SUMMARY OF CONSTRUCTION PROJECTS

DESHA COUNTYCounty Totals

CostLength (Mi)Type WorkJob Name Rte.Job No. Sec. Status Let Date Date

Project Totals

CostLength (Mi)

Sub. Comp.

-PE OnlyGreat River Bridge P.E. (Phase II) (F) New $10,682,965Completed - $10,682,965020315*

-PE OnlyI-69 P.E. (Hwy. 65 – Miss. Rt. 1) New $7,134,860Completed - $7,134,860020316*

Major WideningHwy. 65 Improvements (Gould) (S) 0.1965

Addt'l Rte.-Sec.: Lincoln 65-16

$809,69117 Completed Aug. 2009 Jun. 2012 5.39 $20,242,286020448

ReconstructionWaterman St. – West (Dumas) (S) 0.8254 $3,390,9842 Completed Nov. 2010 May. 2012 0.82 $3,390,984020451

Structure & ApproachesDrainage Canal No. 19 Str. & Apprs. (S) 0.44138 $2,094,3044 Completed Jan. 2009 Jun. 2010 0.44 $2,094,304020465

- Roadside AppurtenancesChoctaw Island Trail (S) $27,841Completed Aug. 2009 Apr. 2012 - $27,841020474*

ResurfacingHwy. 278 – Hwy. 4 (Sel. Secs.) (Overlay) (S) 7.431 $1,444,3841 Completed Jun. 2010 Sep. 2010 7.43 $1,444,384020503

- Roadside AppurtenancesMcGehee SRTS I (2010) $91,052Completed Jul. 2011 Feb. 2014 - $91,052020515*

- Roadside AppurtenancesDumas SRTS I (2010) $61,000Completed May. 2011 Aug. 2011 - $61,000020516*

-EnhancementDumas Choctaw St. Streetscaping (ATEP-11) (S) $153,787Completed May. 2013 Nov. 2013 - $153,787020530*

Structure & ApproachesHwy. 212 Strs. & Apprs. (S) 0.20212

Addt'l Rte.-Sec.: Lincoln 212-5

$1,230,1626 Completed Nov. 2014 Sep. 2016 0.44 $2,733,693020542

-RR CrossingW. Bowles St. R.R. Signal (Dumas) (S) CS $173,282Completed Apr. 2013 Nov. 2013 - $173,282020554*

ResurfacingHwy. 65 – Canal No. 43 (Sel. Secs.) (Overlay) (S) 4.44165 $1,133,4134 Completed Jun. 2013 Nov. 2013 4.44 $1,133,413020558

ResurfacingHwy. 138 – Watson (Overlay) (S) 5.481 $1,036,9711 Completed Apr. 2014 Sep. 2014 5.48 $1,036,971020568

ResurfacingHwy. 65 – East (S) 4.704

Addt'l Rte.-Sec.: Desha 169-1

$1,384,24117 Completed Apr. 2015 Jul. 2015 4.70 $1,384,241020572

ReconstructionDitch No. 43 – Arkansas City (S) 5.094

Addt'l Rte.-Sec.: Desha 4-17S

$12,883,46517 Sub. Completed Apr. 2017 Feb. 2019 5.09 $12,883,465020573

- EnhancementRohwer – Arkansas City (Delta Heritage Trail) (S) - Programmed - - 020574*

ReconstructionDitch No. 43 – West (S) 3.014 $7,448,67017 Completed Jun. 2016 Apr. 2017 3.01 $7,448,670020580

Structure & ApproachesUPRR Str. & Apprs. (McGehee) (S) 0.52278 $5 - $10 M16 Scheduled Aug. 2020 0.52 $5 - $10 M020590

ResurfacingSo. of Watson – Hwy. 165 (Overlay) (S) 10.451

Addt'l Rte.-Sec.: Desha 1-2

$1,385,3411 Completed Feb. 2016 Jul. 2016 10.45 $1,385,341020591

ResurfacingArkansas City – Hwy. 1 (S) 11.884 $7,564,45518 Sub. Completed May. 2019 Feb. 2020 11.88 $7,564,455020619

ResurfacingMonticello – McGehee (Sel. Secs.) (S) 4.70278

Addt'l Rte.-Sec.: Drew 278-15

$904,52916 Completed Jan. 2018 Jul. 2018 24.92 $4,795,927020620

ResurfacingHalley – Hwy. 4 (S) 4.92159 $1,617,0314 Completed Jan. 2018 Oct. 2018 4.92 $1,617,031020622

ResurfacingMcGehee – Kelso (S) 14.481 $4,935,3681 Sub. Completed May. 2019 Sep. 2019 14.48 $4,935,368020623

Program Management

Desha

June 3, 2020

* Job not shown on county map.

