NATO UNCLASSIFIED Statement of Work dated 1 March 2019 (Version 2) NATO UNCLASSIFIED COMMUNICATIONS, AIR AND MISSILE DEFENCE PROGRAMME PROGRAMME DE COMMUNICATIONS, DÉFENSE AÉRIENNE & ANTIMISSILE STATEMENT OF WORK AND TECHNICAL REQUIREMENTS FOR MARTELLO ELECTRONIC SHELTER RESTORATION ‐ S723 1 March 2019 (Version 2)

STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

NATO UNCLASSIFIED Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED 

 

 

COMMUNICATIONS, AIR AND MISSILE DEFENCE PROGRAMME PROGRAMME DE COMMUNICATIONS, DÉFENSE AÉRIENNE & ANTIMISSILE

 

 

 

STATEMENT OF WORK  

AND TECHNICAL REQUIREMENTS 

FOR 

MARTELLO ELECTRONIC SHELTER RESTORATION ‐ S723 

1 March 2019 (Version 2)   

Page 2: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

NATO UNCLASSIFIED Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED 

TABLE OF CONTENTS 

0.  NOTATION CONVENTIONS ................................................................................................ 5 

1.  OBJECTIVE AND SCOPE ..................................................................................................... 1 

2.  REFERENCE DOCUMENTS .................................................................................................. 1 

2.1.  NATO STANDARDS AND PUBLICATIONS ......................................................................................... 1 

2.2.  INTERNATIONAL STANDARDS AND SPECIFICATIONS ........................................................................... 2 

2.3.  EQUIPMENT TECHNICAL MANUALS ............................................................................................... 2 

3.  CURRENT RADAR SYSTEM ................................................................................................. 2 

4.  OVERVIEW OF PROJECT DEVELOPMENT AND CONTRACTOR’S TASKS ............................... 2 

5.  PROJECT MANAGEMENT .................................................................................................. 3 

5.1.  MASTER SCHEDULE .................................................................................................................... 3 

5.2.  PROJECT CONTROLS ................................................................................................................... 4 

6.  TECHNICAL AND INTEGRATION REQUIREMENTS ............................................................... 4 

6.1.  GENERIC.................................................................................................................................. 4 

6.2.  PERFORMANCE SPECIFICATIONS (SEE CONFIDENTIAL ANNEX 0) ......................................... 6 

6.3.  INTERFACE REQUIREMENTS ......................................................................................................... 6 

6.3.1.  DEMARCATION PANEL ................................................................................................................ 7 

6.3.2.  COMMUNICATION FUNCTION BETWEEN RRH AND CRC ..................................................................... 7 

6.3.3.  COMMUNICATION FUNCTION WITH ADP NETWORK INTERFACE ........................................................... 7 

6.3.4.  ACCS NETWORK INTERFACE ........................................................................................................ 8 

6.4.  SYSTEM TIMING AND WAVEFORM GENERATOR (OFF‐MOUNT RECEIVER) .............................................. 8 

6.5.  SIGNAL PROCESSOR ................................................................................................................... 8 

6.6.  EXTRACTOR (PRIMARY RADAR) .................................................................................................... 9 

6.7.  SSR DECODER AND PLOT EXTRACTOR ............................................................................................ 9 

6.8.  JAMMING ANALYSIS RECEIVER ................................................................................................... 10 

6.9.  SYSTEM CLOCK ....................................................................................................................... 10 

6.10.  RCDSS: DATA PROCESSING AND COMMUNICATION ....................................................................... 11 

6.11.  RCDSS: MONITORING AND CONTROL ......................................................................................... 13 

6.12.  RCDSS: BITE REPORTING ......................................................................................................... 17 

6.13.  RCDSS: DATA BUFFER ............................................................................................................. 18 

6.14.  RCDSS: PRIORITY FILTER .......................................................................................................... 19 

6.15.  RCDSS: PERFORMANCE EVALUATION COMPUTER (PEC) ................................................................. 19 

6.16.  REMOTE DISPLAY SYSTEM (RDS) ................................................................................................ 19 

6.17.  PERFORMANCE EVALUATION TOOL (PET) ..................................................................................... 21 

6.17.1.  Radar Raw Data Files ............................................................................................................... 22 

6.17.2.  Data Analysis and Display ....................................................................................................... 23 

6.17.3.  Output Data File ...................................................................................................................... 24 

6.17.4.  PET Environment ...................................................................................................................... 25 

6.17.5.  Test Points ............................................................................................................................... 25 

6.17.6.  Radar Environment Simulator (RES) ........................................................................................ 25 

Page 3: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

NATO UNCLASSIFIED Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED 

6.17.7.  Installation ............................................................................................................................... 27 

6.18.  RELIABILITY, MAINTAINABILITY AND TESTABILITY ........................................................................... 28 

6.18.1.  Reliability ................................................................................................................................. 28 

6.18.2.  Maintainability ........................................................................................................................ 28 

6.18.3.  Testability ................................................................................................................................ 28 

7.  PROJECT DEVELOPMENT AND MAJOR TECHNICAL MILESTONES ..................................... 29 

7.1.  GENERIC................................................................................................................................ 29 

7.2.  SYSTEM REQUIREMENTS REVIEW (SRR) ....................................................................................... 29 

7.3.  CRITICAL DESIGN REVIEW (CDR) ................................................................................................ 29 

7.4.  PRODUCTION AND FACTORY ACCEPTANCE TEST (FAT) .................................................................... 30 

7.5.  DELIVERY, INSTALLATION, INTEGRATION AND SITE ACCEPTANCE TESTING (SAT) ................................... 31 

7.6.  RELIABILITY TEST (RT) .............................................................................................................. 33 

8.  VERIFICATION AND ACCEPTANCE ................................................................................... 33 

8.1.  VERIFICATION AND ACCEPTANCE TEST (V&A‐T) PLAN .................................................................... 33 

8.2.  ACCEPTANCE MILESTONES ........................................................................................................ 35 

8.2.1.  Factory Acceptance of the Integrated Prototype Solution....................................................... 35 

8.2.2.  Provisional Site Acceptance (PSA) ............................................................................................ 35 

8.2.3.  Final Acceptance: (FA) ............................................................................................................. 36 

9.  LOGISTIC SUPPORT DELIVERABLES .................................................................................. 36 

9.1.  DOCUMENTATION ................................................................................................................... 36 

9.2.  CONFIGURATION ..................................................................................................................... 37 

9.3.  TRAINING .............................................................................................................................. 37 

9.4.  SPARE PARTS ......................................................................................................................... 39 

9.4.1.  Installation & Check Out (INCO) Spares ................................................................................... 39 

9.4.2.  Reliability and Provisioning Data ............................................................................................ 39 

10.  QUALITY ASSURANCE ..................................................................................................... 40 

11.  OPTIONS (EVALUATED) ................................................................................................... 40 

APPENDIX 1: SUMMARY OF DELIVERABLE DATA, PRODUCTS AND SERVICES ......................... 41 

APPENDIX 2: ENVIRONMENTAL REQUIREMENTS WITHIN THE DISPLAY SHELTER ................... 43 

APPENDIX 3: ABBREVIATIONS AND ACRONYMS .................................................................... 45 

 

ANNEXES: 

ANNEX 0: MARTELLO S723 REQUIREMENTS 

ANNEX 1: MARTELLO S723 SYSTEM DESCRIPTION 

ANNEX 2: MARTELLO S723 SCHEMATICS 

ANNEX 3: MARTELLO S723 TECHNICAL DOCUMENTATION 

ANNEX 4A: S723 INTERFACE BETWEEN RCDSS AND RDS 

ANNEX 4B: S723 INTERFACE BETWEEN LSD AND RIS&MASE 

 

Page 4: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

NATO UNCLASSIFIED Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED 

AMENDMENT RECORD 

REVISION/AMENDMENT PAGES DATE OF ISSUE REMARKS Version 1 52 Pages and

Annexes below: Annex O Annex 1 Annex 2 Annex 3 Annex 4A Annex 4B

23 JULY 2018 NONE

Version 2 52 Pages

Annex 1

1 March 2019

 

   

Page 5: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

NATO UNCLASSIFIED Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED 

 

0. NOTATION CONVENTIONS 

This  document  contains  both  a  statement  of  work  and  a  set  of  technical  requirements. Paragraphs  stating  deliverables  and  specifying  requirements  are  preceded  by  an alphanumeric code in brackets with the following meaning: 

(Rx): States a generic requirement affecting all deliverables, where “x” is a serial number. 

(R.Tx):  Specifies  a  technical  requirement  for  the  system,  where  “x”  is  a  serial  number. Technical requirements are given at Section 6 of this document. 

(Dx):  States  a  requirement  for  the  Contractor  to  deliver  certain  a  product  (including  data products) or service, where “x” is a serial number. 

(R.Dx.y): Defines specific requirements related to the deliverable “Dx”, where “y” is a serial number. 

Deliverables  and  their  associated  requirements  are  stated  in  Sections  5,  7  and  9  of  this document. 

(R.Qx):  Specifies  quality  assurance  requirements,  where  “x”  is  a  serial  number.  Quality assurance requirements are given in Section 8 of this document.  

(O.Tx): State options for additional technical scope. 

Options are given in Section 11 of this document. 

Tables and bulleted lists following paragraphs stating deliverables or specifying requirements are part of the definition of the deliverable or requirement. 

Paragraphs not preceded by any of the codes listed above do not state outright deliverables or  associated  requirements,  but  contain  essential  information  or  may  complete  the definition of work and acceptance. They may also reflect actions which NSPA will perform. 

Acronyms and abbreviations are normally spelled out when they are used for the first time in  the  document,  except  when  referring  a  commonly  used  term  (e.g.  NATO).  Appendix  3 contains a list of acronyms and abbreviations used. 

Where the “Host Nation” is mentioned, it is to be understood as “Denmark”. 

“Customer”  is  to  be understood  as  “NSPA”  in  its  role  as  Procurement Agent  and Contract Manager  and  “Denmark”  as  the  End  User  for  the  equipment  and  responsible  for  the operations of the radar. 

Page 6: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.1 

 

1. OBJECTIVE AND SCOPE 

This  document  defines  requirements  for  services  and  products  to  be  provided  by  the Contractor  to  the NATO  Support  and  Procurement Agency  (NSPA)  for  the  upgrade of  the Signal Processor (SP), Data Processor (DP), Data Handling (DH) and IFF Processor (Option) in the current configuration of the NATO Martello S723 Air Defense System in Denmark. This upgrade  will  be  referred  hereafter  as  the  Martello  S723  Electronic  Shelter  Restoration (MESR). 

The main  objective  of  the MESR  is  to  extend  the  system  life  cycle  through  a  technology refresh to mitigate system obsolescence and improve system supportability. As such NSPA, is  not  aiming  for  improved  technical  system  performance,  but  to  guarantee  the  original system  performance  with  improved  supportability  for  the  remaining  planned  operational life. 

The  services  and  supplies  covered  by  this  SOW  are  applicable  to  the  equipment  at  one MARTELLO  S723  radar  site,  Radar  Head  Solution  (RHS),  and  at  two  Remote  Operations Center (ROC) as described in Table 1. 

Country  Site name  System  Function  Location  Mod kit 

Denmark  BORNHOLM  S723  Radar head  BORNHOLM  RHS 

Denmark  Karup  ROC  CRC + CARS  KARUP  RS 

Denmark  Mobile CRC  ROC  D‐CRC  KARUP  RS 

Table 1: sites concerned by the MARTELLO S723 Electronic Shelter Restoration 

2. REFERENCE DOCUMENTS 

The  following  is  a  non‐exhaustive  list  of  documents  which,  in  their  most  current version/revision, are relevant in whole or  in part to the object of this SoW. They do not  in principle  constitute  requirements  unless  explicitly  referred  in  other  parts  of  this  SoW.  If there  is  a  conflict  between  the  requirements  of  this  SoW and  any of  the  listed  reference documents, the SoW shall prevail. 

(R1) The Contractor shall be responsible for ensuring that the new equipment complies with all national and international applicable legal requirements. 

2.1. NATO Standards and Publications 

a. AQAP‐2110  (NATO  Quality  Assurance  Requirements  for  Design,  Development  and Production)  

b. AQAP‐2210 (NATO Supplementary Software QA Requirements to AQAP 2110) c. ACMP 1‐7 Allied Configuration Management Publications (Edition 2) d. STANAG 4193 Ed 3: Technical Characteristics of  IFF Mk XA and Mk XII  Interrogators 

and Transponders 

Page 7: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.2 

 

e. 3885.10/SHCCC/382/98,   AIR  COMMAND  AND  CONTROL  SYSTEM  CRITERIA AND STANDARDS  (3rd edition,  final), NATO CONFIDENTIAL  (available only  after  contract award)  

f. STANAG 4370 (Environmental Testing) g. STANAG 4236  (Lightning environmental conditions, affecting  the design of material 

for use by NATO forces) h. STANAG 4327 (Lightning test procedures) i. STANAG  5535  Ed  2/ADatP‐35  Ed  2  (NATO  Standard  Document  for  Air  Surveillance 

and Ground Based Sensors Information Exchange).  

2.2. International Standards and Specifications 

j. ISO 9001:2000 (Quality Management Systems – Requirements) k. MIL‐HDBK‐61A Configuration Management Guide l. MIL‐STD‐100, Engineering Drawings m. MIL‐DTL‐31000, Technical Data Packages n. MIL‐STD 1250, Corrosion control o. ICAO,  International Civil Aviation Organization  ‐ Technical Characteristics of  IFF MK 

XA and MK XII Interrogators and Transponders p. Recommendation CCIT V29 

2.3. Equipment Technical Manuals 

q. MARTELLO S723 TMEs are listed in Annex 3, available and maintained at NSPA 

3. CURRENT RADAR SYSTEM 

The description, performance and technical characteristics of the current radar system and support equipment are reflected in Annexes 0 to 3. 

4. OVERVIEW OF PROJECT DEVELOPMENT AND CONTRACTOR’s TASKS 

Through  this  contract,  the  Contractor  will  replace  the  Signal  Processor  and  the  Radar Control and Display Subsystem (RCDSS) equipment  for  the MARTELLO S723 radars used  in NATO’s Air Defense System. Annex 2 presents a schematic containing the affected parts of the radar system. 

