Upload
farhadmrt6923
View
223
Download
0
Embed Size (px)
Citation preview
7/23/2019 STI Section8
1/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
SECTION 8
STABILITY / STRESS ANALYSIS
OF PROJECT STRUCTURES
8.1 GENERAL
8.1.1 Load Cases Analyzed
The load cases analyzed for the various structures over time in variousreports have been grouped by structure, then by report. Tables andfigures have been created to summarize all the data in the followingsections.
8.1.2 Stability Analyses Methodologies
a. Forrest & Cotton (1962). Serving as SRAs Engineer, Forrest &Cotton used the following methods for analyzing the stability of thestructures:
1) Main Embankment and Dikes (as reported in DesignMemorandum No 3). The main embankment and dikes wereanalyzed using the circular arc method.
2) Spillway (as reported in Design Memorandum No. 2). Handcalculations for sliding and overturning on three sections: theoverflow section, the low-flow section, and the non-overflowsection. Circular arc analysis was also performed on theoverflow section.
3) Powerhouse. To date, no information has been uncoveredthat describes the original powerhouse stability designmethodology.
b. Rone Engineers (1983). Serving as a geotechnical consultant,
Rone performed a liquefaction and stability analysis using thefollowing methods:
1) Main Embankment. The general subsurface of the mainembankment was tested by performing 16 standardpenetration sample borings. The stability analysis followedguidelines recognized by FERC. Using conservativeparameters, a maximum design earthquake acceleration of
Rev. 0 Page 8-112/31/2004
7/23/2019 STI Section8
2/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
0.04 g resulted in a factor of safety greater than 1.15. Theliquefaction potential was also analyzed indicating that thereis no possibility for liquefaction.
2) A stability analysis was performed on Dike No. 2, whichindicated that the embankment was adequately stable.Recommendations were made for adding a small berm withan internal drainage system to control seepage areas.
c. Brown & Roots Toledo Bend Dam Stability Analysis (1988)
1) Main Embankment. The main embankment was analyzedon three separate cross sections using PCSTABL4 softwarewhich calculates the factor of safety against slope failureusing two-dimensional limit equilibrium methods. The factor
of safety was calculated using the Simplified Bishop methodof slices.
PCSTABL4 as used by Brown & Root for the 1988 analyses,was verified for a typical embankment section usingMCAUTO SLOPE ( McDonnell Douglas AutomationCompany product), which is a computer subsystem ofIntegrated Civil Engineering System (ICES). The run wasperformed for the embankment section at Station 116+30.
As reported in Toledo Bend Stability Analysis Verification ofPCSTABL4 Computer Program, dated November 1988 by
Brown & Root USA, Inc., the factor of safety calculated bythe PCSTABL4 program using the Simplified Bishop methodof slices correlated very well with that calculated usingMCAUTO SLOPE.
2) Spillway. Hand calculations were used in 1988 to calculatesliding stability for the spillway. The method of analysis wasa two-dimensional limit equilibrium approach, in accordancewith ETL-1110-2-256. Force equilibrium is satisfied in theapproach. Moment equilibrium was not analyzed. Theanalysis was performed on three different sections of the
spillway: the overflow section, the low-flow section, and thenon-overflow section.
3) Powerhouse. Slipcircle analysis was determined to be morecritical for the powerhouse, and therefore PCSTABL4 wasused to examine the stability of the powerhouse for slidingblock failure, using the simplified Janbu method of slices.The excavated intake channel slope was analyzed for
Rev. 0 Page 8-212/31/2004
7/23/2019 STI Section8
3/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
sudden drawdown and earthquake conditions, also using thePCSTABL4 program.
c. Brown & Roots FERC Inspection Report (1998)
1) Spillway. Further analyses of the spillway only (overflow andlow-flow sections) were undertaken for this report to examinethe effect of the approach slab and drainage system on thestability of the structure against sliding and overturning. Themethod used was hand calculations using the two-dimensional limit equilibrium approach, similar to that used inthe 1988 Stability Analysis.
Note. There is no reference in the above to any analyses ontraining/retaining walls. These are less crit ical in the context
of publ ic safety and are therefore not inc luded in thisAppendix.
8.1.3 Properties of Materials
Material testing reports from the original construction have not beenlocated. Design properties and assumptions made for the variouscalculations have been collected. Concrete compressive and tensilestrength properties for the spillway are summarized in Section 8.2.1,paragraph h. Soil properties for the powerhouse are summarized in Table8.2.10. Soil properties for the main embankment are summarized in
Tables 8.3.3, 8.3.5, and 8.3.7 from the various reports. Soil properties forthe minor dikes are summarized in Tables 8.3.8, 8.3.10, and 8.3.12.
Rev. 0 Page 8-312/31/2004
7/23/2019 STI Section8
4/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
8.2 GRAVITY STRUCTURES
8.2.1 Spillway
a. Sections, Loading Cases and Assumptions. Spillway sections areshown in Figures 8.2-01, 8.2-02, and 8.2-03. Loading conditionsand assumptions are shown in subsequent paragraphs of thereport.
1) Forrest & Cotton (1962). Stability analyses for the spillwayas given in the Forrest & Cotton Design Memorandum No. 2,dated August 1962 are summarized in Table 8.2.1. Thestability analysis calculations for the Intermediate PierMonolith (Figures 8.2-04 and 8.2-05), Low Flow ReleasePier Monolith (Figure 8.2-06), and the Non-Overflow Section
(Figure 8.2-07), are given in the respective figures. Thespillway chute stability analysis calculations are given inFigure 8.2-08.
