241
Steam Generator Integrity Assessment Guidelines Revision 2 Non-Proprietary Version 1012987 Final Report, July 2006 EPRI Project Manager E. Fuller ELECTRIC POWER RESEARCH INSTITUTE 3420 Hillview Avenue, Palo Alto, California 94304-1395 - PO Box 10412, Palo Alto, California 94303-0813 - USA 800.313.3774 650.855.2121 [email protected] - www.epd.com

Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

  • Upload
    others

  • View
    33

  • Download
    5

Embed Size (px)

Citation preview

Page 1: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Steam Generator IntegrityAssessment GuidelinesRevision 2Non-Proprietary Version

1012987

Final Report, July 2006

EPRI Project ManagerE. Fuller

ELECTRIC POWER RESEARCH INSTITUTE3420 Hillview Avenue, Palo Alto, California 94304-1395 - PO Box 10412, Palo Alto, California 94303-0813 - USA

800.313.3774 • 650.855.2121 • [email protected] - www.epd.com

Page 2: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES

THIS DOCUMENT WAS PREPARED BY THE ORGANIZATION(S) NAMED BELOW AS ANACCOUNT OF WORK SPONSORED OR COSPONSORED BY THE ELECTRIC POWER RESEARCH LINSTITUTE. INC. (EPRI). NEITHER EPRI, ANY MEMBER OF EPRI, ANY COSPONSOR, THEORGANIZATION(S) BELOW, NOR ANY PERSON ACTING ON BEHALF OF ANY OF THEM: L(A) MAKES ANY WARRANTY OR REPRESENTATION WHATSOEVER, EXPRESS OR IMPLIED, (I)WITH RESPECT TO THE USE OF ANY INFORMATION, APPARATUS, METHOD, PROCESS, ORSIMILAR ITEM DISCLOSED IN THIS DOCUMENT, INCLUDING MERCHANTABILITY AND FITNESSFOR A PARTICULAR PURPOSE, OR (11) THAT SUCH USE DOES NOT INFRINGE ON ORINTERFERE WITH PRIVATELY OWNED RIGHTS, INCLUDING ANY PARTY'S INTELLECTUALPROPERTY, OR (111) THAT THIS DOCUMENT IS SUITABLE TO ANY PARTICULAR USER'SCIRCUMSTANCE; OR U(B) ASSUMES RESPONSIBILITY FOR ANY DAMAGES OR OTHER LIABILITY WHATSOEVER(INCLUDING ANY CONSEQUENTIAL DAMAGES, EVEN IF EPRI OR ANY EPRI REPRESENTATIVEHAS BEEN ADVISED OF THE POSSIBILITY OF SUCH DAMAGES) RESULTING FROM YOURSELECTION OR USE OF THIS DOCUMENT OR ANY INFORMATION, APPARATUS, METHOD, LPROCESS. OR SIMILAR ITEM DISCLOSED IN THIS DOCUMENT.

ORGANIZATION(S) THAT PREPARED THIS DOCUMENT '1Li

Aptech Engineering

AREVA NP

Electric Power Research Institute

Steve Brown UTennessee Valley Authority

Westinghouse Electric Company LLC UUU

NOTE

For further information about EPRI, call the EPRI Customer Assistance Center at 800.313.3774 ore-mail [email protected]. .

Electric Power Research Institute and EPRI are registered service marks of the Electric PowerResearch Institute, Inc.

Copyright 0 2006 Electric Power Research Institute, Inc. All rights reserved. .

Li

Page 3: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

CITATIONS

This report was prepared under the guidance of the Integrity Assessment Guidelines Committee.

Committee Members

Helen Cothron

James Begley

Steve Brown

Russell Cipolla

Robert Keating

David Ayres

Richard Coe

Joseph Mathew

William Moore

Stephen Leshnoff

Brad Corder

Alan Redpath

Daniel Mayes

Steve Swilley

Edward Blandford

Edward Fuller

Tennessee Valley Authority

AREVA NP

Consultant

Aptech Engineering

Westinghouse

Westinghouse

Southern California Edison

Omaha Public Power District

Southern Nuclear Operating Company

Exelon

Ameren UE

Progress Energy

Duke Power

EPRI

EPRI

EPRI

This report describes research sponsored by the Electric Power Research Institute (EPRI).

The report is a corporate document that should be cited in the literature in the following manner:

Steam Generator Integrity Assessment Guidelines: Revision 2. EPRI, Palo Alto, CA: 2006.1012987.

iii

Page 4: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

REPORT SUMMARY

This report provides guidance for evaluating the condition of steam generator (SG) tubes basedon nondestructive examination (NDE) or in situ pressure testing. This integrity assessment isnormally performed during a reactor refueling outage. Nuclear power plant licensees who followthis document's guidelines will have satisfied their requirements for condition monitoring andoperational assessment as defined in the Nuclear Energy Institute (NEI) initiative, SteamGenerator Program Guidelines, NEI 97-06.

BackgroundDamage to steam generator tubing can impair its ability to adequately perform required safetyfunctions in terms of both structural integrity and leakage integrity. Therefore, assessing tubeintegrity is an important component of a steam generator program, which is required by NEI-97-06. This program establishes a framework for structuring and strengthening existing steamgenerator programs. The fundamental elements that are needed represent a balance of prevention,inspection, evaluation, repair, and leakage monitoring measures.

Objectives" To help licensees support implementation of NEI 97-06.

• To help licensees meet the integrity assessment performance criteria described in NEI 97-06.

* To define requirements and describe in detail implementation procedures for a successfulsteam generator integrity assessment.

ApproachAn ad-hoc committee of licensee experts and additional industry specialists developed theseintegrity assessment guidelines. This document presents common industry practices for integrityassessment that are achievable with current technology. Any revisions to these guidelines areimplemented through the Steam Generator Management Program consensus process, whichrequires adherence to a formal industry review, comment, and approval protocol. Interimguidance will be provided to the industry whenever necessary between guideline revisions.

ResultsThis document describes acceptable methods for degradation assessments, condition monitoring,operational assessments, and secondary-side assessments. Condition monitoring refers toassessing the status of steam generator tubes during an outage to ensure that they maintainedadequate safety margins for the previous operating period. Operational assessment is intended toensure that steam generator tubes will maintain adequate safety margins during the upcoming

V

Page 5: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

operating period. There are other acceptable methods for integrity assessment; however, theyrequire technical justification for their application.

This document is a major rewrite of Revision 1 of the integrity assessment guidelines. The reporthas been completely reorganized. There is more detail in each chapter, there are many fewerappendices, and much new material is included. A great deal of emphasis is placed on providingexamples of how to carry out the essential steps of an integrity assessment. Methods fordetermining probability of detection (POD) of flaws are provided, as are methods for estimatingflaw sizes and how large they might grow over an operating interval. There also is a new chapteron secondary-side integrity.

Since Revision I was published, there have been five occasions when interim guidance wasissued. These are as follows:

* Interim Guidance on New Degradation Mechanisms, August 31, 2001;

* Interim Guidance on Three Mile Island Tube Sever Event, August 18, 2003;

* Interim Guidance on Revised Structural Performance Criteria, SGMP-IG-05-001, January17, 2005;Ca

" Interim Guidance to Communicate Issuance ofNE1 97-06 R2 and Gaps Between Revision 2and Current Guidelines, SGMP-IG-05-002, October 10, 2005; and

* Interim Guidance Regarding Adverse Trend of Foreign Objects in Steam Generators,SGMP-IG-05-04, November 18, 2005.

This document incorporates guidance for these occasions, although the wording may be slightlyLdifferent. In any case, interim guidance is now superseded by this document.

EPRI PerspectiveNEI 97-06 requires condition monitoring and operational assessment of steam generator tubing.These integrity assessment guidelines provide a useful description of how steam generator tubingcan be shown to meet required performance criteria. Using a standard approach facilitatesacceptance and review by regulatory authorities.

This document reflects current industry practices and represents an acceptable method forintegrity assessment. Revisions can be expected as the industry accumulates experience with thisguideline.

KeywordsNuclear steam generatorsDegradation assessmentCondition monitoringOperational assessmentSecondary-side integrity assessmentIntegrity assessment

vi

Page 6: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

CONTENTS

1 INTRODUCTION .................................................................................................................... 1-1

1.1 Objective ........................................................................................................................ 1-1

1.2 Scope ............................................................................................................................. 1-2

1.3 Basic Methodology of Steam Generator Integrity Assessment ...................................... 1-2

1.4 Com pliance Responsibilities .......................................................................................... 1-4

1.5 Contractor Oversight ...................................................................................................... 1-4

2 TUBE INTEGRITY CRITERIA ................................................................................................ 2-1

2.1 Introduction .................................................................................................................... 2-1

2.2 Structural Integrity Performance Criterion ...................................................................... 2-1

2.3 Leakage Integrity Performance Criteria .......................................................................... 2-3

2.4 Performance Acceptance Standards .............................................................................. 2-3

2.5 Discussion of Structural Margins and Bases .................................................................. 2-4

2.5.1 Assessment Factors ............................................................................................... 2-4

2.5.2 Burst Definition ....................................................................................................... 2-4

2.5.3 Collapse Definition .................................................................................................. 2-5

2.5.4 Limits on Yield Strength .......................................................................................... 2-5

2.6 Pressure Load Definitions ............................................................................................. 2-5

3 TUBE INTEGRITY ASSESSM ENT LIMITS ........................................................................... 3-1

3.1 Introduction .................................................................................................................... 3-1

3.2 Tube Integrity Limits ....................................................................................................... 3-1

3.2.1 Condition Monitoring Lim it ...................................................................................... 3-2

3.2.2 Operational Assessm ent Limit ................................................................................ 3-2

3.3 Material Properties ......................................................................................................... 3-6

3.4 Repair Limit .................................................................................................................... 3-6

3.5 Technical Specification Repair Limit .............................................................................. 3-6

3.6 Special Considerations for Tube Integrity Assessment .................................................. 3-7

vii

Page 7: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

3.7 Determ ination of Structural Integrity Lim its .................................................................... 3-7

3.7.1 Tube Burst Event .................................................................................................... 3-7

3.7.2 Significant Contributing Loads ................................................................................ 3-7

3.7.3 Tube Collapse Event ............................................................................................ 3-11

4 NDE M EA SUREM ENT UNCERTA INTIES ............................................................................. 4-1

4.1 Introduction .................................................................................................................... 4-1

4.2 Probability of Detection ................................................................................................... 4-2

4.2.1 Requirements and Limitations for Tube Integrity Applications ............................... 4-2

4.2.2 PO D M odeling ........................................................................................................ 4-3

4.2.3 G LM Calculation of PO D and its Uncertainties ....................................................... 4-5

4.2.4 Experim ental Determ ination of System PO D ........................................................ 4-6

4.2.5 M odel-Assisted PO D Developm ent ........................................................................ 4-7

4.3 Sizing Requirements and Limitations for Tube Integrity Applications ............................. 4-8

4.4 Extension of Qualified NDE Techniques for Tube Integrity Applications ....................... 4-10

5 DEG RA DATIO N G ROW TH RATES .................................................................................... 5-1"

5.1 Introduction .................................................................................................................... 5-1

5.2 Background .................................................................................................................... 5-1

5.3 Data Evaluation Procedures ........................................................................................... 5-2

5.3.1 Conservative Estimate of the Growth Rate Distribution .................................... 5-3

5.3.2 Realistic Estim ate of the G rowth Rate Distribution ................................................. 5-3

5.4 Illustrations of Estimations of Actual Growth Rate Distributions ................................. 5-5

5.4.1 Exam ple 1: AVB W ear Plug on Sizing .................................................................... 5-5

5.4.2 Example 2: Axial PWSCC at Dented Intersections Plug-on-Sizing ........................ 5-7

5.4.3 Example 3: Axial ODSCC in OTSG Tubes Plug on Detection ............................... 5-9

5.5 Default G rowth Rate Distributions ................................................................................ 5-10

