Upload
dangdan
View
213
Download
0
Embed Size (px)
Citation preview
Bank of Jamaica – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
AAMMEENNDDEEDD
B I D D I N G D O C U M E N T S
Issued on: 11August 2013
for
Structural Repairs to Tower Block
RFP # 2013-10-10-02
Procuring Entity: Bank of Jamaica
Bank of Jamaica – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
TTAABBLLEE OOFF CCOONNTTEENNTTSS
PPAAGGEE NNOOSS..
Acronyms
Glossary
SECTION I. INSTRUCTIONS TO BIDDERS 1
SECTION II. BIDDING DATA SHEET 21
SECTION III. FORMS OF BID, QUALIFICATION INFORMATION,
LETTER OF ACCEPTANCE & AGREEMENT
27
Contractor’s Bid
Qualification Information
Letter of Acceptance
Agreement
SECTION IV. GENERAL CONDITIONS OF CONTRACT 37 Part I – F.I.D.I.C. Conditions of Contract
for Construction – 1999 Edition
SECTION V. PARTICULAR CONDITIONS OF CONTRACT 39 Part II – Conditions of Particular Application
Appendix to Tender
SECTION VI. SPECIFICATIONS & PERFORMANCE REQUIREMENTS 55
SECTION VII. DRAWINGS
SECTION VIII. BILLS OF QUANTITIES
Bank of Jamaica – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
SECTION IX. SECURITY FORMS
Bank of Jamaica – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
Acronyms
BDS Bid Data Sheet
CFR Cost and Freight
CIF Cost, Insurance and Freight
CIP Carriage and Insurance Paid to (named place of destination)
CPM Critical Path Method
CPT Carriage Paid to
CV Curriculum Vitae
DAF Delivery at Frontier
DDP Delivered Duty Paid (named place of destination)
DDU Delivered Duty Unpaid
DES Delivered Ex Ship
DEQ Delivered Ex Quay
EXW Ex factory, ex works or ex warehouse
FAS Free alongside Ship
FCA Free Carrier
FIDIC Fédération Internationale des Ingénieurs Conseils (International Federation
of Consulting Engineers)
FOB Free on Board
GCC General Conditions of Contract
GOJ Government of Jamaica
ICC International Chamber of Commerce
IFB Invitation for Bids
ITB Instructions to Bidders
OT Open Tender
SBD Standard Bidding Document
SCC Special Conditions of Contract
TS Technical Specifications and Drawings
UNCITRAL United Nations Commission on International Trade Law
UNDP United Nation Development Programme
Bank of Jamaica – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
Glossary
Procuring Entity One of the two parties to a works contract, the other party
being the “Contractor.”
Contractor The legal entity that is party to and performs a works
contract, the other party to the contract being the
“Procuring Entity.”
Joint Venture An ad hoc association of firms that pool their resources and
skills to undertake a large or complex contract in the role of
“Contractor,” with all firms (partners in the JV) being
legally liable, jointly and severally, for the execution of the
contract in the event of a partner’s withdrawal.
Management
Contractor
A firm, acting in the role of “Contractor,” that does not
normally perform contract construction work directly, but
manages the work of other (sub) contractors, while bearing
full responsibility and risk for price, quality, and timely
performance of the work contract.
Construction
Manager
A consultant, acting as agent of the Procuring Entity,
engaged to coordinate and monitor the timing of
preparation, bidding award, and execution of a number of
different contracts comprising a project, but does not take
on the responsibility for price, quality, or performance of
those contracts.
Nominated
Sub-Contractor
A specialist enterprise selected and approved by the
Procuring Entity to provide pre-specified works included in
the Bill of Quantities and nominated as subcontractor to the
main Contractor for such purpose.
Post-
Qualification
An assessment made by the Procuring Entity after the
evaluation of bids and immediately prior to award of
contract, to ensure that the lowest responsive Bidder is
qualified to perform the contract in accordance with
previously specified prequalification requirements.
Prequalification An assessment made by the Procuring Entity before inviting
bids, of the appropriate level of experience and capacity of
firms expressing interest in undertaking a particular
contract, before inviting them to bid.
Prime
Contractor
A firm that performs a substantial part of a contract
construction work itself and the balance, if any, by
subcontractors, while bearing full responsibility for the
whole contract.
Bank of Jamaica – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
Provisional Sum A sum included provisionally in the Bill of Quantities of a
contract, normally for a specialized part of the Works or for
contingencies, which sum shall be used only on the
instructions of the Procuring Entity/Engineer for payments
to the contractor and/or to nominated subcontractors.
“Slice and
package”
A procedure whereby a large homogeneous project is sliced
into smaller similar contracts, which are bid simultaneously
so as to attract the interest of both small and large firms;
firms offer bids on individual contracts (slices) or on a group
of similar contracts (packages), and award is made to the
combination of bids offering the lowest cost to the
Procuring Entity. Slices comprising a number of similar
construction units together in a small area are sometimes
referred to as “lots,” which are bid concurrently with other
similar “lots” as part of the larger “package.
Turnover The gross earnings of a firm (in this context, a construction
contractor), defined as the billings for contract work in
progress and/or completed, normally expressed on an
annual basis, and excluding income from other sources.
Works The total work involvement in a construction contract,
including the “Permanent” Works or finished product as
specified, and the “Temporary” Works required in by the
Contractor for the execution and completion of the
contract.
In writing For the purpose of this document, means authenticated
handwritten, typed, or printed; a document prepared in
writing can be transmitted by telex, electronic mail,
facsimile, with proof of receipt; and in the form requested
by the sender.
Section I. Instructions to Bidders: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
SSEECCTTIIOONN II..
IINNSSTTRRUUCCTTIIOONNSS TTOO BBIIDDDDEERRSS
Section I. Instructions to Bidders: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
Table of Clauses
A. General .............................................................................................. 1
1. Scope of Bid ............................................................................ 1
2. Source of Funds ....................................................................... 1
3. Fraud and Corruption ................................................................. 1
4. Eligible Bidders ........................................................................ 3
5. Qualifications of the Bidder ......................................................... 3
6. One Bid per Bidder .................................................................... 6
7. Cost of Bidding ........................................................................ 7
8. Site Visit ................................................................................ 7
B. Bidding Documents ................................................................................ 7
9. Contents of Bidding Documents ..................................................... 7
10. Clarification of Bidding Documents ................................................. 7
11. Amendment of Bidding Documents ................................................. 8
C. Preparation of Bids ................................................................................ 8
12. Language of Bid ....................................................................... 8
13. Documents Comprising the Bid ...................................................... 8
14. Bid Prices ............................................................................... 9
15. Currencies of Bid and Payment ..................................................... 9
16. Bid Validity ............................................................................. 9
17. Bid Security .......................................................................... 10
18. Alternative Proposals by Bidders.................................................. 11
19. Format and Signing of Bid.......................................................... 11
D. Submission of Bids............................................................................... 12
20. Submission, Sealing and Marking of Bids ......................................... 12
21. Deadline for Sub-mission of Bids .................................................. 13
22. Late Bids ............................................................................. 13
23. Withdrawal, Substitution and Modification of Bids ............................. 13
E. Bid Opening and Evaluation ................................................................... 14
24. Bid Opening .......................................................................... 14
25. Confidentiality ....................................................................... 14
26. Clarification of Bids ................................................................. 15
27. Examination of Bids and Determination of Responsiveness ................... 15
28. Correction of Errors ................................................................. 16
29. Currency for Bid Evaluation ....................................................... 16
30. Evaluation and Comparison of Bids ............................................... 16
F. Award of Contract ............................................................................... 18
32. Award Criteria ....................................................................... 17
33. Procuring Entity’s Right to Accept any Bid and to Reject any or all Bids ... 18
34. Notification of Award and Signing of Agreement ............................... 18
35. Performance Security .............................................................. 19
36. Advance Payment and Security ................................................... 20
Section I. Instructions to Bidders: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
1
IINNSSTTRRUUCCTTIIOONNSS TTOO BBIIDDDDEERRSS ((IITTBB))
A. General
1. Scope of Bid 1.1 The Procuring Entity as defined1 in Section II
“Bidding Data Sheet” (BDS), invites bids for the
construction of Works, as described in the BDS and
Section V, “Special Conditions of Contract” (SCC).
The name and identification number of the Contract
are provided in the BDS and the SCC.
1.2 The successful Bidder shall be expected to complete
the Works by the Intended Completion Date specified
in the BDS and SCC 1.1 (r).
1.3 Throughout these Bidding Documents:
(a) the term “in writing” means communicated in
written form (e.g. by mail, e-mail, fax, telex, )
with proof of receipt;
(b) if the context so requires, “singular” means
“plural” and vice versa; and
(c) “day” means calendar day.
2. Source of
Funds
2.1 The Procuring Entity has committed funds toward the
cost of the project and intends to apply a portion of the
funds to eligible payments under the contract;
3. Fraud and
Corruption
3.1 Government of Jamaica requires that Bidders,
Suppliers, Contractors, and Consultants, observe the
highest standard of ethics during the procurement and
execution of such contracts. In pursuit of this policy,
GOJ:
(a) defines, for the purposes of this provision, the
terms set forth below as follows:
(i) “corrupt practice” means the offering,
giving, receiving, or soliciting, directly or
indirectly, of anything of value to influence
the action of a public official in the
procurement process or in contract
execution;
1 See Section IV, “General Conditions of Contract,” Clause 1. Definitions.
Section I. Instructions to Bidders: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
2
(ii) “fraudulent practice” means a
misrepresentation or omission of facts in
order to influence a procurement process
or the execution of a contract to the
detriment of Government of Jamaica and
includes collusive practice among bidders
(prior to or after bid submission) designed
to establish bid prices at artificial non-
competitive levels and to deprive
Government of the benefits of free and
open competition;
(iii) “collusive practice” means a scheme or
arrangement between two or more bidders,
with or without the knowledge of the
Procuring Entity, designed to establish bid
prices at artificial non-competitive levels or
to influence the action of any party in the
procurement process or the execution of a
contract; and
(iv) “coercive practice” means harming or
threatening to harm, directly or indirectly,
persons or their property to influence their
participation in the procurement process or
affect the execution of a contract;
(b) will reject a proposal for award if it determines
that the Bidder recommended for award has,
directly or through an agent, engaged in corrupt,
fraudulent, collusive or coercive practices in
competing for the Contract in question;
(c) will sanction a firm or individual, including
declaring them ineligible, either indefinitely or
for a stated period of time, to be awarded a GOJ-
financed contract if it at any time determines
that they have, directly or through an agent,
engaged, in corrupt, fraudulent, collusive or
coercive practices in competing for, or in
executing, a GOJ-financed contract; and
(d) will have the right to require that a provision be
included in Bidding Documents and in contracts
financed by a GOJ, requiring bidders, suppliers,
contractors and consultants to permit GOJ to
inspect their accounts and records and other
Section I. Instructions to Bidders: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
3
documents relating to the Bid submission and
contract performance and to have them audited
by auditors appointed by the GOJ.
4. Eligible
Bidders
4.1 A Bidder, and all parties constituting the Bidder, may
have the nationality of any country. A Bidder shall
be deemed to have the nationality of a country if the
Bidder is a citizen or is constituted, incorporated, or
registered and operates in conformity with the
provisions of the laws of that country. This criterion
shall also apply to the determination of the
nationality of proposed subcontractors.
4.2 A Bidder shall not have a conflict of interest. All
Bidders found to have conflict of interest shall be
disqualified. Bidders may be considered to have a
conflict of interest with one or more parties in this
bidding process, if they are associated, or has been
associated in the past, directly or indirectly, with the
consultant or any other entity that has prepared the
design, specifications, and other documents for the
Project or being proposed as Project Manager for the
Contract. A firm that has been engaged by the
Procuring Entity to provide consulting services for the
preparation or supervision of the Works, and any of
its affiliates shall not be eligible to bid.
4.3 In accordance with the Government of Jamaica
Handbook of Public Sector Procurement Procedures
November, 2008 (http://www.mof.gov.jm) the
Bidder shall have to demonstrate that they have paid
such taxes, duties, fees and other impositions as may
be levied in Jamaica.
4.4 Where deemed necessary, the bidders should be
registered with the National Contracts Commission
“Registry of Public Sector Contractors”
(http://www.ocg.gov.jm).
5. Qualifications
of the Bidder
5.1 All bidders shall provide in Section III, “Form of Bid,
Qualification Information, Letter of Acceptance, and
Agreement,” a preliminary description of the proposed
work method and schedule, including drawings and
charts, as necessary.
5.2 In the event that prequalification of potential
bidders has been undertaken, only bids from pre-
qualified bidders shall be considered for award of
Section I. Instructions to Bidders: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
4
Contract. These qualified bidders should submit with
their bids any information updating their original
prequalification applications or, alternatively,
confirm in their bids that the originally submitted
prequalification information remains essentially
correct as of the date of bid submission. The update
or confirmation should be provided in Section III.
5.3 If the Procuring Entity has not undertaken
prequalification of potential bidders, all bidders shall
include the following information and documents
with their bids in Section III, unless otherwise stated
in the BDS:
(a) copies of original documents defining the
constitution or legal status, place of registration,
and principal place of business of the Bidder;
written power of attorney of the signatory of the
Bid to commit the Bidder;
(b) total monetary value of construction works
performed for each of the last five years;
(c) experience in works of a similar nature and size
for each of the last five years, and details of
work under way or contractually committed;
and clients who may be contacted for further
information on those contracts;
(d) major items of construction equipment
proposed to carry out the Contract;
(e) qualifications and experience of key site
management and technical personnel proposed
for the Contract;
(f) reports on the financial standing of the Bidder,
such as profit and loss statements and auditor’s
reports for the past five years;
(g) evidence of adequacy of working capital for this
Contract (access to line(s) of credit and
availability of other financial resources);
(h) authority to seek references from the Bidder’s
bankers;
(i) information regarding any litigation, current or
during the last five years, in which the Bidder
was/is involved, the parties concerned, and the
disputed amounts; and awards;
Section I. Instructions to Bidders: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
5
[N.B. The Procuring Entity reserves the right not to
award a contract to any party with whom it is
currently in litigation or with whom it has been
previously involved in litigation];
(j) proposals for subcontracting components of the
Works amounting to more than 10 percent of the
Contract Price. The ceiling for sub contractor's
participation is stated in the BDS.
5.4 Bids submitted by a joint venture of two or more
firms as partners shall comply with the following
requirements, unless otherwise stated in the BDS:
(a) the Bid shall include all the information listed in
ITB Sub-Clause 5.3 above for each joint venture
partner;
(b) the Bid shall be signed so as to be legally
binding on all partners;
(c) all partners shall be jointly and severally liable
for the execution of the Contract in accordance
with the Contract terms;
(d) one of the partners shall be nominated as being
in charge, authorized to incur liabilities, and
receive instructions for and on behalf of any and
all partners of the joint venture; and
(e) the execution of the entire Contract, including
payment, shall be done exclusively with the
partner in charge.
(f) a copy of the Joint venture Agreement entered
into by the partners shall be submitted with the
bid; or a Letter of Intent to execute a joint
venture agreement in the event of a successful
bid shall be signed by all partners and submitted
with the bid, together with a copy of the
proposed Agreement.
5.5 To qualify for award of the Contract, bidders shall
meet the following minimum qualifying criteria
(a) an average annual financial amount of
construction work over the period specified in
the BDS of at least the multiple indicated in the
BDS
Section I. Instructions to Bidders: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
6
(b) experience as prime contractor in the
construction of at least the number of works of
a nature and complexity equivalent to the
Works over the period specified in the BDS (to
comply with this requirement, works cited
should be at least 70 percent complete);
(c) proposals for the timely acquisition (own, lease,
hire, etc.) of the essential equipment listed in
the BDS;
(d) a Contract Manager with five years’ experience
in works of an equivalent nature and volume,
including no less than three years as Manager;
and
(e) liquid assets and/or credit facilities, net of
other contractual commitments and exclusive of
any advance payments which may be made
under the Contract, of no less than the amount
specified in the BDS.2
A consistent history of litigation or arbitration awards
against the Applicant or any partner of a Joint
Venture may result in disqualification.
5.6 The figures for each of the partners of a joint
venture shall be added together to determine the
Bidder’s compliance with the minimum qualifying
criteria of ITB Sub-Clauses 5.5 (a) and (e); however,
for a joint venture to qualify, each of its partners
must meet at least 25 percent of minimum criteria of
ITB Sub-Clauses 5.5 (a), (b), and (e) for an individual
Bidder, and the partner in charge at least 40 percent
of those minimum criteria. Failure to comply with
this requirement shall result in rejection of the joint
venture’s Bid. Subcontractors’ experiences and
resources shall not be taken into account in
determining the Bidder’s compliance with the
qualifying criteria, unless otherwise stated in the
BDS.
6. One Bid per
Bidder
6.1 Each Bidder shall submit only one Bid, either
individually or as a partner in a joint venture. A
Bidder who submits or participates in more than one
2 Usually the equivalent of the estimated payments flow over 4-6 months at the average (straight line distribution)
construction rate. The actual period of reference shall depend on the speed with which the Procuring Entity shall
pay the Contractor’s monthly certificates.
Section I. Instructions to Bidders: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
7
Bid (other than as a subcontractor or in cases of
alternatives that have been permitted or requested)
shall cause all the proposals with the Bidder’s
participation to be disqualified.
7. Cost of
Bidding
7.1 The Bidder shall bear all costs associated with the
preparation and submission of his Bid, and the
Procuring Entity shall in no case be responsible or
liable for those costs.
8. Site Visit 8.1 The Bidder, at the Bidder’s own responsibility and
risk, is encouraged to visit and examine the Site of
Works and its surroundings and obtain all information
that may be necessary for preparing the Bid and
entering into a contract for construction of the
Works. The costs of visiting the Site shall be at the
Bidder’s own expense.
B. Bidding Documents
9. Contents of
Bidding
Documents
9.1 The set of Bidding Documents comprises the
documents listed in the table below and addenda
issued in accordance with ITB Clause 11:
Invitation for Bids
Section I Instructions to Bidders
Section II Bidding Data Sheet
Section III Forms of Bid, Qualification
Information, Letter of acceptance,
Agreement
Section IV General Conditions of Contract
Section V Particular Conditions of Contract
Section VI Specifications
Section VII Drawings
Section VIII Bill of Quantities3
Section IX Forms of Securities
10.Clarification
of Bidding
Documents
10.1 A prospective Bidder requiring any clarification of
the Bidding Documents may notify the Procuring
Entity in writing at the Procuring Entity’s address
indicated in the BDS. The Procuring Entity shall
respond to any request for clarification received
3 In lump sum contracts, delete “Bill of Quantities” and replace with “Activity Schedule”.
Section I. Instructions to Bidders: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
8
earlier than 21 days4 prior to the deadline for
submission of bids. Copies of the Procuring Entity’s
response shall be forwarded to all purchasers of the
Bidding Documents, including a description of the
inquiry, but without identifying its source.
11. Amendment
of Bidding
Documents
11.1 Before the deadline for submission of bids, the
Procuring Entity may modify the Bidding Documents
by issuing addenda.
11.2 Any addendum thus issued shall be part of the
Bidding Documents and shall be communicated in
writing to all purchasers of the Bidding Documents.5
Prospective bidders shall acknowledge receipt of
each addendum in writing to the Procuring Entity.
11.3 To give prospective bidders reasonable time in which
to take an addendum into account in preparing their
bids, the Procuring Entity shall extend, as necessary,
the deadline for submission of bids, in accordance
with ITB Sub-Clause 21.2 below.
C. Preparation of Bids
12. Language
of Bid
12.1 All documents relating to the Bid shall be in the
language specified in the BDS.
13.Documents
Comprising
the Bid
13.1 The Bid submitted by the Bidder shall comprise the
following:
(a) The Bid (in the format indicated in Section III);
(b) Bid Security in accordance with ITB Clause 17, if
required;
(c) priced Bill of Quantities;6
(d) Qualification Information Form and Documents;
(e) Alternative offers where invited;
and any other materials required to be completed
4 It may be necessary to extend the deadline for submission of bids if the Procuring Entity’s response results in
substantial changes to the Bidding Documents. See ITB Clause 11 below. 5 It is therefore important that the Procuring Entity maintain a complete and accurate list of recipients of the Bidding
Documents and their addresses. 6 In lump sum contracts, delete “priced Bill of Quantities” and replace with “priced Activity Schedule.”
Section I. Instructions to Bidders: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
9
and submitted by bidders, as specified in the BDS.
14. Bid Prices 14.1 The Contract shall be for the whole Works, as
described in ITB Sub-Clause 1.1, based on the priced
Bill of Quantities7 submitted by the Bidder.
14.2 The Bidder shall fill in rates and prices for all items
of the Works described in the Bill of Quantities.8
Items for which no rate or price is entered by the
Bidder shall not be paid for by the Procuring Entity
when executed and shall be deemed covered by the
other rates and prices in the Bill of Quantities.
Corrections, if any, shall be made by crossing out,
initialing, dating and rewriting.
14.3 All duties, taxes, and other levies payable by the
Contractor under the Contract, or for any other
cause, as of the date 28 days prior to the deadline
for submission of bids, shall be included in the rates,
prices, and total Bid price submitted by the Bidder.9
14.4 The rates and prices10 quoted by the Bidder shall be
subject to adjustment during the performance of the
Contract if provided for in the BDS and SCC and the
provisions of Clause 47 of the General Conditions of
Contract. The Bidder shall submit with the Bid all
the information required under the Special
Conditions of Contract and GCC Clause 47.
15. Currencies
of Bid and
Payment
15.1 The currency(cies) of the bid shall be, as specified in
the BDS.
15.2 Bidders may be required by the Procuring Entity to
clarify their foreign currency requirements and to
substantiate that the amounts included in the rates and
prices,11 if required in the BDS, are reasonable and
responsive to ITB Sub-Clause 15.1.
16. Bid
Validity
16.1 Bids shall remain valid for the period12 specified in
the BDS.
16.2 In exceptional circumstances, the Procuring Entity
7 In lump sum contracts, delete “priced Bill of Quantities” and replace with “priced Activity Schedule.”
8 In lump sum contracts, delete “described in the Bill of Quantities” and replace with “described in the drawings and
specifications and listed in the Activity Schedule.” 9 In lump sum contracts, delete “rates, prices, and.”