2) Rone (1983). Stability analyses for the spillway as given inthe Rone Engineers report, Instrumentation and HydrostaticPressure Relief Systems, are summarized in Table 8.2.2 andshown in Figure 8.2-09.
3) KBR (1988). Stability analyses for the spillway as given inthe Brown & Root report, Toledo Bend Stability Analysis,
dated November 1988, are summarized in Table 8.2.3. Thestability analysis calculations are given in the followingfigures: Case A Overflow Section (Figure 8.2-10) Case B1 Overflow Section (Figure 8.2-11) Case B2 Overflow Section (Figure 8.2-12) Case C Overflow Section (Figure 8.2-13) Case B1 Low Flow Section (Figure 8.2-14) Case D Low Flow Section (Figure 8.2-15) Case A Non-Overflow Section Hydrostatic Loads
(Figure 8.2-16)
Case A Non-Overflow Section Soil Loads(Figure 8.2-17)
Case C Non-Overflow Section Hydrostatic Loads(Figure 8.2-18)
Case C Non-Overflow Section Soil Loads(Figure 8.2-19)
Main Embankment Showing Stability Sections(Figure8.2-20)
Rev. 0 Page 8-412/31/2004
7/23/2019 STI Section8
5/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
Rev. 0 Page 8-512/31/2004
7/23/2019 STI Section8
6/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
Rev. 0 Page 8-612/31/2004
7/23/2019 STI Section8
7/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
Rev. 0 Page 8-712/31/2004
7/23/2019 STI Section8
8/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
4) KBR (1998). Stability analyses for the spillway as given inthe Brown & Root report, Toledo Bend FERC Stability
Analysis, dated October 1998, are summarized in
Table 8.2.4. Main Embankment Stability Section Locationsare shown in Figure 8.2-20. The stability analysiscalculations are given in the following figures:
Case 1 Overflow Section Sliding Analysis(Figure 8.2-21)
Case 1 Overflow Section Overturning Analysis(Figure 8.2-22X)
Case 2 Overflow Section Sliding analysis(Figure 8.2-23)
Case 2 Overflow Section Overturning Analysis(Figure 8.2-24)
Case 3 Overflow Section Sliding Analysis(Figure 8.2-25)
Case 3 Overflow Section Overturning Analysis(Figure 8.2-26X)
Case 4 Overflow Section Sliding Analysis(Figure 8.2-27)
Case 4 Overflow Section Overturning Analysis(Figure 8.2-28)
Case 1 Low Flow Section Sliding Analysis(Figure 8.2-29)
Case 1 Low Flow Section Overturning Analysis
(Figure 8.2-30) Case 2 Low Flow Section Sliding Analysis
(Figure 8.2-31) Case 2 Low Flow Section Overturning Analysis
(Figure 8.2-32)
b. Key Elevations. Table 8.2.5 gives the key elevations of thespillway.
c. Key Lateral Dimensions. Table 8.2.6 gives the key lateraldimensions of the spillway.
d. Piezometer and Drain Locations. Figure 8.2-33 shows the spillwaypiezometer and relief well locations for the spillway.
e. Foundation Shear Strength Parameters. Table 8.2.7 shows theshear strength parameters used in the different analyses conductedto spillway stability.
Rev. 0 Page 8-812/31/2004
7/23/2019 STI Section8
9/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
f. Minimum Cohesion to Meet Stability Criteria. The minimumcohesion intercept providing acceptable factors of safety has notbeen determined, as such. However, due to concerns over thelong term strength parameters of the overconsolidated clays, a 50
percent reduction in cohesion was used in the 1988 analysis asindicated in Table 8.2.7.
g. Negative Crest Pressures on Spillway. Negative crest pressureshave not been addressed in any of the spillway stability analysesundertaken to date.
Rev. 0 Page 8-912/31/2004
7/23/2019 STI Section8
10/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
Rev. 0 Page 8-1012/31/2004
7/23/2019 STI Section8
11/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
Rev. 0 Page 8-1112/31/2004
7/23/2019 STI Section8
12/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
h. Concrete Compressive and Tensile Strength: The following pagestaken from Forrest & Cotton Design Memorandum No. 2, dated
August 1962, provide the concrete design parameters for thespillway. Actual test results from samples taken during constructionare not available.
Rev. 0 Page 8-1212/31/2004
7/23/2019 STI Section8
13/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
5-05. Concrete, general. The symbols, nomenclature, and abbreviations used
herein with respect to plain, reinforced, and prestressed concrete are those used by the
American Concrete Institute. For purposes of referencing working stresses as pertainingto the various concrete components of the spillway, the stresses have been separated
into three groups, as follows:
GROUP I stresses: Applies to miscellaneous concrete not included
under Group II and III stresses.
GROUP II stresses: Applies to concrete in structures that will besubjected to submergence, wave action, and spray.
Included will be most of the mass concrete in the
weirs, piers, non-overflow sections and theretaining walls. Exceptions will be the approach
apron and all prestressed concrete.GROUP III stresses: Applies to prestressed concrete as proposed for the
bridge girders and the trunnion anchorage.
