Submitted by Arkansas. Enhancement: On the Diary screen, a day of the week field should be added next to the date field. The day of the week should compute automatically from the date entered. - PowerPoint PPT Presentation
Citation preview
Submitted by ArkansasEnhancement: On the Diary screen, a day of the week field should be added next to the date field. The day of the week should compute automatically from the date entered.
Benefits: Since time charges and other items are affected by which day of the week they occur on, addition of this field would keep users from having to check a calendar for the day of the week.
Submitted by TAG
Change the screen display to 800 x 600 pixels for those screens that are specifically requested. Others will be changed at a later date. Reference 4367
Submitted by TAG
On the Change Order Items screen, reverse the order of the “Category” and “Project Number” fields and change the tab order to “Line Number”, “Project Number”, “Category.” Add Change Order Explanations to the Services drop down menu
TAG Recommendation3639 General System Enhancements: Add a new interface between SiteManager and FieldManager.
The TAG does not support this interface as written because of cost and the large number of TMRs outstanding for SiteManager. Recommend looking at the possibility of modularizing it.
TAG Recommendation
4042 – Associate funding source for estimate adjustments (for material stockpile)
4274 – All contract adjustments should include funding source allocation.
Recommend 4042 and 4274 should be combined. Nebraska will withdraw #4042
TAG Recommendation
4743 – Create a funding cap. This should be looked at if/when working on 4274.