37
Stormwater Overland Flow TP108 CALCULATIONS Site: 52 North Road, Clevedon Project No. 1169 Prepared by : B Xiao Checked :V Crang Date: 19 August 2017

Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

Stormwater Overland Flow

TP108 CALCULATIONS

Site: 52 North Road, Clevedon

Project No. 1169

Prepared by : B Xiao

Checked :V Crang

Date: 19 August 2017

Page 2: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

Worksheet 1: Runoff Parameters

and Time of Concentration

By B Xiao Date 21/08/2017

Location: catchment A Checked V Crang Date 21/08/2017

Job No 1169

Circle one: Present Developed (Pervious)

1. Runoff Curve Number (CN) and Initial Abstraction (Ia)

Soil name Cover description Curve Area Product

and (cover type, treatment & Number (ha) of CN x

classification hydrologic condition) CN* area

C urban lawn 74 0.36 27

* from Appendix B on TP 108 Totals = 0.36 27

Pervious area 30% of Catchment

CN (weighted) = total product / total area = 74.0

Ia (weighted) = 5 x pervious area / total area = 5.00 mm

2. Time of Concerntration

Channelisation factor ……… C = 0.60 (from Table 4.2)

Catchment length ……… L = 0.16 km (along drainage path)

Catchment slope ……… Sc = 0.025 m/m (by equal area method)

Runoff factor, CN / (200 - CN) = 74.0 / (200-74.0) = 0.59

tc = 0.14 C L0.66

(CN / (200 - CN))-0.55

Sc-0.30

= 0.14 x 0.6 x 0.20.66

x 0.59-0.55

x 0.023-0.30

= 0.102 hrs

SCS Lag for HEC-HMS ………. Tp = 2 / 3 tc = 0.07 hrs

Project: 52 North Road, Clevedon

Page 3: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

Worksheet 1: Runoff Parameters

and Time of Concentration

By B Xiao

Location: Catchment A Checked V Crang

Job No 1169

Circle one: Present Developed (impervious)

1. Runoff Curve Number (CN) and Initial Abstraction (Ia)

Soil name Cover description Curve Area Product

and (cover type, treatment & Number (ha) of CN x

classification hydrologic condition) CN* area

Building, Roads etc 98 0.83 81

* from Appendix B Totals = 0.83 81

impervious area 65%

CN (weighted) = total product / total area = 98.0

Ia (weighted) = 5 x pervious area / total area = 0.00 mm

2. Time of Concerntration

Channelisation factor ……… C = 0.60 (from Table 4.2)

Catchment length ……… L = 0.16 km (along drainage path)

Catchment slope ……… Sc = 0.025 m/m (by equal area method)

Runoff factor, CN / (200 - CN) = 98.0 / (200-98.0) = 0.96

tc = 0.14 C L0.66

(CN / (200 - CN))-0.55

Sc-0.30

= 0.14 x 0.6 x 0.200.66

x 0.96-0.55

x 0.023-0.30

= 0.077 hrs

SCS Lag for HEC-HMS ………. Tp = 2 / 3 tc = 0.05 hrs

Project: 52 North Road, Clevedon

Page 4: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

Worksheet 2: Graphical Peak Flow rate

By B XIAO Date 21/08/2017

Location: Catchment A V CRANG

Job No 1169

Circle one: Present Developed (Pervious)

1. Data (from Worksheet 1)

Catchment area A = 0.0036 km2

Runoff Curve No CN = 74.0

Initial abstraction Ia = 5.00 mm

Time of concentration tc = 0.102 hrs

2.Calculate Storage, S = (1000 / CN - 10) x 25.4 = 89.2 mm

Storm #1

3. Average recurrence Interval, ARI (yr) 100 Year

4. 24 hour rainfalll depth, P24 (mm)

185mm

plus

16.8%

climate

change 217

5. Compute C*= P24 - 2Ia 0.54

P24 - 2Ia + 2S

6. Specific peak flow rate q* 0.132

(from fig 5.1)

7. Peak Flow rate, qp(A) = q* A P24 (m

3 / s) 0.103

8. Runoff depth,Q24 = (P24 - Ia)2

mm 149.20

(P24 - Ia) + S

9. Runoff volume, V24 = 1000 x Q24 A (m3) 537

Project: 52 North Road, Clevedon

Page 5: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

Worksheet 2: Graphical Peak Flow rate

By B Xiao Date 21/08/2017

Location: Catchment A Checked V Crang

Job No 1169

Circle one: Present Developed (impervious)

1. Data (from Worksheet 1)

Catchment area A = 0.0083 km2

Runoff Curve No CN = 98.0

Initial abstraction Ia = 0.00 mm

Time of concentration tc = 0.077 hrs

2.Calculate Storage, S = (1000 / CN - 10) x 25.4 = 5.18 mm

Storm# #1

3. Average recurrence Interval, ARI (yr) 100 Year

4. 24 hour rainfalll depth, P24 (mm)

185mm

plus

16.8%

climate

change 217

5. Compute C*= P24 - 2Ia 0.95

P24 - 2Ia + 2S

6. Specific peak flow rate q* 0.177

(from fig 5.1)

7. Peak Flow rate, qp(A) = q* A P24 (m

3 / s) 0.319

8. Runoff depth,Q24 = (P24 - Ia)2

mm 211.94

(P24 - Ia) + S

9. Runoff volume, V24 = 1000 x Q24 A (m3) 1759

Project: 52 North Road, Clevedon

Page 6: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

Worksheet 1: Runoff Parameters

and Time of Concentration

By B Xiao Date 21/08/2017

Location: catchment B Checked V Crang

Job No 1169

Circle one: Present Developed (Pervious)

