STI Section8

Embed Size (px)

Citation preview

  • 7/23/2019 STI Section8

    1/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    SECTION 8

    STABILITY / STRESS ANALYSIS

    OF PROJECT STRUCTURES

    8.1 GENERAL

    8.1.1 Load Cases Analyzed

    The load cases analyzed for the various structures over time in variousreports have been grouped by structure, then by report. Tables andfigures have been created to summarize all the data in the followingsections.

    8.1.2 Stability Analyses Methodologies

    a. Forrest & Cotton (1962). Serving as SRAs Engineer, Forrest &Cotton used the following methods for analyzing the stability of thestructures:

    1) Main Embankment and Dikes (as reported in DesignMemorandum No 3). The main embankment and dikes wereanalyzed using the circular arc method.

    2) Spillway (as reported in Design Memorandum No. 2). Handcalculations for sliding and overturning on three sections: theoverflow section, the low-flow section, and the non-overflowsection. Circular arc analysis was also performed on theoverflow section.

    3) Powerhouse. To date, no information has been uncoveredthat describes the original powerhouse stability designmethodology.

    b. Rone Engineers (1983). Serving as a geotechnical consultant,

    Rone performed a liquefaction and stability analysis using thefollowing methods:

    1) Main Embankment. The general subsurface of the mainembankment was tested by performing 16 standardpenetration sample borings. The stability analysis followedguidelines recognized by FERC. Using conservativeparameters, a maximum design earthquake acceleration of

    Rev. 0 Page 8-112/31/2004

  • 7/23/2019 STI Section8

    2/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    0.04 g resulted in a factor of safety greater than 1.15. Theliquefaction potential was also analyzed indicating that thereis no possibility for liquefaction.

    2) A stability analysis was performed on Dike No. 2, whichindicated that the embankment was adequately stable.Recommendations were made for adding a small berm withan internal drainage system to control seepage areas.

    c. Brown & Roots Toledo Bend Dam Stability Analysis (1988)

    1) Main Embankment. The main embankment was analyzedon three separate cross sections using PCSTABL4 softwarewhich calculates the factor of safety against slope failureusing two-dimensional limit equilibrium methods. The factor

    of safety was calculated using the Simplified Bishop methodof slices.

    PCSTABL4 as used by Brown & Root for the 1988 analyses,was verified for a typical embankment section usingMCAUTO SLOPE ( McDonnell Douglas AutomationCompany product), which is a computer subsystem ofIntegrated Civil Engineering System (ICES). The run wasperformed for the embankment section at Station 116+30.

    As reported in Toledo Bend Stability Analysis Verification ofPCSTABL4 Computer Program, dated November 1988 by

    Brown & Root USA, Inc., the factor of safety calculated bythe PCSTABL4 program using the Simplified Bishop methodof slices correlated very well with that calculated usingMCAUTO SLOPE.

    2) Spillway. Hand calculations were used in 1988 to calculatesliding stability for the spillway. The method of analysis wasa two-dimensional limit equilibrium approach, in accordancewith ETL-1110-2-256. Force equilibrium is satisfied in theapproach. Moment equilibrium was not analyzed. Theanalysis was performed on three different sections of the

    spillway: the overflow section, the low-flow section, and thenon-overflow section.

    3) Powerhouse. Slipcircle analysis was determined to be morecritical for the powerhouse, and therefore PCSTABL4 wasused to examine the stability of the powerhouse for slidingblock failure, using the simplified Janbu method of slices.The excavated intake channel slope was analyzed for

    Rev. 0 Page 8-212/31/2004

  • 7/23/2019 STI Section8

    3/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    sudden drawdown and earthquake conditions, also using thePCSTABL4 program.

    c. Brown & Roots FERC Inspection Report (1998)

    1) Spillway. Further analyses of the spillway only (overflow andlow-flow sections) were undertaken for this report to examinethe effect of the approach slab and drainage system on thestability of the structure against sliding and overturning. Themethod used was hand calculations using the two-dimensional limit equilibrium approach, similar to that used inthe 1988 Stability Analysis.

    Note. There is no reference in the above to any analyses ontraining/retaining walls. These are less crit ical in the context

    of publ ic safety and are therefore not inc luded in thisAppendix.

    8.1.3 Properties of Materials

    Material testing reports from the original construction have not beenlocated. Design properties and assumptions made for the variouscalculations have been collected. Concrete compressive and tensilestrength properties for the spillway are summarized in Section 8.2.1,paragraph h. Soil properties for the powerhouse are summarized in Table8.2.10. Soil properties for the main embankment are summarized in

    Tables 8.3.3, 8.3.5, and 8.3.7 from the various reports. Soil properties forthe minor dikes are summarized in Tables 8.3.8, 8.3.10, and 8.3.12.

    Rev. 0 Page 8-312/31/2004

  • 7/23/2019 STI Section8

    4/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    8.2 GRAVITY STRUCTURES

    8.2.1 Spillway

    a. Sections, Loading Cases and Assumptions. Spillway sections areshown in Figures 8.2-01, 8.2-02, and 8.2-03. Loading conditionsand assumptions are shown in subsequent paragraphs of thereport.

    1) Forrest & Cotton (1962). Stability analyses for the spillwayas given in the Forrest & Cotton Design Memorandum No. 2,dated August 1962 are summarized in Table 8.2.1. Thestability analysis calculations for the Intermediate PierMonolith (Figures 8.2-04 and 8.2-05), Low Flow ReleasePier Monolith (Figure 8.2-06), and the Non-Overflow Section

    (Figure 8.2-07), are given in the respective figures. Thespillway chute stability analysis calculations are given inFigure 8.2-08.

