Status of the LHCb Experiment LHCb RRB at CERN 25 April 2007 on behalf of the LHCb Collaboration Tatsuya NAKADA CERN and EPFL CERN-RRB-2007-044 24 April 2007

Status of the LHCb Experiment LHCb RRB at CERN 25 April 2007

  • Upload
    kalea

  • View
    35

  • Download
    0

Embed Size (px)

DESCRIPTION

CERN-RRB-2007-044 24 April 2007. Status of the LHCb Experiment LHCb RRB at CERN 25 April 2007. on behalf of the LHCb Collaboration Tatsuya NAKADA CERN and EPFL. Contents. Construction and Installation Cost and Funding Conclusions. I) Construction and Installation. LHCb Spectrometer. - PowerPoint PPT Presentation

Citation preview

Page 1: Status of the LHCb Experiment LHCb RRB at CERN 25 April 2007

Status of the LHCb ExperimentLHCb RRB at CERN

25 April 2007

on behalf of the LHCb Collaboration

Tatsuya NAKADACERN

andEPFL

CERN-RRB-2007-04424 April 2007

Page 2: Status of the LHCb Experiment LHCb RRB at CERN 25 April 2007

25 April 2007 LHCb RRB Status Report 2

Contents

I) Construction and Installation

II) Cost and Funding

III) Conclusions

Page 3: Status of the LHCb Experiment LHCb RRB at CERN 25 April 2007

25 April 2007 LHCb RRB Status Report 3

I) Construction and Installation

LHCb Spectrometer

VELO

RICH1

TT

Magnet

OT

RICH2 Calo. System

Muon System

Page 4: Status of the LHCb Experiment LHCb RRB at CERN 25 April 2007

25 April 2007 LHCb RRB Status Report 4

AECAL

IT+OT

MAG.

LHC CRYO

POINT 7

POINT 1R

AD

IAT

ION

SH

IEL

D

PX SHAFT

RICH2B C

Mu-system

VELO

RB86

HCAL

IP8

RICH1

1) Experimental Area

Page 5: Status of the LHCb Experiment LHCb RRB at CERN 25 April 2007

25 April 2007 LHCb RRB Status Report 5

IP8 now

Page 6: Status of the LHCb Experiment LHCb RRB at CERN 25 April 2007

25 April 2007 LHCb RRB Status Report 6

Gas and cooling pipes installed in the detector areaMost of the long distance cables installedRemaining major work:

complete the shielding wallgas pipe installation on the gantry

The upper part of theshielding wall

Cooling pipes for TT

Page 7: Status of the LHCb Experiment LHCb RRB at CERN 25 April 2007

25 April 2007 LHCb RRB Status Report 7

2) Beam Pipe

stainless steel section (UX85/4)

1st and 2nd 10 mrad Be section (UX85/2-3)

25 mrad Be section (UX85/1)

Al exit window

Leaks in UX85/3 repaired by varnishingserious concern for long term stability due to radiationLHC vacuum group (AT/VAC ) requesting to prepare a replacement piece

Complete beam pipe installed and leak testedbake out in May

Al spare beam pipe now being made by CERN

Page 8: Status of the LHCb Experiment LHCb RRB at CERN 25 April 2007

25 April 2007 LHCb RRB Status Report 8

behind TT

through the magnet

in the calorimeters

end of 25 mradsection

Al bellow

10 mrad section

Page 9: Status of the LHCb Experiment LHCb RRB at CERN 25 April 2007

25 April 2007 LHCb RRB Status Report 9

3) Magnet (funded by Common Fund)

Construction completedand

commissionedWork to incorporate the measured field map

in progress: method being tested by MC data

difference between“true” and “parameterization”By (main component) in the

z = 5 m (in the magnet) plane very small difference

Page 10: Status of the LHCb Experiment LHCb RRB at CERN 25 April 2007

25 April 2007 LHCb RRB Status Report 10

4) VErtex LOcatorVELO tank fully equipped with RF foils and NEG coated

ready to receive the detector modules

(funded by CH, DE, GB, NL)

RF boxes developed some leaks;-between prim.-sec. vacuums no immediate concern-NEGtank saturate may become a problem with high Ibeam?

