Status of LS1 collimator maintenance

O. Aberle – 03/03/14With input from P. Bestmann, S. De Man and J. Lendaro

Page 2: Status of LS1  collimator maintenance

O. Aberle – CWC2

Main activities during the LS1 Collimator exchange (TCTP vs TCT, IR 1, 2, 5

and 8) Collimator installation (TCLP, TCL6 in IR1

and 5) New TCAPD (IR 3) New installation commissioning Collimator standard maintenance Special maintenance TIM / Robot intervention/observations Alignment Outlook

March 03rd 2014

Page 3: Status of LS1  collimator maintenance

O. Aberle – CWC3

Collimator exchange New production of 16 + 4 TCTP New production of 2 + 1 TCSP New production of 2 + 1 TCAPD Preparation of 2 spare TCLP Preparation of 1 spare TCP Layout modification in Pt. 8, removal of 2 TCTVB, shifting TCLIA Pt. 1: Replacement of 4 TCT + by 4TCTP + installation of 2 TCLP and 2 TCT Pt. 2: Replacement of 2 TCT + 2 TCLP by 4 TCTP Pt. 3: Installation of 2 new TCAPD Pt. 5: Replacement of 4 TCT + by 4TCTP + installation of 2 TCLP and 2 TCT Pt. 6: Replacement of 2 TCS by 2 TCSP Pt. 7: Remove first TCP on the right side and the three TCP on the left side

during ventilation door installation (to prevent damage) and exchange the skewed TCP of IR7L (water cooling)

Pt. 8: Replacement of 2 TCT + 2 TCTVB by 4 TCTP

March 03rd 2014

Page 4: Status of LS1  collimator maintenance

O. Aberle – CWC4

New installation commissioning Check each collimator mechanics and

electronics. Full check of controll system Slot and infrastructure (support, cabling, cooling

water) Installation and alignment Vacuum connection and bake-out Collimator standard maintenance

March 03rd 2014

Page 5: Status of LS1  collimator maintenance

O. Aberle – CWC5

Collimator standard maintenance Check each collimator mechanics and

electronics. Cycle from out to in, to anti-collision and back to out. Check 5th axis for clearance Check water cooling flow Check temperature sensors Check switches, LVDT’s, resolvers, motors and

drivers Map sound profile for each collimator Check rails Check roller screws

March 03rd 2014

Page 6: Status of LS1  collimator maintenance

O. Aberle – CWC6

Collimator roller screw replacement (2011-12)

March 03rd 2014

Dust and debris in the end cap and the housing

Some dry screws regreased

Up to date 3 rollers screws have been exchanged.-No linear bearing-2 LVDT‘s-1 motor-2 switches

Page 7: Status of LS1  collimator maintenance

O. Aberle – CWC7

TIM and Robot intervention

March 03rd 2014

Sound inspection of the collimators done with the TIM in S34 (23/24 April 2012).

Visual and acoustic inspections with camera can be useful in the future (TIM automatically, Telemax robot more flexible).

Vacuum disconnection testing with the Telemax robot on-going.

Use of robot for visual inspections/leak tests (He spray).

Profit from the long shutdown to verify the integration and do some hardware tests to confirm the procedures.

Page 8: Status of LS1  collimator maintenance

O. Aberle – CWC8

Alignment

March 03rd 2014

Survey is working in the whole machine. During smoothing, magnets will be aligned

and collimators checked (and adjusted if needed).

IR 3 and IR 7 are equipped with additional targets for remote verification with the stretched wire.

New collimators (TCTP, TCSP, TCLP, TCT (TCL6) and TCAPD) will be aligned.

The TCP’s removed during the installation of the ventilation doors + the skewed TCP in IR7L to be checked (high radiation levels, how much deviation can be tolerated?).

Page 9: Status of LS1  collimator maintenance

O. Aberle – CWC9

Schedule – linked to LS1 LHC planning

March 03rd 2014

 

Number of systems Network Installation

230V power supply cabling 230V powered R2E cabling works Other works Control System

InstallationSystems ready for

commissioningCollimator added

or replaced during LS1

Collimator not modified during

LS1Sector Cooldown L Sector Cooldown R Powering

Tests SeqControls

Commissioning starting date

Controls Commissioning

end dateNew collimators Installation date

New collimators Commissioning/calibration

starting date

New Collimators Commissioning/Calibration end

dateCalibration

starting dateCalibration end

date

US15 4 + 1 for TCL-6 OK OK OK OK   OK YES 6 + 2 TCL6 2 2 June 30 June   3 10. Mrz 14. Mrz1L TCTP 14/04/20141R TCTP 5/03/2014TCL-6 ?

