Upload
others
View
6
Download
0
Embed Size (px)
Citation preview
REPORT
ON
CONSOLIDATED EDISON'S
INDIAN POINT UNIT NO. 3
CONTAINMENT VESSEL
STRUCTURAL INTEGRITY TEST FOR
WEDCO CORPORATION
00 d6 engineers
C 8110240390 750221 PDR ADOCK 0500026 P PDR
REPORT ON
CONSOLIDATED EDISON' S INDIAN POINT UJNIT NO. 3
CONTAINMENT VESSEL STRUCTURAL INTEGRITY TEST
FOR WEDCO CORPORATION
PREPARED BY UNITED ENGINEERS & CONSTRUCTORS INC.
PHILADELPHIA, PENNSYLVANIA 19105
FEBRUARY 21, 1975
TABLE OF CONTENTS
PAGE NO.
I. PURPOSE 1-2
II. CONCLUSIONS 3-5
III. DESCRIPTION OF REACTOR CONTAINMENT STRUCTURE 6-11
I. Location 6 2. General Description of Structure 6-8 3. Design Basis 8 4. Material Specifications 9-11
IV. CONSTRUCTION 12-13
V. TEST PROCEDURES 14-18
1. General Description 14-15 2. Preparation 16-17 3. During Test 17-18 4. After Test 18
VI. INSTRUMENTATION 19-23
1. General Description 19 2. Invar Wire Extensometers 19-21 3. Concrete Crack Measurements 21-23 4. Data Acquisition Equipment 23
VII. TEST DATA 24
VIII. COMPARISON OF TEST DATA WITH"GROSS DEFORMATION 25-33 ACCEPTANCE CRITERIA"
i. Increase in Containment Diameter 25-26 2. Equipment Hatch Deformations 27-28
3. Vertical Elongation 28-29 4. Crack Width 30-32 5. Crack Spacing 32 6. Structural Recovery 32-33 7. Visual Inspection 33
IX. INTERPRETATION OF DATA NOT RELATED TO "GROSS 34-39 DEFORMATION ACCEPTANCE CRITERIA"
1. Equipment Hatch Diameter Change 34-35 2. Radial Deformation in Lower Containment (i.g. #32) 35-36 3. Concrete Cracking 36-39
X. TABLE I - INSTRUMENT LOCATION
-i-
XI. FIGURES
XII. APPENDIX A - UE&C Specification 9321-05-5-6 for "Structural
Integrity Test of Containment Structure"
XIII. APPENDIX B - "Criteria of Structural Integrity of Containment
Structure During Structural.Proof Test".
XIV. APPENDIX C - "Gross Deformation Acceptance Criteria"
XV. REFERENCE 1 "Structural Response of Secondary Containment Vessel During Structural
Integrity Test at Indian Point Power Generating Station Unit No. 3 Consolidated Edison Company" for WEDCO
Corporation, WJE No. 74301, Dated January 31, 1975.
-ii-
FIGURES
FIGURE 1 Stretch Out of Containment Building Outside Instrumentation
FIGURE 2 Stretch Out of Containment Building Inside Instrumentation
FIGURE 3 Liner Diameter Survey at Invar Wires
FIGURE 4 Diameter Change of Cylinder Wall
FIGURE 5 Vertical Deflections
FIGURE 6 Equipment Hatch Area Radial Growth
FIGURE 7 Special Liner Instrumentation
FIGURE 8 Seismic Rebar in Personnel Lock Area
-iii-
PURPOSE
"General Design Criterion 1, Quality Standards and Records" of Appendix A to
10 CFR Part 50 "General Design Criteria for Nuclear Power Plants" requires
that structures, systems and components of nuclear power plants important to
safety be tested to quality standards commensurate with the importance of the
safety function to be performed." In compliance with the above the preopera
tional Structural Integrity Test (S.I.T.) was performed to demonstrate the
structural capability of the containment to withstand postulated pressure loads.
The purpose of this report is to present the results, observations, compari
sons with expected responses and comparison with limiting responses for the
Unit #3 Reactor Containment Vessel during the Structural Integrity Test on
January 12, 1975 to January 14, 1975 and during the subsequent depressuriza
tion which was concluded on January 20, 1975.
The Unit #2 Reactor Containment Vessel was tested as a prototype vessel and
the results are reported in "Containment Vessel Structural Integrity Test for
Westinghouse Electric Corporation" dated May 28, 1971. The measurements taken
included liner strains, rebar strains and deformation patterns at the base of
the structure which were not part of the Gross Deformation Acceptance Criteria
but were used to verify the vessel design and various-design assumptions.
Since the design of Unit #3 is nearly identical to Unit #2 the primary purpose
of the S.I.T. was to verify that the structure was constructed in accordance
with the design drawings. On this basis it was necessary to monitor only those
items included in the "Gross Deformation Acceptance Criteria." This report
will also compare the results of the Unit #3 test with the comparable results
of the Unit #2 test.
-1-
I 1 U I I I I I I I I 3 I
PURPOSE (Continued)
Interpretation of data and conclusions concerning response of the structure
are based primarily on the structural behavior of the Containment Vessel
when subjected to a maximum internal pressure of 54 psig (115 percent of the
design pressure of 47 psig).
II CONCLUSIONS
Most of the S.I.T Instrumentation performed well and the recorded data is
valid. Of the 39 data points results were obtained at 38 points or 97% of
the points installed. At 1G #22 full extension of the gage was reached
soretime after the mid-point of the test. However from use of the points
obtained when results from 1G #22 were recorded and the almost linear in
crease in deformation with pressure noted on the other recording gages the
final reading of 1G #22 can be closely predicted.
The discussion of the results of the S.I.T. is based primarily on measure
ments at 54 psig. To put the magnitude of this pressure in perspective, 54
psig represents approximately 117,000,000 pounds of upward thrust at the
springline of the dome of the Containment Vessel. This is equivalent to the
thrust required to launch 16 Apollo XII rockets. To look at this in another
way, approximately 600,000 pounds of air was required to pressurize the Con
tainment to 54 psig. With this in mind, we present the following results:
1. All gross deformation measurements were less than those predicted in the
"Gross Deformation Acceptance Criteria (Appendix C). These are discussed
in Section VIII of this report.
2. The predictions in the "Criteria of Structural Integrity of the Containment
Structure During Structural Proof Test" (Appendix B) were not exceeded
except for the Equipment Hatch Diameter Change which was comparable to
the acceptance criteria. This does not present any concern and is dis
cussed in Section IX.
3. In general the results of the Unit #3 S.I.T. were less than the results
for Unit #2 as shown in Appendix B. There are several exceptions to this
II CONCLUSIONS (Continued)
to this statement, however, the radial deformations of the containment,
3 which are perhaps the most critical measurements, were less for Unit #3
in all cases. The exceptions to the above statement were:
a) The Equipment Hatch Diameter Change was greater for Unit #3 but within
I acceptable limits.
3b) The vertical. deformations in the cylinder were greater for Unit #3
than for Unit #2 but they were within 50% of the calculated de
formations. This indicates that horizontal concrete cracking was not 3 as great as assumed in design.
3 c) Concrete cracking, particularly in the area of the Personnel Lock was
greater than for Unit #2. The cracking satisfies the requirements of
3 the Gross Deformation Acceptance Criteria (Appendix C) and does not
cause any concern for Structural adequacy. Concrete cracking will be
Idiscussed in. detail in Sections VI II & IX of this report.
5d) Two gages (lG #2 and 1G #5) in the Equipment Hatch area measure radial
deflection slightly in excess of the corresponding gage for Unit #2,
Ihowever, they were both within the calculated and acceptance criteria. Ie) The gage measuring radial deflection at El. 56'-6" (lG #32) was slight
ly in excess of the corresponding gage for Unit #,however, it was
within the calculated and acceptance criteria.
1 4. The recovery of the structure after the test was within the requirements of
3 the Cross Deformation Acceptance Criteria (Appendix C).. No distress was
evident in the liner or concrete at the conclusion of the test.
-4-
II CONCLUSIONS (Continued)
On the basis of the data taken and the detailed information which follows,
the Containment Vessel generally behaved as predicted in design and was
within the limiting behavior and acceptance bounds.
-5-
III DESCRIPTION OF REACTOR CONTAINMENT STRUCTURE
1. Location
Indian Point Unit No. 3 is located adjacent to and south of Unit No. 1 on
a site of approximately 239 acres of land on the east bank of the Hudson
River at Indian Point, Village of Buchanan in upper Westchester County,
New York. The site is about 24 miles north of the New York City boundary
line.
2. General Description of Structure
The Reactor Containment structure is a reinforced concrete vertical right
cylinder with a flat base and hemispherical dome. A welded steel liner
is attached to the inside face of the concrete shell to insure a high de
gree of leak-tightness. All plate-to-plate welds are covered with pressur
ization channels to assure all leakage will be into the Containment during
a Design Basis Accident (DBA).
The structure consists of side walls measuring 148-feet from the liner on
the base to the springline of the dome, and an inside diameter of 135-feet.
The side walls of the cylinder and the dome are 4'-6" and 3'-6" thick re
spectively. The insidE radius of the dome is equal to the inside radius
of the cylinder so that the discontinuity at the springline due to the
change in thickness is on the outer surface. The flat concrete base mat
is 9-feet thick with the bottom liner plate located on top of this mat.
The bottom liner will be covered with 3-feet of concrete, the top of which
forms the floor of the Containment. The base mat is directly supported on
rock and the vector sum of the pressure forces is zero, therefore, no mech
anical anchors are required between the mat and the rock.
-6-
III DESCRIPTION OF REACTOR CONTAINMENT STRUCTURE (Continued)
Two (2) large openings are provided for access into the Containment struc
ture. The Personnel Lock is located in the south east quadrant with a
centerline elevation of 83'-6" and an opening size of 8'-6" diameter. The
Equipment Hatch is located in the north east quadrant of the Containment
with a centerline elevation of 101'-6" and an opening size of 16'-0" diam
eter. The Equipment Hatch has a Personnel Lock insert attached to the
Hatch cover. Eight (8) penetrations for Main Steam and Feedwater Piping,
43 for Mechanical Piping, 60 for Electrical requirements, two (2) for
Containment Ventilation Purge Ducts, and one (1) for the Fuel Transfer
Tube are also provided in the concrete cylinder wall.
Internal structures consist of Equipment Supports, Shielding, Reactor
Cavity, Canal for Fuel Transfer, and miscellaneous concrete and steel
for floors and stairs. All internal structures are supported on the mat
with the exception of fans and other equipment supported on intermediate
floors.
A 3-foot thick concrete ring wall serving as a secondary radiation shield
surrounds the Reactor Coolant system components and supports the 175-ton
polar-type Reactor Containment crane. A 2-foot thick reinforced concrete
floor covers the Reactor Coolant system with removable gratings in the
floor provided for crane access to the Reactor Coolant Pumps. The four
(4) Steam Generators, Pressurizer and various piping penetrate the floor.
The Refueling Canal connects the Reactor Cavity with the Fuel Transfer Tube
to the Spent Fuel Pool in the Fuel Storage Building. The 4'-0" thick con
crete walls of the canal provide shielding during the fuel handling oper
ation. The concrete walls and floor are lined with -inch thick stainless
III DESCRIPTION OF REACTOR CONTAINMENT STRUCTURE (Continued)
steel plate. The linings provide a leakproof membrane that is resistant
to abrasion and damage during fuel handling operation.
For a complete description of the Containment structure, see Chapter 5 in
the Indian Point No. 3 FSAR Docket 50-286.
3. Design Basis
The Containment structure completely encloses the entire Reactor and Re
actor Coolant system and ensures that essentially no leakage of radioactive
materials to the environment would result even if gross failure of the
Reactor Coolant system were to occur. The Liner and penetrations are de
signed to attain a sensitive and accurate means of monitoring and detecting
any leakage through the Containment. The structure provides biological
shielding for both normal and accident situations.,
The basic structural elements considered in the design of the Containment
structure are the base slab, side walls and dome acting as one structure
under all possible loading conditions. The liner is anchored to the con
crete shell by means of stud anchors so that it forms an integral part of
the entire composite structure under all loadings. During the SIT, the
reinforcing in the structure has an elastic response which limits the max
imum strains to insure the integrity of the steel. liner. The lower por
tions of the cylindrical liner are insulated to avoid deformation of the
liner due to restricted radial growth caused by the fixed wall to slab
connection, w hen subjected to a rise in temperature.
For a complete description of the design basis, see Containment Design
Report in Chapter 5 of the Indian Point Unit No. 3 FS -AR Docket 50-286.
II DESCRIPTION OF REACTOR CONTAINMENT STRUCTURE (Continued)
4. Material Specifications
a) Concrete
Concrete is a dense, durable mixture of sound coarse aggregate, fine
aggregate, cement, and water. Aggregates conform to American Society
for Testing Materials Specification C-33-64 "Standard Specifications
for Concrete Aggregates." *Aggregates consist of inert materials that
are clean, hard and durable, free from organic matter and uncoated
with clay or dirt. Fine aggregates consist of natural sand and the
coarse aggregates of crushed stone. Portland Cement conforms to
American Society for Testing and Materials (ASTM) Specification C-150
65 "Standard Specification for Portland Cement, Type II (moderate heat
of hydration requirements). Water is free from any injurious amounts
of acid, alkali, salts, oil, sediment or organic matter. The concrete
3 has a minimum density of 150 lb/ft .The 28-day standard compressive.
strength of the concrete is 3,000 psi. Adequate means of control were
used in the manufacture of the concrete to assure minimum strength re
quirements, placement and curing.
All design and testing of concrete samples was done by an independent
testing laboratory.
b) Reinforcing Steel
Reinforcing steel for the dome, cylindrical walls and base mnat is high
strength deformed billet steel bars conforming to ASTM Designation
A-432 (Designation later revised to A-615 Crade 6 0) Standard "Specifi
cation for Deformed Billet Steel Bars for Concrete Reinforcement."
III DESCRIPTION OF REACTOR CONTAINMENT STRUCTURE (Continued)
This steel has a minimum yield strength of 60,000 psi, a minimum ten
sile strength of 90,000 psi, and a minimum elongation of 7 percent in
an 8-inch specimen or 9% in 2-inches. Reinforcing bars No. 11 and
smaller in diameter were lapped spliced or spliced by the Cadweld pro
cess. Bars No. 14S and 18S were spliced by the Cadweld process. A
certification of physical properties and chemical. content of each heat
of reinforcing steel delivered to the job site was required from the
steel supplier. The splices used to join reinforcing bars were tested
to assure they will develop at least 125% of the minimum yield point
stress of the bar. The test program required cutting out, at random,
completed splices and testing to determine their breaking strength.
The capacity of splices is in accordance with American Concrete In
stitute (ACI) Code 318.
c) Steel Liner
The plate steel liner is carbon steel conforming to ASTM Designation
A442-65 "Standard Specifications for Carbon Steel Plates with Improved
Transition Properties," Grade 60. This steel has a minimum yield
strength of 32,000 psi and a minimum tensile strength of 60,000 psi
with an elongation of 22 percent in an 8 inch gage length at failure.
The liner is -inch thick at the bottom, -inch thick in the first
three courses except 3/4-inch thick at penetrations and 3/8-inch thick
for the remaining portion of the cylindrical walls and -inch thick
in the dome. The liner material was impact tested at a temperature
30OF below the service temperature (50OF) of the liner material. Im
pact testing was done in accordance with Section N331 of Section III
of the American Society of Mechanical Engineers (ASME) Boiler and
Pressure Vessel Code.
-10-
III DESCRIPTION OF REACTOR CONTAINMENT STRUCTURE (Continued)
The liner anchors are -inch diameter bent welding studs at a 14 inch
vertical spacing and 24 inch horizontal spacing in the region of the
3/8-inch liner plate. In the -inch liner plate region, a 28-inch
vertical and 24-inch horizontal spacing was used. The first course
of studs is an Elevation 44'-7 3/4". The studs are centered on vert
ical bars. In the dome 5'-0" by 5'-0" panels are anchored in the cen
ter by studs and by T-bars at the edges. The -inch diameter bent
welding studs are 9 inches long minimum and 9 inches long maximum
with a 2" - 900 hook at the end. Tests show the studs have a yield
value of approximately 52,000 psi and a tensile strength of 65,000 psi
and they can accommodate a shearing deflection of over .1" before
failure. A 100% visual inspection of liner anchors is made prior to
pouring concrete.
d) Liner Insulation
To protect approximately 18'-0" of the lower portion of the Contain
ment liner from severe temperature changes under accident conditions,
the liner is covered with insulation. The basic insulation is 7/8 inch
thick urethane foam cover with a inch thick gold bond fire shield
gypsum board and a 0.019 inch thick stainless steel jacket and backed
with asbestos paper cover on the unexposed side.
-11-
IV CONSTRUCTION
In order to evaluate and determine "as-built" conditions, which are necessary
to provide a basis for evaluating the results of the SIT, the following dis
cusses construction procedures and problems encountered during construction.
The containment liner in the cylinder and dome was erected independant of the
placement of the concrete shell and subjected to survey control during erection
to maintain erection tolerances for out-of-roundness, plumbness and local buck
ling within the requirements United Engineers & Constructors Inc. (UE&C) Specifi
cation 9321-05-225-1. All Deviations from the specification were subsequently
corrected before placement of concrete.
Concrete was placed in 5'-0" lifts. During pouring of concrete, the cylinder
portion of the liner was braced against deflection from concrete loads by a
circular truss on the inside of the liner. The dome portion of the liner was
restrained from buckling during dome concrete pouring by the addition of stiff
eners on the concrete side of the liner. Thus, at completion of liner-concrete
construction the inside liner tolerances were generally within the specification.
An exception to the above statement was found in the southwest quadrant of the
containment between elevations 142'-0" and 154'-0". During construction, after
concrete was poured,inward curvature of the liner plate exceeding specification
tolerances was discovered. Survey records show that this condition did not
exist before concrete was poured. Liner tolerances are specified during liner
erection to provide adequate control of the liner and to assure that no physi
cal interferences will exist with interior structures such as floor framing.
support columns, etc. The liner is not considered a load carrying member in
design and its primary function is to provide the leak tightness required of
the Containment Structure. Consequently the fact that the liner is out of
-12-
I I IV CONSTRUCTION (Continued)
specification tolerance after concrete is poured is not in itself a major con
cern. It is necessary to assure that the liner is backed by concrete and studs
I are intact to prevent uncontrolled independent deformation of the liner from
the concrete structure during accident conditions when the liner is subjected
i to compressive loads from thermal effects. In addition, piping seismic restraints
were attached to the liner in the vicinity of the portion of the Liner discussed
above. Since there is no sure method to check to assure that the liner is backed
5 by concrete it was decided to take advantage of the SIT to assure that the liner
is in fact backed by concrete. Three invar wire gages were attached to the liner
in the vicinity in question with the other end attached to the parked Polar Crane.
(See Figure 7) By comparing the radial deformation of these three points with
I the radial deformation of IG #23 20 ft. away, which is attached to liner plate
f which does not show any deviation from specification and can reasonably be expected
to be backed by concrete, the presence of a large void behind the liner plate
could be easily detected. The maximum difference in the radial deformation of
the three gages on the portion of the liner with inward curvature to 1G #23 occured
I in 1G 39 and was .082". Therefore, it can be concluded that concrete is backing
u the liner plate in this area since a .082" gap between the liner and concrete
could reasonably be expected to occur due to concrete shrinkage.
