109
C Cus fo St ons tom C or Distri Stak D Metro take sulta Cost of ibution kehold Decem opolita 9:00am eho ation Servic n Rates der Ses mber 2, an Hote m – 3:45 lde n No ce App s 2015 ssion # 2013 el, Toron 5pm r otes plicatio 5-2019 #4 nto s on 1 Filed: 2013-12-19 EB-2013-0416 Exhibit A-20-1 Appendix E Page 1 of 109

Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

 

 

CCus

fo

Stonstom C

or Distri

Stak

DMetro

takesultaCost of

ibution

kehold

Decemopolita9:00am

ehoation Servicn Rates

der Ses

mber 2, an Hotem – 3:45

lden Noce Apps 2015

ssion #

2013 el, Toron5pm

r otesplicatio5-2019

#4

nto

s on

1

Filed: 2013-12-19 EB-2013-0416 Exhibit A-20-1 Appendix E Page 1 of 109

Page 2: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Stakeholder Consultation Notes    December 2, 2013 

 

 

Hydro One Networks Inc. | 2 

 

Table of Contents  

1.  Welcome by Allan Cowan, Director Major Applications, Hydro One Networks ............................ 4 

2.  Introductions and Agenda by Bob Betts, Facilitator, OPTIMUS | SBR .......................................... 4 

3.  Application Filing Timeline by Allan Cowan, Director Major Applications, Hydro One 

Networks .................................................................................................................................... 5 

4.  Revenue Requirement and Common Costs by Glenn Scott, Director Corporate Planning 

& Finance, Hydro One Networks and Facilitated Discussion by Bob Betts, Facilitator, 

OPTIMUS | SBR .......................................................................................................................... 5 

5.  Core Work Program by Paul Brown, Director Distribution Asset Management, Hydro One 

Networks and Facilitated Discussion by Bob Betts, Facilitator, OPTIMUS | SBR ........................... 9 

6.  Distribution Cost Allocation / Rate Design by Henry Andre, Manager Distribution Pricing, 

Hydro One Networks & Line Loss Study Update by Benjamin Grunfeld, Consultant, 

Navigant Consulting and Facilitated Discussion by Bob Betts, Facilitator, OPTIMUS | SBR ......... 14 

7.  Custom Framework – Adjustments and Reporting by Allan Cowan, Director Major 

Applications, Hydro One Networks and Facilitated Discussion by Bob Betts, Facilitator, 

OPTIMUS | SBR ........................................................................................................................ 19 

8.  Closing Remarks / Next Steps by Allan Cowan, Director Major Applications, Hydro One 

Networks .................................................................................................................................. 30 

9.  Appendices ............................................................................................................................... 31 

Appendix A  Summary of Stakeholder Session ........................................................................ 31 

Appendix B  Key Actions and Considerations .......................................................................... 32 

Appendix C  Meeting Agenda ................................................................................................... 34 

Appendix D  Presentation Slides…. ..... ….………………………………………………………………………………35 

 

The presentation materials used in this Session and background materials can be found at this link: 

http://www.hydroone.com/RegulatoryAffairs/Pages/DxRates.aspx 

2

Page 3: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Stakeholder Consultation Notes    December 2, 2013 

 

 

Hydro One Networks Inc. | 3 

 

Participants 

Stakeholders 

Shelley Grice, Association of Major Power Consumers of Ontario (AMPCO)  Julie Girvan, Consumers Council of Canada (CCC)  Peter Thompson, Canadian Manufacturers & Exporters (CME)  David MacIntosh, Energy Probe Research Foundation  Roger Higgin, Energy Probe Research Foundation  John McGee, Federation of Ontario Cottagers  Indy J. Butany‐DeSouza, Horizon Utilities Corporation  Patrick Hoey, Hydro Ottawa Limited  Ceiran Bishop, Ontario Energy Board (OEB)  Harold Thiessen , Ontario Energy Board (OEB)  Lisa Brickenden, Ontario Energy Board (OEB)  Miriam Heinz, Ontario Power Authority (OPA)  Tom Ladanyi, Ontario Power Generation Inc. (OPGI)  Alfredo Bertolotti, Power Workers' Union (PWU)  Larry Iwamoto, Powerstream Inc.  Vitalika Quenville, Powerstream Inc.  Paula Zarnett, Rogers Cable Communications  Anita Varjacic, Rogers Partners LLP  Don H. Rogers, Rogers Partners LLP  Daliana Coban, Toronto Hydro‐Electric System Limited (THESL)  Kaleb Ruch, Toronto Hydro‐Electric System Limited (THESL)  Patrick McMahon, Union Gas  Mark Garner, Vulnerable Energy Consumers Coalition (VECC) 

 Hydro One Networks Inc.   Susan Frank, Hydro One, Vice President and Chief Regulatory Officer  Allan Cowan, Hydro One, Director – Major Applications (presenter)  Nicole Taylor, Hydro One, Regulatory Analyst  Naiyu Zhang, Hydro One, Regulatory Analyst  Ruth Greey, Hydro One, Senior Regulatory Advisor  Glenn Scott, Hydro One, Director–Business Planning & Support (presenter)  Ryan Lee, Hydro One, Manager‐Financial Plan & Analysis  Paul Brown, Hydro One, Director‐Distribution Asset Management (presenter)  Lyla Garzouzi, Hydro One, Manager – Distribution Development  Henry Andre, Hydro One, Manager ‐ Distribution Pricing (presenter)  Ian Malpass, Hydro One, Director – Pricing  Rob Berardi, Hydro One, Director – Management Accounting 

 Other Participants 

Bob Betts – Facilitator, OPTIMUS | SBR  Jesse Egger – Notetaker, OPTIMUS | SBR  Nick Mirkovic – Notetaker, OPTIMUS | SBR  Steve Klein – Vice President and Practice Manager, OPTIMUS | SBR  Benjamin Grunfeld (Presenter) – Consultant, Navigant Consulting Inc. 

3

Page 4: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Stakeholder Consultation Notes    December 2, 2013 

 

 

Hydro One Networks Inc. | 4 

 

1. Welcome by Allan Cowan, Director Major Applications, Hydro One Networks 

Allan Cowan welcomed the audience to the fourth stakeholder consultation session pertaining to Hydro 

One’s distribution  custom  rate application  for  test years 2015‐2019. Allan explained  that each of  the 

four  sessions have been different, by design,  in order  to  encourage  transparency  and understanding 

surrounding  the rates application.   He noted  that  the  fourth session was unique  from  the perspective 

that Non‐Disclosure Agreements were  required  to  be  signed  by  participants  due  to Ontario  Security 

Commission  requirements  related  to  the  forward‐looking  nature  of  the  financial  material  to  be 

presented  and discussed.   Allan  stated  that due  to  the  requisite  confidentiality,  the notes  and  slides 

from  the session would not be posted until after  the  rate application  is  filed with  the Ontario Energy 

Board (OEB).  He then indicated that OPTIMUS | SBR was present to facilitate the session and take notes 

and proceeded to introduce Bob Betts.  

 

2. Introductions and Agenda by Bob Betts, Facilitator, OPTIMUS | SBR 

Bob Betts thanked the audience and identified this as the fourth of a series of sessions hosted by Hydro 

One to discuss the upcoming application.   

Bob proceeded to review the agenda for the session. He indicated the day’s session would be split in to 

two primary sections, with  the  first  focusing on quantitative  issues  including  forward‐looking  financial 

projections,  specifically  revenue  requirement,  capital  expenditures,  operating  expenses,  corporate 

common  costs,  customer  classification  study  results  and  overall  bill  impacts.    The  second  section  is 

designed  to  focus  on  the  remaining  issues  that  have  not  yet  been  determined  such  as  annual 

adjustments,  off‐ramps,  and  performance  and  outcome measures.    The  afternoon was  designed  to 

foster  an  interactive discussion between Hydro One  and  stakeholders on  these outstanding matters, 

hopefully resulting in a mutually acceptable approach. 

Bob  continued  by  providing  an  overview  of  emergency  procedures.  He  identified  for  everyone  the 

session  is being recorded for note taking purposes only and  indicated the recordings will be destroyed 

once the notes are accepted.   Bob then proceeded to have all attendees  introduce themselves, stating 

their  name  and  the  organization  they  represent  (see  list  of  participants  above).  Following  the 

introductions, Bob reviewed the procedures for the meeting highlighting general meeting etiquette and 

protocols.  He encouraged the audience to feel free to ask questions and provide comments throughout 

the day. 

In concluding his introductory remarks, Bob emphasized the importance of these sessions to Hydro One 

and  their  objective  to  have  full,  open  and  active  dialogues with  stakeholders  on  all  aspects  of  this 

application. He also  indicated the notes and materials would be available from the Hydro One website 

(www.HydroOne.com/RegulatoryAffairs). Bob then welcomed Allan Cowan back to the podium. 

4

Page 5: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Stakeholder Consultation Notes    December 2, 2013 

 

 

Hydro One Networks Inc. | 5 

 

3. Application Filing Timeline by Allan Cowan, Director Major Applications, Hydro One Networks 

Allan Cowan thanked the audience for their attendance and began by explaining that while Hydro One’s 

original plan called  for an application date  in  the  first quarter of 2014,  the Regulatory Affairs group  is 

now  hoping  to  file  on December  19,  2013.   Allan  described  the December  19th  filing  as  a  high‐level 

application sufficient  to satisfy the OEB’s  filing requirements to  initiate  the application process and to 

remove  the  shroud of  confidentiality  associated with  today’s  information.   He  indicated  that  a  filing 

update would follow on about January 31, 2014, which will include all additional details and supporting 

documentation.   

Allan stressed that Hydro One  is determined  to allow all stakeholders to have ample time  to evaluate 

the filings.   Allan went on to state that the two planned filings would not  include 2013 actual financial 

results due to unavailability at the date of filing; they would be filed in a blue page update scheduled to 

be  filed  in May, 2014.   Allan  then  asked  the  audience  if  there were  any questions pertaining  to  the 

expected timeline. 

 

4. Revenue Requirement and Corporate Common Costs by Glenn Scott, Director Corporate Planning &  Finance,  Hydro  One  Networks  and  Facilitated  Discussion  by  Bob  Betts,  Facilitator, OPTIMUS | SBR 

Glenn Scott  introduced himself and explained  that  the  forward‐looking  financial projections he would 

present would be high level in nature, reflecting the first of two stages in the planned filing process. 

Glenn proceeded  to outline  the material he planned  to  review; an overview of  revenue  requirement, 

rate  increases,  issues  surrounding  regulatory  asset  recovery  and  capital  and  OM&A  expenditures, 

including corporate common cost details.  As a reminder to all present, he reviewed the disclaimer slide 

regarding forward‐looking financial information. 

Glenn  then  went  on  to  explain  the  approach  taken  by  Hydro  One  to  the  application  process  and 

presentation  of  financial  projection  estimates.  To  aid  this  process  he  outlined  Hydro  One’s  value 

proposition,  which  includes  five  principle  goals  that  all  relate  to  the  delivery  of  safe,  reliable  and 

affordable service.  The five goals as presented by Glenn are as follows: 

1. Keeping rates low – annual total bill impact at / less than inflation 

2. Improving customer satisfaction and building a trusted partner relationship 

3. Preserving net income 

4. Full visibility on assets and targeted investments to minimized customer impacts 

5. Improving operating efficiencies and cost savings 

5

Page 6: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Stakeholder Consultation Notes    December 2, 2013 

 

 

Hydro One Networks Inc. | 6 

 

Glenn  stressed  the  importance of Hydro One’s data  analysis  capabilities,  allowing  increased  levels of 

cost savings.  He noted that productivity changes discussed in earlier stakeholder sessions were included 

in Hydro One’s business plan and that the bill impact component of the session would show that Hydro 

One’s proposed  increases are very close  to  the  level of projected  inflation.   Glenn also discussed  the 

customer voice  initiative  implemented within the company; reliability of service and overall bill  impact 

were ranked as the two most prevalent issues by customers, with bill impact rated most important. 

Glenn then went on to highlight key figures as they relate to the calculation of 2015 distribution revenue 

requirement.  The deemed capital structure is 60% debt and 40% common equity.  The average cost of 

debt  is 4.79%, while  the average  cost of equity  is 9.71%.   Overall weighted  cost of  capital  (WACC)  is 

6.76%, with  a  rate base  calculated  at  $6,477M.    The  return on  capital  is  $438M,  income  taxes  total 

$55M, cost of service is $918M (comprised of OM&A at $564M and Depreciation of $354M), resulting in 

a revenue requirement of $1,411M.  Glenn noted that rate base reflects audited 2012 financials. 

At this point Roger Higgin, Energy Probe Research Foundation, asked for the 2013 revenue requirement.  

Ryan Lee, Hydro One, answered that the IRM based total was $1,223M. 

Glenn moved  to a bar  chart  showing  the distribution  rate  increases  from 2013  to 2019  inclusive and 

their principle drivers.   From a historical perspective he noted that there was no  increase  in 2012, and 

the Board approved increases in 2013 of 1.4% and 2.6% in 2014.   

Julie Girvan, Consumers Council of Canada, asked why there are still riders in 2015 to 2019 even though 

the smart meters and smart grid riders would have been eliminated by 2015. Ryan Lee explained that 

some of the regulatory accounts have surplus balance and some have deficit balance. In this case, there 

is a net deficit balance of all accounts for disposition and it is to be recovered from rate payers through a 

rider in 2015. 

 

He then pointed to the requested large increase of 11.5% in 2015 indicating that it is made up of 18.5% 

from four increasing components: rate base at 12.8%, OM&A at 2.6%, Rate Reclassification at 1.8% and 

1.2%  for  changing  rate  riders.    Those  increases  are  being  offset  by  7.0%  attributable  to  decreasing 

components such as the discontinuation of Smart Meters and Smart Grid riders.  He noted that the very 

large  rate  base  component  is  a  catch‐up  of  4  years  of  Capex  at  about  $600 Million  per  year  and 

depreciation  at  about  $300 Million.    As  a  result,  the  2015  rate  base  increase  is  approximately  $1.2 

Billion. 

Glenn tried to further clarify the changes by saying that the Smart Meter and Smart Grid components 

will effectively be moving  into  rate base and OM&A,  representing 4.5% of  the  total 12.8%  rate base 

increase and almost all of the 2.6% OM&A increase. 

Hydro One  is  projecting  increases  for  2016,  2017,  2018  and  2019  to  be  7.4%,  3.6%,  3.0%  and  2.9% 

respectively. Glenn pointed stakeholders  to  two  important characteristics of requested rate change  in 

6

Page 7: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Stakeholder Consultation Notes    December 2, 2013 

 

 

Hydro One Networks Inc. | 7 

 

this period, first that rate  increases due to rate base will remain very consistent and reasonably  low at 

between 4.2% and 3.5%, and second that OM&A actually shows a declining trend over the period. 

Glenn then addressed Hydro One’s concern about the customer  impact of the  large 11.5%  increase  in 

2015.  To mitigate that impact, Hydro One is proposing a rate smoothing strategy that would bring the 

2015  increase down  to 7.0%, with  similar  increases of approximately 7.0%  for 2016, 2017, 2018 and 

2019.  

Glenn  then  presented  specific  revenue  requirement  financial  projection  amounts,  reflecting  the 

percentage  gains  and  offsets  described  above.   He noted  that  the  financials  do  not  exhibit  any  rate 

smoothing  impacts, nor do they  include any  load  impact effects.   The highlights pointed out by Glenn 

include OM&A  costs of $564M, $610M, $614M, $604M  and $600M  for 2015, 2016, 2017, 2018  and 

2019,  respectively.   Other  highlights  include  revenue  requirements  of  $,1,367M,  $1,470M,  $1.525M, 

$1,570M and $1,621M for 2015, 2016, 2017, 2018 and 2019, respectively. 

Glenn moved  on  to  discuss  regulatory  asset  figures, which  breaks  down  to  a  total  of  $40.4M  to  be 

recovered in riders over the next 5 years.  The major components as described by Glenn include pension 

($55.6M), OEB ($9.1M), smart meters ($6.5M), tax (‐$20.7M) and the retail settlement variance account 

(RSVA)  (‐$6.2M). He explained  that  the  total amount would  represent approximately $8M  in  riders  in 

each of the next five years. 

Glenn  then  presented  a  bar  chart  similar  to  the  one  presented  earlier  showing  the  projected  rate 

increases, except in this case, it depicted how Rate Smoothing would be used to establish a steady 7.0% 

rate increase in each of the five years from 2015 to 2019.  He pointed that a deferral account that would 

be used to postpone rate recovery from the first year and the under‐recovery and over‐recovery in each 

year,  emphasizing  that  the  balances  in  the  deferral  account  would  be  subject  to  interest  costs  to 

ratepayers until the smoothing efforts were completed. 

Susan Frank, Hydro One, interjected to point out that the Hydro One board struggled with proposing an 

increase as steep as 11.5%.  However, the primary elements contributing to the increase are related to 

accumulation  from  previous  years’  investments  in  capital  assets;  therefore  the  rate  smoothing was 

being proposed as an alternative  rate  recovery method  for  the OEB  to consider, keeping  in mind  the 

mandate of protecting Ontario energy consumers. Susan pointed out that rate smoothing  is a practice 

commonly used in the United Kingdom, exhibiting recognition to the customer desire for stable energy 

bills.    Susan  stressed  that Hydro One was  not  pushing  this  smoothing  strategy  (7%  steady  over  five 

years) over any other rate recovery pattern, and as always was seeking to work in partnership with the 

OEB and Ontario stakeholders.  Another pattern could be higher in the beginning and lower at the end.  

She restated the point made earlier by Glenn that any deferral of the requested 11.5% increase in 2015 

will  invoke borrowing costs and will therefore represent a more costly option to rate payers.   As such 

Hydro One would be open  to proposals  that Rate Smoothing not be applied or  that  it be modified  to 

reduce carrying costs. 

7

Page 8: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Stakeholder Consultation Notes    December 2, 2013 

 

 

Hydro One Networks Inc. | 8 

 

Glenn  added  that  if  Stakeholders  and  the  OEB  accepted  the  Rate  Smoothing  proposed  in  this 

application,  that  the year 2020 would see  this deferral account  recovery drop off entirely, potentially 

leading to lower rates depending on other cost pressures. 

Peter Thompson, Canadian Manufacturers & Exporters, asked how transmission costs contributed to the 

current discussion.  Susan explained that transmission filings will take place in the spring of 2014.   

John McGee,  Federation  of Ontario  Cottagers,  then  asked  if  borrowing  costs  as  related  to  the  rate 

smoothing  process would  have  any  effect  on  the  organization’s  overall  debt  to  equity  ratio.   Glenn 

replied there would be no change to the debt to equity ratio.   

Mark Garner, Vulnerable Energy Consumers Coalition,  then asked  if borrowing  costs would be  in  the 

tens of millions, perhaps even hundreds of millions. Ryan Lee responded that no, the sum would not be 

in the tens of millions, it would be a smaller amount. 

Roger  Higgin  asked  a  question  regarding  the  relationship  between  increased  distribution  rates  and 

actual  revenue  requirement  increased  year  over  year.    Glenn  replied  that  all  references  to  “Rate 

Increase”  in  the previous slides were really referring to revenue requirement  increases, and therefore 

rate increases to individual customer classes could vary from that and Henry Andre would go in to more 

detail later in the session. 

Tom Ladanyi, Ontario Power Generation, remarked that TransCanada had recently received approval for 

a similar deferral account and were allowed  to claim an equity  return on balances, he asked  if Hydro 

One was expecting that on this smoothing deferral account?  Susan replied this was not the plan, Hydro 

One assumed standard regulatory asset treatment. 