5-06. Strength of concrete. For design purposes, it was assumed that theultimate compressive strength of the concrete in the different components of the
spillway would be as follows:
Spillway component
Ultimate compressive
strength at 28 days in psi
1. General structural concrete 3,000
2. Prestressed trunnion anchorage and bridge girders 5,000
3. Bridge deck 4,000
4. Fill concrete and for other purposes where strength is
not a required property of the material
2,000
Rev. 0 Page 8-1312/31/2004
7/23/2019 STI Section8
14/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
5-07. Allowable unit stresses, plain concrete. The allowable flexure (fc) stress for plainconcrete with assumed Group A loading will be as follows:
Design Strength of Concrete
Nature of Stress
f 'c
proportion
Unit stress for
3000 lb. concrete in psi,
n = 10
Extreme fiber stress in tension:
GROUP I 0.03 f 'c 90
GROUP II 0.02 f 'c 60
5-08. Allowable unit stresses, reinforced concrete. The allowable unit stressesfor reinforced concrete with Group A loading will be as is given in the following
paragraphs:5-08a. Flexure, fc. The allowable flexure stress, fc, for reinforced concrete for
assumed Group A loading will be as follows:
Design Strength of Concrete
Nature of Stress
f 'c
proportion
Unit stress for
3000 lb. concrete in psi,n = 10
Extreme fiber stress in compression:
GROUP I 0.45 f 'c 1,350
GROUP II 0.35 f 'c 1,050
5-08b. Shear, Vc. Allowable shear stresses, Vc, as a measure of diagonal tension,
for assumed Group A loading will be as follows. These stresses are within the GROUP I
stress classification and are all in accordance with the American Concrete Institute
specifications.
Rev. 0 Page 8-1412/31/2004
7/23/2019 STI Section8
15/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
Design Strength of Concrete
Nature of Stress
f 'cproportion
Unit stress for3000 lb. concrete in psi,
n = 10
a. Beams with no web reinf. (1) 0.03 f 'c 90
b. Beams with longitudinal bars
and stirrups or bent bars
0.08 f 'c 240
c. Beams with longitudinal bars
and stirrups plus bent bars (2)
0.12 f 'c 360
d. Punching shear 0.075 f 'c 225
e. Footings 0.025 f 'c 75
(1) Where calculations indicate Vc is not exceeded, nominal vertical stirrups will
be provided throughout the full span of the beam. The minimum stirrup will be #3 barsand the maximum spacing will be one half the beam depth.
(2) The bent bars are to be bent up and suitable to carry at least 0.04fc.
5-08c. Bond, u. The allowable bond, u, for assumed Group A loading will be asfollows. These stresses are all within the GROUP I stress classification.
Design Strength of Concrete
Nature of Stress
f 'c
proportion
Unit stress for
3000 lb. concrete in psi,
n = 10
Deformed ASTM A-305 bars (3):
Top bars 0.07 f 'c 210
In two-way footing except top
bars
0.08 f 'c 240
All others 0.10 f 'c 300
Plain bars hook required (4)
Top bars 0.03 f 'c 90In two-way footing except top
bars
0.036 f 'c 108
All others 0.045 f 'c 135
Rev. 0 Page 8-1512/31/2004
7/23/2019 STI Section8
16/108
7/23/2019 STI Section8
17/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
5-08f. Combined bending and direct stresses. The allowable combined axial and
bending stresses for reinforced concrete columns and walls will be determined inaccordance with the American Concrete Institute Code (ACI-3l8-56).
5-08g. Moduli and coefficients. The modulus of elasticity, Ec, and the coefficient
of expansion of 3,000 pound concrete will be as follows:
Modulus of elasticity, Ec. - 3,000,000 psi
Coef. of expansion - 0.000006 per F.
5-09. Allowable unit stresses, prestressed concrete. Working stresses forprestressed concrete used in trunnion anchorage and. bridge girders will be in accordance
with applicable specifications listed. in paragraph 5-01. The allowable unit stresses for
assumed Group A loading will be as follows. These stresses are all within the GROUP IIIstress classification.
Design Strength of Concrete
Nature of Stress
f 'c i
proportion
Unit stress for
5000 lb. concrete in psi,
n = 6
TEMPORARY STRESSES:
Compression in extreme fiber 0.60 f 'c i 2,400
Tension 0.05 f 'c i 200
STRESSES: UNDER DEAD, LIVE AND IMPACT LOADSCompression in extremefiber 0.40 f 'c i 2,000
Tension in extreme fiber 0 0
ANCHORAGE BEARING STRESSES:
Trunnion anchorage fcp = (0.6 f 'c i) times the cube root of Ac/Ab
The strength of concrete at the time of prestress of trunnion anchorage will be 4,000 psi.
The strength of concrete at the time of cable release will be 4,000 psi.
Rev. 0 Page 8-1712/31/2004
7/23/2019 STI Section8
18/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
i. Alkali Aggregate Reactivity (AAR) Potential. AAR has not beenaddressed in any of the previous reports.
1) Cement with high alkaline content can react with theaggregate in a wet environment. Reactive aggregates aregarnet or silica. The aggregate decomposes into a greatervolume that the original causing the concrete to craze, crackand spall.
2) There is no known preventive or remedy when thesecharacteristics are present.
