107
STORMWATER POLLUTION PREVENTION PLAN FOR JUNEAU INTERNATIONAL AIRPORT MAY 2009

STORMWATER POLLUTION PREVENTION LAN FOR · PDF filePainting ... and responsibilities of the stormwater pollution prevention team required by the 2008 MSGP are included. ... City and

Embed Size (px)

Citation preview

  • STORMWATER POLLUTION PREVENTION PLAN

    FOR

    JUNEAU INTERNATIONAL AIRPORT

    MAY 2009

  • JNU SWPPP i Table of Contents, Certifications

    Table of Contents Stormwater Pollution Prevention Plan

    CHAPTER 1 AIRPORT MANAGER OVERVIEW ............................................................................ 1-1

    1-A DOCUMENT LAYOUT .................................................................................................................. 1-11-B OVERVIEW .................................................................................................................................. 1-1

    CHAPTER 2 PLANNING & ORGANIZATION ................................................................................. 2-1

    2-A OVERVIEW .................................................................................................................................. 2-12-B SITE SPECIFIC DATA ................................................................................................................... 2-12-C STORMWATER POLLUTION PREVENTION TEAM ......................................................................... 2-22-D RECORDS .................................................................................................................................... 2-3

    CHAPTER 3 SITE ASSESSMENT ....................................................................................................... 3-1

    3-A OVERVIEW .................................................................................................................................. 3-13-B ASSESSMENT AREAS ................................................................................................................... 3-3

    3-B.1 Main Ramp ..................................................................................................................... 3-33-B.2 Auto Parking .................................................................................................................. 3-33-B.3 Runway and Taxiway ..................................................................................................... 3-43-B.4 West Ramp ..................................................................................................................... 3-43-B.5 Bulk Fuel Storage ........................................................................................................... 3-53-B.6 FAA Automated Flight Service Station .......................................................................... 3-53-B.7 East Ramp ...................................................................................................................... 3-53-B.8 National Guard Ramp .................................................................................................... 3-53-B.9 D-2 Ramp ....................................................................................................................... 3-63-B.10 TEMSCO Helicopters Ramp .......................................................................................... 3-63-B.11 Float Pond ..................................................................................................................... 3-63-B.12 Drainage Areas along Road System outside Fence ....................................................... 3-6

    3-C DESCRIPTION OF POTENTIAL POLLUTANT SOURCES ................................................................. 3-73-C.1 Inventory of Exposed Materials ..................................................................................... 3-73-C.2 Spills and Leaks ............................................................................................................. 3-9

    3-D NON-STORMWATER DISCHARGES ............................................................................................ 3-103-E NON-STORMWATER DISCHARGE INSPECTIONS ........................................................................ 3-10

    CHAPTER 4 BEST MANAGEMENT PRACTICES (BMPS) ............................................................ 4-1

    4-A OVERVIEW .................................................................................................................................. 4-14-A.1 Baseline BMPs ............................................................................................................... 4-1

    Good Housekeeping ....................................................................................................................... 4-2Visual Inspections .......................................................................................................................... 4-3Spill Prevention .............................................................................................................................. 4-3Spill Response ................................................................................................................................ 4-4Fueling ........................................................................................................................................... 4-4Vehicle Maintenance ...................................................................................................................... 4-5Vehicle, Plane, and GSE Washing ................................................................................................. 4-6Chemical and Hazardous Materials Loading and Unloading ......................................................... 4-6Painting .......................................................................................................................................... 4-6Storage ........................................................................................................................................... 4-6Employee Training ......................................................................................................................... 4-7Education ....................................................................................................................................... 4-7

    4-B ADVANCED BMPS ...................................................................................................................... 4-7Storm Drain Maintenance .............................................................................................................. 4-7

  • JNU SWPPP ii Table of Contents, Certifications

    CHAPTER 5 INSPECTIONS, VISUAL ASSESSMENTS, STORMWATER MONITORING, & TRAINING ............................................................................................................................................... 5-1

    5-A OVERVIEW .................................................................................................................................. 5-15-B ROUTINE FACILITY INSPECTIONS ............................................................................................... 5-15-C QUARTERLY VISUAL ASSESSMENTS .......................................................................................... 5-25-D BENCHMARK MONITORING ........................................................................................................ 5-35-E ANNUAL COMPREHENSIVE SITE INSPECTION ............................................................................ 5-45-F TRAINING ................................................................................................................................... 5-5

    CHAPTER 6 SWPPP CALENDAR & BLANK FORMS .................................................................... 6-1

    6-A SWPPP CALENDAR .................................................................................................................... 6-26-B FACILITY INSPECTION LOG ........................................................................................................ 6-36-C QUARTERLY VISUAL ASSESSMENT LOG .................................................................................... 6-56-D BENCHMARK MONITORING LOG ................................................................................................ 6-66-E ANNUAL SWPPP TRAINING LOG ............................................................................................... 6-76-F EPA MDMR (MSGP DISCHARGE MONITORING REPORT) ........................................................ 6-8

    TABLES

    TABLE 2-1 - FACILITY DATA SHEET .......................................................................................................... 2-1 TABLE 2-2 - JNU POLLUTION PREVENTION TEAM .................................................................................... 2-1 TABLE 3-1 - TENANTS AT JUNEAU INTERNATIONAL AIRPORT .................................................................. 3-1 TABLE 3-2 - INVENTORY OF MATERIALS ................................................................................................... 3-2 TABLE 3-3 - SPILL HISTORY SUMMARY ..................................................................................................... 3-9 TABLE 5-1 - BENCHMARK MONITORING PARAMETERS ............................................................................. 5-3

    Appendices 2008 MSGP .................................................................................................................................. APPENDIX A

    Figures FIGURE 3-1, ASSESSMENT AREAS ................................................................................. INSIDE BACK COVER FIGURE 3-2, STORMWATER DRAINAGE, OUTFALLS, AND INSPECTION AREAS ............... INSIDE BACK COVER

  • JNU SWPPP Airport Manager Overview 1-1

    Chapter 1 Airport Manager Overview

    1-A This document is designed to ensure that Juneau International Airport (JNU) is complying with the Environmental Pr