Overview
•DCS is in operation 24/7
•DCS team activities
• Maintenance
• Development of new features
Generic Panel (improvements)
RP motorization panel (new panel)
• Shows motorization status for all the pots• Log messages and configuration and special commands
RP pot panel (redesign)
• Shows only information of an specific pot• Motorization and Silicon Detectors
LHC handshake (redesign)
• DIP and LHC Handshake are now isolated processes• This should improve stability of the LHC Handshake• Handshake problems reported to the JCOP support,
and some things will be improved, but not everything
Self-Monitoring box
ELMB boxes (under testing)
Sensors box for T1
USB-ethernet adapters
• ELMB -> CANbus -> SYSTEC -> USB -> DIGI -> ethernet
• Will help in maintenance, if a computer crashes,all software can be redeployed to another node
withouthaving to recable in the counting room
• Already in production in the lab• Will be used also in H8
Moving of the laboratory to 506
• Everything ready and operational
• But took several working days….of several people….
LHC information (done)
• Excel file for all the information we need (similar to pinout tables)• Every week something is changing!!!!• Integration of BPM ‘within days’
Consolidation activities (done)
• Exactly the same software in IP5 that in the laboratory• As a ‘shortcut’ to provide something working, the computer
names were hardcoded last year, so it was not possible to debug properly the system before sending to production.
• Migration of SVN repositories• From bigbrother.cern.ch to the central services
• Fixes in the User Interface
DCS in H8 for RpSi
Replication of the production software form IP5
Workforce confirmed
50% PP CERN100% FLR 3 years CERN100% IA 2.5 years CERN20% FR 1 year CERN
50% JS 0.5 year Budapest100% VT 3 months Trainee Kuopio-Helsinki100% JT 3 months Trainee Kuopio100% GP 3 months Summer Student
Issues (from Jira)
• Last 30 days, not in absolute scale
• All maintenance effort on Ivan and Fernando• Is good having trainees, but they need supervision
They stay ‘short’ time have to focus in very specific tasks
13 new issues
7 issues resolved
98 issues open
date
Next steps (same list of Feb)
• Fix internal DCS problems (some parts have to be rewritten to add new functionality)
• Include in the pinout tables the LV max HW currents
• Finish LHC information integration
• RadMon readout
• Fix User Interface problems (to allow FSM operation)
• Propagation of states in the FSM tree (but no automatic actions)
OK
?
DCS status summary (Feb 2010)
DCS status summary (May 2010)
Milestone Plan
• 2 WP closed• 3 WP started
-3 months
Too many things on going
Activity Schedule D8 (done)
Activity Schedule D9 (in progress)
Activity Schedule I7 (in progress)
?