Page 3: SUMMARY OF CONSTRUCTION PROJECTSardot.gov/program_mgmt/gis/JobStatusMaps_2018/21_0_Desha.pdf · 2020-06-05 · SUMMARY OF CONSTRUCTION PROJECTS DESHA COUNTY County Totals Job No

SUMMARY OF CONSTRUCTION PROJECTS

DESHA COUNTYCounty Totals

CostLength (Mi)Type WorkJob Name Rte.Job No. Sec. Status Let Date Date

Project Totals

CostLength (Mi)

Sub. Comp.

ReconstructionHwy. 65 – Yellow Bend Port (S) 5.8535

Addt'l Rte.-Sec.: Chicot 35-9/11

$5 - $10 M10 Scheduled Sep. 2020 8.93 $10 - $15 M020629

ResurfacingHwy. 65 – Arkansas River (Sel. Secs.) (S) 5.71165 $1,820,7834 Completed Feb. 2017 Aug. 2017 5.71 $1,820,783020631

ResurfacingHwy. 165 – Cherry St. (Dumas) (S) 1.1854 $688,4102 Completed Feb. 2018 Oct. 2018 1.18 $688,410020632

ResurfacingHwys. 65 & 159 (Sel. Secs.) (S) 13.2965

Addt'l Rte.-Sec.: Desha 159-9

$7,628,94817 Under Construction Jan. 2020 13.29 $7,628,948020650

ResurfacingHwy. 1 – Kaufman Ln. (McGehee) (S) 2.8465 $2,145,60119 Completed Feb. 2017 Nov. 2017 2.84 $2,145,601020654

ResurfacingHalley – Dewey (S) 0.70208

Addt'l Rte.-Sec.: Chicot 208-3

$207,0722 Under Construction Jan. 2020 8.27 $2,446,411020655

Safety ImprovementsHwy. 65 Access Change (Pickens) (S) 0.2265 < $1 M17 Scheduled 2019 0.22 < $1 M020656*

New LocationHwy. 278 – Hwy. 65 (S) 1.82New

Addt'l Rte.-Sec.: Drew New

$5 - $10 MScheduled 2022 16.97 $75 - $100 M020678

- RR CrossingW. 3rd St. RR Signals (Reed) (S) < $1 MProgrammed - < $1 M020679*

- EnhancementADPHT Delta Heritage Trail: Yancopin – Arkansas River (TAP-18) (S) < $1 MProgrammed - < $1 M020689*

Structure & ApproachesBayou Bartholomew Str. & Apprs. (Hwy. 278) (S) 0.53278 $1 - $5 M16 Scheduled Sep. 2021 0.53 $1 - $5 M020715

- EnhancementArkansas City Delta Heritage Trail Trailhead Impvts. (RTP-19) (S) < $1 MProgrammed - < $1 M020725*

ResurfacingSnow Lake – Elaine (S) 7.4644

Addt'l Rte.-Sec.: Phillips 44-3

< $1 M2 Scheduled 2022 24.16 $1 - $5 M110700

ResurfacingWinchester – Chicot Co. Line (Sel. Secs.) (S) 6.6865

Addt'l Rte.-Sec.: Desha 65-19; Drew 65-19

$1 - $5 M18 Scheduled 2021 13.07 $5 - $10 MA20004

ResurfacingHwy. 138 – Hwy. 65 (S) 4.42159 $1 - $5 M8 Scheduled 2021 4.42 $1 - $5 MA20006