8.2.2 Powerhouse
a. Sections, Loading Cases and Assumptions: Powerhouse sectionsare shown in Figure 8.2-34. Loading conditions and assumptionsare provided in subsequent paragraphs of the report.
1) Forrest & Cotton (1962). No data is available for Forrest &Cottons analyses of the powerhouse. However, a note onthe Power Plant Stability Analysis from the Rone (1983)report states that data on this plate from the power plantstability analyses performed by Forrest & Cotton, Inc.,Consulting Engineers, in 1963.
2) Rone (1983). Stability analyses for the powerhouse asgiven in the Rone Engineers report, Instrumentation andHydrostatic Pressure Relief Systems, are summarized inTable 8.2.8. The stability analysis calculations are given inFigure 8.2-35.
3) KBR (1988). Stability analyses for the powerhouse as givenin the Brown & Root report, Toledo Bend Stability Analysis,dated November 1988 are summarized in Table 8.2.9. Soilproperties used in the stability analysis are given in Table8.2.10. The powerhouse plan view showing the location of
the stability sections used for calculations is given in Figure8.2-36. The stability analysis calculations are given in thefollowing figures:
Powerhouse Sliding Stability Normal Pool(Figure 8.2-37)
Powerhouse Stability Normal Pool (Figure 8.2-38) Powerhouse Seismic (Figure 8.2.39)
Rev. 0 Page 8-1812/31/2004
7/23/2019 STI Section8
19/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
Powerhouse Surcharge Pool (Figure 8.2-40)
b. Key Elevations. (Not available)
c. Key Lateral Dimensions. (Not available)
d. Piezometer and Drain Locations. Figure 8.2-41 shows thepowerhouse piezometer and relief well locations for the spillway.
e. Foundation Shear Strength Parameters. Refer to Table 8.2.10.
f. Minimum Cohesion to Meet Stability Criteria. Refer to paragraph8.2.1f.
g. Negative Crest Pressures on Spillway. (Not applicable)
h. Concrete Compressive and Tensile Strength. (Not available)
i. Alkali Aggregate Reactivity (AAR) Potential. Refer to paragraph
8.2.1i.
8.2.3 Intake and Outlet Works
There are no intake or outlet works associated with this project. Alldischarges from the reservoir are made through the spillway or the
powerhouse.
Rev. 0 Page 8-1912/31/2004
7/23/2019 STI Section8
20/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
Rev. 0 Page 8-2012/31/2004
7/23/2019 STI Section8
21/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
Rev. 0 Page 8-2112/31/2004
7/23/2019 STI Section8
22/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
Rev. 0 Page 8-2212/31/2004
7/23/2019 STI Section8
23/108
Figure 8.2-01
SPILLWAY SLIDDIN STABILITY
TYPICAL PIER SECTIONS
7/23/2019 STI Section8
24/108
Figure 8.2-02
UPSTREAM ELEVATION
OVERFLOW SECTION
7/23/2019 STI Section8
25/108
Figure 8.2-03
UPSTREAM ELEVATION
LOW FLOW SECTION
7/23/2019 STI Section8
26/108
Figure 8.2-04
INTERMEDIATE PIER MONO
STABILITY ANALYSES
Sheet 1 of 2
7/23/2019 STI Section8
27/108
Figure 8.2-05
INTERMEDIATE PIER MONO
STABILITY ANALYSES
Sheet 2 of 2
7/23/2019 STI Section8
28/108
Figure 8.2-06
LOW FLOW RELEASE PIER MO
STABILITY ANALYSES
7/23/2019 STI Section8
29/108
Figure 8.2-07
NON-OVERFLOW SECTION
STABILITY ANALYSES
7/23/2019 STI Section8
30/108
Figure 8.2-08
SPILLWAY CHUTE
STABILITY ANALYSES
7/23/2019 STI Section8
31/108
NOTE:
THE BASE DRAWING INFORMATION ON THIS SHEET WAS TAKEN FROM:
FERC COMMISSION ON INSPECTION OF PROJECT WORKS THAT MI GHT ENDANGER PUBLIC SAFETY
B&R - 1998, APPENDIX D-65
Figure 8.2-09
SPILLWAY STABILITY ANALYSES
OPERATIONAL PROCEDUURES
7/23/2019 STI Section8
32/108
TOLEDO BEND DAM STABILITY
ANALYSIS, B&R - 1988
Figure 8.2-10
CASE A - OVERFLO
SECTION
7/23/2019 STI Section8
33/108
TOLEDO BEND DAM STABILITY
ANALYSIS, B&R - 1988
Figure 8.2-11
CASE B1 - OVERF
SECTION
7/23/2019 STI Section8
34/108
