Sullivan IRvacuum

Embed Size (px)

Citation preview

  • 7/31/2019 Sullivan IRvacuum

    1/33

    1

    IR Vacuum

    M. Sullivan

    MAC Review

    Oct. 25-27, 2006

    M. Sullivan

    for the PEP-II team

    Machine Advisory Committee Review

    October 25-27, 2006

    IR Vacuum Update

  • 7/31/2019 Sullivan IRvacuum

    2/33

    2

    IR Vacuum

    M. Sullivan

    MAC Review

    Oct. 25-27, 2006

    Outline

    Brief recap of last Januarys presentation History General Characteristics NEG heating tests Last January Conclusions

    Attempts to pin down the source More NEG heating tests Software Hardware

    The Answer What it was Present fix Future fix

  • 7/31/2019 Sullivan IRvacuum

    3/33

    3

    IR Vacuum

    M. Sullivan

    MAC Review

    Oct. 25-27, 2006

    History

    We started to notice a large number of beam aborts from highradiation levels from the detector about mid December of lastyear. In retrospect, we have identified events of this type asearly as the beginning of Dec.

    At that time, we were more concerned about the fast dI/dt LERaborts and some of us thought that perhaps these BaBaraborts were a new manifestation of the fast dI/dt aborts.

    It wasnt until Monday, the day after New Years, that we

    discovered we had very fast vacuum spikes somewhere nearthe detector on the LER upstream side whenever the detectoraborted the beam due to high radiation levels.

  • 7/31/2019 Sullivan IRvacuum

    4/33

    4

    IR Vacuum

    M. Sullivan

    MAC Review

    Oct. 25-27, 2006

    Some Characteristics Very fast high pressure spikes. Difficult to see with 6 min history

    buffers.

    Seen in single ring for each beam but at much higher currentsthan colliding beams. Conclusion: either close by or inside sharedbeam pipe.

    Insensitive to orbit (+/- 2mm in Y and +/-8 mm in X at the ends ofthe support tube)

    Radiation levels from the LER beam are consistently higher thanradiation levels from the HER beam

    Exhibits more bunch charge dependence than total current

    dependence

  • 7/31/2019 Sullivan IRvacuum

    5/33

    5

    IR Vacuum

    M. Sullivan

    MAC Review

    Oct. 25-27, 2006

    Interaction Region Layout

    LERHER

    7039 gaugeSIG11LER sensitive

    2187 gauge

    3044 pump

    LER frangible link

    Detector

    7043 pump

    8020 pump

    3027 gauge

    Support tube end bellows

    3027 pump

    NEG pump

    Backward Q2 NEG

    Forward Q2 NEG

  • 7/31/2019 Sullivan IRvacuum

    6/33

    6

    IR Vacuum

    M. Sullivan

    MAC Review

    Oct. 25-27, 2006

    NEG heating test

    In order to try to localize the source of the vacuumspikes we tried heating up some of the NEG pumpsand recording the vacuum readings from thevarious gauges and pumps

    We decided to heat up the two NEG pumps closestto the IP. These are the two NEGs just outboard of

    the ends of the support tube

    We did this without beam and we did not try toregenerate the NEG pumps

  • 7/31/2019 Sullivan IRvacuum

    7/337

    IR Vacuum

    M. Sullivan

    MAC Review

    Oct. 25-27, 2006

    List of Vacuum spikesThe list of vacuum aborts that we had started in January grew to over 200

    entries by the 3rd

    week of March.

  • 7/31/2019 Sullivan IRvacuum

    8/338

    IR Vacuum

    M. Sullivan

    MAC Review

    Oct. 25-27, 2006

    Pressure and Background Ratios

    Forward Q2 NEG

    Backward Q2 NEG

    HERradiationevent

    LERradiationevent

  • 7/31/2019 Sullivan IRvacuum

    9/339

    IR Vacuum

    M. Sullivan

    MAC Review

    Oct. 25-27, 2006

    Conclusions of Last January

    In December we started encountering, with increasing

    frequency, beam aborts associated with high radiationlevels in the detector

    It took us a while to understand that these aborts were anew problem and not an alternate manifestation of theinstabilities we were already trying to identify

    We have identified the cause of these beam aborts to bedue to fast vacuum spikes in the IR.

    All present information points to a region on the forwardside of the detector and probably in the LER beam pipe

    or in the shared beam pipe.