ResurfacingHwy. 278 – Hwy. 65 (S) 0.13277

Addt'l Rte.-Sec.: Drew 277-1

< $1 M1 Scheduled 2021 6.68 $1 - $5 MA20007

RehabilitationSparkman Overlay & Rehab. (Se. Secs.) (S) 1.56 $262,219Completed Jan. 2015 Jun. 2015 1.56 $262,219C20001*

ResurfacingMcGehee Street Impvts. (Sel. Secs.) (S) 0.85CS $239,439Completed Jul. 2013 Oct. 2013 0.85 $239,439C21001*

ResurfacingDumas, Mitchellville and Reed Street Impvts. 2.54CS $381,116Completed Feb. 2014 May. 2014 2.54 $381,116C21002*

-ResurfacingArkansas City Overlay (Sel. Secs.) (S) CS $314,636Completed Sep. 2014 Dec. 2014 - $314,636C21003*

ResurfacingDumas Overlay (Sel. Secs.) (S) 1.08CS $238,770Completed Apr. 2018 Jul. 2018 1.08 $238,770C21004*

-ResurfacingMcGehee Overlay & Rehab. (Sel. Secs.) (S) CS $506,929Sub. Completed Jun. 2019 Oct. 2019 - $506,929C21005*

-ResurfacingMitchellville & Watson Overlay (S) CS $463,350Under Construction Feb. 2020 - $463,350C21006*

Program Management

Desha

June 3, 2020

* Job not shown on county map.

Page 4: SUMMARY OF CONSTRUCTION PROJECTSardot.gov/program_mgmt/gis/JobStatusMaps_2018/21_0_Desha.pdf · 2020-06-05 · SUMMARY OF CONSTRUCTION PROJECTS DESHA COUNTY County Totals Job No

SUMMARY OF CONSTRUCTION PROJECTS

DESHA COUNTYCounty Totals

CostLength (Mi)Type WorkJob Name Rte.Job No. Sec. Status Let Date Date

Project Totals

CostLength (Mi)

Sub. Comp.

ResurfacingArkansas City, Dermott & Tillar Overlay (S) 1.69

Addt'l Rte.-Sec.: Drew CS

$508,486Completed Feb. 2019 May. 2019 4.55 $798,399C76044*

-MiscellaneousMcCallie Boat Ramps and Pkg Lot (Ms River)(s) $1,230,500Under Construction Oct. 2018 - $1,230,500GF0270*

ReconstructionU. of A. Agri. Exp. Sta. Access & Dr. 0.30823 < $1 M1 Programmed 0.30 < $1 MR20048

- PE OnlyPine Bluff – Mississippi Line P.E. 65

Addt'l Rte.-Sec.: Various

- 17 Programmed - - R20089*

Major WideningSouth Gould – Hwy. 159 (No. Dumas) (S) 4.5265 $16,050,26417 Completed Feb. 2009 Jun. 2011 4.52 $16,050,264R20092

ResurfacingCo. Rd. 31 Reconst., Surf., &OLAY(SEL Sec)(s) 3.40CR $571,369Completed Jul. 2012 Oct. 2012 3.40 $571,369SA2129*

ResurfacingDesha County Reseal (Sel. Secs.) (S) 5.73CR $148,125Completed Jun. 2015 Oct. 2015 5.73 $148,125SA2130*

-ResurfacingOakwood Bayou Rd Widening & Base (Sel.sec)(s) CR $238,855Completed Jul. 2017 Oct. 2017 - $238,855SA2131*

- ResurfacingDesha County Reseal No. 2 (Sel. Secs.) (S) CR $76,361Completed Jul. 2017 Oct. 2017 - $76,361SA2132*

ResurfacingOakwood Bayou Rd. Surfacing (Sel. Sec.) (S) 0.93CR $253,837Completed Apr. 2018 Jul. 2018 0.93 $253,837SA2133*

ResurfacingDesha Co. Widening & Base (Sel. Secs.) (S) 1.51CR $229,889Completed Feb. 2018 Jul. 2018 1.51 $229,889SA2134*

ResurfacingDesha County Surfacing No. 14 (Sel. Secs.) (S 1.61CR $314,289Completed Jul. 2018 Nov. 2018 1.61 $314,289SA2135*

$138,542,094155.00Totals For All Projects In Desha County