Status of the Test Beam Line S. Döbert, CLIC Meeting, 1.6.2007 42.5 m 8 m 2 m D F F D D F F D F D DUMP D F D F F D ITB 1.85m CALIFES Probe beam injector LIL-ACS LIL-ACS LIL-ACS D F D D F D D F DUMP 0.75 1.4m 1 DUMP 22.4 m TBL 2.5m Transport path DUMP DUMP 22 m 2.0m D F D F D F D F D F D F D F D F 3.0m 3.0m 6 m D F D F D F D 16.5 m TBTS 16 m TL2’

Status of the Test Beam Line · o Modular Construction: Build FODO lattice first, add PETS units ... ( See CTF3-Note-076) o New TBL-PETS frequency will be 12 GHz ( this decision makes

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Status of the Test Beam Line · o Modular Construction: Build FODO lattice first, add PETS units ... ( See CTF3-Note-076) o New TBL-PETS frequency will be 12 GHz ( this decision makes

Status of the Test Beam Line

S. Döbert, CLIC Meeting, 1.6.2007

42.5 m

8 m

2m

D FFD

DF

F

D F DDUMPD F D

F

FD

ITB

1.85m

CALIFES Probe beam injectorLIL-ACSLIL-ACSLIL-ACSD F D

D F D

DFDUMP

0.75

1.4m

1

DUMP

22.4 mTBL

2.5m

Transport path

DUMP

DUMP 22 m2.0m

DF DF DF DF DF DF DF DF

3.0m3.0m6 m

D F DF DF D

16.5 mTBTS16 m

TL2’

Page 2: Status of the Test Beam Line · o Modular Construction: Build FODO lattice first, add PETS units ... ( See CTF3-Note-076) o New TBL-PETS frequency will be 12 GHz ( this decision makes

Goals and Requirementso High energy spread beam transport, low losses

(Bench mark simulations)

o RF Power Production, Stability(End Energy <50%, 2.6 GW of RF power)

o Alignment (Test procedures for BBA)(100 microns alignment for PETS)

o Drive Beam Stability, Wake fields(no direct measurement of the wake fields)

o ‘Realistic’ show case of a CLIC decelerator

o Industrialization of complicated RF components

o Modular Construction: Build FODO lattice first, add PETS units(Different Designs or Frequencies possible)

Page 3: Status of the Test Beam Line · o Modular Construction: Build FODO lattice first, add PETS units ... ( See CTF3-Note-076) o New TBL-PETS frequency will be 12 GHz ( this decision makes

Status 01/2007o We have a conceptual design including schedule and cost

( See CTF3-Note-076)

o New TBL-PETS frequency will be 12 GHz( this decision makes the TBL-experiment more relevant for CLIC)

o Detailed simulations started (see Erik’s talk)

o Design and Prototyping of key components started (BPM, Movers and PETS)

42.5 m

8 m

2m

D FFD

DF

F

D F DDUMPD F D

F

FD

ITB

1.85m

CALIFES Probe beam injectorLIL-ACSLIL-ACSLIL-ACSD F D

D F D

DFDUMP

0.75

1.4m

1

DUMP

22.4 mTBL

2.5m

Transport path

DUMP

DUMP 22 m2.0m

DF DF DF DF DF DF DF DF

3.0m3.0m6 m

D F DF DF D

16.5 mTBTS16 m

TL2’

Page 4: Status of the Test Beam Line · o Modular Construction: Build FODO lattice first, add PETS units ... ( See CTF3-Note-076) o New TBL-PETS frequency will be 12 GHz ( this decision makes

Reduced plans for shutdown 2007/2008o Because budget constraints revised plan necessary

o Only one module to test the prototype elements

42.5 m

8 m

2m

D FFD

DF

F

D F DDUMPD F D

F

FD

ITB

1.85m

CALIFES Probe beam injectorLIL-ACSLIL-ACSLIL-ACSD F D

D F D

DUMP

0.75

1.4m

1

DUMP

TBL

2.5m

Transport path

DUMP

DUMP 22 m2.0m

DF

3.0m3.0m

D F DF DF D

16.5 mTBTS16 m

TL2’

Page 5: Status of the Test Beam Line · o Modular Construction: Build FODO lattice first, add PETS units ... ( See CTF3-Note-076) o New TBL-PETS frequency will be 12 GHz ( this decision makes