TOLEDO BEND DAM STABILITY
ANALYSIS, B&R - 1988
Figure 8.2-12CASE B2 - OVERFL
SECTION
7/23/2019 STI Section8
35/108
TOLEDO BEND DAM STABILITY
ANALYSIS, B&R - 1988
Figure 8.2-13
CASE C - OVERFLOW
SECTION
7/23/2019 STI Section8
36/108
TOLEDO BEND DAM STABILITY
ANALYSIS, B&R - 1988
Fig 8.2-14
CASE B1 - LOW FLOW
SECTION
7/23/2019 STI Section8
37/108
7/23/2019 STI Section8
38/108
TOLEDO BEND DAM STABILITY
ANALYSIS, B&R - 1988
Figure 8.2-16
CASE A - NON -
OVERFLOW SECTION
HYDROSTATIC LOAD
7/23/2019 STI Section8
39/108
TOLEDO BEND DAM STABILITY
ANALYSIS, B&R - 1988
figure 8.2-17
CASE A - NON-OVERFLO
SECTION SOIL LOADS
7/23/2019 STI Section8
40/108
Figure 8.2-18
CASE C - NON-OVERFL
SECTION HYDROSTA
LOADS
TOLEDO BEND DAM STABILITY
ANALYSIS, B&R - 1988
7/23/2019 STI Section8
41/108
7/23/2019 STI Section8
42/108
Figure 8.2-20
MAIN EMBANKMENT STABILITY
SECTION LOCATIONS
7/23/2019 STI Section8
43/108
CASE1
OV
ERFLOWS
ECTION-SLIDINGANALYSIS
NOTE:
THE BASE DRAWING
INFORMATION ON THIS
SHEET WAS TAKEN FROM:
FERC COMMISSION ONINSPECTION OF PROJECT
WORKS THAT MIGHT
ENDANGER PUBLIC SAFETY
B&R - 1998
APPENDIX D-54
Figure 8.2-2
CASE1
OVERFLOW SEC
SLIDING ANALY
7/23/2019 STI Section8
44/108
CASE1
OV
ERFLOW
SECTION-OVERTURN
ING
ANALYSIS
A p p r o a c h S l a b N o t E f f e c t i v e
NOTE:
THE BASE DRAWING INFORMATION ON
THIS SHEET WAS TAKEN FROM:
FERC COMMISSION ON INSPECTION
OF PROJECT WORKS THAT MIGHT
ENDANGER PUBLIC SAFETY
B&R - 1998, APPENDIX D-58
Figure 8.2-22
CASE1
OVERFLOW SECTION -
OVERTURNING ANALYSIS
7/23/2019 STI Section8
45/108
CASE2
OVER
FLOW
SECTION-SLIDINGANA
LYSIS
ApproachSlabEffective
Figure 8.2-23
CASE 2
OVERFLOW SECTI
SLIDING ANALYSNOTE:
THE BASE DRAWING INFORMATION
ON THIS SHEET WAS TAKEN FROM:
FERC COMMISSION ON INSPECTION
OF PROJECT WORKS THAT MIGHT
ENDANGER PUBLIC SAFETY
B&R - 1998, APPENDIX D-55
7/23/2019 STI Section8
46/108
CASE2
OVERFLOW
SECTION-OVERTURNINGA
NALYSIS
ApproachSlabEffective
NOTE:
THE BASE DRAWING INFORMATION ON
THIS SHEET WAS TAKEN FROM:
FERC COMMISSION ON INSPECTION OF
PROJECT WORKS THAT MIGHT
ENDANGER PUBLIC SAFETY
B&R - 1998, APPENDIX D-59
Figure 8.2-24
CASE 2
OVERFLOW SECTION
OVERTURNING ANALYSIS
7/23/2019 STI Section8
47/108
CASE3
OVE
RFLOW
SECTION-SLIDINGAN
ALYSIS
ApproachSlabNotEffective
Figure 8.2-25
CASE 3
OVERFLOW SECTI)
SLIDING ANALYSNOTE:
THE BASE DRAWING INFORMATION ON
THIS SHEET WAS TAKEN FROM:
FERC COMMISSION ON INSPECTION OF
PROJECT WORKS THAT MIGHT
ENDANGER PUBLIC SAFETY
B&R - 1998, APPENDIX D-59
7/23/2019 STI Section8
48/108
CASE3
OVERFLOW
SECTION-OVERTURNINGANALYSIS
ApproachSlabNotEffective
NOTE:
THE BASE DRAWING INFORMATION ON
THIS SHEET WAS TAKEN FROM:
FERC COMMISSION ON INSPECTION OF
PROJECT WORKS THAT MIGHT
ENDANGER PUBLIC SAFETY
B&R - 1998, APPENDIX D-60
Figure 8.2-26
CASE 3
OVERFLOW SECTION
OVERTURNING ANALYS
7/23/2019 STI Section8
49/108
CASE4
OOVERFLOW
SECTION-SLIDINGANA
LYSIS
ApproachSlabEffective
NOTE:
THE BASE DRAWING INFORMATION ON
THIS SHEET WAS TAKEN FROM:
FERC COMMISSION ON INSPECTION OF
PROJECT WORKS THAT MIGHT
ENDANGER PUBLIC SAFETY
B&R - 1998, APPENDIX D-57
Figure 8.2-27
CASE 4
OVERFLOW SECTI
SLIDING ANALYS
7/23/2019 STI Section8
50/108
7/23/2019 STI Section8
51/108
CASE1
LOW
FLOW
SECTION-SLIDINGANALYSIS
ApproachSlabNotEffective
S
i l W t
1 2 0
f
NOTE:
THE BASE DRAWING INFORMATION ON THIS SHEET
WAS TAKEN FROM:
FERC COMMISSION ON INSPECTION OF PROJECT
WORKS THAT MIGHT ENDANGER PUBLIC SAFETY
B&R - 1998, APPENDIX D-63
Figure 8.2-29
CASE 1
LOW FLOW SECTION
SLIDING ANALYSIS
7/23/2019 STI Section8
52/108
NOTE:
THE BASE DRAWING INFORMATION
ON THIS SHEET WAS TAKEN FROM:
FERC COMMISSION ON INSPECTION
OF PROJECT WORKS THAT MIGHT
ENDANGER PUBLIC SAFETY
B&R - 1998, APPENDIX D-65
Figure 8.3-30
CASE 1 - LOW FLOW SECTION
OVERTURNING ANALYSIS
CASE1
LOW
FLO