5.5.1 Axial Stress Corrosion Cracking ........................................................................... 5-10

5.5.2 Circum ferential Stress Corrosion Cracking .......................................................... 5-15

6 DEG RA DATIO N A SSESSM ENT ........................................................................................... 6-1

6.1 Introduction .................................................................................................................... 6-1

6.2 Purpose .......................................................................................................................... 6-1

6.3 Sources of Inform ation for Degradation Assessm ent ..................................................... 6-3

6.4 Identification of Potential Steam Generator Degradation Mechanisms .......................... 6-4

6.4.1 Degradation in Previously Plugged Tubes ............................................................. 6-4

viii

Page 8: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

6.4.2 Types of Degradation .... ....................................................................................... 6-6

6.4.2.1 Intergranular Attack and Outside Diameter Stress Corrosion Cracking .......... 6-6

6.4.2.2 Primary Water Stress Corrosion Cracking and Intergranular Attack ............... 6-7

6.4.2.3 Tube Fretting and W ear .................................................................................. 6-7

6.4.2.4 Other W ear Dam age ....................................................................................... 6-7

6.4.2.5 Pitting .............................................................................................................. 6-7

6.4.2.6 High Cycle Fatigue ......................................................................................... 6-7

6.4.2.7 Im pingement ................................................................................................... 6-8

6.4.2.8 W astage/Thinning .......................................................................................... 6-8

*6.5 Identification of NDE Techniques .................................................................................... 6-9

6.6 Identification of Inspection Sam ple Plan ........................................................................ 6-9

6.7 Integrity Assessm ent and Repair Lim its ......................................................................... 6-9

6.8 Secondary Side Considerations ................................................................................... 6-10

6.9 Actions Upon Finding Unexpected Degradation .......................................................... 6-10

7 CONDITION M ONITORING .................................................................................................. 7-1

7.1 Introduction .................................................................................................................... 7-1

7.2 Condition M onitoring Evaluation Procedure ................................................................... 7-1

7.3 Structural Integrity Evaluation using Inspection Results ................................................ 7-2

7.3.1 Probabilities and Percentiles .................................................................................. 7-4

7.3.2 Arithm etic Strategy for Com bining Uncertainties .................................................... 7-4

7.3.3 Sim plified Statistical Strategy for Com bining Uncertainties .................................... 7-6

7.3.4 Monte Carlo Strategy for Com bining Uncertainties ................................................ 7-6

7.3.5 Strategy Comparison .............................................................................................. 7-6

7.3.5.1 Arithm etic Evaluation ...................................................................................... 7-7

7.3.5.2 Sim plified Statistical Evaluation ...................................................................... 7-8

7.3.5.3 M onte Carlo Evaluation ................................................................................... 7-9

7.4 Signal Am plitude Approaches to Structural Integrity .................................................... 7-11

7.5 Role of In Situ Pressure Testing ................................................................................... 7-12

7.6 Verification ................................................................................................................... 7-13

8 OPERATIONAL ASSESSM ENT ............................................................................................ 8-1

8.1 Introduction .................................................................................................................... 8-1

8.2 Projection of W orst Case Degraded Tube ...................................................................... 8-2

8.3 Fully Probabilistic Operational Assessm ent M ethods .................................................... 8-4

Page 9: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

8.3.1 Repair on Detection ................................................................................................ 8-4

8.3.2 Repair on NDE Sizing ............................................................................................. 8-5

8.4 Repair on NDE Sizing: General Considerations ............................................................. 8-5

8.4.1 Arithm etic Strategy for Repair on NDE Sizing ........................................................ 8-9

8.4.2 Sim plified Statistical Strategy for Repair on NDE Sizing ........................................ 8-9

8.4.3 Mixed Arithmetic/Simplified Statistical Strategy for Repair on NDE Sizing ............ 8-9

8.4.4 Monte Carlo Strategy for Repair on NDE Sizing .................................................... 8-9

8.4.5 Strategy Com parison for Repair on NDE Sizing ................................................... 8-101 "

8.4.5.1 Example: Cold Leg Thinning at Drilled Tube Support Plates ........................ 8-10 I

8.4.5.2 Arithmetic Strategy ........................................................................................ 8-12

8.4.5.3 Mixed Arithmetic/Simplified Statistical/Monte Carlo Strategy ....................... 8-13

8.4.5.4 Sim plified Statistical Strategy ........................................................................ 8-14

8.4.5.5 M onte Carlo Strategy .................................................................................... 8-14

8.5 Repair on Detection General Considerations ............................................................... 8-15

8.5.1 Arithm etic Strategy for Repair on Detection ......................................................... 8-18

8.5.2 Sim plified Statistical Strategy for Repair on Detection ......................................... 8-18 L8.5.3 Mixed Arithmetic/ Simplified Statistical Strategy for Repair on Detection ............. 8-19

8.5.4 Monte Carlo Strategies for Repair on Detection ................................................... 8-19 L8.5.5 Com parison of Strategies for Repair on Detection ............................................... 8-19

8.5.5.1 Example Equation ......................................................................................... 8-19

8.5.5.2 Arithmetic Strategy ........................................................................................ 8-19

8.5.5.3 M ixed Arithm etic/Sim plified Statistical Strategy ............................................ 8-20 L8.5.5.4 Sim plified Statistical Strategy ........................................................................ 8-20

8.5.5.5 M onte Carlo Strategy .................................................................................... 8-21 L8.6 Signal Am plitude Based Operational Assessm ent ....................................................... 8-21

8.7 Verification ................................................................................................................... 8-23

9 PRIMARY-TO-SECONDARY LEAKAGE ASSESSMENT ..................................................... 9-1

9.1 Introduction .................................................................................................................... 9-1

9.2 Accident Induced Leakage ............................................................................................. 9-1

9.3 Operational Leakage ...................................................................................................... 9-1

9.4 Leak Rate Calculation Methodologies ........................................................................... 9-3

9.5 Validation of Leak Rate Equations ................................................................................. 9-7

9.6 Condition M onitoring Evaluation for Leakage Integrity ................................................... 9-9

9.7 Operational Assessm ent Evaluation for Leakage Integrity ........................................... 9-10

L

L

Page 10: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

9.8 Actions upon Failure to Meet Leakage Integrity Performance Criteria ......................... 9-12

10 MAINTENANCE OF SECONDARY SIDE INTEGRITY ...................................................... 10-1

10.1 Introduction ........................................................................................................... 10-1

10.2 Purpose ...................................................................................................................... 10-2

10.3 Secondary Side Assessm ents .................................................................................... 10-2

10.4 Secondary Side Cleaning ........................................................................................... 10-4

10.5 Secondary Side Visual Inspections ............................................................................ 10-4

10.6 Upper Internals Inspections ........................................................................................ 10-7

11 REPORTING ....................................................................................................................... 11-1

11.1 External Reporting ..................................................................................................... 11-1

11.2 Internal Reporting ....................................................................................................... 11-1

11.2.1 The Degradation Assessm ent Report ................................................................ 11-1

11.2.2 The Condition M onitoring Report ........................................................................ 11-2

11.2.3 The O perational Assessm ent Report ................................................................. 11-2

12 REQUIREM ENTS ............................................................................................................... 12-1

12.1 Introduction................................................................................................................. 12-1

12.2 Tube Integrity Criteria ............................................................................................ 12-1

12.3 Tube Integrity Assessm ent Lim its .............................................................................. 12-2

12.4 NDE M easurem ent Uncertainties ............................................................................... 12-3

12.5 Degradation G rowth Rates ......................................................................................... 12-3

12.6 Degradation Assessm ent ....................................... .................................................... 12-3

12.7 Condition M onitoring .................................................................................................. 12-6

12.8 Operational Assessm ent ....................................................................................... 12-6

12.9 Prim ary-to-Secondary Leakage Assessm ent ........................................................ 12-7

12.10 M aintenance of SG Secondary Side Integrity ........................................................ 12-10

12.11 Reporting ................................................................................................................ 12-12

13 G LOSSARY ........................................................................................................................ 13-1

14 LIST OF ABBREVIATIONS AND ACRONYMS ................................................................. 14-1

15 REFERENCES ................................................................................................................... 15-1

Page 11: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

A APPENDIX A: INDUSTRY TECHNICAL BASES FOR STRUCTURAL INTEGRITYASSESSM ENT ......................................................................................................................... A-1

A.1 Introduction ................................................................................................................... A-1

A.2 Definition of Burst .......................................................................................................... A-2

A.2.1 Burst Condition ...................................................................................................... A-2

A.2.2 Technical Discussion ............................................................................................ A-2

A.2.3 Application - Condition M onitoring ........................................................................ A-3

A.3 Deterministic Structural Performance Criterion Pressure Loading Definition ............... A-3

A.3.1 Background .......................................................................................................... A-3

A.3.2 Statem ent of Structural Perform ance .................................................................... A-3

A.3.3 Definitions ............................................................................................................. A-4

A.3.4 Technical Discussion ............................................................................................ A-5

A.3.5 Limits on Yield Strength ........................................................................................ A-6

A.4 ASM E Code Review ..................................................................................................... A-7

A.4.1 M inim um W all Requirem ents ................................................................................ A-7

A.4.2 Primary Loads from Accidents Events .................................................................. A-8 L

A.4.2.1 ASM E Section III Appendix F Considerations ............................................... A-8

A.4.3 Secondary Loads from Accident Events ............................................................. A-12

A.4.3.1 Definition of Secondary Loads ..................................................................... A-12

A.4.3.2 Code Practice .............................................................................................. A-13

A.4.4 Sum mary of Code Considerations ...................................................................... A-13

A.5 Historical Perspective ................................................................................................. A-14

A.5.1 Regulatory Perspective ....................................................................................... A-14

A.5.2 Application of Industry Definition ......................................................................... A-15

A.5.2.1 Original Design ............................................................................................ A-15

A.5.2.2 Condition Monitoring .................................................................................... A-15

A.5.2.3 Validation of Industry Definition ................................................................... A-16 LA.6 Assessment of Contributing Loads ............................................................................. A-17

A.6.1 Primary Loads ..................................................................................................... A-18A.6.2 Axial Membrane Loads in OTSG Tubing............................A-18

A.6.3 Axial Mem brane Loads in RSG Tubing ............................................................ A-19

A.6.4 Treatm ent of Axial Therm al Loads ................................................................. A-1 9

A.7 Allowable Structural Lim its .......................................................................................... A-21

A.7.1 Tube Burst Condition .......................................................................................... A-21

A.7.2 Plastic Collapse Under Tension and Bending ..................................................... A-22

L.

xii

L

Page 12: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

A.7.3 Circum ferential Degradation ............................................................................... A-22

A.7.4 Axial Degradation ............. ................................................................................... A-23

A.8 Sum m ary and Conclusions ......................................................................................... A-24

A.9 References .................................................................................................................. A-25

B APPENDIX B: MODEL-ASSISTED POD DEVELOPMENT ............................................ B-1

B.1 M odel-Assisted PO D (M APO D) ............................................................................... B-1

B.1.1 Ahat M odeling ................................................................................................... B-1

B.1.2 Noise-Dependent Structural PO D M odeling .................................... .................... B-6

B.1.2.1 Ahat (S/N) M odeling ...................................................................................... B-7

B.1.2 2 M onte Carlo Ahat (S/N) Sim ulation ............................................................... B-7

B.1.2.3 Incorporating Hum an Factor or Personnel Effects ........................................ B-9

B.1.2.4 Illustrating the Dependency of PO D on (S/N) .......................................... B-11

B.1.2.5 PO D M odel Prediction and Validation ......................................................... B-12