Glenn proceeded to summarize OM&A and capital expenditures. He explained that Paul Brown would 

later  speak  to  sustaining, development, operations and  customer  service  for both OM&A and  capital 

expenditures while Glenn would review the somewhat less substantial categories of corporate common 

costs as well as property taxes and rights payment. 

At this point Mark Garner asked  if overall, OM&A and capital expenditure financial projections were  in 

line with previous years.  Glenn replied yes, very much so. 

Glenn  started  by  saying  that  corporate  common  costs  generally move  up  and  down with  the work 

programs, but the Hydro One Board’s emphasis on efficiencies and productivity has  led to the forecast 

for  common  costs  showing  a  decline  from  2015  to  2019,  despite  an  increase  in  Hydro  One  work 

programs.    He  then  described  corporate  common  costs  allocated  to  Distribution,  which  for  OM&A 

expenditures  are  projected  as  $67M  for  2015  and  $62M  for  2016  through  2019.    For  capital 

expenditures, corporate common costs allocated to Distribution range from $85M  in 2015 to $82M  in 

2019, with little deviation in subsequent years.  

Glenn then went into detail with respect to corporate common costs as presented within a transmission 

and  distribution  allocation  context.  He  discussed  that  time  studies  were  conducted  to  derive  the 

8

Page 9: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Stakeholder Consultation Notes    December 2, 2013 

 

 

Hydro One Networks Inc. | 9 

 

allocation of  these  costs. Within OM&A  corporate  common  costs, Glenn noted a  slight movement  in 

transmission and distribution allocations between forecast 2013 and bridge 2014 years in total costs, to 

reflect a one‐time provincial tax credit of $40M for 2013.  He went on to explain the 2014 total sum of 

$144M  is due to a drop  in distribution allocation of $30M  (primarily due to the completion of the CIS 

project) and no repeated tax credit on the transmission side. The 2015 total sum of $137M (decrease of 

$7M) is the result of changes in regulatory costs and an environment provisions reduction. 

Julie Girvan asked Glenn if Hydro One was prepared to “live with” these forecasts for rate purposes and 

Glenn replied “Yes”. 

Glenn concluded by stating that the details of the corporate common costs slides would be available in 

the  second  of  the  two  planned  filings.    The  high  level  information,  as  presented  by  Glenn, will  be 

available in the December filing. 

Bob Betts commented  that  the meeting was moving along very well and  rather  than  taking an early, 

morning‐break he invited Paul Brown to begin his presentation. 

 

5. Core  Work  Program  by  Paul  Brown,  Director  Distribution  Asset  Management,  Hydro  One Networks and Facilitated Discussion by Bob Betts, Facilitator, OPTIMUS | SBR 

Paul Brown began by outlining what he  intended  to  cover during his presentation.   This  included an 

overview of both OM&A and capital expenditures; specifically, sustaining, development, operating and 

customer service details within both expenditure categories. 

Paul  then provided  the  audience with  context  surrounding  the upcoming  application  and Hydro One 

Distribution’s  asset base. Hydro one  serves  approximately  1.2M distribution  customers  comprised of 

both  rural and urban  (mostly  rural)  residential and  small business,  local distribution  companies,  large 

industrial  customers  and  generators  connected  to  the  distribution  grid.  Paul  specifically  noted 

generators as a growing  customer base within  the network. With  respect  to assets, Hydro One owns 

over 120,000 circuit‐km of lines (approximately 3200 feeders), 1.6M poles, 1004 distribution stations, a 

rural system with low density throughout Ontario and a radial system with limited transfer capability. 

Paul explained primary goals, with respect to the management of distribution assets, centered on sound 

investment strategies  to ensure safe,  reliable and efficient power delivery and  to create and enhance 

value for customers. Paul outlined that projects and programs are developed to address customer and 

system growth needs, renew assets at the end of their  life to ensure public/worker safety and service 

continuity and improving reliability and efficiency throughout the organization.  Paul also stressed other 

priorities  include  the modernization of  the distribution  system  to add  customer value and effectively 

responding to unplanned system events. 

Paul then described the four primary components of the OM&A expenditures summary, which  include 

sustaining, development, operations and customer service.  Investments within sustaining are the most 

significant cost driver, with 2015‐2019 test period costs ranging  from $329M to $380M annually.   The 

9

Page 10: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Stakeholder Consultation Notes    December 2, 2013 

 

 

Hydro One Networks Inc. | 10 

 

second most  significant  cost  driver  is  customer  service,  accounting  for  between  $115M  and  $118M 

annually over the five year period under study. 

Paul delved deeper  into  the  sustaining cost category within OM&A expenditures, which  includes cost 

sub‐categories  of  stations,  lines, metering  and  vegetation management.  Specific  cost  items  include 

planned  and  corrective  maintenance,  trouble  call  response,  line  clearing  and  brush  control,  cable 

locates, disconnects and reconnects, environmental and waste management. Costs related  to stations 

are predicted to remain quite stable at $28M to $29M per year over the five year test period, which Paul 

noted is in line with the range of previous years of approximately $26M to $27M. Lines related costs are 

expected  to  rise  slightly, with  a  range  of  $141M  to  $157M  over  the  test  period,  up  from  $148M  in 

forecast year 2013 and $134M in bridge year 2014 in order to address the ramp up in PCB testing of pole 

mounted transformers to meet mandated government PCB requirements. 

Paul  then  explained  that metering  expenditures  rise  in bridge  year 2014  to $19M, up  from $14M  in 

forecast 2013, and are projected to stay constant at $19M throughout the test period, which Paul noted 

was the historical cost  level.   The return to more traditional spending  levels  is due to the dispensation 

that Hydro One  received  from Measurement Canada  for meter  reverifications on  some 2008 – 2014 

meters expires.    

Vegetation management expenditures are ramping up  in 2016 and 2017, then tapering back down for 

2018 and 2019.   The ramp‐up  is required to address a backlog in tree clearing,  in order to allow Hydro 

One  to move  to  an  8‐year  vegetation management  cycle.  Paul  explained  that  a  shorter  vegetation 

management cycle duration has been shown to lower SAIDI although the costs to achieve improvement 

in this cycle are significant. 

Paula Zarnett, Rogers Cable Communications asked  if Hydro One would be filing a benchmarking study 

on  vegetation management.    Lyla  Garzouzi,  Hydro  One,  indicated  that  a  study  would  not  be  filed 

highlighting  that a  study was  filed  in  the EB‐2009‐0096 proceeding and  the  same conclusions are  still 

applicable. 

John McGee, Federation of Ontario Cottagers asked where the savings will come from with respect to 

the 8‐year vegetation management cycle.  Paul indicated that once on an 8 year cycle, we see savings as 

we  go  through  the  next  cycle.  Vegetation management  becomes more  of  a  pruning  small  branches 

effort than a major delimbing and tree removal process. 

Moving  on  from  the  sustaining  component,  Paul  addressed  the  remaining  three  primary  areas  of 

development, operations and customer service.  Development OM&A cost projections range from $15M 

to  $18M within  the  test  period,  in  line with  bridge  year  2014  at  $18M.   Development OM&A  costs 

include  engineering  and  technical  studies  (including  smart  grid  studies),  standards  and  technology 

support and distributed generation connections support. Operating OM&A cost projections range from 

$30M  to $41M over  the  test period, up  from $23M  in  forecast year 2013. The  increase  is due  to  the 

smart  grid  pilot  assets,  such  as  the  DMS,  becoming  part  of  normal  business  and  needing  to  be 

10

Page 11: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Stakeholder Consultation Notes    December 2, 2013 

 

 

Hydro One Networks Inc. | 11 

 

maintained. Operations costs  include operations support, maintenance of operating  infrastructure and 

environmental, health and safety. 

Customer service cost projections are a more significant contributor to OM&A expenditures and range 

from $113M  to $118M over  the  five  year period, down  from $137M  in  forecast 2013 and $134M  in 

bridge  2014.    Customer  service  costs  are  comprised  of  customer  services,  smart  grid  pilot  and 

conservation and demand management.  

Paul  shifted  in  to discussing  smart grid OM&A expenditures. He outlined  that  in an effort  to provide 

some  visibility  to  the  Smart  Grid  OM&A, we  have  created  a  view  for  these  expenditures  that was 

included in the numbers in the slide under Operating and Customer Service expenditure categories. He 

explained  that  the contributing  factors  to  total smart grid expenditures are smart grid pilot costs and 

deployment costs.  Smart grid pilot costs taper over the test period, from $5M in 2015 to $0M in both 

2018  and  2019.  Deployment  costs  increase,  ranging  from  $5M  to  $17M  throughout  the  period,  as 

technologies  that show cost effective benefits will be  further deployed  to deliver customer value and 

operational benefits. 

To conclude  the OM&A section, Paul discussed  the primary drivers of changes  in OM&A costs.   Aging 

assets  and  systemic problems  are  a  significant  factor  in  forecast  costs,  including  issues  such  as  large 

scale testing of transformers for PCB contamination as well as an increased focus on defect corrections.  

Another  significant  factor  to  changes  in OM&A  costs  is  reliability  improvements  and  long‐term  cost 

optimization; a key issue in this area is addressing vegetation maintenance backlogs and maintaining an 

eight year clearing cycle.  At this point Paul explained that he had come to the end of the presentation 

as  it  pertains  to  OM&A  costs,  and  opened  the  floor  to  questions,  before  addressing  the  capital 

programs. 

Harold Thiessen, Ontario Energy Board asked Paul what was the cause of the vegetation maintenance 

backlog mentioned earlier.   Paul explained  that  it  is partially  funding and partially work management, 

which has been exacerbated by several large, unpredicted storms.  

Shelley Grice, Association of Major Power Consumers of Ontario asked Glenn a question about one of 

his slides which  indicated that environmental costs were going down while this presentation  indicates 

they  are  rising.    Ryan  Lee,  Hydro  One  replied  by  saying  that  the  corporate  cost  allocation  for 

environmental  costs  relates  to  amortization  which  is  going  down,  however,  the  environment  costs 

themselves are going up, it is a matter of how it gets classified within the internal structure.  

Paul then moved on to the capital expenditures segment of his presentation, again focusing on the four 

primary cost groups of sustaining, development, operations and customer service.  He started by saying 

that most of the sustainment capital spending pressure facing Hydro One results from the bow wave of 

aging assets. The costs are expected  to  rise  significantly over  the  test period,  ranging  from $208M  in 

2015 to $383M  in 2019.   Sustaining capital expenditures are divided  into Stations, Lines and Metering. 

Principle  cost  sub‐categories  include  station  refurbishments,  mobile  unit  substations,  component 

replacements,  trouble  call  and  storm  damage  response,  large  sustaining  line  projects  and  meter 

11

Page 12: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Stakeholder Consultation Notes    December 2, 2013 

 

 

Hydro One Networks Inc. | 12 

 

upgrades. Paul explained  that Lines and Stations expenditures will be discussed  in more detail shortly 

but  that metering capital expenditures are decreasing  substantially as  the Smart Meter project winds 

down. Offsetting  this will  be  an  upgrade  to metering  telecommunications  infrastructure  that will  be 

completed by 2018.  

Paul then explained that the total fleet of distribution poles is approximately 1.6 million, with an average 

expected  service  life  of  62  years.  Each  year  approximately  20,000  poles  are  installed,  a  figure  that 

includes both new  installations and end of  life  replacement. Paul  stated  that Hydro One  is proposing 

increased funding to address premature decay issues and mitigate the risk of the approaching new wave 

of  poles  reaching  expected  service  life  over  the  period.  Paul  continued  to  explain  that  Hydro  One 

maintains 1,004 distribution and regulating station facilities, with an average expected service life of 50 

years.  The  historical  replacement  rate  is  approximately  four  stations  per  year,  and  Hydro  One  is 

proposing increased funding in this area to manage demographic pressures building up in order to, once 

again, mitigate the risk of the approaching bow wave of stations reaching expected service life over the 

period.  Hydro One believes it must step up the station replacement program to eventually be replacing 

forty stations per year. 

Paul  then  shifted  from  sustaining  to  discuss  development,  which  includes  four  primary  cost  sub‐

categories  including  connections  and  upgrades,  system  capability  reinforcement,  generation 

connections and wholesale revenue meters.   Development capital costs are made up primarily by new 

connections, upgrades driven by load growth, reliability improvements and capital contributions to new 

transmission  connection  capacity.  The  most  substantial  contributors  to  development  capital  are 

connections  and  upgrades  and  system  capability  reinforcement,  ranging  from  $109M  to  $123M  and 

$61M  to  $81M,  respectively,  over  the  2015‐2019  test  period.  Paul  explained  that  system  capability 

reinforcement  expenses  are  relatively  stable  with  the  exception  of  required  payments  (capital 

contributions) that must be paid for Transmission improvements.  Generation connection expenditures 

will ramp down as the amount of connections is expected to decrease. 

Paul then discussed operating and customer service capital. Operating capital is comprised primarily by 

upgrades and expansions  to  the operating  infrastructure and control  facilities, while customer service 

capital is made up primarily by smart grid pilot costs. Paul explained a spike in 2016 operating expenses 

is due  to  the Backup Control Centre new  facility development project.   Paul  then  spoke  to  customer 

service  capital  and  the  declining  spending  in  2017  resulting  from  the winding  down  of Hydro One’s 

Smart Grid pilot project and deployment expenditures will increase as cost effective technologies will be 

implemented.   Paul stressed that Hydro One’s approach embraced cost effective technologies that, by 

design, drive both customer value and operational benefits. 

To conclude his presentation, Paul reviewed the significant drivers to year over year changes  in capital 

costs. He discussed aging assets and systemic challenges  including  the  increasing  replacement  rate of 

wood  poles,  refurbishing  aging  distribution  stations  and  replacing  PCB  contaminated  equipment,  as 

mentioned earlier  in his presentation.   He also again spoke  to reliability  improvements and  long  term 

cost optimization, including the increasing number of line refurbishment projects. 

12

Page 13: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Stakeholder Consultation Notes    December 2, 2013 

 

 

Hydro One Networks Inc. | 13 

 

Mark  Garner  asked  a  question  regarding  the  sustainment  budget,  noting  that  2016  exhibited 

acceleration  in  forecasted  budget  for  lines  relative  to  previous  years.    Paul  responded  that  this  is 

primarily due  to  a necessary  ramp up of  the pole  replacement program.   Mark  then  asked why  this 

acceleration was taking place, and why the ramp up was not conducted in a more uniform manner. Paul 

explained that the plan does ramp up replacement quantities each year so that an additional 5000 EOL 

poles will be replaced per year by 2019.  Mark again asked a question regarding the proposed timeline, 

and why this ramp up did not begin five years prior.  Lyla Garzouzi explained that age demographics play 

an important factor, contributing to a huge spike going back to the 1950’s. At the end of 2011 an asset 

inventory  was  completed,  and  the  detailed  poles  age  information  largely  led  to  the  proposed 

replacement ramp‐up.  She confirmed that ultimately the ramp up is designed to achieve specific yearly 

replacement levels, as mentioned earlier. 

That completed Paul’s presentation.   Bob Betts asked  if  there were any other questions  for Paul and 

there were none at that time so the group took their morning break. 

10:35 AM  Break 

Bob Betts called the meeting back to order and asked if there were any questions that had occurred to 

stakeholders during the break. 

Roger Higgin asked a question  regarding  in‐service assets  in  relation  to  rate base, wondering  if Hydro 

One could mitigate rates by somehow adjusting the revenue requirement for a given year by reflecting 

those projects that failed to go into service in the year in which they were planned to. Susan Frank said 

they were not considering any kind of a variance account to do that and more importantly she was very 

comfortable that they could control this spending to ensure there was no slippage. 

John McGee  then  inquired  as  to  the  dual  filing  strategy  from  the  perspective  of  Intervenors  having 

ample  time  to  review  filings at both  stages. Allan Cowan answered  that Hydro One  is determined  to 

ensure that all parties will have ample time to address the various phases of the application and their 

respective deadlines.  

Susan  then  asked  Allan  to  provide  additional  details  regarding  the  first  planned  filing.  Allan  briefly 

explained that the first stage will include rate base, proposed rates and revenue requirement.  It will not 

contain detailed support for capital expenditure and OM&A, which will be included in the second filing. 

Mark Garner then asked if the OEB will issue a standard notice regarding the appeal process, and when, 

given the dual filing strategy.  Allan responded that discussions are underway, but hopes the notice will 

be provided following the first filing. 

That  concluded  this  round  of  supplemental  questions  and  Bob  Betts  introduced  the  next  presenter 

Henry Andre, and explained that Henry will review cost allocation and rate design issues. 

 

13

Page 14: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Stakeholder Consultation Notes    December 2, 2013 

 

 

Hydro One Networks Inc. | 14 

 

6. Distribution Cost Allocation / Rate Design by Henry Andre, Manager Distribution Pricing, Hydro One Networks and Facilitated Discussion by Bob Betts, Facilitator, OPTIMUS | SBR 

Henry Andre thanked the audience and briefly reviewed the material he planned to cover, including load 

forecast, customer classification, cost allocation, rate design and bill impacts. 

He  began  by  indicating  that  the  load  forecasting  methodology  will  be  the  same  as  in  previous 

distribution applications; he  then addressed  the  load  forecast assumptions. All  forecasts are weather‐

normalized  based  upon  31  years  of  weather  data,  and  are  based  on  an  Ontario  economic  growth 

forecast of 2.4% over the 2015 ‐ 2019 test period.   CDM forecasts assumptions are consistent with the 

OPA’s Long Term Energy Plan, which is expected to be updated very shortly.  When the updates become 

available, the CDM  forecast will also be updated.   Finally the  latest Smart Meter hourly data  for 2012 

was used to update load profiles in determining the cost allocations by rate class. 

Henry  then graphically displayed  the  chart  showing  forecast  customer growth  together with  the  load 

forecast  for  2015  to  2019. He  indicated  that  the  customer  growth  forecast  is  consistent with Hydro 

One’s  typical 10,000  to 15,000 additional customers per year.   The  forecast  load  in GWh  shows  little 

change in 2015 to 2017, with a slight decline in years 2018 and 2019. 

Harold Thiessen, Ontario Energy Board, asked if there had been any significant changes in load profiles 

with the application of the 2012 hourly Smart Meter data which he believed was a new source of data. 

Henry confirmed that this is a new source of data and he doesn’t know yet how significant changes are. 

Alfredo Bertolotti, Power Workers' Union, then asked a question regarding the recently mentioned 2.4% 

Ontario economic growth  forecast assumption. This was answered by explaining  that  the assumption 

comes from a mix of forecasts from both government and financial institutions.  

John McGee  then  commented  that  the  forecasted  decline  in  demand  (consumption)  seemed  a  bit 

ambitious, and asked  if this chart will be updated throughout the five year test period. Henry deferred 

to  Susan  Frank, who  answered  that  the  LTEP  updates  that Henry  referred  to would  lead  to  a  filing 

update,  they had not planned at  this point  to make annual updates  to  load  forecast during  the plan; 

however, she would welcome further discussion about this in the afternoon during the discussion about 

Annual Adjustments. 

Henry  then  discussed  customer  classification  and  associated  revenue  impacts  from  classification 

changes. There are three processes which will lead to potential changes to Customer Classifications.  The 

first  is  the  Board‐directed  Rate  Class  Review  spoken  about  in  previous  stakeholder  sessions, which 

applied new GIS information to Hydro One’s density requirements, within the entire service territory  to 

see if any classification changes were required to align customers with Hydro One’s current definitions.  

