S.No Observation Points Target Date Responsibilities Status 1 GIS Floor Handed over (Two bays) CPL/Andritz 1) Bracing welding is in progress. 6 sets completed out of 8. 2)1no Girder joint completed of 10T EOT crane. 6 nos rail lifted. 2 U-3 Bus Duct Handed Over Andritz Scaffolding for erecting bus ducts from 11th & 12th elements completed on 15-04-14. No work on 16-04-14 due to manpower shortage. 3 U-4 Bus Duct Handed Over Andritz No work due to man power shortage. 4 U-5 Bus Duct Handed Over Andritz Painting of welded joints is in progress. 5 U-6 Bus Duct Handed Over Andritz Enclosure welding between MW2 & MW3 completed and between MW3 & MW4 is in progress. 6 400KV XLPE cable support 3/20/2014 Andritz AHPL has given information that cable supports will be reaching site by 10th of Feb. No further information. 7 Unit - 1 Handed Over Andritz 1) Cable tray erection for Excitation panel is in progress. 2) Main header to cooler trial assembly & tacking completed inside barrel. 3) 80 NB Pipeline works from Accumulator station to OPU completed. remove point 4 8 Unit - 2 Handed Over (inside barrel) AHPL 1) Stator centering is in progress. 2) MIV concreting works withheld due to non availability of base plate. 3) Scaffolding is in progress from cooling water sump for cable tray erection. 9 Unit-3 (EL 777.90 slab completion) 4/30/2014 CPL 1) Slab shuttering works is in progress. Handed over for Upper bracket sole plate erection. 10 Unit-4 (EL 777.90 slab completion) 4/30/2014 CPL Slab staging removal is in progress. 11 Unit-5 (EL 777.90 Slab completed) Handed Over (inside barrel) AHPL/AIPL 1) Grinding of fitting flange is in progress. 5 nos completed out of 10. 12 Unit-6 3/31/2014 Andritz 1) Removal of screen protection from screened cables is in progress in Generator marshalling box & UCB is in progress. 2) Cable termination is in progress in UAB. 3) Cable glanding is in progress in UCB. 4) Angles fixed in the neutral side cut out outside the barrel. Neutral side element (N-EL-1) shifted. 5) Lower bearing housing and Bearing housing bottom plate erection completed. 6) Aeration housing erection is in progress. 7) Air coolers are being shifted & cleaned. Remove point 5 13 Unit-6 (MIV) Handed Over Andritz Compensator fixing and trial checking is in progress for D & D pipeline. 14 U-6 heat exchanger 3/15/2014 CPL Pipeline assembly work is in progress. 15 Balance GT foundation 4/30/2014 AIPL/Andritz 13 bay handed over. 16 Pothead yard Civil Work 3/31/2014 AIPL 1) One blast taken for GT3 foundation excavation. 17 Pothead yard EBOP Work 4/15/2014 Andritz 1) GT #2 tower erection is in progress.Bracing fixing is in progress. Present height of tower is 22.5m. 18 Control block Floor (EL 783.00) Handed Over AHPL/AIPL 1) Cable glanding is in progress in Unit protection panel - 2 2) Gland plate fixed in Unit protection panel - 1. 19 Control Block Floor (EL 777.90) Handed Over Andritz 6 cables laid from DC DB-2 to unit protection panel 1,2 & 3 20 Control Block Floor (EL 770.50) Handed Over Andritz Scaffolding is in progress for cable tray erection from EL 777.90 to EL 770.50 21 Control Block Floor (EL 764.80) Handed Over Andritz No work. 07-04-14 Rotor #2: Pole lead connection to Item #6 & 7 completed. Final lead connection trial assembly is in progress. 4/16/2014 Rotor #3: Tangential key fixing is in progress. 4/14/2014 Stator #4: 1st intermediate pressing completed. Upper bracket-U#1: Cleaning of thrust bearing platform completed. Pivot & spring plate cleaning is in progress. Stator #5: Stator intermediate sole plate blue matching completed. 23 Fire Fighting system Andritz Fire fighting pipeline welding work is in progress in CAT. 7 No's pipe joint root welding completed. 24 Storage Andritz Andritz 22 Service Bay Jobs Present status of Work Front Date: 22-04-14

Status Report 22-04-14

Embed Size (px)

Citation preview

Page 1: Status Report 22-04-14

S.No Observation Points Target Date Responsibilities Status

1 GIS FloorHanded over (Two

bays)CPL/Andritz

1) Bracing welding is in progress. 6 sets completed out of 8.

