Upload
nishant-mahajan
View
20
Download
0
Embed Size (px)
DESCRIPTION
Steel Industry Overview
Citation preview
STEEL INDUSTRY
PROJECTS TODAY DECEMBER 20132266
Shaky present, but reassuring future
Steel Industry:
26-31] PT Profile_Steel Industry.qxp 12/5/2013 4:09 PM Page 26
PROJECTS TODAY DECEMBER 2013 27
teel consumption in the first six months of the
current fiscal 2013-14, remained flat, showing a
meagre year-on-year growth of 0.8 per cent. The
consumption of finished steel, the core component of the
steel industry, also showed a slight rise to 36.58 million tonne
during the April-September period of the current fiscal, as
compared to the 36.28 million tonne consumed during the
same period a year ago.
The falling demand from the two major steel consuming
sectors - Automobiles and Real Estate, led to the overall poor
performance of the steel sector. Auto industry has been
struggling with lacklustre demand since the last fiscal with no
signs of respite in the near future. In case of Real Estate,
including commercial Building sector, the problem is that of
piling up inventories, which has considerably slowed down
the launch of new projects.
At the beginning of this fiscal, World Steel Association (WSA)
had pegged India's steel demand growth rate for the year at
5.9 per cent. However, owing to the constraints faced by steel
using sectors, WSA later slashed its projection to 3.4 per cent.
Thus as compared to the 2.6 per cent growth rate seen in the
last fiscal, India's steel demand is projected to grow by 3.4 per
cent to 74 million tonne, with hopes pinned on investment
activities stirring up the auto and real estate sectors over the
coming months.
Current industry sceneThe 12th Five Year Plan (2012-2017) envisages the steel sector
touching 142.3 million tonne capacity by 2017 from the current
capacity of 85 million tonne. However, going by the current
economic slowdown, it is evident that the sector is most likely
to miss the target by a huge margin.
Lack of growth in steel demand has put downward pressure
on steel prices, forcing a majority of steel producers to defer
their expansion plans.
Apart from lacking demand pull, procedural delays in
receiving environmental clearances, land acquisition, raw
material linkages, etc have also thwarted India's capacity
addition plans through greenfield and brownfield projects.
A major blow to the steel sector came in July 2013 when global
steel giants, Arcelor Mittal and POSCO, abandoned their plans
of setting up mega steel projects in India, citing land
acquisition issues and stiff opposition from locals.
ArcelorMittal abandoned its 12 million tpa steel project in
Orissa due to inordinate delays, problems in acquiring land
S
26-31] PT Profile_Steel Industry.qxp 12/5/2013 4:09 PM Page 27
STEEL INDUSTRY
PROJECTS TODAY DECEMBER 20132288
and securing iron ore linkages. In 2006, ArcelorMittal had
signed an MoU with the Orissa state government for setting
up a 12 million tpa steel unit near Paradip in Keonjhar
district of Orissa involving an investment of `40,000 crore.
The company required around 8,000 acre of land to set up
the steel unit, a captive power unit and a township. The land
acquisition process was underway till 2009, after which the
project was put on hold due to a decline in global demand
for steel and difficulties in securing mines and other
licenses.
South Korean steelmaker, Posco, abandoned its six million
tpa finished steel project worth `32,336 crore in Gadag
district of Karnataka because of stiff protests from local and
religious communities which stalled the land acquisition
process. The project had received in-principal approvals
from State High Level Clearance Committee (SHLCC) in 2010
and had made some progress till 2011. However, since then
the land acquisition was suspended. The project was to be
supported by a 400 MW coal-based power unit.
Other steel projects, accounting for a total of 85 million
tonne of capacity, have also been stuck for want of land,
water, environment and forest clearances.
Indian producers hope that the domestic economy will
quickly regain momentum so that their growing output is
absorbed by local demand, which would obviate the need
of facing intense competition in sluggish international
markets.
Retailing steel garners focusWith demand for steel slowing down due to a slump in
construction activity in the main cities, and lower sales of
automobiles and consumer goods, some of the major steel
producers have come out with the novel idea of supplying
steel products directly to the end users through company-
owned retail shops.
One company which has taken a pioneering step towards
expanding retail outlets is JSW Steel. Over the next five
years, JSW Steel plans to open as many as 5,000 shops in
rural and semi-urban India to sell custom made steel. The
company aims to have 450 low-investment, franchisee-
model outlets by the end of FY14. The company currently
has 425 shops covering 600 districts. JSW will either open
JSW Shoppe, its organised retail brand, or a smaller format
of Shoppe, which will cater to the demand emerging from
rural India.
Essar Steel, which was the first one to enter the retail steel
segment and set up its organised steel shops, currently has
a network of 68 Essar Hypermart stores and about 300
franchisee outlets.
Rashtriya Ispat Nigam has tied up with 761 dealers across
the country to supply TMT (thermo-mechanically treated)
rebars to the rural consumers.
Jindal Steel & Power has adopted what is known as a two-
tier model comprising distributors and dealers. They have
covered all the districts in the country, through a network of
450 distributors and about 1,000 dealers.