The review will result in 135,000 of Hydro One’s total 1.2 million customers changing rate classes.  The 

vast majority,  about  111,000 will  be moving  to  classes with  lower  rates,  and  the  remaining  24,000 

moving  to  higher  rates.  This  largely  results  from  the  growth  of  previous  smaller  communities  now 

becoming dense enough  to move  to classes with  lower  rates.   This change would  result  in a  revenue 

14

Page 15: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Stakeholder Consultation Notes    December 2, 2013 

 

 

Hydro One Networks Inc. | 15 

 

reduction of $39.7 Million.   Henry noted that many customer bills would be  lowered as a result of the 

changes; however rates across all classes would increase by 3.4% to keep the change revenue neutral. 

John McGee asked if the review included all classes and Henry confirmed that it did. 

Mark Garner pointed out that the results show that while 111,562 customers are moving to lower rates 

resulting in a $81 million revenue requirement reduction, 23,685 customers would be facing a total $41 

million  revenue  requirement  increase,  and  that  looks  like  a  very  significant  rate  increase.    Henry 

confirmed that many of those 23,000 customers would be facing very significant increases. 

Julie Girvan asked about the 3.4% increase facing all rate classes resulting from the reclassification and 

how  that  compared  to Glenn  Scott’s  earlier  slide  15 which  showed  only  a  1.8%  impact  from  these 

changes.  Glenn Scott replied that the 1.8% was after adjustments for load forecasts and the other two 

rate classification changes. 

The second process was the Board‐directed review of Seasonal customers which also came out of the 

2013  IRM  Settlement  agreement.    Henry  explained  that  approximately  11,000  of  the  total  157,000 

seasonal customers exhibiting total consumption and monthly consumption patterns similar to those of 

full time residential customers would be switched to a residential classification.  The resulting decrease 

of $6.7M in revenue would translate to an average increase of 0.5% across all rate classes. 

Julie Girvan asked Henry to confirm that the rate reduction for 11,000 seasonal customers would result 

in a rate increase for the remaining seasonal customers that do not change.  Henry confirmed that there 

would be a slight increase but that a later slide will show that it is not unlike the change seen by other 

rate classes. 

John McGee asked Henry to confirm his opinion that this new approach to defining the rate class would 

require  Hydro  One  to  provide  new  definitions  for  certain  rate  classifications;  Henry  confirmed  that 

Hydro One would be doing that, particularly for the seasonal class. 

Peter Thompson asked Henry to confirm that these to Rate Classification changes would by themselves 

represent  almost  a  4%  increase  to manufacturers.   Henry  confirmed  that  taken  independently of  all 

other changes these two would be almost 4%. 

Mark Garner  followed up on his previous question about  the 24,000 customers  facing  large  increases 

from the Rate Class Review, asking if any would exceed a 10% increase and if yes, would Hydro One be 

considering rate mitigation for those customers.  Henry answered yes and yes to the two questions, and 

that approximately 1000 customers will likely need rate mitigation consideration.  

The  third rate classification change would be  the creation of an Unmetered Scattered Load  (USL) rate 

class as per the Board’s 2011 cost allocation review which suggested that all utilities create separate USL 

rate classes and Hydro One will be doing that in this application. 

15

Page 16: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Stakeholder Consultation Notes    December 2, 2013 

 

 

Hydro One Networks Inc. | 16 

 

In  response  to  a  question  from  Julie  Girvan,  Henry  confirmed  that  this  change will  only  affect  the 

General  Service  rate  class  since  all USL  customers  are  in  that  class,  and  the  change will  be  revenue 

neutral within the GS and USL classes. 

Henry then described a number of  important  improvements that will affect cost allocation calculations 

in this application.  These included: 

Hydro One will  be  using  the  Board’s  latest  Cost  Allocation Model  (“CAM”) which  includes  a 

number of changes that the Board had incorporated as a result of their last reviews. 

As was mentioned earlier, Hydro One will be using updated  customer  load profiles based on 

2012 Smart Meter data. 

Incorporating new Density Factors approved in their 2013 IRM Settlement Agreement. 

Improvements to tracking of costs by US of A break‐out. 

Updated Billing and Services factors as required by the Board’s most recent CAM. 

Addressing a number of issues raised at previous applications; things such as allocation of direct 

costs, and others. 

All of these will be discussed in much greater detail in the application evidence. 

Henry then moved on to discuss rate design  issues, explaining first that there  is an  increasing share of 

revenues  that will  be  recovered  through  fixed  charges, moving  from  39%  fixed  and  61%  volumetric 

charges, to 42% fixed and 58% volumetric. This change is again consistent with the Board’s latest CAM.  

This percentage is at the total level, fixed versus volumetric ratios will vary at the rate class level.  

Julie Girvan questioned the jump at some of the class levels and Henry confirmed that some could see 

substantial jumps in their fixed portions, for example UR and R1, with UR moving from $13 to $20 and 

seasonal going from $20 to $25.   Julie warned that there will be significant reaction to those  levels of 

change in the fixed component to the smaller customer with variable usage patterns. 

John McGee agreed with Julie’s concern and suggested that Hydro One might want to consider phasing 

this change in over a longer period of time like 4 or 5 years. 

Hydro One will be proposing to move cost ratios for all customer classes to 1.02 to 0.98 phased‐in over 

the five year period.  

The application will  include several new riders associated with new deferral and variance accounts, as 

well as a rate smoothing rider proposed to mitigate rate impacts.  

The  final  item  regarding  rate  design  in  this  application  is  that  it will  include  an  RTSR  reflecting  the 

proposed 2014 Provincial Transmission rates. 

Henry  finally  moved  on  to  discuss  the  resulting  Bill  Impacts,  first  the  average  2015  bill  impact 

components across all rate classes. The total average distribution impact will be 7.0%, representing 2.3% 

on the Total Bill.  The most significant contributor to these figures is revenue requirement generating a 

15.5% increase in distribution rates or 5.2% on total bill, followed by the net result of Rate Classification 

16

Page 17: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Stakeholder Consultation Notes    December 2, 2013 

 

 

Hydro One Networks Inc. | 17 

 

and Forecast changes creating a 1.8% increase in distribution rates and 0.6% on the total bill.  These are 

offset to some extent by new account riders and the smoothing rider, reducing distribution impacts by 

5.8% and total bill by 1.9%, and distribution impacts by 4.5% and total bill by 1.6% respectively. 

Julie Girvan asked how these figures compare to the 11.5% total increase as presented by Glenn in the 

bar chart on slide 12. Susan Frank answered that these figures represented the smoothed version so the 

total remains the same. Henry commented that the figures are from a consistent set of numbers and do 

not impact the accuracy of Glenn’s earlier numbers.  

John McGee asked if these bill impact estimates for 2015 included HST or any additional fees, to which 

Henry explained that yes, the estimates presented were bottom line impacts. 

To  conclude, Henry  presented  total  bill  impacts  by  rate  class  based  upon  generally  accepted  typical 

consumption  levels.  Henry  pointed  out  that  the  wide  variation  seen  in  2015  was  primarily  due  to 

movement toward a 1.00 revenue to cost ratio for each rate class, moving some up and some down. 

Julie Girvan asked why it appeared that the smoothing process began only in 2016, and not 2015. Henry 

responded that smoothing was applied in 2015 across all rate classes but in 2015 we are also seeing the 

impact of bringing the revenue to cost ratios within Board limits.   

John McGee then asked  if other consumption  levels were considered. Henry replied that there will be 

three  figures  for each  rate class, high consumption,  typical consumption and  low consumption within 

the filed evidence. 

Henry concluded by thanking the audience, asking if there were any further questions, and proceeded to 

introduce Benjamin Grunfeld, Navigant Consulting Inc., and explained that Ben would present the most 

recent findings of the line loss study. 

Benjamin Grunfeld, Navigant Consulting Inc., Line Loss Study Update 

Ben began by stating that actual losses within the 2010‐2012 time period were under study and that the 

study would provide  recommendations  regarding Hydro One’s  reporting of  variances of actual  losses 

going forward.  Ben also noted that individual losses related to specific rate classes were also examined.   

The initial focus was solely on the 2012 calendar year, due to the availability of hourly consumption data 

for  the majority of Hydro One’s  customers  through  smart and  interval meters. Ben explained  the  six 

primary  components  to  the  line  loss  calculation  that  acted  as  the  study’s  source  data;  on  both  the 

purchases side and the consumption side. Ben indicated that essentially, total purchases minus metered 

consumption, is equal to the line losses for a specific period.  

Ben made it clear that the calculation of 2012 losses required the analysis of a large quantity of hourly 

consumption data, and  that  this was not  the standard approach used  in  the  industry. The majority of 

utilities rely upon consumption data direct from their billing system, which  is generally available on an 

aggregate basis for an  individual customer’s billing cycle.   Annual consumption between January 1 and 

December 31  is calculated by summing the consumption that occurs between the  first and  last actual 

17

Page 18: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Stakeholder Consultation Notes    December 2, 2013 

 

 

Hydro One Networks Inc. | 18 

 

meter read. This calculation is then combined with an estimate of the proportion of consumption in the 

last billing  cycle before  the  first meter  read  that occurred within  the  year, as well as an estimate of 

unbilled  consumption  after  the  last  actual meter  read.  Ben  explained  that  unbilled  consumption  is 

typically  estimated  based on  individual  customer’s prior billing  period  consumption. Ben went on  to 

state  that  implementing  this  common  approach  over  a  number  of  years  significantly  reduces  the 

percentage of consumption that is estimated. 

Ben  went  on  to  explain  that  Navigant’s  recommendation  to  Hydro  One  is  to  estimate  customer 

consumption using the capabilities of the new Customer Information System (CIS), and to use that with 

the purchase information to determine actual annual losses on a going forward basis. The CIS is able to 

provide unbilled consumption for Hydro One’s 1.2M customers as of December 31st of each year. This is 

made possible by  the CIS developing a kilowatt‐hour per day metric during a specific base period and 

then applying this base to an unbilled period. Ben believes that using  this method will provide results 

similar to the approach implemented using 2012 hourly consumption data. The base period is developed 

using one of three methods listed below, depending on the availability of the necessary data inputs: 

1. Consumption in the same billing period in the previous year 

2. Consumption in the previous billing period 

3. Consumption estimated by customer class  

Ben also explained that the  level of hourly data that was used to calculate actual  losses  in 2012  is not 

available for prior years.  Interval metered customers, those for whom hourly consumption data would 

be available throughout the period, represent approximately 20% of total consumption. Customers with 

smart meters  and  automated meter  reads  in  2012  represent  approximately  50%  of  consumption.  In 

2010 and 2011 the proportion of customers with smart meters and automated meter reads would be 

lower. Ben wrapped up with these final thoughts; as the amount of hourly data available declines, the 

reliance on billing cycle data increases. As a result, Navigant recommends calculating the actual losses in 

2010  and  2011  using  an  approach  consistent  with  the  approach  that  will  be  used  going  forward, 

estimates based  upon billing  information  adjusted  to  account  for  the billing date.   As  stated  earlier, 

Navigant  expects  that  this  approach  will  yield  similar  results  when  compared  to  the  approach 

implemented using 2012 hourly consumption data. 

Ben then asked if there were any questions.  

John McGee asked if the source data can be broken down by customer class. He noted that Hydro One 

differentiates  loss  factors by class, which  is perhaps unique  in  industry. Ben  replied yes,  sales can be 

broken  down  by  class with minimal  effort;  however,  the  challenge  is when  power  comes  in  to  the 

system, one cannot discern from where it comes and where that same power ultimately ends up.  This 

creates difficulties  in terms of calculating  loss factors for  individual rate classes. Susan added that this 

issue is to be examined within Navigant’s final report, and will be included in the filed evidence. The final 

Navigant report is expected to be completed in January, 2014.  

18

Page 19: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Stakeholder Consultation Notes    December 2, 2013 

 

 

Hydro One Networks Inc. | 19 

 

Susan  needed  all  present  to  be  aware  that  Ben was  here  to  recommend  a way  for  Hydro  One  to 

determine line losses in 2010 and 2011, since clearly Hydro One has not been able to track losses during 

that period. Prior  to 2012 Hydro One’s capabilities were  significantly  less  than present day. So Susan 

asked for Ben to repeat his final recommendation on how to handle 2010 and 2011.  

Ben reiterated that to do a 2012 type of analysis relies on a great deal of calculation based upon a pool 

of dependable hourly data.  That data is not available for 2010 and 2011, and the calculation required to 

do  it  in  the  future  is not warranted based on  the quality of  the  results achieved.   So Navigant’s  final 

recommendation is for Hydro one to rely more heavily on billed meter data that is available on a billing 

cycle basis. For 2010 and 2011, Navigant  is  recommending a  similar approach  to  the “going  forward” 

recommendation. 

Peter Thompson asked  if Hydro One had an account to collect  losses from prior years. Ben responded 

that  Navigant’s  study will  identify  the  variance  in  terms  of  approved  and  actuals  in  both  KWh  and 

dollars.    It  is  then up  to Hydro One and  the Board  to determine where  that gets  reported and  if and 

when it ever gets collected.  

Mark Garner asked  if he was correct that Navigant will compare the study done with the 2012 hourly 

data  to  show  that  it provides  results  that  are not  significantly different  from  results  generated  from 

billing data, using CIS capabilities to adjust consumption to the year end, and the proposal of the hybrid 

methodology  (using  the  old  approach,  but  adjusting  for  the  billed  consumption  versus  actual 

consumption at year end) does not represent a material change.   This  is particular true today with the 

added features of Hydro One’s new CIS. 

This should give all parties comfort that going forward, consumption determined from adjusted billing 

data can be relied upon to reasonably estimate line losses. 

Mark asked if there was any real advantage in smart meter hourly data with respect to cost savings for 

consumers.  Ben  noted  that  this  is  not  common  practice  amongst most  utilities  in Ontario  currently, 

rather utilities use the approach discussed throughout his presentation. 

There were no further questions or comments and the group broke for lunch. 

12:15 PM  Lunch 

7. Custom  Framework – Adjustments and Reporting by Allan Cowan, Director Major Applications, 

Hydro One Networks and Facilitated Discussion by Bob Betts, Facilitator, OPTIMUS | SBR 

Bob Betts welcomed parties back and began  the afternoon by  reminding parties  that  in  the morning 

they heard numbers and the  impacts associated with this application and they clearly have a sense of 

the magnitude of the filing.  The afternoon session is aimed at using that knowledge and applying  it to 

the  items  that have not  yet been determined  in  finalizing  the  application.    These  things  include  the 

reporting and measurement of outcomes, what should be included in annual adjustment process, what 

19

Page 20: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Stakeholder Consultation Notes    December 2, 2013 

 

 

Hydro One Networks Inc. | 20 

 

are appropriate off‐ramps and what kind of  things can be considered  for  recovery during  the plan as 

“Adjustments Outside of Normal Course of Business”. 

He then  invited Allan Cowan back to the podium and  indicated that both Allan and Susan Frank would 

be participating  in  this afternoon’s  interactive  session. Allan began by explaining  that  the  session will 

include four principle focus areas:  Annual Reporting and Outcome Measures; Annual Adjustments, Off 

Ramps  and  Adjustments  Outside  of  the  Normal  Course  of  Business.    He  emphasized  his  hope  that 

everyone would be able to provide their input regarding how Hydro One can address these areas in its 

application. 

Beginning with Outcome Measures, Allan first explained the criteria that Hydro One is using to evaluate 

effective outcome measures, these included: 

The  chosen  outputs must  allow  Stakeholders  to monitor  key  outcomes  committed  to  in  the application 

Metrics need to be measurable, controllable, transparent, and not overly complicated” 

There must be a manageable number of metrics. 

Allan’s next slide presented “Examples of Distribution Outcome Measures” Allan explained  that  these 

are examples of the kinds of outcomes that could be measured and what metric might apply to each.  

The examples included: 

Customer Focus o Customer Satisfaction (i.e. % satisfied) 

Operational Effectiveness o System Reliability (i.e. # kms of forestry brush control & line clearing) o Asset Management (i.e. % of in‐service capital to forecast) o Overall Cost Performance (i.e. % OM&A / gross fixed costs) 

Public Policy Responsiveness o Conservation Demand Management (i.e. Net Annual Peak Demand Savings (MW)) o Renewable Generation (i.e. # of connections, etc.) 

Financial Performance o Liquidity (i.e. current assets / current liabilities) 

Julie Girvan asked how this reporting of outcomes was different from the OEB Performance Scorecard 

being established by the Board.   Susan Frank responded saying from Hydro One’s perspective they are 

two different things. She feels that the OEB Performance Scorecard is intended to measure performance 

over the long term against the OEB’s expectation for all utilities.  The Outcome Measurement concept is 

to allow stakeholders and the OEB to evaluate whether the utility delivered the Outcomes they said they 

would  in  their  particular  long  term  rate  plan,  in  this  case  2015  to  2019.   What  “outcomes”  did  the 

spending promise and were they delivered.  Susan directed the question back to participants “What do 

you and customers want us to report on and be measured against?” 

Mark Garner  states  that  the majority of customer  surveys  show  the  same “motherhood”  issues: “We 

want lower prices and more service” and therefore have little value as a metric for their satisfaction. He 

indicated that his clients would want to know what the objectives are relative to the spending included 

in  the  plan,  and  then  reporting  on whether Hydro One  is meeting  or  has met  those  objectives.  For 

20

Page 21: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Stakeholder Consultation Notes    December 2, 2013 

 

 

Hydro One Networks Inc. | 21 

 

example, a  large amount of money  is  to be  spent on vegetation control, what  is Hydro One’s goal  in 

doing  that:  lower or stable SAIDI/SAIFI results,  lower  long  term costs, reduced number of  tree‐caused 

outages, etc.? Once the goal is established, next choose the metric that can evaluate it, i.e. SAIDI/SAIFI 

reports,  trends  in  tree management  spending  forecasts,  hours  or  dollars  spent  clearing  away  storm 

damage, etc.  He added that Hydro One should share what metrics will be used to measure success with 

consumers.  

Mark added that with respect to the customer focus category, there is too much focus on initiatives that 

are designed  to  show  that Hydro One  is a  ‘good company’,  for example  the wide  range of corporate 

social responsibility initiatives undertaken by Hydro One.  

Julie Girvan then stated that the outage issue should be a key focus of the outcomes reporting and the 

communication of outage maintenance efforts should be evaluated by customers.  She said that in rural 

areas customers need to be kept abreast of outage developments. She noted that somehow measuring 

this aspect of customer service would be ideal, keeping in mind that customers want reliable service at a 

reasonable rate, and not much else.   

Roger Higgins agreed with Julie, and added that customer centric performance measures should be the 

primary focus of any scorecard developed in the future. Susan asks for clarification, and Roger explained 

that scorecards are usually not class specific, but that the technology needed to provide this additional 

information is already in place. He again stressed the importance of customer focus.  

Peter Thompson added that distribution related bill stability is desired from industrial and small business 

clients.  He  then  suggested  that  sharing  five  years  of  distribution  financial  information,  budget  and 

actual, by rate class, would be a level of transparency that would be much appreciated by consumers.  

Mark  then  suggested  that  when  outages  occur,  regardless  of  type  of  outage,  perhaps  surveys  be 

completed by affected  consumers  in order  to  find out how well  the  situation was handled, how well 

consumers were able to understand what was happening surrounding the outage, and so forth. Susan 

responded by using an example of bringing a car  in for service; she stated that a couple days after the 

return of your vehicle, the dealership asks  if you were happy with service. Susan stated that she  is not 

sure how well that style of approach determines if initial goals were actually met.  