10 In lump sum contracts, delete “rates and prices” and replace with “lump sum price.”
11 For lump sum contracts, delete “rates and prices” and replace with “Lump Sum.”
12 The period is a realistic time, usually not less than 35 days nor more than 105, allowing for bid evaluation,
clarifications, and Cabinet’s “no objection” (where awards of Contract are subject to prior review).
Section I. Instructions to Bidders: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
10
may request that the bidders extend the period of
validity for a specified additional period. The
request and the bidders’ responses shall be made in
writing. If a Bid Security is requested in accordance
with ITB Clause 17. A Bidder may refuse the request
without forfeiting the Bid Security. A Bidder
agreeing to the request shall not be required or
permitted to modify its Bid, except as provided in
ITB Clause 17.
17.Bid Security 17.1 If required in the BDS, the Bidder shall furnish as part
of its Bid, a Bid Security in original form as specified in
the BDS.
17.2 The bid security shall be a demand guarantee at the
Bidder’s option, in any of the following forms:
(a) an unconditional bank guarantee;
(b) an irrevocable letter of credit;
(c) a cashier’s or certified check; or
(d) another security indicated in the BDS,
17.3 If a Bid Security is required in accordance with ITB Sub-
Clause 17.1, any bid not accompanied by a Bid Security
in accordance with ITB Sub-Clause 17.1, shall be
rejected by the Procuring Entity as non-responsive.
17.4 The Bid Security of unsuccessful Bidders shall be
returned as promptly as possible upon the successful
Bidder’s furnishing of the performance security.
17.5 The Bid Security may be forfeited:
(a) if a Bidder withdraws its bid during the period
of bid validity specified by the Bidder on the Bid
Submission Sheet, except as provided in ITB
Sub-Clause 16.2; or
(b) if the Bidder does not accept the correction of
its Bid Price pursuant to ITB Sub-Clause 28.
(c) if the successful Bidder fails within the specified
time to:
(i) sign the Contract; or
(ii) furnish the required performance
Section I. Instructions to Bidders: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
11
security.
17.6 The Bid Security of a JV must be in the name of the
JV that submits the bid. If the JV has not been legally
constituted at the time of bidding, the Bid Security
shall be in the names of all future partners as named
in the letter of intent.
18. Alternative
Proposals by
Bidders
18.1 Alternatives shall not be considered, unless
specifically allowed in the BDS. If so allowed, ITB
Sub-Clauses 18.1 and 18.2 shall govern.
18.2 A bidder may submit an alternative bid with or
without a bid for the base case. All bids received,
for the base case, as well as alternative bids
meeting the technical specifications and
performance requirements pursuant to Section VI,
shall be evaluated on their own merits.
18.3 Alternative bids shall provide all information
necessary for a complete evaluation of the
alternative by the Procuring Entity, including design
calculations, technical specifications, breakdown of
prices, proposed construction methods and other
relevant details.
19. Format
and Signing of
Bid
19.1 The Bidder shall prepare one original of the
documents comprising the Bid as described in ITB
Clause 13, bound with the volume containing the
Form of Bid, and clearly marked “ORIGINAL”. In
addition, the Bidder shall submit copies of the Bid, in
the number specified in the BDS, and clearly marked
as “COPIES”. In the event of discrepancy between
them, the original shall prevail.
19.2 The original and all copies of the Bid shall be typed
or written in indelible ink and shall be signed by a
person or persons duly authorized to sign on behalf of
the Bidder, pursuant to ITB Sub-Clause 5.3 (a). All
pages of the Bid where entries or amendments have
been made shall be initialled by the person or
persons signing the Bid.
19.3 The Bid shall contain no alterations or additions,
except those to comply with instructions issued by
the Procuring Entity, or as necessary to correct errors
made by the Bidder, in which case such corrections
shall be initialled by the person or persons signing
Section I. Instructions to Bidders: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
12
the Bid.
19.4 The Bidder shall furnish information as described in
the Form of Bid on commissions or gratuities, if any,
paid or to be paid to agents relating to this Bid, and
to contract execution if the Bidder is awarded the
contract.
D. Submission of Bids
20. Submission,
Sealing and
Marking of
Bids
20.1 Bidders may always submit their bids by mail or by
hand. When so specified in the BDS, bidders shall
have the option of submitting their bids
electronically. Bidders submitting bids electronically
shall follow the procedures specified in the BDS. The
Bidder shall seal the original and all copies of the Bid
in two inner envelopes and one outer envelope, duly
marking the inner envelopes as “ORIGINAL” and
“COPIES”.
20.2 The inner and outer envelopes shall
(a) be addressed to the Procuring Entity at the
address13 provided in the BDS;
(b) bear the name and identification number of the
Contract as defined in the BDS and SCC; and
(c) provide a warning not to open before the
specified time and date for Bid opening as
defined in the BDS.
20.3 In addition to the identification required in ITB Sub-
Clause 20.2, the inner envelopes shall indicate the
name and address of the Bidder to enable the Bid to
be returned unopened in case it is declared late,
pursuant to ITB Clause 22.
20.4 If the outer envelope is not sealed and marked as
above, the Procuring Entity shall assume no
responsibility for the misplacement or premature
opening of the Bid.
20.5 The Proposals shall be deposited in the TENDER BOX
13
The receiving address should be an office that is staffed during normal working hours by personnel authorized to
certify time and date of receipt and assure safekeeping until Bid opening. A post office address is not satisfactory.
The address must be the same as the receiving address described in the Invitation for Bids.
Section I. Instructions to Bidders: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
13
provided at the address specified in the BDS.
21. Deadline
for
Submission of
Bids
21.1 Bids shall be delivered to the Procuring Entity at the
address specified above no later than the time and
date specified in the BDS.
21.2 The Procuring Entity may extend the deadline for
submission of bids by issuing an amendment in
accordance with ITB Clause 11, in which case all
rights and obligations of the Procuring Entity and the
bidders previously subject to the original deadline
shall then be subject to the new deadline.
22. Late Bids 22.1 Any Bid received by the Procuring Entity after the
deadline prescribed in ITB Clause 21 shall be
returned unopened to the Bidder.
23.Withdrawal,
Substitution
and
Modification
of Bids
23.1 Bidders may withdraw, substitute or modify their
Bids by giving notice in writing before the deadline
prescribed in ITB Clause 21.
23.2 Each Bidder’s withdrawal, substitution or
modification notice shall be prepared, sealed,
marked, and delivered in accordance with ITB
Clauses 19 and 20, with the outer and inner
envelopes additionally marked or “WITHDRAWAL,”
“SUBSTITUTION,” OR “MODIFICATION” as appropriate.
23.3 No Bid may be substituted or modified after the
deadline for submission of Bids.
23.4 Withdrawal of a Bid between the deadline for
submission of bids and the expiration of the period of
Bid validity specified in the Bidding Data or as
extended pursuant to ITB Sub-Clause 16.2 may result
in the forfeiture of the Bid Security pursuant to ITB
Clause 17.
23.5 Bidders may only offer discounts to, or otherwise
modify the prices of their bids, by submitting Bid
modifications in accordance with this clause or
included in the initial Bid
Section I. Instructions to Bidders: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
14
E. Bid Opening and Evaluation
24. Bid
Opening
24.1 The Procuring Entity shall open the bids, including
modifications made pursuant to Clause 23, in the
presence of the bidders’ representatives who choose
to attend at the time and in the place specified in
the BDS. Any specific opening procedures required if
electronic bidding is permitted in accordance with
ITB Sub-Clause 20.1, shall be as specified in the BDS.
24.2 Envelopes marked “WITHDRAWAL” shall be opened
and read out first. Bids for which an acceptable
notice of withdrawal has been submitted pursuant to
ITB Clause 23 shall not be opened.
24.3 The bidders’ names, the Bid prices, the total
amount of each Bid and of any alternative Bid (if
alternatives have been requested or permitted), any
discounts, Bid withdrawals, substitutions, or
modifications, the presence or absence of Bid
Security if required, and such other details as the
Procuring Entity may consider appropriate, shall be
announced by the Procuring Entity at the opening.
No bid shall be rejected at bid opening except for
the late bids pursuant to ITB Clause 22. Substitution
Bids and modifications submitted pursuant to ITB
Clause 23 that are not opened and read out at bid
opening shall not be considered for further
evaluation regardless of the circumstances. Late,
withdrawn and substituted bids shall be returned un-
opened to bidders
24.4 The Procuring Entity shall prepare Minutes of the Bid
Opening, including the information disclosed, to
those present, in accordance with ITB Sub-Clause
24.3.14
25.
Confidentiality
25.1 Information relating to the Examination,
Clarification, Evaluation, and Comparison of Bids
and Recommendations for the Award of a contract
shall not be disclosed to bidders or any other
persons not officially concerned with such process
until publication of the award to the successful
Bidder has been announced pursuant to ITB Sub-
Clause 34.4. Any effort by a Bidder to influence the
14
A copy of the minutes should be sent by the Procuring Entity to the National Contracts Commission together with
the Bid evaluation report, for contracts subject to prior review.
Section I. Instructions to Bidders: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
15
Procuring Entity’s processing of bids or award
decisions may result in the rejection of its Bid.
Notwithstanding the above, from the time of bid
opening to the time of Contract award, if any Bidder
wishes to contact the Purchaser on any matter
related to the bidding process, it should do so in
writing.
26. Clarification
of Bids
26.1 To assist in the examination, evaluation, and
comparison of Bids, the Procuring Entity may, at the
Procuring Entity’s discretion, ask any Bidder for
clarification of the Bidder’s Bid, including
breakdowns of unit rates.15 The request for
clarification and the response shall be in writing,
but no change in the price or substance of the Bid
shall be sought, offered, or permitted except as
required to confirm the correction of arithmetic
errors discovered by the Procuring Entity in the
evaluation of the Bids in accordance with ITB Clause
28.
27. Examination
of Bids and
Determination
of
Responsiveness
27.1 Prior to the detailed evaluation of Bids, the
Procuring Entity shall determine whether each Bid
(a) meets the eligibility criteria defined in ITB
Clause 4; (b) has been properly signed; (c) is
accompanied by the Security, if required; and (d) is
substantially responsive to the requirements of the
Bidding Documents.
27.2 A substantially responsive Bid is one which conforms
to all the terms, conditions, and specifications of
the Bidding Documents, without material deviation
or reservation. A material deviation or reservation
is one (a) which affects in any substantial way the
scope, quality, or performance of the Works; (b)
which limits in any substantial way, inconsistent
with the Bidding Documents, the Procuring Entity’s
rights or the Bidder’s obligations under the
Contract; or (c) whose rectification would affect
unfairly the competitive position of other bidders
presenting substantially responsive bids.
27.3 If a Bid is not substantially responsive, it shall be
rejected by the Procuring Entity, and may not
subsequently be made responsive by correction or
withdrawal of the nonconforming deviation or
15
In lump sum contracts, delete “unit rates” and replace with “the prices in the Activity Schedule.”
Section I. Instructions to Bidders: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
16
reservation.
28. Correction
of Errors
28.1 Bids determined to be substantially responsive shall
be checked by the Procuring Entity for any
arithmetic errors. Errors shall be corrected by the
Procuring Entity as follows:16
(a) where there is a discrepancy between the
amounts in figures and in words, the amount in
words shall govern; and
(b) where there is a discrepancy between the unit
rate and the line item total resulting from
multiplying the unit rate by the quantity, the
unit rate as quoted shall govern, unless in the
opinion of the Procuring Entity there is an
obviously gross misplacement of the decimal
point in the unit rate, in which case the line
item total as quoted shall govern, and the unit
rate shall be corrected.
28.2 The amount stated in the Bid shall be adjusted by
the Procuring Entity in accordance with the above
procedure for the correction of errors and, with the
concurrence of the Bidder, shall be considered as
binding upon the Bidder. If the Bidder does not
accept the corrected amount, the Bid shall be
rejected, and the Bid Security may be forfeited in
accordance with ITB Sub-Clause 17.5 (b).
29. Currency
for Bid
Evaluation
29.1 Bids shall be evaluated as quoted in the currency of
the Procuring Entity’s Country in accordance with
ITB Sub-Clause 15.1, unless a Bidder has used
different exchange rates than those prescribed in
ITB Sub-Clause 15.2, in which case the Bid shall be
first converted into the amounts payable in different
currencies using the rates quoted in the Bid and
then reconverted to the Procuring Entity’s currency
using the exchange rates prescribed in ITB Sub-
Clause 15.2.
30. Evaluation
and
Comparison
of Bids
30.1 The Procuring Entity shall evaluate and compare
only the bids determined to be substantially
responsive in accordance with ITB Clause 27.
30.2 In evaluating the bids, the Procuring Entity shall
16
In lump sum contracts, delete from “as follows” to the end, and replace with the following: “as follows: where
there is a discrepancy between the amounts in figures and in words, the amount in words shall govern.”
Section I. Instructions to Bidders: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
17
determine for each Bid the evaluated Bid price by
adjusting the Bid price as follows:
(a) making any correction for errors pursuant to
ITB Clause 28;
(b) excluding provisional sums and the provision, if
any, for contingencies in the Bill of
Quantities,17 but including Daywork,18 where
priced competitively;
(c) making an appropriate adjustment for any
other acceptable variations, deviations, or
alternative offers submitted in accordance with
ITB Clause 18; and
(d) making appropriate adjustments to reflect
discounts or other price modifications offered
in accordance with ITB Sub-Clause 23.5.
30.3 The Procuring Entity reserves the right to accept or
reject any variation, deviation, or alternative offer.
Variations, deviations, and alternative offers and
other factors which are in excess of the
requirements of the Bidding Documents or otherwise
result in unsolicited benefits for the Procuring Entity
shall not be taken into account in Bid evaluation.
30.4 The estimated effect of any price adjustment
conditions under GCC Clause 47, during the period of
implementation of the Contract, shall not be taken
into account in Bid evaluation.
30.519 In the case of several lots, pursuant to ITB Sub-
Clause 30.2 (d), the Procuring Entity shall determine
the application of discounts so as to minimize the
combined cost of all the lots.
32. Award
Criteria
32.1 Subject to ITB Clause 33, the Procuring Entity shall
award the Contract to the Bidder whose Bid has been
determined to be substantially responsive to the
17
In lump sum contracts, delete “Bill of Quantities” and replace with “Activity Schedule.” 18
Daywork is work carried out following instructions of the Project Manager and paid for on the basis of time spent
by workers, and the use of materials and the Contractor’s equipment, at the rates quoted in the Bid. For Daywork
to be priced competitively for Bid evaluation purposes, the Procuring Entity must list tentative quantities for
individual items to be costed against Daywork (e.g., a specific number of tractor driver staff-days, or a specific
tonnage of Portland cement), to be multiplied by the bidders’ quoted rates and included in the total Bid price. 19
If the Bidding Documents include two or more lots, add ITB Sub-Clause 30.5: “In the case of several lots, pursuant
to ITB Sub-Clause 30.2 (d), the Procuring Entity shall determine the application of discounts so as to minimize the
combined cost of all the lots.”
Section I. Instructions to Bidders: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
18
Bidding Documents and who has offered the lowest
evaluated Bid price, provided that such Bidder has
been determined to be (a) eligible in accordance
with the provisions of ITB Clause 4, and (b) qualified
in accordance with the provisions of ITB Clause 5.
33. Procuring
Entity’s Right
to Accept any
Bid and to
Reject any or
all Bids
33.1 Notwithstanding ITB Clause 32, the Procuring Entity
reserves the right to accept or reject any Bid, and to
cancel the bidding process and reject all bids, at any
time prior to the award of Contract, without thereby
incurring any liability to the affected Bidder or
bidders or any obligation to inform the affected
Bidder or bidders of the grounds for the Procuring
Entity’s action.20
N.B. The Procuring Entity reserves the right not to award a contract to any party with
whom it is currently in litigation or with whom it has been previously involved in
litigation.
F. Award of Contract
34. Notification
of Award and
Signing of
Agreement
34.1 The Bidder whose Bid has been accepted shall be
notified of the award by the Procuring Entity prior to
expiration of the Bid validity period in writing. This
letter (hereinafter and in the GCC called the “Letter
of Acceptance”) shall state the sum that the
Procuring Entity shall pay the Contractor in
consideration of the execution, completion, and
maintenance of the Works by the Contractor as
prescribed by the Contract (hereinafter and in the
Contract called the “Contract Price”).
34.2 The Letter of Acceptance shall constitute the
formation of the Contract, subject to the Bidder
furnishing the Performance Security in accordance
with ITB Clause 35 and signing the Agreement in
accordance with ITB Sub-Clause 34.3.
34.3 The Agreement shall incorporate all agreements
between the Procuring Entity and the successful
Bidder. It shall be signed by the Procuring Entity and
20
Procuring Entitys shall not reject bids or annul bidding processes, except as permitted in the Procurement
Guidelines.
Section I. Instructions to Bidders: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
19
sent to the successful Bidder, within 28 days
following the Letter of Acceptance’s date. Within 21
days of receipt, the successful Bidder shall sign the
Agreement and deliver it to the Procuring Entity.
34.4 The Procuring Entity shall promptly respond in
writing to any unsuccessful Bidder who, after
publication of contract award requests the Procuring
Entity in writing to explain on which grounds its bid
was not selected. Prior to the expiration of the
period of bid validity, the Procuring Entity shall
notify the successful Bidder, in writing, that its bid
has been accepted. The notification letter
(hereinafter and in the Conditions of Contract and
Contract Forms called the “Letter of Acceptance”)
shall specify the sum that the Procuring Entity will
pay the Contractor in consideration of the execution
and completion of the Services (hereinafter and in
the Conditions of Contract and Contract Forms called
“the Contract Price”) and the requirement for the
Contractor to remedy any defects therein as
prescribed by the Contract. At the same time,
the Procuring Entity shall inform all unsuccessful
bidders and shall publish the name of the winning
Bidder, and the Price it offered, as well as the duration
and summary scope of the contract awarded.
35.Performance
Security
35.1 Within 21 days after receipt of the Letter of
Acceptance, the successful Bidder shall sign the
contract and deliver to the Procuring Entity a
Performance Security in the amount stipulated in the
GCC and in the form (Bank Guarantee or Bond)
stipulated in the BDS, denominated in the type and
proportions of currencies in the Letter of Acceptance
and in accordance with the GCC.
35.2 If the Performance Security is provided by the
successful Bidder in the form of a Bank Guarantee, it
shall be issued at the Bidder’s option, by a bank
located in the country of the Procuring Entity, or by
a foreign bank acceptable to the Procuring Entity
through a correspondent bank located in the
Procuring Entity’s country.
35.3 If the Performance Security is to be provided by the
successful Bidder in the form of a Bond, it shall be
issued by a surety which the Bidder has determined
Section I. Instructions to Bidders: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
20
to be acceptable to the Procuring Entity.
35.4 Failure of the successful Bidder to comply with the
requirements of ITB Sub-Clauses 35.1 and 34.3 shall
constitute sufficient grounds for cancellation of the
award and forfeiture of the Bid Security. Upon the
successful Bidder’s, signing of the Agreement and
furnishing of the Performance Security pursuant to
ITB Clause 35.1, the Procuring Entity shall promptly
notify the name of the winning bidder to each
unsuccessful bidder and shall discharge the Bid
Securities of the unsuccessful bidders pursuant to ITB
Clause 17.4.
36. Advance
Payment and
Security
36.1 The Procuring Entity shall provide an Advance
Payment on the Contract Price as stipulated in the
GCC, subject to a maximum amount, as stated in the
BDS. The Advance Payment shall be guaranteed by a
Security. Section IX “Security Forms” provides a Bank
Guarantee for Advance Payment form.
Section II. Bidding Data Sheet: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
SSEECCTTIIOONN IIII..
BBIIDDDDIINNGG DDAATTAA SSHHEEEETT
Section II. Bidding Data Sheet: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
BBiiddddiinngg DDaattaa SShheeeett2211
A. General
ITB 1.1
The Procuring Entity is Bank of Jamaica.
Description of the works are as follows:
The facades of the Bank of Jamaica (BOJ) Tower have deteriorated
resulting in spalling and cracking of concrete, exposure of
reinforcement, corrosion of reinforcement and other damaging
effects. The proposed works include the removal of damaged
concrete, corroded reinforcement, placement of new concrete
with additives, placement of new reinforcement and resealing of
the external windows. The Specifications and the Bills of
Quantities describe the works to be performed.
The name and identification of the contract are Structural
Repairs to Tower Block RFP # 2013-10-10-03
ITB 1.2 The Intended Completion Date is 200 days after the
commencement of the works.
ITB 2.1 The Project is Structural Repairs to Tower Block.
ITB 4.3 At the time of the tender the bidder shall present to the Procuring
Entity a valid Tax Compliance Certificate for due taxes in Jamaica.
Overseas bidders will be required to obtain a valid Tax Compliance
Certificate if they are selected for contract award and where any
aspect of the contract will require work to be done in Jamaica.
ITB 4.4 At the time of contract award, if indicated herein in ITB 4.4 below,
the bidder must be registered with the National Contracts
Commission “Register of Public Sector Contractors”.
Under the National Contracts Commission “Register of Public
Sector Contractors”, the required registration grade is: Grade 1 in the category of Civil Engineering or Building Construction.
For more information: http://www.ocg.gov.jm
Failure to submit the above information shall result in the
rejection of the bid.
21
This section should be filled out by the Procuring Entity before issuance of the Bidding Documents.
Section II. Bidding Data Sheet: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
3
ITB 5.322 The information required from bidders in ITB Sub-Clause 5.3 is
modified as follows:
NONE
ITB 5.3 (j) The ceiling for sub contractor's participation is:
20%
ITB 5.4 The qualification data required from bidders in ITB Sub-Clause 5.4
are modified as follows:
NONE
ITB 5.5 The qualification criteria in ITB Sub-Clause 5.5 are modified as
follows:
NONE
ITB 5.5 (a) The multiple is: TWO (2)
The period is: FIVE (5) YEARS
ITB 5.5 (b) The number is: TWO (2)
The period is: FIVE (5) YEARS
22
Delete if prequalification has been conducted.
Section II. Bidding Data Sheet: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
4
ITB 5.5 (c) The essential equipment to be made available for the Contract by
the successful Bidder shall be:
o Cranes
o Hoists
o Concrete Mixers
o Concrete Pumps
ITB 5.5 (e)23 The minimum amount of liquid assets and/or credit facilities net of
other contractual commitments of the successful Bidder shall be
$40,000,000.00
ITB 5.6
Subcontractors’ experience and resources shall be taken into
account.
