Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
STATE OF INDIANA
INDIANA UTILITY REGULATORY COMMISSION
VERIFIED PETITION OF INDIANAPOLIS POWER & ) LIGHT COMPANY ("IPL"), AN INDIANA) CORPORATION, FOR (1) ISSUANCE OF A ) CERTIFICATE OF PUBLIC CONVENIENCE AND ) NECESSITY FOR THE CONSTRUCTION OF A ) COMBINED CYCLE GAS TURBINE GENERATION ) FACILITY ("CCGT"); (2) ISSUANCE OF A ) CERTIFICATE OF PUBLIC CONVENIENCE AND ) NECESSITY TO CONVERT COAL FIRED) GENERATING FACILITIES TO GAS; (3) APPROVAL ) OF THE CONSTRUCTION OF TRANSMISSION, ) PIPELINE AND OTHER FACILITIES; (4» APPROVAL OF ASSOCIATED RATE MAKING AND ) CAUSE NO. 44339 ACCOUNTING TREATMENT; (5) AUTHORITY TO ) TIMELY RECOVER 80% OF THE COSTS ) INCURRED DURING CONSTRUCTION AND) OPERATION OF THE GAS REFUELING PROJECT ) THROUGH IPL'S ENVIRONMENTAL ) COMPLIANCE COST RECOVERY ADJUSTMENT; ) (6) AUTHORITY TO CREATE REGULATORY ) ASSETS TO RECORD (A) 20% OF THE REVENUE ) REQUIREMENT FOR COSTS, INCLUDING,) CAPITAL, OPERATING, MAINTENANCE,) DEPRECIATION TAX AND FINANCING COSTS ON ) THE REFUELING PROJECT WITH CARRYING ) COSTS AND (B) POST-IN-SERVICE ALLOWANCE ) FOR FUNDS USED DURING CONSTRUCTION, ) BOTH DEBT AND EQUITY, AND DEFERRED ) DEPRECIATION ASSOCIATED WITH THE) PROJECTS UNTIL SUCH COSTS ARE REFLECTED ) IN RET AIL ELECTRIC RATES; AND (7) ISSUANCE ) OF A NECESSITY CERTIFICATE TO TRANSPORT ) NATURAL GAS IN INDIANA )
PETITIONER'S NOTICE OF SUBSTITUTION OF WITNESSES AND ' SUBMISSION OF REVISIONS TO DIRECT TESTIMONY
Petitioner Indianapolis Power & Light Company ("IPL"), by counsel, hereby gives notice
of witness substitution and revisions to IPL's prefiled case-in-chief.
-1-
1. Witness Substitution. IPL hereby submits the verified direct testimony of James
Sadtler and Craig Jackson and notifies the Commission and the parties that Ml'. Sadtler is being
substituted for and is adopting the testimony previously prefiled by IPL Witness Bentley and Mr.
Jackson is being substituted for and is adopting the testimony previously prefiled by IPL Witness
Huntington.
2. For the convenience of the Commission and the parties, redline versions of Mr.
Sadtler's and Mr. Jackson's testimonies are attached showing the changes from the previously
prefiled public version of the testimony they are replacing. In addition, clean copies of their
respective testimony are also attached. A clean version of the confidential testimony is being
filed under seal in accordance with Commission procedure. At the evidentiary hearing in this
Cause, clean versions of the direct testimony of Mr. Sadtler and Mr. Jackson will be offered into
evidence. For ease of reference, Petitioner's Exhibit BJB-2 (Confidential) will not be relabeled.
3. Related Changes to Prefiled Case-in-Chief. The following pages ofIPL's prefiled
direct testimony are also being corrected to reflect the witness substitutions. Clean copies of the
public revised pages are attached hereto and the confidential pages will be submitted under seal
pursuant to the Commission's May 28, 2013, Docket Entry. Clean copies of the revised pages
will be included in the court reporter copies offered into evidence at the hearing.
Petitioner's Exhibit KWC-l (Public):
• Table on Page 6 - replace "Barry 1. Bentley" with "James Sadtler"
• Table on Page 6 - replace "Kelly M. Huntington" with "Craig Jackson"
• Page 9, line 9 - replace "Bentley" with "Sadtler"
• Page 15, line 1 - replace "Bentley's" with "Sadtler's"
-2-
• Page 16, line 15 - replace "Bentley" with "Sadtler"
• Page 18, line 3 - replace "Bentley" with "Sadtler"
• Page 19, line 16 - replace "Bentley" with "Sadtler"
Petitioner's Exhibit KWC-l (Confidential):
• Page 18, line 3 - replace "Bentley" with "Sadtler"
• Page 19, line 16 - replace "Bentley" with "Sadtler"
Petitioner's Exhibit HNS-l :
• Page 13, line 14 - replace "Bentley" with "Sadtler"
• Page 13, line 17 - replace "Bentley's" with "Sadtler's"
Petitioner's Exhibit RLB-l (Public):
• Page 8, line 20 - replace "Bentley" with "Sadtler"
• Page 15, line 12 - replace "Huntington" with "Jackson"
Petitioner's Exhibit DCD-l (Public):
• Page 11, line 2 - replace "Huntington" with "Jackson"
Petitioner's Exhibit CFA-l:
• Page 8, lines 21 and 26 - replace "Bentley" with "Sadtler"
Petitioner's Exhibit JLC-l :
• Page 15, line 15 - replace "Huntington" with "Jackson"
4. Additional Revision to Exhibit. Petitioner also submits Petitioner's Exhibit LHA-
4 (Revised). The heading on the third column of this exhibit has been changed from "IURC
Gross EE Related Demand Savings" to "Net Incremental Annual Demand Reductions". A clean
copy of Exhibit LHA-4 (Revised) is attached hereto and will be offered into evidence at the
hearing in this Cause in lieu of the previously filed document.
-3-
Dated this 6th day of August, 2013.
Respectfully submitted,
Teresa Morton yliart o. 14044-49) P. Jason Stephenson (No. 21839-49) Jeffrey M. Peabody (No. 28000-53) BARNES & THORNBURG LLP
11 S. Meridian Street Indianapolis, Indiana 46204 Nyhart Phone: (317) 231-7716 Stephenson Phone: (317) 231-7749 Peabody Phone: (317) 231-6465 Fax: (317) 231-7433 Nyhart Email: [email protected] Stephenson Email: [email protected] Peabody Email: [email protected]
Attorneys for INDIANAPOLIS POWER & LIGHT COMPANY
-4-
CERTIFICATE OF SERVICE
The undersigned hereby certifies that a copy of the foregoing was served upon the
following via electronic mail this 6th day of August, 2013.
Lorraine Hitz-Bradley Randall C. Helmen OFFICE OF UTILITY CONSUMER COUNSELOR
115 W. Washington Street, Suite 1500 South Indianapolis, Indiana 46204 Phone: (317) 232-2494 Fax: (317) 232-5923 Email: [email protected]
Joshua A. Claybourn Robert E. Heidorn Vectren Corporation One Vectren Square 211 N.W. Riverside Drive Evansville, IN 47708 Email: [email protected]
Timothy L. Stewart Anne E. Becker Lewis & Kappes, P. C. One American Square, Suite 2500 Indianapolis, Indiana 46282 Email: [email protected]
INDSOI 1408087vI
-5-
Jennifer A. Washburn Citizens Action Coalition 603 East Washington Street, Suite 502 Indianapolis, Indiana 46204 Phone: (317) 735-7764 Fax: (317) 290-3700 Email: [email protected]
J. David Agnew Lorch N aville Ward, LLC 506 State Street P.O. Box 1343 New Albany, Indiana 47150-1343 Phone: (812) 949-1000 Fax: (812) 949-3773 Email: [email protected]
Iil1<71vlzwt Teresa Mo&n Nyhart
Petitioner's Exhibit BJRJAS-l(PUBLIC)
(PUBLIC)
VERIFIED DIRECT TESTIMONY
OF
BARRY J. BENTLEY
JAMES A. SADTLER
ON BEHALF OF
INDIANAPOLIS POWER & LIGHT COMPANY
CAUSE NO. 44339
SPONSORING PETITIONER'S EXHIBIT BJB-2 (CONFIDENTIAL)
Petitioner's Exhibit BJ-BJAS-l (PUBLIC)
VERIFIED DIRECT TESTIMONY OF BARRY J. BENTLEYJAMES A. SADTLER ON BEHALF OF
INDIANAPOLIS POWER & LIGHT COMPANY
Q1. Please state your name, employer and business address.
AI. My name is Barry J. BentleyJames A. Sadtler. I am employed by Indianapolis Power &
Light Company ("IPL" or "Company"), One Monument Circle, Indianapolis, Indiana
46204.
Q2. What is your position with IPL?
A2. I am Senior Vice President, Customercurrently the Director of Transmission Field
Operations.
Q3. Please describe your duties as Senior Vice President, Customer Director of
Transmission Field Operations.
A3. In this position, my principal responsibilities include transmission, distribution, customer
service, stffitegic cus-tBfRef-ac·eeuHts,afl:d.-s.upply chain.As Director of Transmission Field
Operations. I am responsible for the real time operations for the IPL transmission and
distribution systems. the operation and maintenance of all IPL substations and the
downtown electrical network. This includes the operation and maintenance of the
protective relaying schemes. and supervisol)' control and data acquisition systems. The
real time operation of the transmission system requires coordination with the
Midcontinent Independent System Operator. Inc. (MISO).
Q4. Please summarize your educational and professional qualifications.
A4. I heklreceived a Bachelor of Science tIegr-eeDegree in Electrical Engineering Technology
from Purdue University. I have attended several management courses from the
IPL Witness BentleySadtler- 1
Petitioner's Exhibit BJ-BJAS-l (PUBLIC)
University of MichigLm and the University of Virginia, Darden School of BusinesG. I am
a former member of the East Central l\rea Reliability Council ("BCAR") Operation and
Compli£mce PLmekam a Registered Professional Engineer in the State of Indiana.
Q5. Please summarize your prior work experience.
AS. Including my Cooperative Engineering assignmentG while attending Purdue University, I
have been employed at IPL for over )5 years. My experience includes positions of
increasing reGpom;ibility in the areaG of power generation, tranGmission and distribution,
customer service, supply chain, corporate venture capital, fuel supply, and energy
di~;patching and marketing. I began my career \vith IPL in 198(1 as a Cooperative
Engineering student while attending Purdue University. In 1988, I became a full time
employee, working an an engineer in Pmver Production. In 1990, I became Supervit;or,
Instrument Electrical at the H. T. Pritchard Generation Station. In 1992, I moved to
Supervisor, Maintemmce for all electrical and mechanical maintenance at the Pritchard
Plant. Bet\veen 1993 and 1998, I '.vas Supervisor and then Director, System Operation,
ret;pom;ible for the operation of the tram;mim;ion t;ystem Lmd dit;patching of generation
assets. In 1999, I became Manager, Bulk Power, ',:vhich included responsibility and
oven;ight of the planning, engineering, operations, and maintenance for all IPL
transmission and substation assets. In 2000, I '.vas promoted to Principal in IPL's
Corporate Venturing Group. In 2002, I '.vat; promoted to the Director, Demand
Coordination, responsible for strategic account management for IPL's top 300 retail
CUGtomers. In 2003, I tnmsitioned to the Director, Supply Coordination and later to the
Vice President, Fuel ffild Energy supply, responsible for energy dispatching, wholesale
sales, and fuel procurement for IPL's generation fleet. In 2008, I transitioned from the
IPL Witness BcntleySadtler- 2
Petitioner's Exhibit BJBJAS-l (PUBLIC)
generation Gide of the businestj to the Vice Pretlident, Power Delivery, in IPL'n electric
delivery organization. My responsibilities included the planning, construction, operation,
and maintenance of IPL'n tram;mission and dit;tribution tlystem. I atltlwl1ed my current
position of Senior Vice President, Customer Operations in December 2011. I have been
employed by IPL or one of IPALCO Entemrises. Inc. subsidiaries (Mid America Capital
Resources) since 1980, assuming my current role in December. 201 1. Previously, I have
held a number of management and staff positions at IPL. including overseeing the IPL
Power Supply organization, leading the Supply Coordination Office, managing the Eagle
Valley Generating Station, managing Transmission Operation and Generatjon Dispatch.
overseeing the Transmission Planning, Supply Chain, and Fuel Procurement functions,
Business Development, and engineering support roles in Power Supply and Transmission
& Distribution.
Q6. Have you testified previously before this Commission?
A6. Yes. I testified in Cause No. 43663 on utility tree trimming practices and tariffs related to
service quality. I testified on behalf of the Joint Petitioners in Cause No. 42685, involving
their request to recover their costs associated with taking transmission service under the
Midv{etlt Independent Tramlmitltlion Syntem Operator, Inc.'s ("MISO") Open A.ccem;
Transmission and Energy .Markets Tariff ("TEMT"), and on behalf of the Joint Petitioners
in Cause No. <12962 involving Day Ahead and Real Time R~venue Sufficiency Gum'antee
credits and charges. I also testified in Cause No. 43414 regarding IPL's Purchased Power
Benchmark proceeding, Caut;e No. 43623 regarding Demand Side Management
programs, and numerous Fuel Adjustment Charge proceedings. , I have submitted
IPL Witness BentleySadtler- 3
Petitioner's Exhibit BJBJAS-l (PUBLIC)
testimony on behalf of IPL in some of its previous FAC proceedings (FAC55 through
FAC6?). and in IPL's FAC89 and FAC90 proceedings.
Q7. What is the purpose of your testimony in this proceeding?