B.1.2.6 Applications ................................................................................................. B-14

B.2 References .................................................................................................................. B-19

C APPENDIX C: EXAMPLES OF CONDITION.MONITORING AND OPERATIONAL

ASSESSM ENT LIM IT DETERM INATIO N ........................................................................... C-1

C.A Axial Cracking Exam ples .............................................................................................. C-2

C.1.1 Exam ple of Freespan, Through-wall Axial Crack .................................................. C-2

C.1.2 Condition M onitoring Lim it Using Arithm etic M ethod ............................................ C-3

C.1.3 Condition Monitoring Limit Using Simplified Statistical Method ........................ C-4

C.1.4 G rowth .................................................................................................................. C-6C.1.5 M onte Carlo Analysis ............................................................................................ C-6

C.2 Circum ferential Cracking Exam ples ....................................................................... C-10

C.2.1 Circumferential Cracking with Restricted Lateral Tube Motion, Pressure andBending Loads ............................................................................................................... C -1 0

C .2.2 Input Param eters ............................................................................................ C-I 1

C .2.3 G overning Equations .......................................................................................... C-12

C.2.4 Structurally Significant External Loads ............................................................... C-15

C.2.5 Pressure O nly ..................................................................................................... C -16

C.2.5.1 Calculation of the Structural Lim it ................................................................ C-17

C.2.5.3 Sim plified Statistical Analysis, Pressure O nly ......................................... C-1 9

C.2.5.4 M onte Carlo Analysis, Pressure O nly .......................................................... C-21

C .2.6 Pressure Plus External Bending and Axial Loads ............................................... C-23

Page 13: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

C.2.6.1 Calculation of the Structural Limit, Pressure Plus Bending & AxialLoads ........................................................................................................................ C-24

C.2.6.2 Condition Monitoring Limit, Pressure Plus Bending & Axial Loads ............. C-26

C.2.6.3 Arithmetic Method, Pressure Plus Bending & Axial Loads .......................... C-27

C.2.6.4 Simplified Statistical Analysis, Pressure Plus Bending & Axial Loads ........ C-28

C.2.6.5 Monte Carlo Analysis, Pressure Plus Bending & Axial Loads ..................... C-31

C.2.7 Conclusions ........................................................................................................ C-32 1

C.3 Volum etric Degradation Exam ples ............................................................................. C-33

C.3.1 Example of Uniform 3600 Thinning Over a Given Axial Length .......................... C-33

C.3.2 Structural Lim it .................................................................................................... C-33

C.3.3 Condition M onitoring Lim it .................................................................................. C-34

C.3.4 G rowth ................................................................................................................ C-35

C.3.5 M onte Carlo Analysis .......................................................................................... C-38

C.4 References ................................................................................................................. C-41

xiv

Page 14: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

LIST OF FIGURES

Figure 1-1 Steam Generator RCS Pressure Boundary Assessment; Condition Monitoringand O perational Assessm ent ............................................................................................. 1-3

Figure 2-1 SIPC Im plem entation Logic ...................................................................................... 2-2

Figure 3-1 Condition Monitoring Elements of Tube Integrity Assessment ................................. 3-3

Figure 3-2 Operational Assessment Elements of Tube Integrity (Repair on Sizing) .................. 3-4

Figure 3-3 Operational Assessment Elements of Tube Integrity (Repair on Detection) ............ 3-5

Figure 3-4 Logic for Screening Contributing Loads ................................................................... 3-9

Figure 4-1 Generating a POD Model Using Binary Hit-Miss Data ............................................. 4-4

Figure 4-2 Different POD Models Resulting from the Same Hit-Miss Data ............................... 4-4

Figure 4-3 GLM Workbook for Calculating POD and POD Uncertainties .................................. 4-5

Figure 4-4 Accounting for Data Analyst Uncertainty using a GLM Weighted AverageP O D ................................................................................................................................... 4 -7

Figure 4-5 Model-Assisted Example POD Calculations Using Data for VolumetricDegradation at Tube Support Plate Center and Edges ...................................................... 4-8

Figure 4-6 Regression Plot Format Used for Determining NDE Sizing Errors - Cold LegT hinning D ata ..................................................................................................................... 4-9

Figure 5-1 Global Average Growth rate of Maximum Depth as Voltage Threshold ofAcceptable Sizing Data is Increased .................................................................................. 5-5

Figure 5-2 Comparison of NDE Measured Growth Rates, Actual Physical Growth Ratesand Computer Simulation of NDE Measured Growth Rates for Wear Depth Growth ........ 5-7

Figure 5-3 Distribution of NDE Measured Average Depth Growth Rates of PWSCCIndications Left In Service under an ARC .................................. 5-8

Figure 5-4 Distribution of NDE Measured Length Growth Rates of PWSCC IndicationsLeft In Service under an ARC ............................................................................................ 5-8

Figure 5-5 Comparison of NDE Measured Growth Rates, Actual Physical Growth Ratesand Computer Simulation of NDE Measured Growth Rates for Axial PWSCC ................ 5-11

Figure 5-6 Deceleration Factor for ODSCC and PWSCC Growth Rates Compared to6 11°F ................................................................................................................................ 5-12

Figure 5-7 Comparison of NDE Measured Growth Rate Distribution with ComputerSimulation Result of NDE Measured Growth Rate Distribution, OTSG AxialO D S C C /IG A ..................................................................................................................... 5-13

Figure 5-8 Comparison of NDE Measured Growth Rate Distribution with Best EstimatePhysical Growth Rates Distribution, OTSG Axial ODSCC/IGA ........................................ 5-14

xv

Page 15: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Figure 5-9 Cumulative Distributions of Average Depth Growth Rates of AxialODSCC/IGA (curve on the left is a best estimate distribution, others include NDEsizing uncertainties) ........................................................................................................ 5-15

Figure 6-1 Recirculating Steam Generator Degradation Mechanisms ...................................... 6-2

Figure 6-2 Once Through Steam Generator Degradation Mechanisms .................................... 6-3

Figure 7-1 Condition Monitoring Structural Limit Curves for Axial PWSCC Per ETSS96703.1 at 4155 psi Using Three Strategies for Combining Uncertainties ....................... 7-10

Figure 7-2 Condition Monitoring Plot for Freespan Axial ODSCC/IGA in OTSG Tubing at4 050 psi ............................................................................................................................ 7-12

Figure 8-1 Cumulative Distribution of Cold Leg Thinning Depth Growth Rate NDEMeasurements, Computer Simulation of NDE Measurements, and Best EstimateGrowth Rate Distribution .................................................................................................. 8-12

Figure 8-2 Signal Amplitude-Based Operational Assessment for Freespan AxialODSCC/IGA at OTSG Plants Voltage Illustrated ............................................................. 8-22

Figure 9-1 Calculated and Measured Leak Rates for Axial Cracks in Alloy 600 Tubing atNormal Operating Conditions ............................................................................................. 9-8

Figure 10-1 Process of Recording, Monitoring, and Assessing Data ....................................... 10-3

Figure 10-2 Contingency Planning for Secondary Side Inspection with no PlannedPrimary Side Inspection ................................................................................................... 10-8

Figure A-1 SIPC Implementation Logic ..................................................................................... A-4

Figure B-1 Ahat POD Modelling ................................................................................................ B-3

Figure B-2 ExcelTM Implementation of Ahat POD Modeling for Cold-Leg Thinning ETSSD ata ................................................................................................................................... B 4

Figure B-3 ExcelTM Implementation of Ahat POD Modeling for Cold-Leg Thinning ETSSD ata ................................................................................................................................... B -5

Figure B4 ExcelTM Implementation of Ahat POD Modeling for Cold-Leg Thinning ETSSD ata ................................................................................................................................... B -6

Figure B-5 Monte Carlo Simulation of Ahat (S/N) Data ............................................................ B-8

Figure B-6 Modelling Data Analyst Human Factor Effects using a (S/N) DependentR eporting Probability ......................................................................................................... B-9

Figure B-7 Monte Carlo Generated Noise Dependent Structural POD Model .................... B-1 1

Figure B-8 Cumulative Noise Distributions Used for Noise-Dependent Monte Carlo PODS im ulations ...................................................................................................................... B -12

Figure B-9 Monte Carlo Simulated Noise-Dependent Structural Detection ProbabilitiesShowing the Effects of Increasing and Decreasing Noise .............................................. B-13

Figure B-10 Monte Carlo Predicted POD Compared with Technique Limit and WeightedAverage POD for one the Performance Demonstration Datasets ................................... B-14

Figure B-11 Kolmogorov-Smirnov Comparison of Two Noise Distributions ....................... B-1 5

Figure B-12 Kolmogorov-Smirnov Comparison of Two Noise Distributions ....................... B-1 6Figure B-13 Simulation Logic for Deriving Effective POD .................................................. B-1 7

Figure B-14 Simulation Outputs for +Pt Confirmation ............................................................. B-18 L8Figure B-15 Comparison of Effective POD with Bobbin and +Pt coil PODs (+Pt

C onfirm ation) ................................................................................................................... B-18

Xvi

Page 16: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Figure C-1 Burst Pressure as a Function of Critical Crack Length for the Three Methods ....... C-9

Figure C-2 Burst pressure as a function of PDA for circumferentially cracked tubes [CI] ...... C-13

Figure C-3 Distribution of Growth for Uniform Thinning .......................................................... C-37

Figure C-4 Comparison of CM solutions for a burst pressure of 4.473 ksi ............................. C-39

Figure C-5 Distribution of simulated burst pressures for a sample depth and length ............. C-40

Page 17: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

LIST OF TABLES

Table 4-1 Steam Generator Tube Wall Degradation ............................................. 4-2

Table 4-2 Correlation Coefficient, r*, at 95% confidence level for a positive correlation[19] ................................................................................................................................... 4 -10

Table 4-3 Examples of Extended Applicability of Qualified Techniques .................................. 4-11

Table 7-1 Condition Monitoring Uncertainty Treatment for Structural Integrity .......................... 7-5

Table 8-1 Operational Assessment Uncertainty Treatment for Structural Integrity forRepair on NDE Sizing ....................................................................................................... 8-6

Table 8-2 Operational Assessment Uncertainty Treatment for Structural Integrity forRepair on Detection ........................................................................................................ 8-16

Table A-1 Alloy 600 Typical Properties - Mean Values ............................................................ A-9

Table A-2 Typical Differential Pressures for NSSS Designs ................................................... A-17

Table B-1 Example Monte Carlo POD Simulator Output Data ........................................... B-10

Table C-1 Summary of Critical FDA Results for Circumferential Crack Example ................... C-32

Table C-2 Structural Limit Parameter hsL Solutions for Several L Values ............................... C-34

Table C-3 Relational and Material Uncertainties Calculated at the 95 th Percentile ................. C-35

Table C-4 Postulated Distribution of Growth of Uniform Thinning Indications forOperational Assessment Calculations (OD = 0.875, t = 0.050) ....................................... C-36

xix

Page 18: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

1INTRODUCTION

1.1 Objective

These guidelines present requirements and implementation procedures for meeting the objectivesof steam generator tube integrity assessments including:

1. Identification and characterization of degradation forms within steam generators that requireassessment,

2. Application of appropriate NDE technology, consistent with the expected degradation and inaccordance with the EPRI Steam Generator Examination Guidelines [1].

3. Application of integrity assessment methods, consistent with the expected degradation andrequired safety factor, for use in evaluating integrity at the end of an inspection interval andto ensure integrity during the subsequent inspection interval.

Successful implementation of the above objectives will help ensure that steam generator integritywill be maintained for each degradation form during operation and applicable design basisaccidents.

Licensees should use this document to demonstrate the condition of their steam generatorsrelative to performance criteria used for condition monitoring and operational assessment asdefined in the NEI initiative, Steam Generator Program Guidelines NEI 97-06 [2].