    The most likely location is the forward side support tubeend bellows

    The most likely initiation for the event is an arc

  • 7/31/2019 Sullivan IRvacuum

    10/3310

    IR Vacuum

    M. Sullivan

    MAC Review

    Oct. 25-27, 2006

    The Story Continued.

    Throughout Jan.-Mar. we made several attempts to try to locate the source ofthese vacuum spikes More NEG heating tests with and without beam (the IR vacuum model has

    been greatly improved) We first took out a NEG pump and then later replaced a chamber in the

    incoming LER beam pipe RGA readings indicated a large burst of nitrogen when we had a vacuum

    spike We installed the ability to remotely make a gas burst into the beam pipe.

    This told us we did not have an air leak. The BaBar detector collaboration used the events taken by the detector

    when these vacuum spikes occurred to try to locate the source. Manydifferent analysis techniques were used: from timing differences to trackreconstruction to neutron counting rates

    We also analyzed timing differences between gas signals from the variousgauges and pumps in the area There was an analysis of the shape of the gas pulse from the gauges and

    pumps Im sure I have forgotten a few more

  • 7/31/2019 Sullivan IRvacuum

    11/33

    IR V

  • 7/31/2019 Sullivan IRvacuum

    12/3312

    IR Vacuum

    M. Sullivan

    MAC Review

    Oct. 25-27, 2006

    Side view of BaBar

    Backward

    Q1/Q2bellows

    Forward

    Q1/Q2

    bellows

    Forward

    Q2chamber

    IR V

  • 7/31/2019 Sullivan IRvacuum

    13/3313

    IR Vacuum

    M. Sullivan

    MAC Review

    Oct. 25-27, 2006

    Heating up the

    forward Q2 NEGLuminosity went down when weadded gas.

    The decrease is noticeable at a

    pressure of about 30 nTorr

    Traced to the HER vertical spotsize increasing.

    Luminosity restored as the

    pressure goes down.

    This told us that the HER wassensitive to relatively smallgas bursts

    IR V

  • 7/31/2019 Sullivan IRvacuum

    14/3314

    IR Vacuum

    M. Sullivan

    MAC Review

    Oct. 25-27, 2006

    BaBar Analyses from Brians Talk

    IR Vacuum

  • 7/31/2019 Sullivan IRvacuum

    15/3315

    IR Vacuum

    M. Sullivan

    MAC Review

    Oct. 25-27, 2006

    The Answer

    In late February we were looking at theQ1/Q2 bellows with a bore scope and tryingto see if any of the tiles had come loosewhen it suddenly became clear that we hadincorrectly designed the RF seals that arenext to the tiles. The seals were touchingthe tiles instead of touching the Cu underthe tiles.

    With this knowledge we made new RF sealsand prepared for a ten day access startingon March 19

    IR Vacuum

  • 7/31/2019 Sullivan IRvacuum

    16/3316

    IR Vacuum

    M. Sullivan

    MAC Review

    Oct. 25-27, 2006

    Forward Q1/Q2 bellows section

    Q1 side of

    bellows

    IR Vacuum

  • 7/31/2019 Sullivan IRvacuum

    17/3317

    IR Vacuum

    M. Sullivan

    MAC Review

    Oct. 25-27, 2006

    Close up of damage to the tiles

    IR Vacuum

  • 7/31/2019 Sullivan IRvacuum

    18/3318

    IR Vacuum

    M. Sullivan

    MAC Review

    Oct. 25-27, 2006

    RF seal note the bolt head

    RF finger

    seen inborescopevideos

    IR Vacuum

  • 7/31/2019 Sullivan IRvacuum

    19/3319

    IR Vacuum

    M. Sullivan

    MAC Review

    Oct. 25-27, 2006

    Close up of RF seal

    IR Vacuum

  • 7/31/2019 Sullivan IRvacuum

    20/3320

    IR Vacuum

    M. Sullivan

    MAC Review

    Oct. 25-27, 2006

    Another dark spot on another finger

    IR Vacuum

  • 7/31/2019 Sullivan IRvacuum

    21/3321

    IR Vacuum

    M. Sullivan

    MAC Review

    Oct. 25-27, 2006

    Dark spot corresponds to a pit on the tile

    IR Vacuum

  • 7/31/2019 Sullivan IRvacuum

    22/3322

    M. Sullivan

    MAC Review

    Oct. 25-27, 2006

    Why was the failure located here?