Lisa Brickenden, Ontario Energy Board, suggested a transactional survey to maximize reporting results. 

She stressed that surveys should have subject matter aligned with desired outcomes. Susan responded 

that the challenge  is measuring how well the  initial objectives were understood by the consumer.  It  is 

very simple for a consumer to look at their individual situation and report poor performance, while the 

overall initial performance objectives may have been met or exceeded. Susan returned to the example 

of bringing your vehicle in for a service check, and said that dealerships target a 70% positive feedback 

level.    Susan  stated  that  a  similar model  could  be  considered,  by  asking  consumers  if  a  particular 

transaction met their expectations.   

Mark then repeated that the key elements of an effective strategy are to know if consumers at large are 

satisfied or unsatisfied with service levels in the face of an outage, and that these are more likely to be 

21

Page 22: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Stakeholder Consultation Notes    December 2, 2013 

 

 

Hydro One Networks Inc. | 22 

 

measurable  by  transactional  surveys  than  with  general  surveys.   Mark  added  that  the  operational 

outcome measurements will  report on how  frequently problems occur and allow Hydro One  to make 

improvements  there;  and  while  that  is  important  to  customers,  customer  satisfaction  can  be  best 

measured by how well the problem was handled. 

Lisa then pointed out that in past studies, it has been noted that the earlier the consumer is contacted 

or made aware of outage  information, the more tolerant they are  in terms of being satisfied with the 

end result.  

Ruth Greey, Hydro One,  Senior  Regulatory  Advisor,  pointed  out  that Hydro One  already  conducts  a 

variety of transactional surveys, particularly with large industrial consumers, and that these can be used 

as a launching point to expand coverage using current baseline information.  

Shelley Grice confirmed that a customer‐focused approach is most desired; she then asked if targets to 

measure improvement in this area will be set by Hydro One. Susan responded yes, this will be included 

in the high level plan moving forward.  

Bob Betts then brought up the significant  investment made by Hydro One  in the CIS system build out, 

and wondered  if  this  has  associated Outcome  improvements  that  could  be measured  and  reported 

upon? Susan responded that  it could, and that one of biggest  issues  in consumer service  is the disdain 

for  estimated  bills.  She  believes  that  the  CIS  system  and  smart meter  rollout  will,  over  time,  will 

decrease the need for estimated bills, so perhaps a goal of reducing the number of estimated bills could 

be quantified and reported upon.  

Paul Brown then stated that they are considering how they might be able to measure the value of an 

investment, or  the effectiveness of  the  recent  implementation.   He  stated  that Hydro One will  think 

about  this  issue  further  and  see what  can  be  done.  He  acknowledged  that  this  approach may  not 

shorten the outage, but perhaps ensure that information is more readily available, offering the example 

of providing consumers with an estimated time of service restoration.  

Susan suggested that perhaps Hydro One should have Outcome goals associated with how quickly they 

respond to an outage since that can be controlled. The duration of the Outage is often out of the utilities 

control because it is dependent upon the nature and extent of the damage. 

Ruth suggested  that perhaps Hydro One could be measured against how accurate  their estimation of 

outage time is, for example if they advise customers power will be out for 48 hours, how accurate was 

that compared to actual outage time.  The more accurate it is, the more satisfied the customer will be. 

Paula Zarnett noted that communicating with the customer is essential, repeating the example of letting 

consumers  know  that  the  company  is  aware  of  an  outage,  and  then  later  communicating  that  the 

company believes that service has been restored, perhaps via automatic phone call.  She also suggested 

that consumer interaction should be measured to understand what proportion of consumers is reached 

by the company’s efforts.  

22

Page 23: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Stakeholder Consultation Notes    December 2, 2013 

 

 

Hydro One Networks Inc. | 23 

 

Susan  described  the  activities Hydro One  is  currently  undertaking.  She  then  asked  how many  areas 

should be measured, and how does Hydro One decided which areas are tracked? 

Julie Girvan suggested that related costs should dictate how many areas are measured.  For example, if 

costs to track one particular area are exorbitant, then certain performance tracking initiatives should be 

foregone. 

John McGee then shifted topics to call center performance measurements.  He asked when a consumer 

calls in, what metrics are used to measure the success of the interaction in terms of targets and trends. 

Susan responded that this area is being tracked now, but there could be more emphasis on targets and 

trends. 

Roger Higgin then commented that it’s important to know which specific customers are out of service at 

a given time, stating that Hydro One’s system currently  indicates which transformers, feeders, etc. are 

out, but it is not capable of identifying when and where individual customers are out.  Susan replied that 

they are moving  in  that direction, but  it will be  years before  they  can  identify when each and every 

customer might be out. 

Mark moved to the area of Outcome measurement for operational effectiveness, specifically  in regard 

to development and  if the spending and timing specific development projects  is achieved.   Mark went 

on  to  comment  on  the  area  of  Public  Policy  Responsiveness  saying  that  this  is  very  difficult  to  set 

Outcome expectations for and that perhaps the only measurement  is that the LDC  is not chastised for 

being “unresponsive” to Public Policy. 

Lisa  then  returned  the  conversation  to  the  issue  of  how  many  measurements  are  appropriate, 

suggesting that the number 15 is likely too high. She indicated that the discussion seems to be focused 

on restoration of service and related areas most  important to consumers. She suggested that perhaps 

the outcomes should be focused at a higher level, that is, be related to over goals and objectives, rather 

than making sure that Hydro One didn’t install only 10 poles when they promised to install 15. 

Mark suggested that even having one performance outcome for each of the four major categories might 

be sufficient. 

Susan responded that there are certain levels of detail they can report on, for example a plan to replace 

15 poles ending up with only 10 poles actually being replaced.  The reason why the stated target wasn’t 

met  is more  challenging  to  report,  track  and measure  relative  to  initial  performance  targets.    The 

usefulness of these measurements is debatable.  

Bob then moved the conversation on to public policy responsiveness.  

Lisa Brickenden stated from a Board Staff perspective, not speaking for the Board, that unless specific 

suggestions to policy are included in filed evidence, and not general suggestions or just plain opposition 

to various public policies, then it is not worthwhile to include in filings. The group then generally agreed 

23

Page 24: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Stakeholder Consultation Notes    December 2, 2013 

 

 

Hydro One Networks Inc. | 24 

 

that  the  category of public policy  responsiveness  should more  appropriately be  considered  as public 

policy directives to which that utilities must comply. 

The  conversation  then  shifted  to  financial  performance,  with  Roger  Higgin  and  Peter  Thompson 

suggesting that ROE be the key metric on which performance  is based.   Allan Cowan pointed out that 

ROE is already included in all relevant filings and viewed with great importance.  

Mark Garner then asked if there would be an opportunity to review the outcome performance reports 

thus  allowing  stakeholders  to  identify  concerns  and pursue means  to  address  those  concerns.  Susan 

agreed that this was an appropriate area for consideration and development.  

Lisa then commented that a ‘plan of execution’ metric is soon to be developed by the OEB, and details 

would be forthcoming.  

Lisa then asked that the value proposition slide be shown again (Slide 10 of Glenn Scott’s presentation 

deck  that  includes  keeping  rates  low,  improving  operating  efficiency  and  cost  savings,  improving 

customer  satisfaction  and  building  a  trusted  partner  relationship,  preserving  net  income,  and  full 

visibility  on  assets  and  targeted  investments  to minimized  customer  impacts).  She  commented  that 

these might be  considered when deciding what  to  include as desirable Outcomes. Susan agreed  that 

could be a good possibility. 

Mark then asked about performance measurements, for example if one of the goals is to keep rates low, 

then where in the plan does it explain how that will be done over the 5 year period. Allan responded to 

that particular example by  saying  that  the plan presented by Glenn does  actually  show OM&A  costs 

declining in the later years of the plan, citing measures in the plan to accomplish that including regular 

head‐count management.  Mark then also suggested that bond rating changes could be a useful metric 

for Financial Performance. 

Susan suggested the development of an “Other” category to capture Outcome areas that don’t fit neatly 

into the Board’s four Outcomes. Bob asked the group about their thoughts on “Compensation outcome”  

in this category.  Mark indicated that it would be helpful to be able to see how Total Compensation was 

moving through the five year term. Susan remarked that labor negotiations are conducted on a regular 

schedule, and the  information  is generally shared with a wide range of stakeholders. Mark then noted 

that most people are not worried about specific contracts, but whether overall compensation (including 

contracting out) levels are rising or falling. Susan commented that there has been progress in this area, 

making note of the increased use of contractors and consultants and the added organizational flexibility 

this entails. Mark repeated that overall compensation  levels are the key  indicator;  if rising, then more 

information should be provided as to why and what can be done to mitigate.   

Lisa proposed that there should be some Outcome associated with  Innovation for example developing 

or capitalizing on new technologies related to smart grid pilot initiatives and suggested that successes in 

this  area  could  be  measured,  for  example  a  metric  to  track  innovation  within  the  company  and 

associated costs and benefits.   

24

Page 25: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Stakeholder Consultation Notes    December 2, 2013 

 

 

Hydro One Networks Inc. | 25 

 

Julie Girvan commented that it is important not to forget that dreaming up interesting metrics is not the 

exercise  under  discussion,  that  cost mitigation  should  be  the  key  focus  as well  as  key metrics  that 

customers are interested in, for example those related to rate levels and reliability of service. 

Susan  then  thanked  everyone  for  their  comments  and  suggestions  and  that  the  high  level  of 

participation was very much appreciated.  She then made note that not all ideas can be implemented in 

upcoming  filing, but some will be embraced and certainly warrant  further  focus and  investment  from 

Hydro One. 

In order to provide context to the discussion described above, please find below a list of ideas generated 

by the stakeholder group, as noted by Hydro One as the conversation progressed: 

1. Customer Focus 

− Customer Satisfaction (i.e. % satisfied) 

− Outage Mgmt / Restoration Time Information 

− CELDI (Customer Experiencing Long Interruption Duration) 

− Dx  rate  stability  (by  rate  class) – measure actual  impacts against  filed 

(and as a percentage of total bill) 

− Outage performance surveys  

− Transactional based surveys (measured as % satisfied) – customer class 

specific 

− Reduction of estimated bills 

− Reduction in Outage Restoration time / Reduction in Time to Respond / 

Estimating     actual restoration time 

− Call centre performance 

2. Operational Effectiveness 

− System Reliability (i.e. # kms of forestry brush control & line clearing) 

− # of tree caused outages 

− Reductions of outages by cause code 

− Asset Management (i.e. % of in‐service capital to forecast) 

− Overall Cost Performance (i.e. % OM&A / gross fixed costs) 

− Key Capital  and OM&A  SDOC  (Sustainment, Development, Operations 

and Customer) category objectives  (i.e. # customer  connections under 

Development) 

− OM&A/customer (declining OM&A over plan) 

− Declining ‘regular’ headcount 

3. Public Policy Responsiveness / Directives 

− Conservation  Demand  Management  (i.e.  Net  Annual  Peak  Demand 

Savings (MW)) 

− Renewable Generation (i.e. # of connections, etc.) 

25

Page 26: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Stakeholder Consultation Notes    December 2, 2013 

 

 

Hydro One Networks Inc. | 26 

 

− Should be linked specifically to proposed features of plan  

4. Financial Performance 

− Liquidity (i.e. current assets / current liabilities) 

− ROE (approved vs actual) 

− Capital spend to plan (plan execution) 

− Bond Rating changes 

5. OTHER 

− Links to value proposition 

− Compensation 

− Successes in Smart Grid Pilot area (Innovation) 

Allan  Cowan  then  moved  the  session  on  to  cover  other  issues  to  be  included  in  the  upcoming 

application. First, the annual adjustments, with defined criteria including:    

Externally driven and beyond utility’s control: 

Ongoing / recurring changes either upward/downward: or 

Primarily formula based. 

Examples of Annual Adjustments proposed by Hydro One include:  

1) Cost of Capital 

Based on OEB issued Return On Equity and deemed Short Term debt rate in November of each year, as well as Hydro One’s actual  long  term debt  issued updated every year during the term 

 2) Working Capital 

Based on change in Commodity Prices, including global adjustment. (Discussed at length during Hydro One’s first stakeholder session) 

 3) Tax Rate Changes (100%) 

Flow through based on government directed tax change within the year  

4) 3rd party flow‐through costs 

Based on changes in:  o Retail Transmission Service Rate (RTSR),  o Wholesale Meter Service Charge (WMSC),  o Smart Metering Entity Charge (SME),  o Rural Rate Protection Charge (RRRP),  o OEB Charges 

5) Clearing of Variance Accounts (e.g. RSVAs, pension)  

bi‐annual based on the latest annual  audited financial results. 

26

Page 27: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Stakeholder Consultation Notes    December 2, 2013 

 

 

Hydro One Networks Inc. | 27 

 

Hydro One will present to the Board an update of adjustments for the upcoming year as part of the draft 

rate order filed in November of each year. 

Allan then went on to briefly review two potential off‐ramps, identifying that these are consistent with 

the OEB’s Renewed Regulatory Framework for Electricity (RRFE).  These include: 

Return on Equity falls outside the +/‐ 300 basis point earnings dead band; or  Utility performance erodes to unacceptable levels 

Allan  then  shifted  in  to a discussion pertaining  to  ‘adjustments  that  fall outside  the normal course of 

business’.  The criteria for these include:  

Externally driven and beyond the utility’s control; 

 Unexpected; or 

Having a very material impact on operations.   

Allan listed the examples that proposed by Hydro One including:  

Restructuring of the industry  New Government Directives or Legislation  Market Rules/Code changes  Environmental law changes  Technical standard changes  New  investments  resulting  from  the newly developed Regional Plans   of a significant material 

nature  Material unforeseen weather events  Accounting Framework changes 

With respect to implementation, Hydro One will file when an event or cumulative events take place and 

the situation requires only a particular component of the plan to be examined and possibly tracked in a 

variance account and adjusted  through a  rate  rider/adder.   Allan also noted  that  in  such an event, a 

written proceeding may be required by the OEB. 

Allan briefly recounted the material covered and opened the floor to any questions. He explained that 

the audience should feel free to bring up any issue reviewed throughout the day.  

Roger Higgin asked if any components of the five year plan reflect potential M&A activity. Allan replied 

no, and pointed out that the Norfolk Power acquisition is also not reflected in the plan, that Norfolk shall 

have a separate filing and financial statements.   He went on to say that should any more M&A activity 

take place, the same treatment shall be applied. 

Mark Garner  then  asked  if  any  rate  harmonization will  take  place  as  a  result  of  acquisitions.    Allan 

responded no, not over the 5 year projected period.  

Mark then asked  if working capital annual adjustments would be supported by a  lead/lag study. Allan 

explained that the most recent study will be part of this application.  

27

Page 28: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Stakeholder Consultation Notes    December 2, 2013 

 

 

Hydro One Networks Inc. | 28 

 

Julie  then asked  if  there was  currently any plan  to enact an earning  sharing mechanism  in  the  filing; 

Susan Frank stated that this was not an initiative that was slated for further development.  

Mark then asked about new debt issues and whether there is a standard approach to ensure minimum 

yield is paid by Hydro One. Allan explained that the team works to time the market to obtain the lowest 

rate, however points out that they are unable to dictate rates to the marketplace.  

Peter  Thompson  asked  for  the potential  effect  that  the Annual Adjustments  could have on  the  $1.4 

Billion  revenue  requirement.   Susan  replied  that  the major effect would be associated Cost of Capital 

adjustment.  While Working Capital should be smaller, but it is based upon the commodity price and it is 

difficult  to  say  where  it  could  go  over  five  years.    Susan  summed  up  by  saying  that  all  of  these 

adjustments are by definition beyond their control and therefore largely unpredictable. 

Roger Higgin  then  added  that  it  is  important  to measure  potential  scenarios,  for  example  economic 

recession and potential implications and associated risks in this event.  Allan acknowledged that should 

a  recession  occur  the  budgeted  financials would  be  at  risk.  Susan  stressed  that with  any  five  year 

forecasting exercise, especially as it pertains to OM&A and capital expenditure plans, there is always an 

element of risk with respect to assumptions surrounding demand and revenue levels.   

Peter Thompson asked  if this was an  incentive plan and Allan  indicated  it  is a cost of service plan with 

built  in  productivity.    Peter  asked  if  Hydro  One  had  reviewed  the  PEG  Report with  respect  to  the 

Enbridge  Incentive Rate Plan.   Allan  indicated  that  they had, but  that both circumstances and options 

were different  for Hydro One and Enbridge and Hydro One does not  feel  that  the PEG  report would 

apply to them.  Allan acknowledged that that Enbridge like Hydro One had specific things happening to 

them which required a customized approach  to both,  thus generating  two very different applications.  

The Board has created rules for custom applications for electrics and Hydro One is following those. 

Peter  went  on  to  ask  what  benefits  the  ratepayer  would  see  from  Hydro  One’s  plan.    Allan  first 

mentioned how  this approach avoids  the painful spike  in  rates  that  is  inherent  to  IRM plans  that  this 

Cost of Services application has allowed for mitigation of that. 

Susan added that the plan has productivity built into it, as can be seen by the tight constraints on OM&A 

over the five year term. 

Lisa  then discussed potential efficiency gains over  the  five year period and  from a design  standpoint, 

why  some  sort  of  “carryover  incentive”  is  not  included  in  plan.    Susan  asked  for  clarification,  and 

perhaps a specific example. Lisa offered the example of the allowance of gains achieved (for example, 

spending  less  than  the OEB  approved  amount  in  a  specific  area);  this  amount would  potentially  be 

allowed  to be carried over  to  the next  filing  term. Susan explained  that various deferral and variance 

accounts exist to not only collect shortfalls but also return surpluses to consumers.  

Susan continued to explain that the entire five year plan  is designed to serve the balanced  interests of 

both  Hydro  One  and  their  customers,  and  that  the  information,  financial  or  otherwise,  is  being 

28

Page 29: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Stakeholder Consultation Notes    December 2, 2013 

 

 

Hydro One Networks Inc. | 29 

 

presented in a manner as transparent as possible. She then again confirmed the existence of risk within 

the plan, and stated that the Hydro One Board is confident in the planned filing. 

Mark  then asked how Hydro One plans  to define  ‘material unforeseen weather events’. He asked  for 

clarification on what exactly defines a  ‘material event’. Susan responded  that they will  look  in to how 

they might categorize various events in major buckets.  

Julie  asked  if  there were  any  unforeseen  events  that  should  potentially  be  listed  as  a  cost  savings 

contributor,  to which  Susan  asked  for  specific  examples. Mark  suggested  that  a  restructuring  of  the 

industry might be a potential cost savings contributor.  Susan explained that yes, industry shifts may be 

viewed  in  this manner  and would be  considered  in  the  framework of  an Adjustment Outside of  the 

Normal Course of Business.  

Ceiran Bishop, Ontario Energy Board, asked why that example would be considered outside the normal 

course of business. Susan explained that fundamental operating parameters not  initiated by the utility 

would fall into this group.  

There  was  a  general  discussion  about  the  considering  variations  to  the  300  basis  point  off‐ramp, 

including: the potential for a lower threshold like 200 basis point, or an asymmetrical off‐ramp or an off‐

ramp that had a lower threshold in the case of consecutive years of under or over earning. There was no 

conclusive outcome to that discussion. 