NSPA is seeking a low risk and fast implementation solution, ideally non‐developmental, i.e. an existing design needing  limited adaptation  for specific requirements of  this application. Contractors able to propose such solution are to interpret the design & development tasks outlined below as comprising only this adaptation.    

The Contractor will undertake the following tasks: 

a. Establish the engineering design that will ensure that all current system performance are  met,  including  existing  system  &  operational  control  capabilities  (Local  & Remote); 

b. Establish the engineering design of the R‐SPC Performance Evaluation Tool (PET); c. Develop the new equipment Human Machine Interface and output interfaces; 

Page 8: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.3 

 

d. From a Work Breakdown perspective, due to the estimated duration of the project, the solution will be developed,  tested,  implemented and validated  in  the  following main technical phases: 

i. Development,  to  include  HW  Design  updates  and  SW  scripts  updates  and documentation development.  

ii. Factory Testing.  iii. Installation, Integration and Site Testing.  iv. Reliability Testing. 

e. Upon  contract  award  the  Contractor  will  perform  a  System  Requirements  Review (SRR)  and  the  design  and  development  activities  leading  to  Critical  Design  Review (CDR). 

f. Following CDR approval by the NSPA, the Contractor will conduct factory testing for the solution proposed, before proceeding with site installation and integration of the Modification kit (Modkit) for the radar site, and two Mod kits for the CRC sites. For each complete installation, the Contractor shall perform Site Acceptance Test (SAT) followed  by  a  phase  of  reliability  testing  starting  after  Provisional  Site  Acceptance (PSA). 

g. Provisional Site Acceptance  (PSA) will be achieved  for each site, after  the  technical solution  has  been  tested  and  accepted  at  that  site  and management  and  logistics products have been delivered and accepted. 

h. The  last milestone of  the project  is  Final Acceptance  (FA) which will  be performed simultaneously  for  all  sites  once  all  validation  and  verification  activities  are successfully completed and any observations cleared. 

i. The project also includes logistics support deliverables, i.e. training, documentation, special tools and test equipment and recommended spares lists. 

5. PROJECT MANAGEMENT 

(D1) The Contractor shall assign a Project Manager to be the main Point of Contact (POC) for NSPA in all aspects related with the project. 

5.1. Master Schedule 

(D2) Not  later  than  4  weeks  after  Contract  Award,  the  Contractor  shall  deliver  and maintain  through  the  execution  of  the  contract,  a Master  Schedule  for  the  delivery  of  all products and services in this contract. Within 2 weeks of reception, NSPA shall approve the Master  Schedule or provide  requirements  for  change or  clarification.  The Contractor  shall implement the changes required by NSPA for final agreement. 

By  agreeing  on  the  schedule,  NSPA  considers  the  plan  to  be  a  logical  and  satisfactory approach  to  the  management  of  the  required  activities,  based  upon  the  information provided. The requirements  in  this SoW take precedence over  the Master Schedule  in  the case of conflict, ambiguity or omission.  

(R.D2.1) The  Master  Schedule  shall  indicate  the  planned  dates  for  all  events  and intermediate milestones described in this SoW in order to achieve the Final Acceptance not later than 18 months after Contract Award. The Master Schedule is included as an Annex to the Contract. 

Page 9: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.4 

 

(R.D2.2) The  dates  for  site  installation  and  testing  shall  provide  for  the  consecutive implementation  of  the  upgrade  on  all  sites  in  order  to  minimize  contractor’s  personnel travel and subsistence cost. The site installation schedule shall be considered tentative until it  is confirmed by the Host Nation. NSPA shall provide confirmation of these dates at  least 60 days before the planned operation. 

(R.D2.3) In  case  of  project  changes,  the  Contractor  shall  update  the  Master  Schedule accordingly and submit it for NSPA approval. 

(D3) 90 days before any intervention on site, the Contractor shall communicate to NSPA the  bio  and  security  clearance  data  of  all  the  personnel  (to  include  backup  personnel) involved in the activities on all sites.  

5.2. Project Controls 

(R2) Generally, the Contractor shall keep the NSPA Project Manager informed of any issue 

or risk affecting the schedule or the scope of the project. 

(D4) If  at  any  point  during  the  execution  of  the  Contract,  the  Contractor  foresees  any significant risk to the schedule or circumstance creating a risk to any of the requirements in this  document,  he  shall  inform  NSPA  immediately  in  writing  and  will  seek  agreement  by Contract Amendment. 

(D5) Other  than  the main  technical  events  in  the contract described  in Section 7, NSPA may call for an ad‐hoc Project Review and/or a Technical Interchange Meeting at any point during the execution of the contract. 

(R.D5.1) Ad‐hoc  meetings  called  by  NSPA  will  be  exceptional  and,  unless  otherwise agreed, will  take place at  the contractor  facility  to minimize  the contractor’s cost.  If NSPA requires  contractor  personnel  to  travel  for  this  type  of  meeting,  cost  incurred  by  the contractor shall be considered as a modification to this contract. 

(R.D5.2) The Contractor shall record the minutes of all formal meetings and provide them to NSPA for agreement, in general within 2 weeks of the meeting. 

(R.D5.3) Meeting minutes shall be considered  final only once  they have been signed by the  Contractor,  NSPA  and,  if  in  attendance,  the  Host  Nation.  The  Contractor  shall  not consider  the minutes  as  the  basis  for  changes  to  any  of  the  terms  and  conditions  of  the Contract in the Absence of a formal Contract Amendment. 

6. TECHNICAL AND INTEGRATION REQUIREMENTS 

6.1. Generic 

(R.T1) There  shall  not  be  any  degradation  to  any  of  the  current  radar  operation  and maintenance  functions or  its  technical  characteristics  as  a  consequence of  the MARTELLO S723 Shelter Restoration. 

(R.T2) The  Contractor  shall  provide  the  services,  equipment,  and  facilities  necessary  to design, produce, integrate, deliver, install on the radar and CRC sites, and test; to the extent defined herein, the MESR Modkits. 

Page 10: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.5 

 

(R.T3) The  Contractor  shall  make maximum  use  of  existing  designs,  documentation,  and processes; to the extent such use is economically beneficial. 

(R.T4) The MARTELLO  S723  Shelter  Restoration Mod  kits  will  utilize  commercial  off‐the‐shelf (COTS) components and assemblies to the maximum possible extent and shall: 

Extend  the  life  of  the MARTELLO  S723  system by  at  least  10  years,  by  introducing technologies that eliminate current and foreseeable obsolescence. 

Reduce  or  maintain  the  Life  Cycle  cost  by  improving  the  system  reliability  and availability, and enhance the maintenance features of the radar system;  

(R.T5) All  the equipment delivered and  installed as part of this contract shall be new, not refurbished. 

(R.T6) The COTS hardware and software  to be supplied both  for  the Radar and  the CRCs, shall be of the latest production in the Contractor product line at the time of the order. The Contractor  shall  provide  any  applicable  software  (on  CD/DVD‐ROM)  and  related  User Licenses associated to the COTS hardware and software to be supplied; 

(R.T7) The  entire  system  shall  be  contained within  a  19’’  cabinet  and  shall  use  common hardware platforms based on industry hardware/software standards for both the processing and I/O sub‐systems. The subsystems shall be contained within industry‐standard and rack‐mountable electronic enclosures. 

(R.T8) The upgraded Hardware  (HW) and Software  (SW)  shall  be  integrated  in a modular architecture. The following HW shall be replaced: 

Off‐Mount Receiver (OMR): pulse expander, pulse compression units; 

Signal  Processor  (SP): Multibeam  IF  subsystem  (Master Control Unit  (MCU) + Beam  Processing  Units  (BPU)),  Plot  Forming  Unit  (PFU),  Jamming  Strobe Extractor (JSE) and SLB Detection and Logic; 

RCDSS: Radar Management Processor,  Plot Processor, Display Processors and Work Station; 

SSR Decoder and Plot Extractor  

Radar output data converter and modems 

Maintenance Control Facility 

Performance Evaluation Tool (PET). 

System Clock 

Remote Dispaly System (RDS); 

Radar Environment Simulator (RES)  

(R.T9) The new equipment shall produce the same type of  interface  impedances, control, timing and data signal levels as the original equipment in order to make a proper interface. 

(R.T10) The Human Machine  Interface  (HMI)  of  the RCDSS  shall  be  upgraded,  consistently with the technological upgrade. 

(R.T11)  The  upgraded  radar  system  shall  provide  at  least  all  existing  radar  operational modes and waveforms  (there  is no  requirement but no  limitation  to add new operational 

Page 11: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.6 

 

modes and implement new type of waveforms as long as all those shall remain compatible with the existing antenna and transmitter configuration);  

(R.T12)  The  new  Radar  Data  Processor  shall  not  exceed  50%  of  the  available  capabilities under maximum workload conditions. 

(R.T13)  The  Contractor  shall  deliver  and  install  all  the  relevant  updated  application  and mission software and the related user licenses, where applicable (see also (D32)).  

(R.T14) The mission and application software shall: 

Interface the radar network to the external Automatic Data Processing  

Execute Performance Monitoring and Fault  Isolation  (PMFL) both on  the  radar and on the CRC sites; 

(R.T15)  For any custom developed assemblies, the Contractor shall place all related design specification, development files, manufacturing drawings and VHDL source code (if any)  in escrow  for  future  access  for  the  expected  life  of  the  system.  Therefore,  should  the Contractor  no  longer  be  available  to  support  the  product,  the  escrowed  VHDL  code, drawings, etc., shall be available to NSPA to support the further manufacture of the product by another source. The escrow process shall be set up before FSA. 

6.2. Performance Specifications (See Confidential Annex 0)  

(R.T16)  The modified radar shall provide equivalent or improved:  

Detection capability in the clear, in ground clutter, in atmospheric propagation and extended range clutter for the full detection range of the radar; 

Target angle centered accuracy; 

Range resolution; 

Signal processor dynamic range; 

ECCM capabilities, (e.g. Strobe, in Chaff, Advanced SLB signal processing); 

Digital waveform generation capabilities and pulse compression gain; 

Plot handling capability.  

 

(R.T17)  Equivalent or reduced false alarm rate in clutter and jamming conditions for the full detection range of the radar;  

6.3. Interface Requirements 

(R.T18)  The  Mod  kits  shall  be  compatible,  but  not  limited  in  function,  with  the  existing equipment and must accept the input/output protocols, control signals, triggers and data of the  existing  interfaces  of  other  subassemblies  such  as  the  BITE  and  the  Transmitter  Sub‐system. 

(R.T19)  The radar shall provide accurate plot time stamping. The time of detection shall be provided, with an error of no greater than 10 msec. Time of detection is defined as the time that the center of the beam scans over the reported target’s azimuth. 

Page 12: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.7 

 

6.3.1. Demarcation Panel  

(R.T20)  The Contractor shall develop and install at the Radar Head a physical “Demarcation Panel”, which will be the connection interface between the original system and the RHS/RS Mod kit.  This  Panel  is  intended  to  facilitate  the  connection  to  the  radar  for  all  evaluation purposes. In practice the original radar equipment will have to be kept in the as is condition within the Electronics shelter during the whole evolution period.  

(R.T21)  The  Panel  separates  the  cables,  connectors  and  interfaces  that  are  outgoing  / incoming  to  the  Shelter  from cables,  connectors  and  interfaces  that  are  required  for new equipment installation.  

(R.T22)  The  Demarcation  panel  is  also  intended  to  facilitate  at  any  time  the  swapping between the original system and the RHS/RS Mod kit for operational reasons and in case of discrepancies  encountered  with  the  modification.  It  shall  be  possible  to  perform  the swapping between the two systems in less than 15 min.  

6.3.2. Communication function between RRH and CRC   

(R.T23)  The  existing  radar  data  interface  functionality  to  the  respective  CRC  shall  be preserved, i.e.: 

Distribution of the air picture to the CRC sites; 

Remotely display the status, and control the radar (SR & SSR) from the CRC site; 

Redundancy in the sense that the radar and can be monitored and controlled from at least two CRCs. 

(R.T24)  All  the  communications  equipment  necessary  for  the  data  exchange  between  the Radar systems and the CRCs shall be fully compatible with the existing communications lines between the remote entities and the radar site.  

(R.T25) It shall be possible to establish simultaneous connection from two distinct CRCs to a given  radar head with master or monitoring  capabilities.  The  radar  control  selection  shall follow a master/slave concept. 

6.3.3. Communication function with ADP network interface  

(R.T26)  Radar messages shall be provided to CRCs  for display and tracking purposes. CRCs will be equipped with specific Remote Display System  (RDS) and  interfaces  to  the existing Automatic Data Processing (ADP) network environment.  

(R.T27)  The format for integration in the ADP network is the NATO RSRP Standard Format. The types and format of messages to be delivered to the remote ADP are specified in annex 4B.  

(R.T28)  The CRC RDSs shall display the information available in the RRH RDSs and be able to execute the same level of radar control.  

Page 13: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.8 

 

6.3.4. ACCS Network Interface  

(R.T29)  The Contractor shall implement a UDP/IP interface on the radar site for transmission through ACCS Network interface of radar data. The respective network equipment and user interfaces in ACCS Network interface shall be a Customer responsibility. 

(R.T30)  Option (See Option O.T1.)  

6.4. System Timing and Waveform Generator (Off‐Mount Receiver)  

(R.T31)  The SP shall also  include the Receiver/Exciter functionality and replace the existing up/down converter stages, oscillator and timing controls. 

6.5. Signal Processor  

(R.T32)  Pulse Compression for all  receive beams. The Bidder shall propose and describe  in his bid the methods/techniques to compensate (reduce) the unwanted signal modulations and  time  side  lobes  caused  by  transmitter/receiver  chain  nonlinearities  and  during propagation.  

(R.T33)  The  Bidder  shall  propose  and  describe  in  his  bid  the  chosen methods/techniques used  in  the  Signal  Processor  in  order  for  NSPA  to  evaluate  the  expected  system  clutter performance with the modification. 

