Upload
halia
View
25
Download
0
Embed Size (px)
DESCRIPTION
1 ppm contours. Strategy to reduce uncertainty on a m to < 0.25 ppm. David Hertzog University of Illinois at Urbana-Champaign. Present data rates How to achieve higher rates Statistical and systematic targets Timescales and Support. - PowerPoint PPT Presentation
Citation preview
June 17, 2004 / Collab Meeting
Strategy to reduce uncertainty on a to < 0.25 ppmDavid Hertzog
University of Illinois at Urbana-Champaign
Present data rates
How to achieve higher rates
Statistical and systematic targets
Timescales and Support
1 ppm contours
June 17, 2004 / Collab Meeting
How to achieve a factor of > 2 reduction in world-average a uncertainty
[ppm]Final uncertainty from E821 0.54 2001 systematic from a 0.21
2001 systematic from p 0.17
Target statistical uncertainty 0.20 Target systematic from a 0.10Target systematic from p 0.10
Target E969 overall uncertainty 0.25Final BNL Goal (E821 + E969) 0.22
Implications• Data increase necessary compared to 2001 - run x 12
• Reduction of systematic uncertainties by factor of 2
• More muons are necessary
• Q (integrated) method probable main mode
Goal
June 17, 2004 / Collab Meeting
My rate calculation – standard conditions1. 34 B counts; A = 0.4 → 0.2 ppm statistical (my sim/fit)
2. AGS Intensity = 50 Tp (avg)
3. AGS Rep rate = 2.7 s
4. AGS fill structure = 12;
5. 10,000 +/fill/50 Tp
6. Acceptance E > 1.8 GeV = 0.12 Item Value
Counts needed 3.4 E10
Correct for T0 (30 s) 5.4 E10
Correct for acceptance 4.5E11
Fills @ 10k/fill 4.5E7
Hours required (1600/h) 2812 h
Run-time “uptime” = 0.7 4000 h
Weeks @ 100 h/week 40 weeks
Setup 3-4 weeks
Total 44 weeks
Reduce by More Muon Factor
June 17, 2004 / Collab Meeting
Conservative changes yield factor of 2.6
Item Comment Factor
Replace traceback with calorimeter
Vacuum chamber change ( $50 k)
24 / 23 = 1.04
Use positive muons + cross section is higher 1.2
Add 4th kicker @ 270º(see plot below)
Increased stored muon fraction Fabrication and tracking studies are necessary ( $250 k)
?????
Open up inflector ends(design report)
Task looks reasonable but work must begin ASAP ( $750 k)
1.75
Total 2.2 + ??
Present: CLOSED End Proposed: OPEN End
June 17, 2004 / Collab Meeting
BNL Storage Ring
incoming muons
Quads
KICK
0 500 ns
100kV
4th Kicker
3 Kickers
Present Infle
ctor
Proposed Infle
ctor
June 17, 2004 / Collab Meeting
Next big idea: Double quads in FODO section Hugh & Paul
This gives a reliable factor of 4 more muons Even more quads under consideration now Questions of momentum acceptance need to be addressed
New Beamline Transport
June 17, 2004 / Collab Meeting
Next REALLY big idea: Use backward pion decays Peter (Kammel) & Paul
Gain: Another factor of 2 NO FLASH (no pions, no protons into ring) Double checking kinematics Some significant changes to upstream beamline
5.22 GeV GeV
5.22 GeV
GeV
The “Quad” section
This needs work to go to
5.2 GeV
June 17, 2004 / Collab Meeting
Summary of possibilities that will be considered
Conservative = 2
Quad double = 2
Backward Decay = 4
Net = 16 (!) all of this can’t be right
Basic conclusion: We can find a factor of at least 5 among this set of topics
Basic reality: Some of them won’t work out
June 17, 2004 / Collab Meeting
Maintenance and conventional upgrade tasks should begin soon on conventional systems
e+
TIME
Co
un
ts
New detectors and hodoscopes?
New WFDs New DAQ
Plan B refrigerator a must
Kicker #1 repair
Quad maintenance
Ring de-rusting
Probe replacements
Trolley external calibration
June 17, 2004 / Collab Meeting
Systematic Error Evolution
Field improvements will involve special trolley external calibrations, temperature stability of room, replacement of many fixed probes
Precession improvements will involve new scraping scheme, lower thresholds, more complete digitization periods, better energy calibration
Systematic uncertainty (ppm) 1998 1999 2000 2001 200X
Goal
Magnetic field – p 0.5 0.4 0.24 0.17 0.10
Anomalous precession – a 0.8 0.3 0.3 0.21 0.10
June 17, 2004 / Collab Meeting
Running hours, schedule and costs Time required for - running to 0.66 ppm (statistical)
1000 h (+ setup) = 1250 h
Time required to achieve 0.20 ppm with factor of 5 increase in data rate 2200 h + setup = 2500 h (25 w)
Ready 2 years after funding for shot on demand beam tuning and 2 weeks physics commissioning run
Following year, take 20+ weeks (time depends on factors)
Activity Year
Proposal / PAC 2004
Obtain $$ / start R&D 2005
R&D and Construction 2006
Construction
Commissioning
2007
Full run 2008