Upload
totkumars
View
223
Download
0
Embed Size (px)
Citation preview
8/8/2019 Steam Turbines and Cog en Era Ti On
1/42
Steam Turbines and CogenerationSteam Turbines and CogenerationCyrus Engineer
Director
D. P. Roy
Executive Director
8/8/2019 Steam Turbines and Cog en Era Ti On
2/42
8/8/2019 Steam Turbines and Cog en Era Ti On
3/42
Cut Costs?
How
?
8/8/2019 Steam Turbines and Cog en Era Ti On
4/42
Fixed Deposit 8%
Property in Gurgaon ! 70%
Power thru Cogeneration 80%
Plus Depreciation Benefits of 80%
CO-GENERATION 160%
Return on InvestmentReturn on Investment
8/8/2019 Steam Turbines and Cog en Era Ti On
5/42
Why is Co-Generation so Attractive?As the word CO-GEN goes, it signifies two SeparateGenerations,
co-existing at the same time.
Steam is a basic need of the Process industry.
Generating it at Higher pressure adds just 5 to 20% on the FuelCosts, but Premium Energy (Power) is produced.
5000 Kcal of Coal costs Rs 4.50
5000 Kcal of Electricity costs Rs.26.00
A common misnomer is that energy is being produced.Cogeneration does not produce energy, it merely converts Heatto Electrical energy. Therefore, higher the Energy (Superheat)within the steam, more the power.
8/8/2019 Steam Turbines and Cog en Era Ti On
6/42
NEED FOR CONEED FOR CO--GENERATIONGENERATION GRID POWER (SEB) COST HAS GONE UP.
UNCERTAIN AND UNRELIABLE POWERAVAILABILITY.
HEAVY DEMAND CHARGES PAYMENT INSPITE OFLOAD SHEDDING.
HIGH MAINTAINANCE AND RUNNING COSTS OFD.G. SETS.
HEAVY COMPETITION IN INDUSTRY LEADING TOLOWER REALISATIONS AND PROFITABILITY
HELPS CONSERVE OUR ENVIROMENT
8/8/2019 Steam Turbines and Cog en Era Ti On
7/42
ESSENTIAL REQUIREMENTS
FOR CO-GENERATION
PROCESS STEAM PRESSURE THE PROCESS STEAM PRESSURE (BACK PRESSURE) DETERMINES THE
EFFECTIVENESS OF COGEN.
LOWER THE PRESSURE REQUIREMENT, HIGHER THE POWER GENERATION, BETTER
IS THE PAYBACK.
PROCESS STEAM DEMAND THE PROCESS STEAM REQUIREMENT DETERMINES THE EFFECTIVENESS OF COGEN.
HIGHER THE REQUIREMENT, BETTER IS THE PAYBACK.
POWER REQUIREMENT IN PLANT THE POWER DEMAND WILL DETERMINE THE FOLLOWING :-
BOILER PRESSURE
TYPE OF POWER GENERATOR
8/8/2019 Steam Turbines and Cog en Era Ti On
8/42
8/8/2019 Steam Turbines and Cog en Era Ti On
9/42
TURBO GENSET SELECTIONTURBO GENSET SELECTION
FACTORSFACTORS
TURBINE SELECTION FACTORS STEAM FLOW MAX, AVERAGE AND DESIGN
BACK PRESSURE
POWER OUTPUT ACHIEVABLE
POWER GENERATOR SELECTION FACTORS STEAM FLOW FLUCTUATIONS
POWER LOAD FLUCTUATIONS
TURBINE EFFICIENCY SPECIFIC STEAM TO POWER RATIO
TURNDOWN RATIO
8/8/2019 Steam Turbines and Cog en Era Ti On
10/42
8/8/2019 Steam Turbines and Cog en Era Ti On
11/42
SELECTION OFSELECTION OF
GENERATION MODEGENERATION MODE
STAND ALONEISLAND SYSTEM SYNCHRONISEDGENERATIONIDEAL SYSTEM WHERE STEAM AND POWERLOADS ARE CONSTANT. POWER SPURTSFLUCTUATION MAY NEED STEAM VENTING.