1-1

Page 19: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Introduction

1.2 Scope

As required by NEI 97-06, this document offers guidance and requirements for the evaluationmethods, margin, and uncertainty considerations used to determine tube integrity. It alsoprovides guidance for performing steam generator degradation assessment (DA), conditionmonitoring (CM), operational assessment (OA), and secondary side assessment. Assessment ofsteam generator tube integrity requires an evaluation of both burst and leakage throughout anoperational plant cycle. Information on how to carry out these assessments is provided in thebody of this document with supplemental examples in the appendices. Other approaches may beused with technical justification.

1.3 Basic Methodology of Steam Generator Integrity Assessment

This section summarizes the details of steam generator integrity assessment. This assessmentapplies to steam generator components which are part of the primary pressure boundary (e.g.,tubing, tube plugs, sleeves and other repairs). It also applies to foreign objects and secondaryside structural supports (e.g., tube support plates) that may, if severely degraded, compromisepressure-retaining components of the steam generator.

L

I I

L

LLL

L

1-2

Li

Page 20: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Introduction

Figure 1-1Steam Generator RCS Pressure Boundary Assessment; Condition Monitoring andOperational Assessment

1-3

Page 21: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Introduction

1.4 Compliance Responsibilities

This document presents a general approach and examples for demonstrating steam generator tubeintegrity. Plant specific programs should consider plant design, materials, steam generatorcorrosion experience, and operating philosophy. Performing the assessments herein will helpplant personnel understand what inspections and repairs are necessary and the appropriate lengthof operation between inspections. To meet this goal, an effective corporate policy andmonitoring program are essential and should be based on the following:

1.5 Contractor Oversight

L'LLL

1-4

L

Page 22: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

2TUBE INTEGRITY CRITERIA

2.1 Introduction

This chapter presents analysis margins and acceptance criteria for structural integrity andthrough-wall leakage associated with degraded steam generator tubing.

2.2 Structural Integrity Performance Criterion

The SIPC provides the margins for tube integrity against tube burst or collapse. The structuralintegrity performance criterion is:

2-1

Page 23: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Tube Integrity Criteria

Figure 2-1SIPC Implementation Logic

2-2 U

Page 24: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Tube Integritj, Criteria

2.3 Leakage Integrity Performance Criteria

The leakage integrity performance criteria provide requirements for both operational andaccident leakage.

2.4 Performance Acceptance Standards

The performance acceptance standards for assessing tube integrity to the structural integrity andaccident leakage performance criteria apply to both condition monitoring and operationalassessments. The acceptance standard for structural integrity is:

The acceptance standard for accident leakage integrity is:

2-3

Page 25: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Tube Integrity Criteria

2.5 Discussion of Structural Margins and Bases

2.5.1 Assessment Factors

LLLLiL7LLSteam

generator

tubes

exhibit

a low

probability

of

burst

under

normal

operating

conditions

and

LU2.5.2 Burst Definition

Steam generator tubes exhibit a low probability of burst under normal operating conditions andaccident conditions. The definition of tube burst is:

2-4

L

Page 26: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Tube Integrity Criteria

2.5.3 Collapse Definition

2.5.4 Limits on Yield Strength

2.6 Pressure Load Definitions

2-5

Page 27: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Tube Integrity Criteria

Normal steady-state full power operation as defined in NEI 97-06 [2], and discussed in AppendixA, is:

The conditions existing during MODE 1 operation at the maximum steady state reactorpower as defined in the design or equipment specification. Changes in design parameterssuch as plugging or sleeving levels, primary or secondary modifications, or Thot should beassessed and their effects on differential pressure included if significant.

The limiting accident pressure differential is the maximum or largest pressure differential acrossthe tube wall for the design basis accidents (Service Levels C and D). For most plants, this is thepressure differential during a main steam line break. Apart from pressure loading, othercontributing loads that can occur during the postulated accidents shall be evaluated to determineif these loads contribute significantly to tube burst. Such loads are discussed in Section 2.5.1,Section 3.7.2, and in Appendix A.

Li

Li

LLLL

L

2-6

L

Page 28: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

3TUBE INTEGRITY ASSESSMENT LIMITS

3.1 Introduction

This chapter presents the general requirements for establishing the tube integrity and repair limitsassociated with steam generator tubing, such that the tube integrity performance criteria and theperformance acceptance standards defined in Chapter 2 are satisfied during operation. Tubeintegrity limits are defined for each degradation mechanism.

3.2 Tube Integrity Limits

3-1

Page 29: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Tube hItegrity Assessment Limits

3.2.1 Condition Monitoring Limit

Condition monitoring is the assessment of the current state of the steam generator tubing, and isperformed at the conclusion of each steam generator inspection. The purpose of conditionmonitoring is to confirm that both the structural integrity and accident-induced leakageperformance criteria were satisfied during the past inspection interval.

LL

3.2.2 Operational Assessment Limit

An operational assessment is a forward-looking prediction of the steam generator tube conditionsat the next inspection.

3-2

L

Page 30: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Tube Integrity Assessment Limits

Figure 3-1Condition Monitoring Elements of Tube Integrity Assessment

3-3

Page 31: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Tube Integiity Assessment Limits

L

LFigure 3-2Operational Assessment Elements of Tube Integrity L(Repair on Sizing)

LLI

L

LLI ýL

3-4

L

Page 32: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Tube Integrity Assessment Limits

Figure 3-3Operational Assessment Elements of Tube Integrity(Repair on Detection)

3-5

Page 33: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Tube Integrity Assessment Limits

3.3 Material Properties

3.4 Repair Limit

3.5 Technical Specification Repair Limit

LLCLLL

3-6

Page 34: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

LLLUUUUUUUU

UUL

Tube Integrity Assessment Limits

3.6 Special Considerations for Tube Integrity Assessment

3.7 Determination of Structural Integrity Limits

3.7.1 Tube Burst Event

3.7.2 Significant Contributing Loads

3-7

Page 35: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Tube hutegrity Assessment Limits

3-8

Page 36: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Tube Integrity Assessment Limits

Figure 3-4Logic for Screening Contributing Loads

3-9

Page 37: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Tube Integrity Assessment Limits

L

LL

3-10L

L

Page 38: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Tube Integrity Assessment Limits

3.7.3 Tube Collapse Event

3-11

Page 39: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

4NDE MEASUREMENT UNCERTAINTIES

4.1 Introduction

This chapter addresses NDE system performance measures and their uncertainties associatedwith tube bundle examination for tube integrity applications. Two aspects of performance areconsidered: 1) degradation detection, quantified by Probability of Detection (POD), and 2)degradation sizing, quantified by linear correlations of true-versus-measured values of structuralquantities of interest, such as length and depth of degradation.

4-1

Page 40: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

NDE Measurement Uncertainties

Table 4-1Steam Generator Tube Wall Degradation

4.2 Probability of Detection

4.2.1 Requirements and Limitations for Tube Integrity Applications

4-2

LVU

VVVVVL7VL

Page 41: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

U

LI

L

L

L

NDE Measurement Uncertainties

4.2.2 POD Modeling

A POD model is a functional measure of the ability of an NDE system to detect degradati6n.

4-3

Page 42: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

NDE Measutrement Uncertainties

Figure 4-1Generating a POD Model Using Binary Hit-Miss Data

L

LLLLLLL

Figure 4-2Different POD Models Resulting from the Same Hit-Miss Data

4-4

Page 43: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

NDE Measurement Uncertainties

4.2.3 GLM Calculation of POD and its Uncertainties

4-5

Page 44: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

a-

NDE Measurement Uncertainties

4.2.4 Experimental Determination of System POD

L

LLLLUUL

4-6

Page 45: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

NDE Measurement Uncertainties

Figure 4-3Accounting for Data Analyst Uncertainty using a GLM Weighted Average POD

4.2.5 Model-Assisted POD Development

4-7

Page 46: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

NDE Measurement Uncertainties

LLL

Figure 4-4Model-Assisted Example POD Calculations Using Data for Volumetric Degradation at TubeSupport Plate Center and Edges L

4.3 Sizing Requirements and Limitations for Tube Integrity Applications

L

LLL

L4-8

L

Page 47: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

NDE Measurement Uncertainties

Figure 4-5Regression Plot Format Used for Determining NDE Sizing Errors - Cold Leg Thinning Data

4-9

Page 48: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

NDE Measurement Uncertainties

Table 4-2Correlation Coefficient, r*, at 95% confidence level for a positive correlation [19]

LLL

4.4 Extension of Qualified NDE Techniques for Tube Integrity Applications

4-10

Page 49: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

NDE Measurement Uncertainties

Table 4-3Examples of Extended Applicability of Qualified Techniques

4-11

Page 50: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

5DEGRADATION GROWTH RATES

5.1 Introduction

In this chapter methods are presented to determine degradation growth rates from NDEinspection information. This chapter also provides specific growth rate information from industryservice experience that may be used when plant-specific data are limited.

5.2 Background

5-1

Page 51: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Degradation Growth Rates

5.3 Data Evaluation Procedures

The following procedures can be used to characterize distributions of growth rates for use inOperational Assessments. Two methods are presented. The first method is a simplified approachthat provides a conservative estimate for growth since it includes sizing uncertainties. In somesituations, this method may result in a very conservative value for growth rate distribution, inwhich case a second, more refined method, may be used to give a more realistic estimate forgrowth rate by explicitly accounting for sizing uncertainties.

L5

5-L

Page 52: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

LDegradation Growth Rates

5.3.1 Conservative Estimate of the Growth Rate Distribution

L

5.3.2 Realistic Estimate of the Growth Rate Distribution

5-3

Page 53: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Degradation Growth Rates

L(1U

5-4

Page 54: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Degradation Growth Rates

Measured Average Growth Rates per Cycle versus Voltage Threshold,OTSG Freespan ODSCC

4.5

4

E 3.5

E

X 3

0* 2.5

20

* 1.5

.0

0Z5 0.5.

00 0.1 0.2 0.3 0.4 0.5 0.6

Voltage Threshold for Acceptance of Phase Angle Based Sizing, volts

0.7

Figure 5-1Global Average Growth rate of Maximum Depth as Voltage Threshold of Acceptable SizingData is Increased

5.4 Illustrations of Estimations of Actual Growth Rate Distributions

Three examples of estimating actual physical growth rates from NDE measurements ofdegradation growth are presented below. The first two examples are for plug on sizing repairscenarios and the third is for a plug-on-detection degradation mechanism.

5.4.1 Example 1: A VB Wear Plug on Sizing

5-5

Page 55: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Degradation Growth Rates

LLi

VIi

U

LLLLH

5-6

Page 56: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Degradation Growth Rates

Figure 5-2Comparison of NDE Measured Growth Rates, Actual Physical Growth Rates and ComputerSimulation of NDE Measured Growth Rates for Wear Depth Growth.

5.4.2 Example 2: Axial PWSCC at Dented Intersections Plug-on-Sizing

5-7

Page 57: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Degradation Growth Rates

Figure 5-3Distribution of NDE Measured Average Depth Growth Rates of PWSCC Indications Left InService under an ARC

LLLLLL2

Figure 5-4Distribution of NDE Measured Length Growth Rates of PWSCC Indications Left In Serviceunder an ARC

5-8

L

Page 58: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Degradation Growth Rates

5.4.3 Example 3: Axial ODSCC in OTSG Tubes Plug on Detection

5-9

Page 59: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Degradation Growth Rates

5.5 Default Growth Rate Distributions

LLi

LLL

L5.5.1 Axial Stress Corrosion Cracking

5-10L

L

Page 60: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Degradation Growth Rates

Figure 5-5Comparison of NDE Measured Growth Rates, Actual Physical Growth Rates and ComputerSimulation of NDE Measured Growth Rates for Axial PWSCC

5-11

Page 61: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Degradation Growth Rates

L

Figure 5-6Deceleration Factor for ODSCC and PWSCC Growth Rates Compared to 611"F

LLI

5-12L

U

Page 62: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Degradation Growth Rates

Figure 5-7Comparison of NDE Measured Growth Rate Distribution with Computer Simulation Resultof NDE Measured Growth Rate Distribution, OTSG Axial ODSCClIGA.

