Steering CommitteePeoria/Riverside Transit Study
February 15, 2013
Agenda
1. Definitions of Alternatives
2. Evaluation Results
3. Preferred Alternative
4. Next Steps
2/19/2013 2
Scenario Comparison
2/19/2013 3
Scenario A Scenario C Scenario D Scenario EScenario B
4,050 4,050 3,950 3,950 3,690
Existing Transit Riders
Based on technical analysis and public input, move forward with Scenario B(66th St. North to 81st & Lewis)
Trip Destinations
2/19/2013 4
Destinations for All trips on Route 105 Destinations for Work trips on Route 105
Ride Check Survey
2/19/2013 5
• April 24-26, 2012
(Tuesday – Thursday)
• 9 Routes surveyed
• 9 routes accounted for 64% of total ridership, of which 25% was on Route 105 (Peoria)
• 20% flag stops (5% of riders)
• Major stops at Pine, DAS, 41st
Street, 61st Street, and 81st
Street
• 4,000+ benefitting riders
Grouping On Board + Boardings
N Peoria + S Peoria 1,681
N Peoria + Downtown 2,819
S Peoria + Downtown 3,728
All Segments 4,114
Study Goals
• Goal 1: Improve Transit Access and Regional Mobility
• Goal 2: Support Economic Development
• Goal 3: Invest in Low-Cost, High-Impact Transit Infrastructure
• Goal 4: Build Community Support for the Value of Transit
Peoria-Riverside Transit Study Goals
2/19/2013 6
Description of Alternatives
• Bus Rapid Transit- BRT (based on MAP-21 requirement)
• Bus Rapid Transit Light – BRT Light
• Fast Bus
• Tulsa Enhanced
• Tulsa (+) Plus
• “No Build”
2/19/2013 7
BRT
2/19/2013 8
• Bus Rapid Transit (BRT) 50 min. Trip Time
BRT stops at approx. ½ mi. intervals (36 stations at 19 locations)
10-15 minute headways
5:30am-8:30pm
Monday-Sunday
Shuttle 66th St. N. to 38th St. N.
Replaces Route 105
DEDICATED LANES
TRAFFIC PRIORITY AT SIGNAL
TICKET VENDING MACHINES
NEXT BUS ARRIVAL
PEDESTRIAN CROSSINGS
SIDEWALKS
ILLUMINATION
BRT Light
2/19/2013 9
• BRT LIGHT 50 min. Trip Time
BRT Light stops at approx. ½ mi. intervals (36 stations at 19 locations)
15-20 minute headways
5:30am-8:30pm
Monday-Sunday
Shuttle 66th St. N. to 38th St. N.
Replaces Route 105
X DEDICATED LANES
TRAFFIC PRIORITY AT SIGNAL
TICKET VENDING MACHINES
NEXT BUS ARRIVAL
PEDESTRIAN CROSSINGS
SIDEWALKS
ILLUMINATION
Fast Bus
2/19/2013 10
• FAST BUS 50 min. Trip Time
Fast Bus stops at approx. ½ mi. intervals (36 stations at 19 locations)
30 minute headways (15 min w/rte 105)
5:30am-10:30pm
Monday-Saturday
Local Rt. 105 remains unchanged
X DEDICATED LANES
TRAFFIC PRIORITY AT SIGNAL
TICKET VENDING MACHINES
NEXT BUS ARRIVAL
PEDESTRIAN CROSSINGS
SIDEWALKS
ILLUMINATION
Tulsa Enhanced
2/19/2013 11
• TULSA ENHANCED 60 min. Trip Time
Stops every 2-3 Blocks (approx. 120 stops at 60 locations)
20 minute headways
5:30am-10:30pm
Monday-Saturday
Shuttle 66th St. N. to 38th St. N.
