Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Hydromantis, Inc. Capdet Works Training
StateState--ofof--Art Software for the Design and Preliminary Art Software for the Design and Preliminary Costing of Wastewater Treatment SystemsCosting of Wastewater Treatment Systems
Hydromantis, Inc. Capdet Works Training
CapdetWorks
● ‘Preliminary Design and Costing Tool’ for evaluating WWTP alternatives
● Based on the U.S. EPA CAPDET program.● Hydromantis moved CAPDET to the PC in 1985.● Approximately 200 copies sold to universities,
governments and consultants
Hydromantis, Inc. Capdet Works Training
What Does It Do?
● Designs individual unit processes based on a user specified treatment plant layout
● Costs each unit process● Overriding Capability gives the user
the ability to fine-tune the design and/or costing
Hydromantis, Inc. Capdet Works Training
How does it design ?● EPA Design Algorithms (Originally)● Major changes made in version 2.1 :
Design algorithms based more on influent fractionation (M&E)
Hydromantis, Inc. Capdet Works Training
Design level ● Planning Level Design
± 15 % Capital Cost± 20 % Operation and Maintenance Costs
● To screen various alternatives
Hydromantis, Inc. Capdet Works Training
Costing approach● Unit Costing approach
easier to update costs of each elementeffect of inflation
● Categories of costs:unit process costsindirect project costsdirect project costs
Hydromantis, Inc. Capdet Works Training
LAYOUT SPECIFICATION AND TREATMENT OBJECTIVES
PROCESS DESIGN CALCULATION (ex: tankage, air requirements…)
IDENTIFICATION OF THE MAJOR COSTS (Structural, equipment, O&M)
STRUCTURE SPECIFIED EQUIPMENT POWER REQ. OPERATIONAL(MAN HOUR )
CHEMICAL REQ.
Concrete, Earth, Pipe Works + other
Escalated equipment cost,Cost of installation
ANNUAL O&M COST
Unit Costs
Cost of tank/structure Installed Equipment Cost
CAPITAL COST OF UNIT PROCESS
Maintenance Cost Model Annual Power/Man Power/Chemical Costs
GENERAL AVERAGE COSTS
Hydromantis, Inc. Capdet Works Training
NET PRESENT WORTH● Total NPW = ● Unit Process Construction Cost + ● + Unit Replacement NPW ● + O&M NPW ● – SV NPW ● – Rev. PW
Hydromantis, Inc. Capdet Works Training
PROJECT COST● Total of Unit Process Costs● + Other direct costs :
yard pipinginstrumentationadministrative facilities
● +Land costs
Hydromantis, Inc. Capdet Works Training
PROJECT COST● + Indirect Costs
Engineering FeesAdministrative feesInterest Rate during construction
Hydromantis, Inc. Capdet Works Training
Examples of Applications● Screening of design alternatives based
on cost● Cost to upgrade processes to meet
more stringent effluent criteria
Hydromantis, Inc. Capdet Works Training
BIOLOGICAL REACTOR DESIGN PRINCIPLES IN
CAPDET WORKS
Hydromantis, Inc. Capdet Works Training
Aspects covered● Influent Characterization● Solids mass calculation● Air requirements ● Nutrient requirements● Sludge production
Hydromantis, Inc. Capdet Works Training
Design Principles in CDW: Biological Reactor
● Calculation or Specification of the SRT● Minimum SRT: > 1/(µ - kd)
at the lowest temperaturefor heterotrophs for C removal only
For nitrifiers if nitrification required+ Apply Safety Factor
Hydromantis, Inc. Capdet Works Training
Influent Characterization
● Influent Speciation:VSSin = TSSin * (VSS/TSS)in
ISSin = TSSin – VSSin
Hydromantis, Inc. Capdet Works Training
Influent Characterization
● Biodegradable vs Unbiodegradable Matter
uVSS = F*VSSin (F: unbiod. Fraction)uCODin = 1.5*uVSSin
uSSin = ISSin + uVSSin
bCODin = CODin – uCODin
Hydromantis, Inc. Capdet Works Training
Solids Mass Calculation● Mass of Active Biomass:
M(Xa) = SRTaer*Qin*Yh*BODremoved
(1 + kd,T * SRTaer)● Mass of Endogenous Biomass:
M(Xe) = 0.2*kd*SRTaer*M(Xa)
● Mass of Inert VSS :M(XI) = uVSSin*Qin*SRTaer
Hydromantis, Inc. Capdet Works Training
Solids Mass Calculation● Volatile suspended solids :M(VSS) = M(Xa) + M(Xe) + M(XI)● Inert suspended solids:M(ISS) = ISSin*SRTaer*Qin
● Total mass of solids:M(TSS) = M(VSS) + M(ISS)
Hydromantis, Inc. Capdet Works Training
Reactor Sizing● Reactor volume = Mass of solids
(Solids Conc.)● + Number of batteries, process trains
and tanks in series as a function of flow rate
Hydromantis, Inc. Capdet Works Training
Air requirements● For C Removal only:O2 req. = Qin*(BODremoved)/1000● For C and N removal:O2req = Qin*(BODremoved) + 4.57*Nn
1000
Hydromantis, Inc. Capdet Works Training
Air requirementsOTE = STE*(DOsat – 2)*alpha*1.024(Tw – 20)
9.17Qair = O2 required
(OTE/100)*(1.2*0.21)
Hydromantis, Inc. Capdet Works Training
Nutrient requirements for growth
● Nitrogen: 0.05*BODremoved
● Phosphorus:0.01*BODremoved
Hydromantis, Inc. Capdet Works Training
Sludge Production Calculation
● Sludge total = Vtotal*SSreactor
SRTaer*1000
Hydromantis, Inc. Capdet Works Training
Tutorial 1 – Learn how to…● Build, design and cost a simple layout● See the effect of more stringent
effluent requirements ● Examine the details of design and
costing
Hydromantis, Inc. Capdet Works Training
Tutorial 2 – Learn to…● Customize costing parameters
Units costs, Financial costsCosting IndicesCreate an equipment database
Hydromantis, Inc. Capdet Works Training
Tutorial 3 – Learn to…● Override the physical design● Override the unit process equipment
costs● Override the design safety● Override the blower system
Hydromantis, Inc. Capdet Works Training
Tutorial 4 – Learn to…● Perform a sensitivity analysis:
Plant-wide Process unit
Hydromantis, Inc. Capdet Works Training
Tutorial 5 – Comparing Alternative Designs
● Duplicating a layout● Comparing the costs of different
treatment alternatives● Generating a report