Steam Turbines and Cog en Era Ti On

Embed Size (px)

Citation preview

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    1/42

    Steam Turbines and CogenerationSteam Turbines and CogenerationCyrus Engineer

    Director

    D. P. Roy

    Executive Director

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    2/42

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    3/42

    Cut Costs?

    How

    ?

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    4/42

    Fixed Deposit 8%

    Property in Gurgaon ! 70%

    Power thru Cogeneration 80%

    Plus Depreciation Benefits of 80%

    CO-GENERATION 160%

    Return on InvestmentReturn on Investment

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    5/42

    Why is Co-Generation so Attractive?As the word CO-GEN goes, it signifies two SeparateGenerations,

    co-existing at the same time.

    Steam is a basic need of the Process industry.

    Generating it at Higher pressure adds just 5 to 20% on the FuelCosts, but Premium Energy (Power) is produced.

    5000 Kcal of Coal costs Rs 4.50

    5000 Kcal of Electricity costs Rs.26.00

    A common misnomer is that energy is being produced.Cogeneration does not produce energy, it merely converts Heatto Electrical energy. Therefore, higher the Energy (Superheat)within the steam, more the power.

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    6/42

    NEED FOR CONEED FOR CO--GENERATIONGENERATION GRID POWER (SEB) COST HAS GONE UP.

    UNCERTAIN AND UNRELIABLE POWERAVAILABILITY.

    HEAVY DEMAND CHARGES PAYMENT INSPITE OFLOAD SHEDDING.

    HIGH MAINTAINANCE AND RUNNING COSTS OFD.G. SETS.

    HEAVY COMPETITION IN INDUSTRY LEADING TOLOWER REALISATIONS AND PROFITABILITY

    HELPS CONSERVE OUR ENVIROMENT

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    7/42

    ESSENTIAL REQUIREMENTS

    FOR CO-GENERATION

    PROCESS STEAM PRESSURE THE PROCESS STEAM PRESSURE (BACK PRESSURE) DETERMINES THE

    EFFECTIVENESS OF COGEN.

    LOWER THE PRESSURE REQUIREMENT, HIGHER THE POWER GENERATION, BETTER

    IS THE PAYBACK.

    PROCESS STEAM DEMAND THE PROCESS STEAM REQUIREMENT DETERMINES THE EFFECTIVENESS OF COGEN.

    HIGHER THE REQUIREMENT, BETTER IS THE PAYBACK.

    POWER REQUIREMENT IN PLANT THE POWER DEMAND WILL DETERMINE THE FOLLOWING :-

    BOILER PRESSURE

    TYPE OF POWER GENERATOR

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    8/42

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    9/42

    TURBO GENSET SELECTIONTURBO GENSET SELECTION

    FACTORSFACTORS

    TURBINE SELECTION FACTORS STEAM FLOW MAX, AVERAGE AND DESIGN

    BACK PRESSURE

    POWER OUTPUT ACHIEVABLE

    POWER GENERATOR SELECTION FACTORS STEAM FLOW FLUCTUATIONS

    POWER LOAD FLUCTUATIONS

    TURBINE EFFICIENCY SPECIFIC STEAM TO POWER RATIO

    TURNDOWN RATIO

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    10/42

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    11/42

    SELECTION OFSELECTION OF

    GENERATION MODEGENERATION MODE

    STAND ALONEISLAND SYSTEM SYNCHRONISEDGENERATIONIDEAL SYSTEM WHERE STEAM AND POWERLOADS ARE CONSTANT. POWER SPURTSFLUCTUATION MAY NEED STEAM VENTING.

    THE ONLY SUCCESSFUL SYSTEM ONFLUCTUATION STEAM AND POWER LOADS

    THE SYSTEM IS SUITABLE WHERE POWERREQUIRED IS LESS THAN OR EQUAL TOCOGENERATED POWER

    WHENEVER POWER DEMAND FAREXCEEDS COGEN POSSIBILITY

    WILL OPERATE EVEN WHEN POWER FROM

    SEB FAILS

    NEEDS SYNCHRONISATION FROM SEB OR

    D.G. SET TO OPERATE. TRIPS WHEN GRIDPOWER FAILS.