THE ONLY SUCCESSFUL SYSTEM ONFLUCTUATION STEAM AND POWER LOADS
THE SYSTEM IS SUITABLE WHERE POWERREQUIRED IS LESS THAN OR EQUAL TOCOGENERATED POWER
WHENEVER POWER DEMAND FAREXCEEDS COGEN POSSIBILITY
WILL OPERATE EVEN WHEN POWER FROM
SEB FAILS
NEEDS SYNCHRONISATION FROM SEB OR
D.G. SET TO OPERATE. TRIPS WHEN GRIDPOWER FAILS.
8/8/2019 Steam Turbines and Cog en Era Ti On
12/42
VARIATION OF POWER OUTPUTVARIATION OF POWER OUTPUT
WITH CHANGE IN BACK PRESSUREWITH CHANGE IN BACK PRESSURE
TECHNICAL
PARAMETERS
BACK
PRESSURE3 Kg/cm2 (g)
BACK
PRESSURE4 Kg/cm2 (g)
BACK
PRESSURE5 Kg/cm2 (g)
Turbine Inputconditions
10 TPH
33 Kg/cm2
g)
10 TPH
33 Kg/cm2
g)
10 TPH
33 Kg/cm2
g)
Process SteamPressure
(Back Pressure)
3 Kg/cm2 (g) 4 Kg/cm2 (g) 5 Kg/cm2 (g)
Power outputfrom turbine
600 KW 540 KW 500 KW
8/8/2019 Steam Turbines and Cog en Era Ti On
13/42
VARIATION OF POWER OUTPUT WITHVARIATION OF POWER OUTPUT WITH
CHANGE IN INLET STEAM CONDITIONSCHANGE IN INLET STEAM CONDITIONS
TECHNICAL
PARAMETERS
6 TPH
9 Kg/cm2(g)
6 TPH
21 Kg/cm2(g)
6 TPH
21 Kg/cm2 (g)
6 TPH
33 Kg/cm2(g)
SteamTemperature
2500C
3 Kg/cm2 (g)
145 KW
Dry - 1900C
Saturated 3300C 3500C
Process SteamPressure
(Back Pressure)
3 Kg/cm2 (g) 3 Kg/cm2 (g) 3 Kg/cm2 (g)
Power output
from turbine
220 KW 300 KW 340 KW
Quality ofexhaust Steam
7 % Wet Dry - 2100C Dry - 2100C
8/8/2019 Steam Turbines and Cog en Era Ti On
14/42
VARIATION OF POWER OUTPUT WITHVARIATION OF POWER OUTPUT WITH
CHANGE IN INLET STEAM CONDITIONSCHANGE IN INLET STEAM CONDITIONS
TECHNICAL
PARAMETERS
20 TPH
32 Kg/cm2
(g)
20 TPH
42 Kg/cm2
(g)
6 TPH
63 Kg/cm2
(g)
SteamTemperature
3500C
3 Kg/cm2 (g)
1645 KW
4200C 4800C
Process SteamPressure
(Back Pressure)
3 Kg/cm2 (g) 3 Kg/cm2 (g)
Power output fromturbine
2060 KW 2630 KW
8/8/2019 Steam Turbines and Cog en Era Ti On
15/42
THUMB RULE ON BACK PRESSURETHUMB RULE ON BACK PRESSURE
Use Lowest Possible Back Pressure !
It saves you a lot on Installation and Fuelcosts.
When it comes to Power Produced,
Increasing Back Pressure by 1 Kg/cm2 is the
equivalent of increasing Boiler Steampressure by about 6 Kg/cm2
8/8/2019 Steam Turbines and Cog en Era Ti On
16/42
ADVANTAGES WHEN
PURCHASING FROMCOGEN PACKAGE
SUPPLIERS
1. One point source for both systems
2. Proper System integration with Process
3. One Point Guarantee and Responsibility.
4. Complete Steam piping design.
5. Electrification and Grid Synchronisationassistance.
6. One Point for Boiler and Turbine Service.
8/8/2019 Steam Turbines and Cog en Era Ti On
17/42
Case Study Newsprint Paper MillDamanganga Paper Mills
A single machine produces 140 Tons of Newsprint per day.