I To insure that there was no out-of-roundness at locations where inside diameter
I changes of the Containment structure were measured during the SIT, a Survey
was performed to ascertain the pre test Containment diameters at these locations.
I The results of this survey are shown in Figure 3. Thefdegree of out-of-round
ness did not affect the measurements taken as evidenced by the consistency in
I the results.
I " -13
I
V. TEST PROCEDURES
1. GENERAL DESCRIPTION
After completion of the construction of the entire Containment Vessel,
the SIT was performed. The maximum pressure attained during the test
was 54 psig (maintained for approximately six (6) hours). This pres
sure represented 115% of the design pressure of 47 psig. Readings
and measurements required for the SIT were taken at 0 psig, 12 psig,
21 psig. 41 psig and 54 psig while pressurization took place and at
41 psig, 18 psig, 21 psig, 41 psig and 0 psig during depressurization
and leak testing of the structure. Measurements were commenced one
hour after the Containment reached each pressure level to allow the
pressure and structural response to stabilize., In conjunction with the
SIT an Integrated Leak Rate Test (ILRT) was also performed. The dis
cussion of results of the ILRT and the Sensitive Leak Rate Test per
formed at the conclusion of the SIT and ILRT, is not within the scope
of this report.
The general requirement for the furnishing of all labor, tools,
supervision and equipment necessary to install all equipment and
record and interpret results for the SIT is found in UE&C Specifica
tion 9321-05-5-6 Revision 2 dated July 26, 1974 which is located in
Appendix A. Wiss Janney and Elstner and Associates (WJE) of North
brook, Ill. was retained to do this portion of the work.
criteria of Structural Integrity of the Containment Structure during
Structural Proof Test can be found in Appendix B. This document con
tains the calculated reading of invar wires for 54 psig based on
theoretical design procedures used for sizing structural elements
-14-
V TEST PROCEDURES (continued)
during the design of the Containment structure. These numbers were
used as a guide for interpretating WJE instrumentation readings and
determining whether the structure could be safely pressurized to the
next level.
Appendix C contains the Acceptance Criteria for the test and was
based on gross deformations of the structure. The primary function of
this criteria is to evaluate the performance of the structure during
the test by comparison with observed and measured test data. The
primary considerations include:
a) The increase in Containment Diameter (Expected deformation + 28%).
b) Equipment Hatch deformations (Expected deformation + 30%).
c) Vertical elongation of Containment wall at Elevation 191'-0"
(Expected value + 30%).
d) Maximum concrete crack width.
e) Minimum crack spacing.
f) Gage readings at return to 0 psig.
g) Post Test inspection.
The above acceptance criteria are developed based on the requirements
of Section CC-6213 of ASME Section III Division 2 which requires that
predicted deformations are not exceeded by 30% and rebar does not yield
during the test.
The conclusions reached in comparing acceptance criteria with test
data are discussed in Section VIII.
-15-
V TEST PROCEDURES
2. PREPARATION
Prior to the start of the test, the following steps were taken to
insure successful acquisition of meaningful test data and obtain
all required base data for the test:.
a) All equipment was calibrated in the WE laboratory prior to shipping.
b) Invar wires for measuring Gross Deformations were installed inside
the Containment and properly wired to readout equipment. All of
the wiring inside the Containment was brought to the outside of the
Containment by connection to a space Electrical Penetration.
c) Specified areas were sandblasted to facilitate detailed test crack
inspections. Existing cracks were measured and recorded prior to
the test.
d) The entire structure was surveyed with binoculars, telescopes or
visually to map cracks in the concrete and determine if any signifi
cant cracks were present which should be watched carefully during
the test. The largest crack was marked and plotted for monitoring
during the test. The results of the pre test crack inspection are
found in Reference 1. WJE reported no significant cracks were pre
sent. Small surface cracks are expected in a reinforced concrete
structure from thermal and dryi ng shrinkage. Cracks found were sur
face cracks with very few extending beyond the outer layer of rein
forcing.
e) Gross Deformation instruments were continuously monitored for some
time to establish electrical stability and determine ambient temper
ature effects if any.
-1.6-
f) Within an hour of the start of the pressure test, a complete set
of zero readings were recorded for all WJE instruments. This pro
vided a base for all readings taken during the test.
3. DURING TEST
At each pressure level the gross deformation data required for the SIT,
was obtained using a digital voltmeter, scanner and paper tape printout.
The output of all instrumentation was printed on a paper tape for
permanent records. All raw data obtained from the data system was in
voltage readings. Actual deflection readings were obtained by multi
plying the voltage change from initial reactings by any calibration
constant required.
Measurements of cracks were manually obtained from movable scaffolding
by WJE where required by the specifications.
The data was interpretated jointly by WJE and UE&C. Before proceeding
with pressurization to the next pressure level, the test director
consulted UE&C to assure that all required structural data was obtained
and that there were no indications that the structure was not respond
ing as designed. At no time during the test was there any cause,
related to the SIT, to delay pressurization to the next level. For a
further description of WJE's equipment and function during the SIT,
see Reference l. A complete description of the instrumentation used
during the test is given in Section VI.
In addition to the above, the structure was observed at required
pressure levels with binoculars, telescopes or visually to insure that
.no extreme behavior, including cracking, was occurring during pressuri-
-17-
V TEST PROCEDURES
aztion which would iniicate a problem in structural response to the
internal pressure load. No problems were encountered during the test
that caused any concern relative to the SIT.
4. AFTER TEST
Following completion of the test, all data secured was recorded and
reported by WJE. All equipment was checked for electrical stability
after final readings were taken at 0 psig and removed. A number of
frames were recalibrated in the laboratory to insure that the original
calibration had not changed. A final inspection was made to deter
mine crack widths and check for any visual distortion of the liner
plate. Most cracks returned to their original width and there was
no visual distortion of the linear plate.
-18-
VI INSTRUMENTATION
1. General Description
Location and type of instrumentation used for the SIT is shown in Figures
1 and 2. In addition, Table 1 contains further location details for all
instrumentation. All instrumentation consisted of Invar wire extensometers.
2. Invar Wire Extensometers
Invar wire extensometers were used to measure Gross Deformations of the
wall in the vicinity of the Equipment Hatch, the cylinder wall in the
horizontal and vertical direction, the dome in the horizontaland vertical
directions, and the diameter change of the Equipment Hatch.
Each invar wire measuring device consists of an invar wire spanning the
distance to be measured. The "dead" end is anchored to a fixed object in
side the Containment for measuring vertical or radial changes, or in the
case of wires measuring Containment diameter change, to the liner. The
"live" end is attached to a spring loaded frame which is rigidly attached,
in the direction of measurement, to the point where movement is being
measured. The sensing device is a linear potentiometer positioned between
the spring and actuated by relative movement between the fixed and free
end of the spring loaded frame. The potentiometer is of the infinite reso
lution type with a total resistence of about 2000 ohms. A constant voltage
of 1.4002 volts was applied to each potentiometer. Voltage changes in the
potentiometer are recorded on the external readout system. The data is
multiplied by appropriate correction factors and deformations of the struc
ture in inches are obtained. The UE&C specification (Appendix A) requires
that the instrumentation shall have capability of measuring gross deform
ations from 0 to 2" with a tolerance of + .01". This method of measuring
-19-
VI INSTRUMENTATION (Continued)
Gross Deformations was employed in the following areas:
a) At 15'locations in the thickened Equipment Hatch boss and the trans
ition area from the thickened boss to the 4'-6" cylinder wall to
measure radial deformation of the Containment wall. The live end of
the invar wire was attached to the liner inside the Containment and
the dead end was attached to a fixed object inside the building such
as the polar crane, pressurizer shield wall concrete, or 3'-0" thick
crane wall concrete.
b) At 10 locations, spaced at approximately 10'-0", in the Containment
cylinder wall between elevation 101'-0" and 191'-0" to measure diameter
change in the Containment Structure. These wires are stretched across
the diameter of the structure alternately from Azimuth 1350 to 3150,
150 to 1950 and 750 to 2550. Due to interferences at El. 161'-0", 1G
#23 was attached to the parked crane and consequently measured radius
deformation.
c) At Azimuth 150 on the Containment cylinder wall at Elevation 91'-0"
to measure radial deflection at this point. The "dead" end of the
wire is attached to interior concrete.
d) At Azimuth 3400 on the Containment cylinder wall at El. 56'-6" to
measure radial deflection at this point. The "dead" end of the wire
is attached to interior concrete.
e) At Elevations 95'-0", 143'-0" and 191'-0" on Azimuth 1200 in the Con
tainment cylinder wall to measure vertical deflection of the Contain
ment at these elevations. The "live" end of the wire is located at
the elevation to be measured and the "dead" end is located at elevation
-20-
VI INSTRUMENTATION (Continued)
46'-0" on a 3'-0" thick concrete slab located inside the building and
on top of the 9'-0" thick base mat.
f) Two (2) wires at Azimuths 3000 and 1200, extending from the springline
at elevation 191'-0" to the apex of thedome at elevation 258'-6", to
measure the vertical growth at the apex of the dome. These were angu
lar measurements and were converted to vertical measurements by use of:
an appropriate correction factor.
g) Two (2) wires in the Equipment Hatch stretching from Azimuth 450 to
2250 and 1350 to 3150 to measure the diameter change in the Equipment
Hatch.
h) Redundant gages were provided at Elevation 56'-6" and Elevation 191'-0"
to measure radial and diameter changes respectively. The redundant
gages were within .001" of their corresponding gage.
3. Concrete Crack Measurements
Before, during and after the SIT there are several crack surveys and measure
ments which are required to monitor the structure and provide additional
assurance that it is not responding in an unusual manner.
a) Prior to the test a visual inspection of the exterior exposed concrete
surface of the Containment was done with 7X to 15X binoculars, a Red
field 60X Spotting Scope and visually. Crack Patterns were mapped and
the size of the larger cracks recorded and observed during the test to
determine any enlargement in length or width. At 41 psi and at the
conclusion of the test the visual inspection described above was
repeated.
-21-
VI INSTRUMENTATION (Continued)
b) The largest crack observed in a) above was marked in red felt marking
pen and plotted. The change in width and extension was measured with
a 6X Pocket Comparator and a 1oX Bausch and Lomb crack measuring de
vice and recorded at each pressure level during pressurization. At
the conclusion of the test the measurement was repeated.
c) In the vicinity of the area designated for detailed crack inspection
at mid height of the structure, which is described in d) below, a
visual inspection was performed at 12,21 and/or 41 psig to determine
the pattern and occurance of the initial cracks. I
d) Prior to the test the following 5 areas were sandblasted and a i-0"
grid pattern was provided to facilitate detailed crack measurements
prior to the test, at peak pressure of 54 psig and after the test was
completed.
(1) A 10'-0" wide by 5'-0" high strip on the Containment wall between
Elevations 43'-3" and 48'-3" at Azimuth 1870.
(2) A 10'-0" wide by 5'-0" high strip on the Containment wall between
Elevations 115'-0" and 120'-0" at Azimuter 1290.
(3) A 10'-0" wide by 5'-0" high strip on the Containment wall between
Elevations 186'-0" and 191'-0" at Azimuth 1290.
(4) The upper left hand quadrant (viewed from outside of building) of
the Equipment Hatch Boss including a sector of the 4'-6" wall to
boss junction area.
(5) The upper right hand quadrant (viewed from outside of building) of
the Personnel Lock Boss including a sector of the 4'-6" wall to boss
junction area and 2'-0" of the 4'-6" wall adjacent to the transition
-22-sector.
VI INSTRUMENTATION (Continued)
A complete description of crack measurement and inspection is found
in Reference 1.
4. Data Acquisition Equipment
All data, except cracking information was obtained using a KAYE-TJAS re
cording system which includes a~ digital voltmeter, scanner, paper tape
printout and a clock. The data could be observed on the scanner and it
was printed on tape for permanent records. Sufficient redundancy was also
provided to assure that data would not be lost during the test. All raw
data obtained from the data system was in the form of voltage readings.
All deformation readings were obtained by multiplying the voltage change
from initial readings by any calibration constants required. The data
was reduced rapidly by hand and a quick review of voltage change was
adequate to detect any unexpected trends in structural response.
For further discussion of all the equipment and gages discussed above, see
Reference 1.
-23-
VII TEST DATA
For additional description of test procedures, preparation and instrumentation
and complete reporting of all test data, see the WJE report entitled "Struct
ural Response of Secondary Containment Vessel During Structural Integrity Test
at Indian Point Power Generating Station Unit No. 3 for WEDCO Corporation"
attached herein as Reference 1.
-24-
VIII COMPARISON OF TEST DATA WITH "GROSS DEFORMATION ACCEPTANCE
CRITERIA"
The Gross Deformation Acceptance Criteria, in Appendix C, constitutes the
criteria by which we will determine whether the test has properly demonstrated
the ability of the structure to respond to pressure as intended. On the basis
of this criteria, it can be seen that the structure has been constructed in
accordance with the design drawings to resist pressure loads. Each item in
Appendix C will be discussed below with regard to the above considerations.
1. Increase in Containment Diameter
Appendix C requires that the maximum (limiting) increase in Containment
Diameter shall not exceed 2.078" between Elevation 91'-0" and Elevation
191'-0" for the 54 psig internal pressure load when measured as an average
of all readings. The value of 2.078" is determined by calculating the
maximum expected diameter change based on the classical thin shell
membrane theory using the reinforcing bar and liner area as the spring
constant (i.e.,concrete assumed cracked) and conservatively adding a
factor of 2,8%. The calculated deformation +28% represents the deformation
at which hoop rebar would be expected to yield. Per Section CC-6000 of
ASME Section III Div. 2 this is a required limit on test results.
From test data in Reference 1, Appendix A, Table III, the maximum change
in diameter occurred at Elevation 101'-0" in the cylinder wall and was
equal to 1.39" (.694 radial deflection). This is within the limiting
displacement of 2.035 (@ El. 101'-0" - See Appendix B) and is less than
the calculated displacement of 1.59". Extending gage #22 data to 54 psi
(no data obtain at 54 psig due to faulty gage) a radial deformation of
about .700 was obtained. This will not change any conclusions regarding
-25-
VIII COMPARISON OF TEST DATA WITH "GROSS DEFORMATION ACCEPTANCE
CRITERIA (continued)
increase in diameter. On examining Figure 6, it can be seen that the
maximum radial deflections occurred in the middle portions of the
structure. This is in agreement with observation of crack patterns during
the test where it was discovered that the majority of all cracking occurred
in the middle third of the structure. This accounts for the decrease
in radial deflection in the cylinder wall as it approaches the springline.
A plot of diameter changes in the cylinder wall showing test data,
expected deformations and limiting deformations is found in Figure 4.
At no time does the test data exceed expected or limiting deformation.
In all cases, the radial or diameter growth for Unit #3 between Elevations
91' - 191'-O" is less than that for Unit #2. Since the general pattern
of diagonal rebar in Unit #3 is a greater spacing than for Unit #2, the
expected deformations were slightly greater for Unit #3.. Hence, the design
margin indicated by the test is slightly greater for Unit #3 than it was
for Unit #2.
Based on the above, it can be concluded that for this phase of structural
behavior, the structure has behaved very close to design assump tions and
has considerable safety margin.
It is our opinion that the above criteria is the most significant with
respect to judging the structural response of the Containment Building.
It is the most reliable measured quantity, and is based on the most
reliable theory and shows that the overall rebar configuration in the
structure is capable of elastically carrying pressure load as designed.
The pressure load is the maj or contributor to total rebar stress (See
Containment Design Report in Supplement of Volume of the Indian Point Unit
No. 3 FSAR). -26-
VIII COMPARISON OF TEST DATA WITH "GROSS DEFORMATION ACCEPTANCE
CRITERIA" (continued)
2. Equipment Hatch Deformations
Appendix C requires that Equipment Hatch deformations show the same trend
as computed values and the maximum radial displacement shall not exceed
.990". The value .990" is obtained by increasing the maximum expected
value of .760" by 30%, in accordance with the requirements of CC-6000 of
ASME Section III Div. 2. The analysis method employed in the Equipment Hatch
area was an approximate finite element computer analysis which necessitates
dividing the area into small rectangular elements, and modeling concrete
and rebar within the limits of the computer program to represent the
actual structure. In addition, assumptions must be made concerning the
amount of concrete which will crack during response to load. A complete
description of this analysis is located in the Containment Design Report
in Supplement 6 in Volume 6 of the Indian Point Unit No. 3 FSAR.
From test data in Table I, Appendix A of Reference 1, the maximum value
of radial deformation is .674 in I.G. #3. This is well within the
limiting maximum value of 0.99" and again is very close to the maximum
calculated value of .760". Of the 15 invar wires in the Equipment Hatch
area, no gages exhibit measured values in excess of the expected values in
Appendix B. In addition, all except 2 gages (I.G. #2 & I.G. #5 exhibited
radial deflections less than the corresponding gages on Unit #3. I.G. #2
is 3.2% and I.G. #3 is 6.6% in excess of Unit #2. Considering the statements
made above regarding the uncertainties involved in the analysis and the
influence of concrete cracking, the Equipment Hatch area shows good correlation
with predicted data. On this basis, it can be stated that the Gross
Deformation Acceptance Criteria have been satisfied for radial deformation
in the Equipment Hatch area.
-27-
VIII COMPARISON OF TEST DATA WITH "GROSS DEFORMATION ACCEPTANCE
CRITERIA" (Continued)
Figure 6 shows expected, actual and limiting displacements in the
Equipment Hatch area.
3. Vertical Elongation
Appendix C requires that the total vertical elongation of the Containment
Wall at Elevation 191'-O" (the springline) shall not exceed .959". This
value is based on the calculated .737" plus a 30%~ increase. The .731" is
based on resisting strength of the rebar and liner (concrete assumed
cracked). The 30% increase is for reasons outlined in Item 2 above. Test
data in Table II Appendix A of Reference 1 shows a vertical deflection at
Elevation 191'-O" at 54 psig equal to .334. This is within 50% of the
expected and limiting values. It can be seen in Appendix B that all
vertical deflections including the top of the dome are far below predicted
or limiting values. This is attributed to the fact that no evidence of
extensive horizontal concrete cracking occurred during the pressure test.
Stresses were approximately 450 psi in the vertical direction at the
54 psig pressure load. Present theory would indicate the concrete would
crack at this stress. However, reasons for reduction of horizontal concrete
may be explained by the following:
a) Considerable variation in stresses which cause concrete to fail in
tension.
b) Concrete trial mixes and test cylinders continually exhibiting
compressive strength in excess of the specified 3000 psi during
construction.
c) Vertical cracks from horizontal load (which is twice the vertical load
and resisted by the same area of concrete) formed between 12 psig and
-28-
VIII COMPARISON OF TEST DATA WITH "GROSS DEFORMATION ACCEPTANCE
CRITERIA" (continued)
21 psig indicating cracking stresses between 220 psi and 550 psi, both of
which are above expected values due to the reasons stated in 1) and 2)
above. This is less than the cracking stress in the vertical direction
for two reasons:
1) The dead load adds compressive stress in the vertical direction.