1. Runoff Curve Number (CN) and Initial Abstraction (Ia)

Soil name Cover description Curve Area Product

and (cover type, treatment & Number (ha) of CN x

classification hydrologic condition) CN* area

C urban lawn 74 0.14 10

* from Appendix B on TP 108 Totals = 0.14 10

Pervious area 30% of Catchment

CN (weighted) = total product / total area = 74.0

Ia (weighted) = 5 x pervious area / total area = 5.00 mm

2. Time of Concerntration

Channelisation factor ……… C = 0.60 (from Table 4.2)

Catchment length ……… L = 0.07 km (along drainage path)

Catchment slope ……… Sc = 0.006 m/m (by equal area method)

Runoff factor, CN / (200 - CN) = 74.0 / (200-74.0) = 0.59

tc = 0.14 C L0.66

(CN / (200 - CN))-0.55

Sc-0.30

= 0.14 x 0.6 x 0.150.66

x 0.59-0.55

x 0.045-0.30

= 0.090 hrs

SCS Lag for HEC-HMS ………. Tp = 2 / 3 tc = 0.06 hrs

Project: 52 North Road, Clevedon

Page 7: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

Worksheet 1: Runoff Parameters

and Time of Concentration

By B Xiao Date 21/08/2017

Location: Catchment B Checked V Crang

Job No 1169

Circle one: Present Developed (impervious)

1. Runoff Curve Number (CN) and Initial Abstraction (Ia)

Soil name Cover description Curve Area Product

and (cover type, treatment & Number (ha) of CN x

classification hydrologic condition) CN* area

Building, Roads etc 98 0.32 31

* from Appendix B Totals = 0.32 31

impervious area 65%

CN (weighted) = total product / total area = 98.0

Ia (weighted) = 5 x pervious area / total area = 0.00 mm

2. Time of Concerntration

Channelisation factor ……… C = 0.60 (from Table 4.2)

Catchment length ……… L = 0.07 km (along drainage path)

Catchment slope ……… Sc = 0.006 m/m (by equal area method)

Runoff factor, CN / (200 - CN) = 98.0 / (200-98.0) = 0.96

tc = 0.14 C L0.66

(CN / (200 - CN))-0.55

Sc-0.30

= 0.14 x 0.6 x 0.150.66

x 0.96-0.55

x 0.045-0.30

= 0.069 hrs

SCS Lag for HEC-HMS ………. Tp = 2 / 3 tc = 0.05 hrs

Project: 52 North Road, Clevedon

Page 8: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

Worksheet 2: Graphical Peak Flow rate

By B Xiao Date 21/08/2017

Location: Catchment B Checked V Crang

Job No 1169

Circle one: Present Developed (Pervious)

1. Data (from Worksheet 1)

Catchment area A = 0.0014 km2

Runoff Curve No CN = 74.0

Initial abstraction Ia = 5.00 mm

Time of concentration tc = 0.090 hrs

2.Calculate Storage, S = (1000 / CN - 10) x 25.4 = 89.2 mm

Storm# #1

3. Average recurrence Interval, ARI (yr) 100 Year

4. 24 hour rainfalll depth, P24 (mm)

185mm

plus

16.8%

climate

change 217

5. Compute C*= P24 - 2Ia 0.54

P24 - 2Ia + 2S

6. Specific peak flow rate q* 0.145

(from fig 5.1)

7. Peak Flow rate, qp(B) = q* A P24 (m

3 / s) 0.044

8. Runoff depth,Q24 = (P24 - Ia)2

mm 149.20

(P24 - Ia) + S

9. Runoff volume, V24 = 1000 x Q24 A (m3) 209

Project: 52 North Road, Clevedon

Page 9: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

Worksheet 2: Graphical Peak Flow rate

By B Xiao Date 21/08/2017

Location: Catchment B Checked V Crang

Job No 1169

Circle one: Present Developed (impervious)

1. Data (from Worksheet 1)

Catchment area A = 0.0032 km2

Runoff Curve No CN = 98.0

Initial abstraction Ia = 0.00 mm

Time of concentration tc = 0.069 hrs

2.Calculate Storage, S = (1000 / CN - 10) x 25.4 = 5.18 mm

Storm# #1

3. Average recurrence Interval, ARI (yr) 100 Year

4. 24 hour rainfalll depth, P24 (mm)

185mm

plus

16.8%

climate

change 217

5. Compute C*= P24 - 2Ia 0.95

P24 - 2Ia + 2S

6. Specific peak flow rate q* 0.177

(from fig 5.1)

7. Peak Flow rate, qp(B) = q* A P24 (m

3 / s) 0.123

8. Runoff depth,Q24 = (P24 - Ia)2

mm 211.94

(P24 - Ia) + S

9. Runoff volume, V24 = 1000 x Q24 A (m3) 678

Project: 52 North Road, Clevedon

Page 10: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

Worksheet 1: Runoff Parameters

and Time of Concentration

By B Xiao Date 21/08/2014

Location: catchment C Checked V Crang

Job No 1169

Circle one: Present Developed (Pervious)

