Upload
dodieu
View
216
Download
0
Embed Size (px)
Citation preview
Supply and Demand of Electricity
Electricity “cannot be stored.” Electric power companies adjust supply capacity (power generation) to demand (consumption) instantaneously (put on balance weights in response
to demand). It is impossible to supply electricity beyond the supply capacity of electric power companies (total number of balance weights in hand).
Supply side (power generation) Demand side (load)
Building
Supply
Supply capacity of
electric power companies
Add supply capacity (balance
weights) in response to demand
Supply capacity of
electric power
companies
Make full use of balance
weights in hand
In case “demand exceeds supply capacity,” an unpredictable major blackout may occur.
×
Factory House Store
Demand
Nuclear power
Hydroelectric power
Thermal power
In the world of electricity, the term kWh is used as a unit to represent a total amount (area) of generation or consumption of electricity. On the other hand, the term kW is used as a unit to represent an amount of electricity generated or consumed in a moment (height).
Peak hour supply capacity (kW) of electric power companies has been decreased, because power stations were damaged by the recent earthquake disaster.
Therefore, restriction will be needed at peak hours in terms of kW (height).
9:00 a.m.
kWh (area)
Electricity demand curve
(consumption pattern of a day)
Peak hour supply capacity before
the earthquake disaster
Peak hour supply capacity after
the earthquake disaster
Decrease of supply
capacity
Need to restrict kWs (height)
Electricity demand curve
(consumption pattern of a day)
(kW)
kWh (Represented by Area) and kW (Represented by Height)
Electricity demand curve
(consumption pattern of a day)
kW (height)
1:00 p.m.
5:00 p.m.
9:00 a.m.
1:00 p.m.
5:00 p.m.
9:00 a.m.
1:00 p.m.
5:00 p.m.
Largest power line (extra high-voltage transmission line)
○
×
During planned power outage
Both districts where power outages are conducted and
not conducted exist, even in the same municipality.
Electricity is sent from power stations by large capacity transmission lines, then branched into small capacity transmission lines at each substation and delivered to customers.
The recent planned power outages have been conducted by each primary substation. For this reason, outage and restoration works are to be carried out for all facilities that are connected to the same power line network. The scope of area served by a primary substation is not always identical to an area of a municipality. Therefore, both districts where power outages are conducted and not conducted exist, even in the same municipality.
Planned power outage is conducted
by each primary substation.
Mechanism of Electricity Service Delivery and Scope of Planned Power Outage
Second largest power line (extra high-voltage transmission line)
Slightly large power line (high-voltage distribution line)
Smallest power line (low-voltage distribution line)
Power station
Primary substation
Distribution substationPole transformer
General household
Small factory
General household
Store
Store
General household
Sewage treatment plant, etc.
Building and apartment house
Small and medium factories
Large factoryHospital
Same municipality
Primary substation Distribution substation Pole transformer