2) The concrete was in a state of uniaxial tension under high vertical
loads since the concrete had already cracked from the greater horizontal
loading. Before vertical cracking from horizontal loads occurred, the
concrete was in a state of biaxial tension which could have lowered
the ultimate tensile strength of the concrete in the horizontal
direction.
Figure 5 shows a plot of test data, expected and limiting deflections.
The above results, which indicate little or no horizontal cracking of the
concrete, are are far below design values, indicating that a margin of safety
exists in the structure. The rebar, which carries very little load until the
concrete cracks, will be stressed far below design values; consequently,
the test further demonstrates the ability of the structure to safely
respond to pressure loading.
In all locations of the cylinder the vertical elongation for Unit #3 was
greater than for Unit #2 indicating the existence of more horizontal
cracks. As noted above, however, values are still well within predicted
values. The total vertical growth at the apex of the dome, however, was
less than Unit #3 which indicates that dome concrete cracking was not as
extensive as Unit #2.
-29-
VIII COMPARISON OF TEST DATA WITH "GROSS DEFORMATION ACCEPTANCE
CRITERIA" (continued)
4. Crack Width
a) Appendix C requires that the maximum crack width shall not exceed .035"
averaged over 20'-0" length of crack. The value .035" was determined
by considering several approaches:
1) Recommendations in a paper entitled "Strength and Cracking
Characteristics of Beams with No. 14 and No. 18 Bars Spliced With
Mechanical Splices" by Mete A. Sosen and William L. Gamble was used
assuming the authors' maximum recommended slip in cadweld splices
based on their test results.
2) Recommendations for paper entitled "Determination of Minimum Wall
Thickness and Temperature Steel in Conventionally Reinforced Circ
ular Concrete Silos" from American Concrete Institute (ACI) Journal
July, 1970 by Sargis S. Safarian and Ernest C. Harris were used.
3) Considering the rebar stressed to 32 ksi (the maximum liner stress)
crack spacing and width was determined to accommodate the total
circumferential rebar strain.
4) Experience in testing of Reinforced Concrete Containment Structures.
Of the approaches mentioned above, 4) was considered the most reliable.
Consequently, the crack spacing and width were chosen based on previous
industry experience. The other approaches listed, for the most part,
substantiated the conclusions drawn from 4).
The crack width was averaged over a 20'-0" length to account for any
spalling of concrete due to inadequate concrete cover or any other
local effects which could occur during the test which would not be
-30-
VIII COMPARISON OF TEST DATA WITH "GROSS DEFORMATION ACCEPTANCE
CRITERIA" (Continued)
detrimental to the structural integrity of the Containment.
b) The following are the results of the various crack inspections required
by UE&C Specification 9321-05-5-6 (Appendix A).
i) The pre-test survey did not indicate any extensive cracking which
needed careful watching during the test. Most cracks were less
than .005 inches in width and could be attributed to normal shrinkage
and thermal effects. During the test addition horizontal cracking
was minimal and the majority of the vertical cracks were in the
middle third of the structure. In the membrane region of the
structure, cracks at 54 psi were generally less than .01" in width.
At 0 psig they closed to hairline width in the range of .005".
2) In accordance with the test requirements, the largest crack
measured during the pretest inspection was monitored during
pressurization. The crack occured at El. 99'-0" on Azimuth 2450
and measured .01" in width and increased to .018" at 54 psig. At
0 psig it closed to .01".
3) The largest crack in a sandblasted membrane region occurred at El.
115'-0" and Azimuth 1290 and measured .019" over 5 ft. at 54 psig.
This crack closed to hairline width at 0 psig. The largest crack
in a sandblasted region was .04" at the intersection of the
Personnel Lock boss transition concrete and the 4'-6" thick wall.
It was vertical and located in the Northeast corner. It extended
18". A .03" wide crack was found in the corresponding location in
the Equipment Hatch area. Both of these cracks closed to approx
imately .01" at 0 psig.
-31-
VIII COMPARISON OF TEST DATA WITH "GROSS DEFORMATION ACCEPTANCE
CRITERIA" (continued)
4) As can be seen from the above data,, the cr ack width criteria
is satisfied when averaging the crack widths over 20'-O". At no
point during the test did cracks indicate that any rebar was
stressed near yield.
5) For a complete description of crack surveys, see Appendix B Reference
1. This includes pre-test and test crack pattern mapping.
5. Crack Spacing
Appendix C requires that average crack spacing be not less than 15" excluding
crack patterns in areas affected by discontinuities. This criteria was
established based on experience with other Containment Vessel testing and was
established in a manner similar to and in conjunction with the crack
spacing discussed in 4 above. It was not considered practical to predict
crack spacing at areas of discontinuity due to the many unknowns, previously
discussed, that are associated with reinforced concrete in tension and the
complicated stress patterns at discontinuities also mentioned in prior
discussion.
In the membrane region, the vertical cracks were at approximately 18 inch
spacing, therefore, it is concluded that the above criteria has been
satisfied. The initial crack patterns developed during pressurization from
12 psig to 21 psig.
6. Structural Recovery
An additional requirement which was imposed in Appendix C is that all gage
readings shall return to 30% or less of maximum gage readings when the
Containment is depressurized to 0 psig. This is accordance with the
-32-
VIII COMPARISON OF TEST DATA WITH "GROSS DEFORMATION ACCEPTANCE
CRITERIA" (continued)
requirements of ASME Section III Div. 2 CC-3000. In all cases, this
criteria was satisfied with recoveries in the range of 70%-85%. Most
recoveries were more than 80% with only two gages close to the 70% limit.
Most gages recovered 70% or more at 5 psi.
7. Visual Inspection
The visual inspection of the liner and sandblasted concrete areas of the
Containment after the test showed no distortion of the liner or the
existence of unacceptable cracks.
As can be'seen from the above,all "Gross Deformation Acceptance Criteria"
(Appendix C) have been satisfied and the Containment Structure has successfully
demonstrated its ability to resist 115% of the design pressure load within
acceptable values. All responses were within the range predicted by the
various analytical methods.
-33-
IX INTERPRETATION OF DATA NOT RELATED TO GROSS DEFORMATION
ACCEPTANCE CRITERIA
The "Criteria of Structural Integrity of. Containment Structure During Structural
Proof Test" is located in Appendix B.' This criteria was developed to provide
a working document for reference during the test to aid in identifying any
serious abnormalities in structural behavior. It is not to be confused with
the Gross Deformation Acceptance Criteria in Appendix C described in Section VIII.
Appendix B is a table of preducted strains and deformations at 54 psi based on
analytical models used in design, where many assumptions are approximate and
conservative and consequently will not necessarily represent the exact behavior
of the structure. Although all items contained in Appendix B are not included
in the "Gross Deformation Acceptance Criteria" and are not considered in
justifying the adequacy of the structural integrity of the Containment Vessel,
the information is available and will be discussed below. It must be remembered
that conservative analytical assumptions, variations in material properties
such as modulus of elasticity of steel, compressive concrete strength, tensile
concrete strength and construction variations all contribute to the final
response of the structure; therefore, differences between measured values and
predicted values are not used for reaching conclusions concerning structural
integrity. If this data is viewed on the basis of trends for indications of
structural response, it can provide meaningful conclusions. With this in
mind, a brief review of all data not related to structural acceptance will be
discussed:
1. Eqjuipment Hatch Diameter Change
I.G. #33 and I.G. #34 measured the change in Equipment Hatch diameter. The
average diameter change of the two gages was 0.025". This is in excess of
the value of 0.017" predicted from the finite element computer analysis.
-34-
IX INTERPRETATION OF DATA NOT RELATED TO GROSS DEFORMATION
ACCEPTANCE CRITERIA (continued)
It is also slightly in excess of the Acceptance deflection of 0.022 inches
which is 30% in excess of the predicted value. As discussed above, the
finite element analysis is dependent on many assumptions regarding physical
properties, modeling, concrete cracking, etc. The Equipment Hatch, due to
discontinuity and non-uniform load distribution, is perhaps more sensitive
to these assumptions than any other area. This is not to say that the
validity of the analysis is in question, but to put the problem in perspective
one must look at the magnitude of measured values in I.G. #33 and I.G. #34.
On this basis, the measured values should certainly not be of concern in
assessing the structural capability of the containment structure. Recent
survey information indicates that the Equipment Hatch barrel and the concrete
opening measured on the outside of the Containment Wall are slightly ovalied.
In the finite element analysis model, the opening was idealized as round.
This may have contributed to the difference in magnitude of .008" between
measured and predicted deformation. It should also be remembered that the
gages across the Equipment Hatch Diameter were not included in the original
Unit #2 S.I.T. program but were added at Dr. N. Newmark's request at a site
meeting on May 2, 1969 to have this information available for future
considerations.
2. Radial Deformation in Lower Containment (I.G. #32)
Although I.G. # 32 measured slightly greater radial deformation than
measured by dial gages in the Unit #2 test, the measured radial deflection
of .274" is within the calculated value of .370" and the acceptable limit
of 0.480". El. 56'-6" is in the area of the containment shell influenced
by the discontinuity at the base of the structure. The distribution
-35-
IX INTERPRETATION OF DATA NOT RELATED TO GROSS DEFORMATION
ACCEPTANCE CRITERIA (continued)
of loads in this area is very dependent on the amount of concrete cracking
which occurs. It is, therefore, understandable that predictability of
deformation is more difficult in this area. The S.I.T. results indicate
that the concrete cracking was not as extensive as assumed in the original
design and the original design assumptions regarding concrete cracking
were conservative.
3. Concrete Cracking
The largest concrete crack appeared in a non-sandblasted area in the
vicinity of the Personnel Lock. It was located in the lower right hand
quadrant at the juncture of the transition zone from the thickened boss to
the cylinder wall. At 54 psig, the maximum crack was .1" in width and
extended vertically from the lower right hand corner about 3'-0". (See
Appendix B, Reference 1 for complete details of cracks in this area.)
Vertical cracks opened in all 4 corners of the Personnel Lock Boss and also
in transition zone juncture of the Equipment Hatch Boss. This was typically
the region of the largest cracks for both the Unit #2 and Unit #3 S.I.T.
However, since all other observed cracks in this area were typically in
the order of .03" - .04" it was decided to investigate this crack to
ascertain the impact, if any, of a crack of this magnitude on the behavior
of the structure. It was determined that, since the cracked area meets
the applicable Gross Deformation Acceptance Criteria and it can be under
stood why a crack of this magnitude could occur, the observed crack does
not indicate any failure of the structure to respond to the pressure load
as designed. A brief description of the salient points required to reach
these conclusions follows:
-36-
IX INTERPRETATION OF DATA NOT RELATED TO GROSS DEFORMATION
ACCEPTAN~CE CRITERIA (continued)
a) The average width of cracking over 20'-O" extending both horizontally
and vertically from the 3'-O" long .1" wide crack was .035" and .036"
respectively. This is within the Gross Deformation Acceptance Criteria
(Appendix C) of .035" averaged over 20'-O" when the accuracy of crack
measurement techniques is considered.
b) The juncture of the transition zone with the cylinder wall is a concrete*
discontinuity and cracking of concrete is expected at this point. This
is evidenced typically at all such locations in both Unit #1 and Unit #2.
Since rebar is designed to carrying all primary loads, this type of
concrete cracking, although esthetically disturbing, is not of structural
concern.
c) At all large openings, a discontinuity in shell action is created. The
primary capability to carry the moments and shears created by the dis
continuity is provided by the heavy reinforcement in the thickened boss
area. Review of analysis results indicates that discontinuity moments
and shears are substantially dissapated and shell behavior dominates
at the juncture with the cylinder where the cracks occurred. Thus,
the existence of the cracks do not relate to punching shear or other
discontinuity effects which would cause structural concern. The Unit #2
rebar strain gage test results indicate that the design for discontinuity
loads was conservative. Since Unit #3 is of the same design, there is
no reason to expect a different type response to pressure load.
d) The exterior shield walls outside the Personnel Lock form a rectangular
cross section. For architectural purposes, the thickened boss which
the shield walls butt up against (isolation is provided to allow for
-37-
IX INTERPRETATION OF DATA NOT RELATED TO GROSS DEFORMATION
ACCEPTANCE CRITERIA (continued)
for Containment Shell expansion) is also rectangular in shape. The
analysis of the Personnel Lock area is based upon the Finite Element
Analysis which was performed only for the Equipment Hatch area. The
Equipment Hatch, the surrounding thickened boss and the reinforcing
pattern are circular. In order to make the analysis valid for the
Personnel Lock area a circular reinforcing pattern was also provided.
Therefore, it can be seen that the four corners of the Personnel Lock
area, where larger cracks occurred, were not heavily reinforced and
are not important in the load carrying capability of the area. This
minimal reinforcing contributes to the cracking effect of the concrete
discontinuity discussed in Item b) above.
e) One may wonder, since these facts are applicable in all four corners of
the Lock and also on Unit #2, how the magnitude of the .1" crack can
be explained? A probable explanation is that on Unit #3 the seismic
rebar is located on the outside face of the structure as opposed to
the center of the cross section for Unit #2. This outer rebar, which
strengthens the concrete cover and prevents cracking and spalling, is
at 450 and is continuous around the equipment hatch opening. In order
to bend around the opening, a void of rebar can be visualized at the 4
corners of the thickened boss and transition zone (See Figure 8).
When this occurs, the vertical rebar becomes the facing rebar, but
is located about 9" from the outside face of the concrete. If the
rebar were placed so that the lower right quadrant has seismic rebar
bent to create a void as discussed above the existence of large cracks
in this area becomes inevitable.
-38-
IX INTERPRETATION OF DATA NOT RELATED TO GROSS DEFORMATION
ACCEPTANCE CRITERIA (continued)
f) At the conclusion of the test, the crack closed to .025" which is 75%~
of the maximum reading.. This is within the Gross Deformation Acceptance
Criteria for recovery. The area was closely monitored during depressuri
zation and pressurization after it was discovered and it responded by
opening and closing with pressure variations. This indicates that the
crack is not related to excessive rebar strains and further shows that
no problem exists.
In conc lusion, we have shown that all Gross Deformation Criteria have been
satisfied in the area of the largest cracks, their existence can be explained
by the reinforcing in the area and there is no evidence of structural distress
associated with the cracks. On this basis, it can be concluded that they do not
affect the ability of the structure to resist pressure loading as designed.
-39-
I I I I U I I I I I I I I I I I I I
N.
TABLE 1
TABLE 1
INSTRUMENTATION LOCATION
CYLINDER WALL AND DOME DISPLACEMENTS
INVAR WIRES STRUNG ACROSS DIAMETER OF
CONTAINMENT BUILDING
Sheet I of 3
I
II
]
[NVAR FROM
lIRE AZIMUTH
.G. 16 Interior Concrete
:.G. 17 750, 0'-011
E.G. 18 1350, 0'-0"
E.G. 19 150, 0'-0"
I.G. 20 750, o'-o"
I.G. 21 135 , 0'-0"
I.G. 22 15 , 0'-0"
I.G. 23 Parked Crane
I.G. 24 1350 0-0"
I.G. 25 150, 0'-0"
I.G. 26 1200, 0'-0"
I.G. 26a 7501 '-0"
I.G. 32 Interior Concrete
I.G. 32a Interior Concrete
TO AZIMUTH
150,
2550,
0 315
1950,
0 255
3150,
1510,
2550,
3150,
1950,
3000,
0 255
3400,
1 ,-l'
0'-0"1
0'-0"1
0'-0"1
0'-0"1
0' -0"
0'-0"1
0'-0"1
0'-0"1
0'-0"1
01-i1
3400, 01-0"1
(Work This Table With
ELEVATION
91' -0"
101'-0"
1111-0"
121'-0"
131'-0"
141'-0"
151' -0"
161'-0"
171'-0"
181'-0"
191'-0"
191'-0"
56'-6
56'-6
Figure 2)
TO MEASURE
Radial Displacement
Diameter Change
Diameter Change
Diameter Change
Diameter Change
Diameter Change
Diameter Change
Radial Displacement
Diameter Change
Diameter Change
.Diameter Change
Diameter Change
Radial Displacement
Radial Displacement
INVAR WIRE
I.G. 29
I.G. 30
I.G. 31
INVAR WIRES CONNECTED TO BASE
AT ELEVATION 46'-0" AND CYLINDER WALL
AT AZIMUTH ELEVATION TO MEASURE
4'-0 South of 1200, 0'-0" 95'-0" Vertical Displacement
2'-0 South of 120 0, 0" 143'-0" Vertical Displacement
120 , 0'-0" 191'-0" Vertical Displacement
(Work This Table With Figure 2)
TABLE 1 (cont'd)
DOME DISPLACEMENTSheet 2 of 3
INVAR WIRE
Apex @ El. 258'-6"
Springline (a El. 191'-0" Azimuth 3000, 0'-0"
Springline @ El. 191'-0" Azimuth 1200 0'-0"
Apex @ El. 258'-6"
(Work This Table With Figure 2)
EQUIPMENT HATCH - DIAMETER CHANGE
INVAR WIRES STRUNG ACROSS DIAMETER OF
EQUIPMENT HATCH
INVAR WIRES AZIMUTH OF EOUIPMENT HATCH
I.G. 33 From 450, 0'-0" to 2250, 0'-0"
I.G. 34 From 1350, 0'-0" to 3150, 0'-0"
(Work This Table With Figure 1)
EQUIPMENT HATCH - RADIAL DISPLACEMENT INVAR WIRES STRUNG FROM FIXED POINT INSIDE THE CONTAINMENT BUILDING (CRANE WALL, PRESSURIZER SHIELD WALL, CRANE) TO THE FOLLOWING LOCATIONS
OF THE INSIDE OF THE LINER
INVAR WIRE AZIMUTH ON EQUIPMENT HATCH
(Viewed from Inside)
I.G. 1
I.G. 2
I.G. 3
I.G. 4
3050
3050
3050
2500
FROM
I.G. 27
I.G. 28
ELEVATION
106.66'
110.10'
112.97'
98.42'
TABLE 1 (cont'd)
Sheet 3 of 3
EQUIPMENT HATCH - RADIAL DISPLACEMENT
INVAR WIRES STRUNG FROM FIXED POINT INSIDE THE
CONTAINMENT BUILDING (CRANE WALL, PRESSURIZER
SHIELD WALL, CRANE) TO THE FOLLOWING LOCATIONS
ON THE INSIDE OF THE LINER (cont'd)
INVAR WIRE AZIMUTH ON EQUIPMENT HATCH ELEVATION
(Viewed from Inside)
I.G. 5 2500 96.37'
I.G. 6 2500 94.66'
I.G. 7 1100 98.42'
I.G. 8 1100 96.37'
I.G. 9 1100 94.66'
I.G. 10 550 106.66'
I.G. 12 550 110.10
I.G. 12 550 112.17'
I.G. 13 0 110.5'
I.G. 14 0 116.5'
I.G. 15 00 121.5'
(Work This Table With Figure 1)
FIGURE S
14
~L. -42-G
EL 2 C5,0'-t
v'/ E
-. ____________________________ I t.