(R.T34)  Signal processing parameters shall be adjustable through a HMI in compliance with at  least  the  original  system  capabilities  detailed  in  the  relevant  MARTELLO  S723  system documentation. 

(R.T35)  Each beam shall have logic to the maximization of the signal‐noise‐ratio in different environmental  (clear, clutter, ECM etc.) and Radar Cross Section (RCS) situations. The best beam  processing  from  target  detection  point  of  view  shall  be  based  on  an  automatic selection or combination of the available channel logics. 

(R.T36)  Independent  beam  signal  processing.  Each  channel  shall  contain,  Pulse Compression, MTI/MTD, Clutter maps, CFAR and SLB Logic as in the original system. 

(R.T37)  Clutter  map.  The  radar  shall  automatically  generate  and  maintain  clutter  outline data consisting of  the height,  the strength and the type of clutter,  i.e. ground, weather or chaff within the radar coverage. The clutter map shall provide a resolution of at least 2 km in range, the azimuth 3dB beam width in azimuth and the elevation 3 dB beam width in height. Active ECM shall not  influence  the clutter outline data. The range of  the strength shall be consistent with the actual clutter environment at the radar site. 

(R.T38)  CFAR control by clutter map. The ground clutter map shall have a sufficiently small cell  size  to  control  the detection  thresholds  and  false  alarm  rate  in  strong  ground  clutter areas consistent with the detection requirements. Ground clutter shall be considered up to 300 km. 

(R.T39)  The Signal Processor shall encompass a spare processing channel that can be used in case of failure of one of the 8 receive beams channels. The reconfiguration can be managed either manually  by  site  technicians  or  automatically  by  the  system  (the  automatic  switch function can be either enabled or disabled by the operator).  

Page 14: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.9 

 

6.6. Extractor (Primary Radar)  

(R.T40)  The new system shall, at least, contain and perform all the functions offered by the original primary plot extractor. Among those: 

Range azimuth and elevation bias error correction via site‐dependent and user‐ adaptable data; 

Height error correction; 

The  jamming  strobes  and  plot  extraction  parameters  shall  be  controllable though  a  HMI  with  adaptive  and  manual  set  up.  The  total  number  of  false jamming strobes (including jamming strobes resulting from jamming in the side lobe) shall not exceed 1 per scan for any of the jamming types. 

(R.T41)  The  3D  primary  height  calculation  technique  shall  provide  at  least  the  same information and accuracy as the original system. 

6.7. SSR Decoder and Plot Extractor  

(R.T42)  The secondary extractor shall, at least, contain and perform all the functions offered by the original secondary extractor. Among those:  

(R.T43)  Real time code extraction shall be provided to detect the presence of valid SSR reply pulses and to reject invalid pulses in accordance with the specifications in STANAG 4193.  

(R.T44)  A reply in a triple interlaced interrogation mode is properly decoded with at least a probability of 80% at the output of the extractor.  

(R.T45)  Associate transponder replies with primary Surveillance Radar (SR) plots by position correlation and use of SSR altitude and ADSB information when available. Associated replies shall be reported together with the SR plot or, if association is not successful (e.g.; no radar detection), as an SSR plot.  

(R.T46)  Means  shall  be  provided  to  detect  all  reply  codes,  in  all modes  as  output  by  the transmitter/  receiver  equipment  for  the  purpose  of  producing  range,  azimuth,  code  and height  data  for  each  plot.  Decoded  height  must  be  available  in  increments  of  100  feet. Selection of target for active decoding should be done by rolling ball or similar. Correlation and garbling shall be  indicated as part of the plot code information. Time of detection has also to be part of the SSR plot information.  

(R.T47)  SSR plots shall be extracted with a range resolution and a range accuracy matching that  of  the primary  radar.  The  azimuth  resolution  shall  be equal  to  the  effective  antenna beamwidth. Means shall be provided for minimizing the probability of generating plots from asynchronous signals (as defruiting for instance).  

(R.T48)  The  equipment  shall  detect  automatically  military  emergency,  identification  of position (I/P), all classes of civil emergency and Special Position Indicator (SPI) transponder replies.  

(R.T49)  Audible and visual alarms shall be provided in order to inform the operator when an SSR emergency signal is received.  

(R.T50)  The plot extraction system shall be capable of processing up to 1500 SSR plots per scan  without  any  loss  of  plots,  or  degradation  in  system  performance  due  to  processing 

Page 15: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.10 

 

overload.  The  system  shall  also  be  capable  of  processing  64  SSR  plots  per  antenna beamwidth  without  any  loss  of  plots.  Under  normal  plot  load  (up  to  1500  SSR  plots  per scan),  the  plot  processing  delay  through  the  extractor  shall  not  exceed  30°  except  under conditions of plot overload.  

(R.T51)  Means  shall  be  provided  for  reducing  the  number  of  false  bracket  decodes  from closely‐spaced or overlapping replies.  

(R.T52)  Defruiting. Fruit and non‐synchronous replies shall be effectively removed such that, out of 10 000 fruits per second, less than 2 false plots per second appear in the plot output. Means must be provided to reduce the asynchronous replies and other interference with an effectiveness of 0.998 meaning that out of 1000 fruit replies/sec only 2 fruits replies/sec will be at the output. Defruiting can be part of the IFF extractor.  

(R.T53)  Means  shall  be provided  to  reduce  the probability  of  failing  to declare a  real  plot and of reporting a false plot.  

(R.T54)  deleted  

(R.T55)  SR/SSR Plot Association criteria:  

Means shall be provided to associate transponder replies to the primary radar plots; 

In any mode of operation an SR plot report and an SSR plot report of the same target shall be automatically associated; 

When both SR and SSR detections are available  for a  single plot  report,  the  range, azimuth data and time data  included  in  the SR/SSR plot  report shall be those  from the SR report; 

SR/SSR plot correlation shall be tested during in site test using dedicated flights. 

Means  for  sectorised  power  reduction  or  general  inhibition  of  radiation  shall  be provided (from local control and remote control); 

Range  and  azimuth  bias  error  correction  via  a  site‐dependent  and  used‐adaptable data, (e.g. from lookup table). 

 

6.8. Jamming Analysis Receiver 

(R.T56)  The  new  system  shall  interface  with  the  original  Jamming  Analysis  Receiver  and provide at least the same control and jamming information as the original system.  

6.9. System Clock  

(R.T57)  The  System Clock  (SC)  shall  provide  an  accurate  time  reference  for  the  tagging  of system  data  and  synchronization  of  communication  equipment.  It  shall  include  a  Global Positioning System (GPS) receiver, an external interface for synchronization and an accurate oscillator  to  allow  extended  operation  without  external  synchronization.  Battery  support shall allow the clock to continue running in the event of mains failure. The system clock shall include an indication of current time in hours (0‐24), minutes and seconds in digital form.  

   

Page 16: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.11 

 

(R.T58)  The system clock shall encompass the following equipment:  

• rack  mounted  units,  including  batteries,  receiver  and  interconnecting cables; 

• external antenna; • antenna/shelter cable; 

 

(R.T59)  The  system  clock  shall  provide  a  time data  output with  status  data  to  the RCDSS. The  external  synchronization  shall  conform  to  IRIG  104‐70,  format  B.  Time  required  to achieve  initial synchronization shall be  less than 10 minutes  (assuming a GPS satellite  is  in view). Synchronization shall subsequently be checked and adjusted automatically. Receivers and antenna required for this purpose shall be supplied as part of the SC.  

(R.T60)  The receiver shall accept the GPS satellite signals.  

(R.T61)  The equipment shall operate from the available mains power.  

(R.T62)  In terms of accuracy and stability, the timing source shall be such that timing data contained  in messages  represent  the  true GMT at  least  to  the nearest  1/64  second  at  all times other than during periods of initial synchronization. In the event of loss of time coded transmissions the accuracy shall be maintained for a period of at least 30 days.  

(R.T63)  deleted  

(R.T64)  Antenna feeder. The clock system design shall allow the clock antenna to be located up to 80 meter from the receiver with 30 meter of cable within a Shelter and 50 meter of external cable between the Shelter and the Antenna.  

6.10. RCDSS: Data Processing and Communication 

(R.T65)  The  new  system  shall,  at  least,  contain  and  perform  all  the  Data  Processing  and Communication  functions as  the ones  offered by  the original  RCDSS  equipment.  Amongst those:  

(R.T66)  The  3D  primary  height  calculation  technique  shall  provide  at  least  the  same information and accuracy as the original system (if the function is not already performed by the Signal Processor).  

(R.T67)  Association of primary and secondary plots to form a combined plot.  

(R.T68)  A Multi Scan Correlator function to reduce false plot production significantly in case of heavy clutter or jammer condition.  

(R.T69)  The effects of moving clutter that may be caused by surface vehicles, ground objects and  birds  shall  be  suppressed  by  the Multi  Scan  Correlator.  It  shall  be  possible  to  setup individual  parameters  in  7  different  user  defined  special  processing  areas  and  for  the background.  

(R.T70)  In each special processing area it shall be possible to set the individual clutter filter parameters:   

Minimum Velocity 

Maximum Velocity 

Page 17: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.12 

 

The tracking parameters 

Track Initiation criteria 

Maximum Turn Rate 

Track Coasting 

 

(R.T71)  Setting  start  range  of  a  tracker  special  processing  area  to  zero  shall  disable  the special processing area. 

(R.T72)  If special processing areas overlap the  lowest number special processing area shall take priority. 

(R.T73)  A function enabling to perform the North alignment of the primary radar (e.g. SUN strobe or ADS‐B) in coordination with the PET.  

(R.T74)  Management of the Built In Test Equipment (BITE) with information display.  

(R.T75)  System  Control  commands.  At  least  the  original  system  control  commands  are required.  

(R.T76)  A communication function to:  

Format  and  pass  the messages  listed  in  annexes  4A  and  4B  to  the  ROCs  (Remote Display  System,  RDS).  It  should  be  noted  that  up  to  two  distinct  ROCs  can  be simultaneously connected to a given radar head.  

Receive  primary  and  secondary  radar  systems  control messages  from  the  ROCs  as described in annex 4A. 

 

(R.T77)  Each radar output shall be connected to modems, and the modems outputs shall be connected to crypto devices which will be provided and installed as PFE. The modems to be used by the manufacturer shall be compatible with crypto equipment. The mechanical and electrical  specifications of  the crypto equipment will be provided  to  the contractor  in due time. Suitable place for crypto devices shall be provided at the same rack with modems.  

(R.T78)  A module to maintain and display time and date information received from System Clock  –  GPS,  in manual  (if  the GPS  signals  are missing)  and  automatic mode.  The  system clock will be used for plot time stamping.  

(R.T79)  Information  Time  Delay.  The  time  delay  shall  be  measured  between  the  time  of detection and the ADP interface at the Line Sharing Device (LSD) assuming a sufficient line capacity.  

(R.T80)  Integration within  the existing Automatic Data Processing environment.  The  radar system  will  be  integrated  into  the  existing  NADGE  system.  The  radar  system  shall  be designed  in such a way that the  integration  into the ACCS Network  interface will be easily achievable  (see  also  6.3.4).  This  shall  be  achieved  by  implementing  a  Data  Buffer  and  a Priority Filter. 

(R.T81)  All information produced by, or fed into, the radar system shall be stored in a Data Buffer  (DB).  The  radar  system  shall  derive  subsets  of  this  information  to  be  sent  to  a 

Page 18: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.13 

 

connected  user  (ROC).  Different  users may  require  different  subsets  of  the  Data  Buffer's contents.  

(R.T82)  In addition, by remote controlling the Priority Filter (PF), a remote user may assign priorities to types of data. The radar system shall then assemble the information to be sent in the required order.  

(R.T83)  Information derived by the radar system shall be kept present in the Data Buffer for 30 days and for easy access at a later time.  

(R.T84)  The  DB  and  PF  structures  shall  be  realized  with  software  and  shall  be  well documented.  

(R.T85)  Control Commands from Automatic Data Processing (ADP). The commands received from  the ADP system shall  control  the users Priority Filter with  the mode 4  interrogation, the radar silence function and the area outlines requests.  

(R.T86)  Line  Sharing.  Existing  lines  shall  be  used  for  integration  with  ADP,  i.e. communications between:  

the radar terminals and the radar head  

ADP and the radar head  

 

(R.T87)  It  is  foreseen  that  the  various  interfaces  to  the  LSD  are  subject  to  changes. Therefore, the functions of the LSD shall be provided by software.  

6.11. RCDSS: Monitoring and Control 

(R.T88)  The new System shall, at  least, contain and perform all the CONTROL and DISPLAY functions offered by the original RCDSS display equipment (Maintenance Work Station and Performance Evaluation Computer) in order to:  

Monitor  and  control  all  functions  and  the  performance  of  the  radar  at  the maintenance work station of the radar set 

Monitor and control operational functions and performance of the radar at the TPO (see hereafter) position in the operations center 

Monitor and analyze the ECM, chaff and clutter environment and to control the ECM and clutter reduction facilities of the radar at the ECCMO position in the operations center 

Track  Production  Officer  mode  (TPO)  enabling  monitoring  and  control  of  the peacetime radar facilities 

Electronic  Counter‐Counter  Measures  Officer  mode  (ECCMO)  offering  all  the capabilities of the TPO mode plus monitoring and control of the wartime facilities 

 

(R.T89)  The monitoring and control facility at the Maintenance Work Station shall include all capabilities specified for the facilities at the TPO and ECCMO positions.  

(R.T90)  Information  displayed  at  the  terminals  shall  be  easily  readable.  Graphic, alphanumeric  and  combined  graphic/alphanumeric  presentations  shall  be  provided  to 

Page 19: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.14 

 

accomplish this. Control actions entered by the operator shall be  indicated on the display. The acknowledgement of such control actions shall also be indicated on the display.  

(R.T91)  Control of  the  radar  shall be possible  from  two  local positions  (maintenance work station at the radar head and a position in the bunker) and two remote positions, where the remote positions shall have primary control as default, but the local position can take over in an orderly manner.  

