CVISN Planning Workshop
The Johns Hopkins University Applied Physics Laboratory
Day 0, P2 Work Breakdown Structure Review & Prep!
3/19/2012 8:37 AM P2 - 1
Session Outline
What is a WBS and where is it useful? What is successive decomposition?
How is the WBS used on a program?
How can I tell if I have a good WBS?
Numbering notation.
Examples.
Common errors.
Outline
8/2/2019 Subhadeep Notes
2/18
CVISN Planning Workshop
The Johns Hopkins University Applied Physics Laboratory
Day 0, P2 Work Breakdown Structure Review & Prep!
3/19/2012 8:37 AM P2 - 2
Where is WBS Useful?
Rocket Science?
Brain Surgery?
CVISN?
8/2/2019 Subhadeep Notes
3/18
CVISN Planning Workshop
The Johns Hopkins University Applied Physics Laboratory
Day 0, P2 Work Breakdown Structure Review & Prep!
3/19/2012 8:37 AM P2 - 3
The Work Breakdown Structure Is...
Product-oriented hierarchy of goods and services.
Form: inverted tree; or indented list.
Visualizing the entire project.
Common framework for planning and control.
Vehicle to divide work into tasks that are:
Manageable
Independent
Measurable
Integratable
Graphically displays entire project. Clear definition of all effort.
Top Assembly Drawing of the project.
Product Breakdown Structure or Project Breakdown Structure moreapt name! Or perhaps Work Buildup Structure.
WBS Definition
8/2/2019 Subhadeep Notes
4/18
CVISN Planning Workshop
The Johns Hopkins University Applied Physics Laboratory
Day 0, P2 Work Breakdown Structure Review & Prep!
3/19/2012 8:37 AM P2 - 4
and so on, while it makes sense
more decomposition
more decomposition
Create a WBS via RecursiveProduct-Oriented Decomposition
(Call This Level 1)
Principal Product Associated SupportProduct Level 2
Associated SupportService Level 2
Principal Product
Sub-Product Associated SupportProduct Level 3
Associated SupportService Level 3
Sub-Product
Sub-Sub-Product(s)
Associated SupportProduct Level 4
Associated SupportService Level 4
WBS Construction 2000-01-26
8/2/2019 Subhadeep Notes
5/18
CVISN Planning Workshop
The Johns Hopkins University Applied Physics Laboratory
Day 0, P2 Work Breakdown Structure Review & Prep!
3/19/2012 8:37 AM P2 - 5
Example: Break Down 100% (1 of 2)
100%
Decomposition Summation
2000-01-26
8/2/2019 Subhadeep Notes
6/18
CVISN Planning Workshop
The Johns Hopkins University Applied Physics Laboratory
Day 0, P2 Work Breakdown Structure Review & Prep!
3/19/2012 8:37 AM P2 - 6
Example: Break Down 100% (2 of 2)
and so on, while it makes sense
more decomposition
more decomposition
20% 10%10% 60%
25% 10%5% 20%
20% 3%2%
100%
Summation 2000-01-26
8/2/2019 Subhadeep Notes
7/18
CVISN Planning Workshop
The Johns Hopkins University Applied Physics Laboratory
Day 0, P2 Work Breakdown Structure Review & Prep!
3/19/2012 8:37 AM P2 - 7
Program IntegrationActivity Plan
Project Integration Plan
Product Activity Plan
CVISNProgram
CI
Credentialing
Product Activity Plan
Project Integration PlanSafety
CVIEW
Product Activity Plan
IRP
Program
Project
Product
MoreDecomposition MoreDecompositionMoreDecomposition
More
Decomposition
More
Decomposition
More
Decomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
Principal Product(s) Associated SupportProducts Level 2
Associated SupportServices Level 2
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
(Call This Level 1)
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
MoreDecomposition
By decomposing, eventually.....
.....you get to activities thatcan be assigned and
scheduled.
WBS Construction
8/2/2019 Subhadeep Notes
8/18
CVISN Planning Workshop
The Johns Hopkins University Applied Physics Laboratory
Day 0, P2 Work Breakdown Structure Review & Prep!