5-13

Page 63: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Degradation Growth Rates

L

L

LLLLiLL

Figure 5-8 LIU

Comparison of NDE Measured Growth Rate Distribution with Best Estimate PhysicalGrowth Rates Distribution, OTSG Axial ODSCC/lGA.

L

L

5-14 L

Page 64: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Degradation Growth Rates

Figure 5-9Cumulative Distributions of Average Depth Growth Rates of Axial ODSCCIIGA(curve on the left is a best estimate distribution, others include NDE sizing uncertainties)

5.5.2 Circumferential Stress Corrosion Cracking

5-15

Page 65: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

6DEGRADATION ASSESSMENT

6.1 Introduction

Degradation assessment is the process of identifying and documenting existing and potentialdegradation in planning for an upcoming outage, including inspection plans and related actionsfor the primary and secondary sides of the steam generator.

6.2 Purpose

The overall purpose of the degradation assessment is to ensure that appropriate inspections areperformed during the upcoming outage, and that the requisite information for integrityassessment is provided.

6-1

Page 66: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

a.-

Degradation Assessment

Figure 6-1Recirculating Steam Generator Degradation Mechanisms

6-2

Page 67: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

LL

LL

LL

L

LLL

LL

Degradation Assessment

Figure 6-2Once Through Steam Generator Degradation Mechanisms

6.3 Sources of Information for Degradation Assessment

6-3

Page 68: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Degradation Assessment

6.4 Identification of Potential Steam Generator Degradation Mechanisms

6.4.1 Degradation in Previously Plugged Tubes

6-4

L

Page 69: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Degradation Assessment

6-5

Page 70: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Degradation Assessment

6.4.2 Types of Degradation

6.4.2.1 Intergranular Attack and Outside Diameter Stress Corrosion Cracking

6-6

Page 71: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

L

L

L

L

LLL

Degradation Assessment

6.4.2.2 Primary Water Stress Corrosion Cracking and Intergranular Attack

6.4.2.3 Tube Fretting and Wear

6.4.2.4 Other Wear Damage

6.4.2.5 Pitting

6.4.2.6 High Cycle Fatigue

6-7

Page 72: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Degradation Assessment

6.4.2.7 Impingement

6.4.2.8 Wastage/Thinning

6-8

L

Page 73: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Degradation Assessment

6.5 Identification of NDE Techniques

6.6 Identification of Inspection Sample Plan

6.7 Integrity Assessment and Repair Limits

6-9

Page 74: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Degradation Assessment

6.8 Secondary Side Considerations

6.9 Actions Upon Finding Unexpected Degradation

6-10

U

L

Page 75: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

7CONDITION MONITORING

7.1 Introduction

Condition monitoring (CM) involves the evaluation of inspection results at the end of theinspection interval to determine the state of the steam generator tubing for the most recent periodof operation relative to structural and leakage integrity performance criteria. This chapterprovides guidance on performing structural assessments.

7.2 Condition Monitoring Evaluation Procedure

7-1

Page 76: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

L..

Condition Monitoring

7.3 Structural Integrity Evaluation using Inspection Results

L

1 -~

U

LUL

UU

7-2

Page 77: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Condition Monitoring

7-3

Page 78: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Condition Monitoring

7.3.1 Probabilities and Percentiles

7.3.2 Arithmetic Strategy for Combining Uncertainties

LL

VL

LVV

L

7-4

Page 79: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Condition Monitoring

Table 7-1

Condition Monitoring Uncertainty Treatment for Structural Integrity

7-5

Page 80: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Condition Monitoring

7.3.3 Simplified Statistical Strategy for Combining Uncertainties

7.3.4 Monte Carlo Strategy for Combining Uncertainties

7.3.5 Strategy Comparison

7-6

Page 81: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Condition Monitoring

L

L,

7.3.5.1 Arithmetic Evaluation

7-7

Page 82: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Condition Monitoring

7.3.5.2 Simplified Statistical Evaluation

7-8

L,

Page 83: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Condition Monitoring

7.3.5.3 Monte Carlo Evaluation

7-9

Page 84: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

I-

Condition Monitoring

LLLLi

L

LLL

Figure 7-1Condition Monitoring Structural Limit Curves for Axial PWSCC Per ETSS 96703.1 at 4155psi Using Three Strategies for Combining Uncertainties

7-10

U..

Li

Page 85: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Condition Monitoring

7.4 Signal Amplitude Approaches to Structural Integrity

7-11

Page 86: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Condition Monitoring

Figure 7-2Condition Monitoring Plot for Freespan Axial ODSCCIIGA in OTSG Tubing at 4050 psi

7.5 Role of In Situ Pressure Testing

7-12

L

L

LLLALLAUL

LA

U

j

Page 87: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Condition Monitoring

7.6 Verification

7-13

Page 88: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

8OPERATIONAL ASSESSMENT

8.1 Introduction

Operational Assessment (OA) involves projecting the condition of the SG tubes to the time ofthe next scheduled inspection outage and determining their acceptability relative to the tubeintegrity performance criteria of NEI 97-06 [2].

8-1

Page 89: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

4.-

Operational Assessment

8.2 Projection of Worst Case Degraded Tube

L

8-2

Page 90: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Operational Assessment

8-3

Page 91: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

IOperational Assessment

8.3 Fully Probabilistic Operational Assessment Methods

L8.3.1 Repair on Detection

L

8-4

U

Page 92: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Operational Assessment

8.3.2 Repair on NDE Sizing

8.4 Repair on NDE Sizing: General Considerations

8-5

Page 93: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Operational Assessment

Table 8-1Operational Assessment Uncertainty Treatment for Structural Integrity for Repair onNDE Sizing

L

8-6

Page 94: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Operational Assessment

Table 8-1 (continued)Operational Assessment Uncertainty Treatment for Structural Integrity for Repair onNDE Sizing

8-7

Page 95: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Operational Assessment

Li

8-8

Page 96: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Operational Assessment

8.4.1 Arithmetic Strategy for Repair on NDE Sizing

8.4.2 Simplified Statistical Strategy for Repair on NDE Sizing

8.4.3 Mixed Arithmetic/Simplified Statistical Strategy for Repair on NDE Sizing

8.4.4 Monte Carlo Strategy for Repair on NDE Sizing

8-9

Page 97: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Operational Assessment

8.4.5 Strategy Comparison for Repair on NDE Sizing

8.4.5.1 Example: Cold Leg Thinning at Drilled Tube Support Plates

8-10

Page 98: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

I LOperational Assessment

LL

L

L

LLLLLLLLLL

8-11

L

Page 99: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Operational Assessment

Lj

L

Figure 8-1Cumulative Distribution of Cold Leg Thinning Depth Growth Rate NDE Measurements,Computer Simulation of NDE Measurements, and Best Estimate Growth Rate Distribution

Li8.4.5.2 Arithmetic Strategy

L

L

L

Li

8-12

Page 100: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Operational Assessment

8.4.5.3 Mixed Arithmetic/Simplified Statistical/Monte Carlo Strategy

8-13

Page 101: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Operational Assessment

8.4.5.4 Simplified Statistical Strategy

8.4.5.5 Monte Carlo Strategy

8-14

L.

Li

L

LH

LU,L

L

L

Page 102: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Operational Assessment

8.5 Repair on Detection General Considerations

L

LL

L

LLLLLIL

L

L

8-15

Page 103: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Operational Assessment

Table 8-2Operational Assessment Uncertainty Treatment for Structural Integrity for Repairon Detection

L.

L

L8L

LL

L

8-16

Page 104: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Operational Assessment

Table 8-2 (continued)Operational Assessment Uncertainty Treatment for Structural Integrity for Repairon Detection

8-17

Page 105: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Operational Assessment

8.5.1 Arithmetic Strategy for Repair on Detection

L,LLLLLLj

L

8.5.2 Simplified Statistical Strategy for Repair on Detection

8-18

L

Page 106: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

L Operational Assesshient

8.5.3 Mixed Arithmetic/ Simplified Statistical Strategy for Repair on Detection

8.5.4 Monte Carlo Strategies for Repair on Detection

8.5.5 Comparison of Strategies for Repair on Detection

8.5.5.1 Example Equation

8.5.5.2 Arithmetic Strategy

8-19

Page 107: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Operational Assessment

8.5.5.3 Mixed Arithmetic/Simplified Statistical Strategy

IL

I IL

L8.5.5.4 Simplified Statistical StrategyL

LL

LLLi.

8-20

Li

Page 108: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Operational Assessment

8.5.5.5 Monte Carlo Strategy

8.6 Signal Amplitude Based Operational Assessment

LL

8-21

Page 109: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Operational Assessment

L

LLL

L

L7LFigure 8-2

Signal Amplitude-Based Operational Assessment for Freespan Axial ODSCCIIGA at OTSGPlants Voltage Illustrated

8-22

L

Page 110: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Operational Assessment

8.7 Verification

LL

L

LLL

8-23

Page 111: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

9PRIMARY-TO-SECONDARY LEAKAGE ASSESSMENT

9.1 Introduction

This chapter provides requirements for primary-to-secondary leakage assessment and documentsmethods to calculate leakage.

9.2 Accident Induced Leakage

9.3 Operational Leakage

9-1

Page 112: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

*1

Primary-to-Secondary Leakage Assessment

L

9-2

Page 113: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Prima y-to-Seconda)' Leakage Assessment

9.4 Leak Rate Calculation Methodologies

9-3

Page 114: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

*11j

Primary-to-Secondary Leakage Assessment

1'

Li

9-4i

L

Page 115: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Primaqy-to-Secondary Leakage Assessment

9-5

Page 116: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Prirnay-to-Secondary Leak-age Assessment

U-0

9-6

Page 117: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Primamy-to-Secondawy Leakage Assessment

9.5 Validation of Leak Rate Equations

9-7

Page 118: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Primary-to-Secondary Leakage Assessment

L

L

Figure 9-1Calculated and Measured Leak Rates for Axial Cracks in Alloy 600 Tubing at NormalOperating Conditions

9-8

L

Page 119: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Primai,-to-Secondaiy Leakage Assessment

9.6 Condition Monitoring Evaluation for Leakage Integrity

9-9

Page 120: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Prima9y-Io-Secondaly Leakage Assessment

9.7 Operational Assessment Evaluation for Leakage Integrity

LUUU?LUUVL

9-10

Page 121: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Priinai-to-Secondaiy Leakage Assessment

9-11

Page 122: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Primaqy-to-Secondary Leakage Assessment

9.8 Actions upon Failure to Meet Leakage Integrity Performance Criteria

LiLiLiLiULiLiLL

9-12

Page 123: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

10MAINTENANCE OF SECONDARY SIDE INTEGRITY

10.1 Introduction

10-1

Page 124: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Maintenance of Secondaty Side Integrity

10.2 Purpose

10.3 Secondary Side AssessmentsL

LL

10-2

Page 125: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

U7 U7 r-. 77 r77 U7 r7-- r- r-c r7 r-- U- r-7 U- r- C-7' C-7- IrT

Maintenance of Secondawy Side Integrity

Figure 10-1Process of Recording, Monitoring, and Assessing Data

10-3

Page 126: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Maintenance ofSecondany Side integrity

10.4 Secondary Side Cleaning

10.5 Secondary Side Visual Inspections

10-4

Page 127: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Maintenance of Secondary Side Integrity

10-5

Page 128: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Maintenance of Secondary Side Integrity

ii

10-6

Page 129: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Maintenance of Secondary Side Integrity

10.6 Upper Internals Inspections

10-7

Page 130: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Maintenance of Secondagy Side hItegrity

Figure 10-2Contingency Planning for Secondary Side Inspection with no Planned Primary Side Inspection

10-8

ý -, r- LW LW ~7T ~T LIZ UZC EZ rTi rIZ (77 Liii U r~ r r r - rU-7 r - r -- r - r

Page 131: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

11REPORTING

11.1 External Reporting

Required reporting to the NRC is addressed in each licensee's technical specification and in NEI97-06. The NRC report includes the results of the condition monitoring performed during a SGinspection.