ITB 8.1 The Bidder is required to attend a mandatory site visit at the BOJ,
Nethersole Place Building, Kingston on Tuesday, 03 September 2013
at 10:00 a.m. The cost of visiting this site is to be borne solely by
the Bidder.
Arrangements are to be made with Miss Sian, Mr. Paul Blake at 922-
0750-9 extensions 2402 or 2421 respectively.
The Bidder is assumed to be obtaining for its own interest, all
information that may be deemed necessary for preparing the tender.
BOJ takes no responsibility in respect of any injury, loss of or
damage to property and any other loss however caused, which
might be seen to be the result of the exercise of such permission
to visit the site.
B. Bidding Documents
ITB 10.1 The Procuring Entity’s address for clarification is:
Procurement Administration Section
Bank of Jamaica
Nethersole Place
Kingston, Jamaica
Attention:
Email address: [email protected]
23
Delete if prequalification has been conducted.
Section II. Bidding Data Sheet: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
5
All enquiries regarding the RFP shall be made by: Friday, 6
September 2013.
Responses to all queries will be made available to all Bidders by:
Friday 13 September 2013.
NB. Any amendment to the RFP will be made via the Bank’s
website: http://www.boj.org.jm/rfp.php.
It is therefore incumbent on bidders to monitor the BOJ website.
C. Preparation of Bids
ITB 12.1
The language of the bid is: English
ITB 13.1 Any additional materials required to be completed and submitted by
the Bidders are:
NONE
ITB 14.4 The Contract is subject to price adjustment in accordance with GCC
Clause 47.
ITB 15.1 The currency is: Jamaican Dollars
ITB 15.2
The authority for establishing the rates of exchange shall be the Bank
of Jamaica.
ITB 15.4
Bidders are required to substantiate the rates and prices.
ITB 16.1 The Bid shall be valid for 180 days
ITB 17.1 Bid shall include a Bid Security issued by a bank or a by a surety using
the form for bid security (bank guarantee or bid bond) included in
Section IX Security Forms. The Bid Security shall be $1,300,000.00.
ITB 17.2 The Bid Security amount is $1,300,000.00.
ITB 18.1 Alternative Bids shall not be considered.
ITB 19.1
The number of copies of the Bid to be completed and returned shall
be two (2).
Section II. Bidding Data Sheet: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
6
D. Submission of Bids
ITB 20.1 Bidders shall not submit their bids electronically. Hard copy of the
documents should be delivered to the BOJ and deposited in the
tender box provided.
Packaging Instructions
All envelopes must be sealed. Failure to seal an envelope may result
in the rejection of the proposal.
The Bidder shall use “The Two-Envelope Bidding System”. The
Financial Proposal (original and copy) and the Technical Proposal
(original and copy) must be placed in separate envelopes and clearly
marked “Financial Proposal” and “Technical Proposal” respectively,
with the RFP name and number clearly marked on each.
Both envelopes (containing the Financial and Technical proposals
respectively) shall be placed in one envelope which must be clearly
labelled with the RFP name and number.
The outer envelope shall be free of marks, words, and symbols which
may be used to identify the Bidder.
The envelope containing the Technical Proposal (original and copy),
shall be clearly marked:
TECHNICAL PROPOSAL
RFP No. 2013-10-10-02
Structural Repairs to Tower Block
And shall have the name and return address of the Bidder.
The envelope containing the Technical Proposal shall contain the
documents listed at Appendix 1 Failure to include all these items in
the envelope marked “Technical Proposal” may result in the
disqualification of the bid.
Please ensure that your bid price is not included in the envelope
marked “Technical Proposal”.
The envelope containing the Financial Proposal (original and copy)
shall be clearly marked:
Section II. Bidding Data Sheet: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
7
FINANCIAL PROPOSAL
RFP No. 2013-10-10-02
Structural Repairs to Tower Block
And shall have the name and return address of the Bidder.
The envelope containing the Financial Proposal shall contain the
information described in (Appendix II). Failure to include all the
items listed in (Appendix II) in the envelope marked “Financial
Proposal” may result in the disqualification of the bid.
The inner and outer envelopes shall bear the following additional
identification marks:
RFP No. 2013-10-10-02
Structural Repairs to Tower Block
ATTENTION: Head of Procurement
Procurement Administration Section
Bank of Jamaica
Nethersole Place
Kingston, Jamaica
ITB 20.2 (a) The Procuring Entity’s address for the purpose of Bid submission is: Procurement Administration Section
Bank of Jamaica
Nethersole Place
Kingston, Jamaica
ITB 20.2 (b) Name and Identification number of the contract as given in ITB 1.1
above in this sheet.
ITB 20.2 (c) The warning should read “DO NOT OPEN BEFORE 20 September
2013
ITB 20.5 The Tender Box shall be provided at:
Procurement Administration Section
Bank of Jamaica
Nethersole Place
Kingston, Jamaica
ITB 21.1 The deadline for submission of bids shall be Friday, 20 September
2013
Section II. Bidding Data Sheet: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
8
E. Bid Opening and Evaluation
ITB 24.1
The bid opening shall take place at:
Bank of Jamaica
Nethersole Place
Kingston, Jamaica
Date: Friday, 20 September 2013
Time: 10:15 a.m.
The Financial Opening will take place at:
Bank of Jamaica
Nethersole Place
Kingston, Jamaica
Date: 07 October 2013
Time: 10:00 a.m.
Evaluation will be conducted in accordance with Appendices 3 & 4
ITB 31.1 Domestic contractors shall not receive a margin of preference in Bid
evaluation.
F. Award of Contract
ITB 35.1 The Standard Form of Performance Security acceptable to the
Procuring Entity shall be a Performance Bond.
ITB 36.1 The Advance Payment shall be limited to ten (10) percent of the
Contract Price.
Section II. Bidding Data Sheet: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
9
APPENDIX I
TECHNICAL PROPOSAL
The Technical Proposal will comprise the following:
1. Qualification Information Form
2. Declaration Form
3. Disclaimer
4. Bid Security
Section II. Bidding Data Sheet: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
10
APPENDIX II
FINANCIAL PROPOSAL
The Financial Proposal will comprise the items listed below:
1. Contractor’s Bid, duly completed and signed.
2. Completed Bills of Quantities to include all applicable taxes
Section II. Bidding Data Sheet: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
11
APPENDIX III
EVALUATION METHODOLOGY
The minimum required score for the Technical Evaluation is Eighty (80) points. Tenderers are
required to obtain a minimum of 60% of the points on the Performance (Track Record) and
also a minimum of 60% of the points on the Financial Affairs Criteria. The contractor attaining
the minimum required score will be invited to the opening of the Financial Proposals.
The Technical Evaluation will be awarded based on the following allocation:
1. Qualification Information (60 points)
This criterion will be based on Item 1 of the Technical Proposal (Appendix 1).
2. Technical (25 points)
This criterion will be based on responses to items 1 of the Technical Proposal
(Appendix 1).
3. Management / Project Management Personnel (15 points)
This criterion will be based on responses to item I of the Technical Proposal
(Appendix 1).
The financial proposal will be assessed based on responses to Appendix II
Qualification
The Employer will determine to his satisfaction whether the tenderer that is selected is qualified
to perform the contract satisfactorily. The determination will take into account the tenderer’s
technical and production capabilities.
An affirmative determination is a prerequisite for award of the contract to the tenderer.
The Contractor’s Team available for the project should include at least a structural Engineer
and/or Construction Manager with a minimum of ten (10) years’ experience and professional
certification in order to obtain maximum points. Curriculum Vitae and proof of qualification are
to be provided.
GENERAL EVALUATION FORMULA
A. The Technical Score will be scored using the following formula, where:
Qt is the score of the Technical Proposal
t = Technical weighting (40%)
TP is total points (out of 100) for Technical Proposal,
Qt = TP / 100 x t
Section II. Bidding Data Sheet: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
12
B. The Financial Score will be scored using the following formula, where:
Cf is the score of the Financial Proposal;
c = Cost weighting (60%)
Flow is the lowest Bid price; and
F is the Bid price of the Proposal under consideration,
Cf = c x Flow / F
C. Total Score = Qt + Cf
Total Score
Total Score = Technical Score + Financial Score
Section II. Bidding Data Sheet: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
13
APPENDIX IV
EVALUATION MATRIX
Name of Tender: Structural Repairs to Tower Block
RFP#: 2013-10-10-03
Date: 11 AUGUST 2013
Particulars Bidders
Description
POINTS SCORES
Bid Qualification Checklist
Qualification Information
Declaration Form
Disclaimer Form
TCC
NCC Certification
Technical Proposal
Financial Proposal
Tender Security
A. Qualification Information and Finances 60
Financial Health and Stability Excellent = 30 Good = 25 Average = 20 Poor = 15
30
Years in Business: 5 – 11 yrs. = 2; Over 15 yrs. = 6 11 – 15 years = 4
6
Performance in the last ten years; At least 2 building projects > $150M = 20 At least 3 building projects > $75M = 15 At least 4 building projects > $50M = 10
20
Physical Resources 50 – 75% of equipment = 4 35 – 49% of equipment = 3 25 – 34% of equipment = 2
4
B. Technical Specification 25
Method Statement:
Safety and Quality Control Procedures 20
Project schedule (Gantt Chart) 5
C. Management / Project Management Personnel 15
Key Persons for this project :
Experience >15 years = 5, 11 – 15 years = 3, 5 – 11 years = 1
5
Qualifications (construction related disciplines) Postgraduate degree = 5 Graduate degree = 3 Professional certification = 2
5
Number of team members: >2 members = 5, 2 members = 3, 1 member = 1
5
TOTAL TECHNICAL SCORE 100
Section II. Bidding Data Sheet: BOJ – RFP No. 2013-10-10-02 Structural Repairs to Tower Block
14
SSEECCTTIIOONN IIIIII..
FFOORRMMSS OOFF BBIIDD,, QQUUAALLIIFFIICCAATTIIOONN IINNFFOORRMMAATTIIOONN,,
DDEECCLLAARRAATTIIOONN FFOORRMM,, DDIISSCCLLAAIIMMEERR,, LLEETTTTEERR OOFF
AACCCCEEPPTTAANNCCEE AANNDD AAGGRREEEEMMEENNTT
Section III. Forms of Bid, Qualification Information, Declaration Form, Disclaimer, Letter of
Acceptance & Agreement BOJ - RFP No. 2013-10-10-02 – Structural Repairs to Tower Block ___
27
1. Contractor’s Bid
The Bidder shall fill in and submit this Bid form with the Bid.
__________________________________ [date]
Identification No and Title of Contract: Structural Repairs to Tower Block
To: Bank of Jamaica
Nethersole Place
Kingston, Jamaica
Having examined the Bidding Documents, including addenda [insert list], we offer to
execute Structural Repairs to Tower Block in accordance with the GCC accompanying
this Bid for the Contract Price of:
($ )
The Contract shall be paid in the following currencies:
Currency Percentage payable
in currency
Rate of exchange: one
foreign equals [insert local]
Inputs for which
foreign currency is
required
(a)
(b)
The advance payment required is:
Amount Currency
(a)
(b)
This Bid and your written acceptance of it shall constitute a binding Contract between
us. We understand that you are not bound to accept the lowest or any Bid you receive.
We hereby confirm that this Bid complies with the Bid validity and, if required, Bid
Security as required by the Bidding Documents and specified in the BDS.
Section III. Forms of Bid, Qualification Information, Declaration Form, Disclaimer, Letter of
Acceptance & Agreement BOJ - RFP No. 2013-10-10-02 – Structural Repairs to Tower Block ___
28
We, including any subcontractors or suppliers for any part of the Contract, have
nationalities from eligible countries in accordance with ITB Sub-Clause 4.1;
We have no conflict of interest in accordance with ITB Sub-Clause 4.2;
Our firm, its affiliates or subsidiaries—including any subcontractors or suppliers for any
part of the contract—has not been declared ineligible by the GOJ.
Authorized Signature:
Name and Title of Signatory:
Name of Bidder:
Address:
(Affix company’s stamp/seal)
Section III. Forms of Bid, Qualification Information, Declaration Form, Disclaimer, Letter of
Acceptance & Agreement BOJ - RFP No. 2013-10-10-02 – Structural Repairs to Tower Block ___
29
2. Qualification Information
[The information to be filled in by bidders in the following pages shall be used for
purposes of post-qualification or for verification of prequalification as provided for in
ITB Clause 5. This information shall not be incorporated in the Contract. Attach
additional pages as necessary. Pertinent sections of attached documents should be
translated into English. If used for prequalification verification, the Bidder should fill
in updated information only.]
1. Individual
Bidders or
Individual
Members of
Joint
Ventures
1.1 Constitution or legal status of Bidder: [attach copy]
Place of registration: [insert]
Principal place of business: [insert]
Power of attorney of signatory of Bid: [attach]
1.2 Annual amounts of construction works performed
during the last [insert number pursuant to BDS sub
clause 4.5(a)] years [insert amounts in the national
currency equivalent]
1.3 Number [insert number pursuant to BDS sub clause
4.5 (b)] of works of a nature and amount similar to
the Works performed as prime Contractor over the
last [insert number pursuant to BDS 4.5(b)] years.
[The amounts should be indicated in the same
currency used for Item 1.2 above. Also list details of
work under way or committed, including expected
completion date(s).]
Project name and
country
Name of client and
contact person
Type of work performed
and year of completion
Value of contract
(national currency
equivalent )
(a)
(b)
(c)
(d)
Section III. Forms of Bid, Qualification Information, Declaration Form, Disclaimer, Letter of
Acceptance & Agreement BOJ - RFP No. 2013-10-10-02 – Structural Repairs to Tower Block ___
30
1.4 Major items of Contractor’s Equipment proposed for
carrying out the Works. [List all information requested
below. Refer also to ITB Sub-Clause 5.3 (d).]
Item of Equipment Description, make and
age (years)
Condition (new, good,
poor) and number
available
Owned, leased (from
whom) or to be
purchased
(from whom)
(a)
(b)
(c)
(d)
1.5 Qualifications and experience of key personnel
proposed for administration and execution of the
Contract. [Attach biographical data. Refer also to
ITB Sub-Clause 5.3 (e) and GCC Sub-Clause 9.1.]
Position Name Years of experience
(general)
Years of experience
in proposed position
(a)
(b)
(c)
(d)
1.6 Proposed subcontracts and firms involved. Refer to
GCC Clause 7.
Sections of the Works Value of Sub-contract Sub-contractor
(name and address)
Experience
in similar work
(a)
(b)
(c)
(d)
1.7 Financial reports for the last [insert number; usually
5] years: balance sheets, profit and loss statements,
Section III. Forms of Bid, Qualification Information, Declaration Form, Disclaimer, Letter of
Acceptance & Agreement BOJ - RFP No. 2013-10-10-02 – Structural Repairs to Tower Block ___
31
auditors’ reports, etc. [List below and attach copies.]
1.8 Evidence of access to financial resources to meet the
qualification requirements: cash in hand, lines of
credit, etc. List below and attach copies of support
documents.
1.9 Name, address, and telephone, telex, and facsimile
numbers of banks that may provide references if
contacted by the Procuring Entity.
1.10 Information on current litigation(s) in which the Bidder
is involved.
Other Party(ies)
Cause of Dispute
Amount Involved
(a)
(b)
(c)
(d)
1.11 Proposed Program (work method and schedule).
Descriptions, drawings, and charts, as necessary, to
comply with the requirements of the Bidding
Documents.
1.12 Safety and Quality Control Procedures
Section III. Forms of Bid, Qualification Information, Declaration Form, Disclaimer, Letter of
Acceptance & Agreement BOJ - RFP No. 2013-10-10-02 – Structural Repairs to Tower Block ___
32
2. Joint
Ventures
2.1 The information listed in 1.1 - 1.10 above shall be
provided for each partner of the joint venture.
2.2 The information in 1.11 above shall be provided for
the joint venture.
2.3 Attach the power of attorney of the signatory(ies) of
the Bid authorizing signature of the Bid on behalf of
the joint venture.
2.4 Attach the Agreement among all partners of the joint
venture (and which is legally binding on all partners),
which shows that:
(a) all partners shall be jointly and severally liable
for the execution of the Contract in accordance
with the Contract terms;
(b) one of the partners shall be nominated as being in
charge, authorized to incur liabilities, and
receive instructions for and on behalf of any and
all partners of the joint venture; and
(c) the execution of the entire Contract, including
payment, shall be done exclusively with the
partner in charge.
3. Additional
Requirements
3.1 Bidders should provide any additional information
required in the BDS.
Section III. Forms of Bid, Qualification Information, Declaration Form, Disclaimer, Letter of
Acceptance & Agreement BOJ - RFP No. 2013-10-10-02 – Structural Repairs to Tower Block ___
33
3. Declaration Form
Name of Bidder: ____________________________________________
Address of Bidder: ____________________________________________
____________________________________________
We ( ) hereby declare that to the best of our
information, knowledge and belief and after due inquiry, the Bidder is not insolvent nor
has it taken any corporate action nor has any other steps been taken or legal proceedings
started or threatened against the bidder for its winding up, dissolution or reorganization
or for the appointment of a receiver, administrator, trustee or subsidiary of the Bidder or
any or all of its assets and undertaking.
That, so far as we are aware after due enquiry, no litigation, arbitration or
administrative proceedings are at present current, pending or threatened, which might if
adversely determined have a material adverse effect on the business, assets or financial
condition of the Bidder or hose of any of its subsidiaries.
________________________________________
Signature and Seal
________________________________________
Date
Note:
This letter of authority must be on the letterhead of the Auditor or Legal firm and
must be included by the Bidder with its bid.
Section III. Forms of Bid, Qualification Information, Declaration Form, Disclaimer, Letter of
Acceptance & Agreement BOJ - RFP No. 2013-10-10-02 – Structural Repairs to Tower Block ___
34
4. Disclaimer
TO: Bank of Jamaica
Nethersole Place
Kingston
NAME OF BIDDER:
ADDRESS OF BIDDER:
RFP NAME AND NUMBER: Structural Repairs to Tower Block
RFP # 2013-10-10-02
We, the above-mentioned Bidder for the bid referred to above, hereby verify that the
information contained in our bid document is accurate and hereby acknowledge that
the Bank of Jamaica does not give any representation, warranty or undertaking,
expressed or implied in respect of the information contained in the bid document and
no responsibility or liability will be accepted by the Bank of Jamaica as to the
accuracy or completeness of the document or for any other written or oral
information made available to bidders.
________________________________________
Signature and Seal
________________________________________
Date
Section III. Forms of Bid, Qualification Information, Declaration Form, Disclaimer, Letter of
Acceptance & Agreement BOJ - RFP No. 2013-10-10-02 – Structural Repairs to Tower Block ___
35
5. Letter of Acceptance [Letterhead paper of the Procuring Entity]
[The Letter of Acceptance shall be the basis for formation of the Contract as described
in ITB Clauses 34 and 35. This Standard Form of Letter of Acceptance shall be filled in
and sent to the successful Bidder only after evaluation of bids has been completed.] [insert date]
Identification No and Title of Contract: Structural Repairs to Tower Block
To: [insert name and address of the Contractor]
This is to notify you that your Bid dated [insert date] for execution of the Structural
Repairs to Tower Block for the Contract Price of the equivalent24 of:
($ )
as corrected and modified25 in accordance with the Instructions to Bidders is hereby
accepted by our Agency.
You are hereby instructed to (a) proceed with the execution of the said Works in
accordance with the Contract Documents, (b) sign and return the attached Contract
Documents, and (c) forward the performance security pursuant to ITB Sub-Clause 35.1,
i.e., within 21 days after receipt of this Letter of Acceptance, and pursuant to GCC Sub-
Clause 52.1
Authorized Signature:
Name and Title of Signatory:
Name of Agency:
Attachment: Agreement
24
Delete “of the equivalent” if the Contract Price is expressed wholly in one currency. 25
Delete “corrected and” or “and modified” if not applicable. See Notes on Standard Form of Agreement, next page.
Section III. Forms of Bid, Qualification Information, Declaration Form, Disclaimer, Letter of
Acceptance & Agreement BOJ - RFP No. 2013-10-10-02 – Structural Repairs to Tower Block ___
36
4. Agreement
[The Agreement shall incorporate any corrections or modifications to the Bid resulting
from corrections of errors (ITB Clause 28), price adjustment during the evaluation
process (ITB Sub-Clause 16.3, selection of an alternative offer (ITB Clause 18),
acceptable deviations (ITB Clause 27), or any other mutually-agreeable changes allowed
for in the Conditions of Contract, such as changes in key personnel, subcontractors,
scheduling, and the like.]
This Agreement, made the [insert day] day of [insert month], [insert year] between the
Bank of Jamaica, Nethersole Place, Kingston, Jamaica (hereinafter called “the
Procuring Entity”) and [insert name and address of Contractor] (hereinafter called “the
Contractor”) of the other part.
Whereas the Procuring Entity is desirous that the Contractor execute Structural Repairs
to Tower Block (hereinafter called “the Works”) and the Procuring Entity has accepted
the Bid by the Contractor for the execution and completion of such Works and the
remedying of any defects therein.
Now this Agreement witnesseth as follows:
1. In this Agreement, words and expressions shall have the same meanings as are
respectively assigned to them in the Conditions of Contract hereinafter referred
to, and they shall be deemed to form and be read and construed as part of this
Agreement.
2. In consideration of the payments to be made by the Procuring Entity to the
Contractor as hereinafter mentioned, the Contractor hereby covenants with the
Procuring Entity to execute and complete the Works and remedy any defects
therein in conformity in all respects with the provisions of the Contract.
3. The Procuring Entity hereby covenants to pay the Contractor in consideration of
the execution and completion of the Works and the remedying of defects wherein
the Contract Price or such other sum as may become payable under the provisions
of the Contract at the times and in the manner prescribed by the Contract.
Section III. Forms of Bid, Qualification Information, Declaration Form, Disclaimer, Letter of
Acceptance & Agreement BOJ - RFP No. 2013-10-10-02 – Structural Repairs to Tower Block ___
37
In Witness whereof the parties thereto have caused this Agreement to be executed the
day and year first before written.
The Common Seal of [Witness entity]
was hereunto affixed in the presence of:
Signed, Sealed, and Delivered by the said
in the presence of:
Binding Signature of Procuring Entity [signature of an authorized representative of the
Procuring Entity]
Binding Signature of Contractor [signature of an authorized representative of the
Contractor]
Section IV. General Conditions of Contract: BOJ RFP No. 2013-10-10-02 – Structural Repairs to Tower
Block
SSEECCTTIIOONN IIVV..