    2) Rone (1983). Stability analyses for the spillway as given inthe Rone Engineers report, Instrumentation and HydrostaticPressure Relief Systems, are summarized in Table 8.2.2 andshown in Figure 8.2-09.

    3) KBR (1988). Stability analyses for the spillway as given inthe Brown & Root report, Toledo Bend Stability Analysis,

    dated November 1988, are summarized in Table 8.2.3. Thestability analysis calculations are given in the followingfigures: Case A Overflow Section (Figure 8.2-10) Case B1 Overflow Section (Figure 8.2-11) Case B2 Overflow Section (Figure 8.2-12) Case C Overflow Section (Figure 8.2-13) Case B1 Low Flow Section (Figure 8.2-14) Case D Low Flow Section (Figure 8.2-15) Case A Non-Overflow Section Hydrostatic Loads

    (Figure 8.2-16)

    Case A Non-Overflow Section Soil Loads(Figure 8.2-17)

    Case C Non-Overflow Section Hydrostatic Loads(Figure 8.2-18)

    Case C Non-Overflow Section Soil Loads(Figure 8.2-19)

    Main Embankment Showing Stability Sections(Figure8.2-20)

    Rev. 0 Page 8-412/31/2004

  • 7/23/2019 STI Section8

    5/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    Rev. 0 Page 8-512/31/2004

  • 7/23/2019 STI Section8

    6/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    Rev. 0 Page 8-612/31/2004

  • 7/23/2019 STI Section8

    7/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    Rev. 0 Page 8-712/31/2004

  • 7/23/2019 STI Section8

    8/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    4) KBR (1998). Stability analyses for the spillway as given inthe Brown & Root report, Toledo Bend FERC Stability

    Analysis, dated October 1998, are summarized in

    Table 8.2.4. Main Embankment Stability Section Locationsare shown in Figure 8.2-20. The stability analysiscalculations are given in the following figures:

    Case 1 Overflow Section Sliding Analysis(Figure 8.2-21)

    Case 1 Overflow Section Overturning Analysis(Figure 8.2-22X)

    Case 2 Overflow Section Sliding analysis(Figure 8.2-23)

    Case 2 Overflow Section Overturning Analysis(Figure 8.2-24)

    Case 3 Overflow Section Sliding Analysis(Figure 8.2-25)

    Case 3 Overflow Section Overturning Analysis(Figure 8.2-26X)

    Case 4 Overflow Section Sliding Analysis(Figure 8.2-27)

    Case 4 Overflow Section Overturning Analysis(Figure 8.2-28)

    Case 1 Low Flow Section Sliding Analysis(Figure 8.2-29)

    Case 1 Low Flow Section Overturning Analysis

    (Figure 8.2-30) Case 2 Low Flow Section Sliding Analysis

    (Figure 8.2-31) Case 2 Low Flow Section Overturning Analysis

    (Figure 8.2-32)

    b. Key Elevations. Table 8.2.5 gives the key elevations of thespillway.

    c. Key Lateral Dimensions. Table 8.2.6 gives the key lateraldimensions of the spillway.

    d. Piezometer and Drain Locations. Figure 8.2-33 shows the spillwaypiezometer and relief well locations for the spillway.

    e. Foundation Shear Strength Parameters. Table 8.2.7 shows theshear strength parameters used in the different analyses conductedto spillway stability.

    Rev. 0 Page 8-812/31/2004

  • 7/23/2019 STI Section8

    9/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    f. Minimum Cohesion to Meet Stability Criteria. The minimumcohesion intercept providing acceptable factors of safety has notbeen determined, as such. However, due to concerns over thelong term strength parameters of the overconsolidated clays, a 50

    percent reduction in cohesion was used in the 1988 analysis asindicated in Table 8.2.7.

    g. Negative Crest Pressures on Spillway. Negative crest pressureshave not been addressed in any of the spillway stability analysesundertaken to date.

    Rev. 0 Page 8-912/31/2004

  • 7/23/2019 STI Section8

    10/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    Rev. 0 Page 8-1012/31/2004

  • 7/23/2019 STI Section8

    11/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    Rev. 0 Page 8-1112/31/2004

  • 7/23/2019 STI Section8

    12/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    h. Concrete Compressive and Tensile Strength: The following pagestaken from Forrest & Cotton Design Memorandum No. 2, dated

    August 1962, provide the concrete design parameters for thespillway. Actual test results from samples taken during constructionare not available.

    Rev. 0 Page 8-1212/31/2004

  • 7/23/2019 STI Section8

    13/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    5-05. Concrete, general. The symbols, nomenclature, and abbreviations used

    herein with respect to plain, reinforced, and prestressed concrete are those used by the

    American Concrete Institute. For purposes of referencing working stresses as pertainingto the various concrete components of the spillway, the stresses have been separated

    into three groups, as follows:

    GROUP I stresses: Applies to miscellaneous concrete not included

    under Group II and III stresses.

    GROUP II stresses: Applies to concrete in structures that will besubjected to submergence, wave action, and spray.

    Included will be most of the mass concrete in the

    weirs, piers, non-overflow sections and theretaining walls. Exceptions will be the approach

    apron and all prestressed concrete.GROUP III stresses: Applies to prestressed concrete as proposed for the

    bridge girders and the trunnion anchorage.