Required reporting to the industry is addressed in NEI 97-06. It is important the licensees shareexperiences with the industry in a timely manner through the SGMP and/or the INPO OEprocess. If a performance criterion is exceeded or if a new industry degradation mechanism isidentified, this information should be sent to appropriate SGMP representatives as soon aspossible via e-mail so that lessons learned can be disseminated quickly to the industry. Allappropriate tables in the EPRI Steam Generator Database shall be completed within 120 daysafter startup.

11.2 Internal Reporting

The reporting discussed in this section is not meant to cover all required internal reporting ordocumentation. This section is concerned with required reporting for integrity assessments.Refer to other EPRI Guidelines for additional internal reporting requirements.

11.2.1 The Degradation Assessment Report

I-I

Page 132: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Reporting

11.2.2 The Condition Monitoring Report

LU

11.2.3 The Operational Assessment Report

11-2

Page 133: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

12REQUIREMENTS

12.1 Introduction

12.2 Tube Integrity Criteria

12-1

Page 134: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Requirements

HL

12.3 Tube Integrity Assessment Limits HLHLL

L

12-2

Page 135: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Requirements

12.4 NDE Measurement Uncertainties

12.5 Degradation Growth Rates

12.6 Degradation Assessment

12-3

Page 136: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Requirements

.-U

L

12-4

Page 137: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Requirements

12-5

Page 138: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Requirements

12.7 Condition Monitoring

! I

L

Li

LLLL

12.8 Operational Assessment

12-6

Page 139: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Requirements

-" 12.9 Primary-to-Secondary Leakage AssessmentL

UULL

L2-L

Page 140: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Reqziiremnents .

La

La

12-8

Page 141: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Requirements

12-9

Page 142: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Requirements

12.10 Maintenance of SG Secondary Side Integrity

12-10

Page 143: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Requirements

12-11

Page 144: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Requirements

12.11 Reporting

12-12

Page 145: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

13GLOSSARY

13-1

Page 146: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Glossary

J

13-2

Page 147: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Glossary

13-3

Page 148: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Glossary

UU

13-4I.-

U

Page 149: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Glossary

13-5

Page 150: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

14LIST OF ABBREVIATIONS AND ACRONYMS

AILPC Accident-Induced Leakage Performance Criterion

ARC Alternate Repair Criteria

ASL Axial Secondary Loads

ASME American Society of Mechanical Engineers

AVB Anti-Vibration Bar

AVT All Volatile Treatment

BOC Beginning of Cycle

BP Burst Pressure

B&W Babcock and Wilcox

CAF Corrosion-Assisted Fatigue (High Cycle Fatigue)

CDF Cumulative Distribution Function

CE Combustion Engineering

CEOG Combustion Engineering Owners' Group

CFR Code of Federal Regulations

CLT Cold Leg Thinning

CM Condition Monitoring

CMTR Certified Mill Test Report

DA Degradation Assessment

ECT Eddy Current Testing

EDF Empirical Distribution Function

EFPY Equivalent Full-Power Years

EOC End of Cycle

EPRI Electric Power Research Institute

ETSS Examination Technique Specification Sheet

FDA Fractional Degraded Area

FLB Feed Line Break

FME Foreign Material Exclusion

FOSAR Foreign Object Search and Retrieval

FS Free Span

FSAR Final Safety Analysis Report

14-1

Page 151: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

List ofAbbreviations andAcronyms

GDC General Design Criteria

GLM Generalized Linear Modeling

GPD Gallons Per Day

GR Growth Rate

IAGL Integrity Assessment Guidelines

ICC Intergranular Cellular Corrosion

ID Inside Diameter

IGA Intergranular Attack

IDIGA Inside Diameter Intergranular Attack

IGSCC Intergranular Stress Corrosion Cracking

INPO Institute for Nuclear Power Operations

ISI In-Service Inspection

LAPD Limiting Accident Pressure Differential

LCO Limiting Condition Operation

LOCA Loss of Coolant AccidentLR Leak Rate --'LTL Lower Tolerance Limit

MAPOD Model-Assisted Probability of Detection

MD Maximum Depth

MSLB Main Steam Line Break

NDE Nondestructive Examination L,NEI Nuclear Energy Institute

NMP NDE Measurement Parameter iNOP Normal Operating Pressure

NOPD Normal Operating Pressure Differential

NRC United States Nuclear Regulatory Commission

NSSS Nuclear Steam Supply System

OA Operational Assessment

OD Outside Diameter

ODSCC Outside Diameter Stress Corrosion Cracking

OE Operating Experience

01 Operating Interval

OTSG Once Through Steam Generator

PDA Percent Degraded Area

Pdf Probability Density Function

PICEP Pipe Crack Evaluation Program (a computer program)

14-2

Page 152: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

List ofAbbreviations and Acronyms

PL

POB

POD

POL

PWR

PWSCC

RCPB

RFC

RG

RPC

RSG

SF

SG

SGDD

SGMP

SGPB

SGTR

SIPC

SL

SLB

SR

SRP

SSE

STP

S/N

TRM

TS

TSP

TSPC

TSPE

TW

UTS

W

Primary Load

Probability of Burst

Probability of Detection

Probability of Leak

Pressurized Water Reactor

Primary Water Stress Corrosion Cracking

Reactor Coolant Pressure Boundary

Retirement for Cause

Regulatory Guide

Rotating Pancake Coil

Recirculating Steam Generators

Safety Factor

Steam Generator

Steam Generator Degradation Database

Steam Generator Management Program

Steam Generator Pressure Boundary

Steam Generator Tube Rupture

Structural Integrity Performance Criterion

Structural Limit

Steam Line Break

Stability Ratio

Standard Review Plan

Safe Shutdown Earthquake

Standard Temperature and Pressure (60'F, 760 mm Hg)

Signal-to-Noise Ratio

Technical Requirements Manual

Tubesheet

Tube Support Plate

Tube Support Plate Center

Tube Support Plate Edge

Through Wall

Upper Tubesheet (in OTSGs)

Westinghouse

14-3

Page 153: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

15REFERENCES

1. Pressurized Water Reactor Steam Generator Examination Guidelines: Revision 6,Requirements. EPRI, Palo Alto, CA: 2002. 1003138.

2. "Steam Generator Program Guidelines," Nuclear Energy Institute NEI 97-06, Revision 2,Nuclear Energy Institute, Washington, DC (May 2005).

3. Steam Generator Management Program Administrative Procedures, Revision 1, EPRI, PaloAlto, CA: 2004. 1011274.

4. Steam Generator Degradation Specific Management Flaw Handbook, EPRI, Palo Alto, CA:2001. 1001191

5. Impacts of the Structural Integrity Peiformance Criterion on Steam Generator Tube IntegrityEvahlations, EPRI, Palo Alto, CA: 2004. TR-1009541

6. Annis. C., "Measuring the Reliability of Nondestructive Evaluation Systems." AmericanInstitute of Aeronautics and Astronautics, AIAA-94-1399-CP. 1994.

7. Statistical Engineering Webpage, http://wwv.stastisticalemiineering.com

8. Myers, R.H. and D. Montgomery. "A Tutorial on Generalized Linear Models." Journal ofQuality Technology, Vol. 29, No. 3, July 1997.

9. Meyers, R., et al., "Generalized Linear Models With Applications to Engineering and theSciences," John Wiley and Sons, New York, New York, USA, 2002.

10. Dobson, A. "An Introduction to Generalized Linear Models." Chapman & Hall/CRC 2002.

11. SG-SGDA-02-51, "Tube Integrity Tools Manual," Westinghouse Electric Company,Madison, PA, USA: December, 2002.

12. "Flaw Handbook Tools Theory Manual," Prepared for EPRI by Westinghouse ElectricCompany, Madison, PA, USA: July 2005.

13. Integrity Assessment Examples Manual, EPRI, Palo Alto, CA: 2006. 1012986.

14. "Recombinant DNA - A New Approach to Evahlating the Effects of Plant Noise on NDEDetection and Sizing Capabilities," EPRI SG NDE Conference, July 2002.

15. "DQV on Eddyview - Where We Have Been and Where are We Going?, "EPRI SG NDEConference, July 2004.

16. SG-SGDA-06-02, "Users Manual - Crystal Ball Program for Adjusting NDE PerformanceTest PODs for Alternate Noise Distributions, Westinghouse Electric Company, Madison PA,USA - December 2005.

17. Users Manual - rystal Ball Program for Predicting NDE System POD, EPRI, Palo Alto:2006. 1012988.

15-1

Page 154: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

References

18. Brown, S. D., "NDE System Sizing Error Verification," Letter Report dated November,2005.

19. Beyer, W.H "Handbook of Tables for Probability and Statistics", CRC Publications 1966.

20. "Degradation Growth Rates in OTSG Tubing," AREVA/FANP Document 51-5022969-00,September 2003.

21. "Assessment of Current Understanding of Mechanisms of Initiation, Arrest and Reinitiationof Stress Corrosion Cracks in PWR Steam Generator Tubing," NUREG/CR-5752, ANL-99/4, February 2000.

22. "Sequoyah Nuclear Plant U1CI 0 Steam Generator Inspection Results," TVA Presentation toNRC Staff, April 25, 2000.

23. Three Mile Island Plugged Tube Severance: A Study of Damage Mechanisms, EPRI, PaloAlto, CA: May 2003: 1008438.

24. "Rapidly Propagating Fatigue Cracks in Steam Generator Tubes," NRC Bulletin No. 88-02,United States Nuclear Regulatory Commission, Washington, DC, February 5, 1988.

25. Steam Generator In Situ Pressure Test Guidelines, EPRI, Palo Alto, CA: 2003. 1007904Rev. 2.

26. EPRI Steam Generator Management Program, "ECT Examination Technique SpecificationSheets," www.EPRlq.comrL

27. "Correlation of Burst Pressure with Plus Point Voltage and Length for OTSG AxialODSCC," Framatome Calculation Note 32-5030334-00, August 2003.

28. Technical Basis for Steam Generator Tube Integrity Performance Acceptance Standards,EPRI, Palo Alto, CA: 2006. 1012984.

29. "Alternative Radiological Source Terms for Evaluating Design Basis Accidents at NuclearPower Reactors," Regulatory Guide 1. 183, United States Nuclear regulatory Commission,Washington, DC, July 2000.