GGEENNEERRAALL CCOONNDDIITTIIOONNSS OOFF CCOONNTTRRAACCTT
Section IV. General Conditions of Contract: BOJ RFP No. 2013-10-10-02 – Structural Repairs to Tower
Block
37
CCOONNDDIITTIIOONNSS OOFF CCOONNTTRRAACCTT -- PPAARRTT II
TTHHEE CCOONNDDIITTIIOONNSS OOFF CCOONNTTRRAACCTT SSHHAALLLL BBEE
““CCOONNDDIITTIIOONNSS OOFF CCOONNTTRRAACCTT FFOORR CCOONNSSTTRRUUCCTTIIOONN 11999999
EEDDIITTIIOONN”” FF..II..DD..II..CC.. DDOOCCUUMMEENNTT
THE DOCUMENT IS AVAILABLE FOR VIEWING UP TO THE DEADLINE
FOR RETURN OF BID AT THE FOLLOWING ADDRESS ON WEEKDAYS
BETWEEN THE HOURS OF
9:00 A.M. & 3:00 P.M.
Procurement Administration Section
Bank of Jamaica
Nethersole Place
Kingston, Jamaica
Section V. Particular Conditions of Contract: BOJ - RFP No. 2013-10-10-02 – Structural Repairs to Tower
Block
SSEECCTTIIOONN VV..
PPAARRTTIICCUULLAARR CCOONNDDIITTIIOONNSS OOFF CCOONNTTRRAACCTT
Section V. Particular Conditions of Contract: BOJ - RFP No. 2013-10-10-02 – Structural Repairs to Tower
Block
39
CCOONNDDIITTIIOONNSS OOFF CCOONNTTRRAACCTT -- PPAARRTT IIII
CONDITIONS OF PARTICULAR APPLICATION
CLAUSE 1 - DEFINITIONS
1.1.2.2 The "Employer" is BANK OF JAMAICA, its duly authorized representative or its legal successors.
CLAUSE 3 - THE ENGINEER
Add to sub-clause 3.1: The Engineer or the Contractor’s Representative may require the other to attend a management
meeting in order to review the arrangements for future work. The Engineer shall record the
business of management meetings and supply copies of the record to those attending the
meeting and to the Employer. In the record, responsibilities for any actions to be taken shall be
in accordance with the contract.
Notwithstanding anything in this clause or elsewhere in these Conditions of Contract, the
Engineer shall have no authority to issue any variation(s) to the contract without obtaining the
written permission of the BOJ.
For the purposes of such approval, the signature of the Employer’s Managing Director or his
designate shall be deemed to be the signature of the Employer.
Add to sub-clause 3.4:
Delete the last sentence of sub-clause 3.4 and substitute:
The Employer shall have absolute power to replace the Engineer, and the Contractor has no right
to raise objection to the replacement of the Engineer.
CLAUSE 4 - THE CONTRACTOR
4.2 At the end of the second paragraph of sub-clause 4.2, insert:
If the Performance Security is in the form of a Bank Guarantee, it shall be issued either (a) by a
bank located in the Country, or (b) directly by a foreign bank acceptable to the Employer. If the
Performance Security is not in the form of a bank guarantee, it shall be furnished by a financial
entity registered, or licensed to do business, in the Country.
Section V. Particular Conditions of Contract: BOJ - RFP No. 2013-10-10-02 – Structural Repairs to Tower
Block
40
The Contractor shall furnish a performance bond or bank guarantee of performance in the
amount of 10% of the contract sum, submitting to the Employer the completed performance
security in the form prescribed in the tender document included herein or such other form as may
be approved by the Employer and shall be issued by a local financial institution approved by the
Employer.
The Performance Bond shall remain in full force up to the date of the issue of the performance
certificate for the works. The Performance Bond shall be in favour of and retained by the
Employer as a guarantee for the due execution and proper performance of the contract.
Where a Performance Bond is required under the terms of this contract, the provision of such
bond shall be condition precedent to the disbursement of any funds under the Contract.
Add the following to the end of the sub-clause:
Within 28 days of the successful tenderer’s receipt of notification of award from the Employer,
the successful tenderer shall furnish a performance bond or bank guarantee of performance, and
insurances in the amount of 10% of the contract sum, submitting to the Employer the completed
performance security in the form prescribed in the tender documents.
The Performance Security should be released on completion of the Contract. The Performance
Security shall be in favour of and retained by the Employer as a guarantee for the due execution
and proper performance of the Contract including recovery of any Liquidated or Ascertained
Damages or other sums or costs for which the Contractor may become liable under the Contract
due to his failure to perform.
Note:
The Contractor shall produce Performance Security and Insurances before the signing of
the contract for inspection by the Employer.
Performance Security shall be operative from the commencement of the contract
4.3 Add the following to the end of the sub-clause:
The Contractor shall be responsible for ensuring the attendance of any or all nominated sub-
contractors as the Engineer requires for the proper management and execution of the works.
4.7 Add the following to the end of the sub-clause:
Section V. Particular Conditions of Contract: BOJ - RFP No. 2013-10-10-02 – Structural Repairs to Tower
Block
41
Prior to the setting-out of any part of the works, the Contractor shall check the accuracy of all
such original points, lines and levels of reference given by the Engineer or as may be established
from coordinates of reference stations or previous surveys and having accepted them as correct,
or having checked and reconciled any inaccuracies with the Engineer, shall establish and
maintain suitable reference markers outside the location of all Permanent and Temporary Works
and shall thereafter be responsible for the correctness of the position, levels dimensions and
alignment of all parts of the Works.
CLAUSE 7 – PLANT, MATERIALS & WORKMANSHIP
Add as 7.9:
(1) For the purpose of this Clause:-
1. the expression "Plant" shall mean any constructional Plant and materials for
Temporary Works but shall exclude any vehicles engaged in transporting any
labour, Plant or materials to or from the site;
2. the expression "Agreement for Hire" shall be deemed not to include an agreement
for hire purchase.
(2) All Plant, goods and materials owned by the Contractor or by any Company in which the
Contractor has a controlling interest shall, when on the site be deemed to be the property
of the Employer.
(3) With a view to securing, in the event of a forfeiture, the continued availability for the
purpose of executing the Works, of any hired Plant, the Contractor shall not bring on to
the site any hired Plant unless there is an agreement for the hire thereof which contains a
provision that the owner thereof will on request in writing made by the Employer within
seven (7) days after the date on which any forfeiture has become effective and on the
Employer undertaking to pay all hire charges in respect thereof from such date, hire such
Plant to the Employer on the same terms in all respects as the same was hired to the
Contractor save that the Employer shall be entitled to permit the use thereof by any other
contractor employed by him for the purpose of completing the Works.
(4) In the event of the Employer entering into any agreement for the hire of Plant pursuant to
sub-clause (3) of this Clause all sums properly paid by the Employer under the provisions
of any such agreement and all expenses incurred by him (including stamp duties) in
entering into such agreement shall be deemed to be part of the cost of completing the
Works.
Section V. Particular Conditions of Contract: BOJ - RFP No. 2013-10-10-02 – Structural Repairs to Tower
Block
42
(5) The Contractor shall upon request made by the Engineer at any time in relation to any
item of Plant forthwith notify to the Engineer in writing the name and address of the owner
thereof and shall in the case of hired Plant certify that the agreement for the hire thereof
contains a provision in accordance with the requirements of sub-clause (3) of this Clause.
(6) No Plant (except hired Plant), goods or materials or any part thereof shall be removed
from the site without the written consent of the Engineer which consent shall not be
unreasonably withheld where the same are no longer immediately required for the
purposes of the completion of the Works but the Employer will permit the Contractor the
exclusive use of all such Plant, goods and materials in and for the completion of the
Works until the occurrence of any event which gives the Employer the right to exclude the
Contractor from the site and proceed with the completion of the Works.
(7) Upon the removal of any such Plant, goods or materials as have been deemed to have
become the property of the Contractor.
(8) If the Contractor shall fail to remove any Plant, goods or materials as required within such
reasonable time after completion of the Works as may be allowed by the Engineer then
the Employer may:
1. sell any which are the property of the Contractor; and
2. return any not the property of the Contractor to the owner thereof at the
Contractor's expense; and after deducting from any proceeds of sale, the costs,
charges and expenses of and in connection with such sale and of and in
connection with return as aforesaid shall pay the balance (if any) to the Contractor
but to the extent that the proceeds of any sale are insufficient to meet all such
costs, charges and expenses shall be a debt due from Contractor to the Employer
and shall be deductible or recoverable by the Employer for any monies due or that
may become due to the Contractor under the contract or may be recovered by the
Employer from the Contractor at law.
(9) The Employer shall not at any time be liable for the loss of or injury to any of the Plant,
goods or materials which have been deemed to become the property of the Employer.
(10) The Contractor shall where entering into any sub-contract for the execution of any part of
the Works incorporate in such sub-contract (by reference or otherwise) the provision of
this Clause in relation to Plant, goods or materials brought on to the site by the sub-
contractor.
(11) The operation of this Clause shall not be deemed to imply any approval by the Engineer
of the materials or other matters referred to herein, nor shall it prevent the rejection of any
such materials at any time by the Engineer.
Section V. Particular Conditions of Contract: BOJ - RFP No. 2013-10-10-02 – Structural Repairs to Tower
Block
43
CLAUSE 8 – COMMENCEMENT, DELAYS & SUSPENSION
Clause 8.3 Programme
Add the following at the end of the sub-clause:
Within twenty-eight (28) days after acceptance of his Tender, the Contractor shall submit to the
Engineer the programme in accordance with this clause.
Failure to submit the required programme shall forfeit the right to any future claims for delay.
Delete the last paragraphs and substitute the following:
Should it appear to the Engineer at any time that the actual progress of the Works does not
conform with the approved programme referred to in Sub-Clause 8.3 of this Clause, the Engineer
shall be entitled to require the Contractor to produce a revised programme showing the
modifications to the original programme necessary to ensure completion of the Works or any
Section within the time for completion of the Works as required in Clauses 8.2 and 8.4 or
extended time granted pursuant to Clause 8.4 hereof.
Clause 8.4.1 – Extension of Time for Completion
Exceptionally adverse climatic conditions shall mean rainfall which the National Meteorological
Office of Jamaica states has exceeded the 30-year mean for the location of the works.
CLAUSE 13 – VARIATIONS & ADJUSTMENTS
13.8 Delete in full and insert:
13.8.1 Fluctuations in the Cost of Materials
1. This Contract shall be let on a fluctuating basis with regard to materials, and the
Contractor must price the Appendices of basic prices as failure to do so will result
in no reimbursement for increase in cost of materials. If the said cost of materials
shall be increased or decreased by the manufacturer or the supplier, the net
increase or decrease of such cost of materials shall constitute an adjustment to
Section V. Particular Conditions of Contract: BOJ - RFP No. 2013-10-10-02 – Structural Repairs to Tower
Block
44
the contract Sum to be paid or allowed by the Contractor accordingly. The
Contractor shall give written notice to the Engineer of any such fluctuation who,
upon being satisfied as to the amount of fluctuation shall determine the increase
or decrease of the cost of the works or any part thereof.
a. Variation in price will be allowed or applied only on the materials and goods listed
in Appendix D.
If after the date of Tender and during the Contract period or any authorised
extension thereto, there shall be any increase or decrease in the ruling market
prices of materials or goods listed in the said Appendices and if such an increase
or decrease shall result in an increase or decrease of cost to the Contractor in
carrying out the Works, then the net increase or decrease shall form an addition to
or a deduction from the Contract Price as the case may be.
b. The Contractor shall at the time of tendering enter in the said Appendix the basic
prices of the materials and goods listed. These basic prices shall be the current
landed costs including custom charges, taxes, insurance and freight from the
nearest Jamaican port to the Site in the case of imported materials and shall be
the current cost to the Contractor, including insurance, taxes and freight from the
place of manufacture to the Site, in the case of materials and goods manufactured
in Jamaica. The Contractor shall substantiate the said prices by actual quotations
from suppliers at the time of tendering. He shall also provide other evidence as
required by the Employer. If on such evidence or other evidence it becomes
necessary to amend the prices of materials, then this will be done before the
award of the Contract by mutual agreement. The Contractor shall not insert any
additional materials in the said Appendices.
c. The fact that the Contractor desires to order materials or goods from a supplier
other than that from whom he obtained his original quotation will not be a
justification for an increase under this clause but if the Contractor shall by reason
of such alteration in supplier pay less than the prices quoted at the time of
tendering, the Employer shall receive the benefit of such reduction under the
terms of this clause.
d. The Contractor shall immediately after increase or decrease under this clause
takes place, notify the Engineer in writing. The Contractor shall, from time to time,
as required by the Engineer produce all necessary documents, records and
accounts for the inspection of the Engineer, and shall afford him such information
as will enable him to determine the actual cost delivered and the net cost of
freight, the Custom charges, taxes and insurance paid in respect of the materials
and goods listed, and to decide on any increase or decrease in the Contract Price,
to be allowed or applied in respect of these materials and goods.
Section V. Particular Conditions of Contract: BOJ - RFP No. 2013-10-10-02 – Structural Repairs to Tower
Block
45
e. No variation will be allowed or applied in the Contract Price by way of percentage
or otherwise for overheads, profits, etc., of the Contractor on any of the increases
or decreases which may be allowed or applied under the provisions of this clause.
f. The Provisions of this clause shall not apply to materials for Temporary Works.
g. The provisions of this clause shall apply to such sub-contractors as are employed
on the site.
13.8.2 Fluctuations in the Cost of Labour
1. The Contractor shall be deemed to have based his rates for carrying out the Works on
the rates of wages contained in the Bill of Quantities which are the basic rates of wages
current fourteen (14) days before the date for return of Tenders and in accordance with
the current rates set by the Joint Industrial Council for the Building Industry in Jamaica.
2. If the said basic rates of wages, or the Contractor's contribution to any statutory provident
fund, or any statutory allowances shall be increased or decreased by the Joint Industrial
Council for the Building Industry, the net increase or decrease of such wages,
contributions or allowance shall be an addition to or a deduction from the Contract Price
as the case may be. Provided that, if the Contractor is paying basic rates of wages in
excess of the basic rates shown in the said Schedule, the net increase or deduction from
the Contract Price shall be based on the actual increase or decrease in the basic rates
paid by the Contractor to his employees, or on the actual increase or decrease gazetted
by the Joint Industrial Council for the Building Industry whichever is the less in the case of
an increase or the greater in the case of a decrease;
3. Irrespective of the actual wages paid to the Contractor's labour on the contract, the
Contractor shall classify all his labour, (but excluding all expatriate or indigenous
supervisory staff, engineering assistants or monthly paid personnel, to whom this Clause
shall not apply) into the categories in accordance with those of the Joint Industrial Council
(for the Building Industry), and against each man's name and trade as employed shall
inscribe the appropriate category index on the monthly pay sheet.
4. The Contractor shall, if he intends to claim under this Clause, notify the Engineer within
28 days of the official gazetting of any variation in basic rates of wages. The Contractor
shall prepare separate schedules for each category of Labour in his employ on the
Works, each schedule being an extraction of relevant data from the appropriate monthly
pay sheet.
5. The Schedule shall be presented, duly certified by the Engineer's representative, with the
monthly certificates together with the original pay sheets.
Section V. Particular Conditions of Contract: BOJ - RFP No. 2013-10-10-02 – Structural Repairs to Tower
Block
46
6. No variation will be made in the Contract Price by way of percentage or otherwise for
overheads, profits, etc. on any increase which may be allowed or applied under the
provisions of this clause, with the exception of the net amount of variation in the premium
paid by the Contractor in respect of Workmen's Compensation Insurance directly related
to variation in Labour costs.
7. In the event of any new Government system of Labour Payment being introduced which
materially changes the categories of labour shown in the Schedule of Labour Rates, the
Engineer shall have the power to reclassify the categories of employees, and the
Contractor shall amend the Schedules accordingly.
8. Any variations in the Contract Price in accordance with the provisions of this Clause shall
be applied as follows:-
a. any increase will be allowed for the increase in Joint Industrial Council's (for the
Building Industry) rates or the date when the increase was paid whichever is later:
b. any decrease will be applied from the date of the decrease by the Joint Industrial
Council (for the Building Industry).
CLAUSE 14 – CONTRACT PRICE & PAYMENT
Add the following to the end of the sub-clause 14.2:
Mobilization
An advance of up to 10% of the construction sum shall be available to the contractor at the
beginning of the contract. The following conditions are applicable:
a. The submission of BOJ’s prescribed Mobilization Guarantee for the amount of advance is
a prerequisite for disbursement;
b. Mobilization payment is to be used exclusively for the pre-purchase of material.
c. Included in the 10% advance is the mobilization for all nominated sub-contractors.
The mobilization sum shall be paid by the Employer to the Contractor:
a. Upon execution of the contract.
b. Upon the Employer being satisfied that the Contractor has completed and submitted the
BOJ prescribed Mobilization Guarantee similar to the one contained in the Appendix
hereto for the full amount of the Mobilization payment.
Section V. Particular Conditions of Contract: BOJ - RFP No. 2013-10-10-02 – Structural Repairs to Tower
Block
47
c. Material (including tunnel forms) pro-forma invoice(s) in the sum of 100% of the
mobilization sum is a prerequisite for disbursement;
Retention
Add the following to the end of sub-clause 14.9:
a. 10% of the value of certified work done up to the completion of 50% of construction sum
will be withheld by the BOJ.
a. The limit of retention is 5% of contract sum.
b. 2½ % of the retention amount will be released on the issuing of the Taking-Over
Certificate.
d. The remaining 2½ % will be released on successful completion of the defects liability
period and the issuance of the Performance Certificate.
CLAUSE 17 – RISK & RESPONSIBILITY
Confidential Information
Add the following to the end of sub-clause 17.5:
a) The Contractor shall not at any time whether before or after the termination of this
Agreement divulge or use any unpublished technical information from the Employer and
any other confidential information in relation to the Employer or its affairs or its method of
carrying on business.
CLAUSE 20 - CLAIM, DISPUTES & ARBITRATION
Clauses 20.2, 20.3 and 20.4 – Delete Clause 20 in the Particular Conditions of Contract and add the
following:
20.2 Adjudication
If any dispute or difference of any kind whatsoever arises between the Parties, at any time after
the execution of the Contract, in connection with or arising out of the Contract or the Execution of
Section V. Particular Conditions of Contract: BOJ - RFP No. 2013-10-10-02 – Structural Repairs to Tower
Block
48
the Works then either Party may refer such dispute in writing to a single Adjudicator to be
appointed jointly by the Parties for his decision.
If the parties fail to agree upon the appointment of an Adjudicator, then an Adjudicator shall be
appointed by the Dispute Resolution Foundation of Jamaica or the President of the Jamaican
Institute of Engineers.
Both Parties shall make available to the Adjudicator all such additional information as may be
necessary for making a decision.
Unless either party shall within 28 days of the Adjudicator’s decision notify the other Party of
dissatisfaction with the decision, the decision of the Adjudicator shall be final and binding upon
both Parties.
Clauses 20.5 – 20.6 – Delete both clauses and insert the following:
20.3 Final Determination by Courts
Where notice of dissatisfaction has been given under clause 20.2 the parties shall attempt to
settle the dispute amicably.
If no settlement has been reached within ten (10) days of the date on which notice of
dissatisfaction was given, then either Party shall refer the dispute to be settled by the Court of
Law in Jamaica.
Clause 20.7 – Delete entire clause and insert the following:
20.4 – Failure to Comply with Adjudicator’s Decision
In the event
(i) That neither Party issues a notice of dissatisfaction and
(ii) The Adjudicator’s decision becomes final and binding
(iii) And a party fails to comply with the Adjudicator’s decision
then the other party may, without prejudice to any other rights it may have, refer the failure to
comply with the Adjudicator’s decision, to be settled by a Court of Law in Jamaica.
Clause 20.8 – Delete entire clause.
Section V. Particular Conditions of Contract: BOJ - RFP No. 2013-10-10-02 – Structural Repairs to Tower
Block
49
CLAUSE 21 - TAXATION
Add as Clause 21:
The Contractor shall comply fully with the Laws of Jamaica regarding taxation and no exception
shall be made from any Jamaican rates, taxes, duties or other fiscal levies. Except in respect of
Plant and materials imported and re-exported with the written approval of the Employer and the
relevant Government of Jamaica departments.
Levies
In accordance with the Contractor’s Levy Act 1985, the Employer shall deduct from the gross
amount payable to the contractor and or his sub-contractors under the Contract, a levy equal to
two percent (2%) of the gross amount on every certificate.
Tax Compliance & NHT Contributions
a.) The Contractor shall submit evidence he has a valid TCC prior to the processing of
payments by the BOJ.
Statutory Deductions
a) The Contractor shall ensure that at all times payments of all statutory
deductions for its employees are current and shall in the absence of a
written request by the Employee, provide the latter with proof of payment
of same on a quarterly basis.
b) The Contractor shall at all times be current with the payments of all
statutory deductions, have a valid TCC, and shall submit annual returns
as required by the National Housing Trust’s regulations.
ADDITIONAL CLAUSES:
Information/Signboard
The Contractor shall provide for in the contract sum, the cost of the erection and maintenance of
an information board(s) to be a minimum size of 3.6m x 2.4m on supports with colours, graphics
and lettering. Information is to include the name of the Project, the Employer, all Consultants, the
Contractor and principal sub-contractors, all to be strictly in accordance with the Engineer’s
requirements. The Contractor shall clear away the signboards on completion.
Section V. Particular Conditions of Contract: BOJ - RFP No. 2013-10-10-02 – Structural Repairs to Tower
Block
50
No other advertisement or placards shall be affixed by the Contractor to the Works or to any
temporary work in connection with the main works. The contractor is to remove immediately any
other information, in whatever form, affixed to the signboard.
The Contractor is responsible for obtaining the local Parish Council permission to mount
signboard(s).
Section V. Particular Conditions of Contract: BOJ - RFP No. 2013-10-10-02 – Structural Repairs to Tower
Block
51
Section VI. Specifications & Performance Requirements: BOJ – Structural Repairs to Tower Block
55
SSEECCTTIIOONN VVII..