1. Runoff Curve Number (CN) and Initial Abstraction (Ia)

Soil name Cover description Curve Area Product

and (cover type, treatment & Number (ha) of CN x

classification hydrologic condition) CN* area

C urban lawn 74 0.07 5

* from Appendix B on TP 108 Totals = 0.07 5

Pervious area 30% of Catchment

CN (weighted) = total product / total area = 74.0

Ia (weighted) = 5 x pervious area / total area = 5.00 mm

2. Time of Concerntration

Channelisation factor ……… C = 0.60 (from Table 4.2)

Catchment length ……… L = 0.07 km (along drainage path)

Catchment slope ……… Sc = 0.051 m/m (by equal area method)

Runoff factor, CN / (200 - CN) = 74.0 / (200-74.0) = 0.59

tc = 0.14 C L0.66

(CN / (200 - CN))-0.55

Sc-0.30

= 0.14 x 0.6 x 0.150.66

x 0.59-0.55

x 0.023-0.30

= 0.048 hrs

SCS Lag for HEC-HMS ………. Tp = 2 / 3 tc = 0.03 hrs

Project:52 North Road, Clevedon

Page 11: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

Worksheet 1: Runoff Parameters

and Time of Concentration

By B Xiao Date 21/08/2017

Location: Catchment C Checked V Crang

Job No 1169

Circle one: Present Developed (impervious)

1. Runoff Curve Number (CN) and Initial Abstraction (Ia)

Soil name Cover description Curve Area Product

and (cover type, treatment & Number (ha) of CN x

classification hydrologic condition) CN* area

Building, Roads etc 98 0.16 16

* from Appendix B Totals = 0.16 16

impervious area 65%

CN (weighted) = total product / total area = 98.0

Ia (weighted) = 5 x pervious area / total area = 0.00 mm

2. Time of Concerntration

Channelisation factor ……… C = 0.60 (from Table 4.2)

Catchment length ……… L = 0.07 km (along drainage path)

Catchment slope ……… Sc = 0.051 m/m (by equal area method)

Runoff factor, CN / (200 - CN) = 98.0 / (200-98.0) = 0.96

tc = 0.14 C L0.66

(CN / (200 - CN))-0.55

Sc-0.30

= 0.14 x 0.6 x 0.150.66

x 0.96-0.55

x 0.023-0.30

= 0.036 hrs

SCS Lag for HEC-HMS ………. Tp = 2 / 3 tc = 0.02 hrs

Project: 52 North Road, Clevedon

Page 12: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

Worksheet 2: Graphical Peak Flow rate

By B Xiao Date 21/08/2017

Location: Catchment C Checked V Crang

Job No 1169

Circle one: Present Developed (Pervious)

1. Data (from Worksheet 1)

Catchment area A = 0.0007 km2

Runoff Curve No CN = 74.0

Initial abstraction Ia = 5.00 mm

Time of concentration tc = 0.090 hrs

2.Calculate Storage, S = (1000 / CN - 10) x 25.4 = 89.2 mm

Storm# #1

3. Average recurrence Interval, ARI (yr) 100 Year

4. 24 hour rainfalll depth, P24 (mm)

185mm plus

16.8% climate

change 217

5. Compute C*= P24 - 2Ia 0.54

P24 - 2Ia + 2S

6. Specific peak flow rate q* 0.145

(from fig 5.1)

7. Peak Flow rate, qp(C) = q* A P24 (m

3 / s) 0.022

8. Runoff depth,Q24 = (P24 - Ia)2

mm 149.20

(P24 - Ia) + S

9. Runoff volume, V24 = 1000 x Q24 A (m3) 104

Project: 52 North Road, Clevedon

Page 13: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

Worksheet 2: Graphical Peak Flow rate

By B Xiao Date 21/08/2017

Location: Catchment C Checked V Crang

Job No 1169

Circle one: Present Developed (impervious)

1. Data (from Worksheet 1)

Catchment area A = 0.0016 km2

Runoff Curve No CN = 98.0

Initial abstraction Ia = 0.00 mm

Time of concentration tc = 0.069 hrs

2.Calculate Storage, S = (1000 / CN - 10) x 25.4 = 5.18 mm

Storm# #1

3. Average recurrence Interval, ARI (yr) 100 Year

4. 24 hour rainfalll depth, P24 (mm)

185mm

plus16.8%

climate change 217

5. Compute C*= P24 - 2Ia 0.95

P24 - 2Ia + 2S

6. Specific peak flow rate q* 0.177

(from fig 5.1)

7. Peak Flow rate, qp(C) = q* A P24 (m

3 / s) 0.061

8. Runoff depth,Q24 = (P24 - Ia)2

mm 211.94

(P24 - Ia) + S

9. Runoff volume, V24 = 1000 x Q24 A (m3) 339

Project: 52 North Road, Clevedon

Page 14: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

Worksheet 1: Runoff Parameters

and Time of Concentration

By B Xiao Date 21/08/2017

Location: catchment D Checked V Crang

Job No 1169

Circle one: Present Developed (Pervious)

1. Runoff Curve Number (CN) and Initial Abstraction (Ia)

Soil name Cover description Curve Area Product

and (cover type, treatment & Number (ha) of CN x

classification hydrologic condition) CN* area

C urban lawn 74 0.10 7

* from Appendix B on TP 108 Totals = 0.10 7

Pervious area 30% of Catchment

CN (weighted) = total product / total area = 74.0

Ia (weighted) = 5 x pervious area / total area = 5.00 mm

2. Time of Concerntration

Channelisation factor ……… C = 0.60 (from Table 4.2)