A? There are five parts to my testimony: First, my testimony provides an overview of the
IPL Transmission System. Second, it describes the generator interconnection process
within the IPL and MISO Transmission System. Third, my testimony addresses
transmission reliability issues related to: (a) the short-list of four independent power
producer ("IPP") projects from the June 28, 2012 RFP ("RFP Short List"); (b) the
combined cycle gas turbine ("CCGT") IPL proposes to construct at its Eagle Valley
generating plant ("Eagle Valley CCGT"); and ( c) Harding Street 5&6 Refueling
("Harding Street 5&6 Refueling"). Fourth, my testimony addresses interconnection issues
related to the IPL and MISO transmission system and both the Eagle Valley CCGT and
Harding Street 5&6. Finally, I discuss the impact of the Harding Street 5&6 Refueling on
system reliability in the IPL service territory.
Q8. Are you sponsoring any exhibits in support of your testimony?
A8. Yes. I am sponsoring Petitioner's Exhibit BJB-2 (CONFIDENTIAL), titled
Interconnection Facilities and Network Upgrades.
Q9. Was the exhibit identified above prepared or assembled by you or under your
direction or supervision?
A9. Yes.
QIO. Please provide an overview of IPL's transmission system.
IPL Witness BentleySadtler- 4
Petitioner's Exhibit RJBJAS-l (PUBLIC)
A 10. The IPL transmission system consists of 345 kilovolt ("k V") and 138 k V lines and
substation facilities in and around Indianapolis with additional transmission lines from
Indianapolis to the Petersburg Generating Station in Petersburg, Indiana and to the Eagle
Valley Generating Station in Martinsville, Indiana, as well as interconnecting lines to
other utilities.
Q11. Please explain the term "transmission system" as you are using it.
All. When referring to the transmission system, I am using the North American Electric
Reliability Corporation ("NERC") definition of the Bulk Electric System ("BES") of any
transmission facilities 100 kV and above.
Q12. Please explain how IPL's transmission system is interconnected with the
transmission systems of other electric utilities.
A12. IPL has 345 kV transmission interconnections with Indiana Michigan Power Company
("I&M") (which is part of American Electric Power or AEP) and Duke Energy Indiana,
Inc. ("Duke"), as well as 138 kV interconnections with Duke, Hoosier Energy and
Southern Indiana Gas and Electric Company d/b/a Vectren Energy Delivery of Indiana,
Inc. ("Vectren"). IPL has two 345 kV interconnections with I&M in Indianapolis and one
in Southern Indiana. There are two Dukefive 345 kV interconnections with Duke. three
in the Indianapolis area and tflreetwo in Southern Indiana. There is also one 138 kV
interconnection with Duke in Indianapolis, one in Martinsville, Indiana and two in
Petersburg, Indiana. Lastly, IPL has one 138 kV interconnection with Vectren and one
138 kV with Hoosier Energy in Petersburg, Indiana.
IPL Witness BentleySadtler- 5
Petitioner's Exhibit BJ-BJAS-l (PUBLIC)
Q13. Are you familiar with generator interconnection studies performed with respect to
new generating plants?
A13. Yes.
Q14. Please discuss how the Company determined whether additional transmission
facilities were necessary in past instances in which IPL added a generation resource
prior to joining MISO.
A14. Prior to joining MISO, IPL would perform internal transmission and deliverability studies
utilizing regional models from ECAR, which is the predecessor organization to the
Reliability First Corporation ("RFC"). If the internal studies indicated a potential impact
or provided advantages outside of IPL, a coordinated study would be completed with
neighboring utilities who may have shared in the construction costs of new transmission
facilities as appropriate.
Q15. Did the Company's evaluation process change as a result of its membership in
MISO?
A 15. Yes. IPL now completes preliminary analysis of generation impacts on its transmission
system; however, MISO is responsible for the evaluation of new generator
interconnections to the transmission systems under its functional control, which includes
IPL. MISO's existing procedures for evaluating such generator interconnection are set
forth in Attachment X to its Open Access Transmission Tariff ("OATT").!
Q16. Please describe the process used by MISO to evaluate new generator
interconnections to the transmission system under the functional control of MISO.
! See link at https:llwww.midwestiso.orgiLibrary/Tariff/Pages/Tariff.aspx1.
IPL Witness BentleySadtler- 6
Petitioner's Exhibit BJ-BJAS-l (PUBLIC)
A16. The MISO process for any entity interested in connecting a generator to the transmission
system starts with the submission of an application for interconnection. The application
is used for an initial screening and Feasibility Study. When the application is submitted,
MISO places the Feasibility Study request into a queue with all other requests. The
Feasibility Study will determine whether the interconnection of the generating facility
would result in constraints that exceed a pre-determined level. If the proposed
interconnection does not exceed any of the pre-determined system constraints, the project
will proceed to the Definitive Planning Phase ("DPP") which requires additional funding
for detailed system studies. The applicant may also elect to proceed to the DPP knowing
that electric system upgrades are likely. In order to enter the DPP stage, an applicant
must provide a stability model, point of interconnection, impedance from the substation
to the point of interconnection, all the appropriate technical data, one-line diagram,
generation output, and necessary generator step-up ("GSU") data. The applicant must
also provide proof of site control documentation that demonstrates ownership and
sufficient land area and pay a deposit as non-technical milestones.
In the DPP, a System Impact Study ("SIS") will be conducted to determine steady state
voltage issues, thermal overload constraints, deliverability, short circuit issues, and
transient stability. These studies will alsoA Facility Study is conducted after the SIS to
determine the required transmission upgrades, including a good faith cost and schedule
estimate for construction. The SIS includes an ad hoc group of interested parties that
include interconnection customers, consultants, transmission owners and other
independent system operators such as P JM, along with MISO transmission planning
personnel.
IPL Witness BentleySadtler- 7
Petitioner's Exhibit BJ-BJAS-l (PUBLIC)
Q17. Has IPL requested MISO to begin the study process for the Eagle Valley CCGT?
A 17 . Yes. IPL submitted its initial application for the interconnection to MISO on January 9,
2012. By the June 28, 2012 deadline, IPL provided MISO the appropriate data and
funding and subsequently entered the DPP. MISO held a kickoff meeting for the Central
Area DPP group on August 13,2012 to begin the studies.
Q18. When does IPL anticipate that the MISO review will be complete for the Eagle
Valley CCGT?
A18. IPL anticipates that the MISO review will be complete for the Eagle Valley CCGT before
December 31, 2013.
Q19. What is IPL's role in the MISO study process?
A19. IPL performs preliminary power flow studies, such as load flow, contingency and
short-circuit studies using the NERC criteria to determine the impact of new generation
on the transmission system and to determine what additional transmission facilities and
associated costs are necessary to address any identified impact. However, these are not
provided to MISO. MISO performs independent analysis and provides the analysis to the
SIS group for all stakeholders including IPL to review, provide feedback, raise concerns
and propose solutions.
Q20. Will a Generator Interconnection Agreement be signed for the Eagle Valley CCGT
at the end of the MISO process?
A20. Yes, if the project is approved. A Generator Interconnection Agreement will be signed at
the end of the MISO process and the signatory parties will include IPL as generator
owner, IPL as transmission owner, and MISO as the independent system operator.
IPL Witness BentleySadtler- 8
Petitioner's Exhibit BJBJAS-l (PUBLIC)
Q21. How were the potential transmission impacts related to the RFP Short List and
Eagle Valley CCGT addressed?
A2I. The integration impact analysis was performed by IPL, ABB Power Systems Consulting
("ABB"), and Ventyx, LLC ("Ventyx"). IPL engaged ABBN entyx to study transmission
and deliverability issues related to the RFP Short List and the Eagle Valley CCGT. Three
studies evaluated include: (1) congestion (as detailed in Witness Adkins' testimony); (2)
power transfer; and (3) reactive capability effects (as detailed in Witness Martin's
testimony) of the RFP Short List and the Eagle Valley CCGT. This process identified
any necessary transmission system upgrades or modifications and the associated costs.
IPL also analyzed the direct interconnection facilities and associated costs of the RFP
Short List. As appropriate, a cost adder or credit was applied to the RFP Short List
projects and the Eagle Valley CCGT to reflect these transmission-related costs.
Petitioner's Exhibit BJB-2 (CONFIDENTIAL) provides the estimated costs for
interconnection facilities and network upgrades for the Self Build Eagle Valley CCGT,
Bid 10, Bid 11, Bid 12, and Bid 13.
Q22. Why did IPL hire outside consultants to perform transmission related studies?
A22. IPL hired ABB to perform studies to assess transmission related impacts of the Eagle
Valley CCGT as well as the RFP Short List projects. This was done because the MISO
process to determine the additional transmission facilities necessary to address any
identified impact for the projects under consideration could not be completed in time to
incorporate into the Present Value Revenue Requirement ("PVRR") analysis of the
projects. It was essential to determine the costs of the necessary transmission facilities of
each project so that these costs could appropriately be factored into PVRR analysis of the
IPL Witness BentleySadtler- 9
Petitioner's Exhibit BJBJAS-l (PUBLIC)
projects. The results of the transmission facilities studies for the Eagle Valley CCGT are
provided here and in more detail in Witness Martin's testimony. Witness Martin's
testimony also provides the results of the transmission impact study for each of the RFP
Short List projects and Eagle Valley CCGT. The summary results of the transmission
impact studies for the Eagle Valley CCGT are provided below.
Q23. Why did IPL hire Ventyx to perform congestion analysis?
A23. IPL hired Ventyx to perform congestion analysis on the Eagle Valley CCGT and the RFP
Short List projects to provide economic information for IPL's analysis of all five options.
MISO does not address congestion related issues as part of its interconnection studies.
The details of the congestion analysis and results are presented in Witness Adkins'
testimony for the Eagle Valley CCGT and the RFP Short List projects.
Q24. How were transmission considerations factored into the decision to site the CCGT at
Eagle Valley?
A24. Transmission capacity and transmission congestion were both factors for siting generation
at Eagle Valley. One distinct advantage of using the Eagle Valley site is that IPL has four
existing 138 kV lines from Martinsville to Indianapolis to support the present generation
at Eagle Valley that can be used to support the new CCGT. Also, from a congestion
perspective, the Eagle Valley site was expected to have less congestion related impacts
than alternative sites due to being directly connected to the IPL 138 kV transmission
system in and around Indianapolis. The congestion related benefit is demonstrated in the
congestion studies performed by Ventyx and presented in detail in Witness Adkins'
testimony. Finally, from a transmission operational viewpoint, generation connected to
IPL Witness BentleySadtler-10
Petitioner's Exhibit BJRJAS-l (PUBLIC)
the same 138 kV system that serves IPL customers provides more dynamic operational
flexibility.
Q25. Did the ABB study identify the need for any transmission system upgrades?
A25. Yes. The ABB reactive capability and power transfer transmission studies determined that
additional transmission infrastructure is necessary to support up to a 725 MW CCGT at
the Eagle Valley site. The ABB study also determined the additional transmission
infrastructure and associated cost necessary for each of the RFP Short List projects as
provided in Witness Martin's testimony. As noted in Witness Crawford's testimony, IPL
considered CCGT plants sized from 550 MW to 725 MW, and thus this study could
accommodate the projects considered within this generation output range.
Q26. Please describe the transmission system upgrades identified in the ABB study for
the Eagle Valley CCGT.
A26. Because the four existing 138 kV lines are insufficient to carry the full load of the Eagle
Valley CCGT, a new 138 kV transmission line of approximately 23 miles will be
constructed from the existing Eagle Valley plant and Pritchard substation point of
interconnection site to the IPL Franklin Township substation located on the southeast side
of Indianapolis, Indiana. The new transmission line will be built on the available tower
line segment of the existing line from the Petersburg substation to Hanna substation that
runs adjacent to Eagle Valley. In addition, the existing 138 kV line from Pritchard
substation to Southport substation (132-21) and the 138 kV line from Prichard substation
to Mooresville substation (132-24) will be upgraded to support the new generating
capacity. Atse,At the Mooresville substation a 138kV breaker will be replaced. Also. an
additional 138 kV breaker replacement and bus modifications are needed at the Hanna
IPL Witness BentleySadtler-11
Petitioner's Exhibit :J1J:BJAS-l (PUBLIC)
needed at the Hanna substation to accommodate the increased rating of the 138kV line
from Hanna substation to Southeast substation (132-26).
Q27. Please describe IPL's analysis of the interconnection facilities and associated costs
of the RFP Short List.
A27. IPL reviewed the direct interconnection facilities of the RFP Short List to ensure that all
necessary equipment and associated costs were included for each project to allow a safe
and reliable connection to the transmission system in compliance with all applicable
requirements and standards.
Q28. What were the results ofIPL's analysis of the interconnection facilities and
associated costs of the RFP Short List?
A28. IPL determined that $_would need to be added to Bid 10's cost for two new
345 kV breakers and accessories at the IPLIDuke Gwynneville Substation which are
required to meet IPL Transmission Planning Criteria for a 345 kV substation
configuration. IPL also determined that $_ would need to be added to Bid 11
for the necessary interconnection facilities as no interconnection facilities were included
in their bid. The added to Bid 11 is for a new 345 kV substation which
includes all necessary breakers and a 1 mile loop from the plant substation to the IPL
Petersburg-Hanna Line. No adjustments related to the direct interconnection facilities
were necessary for the other two projects as it was determined that all necessary
equipment and associated costs for the interconnection facilities were included in their
bids.
IPL Witness IjentlcySadtler-12
Petitioner's Exhibit :B!WJAS-l (PUBLIC)
Q29. Is IPL planning to expand the existing substation or construct a new one to
accommodate the CCGT at Eagle Valley?