SSPPEECCIIFFIICCAATTIIOONNSS &&
PPEERRFFOORRMMAANNCCEE RREEQQUUIIRREEMMEENNTTSS
BOJ Specifications
Concrete
Reinforcing Steel Bars & Fabric
Plastering, Paving & Wall Finishes
Glazing
Painting
Section VI. Specifications & Performance Requirements: BOJ – Structural Repairs to Tower Block
1 BS
BBOOJJ SSPPEECCIIFFIICCAATTIIOONNSS
11..00 EXTENT OF WORKS
1.1 The facades of the Bank of Jamaica (BOJ) Tower have deteriorated
resulting in spalling of concrete, cracking of concrete, exposure
of reinforcement, corrosion of reinforcement and other damaging
effects. This damage is concentrated in the projecting fins on
all sides, being more pronounced on the southern and eastern
facades.
1.2 Concrete on sections of the fins and rendering external to the
reinforcement on the fins on all four (4) sides will be removed
thus exposing the reinforcement. Reinforcement which is corroded
by more than 10% of its original diameter will be removed, that
which is 10% or less will be wire-brushed to remove all traces of
rust. The remaining reinforcement and the new bars being
installed will be coated with a rust-inhibiting compound to
reduce if not eliminate the possibility of corrosion.
1.3 Removal or retention of the reinforcement shall be by written
authorisation of the Engineer after visual inspection and
measurement, if necessary, of the reinforcement.
1.4 The material to be used for coating of the reinforcement shall be
Sika Mono Top 910 N or equivalent and shall be applied in
accordance with the manufacturers’ specifications.
1.5 The concrete and wall finish shall be placed in accordance with
Drawings No. 1-6 and these Specifications.
1.6 All windows on all eleven (11) floors from the 3rd Floor to the
14th Floor inclusive (there is no 13
th Floor) are to be resealed.
There are forty (40) windows on each floor as follows:
Floor 3 – 12
Each window has two (2) components per floor
Section A 1 No. 8’-0” x 1’-8”
Section B 1 No. 3’-6” x 1’-8”
Floor 14 – Section A only
The total number of windows is:
440 No. 8’-0” x 1’-8”
400 No. 3’-6” x 1’-8”
22..00 DEMOLITION & REMOVAL OF DAMAGED AREAS
The vertical extent of the works is from a height of 46.58 ft. Above
Mean Sea Level (AMSL) to 185.58 ft. AMSL. There is a great variation
Section VI. Specifications & Performance Requirements: BOJ – Structural Repairs to Tower Block
2 BS
in wind velocities affecting the building during the day. The
velocity is low and/or negligible from before dawn to about 11:00 a.m.
and from then on it increases until after 6:00 p.m. The Contractor
shall therefore ensure that certified safety measures are in place at
all times to protect the workers and pedestrians in the adjoining
areas.
All equipment supporting workers, materials etc. shall be certified on
initial placement by independent authorized entities as to its
conformance to the safety regulations of the Government of Jamaica
(GOJ). Any relocation of the supporting equipment from its initial
positioning shall be subject to new certification. All written
certification is to be presented to the Engineer within twenty-four
(24) hours of inspection and approval.
The Contractor shall ensure at all times that concrete and rendering
being removed does not fall to cause damage or injury to personnel or
property. The areas immediately below the fins shall be restricted to
authorized personnel only and such personnel shall be clothed in the
required safety gear. The roof of the podium of the Tower shall be
protected to ensure that the waterproofing, piping and other equipment
are not damaged by falling debris. Any damage to waterproofing,
piping and other equipment caused by the Contractor and/or his
Employees or Agents shall be reinstated, replaced or repaired to the
satisfaction of the Bank of Jamaica.
The Contractor shall grant access to all authorized Bank of Jamaica
personnel including external Contractors who may be required to
perform work in the area.
All concrete, rendering and reinforcement removed during demolition
and other debris shall be carted away at regular intervals to prevent
accumulation on site.
33..00 PREPARATION OF SURFACES
3.1 Concrete surfaces exposed after demolition shall be coated with
slurry incorporating elastomeric material prior to the final
placement of concrete and surface finishing. The elastomeric
material shall be Sika Cem Pack or equivalent. Placement of the
slurry shall be in accordance with manufacturers’ specifications.
3.2 Reinforcement which is deemed acceptable in accordance with
Section 1.3 shall be prepared in accordance with Section 1.4.
44..00 REMOVAL & REPLACEMENT OF REINFORCEMENT
4.1 Reinforcement shall be removed in accordance with Section 1.3;
Sections of reinforcement to be removed shall be by cutting.
4.2 Splicing of newly-placed reinforcement shall be in accordance
with the drawings.
Section VI. Specifications & Performance Requirements: BOJ – Structural Repairs to Tower Block
3 BS
4.3 Reinforcement to be utilized shall conform to Section 6.0
Reinforcing Steel Bars & Fabric.
55..00 CONCRETE
5.1 The concrete to be used shall be composed of Portland Cement,
fine and coarse aggregate, admixtures as specified and water
prepared and constructed in accordance with these Specifications
at the locations and of the form and dimensions shown on the
Drawings or as directed by the Engineer. It shall be of the
following class:
Slump (mm) Class Nominal Mix Minimum Crushing
Strength of Cubes
at 28 days
62.5 A 1:1.5:3 28 MPa
5.2 Materials
1. Coarse Aggregate
(a) Coarse aggregate shall be crushed stone or gravel consisting
of clean, hard, tough, durable, cubical or angular fragments
of rock of uniform quality throughout. All particles
retained on 3/16” screen shall have at least one fracture
face. It shall be free from soft disintegrated pieces, mud,
and dirt, organic or other injurious material and shall not
contain more than one percent of dust by dry weight. The
maximum size of coarse aggregate shall be 5/8”.
(b) Samples for tests of coarse aggregate will be taken from the
bins at the quarry or from approved storage piles at the
quarry site.
2. Soundness
When tested with magnesium sulphate solution for soundness,
using A.A.S.H.O. Method T-104, coarse aggregate shall not
have a loss of more than 18 percent at the end of five
cycles.
3. Additives
Superplasticisers equivalent to Sikament 90MF shall be used
in accordance with the manufacturers’ specifications to aid
in the compaction of the concrete when placed on the
formwork. Addition to the concrete mix shall be in
accordance with manufacturers’ specifications.
5.3 Concrete
1. General:
Section VI. Specifications & Performance Requirements: BOJ – Structural Repairs to Tower Block
4 BS
a. Concrete shall be proportioned using the ingredients above
and shall have the minimum compressive strengths so defined.
b. All concrete shall have a slump not exceeding 62.5 mm when
tested in accordance with A.A.S.H.O. T119, unless in the
opinion of the Engineer job conditions warrant varying these
limits.
5.4 Slump:
When the slump does not meet the specification requirements,
modification of the concrete mix may be permitted if, in the
opinion of the Engineer, no harmful effect upon the permitted by
the Engineer, modifications shall be limited to the addition of
not more than 25 kilograms of Portland Cement per cubic metre of
concrete to decrease the slump or to the addition of water to
increase the slump. The amount of water or cement added shall be
further limited to the minimum needed to meet slump requirements.
The cost of additional material and the work connected with each
modification shall be borne by the Contractor. The addition of
cement or water, or both, for the purpose of retempering concrete
will not be permitted.
5.5 Vibrators:
a. Vibrators shall be used as directed by the Engineer and
shall be of the mechanical immersion type. They shall be
capable of transmitting vibration to the concrete at
frequencies of not less than 4,500 impulses per minute.
b. Not less than two (2) vibrators shall be available and in
good operating condition at each pouring of concrete in
order to ensure satisfactory and uninterrupted vibration
during placing.
c. Care shall be taken not to over vibrate the concrete.
5.6 Falsework:
All Falsework shall conform to the requirement of good practice,
shall be adequate for the purpose intended and subject to
approval by the Engineer.
5.7 Formwork:
1. Forms shall be built true to lines and grades designated,
shall be strong, stable, firm, mortar-tight and adequately
braced or tied, or both. They shall be designed and
constructed to withstand all loads and pressures including
those imposed by plastic concrete, taking full account of
the stresses due to the rate of pour, effect of vibration
and conditions brought about by construction methods. Where
Section VI. Specifications & Performance Requirements: BOJ – Structural Repairs to Tower Block
5 BS
necessary, forms shall be constructed to compensate for
variations in camber of supporting members and allow for
deflections.
2. If requested, formwork planes shall be submitted to the
Engineer by the Contractor before formwork is started. The
furnishing of such plans, however, shall not serve to
relieve the Contractor of any of his responsibility for the
successful completion of the work.
3. Forms shall be filleted at all sharp corners, unless
otherwise ordered or permitted and shall be given a slight
bevel of draft in the case of projections to ensure
satisfactory removal.
4. Materials for forms and their supports, ties and bracing,
shall be of the type, quality and strength to achieve the
foregoing requirements without impairment to the structural
qualities or appearance of the concrete structure. Form
material in contact with concrete shall be of a quality to
provide the hereinafter required concrete surface
smoothness, and, unless otherwise authorised, the contact
surface shall be oiled with a thin coat of a light, clear
paraffin base oil which will not damage, discolour or adhere
to the concrete, or, as an alternative, the form may be
lined with an approved composition form lining. Materials
and workmanship for forms for concrete to remain exposed in
the finished work shall be such as to provide a smooth
concrete surface of good appearance and texture, free of
voids, indentations, protrusions, or bulges and within
tolerances consistent with good trade practices. If panels
are used, they shall be evenly placed in columns or rows if
their positioning is to be visible after the concrete is
finished. These same requirements shall apply to forms for
concrete not to remain exposed in the finished work except
that minor irregularities where form boards or panels join
the variations in form pattern will be acceptable.
5. Metal ties and anchors to hold the forms in alignment and
location shall be so constructed that the metal work can be
removed to a depth of at least two inches from the concrete
surface without damage to the concrete. All cavities
resulting from the removal of metal ties shall be filled
with an elastomeric compound and the surface finished smooth
and even, and if exposed in the finished work, shall conform
to the texture and colour of adjacent surfaces.
5.8 Handling Materials:
During transportation, handling, storage, and until batched, the
different sizes and kinds of aggregate shall be kept separated,
free from deleterious materials, and methods that result in
segregation of sizes in any one aggregate shall be avoided.
Individual stockpiles for each size and kind shall be kept
separated at the batch plant and at the quarry. Stockpiles shall
Section VI. Specifications & Performance Requirements: BOJ – Structural Repairs to Tower Block
6 BS
be made on hard, well-drained ground areas, paved with planks or
other suitable material. Stockpiles shall be formed in such a
manner that segregation is kept to a minimum. Material shall not
be stocked for such length of time as would result in excessive
fine materials near the bottom of the piles. If washed
aggregates are used, they shall be stockpiled not less than 24
hours before use after washing.
5.9 Mixing Concrete:
Hand mixing will not be permitted.
5.10 Placing Concrete:
General
a. The use of long chutes and troughs for conveying concrete
from the mixers to the forms will be permitted only on
authority from the Engineer. If such conveyors are allowed
and the quality of concrete as it reaches the forms or the
methods of placing or working it therein are not
satisfactory, the Engineer may order their use discontinued
and substitution of a satisfactory method of placing. Where
steep slopes are required, chutes and troughs shall be
equipped with baffle boards or be in short lengths that
reverse the direction of movement. All chutes, troughs and
pipes shall be kept clean and free from coatings or hardened
concrete. Open troughs and chutes shall be either of metal
or metal lined and shall extend as nearly as possible to the
point of deposition. When the discharge must be
intermittent, a hopper or other device for regulating the
discharge shall be provided. A tremie may be used in place
of long chutes and troughs.
b. Unless permission is obtained from the Engineer, concrete
shall not be dropped a distance of more than five (5) feet
and special care shall be taken to fill each part of the
forms by depositing the concrete as near final position as
possible. In no case shall it be moved more than five (5)
feet. The coarse aggregate shall be worked back from the
forms and the concrete forced around the reinforcement
without displacing the bars. After initial set of the
concrete, the forms shall not be jarred and no strain shall
be placed on the ends of projecting reinforcement.
c. Concrete shall be placed in horizontal layers, when less
than a complete layer is placed in one operation, it shall
be terminated in a vertical bulkhead. Each layer shall be
placed and compacted before the preceding layer has taken
initial set, to prevent injury to the green concrete and to
avoid surfaces of separation between the layers.
d. Concrete shall be compacted by continuous working with
suitable tools or by vibrating. The number and type of
vibrators, the length of the vibrating period and the
Section VI. Specifications & Performance Requirements: BOJ – Structural Repairs to Tower Block
7 BS
location of the vibrators shall be as required by the
Engineer.
e. When the placing of concrete is temporarily discontinued,
the necessary keys or joints shall be formed as shown on the
Drawing or as ordered, and the concrete after becoming firm
enough to retain its form, shall be cleaned of laitance and
other objectionable material to sufficient depth to expose
sound concrete.
f. Joints shall be formed only in the locations shown on the
drawings or as permitted by the Engineer. Feather edges at
construction joints will not be permitted.
g. Immediately following the discontinuance of the placing of
concrete, all accumulations of mortar splashed upon
reinforcing steel and the surface of the forms shall be
removed. Dried mortar chips and dust shall not be puddled
into the unset concrete. If accumulations are not removed
prior to the concrete becoming set, care shall be taken not
to injure or break the concrete steel bond, at and near the
surface of the concrete, while cleaning the reinforcing
steel.
h. Workmen will not be permitted to walk in the fresh concrete
after it has been screened and all finishing work shall be
performed from bridges supported above the surface.
5.11 Expansion Joints:
1. Expansion joints shall be built at the locations and to the
dimensions and details shown on the Drawings. Open joints
shall be placed at locations designated on the Drawings and
shall be formed by the insertion and subsequent removal of
templates of wood, metal or other suitable material.
2. Filled joints shall be made with joint filler, the materials
for which shall conform to the requirements of the Drawings.
3. Special types of expansion joints shall conform to the
dimensions and details shown on the Drawings.
5.12 Curing Concrete
1. General:
a. Concrete surfaces exposed to conditions causing premature
drying shall be protected and cured by covering at the
earliest possible moment after they have stiffened enough to
withstand surface damage. Roof and floor slabs and the top
slab of box culverts shall be covered with cotton mats and
shall be continuously kept wet by spraying for not less than
seven (7) days and seven (7) nights including holidays. All
other exposed concrete shall be protected and cured for not
less than seven (7) days and seven (7) nights, including
Section VI. Specifications & Performance Requirements: BOJ – Structural Repairs to Tower Block
8 BS
holidays by covering with cotton mats and spraying with
water, covering with waterproof paper, or sheeting, or
applying liquid membrane as the Engineer may approve or
direct.
b. The Contractor shall have the option of curing concrete by
any of the curing methods described herein.
2. Moist Curing:
After the surface of the concrete has been given its final
finish, it shall be protected by covering. The covering shall be
laid longitudinally over the surface of the finished concrete by
unrolling from a supported roll so as not to bring an excessive
weight upon or to mar the new surface. After placing, these
covers shall be saturated for a period of seven (7) days and
seven (7) nights, including holidays, at the end of which time
they may be removed and no further wetting or artificial curing
will be required.
3. Liquid Membrane-Forming Curing:
a. The liquid curing compound as specified above shall be
applied immediately following the disappearance of the water
sheen following the final finishing and before any marked
dehydration of the concrete or surface checking occurs. The
compound shall be applied by an approved mechanical pressure
sprayer delivering a fine even spray with uniform coverage.
This equipment shall be provided with a suitable device for
adequate agitation of the compound to prevent settlement.
b. Approved hand-held spray bars delivering a fine even spray
may be used, and the compound shall be drawn from a tank
equipped with an approved device to prevent settlement or by
a method which will prevent settlement.
c. If the compound is applied in two (2) increments, the second
application shall follow the first application within 30
minutes. The compound shall be applied in a continuous
uniform film at not less than one gallon for 200 square
feet.
d. Transverse joints shall be protected from the compound by
means of methods approved by the Engineer.
e. When the forms are removed before seven (7) days after the
concrete has been placed, the exposed sides shall be pointed
and cleaned and then covered with the compound which shall
be applied in a continuous film at the same rate as applied
to the surface.
f. If rain falls on the newly coated concrete before the film
has dried sufficiently to resist damage, or if the film is
damaged in any other way, the Contractor will be required to
Section VI. Specifications & Performance Requirements: BOJ – Structural Repairs to Tower Block
9 BS
apply a new coat of material to the affected areas equal in
curing value to that specified for the original coat. The
treated surface shall be protected by the Contractor from
injury for a period of at least seven (7) days and seven (7)
nights, including holidays. All traffic, either foot or
otherwise, will be considered as injurious to the film of
the applied compound.
g. The Contractor shall have on the project sufficient approved
cover sheets or mats, for the protection of the concrete in
case of rain or breakdown of the spray equipment. The mats
shall be maintained in a wet condition, during their period
of use, as elsewhere hereinabove specified.
5.13 Removal of Forms:
The forms for any portion of a structure shall not be removed until
the concrete is strong enough to avoid possible injury from such
removal and in any event not before three (3) days. Forms and their
supports shall not be removed without the approval of the Engineer.
Supports shall be removed in such a manner as to permit the concrete
to uniformly and gradually take the stresses due to its own weight.
The curing process shall be continued for seven (7) days and seven (7)
nights including holidays.
5.14 Finishing:
1. Surface Finish:
The surfaces of all concrete which shall remain exposed shall be
thoroughly worked during the operation of placing by means of
tools of an approved type. The working shall be such as to force
all coarse aggregate from the surface and thoroughly work the
mortar against the forms to produce a smooth finish free from
water and air pockets, segregated materials or honey-comb.
Unless otherwise authorised by the Engineer, the surface of the
hardened concrete shall be finished immediately after the removal
of the forms. All horizontal surfaces shall be given a float
finish and all vertical or sloping surfaces shall be given a
Grout Clean Down Finish or a finish as specified on the Drawings.
2. Float Finish:
a. This finish shall be formed by placing an excess of
materials in the form and removing or striking off such
excess with a template, forcing the coarse aggregate below
the mortar surface. There shall be created no concave
surfaces in which water will be retained. After the
concrete has been struck off as described above, the surface
shall be thoroughly worked and floated with a wood float,
the operation to be performed by skilled experienced
concrete finishers. Before this last finish has set, the
Section VI. Specifications & Performance Requirements: BOJ – Structural Repairs to Tower Block
10 BS
surface shall be lightly stripped with a fine brush to
remove the surface cement film, leaving a fine-grained,
smooth, but sanded texture. Curing, as specified elsewhere
shall follow.
b. Floor slabs shall be finished with a steel float.
5.15 Test Cubes:
1. During the progress of the work, field test cubes 6" x 6" in
size shall be made and cured by the Contractor under the
direction of the Engineer, and in the number of four from
every pour of 100 cubic yards, or part thereof over 20 cubic
yards; two cubes each to be taken at two different times.
For any one pour, four cubes shall be taken regardless of
size of pour. The cubes shall be cured in the field by the
same methods as used for the concrete which they represent.
After curing, the Contractor shall deliver the cubes to an
approved laboratory for compression testing in accordance
with B.S. No.1881. One cube of each pair shall be tested at
seven (7) days and other cube tested at twenty-eight (28)
days. If the compression tests on any cubes do not show
compliance with the required compressive strengths at
twenty-eight (28) days, the placed concrete which is
represented by these cubes shall be subject to removal as
directed by the Engineer.
2. The Contractor shall furnish all equipment, material and
labour necessary for making, curing and transporting the
cubes to the testing laboratory.
66..00 REINFORCING STEEL BARS & FABRIC
6.1. General:
This work shall consist of furnishing and placing reinforcing
steel for concrete structures of the kind, size and quantity
designated to conform with the requirements of the Drawings or as
ordered and in accordance with the Specifications and the
Contract Documents.
6.2 Materials:
1. Reinforcing steel plain bars shall conform to the requirements of
ASTM A15-66, intermediate grade, with tensile strength between
40,000 to 60,000 psi, or B.S. No. 785.
2. Either reinforcing steel plain bars or reinforced steel deformed
bars may be used. Reinforcing steel deformed bars shall conform
to the requirements of ASTM -A1-66, intermediate grade, with
tensile strength between 40,000 to 60,000 psi, or B.S. No. 785.
3. The contractor shall have certified mill and/or laboratory test
results submitted to the Engineer showing compliance with these
Section VI. Specifications & Performance Requirements: BOJ – Structural Repairs to Tower Block
11 BS
requirements. The Contractor shall also have a certificate
submitted by the supplier stating that the reinforcing steel
complies with these requirements.
6.3 Steel Reinforcing Bars & Fabric:
1. Contractor to Check Drawings and Schedules:
The Contractor is responsible for checking the correctness of all
Drawings, Schedules, placement diagrams, etc. and the approval of
the Engineer shall be no way relieve the Contractor of the
responsibility for the correctness of such Drawings, Schedules,
etc.
2. Storage of Reinforcement:
Reinforcing steel shall be protected from injury and
deterioration at all times before being placed in the work it
shall be cleaned of all dirt, loose mill scale and rust, paint,
oil, grease or other foreign material. It shall be stored on
racks and covered to protect from the salt spray.
3. Bending of Bars:
All reinforcing steel bars shall be cold bent. Unless otherwise
shown on the Drawings or authorized by the Engineer, bends shall
be made in accordance with the following requirements:
a. Stirrups and tie bars shall be bent around a pin having a
diameter not less than twice the thickness of the bar.
b. Bends for other bars shall be made around a pin having a
diameter not less than six (6) times the minimum thickness
except for bars one inch or larger.
c. In the case of bars one inch or larger, the bends shall be
made around a pin having a minimum diameter of 8 bar
diameters.
4. Placing of Reinforcement:
All steel reinforcement shall be accurately placed in the
position shown on the Drawings and firmly held during the placing
and setting of concrete. Bars shall be tied at all
intersections. Distances from the forms shall be maintained by
means of stays, blocks, ties, chairs, hangers or other approved
supports. Blocks for holding reinforcement from contact with the
forms shall be precast mortar blocks of approved shape and
dimensions or approved metal chairs. Layers of bars shall be
separated by precast mortar blocks or by other equally suitable
devices. The use of pebbles, pieces of broken stone or block,
metal pipe and wooden blocks shall not be permitted.
Reinforcement in any member shall be placed and then inspected
and approved by the Engineer before the placing of concrete
Section VI. Specifications & Performance Requirements: BOJ – Structural Repairs to Tower Block
12 BS
begins. Concrete placed in violation of this regulation may be
rejected and its removal required.
5. Splices and Laps:
All reinforcement shall be furnished in the full lengths
indicated on the drawings. Splicing of bars except where shown
on the Drawings will not be permitted without the written
approval of the Engineer. Splices shall be staggered in so far
as possible.