2)1no Girder joint completed of 10T EOT crane. 6 nos rail lifted.

2 U-3 Bus Duct Handed Over AndritzScaffolding for erecting bus ducts from 11th & 12th elements completed on 15-04-14. No work

on 16-04-14 due to manpower shortage.

3 U-4 Bus Duct Handed Over Andritz No work due to man power shortage.

4 U-5 Bus Duct Handed Over Andritz Painting of welded joints is in progress.

5 U-6 Bus Duct Handed Over AndritzEnclosure welding between MW2 & MW3 completed and between MW3 & MW4 is in

progress.

6 400KV XLPE cable support 3/20/2014 AndritzAHPL has given information that cable supports will be reaching site by 10th of Feb. No further

information.

7 Unit - 1 Handed Over Andritz

1) Cable tray erection for Excitation panel is in progress.

2) Main header to cooler trial assembly & tacking completed inside barrel.

3) 80 NB Pipeline works from Accumulator station to OPU completed. remove point 4

8 Unit - 2Handed Over

(inside barrel)AHPL

1) Stator centering is in progress.

2) MIV concreting works withheld due to non availability of base plate.

3) Scaffolding is in progress from cooling water sump for cable tray erection.

9 Unit-3 (EL 777.90 slab completion) 4/30/2014 CPL 1) Slab shuttering works is in progress. Handed over for Upper bracket sole plate erection.

10 Unit-4 (EL 777.90 slab completion) 4/30/2014 CPL Slab staging removal is in progress.

11 Unit-5 (EL 777.90 Slab completed)Handed Over

(inside barrel)AHPL/AIPL 1) Grinding of fitting flange is in progress. 5 nos completed out of 10.

12 Unit-6 3/31/2014 Andritz

1) Removal of screen protection from screened cables is in progress in Generator marshalling

box & UCB is in progress.

2) Cable termination is in progress in UAB.

3) Cable glanding is in progress in UCB.

4) Angles fixed in the neutral side cut out outside the barrel. Neutral side element (N-EL-1)

shifted.

5) Lower bearing housing and Bearing housing bottom plate erection completed.

6) Aeration housing erection is in progress.

7) Air coolers are being shifted & cleaned. Remove point 5

13 Unit-6 (MIV) Handed Over Andritz Compensator fixing and trial checking is in progress for D & D pipeline.

14 U-6 heat exchanger 3/15/2014 CPL Pipeline assembly work is in progress.

15 Balance GT foundation 4/30/2014 AIPL/Andritz 13 bay handed over.

16 Pothead yard Civil Work 3/31/2014 AIPL 1) One blast taken for GT3 foundation excavation.

17 Pothead yard EBOP Work 4/15/2014 Andritz1) GT #2 tower erection is in progress.Bracing fixing is in progress. Present height of tower is

22.5m.

18 Control block Floor (EL 783.00) Handed Over AHPL/AIPL1) Cable glanding is in progress in Unit protection panel - 2

2) Gland plate fixed in Unit protection panel - 1.

19 Control Block Floor (EL 777.90) Handed Over Andritz 6 cables laid from DC DB-2 to unit protection panel 1,2 & 3

20 Control Block Floor (EL 770.50) Handed Over Andritz Scaffolding is in progress for cable tray erection from EL 777.90 to EL 770.50

21 Control Block Floor (EL 764.80) Handed Over Andritz No work.

 07-04-14Rotor #2: Pole lead connection to Item #6 & 7 completed. Final lead connection trial assembly

is in progress.

4/16/2014 Rotor #3: Tangential key fixing is in progress.

4/14/2014 Stator #4: 1st intermediate pressing completed.

Upper bracket-U#1: Cleaning of thrust bearing platform completed. Pivot & spring plate

cleaning is in progress.

Stator #5: Stator intermediate sole plate blue matching completed.

23 Fire Fighting system AndritzFire fighting pipeline welding work is in progress in CAT. 7 No's pipe joint root welding

completed.

24 Storage Andritz

Andritz22 Service Bay Jobs

Present status of Work Front Date: 22-04-14