

Presence is not mandatory to consider the Quote for evaluation.

26. SDSC SHAR, SRIHARIKOTA reserves the right to accept or reject any/or all the tenders in part or full

without assigning any reasons thereof.

Page 72: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

Tender No: SHAR/SCSD/2020E1316002 13

Bid Templates

Item Specifications

Sl. No Specifications Compliance (Yes /No) Offered Specifications Remarks

1 Specification 1:

______________________

2 Specification 2:

______________________

3 Specification 3:

______________________

4 Specification 4:

______________________

Vendor Specificied Terms

Description Vendor Terms

GST AND OTHER COSTS, IF ANY: Percentage of applicable GST for the

quoted items along with HSN Code, shall be provided. As per the

Notifications No.47/2017-Integrated tax(Rate) dated 14.11.2017 issued

by Ministry of Finance (Department of Revenue), SDSC SHAR is eligible

for a reduced rate of 5% IGST only wherever IGST is applicable.

Accordingly, Concession Certificate will also be provided).

Page 73: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

Tender No: SHAR/SCSD/2020E1316002 14

CUSTOMS DUTY: We are entitled for Partial Customs Duty Exemption

(10.775%) vide Notification No.05/2018 dt: 25-01-2018 for imports.

Confirm whether CD is applicable and if so whether CD Exemption

Certificate is acceptable and the same is required for exemption.

Both IGST Concession Certificate & CDEC cannot be given to same

item.

Please furnish the list of items for which CDEC is required in Technical

Bid. And submit price details for which CDEC required in Price Bid only.

DELIVERY TERM: FOR SRIHARIKOTA

PAYMENTS TERMS: PLEASE IGNORE THE CLAUSE NO.18 IN PAGE.NO.19

OF ANNEXURE AND CONFIRM YOUR ACCEPTANCE AS MENTIONED

BELOW:

a) Our Standard Payment Term: 100% within 30 days after receipt &

acceptance, installation, testing & commissioning of Emergency Escape

Chute at our site.

(OR the following payment may also be considered)

b) 80% of order cost payment against receipt of complete material at

our site, 10% of order cost after successful assembly/installation of the

multi entry escape chute at our site/building and 10% of order cost

along with taxes against successful testing, commissioning &

acceptance by Department of equipment and system covered under

contract and against submission of Performance Bank Guarantee of

equal amount valid till warranty period plus 2 months claim period.

Page 74: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

Tender No: SHAR/SCSD/2020E1316002 15

Please mention required payment term, if not mentioned we presume

that our standard payment is accepted

Delivery Schedule: Refer clause no.22 in page.n.20 of Annexure.Please

confirm your acceptance.

Warranty: Refer clause no.15 in page.no.17 of Annexure. Please

confirm your acceptance.

LIQUIDATED DAMAGES (LD): Since delivery is the essence of this order,

for delayed delivery, LD @ 1/2% per week or part thereof subject to a

maximum of 10% of the order value will be levied.

FORCE MAJEURE CLAUSE

If at any time during the continuance of the order the performance

in whole or part by either party of any obligation under this order shall

be prevented or delayed by reasons of any war, hostility, acts of

public enemy, civil commotion, sabotage, fire, floods, lightening,

epidemic, quarantine restrictions, strikes, go-slow, lockout or acts of

God, notice of which is given either party to the other within 21 days

from the date of occurrence thereof, neither party shall be reasons of

such eventually be entitled to terminate this order nor shall either

party have any claim for damages against the other in respect of such

non-performance or delay in performance.

PERFORMANCE BANK GUARANTEE (PBG): You have to submit a PBG

from a Nationalized / Scheduled Bank for 10% of the order value at the

Page 75: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

Tender No: SHAR/SCSD/2020E1316002 16

time of supply valid till the completion of warranty period plus 60 days.

This PBG shall be submitted along with dispatch documents such as

Invoice, Warranty Certificate etc.