30. PWR Primary-To-Secondary Leak Guidelines-Revision 3, EPRI, Palo Alto, CA: 2004.1008219

31. Depth Based Structural Analysis Methods for SG Circumferential Indications, EPRI, PaloAlto, CA: 1997. 107197-P1

32. Steam Generator Tubing Burst Testing and Leak Rate Testing Guidelines, EPRI, Palo Alto,CA: 2002. 1006783

33. PICEP: Pipe Crack Evaltation Program, EPRI, Palo Alto, CA: 1987. NP-3596-SR, Rev. I

34. Steam Generator Tube Leakage Experiments and PICEP Calculations, EPRI, Palo Alto, CA:1990. NP-6897-L

35. Depth Based Structural Analysis Methods for SG Circumferential Indications, EPRI, PaloAlto, CA: 1997. 107197-PI

36. Ductile Fracture Handbook, Vohlme 1: Circumferential Throughwall Cracks, EPRI, PaloAlto, CA: 1989. NP-6301-DVI

15-2

Page 155: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

References

37. Ductile Fracture Handbook. Vohlme 2, EPRI, Palo Alto, CA: 1990. NP-6301-DV2

38. Duffy, A. R., Eiber, R. J. and Maxey, W. A., "Recent Work on Flaw Behavior in PressureVessels," Proceedings of the Symposium on Fracture Toughness Concepts for WeldableStructural Steel, UKAEA, Chapman and Hall Ltd., Risley, April 1969.

39. "Pressure and Leak-Rate Tests and Models for Predicting Failure of Flawed Steam GeneratorTubes," NUREG/CR-6664, ANL 99/23, August 2000.

40. Steam Generator Foreign Object Task Force Review Material. EPRI, Palo Alto, CA: 2006.1012921.

15-3

Page 156: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

AAPPENDIX A:STRUCTURAL

INDUSTRY TECHNICAL BASES FORINTEGRITY ASSESSMENT

A.1 Introduction

A-1

Page 157: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix A: Industry Technical Bases for Structural Integrity Assessment

A.2 Definition of Burst

A.2.1 Burst Condition

A.2.2 Technical Discussion

A-2

Page 158: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix A: Industry Technical Bases for Structural Integrity Assessment

A.2.3 Application - Condition Monitoring

A.3 Deterministic Structural Performance Criterion Pressure LoadingDefinition

A.3.1 Background

A.3.2 Statement of Structural Performance

A-3

Page 159: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendir A: hIdustry Technical Bases for Structural Integrity Assessment

Figure A-I1SIPC Implementation LogicL

A.3.3 Definitions

A-4

Page 160: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix A: Industiy Technical Bases for Structural Integrity Assessment

LA.3.4 Technical Discussion

LLL

A-5

Page 161: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix A: Indusiy Technical Bases for Structural Integrity Assessment

L

LLL

A.3.5 Limits on Yield Strength L

LLLL

A-6

Page 162: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix A: Industs, Technical Bases for Structural Integrity Assessment

A.4 ASME Code Review

A.4.1 Minimum Wall Requirements

A-7

Page 163: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix A: Industry Technical Bases for Structural Integrity Assessment

A.4.2 Primary Loads from Accidents Events

A.4.2.1 ASME Section III Appendix F Considerations

A-8

L4Li

Li

Lj

UjLL

LL

L

Page 164: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix A: Industry Technical Bases for Structural Integrity Assessment

Table A-1

L Alloy 600 Typical Properties - Mean Values

LLLL

A-9

Page 165: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix A: Industry Technical Bases for Structural Integrity Assessment

LLLLLLLL

LU

LA-10

Page 166: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix A: Industry Technical Bases for Structural Integrity Assessment

A-1I

Page 167: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix A: Industry Technical Bases for Structural Integrity Assessment

A.4.3 Secondary Loads from Accident Events

A.4.3.1 Definition of Secondary Loads LJ

I,,J

L

L7L

L•L•

LL•L

A-12 L

Page 168: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix A: Industry Technical Bases for Structural Integrity Assessment

A.4.3.2 Code Practice

A.4.4 Summary of Code Considerations

A-13

Page 169: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix A: Industiy Technical Bases for Structural Integrity Assessment

A.5 Historical PerspectiveL

A.5.1 Regulatory Perspective

IL4

L

LLLU 'L

L

A-14

Page 170: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix A: Industry Technical Bases for Structural Integrity Assessment

A.5.2 Application of Industry Definition

A.5.2.1 Original Design

A.5.2.2 Condition Monitoring

A-15

Page 171: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix A: Industry Technical Bases for Structural Integrity Assessment

I I

L

LL

A.5.2.3 Validation of Industry Definition LLLLLL

L

L

A-16

Page 172: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix A: lndustiy Technical Bases for Structural Integrity Assessment

Table A-2Typical Differential Pressures for NSSS Designs

A.6 Assessment of Contributing Loads

A-17

Page 173: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix A: Industry Technical Bases for Strlctural Integrity Assessment

A.6.1 Primary Loads

A.6.2 Axial Membrane Loads in OTSG Tubing

A-18

L.

Page 174: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix A: Industry Technical Bases for Structural Integrity Assessment

A.6.3 Axial Membrane Loads in RSG Tubing

A.6.4 Treatment of Axial Thermal Loads

A-19

Page 175: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

L-a

Appendix A: Industry Technical Bases for Structural Integrity Assessment,

b 4

L•

L;

L

A-2L

Page 176: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix A: Industy Technical Bases for Structural Integrity Assessment

A.7 Allowable Structural Limits

A. 7.1 Tube Burst Condition

L

L

L

L

U

L

L

Page 177: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix A: Industry Technical Bases for Structural Integrity Assessment

A.7.2 Plastic Collapse Under Tension and Bending

A. 7.3 Circumferential Degradation

A-22

LL

LLLLU

LL

Page 178: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

LL

L

L•

Appendix A: Industry Technical Bases for Structural Integrity Assessment

Axial Degradation

A-23

Page 179: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix A: Industry Technical Bases for Structural Integrity Assessment

A.8 Summary and Conclusions

L

L

L

LLiLi

Li

LA-24L

Page 180: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix A: Industiy Technical Bases for Structural Integrity Assessment

A.9 References

Al Title 10 to the Code of Federal Regulations, Part 50.

A2 "Steam Generator Program Guidelines," Nuclear Energy Institute NEI 97-06, Revision 1,Nuclear Energy Institute, Washington, DC (January 2001).

A3 Testimony of James Knight before the Atomic Safety and Licensing Board, U.S. NuclearRegulatory Commission, Washington, DC (January 1975).

A4 Draft Regulatory Guide 1.121, "Bases for Plugging Degraded PWR Steam GeneratorTubes," U.S. Nuclear Regulatory Commission, Washington, DC (August 1976).

A5 ASME Boiler and Pressure Vessel Code, Section III, Division 1, Subsection NB, "Class IComponents," 2004 Edition.

A6 "Burst Pressure Correlation for Steam Generator Tubes with Through-Wall Axial Cracks",EPRI TR-105505, Final Report, October 1997.

A7 "Safety Evaluation Report Related to the Preliminary Design of the Standard ReferenceSystem RESAR-414," NUREG-0491, Docket Number STN 50-572, United States NuclearRegulatory Commission, November 1978.

A8 "Steam Generator In Situ Pressure Test Guidelines," EPRI Report TR-107904-R2, ElectricPower Research Institute, Palo Alto, CA (August 2003).

A9 "Guidelines for Steam Generator Tube Section Removal, Test and Examination", EPRITR-016743-V4R1 Final Report, December 1997.

A10 Steam Generator Tubing Burst Testing and Leak Rate Testing Guidelines, EPRI, Palo Alto,

CA: 2002. 1006783

Al l Draft Regulatory Guide DG-1074, "Steam Generator Tube Integrity," March 1998.

A12 "Impacts of the Structural Integrity Performance Criterion on Steam Generator TubeIntegrity Evaluations," EPRI TR- 1009541, (November 2004).

A13 ASME Boiler and Pressure Vessel Code, Section XI, Rules for the Inservice Inspection ofNuclear Power Plant Components," 2004 Edition.

A14 "Evaluation of Flaws in Austenitic Steel Piping," EPRI NP-4690-SR, Special Report, (July1986).

A15 Cipolla, R. C., D. A. Scarth, G. M. Wilkowski, and V. A. Zilberstein, "Technical Basis forProposed Revision to Acceptance Criteria for ASME Section XI Pipe Flaw Evaluation,"

A-25

Page 181: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

11Appendix A: Industry Technical Bases for Structural Integrity Assessment

PVP Vol. 422, 2001 ASME Pressure Vessel and Piping Conference, Atlanta, Georgia, (July23-26, 2001).

A16 Testimony of Raymond Maccary before the Atomic Safety and Licensing Appeal Board,U.S. Nuclear Regulatory Commission, Washington, DC (January 1976).

A17 Atomic Safety and Licensing Board, LBP-75-27, U.S. Nuclear Regulatory Commission,Washington, DC (May 1, 1975).

A18 Regulatory Guide 1.160, "Assessing and Managing Risk Before Maintenance Activities atNuclear Power Plants," U.S. Nuclear Regulatory Commission, Washington, DC -

A19 Costa, D., "Treatment of Tube Axial Thermal Loads," Report No. 51-5021407-01,AREVA. j

A20 NEI letter to NRC (S.J. Collins), "Industry Steam Generator Program Initiative", datedDecember 17, 1998. i1

L

L

A-26

Page 182: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

BAPPENDIX B: MODEL-ASSISTED PODDEVELOPMENT

B.1 Model-Assisted POD (MAPOD)

B.1.1 Ahat Modeling

B-1

Page 183: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

t-J

Appendix B: Model-Assisted POD Development

LL

L

B-2

L

Page 184: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix B: Model-Assisted POD Development

Figure B-1Ahat POD Modelling

B-3

Page 185: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix B: Model-Assisted POD Development

L

LjLL7Li

Figure B-2Excel TM Implementation of Ahat POD Modeling for Cold-Leg Thinning ETSS Data

B-4

U

Page 186: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix B: Model-Assisted POD Development

Figure B-3ExceITM Implementation of Ahat POD Modeling for Cold-Leg Thinning ETSS Data

B-5

Page 187: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix B: Model-Assisted POD Development

I .;

L

Figure B-4Excel TM Implementation of Ahat POD Modeling for Cold-Leg Thinning ETSS Data

B. 1.2 Noise-Dependent Structural POD Modeling

B-6

Page 188: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix B: Model-Assisted POD Development

B.1.2.1 Ahat (S/N) Modeling

B.1.2 2 Monte Carlo Ahat (S/N) Simulation

B-7

Page 189: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix B: Model-Assisted POD Development

Figure B-5 %JMonte Carlo Simulation of Ahat (SIN) DataL

LiL

LLL

B-8

L

Page 190: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix B: Model-Assisted POD Development

B.1.2.3 Incorporating Human Factor or Personnel Effects

Figure B-6Modelling Data Analyst Human Factor Effects using a (SIN) Dependent ReportingProbability

B-9

Page 191: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix B: Model-Assisted POD Development

Table B-1Example Monte Carlo POD Simulator Output Data

B-1O

Page 192: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

L

LU

LLLUU

LU

U

U

U

Appendix B: Model-Assisted POD Development

Figure B-7Monte Carlo Generated Noise Dependent Structural POD Model

B.1.2.4 Illustrating the Dependency of POD on (SIN)

B-1I

Page 193: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix B: Model-Assisted POD Development

Figure B-8Cumulative Noise Distributions Used for Noise-Dependent Monte Carlo POD Simulations

HU

H

B.1.2.5 POD Model Prediction and Validation

B-12

L

Page 194: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix B: Model-Assisted POD Development

Figure B-9Monte Carlo Simulated Noise-Dependent Structural Detection Probabilities Showing theEffects of Increasing and Decreasing Noise

B-13

Page 195: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix B: Model-Assisted POD Development

'I

Figure B-10Monte Carlo Predicted POD Compared with Technique Limit and Weighted Average PODfor one the Performance Demonstration Datasets

B.1.2.6 Applications

1.0

0.8

CU.0

EC.,

0.6

0.4

LLLLLL

L

L~i

0.2

0.00.0 0.1 0.2 0.3 0.4 0.5

Noise Amplitude, volts

0.6

B-14

Page 196: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

ULUUULULU

Appendix B: Model-Assisted POD Development

Figure B-11Kolmogorov-Smirnov Comparison of Two Noise Distributions

B-15

Page 197: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix B: Model-Assisted POD Development