     

 

UA23 6 + TDI OK OK Planned 28/02/2014 -   OK No 3 (including TDI) 7 30 June -   4 17. Mrz 21. Mrz TCTP 12/05/2014TDI 28/04/2014      

 

UA27 2 OK OK Planned 28/02/2014 -   OK No 2 2 - 11 August   5 24. Mrz 28. Mrz TCTP 12/05/2014       

UJ33 7 - OK OK -   Ok YES 0 18 11 August 15 September   2 25. Feb 07. Mrz TCAPD 14/02/2014       

USC55 4 + 1 for TCL-6 No No. End of March End of MarchCables available around 20th March. TCL-6 cables :  L 15/04 

, R 30/05  No No 6 + 2 TCL6 2 22 September 28 July   10 12. Mai 16. Mai

5L TCTP 14/07/20145R TCTP 9/06/2014TCL-6 ?

     

 

US65 1 - OK OK -   OK System to switch ON 2 0 28 July 5 May   6 31. Mrz 02. Apr 6L TCSP 13/03/20146R TCSP 18/02/2014      

 

TZ76 21 OK In progress Planned end of MarchIn progress. Cables 

reconnection in TZ76: date to confirm 

  OK No 4 (TCP) 34 5 May 11 August   9 22. Apr 09. Mai 7R TCP 18/02/20147L TCP 10/03/2014       

 

UA83 2 OK In progress Planned 3/03/2014 - TCTVB Cabling in progress  OK No 3 1 11 August -   8 14. Apr 18. Apr TCTP 9/06/2014      

 

UA87 5 + TDI OK In progress Planned 3/03/2014 -TCTVB Cabling. Finished: To check 

OK No 3 (including TDI) 6 - 2 June   7 02. Apr 11. Apr TCTP 14/04/2014      

 

BA7 1 OK OK OK -   OK YES 0 1 - -   1 24. Feb 24. Feb -       

Frame given by LHC planning, Julie is coordinating with Vacuum, transport, powering etc…

Cabling and control system availability Installation readiness of new collimators

Page 10: Status of LS1  collimator maintenance

O. Aberle – CWC10

Schedule – details by Jerome

March 03rd 2014

 

Number of systems Control System Installation

Systems ready for commissioning

Collimator added or replaced during LS1

Collimator not modified during

LS1Seq

Controls Commissioning

starting date

Controls Commissioning

end dateNew collimators Installation date

US15 4 + 1 for TCL-6 OK YES 6 + 2 TCL6 2 3 10. Mrz 14. Mrz1L TCTP 14/04/20141R TCTP 5/03/2014TCL-6 ?

UA23 6 + TDI OK No 3 (including TDI) 7 4 17. Mrz 21. Mrz TCTP 12/05/2014TDI 28/04/2014

UA27 2 OK No 2 2 5 24. Mrz 28. Mrz TCTP 12/05/2014UJ33 7 Ok YES 0 18 2 25. Feb 07. Mrz TCAPD 14/02/2014

USC55 4 + 1 for TCL-6 No No 6 + 2 TCL6 2 10 12. Mai 16. Mai5L TCTP 14/07/20145R TCTP 9/06/2014TCL-6 ?

US65 1 OK System to switch ON 2 0 6 31. Mrz 02. Apr 6L TCSP 13/03/20146R TCSP 18/02/2014

TZ76 21 OK No 4 (TCP) 34 9 22. Apr 09. Mai 7R TCP 18/02/20147L TCP 10/03/2014 

UA83 2 OK No 3 1 8 14. Apr 18. Apr TCTP 9/06/2014

UA87 5 + TDI OK No 3 (including TDI) 6 7 02. Apr 11. Apr TCTP 14/04/2014

BA7 1 OK YES 0 1 1 24. Feb 24. Feb -

Page 11: Status of LS1  collimator maintenance

O. Aberle – CWC11

Schedule – linked to LS1 LHC planning

March 03rd 2014

Work has just started First ring collimators put back into operational

statusTCLA.7L3.B2, TCP.6L3.B1, TCSG.5L3.B1

A lot of work in parallel with surface preparation and installation activities.

J. Finelle from the vacuum team will take pictures when ever a collimator will be disconnected from the vacuum system.

All collimators will be checked for alignment errors, re-alignement has already started in several points.

Page 12: Status of LS1  collimator maintenance

O. Aberle – CWC12

Outlook

March 03rd 2014

Improve the sound and image quality for the TIM, very powerful tool for the future.

Investigate on the capabilities of the Telemax or similar robots for inspections and interventions.

Reference sound recording of all collimators? Improve the accessibility to the screw (cap)

(Phase 2!) A regular check during long breaks and shut-

downs with re-lubrication of the screw. Check every slot for 5th axis motion

limitations. Sven De Man is the new reference person for

the LHC tunnel situation concerning collimators