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    12/42

    VARIATION OF POWER OUTPUTVARIATION OF POWER OUTPUT

    WITH CHANGE IN BACK PRESSUREWITH CHANGE IN BACK PRESSURE

    TECHNICAL

    PARAMETERS

    BACK

    PRESSURE3 Kg/cm2 (g)

    BACK

    PRESSURE4 Kg/cm2 (g)

    BACK

    PRESSURE5 Kg/cm2 (g)

    Turbine Inputconditions

    10 TPH

    33 Kg/cm2

    g)

    10 TPH

    33 Kg/cm2

    g)

    10 TPH

    33 Kg/cm2

    g)

    Process SteamPressure

    (Back Pressure)

    3 Kg/cm2 (g) 4 Kg/cm2 (g) 5 Kg/cm2 (g)

    Power outputfrom turbine

    600 KW 540 KW 500 KW

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    13/42

    VARIATION OF POWER OUTPUT WITHVARIATION OF POWER OUTPUT WITH

    CHANGE IN INLET STEAM CONDITIONSCHANGE IN INLET STEAM CONDITIONS

    TECHNICAL

    PARAMETERS

    6 TPH

    9 Kg/cm2(g)

    6 TPH

    21 Kg/cm2(g)

    6 TPH

    21 Kg/cm2 (g)

    6 TPH

    33 Kg/cm2(g)

    SteamTemperature

    2500C

    3 Kg/cm2 (g)

    145 KW

    Dry - 1900C

    Saturated 3300C 3500C

    Process SteamPressure

    (Back Pressure)

    3 Kg/cm2 (g) 3 Kg/cm2 (g) 3 Kg/cm2 (g)

    Power output

    from turbine

    220 KW 300 KW 340 KW

    Quality ofexhaust Steam

    7 % Wet Dry - 2100C Dry - 2100C

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    14/42

    VARIATION OF POWER OUTPUT WITHVARIATION OF POWER OUTPUT WITH

    CHANGE IN INLET STEAM CONDITIONSCHANGE IN INLET STEAM CONDITIONS

    TECHNICAL

    PARAMETERS

    20 TPH

    32 Kg/cm2

    (g)

    20 TPH

    42 Kg/cm2

    (g)

    6 TPH

    63 Kg/cm2

    (g)

    SteamTemperature

    3500C

    3 Kg/cm2 (g)

    1645 KW

    4200C 4800C

    Process SteamPressure

    (Back Pressure)

    3 Kg/cm2 (g) 3 Kg/cm2 (g)

    Power output fromturbine

    2060 KW 2630 KW

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    15/42

    THUMB RULE ON BACK PRESSURETHUMB RULE ON BACK PRESSURE

    Use Lowest Possible Back Pressure !

    It saves you a lot on Installation and Fuelcosts.

    When it comes to Power Produced,

    Increasing Back Pressure by 1 Kg/cm2 is the

    equivalent of increasing Boiler Steampressure by about 6 Kg/cm2

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    16/42

    ADVANTAGES WHEN

    PURCHASING FROMCOGEN PACKAGE

    SUPPLIERS

    1. One point source for both systems

    2. Proper System integration with Process

    3. One Point Guarantee and Responsibility.

    4. Complete Steam piping design.

    5. Electrification and Grid Synchronisationassistance.

    6. One Point for Boiler and Turbine Service.

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    17/42

    Case Study Newsprint Paper MillDamanganga Paper Mills

    A single machine produces 140 Tons of Newsprint per day.

    A Boiler of 12 Ton at 21 Kg pressure operates on Plastic and otherwastes (With proper Flue Gas Scrubbing Plant)

    The turbine produces 9000 units on an average per day on a steam load

    of 200 Tons/day.

    Back pressure is maintained at 2.5 to 3 Kg.

    Power is generated at 80 paise per unit compared to Grid power at Rs.

    5.20 per unit.

    Therefore the saving is Rs.39,000 per day.

    In operation for the last 15 months, it has saved Damanganga Paper Millsover Rs. 1.75 Crores till date.

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    18/42

    Damanganga Paper MillTurbine Installation

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    19/42

    Case Study Best Paper Mills, Vapi.

    A single machine produces 80 Tons of Kraft Paper per day.

    A Boiler of 12 Ton at 32 Kg pressure operates on Coal

    The turbine produces 8000 units on an average per day on a steamload of 160 Tons/day.

    Back pressure is maintained at 2.5 to 3 Kg.

    Power is generated at 1.40 paise per unit compared to Grid powerat Rs. 5.20 per unit.

    Therefore the saving is Rs.30,000 per day.

    In operation for the last 12 months, it has saved Best Paper Millsover Rs. One Crore till date.

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    20/42

    Best Paper MillInstallation Photos

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    21/42

    Case Study TextilesSangam Processors, Bhilwara

    The unit processes Synthetic Cloth (Suitings)

    The connected machinery includes 40 Jiggers, 11 Jet Dyeing, 3 OpenDecadising, 3 Rotary machines, 4 Drying ranges, KD, Zero-Zero, SuperFinish and Hydrolic Jigger.