Catchment length ……… L = 0.12 km (along drainage path)

Catchment slope ……… Sc = 0.007 m/m (by equal area method)

Runoff factor, CN / (200 - CN) = 74.0 / (200-74.0) = 0.59

tc = 0.14 C L0.66

(CN / (200 - CN))-0.55

Sc-0.30

= 0.14 x 0.6 x 0.110.66

x 0.59-0.55

x 0.0270.30

= 0.123 hrs

SCS Lag for HEC-HMS ………. Tp = 2 / 3 tc = 0.08 hrs

Project: 52 North Road, Clevedon

Page 15: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

Worksheet 1: Runoff Parameters

and Time of Concentration

By B Xiao Date 21/08/2017

Location: Catchment D Checked V Crang

Job No 1169

Circle one: Present Developed (impervious)

1. Runoff Curve Number (CN) and Initial Abstraction (Ia)

Soil name Cover description Curve Area Product

and (cover type, treatment & Number (ha) of CN x

classification hydrologic condition) CN* area

Building, Roads etc 98 0.24 24

* from Appendix B Totals = 0.24 24

impervious area 65%

CN (weighted) = total product / total area = 98.0

Ia (weighted) = 5 x pervious area / total area = 0.00 mm

2. Time of Concerntration

Channelisation factor ……… C = 0.60 (from Table 4.2)

Catchment length ……… L = 0.12 km (along drainage path)

Catchment slope ……… Sc = 0.007 m/m (by equal area method)

Runoff factor, CN / (200 - CN) = 98.0 / (200-98.0) = 0.96

tc = 0.14 C L0.66

(CN / (200 - CN))-0.55

Sc-0.30

= 0.14 x 0.6 x 0.110.66

x 0.96-0.55

x 0.027-0.30

= 0.094 hrs

SCS Lag for HEC-HMS ………. Tp = 2 / 3 tc = 0.06 hrs

Project: 52 North Road, Clevedon

Page 16: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

Worksheet 2: Graphical Peak Flow rate

By B Xiao Date 21/08/2017

Location: Catchment D Checked V Crang

Job No 1169

Circle one: Present Developed (Pervious)

1. Data (from Worksheet 1)

Catchment area A = 0.0010 km2

Runoff Curve No CN = 74.0

Initial abstraction Ia = 5.00 mm

Time of concentration tc = 0.123 hrs

2.Calculate Storage, S = (1000 / CN - 10) x 25.4 = 89.2 mm

Storm# #1

3. Average recurrence Interval, ARI (yr) 100 Year

4. 24 hour rainfalll depth, P24 (mm)

185mm

plus 16.8%

climate

change 217

5. Compute C*= P24 - 2Ia 0.54

P24 - 2Ia + 2S

6. Specific peak flow rate q* 0.145

(from fig 5.1)

7. Peak Flow rate, qp(D) = q* A P24 (m

3 / s) 0.031

8. Runoff depth,Q24 = (P24 - Ia)2

mm 149.20

(P24 - Ia) + S

9. Runoff volume, V24 = 1000 x Q24 A (m3) 149

Project: 52 North Road, Clevedon

Page 17: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

Worksheet 2: Graphical Peak Flow rate

By B Xiao Date 21/08/2017

Location: catchment D Checked V Crang

Job No 1169

Circle one: Present Developed (impervious)

1. Data (from Worksheet 1)

Catchment area A = 0.0024 km2

Runoff Curve No CN = 98.0

Initial abstraction Ia = 0.00 mm

Time of concentration tc = 0.094 hrs

2.Calculate Storage, S = (1000 / CN - 10) x 25.4 = 5.18 mm

Storm# #1

3. Average recurrence Interval, ARI (yr) 100 Year

4. 24 hour rainfalll depth, P24 (mm)

185mm

plus 16.8%

climate

change 217

5. Compute C*= P24 - 2Ia 0.95

P24 - 2Ia + 2S

6. Specific peak flow rate q* 0.177

(from fig 5.1)

7. Peak Flow rate, qp(D) = q* A P24 (m

3 / s) 0.092

8. Runoff depth,Q24 = (P24 - Ia)2

mm 211.94

(P24 - Ia) + S

9. Runoff volume, V24 = 1000 x Q24 A (m3) 509

Project: 52 North Road, Clevedon

Page 18: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

Worksheet 1: Runoff Parameters

and Time of Concentration

By B Xiao Date 21/08/2017

Location: catchment E Checked V Crang

Job No 1169

Circle one: Present Developed (Pervious)

1. Runoff Curve Number (CN) and Initial Abstraction (Ia)

Soil name Cover description Curve Area Product

and (cover type, treatment & Number (ha) of CN x

classification hydrologic condition) CN* area

C urban lawn 74 0.12 9

* from Appendix B on TP 108 Totals = 0.12 9

Pervious area 30% of Catchment

CN (weighted) = total product / total area = 74.0

Ia (weighted) = 5 x pervious area / total area = 5.00 mm

2. Time of Concerntration

Channelisation factor ……… C = 0.60 (from Table 4.2)

Catchment length ……… L = 0.10 km (along drainage path)

Catchment slope ……… Sc = 0.007 m/m (by equal area method)