A29. IPL determined that a new substation will be safer, less congested, and less costly to
construct and operate than renovating the existing substation. The existing Pritchard
substation at Eagle Valley would need to be substantially renovated to enable
interconnection of the new Eagle Valley CCGT.
Q30. What are the anticipated construction costs to build the new transmission line,
upgrade the existing transmission lines and for the new substation for the Eagle
Valley CCGT?
A30. The following table details the estimated of the new substation at
Eagle Valley, the cost to both move and upgrade existing transmission lines and
termination equipment at the Pritchard Substation and the cost of the new transmission
line from Martinsville to Indianapolis and other associated cost to support the new
CCGT.
IPL Eagle Valley CCGT Plant I MISO Interconnection Request GI J238
1. New 138 kV substation and
3. New 23.0 mile IPL Pritchard - Franklin Township 138 kV Line and communications for SCAD etc.
4. New IPL 138 kV Breaker and accessories at Franklin Township Sub for New Line
5. Upgrade 15.7 mile 132-24 IPL Pritchard - Mooresville 138 kV Line for clearance m
6. Upgrade 21.6 mile 132-21 IPL Pritchard - Southport 138 kV Line for clearance mitigation, Honey Creek 3-way disconnect switch,
terminal . $-IPL Witness Bettt1eySadtlQr-13
Petitioner's Exhibit UJ:BJIAS-l (PUBLIC)
7. Upgrade IPL 138 kV Hanna Sub to mitigate Hanna - SE 138 kV Line loading with terminal equipment and line re-connected to the bus $_
--~~~---------------------------------------------r--TOTAL TRANSMISSION AND SUBSTATION COSTS
As shown in Witness Guletsky's testimony, the ~for the substation. Item 1 is
included as part of the EPC cost estimate. The remainder of the transmission costs
I~~~~ are included as part of Owner's costs as identified in Witness
Crawford's testimony. The network upgrade cost-ffi...J..1km 3-7 an~ shown in Witness
Martin's testimony and was assessed from the Power Transfer Study results.
Q31. Are the transmission upgrades and associated costs determined by ABB for the
Eagle Valley CCGT and the RFP Short list projects reasonable estimates of the
upgrades and costs that would result from the MISO process?
A31. Yes. The study methodology and approach used by ABB is substantially similar to that
used by MISO. Preliminary results from the MISO Interconnection request J238 studies
for the Eagle Valley CCGT have identified the same upgrades as the ABB studies.
Therefore, the associated costs from ABB' s study should closely match the results of the
MISO study.
Q32. Please discuss the Company's timeline projections associated with the necessary
transmission construction and upgrades it has identified.
A32. Design engineering of this project will begin in the spring of 2013. Detailed engineering
and procurement is planned to commence in April 2014, shortly after the anticipated date
of securing CPCN approval. Construction of the transmission upgrades will take place in
parallel with the construction of the Eagle Valley CCGT and are expected to be
IPL Witness BentleySadtler-14
Petitioner's Exhibit BJB.JAS-l (PUBLIC)
sufficiently complete to allow back-feed power to the Eagle Valley CCGT for testing and
commissioning by May 30, 2016. All transmission upgrades and construction are
planned to be completed in time to allow the Eagle Valley CCGT to achieve an April
2017 commercial operations date.
Q33. Will any of the identified costs be eligible for cost-sharing with other MISO
members?
A33. It may be possible that a small portion of these costs will be eligible for cost sharing with
other MISO members but IPL does not have sufficient information to make that
assumption at this time. If any cost sharing does occur, the benefit of the reduced costs
will be utilized for the benefit of the IPL customers. However, IPL does not believe these
costs will be eligible for cost sharing because the interconnection customer is normally
assessed these costs based on MISO cost sharing procedures.
Q34. What is the significance of the Harding Street 5 & 6 Refueling on transmission
reliability?
A34. Witness Crawford explains the rationale, timing and process to convert the 200 MW
Harding Street Generating Units 5 & 6 from coal as the primary fuel to natural gas as the
primary fuel. In addition to the capacity benefits associated with approximately 200 MW
of generating capability, the IPL 138 kV transmission system benefits include voltage
support by maintaining the existing dynamic volt-ampere reactive ("VAR") power
capability during contingency conditions and frequency response in the IPL service
territory. Continued utilization of Harding Street Units 5 & 6 provides operational
flexibility for planned and unplanned outages on the transmission system and/or for
planned and unplanned outages to the larger coal and gas-fired generation in the IPL
IPL Witness BentleySadtler-15
Petitioner's Exhibit BJ.BJAS-l (PUBLIC)
serVIce territory. This flexibility allows IPL to offer its own generation with low
congestion costs into the market instead of relying on MISO to dispatch higher cost
generation to alleviate operational issues which benefits IPL customers.
Q35. Are there any transmission upgrades necessary as part of the Harding Street 5 & 6
Refueling?
A35. No. After the refueling conversion, Harding Street 5 & 6 will continue to use the existing
interconnection facilities. \
Q36. Would upgrades be required if Harding Street 5 & 6 are not refueled?
A36. The MISO interconnection application and studies were based upon refueling of Harding
Street units 5 & 6. Therefore, additional studies and fees would be needed by MISO to
evaluate this option. In lieu of MISO studies, IPL has performed similar studies to
determine the transmission implications. Based upon our preliminary studies, we believe
additional transmission/substation equipment would be required to support an
incremental 200 MW of import capability from the 345 kV system into the 138 kV IPL
load zone if Harding Street 5 & 6 were retired.
Q37. Is it necessary for the Harding Street 5 & 6 Refueling project to go through the
MISO interconnection process?
A37. No. Harding Street 5 & 6 will continue to use the existing interconnection with similar
output capability from each unit; therefore, it is not necessary to go through the MISO
interconnection process.
Q38. Does this conclude your prefiled direct testimony?
IPL Witness BentleySadtler-16
Petitioner's Exhibit BJBJAS-l (PUBLIC)
A38. Yes, at this time.
INDSO I 1408470y3
IPL Witness BentleySadtler-17
Petitioner's Exhibit KM:H~
VERIFIED DIRECT TESTIMONY
OF
KELLY M. HUNTINCTON
CRAIG JACKSON
ON BEHALF OF
INDIANAPOLIS POWER & LIGHT COMPANY
CAUSE NO. 44339
Petitioner's Exhibit KMHCJ-l
VERIFIED DIRECT TESTIMONY OF KELLY M. HUNTINGTONCRAIG .JACKSON ON BEHALF OF
INDIANAPOLIS POWER & LIGHT COMPANY
Q1. Please state your name, employer and business address.
AI. My name is Kelly M. Huntington. Craig Jackson. I am employed by The Dayton Power
and Light Company ("DP&L"). 1 065 Woodman Drive. Dayton. Ohio. 45432.
02. What is your position and professional relationship with Indianapolis Power &
Light Company ("IPL" or "Company"), One Monument Circle, Indianapolis, Indiana
46204.
Q2. What is your position with IPL?
A2. I am Seniorthe Director. Vice President", and Chief Financial Officer of.{.l2b.;-AES US
Services. LLC. AES US Services. LLC is the AES Strategic Business Unit ("SBU") that
provides services for IPL. and other AES affiliates. pursuant to an Affiliate Services
Agreement filed with the Indiana Utility Regulatory Commission ("IIJRC").
Q3. Please describe your duties as Senior Vice Prc§idcnt and Chief Financial Officer.
A3. I am rC[JpomJible for the Company'tJ financial servicetJ and information technology
functions. My finffilcial services responsibilities include accounting, internal controls
over fimmcial reporting, financing and tremmry, tax, and financial pltmning and
ffilalysis.ln my current position. I report to the President of the SBU who is also CEO of
IPL. I have direct responsibility and oversight for the accounting. tax. financial planning.
treasury. risk management. and internal audit functions onPL and other AES affiliates.
Q4. Please summarize your educational and professional qualifications.
IPL Witness HuntingtonJackson- I
Petitioner's Exhibit KMHCJ-l
A4. I OOMreceived a Bachelor of Science Degree in Management Science from the
Massachusetts Institute of Technology, Cambridge, Massachusetts. I havedegree 10
Business Administration from Bloomsburg University in 1996. I also obtained earned a
Master of Business Administration f)e.gree from Northwestern University'S Kellogg
School of Management, Evanston, Il1inoit;. J am a CFA (Chartered Financial i\nalyst)
chatierholder. degree in Finance from Wright State University in 2001.
Q5. Please summarize your prior work experience.
A5. From 1997 to 1999, I was a Corporate Finance Analyst at BancBoston Robertson
Stephem;. From 1999 to 2001, I wat; an l\t;t;ociate at Thayer Capital Partnem. Since
2003, I have been employed by the AES Corporation holding a wide vat'iety of finatlcial
and leadership assignment,. I joined as a Financial Analyst and was promoted to Senior
Financial Analyst in 2004. I '.vas promoted to Director, Investor Relations in 2005. I was
promoted to Managing Director, Risk Management in 2007. I was promoted to Vice
President, Special Projects, reporting to AES Corporation's President and Chief
Executive Officer, in January 2008. I '.vat; promoted to Vice President! joined DP&L in
February 2000 as a Financial Analyst. Corporate Modeling. In December 2002. I
accepted the position of Team Leader. ISO Settlements. with PPL Comoration. In June
2004. I returned to DPL as Manager, Financial Planning and Analysis, reporting to AE-S
Corporation's Executive Vice Prenident and Chief Financial Officer, in September 2008.
I joined IPL as Seniol-ihe Chief Financial Officer. From Jlme 2004 to May 2012. I was
promoted through several positions of increasing responsibility within the Treasury
organization at DP&L. the last of which was as Vice President and Chief Finatlcial
Of1icer in April 2011.Treasurer.
IPL Witness HuntingtonJackson- 2
Petitioner's Exhibit KMHCJ-l
Prior to joining DP&L in February of 2000. I served in the United States Air Force ("Air
Force") as a Finance Technician. I began my service with the Air Force in May 1996.
Q6. Have you testified previously before this Commission?
A6. No,
Q7. What is the purpose of your testimony in this proceeding?
A 7. The purpose of my testimony is to support the Company's proposed accounting and
ratemaking treatment presented by IPL Witness Cutshaw. My testimony explains the
impact IPL' s construction of a new combined cycle turbine ("CCGT") at the Eagle Valley
generating station ("Eagle Valley CCGT") and refueling of Harding Street Station Units
5&6 (collectively, the "Projects") will have on IPL's financial strength and on IPL's
credit ratings. I also discuss the benefit to customers to maintaining the Company's
ratings and address how earnings erosion can adversely affect the Company's credit rating
and otherwise strain resources. Additionally, I identify the tax benefits that will be
realized as a result of the Eagle Valley CCGT option.
Q8. What are IPL's financial objectives?
A8. At a high level, IPL seeks to maintain the financial strength of an investment grade utility
so that we can deliver reliable service at a reasonable cost to our customers. Maintaining
this investment grade credit profile is important to ensure we have reliable access to the
credit markets at attractive interest rates during all types of economic cycles. This in turn
provides the ability to meet our financial obligations during periods of heavy capital
expenditures.
IPL Witness HuntingtonJackson- 3
Petitioner's Exhibit KMHCJ-l
Q9. What are IPL's capital needs associated with the construction of the Replacement
Generation Projects?
A9. IPL projects that its capital expenditures excluding Allowance for Funds Used During
Construction ("AFUDC") associated with the construction of the Replacement
Generation Projects will total approximately $667 million through 2017.
QIO. Please discuss how IPL plans to finance the construction of the Replacement
Generation Projects.
AIO. IPL plans to finance the projects in a manner that is consistent with its targeted credit
ratings and capital structure. Funding for the Replacement Generation Projects will come
from three primary sources: (1) secured or unsecured debt issued by IPL; (2) operating
cash flow from IPL; and (3) equity investments from IPALCO Enterprises, Inc., IPL's
parent. Tax-exempt debt may also be considered as a component of (1) above to the
extent that a portion of these Projects qualify for this type of financing.
QU. Please explain why it is important for the Company to maintain its investment grade
credit rating.
A 11. As previously explained, the capital needs associated with the construction of these
projects are substantial and as such cannot be funded through internally-generated funds
alone. These funding needs are compounded by the capital necessary to comply with the
Utility Mercury and Air Toxics Standards ("MATS") requirements as outlined in our
request for a Certificate of Public Convenience and Necessity in Cause No. 44242
currently pending before the Commission. Based on supplemental testimony filed in
early January, the capital expenditures for the Utility MATS requirements are estimated
to be $511 million through 2016, excluding AFUDC and removal costs. By following the
IPL Witness HuntingtonJackson- 4
Petitioner's Exhibit KMHCJ-l
Company's plan for funding the Replacement Generation Projects, IPL should have ready
and flexible access to the capital markets and should be able to maintain its current
capital structure, and therefore its investment grade ratings. However, IPL will have
lower credit metrics until it receives recovery of the costs through retail rates. Such lower
metrics will increase the risk that IPL's investment grade credit rating is downgraded.
This will be more fully described later in my testimony. The specific accounting and
ratemaking relief proposed by Witness Cutshaw is also necessary to support this
construction program and maintain IPL's financial strength. Without ready and flexible
access to the capital markets and a supportive ratemaking framework, IPL would not be
able to support this construction program. As a result, IPL's financial strength and
flexibility would decline and as discussed below this would adversely affect customers.
Q12. Please discuss the impact to the Company and its customers if IPL's investment
grade rating is not maintained.
A12. Financial strength and flexibility provide the framework for operational effectiveness
which is necessary to provide safe and reliable service to customers at a reasonable cost.