The focus of discussion went to the Adjustment Outside of the Normal Course of Business.  Mark asked 

what  kind  of  “unforeseen  weather  events”  would  be  considered  “material”;  both  Susan  and  Allan 

answered  “a  major  ice  storm”  as  an  example.    Mark  suggested  that  materiality  still  needs  some 

definition and Susan agreed they would come up with a materiality definition; however, she did indicate 

that Hydro One considered these events to be of very significant  impact, the kind of thing that would 

make them say that they can’t continue business without some relief. 

Mark asked for as definition of Adjustments Outside of the Normal Course of Business as compared to 

an off‐ramp.  Susan said that an off‐ramp applies to things that show that the plan cannot be continued, 

while the Adjustments are things that materially impact parts of the business, but don’t jeopardize the 

entire plan, these would need to be addressed by the Board with specific relief considered by the Board.  

Mark asked that each of the three adjustment options have clear definitions included in the application. 

Lisa asked  for an example of an adjustment  for new  investments  resulting  from  the newly developed 

Regional Plans.  Susan described a scenario which could drive the need for more electricity in a region, 

not  all  of  the  investment  would  be  in  transmission.  There  could  be  some  significant  amount  of 

distribution infrastructure investment that should be eligible for this kind of relief. 

Ceiran asked whether  insufficient visibility with respect  to regional plan outcomes contributes  to  this.  

Susan said yes, and stated that she was unable to speculate what would be coming up and the extent to 

which funding would be available.  

29

Page 30: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Stakeholder Consultation Notes    December 2, 2013 

 

 

Hydro One Networks Inc. | 30 

 

Mark then brought up transmission related  issues, noting there will  likely be many situations over the 

course of the next five years that fall under this category and are likely not anticipated within the plan. 

Susan  responded  that  there  is  uncertainty  surrounding  regional  planning  and  potential  required 

investments  from  distributors;  she  noted  however  that  the  degree  of  uncertainty was  so  high  that 

further discussion at this time is not warrented. 

Bob Betts asked if there were any other items to be discuss, and there were none. 

 

8. Closing Remarks / Next Steps by Allan Cowan, Director Major Applications, Hydro One Networks 

Allan concluded the session by thanking everyone for participating and for their valuable feedback. He 

explained that he hoped to shape the application to reflect as much of this feedback as possible from all 

four stakeholder sessions. He concluded by stating that he wishes the audience well and again extended 

his thanks for their openness and contributions. 

Bob Betts also thanked the audience and adjourned the meeting. 

 

   

30

Page 31: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Stakeholder Consultation Notes    December 2, 2013 

 

 

Hydro One Networks Inc. | 31 

 

9. Appendices 

Appendix A.  Summary of Stakeholder Session  Hydro One’s 4th Stakeholder Session was conducted to present  information to stakeholders and gather 

feedback  on  items  related  to  Hydro  One’s  Distribution  Custom  Rate  Application  2015‐2019.    The  5 

primary topics discussed in the stakeholder session were:  

1. Application Filing Timeline 

2. Revenue Requirement and Common Costs 

3. Core Work Program 

4. Distribution Cost Allocation / Rate Design / Line Loss Study 

5. Custom Framework – Adjustments and Reporting 

Throughout  the  Session,  there was  open  discussion with  stakeholders  covering  questions,  issues  of 

concern, additional  information  for consideration,  requests  for detail or explanation, and  requests  for 

further input and consultation. 

Hydro One’s  internal  specialists  explained  the  rationale,  approach  and  results,  and  indicated where 

further details and explanations would be provided in the filing. 

 

 

 

 

 

 

 

 

 

 

 

 

 

31

Page 32: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Stakeholder Consultation Notes    December 2, 2013 

 

 

Hydro One Networks Inc. | 32 

 

Appendix B.  Key Actions and Considerations  Application Filing Timeline 

Planned initial filing date is December 19, 2013 

The initial filing will include high‐level information and financial projections 

Supplementary  filing with  all  supporting  documentation  and  detailed  financial  projections  to 

follow on approximately January 31, 2014 

Blue page update to be filed in approximately May, 2014 

Hydro One would like to allow all stakeholders to have ample time to evaluate the filings 

 

Revenue Requirement and Common Costs 

 

Five  key  goals  of Hydro One’s  value  proposition  related  to  the  delivery  of  safe,  reliable  and 

affordable service 

o Keeping rates low 

o Improving customer satisfaction and building a trusted partner relationship 

o Preserving net income 

o Full visibility on assets and targeted investments to minimized customer impacts 

o Improving operating efficiencies and cost savings 

 

Key elements of upcoming filings 

o Hydro One ongoing capital structure is 60% debt, 40% common equity 

o Overall cost of capital of 6.76% 

o Rate base of $6,477M 

o Return on capital of $438M 

o Revenue requirement of $1,411M 

 

Hydro One is aware that reliability of service and overall bill impact are the two most prevalent 

issues for consumers 

Rate  smoothing  strategy  proposed  to mitigate  impact  of  planned  2015  rate  increase  (which 

would result in an increase of approximately 7% for each of 2015, 2016, 2017, 2018, 2019) 

 

Core Work Program 

 

Hydro One serves approximately 1.2M customers 

Hydro One  assets  include over  120,000  circuit‐km  of  lines,  1.6M poles  and  1004 distribution 

stations 

Primary  goals  focused  on  sound  investment  strategies  to  ensure  safe,  reliable  and  efficient 

power delivery and to create and enhance value for customers 

32

Page 33: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Stakeholder Consultation Notes    December 2, 2013 

 

 

Hydro One Networks Inc. | 33 

 

Overview of OM&A and capital expenditures (sustaining, development, operating and customer 

service) 

Of  the  four primary  components of OM&A  sustaining, development, operating and  customer 

service,  investments within sustaining are the most significant cost driver, with 2015‐2019 test 

period costs ranging from $329M to $380M annually 

Second most  significant  cost  driver  is  customer  service,  accounting  for  between  $115M  and 

$118M annually over the five year test period 

Vegetation management expenditures will exhibit a sharp  increase  in 2016 and 2017 and then 

stabilize in 2018 and 2019, due to a backlog in tree clearing 

Development OM&A cost projections range from $15M to $18M within the test period 

Operating OM&A cost projections range from $30M to $41M within the test period 

Aging  assets  and  systemic  problems  are  a  significant  factor  in  forecast  costs,  as  is  reliability 

improvements  and  long‐term  cost  optimization  (such  as  addressing  vegetation maintenance 

backlogs and maintaining an eight year clearing cycle) 

Stakeholder concerns focused on implications of the rate smoothing alternative strategy 

 

Distribution Cost Allocation / Rate Design 

Key  topics  include  load  forecast,  customer  classification,  cost  allocation,  rate  design  and  bill 

impacts 

Load  forecast  assumptions  based  upon  31  years  of weather  data  and  an  Ontario  economic 

growth forecast assumed at 2.4% over the five year test period 

Total revenue impact from customer classification changes estimated at ‐$39.7M 

Rates across all classes to increase by 3.4% to maintain revenue requirement needs 

Approximately  11,000  seasonal  customers,  from  a  total  of  approximately  157,000,  to  be 

switched to a residential classification 

Stakeholder concerns focused on economic growth and related demand assumptions, as well as 

revenue impacts from classification changes and related cost ratios 

Hydro One will be releasing new customer classification definitions 

 

Custom Framework – Adjustments and Reporting 

Focus  on  annual  reporting,  the measurement  of Outcomes, Off  Ramps  and what  should  be 

included in the annual adjustment process 

Metrics are required to be measurable, controllable and transparent 

Must be a manageable number of metrics 

Categories  of  outcome measures  included  customer  focus,  operational  effectiveness,  public 

policy responsiveness/directives, financial performance and other 

 

 

33

Page 34: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Stakeholder Consultation Notes    December 2, 2013 

 

 

Hydro One Networks Inc. | 34 

 

Appendix C.  Meeting Agenda  

8:45 a.m.  Registration 

9:05 a.m.  Welcome Allan Cowan, Director Major Applications Hydro One Networks  

9:10 a.m.  Introductions and Agenda  Bob Betts, Facilitator, OPTIMUS|SBR  

9:20 a.m.  Application Filing Timeline Allan Cowan, Director Major Applications Hydro One Networks  

9:30 a.m. 

Revenue Requirement and Common Costs    and Facilitated Discussion 

Glenn Scott, Director Corporate Planning & Finance Hydro One Networks   Bob Betts, Facilitator, OPTIMUS|SBR 

10:30 a.m.  Break 

10:45 a.m. 

Core Work Program    and Facilitated Discussion 

Paul Brown, Director Distribution Asset ManagementHydro One Networks   Bob Betts, Facilitator, OPTIMUS|SBR 

11:30 a.m. 

Distribution Cost Allocation / Rate Design    and Facilitated Discussion 

Henry Andre, Manager Distribution Pricing Hydro One Networks   Bob Betts, Facilitator, OPTIMUS|SBR  

12:30 p.m.  Lunch 

1:30 p.m. 

Custom Framework – Adjustments and Reporting  and Facilitated Discussion 

Allan Cowan, Director Major Applications Hydro One Networks   Bob Betts, Facilitator, OPTIMUS|SBR 

3:30 p.m.  Closing Remarks / Next Steps Allan Cowan, Director Major Applications Hydro One Networks  

3:45 p.m.  Adjourn 

 

34

Page 35: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Dis

trib

utio

n Cu

stom

Rate

A

pplic

atio

n 2

01

5-2

01

9

Stak

ehol

der S

essio

n #4

Dec

embe

r 2, 2

013

Stak

ehol

der

Con

sulta

tion

35

509292
Text Box
Appendix D. Presentation Slides
Page 36: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Agen

da

8:4

5 a

mReg

istr

atio

n

9:0

5 a

mW

elco

me

Alla

n C

owan

, Dire

ctor

Maj

or A

pplic

atio

nsH

ydro

One

Net

wor

ks

9:1

0 a

mIn

trodu

ctio

ns a

nd A

gend

aBo

b Be

tts, F

acili

tato

r, O

PTIM

US|

SBR

9:2

0 a

mA

pplic

atio

nFi

ling

Tim

elin

eA

llan

Cow

an, D

irect

or M

ajor

App

licat

ions

Hyd

ro O

ne N

etw

orks

9:3

0 a

mRe

venu

e Re

quire

men

t and

Com

mon

Cos

ts an

d Fa

cilit

ated

Disc

ussio

n

Gle

nn S

cott,

Dire

ctor

Cor

pora

te P

lann

ing

& F

inan

ceH

ydro

One

Net

wor

ks

Bob

Betts

, Fac

ilita

tor,

OPT

IMU

S|SB

R

10

:30

am

Bre

ak

10

:45

am

Cor

e W

ork

Prog

ram

and

Faci

litat

ed D

iscus

sion

Paul

Bro

wn,

Dire

ctor

Dist

ribut

ion

Ass

et M

anag

emen

tH

ydro

One

Net

wor

ks

Bob

Betts

, Fac

ilita

tor,

OPT

IMU

S|SB

R

11

:30

am

Dist

ribut

ion

Cos

t Allo

catio

n /

Rate

Des

ign

and

Faci

litat

ed D

iscus

sion

Hen

ry A

ndre

, Man

ager

Dist

ribut

ion

Pric

ing

Hyd

ro O

ne N

etw

orks

Bob

Betts

, Fac

ilita

tor,

OPT

IMU

S|SB

R

12

:30

pm

LUN

CH

1:3

0 p

mC

usto

m F

ram

ewor

k –

Adj

ustm

ents

and

Repo

rting

and

Fac

ilita

ted

Disc

ussio

n(in

clud

es a

15m

in B

reak

)

Alla

n C

owan

, Dire

ctor

Maj

or A

pplic

atio

nsH

ydro

One

Net

wor

ks

Bob

Betts

, Fac

ilita

tor,

OPT

IMU

S|SB

R

3:3

0 p

mC

losin

g Re

mar

ks/N

ext S

teps

Alla

n C

owan

, Dire

ctor

Maj

or A

pplic

atio

nsH

ydro

One

Net

wor

ks3:4

5 p

mA

djo

urn

2

36

Page 37: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Faci

litato

r’s

Rem

ark

s

In

trodu

ctio

ns F

acili

tato

r, Bo

b Be

tts &

OPT

IMU

S |

SBR

supp

ort t

eam

M

eetin

g Fa

cilit

ies

Sa

fety

Rev

iew

N

ote

taki

ng p

roce

ss

Pa

rtici

pant

Intro

duct

ions

3

37

Page 38: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Mee

ting P

roce

ss

M

obile

pho

nes

“Off”

or “

Sile

nced

Av

oid

side

disc

ussio

ns w

hile

oth

ers

spea

king

A

ll qu

estio

ns a

re g

ood

ones

A

ll co

mm

ents

are

appr

ecia

ted

M

ater

ials

and

note

s w

ill b

e in

clud

ed in

Hyd

ro O

ne’s

rate

ap

plic

atio

n an

d w

ill b

e po

sted

on H

ydro

One

’s Re

gula

tory

Web

site

once

app

licat

ion

has

been

file

d:

www.HydroOne

.com

/RegulatoryA

ffairs

4

38

Page 39: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

20

15

-20

19

Cus

tom

D

istr

ibut

ion

Rate

A

pplic

atio

nA

pplic

atio

n Fi

ling T

imel

ine

Dec

embe

r 2, 2

013

Alla

n C

owan

Dire

ctor

, Maj

or

App

licat

ions

39

Page 40: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

6

Applic

atio

n Fi

ling T

imel

ine

Fi

ling

Dx

Rate

App

licat

ion

-Dec

embe

r 19t

h , 20

13

Su

pple

men

tal F

iling

-Ja

nuar

y 31

st , 2

014

20

13 A

ctua

l Res

ults

Upd

ate

-May

201

4

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

40

Page 41: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

20

15

-20

19

Cus

tom

D

istr

ibut

ion

Rate

A

pplic

atio

nRev

enue

Req

uire

men

t &

Com

mon

Cos

tsD

ecem

ber 2

, 201

3G

lenn

Sco

tt

Dire

ctor

, Cor

pora

te

Plan

ning

and

Fin

ance

41

Page 42: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

8

Pres

enta

tion

Ove

rvie

w

O

verv

iew

of r

even

ue re

quire

men

t

O

verv

iew

of r

ate

incr

ease

s

Re

gula

tory

ass

et re

cove

ry

C

apita

l and

OM

&A

exp

endi

ture

s–

Cor

pora

te C

omm

on C

ost d

etai

ls

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

42

Page 43: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Forw

ard

-loo

kin

g F

inanc

ial S

tate

men

tsW

eha

vein

clud

edfo

rwar

d-lo

okin

gsta

tem

ents

inth

ispr

esen

tatio

nth

atar

esu

bjec

tto

risks

,un

certa

intie

san

das

sum

ptio

ns.

Such

info

rmat

ion

repr

esen

tsou

rcu

rrent

view

sba

sed

onin

form

atio

nas

atth

eda

teof

this

repo

rt.A

nysta

tem

entc

onta

ined

inth

isdo

cum

entt

hati

sno

tcur

rent

orhi

storic

alis

afo

rwar

d-lo

okin

gsta

tem

ent.

We

have

base

dth

ese

forw

ard-

look

ing

state

men

tson

histo

rical

expe

rienc

e,cu

rrent

cond

ition

san

dva

rious

assu

mpt

ions

belie

ved

tobe

reas

onab

lein

the

circ

umsta

nces

.A

ctua

lre

sults

coul

ddi

ffer

mat

eria

llyfro

mth

ose

proj

ecte

din

the

forw

ard-

look

ing

state

men

ts.Be

caus

eof

thes

eris

ks,

unce

rtain

ties

and

assu

mpt

ions

,un

due

relia

nce

shou

ldno

tbe

plac

edon

thes

efo

rwar

d-lo

okin

gsta

tem

ents.

Exce

ptto

the

exte

ntre

quire

dby

appl

icab

lese

curit

ies

law

san

dre

gula

tions

,we

unde

rtake

noob

ligat

ion

toup

date

orre

vise

any

ofth

ese

forw

ard-

look

ing

state

men

ts,w

heth

erto

refle

ctne

win

form

atio

n,fu

ture

even

tsor

othe

rwise

.

9D

RAFT

-20

13 C

ON

FIDE

NTI

AL

-Pre

limin

ary

Figu

res

43

Page 44: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Valu

e Pr

opos

ition

Safe

, Re

liabl

e &

A

fford

able

Se

rvic

e

Keep

Rat

es L

ow(a

nnua

l tot

al

bill

impa

ct

at/l

ess

than

in

flatio

n)

Impr

ove

Cus

tom

er

Satis

fact

ion

and

Build

a

Trus

ted

Partn

er

Rela

tions

hip

Pres

erve

Net

In

com

e

Impr

ove

Ope

ratin

g Ef

ficie

ncie

s an

d C

ost S

avin

gs

Full

Visib

ility

on

Ass

ets

and

targ

eted

inve

stmen

ts to

min

imiz

e cu

stom

er

impa

cts

10D

RAFT

-20

13 C

ON

FIDE

NTI

AL

-Pre

limin

ary

Figu

res

44

Page 45: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Cost of D

ebt

4.79% 

Rate Base

$6,477M

Cost of C

apita

l6.76%

Cost of Equ

ity9.71%

Capital Structure

60/40

X

Return on Capital

$438M

Cost of Service

$918M

Income Taxes 

$55M

Revenu

e Re

quire

ment

$1,411M

+ + =

20

15

Dx

Rev

enue

Req

uire

men

t 11D

RAFT

-20

13 C

ON

FIDE

NTI

AL

-Pre

limin

ary

Figu

res

OM&A

$564M

Depreciatio

n$354M+

45

Page 46: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

2.6%

3.3%

0.2%

-0.6

%-0

.3%

12.8

%

4.2%

3.5%

3.6%

3.5%

-1.2

%

-3.3

%

-1.3

%

-1.2

%

1.2%

1.8%

-0.1

%-0

.2%

-10.

0%

-5.0

%

0.0%

5.0%

10.0

%

15.0

%

20.0

%

2013

2014

2015

2016

2017

2018

2019

OM

&A

and

Ext

ern

al R

even

ues

Ra

te B

ase

Sm

art M

ete

r -

OM

&A

Sm

art M

ete

r -

RB

Sm

art G

rid

- O

M&

AS

mar

t Gri

d -

RB

Rid

ers

Load

, R

ate

Cla

ss &

Sea

son

alB

oard

App

rove

d

2.6%

11.5

%

7.4%

3.6%

3.0%

2.9%

1.4%Dis

trib

utio

n Rate

Incr

ease

12D

RAFT

-20

13 C

ON

FIDE

NTI

AL

-Pre

limin

ary

Figu

res

7%

+18.

5%

-7.0

%

46

Page 47: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Rev

enue

Req

uire

men

t

13

$Mill

ions

(F

orec

ast)

20

15

20

16

20

17

20

18

20

19

OM

&A

564

610

614

604

600

Dep

. & A

m.

354

373

391

405

417

Retu

rn O

n D

ebt

186

201

216

234

257

Retu

rn o

n Eq

uity

252

269

288

307

323

Inco

me

Tax

5562

6266

69

Rev

enue

Req

uire

men

t1,4

11

1,5

15

1,5

71

1,6

15

1,6

66

Less

: Ext

erna

l Rev

enue

(45)

(45)

(46)

(45)

(45)

Dist

ribut

ion

Ride

rs8

88

88

Rate

s Rev

enue

Req

uire

men

t1,3

75

1,4

78

1,5

33

1,5

78

1,6

29

Dx

Rate

Incr

ease

11.5

%7.

4%3.

6%3.

0%2.