    5-06. Strength of concrete. For design purposes, it was assumed that theultimate compressive strength of the concrete in the different components of the

    spillway would be as follows:

    Spillway component

    Ultimate compressive

    strength at 28 days in psi

    1. General structural concrete 3,000

    2. Prestressed trunnion anchorage and bridge girders 5,000

    3. Bridge deck 4,000

    4. Fill concrete and for other purposes where strength is

    not a required property of the material

    2,000

    Rev. 0 Page 8-1312/31/2004

  • 7/23/2019 STI Section8

    14/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    5-07. Allowable unit stresses, plain concrete. The allowable flexure (fc) stress for plainconcrete with assumed Group A loading will be as follows:

    Design Strength of Concrete

    Nature of Stress

    f 'c

    proportion

    Unit stress for

    3000 lb. concrete in psi,

    n = 10

    Extreme fiber stress in tension:

    GROUP I 0.03 f 'c 90

    GROUP II 0.02 f 'c 60

    5-08. Allowable unit stresses, reinforced concrete. The allowable unit stressesfor reinforced concrete with Group A loading will be as is given in the following

    paragraphs:5-08a. Flexure, fc. The allowable flexure stress, fc, for reinforced concrete for

    assumed Group A loading will be as follows:

    Design Strength of Concrete

    Nature of Stress

    f 'c

    proportion

    Unit stress for

    3000 lb. concrete in psi,n = 10

    Extreme fiber stress in compression:

    GROUP I 0.45 f 'c 1,350

    GROUP II 0.35 f 'c 1,050

    5-08b. Shear, Vc. Allowable shear stresses, Vc, as a measure of diagonal tension,

    for assumed Group A loading will be as follows. These stresses are within the GROUP I

    stress classification and are all in accordance with the American Concrete Institute

    specifications.

    Rev. 0 Page 8-1412/31/2004

  • 7/23/2019 STI Section8

    15/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    Design Strength of Concrete

    Nature of Stress

    f 'cproportion

    Unit stress for3000 lb. concrete in psi,

    n = 10

    a. Beams with no web reinf. (1) 0.03 f 'c 90

    b. Beams with longitudinal bars

    and stirrups or bent bars

    0.08 f 'c 240

    c. Beams with longitudinal bars

    and stirrups plus bent bars (2)

    0.12 f 'c 360

    d. Punching shear 0.075 f 'c 225

    e. Footings 0.025 f 'c 75

    (1) Where calculations indicate Vc is not exceeded, nominal vertical stirrups will

    be provided throughout the full span of the beam. The minimum stirrup will be #3 barsand the maximum spacing will be one half the beam depth.

    (2) The bent bars are to be bent up and suitable to carry at least 0.04fc.

    5-08c. Bond, u. The allowable bond, u, for assumed Group A loading will be asfollows. These stresses are all within the GROUP I stress classification.

    Design Strength of Concrete

    Nature of Stress

    f 'c

    proportion

    Unit stress for

    3000 lb. concrete in psi,

    n = 10

    Deformed ASTM A-305 bars (3):

    Top bars 0.07 f 'c 210

    In two-way footing except top

    bars

    0.08 f 'c 240

    All others 0.10 f 'c 300

    Plain bars hook required (4)

    Top bars 0.03 f 'c 90In two-way footing except top

    bars

    0.036 f 'c 108

    All others 0.045 f 'c 135

    Rev. 0 Page 8-1512/31/2004

  • 7/23/2019 STI Section8

    16/108

  • 7/23/2019 STI Section8

    17/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    5-08f. Combined bending and direct stresses. The allowable combined axial and

    bending stresses for reinforced concrete columns and walls will be determined inaccordance with the American Concrete Institute Code (ACI-3l8-56).

    5-08g. Moduli and coefficients. The modulus of elasticity, Ec, and the coefficient

    of expansion of 3,000 pound concrete will be as follows:

    Modulus of elasticity, Ec. - 3,000,000 psi

    Coef. of expansion - 0.000006 per F.

    5-09. Allowable unit stresses, prestressed concrete. Working stresses forprestressed concrete used in trunnion anchorage and. bridge girders will be in accordance

    with applicable specifications listed. in paragraph 5-01. The allowable unit stresses for

    assumed Group A loading will be as follows. These stresses are all within the GROUP IIIstress classification.

    Design Strength of Concrete

    Nature of Stress

    f 'c i

    proportion

    Unit stress for

    5000 lb. concrete in psi,

    n = 6

    TEMPORARY STRESSES:

    Compression in extreme fiber 0.60 f 'c i 2,400

    Tension 0.05 f 'c i 200

    STRESSES: UNDER DEAD, LIVE AND IMPACT LOADSCompression in extremefiber 0.40 f 'c i 2,000

    Tension in extreme fiber 0 0

    ANCHORAGE BEARING STRESSES:

    Trunnion anchorage fcp = (0.6 f 'c i) times the cube root of Ac/Ab

    The strength of concrete at the time of prestress of trunnion anchorage will be 4,000 psi.

    The strength of concrete at the time of cable release will be 4,000 psi.

    Rev. 0 Page 8-1712/31/2004

  • 7/23/2019 STI Section8

    18/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    i. Alkali Aggregate Reactivity (AAR) Potential. AAR has not beenaddressed in any of the previous reports.

    1) Cement with high alkaline content can react with theaggregate in a wet environment. Reactive aggregates aregarnet or silica. The aggregate decomposes into a greatervolume that the original causing the concrete to craze, crackand spall.

    2) There is no known preventive or remedy when thesecharacteristics are present.

    8.2.2 Powerhouse

    a. Sections, Loading Cases and Assumptions: Powerhouse sectionsare shown in Figure 8.2-34. Loading conditions and assumptionsare provided in subsequent paragraphs of the report.

    1) Forrest & Cotton (1962). No data is available for Forrest &Cottons analyses of the powerhouse. However, a note onthe Power Plant Stability Analysis from the Rone (1983)report states that data on this plate from the power plantstability analyses performed by Forrest & Cotton, Inc.,Consulting Engineers, in 1963.

