Status and Plans Status and Plans of the SPL study of the SPL study R. Garoby – 8/12/2011 First open collaboration meeting on First open collaboration meeting on Superconducting Linacs for High Power Superconducting Linacs for High Power Proton Beams (SLHiPP-1) Proton Beams (SLHiPP-1) December 8-9/2011 CERN December 8-9/2011 CERN

Status and Plans of the SPL study

  • Upload
    blenda

  • View
    42

  • Download
    0

Embed Size (px)

DESCRIPTION

Status and Plans of the SPL study. R. Garoby – 8/12/2011. First open collaboration meeting on Superconducting Linacs for High Power Proton Beams (SLHiPP-1) December 8-9/2011 CERN. OUTLINE Context and organization Recent progress Near future…. F. HP-SPL main characteristics. - PowerPoint PPT Presentation

Citation preview

Page 1: Status and Plans  of the SPL study

Status and Plans Status and Plans of the SPL studyof the SPL study

R. Garoby – 8/12/2011

First open collaboration meeting on First open collaboration meeting on Superconducting Linacs for High Power Superconducting Linacs for High Power

Proton Beams (SLHiPP-1)Proton Beams (SLHiPP-1)December 8-9/2011 CERNDecember 8-9/2011 CERN

Page 2: Status and Plans  of the SPL study

OUTLINEOUTLINE

1.1. Context and organizationContext and organization

2.2. Recent progressRecent progress

3.3. Near future…Near future…

Page 3: Status and Plans  of the SPL study

Option 1 Option 2

Energy (GeV) 2.5 or 5 2.5 and 5

Beam power (MW)2.25 MW (2.5 GeV)

or

4.5 MW (5 GeV)

5 MW (2.5 GeV)

and

4 MW (5 GeV)

Rep. frequency (Hz) 50 50

Protons/pulse (x 1014) 1.1 2 (2.5 GeV) + 1 (5 GeV)

Av. Pulse current (mA) 20 40

Pulse duration (ms) 0.9 1 (2.5 GeV) + 0.4 (5 GeV)

Beam characteristics of the main options

2 beam current 2 nb. of klystrons etc .

HP-SPL main characteristicsHP-SPL main characteristics

8/12/2011 (R.G.) 3 SLHiPP-1 (CERN)

Page 4: Status and Plans  of the SPL study

ResourcesResources

• R & D for a High Power SPL formally supported at CERN in view of potential applications for physics

~1.7 MCHF and 6 FTEs / year

• Collaboration with ESS Fellows and procurement of klystron modulator for SM18

• French in-kind contribution Tuners, Helium tanks, use of Saclay 704 MHz high power test place…

• EC-supported programmes• EuCARD (WP10)

Development and test of beta=1 (CEA) and beta=0.65) 5 cells cavities• CRISP (WP4)

Joint work with ESS and DSY EC-supported manpower for upgrading and exploiting the SM18 test place

• LAGUNA-LBNO EC-supported fellow for studying proton drivers at CERN using LP- or HP-SPL

• DOE-supported programme• BNL Development and test of a =1 cavity

8/12/2011 (R.G.) 4 SLHiPP-1 (CERN)

Page 5: Status and Plans  of the SPL study

Planning of SPL R § DPlanning of SPL R § DModulator

from industry (ESS)

8/12/2011 (R.G.) 5 SLHiPP-1 (CERN)

To be updated at the beginning of 2012

To be updated at the beginning of 2012

Page 6: Status and Plans  of the SPL study

Planning overviewPlanning overview

• Until 2014 Construction and test of a prototype cryomodule with 4 cavities Construction and characterization of sc cavities Upgrade of the SM18 infrastructure (clean room, 704 MHz RF, cryogenics) Preparation for a full size cryomodule

8/12/2011 (R.G.) 6 SLHiPP-1 (CERN)

• Branching point for continuation Recommendations of the European Strategy Group at end 2012/beginning 2013 Updated Scientific Strategy of CERN by new DG: 2014?

Key ingredients for continuation:- Physics! Based on the results of LHC and of the on-going experiments.- Strength / weaknesses of competing options (Linear collider …)- Strength / weaknesses of the SPL-related applications (Proton drivers for facilities, Injectors for LHC-

related future beyond HL-LHC, LHeC …)- CERN strategy for sc RF technology- Politics and collaborations…

Page 7: Status and Plans  of the SPL study

Related R & DRelated R & D

Nb coating of Cu cavities, using the HIPIMS (High Power Nb coating of Cu cavities, using the HIPIMS (High Power Impulse Magnetron Sputtering) technologyImpulse Magnetron Sputtering) technology

– In collaboration with Sheffield Hallam University (UK).– Supported in the context of the construction of LHC spare cavities.– Potentially very attractive technology for the SPL (raw material cost, mechanical Potentially very attractive technology for the SPL (raw material cost, mechanical

stiffness).stiffness).– First results on low beta 704 MHz cavity: end 2012First results on low beta 704 MHz cavity: end 2012

8/12/2011 (R.G.) 7 SLHiPP-1 (CERN)

Page 8: Status and Plans  of the SPL study

Coordinator External partners

RF hardware (low level & high power)

E. Ciapala ESS, Cockcroft Institute + (FNAL, SNS, JLAB, ANL)

Cavities (structures & auxiliary equipment)