9%

Rate

Base

6,4

77

6,7

59

7,0

97

7,5

12

7,9

17

Capex

649

655

639

655

669

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

47

Page 48: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Reg

ulato

ry A

sset

Rec

over

y

Net

bal

ance

col

lect

ed o

ver a

5-y

ear p

erio

d*

Incl

udes

RC

VA, M

icro

FIT,

SPC

and

Pro

ject

Def

erra

l bal

ance

s

Reg

ulato

ry A

sset

s as

of D

ecem

ber

31

st, 2

01

3, plu

s fo

reca

sted

inte

rest

($Millions

)Pe

nsio

n55

.6O

EB9.

1Sm

art M

eter

s6.

5D

SC E

xem

ptio

n5.

5

Tax

(20.

7)Re

tail

Settl

emen

t Var

ianc

e A

ccou

nt (R

SVA

)(6

.2)

Smar

t Grid

(5.2

)O

ther

*(4

.2)

TOTA

L40

.4

14D

RAFT

-20

13 C

ON

FIDE

NTI

AL

-Pre

limin

ary

Figu

res

48

Page 49: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

2.6%

3.3%

0.2%

-0.6

%-0

.3%

12.8

%

4.4%

3.7%

3.6%

3.4%

-1.2

%

-3.3

%

-1.3

%

-1.2

%

1.2%

1.8%

-0.2

%

-4.5

%

-0.6

%

3.2%

3.9%

4.1%

-15.

0%

-10.

0%

-5.0

%

0.0%

5.0%

10.0

%

15.0

%

20.0

%

2013

2014

2015

2016

2017

2018

2019

OM

&A

and

Ext

ern

al R

even

ues

Ra

te B

ase

Sm

art M

ete

r -

OM

&A

Sm

art M

ete

r -

RB

Sm

art G

rid

- O

M&

AS

mar

t Gri

d -

RB

Rid

ers

Load

, R

ate

Cla

ss &

Sea

son

al

De

ferr

ed R

even

ue

Re

quire

me

ntB

oard

App

rove

d

2.6%

7.0%

7.0%

7.0%

7.0%

7.0%

1.4%

Smoo

thed

Dx

Rate

Incr

ease

15

-11.

5%

+18.

5%

Def

erre

d Re

venu

e Re

quire

men

t

($

56M

)($

66M

)

($2

1M)

$38M

$105

M

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

49

Page 50: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

16

OM

&A

Ex

pen

ditu

res

Sum

mary

$Mill

ions

(F

orec

ast)

Fore

cast

Bri

dge

Test

Yea

rs

20

13

20

14

20

15

20

16

20

17

2

01

82

01

9

Susta

inin

g31

832

0 32

9 37

4 38

0 36

3 35

8

Dev

elop

men

t12

18

15

18

17

17

18

Ope

ratio

ns23

30

3034

3542

41

Cus

tom

er

Serv

ice

137

134

118

116

114

113

115

Cor

pora

te

Com

mon

Cos

ts &

Oth

er10

374

67

62

62

62

62

Prop

erty

Taxe

s &

Rig

hts

Paym

ents

45

5 5

5 5

5

TOTA

L5

98

58

15

64

61

06

14

60

46

00

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

50

Page 51: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

17

Capita

l Ex

pen

ditu

res

Sum

mary

$Mill

ions

(F

orec

ast)

Fore

cast

Bri

dge

Test

Yea

rs

20

13

20

14

20

15

20

16

20

17

2

01

82

01

9

Susta

inin

g30

3 28

6 30

8 33

5 36

0 38

0 38

3

Dev

elop

men

t19

3 20

0 22

3 20

6 18

6 18

3 19

9

Ope

ratio

ns9

5 9

19

7 7

4

Cus

tom

er

Serv

ice

1623

2310

40

0

Cor

pora

te

Com

mon

Cos

ts &

Oth

er12

8 11

0 85

85

83

84

82

TOTA

L6

49

6

24

64

9

65

5

63

9

65

5

66

9

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

51

Page 52: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

18

Wha

t are

Cor

por

ate

Com

mon

Co

sts?

H

ydro

One

Cor

pora

te C

omm

on C

osts:

OM

&A

−C

orpo

rate

Com

mon

Fun

ctio

ns &

Ser

vice

s (H

R, F

inan

ce, L

aw, R

eal E

state

& F

acili

ties,

etc

.)−

Ass

et M

anag

emen

t −

Info

rmat

ion

Tech

nolo

gy−

Cos

t of S

ales

Capita

l−

Tran

spor

t, W

ork

& S

ervi

ce E

quip

men

t−

Real

Esta

te−

Info

rmat

ion

Tech

nolo

gy

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

52

Page 53: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

19

OM

&A

Cor

por

ate

Com

mon

Cos

ts

$Mill

ions

(F

orec

ast)

Fore

cast

Bri

dge

Test

Yea

rs

20

13

20

14

20

15

20

16

20

17

2

01

82

01

9

Tota

l Tx

& D

xCo

rpor

ate

Co

mm

on C

osts

13

9

14

4

13

7

13

4

13

6

12

6

13

0

Tran

smiss

ion

Allo

catio

n36

71

70

71

73

64

67

Dist

ribut

ion

Allo

catio

n10

374

67

62

62

62

62

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

53

Page 54: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

20

Capita

l Cor

por

ate

Com

mon

Cos

ts

$Mill

ions

(F

orec

ast)

Fore

cast

Bri

dge

Test

Yea

rs

20

13

20

14

20

15

20

16

20

17

2

01

82

01

9

Tota

l Tx

& D

xCo

rpor

ate

Co

mm

on C

osts

19

3

19

6

15

5

15

3

14

9

15

2

14

7

Tran

smiss

ion

Allo

catio

n66

86

69

69

65

68

65

Dist

ribut

ion

Allo

catio

n12

8 11

0 85

85

83

84

82

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

54

Page 55: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

21

Que

stio

ns?

DIS

CL

OSU

RE

NO

TE

:

FOR

WA

RD

LO

OK

ING

STA

TE

ME

NT

SA

ND

INFO

RM

AT

ION

We

have

incl

uded

forw

ard-

look

ing

stat

emen

tsin

this

repo

rtth

atar

esu

bjec

tto

risks

,unc

erta

intie

san

das

sum

ptio

ns.S

uch

info

rmat

ion

repr

esen

tsou

rcur

rent

view

sba

sed

onin

form

atio

nas

atth

eda

teof

this

repo

rt.A

nyst

atem

entc

onta

ined

inth

isdo

cum

entt

hati

sno

tcur

rent

orhi

stor

ical

isa

forw

ard-

look

ing

stat

emen

t.W

eha

veba

sed

thes

efo

rwar

d-lo

okin

gst

atem

ents

onhi

stor

ical

expe

rienc

e,cu

rren

tcon

ditio

nsan

dva

rious

assu

mpt

ions

belie

ved

tobe

reas

onab

lein

the

circ

umst

ance

s.A

ctua

lres

ults

coul

ddi

ffer

mat

eria

llyfr

omth

ose

proj

ecte

din

the

forw

ard-

look

ing

stat

emen

ts.B

ecau

seof

thes

eris

ks,u

ncer

tain

ties

and

assu

mpt

ions

,und

uere

lianc

esh

ould

notb

epl

aced

onth

ese

forw

ard-

look

ing

stat

emen

ts.E

xcep

tto

the

exte

ntre

quire

dby

appl

icab

lese

curit

ies

law

san

dre

gula

tions

,we

unde

rtake

noob

ligat

ion

toup

date

orre

vise

any

ofth

ese

forw

ard-

look

ing

stat

emen

ts,w

heth

erto

refle

ctne

win

form

atio

n,fu

ture

even

tsor

othe

rwis

e.

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

55

Page 56: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

~BREA

K~

56

Page 57: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

20

15

-20

19

Cus

tom

D

istr

ibut

ion

Rate

A

pplic

atio

nCo

re W

ork

Pro

gra

mD

ecem

ber 2

, 201

3

Paul

Bro

wn

Dire

ctor

, Dist

ribut

ion

Ass

et M

anag

emen

t

57

Page 58: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Pres

enta

tion

Ove

rvie

w

O

verv

iew

of O

M&

A E

xpen

ditu

res

−Su

stain

ing,

Dev

elop

men

t, O

pera

ting

and

Cus

tom

er

Serv

ice

deta

ils

O

verv

iew

of C

apita

l Exp

endi

ture

s−

Susta

inin

g, D

evel

opm

ent,

Ope

ratin

g an

d C

usto

mer

Se

rvic

e de

tails

24D

RAFT

-20

13 C

ON

FIDE

NTI

AL

-Pre

limin

ary

Figu

res

58

Page 59: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Forw

ard

-loo

kin

g F

inanc

ial S

tate

men

ts

We

have

incl

uded

forw

ard-

look

ing

state

men

tsin

this

pres

enta

tion

that

are

subj

ect

toris

ks,

unce

rtain

ties

and

assu

mpt

ions

.Su

chin

form

atio

nre

pres

ents

our

curre

ntvi

ews

base

don

info

rmat

ion

asat

the

date

ofth

isre

port.

Any

state

men

tcon

tain

edin

this

docu

men

ttha

tis

notc

urre

ntor

histo

rical

isa

forw

ard-

look

ing

state

men

t.

We

have

base

dth

ese

forw

ard-

look

ing

state

men

tson

histo

rical

expe

rienc

e,cu

rrent

cond

ition

san

dva

rious

assu

mpt

ions

belie

ved

tobe

reas

onab

lein

the

circ

umsta

nces

.A

ctua

lre

sults

coul

ddi

ffer

mat

eria

llyfro

mth

ose

proj

ecte

din

the

forw

ard-

look

ing

state

men

ts.Be

caus

eof

thes

eris

ks,

unce

rtain

ties

and

assu

mpt

ions

,un

due

relia

nce

shou

ldno

tbe

plac

edon

thes

efo

rwar

d-lo

okin

gsta

tem

ents.

Exce

ptto

the

exte

ntre

quire

dby

appl

icab

lese

curit

ies

law

san

dre

gula

tions

,we

unde

rtake

noob

ligat

ion

toup

date

orre

vise

any

ofth

ese

forw

ard-

look

ing

state

men

ts,w

heth

erto

refle

ctne

win

form

atio

n,fu

ture

even

tsor

othe

rwise

.

25D

RAFT

-20

13 C

ON

FIDE

NTI

AL

-Pre

limin

ary

Figu

res

59

Page 60: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

26

Hyd

ro O

ne’s

Dis

trib

utio

n Bus

ines

s

Cust

omer

Base

–A

bout

1.2

mill

ion

custo

mer

s–

Rura

l and

urb

an–

Resid

entia

l and

sm

all b

usin

ess

–Lo

cal d

istrib

utio

n co

mpa

nies

–La

rge

indu

stria

l cus

tom

ers

Gen

erat

ors

conn

ecte

d to

the

distr

ibut

ion

grid

A

sset

s–

Ove

r 120

,000

circ

uit-k

m o

f lin

es (3

200

feed

ers)

–O

ver 1

.6 m

illio

n po

les

–10

04 d

istrib

utio

n sta

tions

–50

kV

or le

ss–

Rura

l sys

tem

with

low

den

sity

thro

ugho

ut th

e pr

ovin

ce–

Radi

al s

yste

m w

ith li

mite

d tra

nsfe

r cap

abili

ty

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

60

Page 61: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

27

Mana

gin

g D

istr

ibut

ion

Ass

ets

Sy

stem

inve

stmen

t stra

tegi

es to

ens

ure

safe

, rel

iabl

e an

d ef

ficie

nt p

ower

del

iver

y an

d to

cre

ate

valu

e fo

r cu

stom

ers

D

evel

op p

roje

cts

and

prog

ram

s to

:–

Add

ress

cus

tom

er a

nd s

yste

m g

row

th n

eeds

–Re

new

ass

ets

at th

eir e

nd o

f life

to e

nsur

e pu

blic

/wor

ker

safe

ty a

nd s

ervi

ce c

ontin

uity

–Im

prov

e re

liabi

lity/

effic

ienc

y

–M

oder

nize

the

distr

ibut

ion

syste

m to

add

cus

tom

er v

alue

–Ef

fect

ivel

y re

spon

d to

unp

lann

ed s

yste

m e

vent

s

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

61

Page 62: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

28

OM

&A

Ex

pen

ditu

res

Sum

mary

$Mill

ions

(F

orec

ast)

Fore

cast

Bri

dge

Test

Yea

rs

20

13

20

14

20

15

20

16

20

17

2

01

82

01

9

Susta

inin

g31

832

0 32

9 37

4 38

0 36

3 35

8

Dev

elop

men

t12

18

15

18

17

17

18

Ope

ratio

ns23

30

3034

3542

41

Cus

tom

er

Serv

ice

137

134

118

116

114

113

115

Cor

pora

te

Com

mon

Cos

ts &

Oth

er10

374

67

62

62

62

62

Prop

erty

Taxe

s &

Rig

hts

Paym

ents

45

5 5

5 5

5

TOTA

L5

98

58

15

64

61

06

14

60

46

00

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

62

Page 63: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

29

Sust

ain

ing O

M&

A

$Mill

ions

(F

orec

ast)

Fore

cast

Bri

dge

Test

Yea

rs

20

13

20

14

20

15

20

16

20

17

2

01

82

01

9St

atio

ns22

2828

2829

2928

Lines

148

134

141

150

152

155

157

Met

erin

g14

1919

1918

1919

Vege

tatio

n M

anag

emen

t13

413

914

217

818

016

115

3

TOTA

L3

18

32

03

29

37

43

80

36

33

58

Hyd

ro O

ne S

usta

inin

g O

M&

A C

osts

incl

ude:

Pla

nned

& C

orre

ctiv

e M

aint

enan

ce; T

roub

le C

all R

espo

nse;

Line

Cle

arin

g &

Bru

sh C

ontro

l; C

able

Loc

ates

; D

iscon

nect

s/Re

conn

ects;

and

Env

ironm

enta

l & W

aste

Man

agem

ent

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

63

Page 64: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Veg

etatio

n M

ana

gem

ent

30

Tr

ees

wer

e th

e la

rges

t con

tribu

tor (

at 4

4%) t

o H

ydro

O

ne C

orpo

rate

SA

IDI i

n th

e 20

07-1

2 pe

riod.

Sh

orte

r veg

etat

ion

man

agem

ent c

ycle

dur

atio

ns h

as

been

dem

onstr

ated

to lo

wer

SA

IDI.

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

64

Page 65: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

31

$Mill

ions

(F

orec

ast)

Fore

cast

Bri

dge

Test

Yea

rs

20

13

20

14

20

15

20

16

20

17

2

01

82

01

9

Dev

elop

men

t12

18

15

18

17

17

18

Ope

ratin

g23

30

30

34

35

4241

Cus

tom

er S

ervi

ce13

713

4 11

8 11

6 11

5 11

3 11

5

Dev

elop

men

t, O

per

atin

g,

Cust

omer

Ser

vice

OM

&A

Hyd

ro O

ne D

evel

opm

ent

OM

&A

Cos

ts in

clud

e: E

ngin

eerin

g &

Tech

nica

l St

udie

s (in

clud

ing

Smar

t Grid

Stu

dies

); St

anda

rds

& Te

chno

logy

Sup

port;

and

D

istrib

uted

Gen

erat

ion

Con

nect

ions

Sup

port

Hyd

ro O

ne O

per

atin

g O

M&

A C

osts

incl

ude:

Ope

ratio

ns S

uppo

rt; M

aint

enan

ce

of O

pera

ting

Infra

struc

ture

; and

Env

ironm

enta

l, H

ealth

& S

afet

y

Hyd

ro O

ne C

usto

mer

Ser

vice

OM

&A

Cos

ts in

clud

e: C

usto

mer

Ser

vice

s; S

mar

t G

rid P

ilot;

and

Con

serv

atio

n &

Dem

and

Man

agem

ent

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

65

Page 66: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Smart

Gri

d O

M&

A E

xpen

ditu

res 32

Total Smart 

Grid

 Expe

nditu

res

Smart G

rid Pilot

Deployment

+

$Mill

ions

(F

orec

ast)

Fore

cast

Bri

dge

Test

Yea

rs

20

13

20

14

20

15

20

16

20

17

2

01

82

01

9Sm

art G

rid P

ilot

(incl

uded

in C

usto

mer

Ser

vice

)7

95

42

00

Dep

loym

ent

(incl

uded

in O

pera

ting)

06

59

1017

15

TOTA

L7

15

10

13

12

17

15

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

66

Page 67: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

A

ging

ass

ets

and

syste

mic

pro

blem

s –

Larg

e sc

ale

testi

ng o

f tra

nsfo

rmer

s fo

r PC

B co

ntam

inat

ion

–In

crea

sing

focu

s on

def

ect c

orre

ctio

ns

Re

liabi

lity

impr

ovem

ents

and

long

-term

cos

t opt

imiz

atio

n–

Add

ress

ing

vege

tatio

n m

aint

enan

ce b

ackl

ogs

and

mai

ntai

ning

an

eigh

t yea

r cle

arin

g cy

cle

33

Sour

ces

of C

hang

e to

OM

&A

Cos

tM

ain

Driv

ers

for Y

ear-o

ver-Y

ear C

hang

es

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

67

Page 68: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

34

Capita

l Ex

pen

ditu

res

Sum

mary

$Mill

ions

(F

orec

ast)

Fore

cast

Bri

dge

Test

Yea

rs

20

13

20

14

20

15

20

16

20

17

2

01

82

01

9

Susta

inin

g30

3 28

6 30

8 33

5 36

0 38

0 38

3

Dev

elop

men

t19

3 20

0 22

3 20

6 18

6 18

3 19

9

Ope

ratio

ns9

5 9

19

7 7

4

Cus

tom

er

Serv

ice

1623

2310

40

0

Cor

pora

te

Com

mon

Cos

ts &

Oth

er12

8 11

0 85

85

83

84

82

TOTA

L6

49

6

24

64

9

65

5

63

9

65

5

66

9

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

68

Page 69: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

35

Sust

ain

ing C

apita

l

$Mill

ions

(F

orec

ast)

Fore

cast

Bri

dge

Test

Yea

rs

20

13

20

14

20

15

20

16

20

17

2

01

82

01

9St

atio

ns48

5164

6869

7677

Lines

213

204

228

247

267

283

296

Met

erin

g43

3217

2124

2111

TOTA

L303

286

308

335

360

380

383

Hyd

ro O

ne S

usta

inin

g C

apita

l Cos

ts in

clud

e: S

tatio

n Re

furb

ishm

ents;

Mob

ile

Uni

t Sub

statio

ns; C

ompo

nent

Rep

lace

men

ts; T

roub

le C

all &

Sto

rm D

amag

e Re

spon

se; L

arge

Sus

tain

ing

Line

Proj

ects;

and

Met

er U

pgra

des

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

69

Page 70: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Dis

trib

utio

n W

ood P

oles

36

To

tal F

leet

of D

istrib

utio

n W

ood

Pole

s is

appr

oxim

atel

y 1.