TBL-cell

100 cm 25 cm15 cm

TBL cell length 140 cm

PETS: active length max 80 cm

16 cells planned = 22.4 m

23 mm aperture in PETS

24 mm max in Quads/BPM’s

Ion Pump

140 cm

QuadBPM

PETS

RF-Load

Mover

FODO lattice:

β-max = 4.72 m

β-min= 0.83 m

μ-cell = 90 deg

Page 6: Status of the Test Beam Line · o Modular Construction: Build FODO lattice first, add PETS units ... ( See CTF3-Note-076) o New TBL-PETS frequency will be 12 GHz ( this decision makes

TBL2007/2008

BPM

Dipole

MTV

MTV

BPR

Total: ~6 m

Quads

To Test stand

2m

Quads, TL2

Steering

BPM

Prototype Module

WCM

Page 7: Status of the Test Beam Line · o Modular Construction: Build FODO lattice first, add PETS units ... ( See CTF3-Note-076) o New TBL-PETS frequency will be 12 GHz ( this decision makes

Status of the prototype components

PETS: rf design finished (see Igor’s talk), PETS manufacturing and tank design progressing

(see Fernando’s talk)

BPM’s: design of the pick up and front end electronics finished,prototype fabrication started

Quads: New design by Th. Zickler, prototype for next year

Quad-Movers: Ciemat prototype ready to be shipped to CERN

High power rf: directional couplers and loads needed

Low Level rf: conceptual design started

TL2’ diagnostics: Should be ready if started now

Page 8: Status of the Test Beam Line · o Modular Construction: Build FODO lattice first, add PETS units ... ( See CTF3-Note-076) o New TBL-PETS frequency will be 12 GHz ( this decision makes

Prototypes

Quad moving table,

Prototype finished

Page 9: Status of the Test Beam Line · o Modular Construction: Build FODO lattice first, add PETS units ... ( See CTF3-Note-076) o New TBL-PETS frequency will be 12 GHz ( this decision makes

Prototypes

PETS tank

Page 10: Status of the Test Beam Line · o Modular Construction: Build FODO lattice first, add PETS units ... ( See CTF3-Note-076) o New TBL-PETS frequency will be 12 GHz ( this decision makes

Prototypes

12 GHz high power coil load,

Expected delivery ~3 weeks

Page 11: Status of the Test Beam Line · o Modular Construction: Build FODO lattice first, add PETS units ... ( See CTF3-Note-076) o New TBL-PETS frequency will be 12 GHz ( this decision makes

PrototypesBPM

Page 12: Status of the Test Beam Line · o Modular Construction: Build FODO lattice first, add PETS units ... ( See CTF3-Note-076) o New TBL-PETS frequency will be 12 GHz ( this decision makes

PrototypesBPM-analog electronics

Design finished,

PCB finished,

Prototype testing has to be done

Page 13: Status of the Test Beam Line · o Modular Construction: Build FODO lattice first, add PETS units ... ( See CTF3-Note-076) o New TBL-PETS frequency will be 12 GHz ( this decision makes

Tentative TBL-Schedule

Jan-Mar 08 Apr-Jun 08 Jul-Sep 08

Jan-Mar 09

Install a bit more ?

Install up to

8 PETS

1.2 GW

Run with

8 PETS

1.2 GW

Apr-Sep 09

Jul-Dec 06 Jan-Mar 07 Apr-Jun 07 Jul-Sep 07 Oct-Dec 07

Define module ,

Diagnostics,

12 GHz PETS

Fabrication of prototypes

Test of Prototypes

Install 1 Module

Oct-Dec 09

Install

remaining

8 PETS

Run with

16 PETS

2.4 GW

Apr-Jun 10Jan-Mar 10

Oct-Dec 08

Series production

Page 14: Status of the Test Beam Line · o Modular Construction: Build FODO lattice first, add PETS units ... ( See CTF3-Note-076) o New TBL-PETS frequency will be 12 GHz ( this decision makes

Conclusions

With the current budget only prototyping can be done this year

A minimal program of testing one prototype module isfeasible and will help a lot for the project.Prototypes of BPM, electronics, quad mover and PETS arebeing built by our collaborators

If the prototypes are successful and the budget in 2008 sufficient the final project is only slightly delayed