SECURITY DEPOSIT: If Order value exceeds Rs. 5 Lakhs, Security Deposit

shall be submitted @ 10% of order value within 10 days of receipt of

order in the form of Demand Draft/Bank Guarantee or Fixed Deposit

Receipt from a Nationalized/Scheduled Bank valid up to the supply,

erection and commissioning plus two months. The SD shall not carry

any interest, and shall be returned after successful completion of

supply and contractual obligations. In case of poor performance/non-

performance of the contractual obligations SD shall be forfeited. If SD

is not submitted within the stipulated period, Order is liable to be

cancelled in addition to any other action against you.

COMBINED BANK GUARANTEE: In case, if You are unable to provide

two separate BGs, i.e., one for SD and one for PBG, You can submit a

combined BG for SD & PBG for 10% of the Order value valid till the

completion of total contractual obligation (i.e. Supply period +

Warranty period + 60 days). Please confirm.

VALIDITY OF OFFER: - The validity of offers/tenders should be 4

months from the date of opening of the tenders. Tenders shorter than

offer validity mentioned above will not be considered for evaluation.

INSURANCE: Being a Govt. Of India Dept., Insurance is not required at

our cost. Please ensure the safe delivery of the ordered item with

proper transport worthy pack.

Please refer to the Annexure for Item specifications and other terms &

conditions and also mention your compliance. Deviations if any shall

Page 76: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

Tender No: SHAR/SCSD/2020E1316002 17

be mentioned.

Please furnish Name and Address of the party to whom Order to be

placed along with Contact details i.e. E-mail id, Mobile no/ Landline no.

etc.

Any other terms

Remarks if any

Supporting Documents from Vendor

Attachment - I:

Attachment - II:

SUPPORTING DOCUMENTS RELATED TO PRICE BID

SUPPORTING DOCUMENTS RELATED TO PRICE BID

Attachment - I:

Page 77: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

Tender No: SHAR/SCSD/2020E1316002 18

Attachment - II:

UPLOAD ONLY DOCUMENTS SUPPORTING THE PRICE BID LIKE BREAK-UP COST etc. PRICE BID FORM

Price Bid Form

Item Description Slab Range Qty UOM Currency Unit Price Total Price

ESCAPE CHUTE

Design, Supply,

Installation,

Testing and

Commissioning of

Multi Entry

Vertical Personnel

Escape Chute for

PIF building as

details, Quantity,

Specifications,

Drawings given

Annexure 1 & 2

- 1 Lot - - -

Break-up of other taxes and other costs should be specified in respective narration columns.

Sum of these Break-up values should be specified in respective value columns.

Page 78: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

S a t i sh Dhawan Spac e Cen t e r SHAR S a t i sh Dhawan Spac e Cen t e r SHAR S a t i sh Dhawan Spac e Cen t e r SHAR S a t i sh Dhawan Spac e Cen t e r SHAR

Welcome, Materials Master (isro)31 August 2017,

17:16:08 IST

MAIN VIEW HELP

Preview For STANDARD TERMS AND CONDITIONS

Page Destination: Tender Header Format Type : Normal

. :

GOVERNMENT OF INDIA

DEPARTMENT OF SPACE

SATISH DHAWAN SPACE CENTRE

PURCHASE DIVISION

Tele No.08623-225023/225174/225127 Fax No.08623-225170/22-5028 e-Mail ID : [email protected], [email protected], [email protected]

STANDARD TERMS & CONDITIONS

1.OFFERS SHALL BE SENT ONLINE ONLY USING STANDARD DIGITAL SIGNATURE CERTIFICATE OF CLASS III WITH ENCRYPTION / DECRYPTION. THE TENDERS AUTHORISED ONLINE ON OR BEFORE THE OPEN AUTHORISATION DATE AND TIME ONLY WILL BE CONSIDERED AS VALID TENDERS EVEN THOUGH THE BIDS ARE SUBMITTED ONLINE.