    2) Rone (1983). Stability analyses for the powerhouse asgiven in the Rone Engineers report, Instrumentation andHydrostatic Pressure Relief Systems, are summarized inTable 8.2.8. The stability analysis calculations are given inFigure 8.2-35.

    3) KBR (1988). Stability analyses for the powerhouse as givenin the Brown & Root report, Toledo Bend Stability Analysis,dated November 1988 are summarized in Table 8.2.9. Soilproperties used in the stability analysis are given in Table8.2.10. The powerhouse plan view showing the location of

    the stability sections used for calculations is given in Figure8.2-36. The stability analysis calculations are given in thefollowing figures:

    Powerhouse Sliding Stability Normal Pool(Figure 8.2-37)

    Powerhouse Stability Normal Pool (Figure 8.2-38) Powerhouse Seismic (Figure 8.2.39)

    Rev. 0 Page 8-1812/31/2004

  • 7/23/2019 STI Section8

    19/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    Powerhouse Surcharge Pool (Figure 8.2-40)

    b. Key Elevations. (Not available)

    c. Key Lateral Dimensions. (Not available)

    d. Piezometer and Drain Locations. Figure 8.2-41 shows thepowerhouse piezometer and relief well locations for the spillway.

    e. Foundation Shear Strength Parameters. Refer to Table 8.2.10.

    f. Minimum Cohesion to Meet Stability Criteria. Refer to paragraph8.2.1f.

    g. Negative Crest Pressures on Spillway. (Not applicable)

    h. Concrete Compressive and Tensile Strength. (Not available)

    i. Alkali Aggregate Reactivity (AAR) Potential. Refer to paragraph

    8.2.1i.

    8.2.3 Intake and Outlet Works

    There are no intake or outlet works associated with this project. Alldischarges from the reservoir are made through the spillway or the

    powerhouse.

    Rev. 0 Page 8-1912/31/2004

  • 7/23/2019 STI Section8

    20/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    Rev. 0 Page 8-2012/31/2004

  • 7/23/2019 STI Section8

    21/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    Rev. 0 Page 8-2112/31/2004

  • 7/23/2019 STI Section8

    22/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    Rev. 0 Page 8-2212/31/2004

  • 7/23/2019 STI Section8

    23/108

    Figure 8.2-01

    SPILLWAY SLIDDIN STABILITY

    TYPICAL PIER SECTIONS

  • 7/23/2019 STI Section8

    24/108

    Figure 8.2-02

    UPSTREAM ELEVATION

    OVERFLOW SECTION

  • 7/23/2019 STI Section8

    25/108

    Figure 8.2-03

    UPSTREAM ELEVATION

    LOW FLOW SECTION

  • 7/23/2019 STI Section8

    26/108

    Figure 8.2-04

    INTERMEDIATE PIER MONO

    STABILITY ANALYSES

    Sheet 1 of 2

  • 7/23/2019 STI Section8

    27/108

    Figure 8.2-05

    INTERMEDIATE PIER MONO

    STABILITY ANALYSES

    Sheet 2 of 2

  • 7/23/2019 STI Section8

    28/108

    Figure 8.2-06

    LOW FLOW RELEASE PIER MO

    STABILITY ANALYSES

  • 7/23/2019 STI Section8

    29/108

    Figure 8.2-07

    NON-OVERFLOW SECTION

    STABILITY ANALYSES

  • 7/23/2019 STI Section8

    30/108

    Figure 8.2-08

    SPILLWAY CHUTE

    STABILITY ANALYSES

  • 7/23/2019 STI Section8

    31/108

    NOTE:

    THE BASE DRAWING INFORMATION ON THIS SHEET WAS TAKEN FROM:

    FERC COMMISSION ON INSPECTION OF PROJECT WORKS THAT MI GHT ENDANGER PUBLIC SAFETY

    B&R - 1998, APPENDIX D-65

    Figure 8.2-09

    SPILLWAY STABILITY ANALYSES

    OPERATIONAL PROCEDUURES

  • 7/23/2019 STI Section8

    32/108

    TOLEDO BEND DAM STABILITY

    ANALYSIS, B&R - 1988

    Figure 8.2-10

    CASE A - OVERFLO

    SECTION

  • 7/23/2019 STI Section8

    33/108

    TOLEDO BEND DAM STABILITY

    ANALYSIS, B&R - 1988

    Figure 8.2-11

    CASE B1 - OVERF

    SECTION

  • 7/23/2019 STI Section8

    34/108

    TOLEDO BEND DAM STABILITY

    ANALYSIS, B&R - 1988

    Figure 8.2-12CASE B2 - OVERFL

    SECTION

  • 7/23/2019 STI Section8

    35/108

    TOLEDO BEND DAM STABILITY

    ANALYSIS, B&R - 1988

    Figure 8.2-13

    CASE C - OVERFLOW

    SECTION

  • 7/23/2019 STI Section8

    36/108

    TOLEDO BEND DAM STABILITY

    ANALYSIS, B&R - 1988

    Fig 8.2-14

    CASE B1 - LOW FLOW

    SECTION

  • 7/23/2019 STI Section8

    37/108

  • 7/23/2019 STI Section8

    38/108

    TOLEDO BEND DAM STABILITY

    ANALYSIS, B&R - 1988

    Figure 8.2-16

    CASE A - NON -

    OVERFLOW SECTION

    HYDROSTATIC LOAD

  • 7/23/2019 STI Section8

    39/108

    TOLEDO BEND DAM STABILITY

    ANALYSIS, B&R - 1988

    figure 8.2-17

    CASE A - NON-OVERFLO

    SECTION SOIL LOADS

  • 7/23/2019 STI Section8

    40/108

    Figure 8.2-18

    CASE C - NON-OVERFL

    SECTION HYDROSTA

    LOADS

    TOLEDO BEND DAM STABILITY

    ANALYSIS, B&R - 1988

  • 7/23/2019 STI Section8

    41/108

  • 7/23/2019 STI Section8

    42/108

    Figure 8.2-20

    MAIN EMBANKMENT STABILITY

    SECTION LOCATIONS

  • 7/23/2019 STI Section8

    43/108

    CASE1

    OV

    ERFLOWS

    ECTION-SLIDINGANALYSIS

    NOTE:

    THE BASE DRAWING

    INFORMATION ON THIS

    SHEET WAS TAKEN FROM:

    FERC COMMISSION ONINSPECTION OF PROJECT

    WORKS THAT MIGHT

    ENDANGER PUBLIC SAFETY

    B&R - 1998

    APPENDIX D-54

    Figure 8.2-2

    CASE1

    OVERFLOW SEC

    SLIDING ANALY

  • 7/23/2019 STI Section8

    44/108

    CASE1

    OV

    ERFLOW

    SECTION-OVERTURN

    ING

    ANALYSIS

    A p p r o a c h S l a b N o t E f f e c t i v e

    NOTE:

    THE BASE DRAWING INFORMATION ON

    THIS SHEET WAS TAKEN FROM:

    FERC COMMISSION ON INSPECTION

    OF PROJECT WORKS THAT MIGHT

    ENDANGER PUBLIC SAFETY

    B&R - 1998, APPENDIX D-58

    Figure 8.2-22

    CASE1

    OVERFLOW SECTION -

    OVERTURNING ANALYSIS

  • 7/23/2019 STI Section8

    45/108

    CASE2

    OVER

    FLOW

    SECTION-SLIDINGANA

    LYSIS

    ApproachSlabEffective

    Figure 8.2-23

    CASE 2

    OVERFLOW SECTI

    SLIDING ANALYSNOTE:

    THE BASE DRAWING INFORMATION

    ON THIS SHEET WAS TAKEN FROM:

    FERC COMMISSION ON INSPECTION

    OF PROJECT WORKS THAT MIGHT

    ENDANGER PUBLIC SAFETY

    B&R - 1998, APPENDIX D-55

  • 7/23/2019 STI Section8

    46/108

    CASE2

    OVERFLOW

    SECTION-OVERTURNINGA

    NALYSIS

    ApproachSlabEffective

    NOTE:

    THE BASE DRAWING INFORMATION ON

    THIS SHEET WAS TAKEN FROM:

    FERC COMMISSION ON INSPECTION OF

    PROJECT WORKS THAT MIGHT

    ENDANGER PUBLIC SAFETY

    B&R - 1998, APPENDIX D-59

    Figure 8.2-24

    CASE 2

    OVERFLOW SECTION

    OVERTURNING ANALYSIS

  • 7/23/2019 STI Section8

    47/108

    CASE3

    OVE

    RFLOW

    SECTION-SLIDINGAN

    ALYSIS

    ApproachSlabNotEffective

    Figure 8.2-25

    CASE 3

    OVERFLOW SECTI)

    SLIDING ANALYSNOTE:

    THE BASE DRAWING INFORMATION ON

    THIS SHEET WAS TAKEN FROM:

    FERC COMMISSION ON INSPECTION OF

    PROJECT WORKS THAT MIGHT

    ENDANGER PUBLIC SAFETY

    B&R - 1998, APPENDIX D-59

  • 7/23/2019 STI Section8

    48/108

    CASE3

    OVERFLOW

    SECTION-OVERTURNINGANALYSIS

    ApproachSlabNotEffective

    NOTE:

    THE BASE DRAWING INFORMATION ON

    THIS SHEET WAS TAKEN FROM:

    FERC COMMISSION ON INSPECTION OF

    PROJECT WORKS THAT MIGHT

    ENDANGER PUBLIC SAFETY

    B&R - 1998, APPENDIX D-60

    Figure 8.2-26

    CASE 3

    OVERFLOW SECTION

    OVERTURNING ANALYS

  • 7/23/2019 STI Section8

    49/108

    CASE4

    OOVERFLOW

    SECTION-SLIDINGANA

    LYSIS

    ApproachSlabEffective

    NOTE:

    THE BASE DRAWING INFORMATION ON

    THIS SHEET WAS TAKEN FROM:

    FERC COMMISSION ON INSPECTION OF

    PROJECT WORKS THAT MIGHT

    ENDANGER PUBLIC SAFETY

    B&R - 1998, APPENDIX D-57

    Figure 8.2-27

    CASE 4

    OVERFLOW SECTI

    SLIDING ANALYS

  • 7/23/2019 STI Section8

    50/108

  • 7/23/2019 STI Section8

    51/108

    CASE1

    LOW

    FLOW

    SECTION-SLIDINGANALYSIS

    ApproachSlabNotEffective

    S

    i l W t

    1 2 0

    f

    NOTE:

    THE BASE DRAWING INFORMATION ON THIS SHEET

    WAS TAKEN FROM:

    FERC COMMISSION ON INSPECTION OF PROJECT

    WORKS THAT MIGHT ENDANGER PUBLIC SAFETY

    B&R - 1998, APPENDIX D-63

    Figure 8.2-29

    CASE 1

    LOW FLOW SECTION

    SLIDING ANALYSIS

  • 7/23/2019 STI Section8

    52/108

    NOTE:

    THE BASE DRAWING INFORMATION

    ON THIS SHEET WAS TAKEN FROM:

    FERC COMMISSION ON INSPECTION

    OF PROJECT WORKS THAT MIGHT

    ENDANGER PUBLIC SAFETY

    B&R - 1998, APPENDIX D-65

    Figure 8.3-30

    CASE 1 - LOW FLOW SECTION

    OVERTURNING ANALYSIS

    CASE1

    LOW

    FLO

    WS

    ECTION-OVERTURNINGA

    NALYSIS

    ApproachSlabNotEffective

    S

    i l W t

    1 2 0

    f

  • 7/23/2019 STI Section8

    53/108

    NOTE:

    THE BASE DRAWING INFORMATION ON THIS SHEET WAS

    TAKEN FROM:

    FERC COMMISSION ON INSPECTION OF PROJECT WORKS

    THAT MIGHT ENDANGER PUBLIC SAFETY

    B&R - 1998, APPENDIX D-64

    CASE2

    LOW

    FLOW

    SECTION-SLIDINGANALYSIS

    ApproachSlabEffective

    S

    i l W t

    1 2 0

    f

    Figure 8.2-31

    CASE 2

    LOW FLOW SECTION

    SLIDING ANALYSIS

  • 7/23/2019 STI Section8

    54/108

    NOTE:

    THE BASE DRAWING INFORMATION ON THIS SHEET WAS

    TAKEN FROM FERC COMMISSION ON INSPECTION OF

    PROJECT WORKS THAT MIGHT ENDANGER PUBLIC

    SAFETY, B&R - 1998, APPENDIX D-66

    CASE2

    LOW

    FL

    OW

    SECTION-OVERTURNINGANALYSIS

    ApproachSlabEffective

    Figure 8.2-32

    CASE 2

    LOW FLOW SECTION

    OVERTURNING ANALYSIS

  • 7/23/2019 STI Section8

    55/108

    Figure 8.2-33

    PLAN OF

    SPILLWAY PIEZOMETER

  • 7/23/2019 STI Section8

    56/108

    Figure 8.2-34

    POWRHOUSE PLAN

    & SECTIONS

  • 7/23/2019 STI Section8

    57/108

    Source: INSTRUMENTATION AND

    HYDROSTATIC PRESSURE RELIEF

    SYSTEMS, RONE ENGINEERS, INC., 1983

    Figure 8.2-35

    POWER PLANT STABILITY ANAL

    OPERATIONAL PROCEDURE

  • 7/23/2019 STI Section8

    58/108

    Figure 8.2-36

    POWER HOUSE STABILI

    SECTION LOCATIONS

  • 7/23/2019 STI Section8

    59/108

    Figure 8.2-37

    POWER HOUSE

    SLIDING STABILITY

  • 7/23/2019 STI Section8

    60/108

    Figure 8.2-38

    POWER HOUSE NORMAL PO

  • 7/23/2019 STI Section8

    61/108

    Figure 8.2-39

    POWER HOUSE

    SEISMIC

  • 7/23/2019 STI Section8

    62/108

    Figure 8.2-40

    POWR HOUSE

    SURCHARGE POOL

  • 7/23/2019 STI Section8

    63/108

    Figure 8.2-41

    PLAN OF POWRE HOUSE

    PIEZOMETERS

  • 7/23/2019 STI Section8

    64/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    8.3 EMBANKMENT STRUCTURES

    The Toledo Bend Dam embankment structures are identified inTable 8.3.1 with their corresponding key dimensions, elevations, andslopes.

    8.3.1 Main Embankment

    a. Sections, Loading Cases and Assumptions: A section of the MainEmbankment is shown in Figure 8.3-01. This section is taken fromFinal Design, Volume 2, by Forrest & Cotton (1962).

    1) Forrest & Cotton (1963). Stability analyses for the mainembankment as given in the Forrest & Cotton DesignMemorandum No. 3, dated January 1963, are summarizedin Table 8.3.2. Soil properties used in the stability analysisare given in Table 8.3.3. The slope stability analysis for theembankment and dike are shown on Figure 8.3-02. Theembankment stability analysis is given in Figure 8.3-03.

    2) Rone (1983). Stability analyses for the main embankmentas given in the Rone Engineers report, Liquefaction andStability Analysis, are summarized in Table 8.3.4. Soil

    properties used in the stability analysis are given in Table8.3.5. The stability analysis calculations are given in Figure8.3-04.

    3) KBR (1988). Stability analyses for the main embankment asgiven in the Brown & Root report, Toledo Bend Stability

    Analysis, dated November 1988, are summarized in Table8.3.6. Soil properties used in the stability analysis are givenin Table 8.3.7. The embankment plan view showing thelocation of the stability section used for calculations is givenin Figures 8.3-05 and 8.3-06.

    Rev. 0 Page 8-2312/31/2004

  • 7/23/2019 STI Section8

    65/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    Rev. 0 Page 8-2412/31/2004

  • 7/23/2019 STI Section8

    66/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    Rev. 0 Page 8-2512/31/2004

  • 7/23/2019 STI Section8

    67/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    Rev. 0 Page 8-2612/31/2004

  • 7/23/2019 STI Section8

    68/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    Rev. 0 Page 8-2712/31/2004

  • 7/23/2019 STI Section8

    69/108

  • 7/23/2019 STI Section8

    70/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    The stability analysis calculations are given in the following figures:

    Main Embankment Stability Steady SeepageSta. 116+30 (Figure 8.3-07)

    Main Embankment Stability Surcharge Pool Sta.