Runoff factor, CN / (200 - CN) = 74.0 / (200-74.0) = 0.59

tc = 0.14 C L0.66

(CN / (200 - CN))-0.55

Sc-0.30

= 0.14 x 0.6 x 0.110.66

x 0.59-0.55

x 0.0270.30

= 0.109 hrs

SCS Lag for HEC-HMS ………. Tp = 2 / 3 tc = 0.07 hrs

Project: 52 North Road, Clevedon

Page 19: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

Worksheet 1: Runoff Parameters

and Time of Concentration

By B Xiao Date 21/08/2017

Location: Catchment E Checked V Crang

Job No 1169

Circle one: Present Developed (impervious)

1. Runoff Curve Number (CN) and Initial Abstraction (Ia)

Soil name Cover description Curve Area Product

and (cover type, treatment & Number (ha) of CN x

classification hydrologic condition) CN* area

Building, Roads etc 98 0.29 28

* from Appendix B Totals = 0.29 28

impervious area 65%

CN (weighted) = total product / total area = 98.0

Ia (weighted) = 5 x pervious area / total area = 0.00 mm

2. Time of Concerntration

Channelisation factor ……… C = 0.60 (from Table 4.2)

Catchment length ……… L = 0.10 km (along drainage path)

Catchment slope ……… Sc = 0.007 m/m (by equal area method)

Runoff factor, CN / (200 - CN) = 98.0 / (200-98.0) = 0.96

tc = 0.14 C L0.66

(CN / (200 - CN))-0.55

Sc-0.30

= 0.14 x 0.6 x 0.110.66

x 0.96-0.55

x 0.027-0.30

= 0.083 hrs

SCS Lag for HEC-HMS ………. Tp = 2 / 3 tc = 0.06 hrs

Project: 52 North Road, Clevedon

Page 20: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

Worksheet 2: Graphical Peak Flow rate

By B Xiao Date 21/08/2017

Location: Catchment E Checked V Crang

Job No 1158

Circle one: Present Developed (Pervious)

1. Data (from Worksheet 1)

Catchment area A = 0.0012 km2

Runoff Curve No CN = 74.0

Initial abstraction Ia = 5.00 mm

Time of concentration tc = 0.123 hrs

2.Calculate Storage, S = (1000 / CN - 10) x 25.4 = 89.2 mm

Storm# #1

3. Average recurrence Interval, ARI (yr) 100 Year

4. 24 hour rainfalll depth, P24 (mm)

185mm

plus 16.8%

climate

change 217

5. Compute C*= P24 - 2Ia 0.54

P24 - 2Ia + 2S

6. Specific peak flow rate q* 0.145

(from fig 5.1)

7. Peak Flow rate, qp(E) = q* A P24 (m

3 / s) 0.038

8. Runoff depth,Q24 = (P24 - Ia)2

mm 149.20

(P24 - Ia) + S

9. Runoff volume, V24 = 1000 x Q24 A (m3) 179

Project: 52 North Road, Clevedon

Page 21: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

Worksheet 2: Graphical Peak Flow rate

By B Xiao Date 21/08/2017

Location: Catchment E Checked V Crang

Job No 1169

Circle one: Present Developed (impervious)

1. Data (from Worksheet 1)

Catchment area A = 0.0029 km2

Runoff Curve No CN = 98.0

Initial abstraction Ia = 0.00 mm

Time of concentration tc = 0.094 hrs

2.Calculate Storage, S = (1000 / CN - 10) x 25.4 = 5.18 mm

Storm# #1

3. Average recurrence Interval, ARI (yr) 100 Year

4. 24 hour rainfalll depth, P24 (mm)

185mm

plus 16.8%

climate

change 217

5. Compute C*= P24 - 2Ia 0.95

P24 - 2Ia + 2S

6. Specific peak flow rate q* 0.177

(from fig 5.1)

7. Peak Flow rate, qp(E) = q* A P24 (m

3 / s) 0.111

8. Runoff depth,Q24 = (P24 - Ia)2

mm 211.94

(P24 - Ia) + S

9. Runoff volume, V24 = 1000 x Q24 A (m3) 615

Project: 52 North Road, Clevedon

Page 22: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

Worksheet 1: Runoff Parameters

and Time of Concentration

By B Xiao Date 21/08/2017

Location: catchment F Checked V Crang

Job No 1169

Circle one: Present Developed (Pervious)

1. Runoff Curve Number (CN) and Initial Abstraction (Ia)

Soil name Cover description Curve Area Product

and (cover type, treatment & Number (ha) of CN x

classification hydrologic condition) CN* area

C urban lawn 74 0.23 17

* from Appendix B on TP 108 Totals = 0.23 17

Pervious area 30% of Catchment

CN (weighted) = total product / total area = 74.0

Ia (weighted) = 5 x pervious area / total area = 5.00 mm

2. Time of Concerntration

Channelisation factor ……… C = 0.60 (from Table 4.2)

Catchment length ……… L = 0.14 km (along drainage path)

Catchment slope ……… Sc = 0.080 m/m (by equal area method)

Runoff factor, CN / (200 - CN) = 74.0 / (200-74.0) = 0.59

tc = 0.14 C L0.66

(CN / (200 - CN))-0.55

Sc-0.30

= 0.14 x 0.6 x 0.110.66

x 0.59-0.55

x 0.0270.30

= 0.066 hrs

SCS Lag for HEC-HMS ………. Tp = 2 / 3 tc = 0.04 hrs

Project: 52 North Road, Clevedon

Page 23: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

Worksheet 1: Runoff Parameters

and Time of Concentration

By B Xiao Date 21/08/2017

Location: Catchment F Checked V Crang

Job No 1158

Circle one: Present Developed (impervious)