2.THE TENDERER MUST AUTHORISE BID OPENING WITHIN THE TIME STIPULATED IN THE SCHEDULE BY SDSC SHAR. OTHERWISE THE ONLINE BID SUBMITTED WILL NOT BE CONSIDERED FOR EVALUATION. PHYSICAL COPY WILL NOT BE CONSIDERED EVEN THOUGH IT IS RECEIVED BEFORE THE BID SUBMISSION DATE. In case of two-part tenders, parties shall submit their offers as follows:-

1) Part-I – Techno-commercial Bid (No price details shall be mentioned in this bid and shall not upload the details of price along with the techno-commercial bid) 2) Part-II – Price Bid

In view of Two Part Tender, the Offers submitted contrary to above instructions will be summarily rejected. 3.In case, the tenderer is not interested to participate in the tender, the tenderer shall submit regret letter giving reasons, failing which future enquiries will not be sent. 4.Offer Validity: The validity of the offers / tenders should be 90 days (in case of single part tender) and 120 days (in case two part

tender) from the date of opening of the tenders. Tenders with offer validity less than the period mentioned above, will not be considered for evaluation. 5.GST - GST and/or other duties/levies legally leviable and intended to be claimed should be distinctly shown separately in the tender. GST details are given below

GSTIN: 37AAAGS1366J1Z1 LEGAL NAME : SATISH DHAWAN SPACE CENTRE SHAR VALIDITY FROM:29/08/2017

TYPE OF REGISTRATION:REGULAR 6.Customs Duty - SDSC-SHAR is eligible for 100% Customs Duty exemption as per Notification No. 050/2017 539 (b) Dt: 30.06.2017.

This may be taken into account while quoting for import items, if any. In case tenderers offering items considering customs duty exemption, they should also indicate the bill of materials and price, separately, with Customs Duty component and terms and conditions thereto. 8.Advance Payment - Wherever advance payment is requested, Bank Guarantee from any Nationalized Bank/Scheduled Bank should be

furnished. In case of advance payments, if the party is not supplying the material within the delivery schedule, interest will be levied as per the Prime Lending Rate of RBI plus 2% penal interest. Interest will be loaded for advance payments/stage payments as per the prime lending rate of RBI and will be added to the landed cost for comparison purpose. In case of different milestone payments submitted by the parties, a standard and transparent methodology like NPV will be adopted for evaluating the offers.

9.Liquidated Damages - In all cases, delivery schedule indicated in the Purchase Order/Contract is the essence of the contract and if the party fails to deliver the material within the delivery schedule, Liquidated Damages will be levied @ 0.5% per week or part thereof subject to a maximum of 10% of total order value. 10.Performance Bank Guarantee - Performance Bank Guarantee for 10% of the order value should be furnished in the form of Bank

Guarantee from nationalized/scheduled bank or by Demand Draft valid till warranty period plus sixty days as claim period.

Page 1 of 3

Page 79: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

11.Security Deposit – Security Deposit for 10% of the order value is mandatory, if the ordered value is Rs.5.00 lakhs and above. Party shall furnish the Security Deposit in the form of Bank Guarantee from nationalized/scheduled bank or by Demand Draft valid till

completion of the contract period plus sixty days towards claim period for faithful execution of the contract. 12.BANK GUARANTEE FOR FIM: Supplier has to submit Bank guarantee for equal value of Free Issue of Materials (FIM) issued by the Department from Nationalised / Scheduled Bank valid till receipt and acceptance of supply and satisfactory accounting of FIM plus sixty days as claim period.

13.The delivery period mentioned in the tender enquiry, IF ANY, is with the stipulation that no credit will be given for earlier deliveries and offers with delivery beyond the period will be treated as unresponsive. 14.The Department will have the option to consider more than one source of supply and final orders will be given accordingly.