    The turbine produces 7000 units on an average per day on a steam loadof 1,35,000 Kg/day.

    Back pressure is maintained at 2.5 to 3 Kg.

    The Boiler consumes 41 Tons of Lignite or 24 Tons of imported Coal perday.

    Power is generated at Rs. 1.50 per unit. Therefore the saving isRs.21,000 per day.

    In operation for the last 16 months, it has saved Sangam Processorsover a Rs. One Crore till date.

    S P Bhil

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    22/42

    Sangam Processors, BhilwaraInstallation Photos

    Case Study Calcium Carbonate

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    23/42

    Case Study Calcium CarbonateSagar Lime Chem, Saharanpur

    There are 6 Drying Cylinders which consume steam at 2 Kg pressure.

    There is no electrical connection with the Grid. The entire power load of 300 Amps is met by the steam turbine.

    The turbine produces 4500 units on an average per day on a steam loadof 72 Tons/day.

    Back pressure is maintained at 2 to 2.5 Kg.

    Power is generated at Rs. 1.50 per unit.

    Therefore the saving on Grid Power is Rs.15,000 per day or Rs. 50

    Lacs per year.

    In UP there is very poor availability of Power and most units operate DGSets, where power generation cost Rs. 10 per unit. In such case thesavings would be Rs. 38000 per day or Rs. 1.3 Crores per year.

    The additional investment for cogeneration was just 50 Lacs!

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    24/42

    Sagar Lime Chem, Saharanpur

    Installation Photos

    Case Study Rice Mill

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    25/42

    Case Study Rice MillGiriraj Rice Mill, Burdwan

    The plant processes 200 Tons of Paddy per day.

    IBL modified the Plant to suit the Cogen system.

    There is no electrical connection with the Grid.Power load of 380 KW is met by the Back Pressure Steam turbine.A 500 KW condensing Turbine meets the requirement of the Cold Store.

    The Back pressure turbine produces 8500 units on an average per day on asteam load of 190 Tons/day. Back Pressure Turbine Power is generated at80 paise per unit.

    The condensing Turbine Produces 8000 units at Rs. 3.50 per Unit

    The average cost of Power is just Rs 2.10 per unit.

    Therefore the saving on Grid Power is Rs.40,000 per day or Rs. 120 Lacs

    per year.

    The additional investment for Turbo Generation was Rs. 190 Lacs

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    26/42

    Giriraj Rice Mill, Burdwan

    Installation Photos

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    27/42

    Unique Low Pressure Application

    Cochin Kagaz, KeralaCochin Kagaz was

    operating a 10 Ton Husk

    fired Boiler at 10 Kg/cm2

    pressure.

    IBL installed a Superheater

    and Back PressureTurbine.

    Power now generated 200 KWH (4.8 MW per day)

    Steam Inlet pressure to turbine 9 Kg/cm2

    Investment Rs. 50 Lacs, Savings Rs. 40 lacs / year

    Turbine is in operation for last 3 years.

    How Power Generation cost is calculated

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    28/42

    CO GEN SYSTEM 32 KG LOW PRESS SYS

    Process Steam Requirement 7500 Kg/hr 7500 Kg/hr

    Process Steam Pressure 3.5 Kg/cm2 10.5 Kg/cm2Cost of Equipment 17000000 Rs. 8500000 Rs.

    ECONOMICS OF CO GENERATION

    Fuel Consumption with Coal 5000 Kcal/kg 1207 Kg/hr 1085 Kg/hr

    Extra Fuel Consumption for Power Generation 123 Kg/hr

    Cost of Fuel per Kg 3.50 Rs/KgAdditional Fuel Cost 429 Rs/hr

    Additional Fuel Cost per Day 10295 Rs/day

    Power Generated at 7.5 TPH Load 420 KW

    Extra power for Cogen Boiler 30 KW

    Power available to Plant 390 KWPower Produced Per Day 9360 KW/Day

    Basic Cost of Power due to Fuel Only 1.10 Rs/Unit

    Cost Of SEB Power 4.50 Rs/Unit

    Savings in power per unit 3.40 Rs./unit

    Savings in power per day 31825 Rs/day

    Savings in Power Generated per month 954746 Rs/month

    Savings in Power Generated per year 11138707 Rs/year

    DIFFERENTIAL COST OF COGEN

    PROJECT 8500000 Rs.