Two RF boxes

exit window

looking through from upstream

VELO tank and signal cables

Page 11: Status of the LHCb Experiment LHCb RRB at CERN 25 April 2007

25 April 2007 LHCb RRB Status Report 11

Sensor module production completedRight Detector Half fully assembled

undergoing full electrical testsLeft Detector Half assembly close to completionCommissioning of the final electronics in progress

Right Detector Half

constraint system

21 VELO modules+2 pile-up sensors

repeater cards

Page 12: Status of the LHCb Experiment LHCb RRB at CERN 25 April 2007

25 April 2007 LHCb RRB Status Report 12

5) RICH (funded by CERN, CF, GB, IT)

RICH-2: In place and Photon Detector installedIn situ commissioning started

RICH-1: Gas enclosure completed and tested in situC-fibre mirror produced and coated

mirror system being assembled and aligned

CERN CF Mirrors

50

55

60

65

70

75

80

85

90

95

100

200 250 300 350 400 450 500 550 600

W.L. (nm)

R (%)

sc352 N°4

sc354 N°2

sc355 N°3

sc356 N°1

RICH-2 HPD column installation

RICH-1 four uncoatedspherical mirrors

Reflectivity of MgF2 coating

Page 13: Status of the LHCb Experiment LHCb RRB at CERN 25 April 2007

25 April 2007 LHCb RRB Status Report 13

All the HPDs, except spares, producedIn situ readout and slow control commissioning started

RICH-2 temperature reading

A screen shot of RICH DAQ testing

Page 14: Status of the LHCb Experiment LHCb RRB at CERN 25 April 2007

25 April 2007 LHCb RRB Status Report 14

6) Outer Tracker (funded by CERN, CF, CN, DE, NL, PL)

Outer Tracker installation completedInstallation of services in progressIn situ commissioning started

long term stability of TDC count

cabling work OT stations

Page 15: Status of the LHCb Experiment LHCb RRB at CERN 25 April 2007

25 April 2007 LHCb RRB Status Report 15

Progress on the “aging” issue:Problem is not due to the accumulated doseFast gain loss at a particular rate,

expected in the regions closest to the beam pipeAn effective prevention method now identified

warming up to ~40C and flush with gas for many days

50 % gain loss15% efficiency loss/tube

After 10 daysof heating

Expected current profilefor L=21032

y

x

IT

Gain profilebefore heating

NB different scale

Page 16: Status of the LHCb Experiment LHCb RRB at CERN 25 April 2007

25 April 2007 LHCb RRB Status Report 16

All the modules have been installedspecial heating tool needed for in situ treatmentprototype produced and to be tested in the vertical position

Warming up procedure needs to be precisely defined for how long, at which temperature, with which gas flow, all the modules or only the central ones

Recovery is possible with positive and negative HV treatments

heating tool prototype

heaterjacket

Page 17: Status of the LHCb Experiment LHCb RRB at CERN 25 April 2007

25 April 2007 LHCb RRB Status Report 17

7) Silicon Tracker (funded by CERN, CH, DE, ES, UA)

Ladder production almost completed100% for TT and >70% for IT completed

IT detector boxes now finalised

IT improved test system one-sensor and two-sensor detector boxes

Page 18: Status of the LHCb Experiment LHCb RRB at CERN 25 April 2007

25 April 2007 LHCb RRB Status Report 18

TT infrastructure installed and protection of the beam pipeagainst TT frame closing verified

TT cable chain beam pipe

TT frame

RICH-1 window

Digitizer cards: all produced but set back due to deliveredcomponents not matching specificationsbeing repairednot critical, but inconvenient for commissioning

Page 19: Status of the LHCb Experiment LHCb RRB at CERN 25 April 2007

25 April 2007 LHCb RRB Status Report 19

8) Calorimeter System (funded by CERN, CF, ES, FR, RO, RU, UA)

Cabling of Scintillator Pad Detector/Preshower in progressEcal/Hcal front-end all installed and commissioning advanced

C-side 183 PS cables in the cable chainCal front-end cards

Cal racks on the balcony

Page 20: Status of the LHCb Experiment LHCb RRB at CERN 25 April 2007

25 April 2007 LHCb RRB Status Report 20

9) Muon SystemAll MWPCs and GEMs produced and tested, except sparesC-side M2-M5 fully installed and commissioning startedA-side M2-M5 installation of infrastructure being completed

chamber installation in progress

(funded by CERN, CF, IT, RU)

C-side M2 station completed A-side M2 wall

Page 21: Status of the LHCb Experiment LHCb RRB at CERN 25 April 2007

25 April 2007 LHCb RRB Status Report 21

Chambers, tested before installation in the laboratory and at CERN. Tested again after the installation in situ

Procurement for the M1 support components started: some more details to be worked out: very tight schedule

gas tightness test

noise test

0

5

10

15

20

25

2100 2200 2300 2400 2500 2600 2700 2800 2900 3000

HV (V)

