Stakeholder Information UpdateEdmonton-Calgary 500 kV Transmission Development

December 14, 2005

Introduction

Neil Millar, vice-president, Transmission - AESO

Today’s Meeting - Purpose

• Provide stakeholders with a review of project status and milestones

• Provide end-of-project cost estimates

• Provide an update on South KEG conversion costs and engineering considerations

• Provide an update on Genesee-Langdon line siting and landowner consultation

Agenda

• Introduction and context (Neil Millar, AESO)

• Overview of project status (Fred Ritter, AESO)

• Cost estimate update (Stephen Kane, AltaLink)

• S-KEG engineering considerations (Fred Ritter, AESO)

• Landowner consultation update (Dennis Walters, AltaLink)

• Questions

Edmonton–Calgary Reinforcement

Key Elements

• S-KEG lines conversion to 500 kV (Keephills-Genesee-Ellerslie)

• New 500 kV line (Genesee to Langdon)

Benefits

• Necessary to reliably serve Alberta (Red Deer & south)

• Remove barriers to new generation

• Significant line loss savings

EllerslieGenesee

Keep-hills

Wabamun

RossdaleClover

Bar

SarceeJanet Langdon

BattleRiver

MiloWest

Brooks

Metiskow

Red Deer

Benalto

Beddington

Devon

Cordel

Anderson

Jenner

E. Calgary

Lochend

Progress To Date

• AESO filed Need Identification document in May 2004 with EUB

• EUB hearing in December 2004, closing in January 2005

• EUB Approval of Need received in April 2005

• Transformer amendment filed by AESO October 13, 2005

• AltaLink and EPCOR proposal to provide service (PPS) documents for the South KEG conversion received by the AESO in November 2005

Stakeholder Information UpdateEdmonton-Calgary 500 kV Transmission Development

December 14, 2005

Overall Project Status

Fred Ritter, director, Engineering - AESO

South-KEG 500 kV Conversion

• EPCOR & AltaLink have provided proposals for service & estimates for their respective portions

• AESO is reviewing the proposals & engineering considerations

• AESO expects to direct AltaLink and EPCOR to file facilities applications in January 2006

• Continue work with EPCOR Generation on conversion sequence

EllerslieGenesee

Keep-hills

Wabamun

RossdaleClover

Bar

SarceeJanet Langdon

BattleRiver

MiloWest

Brooks

Metiskow

Red Deer

Benalto

Beddington

Devon

Cordel

Anderson

Jenner

E. Calgary

South KEG Conversion – Schedule

• AESO Need Approved by EUB April/05

• AltaLink begins landowner consultation July/05

• AESO files transformer amendment Oct/05

• Functional specification complete Oct/05

• +20% - 10% Estimate Nov/05

• Proposal to provide service to AESO Nov/05

• Facility application filed with EUB Jan/06

• Permit and license issued by EUB July/06

• Equipment & material procurement July/06

• Construction start Sept/06

• +10% -10% Estimate Nov/06

• In-service date Oct/07

Genesee to Langdon 500 kV Line

• AltaLink line optimization work is well underway

• AESO has participated in AltaLink’s landowner open houses along with the EUB

• Continue developing the functional specification and facility application for mid-2006

EllerslieGenesee

Keep-hills

Wabamun

RossdaleClover

Bar

SarceeJanet Langdon

BattleRiver

MiloWest

Brooks

Metiskow

Red Deer

Benalto

Beddington

Devon

Cordel

Anderson

Jenner

E. Calgary

Lochend

Genesee to Langdon 500 kV Line – Schedule

• AESO Need approved April/05

• AltaLink begins landowner consultation July/05

• Functional specification complete Feb/06

• +20% -10% estimate Apr/06

• Proposal to provide service to AESO Apr/06

• Facility application filed with EUB June/06

• Permit and license from EUB Dec/06

• Equipment & material procurement Jan/07

• +10% -10% estimate March/07

• Construction start June/07

• In-service date Sept/09

Questions?