A Boiler of 12 Ton at 21 Kg pressure operates on Plastic and otherwastes (With proper Flue Gas Scrubbing Plant)
The turbine produces 9000 units on an average per day on a steam load
of 200 Tons/day.
Back pressure is maintained at 2.5 to 3 Kg.
Power is generated at 80 paise per unit compared to Grid power at Rs.
5.20 per unit.
Therefore the saving is Rs.39,000 per day.
In operation for the last 15 months, it has saved Damanganga Paper Millsover Rs. 1.75 Crores till date.
8/8/2019 Steam Turbines and Cog en Era Ti On
18/42
Damanganga Paper MillTurbine Installation
8/8/2019 Steam Turbines and Cog en Era Ti On
19/42
Case Study Best Paper Mills, Vapi.
A single machine produces 80 Tons of Kraft Paper per day.
A Boiler of 12 Ton at 32 Kg pressure operates on Coal
The turbine produces 8000 units on an average per day on a steamload of 160 Tons/day.
Back pressure is maintained at 2.5 to 3 Kg.
Power is generated at 1.40 paise per unit compared to Grid powerat Rs. 5.20 per unit.
Therefore the saving is Rs.30,000 per day.
In operation for the last 12 months, it has saved Best Paper Millsover Rs. One Crore till date.
8/8/2019 Steam Turbines and Cog en Era Ti On
20/42
Best Paper MillInstallation Photos
8/8/2019 Steam Turbines and Cog en Era Ti On
21/42
Case Study TextilesSangam Processors, Bhilwara
The unit processes Synthetic Cloth (Suitings)
The connected machinery includes 40 Jiggers, 11 Jet Dyeing, 3 OpenDecadising, 3 Rotary machines, 4 Drying ranges, KD, Zero-Zero, SuperFinish and Hydrolic Jigger.
The turbine produces 7000 units on an average per day on a steam loadof 1,35,000 Kg/day.
Back pressure is maintained at 2.5 to 3 Kg.
The Boiler consumes 41 Tons of Lignite or 24 Tons of imported Coal perday.
Power is generated at Rs. 1.50 per unit. Therefore the saving isRs.21,000 per day.
In operation for the last 16 months, it has saved Sangam Processorsover a Rs. One Crore till date.
S P Bhil
8/8/2019 Steam Turbines and Cog en Era Ti On
22/42
Sangam Processors, BhilwaraInstallation Photos
Case Study Calcium Carbonate
8/8/2019 Steam Turbines and Cog en Era Ti On
23/42
Case Study Calcium CarbonateSagar Lime Chem, Saharanpur
There are 6 Drying Cylinders which consume steam at 2 Kg pressure.
There is no electrical connection with the Grid. The entire power load of 300 Amps is met by the steam turbine.
The turbine produces 4500 units on an average per day on a steam loadof 72 Tons/day.
Back pressure is maintained at 2 to 2.5 Kg.
Power is generated at Rs. 1.50 per unit.
Therefore the saving on Grid Power is Rs.15,000 per day or Rs. 50
Lacs per year.
In UP there is very poor availability of Power and most units operate DGSets, where power generation cost Rs. 10 per unit. In such case thesavings would be Rs. 38000 per day or Rs. 1.3 Crores per year.
The additional investment for cogeneration was just 50 Lacs!
8/8/2019 Steam Turbines and Cog en Era Ti On
24/42
Sagar Lime Chem, Saharanpur
Installation Photos
Case Study Rice Mill
8/8/2019 Steam Turbines and Cog en Era Ti On
25/42
Case Study Rice MillGiriraj Rice Mill, Burdwan
The plant processes 200 Tons of Paddy per day.
IBL modified the Plant to suit the Cogen system.