Replaces Route 105
X DEDICATED LANES
TRAFFIC PRIORITY AT SIGNAL
X TICKET VENDING MACHINES
NEXT BUS ARRIVAL
PEDESTRIAN CROSSINGS
SIDEWALKS
X ILLUMINATION
Tulsa (+) Plus
2/19/2013 12
• TULSA (+) PLUS 70 min. Trip Time
Local and Flag Stops (196 stops in 98 locations)
30 minute headways
5:30am-10:30pm
Monday-Saturday
Improves existing 105 service
X DEDICATED LANES
TRAFFIC PRIORITY AT SIGNAL
X TICKET VENDING MACHINES
X NEXT BUS ARRIVAL
X PEDESTRIAN CROSSINGS
X SIDEWALKS
X ILLUMINATION
No Build
2/19/2013 13
• NO BUILD 75 min. Trip Time
Local and Flag Stops (196 stops in 98 locations)
30 minute headways
5:30am-8:30pm
Monday-Saturday
No change for existing 105
X DEDICATED LANES
X TRAFFIC PRIORITY AT SIGNAL
X TICKET VENDING MACHINES
X NEXT BUS ARRIVAL
X PEDESTRIAN CROSSINGS
X SIDEWALKS
X ILLUMINATION
Evaluation Results
2/19/2013 14
Item Description BRT BRT LIGHT FAST BUSTULSA
ENHANCED
TULSA
PLUS
EXISTING
ROUTE 105
TRAVEL TIME
VISIBILTY AND
PERCEPTION
COMFORT AND
RELIABILITY
SAFETY
CAPITAL COST
OPERATING COST
change from
existing
FEASIBILITY -
Percent of Tulsa Transit
Annual Operating
Budget*
= 1 = 2 = 3 = 4 = 5
$ 20.6M $ 18.6M $16.0M $ 17.6M $ 12.2M $0
$ 3.1M $ 2.7M $ 2.6M $ 2.5M $1.5M $1.3M
+ $1.8M + $1.4M + $1.3M + $1.2M + $0.2MNo Change from
Existing
17% 15% 15% 14% 8% 7%
*Based on Tulsa Transit Annual Operating Budget of $18 M
Item Description BRT BRT LIGHT FAST BUSTULSA
ENHANCED
TULSA
PLUS
EXISTING
ROUTE 105
TRAVEL TIME
VISIBILTY AND
PERCEPTION
COMFORT AND
RELIABILITY
SAFETY
CAPITAL COST
OPERATING COST
change from
existing
FEASIBILITY -
Percent of Tulsa Transit
Annual Operating
Budget*
SUMMARY SCORE
Evaluation Results
15
21 24 25 20 19 18
2/19/2013
= 1 = 2 = 3 = 4 = 5
Fast Bus
2/19/2013 16
• FAST BUS 50 min. Trip Time, Stops @ 1/2 –mi spacing
30 minute headways (15 min w/Rt. 105)
5:30am-10:30pm, Monday-Saturday
X DEDICATED LANES
TRAFFIC PRIORITY AT SIGNAL
TICKET VENDING MACHINES
NEXT BUS ARRIVAL
PEDESTRIAN CROSSINGS
SIDEWALKS
ILLUMINATION
CAPITAL COST $16.0 M
OPERATING COST
change from existing
$2.6 M
+ $1.3 M
FEASIBILITY - Percent of
Annual Operating Budget15%
BRT Light
2/19/2013 17
• BRT LIGHT 50 min. Trip Time, Stops @ 1/2–mi spacing
15-20 minute headways
5:30am-10:30pm, Monday-Saturday
X DEDICATED LANES
TRAFFIC PRIORITY AT SIGNAL
TICKET VENDING MACHINES
NEXT BUS ARRIVAL
PEDESTRIAN CROSSINGS
SIDEWALKS
ILLUMINATION
CAPITAL COST $18.6 M
OPERATING COST
change from existing
$2.7 M
+ $1.4 M
FEASIBILITY - Percent of
Annual Operating Budget15%
Big Questions
• Which option do you think will be best for Tulsa?
• Why is that your favored option?
• Do you think that option will be likely to receive the needed financial support for implementation and operation?
• Is there consensus among the Steering Committee members?
2/19/2013 18
Big Questions
Wrapping up the Planning Process
• MTTA Board (Feb. 26th)
• INCOG Transportation Policy Committee (Feb. 27)
• INCOG Board (March 12)
Potential Sponsors with funding commitment
• City of Tulsa
• MTTA
• Tulsa County
2/19/2013 19
Next Steps
• Environmental Clearance
• Funding Commitments
– Local commitment first
– Federal grants?
• Design
• Implementation
2/19/2013 20