15.The bidders should note that conditional discounts would not have edge in the evaluation process of tenders. 16.Non-acceptance of any conditions wherever called for related to Guarantee/ Warranty, Performance Bank Guarantee, Security Deposit, Liquidated damages are liable for disqualification. 17.Wherever installation/ commissioning involved, the guarantee/warrantee period shall reckon only from the date of installation and

commissioning. 18.Purchase/Price Preference will be extended to the MSMEs under the Public Procurement Policy for MSMEs formulated under the Micro, Small and Medium Enterprises Development Act, 2006 and instructions issued by Government of India from time to time. Vendors who would like to avail the benefit of MSME should clearly mention the same and submit all the documentary evidences to substantiate their claim along with tender itself.

19.The drawings, specifications, end use etc., given by the Centre/Unit along with the tender enquiry are confidential and shall not be disclosed to any third party. 20.SPECIAL CONDITIONS FOR SUBMITTING QUOTATIONS IN FOREIGN CURRENCY BY THE INDIAN AGENTS

The Tenderer should submit the following documents/information while quoting:- a)Foreign Principal's proforma invoice/quote indicating the commission payable to the Indian Agent and nature of after sales service to be rendered by the Indian Agent. b)Copy of Agency agreement with the Foreign Principal and the Indian Agent, precise relationship between them and their mutual

interest in the business. c)Registration and item empanelment of the Indian Agent. d)Agency Commission will be paid only Indian Currency.

e)Compliance of the tax laws by the Indian Agent. 21. High Sea Sales- Against High Sea Sale transactions: a.Offers shall be on all inclusive basis including delivery upto Sriharikota at the risk and cost of the supplier. Customs Clearance is the responsibility of the supplier and at his cost and risk.

b.100% payment will be made within 30 days after receipt and acceptance of the items at our site. c. GST as applicable d.Customs Duty Exemption Certificate and other relevant documents required for Customs clearance will be provided.

e.High Sea Sales Agreement furnished by the supplier in accordance with the terms and conditions of our purchase order will be signed and issued by SDSC-SHAR. 22.The following information/ documents are to be submitted wherever applicable.

1.Product Literature 2.Core banking account number of SBI, RTGS Details 3.PAN No. in quotation and invoices

4.GST Registration details. 5.In case of MSME, registration details / documents from Competent Authority. 23.EXCLUSION OF TENDERS

The following tenders shall be summarily rejected from the procurement process a.Tenders received from vendors who have not qualified in terms of their registration. b.Tenders received against publishing of a limited tender in the CPP portal.

c.Tenders of vendors who have been removed from the vendor list or banned/debarred from having business dealings. d.Unsolicited tenders from vendors. e.The tenders which materially depart from the requirements specified in the tender document or which contain false information.

f.The tenders which are not accompanied by the prescribed Earnest Money Deposit. g.The tenders of vendors who have not agreed to furnish Security Deposit, Performance Bank Guarantee and Liquidated Damages. h.The validity of the tenders is shorter than the period specified in the tender enquiry.

i.The tenders received from vendors or their agents or anyone acting on their behalf, who have promised or given to any official of the Centre/Unit/Department, a gratification in any form, or anything of value, so as to unduly influence the procurement process. j.The tenders received from vendors, who, in the opinion of the Centre/Unit, have a conflict of interest materially affecting fair competition.

Page 2 of 3

Page 80: SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF · 2020. 11. 2. · spec no.: pif/ multi entry escape chute pslv integration facility project multi entry escape chute for pif page

k.The tenders received from Indian agents on behalf of their foreign Principals/OEMs (in cases where the Principals/OEMs also submit their tenders simultaneously for the same item/product in the same tender).

l.In case two or more tenders are received from an Indian agent on behalf of more than one foreign Principal/OEM, in the same tender for the same item/product. m.If a firm quotes ‘NIL’ charges / consideration, the bid shall be treated as un-responsive and will not be considered.

Page 3 of 3