Stakeholder Information UpdateEdmonton-Calgary 500 kV Transmission Development

December 14, 2005

Cost Estimate Update

Stephen Kane, director, 500kV Project Execution - AltaLink

Genesee to Langdon 500kV Line

Original Needs Estimate $299M

(2004 dollars; includes AltaLink & EPCOR costs)

Adjustments• Escalation (04 to 09 dollars) $ 42M• E&S $ 12M

(EUB approves rate for capital projects)

• AFUDC $ 20M(allowance for funds used during construction)

Current as-spent dollars 2009 in-servicedate as per original needs estimate

$373M

South KEG ConversionOriginal Needs Estimate $40M(2004 dollars; includes AltaLink & EPCOR costs)

Adjustments• Escalation (04 to 07 dollars) $3.0M• E&S $1.5M

(EUB approves rate for capital projects)

• AFUDC $0.5M(allowance for funds used during construction)

Current as-spent dollars 2007 in-servicedate as per original needs estimate

$45M

South KEG Conversion

Current as-spent dollars2007 in-service date $45M

Transformer amendment $12M• Escalation, E&S, AFUDC $1.5M

Brushing & Clearing $1.0M• Escalation, E&S, AFUDC $0.2M

Contingency $2.9M

Current as-spent dollars2007 in-service date $62.6M

South KEG Conversion

Other Engineering Considerations

Communications upgrade $1.0M - $4.5M

Substation development staging $1.0M - $5.0M

Transformer specifications $0.5M - $3.0M

Transmission line terminations $1.0M - $2.5M

Contingency $0.1M - $0.5M

Adjustments (Escalation, E&S, AFUDC) $0.3M - $1.5M

Total Potential $3.9M - $17M

(Range reflects potential scope)

Stakeholder Information UpdateEdmonton-Calgary 500 kV Transmission Development

December 14, 2005

S-KEG Engineering Considerations

Fred Ritter, director, Engineering - AESO

AESO Review of TFO SKEG Proposals

• Engineering: Review project service proposals and associated cost estimates

• Review options with EPCOR Transmission and AltaLink to manage cost

• Detailed engineering studies ongoing

• Work with EPCOR Generation to coordinate with planned generator turnarounds where possible to manage costs

• Power Engineers providing ongoing support

• Planning: Review S-KEG conversion steps to determine if lower cost alternatives are possible through different sequencing of the conversion stages

Direction to AltaLink and EPCOR

• The AESO plans to issue direction to AltaLink and EPCOR Transmission in January 2006 to file a facilities application conditional upon:

• the EUB’s approval of the AESO’s transformer amendment; and,

• a review of AltaLink and EPCOR project proposals and options to manage project costs.

South KEG Conversion

Other Engineering Considerations

• Communications upgrade

• Substation development staging

• Transformer specifications

• Transmission line terminations

Stakeholder Information UpdateEdmonton-Calgary 500 kV Transmission Development

December 14, 2005

Landowner Consultation Update

Dennis Walters, director, Major Projects - AltaLink

Siting Update: Genesee - Langdon 500kV line

• Completed first round of landowner consultation, which started in July 2005 and ended with two weeks of Nov/Dec open houses

• Most common landowner issues for new line:

• EMF

• Compensation

• Visual

• Farming impacts

• Land value

• Corridor

• Evaluating input from 2,000 landowners, plus Environmental Impact Assessment and other work

• Early 2006: Refine route as much as possible and begin second round of landowner consultation

• Mid-2006: Plan to file facilities application

• Expect EUB hearing for N-S 500kV line

• Project schedule based on EUB decision by the end of 2006

Siting Update: Genesee-Langdon 500kV line

Siting Update: S-KEG Conversion

• Completed landowner and agency consultation

• All landowner issues addressed

• Plan to file facilities application with EUB early 2006

• Project schedule based on EUB decision by mid-2006

Questions?

Contacts- Project Information

• Andy Kneubuhler, manager, 500 kV Projects

• 539-2758

[email protected]

• Fred Ritter, director, Engineering

• 539-2616

[email protected]

www.aeso.ca – Transmission > Project Updates> Edmonton to Calgary 500 kV Transmission Development