W. Weingarten CEA-Saclay, CNRS-Orsay, Uni Rostock, Stony Brook, DESY + (JLAB, SNS)

Cryomodule (cryostat & cryogenics) V. Parma CEA-Saclay, CNRS-Orsay, Stony Brook + (FNAL)

Beam dynamics (beam parameters) A. Lombardi CEA-Saclay, ESS + (FNAL)

Architecture (layout & geometry, extraction, transfer)

F. Gerigk

Surface treatment and vacuum S. Calatroni

Mechanical design and construction

O. Capatina

Working Groups

Study leader: R. Garoby

Present organizationPresent organization

SPL documentation in EDMS [ https://edms.cern.ch/nav/SLHC-000008 ] SPL meetings in Indico [ http://indico.cern.ch/categoryDisplay.py?categId=1893 ]

SPL Collaboration

8/12/2011 (R.G.) 8 SLHiPP-1 (CERN)

Page 9: Status and Plans  of the SPL study

Principle of the future organizationPrinciple of the future organization

8/12/2011 (R.G.) 9 SLHiPP-1 (CERN)

MotivationMotivationTo better match the needs of the medium term goal of the HP-SPL R&D:

Building and testing a prototype cryomodule with 4 cavities

Main principlesMain principles-«Project-like» structure emphasizing relations between contributions (integrated planning)-Main objectives:

- Design, construction and test of the prototype cryomodule- Components: Cryomodule, Cavities, RF items (Couplers, tuners, …), cryogenics equipment…- Assembly (with adequate tools): cavities string in clean room, inclusion in cryomodule- Tests: cavities in vertical cryostat, assembled cryomodule in bunker.

- Experience in SC RF cavities technology- Fabrication and processing- Test, diagnostics and analysis- Upgrade of the SM18 infrastructure- Cryogenics for efficient operation at 2K- High power RF at 704 MHz (klystron, modulator, high power distribution)- Low Level RF and controls

Page 10: Status and Plans  of the SPL study

OUTLINEOUTLINE

1.1. Context and organizationContext and organization

2.2. Recent progressRecent progress

3.3. Near future…Near future…

Page 11: Status and Plans  of the SPL study

Progress since July 2011Progress since July 2011 (1/2)(1/2)

- Construction of 4 cavities in industry Niobium (finally!) delivered Fabrication contract signed

- Decision to build one additional cavity at CERN in 2012- Test of single cell sample cavity from CEA

In progress- Measurement and test with dumbbell copper cavity

In progress- Upgrade of cryogenics infrastructure in SM18

Planned in 2012- Order of 704 MHz klystron for SM18

Order signed in September 2011- Specification & order of klystron modulator from industry (ESS)

Specifications finalized Supplier selected / order being signed ?

- Preparation of 704 MHz RF components (Low Level and High Power) for SM18 In progress

More details during this

meeting

More More information information

on Fridayon Friday

8/12/2011 (R.G.) 11 SLHiPP-1 (CERN)

Page 12: Status and Plans  of the SPL study

Progress since July 2011Progress since July 2011 (2/2)(2/2)- Review of Cryomodule Conceptual Design on November 4, 2011

(Late but) done - https://indico.cern.ch/conferenceDisplay.py?confId=154284

- Construction & test of High power RF couplers + Review Couplers and coupling boxes built, but problem with Cu-platting High power RF tests started in Saclay Review delayed to the first quarter of 2012

- Specification & construction of tuners and He tanks (CEA) Delayed

- LP-SPL CDR (jointly with PS2) Delayed to 2012…– Organization of future meetings Changed into “SLHiPP” open collaboration events December 2011 meeting organized (CERN) / May 2012 meeting announced (Italy)

More details during this

meeting

8/12/2011 (R.G.) 12 SLHiPP-1 (CERN)

Page 13: Status and Plans  of the SPL study

OUTLINEOUTLINE

1.1. Context and organizationContext and organization

2.2. Recent progressRecent progress

3.3. Near future…Near future…

Page 14: Status and Plans  of the SPL study

Next 12 months (1/2)

… concerning the SPL itself (non-exhaustive list):- Update of the integrated planning taking into account the impact of the

other CERN programmes- Follow-up of cavities construction (in industry and at CERN) and first tests…- Start of upgrade of cryogenics and overall infrastructure in SM18- Tests of High power RF couplers + Review (Q1/2012)- Follow-up of klystron modulator construction in industry (ESS)…- Order of RF components for SM18- Beginning of construction of prototype cryomodule (IN2P3)- Construction of He tanks (CEA)- LP-SPL CDR (jointly with PS2) - SLHiPP-2 meeting (3-4 May, 2012)

8/12/2011 (R.G.) 14 SLHiPP-1 (CERN)

Page 15: Status and Plans  of the SPL study

Next 12 months (2/2)… concerning the applications of the SPL

-Cost estimate of the high power SPL (in the context of EuRo-contribution to the IDS-NF)-Reactivation of studies for proton drivers in future neutrino facilities (in the context of LAGUNA-LBNO):

- LP-SPL as injector of a 2 MW / 30-50 GeV synchrotron- HP-SPL with an accumulator as a 5 MW / 5 GeV proton source

8/12/2011 (R.G.) 15 SLHiPP-1 (CERN)