  • Standard and Guidelines for

    MH development

    Mini Grid Support ProgrammeGopal Raj Suwal

    Programme OfficerESAP/AEPC

  • Project Cycle in Initial stageRequest collection

    Desk (GIS) basedVerification

    Field Verification

    Feasible?If YesIf No

    Stop

    Feasible?If YesIf No

    Stop

    Detail Feasibility Study

    Role ofConsultant

    and support from *RRESC/DEES/DEEU

    Desk (GIS)Identification

    Reactive Project

    Support from*RRESC/DEES/DEEU

    Proactive Project

  • Process & Quality Assurance After DFS

    Assessment Appraisal by AC/ MGSP

    Construction Quality Inspection

    Testing Commissioning

    Power output Verification

    One Year Guarantee Check

    Feedback for Design Aspects

    Feedback for Installation Aspect

    Trainings

    DFS Report from PQ consultant

    TrainingsUpgrading standard/guidelines

    Upgrading standard/guidelines

    Technical Approval from TRC

    Subsidy Approval from REF

  • Guidelines for Project at initial Stage Project Identification

    guidelines Field Verification

    Guidelines Guidelines for Preliminary

    Feasibility studies of Micro Hydro Project

  • Standard and Guidelines for MHP Project

    Guidelines for Detailed Feasibility studies of Micro Hydro Project

    Reference Micro-hydropower Standard

  • Micro hydro Design Aids

    Micro hydro Design AIDS Excel Sheet for MHP

    component Design Prototype Drawings

  • Prototype Drawings Examples

  • Social Mobilization Guidelines

    Guidelines for social mobilization of whole project cycle.

    Helps community to understand, own and operate Micro-hydro project and its process

  • Tariff setting Guidelines

    Guidelines for setting electricity Tariff

    Helps Developer/user community to set / revise tariff on basis of project financial status/cash flow

  • Micro Hydro Operator Training Guidelines

    Guidelines for Training of MHP operators

    Provides in-depth technical solution/ support from water to wire for the operator during Micro hydro Operation

  • Micro-Hydro Project Management Guidelines

    Guidelines for Managers of Micro Hydro Project

    Provides guidance from overall management of Micro hydro project to account keeping

  • Catalogue for Micro hydro Components

    Consist of product description and the price lists of Mechanical and electrical component of MHP

    Supports developer/ consultants /installation companies for providing/ selecting cost effective equipment /products / materials

  • End Use Guidelines

    Guidelines for selecting appropriate/ sustainable end use technology on need basis of local market requirement

  • Model Bidding and Contract Document

    Consist of Standard Model Bidding for selecting Installation companies and contract document for project execution

  • Any Questions

  • THANK YOU

    For Further Queries:Ph +977-01-5536843 ;5539391;5539390Mobile:9851104512email: [email protected]

    mailto:[email protected]

    Standard and Guidelines for MH developmentProject Cycle in Initial stageSlide Number 3Guidelines for Project at initial StageStandard and Guidelines for MHP ProjectMicro hydro Design AidsPrototype Drawings Examples Social Mobilization GuidelinesTariff setting GuidelinesMicro Hydro Operator Training GuidelinesMicro-Hydro Project Management GuidelinesCatalogue for Micro hydro ComponentsEnd Use Guidelines Model Bidding and Contract DocumentAny QuestionsTHANK YOU