Among those: 

(R.T92)  Maintenance  Work  Station.  The  radar  head  shall  be  provided  with  a  means  to continuously  supervise  equipment  operation,  to  operate  the  radar  and  to  support maintenance  actions.  These  means  shall  be  centralized  at  one  position  which  will  be referred  to  as  the  maintenance  work  station.  The  new  maintenance  work  station  shall include at least the following elements:  

A plan position indicator displaying  

PSR videos  

SSR videos 

PSR plots  

SSR plots  

Associated PSR/SSR plots  

Jamming Strobes 

Radar height upon request  

SSR mode/code information on selected plots (only) 

Mode 4 target status information upon request 

Clutter areas outlines  

A monitoring  and  control  facility  to  cover  the  TPO  and  ECCMO  functions  and  the mass raid assessment function. 

Some monitoring devices to display the more detailed equipment status to  include among others the BITE check results. 

A Remote Control & Display to display relevant equipment status data of the radar system. 

Some  control  devices  to  operate  the  radar  head  as  far  as  not  covered  by  the monitoring and control facility to include all control functions.  

 

(R.T93)  Monitoring and Control Facility (TPO). The terminal at the TPO position shall consist of a general purpose, alphanumeric and graphic display (or PPI) and a keyboard. It shall be possible  to select display of video‐status  information. An audible alert and  force attention display capability shall be provided to indicate changes of certain status information. It shall be possible to execute control functions to two (2) Radars with a growth capability to four (4).  

(R.T94)  TPO Video‐Status Information  

For the TPO the following status information shall be available for display:  

Electrical power source go/no go  

PSR overall status go/no go   (**)  

Page 20: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.15 

 

PSR limited operation e.g. (**) 

PSR‐TX/RX modules out, 

processor failure,  

Spine temperature  

PSR TX radiate/not radiate  

PSR detection performance in clear environment  

Radar in maintenance mode  

PSR plot/strobe processing capacity occupied (*) (**)  

Data Buffer processing capacity occupied (*) (**)  

SSR go/no go (**)  

SSR TX radiate/not radiate (**) 

SSR Extractor processing capacity occupied (*) (**)  

PSR Battleshort  

Frequency Mode  

Selected Peacetime Frequency  

PSR Search Mode  

SSR Interlace  

SSR ECM Warning (**) 

Number of PSR and SSR plots per scan for transmission  

Processing channel  

Manual ECM  

Mass raid  

Area outlines for modes of operation, priority filter settings, and clutter filter  

Activated inhibit (PSR, SSR or both): sectors (from azimuth to azimuth)  

Connected  users  conspicuously  indicating  the  ops  center  having  control  over  the radar  

Fire detection (**) 

Notes:  

(*)  Warning threshold shall be selectable, status and overflow shall be indicated.  

(**)   Audible, alert and force attention display.  

(R.T95)  Also the following video shall be available for display for the TPO:  

PSR video (co‐located site only)  

SSR video (co‐located site only)  

PSR plots  

SSR plots  

Associated PSR/SSR plots  

Strobes  

SSR mode/code information  

Mode 4 plots upon request  

Clutter outline data  

Synchronization data (co‐located site only)  

Area outline data  

Page 21: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.16 

 

(R.T96)  TPO Radar Control Functions. It shall be possible for the TPO to execute at least the following control functions:  

PSR Inhibit  

SSR Inhibit 

PSR/SSR Inhibit  

SSR Interlace  

Radar Silence  

Fixed  frequency selection  (to be set anywhere  in  the required operating  frequency bandwidth)  

Filter Setting  

PSR Operating Modes (as applicable)  

Warning threshold control  

PSR processing channel  

 

(R.T97)  Monitoring and Control Facility (ECCMO). The terminal at the ECCMO position shall consist of a general purpose, alphanumeric and graphic display and a keyboard.  It shall be possible to select display of status information. An audible alert and force attention display capability shall be provided to indicate changes of status information. It shall be possible to execute control functions.  

(R.T98)  ECCMO Jamming Information. The status information as specified in (R.T99) shall be available for display for the ECCMO. This shall be accomplished by selecting the TPO‐Mode.  

(R.T99)  In the ECCMO‐Mode the following jamming status information shall be available for display:  

Bearing  and  intensity  of  all  jamming  strobes  in  a  geographic  form  (update  per antenna scan) 

Quantity of jamming strobes per antenna scan and changes thereto 

Frequency,  intensity  and  type  of  jamming  over  the  entire  radar  bandwidth  in  one display (update per antenna scan) 

Azimuth,  intensity,  width,  elevation,  and  type  of  jamming  of  selected  strobes  on request (update per antenna scan) 

Equipment  status  to  include  selected  frequency  (band),  selected  frequency, mode, activated ECCM, selected search modes, SSR ECM warning, radar silence for PSR and SSR (update cycle 1 min) 

 

(R.T100)  ECCMO  Radar  Control  Functions.  It  shall  be  possible  for  the  ECCMO  to execute at least the following control functions:  

PSR Battleshort  

Frequency Modes of operation  

Search Modes of operation  

Activate ECCM's  o SLB  

Page 22: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.17 

 

o High PRF o Stagger PRF 

Warning Threshold Control  

 

(R.T101)  Terminals. TPO and ECCMO terminals can be combined in one workstation.  

(R.T102)  Capability to display information from the original Jamming Analysis Receiver installed within the SPINE.  

(R.T103)  Capability  to  control  the  radar.  The  full  radar  system  should  be  made available  fully  operational  after  reboot  in  not  more  than  6  minutes.  However  this  time requirement might be readjusted depending on the specific SPINE booting process but, shall be minimized.  

(R.T104)  Capability  to  present  the  radar  video  signals  echoes/plots/strobes  in different presentation forms (at least Plan Position Indicator and Range Height Indicator).  

(R.T105)  The  possibility  to  display  overlays  and  grids  when  displaying  radar  signals, including at least geographic maps, range rings and lines of constant latitude and longitude. 

(R.T106)  The possibility to display, record and playback information.  

(R.T107)  A capability to maintain and display time and date information. 

(R.T108)  All display monitors shall be Flat Screen displays having at least 21” of useful area for information display.  

(R.T109)  The load status of HW and SW components shall be reflected in status data of  the  radar  terminals.  In  case of  critical  SW or HW  load  conditions operations personnel shall  be  alerted  prior  to  the  occurrence  of  an  overload  situation.  The  operator may  then take corrective actions to avoid functional degradation of the system. A capability shall be provided  which  allows  the  operator  to  individually  set  the  load  threshold  for  the  alert. Nevertheless,  should  any  overload  condition  occur,  system  functions  of  high  operational priority shall be preserved as long as possible while low priority functions shall be degraded first.  

6.12. RCDSS: Bite Reporting 

(R.T110) BITE reporting is originally made through the RCDSS. The new BITE processor and  display  shall  provide  the  same  status messages  as  the  original  system  regarding  the original  subsystems.  The  new  BITE  shall  interact  with  the  SPINE  which  is  to  remain untouched.  

(R.T111) The BITE reports shall also be sent to a Remote Display System (RDS) located up to 100 meters from the radar. The RDS will be the same display as the one located within the Electronics Shelter.  

(R.T112) The original BITE architecture and associated message structure  is  available at NSPA in the relevant system documentation (list of available documents in Annex 3).  

Page 23: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.18 

 

6.13. RCDSS: Data Buffer 

(R.T113) The  radar  system  shall  have  a  function which  is  referred  to  as  Data  Buffer (DB).  

(R.T114) The  DB  represents  a  database  in  which  all  data  available  in  the  radar  is stored. This comprises target data as well as the actual radar modes of operation and data from  the  built‐in  test  equipment  (BITE).  In  addition,  selection,  sorting  and  association  of various data have to be performed, usually under control of the user of the DB.  

(R.T115) The  DB  structure  shall  be  realized  with  software  and  shall  be  well documented.  

(R.T116) The functions of the DB shall be as follows:  

(R.T117)  Data generated by the extractor or other sources shall be fed into the buffer independent of  the  source of  the data.  This data  is  then available  for  transmission  to  the different operating centers or other users or for use by the radar system.  

(R.T118)  The  DB  shall  be  the  only  interface  between  the  radar  head  and  its environment. Therefore the DB has to maintain radar generated data (e.g. plot data) as well as user received data (e.g. control commands).  

(R.T119)  The setting of a certain mode of operation shall be accomplished by storing the  appropriate  control  data  into  the  DB,  regardless  of  the  source  of  the  data  (radar terminals, manually entered on user's DP system).  

(R.T120) A capability shall be provided to automatically count all PSR and SSR plots per scan in the data buffer for transmission to a user.  

(R.T121)  An  audible  and  visual  warning  shall  be  provided  if  the  numbers  of  plots between two consecutive scans increase or decrease by a percentage figure which shall be selectable in steps of 5, 10 and 30.  

(R.T122)  A  copy  of  the  clutter  map  shall  be  part  of  the  DB.  The  map  may  be transmitted to the user as a set of points which represent the outline contour formed from those sample strengths which exceed a threshold (the ISO clutter level) set by the operator.  

(R.T123) It is a task of the PF to transform the clutter map into the format required by the user.  It must be possible to send the whole map as well as only a set of points, which represent  the  outline  contour  formed  from  those  sample  strengths  which  exceed  a threshold (the ISO clutter level) set by the operator. The transformation of the clutter map performed by the PF may also comprise a reduction of the resolution of the map.  

The set of points (ISO Clutter Line) is sent to the RDS ‐ and then to the NADGE ADP. 

NOTE: A reduction in resolution of the clutter map is controlled by the Remote User(s). 

(R.T124)  The  clutter  map  is  for  interaction  with  the  Remote  Site  only  and  not  for interaction with remote radar integration network.  

Page 24: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.19 

 

6.14. RCDSS: Priority Filter 

(R.T125) The  selection  of  data  to  be  transmitted  to  a  user  shall  be  performed  by  a function called Priority Filter (PF). The PF structure shall be realized with software and shall be well documented.  

(R.T126) Each user shall have his own PF that can be set to best fit operational needs at any time.  

(R.T127) The  PF  shall  be  capable  of  performing  the  selection  of  data  as  well  as  a prioritization of the sorting of data.  

(R.T128) The setting of the PF for a user shall also be part of the DB. The user may set his PF by assigning priorities to types of data.  

A typical assignment may be (in order to decreasing priorities):  

Strobes from a specified sector or cone  

Plots from a specified volume  

Other strobes  

Other plots  

Other data (amplifying data, status data)  

The PF  then has  to  search  the  available  data  in  the DB and  to  decide  about  transmission according to the priority level and free line capacity.  

(R.T129)  Time Tag. Data with  low priorities may be delayed and shall be kept  in  the DB for a certain time. This time shall be user‐selectable and shall be part of the PF setting. Due to possible delays all data in the DB shall be tagged with the time of detection. For this purpose the radar system shall be equipped with a highly accurate real time clock.  

(R.T130)  Formatting of Outgoing Data, Realization of the DB and PF Structures. The PF also  shall  format  the  outgoing  data  into  the  required  message  types.  The  DB  and  PF structures  shall  be  realized with  software and  shall  be well  documented. A  change  to  the message formats or to the logic of the PF shall be possible by software change only. 

6.15. RCDSS: Performance Evaluation Computer (PEC)  

(R.T131) A  computer  called  Performance  Evaluation  Computer  for  the  evaluation  of radar performances in day to day operation as well as for special radar evaluation mission shall  be  a  part  of  the  RCDSS  environment.  This  computer  enables  the  operator  to  record radar  plots  and  off‐line  checks  of  the  system  alignment.  The  PEC  shall  also  offer  a  North alignment capability using Sun strobes or ADS‐B. A new evaluation tool (PET) running on a PC  shall  be  proposed  at  least with  the  same  test/recording  functionalities  as  the  original PEC.  

6.16. Remote Display System (RDS)  

(R.T132) Two types of RDS sites are to be considered:  

•  co‐located with a S723 radar head as in Bornholm 

•  non co‐located with a S723 radar head as in KARUP 

Page 25: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.20 

 

Co‐located and non‐co‐located RDSs are identical except for the fact that the co‐located RDS shall additionally provide the operators (TPO and ECCMO) with the primary and secondary video signals upon selection.  

(R.T133)  The new RDS shall, at least, contain and perform all the functions offered by the  original  RDS  equipment  in  terms  of  display,  data  processing  and  remote  control capabilities. 

(R.T134) The RDS shall perform the Line Sharing Device Functions and shall be a single computer subsystem of the same form as used in the RCDSS (i.e. uses identical elements of hardware  as  well  as  sub‐sets  of  software  elements).  The  Remote  Processor  (RP)  shall support at least the following equipment:  

PPI display and control console  

TPO radar terminal  

ECCMO radar terminal 

EC RES terminal 

ADP interface 

Radar interface  

 

(R.T135) Like for  the RCDSS at the radar head, TPO, ECCMO and EC terminals can be regrouped  in  one.  The  RP  shall  be  designed  to  accommodate  all  necessary  interface processors for communications with the above equipment as integral parts of the computer. These processors shall be connected directly to the internal bus and where necessary have autonomous  access  to  random  access  memory.  The  RP  shall  include  the  line  sharing functions  to allow the same set of  lines  to be used  for all  communications with  the  radar head.  

(R.T136) The RP shall route the data associated with the radar being controlled to and from the ADP  (RIS/MASE network, annex 4B). The RP shall  route  the data associated with the  radar  being  controlled/monitored  to  the  PPI  display  and  the  radar  terminals  as  fitted (annex 4A).  

(R.T137) Capability to display radar reports as listed in paragraph 6.10 and 6.11.  

(R.T138)  The  RDS  shall  provide  a  TPO  and  an  ECCMO  terminal  for  the  control  and monitoring of the radar, together with a single PPI display. The PPI shall display data relating to the radar which is being controlled by the RDS.  