A non-investment grade rating would lead to an increase in overall financing costs and
result in a higher cost of capital. Customers would be adversely affected because higher
capital costs lead to higher rates for electric service and strain resources that could
otherwise be utilized to meet our customers' ongoing need for reliable electric service.
Q13. Please describe the credit rating process and the key factors analyzed by the three
major credit rating agencies.
A13. Credit ratings reflect a credit rating agency's independent judgment of the Company's
credit worthiness and its ability to meet its debt obligations. Credit committees at each
IPL Witness HuntingtonJackson- 5
Petitioner's Exhibit KMHCJ-l
agency determine the ratings of a company based on certain quantitative and qualitative
measures. These factors are used to assess the financial and business risks of
fixed-income issuers. Both Fitch Ratings ("Fitch") and Standard & Poor's ("S&P")
delineate investment grade as any rating equal to "BBB-" or above. Moody's Investors
Service ("Moody's") delineates investment grade as any rating equal to "Baa3" or above.
Non-investment grade ratings at Fitch and S&P are "BB+" or below and "Bal" or below
at Moody's.
Qualitative factors differ somewhat at each of the rating agencies but generally are related
to business risk such as regulation, the ability to recover costs and earn authorized
returns, and fleet diversification. At S&P, these qualitative factors are referred to as the
Business Risk Profile and are rated on a scale from excellent to vulnerable.
Since most electric utilities are highly capital intensive, financial strength and liquidity
are key quantitative factors in determining long-term viability. Over the last several years
each of the rating agencies has become more transparent in their methodologies for
determining financial strength and liquidity. For example, S&P views the following three
financial measures (or Financial Risk Indicative Ratios) as the most important to its
analysis of financial risk: 1) Funds from Operations ("FFO")/ Debt; 2) Debt/Earnings
before Interest, Taxes, Depreciation and Amortization ("EBITDA"); and 3) Debt/Capital.
As a part of its methodology, S&P considers a combination of quantitative and qualitative
factors in a Business and Financial Risk Profile Matrix. The Financial Risk Profile
category of a company is determined by the results of the ratios analysis ("Financial Risk
Indicative Ratios") as mentioned in the financial measures above; and is rated on a scale
of six measures from minimal to highly leveraged. The weaker the Business Profile
IPL Witness HuntingtonJackson- 6
Petitioner's Exhibit KMHCJ-l
category, the stronger the Financial Risk Indicative Ratios must be in order to maintain an
investment grade rating.
The discussion above has focused on S&P and its rating methodology. Moody's and
Fitch employ similar methods in their ratings determinations, although the quantitative
calculations and weightings along with qualitative measures may be slightly different.
Q14. Can you expand on the regulatory factor mentioned above and your thoughts on its
importance in the credit rating process?
A14. Yes. Regulation is a key factor in the credit rating process at all three credit rating
agenCIes. Predictability, full and timely cost recovery and a regulatory environment
supportive of a utility's financial strength are key credit considerations. A utility
operating in a stable, reliable, and highly predictable regulatory environment will be
scored higher than a utility that operates in an unstable, unreliable or highly unpredictable
regulatory environment. To that point, S&P recently revised the regulatory assessment of
Indiana downward from "More Credit-Supportive" to "Credit-Supportive." It is unknown
at this time whether this change in assessment will have a negative impact on IPL's
ratings.
Q15. Please discuss IPL's current credit ratings.
A 15. As of the date of this prefiled testimony, IPL' s credit ratings by the credit rating agencies
are as follows:
Moody's Investors Service Standard & Poor's Fitch Ratings
Corporate Credit Baa2 BBB- BBB-Rating/Issuer Rating Secured Debt A3 BBB+ BBB+
IPL Witness Huntingtonlackson- 7
Petitioner's Exhibit KMHCJ-l
I Unsecured Debt I Baa2 I BBB- I BBB
Q16. Please describe the potential impact the construction of the Replacement Generation
Projects may have to the Company's investment grade credit ratings.
A16. As discussed previously, IPL's credit ratings are expected to stay at investment grade if
the rating agencies continue to view Indiana's regulatory framework as supportive and if
earnings erosion from these large capital projects is avoided. IPL Witness Cutshaw
discusses the specific accounting and ratemaking relief needed to maintain a supportive
framework.
However, IPL's credit metrics will be lower for a period of time as a result of the heavy
construction related to the proposed projects in this proceeding compounded by the
construction expenditures necessary for utility MATS compliance, until recovery through
rates is granted. This could put our credit ratings at risk for downgrade. However, we
believe the rating agencies will look through the temporary time period of lower credit
metrics, as ratios recover nicely in later years when cash flow measures grow stronger and
earnings erosion is avoided as recovery of costs is achieved through supportive
ratemaking.
Q17. Is it easy for a company that has been downgraded to regain its prior credit rating?
A17. No. It is not easy for a company that has been downgraded to regain its prior credit
rating. In this volatile economic climate it is easier for a utility's ratings to decline as a
result of a deficiency than it is for a company's rating to increase once that deficiency has
been remedied. In other words, a company's credit rating can decline quickly, but it takes
IPL Witness Huntingtonlackson- 8
Petitioner's Exhibit KMHCJ-l
longer for the rating to increase as rating agencies need to see an improvement in metrics
over a period of time before granting an upgrade.
Q18. Please describe the financial analysis related to credit worthiness conducted by the
Company in light of Standard & Poor's methodology related to long-term power
purchase agreements.
A 18. S&P views power purchase agreements as fixed, debt-like obligations of a utility and as
such has determined that they should be included in the calculation of financial metrics
on which they base a company's credit worthiness. This method treats fixed capacity
payments as if they were a part of the company's permanent capital structure by
calculating the present value of the fixed (capacity) portion of the annual payment,
discounted at the utility's average cost of debt, and multiplied by a risk factor.
Q19. Please discuss the concept of the risk factor in more detail.
A19. S&P's risk factor reflects the probability of recovery that power purchase agreement costs
will be recovered through rates. This factor varies by state statute or regulatory policy
and can range from 0% to 100%. The greater the certainty of recovery the lower the risk
factor, which results in a lesser amount of debt imputed onto the utility's balance sheet
for each power purchase agreement.
Q20. Are you knowledgeable as to the risk factor assigned to Indiana?
A20. Based on conversations with S&P's staff, the risk factor most likely assigned to Indiana is
25%, reflecting high confidence of recovery through rates for power purchase
agreements. This risk factor, of course, is re-evaluated each time an analysis is done by
S&P and is subject to change.
IPL Witness Huntingtonlackson- 9
Petitioner's Exhibit KMHCJ-l
Q21. Please discuss other adjustments made by S&P related to its evaluation of power
purchase agreements.
A2l. S&P also imputes interest and depreciation expense. Imputed interest is based on the
amount of debt imputed at the embedded debt cost of the utility. Imputed depreciation is
based on the difference between the fixed capacity payment and the amount of imputed
interest for the year.
Q22. Describe the outcome of this analysis as you evaluated the projects competing with
the Eagle Valley CCGT option.
A22. The analysis indicated that the key metrics used to determine IPL's credit rating all
deteriorated using S&P's methodology for the two short-listed tolling projects. However,
these key metrics did not deteriorate significantly enough to trigger an expected
downgrade, and therefore no increased interest expense was expected if IPL were to enter
into either of the proposed tolling agreements. As such, no quantitative adjustment was
made to either tolling project in assessing the Present Value Revenue Requirement
("PVRR"). This nevertheless remains an important qualitative consideration as entering
into either of the tolling agreements would negatively impact key credit rating metrics and
would leave nearly no margin for any other negative event that could result in a credit
rating downgrade.
Q23. Have you identified any tax incentives or other benefits associated with the
construction and proposed financing plan for the Eagle Valley CCGT option?
A23. Yes.
Q24. Please identify the tax incentives or other benefits.
IPL Witness HuntingtonJackson-lO
Petitioner's Exhibit KMH(;J-l
A24. IPL has secured a ten-year real and personal property tax abatement with the Morgan
County Economic Development Corporation. Discussions are on-going to consider
establishing a tax increment finance ("TIF") district; however at this time it is unknown
as to whether this will occur.
The ten-year real and personal property tax abatement represents the maximum allowed
by law and will begin when the plant goes into service. The estimated property tax
abatement savings for a $631 million plant is approximately $23.5 million. This
abatement is unlike declining abatement approaches that start with a 100% abatement that
steadily declines over a ten-year period. We chose to use a ten-year flat 60% abatement.
This approach allows Morgan County to begin immediately receiving additional property
tax revenue and also provides IPL with a reduction in property tax expense.
If the TIF District is established, it will encompass the site of the new facility in Morgan
County. The County has proposed to pledge up to $2 million in TIF assistance for
infrastructure and investment at the plant site.
Morgan County also plans to offer up to $1,500 per employee for training. The training
funds will be in the form of a reimbursable grant to IPL.
Q25. Does this conclude your prepared verified direct testimony?
A25 . Yes, at this time.
INDSQ I J 408476y3
IPL Witness Huntingtonlackson-ll
Petitioner's Exhibit JAS-l(PUBLIC)
(PUBLIC)
VERIFIED DIRECT TESTIMONY
OF
JAMES A. SADTLER
ON BEHALF OF
INDIANAPOLIS POWER & LIGHT COMPANY
CAUSE NO. 44339
SPONSORING PETITIONER'S EXHIBIT BJB-2 (CONFIDENTIAL)
Petitioner's Exhibit JAS-l (PUBLIC)
VERIFIED DIRECT TESTIMONY OF JAMES A. SADTLER ON BEHALF OF
INDIANAPOLIS POWER & LIGHT COMPANY
1 Q1. Please state your name, employer and business address.
2 AI. My name is James A. Sadtler. I am employed by Indianapolis Power & Light Company
3 ("IPL" or "Company"), One Monument Circle, Indianapolis, Indiana 46204.
4 Q2. What is your position with IPL?
5 A2. I am currently the Director of Transmission Field Operations.
6 Q3. Please describe your duties as Director of Transmission Field Operations.
7 A3. As Director of Transmission Field Operations, I am responsible for the real time
8 operations for the IPL transmission and distribution systems, the operation and
9 maintenance of all IPL substations and the downtown electrical network. This includes
10 the operation and maintenance of the protective relaying schemes, and supervisory
11 control and data acquisition systems. The real time operation of the transmission system
12 requires coordination with the Midcontinent Independent System Operator, Inc. (MISO).
13 Q4. Please summarize your educational and professional qualifications.
14 A4. I received a Bachelor of Science Degree in Electrical Engineering Technology from
15 Purdue University. I am a Registered Professional Engineer in the State oflndiana.
16 Q5. Please summarize your prior work experience.
17 A5. I have been employed by IPL or one of IP ALCO Enterprises, Inc. subsidiaries (Mid
18 America Capital Resources) since 1980, assuming my current role in December, 2011.
19 Previously, I have held a number of management and staff positions at IPL, including
IPL Witness Sadtler-l
1
2
3
4
5
Petitioner's Exhibit JAS-l (PUBLIC)
overseeing the IPL Power Supply organization, leading the Supply Coordination Office,
managing the Eagle Valley Generating Station, managing Transmission Operation and
Generation Dispatch, overseeing the Transmission Planning, Supply Chain, and Fuel
Procurement functions, Business Development, and engineering support roles in Power
Supply and Transmission & Distribution.
6 Q6. Have you testified previously before this Commission?
7 A6. Yes, I have submitted testimony on behalf of IPL in some of its previous F AC
8
9
10
11
12
13
14
15
16
17
18
19
20
Q7.
A7.
proceedings (FAC55 through FAC67), and in IPL's FAC89 and FAC90 proceedings.
What is the purpose of your testimony in this proceeding?
There are five parts to my testimony: First, my testimony provides an overview of the
IPL Transmission System. Second, it describes the generator interconnection process
within the IPL and MISO Transmission System. Third, my testimony addresses
transmission reliability issues related to: (a) the short-list of four independent power
producer ("IPP") projects from the June 28, 2012 RFP ("RFP Short List"); (b) the
combined cycle gas turbine ("CCGT") IPL proposes to construct at its Eagle Valley
generating plant ("Eagle Valley CCGT"); and (c) Harding Street 5&6 Refueling
("Harding Street 5&6 Refueling"). Fourth, my testimony addresses interconnection issues
related to the IPL and MISO transmission system and both the Eagle Valley CCGT and
Harding Street 5&6. Finally, I discuss the impact of the Harding Street 5&6 Refueling on
system reliability in the IPL service territory.
21 Q8. Are you sponsoring any exhibits in support of your testimony?
IPL Witness Sadtler-2
1
2
3
4
5
6
7
8
9
10
11
A8.
Q9.
A9.
QIO.
Ala.
Petitioner's Exhibit JAS-l (PUBLIC)
Yes. I am sponsoring Petitioner's Exhibit BJB-2 (CONFIDENTIAL), titled
Interconnection Facilities and Network Upgrades.
Was the exhibit identified above prepared or assembled by you or under your
direction or supervision?
Yes.
Please provide an overview of IPL's transmission system.
The IPL transmission system consists of 345 kilovolt ("kV") and 138 kV lines and
substation facilities in and around Indianapolis with additional transmission lines from
Indianapolis to the Petersburg Generating Station in Petersburg, Indiana and to the Eagle
Valley Generating Station in Martinsville, Indiana, as well as interconnecting lines to
other utilities.
12 Ql1. Please explain the term "transmission system" as you are using it.
13 All. When referring to the transmission system, I am using the North American Electric
14
15
Reliability Corporation ("NERC") definition of the Bulk Electric System ("BES") of any
transmission facilities 100 kV and above.