Unless otherwise shown on the Drawings or as hereinafter
specified all bars shall be lapped a minimum of 40 diameters. In
lapped splices, the bars shall be placed in contact and tied
together.
There shall be no welding of reinforcement unless authorized by
the Engineer in writing.
6. Substitution of Bars:
Substitution of different size bars will be permitted only with
the specific written authorization of the Engineer. If
substitutions are allowed, the resulting area of reinforcement
shall be equal to the area called for on the Drawings or larger.
7. Cover to Reinforcement:
Where concrete is exposed to the ground, reinforcement shall have
a minimum cover of 3 inches of concrete and all other
reinforcement shall have a minimum cover of 2 inches of concrete,
unless otherwise shown on the Drawings.
8. Coating to Reinforcement:
All reinforcement exposed by demolition of existing concrete and
approved for re-use by the Engineer shall be wire-brushed to
remove all debris and coated as stipulated in Section 1.4 or
equivalent. All new reinforcement shall also be coated as above.
77..00 WINDOW SEALING
7.1 All existing sealing and/or caulking material between the masonry
opening and the window frame, and between the glass panel and the
window frame is to be removed. The debris is to be carted away.
The windows are to be resealed in both locations to prevent the
entry of air and/or moisture.
7.2 All surfaces are to be cleaned and free from loose, deleterious
materials before application of the sealant.
7.3 Where joint sizes exceed the manufacturers’ specifications for
sealant application, the joints shall be packed before sealant
application with either foam (backer rod) to form a proper
backing.
Section VI. Specifications & Performance Requirements: BOJ – Structural Repairs to Tower Block
13 BS
7.4 A secondary sealant of bronze caulking compound shall be applied
to joints between window frames and masonry openings. A bronze
silicone sealant shall be applied to joints between glass panels
and window frames.
7.5 The caulking compound and the silicone sealant shall each have a
manufacturers’ warranty of twenty-five (25) years.
7.6 The Bank of Jamaica (BOJ) shall be in continuous operation during
the resealing exercise hence the Contractor shall keep all
windows reasonably clean during the project.
7.7 The Contractor shall clean all windows on completion removing all
debris, discolorations and other surface damage resulting from
the works.
7.8 All windows broken, cracked or damaged during the project shall
be replaced by the Contractor at his own cost.
Section VI. Specifications & Performance Requirements:
BOJ – Structural Repairs to Tower Block
1 C /
1155..00 CCOONNCCRREETTEE
15.1. GENERAL
This work shall include non-prestressed concrete for use in building
works, culverts, walls, manholes, grating inlets, curb inlets,
concrete curbs, drop inlets and other concrete structures as
required. The concrete shall be composed of Portland Cement, fine
and coarse aggregate, admixtures as specified or ordered, and water,
prepared and constructed in accordance with these Specifications, at
the locations and of the form and dimensions shown on the Drawings
or as directed by the Engineer. It shall be of the classes
specified or as directed by the Engineer.
The Concrete shall be of four classes as defined below:
Slump (ins) Class Nominal Mix Minimum Crushing
Strength of Cubes at
Age 28 days - psi
3
A 1:1:2
5000
3 B 1:1.5:3 3750
3 C 1:2:4 3000
4 D 1:3:6 2000
All work shall conform with the requirements of the Specifications
and the Contract Documents.
15.2. MATERIALS
The materials for this work shall conform to the following
requirements:
1. Coarse Aggregate:
a. Coarse aggregate shall be crushed stone or gravel consisting
of clean, hard, tough, durable, cubical or angular fragments
of rock of uniform quality throughout. All particles retained
on 3/16" screen shall have at least one fracture face. It
shall be free from soft disintegrated pieces, mud, dirt,
organic or other injurious material and shall not contain more
than one percent of dust by dry weight.
b. Samples for tests of coarse aggregate will be taken from the
bins at the quarry or from approved storage piles at the
quarry site.
2. Soundness:
When tested with magnesium sulphate solution for soundness, using
A.A.S.H.O. Method T-104, coarse aggregate shall not have a loss of
more than 18 percent at the end of five cycles.
3. Loss on Abrasion:
Section VI. Specifications & Performance Requirements:
BOJ – Structural Repairs to Tower Block
2 C /
a. When tested by means of the Los Angeles Rattler, using
A.A.S.H.O. Method T-96, coarse aggregate shall not have a loss
of more than 40 percent.
b. After 20 hours immersion in water, a previously dried sample
of the coarse aggregate shall not gain in weight more than 17
percent.
c. The proportions in which the sizes of aggregate are to be
combined bay be changed at the direction of the Engineer.
4. Fine Aggregate:
a. Fine aggregate shall be washed natural sand, or sand derived
from crushing suitable gravel or stones, consisting of clean
hard, durable, uncoated particles of rock, free from lumps of
clay, soft or flaky material, loam, organic or other injurious
material.
b. Fine aggregate shall be uniformly graded from coarse to fine and shall meet the following gradation requirements:
Square Mesh Sieves
Percentage Passing
by Weight
3/8”
100
No. 4 97.5 +/- 2.5
No. 16 67.5 +/- 17.5
No. 30 38.5 +/- 18.5
No. 50 20.0 +/- 10
No. 100 6.0 +/- 4
c. Samples for tests of fine aggregate will be taken from
approved storage piles at the site of the batch plant or from
approved storage piles at the producing pit or from the site.
5. Cement:
a. Cement shall be Portland cement and shall conform in every
respect with all the conditions of British Standard 12:1978.
b. Provisions shall be made by the Contractor for storing cement
in a dry place.
c. Approved cement, which has become damaged by the action of the
elements or by any other cause prior to being placed in the
work, shall be rejected and removed from the site of the work.
Cement which contains hardened lumps or cakes shall be rejected and
removed from the site of the work.
6. Water:
The water shall be reasonably clean, shall not be salty or brackish
and shall be free from oil, acid or injurious alkali or vegetable
matter, or other deleterious substances. If required, water shall
be tested as prescribed by A.A.S.H.O. Method T-26. Water shall be
Section VI. Specifications & Performance Requirements:
BOJ – Structural Repairs to Tower Block
3 C /
taken from a public water supply, or any source approved by the
Engineer.
7. Additives:
The use of shall only be permitted where specially approved by the
Engineer on the application of the Contractor to meet requirements
of special circumstances.
15.3. CONCRETE
1. General:
a. Concrete shall be proportioned using the ingredients above and
shall have the minimum compressive strengths so defined.
b. All concrete shall have a slump of 3 to 4 inches when tested
in accordance with A.A.S.H.O. T119, unless in the opinion of
the Engineer job conditions warrant varying these limits.
c. Well in advance of the time when the placing of concrete is
expected to begin, the Contractor shall inform the Engineer as
to the source of all concrete ingredients which he proposes to
use and shall deliver samples of these concrete ingredients to
such testing laboratory as the Engineer may approve to permit
the making of tests on the aggregate to show compliance with
the foregoing requirements for all ingredients. These tests
shall be made at the Contractor's expense and the results
submitted together with the laboratory recommended complete
design mix to the Engineer for approval. The design mix shall
be based on dry weights of cement and aggregates. After
approval, at least three cubes for breaking at an age of seven
days and three for breaking at an age of 28 days will be
tested for each mix designed to be used. All such laboratory
work will be done at the Contractor's expense. If the results
of the seven day breaks are satisfactory to the Engineer he
may give tentative approval of the design mix. If the results
of the twenty-eight day breaks are satisfactory to the
Engineer, he will give approval of the design mix. No
concrete shall be used until the design of the mix has been so
approved.
d. The process shall be repeated at any time when there is a
change made in the quality or quantity of the concrete
ingredients and a new design mix submitted for approval.
e. All aggregates shall be so graded and proportioned as to
produce a plastic workable concrete that can be readily worked
into all corners and angles of the forms and around all
reinforcement without any segregation of the materials or the
collection of any free water on the surface.
2. Waterstops:
a. Waterstops shall be installed in joints as shown on the
Drawings. Should the Drawings fail to indicate a waterstop in
any joint exposed to view or where the seepage of any material
is objectionable, the Contractor shall install a waterstop.
Section VI. Specifications & Performance Requirements:
BOJ – Structural Repairs to Tower Block
4 C /
The waterstop shall extend at least three inches into the
concrete on each side of the joint, shall be joined to be
continuous and shall be carefully protected from damage until
covered or backfilled.
b. Waterstops shall be manufactured, formed and installed so as
to provide for the expansion and contraction movements present
at the joint.
c. Waterstops shall be fabricated from a plastic compound, the
basic resin of which shall be virgin polyvinyl chloride. The
compound shall contain any additional resins, plasticizers,
inhibitors or other materials such that when compounded it
shall meet the performance requirements specified. No
reclaimed polyvinyl chloride shall be used.
d. Waterstops shall be extruded in such a manner that any cross-
section shall be dense, homogeneous and free from porosity or
other imperfections. The cross-section of waterstops shall be
as shown on the Drawings.
3. Weepholes:
Weepholes shall be 4" diameter P.V.C. or Asbestos
Cement Pipe.
15.4. CURING MATERIALS
1. Cotton Mats:
Cotton mats shall conform to the requirements of A.A.S.H.O. M-73.
The mats shall not contain any materials such as dyes, sugar, etc.
that may be injurious to the concrete surface.
2. Waterproof Paper:
Waterproof Paper shall conform to the requirements of A.A.S.H.O. M-
139 and in addition shall not be less than 20 feet in length and
shall be of sufficient width to cover completely the surface of the
concrete.
3. Liquid Membrane-Forming Compound:
Liquid Membrane-Forming Compound shall have 100% resin base and
shall conform to the requirements of A.A.S.H.O. M-148, Type II,
white pigmented.
4. White Polyethylene Sheeting (Film):
White Polyethylene sheeting (film) shall conform to the requirements
of A.A.S.H.O. M-171.
15.5. CONCRETING
Section VI. Specifications & Performance Requirements:
BOJ – Structural Repairs to Tower Block
5 C /
All equipment and tools in the handling of material, trucks for
transporting material, the batching equipment, and concrete truck
mixers used for the mixing of concrete shall be suitable for the
purposes intended and approved by the Engineer.
1. Batching Equipment:
a. Batching equipment shall be such that all materials shall be
measured by weighing. The apparatus provided for weighing the
aggregates and the cement shall be suitably designed and
constructed for this purpose. The coarse aggregate, fine
aggregate and cement shall be weighed separately. The
accuracy of all weighing devices shall be such that successive
batches can be measured to within 1% of the required amount.
Cement in standard packages (sacks) need not be weighed but
bulk cement and fractional packages shall be weighed. All
measuring devices are subject to approval of the Engineer. If
at any time, the Engineer believes the scales are out of
adjustment, they shall be readjusted at the Contractor's
expense. Upon request of the Engineer, the Contractor shall
produce standard test weighs and check weighing equipment.
b. All materials for concrete shall be accurately proportioned.
Compensation in batch quantities of aggregate and water shall
be made to allow for moisture content of the aggregates.
2. Trucking Mixed Concrete:
a. The location and capacity of the batch plant and complement of
the truck mixers for truck mixed concrete shall be adequate
for continuous placement of concrete in the forms.
b. The batch plant, truck mixers and related equipment will be
inspected by the Engineer and these, as well as all methods of
operation related thereto, shall be approved before the
concrete is batched.
c. Concrete shall be incorporated in the work as soon as is
practicable after the time that water is first added to the
mix except that the Engineer reserves the right to vary any
times when necessary to achieve the requirements related to
set, plasticity, slump or air content. The concrete shall be
discharged within one and one-half hours from the time the dry
aggregates are loaded into the truck mixer, otherwise,
disposed of by the Contractor at his expense.
3. Site Mixed Concrete:
a. The concrete shall be mixed in an approved mechanical mixer.
The mixing shall continue for at least two minutes or for such
longer time as is required to ensure a uniformity of colour
and consistency of the mass. The mixer shall be under the
charge of a competent and experienced workman.
b. When mixing ceases for more than 15 minutes, or when changing
to a different type of cement, the mixer and all handling
plant shall be thoroughly washed out and cleaned.
Section VI. Specifications & Performance Requirements:
BOJ – Structural Repairs to Tower Block
6 C /
c. The Contractor shall furnish all equipment necessary and
labour to assist the Engineer in carrying out slump tests and
making test specimens.
4. Slump:
When the slump does not meet the specification requirements,
modification of the concrete mix may be permitted if, in the opinion
of the Engineer no harmful effect upon the permitted by the
Engineer, modifications shall be limited to the addition of not more
than 50 pounds of Portland Cement per cubic yard of concrete to
decrease the slump or to the addition of water to increase the
slump. The amount of water or cement added shall be further limited
to the minimum needed to meet slump requirements. The cost of
additional material and the work connected with each modification
shall be borne by the Contractor. The addition of cement or water,
or both, for the purpose of retempering concrete will not be
permitted.
5. Vibrators:
a. Vibrators shall be used as directed by the Engineer and shall
be of the mechanical immersion type. They shall be capable of
transmitting vibration to the concrete at frequencies of not
less than 4,500 impulses per minute.
b. Not less than 2 vibrators shall be available and in good
operating condition at each pouring of concrete in order to
ensure satisfactory and uninterrupted vibration during
placing.
c. Care shall be taken not to over vibrate the concrete.
15.6. FALSEWORK
All Falsework shall conform to the requirement of good practice,
shall be adequate for the purpose intended and subject to approval
by the Engineer.
15.7. FORMWORK
1. Forms shall be built true to lines and grades designated,
shall be strong, stable, firm, mortar-tight and adequately
braced or tied, or both. They shall be designed and
constructed to withstand all loads and pressures including
those imposed by plastic concrete, taking full account of the
stresses due to the rate of pour, effect of vibration and
conditions brought about by construction methods. Where
necessary, forms shall be constructed to compensate for
variations in camber of supporting members and allow for
deflections.
2. If requested, form work planes shall be submitted to the
Engineer by the Contractor before form work is started. The
furnishing of such plans, however, shall not serve to relieve
Section VI. Specifications & Performance Requirements:
BOJ – Structural Repairs to Tower Block
7 C /
the Contractor of any of his responsibility for the successful
completion of the work.
3. Forms shall be filleted at all sharp corners, unless otherwise
ordered or permitted and shall be given a slight bevel of
draft in the case of projections to ensure satisfactory
removal.
4. Materials for forms and their supports, ties and bracing,
shall be of the type, quality and strength to achieve the
foregoing requirements without impairment to the structural
qualities or appearance of the concrete structure. Form
material in contact with concrete shall be of a quality to
provide the hereinafter required concrete surface smoothness,
and, unless otherwise authorised, the contact surface shall be
oiled with a thin coat of a light, clear paraffin base oil
which will not damage, discolour or adhere to the concrete,
or, as an alternative, the form may be lined with an approved
composition form lining. Materials and workmanship for forms
for concrete to remain exposed in the finished work shall be
such as to provide a smooth concrete surface of good
appearance and texture, free of voids, indentations,
protrusions, or bulges and within tolerances consistent with
good trade practices. If panels are used, they shall be
evenly placed in columns or rows if their positioning is to be
visible after the concrete is finished. These same
requirements shall apply to forms for concrete not to remain
exposed in the finished work except that minor irregularities
where form boards or panels join the variations in form
pattern will be acceptable.
5. Metal ties and anchors to hold the forms in alignment and
location shall be so constructed that the metal work can be
removed to a depth of at least two inches from the concrete
surface without damage to the concrete. All cavities
resulting from the removal of metal ties shall be filled with
a stiff cement mortar of the same proportions used in the body
of the work and the surface finished smooth and even, and if
exposed in the finished work, shall conform to the texture and
colour of adjacent surfaces. With permission of the Engineer,
the Contractor need not remove from the underneath side of
bridge decks portions of metal devices used to support
reinforcing steel providing such devices of materials, or are
adequately coated with material, that will not rust or
corrode.
6. Temporary openings shall be provided at the base of forms
where necessary to facilitate cleaning and inspection
immediately before depositing concrete, as directed by the
Engineer.
15.8. HANDLING MATERIALS
During transportation, handling, storage, and until batched, the
different sizes and kinds of aggregate shall be kept separated, free
from deleterious materials, and methods that result in segregation
of sizes in any one aggregate shall be avoided. Individual
stockpiles for each size and kind shall be kept separated at the
Section VI. Specifications & Performance Requirements:
BOJ – Structural Repairs to Tower Block
8 C /
batch plant and at the quarry. Stockpiles shall be made on hard,
well drained ground areas, paved with planks or other suitable
material. Stockpiles shall be formed in such a manner that
segregation is kept minimum. Material shall not be stocked for such
length of time as would result in excessive fine materials near the
bottom of the piles. If washed aggregates are used they shall be
stockpiled not less than 24 hours before use after washing.
15.9. MIXING CONCRETE
The first batch of concrete materials placed in the mixer shall
contain an additional quantity of sand, cement and water sufficient
to coat the inside surface of the drum without diminishing the
mortar content of the mix. Upon the cessation of mixing for any
considerable length of time, the mixer shall be thoroughly cleaned.
1. Hand mixing:
Hand mixing will be permitted with the permission of the Engineer.
When permitted, it shall be done only on watertight platforms. The
sand shall be spread evenly over the platform and the cement spread
upon it. The sand and cement shall then be thoroughly mixed while
dry by means of shovels until the mixture is of a uniform colour,
after which it shall be formed into a "crater" and water added in an
amount necessary to produce mortar of the proper consistency. The
material upon the outer portion of the "crater" ring shall then be
shoveled to the centre and the entire mass turned and sliced until a
uniform consistency is produced. The coarse aggregate shall then be
thoroughly wetted and added to the mortar, and the entire mass
turned and returned at least 6 times and until all of the stone
particles are thoroughly covered with mortar and the mixture is of a
uniform colour and appearance. Hand mixed batches shall not exceed
1/2 cubic yard in volume and shall be placed within 30 minutes of
mixing. Hand mixing will not be permitted for concrete to be placed
under water.
15.10. PLACING CONCRETE
1. General:
a. The use of long chutes and troughs for conveying concrete from
the mixers to the forms will be permitted only on authority
from the Engineer. If such conveyors are allowed and the
quality of concrete as it reaches the forms or the methods of
placing or working it there in are not satisfactory, the
Engineer may order their use discontinued and substitution of
a satisfactory method of placing. Where steep slopes are
required, chutes and troughs shall be equipped with baffle
boards or be in short lengths that reverse the direction of
movement. All chutes, troughs and pipes shall be kept clean
and free from coatings or hardened concrete. Open troughs and
chutes shall be either of metal or metal lined and shall
extend as nearly as possible to the point of deposition. When
the discharge must be intermittent, a hopper or other device
for regulating the discharge shall be provided. A tremie may
be used in place of long chutes and troughs.
Section VI. Specifications & Performance Requirements:
BOJ – Structural Repairs to Tower Block
9 C /
b. Unless permission is obtained from the Engineer, concrete
shall not be dropped a distance of more than 5 feet and
special care shall be taken to fill each part of the forms by
depositing the concrete as near final position as possible.
In no case shall it be moved more than five feet. The coarse
aggregate shall be worked back from the forms and the concrete
forced around the reinforcement without displacing the bars.
After initial set of the concrete, the forms shall not be
jarred and no strain shall be placed on the ends of projecting
reinforcement.
c. Concrete shall be placed in horizontal layers, when less than
a complete layer is placed in one operation, it shall be
terminated in a vertical bulkhead. Each layer shall be placed
and compacted before the preceding layer has taken initial
set, to prevent injury to the green concrete and to avoid
surfaces of separation between the layers.
d. Concrete shall be compacted by continuous working with
suitable tools or by vibrating. The number and type of
vibrators required, the length of the vibrating period and the
location of the vibrators shall be as required by the
Engineer.
e. When the placing of concrete is temporarily discontinued, the
necessary keys or joints shall be formed as shown on the
Drawing or as ordered, and the concrete after becoming firm
enough to retain its form, shall be cleaned of laitance and
other objectionable material to sufficient depth to expose
sound concrete.
f. Joints shall be formed only in the locations shown on the
Drawings or as permitted by the Engineer. Feather edges at
construction joints will not be permitted.
g. Immediately following the discontinuance of the placing of
concrete, all accumulations of mortar splashed upon
reinforcing steel and the surface of the forms shall be
removed. Dried mortar chips and dust shall not be puddled
into the unset concrete. If accumulations are not removed
prior to the concrete becoming set, care shall be taken not to
injure or break the concrete steel bond, at and near the
surface of the concrete, while cleaning the reinforcing steel.
h. Workmen will not be permitted to walk in the fresh concrete
after it has been screened and all finishing work shall be
performed from bridges supported above the surface.
2. Depositing Concrete Under Water:
a. Concrete shall not be exposed to the action of water before
setting, or deposited in water, except with the approval of
the Engineer and under his immediate supervision. When
concrete is so deposited, the method and manner of placing
shall be as hereinafter designated.
Section VI. Specifications & Performance Requirements:
BOJ – Structural Repairs to Tower Block
10 C /
b. All concrete deposited under water shall be mixed in the
proportions designated for Class "B" Concrete with 10 percent
additional cement.
c. Concrete deposited under water shall be carefully placed in a
compacted mass in its final position by means of a tremie, a
bottom dump bucket or other approved method and shall not be
disturbed after being deposited. Special care must be
exercised to maintain still water at the point of deposit. No
concrete shall be placed in running water and all form work
designed to retain concrete under water shall be watertight.
The consistency of the concrete shall be carefully regulated
and special care shall be exercised to prevent segregation of
the materials. The method of depositing concrete shall be so
regulated as to produce approximately horizontal surfaces.
Concrete deposited under water shall be placed continuously
from start to finish whenever possible, and each succeeding
layer shall be placed before the preceding layer has taken
initial set.
d. When a tremie is used, it shall consist of a suitable hopper
and a tube having a diameter of not less than 10 inches. If
the tube is constructed in sections it shall have watertight
couplings. The means of supporting the tremie shall be such
as to permit the free movement of the discharge end over the
area of the work and shall be such as to permit it to be
rapidly lowered when necessary to choke off or retard the
flow. The discharge end shall be plugged at the start of the
work so as to prevent water from entering the tube and shall
be entirely sealed at all times, and the tremie tube kept full
of concrete to the bottom of the hopper. When a batch is
dumped into the hopper the tremie shall be slightly raised,
but not out of the concrete at the bottom, until the batch
discharges to the bottom of the hopper. The flow shall then
be stopped by lowering the tremie. The flow shall be
continuous until the work is complete.
e. When concrete is placed by means of a bottom dump bucket, the
bucket shall have a capacity of not less than one cubic yard.