    No real answers

    Something to do with the corners of the tiles?

    Something to do with the edges of the RF fingers?

    Perhaps a weak point in the tile? A crack?

    IR Vacuum

  • 7/31/2019 Sullivan IRvacuum

    23/3323

    M. Sullivan

    MAC Review

    Oct. 25-27, 2006

    Picture of bellows before installation in 2002

    This picture is a

    miracle!!

    The correct

    bellows section in

    the correct

    orientation!!!

    Thank you Scott!!

    IR Vacuum

  • 7/31/2019 Sullivan IRvacuum

    24/33

    24

    M. Sullivan

    MAC Review

    Oct. 25-27, 2006

    RF seal repositioned onto bellows

    Tile damageis here

    IR Vacuum

  • 7/31/2019 Sullivan IRvacuum

    25/33

    25

    M. Sullivan

    MAC Review

    Oct. 25-27, 2006

    Cu posts not brazed to the tile

    IR Vacuum

  • 7/31/2019 Sullivan IRvacuum

    26/33

    26

    M. Sullivan

    MAC Review

    Oct. 25-27, 2006

    Present Fix

    We designed and built a set new RF seals so thatthey engage the Cu underneath the tiles

    We took out the bellows section from the other

    side of the detector and placed it in the location ofthe damaged bellows section

    We then reinstalled one of the Mk I bellows on the

    backward side of the detector. This side collectsabout half as much power as the forward side

    All locations had new RF seals in stalled

    IR Vacuum

  • 7/31/2019 Sullivan IRvacuum

    27/33

    27

    M. Sullivan

    MAC Review

    Oct. 25-27, 2006

    New Q1/Q2 Bellows RF Seal

    3/6 - New RF Seal Plate

    submitted to MFD

    3/3 - Prototype RF Seal

    made using existing

    SPEAR3 RF seal die and

    another existing die.

    IR Vacuum

    S

  • 7/31/2019 Sullivan IRvacuum

    28/33

    28

    M. Sullivan

    MAC Review

    Oct. 25-27, 2006

    New RF seal Compound J seal

    IR Vacuum

    M S lli

  • 7/31/2019 Sullivan IRvacuum

    29/33

    29

    M. Sullivan

    MAC Review

    Oct. 25-27, 2006

    New RF seal Side away from Tiles

    IR Vacuum

    M S lli

  • 7/31/2019 Sullivan IRvacuum

    30/33

    30

    M. Sullivan

    MAC Review

    Oct. 25-27, 2006

    New RF seal Close up of tile side

    IR Vacuum

    M Sullivan

  • 7/31/2019 Sullivan IRvacuum

    31/33

    31

    M. Sullivan

    MAC Review

    Oct. 25-27, 2006

    Improved Design

    Current bellows in the forward side (MkII)can absorb 5-10 kW and is currentlyabsorbing about 7 kW

    When we go to higher currents and shorterbunches we will absorb even more power

    Presently building a new design bellows(MkIII) that will absorb less direct power

    from the beam Plan to install the new design this down

    time

    IR Vacuum

    M Sullivan

  • 7/31/2019 Sullivan IRvacuum

    32/33

    32

    M. Sullivan

    MAC Review

    Oct. 25-27, 2006

    Q1/Q2 Blws New Design MkIII

    New concept

    developed based on best

    informationavailable.

    MaximumTile/slot length

    ~2.4

    Absorbing tilesare open to theconvolutions

    No additionaltile setsneeded inbellowscavity.

    HER Arc StyleBellows

    Spring

    Stub

    RF shield

    Possibly reduce

    further the travel and

    offset requirements to

    increase length.

    IR Vacuum

    M Sullivan

  • 7/31/2019 Sullivan IRvacuum

    33/33

    M. Sullivan

    MAC R i

    Summary We finally tracked down the problem to a design flaw in how

    the RF seal was engaged at the edge of the absorber tiles in theQ1/Q2 bellows section

    An arc track had developed on the surface of the tile. Thisexplains why the beam current threshold came down initiallyand then stabilized.

    Once the problem was figured out, new RF seals were madeand installed

    Since the repair, we have had NO unusual abort causingvacuum activity in this area

    We would like to thank all of the people who helped us with thistough problem BaBar collaborators, engineers, technicians,machine shops, experts from other groups, etc.