6 m

illio

n

Expe

cted

Ser

vice

Life

of D

istrib

utio

n W

ood

Pole

is 6

2 ye

ars

A

ppro

xim

atel

y 20

,000

pol

es a

re in

stalle

d ea

ch y

ear (

new

insta

llatio

ns &

en

d of

life

repl

acem

ent)

H

ydro

One

is p

ropo

sing

incr

ease

d fu

ndin

g to

add

ress

pre

mat

ure

deca

y iss

ues

and

miti

gate

risk

of t

he a

ppro

achi

ng b

ow w

ave

of p

oles

reac

hing

ex

pect

ed s

ervi

ce li

fe o

ver t

he p

erio

d.D

RAFT

-20

13 C

ON

FIDE

NTI

AL

-Pre

limin

ary

Figu

res

70

Page 71: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Dis

trib

utio

n St

atio

ns

37

1,

004

Dist

ribut

ion

and

Regu

latin

g St

atio

n Fa

cilit

ies

Ex

pect

ed S

ervi

ce L

ife o

f Dist

ribut

ion

and

Regu

latin

g St

atio

ns is

50

year

s

Hist

oric

al R

epla

cem

ent R

ate

has

been

app

rox.

4 s

tatio

ns/y

ear

H

ydro

One

pro

posin

g in

crea

sed

fund

ing

to m

anag

e de

mog

raph

ic

pres

sure

s an

d m

itiga

te ri

sk o

f the

app

roac

hing

bow

wav

e of

sta

tions

re

achi

ng e

xpec

ted

serv

ice

life

over

the

perio

d.

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

0

100

200

300

400

0-20

21-3

031

-40

41-5

0>5

0

25%

of p

opul

atio

n is

beyo

nd e

xpec

ted

serv

ice

life

Age

Prof

ile

# of stations

Age

Gro

up

71

Page 72: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

38

Dev

elop

men

t Ca

pita

l$M

illio

ns

(For

ecas

t)Fo

reca

stBri

dge

Test

Yea

rs

20

13

20

14

20

15

20

16

20

17

2

01

82

01

9C

onne

ctio

ns &

Upg

rade

s10

410

610

911

211

611

912

3

Syste

m C

apab

ility

Re

info

rcem

ent

6561

8172

6162

74

Gen

erat

ion

Con

nect

ions

2033

3323

92

2

Who

lesa

le

Reve

nue

Met

ers

30

00

00

0

TOTA

L1

93

20

02

23

20

61

86

18

31

99

Hyd

ro O

ne D

evel

opm

ent

Capita

l Cos

ts in

clud

e: N

ew C

onne

ctio

ns; U

pgra

des

Driv

en b

y Lo

ad G

row

th; R

elia

bilit

y Im

prov

emen

ts; a

nd C

apita

l Con

tribu

tions

to n

ew

Tx C

onne

ctio

n C

apac

ity

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

72

Page 73: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

39

Oper

atin

g &

Cus

tom

er S

ervi

ce

Capita

l$M

illio

ns

(For

ecas

t)Fo

reca

stBri

dge

Test

Yea

rs

20

13

20

14

20

15

20

16

20

17

2

01

82

01

9

Ope

ratin

g9

59

197

7 4

Cus

tom

er S

ervi

ce16

2323

104

00

Hyd

ro O

ne O

per

atin

g C

apita

l Cos

ts in

clud

e: U

pgra

des

and

expa

nsio

ns to

the

oper

atin

g in

frastr

uctu

re a

nd c

ontro

l fac

ilitie

s.

Hyd

ro O

ne C

usto

mer

Ser

vice

Capita

l Cos

ts in

clud

e: S

mar

t Grid

Pilo

t

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

73

Page 74: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Smart

Gri

d C

apita

l Ex

pen

ditu

res 40

Total Smart 

Grid

 Expe

nditu

res

Smart G

rid Pilot

Deployment

+

$Mill

ions

(F

orec

ast)

Fore

cast

Bri

dge

Test

Yea

rs

20

13

20

14

20

15

20

16

20

17

2

01

82

01

9Sm

art G

rid P

ilot

(incl

uded

in C

usto

mer

Ser

vice

)16

2323

104

00

Dep

loym

ent

(incl

uded

in S

usta

inin

g)0

67

1516

2020

TOTA

L1

62

93

02

52

02

02

0

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

74

Page 75: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

A

ging

ass

ets

and

syste

mic

pro

blem

s –

Incr

easin

g th

e re

plac

emen

t rat

e of

woo

d po

les

–Re

furb

ishin

g ag

ing

distr

ibut

ion

statio

ns

–Re

plac

ing

PCB

cont

amin

ated

equ

ipm

ent

Re

liabi

lity

impr

ovem

ents

and

long

-term

cos

t opt

imiz

atio

n–

Incr

easin

g nu

mbe

r of l

ine

refu

rbish

men

t pro

ject

s

41

Sour

ces

of C

hang

e to

Capita

l Cos

tM

ain

Driv

ers

for Y

ear-o

ver-Y

ear C

hang

es

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

75

Page 76: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

42

Que

stio

ns?

DIS

CL

OSU

RE

NO

TE

:

FOR

WA

RD

LO

OK

ING

STA

TE

ME

NT

SA

ND

INFO

RM

AT

ION

We

have

incl

uded

forw

ard-

look

ing

stat

emen

tsin

this

repo

rtth

atar

esu

bjec

tto

risks

,unc

erta

intie

san

das

sum

ptio

ns.S

uch

info

rmat

ion

repr

esen

tsou

rcur

rent

view

sba

sed

onin

form

atio

nas

atth

eda

teof

this

repo

rt.A

nyst

atem

entc

onta

ined

inth

isdo

cum

entt

hati

sno

tcur

rent

orhi

stor

ical

isa

forw

ard-

look

ing

stat

emen

t.W

eha

veba

sed

thes

efo

rwar

d-lo

okin

gst

atem

ents

onhi

stor

ical

expe

rienc

e,cu

rren

tcon

ditio

nsan

dva

rious

assu

mpt

ions

belie

ved

tobe

reas

onab

lein

the

circ

umst

ance

s.A

ctua

lres

ults

coul

ddi

ffer

mat

eria

llyfr

omth

ose

proj

ecte

din

the

forw

ard-

look

ing

stat

emen

ts.B

ecau

seof

thes

eris

ks,u

ncer

tain

ties

and

assu

mpt

ions

,und

uere

lianc

esh

ould

notb

epl

aced

onth

ese

forw

ard-

look

ing

stat

emen

ts.E

xcep

tto

the

exte

ntre

quire

dby

appl

icab

lese

curit

ies

law

san

dre

gula

tions

,we

unde

rtake

noob

ligat

ion

toup

date

orre

vise

any

ofth

ese

forw

ard-

look

ing

stat

emen

ts,w

heth

erto

refle

ctne

win

form

atio

n,fu

ture

even

tsor

othe

rwis

e.

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

76

Page 77: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

20

15

-20

19

Cus

tom

D

istr

ibut

ion

Rate

A

pplic

atio

nCo

st A

lloca

tion

/ Rate

Des

ign

Dec

embe

r 2, 2

013

Hen

ry A

ndré

Man

ager

, Dist

ribut

ion

Pric

ing

77

Page 78: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Pres

enta

tion

Ove

rvie

w

Lo

ad F

orec

ast

C

usto

mer

Cla

ssifi

catio

n

C

ost A

lloca

tion

Ra

te D

esig

n

Bi

ll Im

pact

s

44D

RAFT

-20

13 C

ON

FIDE

NTI

AL

-Pre

limin

ary

Figu

res

78

Page 79: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Forw

ard

-loo

kin

g F

inanc

ial S

tate

men

tsW

eha

vein

clud

edfo

rwar

d-lo

okin

gsta

tem

ents

inth

ispr

esen

tatio

nth

atar

esu

bjec

tto

risks

,un

certa

intie

san

das

sum

ptio

ns.

Such

info

rmat

ion

repr

esen

tsou

rcu

rrent

view

sba

sed

onin

form

atio

nas

atth

eda

teof

this

repo

rt.A

nysta

tem

entc

onta

ined

inth

isdo

cum

entt

hati

sno

tcur

rent

orhi

storic

alis

afo

rwar

d-lo

okin

gsta

tem

ent.

We

have

base

dth

ese

forw

ard-

look

ing

state

men

tson

histo

rical

expe

rienc

e,cu

rrent

cond

ition

san

dva

rious

assu

mpt

ions

belie

ved

tobe

reas

onab

lein

the

circ

umsta

nces

.A

ctua

lre

sults

coul

ddi

ffer

mat

eria

llyfro

mth

ose

proj

ecte

din

the

forw

ard-

look

ing

state

men

ts.Be

caus

eof

thes

eris

ks,

unce

rtain

ties

and

assu

mpt

ions

,un

due

relia

nce

shou

ldno

tbe

plac

edon

thes

efo

rwar

d-lo

okin

gsta

tem

ents.

Exce

ptto

the

exte

ntre

quire

dby

appl

icab

lese

curit

ies

law

san

dre

gula

tions

,we

unde

rtake

noob

ligat

ion

toup

date

orre

vise

any

ofth

ese

forw

ard-

look

ing

state

men

ts,w

heth

erto

refle

ctne

win

form

atio

n,fu

ture

even

tsor

othe

rwise

.

45D

RAFT

-20

13 C

ON

FIDE

NTI

AL

-Pre

limin

ary

Figu

res

79

Page 80: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Load F

orec

ast

Ass

umptio

nsK

ey C

hang

es

46D

RAFT

-20

13 C

ON

FIDE

NTI

AL

-Pre

limin

ary

Figu

res

Sa

me

load

fore

cast

met

hodo

logy

use

d as

in p

revi

ous

DX

rate

cas

es

A

ll fo

reca

sts a

re w

eath

er-n

orm

al

O

ntar

io e

cono

my

is fo

reca

st to

gro

w o

n av

erag

e 2.

4% o

ver t

he 2

015-

2019

per

iod

C

DM

fore

casts

are

con

siste

nt w

ith th

e cu

rrent

Lon

g-Te

rm E

nerg

y Pl

an

Sm

art m

eter

hou

rly d

ata

was

use

d in

the

load

pro

file

anal

ysis

by ra

te c

lass

80

Page 81: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

47

20

15

-20

19

Loa

d F

orec

ast

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

GW

h

81

Page 82: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Cust

omer

Cla

ssif

icatio

n

Boa

rd-d

irec

ted R

ate

Cla

ss R

evie

w

–M

any

custo

mer

s w

ill s

ee lo

wer

bill

s as

a re

sult

of th

e ch

ange

how

ever

rate

s ac

ross

all

clas

ses

will

incr

ease

by

3.4%

to h

old

reve

nue

requ

irem

ent n

eutra

l

Boa

rd-d

irec

ted r

evie

w o

f Se

aso

nal c

usto

mer

cla

ss–

Mov

ing

~11k

Sea

sona

l cus

tom

ers

(out

of 1

57k)

with

con

sum

ptio

n pa

ttern

sim

ilar t

o ye

ar-ro

und

custo

mer

s to

resid

entia

l cla

sses

–D

ecre

ase

of $

6.7M

in re

venu

e w

ill re

sult

in a

vera

ge in

crea

se o

f 0.5

% a

cros

s

all r

ate

clas

ses

N

ew U

SL r

ate

cla

ss p

er B

oard

rep

ort

48D

RAFT

-20

13 C

ON

FIDE

NTI

AL

-Pre

limin

ary

Figu

res

# o

f Cu

stom

ers

% o

f Cu

stom

ers

Rev

enue

Im

pact

($

M)

Tota

l1

,22

2,5

92

10

0%

No

Cha

nge

1,08

7,34

589

%

Chang

e1

35

,24

71

1%

(39

.7)

Low

er R

ates

111,

562

9%(8

0.9)

Hig

her R

ates

23,6

852%

41.2

82

Page 83: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Cost

Allo

catio

n

U

sing

Boar

d la

test

CA

M

U

pdat

ed c

usto

mer

load

pro

files

In

corp

orat

ed D

ensit

y Fa

ctor

s w

ithin

CA

M

Im

prov

emen

ts to

trac

king

of c

osts

by U

SofA

U

pdat

ed B

illin

g an

d Se

rvic

es fa

ctor

s

A

ddre

ssed

# o

f iss

ues

raise

d at

pre

viou

s ap

plic

atio

ns

49D

RAFT

-20

13 C

ON

FIDE

NTI

AL

-Pre

limin

ary

Figu

res

83

Page 84: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Rate

Des

ign

In

crea

sing

shar

e of

reve

nues

reco

vere

d vi

a fix

ed

char

ges

Br

ingi

ng re

venu

e-to

-cos

t rat

ios

for a

ll cl

asse

s w

ithin

1.

02 to

0.9

8 ov

er 5

yea

rs

N

ew R

ider

s–

defe

rral/

varia

nce

acco

unt r

ider

–sm

ooth

ing

rider

RT

SR u

pdat

ed to

refle

ct p

ropo

sed

2014

Pro

vinc

ial

Tran

smiss

ion

rate

s

50D

RAFT

-20

13 C

ON

FIDE

NTI

AL

-Pre

limin

ary

Figu

res

84

Page 85: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Ave

rage

2015

Bill

Im

pact

Co

mpon

ents

51D

RAFT

-20

13 C

ON

FIDE

NTI

AL

-Pre

limin

ary

Figu

res

Dis

trib

utio

n Im

pact

Tota

l Bill

Im

pact

Reve

nue

Requ

irem

ent

15.5

%5.

2%Ra

te C

lass

Rev

iew

, Sea

sona

l Rev

iew

& L

oad

Fore

cast

1.8%

0.6%

Net

Varia

nce/

Def

erra

l Rid

ers

-5.8

%-1

.9%

Smoo

thin

g Ri

der

-4.5

%-1

.6%

Fixe

d/Vo

lum

etric

Cha

nges

No

Impa

ctRe

venu

e-to

-Cos

t Rat

ioC

hang

esN

o Im

pact

TOTA

L7

.0%

2.3

%

85

Page 86: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

52

“Typ

ical”

Tot

al B

ill Im

pact

s by

Rate

Cla

ssRate

Cla

ssBill

A

ssum

ptio

n2

01

52

01

62

01

72

01

82

01

9

UR

800

kWh

-3.2

%0.

6%0.

4%0.

4%0.

7%

R1

800

kWh

-1.0

%1.

4%0.

9%0.

7%1.

1%

R2

800

kWh

2.9%

4.4%

4.5%

5.0%

5.1%

Seaso

nal

400

kWh

2.9%

4.2%

4.6%

4.9%

5.0%

Gse

2,00

0 kW

h3.

5%2.

4%2.

5%2.

7%2.

8%

Uge

2,00

0 kW

h8.

3%1.

5%2.

4%2.

7%2.

5%

GSd

35,0

00 k

Wh

120

kW5.

7%2.

9%4.

2%4.

7%4.

3%

Ugd

35,0

00 k

Wh

120

kW4.

9%1.

9%2.

8%3.

2%2.

9%

St. Lg

t50

0 kW

h9.

5%4.

0%4.

5%4.

5%4.

4%

Sen.

Lgt

50 k

Wh

11.6

%8.

8%9.

2%9.

2%8.

0%

USL

500

kWh

1.7%

-0.3

%1.

4%0.

5%1.

3%

Dgen

2,00

0 kW

h17

.8%

15.1

%13

.7%

12.3

%9.

2%

ST50

0,00

0 kW

h1,

000k

W2.

1%0.

4%0.

3%0.

4%0.

4%

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

86

Page 87: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

53

Que

stio

ns?

DIS

CL

OSU

RE

NO

TE

:

FOR

WA

RD

LO

OK

ING

STA

TE

ME

NT

SA

ND

INFO

RM

AT

ION

We

have

incl

uded

forw

ard-

look

ing

stat

emen

tsin

this

repo

rtth

atar

esu

bjec

tto

risks

,unc

erta

intie

san

das

sum

ptio

ns.S

uch

info

rmat

ion

repr

esen

tsou

rcur

rent

view

sba

sed

onin

form

atio

nas

atth

eda

teof

this

repo

rt.A

nyst

atem

entc

onta

ined

inth

isdo

cum

entt

hati

sno

tcur

rent

orhi

stor

ical

isa

forw

ard-

look

ing

stat

emen

t.W

eha

veba

sed

thes

efo

rwar

d-lo

okin

gst

atem

ents

onhi

stor

ical

expe

rienc

e,cu

rren

tcon

ditio

nsan

dva

rious

assu

mpt

ions

belie

ved

tobe

reas

onab

lein

the

circ

umst

ance

s.A

ctua

lres

ults

coul

ddi

ffer

mat

eria

llyfr

omth

ose

proj

ecte

din

the

forw

ard-

look

ing

stat

emen

ts.B

ecau

seof

thes

eris

ks,u

ncer

tain

ties

and

assu

mpt

ions

,und

uere

lianc

esh

ould

notb

epl

aced

onth

ese

forw

ard-

look

ing

stat

emen

ts.E

xcep

tto

the

exte

ntre

quire

dby

appl

icab

lese

curit

ies

law

san

dre

gula

tions

,we

unde

rtake

noob

ligat

ion

toup

date

orre

vise

any

ofth

ese

forw

ard-

look

ing

stat

emen

ts,w

heth

erto

refle

ctne

win

form

atio

n,fu

ture

even

tsor

othe

rwis

e.

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

87

Page 88: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

©201

3 Nav

igant

Cons

ulting

Ltd.

Co

nfide

ntial

and p

ropr

ietar

y. Do

not d

istrib

ute or

copy

.

ENER

GY

DISP

UTES

& IN

VEST

IGAT

IONS

ECO

NOM

ICS

• F

INAN

CIAL

ADV

ISO

RY •

MAN

AGEM

ENT

CONS

ULTI

NG

Decem

ber 2

, 2013

Line Loss Study Update

Prepared for Hydro One Networks, Inc.

88

Page 89: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

55©2

013 N

aviga

nt Co

nsult

ing L

td.

Confi

denti

al an

d pro

priet

ary.

Do no

t dist

ribute

or co

py.

EN

ER

GYDISC

USSI

ON D

RAFT

»Init

ial fo

cus w

as on

2012

beca

use o

f the a

vaila

bility

of ho

urly

data

(from

smar

t mete

rs an

d inte

rval

meter

s) re

pres

entin

g the

majo

rity (7

2%) o

f Hyd

ro O

ne cu

stome

rs’ el

ectric

ity co

nsum

ption

»The

re ar

e six

major

comp

onen

ts to

the lo

ss ca

lculat

ion

Navigant was retained to calculate actual system‐wide losses from 2010 to 

2012 and to recommend a methodology for Hydro One going forward

Line Loss S

tudy Upd

ate PU

RCHA

SES

CONS

UMPT

ION

IESO

Se

ttleme

nt Da

ta(m

onthl

y, da

ily)

Distr

ibuted

Ge

nera

tion

(mon

thly)

Tran

sfers

from

Host

Distr

ibutor

s(m

onthl

y)

89%

9%2%

% of

Total

Pur

chas

es72

%27

%1%

% of

Total

Con

sump

tion

Stre

et an

d Se

ntine

l Lig

hting

(hou

rly es

t.)

Smar

t / Int

erva

l Me

tered

(hou

rly)

‘Matc

h’ to

custo

mers

with

hour

ly da

ta to

estim

ate

unbil

led in

2012

Bulk

Meter

ed(b

illing

perio

d)

89

Page 90: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

56©2

013 N

aviga

nt Co

nsult

ing L

td.

Confi

denti

al an

d pro

priet

ary.

Do no

t dist

ribute

or co

py.