WS
ECTION-OVERTURNINGA
NALYSIS
ApproachSlabNotEffective
S
i l W t
1 2 0
f
7/23/2019 STI Section8
53/108
NOTE:
THE BASE DRAWING INFORMATION ON THIS SHEET WAS
TAKEN FROM:
FERC COMMISSION ON INSPECTION OF PROJECT WORKS
THAT MIGHT ENDANGER PUBLIC SAFETY
B&R - 1998, APPENDIX D-64
CASE2
LOW
FLOW
SECTION-SLIDINGANALYSIS
ApproachSlabEffective
S
i l W t
1 2 0
f
Figure 8.2-31
CASE 2
LOW FLOW SECTION
SLIDING ANALYSIS
7/23/2019 STI Section8
54/108
NOTE:
THE BASE DRAWING INFORMATION ON THIS SHEET WAS
TAKEN FROM FERC COMMISSION ON INSPECTION OF
PROJECT WORKS THAT MIGHT ENDANGER PUBLIC
SAFETY, B&R - 1998, APPENDIX D-66
CASE2
LOW
FL
OW
SECTION-OVERTURNINGANALYSIS
ApproachSlabEffective
Figure 8.2-32
CASE 2
LOW FLOW SECTION
OVERTURNING ANALYSIS
7/23/2019 STI Section8
55/108
Figure 8.2-33
PLAN OF
SPILLWAY PIEZOMETER
7/23/2019 STI Section8
56/108
Figure 8.2-34
POWRHOUSE PLAN
& SECTIONS
7/23/2019 STI Section8
57/108
Source: INSTRUMENTATION AND
HYDROSTATIC PRESSURE RELIEF
SYSTEMS, RONE ENGINEERS, INC., 1983
Figure 8.2-35
POWER PLANT STABILITY ANAL
OPERATIONAL PROCEDURE
7/23/2019 STI Section8
58/108
Figure 8.2-36
POWER HOUSE STABILI
SECTION LOCATIONS
7/23/2019 STI Section8
59/108
Figure 8.2-37
POWER HOUSE
SLIDING STABILITY
7/23/2019 STI Section8
60/108
Figure 8.2-38
POWER HOUSE NORMAL PO
7/23/2019 STI Section8
61/108
Figure 8.2-39
POWER HOUSE
SEISMIC
7/23/2019 STI Section8
62/108
Figure 8.2-40
POWR HOUSE
SURCHARGE POOL
7/23/2019 STI Section8
63/108
Figure 8.2-41
PLAN OF POWRE HOUSE
PIEZOMETERS
7/23/2019 STI Section8
64/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
8.3 EMBANKMENT STRUCTURES
The Toledo Bend Dam embankment structures are identified inTable 8.3.1 with their corresponding key dimensions, elevations, andslopes.
8.3.1 Main Embankment
a. Sections, Loading Cases and Assumptions: A section of the MainEmbankment is shown in Figure 8.3-01. This section is taken fromFinal Design, Volume 2, by Forrest & Cotton (1962).
1) Forrest & Cotton (1963). Stability analyses for the mainembankment as given in the Forrest & Cotton DesignMemorandum No. 3, dated January 1963, are summarizedin Table 8.3.2. Soil properties used in the stability analysisare given in Table 8.3.3. The slope stability analysis for theembankment and dike are shown on Figure 8.3-02. Theembankment stability analysis is given in Figure 8.3-03.
2) Rone (1983). Stability analyses for the main embankmentas given in the Rone Engineers report, Liquefaction andStability Analysis, are summarized in Table 8.3.4. Soil
properties used in the stability analysis are given in Table8.3.5. The stability analysis calculations are given in Figure8.3-04.
3) KBR (1988). Stability analyses for the main embankment asgiven in the Brown & Root report, Toledo Bend Stability
Analysis, dated November 1988, are summarized in Table8.3.6. Soil properties used in the stability analysis are givenin Table 8.3.7. The embankment plan view showing thelocation of the stability section used for calculations is givenin Figures 8.3-05 and 8.3-06.
Rev. 0 Page 8-2312/31/2004
7/23/2019 STI Section8
65/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
Rev. 0 Page 8-2412/31/2004
7/23/2019 STI Section8
66/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
Rev. 0 Page 8-2512/31/2004
7/23/2019 STI Section8
67/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
Rev. 0 Page 8-2612/31/2004
7/23/2019 STI Section8
68/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
Rev. 0 Page 8-2712/31/2004
7/23/2019 STI Section8
69/108
7/23/2019 STI Section8
70/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
The stability analysis calculations are given in the following figures:
Main Embankment Stability Steady SeepageSta. 116+30 (Figure 8.3-07)
Main Embankment Stability Surcharge Pool Sta.