The bucket shall be lowered gradually and carefully until it
rests upon the concrete already placed. It shall then be
raised slowly as the concrete is discharged, the intent being
to maintain, as nearly as possible, still water at the point
of discharge and to avoid agitating the mixture.
f. Before placing substructure concrete, all laitance or other
unsound material shall be removed from the surface of the
underwater concrete.
15.11. CONSTRUCTION JOINTS
1. When the placing of concrete is to be interrupted and a
construction joint formed, provision shall be made for
interlocking with the succeeding layer by roughening the
surface and providing keyways, dowels or similar construction
joints as shown on the Drawings or as ordered.
Section VI. Specifications & Performance Requirements:
BOJ – Structural Repairs to Tower Block
11 C /
2. In joining fresh concrete that has already set, the work
already in place shall have its surface cut over thoroughly
with a suitable tool to remove all loose and foreign material.
This surface shall then be washed and scrubbed with wire
brooms and thoroughly drenched with water until saturated. It
shall remain saturated until the new concrete is placed.
Immediately prior to the placing of the new concrete, all
forms shall be drawn tight against the concrete already in
place and the old surface shall be thoroughly coated with neat
cement or other suitable bonding material.
3. In construction joints exposed to view or other construction
joints where seepage of water is particularly objectionable, a
waterstop shall be inserted. This strip shall be placed not
less than 3 inches from the face of the concrete and shall
extend into each section of the concrete a distance of not
less than 3 inches.
15.12. EXPANSION JOINTS
1. Expansion joints shall be built at the locations and to the
dimensions and details shown on the Drawings. Open joints
shall be placed at locations designated on the Drawings and
shall be formed by the insertion and subsequent removal of
templets of wood, metal or other suitable material.
2. Filled joints shall be made with a joint filler, the materials
for which shall conform to the requirements of the Drawings.
3. Special types of expansion joints shall conform to the
dimensions and details shown on the Drawings.
15.13. CURING CONCRETE
1. General:
a. Concrete surfaces exposed to conditions causing premature
drying shall be protected and cured by covering at the
earliest possible moment after is has stiffened enough to
withstand surface damage. Roof and floor slabs and the top
slab of box culverts shall be covered with cotton mats and
shall be continuously kept wet by spraying for not less than
seven days and seven nights including holidays. All other
exposed concrete shall be protected and cured for not less
than seven days and seven nights, including holidays by
covering with cotton mats and spraying with water, covering
with waterproof paper, or sheeting, or applying liquid
membrane as the Engineer may approve or direct.
b. The Contractor shall have the option of curing concrete by any
of the curing methods described herein.
2. Moist Curing
After the surface of the concrete has been given its final
finish, it shall be protected by covering. The covering shall
be laid longitudinally over the surface of the finished
Section VI. Specifications & Performance Requirements:
BOJ – Structural Repairs to Tower Block
12 C /
concrete by unrolling from a supported roll so as not to bring
an excessive weight upon or to mar the new surface. After
placing, these covers shall be saturated for a period of 7
days and seven nights, including holidays, at the end of which
time they may be removed and no further wetting or artificial
curing will be required.
3. Cover Sheet Curing
a. As soon practicable after the finishing operations, paper or
polyethylene cover sheets as specified above shall be placed
in such a manner that the surface of the concrete shall not be
marred. The adjoining covers shall overlap at least 12 inches
and the lap shall be securely weighted down to form a closed
joint. On removal of the forms, the edges shall be covered
down to the bottom. The cover sheets shall remain in place
for a period of 7 days and 7 nights, including holidays.
b. In the event that hair-cracking develops before the cover can
be placed, the procedure set forth shall be modified at the
direction of the Engineer. Moist curing mats shall then be
used for the initial 24 hours of the curing period, and the
cover sheets placed for the remainder of the curing period.
c. Before reusing paper or polyethylene covers, they shall be
checked for holes or tears, and any such perforations shall be
repaired.
d. Covers which have become unserviceable will be rejected by the
Engineer.
4. Liquid Membrane-Forming Curing:
a. The liquid curing compound as specified above shall be applied
immediately following the disappearance of the water sheen
following the final finishing and before any marked
dehydration of the concrete or surface checking occurs. The
compound shall be applied by an approved mechanical pressure
sprayer delivering a fine even spray with uniform coverage.
This equipment shall be provided with a suitable device for
adequate agitation of the compound to prevent settlement.
b. Approved hand-held spray bars delivering a fine even spray may
be used, and the compound shall be drawn from a tank equipped
with an approved device to prevent settlement or by a method
which will prevent settlement.
c. If the compound is applied in two increments the second
application shall follow the first application within 30
minutes. The compound shall be applied in a continuous
uniform film at not less than one gallon for 200 square feet.
d. Transverse joints shall be protected from the compound by
means of methods approved by the Engineer.
e. When the forms are removed before 7 days after the concrete
has been placed, the exposed sides shall be pointed and
cleaned and then covered with the compound which shall be
Section VI. Specifications & Performance Requirements:
BOJ – Structural Repairs to Tower Block
13 C /
applied in a continuous film at the same rate as applied to
the surface.
f. If rain falls on the newly coated concrete before the film has
dried sufficiently to resist damage, or if the film is damaged
in any other way, the Contractor will be required to apply a
new coat of material to the affected areas equal in curing
value to that specified for the original coat. The treated
surface shall be protected by the Contractor from injury for a
period of at least 7 days and 7 nights, including holidays.
All traffic, either foot or otherwise, will be considered as
injurious to the film of the applied compound.
g. The Contractor shall have on the project sufficient approved
cover sheets or mats, for the protection of the concrete in
case of rain or breakdown of the spray equipment. The mats
shall be maintained in a wet condition, during their period of
use, as elsewhere hereinabove specified.
15.14. REMOVAL OF FORMS
1. The forms for any portion of a structure shall not be removed
until the concrete is strong enough to avoid possible injury
from such removal. Forms and their supports shall not be
removed without the approval of the Engineer. Supports shall
be removed in such a manner as to permit the concrete to
uniformly and gradually take the stresses due to its own
weight.
2. To facilitate finishing, side forms carrying no load may be
removed after 24 hours with the permission of the Engineer,
but the curing process shall be continued for 7 days and 7
nights, including holidays.
15.15. FINISHING
1. Surface Finish:
The surfaces of all concrete which shall remain exposed shall be
thoroughly worked during the operation of placing by means of tools
of an approved type. The working shall be such as to force all
coarse aggregate from the surface and thoroughly work the mortar
against the forms to produce a smooth finish free from water and air
pockets, segregated materials or honey-comb. Unless otherwise
authorised by the Engineer, the surface of the hardened concrete
shall be finished immediately after the removal of the forms. All
horizontal surfaces shall be given a float finish and all vertical
or sloping surfaces shall be given a Grout Clean Down Finish or a
finish as specified on the Drawings.
2. Float Finish:
a. This finish shall be formed by placing a excess of materials
in the form and removing or striking off such excess with a
Section VI. Specifications & Performance Requirements:
BOJ – Structural Repairs to Tower Block
14 C /
template, forcing the coarse aggregate below the mortar
surface. There shall be created no concave surfaces in which
water will be retained. After the concrete has been struck
off as above described the surface shall be thoroughly worked
and floated with a wood float, the operation to be performed
by skilled experienced concrete finishers. Before this last
finish has set, the surface shall be lightly stripped with a
fine brush to remove the surface cement film, leaving a fine
grained, smooth, but sanded texture. Curing, as specified
elsewhere shall follow.
b. Floor slabs shall be finished with a steel float.
15.16. TEST CUBES
1. During the progress of the work, field test cubes 6"x6" in
size shall be made and cured by the Contractor under the
direction of the Engineer, and in the number of four from
every pour of 100 cubic yards, or part thereof over 20 cubic
yards; two cubes each to be taken at two different times. For
any one pour, four cubes shall be taken regardless of size of
pour. The cubes shall be cured in the field by the same
methods as used for the concrete which they represent.
After curing the Contractor shall deliver the cubes to an
approved laboratory for compression testing in accordance with
B.S. No.1881. One cube of each pair shall be tested at seven
days and other cube tested at twenty-eights days. If the
compression tests on any cubes do not show compliance with the
required compressive strengths at twenty-eight days, the
placed concrete which is represented by these cubes shall be
subject to removal as directed by the Engineer.
2. The Contractor shall furnish all equipment, material and
labour necessary for making, curing and transporting the cubes
to the testing laboratory.
15.17. JOINT SEAL
1. The Contractor shall seal joints where shown on the Drawings
and elsewhere where directed by the Engineer.
2. Before placement of the sealing material the joints shall be
thoroughly cleaned of all scale, loose concrete dirt, dust,
other foreign matter. Projections of concrete into the joint
space shall be removed. The joint shall be cleaned and dry
before the sealing compound is applied.
3. The joints shall be sealed in a neat and workmanlike manner,
free from all dust and foreign matter.
4. When the work is completed, the joints shall effectively seal
against infiltration of moisture and water.
Section VI. Specifications & Performance Requirements:
BOJ – Structural Repairs to Tower Block
15 C /
5. The sealing compound shall be flush with, or not more than
one-eighth of an inch above the adjacent surface of concrete.
Where directed by the Engineer, the joint shall be smoothed
leveled to the adjacent surface by cutting off all excess
compound after the application. Any joint material which does
not adhere or bond with the concrete surface of the joint
shall be immediately removed and replaced at the Contractor's
expense.
6. The product of only one manufacturer shall be used on any one
structure.
Section VI. Specifications & Performance Requirements:
BOJ – Structural Repairs to Tower Block
1 RS /
1199..00 RREEIINNFFOORRCCIINNGG SSTTEEEELL BBAARRSS && FFAABBRRIICC
19.1. GENERAL
This work shall consist of furnishing and placing reinforcing steel
for concrete structures of the kind, size and quantity designated to
conform with the requirements of the Drawings or as ordered and in
accordance with the Specifications and the Contract Documents.
19.2. MATERIALS
1. Reinforcing steel plain bars shall conform to the requirements
of ASTM A15-66, intermediate grade, with tensile strength
between 70,000 to 90,000 psi, or B.S. No. 785.
2. Either reinforcing steel plain bars or reinforced steel
deformed bars may be used. Reinforcing steel deformed bars
shall conform to the requirements of ASTM -A1-66, intermediate
grade, with tensile strength between 70,000 to 90,000 psi, or
B.S. No. 785.
3. The contractor shall have certified mill and/or laboratory
test results submitted to the Engineer showing compliance with
these requirements. The Contractor shall also have a
certificate submitted by the supplier stating that the
reinforcing steel complies with these requirements.
19.3. STEEL REINFORCING BARS AND FABRIC
1. Contractor to Check Drawings and Schedules:
The Contractor is responsible for checking the correctness of
all Drawings, Schedules, placement diagrams, etc. and the
approval of the Engineer shall be no way relieve the
Contractor of the responsibility for the correctness of such
Drawings, Schedules, etc.
2. Storage of Reinforcement:
Reinforcing steel shall be protected from injury and
deterioration at all times. Before being placed in the work
it shall be cleaned of all dirt, loose mill scale and rust,
paint, oil, grease or other foreign material. It shall be
stored on racks and covered.
3. Bending of Bars:
All reinforcing steel bars shall be cold bent. Unless
otherwise shown on the Drawings or authorized by the Engineer,
bends shall be made in accordance with the following
requirements:
a. Stirrups and tie bars shall be bent around a pin having a
diameter not less than twice the thickness of the bar.
Section VI. Specifications & Performance Requirements:
BOJ – Structural Repairs to Tower Block
2 RS /
b. Bends for other bars shall be made around a pin having a
diameter not less than 6 times the minimum thickness except
for bars one inch or larger.
c. In the case of bars one inch or larger, the bends shall
be made around a pin having a minimum diameter of 8 bar
diameters.
4. Placing of Reinforcement:
All steel reinforcement shall be accurately placed in the
position shown on the Drawings and firmly held during the
placing and setting of concrete. Bars shall be tied at all
intersections, except where the spacing is less than one foot
in each direction, when alternate intersections shall be tied
unless otherwise indicated on the Drawings. Distances from
the forms shall be maintained by means of stays, blocks, ties,
chairs, hangers or other approved supports. Blocks for
holding reinforcement from contact with the forms shall be
precast mortar blocks or approved shape and dimensions or
approved metal chairs. Layers of bars shall be separated by
precast mortar blocks or by other equally suitable devices.
The use of pebbles, pieces of broken stone or block, metal
pipe and wooden blocks shall not be permitted. Reinforcement
in any member shall be placed and then inspected and approved
by the Engineer before the placing of concrete begins.
Concrete placed in violation of this regulation may be
rejected and its removal required.
5. Splices and Laps:
All reinforcement shall be furnished in the full lengths
indicated on the drawings. Splicing of bars except where
shown on the Drawings will not be permitted without the
written approval of the Engineer. Splices shall be staggered
in so far as possible.
Unless otherwise shown on the Drawings or as hereinafter
specified all bars shall be lapped a minimum of 40 diameters.
In lapped splices, the bars shall be placed in contact and
tied together. Welding of reinforcing steel for the purpose
of splicing shall not be permitted.
6. Substitution of Bars:
Substitution of different size bars will be permitted only
with the specific written authorization of the Engineer. If
substitutions are allowed, the resulting area of reinforcement
shall be equal to the area called for on the Drawings or
larger.
7. Cover to Reinforcement:
Where concrete is exposed to the ground, reinforcement shall
have a minimum cover of 3 inches of concrete and all other
reinforcement shall have a minimum cover of 2 inches of
concrete, unless otherwise shown on the Drawings.
Section VI. Specifications & Performance Requirements:
BOJ – Structural Repairs to Tower Block
PPW/1
2244..00 PPLLAASSTTEERRIINNGG,, PPAAVVIINNGG && WWAALLLL FFIINNIISSHHEESS
24.1 Sand
The sand shall be clean silica sand substantially free from salts,
alkali, loam clay or other deleterious matter, and entirely suitable
for rendering. It shall be stored to prevent its contamination with
solid or other chemical or vegetable impurities. Sand for
undercoats shall pass a 16 gauge sieve, and for finishing coats it
shall pass a 24 gauge sieve, for external walls and for internal
walls where specified and shall pass a 32 gauge sieve elsewhere
internally.
24.2 Cement
Cement is to be as described in concreting, and suitably cured for
plaster work.
24.3 Water
Water for mixing shall be clean and free from deleterious matter.
24.4 Mix and Application
All materials shall be stored, measured mixed and used in accordance
with recognised good practice as set out in British Standard Code or
Practice C.P. 211 (1949).
Cement and sand for internal and external plastering shall be
composed of 1 part of cement to 3 parts of sand proportioned by
volume in suitable gauge boxes. The mixture shall be wetted while
being well turned over with sufficient water to obtain a workable
plastic mass, and shall be used within half an hour after being
mixed with water.
The surface to be rendered shall be thoroughly hacked and wetted
before work is started. The undercoat shall be thrown on from the
trowel, levelled with a straight edge, scratched and allowed to dry
for not less than three days. The undercoat shall be well wetted
before the finishing coat is applied. The finishing coat shall be
thrown on from the trowel, levelled with a straight edge and brought
to a smooth wood float finish. Rendering shall be kept damp for at
least seven days after being applied.
Two coats rendering shall finish not less than 1/2" thick and shall
consist of a scratch coat with sand to pass a 16 gauge sieve and a
final coat with sand to pass a 24 gauge sieve. All rendering shall
be finished with a wood float to a fine granite finish unless
otherwise described.
24.5 Making Good
Section VI. Specifications & Performance Requirements:
BOJ – Structural Repairs to Tower Block
PPW/2
All making good or "patching" must be cut out to a rectangular shape
with undercut edges so as to form a dove tailed key and finish flush
with the surrounding surface.
24.6 Pebble Dash Finish
Pebble dash on external walls shall be applied in accordance with
B.S. Practice. Pebbles shall range in size from 1/4" - 1/2" and
thrown on dry on a 1/2" thick cement sand (1:3) backing coat at the
rate of 0.10 tons per square yard. Pebbles shall be free from clay,
vegetable or other deleterious matter and obtained from a source
approved by the Architect.
24.7 Sprayed Surface Finishes
The sprayed surface finishes shall be "Glaz-Tex" or "Renda-Tex" as
obtained from Caribspray Limited, 127 to 129 Maxfield Avenue,
Kingston 10 or other equal and approved. The finishes shall be of
the colour and texture described and shall be applied to the
concrete or plywood walls or ceilings by a firm approved by the
Architect and strictly in accordance with manufacturer’s
instructions. The rates for surface finishes shall include for all
edges, arises, cutting to line and for masking out of the adjacent
work and for taping joints as necessary.
24.8 Cement and Sand Paving and Screed
The proportions of the mix for cement and sand paving screed shall
be one part Portland Cement and three parts of sand (1:3).
Before laying screeds, the surface of the concrete shall be
roughened and thoroughly cleaned down and coated with a cement
slurry to provide the necessary key.
24.9 Paving
Surface finishing of the concrete floors and steps etc., shall be
steel or wood float finish to be carried out within thirty (30)
minutes of placing concrete. Care shall be taken not to have draw
too much excess fines to the surface and on no account shall neat
cement or a cement sand mix be dusted into or added to the concrete
surfaces. All surfaces showing such additions shall be rejected by
the Architect and the concrete floor demolished and removed from the
site. Float finish shall be left perfectly level or to the required
falls and shall be free from any trowel marks or other defects and
imperfections.
Floor hardeners shall be as described in "Concreting" to produce a
hard dense surface with high abrasive resistance, impervious to the
penetration of heavy oils, and or alkali, solutions, and to be used
strictly in accordance with the Manufacturers' instructions.
24.10 Cement Floor Tiling
Section VI. Specifications & Performance Requirements:
BOJ – Structural Repairs to Tower Block
PPW/3
The cement floor tiling shall be obtained from Vibro Tiles Limited,
Black River, St. Elizabeth. The tiles shall be properly cured, free
from hair cracks, discolouration, chipped arrises and from all
defects and be sound and hard and of a colour and texture as
approved by the Architect.
The tiles shall be laid, bedded and jointed in cement mortar (1:3)
and grouted with a mortar to match the colour of the tiles or as
directed by the Architect.
24.11 Terrazzo Floor Tiling
The terrazzo floor tiles are to be hydraulically pressed tiles
composed of coloured cement and hard wearing aggregate with keyed
backs and obtained from Gore Brothers Limited, or other approved
supplier. The tiles are to be properly cured, free from hair
cracks, discolouration, chipped arrises and from all other defects
and be sound, hard square tiles of colours approved by the
Architect.
The tiles shall be laid square, bedded and jointed in cement mortar
(1:3) and grouted up with neat tinted or white cement to match or
contrast with the tiles. After the tiling has been set, all surfaces
shall be ground, neutralized and sealed to the satisfaction of the
Architect.
The Contractor is to allow for providing tiles of differing colours
in various rooms if required.
24.12 Wall Tiling
The wall tiles shall be standard quality white to B.S., 1281 (1966).
Tiles shall be true to shape, free from all blemishes and from a
manufacturer approved by the Architect. All external angles shall
be rounded edge tiles of radius approved by the Architect and shall
bond with the tiling on each side.
The wall rendering or backing coat for tiles shall be cement sand
(1:3) applied 1/2" thick and finished with a steel float. The walls
shall be well wetted before applying the rendering.
The tiles shall be bedded in "Unibond" adhesive or other equal and
approved all in accordance with the manufacturer's instructions and
pointed in white cement.
24.13 Samples
The Contractor will be required to provide samples of the several
types of the floor finishes together with samples of the adhesive
and varnish to be used all as and when required by the Architect.
24.14 Protection
Section VI. Specifications & Performance Requirements:
BOJ – Structural Repairs to Tower Block
PPW/4
The Contractor shall allow for protection all the floor finishes and
leaving clean and perfect on completion. Carpets shall be properly
protected to the approval of the Architect while the hard pavings
shall be protected with a 2" layer of clean, moist, softwood sawdust
until the completion of the works. The sawdust shall be kept
continuously moist and cleared away on completion.
24.15 Prices to include for
The prices for plastering, paving and tiling shall include all
necessary dubbing out to obtain a true plane, extra labour working
behind and around pipes etc., forming neat angles, working in narrow
widths around stanchion projections, supply fixing and clearing away
all temporary rules and battens required.
Section VI. Specifications & Performance Requirements:
BOJ – Structural Repairs to Tower Block
GL/1
2266..00 GGLLAAZZIINNGG
26.1 Material
The glass shall be required to be the best of its respective kind
free from waves, air bubbles, air holes specks and other defects and
comply with B.S. 952.
Putty for use in glazing to woodwork shall be required to be
composed of the best linseed oil whiting and comply with B.S. 544.
26.2 Fixing Glass
All glass (unless fixed with beads and neoprene rubber gasket
strips) shall be required to be back puttied, sprigged, puttied
cleaned off and neatly finished.
Rebates shall be required to be painted one coat oil paint of dark
colour in addition to priming before glazing.
On completion, all glass shall be cleaned in and out to the
satisfaction of the Architect.
Section VI. Specifications & Performance Requirements:
BOJ – Structural Repairs to Tower Block
PA/1
2277..00 PPAAIINNTTIINNGG
27.1 Materials
The paints and varnishes shall be required to be the best quality
obtainable from one of the following firms: -
Sherwin Williams Limited
Berger Paints (Jamaica) Limited
West Indies Paints Limited
Brandram - Henderson (West Indies) Limited,
or other manufacturer approved by the Engineer and used strictly in
accordance with their printed instruction.
27.2 Sample Panels
2'0" x 2'0" sample boards showing the colours and tints of the
various paints, stains, varnishes, lacquers etc. to be used shall be
submitted to and be approved by the Engineer prior to painting.
27.3 Preparation
All surfaces are to be prepared with the correct knotting primers
sealers and stopping as required by the manufacturer's instructions
for each type of paint and surface and shall be applied accordingly.
All paints shall be thoroughly mixed or stirred before use. They
shall be so stored and sealed to minimize exposure to drying and
extremes of temperature.
The final coat of paint shall be applied after all dirty trades have
been completed. The protection of the finished work and touching up
shall be the Contractor's responsibility.