16 Q12. Please explain how IPL's transmission system is interconnected with the
17 transmission systems of other electric utilities.
18 A12. IPL has 345 kV transmission interconnections with Indiana Michigan Power Company
19 ("I&M") (which is part of American Electric Power or AEP) and Duke Energy Indiana,
20
21
22
Inc. ("Duke"), as well as 138 kV interconnections with Duke, Hoosier Energy and
Southern Indiana Gas and Electric Company d/b/a Vectren Energy Delivery of Indiana,
Inc. ("Vectren"). IPL has two 345 kV interconnections with I&M in Indianapolis and
IPL Witness Sadtler-3
1
2
3
4
5
Petitioner's Exhibit JAS-l (PUBLIC)
one in Southern Indiana. There are five 345 kV interconnections with Duke, three in the
Indianapolis area and two in Southern Indiana. There is also one 138 kV interconnection
with Duke in Indianapolis, one in Martinsville, Indiana and two in Petersburg, Indiana.
Lastly, IPL has one 138 kV interconnection with Vectren and one 138 kV with Hoosier
Energy in Petersburg, Indiana.
6 Q13. Are you familiar with generator interconnection studies performed with respect to
7 new generating plants?
8 A13. Yes.
9 Q14. Please discuss how the Company determined whether additional transmission
10
11
facilities were necessary in past instances in which IPL added a generation resource
prior to joining MISO.
12 A14. Prior to joining MISO, IPL would perform internal transmission and deliverability studies
13 utilizing regional models from ECAR, which is the predecessor organization to the
14 Reliability First Corporation ("RFC"). If the internal studies indicated a potential impact
15 or provided advantages outside of IPL, a coordinated study would be completed with
16 neighboring utilities who may have shared in the construction costs of new transmission
17 facilities as appropriate.
18 Q15. Did the Company's evaluation process change as a result of its membership in
19 MISO?
20 A 15 . Yes. IPL now completes preliminary analysis of generation impacts on its transmission
21 system; however, MISO is responsible for the evaluation of new generator
22 interconnections to the transmission systems under its functional control, which includes
IPL Witness Sadtler-4
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
Q16.
A16.
Petitioner's Exhibit JAS-l (PUBLIC)
IPL. MISO's existing procedures for evaluating such generator interconnection are set
forth in Attachment X to its Open Access Transmission Tariff ("OATT"). 1
Please describe the process used by MISO to evaluate new generator
interconnections to the transmission system under the functional control of MISO.
The MISO process for any entity interested in connecting a generator to the transmission
system starts with the submission of an application for interconnection. The application
is used for an initial screening and Feasibility Study. When the application is submitted,
MISO places the Feasibility Study request into a queue with all other requests. The
Feasibility Study will determine whether the interconnection of the generating facility
would result in constraints that exceed a pre-determined level. If the proposed
interconnection does not exceed any of the pre-determined system constraints, the project
will proceed to the Definitive Planning Phase ("DPP") which requires additional funding
for detailed system studies. The applicant may also elect to proceed to the DPP knowing
that electric system upgrades are likely. In order to enter the DPP stage, an applicant
must provide a stability model, point of interconnection, impedance from the substation
to the point of interconnection, all the appropriate technical data, one-line diagram,
generation output, and necessary generator step-up ("GSU") data. The applicant must
also provide proof of site control documentation that demonstrates ownership and
sufficient land area and pay a deposit as non-technical milestones.
In the DPP, a System Impact Study ("SIS") will be conducted to determine steady state
voltage issues, thermal overload constraints, deliverability, short circuit issues, and
I See link at https:llwww.midwestiso.org/Library/Tariff/Pages/Tariff.aspx
IPL Witness Sadtler-5
Petitioner's Exhibit JAS-l (PUBLIC)
1 transient stability. A Facility Study is conducted after the SIS to determine the required
2 transmission upgrades, including a good faith cost and schedule estimate for construction.
3 The SIS includes an ad hoc group of interested parties that include interconnection
4 customers, consultants, transmission owners and other independent system operators such
5 as P JM, along with MISO transmission planning personnel.
6 Q17. Has IPL requested MISO to begin the study process for the Eagle Valley CCGT?
7 A 17 . Yes. IPL submitted its initial application for the interconnection to MISO on January 9,
8
9
10
2012. By the June 28, 2012 deadline, IPL provided MISO the appropriate data and
funding and subsequently entered the DPP. MISO held a kickoff meeting for the Central
Area DPP group on August 13,2012 to begin the studies.
11 Q18. When does IPL anticipate that the MISO review will be complete for the Eagle
12 Valley CCGT?
13 A18. IPL anticipates that the MISO review will be complete for the Eagle Valley CCGT before
14 December 31, 2013.
15 Q19. What is IPL's role in the MISO study process?
16 A19. IPL performs preliminary power flow studies, such as load flow, contingency and short-
17 circuit studies using the NERC criteria to determine the impact of new generation on the
18 transmission system and to determine what additional transmission facilities and
19 associated costs are necessary to address any identified impact. However, these are not
20 provided to MISO. MISO performs independent analysis and provides the analysis to the
21 SIS group for all stakeholders including IPL to review, provide feedback, raise concerns
22 and propose solutions.
IPL Witness Sadtler-6
Petitioner's Exhibit JAS-l (PUBLIC)
1 Q20. Will a Generator Interconnection Agreement be signed for the Eagle Valley CCGT
2 at the end of the MISO process?
3 A20. Yes, if the project is approved. A Generator Interconnection Agreement will be signed at
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
Q21.
A21.
the end of the MISO process and the signatory parties will include IPL as generator
owner, IPL as transmission owner, and MISO as the independent system operator.
How were the potential transmission impacts related to the RFP Short List and
Eagle Valley CCGT addressed?
The integration impact analysis was performed by IPL, ABB Power Systems Consulting
("ABB"), and Ventyx, LLC ("Ventyx"). IPL engaged ABB/Ventyx to study transmission
and deliverability issues related to the RFP Short List and the Eagle Valley CCGT. Three
studies evaluated include: (1) congestion (as detailed in Witness Adkins' testimony); (2)
power transfer; and (3) reactive capability effects (as detailed in Witness Martin's
testimony) of the RFP Short List and the Eagle Valley CCGT. This process identified
any necessary transmission system upgrades or modifications and the associated costs.
IPL also analyzed the direct interconnection facilities and associated costs of the RFP
Short List. As appropriate, a cost adder or credit was applied to the RFP Short List
projects and the Eagle Valley CCGT to reflect these transmission-related costs.
Petitioner's Exhibit BJB-2 (CONFIDENTIAL) provides the estimated costs for
interconnection facilities and network upgrades for the Self Build Eagle Valley CCGT,
Bid 10, Bid 11, Bid 12, and Bid 13.
21 Q22. Why did IPL hire outside consultants to perform transmission related studies?
22 A22. IPL hired ABB to perform studies to assess transmission related impacts of the Eagle
23 Valley CCGT as well as the RFP Short List projects. This was done because the MISO
IPL Witness Sadtler-7
Petitioner's Exhibit JAS-l (PUBLIC)
1 process to determine the additional transmission facilities necessary to address any
2 identified impact for the projects under consideration could not be completed in time to
3 incorporate into the Present Value Revenue Requirement ("PVRR") analysis of the
4 projects. It was essential to determine the costs of the necessary transmission facilities of
5 each project so that these costs could appropriately be factored into PVRR analysis of the
6 projects. The results of the transmission facilities studies for the Eagle Valley CCGT are
7 provided here and in more detail in Witness Martin's testimony. Witness Martin's
8 testimony also provides the results of the transmission impact study for each of the RFP
9 Short List projects and Eagle Valley CCGT. The summary results of the transmission
10 impact studies for the Eagle Valley CCGT are provided below.
11 Q23. Why did IPL hire Ventyx to perform congestion analysis?
12 A23. IPL hired Ventyx to perform congestion analysis on the Eagle Valley CCGT and the RFP
13 Short List projects to provide economic information for IPL's analysis of all five options.
14 MISO does not address congestion related issues as part of its interconnection studies.
15 The details of the congestion analysis and results are presented in Witness Adkins'
16 testimony for the Eagle Valley CCGT and the RFP Short List projects.
17 Q24. How were transmission considerations factored into the decision to site the CCGT at
18 Eagle Valley?
19 A24. Transmission capacity and transmission congestion were both factors for siting
20
21
22
23
generation at Eagle Valley. One distinct advantage of using the Eagle Valley site is that
IPL has four existing 138 kV lines from Martinsville to Indianapolis to support the
present generation at Eagle Valley that can be used to support the new CCGT. Also,
from a congestion perspective, the Eagle Valley site was expected to have less
IPL Witness Sadtler-8
1
2
3
4
Petitioner's Exhibit JAS-l (PUBLIC)
congestion related impacts than alternative sites due to being directly connected to the
IPL 138 kV transmission system in and around Indianapolis. The congestion related
benefit is demonstrated in the congestion studies performed by Ventyx and presented in
detail in Witness Adkins' testimony. Finally, from a transmission operational
5 viewpoint, generation connected to the same 138 kV system that serves IPL customers
6 provides more dynamic operational flexibility.
7 Q25. Did the ABB study identify the need for any transmission system upgrades?
8 A25. Yes. The ABB reactive capability and power transfer transmission studies determined
9 that additional transmission infrastructure is necessary to support up to a 725 MW CCGT
10 at the Eagle Valley site. The ABB study also determined the additional transmission
11 infrastructure and associated cost necessary for each of the RFP Short List projects as
12 provided in Witness Martin's testimony. As noted in Witness Crawford's testimony, IPL
13 considered CCGT plants sized from 550 MW to 725 MW, and thus this study could
14 accommodate the projects considered within this generation output range.
15 Q26. Please describe the transmission system upgrades identified in the ABB study for
16 the Eagle Valley CCGT.
17 A26. Because the four existing 138 kV lines are insufficient to carry the full load of the Eagle
18
19
20
21
22
23
Valley CCGT, a new 138 kV transmission line of approximately 23 miles will be
constructed from the existing Eagle Valley plant and Pritchard substation point of
interconnection site to the IPL Franklin Township substation located on the southeast side
of Indianapolis, Indiana. The new transmission line will be built on the available tower
line segment of the existing line from the Petersburg substation to Hanna substation that
runs adjacent to Eagle Valley. In addition, the existing 138 kV line from Pritchard
IPL Witness Sadtler-9
1
2
3
4
5
6
Petitioner's Exhibit JAS-l (PUBLIC)
substation to Southport substation (132-21) and the 138 kV line from Prichard substation
to Mooresville substation (132-24) will be upgraded to support the new generating
capacity. At the Mooresville substation a 138kV breaker will be replaced. Also, an
additional 138 kV breaker replacement and bus modifications are needed at the Hanna
substation to accommodate the increased rating of the 138kV line from Hanna substation
to Southeast substation (132-26).
7 Q27. Please describe IPL's analysis of the interconnection facilities and associated costs of
8 the RFP Short List.
9 A27. IPL reviewed the direct interconnection facilities of the RFP Short List to ensure that all
10
11
12
necessary equipment and associated costs were included for each project to allow a safe
and reliable connection to the transmission system in compliance with all applicable
requirements and standards.
13 Q28. What were the results of IPL's analysis of the interconnection facilities and
14 associated costs of the RFP Short List?
15 A28. IPL determined that $_ would need to be added to Bid 10's cost for two new
16
17
18
19
20
21
22
23
345 kV breakers and accessories at the IPLIDuke Gwynneville Substation which are
required to meet IPL Transmission Planning Criteria for a 345 kV substation
configuration. IPL also determined that $_ would need to be added to Bid 11
for the necessary interconnection facilities as no interconnection facilities were included
in their bid. The $_ added to Bid 11 is for a new 345 kV substation which
includes all necessary breakers and a 1 mile loop from the plant substation to the IPL
Petersburg-Hanna Line. No adjustments related to the direct interconnection facilities
were necessary for the other two projects as it was determined that all necessary
IPL Witness Sadtler-l 0
Petitioner's Exhibit JAS-l (PUBLIC)
1 equipment and associated costs for the interconnection facilities were included in their
2 bids.
3 Q29. Is IPL planning to expand the existing substation or construct a new one to
4 accommodate the CCGT at Eagle Valley?
5 A29. IPL determined that a new substation will be safer, less congested, and less costly to
6 construct and operate than renovating the existing substation. The existing Pritchard
7 substation at Eagle Valley would need to be substantially renovated to enable
8 interconnection of the new Eagle Valley CCGT.
9 Q30. What are the anticipated construction costs to build the new transmission line,
10 upgrade the existing transmission lines and for the new substation for the Eagle
11 Valley CCGT?
12 A30. The following table details the estimated $_ cost of the new substation at
13
14
15
16
Eagle Valley, the cost to both move and upgrade existing transmission lines and
termination equipment at the Pritchard Substation and the cost of the new transmission
line from Martinsville to Indianapolis and other associated cost to support the new
CCGT.
IPL Eagle Valley CCGT Plant I MISO Interconnection Request GI J238
1. New 138 kV substation and re-
3. New 23.0 mile IPL Pritchard - Franklin Township 138 kV Line and communications for contro etc.
4. New IPL 138 kV Breaker and accessories at Franklin Township Sub for New Line
5. Upgrade 15.7 mile 132-24 IPL Pritchard - Mooresville 138 kV Line for clearance
IPL Witness Sadtler-ll
1
2
3
4
5
6
Petitioner's Exhibit JAS-l (PUBLIC)
6. Upgrade 21.6 mile 132-21 IPL Pritchard - Southport 138 kV Line for clearance mitigation, Honey Creek 3-way disconnect switch,
terminal 7. Upgrade IPL 138 kV Hanna Sub to mitigate Hanna - SE 138 kV
Line loading with terminal equipment and line re-connected to the bus TOTAL TRANSMISSION AND SUBSTATION COSTS
As shown in Witness Guletsky's testimony, the $_ for the substation, Item 1 is
included as part of the EPC cost estimate. The remainder of the transmission costs
($_), Items 2-7 are included as part of Owner's costs as identified in Witness
Crawford's testimony. The network upgrade cost, Item 3-7 are shown in Witness
Martin's testimony and was assessed from the Power Transfer Study results.