    116+30 (Figure 8.3-08) Main Embankment Stability Rapid Drawdown

    Sta. 116+30 (Figure 8.3-09) Main Embankment Stability Seismic Sta. 116+30

    (Figure 8.3-10) Main Embankment Stability Steady Seepage

    Sta. 130+50 (Figure 8.3-11) Main Embankment Stability Surcharge Pool Sta.

    130+50 (Figure 8.3-12) Main Embankment Stability Rapid Drawdown

    Sta. 130+50 Figure 8.3-13) Main Embankment Stability Seismic Sta. 130+50

    (Figure 8.3-14) Main Embankment Stability Steady Seepage

    Sta. 151+70 (Figure 8.3-15) Main Embankment Stability Surcharge Pool Sta.

    151+70 (Figure 8.3-16) Main Embankment Stability Rapid Drawdown

    Sta. 151+70 (Figure 8.3-17) Main Embankment Stability Seismic Sta. 151+70

    (Figure 8.3-18)

    Main Embankment Stability Steady SeepageSta. 178+20 (Figure 8.3-19) Main Embankment Stability Seismic Sta. 178+20

    (Figure 8.3-20)

    b. Potential for Uncontrolled Seepage at Toe. The embankment isdesigned with a pervious drainage blanket to control seepage.Relief wells have been installed to control the piezometricpressures of the foundation soils.

    c. Summary of Liquefaction Analysis. The liquefaction potential was

    previously evaluated by Rone Engineering, Inc., in their reporttitled, Liquefaction and Stability Analysis, Toledo Bend Dam,dated July 1983. The liquefaction potential was not found to be anissue.

    d. Summary of Deformation Analysis. Soil deformation analysis dueto stability induced strains has not been performed as the

    Rev. 0 Page 8-2912/31/2004

  • 7/23/2019 STI Section8

    71/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    conventional analysis factors of safety are satisfactory, based onstrength parameters derived by commonly accepted procedures.

    e. Procedures Used to Determine Soil Properties.

    The shear strength properties of soils were determined asdescribed in the following paragraphs. Soil classification tests forthe 1988 investigations included moisture control, dry density, andplasticity index.

    f. Procedures Used to Determine Soil Strengths.

    1) Soil shear strength parameters used in the 1988 stabilityanalysis by B&R were obtained from the MRA geotechnicalreport prepared by McBride & Ratcliff, titled Geotechnical

    Investigation Toledo Bend Dam, dated November 1988.The tests were performed as consolidated, undrained tiaxialtests with pore pressure measurements on samples from thespillway, powerhouse, and embankment areas.

    2) FERC and COE guidelines for steady seepage stabilitycases analyzed require use of the shear strength defined bythe S-curve (effective stress envelope) up to the normalstress where the S-curve and R-curve (total stress envelope)intersect, which is the point of the mobilized pore pressure.Thereafter, the shear strength defined by the average of theR-curve and S-curve was used.

    3) Cohesive embankment zones for the steady seepage caseswere subdivided to delineate the depths below whichstrength parameters defined by the average of the total andeffective stress envelopes became effective. This transitiondepth was based on the normal stress at which the R-curveand S-curve presented in the MRA report intersected foreach material type.

    4) The minimum shear strength obtained from the combined S-curve and R-curve was used for the rapid drawdown cases.The same shear strength was used for the earthquake

    analysis as was used for steady seepage cases.5) Cohesive foundation strata were assigned appropriate

    strength values in a similar manner, depending on normalstress and material type. The derivation of the angle ofinternal friction for granular soils is presented in the report byMRA. The same angle was used for all stress conditions.

    g. Shear Strength Parameters

    Rev. 0 Page 8-3012/31/2004

  • 7/23/2019 STI Section8

    72/108

  • 7/23/2019 STI Section8

    73/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    8.3.2 Dike Nos. 1, 2 and 3

    a. Sections, Loading Cases and Assumptions. A section of theTypical Embankment Saddle Area is shown in Figure 8.3-21. Thissection is taken from Final Design, Volume 2, by Forrest & Cotton(1962).

    1) Forrest & Cotton (1963). The analyses that were conductedby Forrest & Cotton on the dikes are unknown. Thefollowing extract from the Forrest & Cotton DesignMemorandum No. 3, Embankment and General ConstructionSchedule, dated January 1963, is the only informationavailable related to the original dike design. Soil propertiesused in the stability analysis are given in Table 8.3.8.

    4-21. Dike design. A typical trial section similar to the embankmentsection was initially selected for design analysis. The stability analysis of the

    typical dike section was made, assuming the strength of the compacted materials

    to be the same as adopted for compacted materials in the main embankmentsection. The strength of the foundation material was assumed to have a cohesion

    of 1400 psf and an angle of internal friction of zero degrees. The analysis for the

    maximum section of the dike, height of about 66 feet, indicates that a factor ofsafety of 1.33 would be obtained at the end of construction condition. Adopted

    dike sections are shown on Plate I-7. The adopted section differs slightly from the

    section used in the slope stability analysis. However, the stability of the adoptedsection will obviously be equal to, or greater than, the section analyzed.

    2) Rone (1983). Stability analyses for Dike No. 2 as given inthe Rone Engineers report, Liquefaction and Stability

    Analysis, are summarized in Table 8.3.9. Soil propertiesused in the stability analysis are given in Table 8.3.10. Thestability analysis calculations are given in Figure 8.3-22.