3/19/2012 8:37 AM P2 - 8
Example Extended WBS for a Complex Program
Note the different orientationsfrom top to bottom.
WBS unfolds and evolves as
scope and design become known.
WBS Definition
The Work to
be Done!
8/2/2019 Subhadeep Notes
9/18
CVISN Planning Workshop
The Johns Hopkins University Applied Physics Laboratory
Day 0, P2 Work Breakdown Structure Review & Prep!
3/19/2012 8:37 AM P2 - 9
History
Clinical Exam
Imaging
Blood &Tissue Tests
Likely Diagnosis
Risk Assessment
Education of Patient
Alternative Analysis& Trade-Offs
Treatment Plan
1.0 Diagnosis
Communications AmongTeam
Patient & TeamPositioning
(for neurosurgery)
Acquisition of NeededInstruments & Equipment
Scheduling of NeededSpecialists
Practice Run-Throughs
2.0 Plan forOperation
Verify Patient Can HandleStress of Surgery
Stop Drugs that WouldInterfere with Surgery
3.0 PreoperativePatient Care
Verify Patient Identity &Location of Surgery
Anesthesia
Patient Underthe Knife
Vital Signs &Fluid-Loss Monitoring
NeurophysiologicalMonitoring
(during neurosurgery)
Maintain Neat & CleanOperative Field
Wrap-up: VerifySmall Part Count
(sponge, needle, cottonoid, Michel clips)
Operative Notes &Chart Updates
4.0 Execution ofOperation
Written Care Orders
Briefing of Recovery Staffby Surgeon
Vital Signs &Fluid-Loss Monitoring
NeurophysiologicalMonitoring
5.0 PostoperativePatient Care
Follow-up Clinical Visits
Physical Therapy
6.0 Long-TermPatient Care
Surgical TreatmentProject
WBS for Brain Surgery (tree format)
Sources:1.Bailey & Lovess Short Practice of Surgery, 22nd Edition, edited by Charles V. Mann, R.C.G.Russell, and Norman S. Williams. Chapman & Hall Medical, 1995. ISBN 0-412-49490-6.
2. Brain Surgery Complication Avoidance and Management, by Michael L. J. Apuzzo, M.D.Churchill Livingstone, Inc., 1993. ISBN 0-443-08709-1. See Chapter 1, Preoperative and SurgicalPlanning for Avoiding Complications by Robert G. Grossman.
8/2/2019 Subhadeep Notes
10/18
CVISN Planning Workshop
The Johns Hopkins University Applied Physics Laboratory
Day 0, P2 Work Breakdown Structure Review & Prep!
3/19/2012 8:37 AM P2 - 10
Surgical Treatment Project
1.0 DiagnosisHistory
General Medical ConditionSpecific ComplaintClerking?? (for elective surgery??)
Clinical ExamImaging
Ultrasonography
Plain Radiography (X-Ray)Computed Tomography (CAT Scan)Magnetic Resonance Imaging (MRI)
Blood and Tissue TestsLikely DiagnosisRisk AssessmentEducation of Patient (e.g. anatomy)Alternative Analysis & Trade-OffsTreatment Plan
2.0 Planning of the OperationCommunications Among TeamPatient and Team Positioning (for neurosurgery)Acquisition of Needed Instruments & EquipmentScheduling of Needed SpecialistsPractice Run-Throughs
3. 0 Preoperative Patient Care
Verify Patient can Handle Stress of SurgeryStop Drugs that Would Interfere with Surgery
4.0 Execution of the Operation (Actual Surgery)Verify Patient Identity and Location of SurgeryAnesthesiaPatient Under the Knife
Real-time Diagnostic BiopsiesTherapeutic Surgery
Vital Signs and Fluid-Loss MonitoringNeurophysiological monitoring (during neurosurgery)Maintain Neat and Clean Operative FieldWrap-up: Verify Small Part Count (sponge,
needle, cottonoid, Michel clips)Operative Notes and Chart Updates
5.0 Postoperative CareWritten Care Orders
Briefing of Recovery Staff by SurgeonVital Signs and Fluid-Loss MonitoringNeurophysiological Monitoring
6.0 Long-Term Patient CareFollow-up Clinical VisitsPhysical Therapy
WBS for Brain Surgery (indented list)
8/2/2019 Subhadeep Notes
11/18
CVISN Planning Workshop
The Johns Hopkins University Applied Physics Laboratory
Day 0, P2 Work Breakdown Structure Review & Prep!