U. 2~----- ---
E L 170 C> L IGO-O
1?- ~ ,-0
(TrIP~ 5 MT
~SPRlNG LINE (EL. I~l-o')
'F I9Ko
I r~EL.,S6-O I
187"
L.48L3 EL. 433E
EL. 12o.0
E L 115'o
161. 3 4
N
-9 00( E)
180o(s)
-3 -J
LoCAT ICK
1N$TRYMEt.JTATIcL-w rA~
SANDBLA5TED ,L)RFACE
Gf(JRE I
P LAN4
II
.............
----------
EL.Z58 -6 .- j
EL. Z4O'-O----14.,_ EL. E30 -O0
EL-.2 10'-O 0b
EL. 190t-0----*-~
E L. I180'- 0__
EL.1 0 1- ---------- I.G. I L.C 1
I.G.3
ELI I~-O----- ~EL. Io'-G~x- EL10 0-- .EQUIPJ)4kCY
EL.8& 0I.G.0
E L.G C)- 0I.G.5
EL. 5O--,-*
(TOP OF BASE MAT)'
lW5Tp~uMvENTATION SYMBOLS
+ INVAR WIRE~ GUAGE (I.G.~)
00o (N*)
4EQU IP. H ATC H
2700(W)
~PER SCNQWEL
LO0(S
NOTE:
FOR INSTRUMENTATION LOCATION SEE TABLE
FIGURE IL STRETCH- OUT OF CONTA9'WKIKT BUILDINJG INSIDE INSTRUYMENTAT1(r'N
9 C) " (E)
LOCATION PLAN
/ Jo
,'4)
'I
7 -~ -,
/Y
SPRING LINE., I5 3 OIFT. /
13 5. 14 FT.
1352 0 FoT134.193 FT'
134..._9 2-FT.
1 34.189 FT.
135.. FT.
134.16CFT.
-"EL.4ro'-O
KEY PLAN
EL. 191'- 0
.EL. -TILo
. __ _ E L 1- Io0
E.. EL. 15 '-0
K ,-EL. I4_1:0
-KEL1'-I0 ... /EL. II I-O
.... E...K . L. oI .o
FIGURE 3 LEL. 4 35- LINER DIAMETER
SURVEY AT IkHVAR WIRES
SECTION A-A
2 2
vi ui Vi
W 0
J9 1 P - - L . ....------... -"
vii4
I'J (G I'- o
IS 8 O I'0 - - t.. . ....... ...... . ... ... ... . .
I7-C --------I I
< 141- - ---
2 1
oo 0,. .04.I-OZo3,Q W7,09
< 141 -0 . . . .... . ....... .. ....... ..... .... ... ...
t2 ' . . . I
_ i--- H/ -i
• 00 30 40.50 .Go.7o .9o . 1 0 .2o .300 .40 .,70.50.0 , 0, ,,E .2o.5o.40o
DIAMETER CHANGE (INCHES) IN CYLINDER WALL
.LEGEND THEORETICAL DEFLECTION @ 5-4 PS. IG.
LIMITING DEFLECTION @ 54 P.S.I.G. ACTUAL DEFLECTIOI'] DURING PRESSURIZATION
FIGURE 4 DIAMET.R C;., G7.E
OF CYL i N DE' L.L
cc- a: ":'
(~\j - . --
,30 .40 Q .60 .70 .80 .90 .6o .10 .ZO .30 .40 ,
VERTICAL DEFLECTION (INCHES)
IN CYLINDER WALL
LEGENDTHEORETICAL DEFLECTION @ 54 P.S.I.G.
LIMITING DEFLECTION @ 54 P.S.I.G.
ACTUAL DEFLECTION DURING PPESSURIZATION
FIGURE 5 SHEET 1 OF 2
VERTICAL DEFLECTIONS
iWVAP. WRE GAUGES
3I1'-0
I81r-o
171
I(iL0
15 1- c
41'-0
13! -0
I I'0
111~0
qkt0
GO P516
50PSIG
40 P5SG -
so Psv~
?OPSIG
1O PSiG
U I.I,
2 4.) -I
- Ip 4 -r .. .
-I I - - --/....
]1
,1<
* I
***~*.f f
K K
-- Il
'I
- 1
i I r
I . 1
, I
S I I
-m . - I . . . .
-60 Hi.H30'40.-tlfrrT-ttt- I II I95 .2,i ..*4 ++4f++tt 10 .+H+ H+ t +. .... 0 ,O30. .50 GO 70.80.903 .40.50 .7 . 0.0 ., . , . 0
VERTICAL DISPLACEMENT (INCHES)
AT APEX OF DOME@ EL .43'-0"
LEGEND I - am--I
-mmw - -
THEORETICAL DEFLECTION-7 BASED ON
LIMITING DEFLECTION CRACKED CONC,
EN FIGURE 5 ACTUAL DEFLEC.ITION UNCRACKEDSHEET 2 OF 2 VERTICAL DEFLECTION
ACTUAL DEFLECTION ND DURING DEPRESSURIZATIOJUNCRACKED
Ld
Lk Irv
IlL
RELATI10N
F-
TO BAS E
cloI c-- )s I i5r,
RADIAL SLAEhT c'A I.G. I (EL.IOG.GG.')
0 ..5 30AC o ., .83.9'1.00 RADIAL DISPLACEMENT (INCHES)
I. G84Y
* I * I o~o~05 orA -. 7' 80 9a,
RADIAL DISPLACEMENT(INCHES)L G. L-(E L.I 10. 10-)
0.00 1 .0~ O7 8' .90 00
LEGEND IG3(i.1.7 THEORETICAL DELECTI0N (ASSUMING CONCRETE CRACKED) LIMITING DEFLECTICN (ASSUMING CCNCRETE CRACKED)
~-ACTUAL DEFLECTION D, RiNG PRESSURIZATION ACTUAL DEF LECTION DURING CEPRESSURIZATION
GOPSIG-
.1 .~ 30~ .560 .0~ 1.00
RADIAL DISPLACEMENT(INCHES)
-40PSIG- _7Z-
3OPSIG---
10 PSIG
0 PS 1G.
I.G.5EL.S.37I
44/- I - -4----- 4.-.- '1.-i - I ~717f7 - -.- v-- I-I-
4SI "S" I.R0AD0I3AL 50SPLACEME0 T (INCHES)
RAIA IS.P(L.CEMENTIGURE G
EQUIPMENT HATCH AREA RADIAL GROWTH
I.G.5(EL.%.371)
F
-Z -
FT
I A
F
k 35. .5*-;-1 1*w I a
0.0 10 .2 O .3 0 'SO .GO 0 .0 r1
RADIAL DISPLACEMENT (INCHES)
GO PSIG-
50P~l~f~~ztztizLLIz
-40 PSIG
3OPSIG-
20 PS
OPSI
in: --- 4; - 1 4 -'!1- - 1I-1 -1 -1
I r- v/vI~ .'..-44~4,~I"'.~4+.-4~4 I 'flI II I'* * . * 5. 65 75* *BSS
0 o '10* .20 .30 0' '~ 70' .80' cXT 1.0 RADIAL DISPLACEMENT (iNcHE~s RADIAL DISPLACEMENT_(iNCHE5L)
1.G. 8(EL. S9G.3 7'). LEGEND:THEORETICAL DEF'LECIVN NO~A CCNCRET E CIRACKED) LIMITING DEFLECT ION (ASSt;MI NG C--NCQRETE CRACKED)
GO PSIG
-- I
K4L4OPSIG- 6.
3OPSIG--/ U)
ZOPSIG----------------
OPSIG- .Oj 15
0600 1 io '30 .40 * .50a 01.00 RADIAL DISPLACEMENT (INCHES)
- ACTUAL DEFLECTION r>j DU.G =RESSUR.(ZAT IONl ACTUAL IDEFLECT71CN DULRiNG DEPRE-SSULRIZA~iCN4
GO PSIG-- ~_
50PSIG-
Lii
3OPSIG-I, U)
2OPSIG- - ---- - - - -(1
OPSIG0.00 .20l .30 .0.6.0 .70' .cU *i0
RADIAL D ISPL ACEMENT (INCHES)
I. G. I I (EL.I 10. 101)
GopsiG.
50 F
qO PSIG
30 PSIG
20 PS IG
-I -4- F -1 - 1- F14i4 14. fJ.-/
---- -7- -
/ - .- - ~-
- .1.- I -4 -i 4- -'- 4-4- + -4.- -4-4-
PSIG-
OPSIG- .0 j 35 45 * Sj' 65 '75. 5 5
00, .53O~ 0 6 60* .7a'.8a .9a' 1.00 RADIAL DISPLACEMENT_(iNCHES)
I. G. 12 (E L. 112.)846)I.G.IO (ErL.10Oro. Gro) FIGURE G -SHEET20F 3
QUIPMENT HATCH IADIAL GROWTH
oll
Ilopsir. I I I I I i I I
G. 7 (E L.9 8.42.')
i i i i i i i i i i i
) ps I r, i i 1 1 1 yq - i i i7.- i 1 -
FI
j 1%3 -
-M
IV rilk7"I
lw
SM I j I %J -
A
GO PSIG
5C PS IG
40PSIG
30PSIG
2CPSIG-
10 PSIG
0 PSIG
RADIAL DISPLACEMENT (,\CHES) I.G. 13 (EL.110.5')
60 PSIG
50 PS IG
4CPSIG'
3OPSIG
ZCPSIG-
10 PSIG
0 PSIGO .- '- - : -. . - go. 1.00
0.0004 0 ,50 . .i 0 u ..8OO RADIAL DISPLACEMENT (INCHES)
I.G. 14 (EL.IIG.5')
GO PSIG
5CPSIG
40PSIG
I.G. 15
LEGEND: THEORETICAL DEFLECTION (ASSUMING CONCRETE CRACKED)
rn-m LIMITING DEFLECTION (ASSUMING CONCRETE CRACKED) ACTUAL DEFLECTION DURING PRESSURIZATION ACTUAL DEFLECTION DURING DEPRESSURIZATION
FIGURE 3 SHEET 3 OF 3
EQUIPMENT HATCH RADIAL GROWTH
II
-- -.-- ---
:: / ! o/"
- - ~ - Z /
0 . .90i!.CC .-4 - -IS .GO .7 . - -gO -,
RADIAL DISPLACEMENT (INCHES)
3OPSIG
2c PS)G
10 ,rflG
0 PSIG
I. G. 15 (E:L. 121.5')
0
- -4--
-4-
- , (37
G ~7.37
0
,7/
~1.22
2700
G7 0 -:.5a4s
-~1
~
6727
(~7~2~
~
~772~S
c~7.Z7
C727
4
C4'3~ I
4
~7.I 4.
~1.21 4
~Th3~
67.321
7-6
4~7.51
4
~ 39* Xi4O~
IC 40
c~7.3l4
c7-34
G7. ZI
GT.54
G~Th27
G7.~'2
~7~Z 9.
272
aT'Y7
6-738
~G7,2r,
:G754
27e zle~
E.L 14'-
ro* 5
EL 152'- 0
C7,34
jc7.2h
EL I 4'- 0G-7.357
EL-144 -0
E.L 142'70
EL 15
G7.3
RAIDIUS (IN FEET) - IGURE I-7 LNEE IO4ST17.OME 4TATIOI 4
67,54.
6.7,34
- .1- 3 o a C.(L rEgOWEL LOCK.
FIGURE 8 "EISPC EbAR
IN.pER.SONNFL LOCK AREA
APPENDIX A
UE&C SPECIFICATION 9321-05-5-6
FOR
STRUCTURAL INTEGRITY TEST OF
CONTAINMENT STRUCTURE
P RO0P R I E TO0R Y I N FOR MA TIO N
This document is the property of UE&C. It is submitted in confidence
and upon the condition that it will not be reproduced in whole or in part nor
will the information contained in it be disclosed except as required for this
specific report.
UNITED ENGINEERS & CONSTRUCTORS INC.
PHILADELPHIA, PENNSYLVANIA 19105
SPECIFICATION
for
STRUCTURAL INTEGRITY TEST OF CONTAINMENT STRUCTURE
for WESTINGHOUSE ELECTRIC CORPORATION
INDIAN POINT GENERATING STATION - UNIT NO. 3 CONSOLIDATED EDISON COMPANY OF NEW YORK
ry 18, 1972 Spec. No. 9321-05-5-6
-6,1972 1974
Date: Rev. 1: Rev. 2:
Februa
June 2 July 2
DESCRIPTION
The containment structure is a reinforced concrete structure comprised of a right vertical cylinder 135' I.D. with 4-1/2' thick walls, 148' from the base to the springline, a hemispherical dome 3-1/2' thick and a 9' thick flat base.
After constructionhas been completed, the structure shall be pressurized by Others and the test noted in this specification plus an integrated leak test by Others will be performed.
SCOPE OF WORK
Furnish all technical assistance, special tools, supervision and equipment necessary to install all equipment, record results, interpret results and prepare a final report for the test requirements as shown on UE&C Dwg. 9321-F-14913 and specified herein.
WORK INCLUDED
1. Furnish remote recorders, on a rental basis, for recording structural deformations.
2. Furnish time sharing computer installation for reduction of data from remote recorders (or approved equal method);
3. Investigate and determine crack patterns and sizes of cracks in the concrete.
4. Review locations and supervise installation of gross deformation measuring devices, both horizontal and vertical, at increments not exceeding 10' in height as shown on UE&C Dwg. 9321-F-14913. Provide redundancy where required on drawings.
5. Provide complete report of crack widths and gross deformations in the format in Appendix A to this specification.
WORK NOT INCLUDED
1. Furnish and install steel liner.
2. Furnish and install reinforcing.
3. Furnish and install concrete.
4. Furnish and install liner insulation.
5. Furnish and install pressurization equipment and pressurize containment.
6. Provide construction craft labor.
UE&C Spec. No. 9321-05-5-6 Page I Rev. 7/26/74
WORK NOT INCLUDED (continued)
7. Integrated leak test.
8. Provide penetration with pigtails for gross deformation instrumentation connections.
9. Furnish and weld attachments to the liner.
10. Temperature recording equipment inside the containment.
GENERAL
1. The tests will be performed when the containment structure is under the action of 0, 12, 21, 41, 54, 41, 18, 21, 41 and 0 psig internal pressure. The pressure shall be held constant for at least one hour then deformations shall be recorded and the data reduced at each of these pressures. Time for pressurization and return to 0 psig is estimated as eight (8) days. Both the concrete and liner shall be visually inspected after the test to insure there is no visual distortion of the liner plate and to determine the size and location of any residual concrete cracks.
2. Before testing starts, the following areas shall be sandblasted or acid etched by Others. This Subcontractor shall inspect, locate and measure cracks in these areas prior to the test, @ 54 psig and after the test.
a) Quadrant of "boss" around Equipment Hatch and Personnel Lock.
b) 10' wide by 5'-0 high areas at the base wall intersection, at mid-height of the wall and at the wall-dome intersection.
The Subcontractor shall examine these locations in detail and locate and record any existing cracks.
Lighting and movable scaffolding shall be provided by the Contractor for the Subcontractor's use in the above.
3. The exposed surface of the containment shell, other than the areas described in Item #2, shall be visually inspected prior to pressurization. The largest crack shall be mapped, the area surrounding the crack marked with red fiber and the behavior of this area carefully observed during the test. In addition, at 41 psi and at fhe conclusion of the test, the visual inspection shall be repeated. A visual survey shall also be performed by this Subcontractor to identify typical crack patterns at the mid-height of the wall in the vicinity of the area described in Item #2 (12, 21, or 41 psi depending on when initial crack patterns first appear).
4. The method of attachment, placement and cable routing of all temporary gauges, junction boxes, cables, jigsjfixtures, etc., to any part of the containment structure, access ways, permanent structures or equipment by the Subcontractor shall be subject to the approval of the Contractor.
-UE&C Spec. No. 9321-05-5-6 Page 2 Rev. 7/26/74
GENERAL (continued)
5. Instrumentation shall have capability of measuring gross deformations from 0 to 2" with tolerance of + .01"1 except where noted on UE&C Dwg. 9321-F-14913. Prior to the test, the Subcontractor will be supplied with calculations predicting anticipated gross deformation and crack measurements.
6. Since the pressurization of the structure will be performed by Others, the Subcontractor shall be required to coordinate his activities with the Subcontractor pressurizing the building.
7. Each gauge and redundant gauge shall be clearly marked and tagged with identifying number relating the number to the location in the structure. These identifying numbers shall be in accordance with identifying numbers on UE&C Dwg. 9321-F-14913.
8.. All equipment used shallI be checked, calibrated and temperature recorded prior to taking actual measurements and the percent errors recorded and corrected in measurements taken during containment pressurization.
9. Temperature recording shall be taken by Others during containment pressurization and containment measurements and corrections made from base established prior to containment pressurization.,
10. Subcontractor shall prepare in detail and submit to the contractor for approval, a procedure outlining test preparation and how all data are to be obtained, recorded and reduced to final form.
11. If possible, all gauges recording strains or deformations shall be zeroed while the interior of the containment is at ambient temperature and again when the test temperature has been reached. The reading at test temperature shall provide the zero basis for test results.
12. All readings shall be reduced *to deformation measurements within 30 minutes after they are taken at the various containment pressure levels specified in Item 1, GENERAL. The Subcontractor shall provide evidence, based on prior comparable use of the instrumentation required to meet this specification that a,,90 percent or better reliability has been achieved.
UE&G Spec. No. 9321-05-5-6 Page 3 Rev. 7/26/74
APPENDIX A
FORMAT FOR FINAL REPORT
1. INTRODUCTION
2. OBJECTIVES OF TEST
STRUCTURE DESCRIPTION
TEST PROGRAM
DISPLACEMENT INST RUMENTAT ION
DATA ACQUISITION
CRACK INSPECTION
TEST RESULTS
SUMMARY
UE&C Spec. No. 9321-05-5-6 Appendix A
APPENDIX B
CRITERIA OF STRUCTURAL INTEGRITY
OF
CONTAINMENT STRUCTURE DURING
STRUCTURAL PROOF TEST
CRITERIA OF ACCEPTANCE OF STRUCTURAL INTEGRITY OF CONTAINMENT STRUCTURE DURING STRUCTURAL PROOF TEST
PURPOSE
To provide assurance of structural adequacy, the Indian Point Unit
No. 3 Containment structure will be pressurized and various measurements will
be taken to evaluate structural behavior. Testing will be performed under
UE&C P.O. 9321-05-5-6.
The following lists specific items to be measured, pressure at which
measurement will be taken, and acceptable deviation from anticipated values.
Drawing No. 9321-F-14913
Vertical Deflection Section "E-E"
MEASURED VERTICAL DEFLECTION (in)
ELEVATIONCALCULATED VERTICAL
DEFLECTION (in)
ACCEPTANCE DEFLECTION (in)
I.G. 29 951-0"
I.G. 30 143'-0" I.G. 31 191'-0" I.G. 27 & 28 262'-0"
Section "A-A"
0.234 0.485 0.737 1.566
MEASURED RADIAL DEFLECTION (in)
GAUGE NO. @ EQUIP. HATCH
I.G. #1 I.G. #2 I.G. #3 I.G. #4 I.G. #5 I.G. #6 I.G. #7 I.G. #8 I.G. #9 I.G. #10 I.G. #11 I.G. #12 I.G. #13 I.G. #14 I.G. #15
CALCULATED RADIAL DEFLECTION (in)
ACCEPTANCE DEFLECTION (in)
GAUGE IDENT. NO.