    3) KBR (1988). Stability analyses for Dike No. 2 as given in the

    Brown & Root report, Toledo Bend Stability Analysis, datedNovember 1988, are summarized in Table 8.3.11. Soilproperties used in the stability analysis are given in Table8.3.12. Dike No. 2 plan view showing the location of thestability section used for calculations is given in Figure8.3-23. The stability analysis calculations are given in thefollowing figures:

    Rev. 0 Page 8-3212/31/2004

  • 7/23/2019 STI Section8

    74/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    Dike No. 2 Stability Steady Seepage (Figure 8.3-24) Dike No. 2 Stability Surcharge Pool (Figure 8.3-25) Dike No. 2 Stability Rapid Drawdown (Figure 8.3-26) Dike No. 2 Stability Seismic (Figure 8.3-27)

    Rev. 0 Page 8-3312/31/2004

  • 7/23/2019 STI Section8

    75/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    Rev. 0 Page 8-3412/31/2004

  • 7/23/2019 STI Section8

    76/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    Rev. 0 Page 8-3512/31/2004

  • 7/23/2019 STI Section8

    77/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    Rev. 0 Page 8-3612/31/2004

  • 7/23/2019 STI Section8

    78/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    b. Potential for Uncontrolled Seepage at Toe. (Not available)

    c. Summary of Liquefaction Analysis. (Not available)

    d. Summary of Deformation Analysis. (Not available)

    e. Procedures Used to Determine Soil Properties. (Not available)

    f. Procedures Used to Determine Soil Strengths. (Not available)

    Rev. 0 Page 8-3712/31/2004

  • 7/23/2019 STI Section8

    79/108

  • 7/23/2019 STI Section8

    80/108

  • 7/23/2019 STI Section8

    81/108

    Figure 8.3-03

    EMBANKMENT

    STABILITY ANALYSIS

  • 7/23/2019 STI Section8

    82/108

  • 7/23/2019 STI Section8

    83/108

  • 7/23/2019 STI Section8

    84/108

    Figure 8.3-06

    MAI EMBANKMENT AND

    SPILLWAY STABILITY

    SECTION LOCATIONS

  • 7/23/2019 STI Section8

    85/108

    Figure 8.3-07

    MAIN EMBANKMENT

    STEADY SEEPAGE

    STATION 116+30

  • 7/23/2019 STI Section8

    86/108

  • 7/23/2019 STI Section8

    87/108

    Figure 8.3-09

    MAI EMBANKMENT RAPID

    DRAWDOWN

    STATION 116+30

  • 7/23/2019 STI Section8

    88/108

    Figure 8.3-10

    MAIN EMBANKMENT SEISM

    STATION 116+30

  • 7/23/2019 STI Section8

    89/108

  • 7/23/2019 STI Section8

    90/108

  • 7/23/2019 STI Section8

    91/108

    Figure 8.3-13

    MAIN EMBANKMENT

    RAPID DRAWDOWN

    STATION 130+50

  • 7/23/2019 STI Section8

    92/108

  • 7/23/2019 STI Section8

    93/108

    Figure 8.3-15

    MAIN EMBANKMENT STEAD

    SEEPAGE

    STATION 151+70

  • 7/23/2019 STI Section8

    94/108

    Figure 8.3-16

    MAIN EMBANKMENT

    SURCHARGE POOL

    STATION 151+70

  • 7/23/2019 STI Section8

    95/108

    Figure 8.3-17

    MAIN EMBANKMENT

    RAPID DRWDOWN

    STATION 151+70

  • 7/23/2019 STI Section8

    96/108

    Figure 8.3-18

    MAIN EMBANKMENT

    SEISMIC

    STATION 151+70

  • 7/23/2019 STI Section8

    97/108

    Figure 8.3-19

    MAIN EMBANKMENT

    STEADY SEEPAGE

    STATION 178+20

  • 7/23/2019 STI Section8

    98/108

    Figure 8.3-20

    MAIN EMBANKMENT

    SEISMIC

    STATION 178+20

  • 7/23/2019 STI Section8

    99/108

  • 7/23/2019 STI Section8

    100/108

    Figure 8.3-22

    DIKE NO. 2

    STABILITY ANALYSES

    SUMMARY OF RESULTS

    Source: Liquefaction aStability analysis, Rone

    Engineers, Inc., 1983

  • 7/23/2019 STI Section8

    101/108

    Figure 8.3-23

    DIKE NO. 2 STABILITY

    SECTION LOCATION

  • 7/23/2019 STI Section8

    102/108

    Figure 8.3-24

    DIKE NO. 2

    STEADY SEEPAGE

  • 7/23/2019 STI Section8

    103/108

  • 7/23/2019 STI Section8

    104/108

    Figure 8.3-26

    DIKE NO. 2

    RAPID DRAWDOWN

  • 7/23/2019 STI Section8

    105/108

    Figure 8.3-27

    DIKE NO. 2

    SEISMIC

  • 7/23/2019 STI Section8

    106/108

  • 7/23/2019 STI Section8

    107/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    8.5 WATER CONVEYANCE SYSTEM

    No water conveyance systems are associated with the Toledo Bend Dam.

    Rev. 0 Page 8-3912/31/2004

  • 7/23/2019 STI Section8

    108/108

    Toledo Bend Project - STI Section 8Stability/Stress Analysis of Project Structures

    8.6 SUMMARY OF FACTORS OF SAFETY ACHIEVED

    8.6.1 Gravity Structures

    a. See Section 8.2.1 for the summary of factors of safety, materialproperties, and hydrostatic conditions assumed for the spillway.

    b. See Section 8.2.2 for the summary of factors of safety, materialproperties, and hydrostatic conditions assumed for thepowerhouse.

    8.6.2 Embankment Structures

    a. See Section 8.3.1 for the summary of factors of safety, materialproperties, and hydrostatic conditions assumed for the mainembankment.

    b. See Section 8.3.2 for the summary of factors of safety, materialproperties, and hydrostatic conditions assumed for the Dikes 1, 2,and 3.