There is no electrical connection with the Grid.Power load of 380 KW is met by the Back Pressure Steam turbine.A 500 KW condensing Turbine meets the requirement of the Cold Store.
The Back pressure turbine produces 8500 units on an average per day on asteam load of 190 Tons/day. Back Pressure Turbine Power is generated at80 paise per unit.
The condensing Turbine Produces 8000 units at Rs. 3.50 per Unit
The average cost of Power is just Rs 2.10 per unit.
Therefore the saving on Grid Power is Rs.40,000 per day or Rs. 120 Lacs
per year.
The additional investment for Turbo Generation was Rs. 190 Lacs
8/8/2019 Steam Turbines and Cog en Era Ti On
26/42
Giriraj Rice Mill, Burdwan
Installation Photos
8/8/2019 Steam Turbines and Cog en Era Ti On
27/42
Unique Low Pressure Application
Cochin Kagaz, KeralaCochin Kagaz was
operating a 10 Ton Husk
fired Boiler at 10 Kg/cm2
pressure.
IBL installed a Superheater
and Back PressureTurbine.
Power now generated 200 KWH (4.8 MW per day)
Steam Inlet pressure to turbine 9 Kg/cm2
Investment Rs. 50 Lacs, Savings Rs. 40 lacs / year
Turbine is in operation for last 3 years.
How Power Generation cost is calculated
8/8/2019 Steam Turbines and Cog en Era Ti On
28/42
CO GEN SYSTEM 32 KG LOW PRESS SYS
Process Steam Requirement 7500 Kg/hr 7500 Kg/hr
Process Steam Pressure 3.5 Kg/cm2 10.5 Kg/cm2Cost of Equipment 17000000 Rs. 8500000 Rs.
ECONOMICS OF CO GENERATION
Fuel Consumption with Coal 5000 Kcal/kg 1207 Kg/hr 1085 Kg/hr
Extra Fuel Consumption for Power Generation 123 Kg/hr
Cost of Fuel per Kg 3.50 Rs/KgAdditional Fuel Cost 429 Rs/hr
Additional Fuel Cost per Day 10295 Rs/day
Power Generated at 7.5 TPH Load 420 KW
Extra power for Cogen Boiler 30 KW
Power available to Plant 390 KWPower Produced Per Day 9360 KW/Day
Basic Cost of Power due to Fuel Only 1.10 Rs/Unit
Cost Of SEB Power 4.50 Rs/Unit
Savings in power per unit 3.40 Rs./unit
Savings in power per day 31825 Rs/day
Savings in Power Generated per month 954746 Rs/month
Savings in Power Generated per year 11138707 Rs/year
DIFFERENTIAL COST OF COGEN
PROJECT 8500000 Rs.
Interest Cost @ 12% per day 2795 per day
Interest Cost @ 12% per unit 0.30 Rs./unit
Final Power Cost 1.40 Rs./unit
Payback Period 1 year
How Power Generation cost is calculated
8/8/2019 Steam Turbines and Cog en Era Ti On
29/42
About
IB Turbo was incubated by Industrial Boilers Ltd. to
cater to the requirement of Small Steam Turbines in2001.
IB Turbo started manufacturing turbines in 2002.