1. Runoff Curve Number (CN) and Initial Abstraction (Ia)

Soil name Cover description Curve Area Product

and (cover type, treatment & Number (ha) of CN x

classification hydrologic condition) CN* area

Building, Roads etc 98 0.54 53

* from Appendix B Totals = 0.54 53

impervious area 65%

CN (weighted) = total product / total area = 98.0

Ia (weighted) = 5 x pervious area / total area = 0.00 mm

2. Time of Concerntration

Channelisation factor ……… C = 0.60 (from Table 4.2)

Catchment length ……… L = 0.14 km (along drainage path)

Catchment slope ……… Sc = 0.080 m/m (by equal area method)

Runoff factor, CN / (200 - CN) = 98.0 / (200-98.0) = 0.96

tc = 0.14 C L0.66

(CN / (200 - CN))-0.55

Sc-0.30

= 0.14 x 0.6 x 0.110.66

x 0.96-0.55

x 0.027-0.30

= 0.050 hrs

SCS Lag for HEC-HMS ………. Tp = 2 / 3 tc = 0.03 hrs

Project: 52 North Road, Clevedon

Page 24: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

Worksheet 2: Graphical Peak Flow rate

By B Xiao Date 21/08/2017

Location: Catchment F Checked V Crang

Job No 1158

Circle one: Present Developed (Pervious)

1. Data (from Worksheet 1)

Catchment area A = 0.0023 km2

Runoff Curve No CN = 74.0

Initial abstraction Ia = 5.00 mm

Time of concentration tc = 0.123 hrs

2.Calculate Storage, S = (1000 / CN - 10) x 25.4 = 89.2 mm

Storm# #1

3. Average recurrence Interval, ARI (yr) 100 Year

4. 24 hour rainfalll depth, P24 (mm)

185mm

plus 16.8%

climate

change 217

5. Compute C*= P24 - 2Ia 0.54

P24 - 2Ia + 2S

6. Specific peak flow rate q* 0.145

(from fig 5.1)

7. Peak Flow rate, qp(F) = q* A P24 (m

3 / s) 0.072

8. Runoff depth,Q24 = (P24 - Ia)2

mm 149.20

(P24 - Ia) + S

9. Runoff volume, V24 = 1000 x Q24 A (m3) 343

Project: 52 North Road, Clevedon

Page 25: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

Worksheet 2: Graphical Peak Flow rate

By B Xiao Date 21/08/2017

Location: Catchment F Checked V Crang

Job No 1169

Circle one: Present Developed (impervious)

1. Data (from Worksheet 1)

Catchment area A = 0.0054 km2

Runoff Curve No CN = 98.0

Initial abstraction Ia = 0.00 mm

Time of concentration tc = 0.094 hrs

2.Calculate Storage, S = (1000 / CN - 10) x 25.4 = 5.18 mm

Storm# #1

3. Average recurrence Interval, ARI (yr) 100 Year

4. 24 hour rainfalll depth, P24 (mm)

185mm

plus 16.8%

climate

change 217

5. Compute C*= P24 - 2Ia 0.95

P24 - 2Ia + 2S

6. Specific peak flow rate q* 0.177

(from fig 5.1)

7. Peak Flow rate, qp(F) = q* A P24 (m

3 / s) 0.207

8. Runoff depth,Q24 = (P24 - Ia)2

mm 211.94

(P24 - Ia) + S

9. Runoff volume, V24 = 1000 x Q24 A (m3) 1144

Project: 52 North Road, Clevedon

Page 26: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

Worksheet 1: Runoff Parameters

and Time of Concentration

By B Xiao Date 21/08/2017

Location: catchment G Checked V Crang

Job No 1169

Circle one: Present Developed (Pervious)

1. Runoff Curve Number (CN) and Initial Abstraction (Ia)

Soil name Cover description Curve Area Product

and (cover type, treatment & Number (ha) of CN x

classification hydrologic condition) CN* area

C urban lawn 74 0.13 10

* from Appendix B on TP 108 Totals = 0.13 10

Pervious area 30% of Catchment

CN (weighted) = total product / total area = 74.0

Ia (weighted) = 5 x pervious area / total area = 5.00 mm

2. Time of Concerntration

Channelisation factor ……… C = 0.60 (from Table 4.2)

Catchment length ……… L = 0.14 km (along drainage path)

Catchment slope ……… Sc = 0.080 m/m (by equal area method)

Runoff factor, CN / (200 - CN) = 74.0 / (200-74.0) = 0.59

tc = 0.14 C L0.66

(CN / (200 - CN))-0.55

Sc-0.30

= 0.14 x 0.6 x 0.110.66

x 0.59-0.55

x 0.0270.30

= 0.066 hrs

SCS Lag for HEC-HMS ………. Tp = 2 / 3 tc = 0.04 hrs

Project: 52 North Road, Clevedon

Page 27: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

Worksheet 1: Runoff Parameters

and Time of Concentration

By B Xiao Date 21/08/2017

Location: Catchment G Checked V Crang

Job No 1158

Circle one: Present Developed (impervious)

1. Runoff Curve Number (CN) and Initial Abstraction (Ia)

Soil name Cover description Curve Area Product

and (cover type, treatment & Number (ha) of CN x

classification hydrologic condition) CN* area

Building, Roads etc 98 0.30 29

* from Appendix B Totals = 0.30 29

impervious area 65%

CN (weighted) = total product / total area = 98.0

Ia (weighted) = 5 x pervious area / total area = 0.00 mm

2. Time of Concerntration

Channelisation factor ……… C = 0.60 (from Table 4.2)