(R.T139)  All terminals in an RDS shall be of identical type to those used in the RCDSS, and  shall  consist of a display and keyboard.  The  terminals  shall  incorporate alphanumeric and graphics displays. Control actions entered by the operator at an RDS terminal shall be indicated  on  the  display,  normally  on  a  single  line  at  the  bottom  of  the  display,  and acknowledgement  that  the  input  command  has  been  actioned  shall  be  indicated  on  the same display. All data entry at the RDS radar terminals shall be validated. Invalid entry shall result  in  the  data  being  aborted  and  data  entry  (i.e.  control)  then may  be  recommenced again.  

Page 26: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.21 

 

(R.T140) The RDS shall have the capability to operate at the required link rates without any data degradation or reduction of operational facilities and capabilities.  

(R.T141) RDS/RADAR ‐ PPI Data (when co‐located at radar). When a ROC and a radar head  are  co‐located,  the  radar  head  shall  provide  the  following  signals  for  the  RDS  PPI display:  

Delayed Display Trigger  

ACP and delayed NM (NRP) 

The  "delayed"  signals  are  timed  to match  the  processing  delays  within  the  Signal Processor 

Videos 2 PSR and 2 SSR 

 

(R.T142) Capability to present the radar plots/tracks/strobes in different presentation forms at least Plan Position Indicator and Range Height Indicator.  

(R.T143) The  possibility  to  display  overlays  and  grids  when  displaying  radar  signals, including at least geographic maps, range rings and lines of constant latitude and longitude.  

(R.T144) The possibility to display, record and playback information.  

(R.T145) A module to maintain and display time and date information 

(R.T146) All display monitors shall be Flat Screen displays having at least 21” of useful area for information display. 

(R.T147) ADP. Direct conversion of the radar data into RSRP format for transmission to radar  integration  network  (serial  line  although  Ethernet  TCP/IP  is  acceptable).  Refer  to annex 4B for a description of the messages format.  

(R.T148) Loop  test  function  to  check  and measure  the  status  and  capabilities  of  the communication lines.  

(R.T149) The  communication  functions  shall  be  compatible  with  the  crypto  devices installed by the Host Nation to decrypt radar head messages.  

6.17. Performance Evaluation Tool (PET)  

(R.T150) A  new  Performance  Evaluation  Tool  (PET)  running  on  the  PEC  shall  be proposed  at  least  with  the  same  test/recording  functionalities  as  the  original  PEC.  This includes Data Analysis and Display, Output Data File and PET Environment. 

(R.T151) A dedicated  Computer with  specific  interfaces  shall  be  installed  for  hosting PET software. This tool will be used at least:  

by the site technicians for standard system maintenance 

during periodic site visits by NSPA R‐SPC engineers 

for OSM 

for system acceptance tests 

It  shall  be  possible  to  check  the  alignment  of  the  surveillance  radar  and  the secondary surveillance radar  to  true north by using solar  radiation and to evaluate radar performance by using flight data 

Page 27: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.22 

 

These facilities shall record, store, process, analyze and display radar target data as well as manual input data if necessary and shall be interfaced with the radar head in an appropriate manner (refer to the PET requirements) 

 

(R.T152)  At least the following additional capabilities are required:  

verification  of  the  good  working  state  of  the  beam  calibration  loop  with  manual adjustment capabilities  

verification of the beam alignment for the height calculation 

verification  of  the  stability  and  performance  of  the  Tx  pulse  expander  and  pulse compression units 

verification of the good working state of the SLB logic 

verification  of  the  good  working  state  of  the  target  detection  logic  in  different clutter/ECM etc conditions 

verification of the antijamming capabilities 

verification of  the  correct  removal  of  “n”‐th‐time  (n≥2)  around echo  for  targets of large RCS  

 

(R.T153)  The  SPINE  shall  remain  untouched  by  the  system  upgrade:  none  of  the equipment/sensors  implemented  by  the  contractor  and  necessary  to  apply  the  different tests shall be installed inside the SPINE.  

(R.T154)  deleted  

(R.T155)  The  PET  shall  have  a  specific  analysis  software  package  and  contain  a Graphical User  Interface  for operator controls and display. The PET shall allow  for specific analysis  of  data  recorded  from  the  radar  for  evaluation  of  radar  operations  and performance  as  the  original  PEC. Only  the  types  of  analysis  offered  by  the  PEC  are  to  be retained but not the way they are displayed. The data recorded by the PET in real‐time shall include upon selection by the operator:  

All incoming plots and jamming strobes 

All radar status messages 

 

(R.T156)  The PET shall be able to record all measured information in real time mode and  the  input/output  data  of  the  DSP  sub‐software  module  analyses  result  shall  also  be processed and displayed in real time. (The plot output time delay with regard to real time is determined by Contractors but shall be better than or equal to the original as  indicated in Table 1 in Annex 3).  

6.17.1. Radar Raw Data Files  

(R.T157)  The radar RAW data is related to the radar settings in any operation mode. The  radar  RAW data  recordable  by  the new  system  shall,  at  least,  cover  the  type of  data recorded  by  the  original  RCDSS  equipment.  In  addition  at  least  the  following  information shall be recordable in order to be further analyzed and displayed:  

Page 28: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.23 

 

Incoming (receive beams) and outgoing (expanded pulse) IF signals of the Electronics Shelter, 

Raw video for each beam before and after pulse compression 

Raw video before and after CFAR 

Data  of  all  beam  channels  before  automatic  selection  on  combination  of  the  best channel(s) logic of the signal channels and after it 

clutter/chaff map built by the new system 

Jamming  information  from  the  original  Jamming  Analysis  Receiver  (JAR)  and  from the Signal Processor 

Mass Raid 

Beam alignment information 

 

(R.T158) The  RAW  data  files  and  PLOT  files  are  to  be  analyzed  and  results  are displayed  to  the  operator.  The  results  of  the  analysis  of  the  RAW  data  are  also  to  be transferred  into an OUTPUT data  file  readable and  transportable on platforms external  to the site.  

6.17.2. Data Analysis and Display  

(R.T159) The RAW data and PLOT analysis is at least to be displayed as follows:  

Maps: 

DTM (Digital Terrain) 

Radar coverage  

Clutter  

SR/SSR plot association and alignment 

SR/SSR plot accuracy 

SSR decoding statistics 

Sun position/strobe calculation 

Azimuth Accuracy /Jammer strobe resolution Accuracy  

 

Plots: 

PSR Plots 

SSR Plots 

Combined Plots 

Jamming Strobes/Sectors 

Mass Raid Analysis 

Jamming Analysis 

Radar System Status 

Azimuth Status messages 

 

(R.T160) Range performance worksheet (Preferably Blake Chart type)  

Page 29: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.24 

 

(R.T161) Pd (Probability of detection)  

(R.T162) Pfa (Probability of false alarm) analysis 

(R.T163) Automatic Rx. Gain Equalization and alignment analysis 

(R.T164)  Shape  of  the  Expander  Output  IF  waveform  with  visual  indication  of compliance with specifications.  

(R.T165)  Shape  of  the  Compressed  Pulses with  visual  indication  of  compliance with specifications (for all beams and SLB channel).  

(R.T166)  Clutter map  performance  analysis:  PPI  representation  of  the  Improvement Factor  (IF), with visual  indication of  compliance with specifications. The  IF evaluation shall be user selectable to be performed using real clutter or a CFP Radar Target Generator.  

(R.T167)  PPI representation of Jamming Strobes.  

(R.T168)  PPI representation of the Jamming information of the JAR and the SP 

(R.T169)  PPI Mass  raid  representation  can  be  filtered  for  position,  beam messages, and frequency.  

(R.T170)  The Digital Signal Processing (DSP) Performance check function can calculate the amplitude or phase for the selected data. Analysis results can be displayed in the form of tabular lists and 2‐D graphs.  

(R.T171)  DSP Performance. This analysis task shall use, at least, two types of data files recorded from the DSP prior to plot extraction to evaluate DSP performance:  

DSP DDM (Digital Demodulation) files: These files contain “raw” I & Q (In‐phase and Quadrature)  data  for  the  8 Main  and  SLB  channels.  DDM  files  can  be  filtered  for beam messages, short/long range and frequency. 

DSP envelope files: These files contain data already processed by the DSP. Envelope files  can be  filtered  for  position,  beam messages,  short/long  range  and  frequency. The DSP Performance function can calculate the amplitude or phase for the selected data  for  the  8  receive  channels  and  the  SLB  channel.  Analysis  results  can  be displayed in the form of tabular lists and 2‐D graphs. 

 

(R.T172)  Plot  loading  statistics  represented  per  beam  as  a  function  of  time  (scan): combined plots, SR plots, SSR plots, false alarms.  

(R.T173)  SR/SSR alignment (range, azimuth and height).  

The display environment shall offer the capability to print the displayed results and to save them as a picture file (at least in JPEG format). 

6.17.3. Output Data File  

(R.T174) The  output  file  compiles  the  results  of  the  analysis.  At  least  two  types  of output files shall be considered: the output radar data file and the output plot data file.  

(R.T175)  Those files are to be produced in ASCII (text).  

Page 30: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.25 

 

(R.T176)  The  OUTPUT  radar  data  file  is  to  present  the  results  of  the  analysis;  its structure shall be suggested by the contractor and approved by NSPA at the end of design phase.  

(R.T177)  The  OUTPUT  plot  data  file  shall  present  at  least  the  following  plot information:  

For each PSR,SSR combined plot: range, azimuth, elevation angle, detection time 

For each combined/primary plot: Beam number 

For each combined/primary plot: Mass raid flag 

For each combined/primary plot: calculated height 

For combined/secondary plots: IFF codes for each interrogation mode 

For jamming strobes: azimuth, elevation, frequency 

6.17.4. PET Environment 

(R.T178)  The  PET  shall  be  developed  and  run  under  a  high  level  programming environment (like MATLAB or NATIONAL  INSTRUMENTS/LABVIEW for  instance)  in order to facilitate the migration to other analysis tools external to the radar.  

6.17.5. Test Points 

(R.T179)  A number of tests and monitoring points shall be made available on a front plate within the Display Shelter for maintenance and verification purposes.  

(R.T180)  The  following  Radar  Timing  Signals  test  points  shall  be  made  available mounted as a female BNC connector:  

NRP true 

NRP corrected 

ACP 

Trigger 

 

(R.T181)  The  monitoring  of  the  Expander  Output  IF  and  compressed  pulses  for  all beams shall be made available on SMA front plate connectors. 

(R.T182)  Separate Analogue Radar logarithmic video for each of the 8 beams and SLB channel (one distinct test point for each of the 8 beams and SLB channel).  

(R.T183)  One or several external connection points to the RRH LAN(s). 

 

6.17.6. Radar Environment Simulator (RES) 

(R.T184) The  RES  shall  produce  a  fully  realistic  simulation  of  primary  radar  signals received by the S723 under normal and hostile (ECM) conditions in order to;  

Train  the  site  personnel  in  the  optimization  of  the  radar  system  settings  for detection within a predefined environment,  

Page 31: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.26 

 

Provide  a  realistic  ECM environment with  compromising  the  radar  system’s  active ECCM capabilities to hostile ELINT/SIGINT observations,  

Assess the radar’s effectiveness under EW conditions.  

 

(R.T185) The RES shall generate simulated signals to be mixed with live signals of the primary radar.  

(R.T186) These  signals  shall  include a  range of different  types of  targets, which  shall have a target identity tag hidden from the operator, together with simulated jamming and chaff to be reproduced over the complete operating frequency band of the radar.  

(R.T187) The  RES  target  identity  tag  shall  be  included  in  all  associated  output messages (i.e.; plot, strobe and chaff).  

(R.T188) The RES shall simulate all radar processes prior to the point of signal injection (e.g. Transmitter frequency, power and waveform, antenna gain patterns, propagation, etc.) and respond to all radar controls.  

(R.T189)  RES  shall  be  capable  to  accept  both pre‐programmed  scenarios  and online commands for processing.  

(R.T190) RES control shall be both local and remote from any CE and/or RRH.  

(R.T191) Targets and any associated ECM effects (e.g.; jamming and chaff dispensing) shall  automatically  cease when  the  target  is  declared  killed  by  any  CE.  However,  already shown chaff will continue blooming in accordance with the established parameters.  

(R.T192) The radar performance shall not be degraded by the addition of the RES.  

(R.T193) The  RES  shall  be  used  also  for  testing  purposes,  therefore  should  contain validated  target models  to assure  that  the  test  results which are generated using  the RES are indicative of system performance.  

(R.T194) Exercise duration: At least two hours with maximum simulation load.  

(R.T195) Target Capability:  

(1) Up to 60 targets of which 12 are controllable in real time, the rest being pre‐

programmed, 

(2) Up to 12 jamming aircraft of which 4 are controllable in real time, the rest being 

pre‐programmed, 

(3) Three aircraft may overlap in azimuth on any bearing, two may be active 

jammers, and one may be a chaff dispenser. 

 

(R.T196) Active Jamming Simulation Capability 

(1) Twelve active jamming aircraft per scan of which up to four can be controlled, 

the rest being pre‐programmed, 

Page 32: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.27 

 

(2) It shall be possible to simulate synchronous repeater jamming together with at 

least two other types of active jamming from any source in the entire frequency 

band.  

 

(R.T197) Jamming power levels: 1 to 70 dB above radar system noise level. 

(R.T198) Chaff Simulation Capability 

(1) Four of the 12 active jammers can also be chaff dispensers, each being able to 

drop three legs of chaff of total mass one ton distributed in the appropriate 

wavebands, 

(2) Chaff parameters will be controllable (horizontal and vertical speed blooming 

rates, spread, density, turbulence), 

(3) Up to 12 chaff legs per scan and up to eight chaff legs to be positioned 

simultaneously, 

(4) The bloomed chaff velocity spectrum shall be consistent with the radial velocity 

spectrum of any collocated live weather. 

 

(R.T199) The RES shall provide the following capabilities:  

(1) Start/stop RES simulation,  

(2) Setting the sectors in which the RES shall be active,  

(3) Choose up to 16 exercise programs,  

(4) Interrupt a simulation program at any point during the exercise and subsequently 

restart the program at any point in time in the scenario,  

(5) Initiate up to 4 targets and modify their track and jamming parameters at any 

point during an exercise or during normal day‐to‐day operation (controllable 

jamming targets).  