Today, IBT Turbines are in operation in all parts ofIndia as well as in Singapore, Thailand and Vietnam
8/8/2019 Steam Turbines and Cog en Era Ti On
30/42
IB Turbo Range of Steam Turbines
Model BT 4 & BT - 6
Type Back Pressure Single Stage. Operating range 100 to 800 KW
Inlet Pressure 8.5 Kg/cm2 to 37 Kg/cm2
Inlet Steam temp. range Saturated at 99% Dryness to 3800C
Back Pressure 1.1 Ata to 5 Kg/cm2
Power Outputs available
Induction Generation
Alternator Based Synchronised Generation
Alternator Based Stand Alone
Status 100 Turbines in Operation
8/8/2019 Steam Turbines and Cog en Era Ti On
31/42
Model MBT 6
Type Bleed + Back PressureTurbine Operating range 1 to 3 MW
Inlet Pressure 33 Kg/cm2 to 63 Kg/cm2 Inlet Steam temp. Superheated 300 - 4800C Back Pressure Upto 9 Kg/cm2
Model BCT 6
8/8/2019 Steam Turbines and Cog en Era Ti On
32/42
Model BCT 6 Type Bleed + Condensing Turbine Operating range 1 to 3 MW Inlet Pressure 8.5 Kg/cm2 to 63 Kg/cm2
Inlet Steam temp. Superheated 300 - 4500C Back Pressure 1.1 Ata to 9 Kg/cm2
Power Outputs available Alternator Based Stand AloneAlternator Based Grid Parallel
8/8/2019 Steam Turbines and Cog en Era Ti On
33/42
Induction Generator with BT- 4 Turbine
8/8/2019 Steam Turbines and Cog en Era Ti On
34/42
BT- 6 Turbine with Alternator (600 KW)
Ashoka Distillery, Hatim
AGROPAK-TD
8/8/2019 Steam Turbines and Cog en Era Ti On
35/42
AGROPAK TDThe Power Generation
High Pressure FBC Boiler
Built-in Superheater Choice of Fuel Feeding Systems
- In Bed for Coal, Lignite, Saw Dust.
- Over Bed for Rice Husk.
Bio Gas Compatible. Microprocessor Controlled Fuel Feeder
Water cooled, Suvega Tube Waterwall.
Packaged Concept, Minimum welding atInstallation site. No Expansion of tubes
Steady Steam Pressure and Temperature forcritical turbine applications.
Loaded with high efficiency drum internals.
8/8/2019 Steam Turbines and Cog en Era Ti On
36/42
BI-DRUM
The Power GenerationHigh Pressure FBC Boiler
High Efficiency Boiler.
Built-in Superheater
Choice of Fuel Feeding Systems
- In Bed for Coal, Lignite, Saw Dust.- Over Bed for Rice Husk.
Bio Gas Compatible.
Microprocessor Controlled Fuel Feeder
Loaded with high efficiency drum internals.
8/8/2019 Steam Turbines and Cog en Era Ti On
37/42
Round the year availability
Low Cost of Fuel
Ease of Operation
Less Pollution Less Labour Requirement
Low Power Consumption
Essentials for selection of Boiler fuelsFuels appropriate for
Cogeneration in Indian Context
Coal
Lignite
BagasseSaw Dust
Rice Husk
Natural GasAgro Residues
Industrial wastes
H h d i
8/8/2019 Steam Turbines and Cog en Era Ti On
38/42
How much does it cost to
Generate Power ?
Thru Back Pressure Turbine Between Rs. 0.80 per unit to Rs. 1.50 per unit.
Thru Condensing Turbine Between Rs. 3.00 per unit to Rs. 4.50 per unit.
Thru Bleed + Condensing Turbine Between Rs. 2.50 per unit to Rs. 4.00 per unit.
8/8/2019 Steam Turbines and Cog en Era Ti On
39/42
Successful Industrial ApplicationsSynchronised Generation
Paper
Textiles Food Processing Breweries
Malt
Stand Alone Generation Distilleries Rice Calcium Carbonate Solvent extraction
8/8/2019 Steam Turbines and Cog en Era Ti On
40/42
WORLDWIDE SUPPORTUSA (Sold as Moss Boilers)Belgium (Sold as BIC)Malaysia (Sold as Visdamax)
ThailandKenyaNepalSri Lanka
TurkeyAustraliaBangladeshMyanmar
8/8/2019 Steam Turbines and Cog en Era Ti On
41/42
NATIONWIDE SUPPORTIBL OFFICES AND REPRESENTATIVESMUMBAI
VAPINEW DELHIKOLKATTACHENNAI
HYDERABADAHMEDABADSURATBHARUCH
PANIPATAMRITSARINDOREBHILWARA
PALI
8/8/2019 Steam Turbines and Cog en Era Ti On
42/42
See us at www.indboilers.com