Catchment length ……… L = 0.14 km (along drainage path)

Catchment slope ……… Sc = 0.080 m/m (by equal area method)

Runoff factor, CN / (200 - CN) = 98.0 / (200-98.0) = 0.96

tc = 0.14 C L0.66

(CN / (200 - CN))-0.55

Sc-0.30

= 0.14 x 0.6 x 0.110.66

x 0.96-0.55

x 0.027-0.30

= 0.050 hrs

SCS Lag for HEC-HMS ………. Tp = 2 / 3 tc = 0.03 hrs

Project: 52 North Road, Clevedon

Page 28: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

Worksheet 2: Graphical Peak Flow rate

By B Xiao Date 21/08/2017

Location: Catchment G Checked V Crang

Job No 1158

Circle one: Present Developed (Pervious)

1. Data (from Worksheet 1)

Catchment area A = 0.0013 km2

Runoff Curve No CN = 74.0

Initial abstraction Ia = 5.00 mm

Time of concentration tc = 0.123 hrs

2.Calculate Storage, S = (1000 / CN - 10) x 25.4 = 89.2 mm

Storm# #1

3. Average recurrence Interval, ARI (yr) 100 Year

4. 24 hour rainfalll depth, P24 (mm)

185mm plus

16.8% climate

change 217

5. Compute C*= P24 - 2Ia 0.54

P24 - 2Ia + 2S

6. Specific peak flow rate q* 0.145

(from fig 5.1)

7. Peak Flow rate, qp(F) = q* A P24 (m

3 / s) 0.041

8. Runoff depth,Q24 = (P24 - Ia)2

mm 149.20

(P24 - Ia) + S

9. Runoff volume, V24 = 1000 x Q24 A (m3) 194

Project: 52 North Road, Clevedon

Page 29: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

Worksheet 2: Graphical Peak Flow rate

By B Xiao Date 21/08/2017

Location: Catchment G Checked V Crang

Job No 1169

Circle one: Present Developed (impervious)

1. Data (from Worksheet 1)

Catchment area A = 0.0030 km2

Runoff Curve No CN = 98.0

Initial abstraction Ia = 0.00 mm

Time of concentration tc = 0.094 hrs

2.Calculate Storage, S = (1000 / CN - 10) x 25.4 = 5.18 mm

Storm# #1

3. Average recurrence Interval, ARI (yr) 100 Year

4. 24 hour rainfalll depth, P24 (mm)

185mm plus

16.8% climate

change 217

5. Compute C*= P24 - 2Ia 0.95

P24 - 2Ia + 2S

6. Specific peak flow rate q* 0.177

(from fig 5.1)

7. Peak Flow rate, qp(F) = q* A P24 (m

3 / s) 0.115

8. Runoff depth,Q24 = (P24 - Ia)2

mm 211.94

(P24 - Ia) + S

9. Runoff volume, V24 = 1000 x Q24 A (m3) 636

Project: 52 North Road, Clevedon

Page 30: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

OVERLAND FLOWPATH CALCULATION

SECTION A-A

PROJECT : 52 North Road, Clevedon

Job No. : 1169 Calculation by : B Xiao

Date : August 2017 Checked by: V Crang

Qd (100) 1 in 100 year storm, use TP108

Qd(100) = Qd(100)pervious+Qd(100)impervious

Qd (100)pervious = 0.103 m³/s

Qd (100)impervious = 0.319 m³/s

Qd (100) = 0.422 m³/s

Qc = A*R^(2/3)*S^(1/2)/n

n = 0.013 concrete

S = 1.90% longitudinal grade

H= 0.11 m

W = 6.0 m

P = 6.27

R = A/P

A = 0.31 m2

R = 0.049 m

Qc (capacity)= 0.444 m3/s > Qd (net) = 0.422 m³/s OK

Page 31: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

OVERLAND FLOWPATH CALCULATION

SECTION B-B

PROJECT : 52 North Road, Clevedon

Job No. : 1169 Calculation by : B Xiao

Date : August 2017 Checked by: V Crang

Qd (100) 1 in 100 year storm, use TP108

Qd(100) = Qd(100)pervious+Qd(100)impervious

Qd (100)pervious = 0.147 m³/s from TP108 calcls(CATCHMENT A+B)

Qd (100)impervious = 0.442 m³/s from TP108 calcls(CATCHMENT A+B)

Qd (100) = 0.589 m³/s

Qc = A*R^(2/3)*S^(1/2)/n

n = 0.020 concrete+berm grass

S = 0.60% longitudinal grade

H= 0.19 m

W = 10.14 m

P = 10.41

R = A/P

A = 0.84 m2

R = 0.081 m

Qc (capacity)= 0.609 m3/s > Qd (net) = 0.59 m³/s OK

Page 32: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

OVERLAND FLOWPATH CALCULATION

SECTION C-C

PROJECT : 52 North Road, Clevedon

Job No. : 1169 Calculation by : B Xiao

Date : August 2017 Checked by: V Crang

Qd (100) 1 in 100 year storm, use TP108

Qd(100) = Qd(100)pervious+Qd(100)impervious

Qd (100)pervious = 0.169 m³/s from TP108 calcls(CATCHMENT A+B+C)

Qd (100)impervious = 0.503 m³/s from TP108 calcls(CATCHMENT A+B+C)