Count per pad per 100 sec

M5R1#08 horizont M1R2#04 horizont

2500V TH=4fC@15mV/fC 2500V TH=5fC@15mV/fC

300V

0.07Hz/pad

0.14Hz/pad

X-talk~0.5/14=3.6%

X-talk~0.25/7=3.6%

M5R1

M1R2

TH=7fC@15mV/fC

plateau test with cosmicsbefore installation

Page 22: Status of the LHCb Experiment LHCb RRB at CERN 25 April 2007

25 April 2007 LHCb RRB Status Report 22

10) Trigger and Online(funded by CERN, CF, CH, DE, FR, ES, IT, NL)

Level-0 trigger consists of four componentsPile-up L0

CalorimetersL0

MuonL0

DecisionUnit

readyin production

They aremostly a part ofthe calorimeter

electronicsfour dedicated

detectors integratedin VELO

HLT is now optimized for 1 MHz readout data

muon processors L0DU

already enough produced for commissioning quadrant

Page 23: Status of the LHCb Experiment LHCb RRB at CERN 25 April 2007

25 April 2007 LHCb RRB Status Report 23

Installation of the online equipment and necessary cablingprogressing in the control room (surface) and in the barrack (accessible part of the underground area)

on thesurface

undergroundbarrack

storage disk array TELL1’s

Data networkswitches

Control room

Page 24: Status of the LHCb Experiment LHCb RRB at CERN 25 April 2007

25 April 2007 LHCb RRB Status Report 24

11) ComputingPhysics quality software in place

Reconstruction package released to be used for physics performance studies in preparation for data

Further tracking optimization for 900 GeV data, if needed

Global alignment challenge to be launched soon

Data Challenge 06 on going LHCb GRID computing after MC production,

i.e. reconstruction and stripping still encounters difficultyin data access. Closely working with the site, LCG projectand middleware developers to overcome the problem

Full testing of analysis in a GRID environment is stillpending.

Page 25: Status of the LHCb Experiment LHCb RRB at CERN 25 April 2007

25 April 2007 LHCb RRB Status Report 25

III) Cost and FundingChange from the last RRB in October 2006Cost: No change 75.341 MCHF

Funding: New contributions Spain (20 kCHF), UK (400 kCHF)

requests made for CPU’s in 2006 approvedFR (300 kCHF)

in addition to already made extra contributionBR (55 kCHF)

first contribution to the detector costUS-NSF (30 kCHF)

2007 contribution to the CPU’s450 kCHF request for 2007-2009 not approved

Missing: 497 kCHF(Was 1302 kCHF at the time of the October 2006 RRB)

Page 26: Status of the LHCb Experiment LHCb RRB at CERN 25 April 2007

25 April 2007 LHCb RRB Status Report 26

(in kCHF) MoU Extra for Extra forCountry signed detector CPUBrazil 0 0 55China 100 0 0France 7500 0 800Germany BMBF 3757 381 300Germany MPG 2200 0 0Italy 10000 847 0Netherlands 6300 381 0Poland 500 0 0Romania 300 0 0Russia 2500 0 0Spain 2000 0 20Switzerland 7900 0 0UK 10300 44 400Ukraine 200 0 0US-NSF 0 0 560CERN 16700 799 0

April 2007Total Cost75.341 MCHF

Total funding74.844 MCHF

Still missing497 kCHF

Page 27: Status of the LHCb Experiment LHCb RRB at CERN 25 April 2007

25 April 2007 LHCb RRB Status Report 27

Total CPU needs: 3.420 MCHFmissing 497 kCHF not an immediate problempossible further contribution from BR, and others

Additional cost on horizon:

-replacement Be beam pipe section: UX85/3expected to be substantial; i.e. O(MCHF)

needed only in a few years but long production timecommitment required soon…

-VELO replacement RF boxescost expected to be not high

but expert manpower and R&D may be needed

Page 28: Status of the LHCb Experiment LHCb RRB at CERN 25 April 2007

25 April 2007 LHCb RRB Status Report 28

III) Conclusions1)Installation of the spectrometer is nearing completion, and

commissioning has started for many subdetectors. Computing and physics preparation for data ongoing.

2)Schedule is still tight, in particular, for the production ofIT, RICH-1 mechanics integration, and Muon system installation

3)Further additional contributions approved for the CPU farm55 kCHF (Brazil), 300 kCHF (France), 20 kCHF (Spain), 400 kCHF (UK) and 30 kCHF (US-NSF)

497 kCHF still missing for the CPU farm.Vacuum pipe replacement will require additional money.Continue to seek extra funding: pending request to Italy, further requests to Brazil, US-NSF, etc.

Page 29: Status of the LHCb Experiment LHCb RRB at CERN 25 April 2007

25 April 2007 LHCb RRB Status Report 29