116+30 (Figure 8.3-08) Main Embankment Stability Rapid Drawdown
Sta. 116+30 (Figure 8.3-09) Main Embankment Stability Seismic Sta. 116+30
(Figure 8.3-10) Main Embankment Stability Steady Seepage
Sta. 130+50 (Figure 8.3-11) Main Embankment Stability Surcharge Pool Sta.
130+50 (Figure 8.3-12) Main Embankment Stability Rapid Drawdown
Sta. 130+50 Figure 8.3-13) Main Embankment Stability Seismic Sta. 130+50
(Figure 8.3-14) Main Embankment Stability Steady Seepage
Sta. 151+70 (Figure 8.3-15) Main Embankment Stability Surcharge Pool Sta.
151+70 (Figure 8.3-16) Main Embankment Stability Rapid Drawdown
Sta. 151+70 (Figure 8.3-17) Main Embankment Stability Seismic Sta. 151+70
(Figure 8.3-18)
Main Embankment Stability Steady SeepageSta. 178+20 (Figure 8.3-19) Main Embankment Stability Seismic Sta. 178+20
(Figure 8.3-20)
b. Potential for Uncontrolled Seepage at Toe. The embankment isdesigned with a pervious drainage blanket to control seepage.Relief wells have been installed to control the piezometricpressures of the foundation soils.
c. Summary of Liquefaction Analysis. The liquefaction potential was
previously evaluated by Rone Engineering, Inc., in their reporttitled, Liquefaction and Stability Analysis, Toledo Bend Dam,dated July 1983. The liquefaction potential was not found to be anissue.
d. Summary of Deformation Analysis. Soil deformation analysis dueto stability induced strains has not been performed as the
Rev. 0 Page 8-2912/31/2004
7/23/2019 STI Section8
71/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
conventional analysis factors of safety are satisfactory, based onstrength parameters derived by commonly accepted procedures.
e. Procedures Used to Determine Soil Properties.
The shear strength properties of soils were determined asdescribed in the following paragraphs. Soil classification tests forthe 1988 investigations included moisture control, dry density, andplasticity index.
f. Procedures Used to Determine Soil Strengths.
1) Soil shear strength parameters used in the 1988 stabilityanalysis by B&R were obtained from the MRA geotechnicalreport prepared by McBride & Ratcliff, titled Geotechnical
Investigation Toledo Bend Dam, dated November 1988.The tests were performed as consolidated, undrained tiaxialtests with pore pressure measurements on samples from thespillway, powerhouse, and embankment areas.
2) FERC and COE guidelines for steady seepage stabilitycases analyzed require use of the shear strength defined bythe S-curve (effective stress envelope) up to the normalstress where the S-curve and R-curve (total stress envelope)intersect, which is the point of the mobilized pore pressure.Thereafter, the shear strength defined by the average of theR-curve and S-curve was used.
3) Cohesive embankment zones for the steady seepage caseswere subdivided to delineate the depths below whichstrength parameters defined by the average of the total andeffective stress envelopes became effective. This transitiondepth was based on the normal stress at which the R-curveand S-curve presented in the MRA report intersected foreach material type.
4) The minimum shear strength obtained from the combined S-curve and R-curve was used for the rapid drawdown cases.The same shear strength was used for the earthquake
analysis as was used for steady seepage cases.5) Cohesive foundation strata were assigned appropriate
strength values in a similar manner, depending on normalstress and material type. The derivation of the angle ofinternal friction for granular soils is presented in the report byMRA. The same angle was used for all stress conditions.
g. Shear Strength Parameters
Rev. 0 Page 8-3012/31/2004
7/23/2019 STI Section8
72/108
7/23/2019 STI Section8
73/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
8.3.2 Dike Nos. 1, 2 and 3
a. Sections, Loading Cases and Assumptions. A section of theTypical Embankment Saddle Area is shown in Figure 8.3-21. Thissection is taken from Final Design, Volume 2, by Forrest & Cotton(1962).
1) Forrest & Cotton (1963). The analyses that were conductedby Forrest & Cotton on the dikes are unknown. Thefollowing extract from the Forrest & Cotton DesignMemorandum No. 3, Embankment and General ConstructionSchedule, dated January 1963, is the only informationavailable related to the original dike design. Soil propertiesused in the stability analysis are given in Table 8.3.8.
4-21. Dike design. A typical trial section similar to the embankmentsection was initially selected for design analysis. The stability analysis of the
typical dike section was made, assuming the strength of the compacted materials
to be the same as adopted for compacted materials in the main embankmentsection. The strength of the foundation material was assumed to have a cohesion
of 1400 psf and an angle of internal friction of zero degrees. The analysis for the
maximum section of the dike, height of about 66 feet, indicates that a factor ofsafety of 1.33 would be obtained at the end of construction condition. Adopted
dike sections are shown on Plate I-7. The adopted section differs slightly from the
section used in the slope stability analysis. However, the stability of the adoptedsection will obviously be equal to, or greater than, the section analyzed.
2) Rone (1983). Stability analyses for Dike No. 2 as given inthe Rone Engineers report, Liquefaction and Stability
Analysis, are summarized in Table 8.3.9. Soil propertiesused in the stability analysis are given in Table 8.3.10. Thestability analysis calculations are given in Figure 8.3-22.