All new rendered or concrete surfaces shall be cleaned off, rubbed
down as necessary and shall be completely dry and clean of
efflorescence before any paint is applied.
All existing walls shall be properly cleaned off or washed down
before painting. All defective plaster shall be cut out and made
good in approved fashion before painting. Slight cracks shall be
made good with stopping.
In no case shall any paint or distemper be applied to concrete or
rendered surfaces until such surfaces are completely dried out and
clear of efflorescent tendencies.
All iron and steel work, before painting, is to be scraped and
cleaned with wire brush until all grease, scale, fur and loose
substances are removed. Each coat is to be carefully and evenly
applied. No coat is to be applied until the previous coat is hard,
dry and free from moisture.
Section VI. Specifications & Performance Requirements:
BOJ – Structural Repairs to Tower Block
PA/2
Where steelwork is shop-primed, any areas of damaged primer shall be
touched up in two coats of primer similar to that which was applied
in the shop and prepared as described above for iron and steelwork.
All paint on woodwork shall be rubbed down with fine glass paper
between each coat. Each coat shall be hard, dry and free from
moisture or condensation before the next coat is applied. All paint
on wood doors and frames shall be applied by means of spraying and
not by brushes. When spraying is being carried out the Contractor
must allow for protecting the adjoining work and leaving it free
from any spray.
All knots are to receive two coats of knotting applied thinly and
well brushed in. Loose knots shall be removed and the holes plugged
with sound wood. Large knots shall be cut back and made good with
hard stopping.
All woodwork specified as painted is to be primed before being fixed
in position.
The prices for painting shall include for all preparatory work as
described in this clause.
27.4 Workmen
Only skilled workmen are to be employed. A properly qualified
painting foreman is to be constantly on the job while the work is in
progress.
27.5 Fittings
All removable metal fittings are to be removed before the
preparatory processes are commenced and are to be fixed on
completion.
27.6 Colours
The Contractor is to allow for selecting and for carrying out the
painting work in the differing colours as directed by the Engineer
or shown in the painting schedule. The Contractor shall also allow
for painting individual rooms in "multi" or "parti" colours as
directed.
27.7 Covering Power
If any of the painted or decorated surfaces are deficient in
covering power, further coats must be added at the Contractor's own
expense, to the entire satisfaction of the Engineer.
27.8 Back Priming
Section VI. Specifications & Performance Requirements:
BOJ – Structural Repairs to Tower Block
PA/3
All exterior trim shall be back-primed before installation with
approved exterior base coat and all interior trim with approved
enamel undercoat. Tops, bottoms and edges of doors shall be
finished the same as the balance of the doors after they have been
fitted by the joiner.
27.9 Application
Rendered or concrete surfaces - Prepare as described and apply one
undercoat the same colour as finishing coat and one finishing coat
of emulsion paint.
Wood surfaces - paint - Knot, prime stop and fill as described rub
down and apply one undercoat and two finishing coats of oil paint.
Wood surfaces - natural finish - Prepare as described, rub down
apply one coat of approved wood sealer, one coat approved stain and
two coats of clear lacquer or clear varnish as described.
Metal work - Prepare as described and apply one coat of zinc
chromate primer and two finishing coats of alkalyd enamel. Touch up
shop primed metal work before applying finishing coats of paint.
Galvanised metal work shall be primed with an approved primer
suitable for galvanised work.
27.10 Completion
Allow for thorough cleaning of all floors, fittings, etc. cleaning
all glass both sides, touching up paint work where necessary,
clearing away all debris and rubbish and handing over the building
in a satisfactory condition, to the approval of the Engineer.
Section VII. Drawings: BOJ – Structural Repairs to Tower Block
SSEECCTTIIOONN VVIIII.. DDRRAAWWIINNGGSS
Section VII. Drawings: BOJ – Structural Repairs to Tower Block
Section VII. Drawings: BOJ – Structural Repairs to Tower Block
Section VII. Drawings: BOJ – Structural Repairs to Tower Block
Section VII. Drawings: BOJ – Structural Repairs to Tower Block
Section VII. Drawings: BOJ – Structural Repairs to Tower Block
Section VII. Drawings: BOJ – Structural Repairs to Tower Block
Section VIII. Bills of Quantities: BOJ – Structural Repairs to Tower Block
SSEECCTTIIOONN VVIIIIII.. BBIILLLLSS OOFF QQUUAANNTTIITTIIEESS
Section VIII. Bills of Quantities: BOJ – Structural Repairs to Tower Block
Section VIII. Bills of Quantities: BOJ – Structural Repairs to Tower Block
Section VIII. Bills of Quantities: BOJ – Structural Repairs to Tower Block
Section VIII. Bills of Quantities: BOJ – Structural Repairs to Tower Block
Section VIII. Bills of Quantities: BOJ – Structural Repairs to Tower Block
Section VIII. Bills of Quantities: BOJ – Structural Repairs to Tower Block
Section VIII. Bills of Quantities: BOJ – Structural Repairs to Tower Block
Section VIII. Bills of Quantities: BOJ – Structural Repairs to Tower Block
Section XI. Security Forms: BOJ – Structural Repairs to Tower Block
Section XI. Security Forms: BOJ – Structural Repairs to Tower Block
SSEECCTTIIOONN IIXX.. SSEECCUURRIITTYY FFOORRMMSS
Section XI. Security Forms: BOJ – Structural Repairs to Tower Block
FORM OF BID SECURITY (Bank Guarantee)
[If required, the Bank/Bidder shall fill in this Bank Guarantee form in
accordance with the instructions indicated in brackets.]
________________________________
[insert bank’s name, and address of issuing branch or office]
Beneficiary: Bank of Jamaica
Nethersole Place
Kingston
Date: [insert date]
BID GUARANTEE No.: [insert number]
We have been informed that [insert name of the Bidder; if a joint venture, list
complete legal names of partners] (hereinafter called "the Bidder") has submitted
to you its bid dated [insert date] (hereinafter called "the Bid") for the
execution of STRUCTURAL REPAIRS TO TOWER BLOCK under Invitation for Bids No.
[insert IFB number] (“the IFB”).
Furthermore, we understand that, according to your conditions, Bids must be
supported by a Bid Guarantee.
At the request of the Bidder, we [insert name of bank] hereby irrevocably
undertake to pay you any sum or sums not exceeding in total an amount of ([insert
amount in words]) [insert amount in figures expressed in the currency of the
Procuring Entity’s Country or the equivalent amount in an international freely
convertible currency] upon receipt by us of your first demand in writing
accompanied by a written statement stating that the Bidder is in breach of its
obligation(s) under the bid conditions, because the Bidder:
(a) has withdrawn its Bid during the period of bid validity
specified by the Bidder in the Form of Bid; or
(b) does not accept the correction of errors in accordance with the
Instructions to Bidders (hereinafter “the ITB”) of the IFB; or
(c) having been notified of the acceptance of its Bid by the Procuring
Entity during the period of bid validity, (i) fails or refuses to
execute the Contract Form, if required, or (ii) fails or refuses to
furnish the Performance Security, in accordance with the ITB.
This Guarantee shall expire: (a) if the Bidder is the successful bidder, upon
our receipt of copies of the Contract signed by the Bidder and of the Performance
Security issued to you by the Bidder; or (b) if the Bidder is not the successful
bidder, upon the earlier of (i) our receipt of a copy of your notification to the
Bidder that the Bidder was unsuccessful, or (ii) twenty-eight days after the
expiration of the Bidder’s Bid.
Consequently, any demand for payment under this Guarantee must be received by us
at the office on or before that date.
This Guarantee is subject to the Uniform Rules for Demand Guarantees,
International Chamber of Commerce Publication No. 458.
_____________________________
[signature(s) of authorized representative(s) ]
Section XI. Security Forms: BOJ – Structural Repairs to Tower Block
FORM OF BID SECURITY (Bid Bond)
[If required, the Surety/Bidder shall fill in this Bid Bond Form in
accordance with the instructions indicated in brackets.]
BOND NO. [insert Bond number]
BY THIS BOND [insert name of Bidder; if joint venture, insert complete
legal names of partners] as Principal (hereinafter called “the
Principal”), and [insert name, legal title, and address of Surety],
authorized to transact business in JAMAICA, as Surety (hereinafter called
“the Surety”), are held and firmly bound unto BANK OF JAMAICA, NETHERSOLE
PLACE, KINGSTON as Obligee (hereinafter called “the Procuring Entity”) in
the sum of [insert amount in words], [insert amount in figures expressed
in the currency of the Purchaser’s Country or the equivalent amount in an
international freely convertible currency] for the payment of which sum,
well and truly to be made, we, the said Principal and Surety, bind
ourselves, our successors and assigns, jointly and severally, firmly by
these presents.
WHEREAS the Principal has submitted a written Bid to the Procuring Entity
dated the [number] day of [month], [year], for the STRUCTURTAL REPAIRS TO
TOWER BLOCK (hereinafter called the “Bid”).
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that if the
Principal:
(1) withdraws its Bid during the period of bid validity specified in the
Form of Bid; or
(2) refuses to accept the correction of its Bid Price, pursuant to ITB
Sub-Clause 28.2; or
(3) having been notified of the acceptance of its Bid by the Procuring
Entity during the period of Bid validity;
(a) fails or refuses to execute the Form of Agreement in accordance
with the Instructions to Bidders, if required; or
(b) fails or refuses to furnish the Performance Security in
accordance with the Instructions to Bidders;
then the Surety undertakes to immediately pay to the Procuring Entity up
to the above amount upon receipt of the Procuring Entity’s first written
demand, without the Procuring Entity having to substantiate its demand,
provided that in its demand the Procuring Entity shall state that the
demand arises from the occurrence of any of the above events, specifying
which event(s) has occurred.
The Surety hereby agrees that its obligation shall remain in full force
and affect up to and including the date 28 days after the date of
expiration of the Bid validity as stated in the Invitation to Bid or
extended by the Procuring Entity at any time prior to this date, notice
of which extension(s) to the Surety being hereby waived.
IN TESTIMONY WHEREOF, the Principal and the Surety have caused these
presents to be executed in their respective names this [insert number]
day of [month], [year]
Section XI. Security Forms: BOJ – Structural Repairs to Tower Block
Principal: _______________________ Surety:
______________________________
Corporate Seal (where appropriate)
_______________________________ ________________________________
[insert signature(s) of authorized [insert signature(s) of authorized
representative(s)] representative(s)]
_______________________________ ________________________________
[insert printed name and title] [insert printed name and title]
Section XI. Security Forms: BOJ – Structural Repairs to Tower Block
PERFORMANCE BANK GUARANTEE
(Unconditional)
[The bank/successful Bidder providing the Guarantee shall fill in this
form in accordance with the instructions indicated in brackets, if the
Procuring Entity requires this type of security.]
[insert bank’s name, and address of issuing branch or office]
Beneficiary: Bank of Jamaica
Nethersole Place
Kingston
Date: [insert date]
PERFORMANCE GUARANTEE No.: [insert Performance Guarantee number]
We have been informed that [insert name of Contractor] (hereinafter
called "the Contractor") has entered into Contract No. [insert reference
number of the Contract] dated with you, for the execution of [insert name
of Contract and brief description of Works] (hereinafter called "the
Contract").
Furthermore, we understand that, according to the conditions of the
Contract, a performance guarantee is required.
At the request of the Contractor, we [insert name of Bank] hereby
irrevocably undertake to pay you any sum or sums not exceeding in total
an amount of ([insert amount in words]),26 [insert amount in figures] such
sum being payable in the types and proportions of currencies in which the
Contract Price is payable, upon receipt by us of your first demand in
writing accompanied by a written statement stating that the Contractor is
in breach of its obligation(s) under the Contract, without your needing
to prove or to show grounds for your demand or the sum specified therein.
This guarantee shall expire no later than twenty-eight days from the date
of issuance of the Taking-Over Certificate, calculated based on a copy of
such Certificate which shall be provided to us, or on the [insert number
day of [insert month], [insert year],27 whichever occurs first.
Consequently, any demand for payment under this guarantee must be
received by us at this office on or before that date.
26
The Guarantor (bank) shall insert an amount representing the percentage of the Contract Price specified in the
Contract and denominated either in the currency(ies) of the Contract or a freely convertible currency acceptable to
the Procuring Entity. 27
Insert the date twenty-eight days after the expected Completion date. The Procuring Entity should note that in the
event of an extension of the time for completion of the Contract, the Procuring Entity would need to request an
extension of this Guarantee from the Guarantor. Such request must be in writing and must be made prior to the
expiration date established in the Guarantee. In preparing this Guarantee, the Procuring Entity might consider
adding the following text to the form, at the end of the penultimate paragraph: “The Guarantor agrees to a one-
time extension of this Guarantee for a period not to exceed [six months][one year], in response to the Procuring
Entity’s written request for such extension, such request to be presented to the Guarantor before the expiry of the
Guarantee.”
Section XI. Security Forms: BOJ – Structural Repairs to Tower Block
This guarantee is subject to the Uniform Rules for Demand Guarantees,
International Chamber of Commerce Publication No. 458, except that
subparagraph (ii) of Sub-article 20(a) is hereby excluded.
_____________________
[signature(s) of an authorized representative(s) of the Bank ]
Section XI. Security Forms: BOJ – Structural Repairs to Tower Block
PERFORMANCE BOND
[The Surety/successful Bidder providing the Bond shall fill in this form
in accordance with the instructions indicated in brackets, if the
Procuring Entity requires this type of security]
By this Bond, [insert name and address of Contractor] as Principal
(hereinafter called “the Contractor”) and [insert name, legal title, and
address of surety, bonding company, or insurance company] as Surety
(hereinafter called “the Surety”), are held and firmly bound unto BANK OF
JAMAICA, NETHERSOLE PLACE, KINGSTON as Obligee (hereinafter called “the
Procuring Entity”) in the amount of [insert amount of Bond] [insert
amount of Bond in words],28 for the payment of which sum well and truly to
be made in the types and proportions of currencies in which the Contract
Price is payable, the Contractor and the Surety bind themselves, their
heirs, executors, administrators, successors, and assigns, jointly and
severally, firmly by these presents.
Whereas the Contractor has entered into a Contract with the Procuring
Entity dated29 the [insert number] day of [insert month], [insert year]
for [insert name of Contract] in accordance with the documents, plans,
specifications, and amendments thereto, which to the extent herein
provided for, are by reference made part hereof and are hereinafter
referred to as the Contract.
Now, therefore, the Condition of this Obligation is such that, if the
Contractor shall promptly and faithfully perform the said Contract
(including any amendments thereto), then this obligation shall be null
and void; otherwise it shall remain in full force and effect. Whenever
the Contractor shall be, and declared by the Procuring Entity to be, in
default under the Contract, the Procuring Entity having performed the
Procuring Entity’s obligations thereunder, the Surety may promptly remedy
the default, or shall promptly:
(1) complete the Contract in accordance with its terms and
conditions; or
(2) obtain a Bid or bids from qualified bidders for submission to the
Procuring Entity for completing the Contract in accordance with
its terms and conditions, and upon determination by the Procuring
Entity and the Surety of the lowest responsive Bidder, arrange
for a Contract between such Bidder and Procuring Entity and make
available as work progresses (even though there should be a
default or a succession of defaults under the Contract or
Contracts of completion arranged under this paragraph) sufficient
funds to pay the cost of completion less the balance of the
Contract Price; but not exceeding, including other costs and
damages for which the Surety may be liable hereunder, the amount
set forth in the first paragraph hereof. The term “Balance of
the Contract Price,” as used in this paragraph, shall mean the
total amount payable by the Procuring Entity to the Contractor
under the Contract, less the amount properly paid by the
Procuring Entity to the Contractor; or
28
An amount is to be inserted by the Surety, representing the percentage of the Contract Price specified in the
Contract Data, and denominated either in the currency(ies) of the Contract or in a freely convertible currency of
type and amount acceptable to the Procuring Entity. 29
Date of Letter of Acceptance or Agreement.
Section XI. Security Forms: BOJ – Structural Repairs to Tower Block
(3) pay the Procuring Entity the amount required by the Procuring
Entity to complete the Contract in accordance with its terms and
conditions up to a total not exceeding the amount of this Bond.
The Surety shall not be liable for a greater sum than the specified
penalty of this Bond.
Any suit under this Bond must be instituted before the expiration of one
year from the date of issuance of the Certificate of Completion.
No right of action shall accrue on this Bond to or for the use of any
person or corporation other than the Procuring Entity named herein or the
heirs, executors, administrators, successors, and assigns of the
Procuring Entity.
In testimony whereof, the Contractor has hereunto set its hand and
affixed its seal, and the Surety has caused these presents to be sealed
with its corporate seal duly attested by the signature of its legal
representative, this [insert day] day of [insert month], [insert year].
Signed by [insert signature(s) of authorized representative(s) ]
on behalf of [name of Contractor] in the capacity of [insert title(s)]
In the presence of [insert name and signature of witness]
Date [insert date]
Signed by [insert signature(s) of authorized representative(s) of
Surety]on behalf of [name of Surety ] in the capacity of [insert
title(s)]
In the presence of [insert name and signature of witness]
Date [insert date]
Section XI. Security Forms: BOJ – Structural Repairs to Tower Block
BANK GUARANTEE FOR ADVANCE PAYMENT
The bank/successful bidder providing the Guarantee shall fill in this
form in accordance with the instructions indicated in brackets, if an
Advance Payment is to be provided under the Contract
[insert Bank’s name, and address of issuing branch or office]
Beneficiary: Bank of Jamaica
Nethersole Place
Kingston
Date: [insert date]
ADVANCE PAYMENT GUARANTEE No.: [insert number]
We have been informed that [insert name of Contractor] (hereinafter
called "the Contractor") has entered into Contract No. [insert reference
number of the contract] dated [insert date] with you, for the execution
of [insert name of contract and brief description of Works] (hereinafter
called "the Contract").
Furthermore, we understand that, according to the conditions of the
Contract, an advance payment is to be made against an advance payment
guarantee in the sum or sums indicated below.
At the request of the Contractor, we [insert name of Bank] hereby
irrevocably undertake to pay you any sum or sums not exceeding in total
an amount of [insert amount in figures] ([insert amount in words]30) upon
receipt by us of your first demand in writing accompanied by a written
statement stating that the Contractor is in breach of its obligation
under the Contract because the Contractor used the Advance Payment for
purposes other than the costs of mobilization in respect of the Works.
It is a condition for any claim and payment under this guarantee to be
made that the Advance Payment referred to above must have been received
by the Contractor on its account number [insert account number] at
[insert name and address of Bank].
The maximum amount of this guarantee shall be progressively reduced by
the amount of the Advance Payment repaid by the Contractor as indicated
in copies of interim statements or payment certificates which shall be
presented to us. This guarantee shall expire, at the latest, upon our
receipt of a copy of the Interim Payment Certificate indicating that
eighty (80) percent of the Contract Price has been certified for payment,
or on the [insert number] day of [insert month], [insert year],31
30
The Guarantor shall insert an amount representing the amount of the Advance Payment and denominated either in
the currency(ies) of the Advance Payment as specified in the Contract, or in a freely convertible currency acceptable
to the Procuring Entity. 31
Insert the expected expiration date of the Time For Completion. The Procuring Entity should note that in the event
of an extension of the Time For Completion of the Contract, the Procuring Entity would need to request an extension
of this guarantee from the Guarantor. Such request must be in writing and must be made prior to the expiration
date established in the guarantee. In preparing this guarantee, the Procuring Entity might consider adding the
following text to the form, at the end of the penultimate paragraph: “ We agree to a one-time extension of this
Section XI. Security Forms: BOJ – Structural Repairs to Tower Block
whichever is earlier. Consequently, any demand for payment under this
guarantee must be received by us at this office on or before that date.
This guarantee is subject to the Uniform Rules for Demand Guarantees,
International Chamber of Commerce Publication No. 458.
_____________________
[insert signature(s) ) of authorized representative(s) of bank]
____________________________
guarantee for a period not to exceed [six months][one year], in response to the Procuring Entity’s written request for
such extension, such request to be presented to us before the expiry of the guarantee.”
]
INVITATION FOR BIDS (IFB)
Date: 20 September 2013
Structural Repairs To Tower Block: RFP # 2013-10-10-02
Bank of Jamaica invites sealed bids from eligible and qualified bidders for Structural Repairs to the Tower
Block. The facades of the Bank of Jamaica (BOJ) Tower have deteriorated resulting in spalling and cracking
of concrete, exposure of reinforcement, corrosion of reinforcement and other damaging effects. The
proposed works include the removal of damaged concrete, corroded reinforcement, placement of new
concrete with additives, placement of new reinforcement and resealing of the external windows. The
Specifications and the Bills of Quantities describe the works to be performed.
1. Eligibility: Bidders must possess a valid Tax Compliance Certificate and must be registered with the
National Contracts Commission in the following categories in order to participate:
(i) Civil Engineering –Grade 1, or
(ii) Building Construction –Grade 1
2. Availability: Interested eligible bidders may obtain further information from Head of Procurement, at
e-mail address [email protected] and may retrieve the bid documents which are available on the
Bank’s website (www.boj.org.jm) under the section “Tender” or at (www.boj.org.jm/rfp.php).
3. Bid Validity & Return of Bid: Bids shall be valid for a period of 180 days after bid closing and shall be
deposited in the tender box located at the Bank's information desk no later than the dates and the times
designated in the respective RFP on or before 20 September 2013. Late bids will be rejected.
4. Queries and Clarifications: All queries and requests for clarifications must be made by emailing
[email protected] on or before 06 September 2013, Subject: Queries/Clarification- RFP #2013-10-
10-02. Structural Repairs To Tower Block. Responses will be made available on the Bank's website
http://www.boj.org.jm/rfp.php by 13 September 2013.
5. Bid Security: Bids shall include a Bid Security issued by a bank or a by a surety using the form for bid
security (bank guarantee) included in Section IX Security Forms. The Bid Security shall be
$1,300,000.00.
6. Bid Opening: Bids will be opened in the presence of the bidders’ representatives who choose to attend at
the Bank of Jamaica, Nethersole Place, Kingston, Jamaica 10:15 a.m. on 20 September2013
7. Mandatory Site Visit: Bidders are required to attend a mandatory site visit at the BOJ, Nethersole Place
Building, and Kingston on Tuesday, 03 September 2013 at 10:00 a.m.
The Bank of Jamaica is not obliged to accept the lowest or any bid and reserves the right to terminate the
bid process at any point prior to the award of contract without incurring any liabilities to participating
bidders.