map-lab was selected to assist Suffolk University and their Theater Department to oversee the second phase of a multi-phase renovation to the C. Walsh Theater. The project was conceived as a thesis project by Jim Bernhardt while completing his Masters Degree in Theater Production at Boston University and consisted of a full backstage renovation of the C. Walsh Theater. map-lab worked with Epstein Joslin Architects and the client team to outline various options and their respective costs. By working iteratively with the client team, four options were created, and map-lab assembled full project budgets for that would be reviewed by the University. BUDGET Project Suffolk University C. Walsh Theater Number Client/User Suffolk University map-lab Date: 12.11.2008 Vendor Full Scope Option Reduced Scope Option Minor Scope Option Budget Account Number PO Number PO Amount Expended to Date Balance PO) Construction Construction Cost Suffolk Construction $2,051,007.00 $1,009,320.00 $778,910.00 Related Project Costs Furniture, Fixtures, & Equipment $5,000.00 $5,000.00 $5,000.00 Telephone $2,500.00 $2,500.00 $2,500.00 Data $2,500.00 $2,500.00 $2,500.00 Moving/ Storage $2,500.00 $2,500.00 $2,500.00 Moving Consultant A/V included above included above Asbestos Testing Covino $1,500.00 $1,500.00 $1,500.00 Abatement Not Necessary Sub-Total $2,065,007.00 $1,023,320.00 $792,910.00 A/E and PM Costs Pre-Design Epstein Joslin $27,200.00 $27,200.00 $27,200.00 Architecture/Engineering Epstein Joslin $179,380.00 $124,885.00 $96,800.00 Study Management map-lab $15,600.00 $15,600.00 $15,600.00 Project Management map-lab $55,000.00 $50,000.00 $40,000.00 Inspection Other reimbursable exp. $10,000.00 $10,000.00 $10,000.00 Sub-Total $287,180.00 $227,685.00 $189,600.00 Other Land Mitigation Taxes coordinate iterative design process assess design options define project costs SUFFOLK UNIVERSITY C. WALSH THEATRE BOSTON, MA SUFFOLK UNIVERSITY MANAGEMENT project location client project type

Suffolk-CWalsh-Th

Embed Size (px)

DESCRIPTION

http://www.map-lab.com/storage/project-profiles/suffolk-university-c-walsh-theatre/Suffolk-CWalsh-Theatre-ProjectPage.pdf

Citation preview

map-lab was selected to assist Suffolk University and their Theater Department to oversee the second phase of a multi-phase renovation to the C. Walsh Theater. The project was conceived as a thesis project by Jim Bernhardt while completing his Masters Degree in Theater Production at Boston University and consisted of a full backstage renovation of the C. Walsh Theater. map-lab worked with Epstein Joslin Architects and the client team to outline various options and their respective costs. By working iteratively with the client team, four options were created, and map-lab assembled full project budgets for that would be reviewed by the University. BUDGET

Project Suffolk University C. Walsh Theater

Number

Client/User Suffolk University

map-labDate: 12.11.2008

Vendor Full Scope Option Reduced Scope Option Minor Scope OptionBudget Account Number PO Number PO Amount

Expended to Date

Balance (under PO)

DepreciationLife

Construction

Construction Cost Suffolk Construction $2,051,007.00 $1,009,320.00 $778,910.00 $0

Related Project Costs

Furniture, Fixtures, & Equipment $5,000.00 $5,000.00 $5,000.00 10

Telephone $2,500.00 $2,500.00 $2,500.00 5

Data $2,500.00 $2,500.00 $2,500.00

Moving/ Storage $2,500.00 $2,500.00 $2,500.00

Moving Consultant

A/V included above included above 5

Asbestos Testing Covino $1,500.00 $1,500.00 $1,500.00 50

Abatement Not Necessary

Sub-Total $2,065,007.00 $1,023,320.00 $792,910.00

A/E and PM Costs

Pre-Design Epstein Joslin $27,200.00 $27,200.00 $27,200.00

Architecture/Engineering Epstein Joslin $179,380.00 $124,885.00 $96,800.00 50

Study Management map-lab $15,600.00 $15,600.00 $15,600.00

Project Management map-lab $55,000.00 $50,000.00 $40,000.00 50

Inspection

Other reimbursable exp. $10,000.00 $10,000.00 $10,000.00 50

Sub-Total $287,180.00 $227,685.00 $189,600.00

Other

Land

Mitigation

Taxes

Financial

Legal

Sub-Total $0.00 $0.00

Contingency

Project Contingency $200,000.00 $100,000.00 $75,000.00

Project Cost Estimate

Total Project Cost $2,552,187.00 $1,351,005.00 $1,057,510.00

Indicies (for information only)

Area (in SF)

Project Cost per SF 1,414 1,414 1,414

Construction Cost per SF $1,451 $714 $551

Notes

coordinate iterative design processassess design optionsdefine project costs

Suffolk univerSity c. walSh theatre

BOSTON, MA

SUFFOLK UNIVERSITY

MANAGEMENT

project

location

client

project type