Qd (100) = 0.672 m³/s

Qc = A*R^(2/3)*S^(1/2)/n

n = 0.020 concrete+grass

S = 5.10% longitudinal grade

H= 0.17 m

W = 6.3 m

P = 6.43

R = A/P

A = 0.39 m2

R = 0.060 m

Qc (capacity)= 0.672 m3/s > Qd (net) = 0.67 m³/s OK

Page 33: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

OVERLAND FLOWPATH CALCULATION

SECTION D-D

PROJECT : 52 North Road, Clevedon

Job No. : 1169 Calculation by : B Xiao

Date : August 2017 Checked by: V Crang

Qd (100) 1 in 100 year storm, use TP108

Qd(100) = Qd(100)pervious+Qd(100)impervious

Qd (100)pervious = 0.116 m³/s from TP108 calcls CATCHMENT D+1/2 (A+B+C)

Qd (100)impervious = 0.344 m³/s from TP108 calcls CATCHMENT D+1/2 (A+B+C)

Qd (100) = 0.460 m³/s

Qc = A*R^(2/3)*S^(1/2)/n

n = 0.020 concrete+grass

S = 0.70% longitudinal grade

H= 0.21 m

W = 8.53 m

P = 8.66

R = A/P

A = 0.63 m2

R = 0.073 m

Qc (capacity)= 0.464 m3/s > Qd (net) = 0.46 m³/s OK

Page 34: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

OVERLAND FLOWPATH CALCULATION

SECTION E-E

PROJECT : 52 North Road, Clevedon

Job No. : 1169 Calculation by : B Xiao

Date : August 2017 Checked by: V Crang

Qd (100) 1 in 100 year storm, use TP108

Qd(100) = Qd(100)pervious+Qd(100)impervious

Qd (100)pervious = 0.154 m³/s from TP108 calcls CATCHMENT D+E+1/2 (A+B+C)

Qd (100)impervious = 0.455 m³/s from TP108 calcls CATCHMENT D+E+1/2 (A+B+C)

Qd (100) = 0.609 m³/s

Qc = A*R^(2/3)*S^(1/2)/n

n = 0.020 concrete+grass

S = 0.70% longitudinal grade

H= 0.15 m

W = 15.00 m

P = 15.10

R = A/P

A = 0.94 m2

R = 0.062 m

Qc (capacity)= 0.619 m3/s > Qd (net) = 0.61 m³/s OK

Page 35: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

OVERLAND FLOWPATH CALCULATION

SECTION F-F

PROJECT : 52 North Road, Clevedon

Job No. : 1169 Calculation by : B Xiao

Date : August 2017 Checked by: V Crang

Qd (100) 1 in 100 year storm, use TP108

Qd(100) = Qd(100)pervious+Qd(100)impervious

Qd (100)pervious = 0.072 m³/s from TP108 calcls

Qd (100)impervious = 0.207 m³/s from TP108 calcls

Qd (100) = 0.279 m³/s

Qc = A*R^(2/3)*S^(1/2)/n

n = 0.020 concrete+ grass

S = 5.80% longitudinal grade

H= 0.09 m

W = 3.86 m

P = 3.86

R = A/P

A = 0.18 m2

R = 0.047 m

Qc (capacity)= 0.284 m3/s > Qd (net) = 0.28 m³/s OK

Page 36: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

OVERLAND FLOWPATH CALCULATION

SECTION G-G

PROJECT : 52 North Road, Clevedon

Job No. : 1169 Calculation by : B Xiao

Date : August 2017 Checked by: V Crang

Qd (100) 1 in 100 year storm, use TP108

Qd(100) = Qd(100)pervious+Qd(100)impervious

Qd (100)pervious = 0.126 m³/s from TP108 calcls CATCHMENT G+1/2 (A+B+C)

Qd (100)impervious = 0.368 m³/s from TP108 calcls CATCHMENT G+1/2 (A+B+C)

Qd (100) = 0.494 m³/s

Qc = A*R^(2/3)*S^(1/2)/n

n = 0.020 concrete+grass

S = 2.80% longitudinal grade

H= 0.18 m

W = 5.08 m

P = 6.56

R = A/P

A = 0.39 m2

R = 0.059 m

Qc (capacity)= 0.498 m3/s > Qd (net) = 0.49 m³/s OK

Page 37: Stormwater Overland Flow TP108 CALCULATIONS · Worksheet 2: Graphical Peak Flow rate By B Xiao Date 21/08/2017 Location: Catchment A Checked V Crang Job No 1169 Circle one: Present

OVERLAND FLOWPATH CALCULATION

SECTION H-H

PROJECT : 52 North Road, Clevedon

Job No. : 1169 Calculation by : B Xiao

Date : August 2017 Checked by: V Crang

Qd (100) 1 in 100 year storm, use TP108

Qd(100) = Qd(100)pervious+Qd(100)impervious

Qd (100)pervious = 0.241 m³/s from TP108 calcls CATCHMENT A+B+C+D+E

Qd (100)impervious = 0.710 m³/s from TP108 calcls CATCHMENT A+B+C+D+E

Qd (100) = 0.951 m³/s

Qc = A*R^(2/3)*S^(1/2)/n

n = 0.032 grass

S = 4.30% longitudinal grade

H= 0.18 m

W = 3.87 m

P = 3.91

R = A/P

A = 0.55 m2

R = 0.140 m

Qc (capacity)= 0.956 m3/s > Qd (net) = 0.95 m³/s OK