LOCATED ELEVATION
CALCULATED DIAMETER CHANGE (in)
ACCEPTANCE CHANGE (in)
MEASURED DIAMETER
CHARGE
Unit #3 Unit #2
0.79 (radial) 1.59 1.59 1.59 1.59 1.59 1.62
IDENT.Unit #3 Results.
Unit #2 Results
0.304 0.631 0.959 2.036
.093
.200
.334
.586
.080
.100
.260
.640
Unit #3
.544
.640
.674
.553
.661
.659
.585
.631
.524
.583
.633
.591
.502
.543
.556
Unit #2
.62
.68
.62
.62
.63
.72
.74
.59
.72
.71
.57
.55
.64
I.G. I.G. I.G. I.G. I.G. I.G. I.G.
91'-0" 101' -0" 1111-0", 121'-0" 131'-0" 141'-0" 151'-0"
1.011 2.035 2.035 2.035 2.035 2.035 2.078
.654 1.388 1.114 1.302 1.156 1.336
.720 1.430 1.450 1.470 1.470 1.400 1.300
GAUGE IDENT. NO.
MEASURED DIAMETER CHARGE
LOCATED
ELEVATION
CALCULATED ACCEPTANCE DIAMETER CHANGE (in) CHANGE (in) Unit #3
.810 (radial) 1.62 1.62 1.61
0.370 (radial)
Equipment Hatch Diameter Change Calc. Radial Deflection (in)
I.G. #33 I.G. #34
0.017 inch
Acceptance Deflection
0.022 inch
Measured Deflection Unit #3 Unit #2
.025 (ave) .0067
I.G. 23 I.G. 24 E.G. 25 I.G. 26
I.G. 32
161'-0" 171'-0" 181'-0" 191'-0"
56'-6"
Unit #2
1.039 2.078 2.078
2.061
0.480
.596 1.350 1.200
.926
0.274
.700 1.350 1.200 1.050
0.240
APPENDIX C
GROSS DEFORMATION ACCEPTANCE
CRITERIA
GROSS DEFORMATION ACCEPTANCE CRITERIA
The following criteria are proposed as a measure of Containment structural perform
ance during and after the strength test at 54 psig which represents 115% of the
design pressure of 47 psig:
1. The increase in Containment diameter shall not exceed 1.62 in. + 28 percent,
or 2.078 in. for invar tape measurements between El. 91'-0" and El. 191"-0'
when measured as an average of all readings.
2. Equipment Hatch distortions shall show the same trend as trend as computed
values and the maximum radial displacement shall not exceed .76 + 30% or 0.99".
3. The expected total vertical elongation of the Containment wall measured at
El. 191'-0" shall not exceed .737 inches + 30% or .959 inches.
4. The maximum concrete crack width shall not exceed .035" averaged over a 20'-0"
length of crack.
5. The average crack spacing for both the horizontal and vertical directions of
the Containment cylindrical wall shall not be less than 15 inches. These (2)
averages shall exclude crack patterns in areas affected by discontinuities
such as penetrations through the Containment wall.
6. All gauge readings after 24 hours complete depressurization are to return to
zero or equal or less than 30% of the maximum reading recorded at pressure
54.0 psig.
Both concrete and liner will be visually inspected after the test. There shall be
no visual distortion of the liner plate in excess of values presently recorded in
construction surveys. Only very small, hairline cracks in the concrete (.010")
GROSS DEFORMATION ACCEPTANCE CRITERIA (Continued)
will be considered acceptable. However, it is fully expected there will be small
residual cracks as a result of shrinkage in the concrete.
If any of the foregoing criteria is not met, an engineering evaluation of the test
results will be performed to determine the reasons for failure to meet the criteria
and the course of action required, if any.
Prior to the test, a table of predicted deformations, crack widths and crack spac
ings will be developed for an internal pressure of 54 psig. These expected measure
ments will be predicted from the analytical model and are to be used as a basis
for verifying satisfactory structural response. Conclusions concerning the accept
ance of the structural response will be based on only the six (6) criteria given
above.
REFERENCE I
STRUCTURAL RESPONSE OF SECONDARY CONTAINMENT VESSEL
DURING STRUCTURAL INTEGRITY TEST AT
INDIAN POINT POWER GENERATING STATION UNIT NO. 3
CONSOLIDATED EDISON COMPANY
FOR
WEDCO CORPORATION
BY
WISS, JANNEY, ELSTNER &
ASSOCIATES, INC.
I
w 1 ! s S,
J j a n
E IAI t n
. e
! a a
A s s 0 C
.a t e i s
I i
'I I
STRUCTURAL RESPONSE OF SECONDARY CONTAINMENT VESSEL
DURING STRUCTURAL INTEGRITY TEST AT
INDIAN POINT POWER GENERATING STATION UNIT NO. 3
CONSOLIDATED EDISON COMPANY
for
WEDCO CORPORATION
WJE NO. 74301
January 31, 1975
STRUCTURAL RESPONSE OF SECONDARY CONTAINMENT VESSEL
w DURING STRUCTURAL INTEGRITY TEST AT i
s, INDIAN POINT POWER GENERATING STATION UNIT NO. 3
a CONSOLIDATED EDISON COMPANY a n n e for
E WEDCO CORPORATION
S t n e January 31, 1975 r a
A CONTRACTURAL REQUIREMENTS S S. 0
CThe structural behavior testing described hereunder was performed 1 a t e during the structural integrity test of the secondary containment vessel, S
Unit No. 3, Indian Point Generating Station, Consolidated Edison Company.
Wiss, Janney, Elstner and Associates were retained by WEDGO Corporation
to install the prescribed instrumentation, monitor the response of the
instruments, conduct crack surveys prior to and during structural integ
rity testing, and to report on the results-of this structural behavior
study.
The location of test instrumentation was planned by United Engineers
and Constructors, Inc. The work was conducted in accordance with United
Engineers and Constructors Specification No. 9321-05-5-6, as modified by
subsequent directions required by field conditions. All installation
was performed or supervised by WJE personnel. That part of the work
normal to their skills (routine installation of electrical lead wire,
etc.) was performed by tradesmen.
OBJECTIVES OF STRUCTURAL TESTING
The instrumentation was planned and installed to serve two
W purposes. First, the satisfactory response of the structure to specified
S test pressures would be confirmed; second, the criteria assumed in the S,
J structural design would be confirmed. a n n e Y. DESCRIPTION OF THE SECONDARY CONTAINMENT VESSEL
E 1 t The containment structure is a reinforced concrete, right-vertical n e r cylinder with a flat base and hemispherical dome. The sidewalls rise
a 148 ft from the top of the base mat (Elev. 43 ft 0 in.) to the spring
A line of the dome (Elev. 191 ft 0 in.). The sidewalls are 4 ft 6 in. thick S S 0 C and the dome is 3 ft 6 in. thick. The cylinder walls are rigidly coni a t nected to the 9 ft thick base mat. e S
Major discontinuities occur in the structure at the following
locations:
A. At Azimuth 600, thickened boss area around equipment
hatch opening, centerline Elev. 101 ft 6 in.
B. At Azimuth 1760, a thickened boss area around the
personnel lock, centerline Elev. 83 ft 6 in.
C. At penetrations located in the electrical tunnel and
pipe bridge areas. These areas are not thickened.
The interior wall of the containment vessel is lined with a 3/8 in.
thick steel plate, continuously welded to form an airtight seal. The
liner plate is thickened to 3/4 in. around the equipment hatch.
-2-
DISPLACEMENT INSTRUMENTATION
Gross deformation measurements at the equipment hatch, radial
W displacements from Elev. 56 ft 6 in. to 191 ft 0 in., and all vertical iS s, displacements were obtained using invar wire extensometers.
a , a The invar wire extensometers were located entirely inside the n e structure and were connected to an external power supply and read-out E equipment by electrical leads which extended through penetrations in
S t the cylinder wall. n r Each extensometer consisted of an invar wire spanning the disa
tance to be measured. One end (the "ded" &nd) was fixed to the steel s liner, and the "live" end of the wire was attached to a spring-loaded
s frame which was rigidly attached to the liner plate in the direction
t of measurement. Deformations of the structure were measured thus with a linear potentiometer mounted in each frame. The potentiometers are
of the infinite resolution type with a total resistance of about 2000 ohms.
A constant voltage of 1.4002 volts was applied to each potentiometer.
At each measurement, voltage is measured between the movable contact
point and each end of the resistor. The voltage changes are recorded
on the external read-out system.
Prior to shipment to the field, all the frames were calibrated
in our laboratories. As a further check, calibrations were obtained on a number of the extensometers after they were installed in the structure
just prior to the test. After completion of testing, a number of the 3 frames were recalibrated in the laboratory to insure that the original
calibration had not changed.
9 -3-
DATA ACQUISITION EQUIPMENT
All data were obtained using a KAYE-DAS recording system. The
W system is a digital data acquisition system designed to collect rapidly i S s, and transform raw analog data into a permanent paper tape record. The
Ja system sequentially samples, measures and records data in the 2 millivolt n n e to 2 volt range, the Hz to 2 MHz frequency range, and the 40 microsecond
E to 10 second period range. I S t The KAYE system includes a scanner, an integrated digital voltn e r meter, a printer and clock. a
CRACK INSPECTION A S S 0 c Prior to the structural integrity test, the entire structure was a t e surveyed for cracks. The survey was made with the aid of variable S
power (7X to 15X) binoculars and a Redfield 60X Spotting Scope. Observa
tions were made from all accessible walkways, roof tops and scaffolding
available. Access to the dome for inspection was obtained using a
"Sky-Climber" traveling scaffold.
STRUCTURAL INTEGRITY TEST
The structural integrity test was performed in conjunction with
the integrated leak rate test. Gross deformation measurements were
obtained at the following pressure levels: 12, 21, 41, 54, 41, 18, 21,
41, 12 psig. Detailed crack inspections were made at 0, 54, 0 psig.
The detailed grid area at mid-height, and a crack (largest observed
during the pre-test inspection) were monitored at 12, 21, 41 and 54 psig
during pressurization.
At each pressure level where structural data was required, pres
surization was halted and the structure remained at that pressure for
one (1) hour before data was obtained.
The data obtained at each pressure level was reduced on site,
plotted and reviewed by the U.E.& C. representative prior to starting
to pressurize to the next increment.
The structural integrity test was started on January 12, 1975
at 1515 hours and was terminated on January 20, 1975 at 1100 hours.
A time pressure curve is presented in Fig. 1.
TEST RESULTS
Radial Displacements Near Equipment Hatch
Invar wire extensometers were used to monitor the radial displace
ments near the equipment hatch at fifteen locations, as shown in Fig. 3
of Appendix A. The detailed displacement data are provided in Table I
of Appendix A. The radial displacements near the equipment hatch were
compatible with those found in the uninterrupted cylinder wall (Table 3).
Radial Displacements of Cylinder Wall
At elevations above 56 ft 6 in. to the springline, Elev. 191 ft 0 in.,
the radial displacements of the cylinder wall were monitored with the
invar wire extensometers located at Azimuths 15', 750, 1350 and 3400.
Extensometers were located at 10 ft intervals. Table 3 of Appendix A
provides the detailed data from these extensometers. Instrument IG22 was
__ __ )__ _ - 1 ~ - m
Note" GSIT Data PointsPressure (psi9 )
Time hrs 2400 2400 2400 2-400 2.400 2400 2400 2-400
Date 1-12-75 1-13-75 1-14-75 1-15-75' I-IG-75 1-17-75 1-18-75 l-lq-7E. 1-20-75
PRESSURE VERSUS TIME, STRUCTURAL INTEGRITY TEST
FIG. I
2400
improperly set prior to the test, resulting in exceeding the instrument
range prior to reaching peak pressure. Although the maximum deflection
at this point was not obtained, the total number of extensometers have w s provided an accurate record of the cylinder wall displacements. S,
J The radial displacements of the cylinder wall, measured at 10 ft a n n intervals from Elev. 56 ft 6 in. to the springline, have been plotted e
E to develop the relationship shown in Fig. 2. The distortion of the
S cylinder wall throughout its entire height can thus be seen at the t n e various levels of test pressure. r
a
Cylinder Growth and Dome Displacement A S S 0 c The cylinder vertical growth was measured relative to the base i a t at three elevations of the wall, 95, 143 and 191 ft, at Azimuth 1200. e S The displacement of the apex of the dome was measured relative to two
positions on the springline. These data, corrected to reflect vertical
displacement relative to the base, are shown in Table 2 of Appendix A.
The data indicate that vertical growth of the cylinder is about
one-half the radial displacement of the wall at maximum pressure. The
vertical displacement of the apex of the dome relative to the spring
line is about one-half the radial displacement.
Diameter Change of Equipment Hatch
The change in diameter of the equipment hatch ,during the pressure
test was monitored across two diameters. The data is shown in Table 4
of Appendix A. The maximum change observed was 0.03 in.
-7-
I8G
J.G
14G
12G
8G
G
4G
122 2.1
.2 .4 . RADIAL .DISPLACEMENT -IN.
RADIAL DISPLACEMENT OF CYLINDER WALL AT AZIMUTHS 15, 75" 135c, 3400
;71G. 2.
54
Crack Patterns
The total structure was optically surveyed to reveal cracking
which existed prior to the structural integrity test; and during the
test, the total structure also was surveyed for any major cracking.
During the test, specific attention was paid to:
1. The upper left-hand quadrant of the equipment
hatch boss
2. The upper right-hand quadrant of the personnel
lock boss
3. The 10 x 5 ft gridded area at Azimuth 1290 and
Elev. 115 ft
4. The 10 x 5 ft gridded area at Azimuth 1290 and
Elev. 186 ft
5. The 10 x 5 ft gridded area at Azimuth 3280 and
Elev. 43 ft 3 in.
6. The largest crack observed during the pre-test
located at Azimuth 245' and above Elev. 94 ft
above
above
above
inspection
Pretest Survey
The pretest crack inspection revealed surface crazing which was
not considered of any significance. Cracking that was recorded con
sisted of horizontal cracks less than 0.005 in. in width at construction
joints. Spider cracking generally consisted of three or four cracks
less than 0.005 in. in width and approximately 8 to 1 0 in. long at
almost all of the scaffolding insert holes.
Vertical cracking observed generally was random in nature and
occurred to the greatest extent between Elev. 100 ft 0 in. (approxi
mately) and 170 ft 0 in. Below 100 ft and above 170 ft, cracking
W was found to be much less prevelant. About 99% of all cracks observed S S s, were less than 0.005 in. in width. Approximately 1% of the cracks were J a between 0.01 in. and 0.005 in. in width. Appendix B contains drawings n e Y, showing cracking of a width between 0.005 and 0.01 in.
E 1 Cracking observed in the dome, from the springline to the apex, S t n were less than 0.01 in. Cracking occurred at form lines and was e r a associated with shrinkage of the surface.
A Development of Cracks During Test S S 0
The crack patterns developed under imposed test load at the a t e
S locations which were monitored, are presented in Appendix B. Excluding
the personnel lock boss, (which will be discussed separately), the crack
survey performed during the conduct of the test did not reveal any crack
which exceeded the test criteria (crack width of 0.035 in. over a length
of 20 ft). The majority of cracks observed generally were very fine
and were less than 0.005 in. in width. Some extension of the vertical
cracks was observed, but again was very small. The maximum crack width
measured in a detailed survey area was 0.019 in. over a 5 1/2 ft length.
This crack occurred at Elev. 115 ft 0 in. on Azimuth 129'. Maximum
crack measured at the equipment hatch boss was 0.03 and occurred at the
intersection of the wall and boss.
Monitoring of a typical large crack at Elev. 99 ft on Azimuth 2450
showed a widening to 0.018 in. starting from 0.01 in..
New cracks, which developed duringthe test, were vertical in
direction and the spacing was approximately 18 in. en center. No new
horizontal cracks were noted and the old cracks did not increase perw i ceptibly in width. The majority of cracking was concentrated in the s s,
middle third of the structure, with little or no new cracking being a n observed in the remaining portions of the structure. e
E Post-Test Crack Survey s t e At the conclusion of the test, the structure was surveyed again. r a Cracks, which were observed to open, or extension of cracks, which were
A seen at the test load, all returned essentially to a pre-test condition. s S o The crack patterns observed, widening and/or extensions, were considered c i a normal for the structure. t e S
Development of Cracking at Personnel Lock
During the course of the test, it was observed that large cracks
(exceeding 0.04 in.), but short in length, had developed aroung the
personnel lock boss. The major cracking observed occurred outside of
the detailed crack inspection area. Major cracking occurred at the four
corners of the bossed area. The maximum crack width observed was 0.10 in.
occurring in the lower right-hand corner. The major crack (0.10 in.)
tapered to 0.006 in. in 3 ft. Detailed drawings are presented in
Appendix B. The behavior of the crack was closely monitored during the
remainder of the test. The behavior of the crack with the loading and
unloading sequence would indicate that the cracking is an extremely
-10-
local condition. The crack did not propogate or widen during the
long hold periods when it was subjected to high test pressures.
W SUMMARY 1 S S,
J Interpretation of the data in light of the design concepts is
a nl not within the scope of our assignment. However, we feel that our many n e
Y, years of experience in observing the performance of reinforced c oncrete
E 1 structures under many types of test loading requires that a general S t
e commentary be made as follows regarding the behavior of this structure r
a under the application of the test loading:
A 1. The cracks, which were observed in the design and inspection S 0 C areas prior to testing, were fine and of the character that i a t e should be expected as resulting from thermal and drying
shrinkage. They are believed to be surface cracks and very
few probably extend beyond the outer layer of reinforce
ment.
2. The additional cracking and the extension and widening of
existing cracking, which occurred during the application
of test pressures, did not develop to the extent that yield
ing of reinforcement was indicated at any point on the
structure.
3. The cracking observed around the personnel lock appears to
be an extremely local condition. The crack did reduce in
width to acceptable limits in a very short distance.
4. The gross deformation measurements were well within pre
dicted values.
-11-
5. The overall performance of the structure was generally
elastic. The deformation measured immediately after the
test had a recovery of more than 80% with the exception
W of Gages IG 26 and IG 26A. These instruments were i s, located at the springline and redundant full diameter
J a measurements. n n e YRespectfully submitted, E I WISS, JANNEY, ELSTNER AND ASSOCIATES, INC. S tn/ n e 61-6 4-v-. r
a Robert Krause Assistant Director of Power Engineering
A Services s Reg. Prof. Eng., Illinois - 22449 s
a V -- <' :-t '" k . .. . -.
e Ted M. Brown
Director of Power Engineering Services Reg. Struc. Eng., Illinois - 2767
RK:TMG:RG
-12-
w i s S,
J a n n e y,
E
S t n e r a
A APPENDIX A s s 0 DISPLACEMENT DATA C i a t e s
m' an " a lm '110,--, ' lw 'i ,, I EL. 121.5'
I.G. 5 I
I.G. 14
I. G.
LG.