U

UU

Figure B-12Kolmogorov-Smirnov Comparison of Two Noise Distributions U

UUU

UUUU

B-16

Page 198: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

U

LLU

LLLU

LLLIiUUL

Appendix B: Model-Assisted POD Development

Figure B-13Simulation Logic for Deriving Effective POD

B-17

Page 199: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix B: Model-Assisted POD Development

Simulation Outputs

for +Pt Confirmation

Figure B-14 L

Figure Bo15 (Comparison of Effective POD with Bobbin and +Pt coil PODs (+Pt Confirmation)

B-18

Page 200: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix B: Model-Assisted POD Development

B.2 References

BI Berens, A.P. and P.W. Hovey, "Evaluation of NDE Reliability Characterization," AFWAL-TR-81-4160, Vol. 1, Air Force Wright Aeronautical Laboratories, WPAFB, OH, December1981

B2 Berens, A.P. and P.W. Hovey, "Flaw Detection Reliability Criteria, Volume I - Methodsand Results" AFWAL-TR-84-4022, Vol. 1, Air Force Wright Aeronautical Laboratories,WPAFB, OH, April 1984

B3 Berens, A.P., "NDE Reliability Data Analysis," ASM Metals Handbook Volume 17Nondestructive Evaluation and Quality Control, 9"' Ed., American Society of MetalsInternational, Materials Park, OH, 1989

B4 MIL-HDBK-1823, "Department of Defense Handbook - Nondestructive Evaluation SystemReliability Assessment," April 1999

B5 Berens, A.P. "Probability of Detection (POD) Analysis for the Advanced retirement forCause (RFC)/Engine Structural Integrity Program (ENSIP) Nondestructive Evaluation(NDE) System- Volume 1: POD Analysis " AFRL-ML-WP-TR-2001-4010, Air ForceResearch Laboratory, WPAFB, OH, January, 2000

B6 Berens, A.P. "Probability of Detection (POD) Analysis for the Advanced retirement forCause (RFC)/Engine Structural Integrity Program (ENSIP) Nondestructive Evaluation(NDE) System - Volume 2: POD Users Manual" AFRL-ML-WP-TR-2001-401 1, Air ForceResearch Laboratory, WPAFB, OH, January, 2000

B7 "Monte Carlo POD Simulator Users Guide" Aptech Engineering Services Report, Preparedunder Task 6b of the EPRI Tools for Tube Integrity Assessment Program, Draft dated July,2004

B8 "Guidelines for NDE and Destructive Exam Data Acceptability for NDE POD and SizingPerformance Evaluations" Westinghouse/Aptech Engineering Report prepared under Task 3of EPRI Tools for Tube Integrity Assessment Program, July 2003

B-19

Page 201: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

CAPPENDIX C: EXAMPLES OF CONDITIONMONITORING AND OPERATIONAL ASSESSMENTLIMIT DETERMINATION

C-1

Page 202: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix C:- Examples of Condition Monitoring and Operational Assessment LimitDetermination

C.1 Axial Cracking Examples

C. 1. 1 Example of Freespan, Through-wall Axial Crack

La

La

La

La

LLL

LL

C-2

Page 203: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix C: Examples of Condition Monitoring and Operational Assessment LimitDetermination

C. 1.2 Condition Monitoring Limit Using Arithmetic Method

C-3

Page 204: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix C: Examples of Condition Monitoring and Operational Assessment LimitDetermination

L

&-j

C. 1.3 Condition Monitoring Limit Using Simplified Statistical Method

LLLL

Li

LLLL

C-4

L

Page 205: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix C: Examples of Condition Monitoring and Operational Assessment LimitDetermination

C-5

Page 206: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix C: Examples of Condition Monitoring and Operational Assessment LimitDetermination

C.1.4 Growth

C.1.5 Monte Carlo Analysis

C-6

I-

I-

L

iiKKKKKKLK

L

Page 207: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix C: Examples of Condition Monitoring and Operational Assessment LinitDetermination

C-7

Page 208: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix C:- Examples of Condition Monitoring and Operational Assessment LimitDetermination

U.

Ls

LLLLi

L

LILLLLIU

C-8 L

L

Page 209: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix C: Examples of Condition Monitoring and Operational Assessment LimitDetermination

Figure C-1Burst Pressure as a Function of Critical Crack Length for the Three Methods

C-9

Page 210: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix C: Examples of Condition Monitoring and Operational Assessment LimitDetermination

C.2 Circumferential Cracking Examples

C.2.1 Circumferential Cracking with Restricted Lateral Tube Motion, Pressure andBending Loads

C-10

Page 211: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix C: Examples of Condition Monitoring and Operational Assessment Linit

Determination

C.2.2 Input Parameters

C-1I

Page 212: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

L..

Appendix C: Examples of Condition Monitoring and Operational Assessment LimitDetermination

C.2.3 Governing Equations

U

L

LL

C-12

Page 213: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix C: Examples of Condition Monitoring and Operational Assessment LimitDetermination

Figure C-2Burst pressure as a function of PDA for circumferentially cracked tubes [Cl]

C-13

Page 214: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix C: Examples of Condition Monitoring and Operational Assessment LimitDetermination

L

LL

L

L

L

CJ

Li

C-14

L

Page 215: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix C: Examples of Condition Monitoring and Operational Assessment LimitDetermination

C.2.4 Structurally Significant External Loads

C-15

Page 216: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix C: Examples of Condition Monitoring and Operational Assessment LimitDetermination

C.2.5 Pressure Only

LLiiLUUU

C-16

L

Page 217: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix C: Examples of Condition Monitoring and Operational Assessment LimitDetermination

C.2.5.1 Calculation of the Structural Limit

C-17

Page 218: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix C: Examples of Condition Monitoring and Operational Assessment LimitDetermination

C.2.5.2 Arithmetic Method, Pressure Only

C-18

Page 219: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix C: Examples of Condition Monitoring and Operational Assessment LimitDetermination

C.2.5.3 Simplified Statistical Analysis, Pressure Only

C-19

Page 220: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix C: Examples of Condition Monitoring and Operational Assessment LimitDetermination

LLLLL

LLL

C-20

Page 221: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix C: Examples of Condition Monitoring and Operational Assessment LimitDetermination

C.2.5.4 Monte Carlo Analysis, Pressure Only

C-21

Page 222: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix C: Examples of Condition Monitoring and OperationalAssessment LimitDetermination

LIiLUUUU

L

U

C-22

Page 223: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix C: Examples of Condition Monitoring and Operational Assessment LimitDetermination

C.2.6 Pressure Plus External Bending and Axial Loads

C-23

Page 224: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix C: Examples of Condition Monitoring and Operational Assessment LimitDetermination

C.2.6.1 Calculation of the Structural Limit, Pressure Plus Bending & Axial Loads

L

L

LIL

LC-24

L

Page 225: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

LLU

Appendix C: Examples of Condition Monitoring and Opelational Assessment LimitDetermination

C-25

Page 226: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix C: Examples of Condition Monitoring and Operational Assessment LimitDetermination

C.2.6.2 Condition Monitoring Limit, Pressure Plus Bending & Axial Loads

C-26

Page 227: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

L Appendix C.: Examples of Condition Monitoring and Operational Assessment Limit

LO DeterminationC.2.6.3 Arithmetic Method, Pressure Plus Bending & Axial Loads

L

LL

LL

LLL I

C-27LL

Page 228: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix C: Examples of Condition Monitoring and Operational Assessment LimitDetermination

C.2.6.4 Simplified Statistical Analysis, Pressure Plus Bending & Axial Loads LL'LLL

LiLL

C-28

Page 229: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix C: Examples of Condition Monitoring and Operational Assessment LimitDetermination

C-29

Page 230: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendir C: Examples of Condition Monitoring and Operational Assessment LimitDetermlination

L.

U

U

4.

LL

L

C-30

Page 231: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix C: Examples of Condition Monitoring and Operational Assessment LimitDetermination

C.2.6.5 Monte Carlo Analysis, Pressure Plus Bending & Axial Loads

C-31

Page 232: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix C: Examples of Condition Monitoring and Operational Assessment LimitDetermination

i !

U

UC.2.7 Conclusions

Table C-1Summary of Critical FDA Results for Circumferential Crack Example

LAUI

C-32

Page 233: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix C: Examples of Condition Monitoring and Operational Assessment Limit

L ~C.3 Volumetric Degradation Examples D emnto

L C.3.1 Example of Uniform 360 0 Thinning Over a Given Axial Length

L C.3.2 Structural Limit

LL

LL

LLLL

LLL

Page 234: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix C: Examples of Condition Monitoring and Operational Assessment LimitDetermination

Table C-2Structural Limit Parameter hsL Solutions for Several L Values

C.3.3 Condition Monitoring Limit

C-34

Page 235: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix C: Examples of Condition Monitoring and Operational Assessment LimitDetermination

Table C-3Relational and Material Uncertainties Calculated at the 95 th Percentile

C.3.4 Growth

C-35

Page 236: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix C: Examples of Condition Monitoring and Operational Assessment Limit Determination

Table C-4Postulated Distribution of Growth of Uniform Thinning Indications for Operational Assessment Calculations (OD = 0.875, t =0.050)

C-36

rx ~ 17 E~rzz r7- tzz- r-c rizi r-_ r~ L tI [ r, r , r

Page 237: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

V-7 Sf7 F- 7 r~ r7 V-- SF- C=7 U7 1-7 r7 U>_!?r r-, Ur- C r -u rz

Appendix C: Examples of Condition Monitoring and Operational Assessment Limit Determination

Figure C-3Distribution of Growth for Uniform Thinning

C-37

Page 238: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix C.: Examples of Condition Monitoring and Operational Assessment LimfitDetermination

C.3.5 Monte Carlo Analysis

Lj

LiUL

UUL

C-38 L

L

Page 239: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

V1777 r-7 r7 -- U7-- E77] 9771 r7l 1717 FiT U r - r- - r-- U r-

Appendix C: Examples of Condition Monitoring and Operational Assessment Limit Determination

Figure C-4Comparison of CM solutions for a burst pressure of 4.473 ksi

C-39

Page 240: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix C: Examples of Condition Monitoring and Operational Assessment Limit Determnination

Figure C-5Distribution of simulated burst pressures for a sample depth and length

C-40

r7 r- > rr rz 7 rz rn z z rz 'v ix r7ci r( - r --- F

Page 241: Steam Generator Integrity Assessment Guidelines · Generator Program Guidelines, NEI 97-06. Background Damage to steam generator tubing can impair its ability to adequately perform

Appendix C: Examples of Condition Monitoring and Operational Assessment LimitDetermination

CA References

C1 Steam Generator Degradation Specific Management Flaw Handbook, EPRI, Palo Alto, CA:January 2001. 1001191

C2 Burst Pressure Correlation for Steam Generator Tubes With Throughwall Axial Cracks,EPRI, Palo Alto, CA: 1997. TR-105505

C3 Impacts of the Structural Integrity Performance Criterion on Steam Generator Tube IntegrityEvaluations, EPRI, Palo Alto, CA: 2004. 1009541

C4 McKay, M. D., R. J. Beckman, and W. J. Conover, "A Comparison of Three Methods forSelecting Values of Input Variables in the Analysis of Output from a Computer Code,"Technometrics, Vol. 21, No. 2, May 1979.

C5 Pressurized Water Reactor Steam Generator Examination Guidelines: Revision 6, EPRI, PaloAlto, CA: September 1997. 1003138.

C-41