    Interest Cost @ 12% per day 2795 per day

    Interest Cost @ 12% per unit 0.30 Rs./unit

    Final Power Cost 1.40 Rs./unit

    Payback Period 1 year

    How Power Generation cost is calculated

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    29/42

    About

    IB Turbo was incubated by Industrial Boilers Ltd. to

    cater to the requirement of Small Steam Turbines in2001.

    IB Turbo started manufacturing turbines in 2002.

    Today, IBT Turbines are in operation in all parts ofIndia as well as in Singapore, Thailand and Vietnam

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    30/42

    IB Turbo Range of Steam Turbines

    Model BT 4 & BT - 6

    Type Back Pressure Single Stage. Operating range 100 to 800 KW

    Inlet Pressure 8.5 Kg/cm2 to 37 Kg/cm2

    Inlet Steam temp. range Saturated at 99% Dryness to 3800C

    Back Pressure 1.1 Ata to 5 Kg/cm2

    Power Outputs available

    Induction Generation

    Alternator Based Synchronised Generation

    Alternator Based Stand Alone

    Status 100 Turbines in Operation

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    31/42

    Model MBT 6

    Type Bleed + Back PressureTurbine Operating range 1 to 3 MW

    Inlet Pressure 33 Kg/cm2 to 63 Kg/cm2 Inlet Steam temp. Superheated 300 - 4800C Back Pressure Upto 9 Kg/cm2

    Model BCT 6

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    32/42

    Model BCT 6 Type Bleed + Condensing Turbine Operating range 1 to 3 MW Inlet Pressure 8.5 Kg/cm2 to 63 Kg/cm2

    Inlet Steam temp. Superheated 300 - 4500C Back Pressure 1.1 Ata to 9 Kg/cm2

    Power Outputs available Alternator Based Stand AloneAlternator Based Grid Parallel

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    33/42

    Induction Generator with BT- 4 Turbine

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    34/42

    BT- 6 Turbine with Alternator (600 KW)

    Ashoka Distillery, Hatim

    AGROPAK-TD

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    35/42

    AGROPAK TDThe Power Generation

    High Pressure FBC Boiler

    Built-in Superheater Choice of Fuel Feeding Systems

    - In Bed for Coal, Lignite, Saw Dust.

    - Over Bed for Rice Husk.

    Bio Gas Compatible. Microprocessor Controlled Fuel Feeder

    Water cooled, Suvega Tube Waterwall.

    Packaged Concept, Minimum welding atInstallation site. No Expansion of tubes

    Steady Steam Pressure and Temperature forcritical turbine applications.

    Loaded with high efficiency drum internals.

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    36/42

    BI-DRUM

    The Power GenerationHigh Pressure FBC Boiler

    High Efficiency Boiler.

    Built-in Superheater

    Choice of Fuel Feeding Systems

    - In Bed for Coal, Lignite, Saw Dust.- Over Bed for Rice Husk.

    Bio Gas Compatible.

    Microprocessor Controlled Fuel Feeder

    Loaded with high efficiency drum internals.

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    37/42

    Round the year availability

    Low Cost of Fuel

    Ease of Operation

    Less Pollution Less Labour Requirement

    Low Power Consumption

    Essentials for selection of Boiler fuelsFuels appropriate for

    Cogeneration in Indian Context

    Coal

    Lignite

    BagasseSaw Dust

    Rice Husk

    Natural GasAgro Residues

    Industrial wastes

    H h d i

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    38/42

    How much does it cost to

    Generate Power ?

    Thru Back Pressure Turbine Between Rs. 0.80 per unit to Rs. 1.50 per unit.

    Thru Condensing Turbine Between Rs. 3.00 per unit to Rs. 4.50 per unit.

    Thru Bleed + Condensing Turbine Between Rs. 2.50 per unit to Rs. 4.00 per unit.

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    39/42

    Successful Industrial ApplicationsSynchronised Generation

    Paper

    Textiles Food Processing Breweries

    Malt

    Stand Alone Generation Distilleries Rice Calcium Carbonate Solvent extraction

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    40/42

    WORLDWIDE SUPPORTUSA (Sold as Moss Boilers)Belgium (Sold as BIC)Malaysia (Sold as Visdamax)

    ThailandKenyaNepalSri Lanka

    TurkeyAustraliaBangladeshMyanmar

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    41/42

    NATIONWIDE SUPPORTIBL OFFICES AND REPRESENTATIVESMUMBAI

    VAPINEW DELHIKOLKATTACHENNAI

    HYDERABADAHMEDABADSURATBHARUCH

    PANIPATAMRITSARINDOREBHILWARA

    PALI

  • 8/8/2019 Steam Turbines and Cog en Era Ti On

    42/42

    See us at www.indboilers.com