3) KBR (1988). Stability analyses for Dike No. 2 as given in the
Brown & Root report, Toledo Bend Stability Analysis, datedNovember 1988, are summarized in Table 8.3.11. Soilproperties used in the stability analysis are given in Table8.3.12. Dike No. 2 plan view showing the location of thestability section used for calculations is given in Figure8.3-23. The stability analysis calculations are given in thefollowing figures:
Rev. 0 Page 8-3212/31/2004
7/23/2019 STI Section8
74/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
Dike No. 2 Stability Steady Seepage (Figure 8.3-24) Dike No. 2 Stability Surcharge Pool (Figure 8.3-25) Dike No. 2 Stability Rapid Drawdown (Figure 8.3-26) Dike No. 2 Stability Seismic (Figure 8.3-27)
Rev. 0 Page 8-3312/31/2004
7/23/2019 STI Section8
75/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
Rev. 0 Page 8-3412/31/2004
7/23/2019 STI Section8
76/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
Rev. 0 Page 8-3512/31/2004
7/23/2019 STI Section8
77/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
Rev. 0 Page 8-3612/31/2004
7/23/2019 STI Section8
78/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
b. Potential for Uncontrolled Seepage at Toe. (Not available)
c. Summary of Liquefaction Analysis. (Not available)
d. Summary of Deformation Analysis. (Not available)
e. Procedures Used to Determine Soil Properties. (Not available)
f. Procedures Used to Determine Soil Strengths. (Not available)
Rev. 0 Page 8-3712/31/2004
7/23/2019 STI Section8
79/108
7/23/2019 STI Section8
80/108
7/23/2019 STI Section8
81/108
Figure 8.3-03
EMBANKMENT
STABILITY ANALYSIS
7/23/2019 STI Section8
82/108
7/23/2019 STI Section8
83/108
7/23/2019 STI Section8
84/108
Figure 8.3-06
MAI EMBANKMENT AND
SPILLWAY STABILITY
SECTION LOCATIONS
7/23/2019 STI Section8
85/108
Figure 8.3-07
MAIN EMBANKMENT
STEADY SEEPAGE
STATION 116+30
7/23/2019 STI Section8
86/108
7/23/2019 STI Section8
87/108
Figure 8.3-09
MAI EMBANKMENT RAPID
DRAWDOWN
STATION 116+30
7/23/2019 STI Section8
88/108
Figure 8.3-10
MAIN EMBANKMENT SEISM
STATION 116+30
7/23/2019 STI Section8
89/108
7/23/2019 STI Section8
90/108
7/23/2019 STI Section8
91/108
Figure 8.3-13
MAIN EMBANKMENT
RAPID DRAWDOWN
STATION 130+50
7/23/2019 STI Section8
92/108
7/23/2019 STI Section8
93/108
Figure 8.3-15
MAIN EMBANKMENT STEAD
SEEPAGE
STATION 151+70
7/23/2019 STI Section8
94/108
Figure 8.3-16
MAIN EMBANKMENT
SURCHARGE POOL
STATION 151+70
7/23/2019 STI Section8
95/108
Figure 8.3-17
MAIN EMBANKMENT
RAPID DRWDOWN
STATION 151+70
7/23/2019 STI Section8
96/108
Figure 8.3-18
MAIN EMBANKMENT
SEISMIC
STATION 151+70
7/23/2019 STI Section8
97/108
Figure 8.3-19
MAIN EMBANKMENT
STEADY SEEPAGE
STATION 178+20
7/23/2019 STI Section8
98/108
Figure 8.3-20
MAIN EMBANKMENT
SEISMIC
STATION 178+20
7/23/2019 STI Section8
99/108
7/23/2019 STI Section8
100/108
Figure 8.3-22
DIKE NO. 2
STABILITY ANALYSES
SUMMARY OF RESULTS
Source: Liquefaction aStability analysis, Rone
Engineers, Inc., 1983
7/23/2019 STI Section8
101/108
Figure 8.3-23
DIKE NO. 2 STABILITY
SECTION LOCATION
7/23/2019 STI Section8
102/108
Figure 8.3-24
DIKE NO. 2
STEADY SEEPAGE
7/23/2019 STI Section8
103/108
7/23/2019 STI Section8
104/108
Figure 8.3-26
DIKE NO. 2
RAPID DRAWDOWN
7/23/2019 STI Section8
105/108
Figure 8.3-27
DIKE NO. 2
SEISMIC
7/23/2019 STI Section8
106/108
7/23/2019 STI Section8
107/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
8.5 WATER CONVEYANCE SYSTEM
No water conveyance systems are associated with the Toledo Bend Dam.
Rev. 0 Page 8-3912/31/2004
7/23/2019 STI Section8
108/108
Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures
8.6 SUMMARY OF FACTORS OF SAFETY ACHIEVED
8.6.1 Gravity Structures
a. See Section 8.2.1 for the summary of factors of safety, materialproperties, and hydrostatic conditions assumed for the spillway.
b. See Section 8.2.2 for the summary of factors of safety, materialproperties, and hydrostatic conditions assumed for thepowerhouse.
8.6.2 Embankment Structures
a. See Section 8.3.1 for the summary of factors of safety, materialproperties, and hydrostatic conditions assumed for the mainembankment.
b. See Section 8.3.2 for the summary of factors of safety, materialproperties, and hydrostatic conditions assumed for the Dikes 1, 2,and 3.