7 Q31. Are the transmission upgrades and associated costs determined by ABB for the
8 Eagle Valley CCGT and the RFP Short list projects reasonable estimates of the
9 upgrades and costs that would result from the MISO process?
10 A31. Yes. The study methodology and approach used by ABB is substantially similar to that
11 used by MISO. Preliminary results from the MISO Interconnection request 1238 studies
12 for the Eagle Valley CCGT have identified the same upgrades as the ABB studies.
13 Therefore, the associated costs from ABB' s study should closely match the results of the
14 MISO study.
15 Q32. Please discuss the Company's timeline projections associated with the necessary
16 transmission construction and upgrades it has identified.
17 A32. Design engineering of this project will begin in the spring of2013. Detailed engineering
18 and procurement is planned to commence in April 2014, shortly after the anticipated date
IPL Witness Sadtler-12
1
2
3
4
Petitioner's Exhibit JAS-l (PUBLIC)
of securing CPCN approval. Construction of the transmission upgrades will take place in
parallel with the construction of the Eagle Valley CCGT and are expected to be
sufficiently complete to allow back-feed power to the Eagle Valley CCGT for testing and
commissioning by May 30, 2016. All transmission upgrades and construction are
5 planned to be completed in time to allow the Eagle Valley CCGT to achieve an April
6 2017 commercial operations date.
7 Q33. Will any of the identified costs be eligible for cost-sharing with other MISO
8 members?
9 A33. It may be possible that a small portion of these costs will be eligible for cost sharing with
10 other MISO members but IPL does not have sufficient information to make that
11 assumption at this time. If any cost sharing does occur, the benefit of the reduced costs
12 will be utilized for the benefit of the IPL customers. However, IPL does not believe these
13 costs will be eligible for cost sharing because the interconnection customer is normally
14 assessed these costs based on MISO cost sharing procedures.
15 Q34. What is the significance of the Harding Street 5 & 6 Refueling on transmission
16 reliability?
17 A34. Witness Crawford explains the rationale, timing and process to convert the 200 MW
18
19
20
21
22
23
Harding Street Generating Units 5 & 6 from coal as the primary fuel to natural gas as the
primary fuel. In addition to the capacity benefits associated with approximately 200 MW
of generating capability, the IPL 138 kV transmission system benefits include voltage
support by maintaining the existing dynamic volt-ampere reactive ("VAR") power
capability during contingency conditions and frequency response in the IPL service
territory. Continued utilization of Harding Street Units 5 & 6 provides operational
IPL Witness Sadtler-13
1
2
3
4
5
Petitioner's Exhibit JAS-l (PUBLIC)
flexibility for planned and unplanned outages on the transmission system and/or for
planned and unplanned outages to the larger coal and gas-fired generation in the IPL
service territory. This flexibility allows IPL to offer its own generation with low
congestion costs into the market instead of relying on MISO to dispatch higher cost
generation to alleviate operational issues which benefits IPL customers.
6 Q35. Are there any transmission upgrades necessary as part of the Harding Street 5 & 6
7 Refueling?
8 A35. No. After the refueling conversion, Harding Street 5 & 6 will continue to use the existing
9 interconnection facilities.
10 Q36. Would upgrades be required if Harding Street 5 & 6 are not refueled?
11 A36. The MISO interconnection application and studies were based upon refueling of Harding
12 Street units 5 & 6. Therefore, additional studies and fees would be needed by MISO to
13 evaluate this option. In lieu of MISO studies, IPL has performed similar studies to
14 determine the transmission implications. Based upon our preliminary studies, we believe
15 additional transmission/substation equipment would be required to support an
16 incremental 200 MW of import capability from the 345 kV system into the 138 kV IPL
17 load zone if Harding Street 5 & 6 were retired.
18 Q37. Is it necessary for the Harding Street 5 & 6 Refueling project to go through the
19 MISO interconnection process?
20 A37. No. Harding Street 5 & 6 will continue to use the existing interconnection with similar
21 output capability from each unit; therefore, it is not necessary to go through the MISO
22 interconnection process.
IPL Witness Sadtler-14
Petitioner's Exhibit JAS-l (PUBLIC)
1 Q38. Does this conclude your prefiled direct testimony?
2 A38. Yes, at this time.
INDSOI l408470v3
IPL Witness Sadtler-I5
VERIFICATION
I, James Sadtler, DirectOl' of Transmission Field Operations for Indianapolis Power &
Light Company, affirm under penalties of pmjury that the foregoing representations are true and
correct to the best of my knowledge, information and belief,
~-?-n~~--~Sadtler
,J
Dated: August~, 2013
VERIFIED DIRECT TESTIMONY
OF
CRAIG JACKSON
Petitioner's Exhibit CJ-l
ON BEHALF OF
INDIANAPOLIS POWER & LIGHT COMPANY
CAUSE NO. 44339
Petitioner's Exhibit CJ-l
VERIFIED DIRECT TESTIMONY OF CRAIG JACKSON ON BEHALF OF
INDIANAPOLIS POWER & LIGHT COMPANY
1 Q1. Please state your name, employer and business address.
2 AI. My name is Craig Jackson. I am employed by The Dayton Power and Light Company
3 ("DP&L"), 1065 Woodman Drive, Dayton, Ohio, 45432.
4 Q2. What is your position and professional relationship with Indianapolis Power &
5 Light Company ("IPL" or "Company")?
6 A2. I am the Director, Vice President, and Chief Financial Officer of AES US Services, LLC.
7 AES US Services, LLC is the AES Strategic Business Unit ("SBU") that provides
8 services for IPL, and other AES affiliates, pursuant to an Affiliate Services Agreement
9 filed with the Indiana Utility Regulatory Commission ("IURC").
1 0 Q3. Please describe your duties as Chief Financial Officer.
11 A3. In my current position, I report to the President of the SBU who is also CEO of IPL. I
12 have direct responsibility and oversight for the accounting, tax, financial planning,
13 treasury, risk management, and internal audit functions oflPL and other AES affiliates.
14 Q4. Please summarize your educational and professional qualifications.
15 A4. I received a Bachelor of Science degree in Business Administration from Bloomsburg
16 University in 1996. I also earned a Master of Business Administration degree in Finance
17 from Wright State University in 2001.
18 Q5. Please summarize your prior work experience.
19 AS. I joined DP&L in February 2000 as a Financial Analyst, Corporate Modeling. In
20 December 2002, I accepted the position of Team Leader, ISO Settlements, with PPL
IPL Witness Jackson-l
1
2
3
4
5
6
Petitioner's Exhibit CJ-l
Corporation. In June 2004, I returned to DPL as Manager, Financial Planning and
Analysis, reporting to the Chief Financial Officer. From June 2004 to May 2012, I was
promoted through several positions of increasing responsibility within the Treasury
organization at DP&L, the last of which was as Vice President and Treasurer.
Prior to joining DP&L in February of 2000, I served in the United States Air Force ("Air
Force") as a Finance Technician. I began my service with the Air Force in May 1996.
7 Q6. Have you testified previously before this Commission?
8 A6. No.
9 Q7. What is the purpose of your testimony in this proceeding?
10 A7. The purpose of my testimony is to support the Company's proposed accounting and
11
12
13
14
15
16
17
18
ratemaking treatment presented by IPL Witness Cutshaw. My testimony explains the
impact IPL's construction of a new combined cycle turbine ("CCGT") at the Eagle
V alley generating station ("Eagle Valley CCGT") and refueling of Harding Street Station
Units 5&6 (collectively, the "Projects") will have on IPL's financial strength and on
IPL's credit ratings. I also discuss the benefit to customers to maintaining the
Company's ratings and address how earnings erosion can adversely affect the Company's
credit rating and otherwise strain resources. Additionally, I identify the tax benefits that
will be realized as a result of the Eagle Valley CCGT option.
19 Q8. What are IPL's financial objectives?
20 A8. At a high level, IPL seeks to maintain the financial strength of an investment grade utility
21
22
so that we can deliver reliable service at a reasonable cost to our customers. Maintaining
this investment grade credit profile is important to ensure we have reliable access to the
IPL Witness Jackson-2
1
2
3
Petitioner's Exhibit CJ-l
credit markets at attractive interest rates during all types of economic cycles. This in turn
provides the ability to meet our financial obligations during periods of heavy capital
expenditures.
4 Q9. What are IPL's capital needs associated with the construction of the Replacement
5 Generation Projects?
6 A9. IPL projects that its capital expenditures excluding Allowance for Funds Used During
7
8
Construction ("AFUDC") associated with the construction of the Replacement
Generation Projects will total approximately $667 million through 2017.
9 QIO. Please discuss how IPL plans to finance the construction of the Replacement
10 Generation Projects.
11 A10. IPL plans to finance the projects in a manner that is consistent with its targeted credit
12
13
14
15
16
ratings and capital structure. Funding for the Replacement Generation Projects will come
from three primary sources: (1) secured or unsecured debt issued by IPL; (2) operating
cash flow from IPL; and (3) equity investments from IPALCO Enterprises, Inc., IPL's
parent. Tax-exempt debt may also be considered as a component of (1) above to the
extent that a portion of these Projects qualify for this type of financing.
17 Q11. Please explain why it is important for the Company to maintain its investment grade
18 credit rating.
19 All. As previously explained, the capital needs associated with the construction of these
20
21
22
projects are substantial and as such cannot be funded through internally-generated funds
alone. These funding needs are compounded by the capital necessary to comply with the
Utility Mercury and Air Toxics Standards ("MATS") requirements as outlined in our
IPL Witness Jackson-3
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
Petitioner's Exhibit CJ-l
request for a Certificate of Public Convenience and Necessity in Cause No. 44242
currently pending before the Commission. Based on supplemental testimony filed in
early January, the capital expenditures for the Utility MATS requirements are estimated
to be $511 million through 2016, excluding AFUDC and removal costs. By following the
Company's plan for funding the Replacement Generation Projects, IPL should have ready
and flexible access to the capital markets and should be able to maintain its current
capital structure, and therefore its investment grade ratings. However, IPL will have
lower credit metrics until it receives recovery of the costs through retail rates. Such
lower metrics will increase the risk that IPL's investment grade credit rating is
downgraded. This will be more fully described later in my testimony. The specific
accounting and ratemaking relief proposed by Witness Cutshaw is also necessary to
support this construction program and maintain IPL's financial strength. Without ready
and flexible access to the capital markets and a supportive ratemaking framework, IPL
would not be able to support this construction program. As a result, IPL's financial
strength and flexibility would decline and as discussed below this would adversely affect
customers.
17 Q12. Please discuss the impact to the Company and its customers if IPL's investment
18 grade rating is not maintained.
19 AI2. Financial strength and flexibility provide the framework for operational effectiveness
20
21
22
which is necessary to provide safe and reliable service to customers at a reasonable cost.
A non-investment grade rating would lead to an increase in overall financing costs and
result in a higher cost of capital. Customers would be adversely affected because higher
IPL Witness Jackson-4
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
Q13.
A13.
Petitioner's Exhibit CJ-l
capital costs lead to higher rates for electric serVice and strain resources that could
otherwise be utilized to meet our customers' ongoing need for reliable electric service.
Please describe the credit rating process and the key factors analyzed by the three
major credit rating agencies.
Credit ratings reflect a credit rating agency's independent judgment of the Company's
credit worthiness and its ability to meet its debt obligations. Credit committees at each
agency determine the ratings of a company based on certain quantitative and qualitative
measures. These factors are used to assess the financial and business risks of fixed
income issuers. Both Fitch Ratings ("Fitch") and Standard & Poor's ("S&P") delineate
investment grade as any rating equal to "BBB-" or above. Moody's Investors Service
("Moody's") delineates investment grade as any rating equal to "Baa3" or above. Non
investment grade ratings at Fitch and S&P are "BB+" or below and "Bal" or below at
Moody's.
Qualitative factors differ somewhat at each of the rating agencies but generally are
related to business risk such as regulation, the ability to recover costs and earn authorized
returns, and fleet diversification. At S&P, these qualitative factors are referred to as the
Business Risk Profile and are rated on a scale from excellent to vulnerable.
Since most electric utilities are highly capital intensive, financial strength and liquidity
are key quantitative factors in determining long-term viability. Over the last several
years each of the rating agencies has become more transparent in their methodologies for
determining financial strength and liquidity. For example, S&P views the following three
financial measures (or Financial Risk Indicative Ratios) as the most important to its
IPL Witness Jackson-5
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
Q14.
A14.
Petitioner's Exhibit CJ-l
analysis of financial risk: 1) Funds from Operations ("FFO")/ Debt; 2) Debt/Earnings
before Interest, Taxes, Depreciation and Amortization ("EBITDA"); and 3) Debt/Capital.
As a part of its methodology, S&P considers a combination of quantitative and qualitative
factors in a Business and Financial Risk Profile Matrix. The Financial Risk Profile
category of a company is determined by the results of the ratios analysis ("Financial Risk
Indicative Ratios") as mentioned in the financial measures above; and is rated on a scale
of six measures from minimal to highly leveraged. The weaker the Business Profile
category, the stronger the Financial Risk Indicative Ratios must be in order to maintain
an investment grade rating.