3/19/2012 8:37 AM P2 - 11
WBS is The Basis For......
Cost estimates and budgets.
Milestones & schedules.
Responsibility assignment.
Allocation of resources.
Schedule horizontal and vertical traceability.
Risk analysis.
Concurrence of participants.
Integrating the total project effort.
Summarizing costs, schedules, performance.
Forcing the Project Manager to think through all elementsof the project.
WBS Definition
8/2/2019 Subhadeep Notes
12/18
CVISN Planning Workshop
The Johns Hopkins University Applied Physics Laboratory
Day 0, P2 Work Breakdown Structure Review & Prep!
3/19/2012 8:37 AM P2 - 12
Tests for a Good WBS:
Product-oriented hierarchy of goods and services.
Top level may be dictated by contract.
Basis for cost estimating, project organization, assigning responsibility,task scheduling, and status reporting.
Basis for understanding and communication.
Each element should be manageable.
Based on System Engineering: interfaces are minimized; units are
stand-alone testable. Eliminating one product element will delete the associated costs.
Segregate recurring from non-recurring costs.
Identifies and defines all effort to be expended: correlation of lowerlevels to specification tree, contract line items, data items, and work
statement tasks. Useful! Reflects the way the work is managed and performed.
Sufficiently low level to establish adequate visibility and confidence forcost estimating, project planning, and project control.
Technical/cost/schedule can be integrated at every level for each
element. WBS Definition
8/2/2019 Subhadeep Notes
13/18
CVISN Planning Workshop
The Johns Hopkins University Applied Physics Laboratory
Day 0, P2 Work Breakdown Structure Review & Prep!
3/19/2012 8:37 AM P2 - 13
WBS Levels & Numbering Notation
1. Project Management
2.1 Magnetometer
2.2 Spectrograph
2. Science Instruments
3.1 Propulsion Subsystem
3.2 Attitude Control Subsystem
3.3.1.1 Processor Card
3.3.1.2 Memory Card
3.3.1 C&DH Hardware
3.3.2 C&DH Software
3.3.3 Subsystem Integration
3.3 Command & Data Handling Subsystem
3. Spacecraft Bus 4. Ground Support Equipment
Satellite Mission Project
Satellite Mission Project1. Project Management2. Science Instruments
2.1 Magnetometer
2.2 Spectrograph
3. Spacecraft Bus
3.1 Propulsion Subsystem3.2 Attitude Control Subsystem
3.3 Command & Data Handling Subsystem
3.3.1 C&DH Hardware3.3.1.1 Processor Card3.3.1.2 Memory Card
3.3.2 C&DH Software
3.3.3 Subsystem Integration
4. Ground Support Equipment WBS Definition
Level 1
(Level 1)
Level 2
(Level 2)
Level 3
(Level 3)
Level 4
(Level 4)
Level 5
(Level 5)
8/2/2019 Subhadeep Notes
14/18
CVISN Planning Workshop
The Johns Hopkins University Applied Physics Laboratory
Day 0, P2 Work Breakdown Structure Review & Prep!
3/19/2012 8:37 AM P2 - 14
Exercise
Scenario Exercise
Imagine you are working at the
Atlantic Pacific Sea VisionFountain Pen Manufacturing Company
Lets develop a WBS for our proposedmechanical pencil project.
Motto: Yesterdays Technology Solving
Todays Problems Tomorrow
8/2/2019 Subhadeep Notes
15/18
CVISN Planning Workshop
The Johns Hopkins University Applied Physics Laboratory
Day 0, P2 Work Breakdown Structure Review & Prep!