SAIL's retail channel is expected to increase more than two
fold and handle steel products of more than one million tpa
from the current level of around 0.5 million tpa. SAIL has
about 2,900 dealers in 611 districts across the country. The
26-31] PT Profile_Steel Industry.qxp 12/5/2013 4:09 PM Page 28
PROJECTS TODAY DECEMBER 2013 29
company outlets have been given a distinct identity as
'Apna SAIL Shops' and act as retail outlets for the company,
Even while the companies are rapidly expanding their
presence in the rural landscape with their own retail chains,
these outlets still contribute only a very small part of their
total sales.
Retail steel consists mainly of construction products like
corrugated roofs, bars and rods. So far, retailing forms only
a small part of the total steel market, with roughly 25 per
cent of the big steel companies' production going to the
retail sector.
Even though retail lacks the scope of profit compared to
conventional markets, the segment is expected to offer
longer term benefits. Especially in times of economic
slowdown, the retail segment can provide the much
needed cushion for steel companies.
The rural-urban mix may not change significantly for these
companies for years to come but still these stores are
important as they help in pushing the company's brand
name deeper into rural pockets. Organised retail is
helping steel companies maintain and sustain their
volumes, and supports growth in semi urban and rural
areas providing year-on-year growth in times of slowdown
and volatility.
New Steel ProjectsIn the twelve months ended 30 September 2013, a total of
112 fresh projects worth `6,809 core were announced in the
Iron & Steel industry. Most notable amongst these was the
Hot Rolled Coils project by Uttam Galva Steels worth `1,400
crore. The three million tpa project is proposed to come up
at Kalinganagar in Jajpur district of Orissa. Among the other
large steel projects, those of Allied Strips, Bajran Steel and
Mackeil Ispat are notable ones.
Allied Strips proposes to set up a galvanized pipes project
worth `980 crore at Gollapuram in Anantpur district of
Andhra Pradesh with a capacity of 4.93 lakh tpa.
Shri Bajran Steel and Power proposes to set up a one million
tpa finished steel project at Beoharai in Shahadol district of
Madhya Pradesh. The project is estimated to cost `780
crore.
Mackeil Ispat & Forging will invest `500 crore to expand the
capacity at its steel melting shop at Durgapur in Bardhaman
district of West Bengal by 0.3 million tpa.
Growth in ProjexThe five year trend in projex investment in the Iron & Steel
industry indicates a fall in the last two years. The fresh
investment which reached its peak in 2011 at `629,614 crore,
has been failing since then to reach `482,049 crore by 2013.
Trend in project execution The trend in projects under execution suggest a revival in
project execution after a steep fall in 2012. After peaking at
`279,142 crore in 2011, the total amount of projex under
execution fell to `236,534 crore in 2012. But the under-
execution investment has improved to `272,081 crore by
September 2013.
With hopes of economic downturn bottoming out in the
second half of the current fiscal, many steel companies
have started chalking out future expansion plans.
26-31] PT Profile_Steel Industry.qxp 12/5/2013 4:09 PM Page 29
STEEL INDUSTRY
PROJECTS TODAY DECEMBER 20133300
Tata SteelTata Steel, the flagship company of Tata Group, is setting up
a six million tpa integrated steel plant at Kalinganagar
Industrial Complex near Duburi in Jajpur district of Orissa.
The company is implementing the project in phases,
wherein the first phase, estimated to cost `25,000 crore,
with a capacity build-up of three million tpa, is underway,
which is likely to be operational by March 2015. The
company is currently constructing the first module of the
project on 1,700 acre of land it has in its possession, with
plans to scale up the capacity to six million tonne as and
when it takes possession of the rest of the 3,500 acre it has
been allotted.
Tata Steel is also implementing a 50,000 tpa ferro alloys
plant and 0.4 million tonne bar mill at Gopalpur in Ganjam
district of Orissa. The project, estimated to cost `1,000 crore
is likely to be commissioned by FY15.
Jamshedpur Continuous Annealing & Processing Company,
a joint venture between Nippon Steel & Sumitomo Metal
Corporation and Tata Steel is undertaking the construction
of a 0.6 million tpa continuous annealing and processing
line. Currently work on the project is running as per
schedule.
JSW Steel JSW Steel is expanding the production capacity of its steel
unit at Vijayanagar, Toranagallu in Bellary district of
Karnataka. The capacity of 10 million tpa will be achieved in
two phases as follows:
In Phase-I - the capacity will be expanded from four
million tpa to seven million tpa
In Phase II - the capacity will be expanded from seven
million tpa to 10 million tpa
The project also includes facilities such as beneficiation
plant to be implemented in two phases; a pellet plant; and
a 300 MW captive power plant. The project is estimated to
cost `10,000 crore and is likely to be commissioned by
March 2015.
Jindal Steel & PowerJindal Steel & Power (JSPL) is setting up an integrated steel
plant with a capacity of three million tpa along with a 1,320
MW captive power plant at Patratu in Jharkhand. The
company has already commissioned 1.6 million tpa wire
and bar mill and the balance facility is likely to be
commissioned by June 2015.