The discussion above has focused on S&P and its rating methodology. Moody's and
Fitch employ similar methods in their ratings determinations, although the quantitative
calculations and weightings along with qualitative measures may be slightly different.
Can you expand on the regulatory factor mentioned above and your thoughts on its
importance in the credit rating process?
Yes. Regulation is a key factor in the credit rating process at all three credit rating
agencies. Predictability, full and timely cost recovery and a regulatory environment
supportive of a utility's financial strength are key credit considerations. A utility
operating in a stable, reliable, and highly predictable regulatory environment will be
scored higher than a utility that operates in an unstable, unreliable or highly unpredictable
regulatory environment. To that point, S&P recently revised the regulatory assessment of
Indiana downward from "More Credit-Supportive" to "Credit-Supportive." It is
unknown at this time whether this change in assessment will have a negative impact on
IPL's ratings.
IPL Witness lackson-6
Petitioner's Exhibit CJ-l
1 Q15. Please discuss IPL's current credit ratings.
2 A15. As of the date of this pre filed testimony, IPL's credit ratings by the credit rating agencies
3 are as follows:
Moody's Investors Service Standard & Poor's Fitch Ratings
Corporate Credit Baa2 BBB- BBB-Rating/Issuer Rating Secured Debt A3 BBB+ BBB+
Unsecured Debt Baa2 BBB- BBB
4
5 Q16. Please describe the potential impact the construction of the Replacement Generation
6 Projects may have to the Company's investment grade credit ratings.
7 A16. As discussed previously, IPL's credit ratings are expected to stay at investment grade if
8 the rating agencies continue to view Indiana's regulatory framework as supportive and if
9 earnings erosion from these large capital projects is avoided. IPL Witness Cutshaw
10 discusses the specific accounting and ratemaking relief needed to maintain a supportive
11 framework.
12 However, IPL's credit metrics will be lower for a period of time as a result of the heavy
13 construction related to the proposed projects in this proceeding compounded by the
14 construction expenditures necessary for utility MATS compliance, until recovery through
15 rates is granted. This could put our credit ratings at risk for downgrade. However, we
16 believe the rating agencies will look through the temporary time period of lower credit
17 metrics, as ratios recover nicely in later years when cash flow measures grow stronger
18 and earnings erosion is avoided as recovery of costs is achieved through supportive
19 ratemaking.
IPL Witness lackson-7
Petitioner's Exhibit CJ-l
1 Q17. Is it easy for a company that has been downgraded to regain its prior credit rating?
2 A17. No. It is not easy for a company that has been downgraded to regain its prior credit
3
4
5
6
7
rating. In this volatile economic climate it is easier for a utility's ratings to decline as a
result of a deficiency than it is for a company's rating to increase once that deficiency has
been remedied. In other words, a company's credit rating can decline quickly, but it
takes longer for the rating to increase as rating agencies need to see an improvement in
metrics over a period of time before granting an upgrade.
8 Q18. Please describe the financial analysis related to credit worthiness conducted by the
9
10
Company in light of Standard & Poor's methodology related to long-term power
purchase agreements.
11 A18. S&P views power purchase agreements as fixed, debt-like obligations of a utility and as
12 such has determined that they should be included in the calculation of financial metrics
13 on which they base a company's credit worthiness. This method treats fixed capacity
14
15
16
payments as if they were a part of the company's permanent capital structure by
calculating the present value of the fixed (capacity) portion of the annual payment,
discounted at the utility's average cost of debt, and multiplied by a risk factor.
17 Q19. Please discuss the concept of the risk factor in more detail.
18 A19. S&P's risk factor reflects the probability of recovery that power purchase agreement
19
20
21
22
costs will be recovered through rates. This factor varies by state statute or regulatory
policy and can range from 0% to 100%. The greater the certainty of recovery the lower
the risk factor, which results in a lesser amount of debt imputed onto the utility's balance
sheet for each power purchase agreement.
IPL Witness lackson-8
Petitioner's Exhibit CJ-l
1 Q20. Are you knowledgeable as to the risk factor assigned to Indiana?
2 A20. Based on conversations with S&P's staff, the risk factor most likely assigned to Indiana
3
4
5
is 25%, reflecting high confidence of recovery through rates for power purchase
agreements. This risk factor, of course, is re-evaluated each time an analysis is done by
S&P and is subject to change.
6 Q21. Please discuss other adjustments made by S&P related to its evaluation of power
7 purchase agreements.
8 A21. S&P also imputes interest and depreciation expense. Imputed interest is based on the
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
Q22.
A22.
amount of debt imputed at the embedded debt cost of the utility. Imputed depreciation is
based on the difference between the fixed capacity payment and the amount of imputed
interest for the year.
Describe the outcome of this analysis as you evaluated the projects competing with
the Eagle Valley CCGT option.
The analysis indicated that the key metrics used to determine IPL's credit rating all
deteriorated using S&P's methodology for the two short-listed tolling projects. However,
these key metrics did not deteriorate significantly enough to trigger an expected
downgrade, and therefore no increased interest expense was expected if IPL were to enter
into either of the proposed tolling agreements. As such, no quantitative adjustment was
made to either tolling project in assessing the Present Value Revenue Requirement
("PVRR"). This nevertheless remains an important qualitative consideration as entering
into either of the tolling agreements would negatively impact key credit rating metrics
and would leave nearly no margin for any other negative event that could result in a
credit rating downgrade.
IPL Witness Jackson-9
Petitioner's Exhibit CJ-l
1 Q23. Have you identified any tax incentives or other benefits associated with the
2 construction and proposed financing plan for the Eagle Valley CCGT option?
3 A23. Yes.
4 Q24. Please identify the tax incentives or other benefits.
5 A24. IPL has secured a ten-year real and personal property tax abatement with the Morgan
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
County Economic Development Corporation. Discussions are on-going to consider
establishing a tax increment finance ("TIF") district; however at this time it is unknown
as to whether this will occur.
The ten-year real and personal property tax abatement represents the maximum allowed
by law and will begin when the plant goes into service. The estimated property tax
abatement savings for a $631 million plant is approximately $23.5 million. This
abatement is unlike declining abatement approaches that start with a 100% abatement that
steadily declines over a ten-year period. We chose to use a ten-year flat 60% abatement.
This approach allows Morgan County to begin immediately receiving additional property
tax revenue and also provides IPL with a reduction in property tax expense.
If the TIF District is established, it will encompass the site of the new facility in Morgan
County. The County has proposed to pledge up to $2 million in TIF assistance for
infrastructure and investment at the plant site.
Morgan County also plans to offer up to $1,500 per employee for training. The training
funds will be in the form of a reimbursable grant to IPL.
21 Q25. Does this conclude your prepared verified direct testimony?
22 A25. Yes, at this time.
IPL Witness J ackson-l 0
Petitioner's Exhibit CJ-l
INDSOI 1408476v3
IPL Witness Jackson-II
VERIFICATION
I, Craig Jackson, Director, Vice President, and Chief Financial Officer of AES US
Services, LLC, affmn under penalties of peJjury that the foregoing representations are true and
correct to the best of my knowledge, information and belief.
c(d~ Dated: August S , 2013
Petitioner's Exhibit KWC-l (PUBLIC) REVISED
I AI2. We will plan to seek recovery for portions of the Projects not timely recovered in a future
2 rate proceeding.
3 IV. IPL WITNESSES
4 Q13. Please identify the other witnesses and the subject matter of their respective
5 testimony offered by IPL in support of its Petition.
6 Al3. IPL's evidence includes testimony and evidence from the following witnesses:
Herman N. Schkabla
Richard L. Benedict
Paula M. Guletsky, Sargent & Lundy
James Sad tier
Dennis C. Dininger
IPL's integrated resource planning process and current IRP, IPL's need for additional generation and discussion of how IPL's proposal is consistent with IPL's IRP, Present Value Revenue Requirement analysis of the proposed Projects and the short listed alternatives, economic analysis of bringing small coal units into compliance with current/future environmental requirements, IPL's load forecast and the State Utility Forecast Group's ("SUFG's) "Indiana Electricity
. ections: The 2011 Forecast" Discusses the Request for Proposal conducted to identify and analyze CCGT options and the review and analysis of short listed CCGT and describe the CCGT site Eagle Valley CCGT Engineering, Procurement and Construction ("EPC") cost estimate, Harding Street 5&6 Refueling cost estimate, cost estimate of bringing Harding Street 5&6 into compliance with current/future environmental uirements Transmission system connection and upgrades, Interconnection issues Fuel mix and source identification, Midwest Independent Transmission System Operator, Inc.! ("MISO") issues, natural gas
and s
J On April 26, 2013, MISO changed its name to the Midcontinent Independent System Operator, Inc. Due to the timing of this name change, IPL's Case-In-Chief reflects the prior name.
IPL Witness Crawford - 6
Petitioner's Exhibit KWC-l (PUBLIC) REVISED
1 has recently contracted to purchase about 100 MW of energy from solar facilities located
2 throughout its service territory pursuant to its Rate REP Tariff. As discussed by IPL
3 Witness Allen, IPL also uses demand-side management, which currently represents
4 approximately 62.7 MW of capacity, to meet the need for electricity within our service
5 area.
6 All of these resources are discussed in IPL's most recent IRP, a copy of which is included
7 as an exhibit to IPL Witness Schkabla's testimony.
8 Q17. How does IPL deliver this electricity to its customers?
9 A17. As more fully described by Witness Sadtler, electricity is delivered to IPL customers over
lOa network of transmission and distribution lines. IPL is also a member of and follows the
11 rules of the MISO as detailed in Witness Dininger's testimony.
12 VI. NEED FOR PROPOSED PROJECTS
13 Q18. What causes IPL's need for additional generation resources?
14 A18. The need for new generation resources stems from IPL's obligation to provide reasonably
15 and adequate electricity to meet the current and future needs of its retail customers.
16 Environmental Protection Agency ("EPA") rules, as described in IPL Witness Oliger's
17 testimony, will directly or indirectly result in the shutdown or refueling of up to six (6)
18 older coal units and five (5) associated oil/diesel-fired units. In addition, unit
19 obsolescence and falling natural gas and market prices have contributed to the decision to
20 retire these units. In total, these eleven (11) units comprise 607 MW of capacity (MISO
21 Installed Capability rating). Significant retrofitted controls would be required on the six
22 older coal-fired units as discussed by Witnesses Guletsky & Schkabla in order to comply
IPL Witness Crawford - 9
1
2
3
Petitioner's Exhibit KWC-l (PUBLIC) REVISED
were not refueled, as described by Witness Sadtler's testimony. Finally the combination
of the Harding Street 5&6 Refueling and the Eagle Valley CCGT match well with IPL's
capacity needs.
4 Q25. When does IPL need to bring the Projects on line?
5 A25. Because the six (6) small coal units do not comply with the MATS Rule, they are
6 currently required to shut down by April 2016 and the timing of the new Projects has
7 been developed with this fact in mind. However, IPL is also pursuing potential options to
8 keep the Eagle Valley units in service through early 2017.
9 The Harding Street Units 5&6 Refueling has been developed to allow completion of the
10 conversion from burning coal to burning natural gas by April 2016. This will allow the
11 units to meet the April 2016 deadline and integrate into the overall outage schedule at
12 Harding Street Station. This schedule also allows the units to be on-line during the
13 period of peak summer demand.
14 The schedule for the Eagle Valley CCGT includes approximately 12 months for
15 engineering and to procure long-lead items and approximately 24 months of major
16 construction on site. Thus, if the CPCN is issued no later than April 2014, IPL plans for
17 commercial operation of the Eagle Valley CCGT in April 2017. As in the case of
18 Harding Street Station Units 5&6, this commercial operation date is tied to being on-line
19 before the beginning of the period of peak summer demand. A delay in issuance of a
20 CPCN beyond April 2014 will impact the ability of IPL to achieve commercial operation
21 in time to be accredited for 2017 capacity needs.
22 VII. CCGT PROJECT
IPL Witness Crawford - 15
Petitioner's Exhibit KWC-l (PUBLIC) REVISED
1 Q26. Please summarize IPL's proposal to construct a new CCGT at the Eagle Valley site.
2 A26. IPL proposes to build the Eagle Valley CCGT at its existing Eagle Valley site. The
3 proposed CCGT will have a generation capacity of 550-725 MW and is estimated to cost
4 approximately $631 million, not including AFUDC or financing charges. The target in-
5 service date is spring 2017.
6 As explained by Witness Guletsky, the Eagle Valley site is an existing site. IPL has other
7 generating facilities at this site which will be retired-in-place prior to the commercial
8 operation of the Eagle Valley CCGT. IPL has been active on this site for nearly sixty
9 years and has strong local support for the continued use of the site for power generation.
10 This is reflected in the fact that the Morgan County Board approved a 10-year tax
11 abatement if the proposed Eagle Valley CCGT is built. As described by Witness
12 Benedict, this site has water, land, and transmission, as well as good access into the
13 MISO market and close proximity to IPL customers. Additionally, the site has access to
14 interstate and intrastate pipelines within a 12-mile radius.
15 As explained by Witness Sadtler, an additional 13 8 kilovolt ("kV") transmission line will
16 need to be built. The proposed transmission line would run approximately 23 miles from
17 the existing Eagle Valley plant and Pritchard substation point of interconnection site to
18 the IPL Franklin Township substation located on the southeast side of Indianapolis,
19 Indiana. The new transmission line would be built on the spare tower line segment of the
20 existing Petersburg substation to Hanna substation transmission line that runs adjacent to
21 the Eagle Valley site.