 

6.17.7. Installation  

(R.T200) The S723 RHS Modkit shall be contained in one 19 inch cabinet to be installed outside  the Electronics shelter  (in an equipment room next  to  the shelter  room) and shall accept the mains available in the equipment room.  

(R.T201) The cabinet  shall not make use of  the S723 original air  conditioning system and shall therefore contain a cabinet ventilation and cooling system.  

(R.T202) The  cabinet  shall  include  a  UPS  in  order  to  supply  all  software‐based equipment  for  a  minimum  period  of  15  minutes.  This  is  applicable  for  both  Radar  Head Solution (RHS) and Remote Solution (RS).  

Page 33: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.28 

 

6.18. Reliability, Maintainability and Testability 

6.18.1. Reliability 

(R.T203) The system shall have the following reliability characteristics:  

Minimum MTBF = 1400 hrs 

Minimum MTBCF = 6000 hrs 

where  failures  shall  include  all  hardware  faults within  the  installed  equipment  as well  as software faults that degrade the performance of the system with respect to its specification.  Critical  failures  are  those  failures  which  result  in  a  cessation  of  the  system  capability  to perform its mission and require immediate corrective action.  

6.18.2. Maintainability 

The system shall have the following maintainability characteristics: 

(R.T204) At least 95% of all maintenance tasks (HW and SW) shall require skills, tools and test equipment such that they can be carried out at Organizational Level1.  

(R.T205) Maximum MTTR(O‐level) = 20 minutes.  

(R.T206) The  system  shall  not  require  organizational  level  preventive  maintenance other than visual checks and start‐up self‐calibration and/or test. 

6.18.3. Testability 

The system shall have the following Built‐in‐Test (BIT) capability: 

(R.T207) The  radar  shall  provide  BIT  capabilities  to  meet  the  maintainability requirement using On‐Line & Off‐Line diagnostics. 

(R.T208) The new BIT equipment (BITE) shall be compatible with the existing BITE.  

(R.T209) Start‐up BITE shall be initiated at system/equipment power‐up and it shall be able to diagnose the respective LRU in less than 5 minutes.  

(R.T210) On‐line  BIT  shall  be  able  to  detect  98%  of  the  LRU  failures.  On‐line  BIT isolation capability shall be as follow:  

100% of the failures within a group of not more than 3 LRUs; 95% of the failures within a group of not more than 2 LRUs; 90% of the failures to 1 LRU.  

   

                                                            1 Organizational  Level Maintenance  includes  fault monitoring  by BITE  and/or  visual  inspection,  removal  and replacement of LRUs, system functional testing and preventive maintenance tasks. The maintainers use simple test equipment (standard and special‐to‐type) in addition to BITE for on and off line diagnostics.  O‐level support for SW includes all those tasks that are within the capabilities of a system manager, i.e. on and off line diagnostics, manual restart, upload of SW upgrades and patches, etc. 

Page 34: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.29 

 

 

7. PROJECT DEVELOPMENT AND MAJOR TECHNICAL MILESTONES 

7.1. Generic 

(D6) The Contractor shall develop the design of the equipment  integration and any Non Developmental Item (NDI) adaptation required to adapt the equipment to the particularities of this project. 

7.2. System Requirements Review (SRR) 

(D7) Within 4 weeks of Contract Award, the Contractor shall organize a SRR meeting to be attended by NSPA at his facility 

(R.D7.1) During  the  SRR  the  Contractor  and  NSPA  shall  conduct  a  joint  review  of  the requirements in this Statement of Work to ensure a mutual understanding. The Contractor shall  present  and  justify  in  detail  all  technical  and  programmatic  aspects  of  his  proposal, including:  

i. Requirements  functional  allocation  to  subsystems  (Modkit  functional  block diagram) 

ii. Implementation of System Interfaces 

iii. Initial assessment of reliability, testability and maintainability requirements 

iv. Verification strategy 

v. Assumed contributions/support from NSPA and Host Nation  

vi. Schedule details, including required downtime. 

(D8) Within 1 week of the completion of SRR the Contractor shall prepare and deliver the SRR meeting record, including any issues, agreed actions and closure plans and shall submit it for acceptance to NSPA. 

7.3. Critical Design Review (CDR) 

(D9) The Contractor shall organize a CDR meeting to be attended by NSPA at his facility. 

(R.D9.1) The  Contractor  shall  obtain  from  NSPA  the  authorization  to  call  the  CDR meeting, which shall be in principle granted.  

Since the starting point of the design will be based in an existing and tested solution, NSPA doesn’t require the execution of a Preliminary Design Review. 

(R.D9.2) At CDR, the initial Product Baseline (PBL) shall be established and the Contractor shall  provide  evidence  that  the  stable  design  meets  the  requirements  in  this  SoW.  In particular, the Contractor shall: 

a. Provide the final identification list of legacy HW and SW to be removed. 

b. Provide evidence that the design meets the requirements in Section 6, to include: 

Page 35: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.30 

 

• detailed review of the initial HW and SW PBL to meet the requirements in 

Section 6, including a HW Configuration Tree (D32)   

• fully  developed  RM&T  prediction.  The  Contractor  is  not  bound  to  use  any particular  methodology  for  RM&T  modelling,  but  NSPA  may  require  a justification of the methodology used, which must have a sound engineering approach. 

• detailed  assessment  on  obsolescence  mitigation  and  supportability improvement achieved by the new design; 

• assessment  of  the  impact  of  the  new  design  on  system  basic  power requirement. 

c. Review the RSPL. 

d. Provide an initial Special Tools and Test Equipment (STTE) list (if applicable). 

e. Brief  on  production  planning  and  risks  related  to  production  of  the  prototype  or production units. 

f. Present the Baseline Assessment (BA) procedures for NSPA acceptance (see D16); 

g. Present  the  final  Verification  and  Acceptance  Test  Plan,  including  a  Verification Requirements Traceability Matrix for NSPA acceptance (see Section 8.1). 

h. Present relevant elements of logistics support related with the requirements of this contract. 

i. Provide a full analysis of required documentation changes (see D27).  

j. Review the status of technical risks. 

k. Review the Master Schedule. 

(D10) The  Contractor  shall  submit  the  information  package  for  review  at  CDR  at  least  4 weeks ahead of the meeting. 

(D11) Within 1 week of the completion of CDR the Contractor shall prepare and deliver the CDR meeting record, including any issues, agreed actions and closure plans and shall submit it for acceptance to NSPA. 

7.4. Production and Factory Acceptance Test (FAT) 

(D12) Following CDR, the Contractor shall complete the physical production of all the new equipment and software required for the modification as per the design approved at CDR.  

(R.D12.1) The Contractor shall be responsible for the procurement of all material required for production of the Modkits. 

(R.D12.2) The equipment shall comprise one Modkit for the Remote Radar Head site and two Modkits for the CRC sites 

(D13) Upon completion of the production, the Contractor shall perform FAT on every Mod kit  and  within  2  weeks  of  the  completion  of  FAT  shall  submit  to  NSPA  the  respective Certificate  of  Completion  and  Factory  Acceptance  Test  Report.  Within  ten  (10)  calendar days,  NSPA will  review  the  Certificate  and  the  Report  and  provide  any  comments.  In  the absence of comments in this period, the Certificate of Completion and the Test Report will be deemed accepted. 

Page 36: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.31 

 

(R.D13.1) The Contractor  shall  provide NSPA with 30 days notice of  the exact  scheduled FAT  date  and NSPA  shall  have  the  option  to  nominate  staff  to witness  the  tests.  If  NSPA decides  not  to  provide  a  witness,  the  FAT  shall  be  conducted  by  the  Contractor  as scheduled, and the Contractor’s Quality Assurance organization will observe the testing on behalf of Customer. 

(R.D13.2)  The FAT Report shall contain the following information: 

P/N and S/N of the kits tested; 

P/N of the sub‐assemblies tested; 

List of performed system sub‐tests; 

Recorded test  results with a note “Passed” or “Failed”  IAW the V&A‐T Plan, where applicable; 

Recommended course(s) of action with respect to each of the failed sub‐tests; 

Overall  Pass/Fail  conclusion.  A  conclusion  of  “Pass”  shall  entail  the  Contractor’s assessment that the design is mature for implementation in operational systems; 

Any  other,  as  appropriate  (data  recording  and  analysis  files,  printouts,  pictures, records).  

7.5. Delivery, Installation, Integration and Site Acceptance Testing (SAT) 

(D14) Upon  completion  of  FAT,  the  Contractor  shall  pack  and  deliver  under  his responsibility;  install  and  integrate  the developed HW and  SW  (Modkits)  in  the  radar  site and 2 CRCs (see Table 1) in accordance with the Master Schedule (see (D2)).  

(D15) The Contractor  shall  also be  responsible  for  the  shipment  to  the  sites of  the  INCO spares  (see  9.4.1),  tools  and  test  equipment  property  of  the  Contractor  required  for  the installation, integration and testing. 

(D16) Before the removal of the currently installed equipment and installation of the Mod kit on each site,  the Contractor, the NSPA representative and a representative of the Host Nation shall  jointly perform a Baseline Assessment (BA) to evaluate the status of the radar system. The Contractor  shall  reflect  the  result of  this  evaluation  in  a Baseline Assessment Report, which shall be signed by the three parties. 

(R.D16.1) The  purpose  of  this  BA  is  to  assess  and  document  the  radar  operational  and technical  performance  status  by  using  the  available  on‐line  and  off‐line  tests  and performance checks. The Contractor may also use their own test sets and special tools and test equipment.  

(R.D16.2) The BA tests to be performed shall be described in the V&A‐T Plan.  

(R.D16.3) The Baseline Assessment Report  shall  detail  the  system status and all  relevant system  faults  or  conditions  prior  to  the  implementation  of  the  modification.  For  each condition,  this  report  shall  also  state  the assessment and way  ahead agreed by  the  three parties; for example:  

An assessment that the condition may affect or be affected by the  implementation of the modification or the subsequent test activities, and corrective action must be taken prior to the implementation; 

Page 37: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.32 

 

The acknowledgement that the condition will persist after the implementation of the modification, but it is unrelated to the requirements of the new equipment and the system operation and testing can be conducted in the presence of this condition; 

Any other agreement reached with respect to each condition. 

(R.D16.4) This  Baseline  Assessment  shall  be  repeated,  after  the  completion  of  the modification  activities  as  part  of  the  SAT,  to  verify  that  no  technical  or  operational degradation has been introduced.  

(D17) Prior to each Mod kit installation the Contractor shall, in case the space is needed for the Mod kits, remove all hardware and software being replaced or no longer needed. 

NSPA and the Host Nation shall be responsible for the storage and disposal of the removed equipment, no longer required. 

(D18) Upon removal of the equipment being replaced or no longer needed, the Contractor shall proceed with the installation and integration activities.  

The  Host  Nation  shall  make  the  MARTELLO  S723  Radar  System  available  for  use  by  the Contractor in accordance with the Master Schedule (see (D2)). 

(D19) deleted 

(R.D19.1) The Contractor shall be responsible for the Modkit installation and all checkout activities,  including  the  verification  activities  in  accordance with  the  requirements  of  this SoW.  

(D20) The Contractor shall be responsible to bring the modified radar performance up to the MARTELLO S723 Specification (see Annex 0), except where limited by the performance recorded during the BA.  

(D21) Upon completion of each  installation and  integration,  the Contractor  shall  conduct SAT in accordance with the V&A‐T Plan and in the presence of NSPA and Host Nation staff, who will follow the progress of the SAT activities.  

(D22)  Within  1  week  of  completion  of  the  SAT,  the  Contractor  shall  provide  a  SAT  test report  and  Certificate  of  Completion  in  Contractor’s  format.  The  mutually  agreed  SAT Report will be signed by NSPA, Host Nation and Contractor representatives. The SAT Report will  be  the main  element  providing  evidence  for  Provisional  Site  Acceptance  (see  Section 8.2.2). 

(R.D22.1) The SAT Report shall contain the following information:  

P/N and S/N of the items tested (at LRU level) 

List of performed system sub‐tests; 

Recorded test results with a note “Passed” or “Failed” IAW the V&A‐T Plan; 

Recommended course(s) of action with respect to each of the failed sub‐tests; 

Overall Pass/Fail conclusion; 

Any  other,  as  appropriate  (data  recording  and  analysis  files,  printouts,  pictures, records). 

Page 38: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.33 

 

(R.D22.2) In case of test failure or other  issues related to the test results, NSPA will have fifteen (15) calendar days to provide comments. In the absence of comments in this period, the Certificate of Completion and the Test Report will be deemed accepted.  

(R.D22.3) In  case  of  test  failure  or  NSPA  raised  issues  with  respect  to  test  results,  the Contractor and NSPA will agree on appropriate corrective/recovery actions. The Contractor shall  be  responsible  to put  in place all  the actions agreed  (including  the Modkit  retrofit  if necessary)  to be compliant with the required performance at no additional cost  for NSPA. After  implementation of the corrective actions agreed and repetition of the corresponding tests, the Contractor shall submit a new SAT Report to NSPA.  

7.6. Reliability Test (RT) 

(D23) Upon  confirmation  of  successful  SAT,  the  Contractor  and NSPA  shall  agree  on  the exact date of commencement of the Reliability Test (RT) periods.  

(R.D23.1) The observation period and failure tolerances shall be such that the probability of  acceptance  in  case  of  the  system  not meeting  the  reliability  requirements  is  less  than 20%. 

(R.D23.2) The  duration  of  the  RT  for  the  radar  site  shall  be  such  that  reliability  testing finishes simultaneously in all 3 sites.  

(R.D23.3) During  the  RT  period,  NSPA  shall  report  to  the  Contractor  all  relevant  events regarding the Reliability Test in accordance with the V&A‐T Plan. The Contractor shall either acknowledge  that  the  event  is  to  be  considered  as  a  failure  to  be  counted  in  the  RT,  or provide rationale for rejecting the event as related to the RT. 

(R.D23.4) In  the  event  of  failure  of  the  Reliability  Test,  and  after  implementation  of  the corrective actions, a new monitoring period will be observed.    