JSPL is also setting up a six million tpa steel plant at
Kerjenga near Angul in Orissa. JSPL has already
commissioned 2.5 million tpa capacity out of six million
tpa in the first phase of the project. Work on the 3.5 million
tpa of the project is likely to be commissioned by
December 2015.
Posco IndiaPosco of Korea, had proposed to set up an eight million
tpa steel plant in Paradip, Orissa, for which the company
had signed an MoU in June 2005 with the state
government to set up the project, envisaging an
investment of `12,000 crore in the first phase. Due to
various regulatory delays, the company could not
commence the construction activity of the project. The
MoU expired in June 2010 and the company is pursuing its
renewal.
26-31] PT Profile_Steel Industry.qxp 12/5/2013 4:09 PM Page 30
PROJECTS TODAY DECEMBER 2013 31
As of October 2013, the company was yet to get captive iron
ore mines even though the state government has
recommended a prospecting licence for Khandadhar mines
in the Sundergarh district. Posco's other steel sector
investment is in Maharashtra, where it is setting up a cold
rolled steel plant with a capacity of two million tpa at
Mangaon in Raigarh district of the state.
Steel Authority of India (SAIL)SAIL intends to ramp up its capacity to 50 million tpa by
2025, entailing an investment of `1.5 lakh crore. SAIL is
close to achieving 24 million capacity with its ongoing
modernization and expansion work scheduled for
completion in 2014.
The investment will be funded through internal accruals
and debt.
In 2014-15, SAIL plans to spend `3,300 crore on its Bhilai
steel plant, as part of its ongoing `72,000 crore
modernisation and expansion programme to take its
capacity to 24 million tpa from 14 million tpa now. The
company also plans to invest `2,234 crore in its Rourkela
steel plant, `1,280 crore in IISCO plant, `800 crore in
Durgapur plant, and `860 crore in the Bokaro plant.
Rashtriya Ispat Nigam (RINL)The central government owned company has embarked on
a major expansion project at its plant in Viskhapatnam. The
company intends to attain 10 million tpa capacity, entailing
an investment of `20,000 crore.
RINL is currently implementing the expansion phase-wise,
wherein, under the first phase of the expansion, the
capacity is being ramped up from three to 6.3 million tonne
with an investment of `12,500 crore.
Further, RINL has also decided to invest approx `23,000
crore on the next phase of the expansion, which would give
it an additional four million tonne capacity.
Along with the first phase of expansion, which is at
stabilisation stage, RINL is also investing about `7,500 crore
on capital repairs of Blast Furnaces Krishna and Godavari
and other facilities, opting for pulverised coal injection to
substitute blast furnace coal, upgrading three converters,
and increasing techno-economic parameters of Steel Melt
Shop-1. All these initiatives will increase the capacity by one
million tonne, thereby taking the production to 7.3 million
tonne by 2014.
MescoMesco Steel has proposed to ramp up its steel making
capacity at its Kalinganagar plant in Orissa. Mesco will
invest `8,000 crore to take the capacity from the current 1.2
million tpa to 3.5 million tpa. This will be Phase-II of the
project and will be completed in five years. In Phase-I,
Mesco had invested `2,500 crore to set up the 1.2 million
tpa Kalinganagar steel plant at Jajpur district in Orissa.
OutlookPMO has set out a vision of enhancing India's steel-making
capacity to 300 million tpa by 2025 from the current 85
million tpa, which would call for investment of over $200
billion. As per the current scenario with subdued project
investment in the first two years, where even the 12th five
year plan target of 142 million tpa seems out of reach,
achieving 2025 target seems difficult. However, policy
logjam is expected to be a passing phase and surge in steel
demand following resurgence in infrastructure investment
in the remaining three years of the 12th plan and during a
more ambitious 13th Plan, would probably help a speedier
progress in steel capacity build-up.
Thus, the Steel Ministry has asked states to come up with
land and ore availability plans for setting up ultra mega
projects that would enable reaching the 300 million tpa
capacity by 2025. Talks are also proposals for setting up an
entity or special purpose vehicle (SPV) on the lines of Power
Finance Corporation (PFC) to fund mega steel projects.
The Steel Ministry has also mooted a proposal for a joint
venture (JV) between iron ore miner, NMDC and Orissa
Mining Corporation (OMC) to offer stronger iron ore supply
linkages to domestic steel producers.
The Ministry could also facilitate setting up of
manufacturing units for equipment required in steel plants
and reduce dependence on imports of such items, which
may save $120 billion in forex outflows for adding this
additional capacity.
Overall, with the per capita consumption of steel placed at
only around 51.7 kg, as against the world average of 202.70
kg, there is tremendous potential for improvement in the
domestic steel consumption given the economy's large
untapped markets, especially in rural areas, as also
investment imperative on infrastructure inadequacies.
Globally, we expect to see continued recovery in steel
demand in 2014 with the developed economies,
progressing further into positive growth and developing
economies consolidating their rates. Steel production
during January-October 2013 was 3.2 per cent higher,
compared to around 0.6 per cent in the corresponding
period of 2012.
26-31] PT Profile_Steel Industry.qxp 12/5/2013 4:09 PM Page 31