1 LHC Days in Split Status of LHCb construction 06.10.2004 Rustem DZHELYADIN (IHEP, Protvino) Study of CP violation in B meson decays Vertex reconstruction Particle ID up to 100GeV Magnet spectrometer Calorimeters Muon system Efficient multilevel trigger Experiment control and Data acquisition Systems On behalf of the LHCb Collaboration

Study of CP violation in B meson decays - CERNlhcb-doc.web.cern.ch/lhcb-doc/presentations/conferencetalks/... · Study of CP violation in B meson decays ... VErtex LOcator ... Silicon

  • Upload
    vocong

  • View
    215

  • Download
    0

Embed Size (px)

Citation preview

1

LHC Days in SplitStatus of LHCb construction

06.10.2004 Rustem DZHELYADIN (IHEP, Protvino)

Study of CP violation in B meson decaysVertex reconstructionParticle ID up to 100GeVMagnet spectrometerCalorimetersMuon system

Efficient multilevel triggerExperiment control andData acquisition Systems

On behalf of the LHCb Collaboration

2

Status of LHCb construction

Beam pipe

06.10.2004 Rustem DZHELYADIN (IHEP, Protvino)

3

Status of LHCb construction

Dipole magnet

06.10.2004 Rustem DZHELYADIN (IHEP, Protvino)

20/01/2004

17/11/2003

12/12/2003

Magnet install in 2003-04

4

Status of LHCb construction

Dipole magnet

06.10.2004 Rustem DZHELYADIN (IHEP, Protvino)

01/09/2004

Magnet assembly doneMoved to working location

(~1500 ton)Connected to supplies

Currently preparing forfield measurement

Ready for detector installin November 2004

5

Status of LHCb construction

VErtex LOcator

06.10.2004 Rustem DZHELYADIN (IHEP, Protvino)

IP

6

Status of LHCb construction

VErtex LOcator

06.10.2004 Rustem DZHELYADIN (IHEP, Protvino)

7

Status of LHCb construction

VErtex LOcator

06.10.2004 Rustem DZHELYADIN (IHEP, Protvino)

VELO mechanicsunder construction

8

Status of LHCb construction

VErtex LOcator

06.10.2004 Rustem DZHELYADIN (IHEP, Protvino)

Final prototype test in 2004Mass production in 2005

-2oC

-7oC

-14oC

-22oC

-25oC

9

Status of LHCb construction

Upstream integration

06.10.2004 Rustem DZHELYADIN (IHEP, Protvino)

TT siliconRICH1

VELO

10

Status of LHCb construction

RICH 1

06.10.2004 Rustem DZHELYADIN (IHEP, Protvino)

Gas enclosure

Beryllium spherical mirrors

Quartz windows

Seal directly to the VELO exit window

Glass secondary plane mirrors (outside the acceptance)

Magnetic shields (each ~8 tonnes of “Armco” iron)

7x14 HPD arrays

Exit windowseals tobeampipe

∫Bdl~0.15 Tm

11

Status of LHCb construction

Silicon Tracker

06.10.2004 Rustem DZHELYADIN (IHEP, Protvino)

Trigger TrackerTTa and TTb ladder structure

Prototype half-ladder under test

12

Status of LHCb construction

Silicon Tracker

06.10.2004 Rustem DZHELYADIN (IHEP, Protvino)

Beam-test lay-out

13

Status of LHCb construction

Inner Tracker

06.10.2004 Rustem DZHELYADIN (IHEP, Protvino)

Finalizing detailsWafer production in 2005

14

Status of LHCb construction

Outer Tracker

06.10.2004 Rustem DZHELYADIN (IHEP, Protvino)

185 F-modules

124 S-modules

Three production facilities operational

15

Status of LHCb construction

Outer Tracker

06.10.2004 Rustem DZHELYADIN (IHEP, Protvino)

Straw tube chamber production site

16

Status of LHCb construction

Outer Tracker

06.10.2004 Rustem DZHELYADIN (IHEP, Protvino)

¼ medium station

Mass production achieve nominal rate at 3 sites,

completion in 2005

17

Status of LHCb construction

RICH 2

06.10.2004 Rustem DZHELYADIN (IHEP, Protvino)

Construction of mechanicsMirrors to be installed soon

18

Status of LHCb construction

RICH 2

06.10.2004 Rustem DZHELYADIN (IHEP, Protvino)

Readout chip

Silicon sensor

Bump-bonding

Packaging

Ceramic carrier

Brazing and gold-plating

HPD encapsulation

Prototype and technology verified484 + spares HPD production started

Hybrid Photo Detector construction

19

Status of LHCb construction

Calorimeters

06.10.2004 Rustem DZHELYADIN (IHEP, Protvino)

Single Particle Detector and

Pre-Shower

Supermodule

MaPMT+VFE

Fiber mapping

20

Status of LHCb construction

Calorimeters (ECAL)

06.10.2004 Rustem DZHELYADIN (IHEP, Protvino)

ECAL – 3300 modules assembly completedUnder cosmic test Preparing for installation in 2005

21

Status of LHCb construction

Calorimeters (ECAL)

06.10.2004 Rustem DZHELYADIN (IHEP, Protvino)

ECAL support construction

22

Status of LHCb construction

Calorimeters (HCAL)

06.10.2004 Rustem DZHELYADIN (IHEP, Protvino)

HCAL modules construction (completion in 2004)

23

Status of LHCb construction

Calorimeters (HCAL)

06.10.2004 Rustem DZHELYADIN (IHEP, Protvino)

HCAL optics assembly

Tiles -12 ton

Fibers – 80 km

Iron – 500 t

24

Status of LHCb construction

Calorimeters (HCAL)

06.10.2004 Rustem DZHELYADIN (IHEP, Protvino)

HCAL support constructionDelivery in 2004

25

Status of LHCb construction

Calorimeters (HCAL)

06.10.2004 Rustem DZHELYADIN (IHEP, Protvino)

HCAL modules (in total 52)• test pile-up of 8 modules• cabling and final test

26

Status of LHCb construction

Muon System

06.10.2004 Rustem DZHELYADIN (IHEP, Protvino)

Muon shield assembly in cavern(completion 2004)

27

R4

R3

R2R1

Status of LHCb construction

Muon System

06.10.2004 Rustem DZHELYADIN (IHEP, Protvino)

Regions in muon station

Beam pipe

5 muon stations4 regions in each

28

Status of LHCb construction

Muon System

06.10.2004 Rustem DZHELYADIN (IHEP, Protvino)

3-GEM

Total: 1368 MWPC + 24 3-GEM + Spares 5 production sites in operation

29

Status of LHCb construction

Muon System

06.10.2004 Rustem DZHELYADIN (IHEP, Protvino)

Muon MWPC production

30

Status of LHCb construction

Muon System

06.10.2004 Rustem DZHELYADIN (IHEP, Protvino)

31

Status of LHCb construction

Summary

06.10.2004 Rustem DZHELYADIN (IHEP, Protvino)

Detector construction is advancing well

Installation schedule • 2004 – magnet, muon shielding• 2005 – calorimeters, RICH, supports• 2006 – trackers, electronics

Meet physics goals with LHC start up in 2007