EN

ER

GYDISC

USSI

ON D

RAFT

»This

is no

t the s

tanda

rd ap

proa

ch us

ed in

the i

ndus

try»M

ost u

tilitie

s rely

on co

nsum

ption

data

from

their b

illing

syste

m–

Actua

l con

sump

tion f

or a

given

custo

mer w

ithin

a yea

r, as

mea

sure

d by t

he co

nsum

ption

that

occu

rs be

twee

n the

first

and l

ast a

ctual

meter

read

with

in the

year

, is au

gmen

ted w

ith:

(i)an

estim

ate of

the p

ropo

rtion o

f con

sump

tion i

n the

last

billin

g cyc

le be

fore t

he fir

st me

ter re

ad th

at oc

curre

d wi

thin t

he ye

ar an

d(ii)

an es

timate

of un

billed

cons

umpti

on af

ter th

e las

t actu

al me

ter re

ad–

Unbil

led co

nsum

ption

is ty

picall

y esti

mated

base

d on a

n ind

ividu

al cu

stome

r’s pr

ior ye

ar or

prior

billin

g pe

riod c

onsu

mptio

n

»Usin

g this

stan

dard

appr

oach

cumu

lative

ly ov

er a

numb

er of

year

s, the

perce

ntage

of c

onsu

mptio

n tha

t is ‘e

stima

ted’ is

sign

ifican

tly re

duce

d (e.g

. ove

r one

year

it mi

ght r

epre

sent

~8%

, but

over

five

year

s it w

ould

be ap

prox

imate

ly ~1

.5%)

Navigant’s calculation of actual losses in 2012 required the collation and 

analysis of a large quantity of hourly consumption data

Line Loss S

tudy Upd

ate

Jan 1

Dec 3

1Fir

st ac

tual m

eter r

ead w

ithin

the pe

riod

Last

actua

l mete

r rea

d with

in the

perio

d

Actua

l Con

sump

tion

Estim

ate of

Unb

illed C

onsu

mptio

nPr

opor

tion o

f con

sump

tion i

n prio

r billi

ng cy

cle w

ithin

the ye

ar

90

Page 91: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

57©2

013 N

aviga

nt Co

nsult

ing L

td.

Confi

denti

al an

d pro

priet

ary.

Do no

t dist

ribute

or co

py.

EN

ER

GYDISC

USSI

ON D

RAFT

»Hyd

ro O

ne’s

new

CIS

is ca

pable

of

deter

minin

g unb

illed c

onsu

mptio

n for

each

of

Hydr

o One

’s ~1

.2 mi

llion c

ustom

ers a

s of

Dece

mber

31 of

each

year

»The

CIS

uses

custo

mer c

onsu

mptio

n data

by

billin

g cyc

le to

estim

ate un

billed

cons

umpti

on

and r

even

ue on

a mo

nthly/

annu

al ba

sis»T

he sy

stem

deve

lops a

kilow

att-h

our p

er da

y me

tric du

ring a

spec

ified b

ase p

eriod

and

appli

es it

to un

billed

perio

d–

The b

ase p

eriod

is de

velop

ed us

ing on

e of

three

meth

ods,

depe

nding

on th

e ava

ilabil

ity of

da

ta in

the sy

stem

(pict

ured

, to th

e righ

t)

»Nav

igant

expe

cts th

at thi

s app

roac

h will

yield

simila

r res

ults w

hen c

ompa

red t

o the

appr

oach

im

pleme

nted u

sing 2

012 h

ourly

cons

umpti

on

data

Going forward, Navigant recommends that Hydro One use the 

capabilities of its new CIS to determine actual losses on an annual basis

Line Loss S

tudy Upd

ate

•Ba

sed

on ac

tual m

eter r

eads

•If a

n actu

al me

ter re

ad is

not

avail

able

the sy

stem

will m

ove

to the

next

meter

read

•Sy

stem

adjus

ts for

chan

ges

billin

g cyc

le len

gth

•If a

full b

illing

perio

d is n

ot av

ailab

le, sy

stem

will p

ro-ra

te the

cons

umpti

on ba

sed o

n the

me

ter re

ad da

ta av

ailab

le

•Sy

stem

will e

stima

te co

nsum

ption

using

a cu

stome

r pro

file de

velop

ed

for ea

ch ra

te cla

ss (e

.g. R

1, R2

, Sea

sona

l, etc.

)

1. Co

nsum

ptio

n in

th

e sam

e billi

ng

perio

d in

the

prev

ious

year

, or

2. Co

nsum

ptio

n in

th

e pre

vious

billi

ng

perio

d, o

r 3. Co

nsum

ptio

n es

timat

ion

by

cust

omer

clas

s

91

Page 92: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

58©2

013 N

aviga

nt Co

nsult

ing L

td.

Confi

denti

al an

d pro

priet

ary.

Do no

t dist

ribute

or co

py.

EN

ER

GYDISC

USSI

ON D

RAFT

»The

amou

nt of

hour

ly co

nsum

ption

data

for H

ydro

One

custo

mers

decli

nes p

rior t

o 201

2–

Inter

val m

etere

d cus

tomer

s, tho

se fo

r who

m ho

urly

cons

umpti

on da

ta wo

uld be

avail

able

throu

ghou

t the

perio

d, re

pres

ent ~

20%

of to

tal co

nsum

ption

–Cu

stome

rs wi

th sm

art m

eters

and a

utoma

ted m

eter r

eads

in 20

12 re

pres

ent ~

50%

of co

nsum

ption

»As t

he am

ount

of ho

urly

data

avail

able

decli

nes,

the re

lianc

e on b

illing

cycle

data

incre

ases

»As a

resu

lts, N

aviga

nt re

comm

ends

calcu

lating

the a

ctual

losse

s in 2

010 a

nd 20

11 us

ing an

ap

proa

ch co

nsist

ent w

ith th

e app

roac

h tha

t will

be us

ed go

ing fo

rwar

d

»Nav

igant

expe

cts th

at thi

s app

roac

h will

yield

simila

r res

ults w

hen c

ompa

red t

o the

appr

oach

im

pleme

nted u

sing 2

012 h

ourly

cons

umpti

on da

ta

The level of hourly data that was used to calculate actual losses in 2012 is 

not available for prior years

Line Loss S

tudy Upd

ate

92

Page 93: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

59

Que

stio

ns?

DIS

CL

OSU

RE

NO

TE

:

FOR

WA

RD

LO

OK

ING

STA

TE

ME

NT

SA

ND

INFO

RM

AT

ION

We

have

incl

uded

forw

ard-

look

ing

stat

emen

tsin

this

repo

rtth

atar

esu

bjec

tto

risks

,unc

erta

intie

san

das

sum

ptio

ns.S

uch

info

rmat

ion

repr

esen

tsou

rcur

rent

view

sba

sed

onin

form

atio

nas

atth

eda

teof

this

repo

rt.A

nyst

atem

entc

onta

ined

inth

isdo

cum

entt

hati

sno

tcur

rent

orhi

stor

ical

isa

forw

ard-

look

ing

stat

emen

t.W

eha

veba

sed

thes

efo

rwar

d-lo

okin

gst

atem

ents

onhi

stor

ical

expe

rienc

e,cu

rren

tcon

ditio

nsan

dva

rious

assu

mpt

ions

belie

ved

tobe

reas

onab

lein

the

circ

umst

ance

s.A

ctua

lres

ults

coul

ddi

ffer

mat

eria

llyfr

omth

ose

proj

ecte

din

the

forw

ard-

look

ing

stat

emen

ts.B

ecau

seof

thes

eris

ks,u

ncer

tain

ties

and

assu

mpt

ions

,und

uere

lianc

esh

ould

notb

epl

aced

onth

ese

forw

ard-

look

ing

stat

emen

ts.E

xcep

tto

the

exte

ntre

quire

dby

appl

icab

lese

curit

ies

law

san

dre

gula

tions

,we

unde

rtake

noob

ligat

ion

toup

date

orre

vise

any

ofth

ese

forw

ard-

look

ing

stat

emen

ts,w

heth

erto

refle

ctne

win

form

atio

n,fu

ture

even

tsor

othe

rwis

e.

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

93

Page 94: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

~LU

NCH

~

94

Page 95: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

20

15

-20

19

Cus

tom

D

istr

ibut

ion

Rate

A

pplic

atio

nCu

stom

Fra

mew

ork

:A

dju

stm

ents

& R

epor

ting

Dec

embe

r 2, 2

013

Alla

n C

owan

Dire

ctor

, Maj

orA

pplic

atio

ns

95

Page 96: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Pres

enta

tion

Ove

rvie

w

A

nnua

l Rep

ortin

g/O

utco

me

Mea

sure

s

A

nnua

l Adj

ustm

ents

O

ff Ra

mps

A

djus

tmen

ts O

utsid

e of

Nor

mal

Cou

rse

of B

usin

ess

62D

RAFT

-20

13 C

ON

FIDE

NTI

AL

-Pre

limin

ary

Figu

res

96

Page 97: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Forw

ard

-loo

kin

g F

inanc

ial S

tate

men

ts

We

have

incl

uded

forw

ard-

look

ing

state

men

tsin

this

pres

enta

tion

that

are

subj

ect

toris

ks,

unce

rtain

ties

and

assu

mpt

ions

.Su

chin

form

atio

nre

pres

ents

our

curre

ntvi

ews

base

don

info

rmat

ion

asat

the

date

ofth

isre

port.

Any

state

men

tcon

tain

edin

this

docu

men

ttha

tis

notc

urre

ntor

histo

rical

isa

forw

ard-

look

ing

state

men

t.

We

have

base

dth

ese

forw

ard-

look

ing

state

men

tson

histo

rical

expe

rienc

e,cu

rrent

cond

ition

san

dva

rious

assu

mpt

ions

belie

ved

tobe

reas

onab

lein

the

circ

umsta

nces

.A

ctua

lre

sults

coul

ddi

ffer

mat

eria

llyfro

mth

ose

proj

ecte

din

the

forw

ard-

look

ing

state

men

ts.Be

caus

eof

thes

eris

ks,

unce

rtain

ties

and

assu

mpt

ions

,un

due

relia

nce

shou

ldno

tbe

plac

edon

thes

efo

rwar

d-lo

okin

gsta

tem

ents.

Exce

ptto

the

exte

ntre

quire

dby

appl

icab

lese

curit

ies

law

san

dre

gula

tions

,we

unde

rtake

noob

ligat

ion

toup

date

orre

vise

any

ofth

ese

forw

ard-

look

ing

state

men

ts,w

heth

erto

refle

ctne

win

form

atio

n,fu

ture

even

tsor

othe

rwise

.

63D

RAFT

-20

13 C

ON

FIDE

NTI

AL

-Pre

limin

ary

Figu

res

97

Page 98: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Ann

ual R

epor

ting

Out

com

e M

easu

res

Crite

ria:

O

utpu

ts to

allo

w B

oard

and

Inte

rven

ors

to m

onito

r key

ou

tcom

es c

omm

itted

to in

the

appl

icat

ion

M

etric

s ne

ed to

be

mea

sura

ble,

con

trolla

ble,

and

tra

nspa

rent

M

anag

eabl

e nu

mbe

r of m

etric

s

64D

RAFT

-20

13 C

ON

FIDE

NTI

AL

-Pre

limin

ary

Figu

res

98

Page 99: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

C

usto

mer

Foc

us−

Cus

tom

er S

atisf

actio

n (i.

e. %

sat

isfie

d)

O

pera

tiona

l Effe

ctiv

enes

s−

Syste

m R

elia

bilit

y (i.

e. #

km

sof

fore

stry

brus

h co

ntro

l & li

ne c

lear

ing)

−A

sset

Man

agem

ent (

i.e. %

of i

n-se

rvic

e ca

pita

l to

fore

cast)

−O

vera

ll C

ost P

erfo

rman

ce (i

.e. %

OM

&A

/ gr

oss

fixed

cos

ts)

Pu

blic

Pol

icy

Resp

onsiv

enes

s−

Con

serv

atio

n D

eman

d M

anag

emen

t (i.e

. Net

Ann

ual P

eak

Dem

and

Savi

ngs

(MW

))−

Rene

wab

le G

ener

atio

n (i.

e. #

of c

onne

ctio

ns, e

tc.)

Fi

nanc

ial P

erfo

rman

ce−

Liqui

dity

(i.e

. cur

rent

ass

ets

/ cu

rrent

liab

ilitie

s)

65

Exam

ple

s of

Dis

trib

utio

nO

utco

me

Mea

sure

s

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

99

Page 100: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Ann

ual A

dju

stm

ents

Crite

ria:

Ex

tern

ally

driv

en b

eyon

d ut

ility

’s co

ntro

l

Ong

oing

/ re

curri

ng c

hang

es e

ither

upw

ard/

dow

nwar

d

Form

ula

base

d

66D

RAFT

-20

13 C

ON

FIDE

NTI

AL

-Pre

limin

ary

Figu

res

100

Page 101: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Ann

ual A

dju

stm

ents

Adju

stm

ents

:

(1) C

ost o

f Cap

ital

Base

d on

OEB

issu

ed R

etur

n O

n Eq

uity

and

dee

med

Sho

rt Te

rm d

ebt

rate

in N

ov e

ach

year

and

on

Hyd

ro O

ne’s

actu

al lo

ng te

rm d

ebt

issue

d

(2) W

orki

ng C

apita

lBa

sed

on c

hang

e in

Com

mod

ity P

rices

(in

clud

ing

glob

al a

djus

tmen

t)

(3) T

ax R

ate

Cha

nges

(100

%)

Base

d on

gov

ernm

ent d

irect

ed ta

x ch

ange

with

in th

e ye

ar

67D

RAFT

-20

13 C

ON

FIDE

NTI

AL

-Pre

limin

ary

Figu

res

101

Page 102: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Adju

stm

ents

(co

nt’d

):

(4) 3

rdpa

rty fl

ow-th

roug

h co

sts

Base

d on

cha

nge

in:

-Re

tail

Tran

smiss

ion

Serv

ice

Rate

(RTS

R),

-W

hole

sale

Met

er S

ervi

ce C

harg

e (W

MSC

), -

Smar

t Met

erin

g En

tity

Cha

rge

(SM

E),

-Ru

ral R

ate

Prot

ectio

n C

harg

e (R

RRP)

, -

OEB

Cha

rges

(5) C

lear

ing

of V

aria

nce

Acc

ount

s (e

.g. R

SVA

s, p

ensio

n)

Sc

hedu

le b

i-ann

ually

(i.e

2016

and

201

8) b

ased

on

the

late

st ye

ar-e

nd a

udite

d fin

anci

al a

ctua

ls.

Ann

ual A

dju

stm

ents

68D

RAFT

-20

13 C

ON

FIDE

NTI

AL

-Pre

limin

ary

Figu

res

102

Page 103: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Imple

men

tatio

n:

H

ydro

One

will

pre

sent

to th

e Bo

ard

an u

pdat

e of

ad

justm

ents

for t

he u

pcom

ing

year

as

part

of th

e dr

aft

rate

ord

er fi

led

in N

ovem

ber o

f eac

h ye

ar.

Ann

ual A

dju

stm

ents

69D

RAFT

-20

13 C

ON

FIDE

NTI

AL

-Pre

limin

ary

Figu

res

103

Page 104: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

The

Boa

rd’s

Ren

ewed

Reg

ulato

ry F

ram

ewor

k f

or

Elec

tric

ity o

utlin

ed t

hat

a r

egul

ato

ry r

evie

w m

ay

be

initi

ate

d if

:

Re

turn

on

Equi

ty is

out

side

the

+/-3

00 b

asis

poin

t ear

ning

s de

adba

nd; o

r

Pe

rform

ance

ero

des

to u

nacc

epta

ble

leve

ls

Off

-Ram

ps

70D

RAFT

-20

13 C

ON

FIDE

NTI

AL

-Pre

limin

ary

Figu

res

104

Page 105: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Crite

ria:

Ex

tern

ally

driv

en b

eyon

d ut

ility

’s co

ntro

l

Une

xpec

ted

Ve

ry m

ater

ial i

mpa

ct

71

Adju

stm

ents

Out

side

of N

orm

al

Cour

se o

f Bus

ines

s

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

105

Page 106: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Adju

stm

ents

:

Re

struc

turin

g of

the

indu

stry

N

ew G

over

nmen

t Dire

ctiv

es o

r Leg

islat

ion

M

arke

t Rul

es/C

ode

chan

ges

En

viro

nmen

tal l

aw c

hang

es

Tech

nica

l sta

ndar

d ch

ange

s

New

inve

stmen

ts re

sulti

ng fr

om th

e ne

wly

dev

elop

ed

Regi

onal

Pla

ns

M

ater

ial u

nfor

esee

n w

eath

er e

vent

s

Acc

ount

ing

Fram

ewor

k ch

ange

s

72

Adju

stm

ents

Out

side

of N

orm

al

Cour

se o

f Bus

ines

s

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

106

Page 107: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Imple

men

tatio

n:

H

ydro

One

will

file

whe

n an

eve

nt o

r cum

ulat

ive

even

ts ar

e m

ater

ially

impa

ctiv

e

Requ

ires

only

a p

artic

ular

com

pone

nt o

f the

pla

n to

be

exam

ined

and

pos

sibly

trac

ked

in a

var

ianc

e ac

coun

t an

d ad

juste

d th

roug

h a

rate

ride

r/ad

der

M

ay re

quire

a w

ritte

n pr

ocee

ding

73

Adju

stm

ents

Out

side

of N

orm

al

Cour

se o

f Bus

ines

s

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

107

Page 108: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

74

Que

stio

ns?

DIS

CL

OSU

RE

NO

TE

:

FOR

WA

RD

LO

OK

ING

STA

TE

ME

NT

SA

ND

INFO

RM

AT

ION

We

have

incl

uded

forw

ard-

look

ing

stat

emen

tsin

this

repo

rtth

atar

esu

bjec

tto

risks

,unc

erta

intie

san

das

sum

ptio

ns.S

uch

info

rmat

ion

repr

esen

tsou

rcur

rent

view

sba

sed

onin

form

atio

nas

atth

eda

teof

this

repo

rt.A

nyst

atem

entc

onta

ined

inth

isdo

cum

entt

hati

sno

tcur

rent

orhi

stor

ical

isa

forw

ard-

look

ing

stat

emen

t.W

eha

veba

sed

thes

efo

rwar

d-lo

okin

gst

atem

ents

onhi

stor

ical

expe

rienc

e,cu

rren

tcon

ditio

nsan

dva

rious

assu

mpt

ions

belie

ved

tobe

reas

onab

lein

the

circ

umst

ance

s.A

ctua

lres

ults

coul

ddi

ffer

mat

eria

llyfr

omth

ose

proj

ecte

din

the

forw

ard-

look

ing

stat

emen

ts.B

ecau

seof

thes

eris

ks,u

ncer

tain

ties

and

assu

mpt

ions

,und

uere

lianc

esh

ould

notb

epl

aced

onth

ese

forw

ard-

look

ing

stat

emen

ts.E

xcep

tto

the

exte

ntre

quire

dby

appl

icab

lese

curit

ies

law

san

dre

gula

tions

,we

unde

rtake

noob

ligat

ion

toup

date

orre

vise

any

ofth

ese

forw

ard-

look

ing

stat

emen

ts,w

heth

erto

refle

ctne

win

form

atio

n,fu

ture

even

tsor

othe

rwis

e.

DRA

FT -

2013

CO

NFI

DEN

TIA

L -P

relim

inar

y Fi

gure

s

108

Page 109: Stake holder Consultation Notes - Hydro One...Overall weighted cost of capital (WACC) is 6.76%, with a rate base calculated at $6,477M. The return on capital is $438M, income taxes

Than

k yo

u fo

r atte

ndin

g!C

heck

our

web

site

for f

urth

er in

form

atio

n:w

ww

.Hyd

roO

ne.c

om/R

egul

ator

yAffa

irs

Any

que

stion

s or

com

men

ts ca

n be

dire

cted

to:

Regu

lato

ry@

Hyd

roO

ne.c

om

109