22 Q27. Please identify the major components of the Eagle Valley CCGT.
IPL Witness Crawford - 16
1
2
3
4
5
Petitioner's Exhibit KWC-l (PUBLIC) REVISED
through the Definitive Planning Process ("DPP") stage. It is projected that the
interconnection agreement will be signed before the end of 2013 as described more fully
by Witness Sadder.
Likewise, IPL filed an air-permit application at IDEM in October 2012. The final air-
permit is expected late in 2013 or early in 2014.
6 Q29. Please summarize the cost estimate of the Eagle Valley CCGT Project.
7 A29. The estimated cost of the construction of the Eagle Valley CCGT is summarized in the
8
9 10
table below in millions of dollars:
EPC Costs (without escalation)
Owner's Costs
Owner's Contingency
Escalation
Total (excludes AFUDC cost)
$476 ....................• ................. -.-• $631
11 Q30. How was the cost estimate developed?
12 A30. As described in Witness Guletsky's testimony, the EPC Cost of the Eagle Valley CCGT
13 is based on a detailed 600+ line item cost build-up prepared by S&L and covered a range
14 of different turbine configurations. IPL and S&L sought budgetary bids for every piece
15 of equipment expected to cost more than $1 million. S&L used the budgetary bids, in-
16 house engineering and recent experience to generate the estimate. In addition, multiple
17 meetings, reviews and revisions took place based on review and input. Multiple meetings
18 were also held with turbine manufacturers (GE, Siemens and Mitsubishi) and EPC
19 contractors (Chicago Bridge & Iron, SNC Lavalin, CH2M Hill and Bechtel) from which
20 capital costs, operating costs, performance characteristics and construction schedules
IPL Witness Crawford - 18
1
2
3
4
5
6
7
Petitioner's Exhibit KWC-l (PUBLIC) REVISED
were secured. Collectively, this body of information was used to generate the Eagle
Valley CCGT EPC cost estimate that would cover the different turbines that might be
used. In order to achieve the reasonably lowest life cycle cost for IPL customers, IPL
intends to conduct an RFP process to establish the Eagle Valley CCGT with the lowest
reasonable cost, reliable turbine configuration.
IPL owner's costs are also included in the budget estimate as part of the project costs.
The Company has used an escalation rate of" per year.
8 Q31. What are Owner's costs?
9 A31. Owner's costs are generally those items that are not expected to be included as part of an
10
11
12
13
14 15 16
17
18
19
20
EPC contract and include the cost of transmission upgrades, the natural gas lateral,
professional services (e.g., Owner's Engineer), taxes, insurance, permitting fees, plant
personnel, project management, contract administration costs, and start-up.
For the Eagle Valley CCGT, the Owner's Costs are as follows in millions of dollars:
Witnesses Sadtler and Dininger will provide further detail regarding the cost estimates
related to the Transmission and Natural Gas Lateral costs. Other Owner's costs include:
(1) equipment spares; (2) mobilization & start-up; (3) permitting, land, legal, &
development costs; (4) Emission Reduction Credits ("ERCs"); (5) insurance; and (6)
project management.
21 Q32. Please describe the Owner's Contingency.
IPL Witness Crawford - 19
1
2
Petitioner's Exhibit HNS-l REVISED
IPL in the summer of2012 to focus on CCGT generation alternatives. The RFP process
is discussed in detail in the testimony of Witness Benedict.
3 Q20. Please describe the next phase of the updated analysis conducted by IPL.
4 A20. Having identified a CCGT as the preferred new resource option, the next phase in the
5 updated analysis was to compare the Eagle Valley CCGT self-build option against the
6 short listed project proposals that resulted from the RFP process described by IPL
7 Witness Benedict in his testimony.
8 Q21. Please describe the analysis process that was used to evaluate the Eagle Valley
9 CCGT against the request for proposals ("RFP") short list alternatives.
10 A21. The Eagle Valley CCGT and the RFP short list units were individually represented in the
11 Midas Gold modeling to determine the relative cost to customers on a comparative PVRR
12 basis. Because of the locational differences of the resource options being evaluated, it
13 was important to appropriately incorporate the transmission cost implications as
14 described in the testimony of Witnesses Sadtler, Adkins, and Martin into the comparative
15 PVRR results.
16 Q22. Please describe how the results of the IPL interconnection facilities study and ABB
17 power transfer study and reactive capability study presented in Witness Sadtler's
18 and Martin's testimony were incorporated into the Midas Gold Model PVRR
19 comparative results.
20 A22. The capital costs for the required transmission facilities identified for each of the CCGT
21 options in the respective studies were included as incremental capital costs for each of the
22 alternatives in the Midas Gold modeling.
IPL Witness Schkabla -13
1
2
3
4
5
6
7
8
9
10
11
12
Petitioner's Exhibit RLB-l (PUBLIC) REVISED
Given that challenge, it was altogether necessary and appropriate to consider locational
factors for various bid proposals. Because IPL' s need for capacity and energy was
prompted largely by the planned retirement of the Eagle Valley and Harding Street units,
IPL issued the RFP with the goal of obtaining resources that could replace, or at least
closely approximate, the system support of the units that were slated for retirement.
Bidders were put on notice that whatever proposal they submitted, it would be
compared with IPL's self-build option of a CCGT that would connect to IPL's 138 kV
transmission system and would likely operate in a 40 percent to 60 percent capacity
factor range. Thus, rather than the RFP respondents simply competing against other
bidders, respondents were also competing against an option available to IPL at the time it
recognized the need for new capacity located on the 138 kV system. In this way, the RFP
established a robust competitive solicitation for new capacity.
13 Q18. Were any adjustments made to the information received from the short-listed
14 bidders from the RFP concerning transmission issues within MISO Zone 6?
15 A18. Yes. IPL engaged ABB/Ventyx to study transmission and deliverability issues related to
16 the short-listed bids from the RFP and the Eagle Valley CCGT. This study evaluated
17 congestion (as detailed by IPL Witness Adkins), and power transfer and reactive
18 capability effects (as detailed by IPL Witness Martin) of the four projects and the Eagle
19 Valley CCGT.
20 Additionally, as discussed by IPL Witness Sadtler, IPL analyzed the
21 interconnection facilities and associated costs of each bid.
IPL Witness Benedict - 8
Petitioner's Exhibit RLB-l (PUBLIC) REVISED
1 A28. Yes. As noted by Witness Schkabla, the Eagle Valley CCGT has the lowest PVRR of the
2 projects evaluated. There are additional qualitative reasons for selecting the Eagle Valley
3 CCGT as noted below.
4 In the case of a 20-year, long-term contract it is difficult to project prices long-
5 term and capture those prices within the confines of a contract. Long-term contacting
6 creates difficulties because either the seller or the buyer is sometimes significantly "out
7 of the money" under the contract as compared to prevailing market prices. Additionally,
8 as we have seen in other relatively recent situations, the congestion picture on the
9 transmission grid can change over time. With a self-build option, potential disputes
10 between buyer and seller regarding congestion and curtailment risk can be avoided.
11 In addition there are imputed debt considerations associated with a long-term
12 contract as discussed by IPL Witness Jackson. While IPL has not applied any
13 quantitative adjustment to either of the two tolling bids due to imputed debt in the PVRR
14 calculation, it is a qualitative consideration as it negatively impacts some of the financial
15 metrics used by Standard & Poor's to establish IPL's credit rating.
16 Both of the tolling bids also placed limits on the number of starts and/or
17 additional costs for exceeding a certain number of starts. Bid 12 imposes a limit of 120
18 starts per year, while Bid 10 imposes additional costs above 100 starts per year and a
19 limit of 200 starts per year. While a quantitative adjustment was not made to the PVRR
20 calculation in either case, it is a qualitative consideration.
21 Finally the Eagle Valley CCGT is more advanced in its development than any of
22 the four bids and has relatively lower development and schedule risk.
IPL Witness Benedict - 15
Petitioner's Exhibit DCD-l (PUBLIC) REVISED
1 A27. Yes. IPL has the requisite financial, technical and managerial ability to provide the
2 service. IPL Witness Jackson describes IPL's plans to finance these projects and the
3 Company's credit ratings. With respect to the technical and managerial ability, IPL has
4 experience managing utility infrastructure and will contract with others to manage the
5 pipeline as necessary to ensure compliance with state and federal regulations.
6 Q28. Does the public convenience and necessity require the provision of the requested
7 service giving consideration to the availability of gas service from any gas utility
8 authorized to serve end use customers within the geographic area covered by the
9 application?
10 A28. Yes. Authorizing IPL to transport natural gas to the Eagle Valley CCOT will support the
11 public convenience and necessity by providing the authorizations necessary for IPL to
12 secure gas for this necessary facility at the most reasonable cost.
13 Q29. Will the public interest be served by the issuance of the necessity certificate?
14 A29. Yes. IPL Witnesses Crawford and Schkabla all explain the need for and importance to
15 IPL's customers of constructing the Eagle Valley CCOT. Issuance of this necessity
16 certificate will enable IPL to supply natural gas to the Eagle Valley CCOT in the most
17 cost effective manner. A certificate will afford IPL the flexibility to transport natural gas
18 across an IPL owned pipeline if that option is the best method for securing gas for the
19 Eagle Valley CCOT.
20 Q30. Does this conclude your prefiled direct testimony?
21 A30. Yes,itdoes.
IPL Witness Dininger-ll
1 2 3 4 5 6 7
8 Q13.
9 A13.
10
11
12
13
14 Q14.
15 A14.
16
17
18
19
20
21
22
23
24
25
26
Petitioner's Exhibit CFA-l REVISED
• Ventyx updated the annual inflation factors for Variable O&M; • Ventyx reviewed the assumptions regarding electric demand, generation
expansion and generation retirements and found them comparable to the Ventyx assumptions from the Spring 2012 Reference Case; and
• Ventyx retired the IPL generating units: Eagle Valley 1-6 and Harding Street 3-4 and also converted Harding Street 5-6 from coal-fired to gas-fired with a limitation on capacity factor.
Why were changes to the MISO database necessary?
IPL has conducted a robust economic analysis of the five generation alternatives using
the Strategic Planning Model. This congestion analysis is designed to augment that
economic analysis. It is critical for an "apples to apples" comparison that the underlying
assumptions be consistent between the Strategic Planning Model economic analysis and
the PROMOD IV Model congestion analysis.
What inputs were provided for the five generation alternatives?
Ventyx received the modeling parameters for each of the five generation alternatives
under consideration: Eagle Valley CCGT, Bid 10, Bid 11, Bid 12, and Bid 13. The
general modeling parameters and respective heat rate curves for the Eagle Valley CCGT
were provided by IPL, while the general modeling parameters and respective heat rate
curves for the RFP generation alternatives were based upon data submitted to IPL by the
project bidders. IPL Witness Martin, from Ventyx's parent company ABB, provided the
transmission network upgrades and IPL Witness Sadtler provided the interconnection
facilities necessary for each of the five generation alternatives. As a result, each of the
five generation alternatives were independently added to the PROMOD IV model's
"business as usual" scenario along with any transmission network upgrades and
interconnection facilities associated with the generation alternative as provided by IPL
Witnesses Martin and Sadtler and described in their testimony.
IPL Witness Adkins -8
Petitioner's Exhibit JLC-l REVISED
1 Q34. How does IPL intend to recover the portion of the Harding Street 5&6 Refueling not
2 timely recovered?
3 A34. We plan to seek recovery in a future rate proceeding.
4 Eagle Valley CCGT Accounting and Ratemaking Treatment
5 Q35. Why is IPL requesting that the Commission authorize the proposed accounting
6 treatment with respect to post-in-service AFUDC and the deferral of depreciation
7 for the Eagle Valley CCGT Project?
8 A35. The request is necessary because of the magnitude of the Project. Unless the requested
9 authorization is obtained, the Company will suffer a severe negative impact on its
10 earnings during the period between the in-service date(s) of the Project and the issuance
11 of an order authorizing recovery of a return on the Project and including depreciation
12 expense thereon in its recoverable operating expenses. The Company will also lose any
13 opportunity to recover the carrying costs of the Project incurred during the interim period.
14 This accounting change is also necessary to assist the Company in attracting permanent
15 capital at reasonable rates as discussed by Witness Jackson.
16 Q36. Can you put the magnitude of the Project into perspective?
17 A36. Yes. As noted in the testimony of Witness Crawford the construction costs for the Eagle
18 Valley CCGT are $631 million (excluding AFUDC), which represents 31.4% of the Total
19 Company Original Cost Rate Base as of December 31, 2012 recently reported on Form
20 PR in the FERC Form 1. And the rate base reflected on Form PR does not yet reflect the
21 $511 million of construction costs (excluding AFUDC and removal costs) which IPL is
22 seeking timely recovery of in pending Cause No. 44242.
IPL Witness Cutshaw-IS
Year
2013
2014
2015
2016
2017
2018
2019
Petitioner's Exhibit LHA - 4 REVISED
Incremental Amount of Energy Efficiency and Demand Savings
(EE Related) Included in IPL Load Forecast
IURC Target {% of IURC Gross Energy Net Incremental
Weather Savings Target Annual Demand
Normalized Sales) {MWh) Reductions {MW)
0.90% 127,351 14 1.10% 156,027 16 1.30% 186,006 17 1.50% 216,018 17 1.70% 248,073 20 1.90% 279,823 21 2.00% 295,594 20
Extension beyond 2019
2020 1.00% 147,572 11
Note: The Demand Savings are only the Demand Savings that are expected to
result from the deployment of energy efficiency programs.
The Load Forecast also assumes a going level of Load Management programs
(ACLM for example) of 67 MW per year.