EL.
I. G.
EL. G.37'
I..G. G
EL. IIG.5
EL. 112..17'
EL. 110.5' EL. I
GG'
9e.4Z
I.G. 9
AZ I CO-
F IG,, 2 - EXTE.N'01t"ETIM,. rU N'_ ' F ,T H/.1" H I, H .....
m m) ' - - m m m -
D.E., 00 IS O
EL. 180'-0
EL. IGO-0"
EL. 140'-0"
EL, IZOLO"
EL. iOO'!_0
EL. 80O'-0
EL. GO -O"
EL. 50'-0"
D.E. 750
L.E. L.E. IZ00 1350
_1G. ZG a EL. I91!-o"
D0UBLE & M .G. 2-S . EL. IBI -O"
I.G. 2.2. EL. 151'-0"
ZI-0"
Z.G. 1l EL. 1I21'-0"
I.G. 23 EL. IGI0"
OFF 12.0' /--
M".G. 20 EL. I31'O"
.-I.G. 17 EL. 101L0 ''
I.G. IG EL. 91!-0"
4"-o 0FF 120'
L.P. Iq5 °
I 950 2550
I 1.G. ZG,27 8 31
EL. 1I '-O"
T.G, Z4 EL. 171'-0"
G. 30 _. 143-o '"
T.G. 21 EL. 141',-C)"
I.-. 1 EL. II I'-0"
1. Z.G. 29 EL. 35-0"
L.E. 12550
I.G. 25 EL. IZI'-0"
1.G. 22 EL, 151'-0"
I.G. Iq F-L. I ZI'-O"
r iT.G. ZGa. EL. 191" 0 '
DOUBLE
I.G. 23 EL. I L'-0"
". G. 2.0 EL. 131 '
IG. 17 EL. 10I'-0"
-~ __________ J. 1* I _______
L.E. D.E. D.E. 300° SIO 34-00 3cO °
I 2 "I.G. 2_G & Z5 EL. 191L-O'
)-.G. '24 EL. 171' 0"
I.G. 21 EL. 141'-O"
".G. 18 EL. I1 I'-0"
DOUBLE 1.G, 32EL. 5G'-G ' (
I II
FIG. 4 - EXTENSOMETER CYLINDER WALL
LOCATION ON
E-L. I eO'-0"
EL. J 40'-0"
EL. IZO'-O" EL. 140'lO"
:ELI zo0
-SL. 100!-0"'
-EL. 80o"
-EL. 50'-o"
EL. 50'- 0"
'270 °
EL. 43'-O0"
FIG.---5 - VERTICAL AND DOME
EXTENSOMETER LOCATIONS
m m m i m ms wi -o m6
TABLE I
RADIAL DISPLACEMENT OF WALL
NEAR EQUIPMENT HATCH - INCHES
DATE TIME PRESS.
1/12/75 1/13/75 1/14/75 1/14/75 2200 1036 0030 1715 12 21 41 54
0.036 0.099 0.372 0.544
0.044 0.115 0.441 0.640
0.048 0.132 0.470 0.674
0.042 0.094 0.373 0.553
0.040 0.116 0.454 0.661
0.039 0.118 0.458 0.659
0.033 0.094 0.391 0.585
0.012 0.083 0.416 0.631
0.045 0.121 0.383 0.524
0.031 0.094 0.384 0.583
0.036 0.103 0.415 0.633
0.036 0.102 0.395 0.591
- 0.028 0.079 0.327 0.502
0.029 0.086 0.355 0.543
1/15/75 0218
41
0.458
0.544
0.564
0.476
0.559
0.552
0.518
0.550
0.459
0.509
0.544
0.510
0.430
0.481
1/15/75 1/18/75 1/20/75 1/20/751/15/75 1030 18
0.260
0.297
0. 303
0.263
0.305
0.295
0.292
0.295
0.270
0.283
0.295
0.230
0.235
0.264
1534 21
0.269
0.306
0.314
0.267
0.316
0.313
0.292
0.296
0.281
0.288
0.303
0.285
0.243
0.264
0945 41
0.420
0.496
0.523
0.430
0.511
0.512
0.460
0.484
0.428
0.451
0.487
0.457
0.382
0.413
0539 12
0.205
0.235
0.243.
0.209
0.240
0.235
0.233
0.229
0.216
0.224
0.233
0.223
0.185
0.209
0.363 0.556 0.489 0.268 0.268 0.426 0.214 0.111
1100 0
0.106
0.122
0.128
0.107
0.124
0.122
0.127
0.098
0.113
0.119
0.122
0.122
0.095
0.113
IGl
IG2
IG3
IG4
IG5
IG6
IG7
IG8
IG9
IG10
IGI
IGI2
IGI3
IG14
IG15 0.029 0.089
m u~ ~ m -I Nm rn m
TABLE II
VERTICAL DISPLACEMENT OF WALL AND DOME - INCHES
DATE 1/12/75 1/13/75 1/14/75 1/14/75 1/15/75 1/15/75 1/15/75 1/18/75 1/20/75 1/20/75 TIME 2200 1036 0030 1715 0218 1030 1534 0945 0539 1100 PRESS. 12 21 41 54 41 18 21 41 12 0
IG29 (wall) . 0.000 0.008 0.053 0.093 0.085 0.037 0.039 0.070 0.028 0.008 46' to 95'0" at Az. 1200
IG30 (wall) 0.015 0.032 0.121 0.200 0.166 0.071 0.072 0.136 0.057 0.025 46' to 143'0" at Az. 1200
IG31 (wall) 0.021 0.050 0.195 0.334 0.295 0.143 0.144 0.226 0.120 0.058 46' to 191'0" at Az. 1200
IG27 (Dome) 0.042 0.098 0.349 0.586 0.509 0.249 0.251 0.417 0.208 0.101 46' to 262'0" at Az. 1200
IG28 (Dome) 0.042 0.094 0.337 0.577 0.498 0.241 0.242 0.402 0.206 0.099 46' to 262'0" at Az. 3000.
TABLE III
RADIAL DISPLACEMENTS OF CYLINDER WALL - INCHES
DATE TIME PRESS.
1/12/75 2200 12
1/13/75 1036 21
1/14/75 0030 41
1/14/75 1/15/75 1/15/75 1715 0218 1030 54 41 18
1/15/75 1534 21
1/18/75 0945 41
1/20/75 0539 12
1/20/75 1100 0
AZIMUTH 150
0.034 0.022 0.025 0.037
0.119 0.118 0.108 0.101
0.4 74 0.475 0.491 0.430
0.654 0.651
0.600
0.527 0.555
0.514
0. 265 0.299 0.343 0.299
0.282 0.297 0.342 0.300
0.504. 0.508 0.511 0.477
0.205 0.247 0.292 0.256
0.108 0.129 0.179 0.152
AZIMUTH 750
IG17 (El. 101) IG20 (El. 131) IG23 (El. 161) IG26 (El. 191) IG26a (El. 191)
0.037 0.035 0.019 0.030 0.026
AZIMUTH 1350
0.033 0.039 0.037
AZIMUTH 3400
IG32 (El. 56?6"?) IG32a (El. 56 6"1)
IG16 IG19 IG22 IG25S
(El. (El. (El. (El.
91) 121) 151) 181)
0.118 0.095 0.072 0.069 0.063
0.470 0.394 0.396 0. 316 0. 316
IG1 8 ICG21 IG24
0.694 0.578 0.596 0.463 0.464
(El. (El. (El.
111) 141) 171)
0.592 0.498 0.518 0.410 0.422
0. 319 0.281 0. 276 0.248 0.257
0.330 0.282 0. 276. 0.248 0.256
0.092 0.137 0.111
0.541 0.440 0.441 0.356 0.336
0.400 0.486 0.475
0.253 0.234 0.227 0.214 0. 219
0.557 0.668 0.675
0.133 0.129 0.130 0.138 0.141
0.480 0.562 0.627
0.023 0.021
0.257 0.313 0. 319
0.050 0.052
0.257 0.319 0. 321
0.182 0.183
0.433 0.529 0.525
0.274 0. 273
0.212 0.261 0.267
0.231 0.234
0.121 0.150 0.162
0.121 0.123
0.123 0.125
0.209 0.208
0.101 0.105
01.047 0.049
TABLE IV
DIAMETER
DATE TIME PRESS.
IG33
IG34
IG38
IG39
1/12/75 2200 12
0.005
0.005
0.018
0.036
1/13/75 1036 21
0.009
0.008
0.070
0.099
1/14/ 75 0030 41
0.018
0.018
0.412
0.474
CHANGE OF EQUIPMENT-HATCH SHELL - INCHES
1/14/75 1715 54
0.030
0.021
0.625
0.678
1/15/75 0218 41
0.024
0.016
0.525
0.586
1/15/75 1030 18
0.010
0. 006
0. 256
0.321
1/15/75 1534 21
0.011
0.005
0.261
0.330
1/18/75 0945 41
0.019
0.011
0.454
0.522
1/20/75 0539 12
0.002
0.002
0.214
0.259
1/20/75 1100 0
0.000
0.004
0.116
0.150
IG4O .025 .078 0.413 0.594 0.509 0.271 0.273 046 022015IG40 0.025 0.078 0.446 0.226 0.135
- M, a m m M M, M Mm m M ,MM M,
-NJ q *PDAINT K 2ISRMENTN 5 ~~~j 11
-UNEI ION 13
*S307HT IT:I ' I F i~- HF iT C
--- --- --
-- - -. ' - - -
t ___0_
LTI' _ _LA_ _ _
7- L V I
R N [ f___ ___q_ [
___________________TRCTURAL I__ NTEGT ______ST 1 _ _ _ - )---- - -I ~I - - i -S: -I L
Im m sm m m m M" m , m m m -Ma m
Dz 1 DFi N P 0 INT
wEDCO *::7"H30A1-i
NTN s r R 1 NT.--N
R CH NE. N O ;-t
LOCF9T I ON "' EV-j M Tj-- IT -- -- I
' I i M T H T H V
I7 H 7 4.. I 1 - - - A -------
. .. . . . - . I
___________ 117
-- --- -- - _ ---
I * 1 1
----- --_
-- - - --..-. I 17I1
__ _I-i0I
Lr i tl Mm
S-_ _ STRU CT URAFL I iNT EIT T-S E:. fbA.__
- m m m m m - m - - m
117111jND 1:N WAIN .... N. .. H.
LA I
-I F K.
-. F F . 4 ---. 4 I . K. F I F F I F .
_________ I >1 F
F F F V F F F ~1~1 K. ___ ____K
-I . ___-~__
L
I I -~ I 711.
-:Aj1~
I . -
I;. I.. I.
Fl.
-H----.' I E~-z
L ~F
V--i E7K 1-u -i::
-1L IFM
I I ________
4-
-V.-
F F - T * ~ -. I-
LM T- - F
3~~~~~.. -_ _ ------ I-1117 -< -- .. I---
------ -- _4- ~ - - :
I_ I ........... - ij7 _ _ __ 10
~.4 T P-H AT C H 4~~~1~~~ I,
- F -
1 I -_
J 2 4 .1
-F----- I-
F - -.
I 5-,-, _7FL Lim _
-L iT E ----- --------- ~ RTELE -1I ST RU,:TUIRq AL:I NTEGR1t ...... ..
F - I
<I iN STRUM-ETNh
1:!1CR NM N O II:-
+t -
w
1f7
4 -- '------~
- I
LV J3171127
I--..-
*.L.J.ZLA -i -.
m m m - ~ m m
K UNDAP -=C I N.7
E: DCO -47H30l
*71 INETRUJMEN.T 4,'ND,-: -~
I ~ ~~ RIME: NI El:::.----- _
0. C I---- 1 .. , . V--
I. 7:F 7
I!-
T- t _
* I
1.2.: K
"'-.4 I.,
I--.- '
-~~1
--- --
I-- I
4-
________ I 4-4 _________
4 I
4-
--ivI-~. , 4'
.ji7 - 7
- -4
--4 7~iE-L -i
-4- -1----
.72z11+±'if'-~
-- 4--.
- _____________ F I
* .1,
Cm -- ------ ---T~
- ~~ .* ._ _ I. _* -I L rIr ----- --
I_- --- -. LL i
_________ISTRUCTURAL I NLT EtR I TY: TE S T I .
I-I -.- -
i-u"
~d ~ ~+i.- 7 L _________ .1 _________ 4- -v I-.~-.--I ___
Ta
--
I--
--
M M M M M M M M M M M M rM M
1:I f iNFINT,I NS~RUMENT-'..,... T Sa
------- .- - -C-HR N N E-N- 4 -- }---j
.... T 1 N E M U IL- HME.N-T1 '-.H R TCH: -----
-- - - - - -- - -----
- -- ----
0-7
r-74
--- t l.fi Lrl ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ r L __ _ _ _ _ _ _ _ _ __ _ _ _ __ _ _ _ _ _ _ _ _ _ _ _ _ _ _
-- I-.
fV7jj~~f I ________ ________
F --- _- I
C5 M& I n
L1E-- .J -N NEY, ,E L STN E RR HNL R~D -S..5TE~
- -IS T IJETRU TURR-J1 1;7r TY TE:ET - -~ -- j7
m m- m - m m m m m m -
19N POI -N.T
--- ----
L4SL L 0-
1 . f---r----F-
-F -F..______r..;:RRME N.[ _ _
..AJC9
'7
*ION:
--j27
7t 7 27
:LtjPM E
* i--I-
\Tl- -H
.. ... .
I-- 44 I
I
I-- I~-I-~ j j~I7 _______-I
.:L - =w_ _ _ _
K~~ IJ1T- - --- -I- -1-
- -- 4
<ri 14-2 7 1----A
+ ____ _ _____ __ ____ _--- - --- ~ - - - ---
ij 7
14II.=J3J1L13 UL.I I
I!-. [:S3
___ I I ,FI - 7 -. :
.... . - ----- - - - -
-+ +
q I
____ ____ ____ ____ STRUJCTUR L- _________ _________
A .- [..--- I
j F { L t I - .1 I I- . -. I .1 .
_T ---------
mmm -- mm m mm m m m m
rDINPEI~N I N-TRUMENTNDLIZmc _
0.__ 1_ F RR-M E N D E
~EDC * <H:I __9 T. 1 0 N__ E_ __ __ ___t
__ _ __ __ ___ _ __Ko ~FLF1NN77.N I. f__ __
I I
I _ 1 I ------------ 1.LL- __J
_ 1 -
I- IF~ I:-
____ ______ ____ _______ ______ ______ 1_______ ______ ______
C3II _ _ __ _ ___: _ _ _ ._
LZOi
I fZ ....-~ ---J
_ __- -- IE S m -
LS - Z-- .--< *R _F RA A L_ S L N i :
___ IISTRUCTURAL !A NT~hR! T TEST: I
-I---
-4
I
mmmmm~mmm~mminmm
77 ------
NITV~~' I . CHANNEL D
W ~E D C #_*_7H:30I1-- - R1 FRME N t 0. d z~~n LOCAT. LON E: MQLJ 1: P M E 'l-H
-1 ------ _ 1__ _ _ _ _ _ _ _ _ __ _ _ _ __ 7 _ __ __ _ __ _ _ _
____ _________ _____ __f -- -.T .
----- --~ I ...... _ _ _ I t- _ _
__7 _ ___ TI
-f-1
t-w--
- I
- I-- -V ZK§i-;7 7i ~34Yji+zff+:1 I L
____77 771
____~~~~ TUTRLINE~'T Is~I
- 1
____ I I2V+9
-- I-
.1 -A
{IIIVT: I
m m m m - m m - m m m - - m m m m -
- ---- - -- . < 7 T T I -3 N P
_ _ _ _ _ _ _ _~ ~ ~ ~ ~ ~ ~~~~~~~ ----- _ _ _ _ _ _ _ _ _ _ _ _ _ t 1 ---- 1- ----
- -.. - ----
0- -- -----
mm. mm I
IL- T- N, E .I9
_____ ~TR U CITUR 9L INTE:ER' TY T E ST
--------
- 2
~~1
I
m = m =m = m m =m - = m = = = m =m
-P IP I - -,I -- 1l0L E1' ZL~J~I D~ IRN F1 N NT T RI NT U~ETN
WED~CD 7H I IM 0:1_ FRAME Nas____ _ __ _ _ _
... _ .... _ ___ L ~ ~ t i iE U I V-j T
_ - ----- _--_---_
U-1I _j.
hrzU5 iL1 * * -i -- ----- _
____ ___ ___ __ _ ___ ___ V __ ___ _ I1 - ~ 7 ~ fj-A TI~ ~ ~ ~~~~~~~~~--- -----__________. . ___r ______
___ ___ __ ~ I 7 < * I ___ _ - ----
Li.. .. ...... ___ _ ___ _ _ I t11L+
I7J141
I. * 4 I * I.
K!111 I N L~E,
L . Lm m aI- F I __L -F
ST Ut' R'F L I NT 'SI TY_ ES
4 I--
---- ---
±
---- ----
* 4 -- I
I --14
=m m m - m m - m m M m m = -
-1IN D RN --- = lINT
7 LA 3
* I
AI NSTRUMEr 4 T IN~i-t
~HRN 4 L Li--.
p 1 -LOCF1t I [IN
.T1
7 F
-I I
E: M ULJ
___________ I... I.
i I
:E2
K-L-k I~K- I
-- I 2z4L --- I---
V ----4 --- 1 -4 -F---
i~ ~~ ~~~~~~~~~ -- ---___ -----_ ~ ~ -~-- F- i---
_ _ _ _~- ---_ ------ +
_ _ _ _ _ _ _ '-f'- 7--_
- - -- - 1 7
..- .. r. Li LM I aU
R-F- Ic -N :>
Li T R U- I NITEERIA TY T' EST',
j+i'491:
-I
---- - ' -- - ------- 0
C3-
Sj~r ~ +
I ~AV§1IV2Y1*~:.1 -:1 {~i J~ud K~ + '4 -- ~-- -
- ---- - ------ -
----------
:7
I I
7-7
;;e,---------- -
mm~mmm~m
I~ ~ -N II .- -F1
F- ~rCO 7 7L-430I 1!
I. I * * I-
.... ...... :J:F '
I-- E I-
_Lrl
- I K~ [..j: T
I * ~- * F I. 'F .. F. -, -F I
-, - I i I 4 1 I K -I- Ii I.
IlNSTRUMENT:-:-jNO;rEI L -~ -CH R N N E7L-NO r-i-*'---~R RME NI J--13i __
LOCIT ION H [REN HTC Hf: ___ ~ ~ _____ T: ____
i-si-4 _________________ 4 , 4.. ~ I 4- . I
-4
f-i~ 4
*1'
F I. * .~ I ** I
-F .1 . I
I. >4:
-I-
..... ---- -- --
1.9-i I-
-- I--
1: I--
-4. VX17
I * 4--- -- -
- - i---r------f---- 7
I ___
* J j--V----j F-- 1TH ______
7 ~ -F---- ~ -*--
1 ~. - > 1t 1 I ~1-~ '-*---f
LLJ 7i, - - - **
I-in-
F
*1 I:
* I.I . t I :1 p- LI iT y.---}-. ~K.. 41
L~umK:>}z________________ 4 . 4. 4-.---- 4---- 4--- I
--- -I -- -= r-4 --. LM
-- -m :: , =1 -- I- . 4 *I-- - I- -_ _
-7
-_~~ L_ _ _ -_ _- __ _ _T
- K rsI- d NN-EY.:'--. E LE+-N E R-9 SN~ A ~ J T~I I: ---
STR U CTULlR RL 1 1 NTEERA1TY TEST I-
. .... ..... ...