(D24) Within 2 weeks of the completion of the Reliability Test period, the Contractor shall submit  to  NSPA  the  Reliability  Test  Report  including  an  analysis  comparing  the  results achieved with the requirements specified in Section 6. 

8. VERIFICATION AND ACCEPTANCE 

(D25) The Contractor shall conduct a verification program reflected in the V&A‐T Plan (see also Section 8.1) with the ultimate objective to demonstrate to the satisfaction of NSPA that all  requirements  in  this SoW have been met, as well  as  intermediate objectives  to ensure that the different stages of technical maturity of the developed HW and SW are achieved.  

(D26) The  Contractor  shall  grant  NSPA  representatives  unrestricted  access  to  all  testing activities in the V&A‐T Plan and to the resulting data collected. 

8.1. Verification and Acceptance Test (V&A‐T) Plan 

(D27) Not later than 8 weeks prior to the commencement of the first Factory Acceptance Test the Contractor shall deliver the final Verification and Acceptance Test (V&A‐T) Plan to NSPA for approval. Within 2 weeks of reception of the V&A‐T Plan, NSPA shall approve the Plan  or  provide  motivated  requirements  for  change  or  clarification.  The  Contractor  shall 

Page 39: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.34 

 

either (a) accept and  implement NSPA change requirements or (b) propose an alternative. The V&A‐T will have as ultimate objective to demonstrate that the technical requirements in Section 6 have been achieved. 

NSPA  will  reject  proposals  for  the  V&A‐T  Plan  that  do  not  appropriately  address  the verification of all requirements in this SoW. 

(R.D27.1) The Contractor shall propose a V&A‐T Plan which comprises as a minimum the following major formal verification activities: 

a. Factory Acceptance Test  (FAT) This test shall have the objective to ensure that the developed/purchased HW and SW will respond as expected when integrated into the radar system and thus the design  is mature  for  implementation  in the field.  It shall be conducted by the Contractor at his facility on all prototype HW and SW (normally using a  radar emulator). Prototype HW and SW having successfully passed FAT will become 1st production units. The Contractor may propose FAT  in several phases to deal with independent and integrated testing of different modification kits, but there shall be at least one FAT phase testing the complete solution. 

b. Site  Acceptance  Test  (SAT):  Shall  be  conducted  by  the  Contractor  on  operational systems  following  all  installations  to  demonstrate  that  the  full  scope  of  Technical Requirements  stated  in  Section  6  have  been met,  including  all  radar  performance characteristics. 

For the 2nd CRC SAT the Contractor shall develop a verification program sub‐set, not including  the  TR  associated  with  the  SW  design,  unless  additional  changes  were applied after the first production units SAT. 

The  Contractor  shall  conduct  SAT  in  the  presence  of  NSPA  and  Host  Nation  (HN) representatives, who will countersign the SAT Test Reports. 

c. Reliability Test (RT): Shall be conducted following successful SAT at each site under 

the  conditions  in  the  agreed  V&A‐T  Plan.  The  RT  shall  have  the  objective  to 

demonstrate that the system is reliable and stable.  

d. Validation  and Verification  of  Documentation: Shall  be  conducted by NSPA on  all 

documentation provided as part of  the contract  (see section 9.1). The planning  for 

validation of documentation may include partial documentation deliveries. 

(R.D27.2) The Contractor shall propose for the verification of each of the requirements in this SoW the most efficient method (analysis,  test, demonstration or  inspection) providing adequate confidence. 

(R.D27.3) The  V&A‐T  Plan  shall  include  a  Verification  Requirements  Traceability  Matrix, depicting  for  each  requirement  the  formal  verification  stage(s)  in which  it will  be  verified and the verification methodology (analysis, inspection, demonstration or test) 

(R.D27.4) The V&A‐T Plan shall include for all testing and verification activities at least the following: 

List of proposed sub‐tests and requirements verified; 

Detailed description of the test procedures for each sub‐test; 

Page 40: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.35 

 

Test  equipment  or  any  requirement  for  NSPA  or  Host  Nation  furnished  property, information, or manpower support; 

Pass/fail criteria and tolerances, where applicable; 

Reference documents and standards.   

(R.D27.5) The Contractor shall propose for the verification of each of the requirements in this SoW the most efficient method (analysis,  test, demonstration or  inspection) providing adequate confidence. 

(R.D27.6) The Contractor shall ensure that verification approach and procedures consider any  site  specific  factor  that  may  affect  implementation  and  compliance  of  the  solution developed under this contract.  

8.2. Acceptance Milestones 

There shall be three major acceptance milestones: (1) Factory Acceptance of the Integrated Prototype  Solution,  (2)  Provisional  Site Acceptance  (PSA)  for  Radar  and CRC  sites,  and  (3) Final Acceptance. 

8.2.1. Factory Acceptance of the Integrated Prototype Solution (FAT) 

Acceptance  of  the  Integrated  Prototype  Solution  is  the  act  whereby  NSPA  formally 

acknowledges that the integrated solution as design and built is mature for implementation 

in the field. 

This  milestone  will  be  achieved  upon  successful  completion  of  FAT  for  the  complete 

integrated  solution.  Subsequently,  NSPA  will  issue  a  notification  to  the  Contractor 

containing confirmation of Acceptance of the Integrated Prototype Solution. 

8.2.2. Provisional Site Acceptance (PSA) 

PSA  is  the  act  whereby  NSPA  will  formally  acknowledge  for  each  installation  that  the 

technical requirements for the system and requirements for the logistics deliverables have 

been  achieved,  though  there  may  be  minor  discrepancies,  which  the  Contractor  shall 

commit to resolve to achieve FA. 

PSA will be achieved for each installation upon successful completion of the SAT, a minimum 

of 3 months of successful RT and acceptance of logistics deliverables.  

PSA  for each  site may be achieved with minor discrepancies,  after  approval by NSPA of  a 

Discrepancies Clearance Plan (DCP), which implementation schedule shall be incorporated in 

the Master Schedule. 

Once  all  conditions  for  PSA  have  been  achieved,  NSPA  will  issue  a  PSA  Protocol,  to  be 

countersigned by the Contractor, containing confirmation of PSA for the specific site. NSPA 

may require to convene a meeting with the Contractor to complete each PSA Protocol.  

Page 41: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.36 

 

After PSA, the Contractor shall keep NSPA informed of the progress on the implementation 

of the DCP. 

8.2.3. Final Acceptance: (FA) 

FA is the act whereby NSPA will definitively accept all delivered products and services in this 

SoW, for all sites, as complying with the contractual requirements, determining the start of 

the warranty period for all sites and INCO Spares. 

FA  will  be  achieved  for  the  complete  scope  of  this  contract  once  PSA  of  the  last  site  is 

achieved,  the observations/discrepanies  from PSA for all sites are cleared, Reliability Tests 

are successful for all sites and INCO spares and all logistics products are delivered. 

Once  all  conditions  for  FA  have  been  achieved,  NSPA  will  issue  a  Final  Acceptance 

Certificate. 

9. LOGISTIC SUPPORT DELIVERABLES 

9.1. Documentation 

(D28) The contractor shall analyze the TMEs included in Annex 3 that are affected by this upgrade.  

(D29) Technical Manual Updates (in preliminary version) shall be made available  in paper copies by the Contractor to support the Operation and Maintenance (O&M) training courses (1 per each student) 4 weeks prior to training starting date. 

(D30) Final  Technical  Manual  Updates  that  incorporate  the  MARTELLO  S723  Shelter Restoration Mod  kits  into  the  standard MARTELLO  S723  Radar  baseline manuals  shall  be supplied by the Contractor 4 weeks after the completion of the training program. 

(R.D30.1) NSPA  will  conduct  documentation  validation  activities  concurrently  with  the installation  periods  or  upon  receipt  of  documentation  deliverables,  and  will  notify  the Contractor  of  any  discrepancies  identified.  The  Contractor  shall  rectify  all  recognized documentation discrepancies in order to achieve Final Acceptance (See Section 8). 

(R.D30.2) Documentation  updates  shall  be  provided  only  for  the  pages  that  have  been changed  (Change  Pages)  from  the  original  versions  and  shall  provide organizational/intermediate operations and maintenance instructions for the Radar System after  incorporation of  the MARTELLO  S723  Shelter  Restoration Modkit. Where  applicable, new manuals shall be provided. 

(R.D30.3) The  updates  shall  be  provided  in  a  non‐proprietary2 editable  electronic  format (i.e. editable pdf for text/tables and SVG for schematics or drawings). 

                                                            2 For the purpose of this requirement, MS Word is accepted as a non‐proprietary format.  

Page 42: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.37 

 

(R.D30.4) For COTS equipment, existing operation and maintenance manuals presented in the manufacturer's format shall be supplied. Appropriate references to these OEM manuals will be made, as required, in the applicable system Technical Manuals. 

(R.D30.5) All manuals shall be written in English language. 

(D31) Within  4 weeks  from  the  First  Kit  Installation  date,  the  Contractor  shall  deliver  to NSPA the update to the System Specification and System Interface Control Documentation (ICD) under the new configuration.  

(R.D31.1) The ICD shall include all interfaces of the “Radar Head Solution”, both to the rest of the radar system and the ROC. 

(D32) After  SAT  for  each  installation,  the  Contractor  shall  deliver  all  Software  installed during  the  implementation  of  the  upgrade  (including  COTS  Software)  on  CD/DVD‐ROM support:  1  copy  for  NSPA,  1  copy  for  the  Danish  Air  Force,  1  copy  per  site  where  the software is installed. 

9.2. Configuration 

(D33) As part of CDR, the Contractor shall provide the configuration  identification data in the form of a hierarchical tree representation of the ModKits up to component level listing: 

ModKits’ P/N; 

ModKits’ main subassembly P/N; 

ModKits’ LRU P/N. 

9.3. Training 

(D34) The Contractor shall prepare a Training Plan and shall submit it to NSPA (Contractor Format) at  least three (3) months before the scheduled training start date. Within four (4) weeks of reception NSPA shall provide any written feedback. 

(R.D34.1) The  Training  Plan  shall  provide  the  definition  of  all  specific  training implementation elements to meet the training requirements below (R.D34.x). In particular, the Training Plan shall contain at least the following: 

Duration proposed for the operators and maintainers course, such that the training objectives are met; 

Outline of the operators and maintainers course (training syllabus) and class plan; 

Description and methodology of planned induced failures; 

Recommended class schedule and starting date; 

RADAR downtime schedule; 

Location of training (for operators course);  

List of training devices/aids/equipment required to support each course (if any); 

List of test equipment and tools required (if any); 

List  of  documentation  required  for  the  course  (i.e.  Technical  manuals  and  other related  technical  data,  specific  training  documentation  to  be  provided  by  the contractor); 

Page 43: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.38 

 

(D35) Upon  completion  of  the  SAT  activities  on  the  site(s),  the  Contractor  shall  deliver training to designated personnel according to the Training Plan. 

(R.D35.1) Two types of training courses shall be provided: 

Site  Maintenance  Training  course  –  to  site  radar  technicians  and  maintenance personnel; 

Operators’ Training course – to operators from the Radar and CRC sites. 

(R.D35.2) The  Site Maintenance  Training  course  shall  be  performed  at  the  radar  site.  It shall  provide  an  overview  of  the  new  hardware/software  configuration  of  the  upgraded radar system and the necessary knowledge for the operation and maintenance at site level (HL1  and  HL2).  This  training  will  provide  classroom  and  hands‐on  equipment  training  of operation, maintenance procedures, fault isolation and repairs to the upgraded equipment (through induced faults). The duration of the course shall be a maximum of 10 working days. 

(R.D35.3) The  training  course  documentation  will  be  provided  in  accordance  with  the requirements listed at Paragraph 9.1 

(R.D35.4) The Operator’s Training course shall be performed at one of the CRC sites, to be defined  in  accordance with  the  installation  sequence.  It  shall  provide  an  overview  of  the new  hardware/software  configuration  of  the  upgraded  radar  system  and  the  RCDSS.  This training  will  provide  classroom  and  hands‐on  equipment  training  on  the  RCDSS.  The duration of the course shall be a maximum of 5 working days.  

(R.D35.5) The maximum number of students to be trained in each course is six (6).  

(R.D35.6) Training  shall  be  conducted  based  on  a  5‐day week  and  8‐hour  day,  including periodic breaks and lunch breaks. 

(R.D35.7) In  the  event  that  the  Upgraded  portion  of  the  Radar  System  fails  during  the training period, the course(s) shall be continued at such time as the repair or replacement is completed and at such time the course(s) shall be resumed for the period of time that was remaining in the course at the time of failure. 

(R.D35.8) All Host Nation and Contractor holidays will be considered in the determination of the training schedule. 

(R.D35.9) The  Upgrade  Training  shall  be  designed  for  students  who  have  a  basic understanding and familiarity with the current MARTELLO S723 Radar System. 

(R.D35.10) All  courses  shall  be  taught  in  English  language.  Students  will  be  assumed  to possess sufficient English language skills. 

(R.D35.11) At  the  completion  of  each  Training  Course  the  Contractor  and  the  Training Senior Attendee shall sign a “Training Completion Certificate” certifying the training course completion  in  accordance  with  the  requirements  of  this  SoW.  The  Contractor  shall  also provide each trainee with a Certificate of Training Completion. 

NSPA and the Host Nation shall be responsible for the provision of the following in‐country: 

A classroom facility on site to enable the proper  instruction;  the Training Plan shall provide details of those facilities and equipment necessary for training; 

Office space for the Contractor’s Instructors, including a desk and phone; 

Page 44: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.39 

 

An operational Radar System for the duration of the training period. 

The Host Nation shall provide the appropriate radar downtime for the Upgraded System in order to support the training activities, in accordance with the Master Schedule (see (D2)). 

9.4. Spare Parts  

9.4.1. Installation & Check Out (INCO) Spares 

(D36) The Martello Electronic Shelter Restoration specified in this SoW shall be considered as  spares  inclusive  service.  The  contractor  shall  therefore  be  responsible  for  defining  and then providing a set of spares  to be used during all phases of production,  installation and testing  to  ensure  immediate  replacement  of  failed  parts.  These  spares  shall  be  known  as Installation & Check Out (INCO) Spares.  