3/19/2012 8:37 AM P2 - 16
Where Does the Work Get Done?!!
Satellite Mission Project1. Project Management2. Science Instruments3. Spacecraft Bus
3.1 Propulsion Subsystem3.2 Attitude Control Subsystem3.3 Command & Data Handling Subsystem
3.3.1 C&DH Hardware3.3.1.1 Processor Card
3.3.1.1.1 Engineering Design3.3.1.1.2 Layout & Package Design3.3.1.1.3 Fabrication3.3.1.1.4 Assembly & Test
3.3.2 C&DH Software3.3.2.1 Command Parsing Module
3.3.2.1.1 Architectural Design
3.3.2.1.2 Detailed Design3.3.2.1.3 Coding3.3.2.1.4 Unit Test
3.3.3 Subsystem Integration3.3.3.1 Integration Plan3.3.3.1 Integrate Instruments with Bus
4. Ground Support Equipment WBS Definition
Product-Oriented
Nouns
Process-Oriented
Here is real work!
Verbs
8/2/2019 Subhadeep Notes
16/18
CVISN Planning Workshop
The Johns Hopkins University Applied Physics Laboratory
Day 0, P2 Work Breakdown Structure Review & Prep!
3/19/2012 8:37 AM P2 - 17
Typical WBS for a State CVISN Program
WBS Sample
1.1 Planning &Coordination
1.2 CarrierCoordination
1.3 Showcases
& Outreach
1.4 RegionalCoordination
1.5 O & M Planning
1.6 Training
1.7 Policy
1.8 Subcontract &Procurement Mgt
1. ProgramManagement
2.1 SystemRequirements
Definition
2.2 SystemDesign
2.3 Architecture
Conformance
2.4 SystemIntegrationand Test
2.5 InteroperabilityTesting
2. SystemEngineering &
Integration
3.1 Proj Mgt
3.2 Sys Engr &Integration
3.3 Subcontract &
Procurement Mgt
3.4 CV InformationExchange
Window (CVIEW)
3.5 ASPEN
3.6 SAFETYNET
3.7 Builds 1...n
3. SafetyProject
4.1 Proj Mgt
4.2 Sys Engr &
4.3 Subcontract &
Procurement Mgt
4.4 InternationalRegistrationPlan (IRP)
4.5 InternationalFuel Tax
Agreement (IFTA)
4.6 CredentialingInterface
4.7 Motor CarrierHome Page &
Web Credentialing
4.8 Carrier CredSystems
(CAT or module)
4.9 Intra-StateRegistration
4.10 Builds 1...n
4. CredentialsProject
5.1 Proj Mgt
5.2 Sys Engr &Integration
5.3 Subcontract &
Procurement Mgt
5.4 RoadsideOperations
5.5 Screening
5.6 Site Mods
5.7 CarrierE-ScreeningEnrollment
5.8 Builds 1...n
5. E-ScreeningProject
6.1 Self-Evaluation
6.2 National Evaluation(Funded Separately)
6. Evaluation
StateCVISN Program
2001-06-14
Level 1
Level 2
Level 3
8/2/2019 Subhadeep Notes
17/18
CVISN Planning Workshop
The Johns Hopkins University Applied Physics Laboratory
Day 0, P2 Work Breakdown Structure Review & Prep!
3/19/2012 8:37 AM P2 - 18
Elements Not to Include in WBS
Do not use the structure of the contractors organization as the basis
of a WBS. At the top levels do not begin by decomposing into the functions or
cost categories associated with developing those products.
Adapted fromDepartment of Defense HandbookWork Breakdown Structure, MIL-HDBK-881.Available at:http://www.acq.osd.mil/pm/newpolicy/wbs/wbs.html.
Includes examples from the defense industry.
Program
Design Build Test
Hardware Software
What not to do!
Do not use generic names -- use actual system names andnomenclature.
No disembodied software -- software developed to reside on specificequipment must be identified as a subset of that equipment.
WBS Definition