--------- --------- ---
-- - ----------- ---------- - - --------- -------
- mmm mmm - - -- - --- - - --
- 7 ---- - ... ..
-LI I
JL -I
I
V-Li-[. V
I
il NS . M, NT-- N ---- --- __
4HANNEL Nj
.LT3CF R T ON 13 NMNT H.F CH EM L M TJ4 i ________--f--
* ~
I I j
II
I-I
£_ff1
TI -. _____ [~-- -
-I--i-. -
-j - I- -; iL2~. .~..
4 ii -L r -. -- t- -I -
p -4 _ f ____ ____ IT
1.~
-4
Li -~ i~V 4--.I - -.
- I
171414- ----4- -I -
K--'_ -_
4-n---- -F----
I-___~ ----- --- - zS- ----- -------
.... .....
-1 Mm 4~~ ---- ------
LO TI R*L INESRlT ET
- J I - -- .: . .. . .
I I . . I i
- --- - ----- - - m m - m -
FIND-F I AN PD I NT:7 ~ThFN177T7 :3
E~C7 H* 0-:1
- I0-
7 I ---I
. 1 .1 I -
w
IN S T U ENT7fN F~1 1~ __ I CHRANNL N U IIK
~-7 ~ - - R M E r.o _ _ R M :. 3-7
j ___________ I ~ IT .4. ____ I ~~-- __ ___ _
I-. I-. f{Y
LOCIRT I ON: j::'E
I:
r ~-~r-
-iM-- J11I A CH
.JLiL7L7 iL7IA I -
4.- 4 -4- -4- ___ ~ ___ I...L.J ___ I -A ___ I 4
K.)47LifiT~~rj~Ji7~,L.L
-I-- L11f z:~1Z7
------ I
I--
-7I-
r~~~ ______
----- ---- - _ _ _ ----- I-...- ---
---- -- -- -- -- - --- ----- r -
L1--. - 7
o__I ___~~~~ __pwL{I V
_ _ _ _ _ _ _1 7 1
L4 - :, I I I M I I -
__- R I__ __ IN > _1
: !- --- -_ - - -
'STRJCTUJRAL 1A NTE ESR;iTYTT ____IT Y: T , IV *T
LII 777 F77
_-i--
_____I -~ -I-- -
i - - -----
w-:
----- -- ---
M m0 W no an ON M -K M MMW MwM
17 ~IA 'I~ ~ P ND 4FN MNT
NWF7 T W- NE D *3: 7 '3 0
'I
60- i __
- ~H.
-0 nT ~
K 0
LLLJ1 I .1
F-
-I '~ ~ _____
7 4.......
I.
I. .
__________ __________ I _________ .9 __________
-- --- --
-I I-
-~ ~ 7L-l >
~lK.1
[ i*i *1 i.
I.
IINSTRU 1EN I, k IIE3
FME: NOrE1:
L-~~ O3CRT1 3N
L
I..
4.
~- zzr -
ThI-h-u-
I .. L...
-I---
EU IPM EN HATC T* 9i
* -. 1~ I- -
t ___1 ---
.71 -
- II r -
-4- -L j j.
I -
-_______ -- ______ -. * ---.- - - 7 T I
.. . . .... .
______ RA[>--I-i AL . -E:.F7N )__ _ _
F EE LrNNE EL T.NE ---- _Fj mLs_ STRUCTURAL I NTEIBRiTY 7E ST
--- -VI-P-I -I-.
* :j. £z7imj
.1
* I ~~-iiKi..1_:{:~v7 {>...v:.... -I-.
I: .2..~lTW .7...,.27 -~ _ _
-: I ________ ________
-t II
-- -------- -- ----
TF7
j
OR -t -m NW m) m .m Im" -I Im, so ml No no"m M:
I I I N
II3 o it
L cIC 19 T' O l Fi fL:-E -, ~ ~ ~ -- -- ---- _ I {L
---------- _ _ _ --- ----
Ir:
........ .-.
_ _ _ _~~~~~~~~~~~~ J__ _ _ _ _I-_ _ _ _ _ _ _ _ _ _ _ _ _ _ _
.... ... ...... .... _______ ._________ ... _______ 1 ~ ~~~ .7 ... .- .1 1I-- I
i71
- ~~ -- _- _----
RFI~>I AL EEF.R F1 LN)S 0~~1+
STRUCTURAL I NTEEHRI TY( TES-T~
-~M IM ) SMmm
-:N__I f; IN ONT
Eu-N--T 3 0II _____
-t .1
:1
NI NST RULiMlE:NT 1 N r I7 Cli Rl N N EL-N _r 14~
FRAME N0. E3_ LOCAT ION :AL'L--E-L
4-7 _
7-71 _j
-~ t~i~i~ -- --.------ -
1 - ;. -- ------ _
U1 -- -- --i
... ....... I I ~~~~ ~~_ _ _ _ r H- _ _
_ _ I -_ _ - - -- - .C=L
I -7--
S~~1~~~~~~ jti -n- -t-I- .- I ~ - - ~-~----t------- .-.
~ n.<I ~ - ... J7 ________ ii>
1: S -I....
LS N : ... ND I _ T
-------- _- v
____________ TRUCTURA9L I NTF-EER I TY TEEST I
I
own mm M MW WW am 'as Me M! *a M m m m)A
ND~ I N P D I N T -- -----------I D1:RiNI: 01 T:I NSTRU ~E NT-: 'N 3':'EI8
Ill ~WE~CD * 7H~0lI IFRAME N*O 721 .
I ~~ 0 If R T: 1O0I N ':WALI.-:ELLI 74
-j - rd
_______a wj: A E_ 0' ~ :'I_______ _____
_ _ _ _~~~ L'II ' _ _ I.
--- -- -- - -- - -- : .= _ _ _ V77'>7 m_ -I -- -- ---- _ _ _ _
Lrl F
i a
I I ___ ___ ___ ___ ___ __
___RA~
IAJF9 N, N E Y
Liq LX3
IRLJ EF1L; _
..... .....
STRUCTURRL I NTEER;I
m
''I I.. EN)' 1<
7: -I.
I - -
TY TES.T
i1~~1-7.1 A
I E~'
AW o- lm SO No -K an mm I - W No
-' IST N I C}-IANN~~UEINT ---. 7
------------___ __ __ __ __ __ -__ _ --- ...... .... ,
E RR ME N --- --
-- ---1--
I -----
-- ~~~~- -------- 41 _ _ _
LA --- ---
----- ------ - --
-'iD Fi1
c3- rs I. I .. L.
- I.---.-. -_____
-r I. f--i
4-. ,...I
__- 5S __jFIN N EY-1 ELETNER fIgND -l. S TRU CTURRL 1 NTEGiR: I TY :T ET
~JCJJ1TL~ ILL.LV7 :1!
i
m m ml m in - I -
IN~~I~N.~ONI INSTRUMENT ND:i~
W 3:201CHR E: U-hN -N N 0 ___
WDC * FRRM NOI 1: [-----0 ~ ---
[~~~~~~~~ R _______ .------- L ! _________ --------- _______
.I I I T** .
71 -:7
-- ---- -
:77 -- ---- .......
_ _ _ _ _ _ _ _ __ _ _ _j__ _ F L _
Lj
.- . -_ _ -------- - --
0-I
_ _ _ _ _ _ _ _ __._ _
BF9 D-LR-L_ -D-
L-1: i
~;_~ IMI
- 9 .FNN EY, EL ET NER F=
STRUCTURFIL- A NTEERIJ T- -S~T
m
C mITEs_
.4..:
--------
------
_ kJIE.E * I I
- w - -m go" i, an o" Mn Mg
S-0F
_ _ L-1_ 4 -1
JI
I.
* 4 4
-H-I
NSTRUM~ENT, 1 N C 1'021 RAN-N-E-LNO
R RM E NO 4-38
LDCR
~1~
I O W!N lL L
I.-I-
-v---------
4 44 * - -+- -I-- , ____.drL~ 4 + V1 ______
44 F
.4
I...
.4I..
-V.. I
C3:= --------
+ *+
4- 7-H.v4 1
4 ~~'~1~
..M. . . . . . . . . .
D F- .---.I N
[MT________ STRUCTURFILI! I NTEESl TY ___-
t~ --------
-- -- -- --
- ~ili4 Li
Lrimm
mm--- --------
-- -- --------
on m so I m so m -m Pa No W amI-Won MM mg
I "S T R U_ M_ _ __.--i r3.
*1 .-- 4 2 __32! i
E: D- C 3 *I7,i3
0 .V .
_m t ----------_ i i *4
-4 LT V- -4-~
F -T
A_ ---------- 4
-A SFT N R F
K TRLJCTU R L- I NTEE=FRIlTY TE~
221411<
17~
to Am so ow --
I- * IFND-I RN - FA D I NT
WE DC * 7"30I1
s-:F-I
I IA NSTRUMENT- INllK -I ~-HNNEL
!I T -FRAME NO:
I,--
V& -~ ______________________ 4 __________ 4 -.. ~'----
-- 4- 4 H
I IOCHT I ON: N L' L- -'E I
I j *i *-*~ 7
I.
* I 'I ~ II -, A :1-.. Ii.. - -. .1- 4. F-AL
* * I *-I1-~ 11*4*~~
--- 4- ----A
+ - *~-~:zj ii f 7+i~~ 1 '7TH1
----- - l
- 2H--- F
-4 -I-
-IL.- Lii
I---- -
- I
- ---- F. -
-I ~
zH 1'79V~flF3I7iI
I~~~~ < I I- -7
-- T--
-~ ~ ~ ~~~~~~ L 7______ ___ ___ ___
-4-
I -Ii r ____
I-
-.. ...
4.-
4- -1 :1.: ,~ . II - I-
I I I I
LJINNE Y/ 'E LTNER: iTRUCTURFIL 1 NTEER
L N
I I ~ - I
i-----I-.- H ______ ______
- 17- 71 * I -- I . 4.i~
I. -~
I I I
TY TES5T
---- "F
-i
- 4----.-
-- --------
- - m - - - - ~ m m - m - -
IND IAN'7[ PI NT
-0
~~T~I07
I.
4.
- I.
I .:
I-.
IN STRUME T. N~ M~: 24 ±j
F-RME NO C3lKiI.. LO1CRTIO I O :NWLL_ E LI - 7~.Y
LI * -j - .7
- I - .-.
-l -4 ~ +
* .1-l
- I .-
p -- --- -
I - -
i::t ~ I---- I ~tuLI7. -.1-- tmzz:x
~uJ I fL7W~ ~
- pI -
- --- ---------
0 - --
-0-
m~~7 V-77711
- _ ~- -7
r ~ -1- I~ q L.-...L
RRD --. I -1--- I -H
-- ---- -
,STRUJCTURRL-: INTEErR!I: TYTEST 1 I
-; -- -----1............VI E 1 '
I I
m m mas IM nSm ,M~
~~JN' DI IT1 - -= 3 F
W E D-C M: 7HtA: 01
E
0 _____ -
--SR M N --- N---- - --- -1-
H RNNELYhD *
F*RARM E N~~
J-:
L 13 9T NAL 1N F9 -SP ~ j
-4- IA j-+ -r -~ -I .1 ________
_______________ I 1 -**-t------------
I ~ I -~ _____ ~--t 1.-----*
-- - -- -
.. Z1
7 :7
_~~ ~ ~ ------ _------- _ _
-~~~- - ----- L ____ ___I__
-I-I-
- -I' .1- - -
I- _ _0
L I-- R RDtvqfN N( N) __ ___ __E__
~STRUCTURFqL I . NTES I 1T TEST
-1-
-t -
4-
4-
.1
M, M M@ M - -,M M.M eN a $M M M 'W
---- 1 ---- 4'NE
C-HRNN EL_ N Li 1 j
F- R R-L 3
LI _ 1.
I. F-'--
I ~ ~ --- - ----- t -- -
utx J. .-1---
1 I7t7H Vy-i
2222214 Li> A4 ---1-
-I--i-- 121§1Jz -IT-:--- 2 227122
-~ ~ J 2 1 24 :422 -- -
-~ - ___-1~i ~: I~ I -----2------ -1-- -4--i-- -
F --- t -- ~--* -
172L24 -I - ~- -~
- - V-'- ~r:-9zzF2 V ~-. _ I - - ~ --V
* - I--I ~h'' -- --- ,--- -4 I-.~-~ -4-~~~~*-
74,_~ T7 -
*I.~ l~
TT_ _
___________ ETRUCTU~RRL" I NTEEBRI TY, TEST
-~ 1721 1j1§-t->-' -I--
I - 4
- - I--I-~-j. - i-i - -
4-2
I. -
-1-4
1-I- _____
I-I
I. 1 -
Ei~~C LIE~_
c f
FIT
M- m -m m m m m- " m m m m M
- ----- i- --- *
I ___________
K V.
K; LA:
A
--- Si K-
H.-
[3AI NT.-'
7 L230 1,.1
.1 -i
7 7.
7 7 7 , 7
7 -.1 ___
I N S TR U ME rKi TJ ND
-1 STU~lNT NE:1-Z'1E13SR
-C-HARNN EL NO --:3 S FRRME NMD . 1 -f_ : 7
Lo0C Fi T10N JKNWAiL:L--: EL.
]7i
* I
* -I
Lnp.sv A
I 4~ii'7+A
~~1~ - f-.-.4.---
- --------- _ _
I~1 T. I.
-.17 I
* 7
.7 I
-i-I-. ~1* i.~*.
I.2
- ~ 4 -~-!-~--~t--
-~- -- - ----
Ix i
I7
:1 _ _
-~._ .A L .L .. .
JiTRLICTUR1L 1.NTIERlT( iTES=TI
1 Al -7-it--i-A-:..
IL. . 1 iA Al I -~
_FLJ S.
____ ___ I . __T
-- - -. .. . .
O.A.: --------- -----
m M m m M M- M- MMMMM MMMM
IINLI,-1N':-: PON NSTRUMENTNO; A~E7 .7
F
I ~ ~ ~ ~~~ .............i - _ _ _ _ _ _
F9 I T N
-. 7 7
0-t
I_________ *1 ____ ___ -~--______ I .1 ______ _______ _____7i + - I - - - - - - h-
r-l: r7-1
-- L: S. S I EEN JNEY:/ "ELETNER -.F~ FSEE
S T R TU CT UR F9L 1NTEERI TY. T EST:
* ... I777~
.:17)77
1T-1
.4 ..
*1
- .... i :E I 4-.
- m ~ m m - m - m m m
1 IN PFOI NT::
-U N
:ELI
.... ...... ..
Lrl
ME
I . .....
- -E -7i 7 7 i i
INSTRUMENT- NOC- 1
-RRME NO::9
.1 II FI I. Ex
-..-.-.- t----- 1--I I I I .1 I
I .I I V _ _I-.
J~wv __zi
-177~
- I .4
-i -
- - 4-
______ _________ ________ _________ 4 -I- 1. *~, I
- I.- I. I~ I
v-i :1
I,
4717
-7 - t..jiji-.-.
-. K.J2VLffi
27 1- t'?7hI~ V - -----t ~ I2Th+..
--- 'a ~ - I____ ------.....
-- ~ ~ ----- ------_ _ I _ _ _ _ _ _ _ _ _ _ ....__ _ ...._
_ _ _ _ _ _ _I:_ _ _ _ _ __ _
E--AC- 7.9-D E-.
-F.=N.NE.Y, -. 'ELETNER -- AIN,D--.-HESED3- A-HL-S
STRUCTURRL I NTEE !I TY ;T E ST-
-. - -- - -
j>K2: j..1L V.
I I
__ L11s
------- at
..........
m m m m m m m - m
'IFI I O I N T -E 1 O * 7H-7
W- E4 D -C 0: 4
.177
K ~ Lfl
LF1
4 4 i .44 4 4 4
10 .4~4.44.44i I
1~~
I,,
-NO 1: E2~ sAHNNUE NT
'I :FRRME_:NO
LOCA9T I ON 1:
Tr4
--. ~,
W R LiL
-l 4.~ 44.
- 7------.'
4.4
- -4 44
.4 .4..1 i'
4 4' 4.. ~:.I4- - -1 -
.4 - 1 4 4 4 ___________________ ________________________________________________________________ 44 _______________......-1 -
I -~ -.4jj.-rI I -
I ~ i I .27 24~
4.-.-4 4 4 L...4.......L _______ L _____ 44 4 44 .4. P 44.4.44.4.44.4 . .. .x.!
4 4 .4
44. . j 4.
4.4. 1~~~
4 '44 ~1
* 4.1......I...
.1
.4 4 I. i .4
4...... *1.4 - A -.
I..~ I
~'1 441
I -4-->1: I- -~ -~ ' I
4 4 ~ _____________
44.. j 4 4..
* .:-.4} I
'-.4. +
4- 4.
-- 4.............
- 1~~**7
I 4 4 4 .4 4 4 1
.1.-.4--.-'.
_______ __________
__________
-4 1 4 4 4 4.K'
-l -.
4 4 4 4 4 __ 4 4~~4. 4.4 4..44..4 4.44.444. 4.444.44
1--:~~: 2.LiJ1> 71V44 4.4 44. 4 4
4 ..- I. IL. 1 . 1' 4 .
j 4** 4 .4
M- Ina
-L- R - -L R -. ._: 4 4 .:_
STR UT LCTURRiL I NTERIlTYTS
I . 1 -: V2:z1711. 1 4 I~ -4 ~ 4.4.4...4........ .4~ ~4..44..44.
I.
E L. 9~FT I
4 - 4.4 .4 44.444
4.-i
- --- 7~~::j - ~.4
________4.1- -i 4 ___74___
*-I
.
I ___
--- --- 4
4 I
-4
m m m mmm mimmmmm m mm mm m
I N D IAfN; POC:I N T:
S:1
I- I
Lrl __
I _ _ _ _ _ _ _ _ _ _ _ _ _ _
4
K1 NSTRUMENT. NO ME0 m~r-H RNNEL-N[03
-- - -- - -R: i R ME NO f ~ S 7---------L 74
L 0 LC FiO rN WF9LL E L 7r
LI I
. .. . .. ......
F7% ____ I _ __I I . ...
U-1AL DEF . -0t . T-- I .
R R DEFLI 1W S S U:J 9N N EY, E:Lr\NE:F' FINE SSi0:C I REE
j________ TRUCTUJRRL I rITEGiRATY .TE:ET I I.:
m- m m m m m m m mmm
--- I ND A N W:F I NT ..- HA N LI~ ~~L N V _IN STR UME N ND
K >~~~- ---------~-j
-7
-0
_ _~~7- - - 7_ _ _ _ _ _ __ z z z -
L+0-___
.1 ... ... ._
_ _
U_-1,_ _ _
-, --- j f9- -N E L S.TTN : - ,--,---- [ _____ -. LJ~ m L)~~~ ~ ~ ~ I iFRFiTEC
* TRC~jFL N: TERA TY TEST..