(R.D36.1) The INCO spares will be procured by NSPA under this SoW and retained by the contractor during the execution of the contract.  

(R.D36.2) The  shipment  of  the  INCO  spares  to  the  customer  sites  to  be  used  during installation  and  testing  activities  shall  be  performed  by  the  contractor  together  with  the modification kits. 

(R.D36.3) The contractor shall  return the full set of  INCO spares to NSPA in a serviceable condition before the Final Acceptance3.  

(R.D36.4) The contractor shall provide a list of INCO spares to NSPA. 

9.4.2. Reliability and Provisioning Data 

(D37) As  part  of  CDR  (see  D9)  the  Contractor  shall  deliver  a  Recommended  Spare  Parts Lists (RSPL). 

(R.D37.1) The  RSPL  will  contain  the  proposed  spares  required  to  support  the  upgraded system  for  a  period  of  2  years with  90%  confidence.  Those  items  to  be  part  of  the  INCO Spares as defined in 9.4.1 will be identified as such within the RSPL. 

(R.D37.2) The  RSPL  shall  identify  critical  LRUs  (i.e.  equipment  at  the  LRU  level,  which failure renders the system non‐operational). 

(R.D37.3) Part in the RSPL shall be identified by manufacturer part number and cage code. If existing, alternative part numbers, alternative cage codes and NATO Stock Numbers shall also be included. 

(D38) As  part  of  CDR  (see  D9)  the  Contractor  shall  deliver  a  Reliability  Data  List  (RDL) containing  MTBCF  data  for  all  hardware  LRUs  in  the  new  system  configuration  and  the associated equipment susceptible of being replaced at organizational level. 

                                                            3 Items to be returned to NSPA as part of the INCO Spares Set, which are being repaired under warranty will be returned  upon  completion  of  repair  and  will  not  be  a  reason  for  NSPA  to  not  issue  a  notification  to  the Contractor with the confirmation of Final Acceptance. 

Page 45: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.40 

 

(R.D38.1) Part in the RDL shall be identified by manufacturer part number and cage code. If existing, alternative part numbers, alternative cage codes and NATO Stock Numbers shall also be included. 

(R.D38.2) Both RDL and RSPL shall be delivered  in an editable electronic  format  (e.g. MS Excel).  

10. QUALITY ASSURANCE 

(R.Q1) The  Contractor  shall  conduct  quality  management  activities  in  this  project  in accordance  with  an  internationally  recognized  standard  for  quality management  systems (e.g. AQAP 2110, ISO 9001, AS9100).  

11. OPTIONS (EVALUATED) 

The  following  requirements  reflect  optional  technical  scope.  If  the  options  are  exercised, they  shall  be  considered  as  technical  requirements  under  Section  6  of  the  SoW  and  all service  and  data  deliverables  defined  in  Sections  5,  7,  8,  9  and  10  shall  be  applicable  to these requirement. 

(O.T1) For integration into the ACCS Network (see 6.3.4), the radar system shall support the 

following  AWCIES  (ACCS‐Wide  Communication  Information  Exchange  Standard)/Mil‐

ASTERIX message categories compliant with ADatP‐35 Ed. 2 (NATO STANAG 5535 Ed. 2). 

‐ 155 – Sensor Monitoring; 

‐ 156 – Radar Control; 

‐ 157 – Service Data; 

‐ 158 – Strobe Report;  

‐ 159 – Target Report; 

‐ 180 – Sensor Track. 

(R.OT1.1) The contractor shall  implement  in  the ACCS  interface  (6.3.3) all RDS control and 

monitoring functions admissible by the Mil‐ASTERIX Data Item Catalogue.   

(O.T2) The  contractor  shall  integrate  an  IFF  Interrogator  compliant  with  NATO  STANAG 

4193 Ed. 3 with the aim of extending the system capability to IFF Mode 5, Level 1 and Level 

2. 

(R.OT2.1) The RCDSS and RDS shall include the necessary functionality to perform all control 

and monitoring messages enabling Mode 5 Level 1 and Level 2 operations.   

(R.OT2.2) The  ACCS  Network  Interface  shall  include  all  Mode  5  control  and  monitoring 

messages defined in ADatP‐35 Ed 2.  

 

 

Page 46: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.41 

 

APPENDIX 1: SUMMARY OF DELIVERABLE DATA, PRODUCTS AND SERVICES 

The Table below lists the deliverable products and services under this contract. It is provided as a quick reference for convenience.  

In case of any inconsistency between this table and the Text in the SoW document body, the text in the document body shall prevail. 

Serial  Deliverable  Type  When 

D1 Nominate a Project Manager (PM) 

Service  Contract Award 

D2  Master Schedule  Data  First Delivery with Proposal 

4 weeks after Contract Award 

D3 Contractor Staff Personal Data + Sec Clearance 

Data  90 days before site installations 

D4  Risk Updates  Data  When required 

D5  Attend Ad‐Hoc PMR/TIM  Service When required 

D6  SP/Exc Design  Service Per Contractor Schedule (Complete by CDR) 

D7  SRR  Service  4 weeks after CA 

D8  SRR Meeting Record  Data  1 week after SRR 

D9  CDR  Service Per Master Schedule 

D10  CDR Information Package  Data  4 Weeks ahead of CDR 

D11  CDR meeting record  Data  1 week after CDR 

D12  Production  Service  Per Contractor Schedule 

D13  FAT & FAT Report & FAT CoC Service /

 Data 

Per Master Schedule (upon completion of production for each kit) 

‐ Notify 30 days ahead ‐ FAT Report & CoC within 2 weeks of FAT 

D14 

D15 Packaging, Delivery and Installation (Modkits, T&TE) 

Service/

Material After completion of FAT 

D16  Baseline Assessment Service / 

Data Per Master Schedule (With legacy configuration) 

D17 Remove and/or disconnect legay HW&SW 

Service  Per Master Schedule (Before installation) 

D18  Installation of Mod kits   Service  Per Master Schedule 

D19 Ensure Pre‐BA Radar Performance 

Service  Per Master Schedule 

D20  SAT  Service  Per Master Schedule 

D21  SAT Test Report  Data 1 week after completion of SAT 

D22  Reliability Test (RT)  Service  Per Master Schedule 

D23  Reliability Test Report  Data  2 Weeks after completed RT 

D24, D25 

Conduct of V&AT Programme  Service  V&AT activities as per master schedule 

D26  V&A‐T Plan  Data SRR (v1), CDR (v2) 

Page 47: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.42 

 

8 weeks before 1st FAT (Final) 

D27 Analysis of documentation changes 

Data 4 weeks ahead of CDR (Part of CDR Information Package) 

D28, 

D29 Technical Manual Updates  Data 

‐ 4 weeks ahead of Training start (prelim) ‐ 4 weeks after Training completion (final) 

D30  System Spec and ICD  Data  4 weeks after first site installation 

D31  SW delivery  Data  After SAT 

D32  Configuration Tree  Data 4 weeks ahead of CDR (Part of CDR Information Package) 

D33  Training Plan  Data 3 months before Training start 

D34  Training  Services Start following SAT and as per Master Schedule 

D35  INCO Spares  Material At the start of first installation 

D36  RSPL  Data 4 weeks ahead of CDR (Part of CDR Information Package) 

D37  RDL  Data 4 weeks ahead of CDR (Part of CDR Information Package) 

 

Note A1:  All  the  deliverables  that  require  delivery  of  certain  documents  are  noted  in  the column “Type” with mentioning “Data”. 

Note A2: Whilst timing for some of the intermediate milestones is not specified in this SoW, the  Master  Schedule  shall  be  such  that  FA  is  achieved  not  later  than  18  months  after Contract Award.  

 

 

   

Page 48: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.43 

 

APPENDIX 2: ENVIRONMENTAL REQUIREMENTS WITHIN THE DISPLAY SHELTER 

These specifications are based on standards and Allied Environmental Conditions and Test 

Publication (AECTP), which are accepted and approved by NATO. If there are contradictions 

in terms of the requirements listed below and requirements stated in STANAG 4370, the 

specification below supersedes. 

They are applicable for the equipment installed WITHIN the Display Shelter. 

Temperature and Humidity 

Requirement

MinInside/Outside

Typ.

Max

Unit

Notes

TemperatureOperatingWITHINtheDisplayShelter

0° +20° +40° Celsius

TemperatureNon‐OperatingWITHINtheDisplayShelter

10° N/A 65°

HumidityOperating 40% 55% 80% Condensationmust

notbeallowedtodHumidityOperating

forGPSSystemClockAntennasystem

5% 55% 90% Withpossiblecondensation

AirSaltContent 0.75 (1)* Micro‐grams/m3

*forGPSSystemClockAntennasystem(gram/m3)

AirOzonContent 220 (1)* Micro‐grams/m3

*forGPSSystemClockAntennasystem(gram/m3)

HumidityNon‐Operating 95% Noncondensingwhenpacked

AtmosphericPressure 500 1050 mb

AltitudeOperating

10,000 Feet

AltitudeNon‐Operating

40,000 FeetDuringairbornetransport

Table 4 ‐ Standards Environmental Conditions ‐ Temperature and Humidity 

Shock and Vibration (Operating) 

The assembly shall be designed to withstand: 

Shock: Half sine shock pulse 6 G peak (±1 G) for 10 ms (±3 ms), applied once in all three axis. 

Page 49: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.44 

 

Vibration test as indicated here below: 

1.5 G (± 6 mm max displacement) 

5 to 22 Hz, 0.010 in Double Amplitude 

22 ‐ 500 Hz, 0.025 peak 

500 ‐ 22 Hz, 0.025 peak 

22 to 5 Hz, 0.010 in Double Amplitude 

Shock and Vibration (Not Operating) 

The assembly shall be designed to withstand 

Shock: MIL‐STD‐810C1, Method 516.2, Procedure 1, Figure 516.2‐2. 

Half sine shock 

Pulse for ground equipment, 30 g peak, 11 ms duration. 

Vibration test as below indicated: 

MIL‐STD‐810C, Method 514.2, Category G (equipment transported as cargo), Procedure X, 

table 514.2‐VII (rail, air, semi‐trailer), Figure 514.2‐7, Curve AA is to be used for vibration 

isolated items 

These requirements will be demonstrated by analysis of operating characteristics of the 

used equipment during the FAT. 

EMI Radiation Emitted 

There are no EMI related specific requirements, which have to be applied in new equipment 

of the MARTELLO S723 radar, but the EMI/RFI emanating from the new equipment shall not 

cause any trouble to the other electronic circuits of the radar systems. 

However a Lightning protection system is required, for which the STANAG 4236 and STANAG 

4327 shall be applied.   

Page 50: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.45 

 

APPENDIX 3: ABBREVIATIONS AND ACRONYMS 

 

ADatP  Allied Data Publication 

ADS‐B  Automatic Dependent Surveillance – Broadcast 

AQAP  Allied Quality Assurance Publication 

ASTERIX  All‐purpose Structured EUROCONTROL Radar Information Exchange 

AWCIES  ACCS‐Wide Communication Information Exchange Standard 

BA  Baseline Assessment 

CFP  Customer Furnished Property 

CNIF  Clutter to Noise Improvement Factor 

COTS  commercial off‐the‐shelf 

CRC  Control and Reporting Centre 

DP  Data Processor 

EC  Exercise Controller 

EUROCONTROL  European Organization for the Safety of Air Navigation 

FA  Final Acceptance 

FAT  Factory Acceptance Test 

FT  Factory Test 

HL  Hardware Level (maintenance) 

HMI  Human Machine Interface 

HW  Hardware 

I&CO (or INCO)  Installation and Check‐Out 

IAW  In Accordance With 

ICD  Interface Control Document 

IF  Improvement Factor or Intermediate frequency (clear through context) 

IFF  Identification Friend or Foe 

ITU  International Telecommunications Union 

LRU  Line Replaceable Unit 

MFI  Monitoring and Fault Isolation 

Modkit  Modification kit 

MSSR  Mono pulse Secondary Surveillance Radar 

MTBCF  Mean Time between Critical Failures 

MTBF  Mean Time between Failures 

NATO  North Atlantic Treaty Organization 

NDI  Non Developmental Item 

NLT  Not Later Than 

NRP  North Reference Pulse 

NSPA  NATO Support and Procurement Agency 

O&M  Operation and Maintenance 

ODAS  Offline Detection Analysis Software 

OEM  Original Equipment Manufacturer 

P/N  Part Number 

PDF  Portable Document Format  

PMFL  Performance Monitoring and Fault Isolation 

Page 51: STATEMENT OF WORK AND TECHNICAL ... - eportal.nspa.nato.int · The following is a non‐exhaustive list of documents which, in their most current version/revision, are relevant in

Statement of Work dated 1 March 2019 (Version 2) 

NATO UNCLASSIFIED MARTELLO S723 Electronic Shelter Restoration 

NATO UNCLASSIFIED p.46 

 

PMR/TIM  Program Management Review / Technical Interchange Meeting 

PRF  Pulse Repetition Frequency 

PSA  Provisional Site Acceptance 

PSR  Primary Surveillance Radar 

RADNET  Radar Network 

RCDSS   Radar Control and Display Sub‐System 

RDS  Remote Display System 

RES  Radar Environment Simulator 

RF  Radio Frequency 

RP  Remote Processor 

R‐SPC  Radar – System Performance Check 

RSPL  Recommended Spare Parts List 

S/N  Serial Number 

SAT  Site Acceptance Test 

SGS  Scenario Generator Software 

SLB  Sidelobe Lobe Blanking 

SoW  Statement of Work 

SPT&A  System Performance Test and Alignment 

SSR  Secondary Surveillance Radar 

STANAG  Standardization Agreement 

STC  Sensitivity Time Control 

SW  Software 

TIM  Technical Interchange Meeting 

TME  Technical Manual Equipment 

TMs  Technical Manuals 

UDP/IP  User Datagram Protocol/Internet Protocol 

UPS  Uninterruptible Power Supply 

V&A‐T  Verification and Acceptance Test (Plan)