=- m m m m m m m m m m
*D b ' **:- 3 I I
I ______
I NST R UM E NT ND
FRRME_:NO:I
L1CF1TI ON :FLL . s.LL.717+ :tr::
-- I-----
T 7711 77:71:
.. ~~~~_ I ______ ______
LA --- --- -
I --
-I
___________ I ____
* I
1~~
I. I 17.* . I.
~
TV 'f -177t11§ZT
:11~. 71 j-1 . I j: > -T -7
L I. -- ---
_ _ _ I t-~~- ---.---------- _ _
0_ _ _ _ _ _ _ _ _ _ _ _ - -- --- ---- --- ----
- -- -- -
w.
Li-Irr- Lqi CM ----cm -M Mm Mm.mm am am
77.177I R_9 D--F9_ .E F..Iic _L _>
__ TRUJCTURA=L:IlN EG~lT :
t
F~~ }N>:IAN 'F I NT. ;iiL.IF--i-I j NI~~r3 F TV: ,<211~ NSTRUM,1ENT - :' E2 LufiND- >
IC_14 _NN EITN :.3-71 FRAiME NO 72
--- --- ---
____i -ILI-i
4-
___ Fl. N- FL-~j St, C
_____--.NI> R --..SSO-V-F___________________________TEST
- m m m m m m m - m - m - m m
IND IN MW OINT
W~U E D 7 C-:- ti :
.1 . .1_________________ I ~ ~. *:* F
777 t 0
--- -_ _-
I - : -
* * I
......................v.---~I. ...~I V.71 F 7 K.- . . I
1FF .1. .............................................. I* .-.......* . . I
-. .- I I...
i.
I NS T RU M EN T-lN[11r3' ......-.... 4
-- C-H R N- L---N.M 4:' -R RM E NO 13 i S
IiLOCRTlFOCNIE 0. H F T CH EL
~1~. i
I 1 .1 p--A
..............................................................................................................................................7
* . I I *j> I-
~I~
7- _7_____ I. I.
* I- --.- I * .--- -
q m I _ _ _ _ _ _ _ _ _ _ _
h- LI~~ - -__ _ --_ -~ -- _ _
... .. ..... I. ij .
I~~~~~~~~~~~~~~~. _______ _________ .______ ______
_7I
_ _ _ _ _ __._ _ __
_
i1i..~iAJ ..1 * . I
I E9
rn -9- -E T- .R i- B N. ES ,
_____9- H N E E SC T N E F9 ND--h:-L2
STRU'CTbUR L INttE E RAT T EE ST.
ci
.C-.1 Li-T2
--- - -
I -- -
___________ -. *. I ____ I
---I-----* .1I-.
a
I
77 ---------
. . . . . . . . . . ...
S-S 0-
. I
------- -- -
m m- m m m m m m m m m m
F N IR N PiTNT I NT T.: R K 2 :* * 2 CH RNNEL: -NO =7L. . 1- q
W DC E: DH 0 C. M. L- 0:AM NOL..
I~.-
I I
.1 I.~1 LOC TIN
E .1 . . -
LI . . . ~1
*1
*1.
H 1 T C H - -,Sl -
* I I - I ..- -t 4
i..-. *1
..7.4 47~
1K -
1j712:
_ _ _~~~ ..._ _ .-. . . . ......
tI 0
:. .. I .. .._ _ 1 .~- t -.f c ._._.
*F9 M- >
-:'- E.M-~ JHFN N EY E L ST N E.R FND S____ _ T_ SRU T U R 9L I NTEERA TYi TEST
- I --- ------
4~4
.1~.~
CIF~TE~_________
- --- -
7 - 7I
I
. I
- ' -- m m--= ---- =m m===
~iTMN 1 RN j F P 14-41T IFNrR.~ NO... m -:I3S E3< . _ _ .. .. ..
-U N ~ 7H3 F R NE I I ~ ~ I~ I R RF M E N O - L 4
__ _ p . i . . F . ~ .. ..... . i. .I
j
--' - --
IfI R--~~~
__-D1 L9 4'.- D-E ' -]i -N->
I i TRUCTL'RRL;1INTESRITY TE2sT
I-.
- - ---=-m- =- = = = = m = = =-
___________ ITIRUMFNT 'N 13 J__
W E D 7.m"H20l1 :4M N
TIL
7-- ___r
-- -- -
---- ---- - I d t -.
~ZI7 7
C3 2
____ ___ ___ _ _ _ F- ___ ___
.. ... .. --- ----r4- - 1
--- --- -- -- _ _ _ _
__l 4 i. . . . . . . .
RA~LRLPLas;] as)
EMTRUCTURF1L INTEESR1 7Y TE2ST
[
I *---
-I.
I-
- ~ ~ 71.7.j ~
..... .LFITE~ *i {:.j~ *1
.1
____~VLLEE * . I
I
= m - - -- - -= -m -m - -- -
----- NDI FqN- POINT I tK - J. : NS R -'-JN------I
WE__ _ D C 0:: -7L ___ 0 1_ _ __ F RRME NO:00
J LOCHT I ON EL
I- .......- F
I.a ___._------
_ wA
LrI L q
___- L- I
1 01
Fp p
-~1*7 U- * T. I
JH~N.NEY/. 'EL-'iTNER .R NDi--F S-SEiEJCI-F
... TRLJCTURRL-. I NTE:ERI TY ... F ... .... F .. .- - - -
*1 -. :r:: 7>.j7>{>9: I.
TELEirn.4 -.. ... ... 1
.4... A I- SEi
w i s S,
J a n n e
E 1 S
t n e r a
A APPENDIX B s s 0 CRACK SURVEYS c i a t e s
ELEV. 193'-0
ELEV. 188'-0
ELEV. 120'-.0"
ELEV. I15'-0
ELEV..48'- 0"
4 ,
I I
ELEV. .473'-0" 0 1 2 .= 5 4 5 ro 7 6 9 0
INDIAN POINT GENERATING STATION Unit No. 3
CRACK SURVEY-AZIMUTH °
JOB No. 74301Date I-G -75 Time 10: 40 .
Pressure "0"BEEOSE- Tr-Er')
&L , C,CK.S ,&r4l.E 0 005I CD
5KALLE. UNIL F_-S C74E ,WL5E INDICAE-=D.
wE I 1 I I
I WI I v3 I
V
I I
V
I WE ELEV. 43-0"
ELEV. 193'-(
ELEV. 188-0
ELEV. 120'-C
ELEV. 115'-0
ELEV. 48'-"
4-
1 2 5 4 7 ~5 (~ io
)IAN POINT GENERATING STATI Unit No. 3
CRACK SURVEY- AZIMUTH
JOB No. 74301Date 1- 14-74
Time 17:ZO -. <. e.H.
Pressure s4- PsLI _
11
)"
I,
--
().0c .5
\ ( - .()10.
. O D O E 5
IN[ ON
ELEV. 193'-0"
ELEV. 188'-0"
ELEV. 120'-0"
ELEV. 115'-0
ELEV. 48'-0'
.4
3
ELEV. 43'-0"
r I - I ____ I r
2±~~
-j _ IYi~ 0.
---4 -- _
--- F--0 1 2- 3 4 5 6 7 5 9 8Q
INDIAN POINT GENERATING STATION Unit No. 3
CRACK SURVEY- AZIMUTH 1250
JOB No. 74301 Date 1--0-75
Time t,:!5 P.K. 4<S=_ o
Pressure "0 'sL T TET) lNDC- .
ELEV. 19'3'- 0
ELEV. 188'-0'
ELEV. 120'-O'
ELEV. 115'-0
ELEV. 48'-'
ELEV. 43-0"
INDIAN POINT GENERATING STATION Unit No. 3
CRACK SURVEY- AZIMUTH 12E
JOB No. 74301Date .6-73 Time 0a00o 2.K.
Pressure "1" (- -)
ALL CR-6CA<5 A;2F 0.00&'02O 5MALLE-Ve, UNLE-SS. OT4F--WI.5. IND I CLSI-'T D.
" i7 15 9 IC
li -T7
11 7-A,
II
1 2 . 4 5 r "7 8 9 0ELEV. 193'-O'
ELEV. 188'-0"
ELEV. 120-0"
ELEV. 115'-O
ELEV. 48'-"
ELEV. 43-0 '
F Ur LJNE
ALL. CI L Z.< 1t5 TI4E -<TEEN.IS4,N OF [)K5v-.I.':
;'-4Q'TEE ON DD--.Avi?4.
INDIAN POINT GENERATING STATION Unit No. 3
CRACK SURVEY-AZIMUTH I2 g °
JOB No. 74301 Date 1-14-75
Time ooni, Pressure" 41 P-L e. .
AT 41 PsL 0CKINiS OCT-4JJ1NIG MOSTL'<
IN TI4E F IM O= E . SION5 L- OLD C2-.CK5 OZ--. WIEE-NINE7 COf-" "T4E[A.
GEMk--AL C-2AOKI MG
APF_4P~t 70 Ef ;- 9
I I
012 3 4 5 4: 7 8 9 0 ELEV. 193'- 0"
EL -.D y;5 ; ELEV 188"_0".,:07 -- J " !
- \ C 7
ELEV. 120'- 0
ELEV. 115'-0
ELEV. 48'-0"
ELEV. 4;3'-0"
IN[)IAN POINT GENERATING STATI Unit No. 3
CRACK SURVEY-AZIMUTH 12g
JOB No. 74301
ION
Date 1 -14-75 Time . :15 k.
Pressure . P_5.ALL CPACV,.2 4PE o.CQ5 " oQ 5M4LLE=, UNLE ,,5D Cn-=WII N DI CTE D.
IN[)IAN POINT GENERATING STATI Unit No., 3
CRACK SURVEY-AZIMUTH 129°
JOB No. 74301
ION
Date 1-20-75 Time 15:4s Q.k ALL Cp_c4 ARE Q 0 o DPs"o
PreLLe, UL,,ISS P--.LWl Pressure "2 P. 5L (Ar-Tr-P TrEsT),,C-r.
ELEV. 193'-0"
V
I I N I j I I I 1 I
I I I I 'I
20 19 18
17
16
15
14
13
12
10
9
8
7
6
5 4
2
___ -__ o .,_
- AIjI- 1 K - ~
±1 I F---______
20 13 18 17,IG I 14 15 12 11 10 3 5 ' 7 G 5 4 3 Z 1 0
INDIAN POINT GENERATING STATION Unit No. 3
EQUIPMENT HATCH BOSS
JOB No.74501 p
Date -0- 75
Time o6:,oo
Pressure "0" PsL L -4)_..cW
Surveyed by .K. 0E ,-__
20 19 '0
.1 1_ _Y_ E
17
16
15 1 14.
13 101
I Il 4
-A-F
2019 18 17 I15i 141I121 19 8 7 C 5 4 5 2 10
INDIAN POINT GENERATING STATION
Unit No. 3 EQUIPMENT HATCH BOSS
JOB No.74301
Date 1-14--75
Time : l1
Pressure 54 p5L
Surveyed by '.K.
A4W C2&c-Is 42E 0.00O5!, op!5 1 E.) Ut.JL.= SS Cr4E-RWl,5E= INDICATED
I I
h-I I I I WI I.. 1 I I
hIVE
U WI I I
20
19
18
17
16
15
14
13
12
11
I0
9
8
7 6
5 4
3
2.
I J ,
i 77
_1__!2/ '
20 19 18 17 I 15 i4 15 11 J1 9 8 7 G 5 4 3 2 10
INDIAN POINT GENERATING STATION Unit No. 3
EQUIPMENT HATCH BOSS JOB No.74301 p
Date ,-2o-7 Time : o
Pressure o psL (L4pte 1-Eir) ALL c. 1.2 G_ o op
Surveyed by , ,N ~W-5_
ELEV. 83'- 6
I I 2
/~ k '
______ .1- -~ 4 4'
N_ 14 HI_3 4 5 6 7 8 9 -10
PERS. LOCK
INDIAN POINT GENERATING STATION Unit No. 3
PERSONNEL LOCK BOSS AREA JOB No. 74301
Date 1-G-75
TIme 1 .oo Pressure It 0pL
Surveyed 12K.
A"w C1L--'KS &REM O.0-51 cO
SM,6LU UNLE, W-D.
T
9
8
7
6
5
4
3
2
PERS. LOCK
INDIAN POINT GENERATING
Unit No. 3 PERSONNEL LOCK BOSS
JOB No. 74301
Date 1-14-75
Time s -:j5
Pressure 54 .sL
Surveyed S.I,
NLCR4.CK-5 WRE 0,::)5" OP.
5M \I 2)U 1N.JEZ;, cZ7Tl4P \A 1
AREA
Ln55 T-AAK, - i'
CI2&:K TAI"Q5 F=Cv 0.10" 47 7'4E COF IJ. TO .025 4T " 'S --C 11 4
PER5OWN EL LOCK 5055 AREA
Date: 1/14/74
Time: 15:15
Prssure: 54 Psi. 5urveyed bg: :
-- 04it X 15i Lo,'47
APPR-c Ot /,T-- A .&T T64EC :':I. ::
.015"
.02.5 "--
.04" FOR I-o
.01" FOR .C
0'cx 0."
NOT ACC-SS;PLCL
-1
-± -05 00"
_-.075"
DIGPLACED fI"
PEReONNEL LOCK BOSS AREA
Date
Time- 1300 Hrs Pressure - 41 p.s.i.
Surveyed by - SGP
NOTE
ALL CRACKS ARF- O.OO5" UNLESS NOTED.
.05* 002
.C:c&51
.004 11
.O151i r-0 21C'-.
,007 P
- .01 +
.015 i
.0C5' D
. .C-c5 :
SEYOKID WALL_
-,025
D!r: PLA CEr) /
PERSCNNl'EL LOCK BOSS AREA
Date: 1/20/7,5
Time: 15:00 HR5.
Preosure •!"O 2PSL AMEP TES--T
Surveyed by: i.K.
NOTE: ALL C-ACKS A4E O.005 I
UlLE D5 OT44E.W15E H0-1 ,.
DATE: I./17/74 TIME: 13:00 MAPPIED 5Y- 2 \WOLFF
- ---
... EL. 7.5'n EL
/ 1 f~~t,4 F-'-TTeD F 1O. ' ~~~TO gQU LIrm IY- I
F2C
- - - I
F I *
F I~ F F
F I
F F' F I
F F
F I F F
4CDe
1.1_ L I t ! / J i j
DO~ME AJZE/
F I
i t
I .:IFE. F'O A FI F! ID M
F .F .. i
,rzI F I F I
2010
ir.)ZKCD po
DATE: 12/17/74 TIMG- 15:OO KAPPED y: P.V\/OLFF-
, . , ,
. .... I-
:.- -
< I f
, :.: . . . . .
S .. .... .. ....... .. ..... ....... ... ,L L.. ............ ..
1000....
r
70 oAL.95'
I I I' I
IH$F~CTI~D F~OH
\
.. .. .
DATE-: 12/17/74 TIKAE-: 13:30 MAPPED BY: R.V/0LFF
I 11951
E... ......
I1 1-j
i~olo170r160015(D
I: JJ
I p
IEL. '2G'-2I 'Y*
IK5P~OTE=-D FROM~ AREA.
DATE: 12/17/74
II I
.. L i J..
TIME: 13-50
JL't 1 /4
MAPPED BY: P-, WOL;FE.1
Ti j -I
Ii
*DOME Z 2Z
EL
22Y~
* I
210b
- -
* *1
4 2L300 9Qb
.......
' LAC):-,
DATE: 12/17/74 TIME" I:5 MAPPIED 5Y: R. WOLF-
It
* I I
* I
.~L. 2W~'
- I
2~0o ~ 24o~
* I.
*1
OINPECTE H-:.Cl
:.i
DATE 2/17/74 7Tf
al I I : i' I .i . I I ,
: I i ii i . ..
MAPPP-ID 5Y: Q,\A/OLF"
t o I
E I ". i t
/
(I)
35c~01~iiii
II
~~0e - -
TIME : 5 :5C0
2~ZL
IM5PECTED f=CM DOME 1RE4
' EL. 193'
I
I 16
II I
)ATE: 12/18/74
*.
I.
II
(
TIME:130 MAPPED
P-Q~LPMI1VfFH4TO"-4
55 * * . I , I • : I. . .
LBL 43• ___
S5...0400
... . . . . .. . . .. .. .. . .. . .
iI
i! : ;2 0
1031
~QO
EY: R ,WOLPF
i ! " : : i . . .
rl
J DATE: 12/q/'74 EL. _7 -1 .7,77....
175'i-i
I
1,4N IA
T1ME: 10:50 MkPPED Y" RI. WOLPF
I
* I * I
lie)
Io~
FUEL !T5C 2AG,1UILDll9
I EL.45
Is
II . . L . .; : ! . ;
.- -! . -I .; -.Ii.
IFNA=
IICY eQ0 CO
75
58
... 00._ _ ..... "'0
1101 I 00 °E Q:) _/ v
DATE 1,2/ 19/74IEL. 193'
.. I 178
I
1C:3I
TIME : 05:50
NE
I -- 5 ' 7. ,... .. ... . ...
i -_ .-.i
Pr=,R50l NEL
170
* I * I
L K A.ZIMUTH f ZOC1AO 40 kNE EIRIO CC icc) Qz F4A1' W9ILDINE,
D ALLEy WAY, Z-LC:
I -
1500
1 cII: " ii:40
Ii t1
P - i bo-
w4APPED bY: .VOF
MASPPED BY: . WOLFF
)1'
73' 5 I0 'WI A I <K: p
PAN W0OM
.. I 1,o
I
14$' "i
11(s
Io
I:
DATE : 12/193/74 TIME ". 14:00
! .
2 10024E°
DATE: 12/19/74
17. ~I .78 1.
I I
TIME: 15:50 MAxPPED EY . R. WOLPP
' lei
1035
75'L.
ii I I
I- I I ____________-
2S00
I I
SSHIEWD WALLPEEN ET;ZATMOl
II
I.,.,. I..
* I
'I
2 7 0 " 2 5 0 0 ° 2 5 0
i
4 -.- 0"
II 1 - ;.. I ;- !, :,
DATE: 12/13/74 TIME: 14:00 MAPPED BY • R. WOLPFIL. ~91' I
wE 178'
148 U* 4"'
118
751
* I ( F
p jI. I
I I j ii II, I II'
~G00~, 4.0
I.
* . I.
IL431 I-.
I I
3200
51 iI,
SI Ci l
500!
D4TE-: 1/ PJ L. 3TT'
I
I H I
tFo
20/74. "
I i
- - -. . ... .. .....
FIME: Oc5:~O M.PPED BY :. WOLFF
U
0
S 1 i _! 1. EL S5 ; :
I: I. -I -
I I
I'A4JO~ CZt~ZK
P, L 01010i1
1
I U I I I I I I I I I U I I I I I I
<I